Академический Документы
Профессиональный Документы
Культура Документы
Saunders GS :
Interpretation and Application
By David Casselman, Ontario Power Generation, Cornwall ON, Canada,
Keith Eastman, Ontario Power Generation, Cornwall ON, Canada,
and Marc R. Bissonnette, VibroSystM, Longueuil QC, Canada
ABSTRACT
The expertise of R.H. Saunders GS Production staff in analyzing and interpreting data
from the generator on-line monitoring systems installed in the 1980s & 1990s, will
result in significant competitive advantages for the facility in the advent of an open
market in Ontario. These include increased energy production and revenues,
improved reliability and capacity availability factor, as well as reduced risk of
generating equipment damage and lowered maintenance costs. This technology
can be installed in most hydroelectric facilities. However, to achieve the full potential
from generator on-line monitoring, personnel must be trained in data interpretation
and application.
Introduction
The generator On-Line Monitoring (OLM) systems described in this paper were first
installed at R.H. Saunders GS in 1989, in response to decreased generator air gaps
and indications of rotor/stator contact on generators G1 & G14. Since then, the
monitoring equipment has operated reliably and the dynamic readings have provided
valuable information of in-service generating equipment behavior and performance.
Condition monitoring equipment is becoming common throughout the hydroelectric
generation industry. Many monitoring products are offered that claim analysis
capabilities of hydroelectric machines. However, effective analysis of this information
is still in its infancy; many utilities do not have knowledgeable and experienced staff
capable of interpreting this information to the greatest extent possible and using OLM
equipment to its maximum capability.
This is not the case at R.H. Saunders GS where Production staff has developed an
expertise related to the analysis of the plant OLM information that is recognized within
Ontario Power Generation (OPG) and worldwide. They pro-actively assimilate,
interpret, analyze and apply information provided from the OLM systems. Their efforts
have resulted in avoidance of production losses and forced unit outages, increased
energy production, revised maintenance programs and improved maintenance as
well as overhaul planning processes. The result is an increase of the station
capacity availability factor with financial benefits estimated at several million dollars
during the past fifteen years.
History
The St. Lawrence River Power Project, opened in 1958, is an international hydroelectric generating complex. It is operated jointly as two separate stations of sixteen
units each by Ontario Power Generation (OPG) and New York Power Authority (NYPA).
R.H. Saunders GS, OPGs second largest hydroelectric station, consists of an equal
number of General Electric (GE) and Westinghouse machines. It is a run-of-the-river
plant with a capacity of 1030 MW providing economical base load to a grid consisting
primarily of nuclear and thermal generated power. This makes R.H. Saunders GS a
vital component in Ontarios power grid.
FIGURE 2 Cross-section of
powerhouse
The existing AGMS equipment was enhanced and expanded to a ZOOM system
during the major generating unit rehabilitation programs with the addition of:
Shaft run-out
Blade tip clearance
Split phase currents (red, white & blue)
Stator and rotor currents
Power output
Stator voltage
Wicket gate position
As a result of experience gained evaluating parameter information, efforts are now
concentrated to specifically review and evaluate three on-line monitoring parameters:
rotor/stator air gap, shaft run-out and runner blade/throat ring clearance. These three
parameters are extremely useful in providing information about the generator/turbine
assemblies:
Generator air gap polar plots are routinely observed to determine
air gaps as well as rotor and stator core centres;
Shaft run-out and air gap trends indicate potential
electrical/mechanical/hydraulic imbalances, bearing problems, and
unit alignment;
Runner blade clearance trending indicates throat ring roundness,
runner centre and unit alignment.
Evaluation of this OLM information provides the overall condition and performance of
the generating units as well as identifies potential operational problems. Specific
examples of operational benefits are illustrated.
CASE STUDIES
Case 1 New Maintenance Guidelines
New maintenance guidelines have been developed based on analysis of the
generator/turbine OLM trending information (Table 1). For example, routine unit
inspections and maintenance downtime have been reduced by at least five days for
each planned unit outage. In addition, several types of unit inspections have been
extended from one to three years or eliminated. Other benefits of OLM are:
non-intrusive maintenance with reduced risks and safety issues, as well as
elimination of human errors in manual readings and in data recordings thus ensuring
greater accuracy and reliability.
