Вы находитесь на странице: 1из 50

MATERIALS TAKE- OFF AND COST ESTIMATES

PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.
I.

QTY.

UNIT

MATERIAL COST
UNIT

TOTAL

LABOR COST
UNIT

TOTAL

GENERAL REQUIREMENTS
1.1 Mobilization / Demobilization

lot

0.00

lot

0.00

(Inc. temporary facilities such as field office,


bodega, cleaning and moving out
including temporary connections for
water and electricity)
1.2 Construction Safety
Total Cost of General Requirements

0.00

II. SITE WORKS


2.1 Site Clearing and Grubbing

748 sq.m.

(removal of structures & obstruction incl.


trees and stumps)
Equipment Requirement :
1 - Backhoe

2 eq.d.

0.00

1 - Chainsaw

3 eq.d.

0.00

3 md.

0.00

3 md.

0.00

12 md.

0.00

Manpower Requirement :
1 - Project Engineer
1 - Foreman
4 - Laborer
Total Cost of Site Clearing and Grubbing
2.2 Soil Poisoning
2.3 Excavation incl. disposal of waste

0.00
748 sq.m.
1876.22 cu.m.

Equipment Requirement :
1 - Payloader/Backhoe

18 eq.d.

0.00

2 - Dumptrack

36 eq.d.

0.00

18 md.

0.00

Manpower Requirement :
1 - Project Engineer

Pg. 1 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

1 - Foreman

18 md.

0.00

4 - Laborer

72 md.

0.00

Total Cost of Excavation incl. disposal of waste


2.4 Backfilling and Compaction

0.00

1886.02 cu.m.

Material Requirements
Earthfill

1886.02 cu.m.

350.00

Equipment Requirement
1 - Baby Roller / Plate Compactor

15 eq.d.

0.00

1 - Payloader

10 eq.d.

0.00

15 md.

0.00

15 md.

0.00

120 md.

0.00

Manpower Requirement
1 - Project Engineer
1 - Foreman
8 - Laborer
Total Cost of Backfilling and Compaction
2.5 Gravel Base Coarse

0.00

0.00

142.56 cu.m.

Material Requirements
Gravel

142.56 cu.m.

800.00

Equipment Requirement :
1 - Backhoe

6 eq.d.

0.00

1 - Project Engineer

6 md.

0.00

1 - Foreman

6 md.

0.00

48 md.

0.00

Manpower Requirement

8 - Laborer
Total Cost of Gravel Base Coarse

0.00

0.00

Total Cost of Site Works

0.00

0.00
Pg. 2 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

III. FORMWORKS & SCAFFOLDS

748 sq.m.

184 - 2 x 4 x 10 coco lumber

1226.67 bd.ft.

0.00

328 - 2 x 4 x 8 coco lumber

1749.33 bd.ft.

0.00

7735 bd.ft.

0.00

6,888 bd.ft.

0.00

1547 - 2 x 3 x 10 coco lumber


1722 - 2 x 3 x 8 coco lumber
5mm x 4 x 8 Ordinary Plywood

304 sheets

0.00

4" CW Nails

10 box

0.00

3" CW Nails

5 box

0.00

2 1/2" CW Nails

8 box

0.00

2" CW Nails

8 box

0.00

1" CW Nails

2 box

0.00

TOTAL

Manpower Requirement
1 - Project Engineer
1 - Foreman

25 md.

0.00

25 md.

0.00

5 - Carpenter

125 md.

0.00

5 - Laborer

125 md.

0.00

Total Cost of Formworks & Scaffolds

0.00

0.00

IV. REINFORCED CONCRETE WORKS


4.1 Foundation

301.997 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps

302 cu.m.

0.00

110 - 20 mm x 9.0 m. def. bars (gr. 60 2441.34

kg.

0.00

210 - 20 mm x 7.5.0 m. def. bars (gr.

3883.95

kg.

0.00

1068 - 20 mm x 6.0 m. def. bars (gr. 6

15802

kg.

0.00

40 - 16 mm x 9.0 m. def. bars (gr. 60)

568.08

kg.

0.00

1030 - 16 mm x 6.0 m. def. bars (gr. 6 9752.04

kg.

0.00

5 rolls

0.00

# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator

10 eq.d.

0.00

Pg. 3 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

Manpower Requirements
1 - Project Engineer

53 md.

0.00

1 - Foreman

53 md.

0.00

424 md.

0.00

424 md.

0.00

1060 md.

0.00

8 - Steelman
8 - Mason
20 - Laborer
Total Cost of Foundation
4.2 Footing Tie Beam

0.00
16.107 cu.m.

Premix Concrete w/ pumpcrete (4000 ps 16.107 cu.m.

0.00

96 - 16 mm x 7.5.0 m. def. bars

1136.16

kg.

0.00

144 - 16 mm x 6.0 m. def. bars

1363.39

kg.

0.00

232 - 10 mm x 6.0 m. def. bars

858.864

kg.

