Академический Документы
Профессиональный Документы
Культура Документы
PROJECT
LOCATION
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
I.
QTY.
UNIT
MATERIAL COST
UNIT
TOTAL
LABOR COST
UNIT
TOTAL
GENERAL REQUIREMENTS
1.1 Mobilization / Demobilization
lot
0.00
lot
0.00
0.00
748 sq.m.
2 eq.d.
0.00
1 - Chainsaw
3 eq.d.
0.00
3 md.
0.00
3 md.
0.00
12 md.
0.00
Manpower Requirement :
1 - Project Engineer
1 - Foreman
4 - Laborer
Total Cost of Site Clearing and Grubbing
2.2 Soil Poisoning
2.3 Excavation incl. disposal of waste
0.00
748 sq.m.
1876.22 cu.m.
Equipment Requirement :
1 - Payloader/Backhoe
18 eq.d.
0.00
2 - Dumptrack
36 eq.d.
0.00
18 md.
0.00
Manpower Requirement :
1 - Project Engineer
Pg. 1 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
1 - Foreman
18 md.
0.00
4 - Laborer
72 md.
0.00
0.00
1886.02 cu.m.
Material Requirements
Earthfill
1886.02 cu.m.
350.00
Equipment Requirement
1 - Baby Roller / Plate Compactor
15 eq.d.
0.00
1 - Payloader
10 eq.d.
0.00
15 md.
0.00
15 md.
0.00
120 md.
0.00
Manpower Requirement
1 - Project Engineer
1 - Foreman
8 - Laborer
Total Cost of Backfilling and Compaction
2.5 Gravel Base Coarse
0.00
0.00
142.56 cu.m.
Material Requirements
Gravel
142.56 cu.m.
800.00
Equipment Requirement :
1 - Backhoe
6 eq.d.
0.00
1 - Project Engineer
6 md.
0.00
1 - Foreman
6 md.
0.00
48 md.
0.00
Manpower Requirement
8 - Laborer
Total Cost of Gravel Base Coarse
0.00
0.00
0.00
0.00
Pg. 2 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
748 sq.m.
1226.67 bd.ft.
0.00
1749.33 bd.ft.
0.00
7735 bd.ft.
0.00
6,888 bd.ft.
0.00
304 sheets
0.00
4" CW Nails
10 box
0.00
3" CW Nails
5 box
0.00
2 1/2" CW Nails
8 box
0.00
2" CW Nails
8 box
0.00
1" CW Nails
2 box
0.00
TOTAL
Manpower Requirement
1 - Project Engineer
1 - Foreman
25 md.
0.00
25 md.
0.00
5 - Carpenter
125 md.
0.00
5 - Laborer
125 md.
0.00
0.00
0.00
301.997 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
302 cu.m.
0.00
kg.
0.00
3883.95
kg.
0.00
15802
kg.
0.00
568.08
kg.
0.00
kg.
0.00
5 rolls
0.00
# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator
10 eq.d.
0.00
Pg. 3 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
Manpower Requirements
1 - Project Engineer
53 md.
0.00
1 - Foreman
53 md.
0.00
424 md.
0.00
424 md.
0.00
1060 md.
0.00
8 - Steelman
8 - Mason
20 - Laborer
Total Cost of Foundation
4.2 Footing Tie Beam
0.00
16.107 cu.m.
0.00
1136.16
kg.
0.00
1363.39
kg.
0.00
858.864
kg.
0.00
2 rolls
0.00
# 16 Tie Wire
0.00
Equipment Requirement
1 - Concrete Vibrator
2 eq.d.
0.00
5 md.
0.00
Manpower Requirements
1 - Project Engineer
1 - Foreman
5 md.
0.00
8 - Steelman
40 md.
0.00
4 - Mason
20 md.
0.00
16 - Laborer
80 md.
0.00
0.00
23.919 cu.m.
0.00
0.00
142.02
kg.
0.00
833.184
kg.
0.00
721.89
kg.
0.00
2 rolls
0.00
Pg. 4 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
Equipment Requirement
1 - Concrete Vibrator
2 eq.d.
0.00
1 - Project Engineer
4 md.
0.00
1 - Foreman
4 md.
0.00
8 - Steelman
32 md.
0.00
4 - Mason
16 md.
0.00
16 - Laborer
64 md.
0.00
Manpower Requirements
0.00
0.00
38.298 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 38.298 cu.m.
0.00
11275
kg.
