LARSEN & TOUBRO CONSTRUCTION

Quality Assurance Plan


BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 1 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

CONSTRUCTION WORK PROCEDURE


FOR
TYPICAL TOILETS WATER PROOFING WORKS
(UPPAL DEPOT) IN HMRP
Document No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00.
Works at
Stations

Depots

Viaduct

Casting yard

Discipline
Civil

Mechanical

Electrical

Railways

Issue status
For review

For approval

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 3 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

INDEX
Clause

Clause Description

1.0

SCOPE OF WORK

2.0

TECHNICAL SPECIFICATION REFERENCES

3.0

OPERATING STRATEGY

4.0

SEQUENCE OF ACTIVITIES

5.0

CONSTRUCTION METHODOLOGY

6.0

QUALITY CONTROL & QUALITY ASSURANCE


6.1

INSPECTION PLAN (IP)

6.2

TEST PLAN (TP)

6.3

QUALITY FORMATS

7.0

8.0

Page No.

ENVIRONMENT, HEALTH & SAFETY


7.01

ENVIRONMENTAL TEST

7.02

HEALTH

7.03

SAFETY
ATTACHEMENTS/ANNEXURES

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 4 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

SCOPE OF WORK:

This Construction Work Procedure is applicable for execution of Typical Toilet Water Proofing works as per
approved drawing and technical specification, at Uppal Depot, Hyderabad Metro Rail Project.
This work procedure includes the following:

a.
b.
c.
d.
e.
2

Surface Preparation & Cleaning of Joint portion


Pressure Grouting/Injection Grouting
Water Pond test
Water Proofing coat
Protective layer

TECHNICAL SPECIFICATION REFERENCES:

2.1. CODES & SPECIFICATIONS:

IRS: Concrete Bridge Code


MORTH Specifications
National Building Code of India (NBC 2005)
IS 3370 part-1 Method of Hydro test
Safety, Health & Environment (SHE) Manual document no.: L&TMRHL/OE/SATGE2A/D-8/2, Rev 1.
Safety, Health & Environment CONDITIONS Document no.: L&TMRHL/OE/STAGE2A/D-8/1, Rev 0.

2.2 DRAWINGS:
i)
S.No

MAIN WORK DRAWINGS:


Drawing NO.
As per technical Specifications and
Manufacturers recommendations

Rev no

Description

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 5 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
3.0

OPERATING STRATEGY:

3.1

ORGANISATION CHART

XXXXXXXX
PROJECT MANAGER

XXXXXXX
PLANNING

xxxxxxxxxxxx
CONSTRUCTION
MANAGER

XXXXXXX
P&M
INCHARGE

XXXXXXX
SHE MANAGER

XXXXXX
QUALITY

xxxxxxxxxxx
Site Engineer
(Day & Night)
XXXXXX
P&M Engineer

Safety
Steward

Xxxxxxxx
Q/C Engineer

xxxxxxxx
Q/A Engineer

XXXXXXXX
Site Engineer
(Day & Night)

3.1.1 Roles & Responsibilities


3.1.1.1. Project Manager

Organize & manage all resources and field activities to achieve an efficient and effective completion
of the contract, within the agreed time and cost, whilst paying due regard to safety and meeting
Quality requirements.

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 6 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
3.1.1.2. Planning Engineer:

Ensures information to LTMRHL at various stage of the activity.


Co-ordinates with all concern departments for technical and administrative help.
Coordinates to get statutory permits from all concerned.
Monitors optimum utilization of machine and equipment.
Involves in Safety and Quality Pep talks regularly.

3.1.1.3. Construction Manager:

Ensure the construction activity as per approved construction & work methods.
Ensure completion of activities to meet the project time schedules
Organize & manage all resources and field activities to achieve an efficient and effective completion
of the contract, within the agreed time and cost, whilst paying due regard to safety and meeting
Quality requirements.
Implementation of Project Quality Plan, EHS Plan, Liaison with Customer, Regional, Head Office and
local authorities.
Negotiation with S/c and suppliers for fixing rates.
Improving Customer satisfaction including handling customer complaints

3.1.1.4. Site Engineer:

Co-ordinate with Water proofing agency on day to day activities to monitor work sequence &
progress.
Ensure the materials brought to site for work is approved one only.
To ensure the work shall be executed and inspected stage wise as per approved work procedure.
Interacts with the LTMRHL Representatives and generates RFIs for inspection activity as per Inspection
plan.
To ensure that the relevant project specification, approved working procedure and approved shop
drawings are available in coordination with construction manager and QC engineer.
Submits the requirement of materials and other resources for his work to Construction manager.
Liaison with internal departments like Planning cell, Quality control cell, Plant & Machinery
department, Safety department and Stores for synchronizing all activities in execution.
Ensures to implement all mandatory safety requirements within his work limits.
Ensure all works are carried out as per the working procedure.
Follows the Inspection plan, Test plans and submits records to LTMRHL for their reviews and approval
through EDMS.
Maintain all format and checklist

3.1.1.5. P&M Incharge:

Responsible for equipment fitness inspection, monitoring and maintain records.


Responsible for all mechanical and electrical equipments ensuring continuous availability and proper
functioning of P&M at site.
Ensure periodic preventive maintenance & timely breakdown repairs of all machinery & electrical
equipment as per their inspection manuals.
Ensure operation of P&M as per company norms

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 7 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
3.1.1.6. P&M Engineer:

Responsible for Operational inspection and maintenance of P&M equipments on regular basis
Reporting of required data related for operation and maintaining records.
Responsible for co-ordination with site engineer for arranging dewatering pump.
Responsible for arranging power supply at workplace day to day basis by co-ordination with site
engineer.
Ensure continuous availability and proper functioning of P&M at site.
Ensure periodic preventive maintenance & timely breakdown repairs of all machinery & electrical
equipment as per their inspection manuals.

