Академический Документы
Профессиональный Документы
Культура Документы
J.F.W. Joustra
Tunnel Engineering Consultants (TEC)/Witteveen Bos
A.M. Talmon
WL | Delft Hydraulics, Delft, Netherlands
B. Grote
T & E Consult
ABSTRACT: Measurements are presented that were performed in the pressure chamber of an EPB TBM. The
TBM operated in saturated sand with a high water table. Foam was applied for soil conditioning. Different from
a slurry shield there was no direct relation between vertical the pressure gradient and the density of the sand
water foam mixture in the pressure chamber. The pressure measurements differ considerably for different rings.
The density of the mixture was measured by taking samples from the pressure chamber during excavation.
Densities found indicate a porosity higher than the maximum porosity of the sand. Horizontal pressure gradients were measured during drilling depending on the rotation direction of the cutter head. A possible explanation is presented in the paper.
INTRODUCTION
MEASUREMENTS
Measurements performed
sand
sand
30m
middle to coarse sand
with gravel
sand
sand
318
813
peat
809
vert.press.grad(kPa/m)
0
E9
E1
2.5
W1
315
E8
45
E2
30
25
20
15
10
5
4.50
17.5
4.25
0.0
positive
rotation
E6
W2
90
3.50
E4
E5
225
W3
15.0
3.75
12.5
E5
3.25
3.00
E2
2.50
2.25
7.5
E1
2.00
135
10.0
E4
E3
2.75
5.0
status
1.75
1.50
screw
conveyor
STATUS
270
4.00
E3
pressure (bar)
E7
2.5
1.25
180
1.00
0.0
12:00
12:30
13:00
13:30
14:00
14:30
TIME
2.2
Density measurements
Pressure measurements
Status
Meaning
1
2
3
4
5
6
810
-5
-4
-3
-2
-1
0
pressure (bar)
11:50:52
11:51:38
12:00:00
12:04:31
12:04:35
12:30:01
13:00:03
13:30:02
13:34:00
4.50
4.25
4.00
3.75
3.50
3.25
3.00
2.75
2.50
2.25
2.00
1.75
1.50
1.25
1.00
W2
W1
E3
E1
12:00
12:30
13:00
TIME
13:30
14:00
14:30
2
3
4
2.5
3.0
3.5
4.0
rpm
2.0
Pressure (bar)
0
-1
-2
5
pressure (bar)
00:30:00
01:00:00
01:30:00
4
E6
3
E4
2
1
0
00:30:00
01:00:00
TIME
01:30:00
811
(Bezuijen & Schamine, 2001). A more constant pressure may lead to a smoother drilling process with less
stops. Now it can be seen from Figure 3, the status,
that there are sometimes a lot of stops during drilling.
-5
E1E9 E9
-4 E1
-3
0:26:02
E2 E2
E8
E8
0:40:03
-2
-1
E3
E3
3.1
E7
E7
0
1
2
E6
E6
E4
E4
3
E5 E5
4
2.0
2.5
3.0
3.5
pressure (kPa)
4.0
rpm
1
0
-1
-2
4.50
pressure (bar)
4.25
4.00
3.75
25
E6
3.50
3.25
3.00
E4
2.75
DISCUSSION
Vertical gradient
2.50
12:00:00
12:30:00
13:00:00
13:30:00
14:00:00
14:30:00
(1)
TIME
812
Horizontal gradient
0
315
45
2.5
mixture
level
270
mixture
level
0.0
90
rotation
225
135
p
180
Figure 9. Sketch of possible pressure distribution due to rotation of cutter head without effective stress, see further text.
813
2
rpm
1
0
-1
pressure (bar)
-2
5.0
4.5
E6
E4
4.0
W3
3.5
3.0
E5
2.5
2.0
00:30:00
01:00:00
TIME
01:30:00
ACKNOWLEDGEMENTS
CONCLUSIONS
REFERENCES
Bakker K.J., Teunissen E.A.H., Berg P. van den,
Smits M. Th. J.H., 2003, K100 research at the second
Heinenoord tunnel. Proc. ITA 2003, Amsterdam,
Bezuijen A., Pruiksma J.P., Meerten H.H. van 2001. Pore
pressures in front of tunnel, measurements, calculations
and consequences for stability of tunnel face. Proc. Int.
Symp. on Modern Tunneling Science and Techn. Kyoto.
Bezuijen, A., & P.E.L. Schamine, 2001, Simulation of the
EPB-shield TBM in model tests with foam as additive,
Proc. Int. Symp. on Modern Tunneling Science and Techn.
Kyoto.
Bezuijen A. Influence of soil permeability on the properties
of a foam mixture in a TBM. 3rd Int. Symp. on Geotch.
Aspects of Underground Construction in Soft Ground,
IS-Toulouse.
Joustra, J.F.W., 2002, Additional data analysis independent
research project Botlek Rail Tunnel, the EPB-process
(in Dutch), Delft University of Technology report.
2001.BT.5566.
Mair, R.J., Merrit, A.S., Borghi, X., Yamazaki, H., and
Minami T., 2003. Soil conditioning of Clay Soils.
Tunnels and Tunnelling International, April.
Talmon A.M. & A. Bezuijen, 2002, Muck discharge by the
screw conveyor of an EPB Tunnel Boring Machine, 3rd Int.
Symp. on Geotch. Aspects of Underground Construction
in Soft Ground, IS-Toulouse.
814