0.00

2 rolls

0.00

# 16 Tie Wire

0.00

Equipment Requirement
1 - Concrete Vibrator

2 eq.d.

0.00

5 md.

0.00

Manpower Requirements
1 - Project Engineer
1 - Foreman

5 md.

0.00

8 - Steelman

40 md.

0.00

4 - Mason

20 md.

0.00

16 - Laborer

80 md.

0.00

Total Cost of Footing Tie Beam


4.3 Grade Beam/ Wall Footing

0.00
23.919 cu.m.

Premix Concrete w/ pumpcrete (4000 ps 23.919 cu.m.

0.00

12 - 16 mm x 7.5.0 m. def. bars


88 - 16 mm x 6.0 m. def. bars
195 - 10 mm x 6.0 m. def. bars
# 16 Tie Wire

0.00

142.02

kg.

0.00

833.184

kg.

0.00

721.89

kg.

0.00

2 rolls

0.00

Pg. 4 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

Equipment Requirement
1 - Concrete Vibrator

2 eq.d.

0.00

1 - Project Engineer

4 md.

0.00

1 - Foreman

4 md.

0.00

8 - Steelman

32 md.

0.00

4 - Mason

16 md.

0.00

16 - Laborer

64 md.

0.00

Manpower Requirements

Total Cost of Grade Beam / Wall Footing


4.4 Ground Floor Column

0.00

0.00

38.298 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 38.298 cu.m.

0.00

508 - 20 mm x 9.0 m. def. bars

11275

kg.

0.00

532 - 10 mm x 6.0 m. def. bars

1969.46

kg.

0.00

6 rolls

0.00

# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator

3 eq.d.

0.00

1 - Project Engineer

15 md.

0.00

1 - Foreman

15 md.

0.00

8 - Steelman

120 md.

0.00

8 - Mason

120 md.

0.00

20 - Laborer

300 md.

0.00

Manpower Requirements

Total Cost of Ground Floor Column


4.5 Second Floor Girder / Beam

0.00

0.00

27.507 cu.m.

Premix Concrete w/ pumpcrete (4000 ps 27.507 cu.m.

0.00

76 - 20 mm x 7.5.0 m. def. bars

1405.62

kg.

0.00

317 - 20 mm x 6.0 m. def. bars

4690.33

kg.

0.00
Pg. 5 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

10 - 16 mm x 6.0 m. def. bars


453 - 10 mm x 6.0 m. def. bars
# 16 Tie Wire

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

94.68

kg.

0.00

1677

kg.

0.00

3 rolls

0.00

TOTAL

Equipment Requirement
1 - Concrete Vibrator

2 eq.d.

0.00

1 - Project Engineer

9 md.

0.00

1 - Foreman

9 md.

0.00

72 md.

0.00

72 md.

0.00

180 md.

0.00

Manpower Requirements

8 - Steelman
8 - Mason
20 - Laborer
Total Cost of Second Floor Girder/ Beam
4.6 Ground Floor Slab

0.00

0.00

46.196 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 46.196 cu.m.

0.00

442 - 10 mm x 6.0 m. def. bars

kg.

0.00

1 rolls

0.00

# 16 Tie Wire

1636.28

Equipment Requirement
1 - Concrete Vibrator

4 eq.d.

0.00

1 - Project Engineer

5 md.

0.00

1 - Foreman

5 md.

0.00

8 - Steelman

40 md.

0.00

8 - Mason

40 md.

0.00

100 md.

0.00

Manpower Requirements

20 - Laborer
Total Cost of Ground Floor Slab
4.7 Second Floor Slab

0.00

0.00

40.287 cu.m.
Pg. 6 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 40.287 cu.m.

0.00

1518 - 12mm x 6.0 m. def. bars


1103 - 10 mm x 6.0 m. def. bars
# 16 Tie Wire

8087.9

kg.

0.00

4083.31

kg.

0.00

4 rolls

0.00

Equipment Requirement
1 - Concrete Vibrator

4 eq.d.

0.00

13 md.

0.00

Manpower Requirements
1 - Project Engineer
1 - Foreman

13 md.

0.00

8 - Steelman

104 md.

0.00

8 - Mason

104 md.

0.00

20 - Laborer

260 md.

0.00

Total Cost of Second Floor Slab


4.8 Second Floor Cantilever Slab

0.00

0.00

8.281 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
346 - 16mm x 6.0 m. def. bars
# 16 Tie Wire

8.281 cu.m.
3275.93

0.00

kg.

0.00

1 rolls

0.00

Equipment Requirement
1 - Concrete Vibrator

1 eq.d.

0.00

1 - Project Engineer

5 md.

0.00

1 - Foreman

5 md.

0.00

8 - Steelman

40 md.

0.00

4 - Mason

20 md.

0.00

15 - Laborer

75 md.

0.00

Manpower Requirements

Total Cost of Second Floor Cantilever Slab

0.00

0.00
Pg. 7 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

4.9 1st to 2nd Stair Case A

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

6.99 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps

6.99 cu.m.