3.1.1.7. Quality Head/Incharge:

Review & advice Quality Assurance Management Plans for Approval


Issue and validate codes & standards.
Deploy & control movement of QA/QC staff of the project
Monitor & control Quality performance of HMRL jobs
Conduct Internal Audits of the project
Monitor Corrective & Preventive actions
Procurement inspection/C0-ordination of Specialized vendor items

3.1.1.8. Quality Engineer(QC/QA):

Check the quality of materials cement, Fine aggregate and Coarse aggregates etc.
Check and ensure the water proofing materials batch number, manufacturing date, MTC and expiry
date before opening the seal for usage.
Responsible for inspecting the stage wise work as per IPT and clearing for next stage activity after
getting clearance from LTMRHL.
Responsible for the compressive strength of the concrete, cement mortar batched at site or RMC
Identify material sources, and conduct material tests and ensure conformity with specifications &
standards
Conduct Routine Tests on materials as per ITP for conformance and maintain records.
Identify, Calibrate and maintain Master List of Testing and Measuring Equipment
Responsible for submission of all reports related to quality matters

3.1.1.9. Quality Supervisor/Mate:

Responsible for casting of concrete/Mortar cubes for every batch produced from the plant or site.
Responsible for the compressive strength of the concrete/Mortar batched at site.

3.1.1.10. SHE Manager:

Disseminate and Communicate HSE Policy, HSE Management System requirements to site personnel.
Provide necessary advice, information and support in the effective implementation of the HSE
Management System requirements and this HSE plan.
Updating the HSE Plan to the requirements of the activities being carried out when there is a revision.
Plan and conduct Internal HSE training programs, initiate drive to promote HSE awareness and
performance

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 8 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

Carry out HSE inspection of Work Area, Work Method, etc. as per the IMS requirement.
Advising line management in preparing HSE risk assessment for the new activities.
Creating HSE awareness through PEP talks.
Conduct investigation of all incidents / dangerous occurrences & recommend appropriate corrective
measures.
Advice & co-ordinate for implementation of Work Permit Systems.
Convene HSE Committee meeting & minute the proceedings for circulation & follow-up action.
Plan procurement of PPE & safety devices and inspect before use as per laid down norms.
Report to CHSEM on all matters pertaining to status of HSE and promotional programme at site level.
Facilitate screening of workmen and conduct HSE induction.
Monitoring administration of First Aid.
Conduct Fire Drill, Procure, inspect and arrange to maintain Fire Extinguishers.
Organise campaigns, competitions & other special emphasis programmes to promote HSE in the
workplace.
Record, analyse and cascade lateral learning points from First Aid Cases, Near Miss Cases & Accidents
to all project personnel and analyse the trends & effectiveness.
Maintain all HSE related documents & Update HSE training records

3.1.1.11. Safety Engineer:

Identify potentially unsafe acts, areas and implement practice measures and educate staff &
workmen.
Investigate unsafe occurrences and initiate corrective steps.
Discuss near miss accidents with staff and workmen
Involves in regular safety pep talks, periodical demonstrations of safe practices in work.
Helps to provide necessary safety materials as per work requirements.
Implement EHS system at site; supervise for the safety lapse before commencement of work.
Organize training programs for safety awareness.
Coordinates with site administration, first-aid centre, doctors & hospitals during emergency.

3.2 RESOURCE SOURCING:


3.2.1. WORKMEN:
S.No

Manpower
(other than in organization chart)

Nos. per
Day Shift

Nos For
Night Shift

1
2
3

Applicators
Helpers
Mason

02
04
02

02
04
02

4
5

Unskilled
Vendor Supervisor

10
01

10
01

Total Manpower

19

Remarks

19

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 9 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
3.2.2 Materials
1
2
3
4
5
6
7

Cement
Water
CEBEX 200
NITOBOND SBR Latex
HYDROPROOF
SILICA SAND
CONPLAST X 421 IC

3.2.2.1. Cement:

Ordinary Portland cement (OPC) of the following grade shall be used.


43 grade Ordinary Portland Cement conforms to IS: 8112.
53 grade Ordinary Portland Cement conforms to IS: 12269.
Approval of sources and brands of cement shall be obtained from LTMRHL.

3.2.2.2. Water:

Water shall be conformed the IS: 3025 and IRS Concrete Bridge code
Water shall be potable and free from substances that may be deleterious to concrete or
steel. Water shall be fresh, clean and free from injurious amounts of oil, salts, acids, alkali,
other chemicals and organic matter.

3.2.2.3. CEBEX 200:

Cebex 200 is a plasticising and hydrogen free expansion grout admixture is supplied as a powder.
Cebex 200 is a suitable pressure grouting admixture complying with ASTM C827

3.2.2.4. NITOBOND SBR(Latex):

Nitobond SBR (latex) is modified styrene butadiene emulsion specially designed for use as a bonding aid and
gauging liquid for cementitious systems.
Nitobond SBR (Latex) shall be procured only after obtaining approval from LTMRHL.
Nitobond SBR (latex) materials shall be used and application done as per manufacturer specification and
recommendations.

3.2.2.5. HYDROPROOF:
Hydroproof is single component acrylic polymer from cement based water proof composite
coating membrane.
Hydroproof formulated to be mixed with cement on site or simply brush applied over
concrete or masonry surface to provide an effective waterproof membrane.
Hydroproof shall be used and application done as per manufacturer specification and
recommendations.
3.2.2.6. SILICA SAND or RIVER SAND:

River sand shall conform to IS 2836 and IS 383.

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 10 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

3.2.2.7. CONPLAST X 421 IC:

Conplast X421IC is a dark brown liquid based on lignosulphonates which mixes readily with
water and therefore disperses evenly.
Conplast X421IC shall be conformed to IS 2645 2003.
3.2.3

EQUIPMENTS:

Sl.No.

Machinery

Nos. per Day

Remarks

Chipping Machine

One No

For chipping excess concrete and bulging


portion

Marble/Cutting Machine

One No

LPG Cylinder with Heating Torch

As per Site requirement

Spray Machine-Grew 2030

As per Site requirement

Pressure Grouting Machine 40 PSI

As per Site requirement

Epoxy Grout Machine- Cowgley

As per Site requirement

Wooden Float

As per Site requirement

Brush

As per Site requirement

Rollers

As per Site requirement

10

Mason Trowel

As per Site requirement

Batching Plant

As per Site requirement

12

Chiller Plant

As per site requirement

13

Loader

As per site requirement

14

Tippers

As per site requirement

15

Concrete pump /Boom placer

For Concrete pumping.