0.00
1969.46
kg.
0.00
6 rolls
0.00
# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator
3 eq.d.
0.00
1 - Project Engineer
15 md.
0.00
1 - Foreman
15 md.
0.00
8 - Steelman
120 md.
0.00
8 - Mason
120 md.
0.00
20 - Laborer
300 md.
0.00
Manpower Requirements
0.00
0.00
27.507 cu.m.
0.00
1405.62
kg.
0.00
4690.33
kg.
0.00
Pg. 5 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
94.68
kg.
0.00
1677
kg.
0.00
3 rolls
0.00
TOTAL
Equipment Requirement
1 - Concrete Vibrator
2 eq.d.
0.00
1 - Project Engineer
9 md.
0.00
1 - Foreman
9 md.
0.00
72 md.
0.00
72 md.
0.00
180 md.
0.00
Manpower Requirements
8 - Steelman
8 - Mason
20 - Laborer
Total Cost of Second Floor Girder/ Beam
4.6 Ground Floor Slab
0.00
0.00
46.196 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 46.196 cu.m.
0.00
kg.
0.00
1 rolls
0.00
# 16 Tie Wire
1636.28
Equipment Requirement
1 - Concrete Vibrator
4 eq.d.
0.00
1 - Project Engineer
5 md.
0.00
1 - Foreman
5 md.
0.00
8 - Steelman
40 md.
0.00
8 - Mason
40 md.
0.00
100 md.
0.00
Manpower Requirements
20 - Laborer
Total Cost of Ground Floor Slab
4.7 Second Floor Slab
0.00
0.00
40.287 cu.m.
Pg. 6 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 40.287 cu.m.
0.00
8087.9
kg.
0.00
4083.31
kg.
0.00
4 rolls
0.00
Equipment Requirement
1 - Concrete Vibrator
4 eq.d.
0.00
13 md.
0.00
Manpower Requirements
1 - Project Engineer
1 - Foreman
13 md.
0.00
8 - Steelman
104 md.
0.00
8 - Mason
104 md.
0.00
20 - Laborer
260 md.
0.00
0.00
0.00
8.281 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
346 - 16mm x 6.0 m. def. bars
# 16 Tie Wire
8.281 cu.m.
3275.93
0.00
kg.
0.00
1 rolls
0.00
Equipment Requirement
1 - Concrete Vibrator
1 eq.d.
0.00
1 - Project Engineer
5 md.
0.00
1 - Foreman
5 md.
0.00
8 - Steelman
40 md.
0.00
4 - Mason
20 md.
0.00
15 - Laborer
75 md.
0.00
Manpower Requirements
0.00
0.00
Pg. 7 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
6.99 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
6.99 cu.m.
0.00
321.912
kg.
0.00
229.524
kg.
0.00
12
kg.
0.00
# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator
1 eq.d.
0.00
1 - Project Engineer
2 md.
0.00
1 - Foreman
2 md.
0.00
4 - Steelman
8 md.
0.00
8 md.
0.00
20 md.
0.00
Manpower Requirements
4 - Mason
10 - Laborer
Total Cost of 1st to 2nd Stair Case A
4.10 1st to 2nd Stair Case B
0.00
0.00
9.752 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
54 - 16mm x 6.0 m. def. bars
60 - 10 mm x 6.0 m. def. bars
# 16 Tie Wire
9.752 cu.m.
0.00
511.272
kg.
0.00
222.12
kg.
0.00
15
kg.
0.00
Equipment Requirement
1 - Concrete Vibrator
1 eq.d.
0.00
3 md.
0.00
Manpower Requirements
1 - Project Engineer
1 - Foreman
3 md.
0.00
4 - Steelman
12 md.
0.00
4 - Mason
12 md.
0.00
Pg. 8 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
8 - Laborer
QTY.
UNIT
LABOR COST
TOTAL
UNIT
24 md.
MATERIAL COST
UNIT
TOTAL
0.00
0.00
0.00
17.483 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 17.483 cu.m.
0.00
7516.37
kg.
0.00
1791.77
kg.
0.00
5 rolls
0.00
# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator
2 eq.d.
0.00
1 - Project Engineer
10 md.
0.00
1 - Foreman
10 md.
0.00
8 - Steelman
80 md.
0.00
80 md.
0.00
200 md.
0.00
Manpower Requirements
8 - Mason
20 - Laborer
Total Cost of Second Floor Column
4.12 Third Floor Girder / Beam
0.00
0.00
27.509 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 27.509 cu.m.