0.00

34 - 16mm x 6.0 m. def. bars

321.912

kg.

0.00

62 - 10 mm x 6.0 m. def. bars

229.524

kg.

0.00

12

kg.

0.00

# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator

1 eq.d.

0.00

1 - Project Engineer

2 md.

0.00

1 - Foreman

2 md.

0.00

4 - Steelman

8 md.

0.00

8 md.

0.00

20 md.

0.00

Manpower Requirements

4 - Mason
10 - Laborer
Total Cost of 1st to 2nd Stair Case A
4.10 1st to 2nd Stair Case B

0.00

0.00

9.752 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
54 - 16mm x 6.0 m. def. bars
60 - 10 mm x 6.0 m. def. bars
# 16 Tie Wire

9.752 cu.m.

0.00

511.272

kg.

0.00

222.12

kg.

0.00

15

kg.

0.00

Equipment Requirement
1 - Concrete Vibrator

1 eq.d.

0.00

3 md.

0.00

Manpower Requirements
1 - Project Engineer
1 - Foreman

3 md.

0.00

4 - Steelman

12 md.

0.00

4 - Mason

12 md.

0.00
Pg. 8 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.
8 - Laborer

QTY.

UNIT

LABOR COST

TOTAL

UNIT

24 md.

Total Cost of 1st to 2nd Stair Case B


4.11 Second Floor Column

MATERIAL COST
UNIT

TOTAL
0.00

0.00

0.00

17.483 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 17.483 cu.m.

0.00

508 - 20 mm x 6.0 m. def. bars

7516.37

kg.

0.00

484 - 10 mm x 6.0 m. def. bars

1791.77

kg.

0.00

5 rolls

0.00

# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator

2 eq.d.

0.00

1 - Project Engineer

10 md.

0.00

1 - Foreman

10 md.

0.00

8 - Steelman

80 md.

0.00

80 md.

0.00

200 md.

0.00

Manpower Requirements

8 - Mason
20 - Laborer
Total Cost of Second Floor Column
4.12 Third Floor Girder / Beam

0.00

0.00

27.509 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 27.509 cu.m.

0.00

76 - 20 mm x 7.5.0 m. def. bars

1405.62

kg.

0.00

317 - 20 mm x 6.0 m. def. bars

4690.33

kg.

0.00

94.68

kg.

0.00

1677

kg.

0.00

3 rolls

0.00

10 - 16 mm x 6.0 m. def. bars


453 - 10 mm x 6.0 m. def. bars
# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator

2 eq.d.

0.00

Pg. 9 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

Manpower Requirements
1 - Project Engineer

9 md.

0.00

1 - Foreman

9 md.

0.00

72 md.

0.00

72 md.

0.00

180 md.

0.00

8 - Steelman
8 - Mason
20 - Laborer
Total Cost of Third Floor Girder/ Beam
4.13 Third Floor Slab

0.00

0.00

48.568 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps 48.568 cu.m.

0.00

1518 - 12mm x 6.0 m. def. bars


1103 - 10 mm x 6.0 m. def. bars
# 16 Tie Wire

8087.9

kg.

0.00

4083.31

kg.

0.00

4 rolls

0.00

Equipment Requirement
1 - Concrete Vibrator

4 eq.d.

0.00

14 md.

0.00

Manpower Requirements
1 - Project Engineer
1 - Foreman

14 md.

0.00

8 - Steelman

112 md.

0.00

8 - Mason

112 md.

0.00

20 - Laborer

280 md.

0.00

Total Cost of Third Floor Slab


4.14 Third Floor Cantilever Slab

0.00

0.00

8.281 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
346 - 16mm x 6.0 m. def. bars
# 16 Tie Wire

8.281 cu.m.
3275.93

0.00

kg.

0.00

1 rolls

0.00

Equipment Requirement
Pg. 10 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

1 - Concrete Vibrator

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

1 eq.d.

0.00

5 md.

0.00

Manpower Requirements
1 - Project Engineer
1 - Foreman

5 md.

0.00

8 - Steelman

40 md.

0.00

4 - Mason

20 md.

0.00

15 - Laborer

75 md.

0.00

Total Cost of Third Floor Cantilever Slab


4.15 2nd to 3rd Stair Case A

0.00

0.00

6.99 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps

6.99 cu.m.

0.00

34 - 16mm x 6.0 m. def. bars

321.912

kg.

0.00

62 - 10 mm x 6.0 m. def. bars

229.524

kg.

0.00

12

kg.

0.00

# 16 Tie Wire
Equipment Requirement
1 - Concrete Vibrator

1 eq.d.

0.00

1 - Project Engineer

2 md.

0.00

1 - Foreman

2 md.

0.00

4 - Steelman

8 md.

0.00

8 md.

0.00

20 md.