16

Transit mixers

17
18

Air Compressor
Stone chiselers

1 no. /As per site


requirement
Nos
as
per
site
requirement
01
As per site requirement

19

Water Pump(1/2/5 HP)

As per site requirement

For Curing of Concrete

For concrete production(Calibrated once


in a month)
For
Water
cooling
for
concrete
production.
For bulk materials loading to batching
plant bins
For shifting of materials

For transporting the concrete


batching plant to site.
As per site requirement for cleaning
For joint preparation & cleaning

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

from

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 11 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
4.0 WORK SEQUENCE:
4.01. Surface preparation
4.02. Injection Grouting/Pressure Grouting
4.03. Water pond testing
4.04. Application of Water Proofing coat
4.05. Protective Layer Finishing

5.

CONSTRUCTION METHODOLOGY:

5.01 Surface Preparation:

The joint inspection shall be done prior to surface preparation along with LTMRHL.
If any defect identified, the same should be rectified with approved methodology by LTMRHL.
The concrete surface and construction joints location (Slab & Beam) has to be clean thoroughly by
removing the debris and mortar droppings, loose particles and any other foreign materials, which may
affect the adhesion the further treatments with the mother surface.
If any honeycombs/defects are identified in concrete surface, loose particles shall be removed from
that surface by and it should be finished with approved materials and approved CWP.
HYDROPROOF XTRA and packing the all honeycombed area either Conbextra GP2 / Renderoc RG of
FOSORC

Note: CWP for rectification works shall be submitted separately and obtained approval from LTMRHL.
5.02. Injection Grouting/Pressure Grouting:

5.02.1. Fixing of Nozzles:

The entire construction joint portion at every one meter c/c holes shall be drilled for fixing of nozzles
with drilling machine to the required depth as per annexure scheme drawing.( Annexure xx)
PVC/GI nozzles shall be fixed in to holes and gap shall be filled with quick setting cement only.
The nozzles shall be fixed from inside only. Outside the joint shall be filled with renderoc plug after
cleaning the in around joint.

5.02.2. Mixing of grout Materials:

The approved grout materials shall be procured and shifted to site grouting location.
The grout materials (CEBEX 200 plasticizing and hydrogen free expansion grout admixture) shall be
mixed with cement and water.
The grout materials one pocket (225 grams) shall be mixed with one bag of cement.
Mixing of grout materials shall be done with mechanically powered slow speed drill machine fitted
with stirrer
The cement shall be slowly added to Cebex 200 grout mixture along with water (20 to 22 liters per
bag) and mixed with drill machine.
Mixing shall be continued for 5 minutes as per manufacturer recommendations, till it become smooth
even consistency obtained.

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 12 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
5.02.3. Injection/Pressure Grouting:

After nozzles set completely, the pressure grouting application shall be started.
The grouting machine pipe out let shall be fitted with existing nozzles.
The grout materials shall be grouted with pressure grouting machine (40 Psi capacity) in to nozzles till it
get filled and grout materials shall come out from the nozzle.
The mixed grout materials shall be consumed within 30 minutes of final mixing time.
After completion of grouting the nozzle shall be sealed with renderoc plug materials only.
The nozzles shall be removed after 24 hours or the grout is set, whichever is later.
The exposed portion of nozzles from concrete surface shall be cut and removed.
The depressions shall be filled with renderoc plug materials and finished to match wall surface.

5.03.

Water Ponding Test:

After completion of Injection/pressure grouting, water shall be filled in water tank up to a free board
level.
Water ponding test shall conform the section 10 of IS3370-Part 1.
The water shall be filled up to free board level.
The water level (initial level) shall be marked on wall surface at all corners.
The water level shall be monitored and recorded at subsequent intervals of 24 hours over a period of
seven days along with LTMRHL.
The water ponding test shall be continued for 7 days and level shall be recorded.
The continuous observation shall be done for outer wall surface for any leakage
The total drop in surface level over a period of seven days shall be taken as an indication of the water
tightness of the tank.
If the total drop in surface water level does not exceed 40 mm for a period of seven days, tank may
be deemed to be water-tight.
If the structure does not satisfy the condition of test, and the daily drop in water level decreasing, the
period of test may be extended for a further seven days and if specified limit is then reached, the
structure may be considered as satisfactory.
If any leakage found, it shall be rectified by pressure grouting as explained above in section 5.02.

5.04.

Application of Water Proofing Coat:

5.04.1. Surface Preparation:

After completion of water pond test, water shall be drained out and allow to get dry
concrete surface.
The entire surface to be treated must be ensured thoroughly cleaned.
The surface must also be free from oil, grease, wax or any other foreign materials which might
affect adhesion.
5.04.2. Priming/First Coat:

The approved materials only shall be procured for application.

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 13 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

The primer/first coat shall be prepared with the ratio of 1:2:4 (1 part of Hydroproof: 2 part of
Water: 4 parts of cement)
Mixing shall be done thoroughly with slow speed drilling machine attached with mixing
paddle till it get uniform colour and consistent slurry avoiding any lump formation.
Do not mix more than two minutes.
The mixing materials shall be consumed with in pot life(30 minutes).
Retempering the mix with water should not be done. Occasionally stir the materials till the
entire quantity is applied.
Before application of water proofing paint, the concrete surface shall be weted.
The application shall be done by using paint brush consistently and the application shall be
overlapped 300 mm minimum over the vertical and horizontal surface.
The same paint shall be be applied on wall surface for minimum height of 300 mm from
finished floor level(FFL).
The minimum thickness shall be 1 to 2 mm.
The priming/first coat should be allowed to dry for 5-6 hours.

Note: To control the thickness of coat, the area coverage shall be monitored as per
manufacturer specification, ie. 16 -17 sqm/ liter for Priming/First Coat
5.04.3. Second Coat/Final Coat Application:

After drying of first coat application, second coat application shall be applied.
The second/final coat shall be prepared with the ratio of 1:2 (1 part of Hydroproof: 2 parts of
cement)
The application shall be done same as explained above in section 5.04.2.
When the second coat is in green status, silica/coursed sand shall be sprinkled prior to ensure
bonding with water proof plaster.(grain size of coarse sand shall conform to table 1 of
IS1542)
After application of final coat, initial air drying shall be allowed for 2 to 6 hours. During this
period water should not be used for curing.
Moist curing should be done for the next 24 hours by spraying water on hydroproof coating.
Following moist curing, hydroproof should be allowed to dry for three days before subjecting
it to submersion in water.
Note: To control the thickness of coat, the area coverage shall be monitored as per
manufacturer specification, ie. 4.5 -5.0 sqm/ liter for / Coat

5.05.