0.00
1405.62
kg.
0.00
4690.33
kg.
0.00
94.68
kg.
0.00
1677
kg.
0.00
3 rolls
0.00
2 eq.d.
0.00
Pg. 9 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
Manpower Requirements
1 - Project Engineer
9 md.
0.00
1 - Foreman
9 md.
0.00
72 md.
0.00
72 md.
0.00
180 md.
0.00
8 - Steelman
8 - Mason
20 - Laborer
Total Cost of Third Floor Girder/ Beam
4.13 Third Floor Slab
0.00
0.00
48.568 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 48.568 cu.m.
0.00
8087.9
kg.
0.00
4083.31
kg.
0.00
4 rolls
0.00
Equipment Requirement
1 - Concrete Vibrator
4 eq.d.
0.00
14 md.
0.00
Manpower Requirements
1 - Project Engineer
1 - Foreman
14 md.
0.00
8 - Steelman
112 md.
0.00
8 - Mason
112 md.
0.00
20 - Laborer
280 md.
0.00
0.00
0.00
8.281 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
346 - 16mm x 6.0 m. def. bars
# 16 Tie Wire
8.281 cu.m.
3275.93
0.00
kg.
0.00
1 rolls
0.00
Equipment Requirement
Pg. 10 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
1 - Concrete Vibrator
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
1 eq.d.
0.00
5 md.
0.00
Manpower Requirements
1 - Project Engineer
1 - Foreman
5 md.
0.00
8 - Steelman
40 md.
0.00
4 - Mason
20 md.
0.00
15 - Laborer
75 md.
0.00
0.00
0.00
6.99 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
6.99 cu.m.
0.00
321.912
kg.
0.00
229.524
kg.
0.00
12
kg.
0.00
# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator
1 eq.d.
0.00
1 - Project Engineer
2 md.
0.00
1 - Foreman
2 md.
0.00
4 - Steelman
8 md.
0.00
8 md.
0.00
20 md.
0.00
Manpower Requirements
4 - Mason
10 - Laborer
Total Cost of 2nd to 3rd Stair Case A
4.16 2nd to 3rd Stair Case B
0.00
0.00
9.752 cu.m.
Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
54 - 16mm x 6.0 m. def. bars
60 - 10 mm x 6.0 m. def. bars
9.752 cu.m.
0.00
511.272
kg.
0.00
222.12
kg.
0.00
Pg. 11 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
# 16 Tie Wire
UNIT
15
kg.
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
0.00
Equipment Requirement
1 - Concrete Vibrator
1 eq.d.
0.00
1 - Project Engineer
3 md.
0.00
1 - Foreman
3 md.
0.00
4 - Steelman
12 md.
0.00
4 - Mason
12 md.
0.00
8 - Laborer
24 md.
0.00
Manpower Requirements
V.
0.00
0.00
0.00
0.00
MASONRY WORKS
5.1 Ground Floor
541.96 sq.m.
Material Requirements
6" CHB (machine made)
349 - 10 mm x 6.0 m. def. bars
#16 GI Tie Wire
Portland Cement
Coarse Sand
6,775
pc.
0.00
1292
kg.
0.00
30
kg.
0.00
542 bag
0.00
46 cu.m.
0.00
Manpower Requirements
1 - Project Engineer
14 md.
0.00
1 - Foreman
14 md.
0.00
4 - Steelman
56 md.
0.00
4 - Mason
56 md.
0.00
112 md.
0.00
8 - Laborer
Total Cost of Ground Floor Masonry
5.2 Second Floor
0.00
0.00
374.66 sq.m.
Pg. 12 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
Material Requirements
6" CHB (machine made)
235 - 10 mm x 6.0 m. def. bars
#16 GI Tie Wire
Portland Cement
Coarse Sand
4,684
pc.
0.00
869.97
kg.
0.00
23
kg.
0.00
375 bag
0.00
32 cu.m.
0.00
Manpower Requirements
1 - Project Engineer
9 md.
0.00
1 - Foreman
9 md.
0.00
4 - Steelman
36 md.
0.00
4 - Mason
36 md.
0.00
8 - Laborer
72 md.
0.00
0.00
0.00
0.00
0.00
248.22 sq.m.