0.00

Manpower Requirements

4 - Mason
10 - Laborer
Total Cost of 2nd to 3rd Stair Case A
4.16 2nd to 3rd Stair Case B

0.00

0.00

9.752 cu.m.

Material Requirements
Premix Concrete w/ pumpcrete (4000 ps
54 - 16mm x 6.0 m. def. bars
60 - 10 mm x 6.0 m. def. bars

9.752 cu.m.

0.00

511.272

kg.

0.00

222.12

kg.

0.00
Pg. 11 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

# 16 Tie Wire

UNIT

15

kg.

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

0.00

Equipment Requirement
1 - Concrete Vibrator

1 eq.d.

0.00

1 - Project Engineer

3 md.

0.00

1 - Foreman

3 md.

0.00

4 - Steelman

12 md.

0.00

4 - Mason

12 md.

0.00

8 - Laborer

24 md.

0.00

Manpower Requirements

V.

Total Cost of 2nd to 3rd Stair Case B

0.00

0.00

Total Cost of Reinforced Concrete Works

0.00

0.00

MASONRY WORKS
5.1 Ground Floor

541.96 sq.m.

Material Requirements
6" CHB (machine made)
349 - 10 mm x 6.0 m. def. bars
#16 GI Tie Wire
Portland Cement
Coarse Sand

6,775

pc.

0.00

1292

kg.

0.00

30

kg.

0.00

542 bag

0.00

46 cu.m.

0.00

Manpower Requirements
1 - Project Engineer

14 md.

0.00

1 - Foreman

14 md.

0.00

4 - Steelman

56 md.

0.00

4 - Mason

56 md.

0.00

112 md.

0.00

8 - Laborer
Total Cost of Ground Floor Masonry
5.2 Second Floor

0.00

0.00

374.66 sq.m.
Pg. 12 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

Material Requirements
6" CHB (machine made)
235 - 10 mm x 6.0 m. def. bars
#16 GI Tie Wire
Portland Cement
Coarse Sand

4,684

pc.

0.00

869.97

kg.

0.00

23

kg.

0.00

375 bag

0.00

32 cu.m.

0.00

Manpower Requirements
1 - Project Engineer

9 md.

0.00

1 - Foreman

9 md.

0.00

4 - Steelman

36 md.

0.00

4 - Mason

36 md.

0.00

8 - Laborer

72 md.

0.00

Total Cost of Second Floor Masonry

0.00

0.00

Total Cost of Masonry Works

0.00

0.00

VI. TILE WORKS


6.1 Ground Floor

248.22 sq.m.

Material Requirements
6.1.1 Flooring
0.60 x 0.60 Porcelain Tiles
Portland Cement
Fine Sand
Grouting Cement
6.1.2 Comfort Room
0.30 x 0.30 Ceramic tiles (Mariwasa)
Portland Cement
Fine Sand
Grouting Cement
Tile Trim
6.1.3 Sink / Lavatory

184.06 sq.m.
520

pc.

0.00

57 bag

0.00

5 cu.m.
10 bag

0.00
0.00

59.12 sq.m.
690

pc.

0.00

18 bag

0.00

1.5 cu.m.

0.00

8 bag

0.00

19 lgth.

0.00

5.04 sq.m.
Pg. 13 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

0.60 x 0.60 Porcelain Tiles


Portland Cement
Fine Sand

QTY.

UNIT

20

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

pc.

0.00

2 bag

0.00

0.20 cu.m.

TOTAL

0.00

Grouting Cement

1 bag

0.00

Tile Trim

3 lgth.

0.00

Manpower Requirements
1 - Project Engineer

11 md.

0.00

1 - Foreman

11 md.

0.00

5 - Installer

55 md.

0.00

5 - Helper

55 md.

0.00

Total Cost of Ground Floor tiles


6.2 Second Floor

0.00

0.00

272.10 sq.m.

Material Requirements
6.2.1 Flooring
0.60 x 0.60 Granite Base Tile Unglazed
Portland Cement
Fine Sand
Grouting Cement
6.2.2 Comfort Room
0.30 x 0.30 Ceramic tiles
Portland Cement
Fine Sand

184.06 sq.m.
520

pc.

0.00

57 bag

0.00

5 cu.m.
10 bag

0.00
0.00

73.24 sq.m.
820

pc.

0.00

23 bag

0.00

2 cu.m.

0.00

Grouting Cement

10 bag

0.00

Tile Trim

25 lgth.

0.00

6.2.3 Sink / Lavatory


0.60 x 0.60 Porcelain Tiles
Portland Cement
Fine Sand

14.80 sq.m.
45

pc.

0.00

5 bag

0.00

0.50 cu.m.

0.00

Grouting Cement

2 bag

0.00

Tile Trim

5 lgth.

0.00
Pg. 14 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

Manpower Requirements
1 - Project Engineer

12 md.

0.00

1 - Foreman

12 md.

0.00

5 - Installer

60 md.

0.00

5 - Helper

60 md.