Protective Layer Finishing :

5.05.1. Cement Concrete on Floor:

The concrete portion of floor area shall be free from debris and other foreign materials.
Floor area shall be cleaned properly before starting of concrete activity.
40 mm thick level pads shall be fixed at every 6 0 intervals and slope shall be maintained as
per specification and drawings.
After obtaining the clearance and approval of level pads from LTMRHL,(Refer Pour Card)
place the concrete order to batching plant trough QA/QC dept.

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 14 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

Toilet slab/sunken slab area should be free from debris and any other foreign materials. Keep
the sufficient manpower, tools for placing and compaction of concrete.
Ensure the grade of concrete should be as per GFC drawing before unloading from transit
mixer.
The concrete workability & temperature should be checked and recorded at batching plant
and also at site before unloading of concrete from transit mixture.
The concrete should be placed from one end and Concrete shall be compacted
immediately after placing and leveled uniformly with using hammer/floats made of steel
channels (ISMC) and long handles for manual compaction.
The approved water proofing admixture (conplast X421IC) should be mixed along with
concrete at batching plant as per manufacturer recommendations. The concrete shall be
stiff as possible ( 50 15 mm) at pour location.
The concrete surface shall be finished smoothly before final setting of concrete.
5.05.2. Water Proof Plastering:

Fix plaster buttons (50mm X 50mm size) at 2.0m intervals on the wall surface to a depth of 18mm.
The level pads shall be fixed line and plumb in order to maintain uniform thickness of plaster.
Plastering Mortar shall be prepared in proportion of 1:4, cement : sand
Volumetric boxes to be made and used for measurement.
Cement and sand to be mixed and blended together using a mechanical mixer machine or
manually. Water to be added to obtain required consistency. Water shall be added to such quantity
of dry mix prepared, which can be consumed within 30 minutes of mixing water. Unused Mortar shall
not be reworked with addition of water.
The approved water proofing compound should be added(for better results water proofing
compound shall be mixed with water, then it to be added to mortar) to the mix while mixing mortar,
125 ml of water proofing compound to 50 kg of cement bag.
The water proofing compound materials make and product approval should be obtained from
LTMRHL before using in plastering.
The surface to be plastered shall be dampened with water prior to applying the plaster mix.
The prepared Plaster Mix to be dashed against the wall with force.
Carryout plastering with reference of guide levels and finish to smooth using straight Edge, trowel and
spatula.
Polythene sheet can be laid at the floor surface, so that the fallen plaster mix can be collected and
reapplied within 30 minutes of mixing water.
Check the surface levels using straight edge and verticality with plumb and finish smooth without
undulations.
Plastering around the MEP Pipe fixtures to be trowelled to smoothness and squareness to be checked
prior to drying of mortar.
The flatness, right angle and plumb shall be checked whilst the mortar is green, so that the same shall
be rectified immediately.
The plastered surface shall be kept wet for a period of 7 days from the date of applying plaster.

5.05.3. Bore Packing(Gap Packing):

Where ever the outlets of plumbing pipes are there, the gap between the pipe and concrete/wall
surface shall be filled with non-shrink grout (Conbextra GP2) materials.
Sunken portion of toilet shall be filled with brick bat coba or any other filling materials and level the
surface to the required level as per GFC drawing.

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 15 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

Laying of Brick bat Coba:

The brick bat coba materials grade shall be obtained approval from LTMRHL before using at site.
The brick bat of size 25 to 40 mm out of well burnt bricks shall be used for brick bat coba.
The brick bats coba shall be mixed in the ration of 1:4:8(1 cement/4 fine aggregate/8 brick bats) in
mechanical mixture and filled in sunken portion to the required level.

5.06.

Curing:

Exposed surfaces of concrete shall be kept continuously in a damp or wet condition by ponding or
covering with a layer of sacks, canvas, Hessian or by similar materials and shall be kept constantly wet
at least for a period of 14 days

6. QUALITY CONTROL & QUALITY ASSURANCE:


6.1 Inspection Plan:
6.2 Test Plan:

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 16 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
6.1. Inspection Plan for UG Sump Water Proofing works at
Sl.
No
1

Description of sub-activity
Fixing of temporary bench marks

Uppal depot area:


Check by
L&T C

Check
by
LTMRHL

RFI, Check list

RFI, Check list

MTC

QCP

QHP

Surface Preparation and construction joints


location cleaning
Drilling the holes at construction joint location
at every 1 mts c/c
Fixing of Nozzles(PVC/GI) in to holes
Filling of gaps around nozzles with quick
setting cement or any grout materials
Receipt & Stacking of grout materials
(Cebex 100)
Mixing of grout materials

Injection/Pressure grouting through nozzles

Water ponding test

10

Dewatering of tested water


Application of water proofing coat
a. Application of primer/First coat
b. Application of Second/Final coat
Protective Layer Finishing: 1.Cement
Concrete

2
3
4
5
6

11

Documentation
RFI, L F book, list of
TBMs

RFI, checklist

Approval for sources of concrete ingredients

RFI, Test reports and

Mix design of concrete and its approval

RFI, mix design


approval

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Format No

Remarks

LTMRHL/CMP011F01(Rev 01)
LTMRHL/AF3(Rev01)

List of RFIs through


EDMS

L&TC/B&F/TF 67

List of RFIs through


EDMS

L&TC/B&F/TF 67

List of RFIs through


EDMS

LRMRHL/CMP011F01(Rev01)
LRMRHL/CMP011F01(Rev01)

List of RFIs through


EDMS
List of RFIs through
EDMS

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 17 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
LTMRHL/TF8
LTMRHL/

Batch sheets and trip


sheets
-

Concrete pour card

LTMRHL/CF2

RFI, Pre-concrete
checklist and pour
cards

LRMRHL/CMP011F01(Rev01)
LTMRHL/CF2

Pour Card, slump test


records

LTMRHL/CF2
LTMRHL/TF9

Checklist

LTMRHL/TF7

LTMRHL/CF3

Production of concrete

Transportation of concrete

Temperature of concrete

Rain and hot weather protection

Placing of concrete on floor.