Material Requirements
6.1.1 Flooring
0.60 x 0.60 Porcelain Tiles
Portland Cement
Fine Sand
Grouting Cement
6.1.2 Comfort Room
0.30 x 0.30 Ceramic tiles (Mariwasa)
Portland Cement
Fine Sand
Grouting Cement
Tile Trim
6.1.3 Sink / Lavatory
184.06 sq.m.
520
pc.
0.00
57 bag
0.00
5 cu.m.
10 bag
0.00
0.00
59.12 sq.m.
690
pc.
0.00
18 bag
0.00
1.5 cu.m.
0.00
8 bag
0.00
19 lgth.
0.00
5.04 sq.m.
Pg. 13 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
20
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
pc.
0.00
2 bag
0.00
0.20 cu.m.
TOTAL
0.00
Grouting Cement
1 bag
0.00
Tile Trim
3 lgth.
0.00
Manpower Requirements
1 - Project Engineer
11 md.
0.00
1 - Foreman
11 md.
0.00
5 - Installer
55 md.
0.00
5 - Helper
55 md.
0.00
0.00
0.00
272.10 sq.m.
Material Requirements
6.2.1 Flooring
0.60 x 0.60 Granite Base Tile Unglazed
Portland Cement
Fine Sand
Grouting Cement
6.2.2 Comfort Room
0.30 x 0.30 Ceramic tiles
Portland Cement
Fine Sand
184.06 sq.m.
520
pc.
0.00
57 bag
0.00
5 cu.m.
10 bag
0.00
0.00
73.24 sq.m.
820
pc.
0.00
23 bag
0.00
2 cu.m.
0.00
Grouting Cement
10 bag
0.00
Tile Trim
25 lgth.
0.00
14.80 sq.m.
45
pc.
0.00
5 bag
0.00
0.50 cu.m.
0.00
Grouting Cement
2 bag
0.00
Tile Trim
5 lgth.
0.00
Pg. 14 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
Manpower Requirements
1 - Project Engineer
12 md.
0.00
1 - Foreman
12 md.
0.00
5 - Installer
60 md.
0.00
5 - Helper
60 md.
0.00
0.00
0.00
0.00
0.00
1.00
lot
2 unit
0.00
1 unit
0.00
1 unit
0.00
2 unit
0.00
1 unit
0.00
4 unit
0.00
6 unit
0.00
1 unit
0.00
3 unit
0.00
1 unit
0.00
1 unit
0.00
Manpower Requirements
1 - Project Engineer
10 md.
0.00
1 - Foreman
10 md.
0.00
2 - Installer
20 md.
0.00
2 - Helper
40 md.
0.00
0.00
0.00
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
Material Requirements
D - 3 (0.90 x 2.10 Metal Door & Jamb)
1 unit
0.00
1 unit
0.00
2 unit
0.00
1 unit
0.00
4 unit
0.00
2 unit
0.00
5 unit
0.00
1 unit
0.00
4 unit
0.00
1 unit
0.00
1 unit
0.00
1 unit
0.00
1 unit
0.00
Door Knob
set
0.00
10 gal.
0.00
Metal Primer
2" Paint Brush
pc.
0.00
Manpower Requirements
1 - Project Engineer
10 md.
0.00
1 - Foreman
10 md.
0.00
2 - Installer
20 md.
0.00
2 - Helper
40 md.
0.00
0.00
0.00
0.00
0.00
305.60 sq.m.
Material Requirements
Portland Cement
Fine Sand
69 bag
8 cu.m.
0.00
0.00
Manpower Requirements
Pg. 16 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
1 - Project Engineer
2 md.
0.00
1 - Foreman
2 md.
0.00
2 - Mason
4 md.
0.00
4 - Laborer
8 md.
0.00
0.00
0.00
349.88 sq.m.
Material Requirements
Portland Cement
Fine Sand
79 bag
9 cu.m.
0.00
0.00
Manpower Requirements
1 - Project Engineer
8 md.
0.00
1 - Foreman
8 md.
0.00
3 - Mason
24 md.
0.00
3 - Laborer
24 md.
0.00
0.00
0.00
0.00
0.00
1.00
lot
9 lgth.
0.00
54 lgth.
0.00
Welding Rod
10
kg.
0.00
Metal Primer
2 gal.
0.00
pc.
0.00
Hacksaw Blade
pc.
0.00
90
pc.
0.00
Pg. 17 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
8
pc.
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
0.00
Manpower Requirements
1 - Project Engineer
5 md.
0.00
1 - Foreman
5 md.
0.00
1 - Welder
5 md.
0.00
10 md.