0.00

Total Cost of Second Floor tiles

0.00

0.00

Total Cost of Tile Works

0.00

0.00

VII. DOORS AND WINDOWS

1.00

lot

7.1 Ground Floor


Material Requirements
D - 3 (0.90 x 2.10 Metal Door & Jamb)

2 unit

0.00

D - 6 (0.80 x 1.80 Metal Door & Jamb)

1 unit

0.00

D - 7 (1.0 x 2.10 Metal Door & Jamb)

1 unit

0.00

D - 4 (0.90 x 2.10 Steel Grill Door)

2 unit

0.00

D - 5 (0.80 x 2.10 Steel Grill Door)

1 unit

0.00

D - 8 (0.60 x 1.80 Flush Door)

4 unit

0.00

W - 1 (3.20 x 2.0 Steel Casement Wind

6 unit

0.00

W - 2 (3.20x 1.40 Steel Casement Win

1 unit

0.00

W - 3 (4.0 x 0.585 Steel Grill Window)

3 unit

0.00

W - 4 (4.0 x 1.10 Steel Grill Window)

1 unit

0.00

W - 5 (2.50 x 1.10 Steel Grill Window)

1 unit

0.00

Manpower Requirements
1 - Project Engineer

10 md.

0.00

1 - Foreman

10 md.

0.00

2 - Installer

20 md.

0.00

2 - Helper

40 md.

0.00

Total Cost of Ground Floor Doors & Windows

0.00

0.00

7.2 Second Floor


Pg. 15 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

Material Requirements
D - 3 (0.90 x 2.10 Metal Door & Jamb)

1 unit

0.00

D - 9 (0.90 x 2.10 Metal Dutch Door )

1 unit

0.00

D - 4 (0.90 x 2.10 Steel Grill Door)

2 unit

0.00

D - 5 (0.80 x 2.10 Steel Grill Door)

1 unit

0.00

D - 8 (0.60 x 1.80 Flush Door w/ access

4 unit

0.00

D - 10 (0.70 x 2.10 PVC Door)

2 unit

0.00

W - 1 (3.20 x 2.0 Steel Casement Wind

5 unit

0.00

W - 2 (3.20x 1.40 Steel Awning Window

1 unit

0.00

W - 3 (4.0 x 0.585 Steel Grill Window)

4 unit

0.00

W - 4 (4.0 x 1.10 Steel Grill Window)

1 unit

0.00

W - 5 (2.50 x 1.10 Steel Grill Window)

1 unit

0.00

W - 6 (1.60 x 2.0 Steel Casement Wind

1 unit

0.00

W - 7 (0.80x 1.40 Steel Awning Window

1 unit

0.00

Door Knob

set

0.00

10 gal.

0.00

Metal Primer
2" Paint Brush

pc.

0.00

Manpower Requirements
1 - Project Engineer

10 md.

0.00

1 - Foreman

10 md.

0.00

2 - Installer

20 md.

0.00

2 - Helper

40 md.

0.00

Total Cost of Second Floor Doors & Windows

0.00

0.00

Total Cost of Doors & Windows

0.00

0.00

VIII. PLASTERING WORKS


1. Ground Floor

305.60 sq.m.

Material Requirements
Portland Cement
Fine Sand

69 bag
8 cu.m.

0.00
0.00

Manpower Requirements
Pg. 16 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

1 - Project Engineer

2 md.

0.00

1 - Foreman

2 md.

0.00

2 - Mason

4 md.

0.00

4 - Laborer

8 md.

0.00

Total Cost of Ground Floor Plastering


2. Second Floor

0.00

0.00

349.88 sq.m.

Material Requirements
Portland Cement
Fine Sand

79 bag
9 cu.m.

0.00
0.00

Manpower Requirements
1 - Project Engineer

8 md.

0.00

1 - Foreman

8 md.

0.00

3 - Mason

24 md.

0.00

3 - Laborer

24 md.

0.00

Total Cost of Second Floor Plastering

0.00

0.00

Total Cost of Plastering Works

0.00

0.00

IX. STEEL WORKS

1.00

lot

9.1 Second Floor


Material Requirements
9.1.1 Railing
16mm Square bar

9 lgth.

0.00

12mm Square bar

54 lgth.

0.00

Welding Rod

10

kg.

0.00

Metal Primer

2 gal.

0.00

2" Paint Brush

pc.

0.00

Hacksaw Blade

pc.

0.00

90

pc.

0.00

9.1.2 Embedded Bolt


1/2" x 6" Stainless Bolt

Pg. 17 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

20mm x 30mm Anchor Bolt

QTY.

UNIT
8

pc.

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

0.00

Manpower Requirements
1 - Project Engineer

5 md.

0.00

1 - Foreman

5 md.

0.00

1 - Welder

5 md.

0.00

10 md.