Sampling, Casting and testing of workability


by slump cone method and casting of cubes
for compressive strength
Compressive strength of Cubes

10

Compaction of concrete and finishing

11

Curing for Cement concrete

Post- concrete check


list

12

Post concrete check

RFI, Post- concrete LRMRHL/CMP011F01(Rev01)


check list
LTMRHL/TF3

List of RFIs through


EDMS

List of RFIs through


EDMS

Protective Layer Finishing: 1.Cement Plastering


1

Plastered Wall/concrete Surface Preparation &


Cleaning

2
3
4
5

Fixing of Button Markings


Preparation & mixing of mortar
Plastering
Trueness and plumb

W
W
W
W

R
R
R
R

6
7

Surface smoothness or roughness


Curing

W
W

R
R

RFI and Check list

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LRMRHL/CMP011F01(Rev01)
L&T C/B&F/TF 19
LTMRHL/TF7

List of RFIs through


EDMS

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 18 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
8

Compressive strength of cement mortar

1
2
3
4
5
6
7

Others:
Housekeeping check list
Excavation Clearance permit
Pep talk report
Vehicle & earth moving equipment inspection
Equipment fitness report
Weekly environment inspection
Electrical safety check list
QCP
QHP
W
R
EDMS
QC

Quality Control Point


Quality Hold Point
Witness
Review
Enterprise Data Management System
Quality Control

W
W
W
W
W
W
W

R
W
R
R
R
R
R
MTC
TBM
RFI
BBS
LF
PCC

Inspection

Manufacturer Test Certificate


Temporary Bench Mark
Request for Inspection
Bar Bending Schedule
Level Field Book
Profile correction concrete

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

HMRP-31-A-rev 00
HMRP-14-C-Rev 00
HMRP-12-A-Rev 00
HMRP-09-AS-Rev00
HMRP-15-B Rev 00
HMRP-28-A3 Rev00
HMRP-09-A2 Rev00

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 19 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
6.2. Test Plan for Grout materials and concreting application works for Toilet Water Proofing Works at Uppal depot area:
Grouting Materials for routine tests during permanent works
S.No.
TEST TYPE
CODE OF PRACTICE
1
Conbextra GP2 or Rendroc RG
IS1786
2
Cebex 200
BS8110
3
Nitobond SBR(Latex)
BS 6319
Manufacturer
4
HYDROPROOF
specification
5
Conplast X 421 IC
IS 2645
6
Nitocote EP 405
IS 9833-1981
Concrete For routine tests during permanent works
CODE OF
S.No.
TEST TYPE
PRACTICE
1

Cement

IS 4031-Part1 to 6

Flyash

IS 3812-Part1

Water

IS 3025

Admixture

IS 9103

FREQUENCY OF TESTING
02 tests for every Consignment
MTC to be maintained for every batch
MTC to be maintained for every batch

As per manufacturer specification


MTC to be maintained for every batch
MTC to be maintained for every batch
FREQUENCY OF TESTING
MTC to be maintained and in-house tests
for setting time and strength once per
week and third party test once for every
three months
MTC, Third party test for physical
/chemical properties once per week
1 per source per 3 months
MTC to be maintained for every batch and
Third party uniformity test per each batch

Sieve Analysis of aggregate

IS 2386 Part-1

Once per source per day (CA,FA and all


in aggr)

6
7
8
9
10

Los Angeles Abrasion value


Aggregate Impact Value
Flakiness Index and Elongation Index
Deleterious Content
Water Absorption of aggregate
Soundness with Sodium Sulphate
5cycles
Crushing Value of aggregate

IS 2386 Part-4
IS 2386 Part-4
IS 2386 Part-1
IS 2386 3
IS 2386 Part-3

1 per source change


Once per source per week
Once per source per week
Once per Source
Once per month

IS 2386 Part-5

1 per source change

IS 2386 Part-4

1 per source change

11
12

SPECIFICATION REQUIREMENT
Fe500 as per IS1786
Shall conform to BS 8110 part 1
Shall conform to BS 6319

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Shall conform to IS 2645 2003


Shall conform to IS 9833-1981
SPECIFICATION REQUIREMENT
Shall confirm to IS12269
Shall confirm to IS3812-Part1
Shall confirm to clause 4.3 of IRS:CBC
Shall confirm to ASTM C494 /C-260/ IS9103
Shall conform to 20 mm size graded aggregate
conforming Table-2 IS 383, Zone 1&2 of table 4
IS383 and 20 mm size all-in-aggregate of Table 5 of
IS 383.
50%
45%
35% for flakiness index
3%
3%
12% for Coarse aggregate and <10% for Fine
aggregate
45%

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 20 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
13

Workability of concrete & temperature

14

Compressive strength of concrete

15
16
17
18

Chloride content in hardened concrete


Sulphate content in hardened concrete
Drying shrinkage
Permeability

19

Once per transit mixer per grade of


concrete

IS 1199

BS1881 Part 6
BS1881 Part 6
BS 1881
MoRT&H
As per approved
Calibration of batching plant
method
Plastering For routine tests during permanent works

Cement

IS 12269

2
3

Sieve Analysis of Fine aggregate


Water

IS 1542
IS 3025

Compressive strength of cement mortar

Water Proofing compound

Other tests
S.No.
TEST TYPE
1
Calibration of auto level
2

Environment monitoring

3
4

Illumination monitoring
Noise levels monitoring

As per Manufacturer
specification

A.P State
Pollution Board
BOCW act
BOCW act

Once per month

2% variation in each ingredient

No of samples
1
2
3
4
4+1 for every 50cum or
part thereof

MTC to be maintained and in-house tests


for setting time and strength once per
week
Once per source per day
1 per source per 3 months
One set of sample per batch(for 28 days
strength)

IS 2250-1981

CODE OF PRACTICE

1 per grade of concrete per 3 months


1 per grade of concrete per 3 months
1 per grade of concrete per 6 months
1 per grade of concrete till 60 samples

(1 sample is a set of 3nos. Of 150x150x150mm


cubes, in addition to this 1 sample to be taken for 7
days strength determination.) The compressive
strengths shall confirm to target mean strength. If
any individual cube strength is less than the target
2
strength by 3N/mm , standard deviation shall be
applied. Mean strength any three cubes shall be
fck+3Mpa but not equal.
0.5% by the weight of cement
3.7% by the weight of cement
0.05%
<25mm