0.00
2 - Laborer
Total Cost of Second Floor Steel Works
0.00
0.00
0.00
0.00
X. PLUMBING WORKS
1.00
lot
Water Closet
set
0.00
Floor Drain
set
0.00
Urinal
set
0.00
Lavatory w/ faucet
set
0.00
set
0.00
24 lgth.
0.00
8 lgth.
0.00
15 lgth.
0.00
12
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
100mm Elbow
15
pc.
0.00
75mm Elbow
15
pc.
0.00
50mm Elbow
15
pc.
0.00
pc.
0.00
pc.
0.00
Pg. 18 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
75mm P - Trap
pc.
0.00
50mm P - Trap
pc.
0.00
50mm Tee
pc.
0.00
Solvent Cement
3 can
0.00
2 lgth.
0.00
10 lgth.
0.00
10 lgth.
0.00
TOTAL
pc.
0.00
23
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
mtr.
0.00
PPR Nipple
0.50
Manpower Requirements
1 - Project Engineer
13 md.
0.00
1 - Foreman
13 md.
0.00
2 - Plumber
26 md.
0.00
2 - Helper
26 md.
0.00
0.00
0.00
set
0.00
Floor Drain
set
0.00
Urinal
set
0.00
Lavatory w/ faucet
set
0.00
set
0.00
Pg. 19 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
11 lgth.
0.00
7 lgth.
0.00
20 lgth.
0.00
13
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
13
pc.
0.00
75mm Elbow
pc.
0.00
50mm Elbow
15
pc.
0.00
pc.
0.00
pc.
0.00
75mm P - Trap
pc.
0.00
50mm P - Trap
pc.
0.00
11
pc.
0.00
3 can
0.00
2 lgth.
0.00
10 lgth.
0.00
12 lgth.
0.00
100mm Elbow
50mm Tee
Solvent Cement
10.2.3 Water Line
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
pc.
0.00
0.5 mtr.
0.00
PPR Nipple
Manpower Requirements
Pg. 20 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
1 - Project Engineer
15 md.
0.00
1 - Foreman
15 md.
0.00
2 - Plumber
30 md.
0.00
2 - Helper
30 md.
0.00
0.00
0.00
0.00
0.00
1.00
lot
set
0.00
set
0.00
Material Requirements
Main Breaker : 400AT/500AF, 3P, 230V,
50KAIC
Brs. 5-100AT/100AF, 3P, 230V, 25KAIC
1-60AT/100AF, 3P, 230V, 25KAIC
w/ grounding & neutral terminal
ECB : 60AT/100AF, 3P, 230V, 25KAIC
in NEMA - 3R Encl.
100mm RSC Pipe
3 lgth.
0.00
0.00
7 lgth.
0.00
0.00
pc.
pc.
33 lgth.
0.00
pc.
0.00
pc.
0.00
4 mtr.
0.00
30 mtr.
0.00
21 mtr.
0.00
28 mtr.
0.00
100 mtr.
0.00
2
2
Electrical tape
10
roll
0.00
kg.
0.00
2 bag
0.00
Concrete Pedestal
0.00
lot
Pg. 21 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
Manpower Requirements
1 - Project Engineer
12 md.
0.00
1 - Foreman
12 md.
0.00
2 - Electrician
24 md.
0.00
4 - Helper
96 md.
0.00
0.00
0.00
set
0.00
set
0.00
set
0.00
set
0.00
10
set
0.00
set
0.00
28
set
0.00
set
0.00
set
0.00
17
set
0.00
set
0.00
set
0.00
40 lgth.
0.00
106 lgth.
0.00
Conduit Fittings
lot
0.00
600 mtr.
0.00
1200 mtr.
0.00
450 mtr.
0.00
2
2
2
60
pc.
0.00
75
pc.
0.00
Pg. 22 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
5
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
pc.
0.00
pc.
0.00
10
kg.
0.00
Electrical Tape
15
roll
0.00
12.5 mtr.
0.00
pc.
0.00
3 can
0.00
TOTAL
Manpower Requirements
1 - Project Engineer
10 md.
0.00
1 - Foreman
10 md.
0.00
2 - Electrician
20 md.
0.00
4 - Helper
80 md.
0.00
0.00
0.00
set
0.00
set
0.00
set
0.00
set
0.00
13
set
0.00
set
0.00
27
set
0.00
set
0.00
set
0.00
17
set
0.00
set
0.00
set
0.00
35 lgth.