0.00

2 - Laborer
Total Cost of Second Floor Steel Works

0.00

0.00

Total Cost of Steel Works

0.00

0.00

X. PLUMBING WORKS

1.00

lot

Water Closet

set

0.00

Floor Drain

set

0.00

Urinal

set

0.00

Lavatory w/ faucet

set

0.00

Laboratory Sink w/ Gooseneck Faucet

set

0.00

10. 1 Ground Floor


Material Requirements
10.1.1 Fixtures

10.1.2 Sewer Line


100mm PVC Pipe S1000

24 lgth.

0.00

75mm PVC Pipe S1000

8 lgth.

0.00

50mm PVC Pipe S1000

15 lgth.

0.00

100mm x 100mm Wye

12

pc.

0.00

100mm x 75mm Wye Reducer

pc.

0.00

100mm x 50mm Wye Reducer

pc.

0.00

75mm x 75mm Wye

pc.

0.00

100mm Elbow

15

pc.

0.00

75mm Elbow

15

pc.

0.00

50mm Elbow

15

pc.

0.00

100mm Clean Out

pc.

0.00

75mm Clean Out

pc.

0.00
Pg. 18 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

75mm P - Trap

pc.

0.00

50mm P - Trap

pc.

0.00

50mm Tee

pc.

0.00

Solvent Cement

3 can

0.00

63mm PPR Pipe (PN 25)

2 lgth.

0.00

32mm PPR Pipe (PN 20)

10 lgth.

0.00

20mm PPR Pipe (PN 20)

10 lgth.

0.00

TOTAL

10.1.3 Water Line

32mm PPR Elbow

pc.

0.00

20mm PPR Elbow

23

pc.

0.00

32mm x 20mm PPR Tee

pc.

0.00

32mm PPR Tee

pc.

0.00

20mm PPR Tee

pc.

0.00

63mm PPR Coupling (PN 25)

pc.

0.00

32mm PPR Coupling (PN 20)

pc.

0.00

20mm PPR Coupling (PN 20)

pc.

0.00

mtr.

0.00

PPR Nipple

0.50

Manpower Requirements
1 - Project Engineer

13 md.

0.00

1 - Foreman

13 md.

0.00

2 - Plumber

26 md.

0.00

2 - Helper

26 md.

0.00

Total Cost of Ground Floor Plumbing

0.00

0.00

10. 2 Second Floor


Material Requirements
10.2.1 Fixtures
Water Closet

set

0.00

Floor Drain

set

0.00

Urinal

set

0.00

Lavatory w/ faucet

set

0.00

Laboratory Sink w/ Gooseneck faucet

set

0.00
Pg. 19 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

10.2.2 Sewer Line


100mm PVC Pipe S1000

11 lgth.

0.00

75mm PVC Pipe S1000

7 lgth.

0.00

50mm PVC Pipe S1000

20 lgth.

0.00

100mm x 100mm Wye

13

pc.

0.00

100mm x 75mm Wye Reducer

pc.

0.00

100mm x 50mm Wye Reducer

pc.

0.00

75mm x 75mm Wye

pc.

0.00

75mm x 50mm Wye

pc.

0.00

13

pc.

0.00

75mm Elbow

pc.

0.00

50mm Elbow

15

pc.

0.00

100mm Clean Out

pc.

0.00

75mm Clean Out

pc.

0.00

75mm P - Trap

pc.

0.00

50mm P - Trap

pc.

0.00

11

pc.

0.00

3 can

0.00

63mm PPR Pipe (PN 25)

2 lgth.

0.00

32mm PPR Pipe (PN 20)

10 lgth.

0.00

20mm PPR Pipe (PN 20)

12 lgth.

0.00

100mm Elbow

50mm Tee
Solvent Cement
10.2.3 Water Line

32mm PPR Elbow

pc.

0.00

20mm PPR Elbow

pc.

0.00

32mm x 20mm PPR Tee

pc.

0.00

32mm PPR Tee

pc.

0.00

20mm PPR Tee

pc.

0.00

63mm PPR Coupling (PN 25)

pc.

0.00

32mm PPR Coupling (PN 20)

pc.

0.00

20mm PPR Coupling (PN 20)

pc.

0.00

0.5 mtr.

0.00

PPR Nipple
Manpower Requirements

Pg. 20 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

1 - Project Engineer

15 md.

0.00

1 - Foreman

15 md.

0.00

2 - Plumber

30 md.

0.00

2 - Helper

30 md.

0.00

Total Cost of Second Floor Plumbing

0.00

0.00

Total Cost of Plumbing Works

0.00

0.00

XI. ELECTRICAL WORKS


11.1 Main Distribution Panel (MDP 1)

1.00

lot

set

0.00

set

0.00

Material Requirements
Main Breaker : 400AT/500AF, 3P, 230V,
50KAIC
Brs. 5-100AT/100AF, 3P, 230V, 25KAIC
1-60AT/100AF, 3P, 230V, 25KAIC
w/ grounding & neutral terminal
ECB : 60AT/100AF, 3P, 230V, 25KAIC
in NEMA - 3R Encl.
100mm RSC Pipe

3 lgth.