Quantity
1-5 cum
6-15 cum
1630cum
31-50cum
51 above

IS 516

17525mm & <30C

MTC should review for every batch

Shall confirm to IS12269


Shall conform to IS 1542
Shall confirm to IRS:CBC
Shall conform to IS 2250-1981
As per Manufacturer specification &
recommendation

FREQUENCY OF TESTING
Once per 6 months

SPECIFICATION REQUIREMENT
<2mm per Km

Once per 6 months (air and ground water)

As per APPB norms comparing to base line reading

Once per week


Once per week

>33 lux (using calibrated lux meter)


<63 dB (using calibrated decibel meter)

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 21 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
7. ENVIRONMENT, HEALTH & SAFETY:
7.1. ENVIRONMENTAL:

Vehicle / machinery and equipment operation, maintenance and refuelling shall be carried out in such a
fashion that spillage of fuels and lubricants does not contaminate the ground.
Shall ensure that no trees / branches to be fell by labourer for fuel, warmth during winter. Enough provision of
fuel to be ensured.
General refuse shall be stored in enclosed bins or units and it should to be separated from construction and
chemical wastes.

7.2. HEALTH:

Section In-charge / Engineer shall ensure all workers are screened before engaging them for duties.
In-charge shall ensure availability of first aider with first aid kit.
Shed / shelter shall be provided for workers for weather protection along with drinking water.

7.3. SAFETY:

All transit mixers / tankers shall be provided with reverse horns.


Flagman shall be provided at all exit points of the trucks / tippers.
Warning Sign Boards like Men at Work, Deep Excavation, Go Slow etc shall be displayed at work area.
The speed of vehicles plying in the work area shall be restricted to 15kmph maximum.
Levelling staff shall be made of wood.
If night work is to be carried out the area shall be sufficiently provided with lighting.
It shall be ensured that the safety belts were worn, tied and anchored properly while working at heights.
All working platforms shall be tied at the both ends firmly.
For taking down the concrete, chutes shall be used.
The working condition of the reinforcement cutting and bar bending machines limit switches shall be ensured
before starting the days work.
Hand gloves shall be used for cutting, bending and shifting of reinforcement rods.
The electrical connections for vibrators / lighting shall be given by qualified / experienced P&M personnel
through ELCB only.
Ensure that all moving parts of vibrator / compressor if any shall be provided with guards.
If concrete is being done by crane, the capacity of crane and its reach shall be reviewed.
Sign Boards/warning signs shall be displayed at prominent locations near to work places.

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 22 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

REFERENCE :

L&T METRO RAIL HYDERABAD Ltd.

SAF 30

SITE EMERGENCY CONTACT LIST


Name of the Contractor: L&T ECCD B&F IC

Contract No. ---

The following persons have been appointed to be our representatives on site for all site safety emergencies.

Position

Name of
Representative
RAJESH B KONDLE(RBK)

A G CHANDRA SEKHAR
S K JHA
K. SRINIVAS

P CHAITHANYA

Home
Tel.
-

Mobile No.

PM

7799699880

CM

9963027004

PROJECT HEAD

K. SRINIVAS REDDY

Dr. KARUNAKAR

Office
Tel.
-

ACM

9849949767

9912855721

EHSM

9666097111

DOCTOR

9985738741

886998920

IR

Project Manager
Signature

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 23 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP
LARSEN & TOUBRO LIMITED ECC DIVISION B & F IC
CONTINGENCY PLAN FOR HYDERABAD METRO RAIL PROJECT

Ambulance vehicle Number;


(Stationed at Uppal Depot)

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 24 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

LIST OF HOSPITALS IN HYDERABAD (NEARBY WORK PLACE)


Sl Name of the
No
Hospital
1
CARE
HOSPITALS
2
MEDICITI
HOSPITALS

Hospital Location

Contact No:

Exhibition Grounds Road, Nampally, Hyderabad - 500


004
5-9-22, Secretariat Road, Hyderabad - 500 063

+9140 30417777, 30417488


+9140 23231111

YASHODA
HOSPITALS

Nalgonda X Roads, Malakpet, Hyderabad - 500 036

+9140 24555555

IMAGE
HOSPITALS

Madhapur, Hyderabad - 500 081

+9140 23116666, 23116000

APOLLO
HOSPITAL

Jubilee Hills, Hyderabad - 500 033

+9140 23607777, 23607760

JAGDAMBA
HOSPITAL

#1-1-380/3, Gandhi Nagar, Hyderabad - 500 080

+9140 27613419, 27613420

IMAGE
HOSPITALS

903/F12 & 13, Ameerpet, Hyderabad 500 016

+9140 23750000

SWAPNA
NURSING HOME

6-3-1111/19, Nishanth Bagh, Begum pet


Hyderabad 500016

+9140 23402417, 23405019

4-1-1227, King Koti


Road, Hyderabad,
Andhra Pradesh, India
10
GLOBAL
Lakdi-kaHOSPITALS
Pul,
Hyderabad
Andhra Pradesh, India
11 JAYABHUSHAN
Santosh Nagar
HOSPITALS
Colony,
Mehdipatnam,
Hyderabad
12
KAMINENI
: Cross
Road, L B Nagar , Hyderabad- 500068 , Andhra
HOSPITALS
Pradesh
9

KAMINENI
HOSPITALS

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

+9140 66924444

+9140 23244444

+9140 66563334

+9140 39879999

LARSEN & TOUBRO CONSTRUCTION


Quality Assurance Plan
BUILDINGS & FACTORIES INDEPENDENT
No: HM-LE-NDPNDP-M0301-DOC-MS-QMS-00-092 Rev 00
COMPANY
Page 25 of 25
HYDERABAD METRO RAIL PROJECT
Construction work procedure for Typical Toilets Water Proofing works(UPPAL DEPOT) in HMRP

8. ATTACHEMENTS/ ANNEXURES:
1. Annexure 1 Risk Assessment
2. Annexure 2 Incident Flow
3. Annexure 3 - Formats

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

RISK ASSESSMENT/ SUMMARY SHEET

CONTRACTOR NAME: L&T CONSTRUCTION

RISK ASSESSMENT FOR: WATER PROOFING WORKS

Originator Name (Print): K. SRINIVAS

Contract:

Signature:

Date: 13.07.2013

KEY:

L = Likelihood

S = Severity

R = Risk (Likelihood x Severity)

RISK RANKING:

L = Low priority to be implemented when resources


allow.