0.00
Pg. 23 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
150 lgth.
1
lot
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
0.00
0.00
600 mtr.
0.00
1200 mtr.
0.00
450 mtr.
0.00
8 lgth.
0.00
pc.
0.00
8 mtr.
0.00
50 mtr.
0.00
25 mtr.
0.00
60
pc.
0.00
75
pc.
0.00
pc.
0.00
Pullboxes
pc.
0.00
kg.
0.00
15
roll
0.00
12.5 mtr.
0.00
Electrical Tape
1/2mm Flexible Mettalic Pipe
TOTAL
pc.
0.00
3 can
0.00
Manpower Requirements
1 - Project Engineer
10 md.
0.00
1 - Foreman
10 md.
0.00
2 - Electrician
20 md.
0.00
4 - Helper
80 md.
0.00
0.00
0.00
0.00
0.00
sq.m.
Material Requirements
100mm PVC Pipe S1000
69 lgth.
0.00
100mm Elbow
23
pc.
0.00
4.00
can
0.00
Pg. 24 of 19
19 October 2012
: CONSTRUCTION OF
:
ITEM
DESCRIPTION
NO.
QTY.
UNIT
MATERIAL COST
UNIT
LABOR COST
TOTAL
UNIT
TOTAL
Manpower Requirements
1 - Project Engineer
3 md.
0.00
1 - Foreman
3 md.
0.00
1 - Laborer
3 md.
0.00
0.00
0.00
0.00
INDIRECT COST
OCM (12%)
Contractor's Profit (10%)
VAT & Withholding Tax (12%)
TOTAL INDIRECT COST
SUB-TOTAL (ABC)
ADMINISTRATIVE COST (3.5%)
TOTAL ESTIMATED COST
Prepared by:
Noted :
Engr.
Quantity Surveyor/Estimator
PROJECT MANAGER
Pg. 25 of 19
19 October 2012
TOTAL
ITEM COST
0.00
0.00
0.00
0.00
0.00
*** 70cu.m./4hrs.
Pg. 26 of 19
19 October 2012
TOTAL
ITEM COST
0.00
0.00
#DIV/0!
0.00
0.00
#DIV/0!
#DIV/0!
Pg. 27 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
2441.34
3883.95
15802.128
568.08
9752.04
Pg. 28 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
1136.16
16
1363.392
858.864
858.864
0.00
#DIV/0!
142.02
833.184
721.89
858.864
Pg. 29 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
11274.552
1969.464
0.00
#DIV/0!
1405.62
4690.332
Pg. 30 of 19
19 October 2012
TOTAL
ITEM COST
94.68
1677.006
0.00
#DIV/0!
1636.284
0.00
#DIV/0!
Pg. 31 of 19
19 October 2012
TOTAL
ITEM COST
8087.904
4083.306
0.00
#DIV/0!
3275.928
0.00
#DIV/0!
Pg. 32 of 19
19 October 2012
TOTAL
ITEM COST
321.912
229.524
0.00
#DIV/0!
511.272
222.12
Pg. 33 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
7516.368
1791.768
0.00
#DIV/0!
1405.62
4690.332
94.68
1677.006
Pg. 34 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
8087.904
4083.306
0.00
#DIV/0!
3275.928
Pg. 35 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
321.912
229.524
0.00
#DIV/0!
511.272
222.12
Pg. 36 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
0.00
0.00
1291.998
0.00
#DIV/0!
Pg. 37 of 19
19 October 2012
TOTAL
ITEM COST
869.97
0.00
#DIV/0!
0.00
#DIV/0!
0.00
511.2777777778
Pg. 38 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
Pg. 39 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
0.00
0.00
222.12
0.00
Pg. 40 of 19
19 October 2012
TOTAL
ITEM COST
1.68
3696
700
4396
0.00
0.00
#DIV/0!
0.00
7.64
68.76
Pg. 41 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
8.747
78.723
0.00
#DIV/0!
0.00
#DIV/0!
Pg. 42 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
0.00
0.00
Pg. 43 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
Pg. 44 of 19
19 October 2012
TOTAL
ITEM COST
Pg. 45 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
0.00
0.00
222.12
Pg. 46 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
Pg. 47 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
Pg. 48 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
0.00
#DIV/0!
0.00
Pg. 49 of 19
19 October 2012
TOTAL
ITEM COST
0.00
#DIV/0!
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
6,000,000.00
Pg. 50 of 19
19 October 2012