TABLE 1 Comparison of Unit Maintenance Downtime / Before vs. After OLM
Duration
Labour
Generation
Losses
1
Before OLM
(mid-1980s)
OLM-assisted
(mid-1990s)
Gains
2 weeks x unit
x year
= 32 wk/yr
7 electricians
+ 10 mechanics
= 544 pers./wk/yr
1 week x unit
every 3 years
= 5.3 wk/yr
7 electricians
+ 10 mechanics
= 90 pers./wk/yr
Over a 2
month/year period
instead of 6
Staff assigned to
other jobs;
Reduced annual
staff requirement
Approximately
200 TWh/yr of
power generation
@ 57 MW
x 80% 3
= 245 TWh/yr
@ 66 MW
x 80%
= 47 TWh/yr
2
Pre-refurbishment unit capacity
Post-refurbishment uprated unit capacity
3
Average capacity factor
420
Display Upstream
Zoom 2 X
440
45
400
A
i 380
r
315
360
G
a
340
p
225
320
(
m
300
i
l
s 280
)
260
135
240
220
200
2001-02-14
19:00:00
0.008
GGB 0
0.006
0.004
0.002
TGB 0
.9
8
4.
08
.9
8
13
.0
8.
98
25
.0
8.
98
3.
09
.9
8
8.
09
.9
8
15
.0
9.
98
16
.0
9
16 .98
St .09
ud .9
In 8
s
7. p.
11
.9
8. 8
11
.9
8
9.
11
.9
8
16
.1
1.
98
23
.1
1.
98
7.
12
.9
8
17
.1
2.
98
28
.1
2.
98
.9
8
07
19
.
07
06
.9
11
.
.9
8
0.000
06
.9
6.
Average
Rotor Center
Stator Center
.9
8
Minimum
Minimum
Minimum
Minimum
05
(Top)
(Top)
(Top)
(Top)
2.
2000-12-20
2001-01-17
19:00:00
19:00:00
18 day(s)
22:36:20
01:00:10 G9 AIR GAP 45 DEG (I2)
Generator
01:00:10 G9 AIR GAP 315 DEG (I8) Generator
01:00:10 G9 AIR GAP 225 DEG (I6) Generator
01:00:10 G9 AIR GAP 135 DEG (I4) Generator
26
.
2000/10/07
2000/10/07
2000/10/07
2000/10/07
Rounout (in.)
2000-11-22
19:00:00
mils
mils
mils
mils
01
-80.490
-44.004
58.377
67.886
20
.
2000-10-25
20:00:00
BEFORE
AFTER
Cursor at 0
485.90 mils 402.49 mils
Stator Roundness
217.25 mils 91.55 mils
Stator Center Offset
89.56 mils 31.41 mils
at 351
at 277
Maximum Gap
506.60 mils 450.98 mils
Pole 8
Pole 8
at 26
at 237
Minimum Gap
214.38 mils 288.23 mils
Pole 60
Pole 64
at 147
at 126
Mean Gap
376.71 mils 377.03 mils
140
750
750
130
130
700
120
650
A
i 600
r
110
100
90
G 550
a
p
500
80
(
m 450
i
l
400
s
)
350
70
60
50
40
D
i
s
p
l
a
c
e
m
e
n
t
(
m
i
l
s
)
700
120
650
A
i 600
r
110
G 550
a
p
500
90
(
m 450
i
l
400
s
)
350
100
80
Turbine bearing vibration remained low:
4.25 mils pk-pk
Rotor profiles have changed;
Sensor 121 showed shaft displacement
over 1 turn
70
60
50
40
D
i
s
p
l
a
c
e
m
e
n
t
(
m
i
l
s
)
300
300
30
30
301: 115.43 mils pk-pk
250
250
20
20
70
99,49
81,27
409,69
379,62
mils
mils
mils
mils
60
G1
G1
G1
G1
270dg
270dg
121dg
301dg
50
40
30
20
Pole:7
GEN BEARING DISPLACEMENT
1998/06/16
TURB BEARING DISPLACEMENT 1998/06/16
GENERATOR AIR GAP
1998/06/16
GENERATOR AIR GAP
1998/06/16
70
10
01:00:19
01:00:19
01:00:19
01:00:19
94,7
94,7
94,7
94,7
RPM
RPM
RPM
RPM
AUTO
AUTO
AUTO
AUTO
138,07
79,66
396,21
422,96
mils
mils
mils
mils
60
G1
G1
G1
G1
270dg
270dg
121dg
301dg
50
40
30
20
Pole:7
GEN BEARING DISPLACEMENT
1998/06/17
TURB BEARING DISPLACEMENT 1998/06/17
GENERATOR AIR GAP
1998/06/17
GENERATOR AIR GAP
1998/06/17
10
10:46:17
10:46:17
10:46:17
10:46:17
94,7
94,7
94,7
94,7
RPM
RPM
RPM
RPM
CHECK
CHECK
CHECK
CHECK
230
B
l 220
a
d
e 210
T 200
i
p 190
C
l
e
a
r
a
n
c
e
Slotting
Between
Units
2&3
180
Slotting
Between
Units
2&1
170
160
150
140
(
m 130
i
l 120
s
)
110
-14,55 mils
-27,77 mils
34,97 mils
17,23 mils
1996-11-13
1996-11-20
19:00:00
19:00:00
18 day(s)
18:52:48
1995/12/18 17:12:33
G2 Blade Tip Clear.