M = Medium priority to be scheduled as soon as practicable.

H = High priority to be acted on


immediately.

Task/Element

Confine Space

Potential Hazards

Low Oxygen Level


Suffocation
Chemical

Shifting of materials

Working Platform

Mixing & Placing


(Application)

Improper shifting of
materials
Fall of material, hitting,
slip & fall

Population at
Risk

Workmen
Employee &
Workmen
Employee &
Workmen
Employee &
Workmen

Risk Rating

Revised Rating
Control Measures/ Follow-up Checklist

Ref: HM RP 12A Rev 00


Ref: HMRP-14-A Confined Space Permit

Ref: HM RP 12A Rev 00


Ref: HMRP 31A Rev 00

Ref: HMRP 31A Rev 00

Ref: HMRP-12-A Rev 00


Ref: HMRP-09-C1 & C2 Rev 00
Ref: HMRP-09-D Rev 00
Ref: HMRP-31-A Rev 00
Ref: HM RP 12A Rev 00
Ref: HMRP 31A Rev 00
Ref: HMRP-28-A Rev 00

Spillage of chemical

Employee &
Workmen

Nonuse of
PPEs

Employee &
Workmen

Ref: HMRP 12A Rev00

No approach/
No access

Employee &
Workmen

Ref: HM RP 12A Rev 00


Ref: HMRP 31A Rev 00
Ref: HMRP 09A 13 Rev00

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

CONTRACTOR NAME: L&T CONSTRUCTION

RISK ASSESSMENT FOR:

Originator Name (Print): K. SRINIVAS

Contract:

Signature:

Date: 13.07.2013

KEY:

L = Likelihood

RISK RANKING:
Task/Element

L = Low priority to be
implemented when resources
allow.
Population
Risk Rating
Potential Hazards
at Risk

Confine Space

Shifting of
Materials

Working
Access /egress
/ Working
Platform

Mixing /
Placing / Grout
(Application)

Low Oxygen Level


Suffocation

Employees /
Workmen

Chemical
Injury to arms/
eyes

Employee &
Workmen

Improper shifting of
Materials

Employee &
Workmen

Falling of material,
hitting, slip & fall

Spillage of chemical

Employee &
Workmen

WATER PROOFING WORKS

S = Severity

R = Risk (Likelihood x Severity)

M = Medium priority to be scheduled as


soon as practicable.

H = High priority to be acted on


immediately.

1. Confined Space permit shall be obtained prior to


enter the sump.
2. Conduct gas testing prior to entry inside the sump
3. The persons shall be given PEP talk required to enter
the confined space been trained in dealing
with the specified hazards
4. Continues watch a rescue team equipped with
emergency rescue devices rope are put on standby
5. 24v hand lamp shall been provided for adequate
lighting
6. Exhaust / fresh-air-flow fan shall be provided

1. MSDS is briefed to the worked with dos and donts.


2. Hand gloves, goggles are provided for handling the
chemical.

1. Proper handling shall be ensured without dropping


the containers on the ground.

1. Nose mask and rubber hand gloves shall be provided


to the worker.
2. PEP talk shall be conducted for all workmen engaged
in the activity.
3. Step Ladder shall be utilized for the activity properly
supported by 2 workmen.
4. Workmen shall not overreach on the step ladder.
5. Continuous supervision by site engineer shall be
ensured.

1. Conduct Pep Talk before everyday work starts.


2
3
M 2.
3. Ensure 100% mandatory PPE.
Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM
4. Carrying container sealed condition.

Employee &
Workmen

Revised Rating
L
S
R

Control Measures

5. Recap after every withdrawal.


6. Taking the full quantities by proper draining.
7. Usage of trays for handling or transferring to other
containers.

No approach/
No access

Employee &
Workmen

Employee &
Workmen

1. Goggles / Hand gloves (Rubber)/ Safety belts/ Shoes


shall be worn by all persons.

1. Approach staircase is kept safe & free from material


stacking.
2. Working platform shall be provided for height work.
3. Edge protection like guard rails shall be provided for
platforms
4. Life Line & Full Body Harness shall be used while
working above 6 Feet height.

RISK MATRIX
SEVERITY

PROBABILITY

Nonuse of
PPEs

4
5

L
M

M
M

M
H

H
H

H
H

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO LIMITED :: ECC DIVISION


BUILDINGS AND FACTORIES OPERATING COMPANY

Ref: HMRP 12A Rev00


PEP TALK REPORT

Identity / Name of the Site

Location

Name of the Section Incharge

Name of the HSEO

Name of the Sub-Contractor/Dept.:


Number of workmen present

Date & Time

Topics discussed

Response of workmen

Remark / Any significant problem :


identified

Signature:

-----------------------HSEO

---------------------Site Engineer

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

LARSEN & TOUBRO LIMITED - ECC DIVISION


BUILDINGS AND FACTORIES OPERATING COMPANY
Ref: HMRP-28-A Rev 00
ENVIRONMENT INSPECTION CHECKLIST
Name of the Project:
Location:
Description

Sl.No

Land

Land contamination due to storage of


inflammable substances

Disposal of oils

Disposal of batteries

Reduction in usage of non bio degradable


items

Disposal of waste

Wood waste

Concrete waste

Food related waste

Biological waste

10

Others

II

Water

Water Stagnation (esp. canteen, camps)

Contamination due to run off water

Contamination due to oil spillage

Conservation measures

Quality of drinking water

Sewage disposal

III

Air

Dust pollution & its mitigation

Exhaust emissions

Obnoxious gases release

IV

Noise

Acoustic arrangement for DG

Date:
Observation

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Measures

Description

Sl.No

Noise levels in the workplace

Noise levels outside workplace

Site Engineer

Observation

EHS OFFICER

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Measures

CONSTRUCTION VESSEL OR CONFINED SPACE ENTRY PERMIT


Ref: HMRP-14-A Rev 00
___________________________________________________________________________
Project

: Hyderabad Metro Rail

Client

: Hyderabad Metro Rail Limited

Independent Engineer

: Louis Berger Consulting Pvt.Ltd

Concessionaire

: L&T Metro Rail Hyderabad Limited

Contractor

: L&T Construction

B&F IC

Infra IC

___________________________________________________________________
To identify safe work practices related to working inside a confined space or a vessel or a plant / equipment.
A.
1.
2.
3.