0.00

100mm RSC Elbow

0.00

110mm PVC Pipe

7 lgth.

0.00

110mm PVC Elbow

0.00

40mm PVC Pipe

pc.
pc.

33 lgth.

0.00

40mm PVC Elbow

pc.

0.00

100mm Entrance Cap

pc.

0.00

8.0mm2 THHN Wire

4 mtr.

0.00

22mm THHN Wire

30 mtr.

0.00

30mm THHN Wire

21 mtr.

0.00

50mm2 THHN Wire

28 mtr.

0.00

100 mtr.

0.00

2
2

250mm THHN Wire


2

Electrical tape

10

roll

0.00

Ga. 14 Tie Wire

kg.

0.00

Cable Tie 12"

2 bag

0.00

Concrete Pedestal

0.00

lot

Pg. 21 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

Manpower Requirements
1 - Project Engineer

12 md.

0.00

1 - Foreman

12 md.

0.00

2 - Electrician

24 md.

0.00

4 - Helper

96 md.

0.00

Total Cost of Main Distribution Panel

0.00

0.00

11.2 Ground Floor


Material Requirements
LPPB - 1

set

0.00

Thumbler 1-Gang Switch, 15A, 250V

set

0.00

Thumbler 2-Gang Switch, 15A, 250V

set

0.00

100AT/100AF, 3P, 230V, 25KAIC


Brs. 5-20AT/100AF,2P, 230V, 10KAIC
9-30AT/100AF, 2P, 230V, 10KAIC
w/ grounding & neutral terminal

Thumbler 3way, 1-Gang Switch, 15A,

set

0.00

10

set

0.00

1 - 40W, FL-Box type w/ electronic balla

set

0.00

2 - 40W, FL-Box type w/ electronic balla

6" Pinlight w/ 23W CFL lamp

28

set

0.00

Emergency Light, Twin Bulb

set

0.00

Convenience Outlet 1 gang, 3 prong, 2

set

0.00

Convenience Outlet duplex, 3 prong, 2

17

set

0.00

Single Convenience Outlet w/ GFCI

set

0.00

Aircon Outlet, 3 prong, 250V

set

0.00

25mm PVC Pipe

40 lgth.

0.00

20mm PVC Pipe

106 lgth.

0.00

Conduit Fittings

lot

0.00

5.5mm THHN Wire

600 mtr.

0.00

3.5mm THHN Wire

1200 mtr.

0.00

2.0mm THHN Wire

450 mtr.

0.00

2
2
2

Utility Box 2"x4" D.T. metal ga. 18

60

pc.

0.00

Junction Box 4x4 D.T. metal ga.18 w/ c

75

pc.

0.00
Pg. 22 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

Square Box 4 11/16D.T. metal ga.18 w/


Pullboxes

QTY.

UNIT
5

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

pc.

0.00

pc.

0.00

GI Tie Wire ga. 16

10

kg.

0.00

Electrical Tape

15

roll

0.00

12.5 mtr.

0.00

1/2mm Flexible Mettalic Pipe


1/2mm Straight Connector

pc.

0.00

200cc PVC Solvent

3 can

0.00

TOTAL

Manpower Requirements
1 - Project Engineer

10 md.

0.00

1 - Foreman

10 md.

0.00

2 - Electrician

20 md.

0.00

4 - Helper

80 md.

0.00

Total Cost of Ground Floor Electrical

0.00

0.00

11.3 Second Floor


Material Requirements
LPPB - 1

set

0.00

Thumbler 1-Gang Switch, 15A, 250V

set

0.00

Thumbler 2-Gang Switch, 15A, 250V

set

0.00

100AT/100AF, 3P, 230V, 25KAIC


Brs. 5-20AT/100AF,2P, 230V, 10KAIC
9-30AT/100AF, 2P, 230V, 10KAIC
w/ grounding & neutral terminal

Thumbler 3way, 1-Gang Switch, 15A,

set

0.00

13

set

0.00

1 - 40W, FL-Box type w/ electronic balla

set

0.00

2 - 40W, FL-Box type w/ electronic balla

6" Pinlight w/ 23W CFL lamp

27

set

0.00

Emergency Light, Twin Bulb

set

0.00

Convenience Outlet 1 gang, 3 prong, 2

set

0.00

Convenience Outlet duplex, 3 prong, 2

17

set

0.00

Single Convenience Outlet w/ GFCI

set

0.00

Aircon Outlet, 3 prong, 250V

set

0.00

25mm PVC Pipe

35 lgth.

0.00
Pg. 23 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

20mm PVC Pipe


Conduit Fittings

QTY.

UNIT

150 lgth.
1

lot

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT
0.00
0.00

5.5mm2 THHN Wire

600 mtr.

0.00

3.5mm THHN Wire

1200 mtr.

0.00

2.0mm THHN Wire

450 mtr.

0.00

40mm PVC Pipe

8 lgth.

0.00

40mm PVC Elbow

pc.

0.00

8.0mm THHN Wire

8 mtr.