1995/12/18 17:12:33
G2 Blade Tip Clear.
1995/12/18 17:12:33
G2 Blade Tip Clear.
1995/12/18 17:12:33
G2 Blade Tip Clear.
1996-11-27
19:00:00
170dg
350dg
260dg
80dg
Minimum
Minimum
Minimum
Minimum
FINANCIAL BENEFITS
Effective interpretation of OLM data by R.H. Saunders GS Production staff has
increased the availability factor at the plant. The benefits in additional power
generation can quickly add up to hundreds of thousands, even millions of dollars
annually.
Spending just five minutes a day to check critical machines, half an hour a week to
overview all parameters, and one day a month to record a complete set of data for
trending (total 1.5 day per month for one person) generates a lot of spare time to
many people for other tasks, not to mention revenues.
CONCLUSION
The OLM system has proven to be an extremely valuable tool. OLM results analysis at
R.H. Saunders GS by Production staff experienced in data interpretation falls in line
with OPGs less intrusive maintenance approach. It has reduced the risk of
equipment damage, lowered maintenance costs, and increased reliability statistics,
capacity availability factor, energy production and revenues. Based on the cases
illustrated, our experience shows that the money and labour invested in OLM
equipment has been paid back manyfold. This initiative places R.H. Saunders GS in
a more competitive position as it enters into the open market.
REFERENCES
Casselman D., Curtis G.R. & Mohino A., R.H.Saunders Generating Station: Crisis
Management, Hydrovision Conference 2000, Charlotte, North Carolina
Case Study: R.H. Saunders GS On-line Machine Condition Monitoring Contributes to
Significant Operations & Maintenance Savings, Water Power & Dam Construction,
June 1999, page 18.
Eastman K.T., Ho M.S. & Adeghe L.N., Innovative Techniques to Mitigate Concrete
Expansion R.H. Saunders GS, Hydrovision Conference 1998, Reno, Nevada
Kee D.C., Liscio L., Ho M.S. & Eastman K.T., Rehabilitating R.H. Saunders:
Enhancing Value, Special Report, Hydro Review, Volume XVII, No. 7, December
1998, pages 44 51.
Goodeve T.E., Pollock G.B. & Bissonnette M.R., Vital Signs Monitoring of Hydraulic
Turbine/Generators, CEA Spring 1992 Meeting, March 1992, Vancouver, BC, Canada.
Pollock G.B. & Lyles J.F., Vertical Hydraulic Generators: Experiences with Air Gap
Monitoring, IEEE/PES 1992 Winter Meeting, January 1992, New York, NY, USA.
Urban D.A., G1 Loss of Rotor to Stator Air Gap at R.H. Saunders GS: A Success
Story, Ontario Hydro Internal Memorandum, December 1991.
AUTHORS
David Casselman, Production Manager, R.H. Saunders GS, Ontario Power
Generation, has thirty one years of hydroelectric, transmission and retail maintenance
and operating experience. David has extensive experience with generator/turbine
on-line monitoring equipment.
Keith T. Eastman, P.Eng., M.Eng., Senior Plant Engineer, R.H. Saunders GS,
Ontario Power Generation, has twenty two years of hydroelectric and transmission
technical field services experience. He was a team leader involved with all phases of
the Concrete Rehabilitation Project.
Mr. Marc R. Bissonnette, P.Eng., is an Electrical Engineering graduate of the University
of Sherbrooke (Sherbrooke, Canada) in 1986. Since 1987, he has been involved with
the ongoing development and marketing of monitoring systems for large rotating
machines. Mr. Bissonnette is presently Sales Manager for VibroSystMs Machine
Condition Monitoring Division.
Ackowledgements
The authors wish to thank Mr. Dean MacIntosh of Ontario Power Generation and
Mr. Rjean Beaudoin of VibroSystM for their contribution to this paper.
1
2