0.00

22mm THHN Wire

50 mtr.

0.00

30mm2 THHN Wire

25 mtr.

0.00

Utility Box 2"x4" D.T. metal ga. 18

60

pc.

0.00

Junction Box 4x4 D.T. metal ga.18 w/ c

75

pc.

0.00

Square Box 4 11/16D.T. metal ga.18 w/

pc.

0.00

Pullboxes

pc.

0.00

GI Tie Wire ga. 16

kg.

0.00

15

roll

0.00

12.5 mtr.

0.00

Electrical Tape
1/2mm Flexible Mettalic Pipe

TOTAL

1/2mm Straight Connector

pc.

0.00

200cc PVC Solvent

3 can

0.00

Manpower Requirements
1 - Project Engineer

10 md.

0.00

1 - Foreman

10 md.

0.00

2 - Electrician

20 md.

0.00

4 - Helper

80 md.

0.00

Total Cost of Second Floor Electrical

0.00

0.00

Total Cost of Electrical Works

0.00

0.00

XII. STORM DRAINAGE

sq.m.

Material Requirements
100mm PVC Pipe S1000

69 lgth.

0.00

100mm Elbow

23

pc.

0.00

4.00

can

0.00

400cc PVC Solvent

Pg. 24 of 19
19 October 2012

MATERIALS TAKE- OFF AND COST ESTIMATES


PROJECT
LOCATION

: CONSTRUCTION OF
:

ITEM

DESCRIPTION

NO.

QTY.

UNIT

MATERIAL COST
UNIT

LABOR COST

TOTAL

UNIT

TOTAL

Manpower Requirements
1 - Project Engineer

3 md.

0.00

1 - Foreman

3 md.

0.00

1 - Laborer

3 md.

0.00

Total Cost of Storm Drainage

0.00

TOTAL DIRECT COST

0.00

0.00

INDIRECT COST
OCM (12%)
Contractor's Profit (10%)
VAT & Withholding Tax (12%)
TOTAL INDIRECT COST
SUB-TOTAL (ABC)
ADMINISTRATIVE COST (3.5%)
TOTAL ESTIMATED COST

Prepared by:

Noted :

Engr.
Quantity Surveyor/Estimator

PROJECT MANAGER

Pg. 25 of 19
19 October 2012

TOTAL
ITEM COST
0.00

0.00
0.00

0.00
0.00
*** 70cu.m./4hrs.

Pg. 26 of 19
19 October 2012

TOTAL
ITEM COST

0.00

0.00

#DIV/0!

0.00
0.00

#DIV/0!

#DIV/0!
Pg. 27 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

2441.34
3883.95
15802.128
568.08
9752.04

Pg. 28 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

1136.16

16

1363.392
858.864
858.864

0.00

#DIV/0!

142.02
833.184
721.89
858.864

Pg. 29 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

11274.552
1969.464

0.00

#DIV/0!

1405.62
4690.332
Pg. 30 of 19
19 October 2012

TOTAL
ITEM COST
94.68
1677.006

0.00

#DIV/0!

1636.284

0.00

#DIV/0!

Pg. 31 of 19
19 October 2012

TOTAL
ITEM COST

8087.904
4083.306

0.00

#DIV/0!

3275.928

0.00

#DIV/0!
Pg. 32 of 19
19 October 2012

TOTAL
ITEM COST

321.912
229.524

0.00

#DIV/0!

511.272
222.12

Pg. 33 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

7516.368
1791.768

0.00

#DIV/0!

1405.62
4690.332
94.68
1677.006

Pg. 34 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

8087.904
4083.306

0.00

#DIV/0!

3275.928

Pg. 35 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

321.912
229.524

0.00

#DIV/0!

511.272
222.12
Pg. 36 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

0.00

0.00

1291.998

0.00

#DIV/0!

Pg. 37 of 19
19 October 2012

TOTAL
ITEM COST

869.97

0.00

#DIV/0!

0.00

#DIV/0!

0.00

511.2777777778

Pg. 38 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

Pg. 39 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

0.00

0.00

222.12

0.00

Pg. 40 of 19
19 October 2012

TOTAL
ITEM COST

1.68
3696

700

4396

0.00
0.00

#DIV/0!

0.00

7.64
68.76

Pg. 41 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!
8.747
78.723

0.00

#DIV/0!

0.00

#DIV/0!

Pg. 42 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

0.00

0.00

Pg. 43 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

Pg. 44 of 19
19 October 2012

TOTAL
ITEM COST

Pg. 45 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

0.00

0.00

222.12

Pg. 46 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

Pg. 47 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

Pg. 48 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!

0.00

#DIV/0!

0.00

Pg. 49 of 19
19 October 2012

TOTAL
ITEM COST

0.00

#DIV/0!
0.00

0.00
0.00
0.00

0.00

0.00
0.00
0.00
0.00

6,000,000.00

Pg. 50 of 19
19 October 2012

Вам также может понравиться