The person taking permit (permittee) to fill up.


IDENTITY OF THE CONFINED SPACE
LOCATION
PURPOSE OF ENTRY

DATE :

4. VALIDITY OF CONFINED SPACE PERMIT


FROM : (Time) _____________ (DATE) _____________
TO
: (Time) _____________ (DATE) _____________
5. HAS THE VESSEL / EQUIPMENT / SPACE BEEN CLEANED, PURGED, ISOLATED

YES

6. HAVE ALL THE ELECTRICAL / AIR / HYDRAULIC EQUIPMENT / DRIVES BEEN DISCONNECTED

YES

7. HAVE THE PERSONS REQUIRED TO ENTER THE CONFINED SPACE BEEN TRAINED IN DEALING
WITH THE SPECIFIED HAZARDS
8. PPE PROVIDED
9. HAS A RESCUE TEAM EQUIPPED WITH EMERGENCY RESCUE DEVICES PUT ON STANDBY

YES
YES
YES

10. HAS 24V HAND LAMP BEEN PROVIDED

YES

11. EXHAUST / FRESH-AIR-FLOW FAN BEEN PROVIDED

YES

12. TESTS REQUIRED


A.
B.
C.
D.
E.
F.
G.

OXYGEN LEVEL (19.5% - 23.5%)


EXPLOSIBILITY (0%)
CARBON MONOOXIDE LEVEL (50 PPM Max )
CARBON DIOXIDE LEVEL (1200 ppm Max)
TEMPERATURE
AIR FLOW
OTHERS

13. LIST OF AUTHORIZED PERSONS TO WORK INSIDE A CONFINED SPACE & THE RESCUE TEAM (LIST TO BE
ENCLOSED)
I have checked the above points and found conditions suitable to undertake the work.
_____________________
Name of the permittee
(Site Engineer)

__________________
Signature

______________________
Designation

B) The person giving permit (Issuing Authority) to fill up


The precautions and safe conditions mentioned above have been verified and the work can be started.
Name & Signature of
Issuing authority
C) Time ____________

FOR L&TC

________________________
Section In-charge

_______________
EHSO

Date____________________ at which the permit closed & filed.

FOR LTMRHL/LBC

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

IDENTIFICATION OF ENVIRONMENTAL ASPECTS AND IT'S IMPACTS


NAME OF THE OPERATION Water Proofing Works

Shifting of Materials /
Fixing & Placing
(Application)
1

Chemical
Spillage

AIR

WATER

Dust due to
the mixing /
Pollution /
Vapors
Air pollution
due to
emissions
from diesel
engines

Contamination Due to
flowing to nearby
drains

LAND

Contamination

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

RATINGS

OTHER

Noise level of that area


may increase
Disturbance to local
community
Mud scaling on the road /
location

DURATION

IMPACT

PROBABILITY

ASPECT

SEVERITY

ACTIVITY

SCALE

S.No.

Note:

SCALES:

RATINGS
1

SCALE OF
IMPACT
Localized

SEVERITY OF
IMPACT
very low

PROBABILITY OF
OCCURANCE
Rare

Department

Low

Once a year

Factory

Moderate

Once a month

City

High

Once a week

Global

Very high

Intermittently/
when activity goes
on

DURATION
OF IMPACT
LAST
Momentary
Lasts for a
day
Lasts for a
month
As long as
aspect
continues

Total= Scale x Severity x Probability x Duration


Total rating if >150 or any Legal Compliance is observed then Operation
Control Procedure required.

Permanent

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

INCIDENT COMMUNICATION FLOW CHART

MINOR INCIDENTS
(Such as Near miss, First-Aid, Property damage, Traffic zone
incidents etc.)
STEPS

L&T Construction

LTMRHL
Receive SMS
(by EHS Department)
Receive e-mail
(by EHS Department)

Inform
By SMS Immediately
Identify, Register and send
e-mail (register in .exl)
Complete correction

Investigate

1
2

Propose Corrective Action

MAJOR INCIDENTS
(such as Dangerous Occurrences, LTI, Fatal, Working zone incidents)

STEPS
1
2

L&T Construction

LTMRHL

Inform
By SMS Immediately
Identify, Register and send email (register in .exl)

Receive SMS
(by EHS Department)
Receive e-mail
(by EHS Department)

Complete Correction

Within 24 hrs., prepare report in


the prescribed format

Send report by Email within 24


hrs. of incidence

Receive a written report in a


prescribed format
(by EHS Department)

Implement Corrective
Action

Inform to all personnel,


Statutory authorities as per
Clause 14.2 of SHE Contract
conditions

Record and Update


Register

Send copies by e-mail

Receive a copy of the said


communication

Investigate and report

Attend and receive an


Investigation report

(by EHS Department)

Receive updated register


every Saturday by e-mail

Inform By e-mail

(by EHS Department)

Discuss in
weekly review meeting

Discuss in
weekly review meeting

LTMRHL EHS TEAM


1. K.P.SREEHARI7702555383
2. Prakash Rahamatkar- 7702222693
3. Bhaskar Kunadharaju- 9866299599

(by EHS Department)

Propose Corrective Action

10

Implement Corrective Action


Circulate the incident report to
all Interested Parties through
EDMS
Discuss in
weekly review meeting

11
12

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Discuss in
weekly review meeting

Format No: LTMRHL/CMP 011 F01 (Rev.01)

REQUEST FOR INSPECTION


PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
: L&T Construction
B&F IC

Infra IC

EDMS submission No:


RFI No :

Date:

Date:

Discipline: CIVIL / MECHANICAL / ELECTRICAL / RAILWAYS


Activity:

ITEM LOCATION
Corridor No:
Stage No:.
Area name:

Drawing Number:

Quality Hold Point

Quality Control Point

Details of item :

Reduced From:
level

To:

Requested by:

Quantity:

Inspected by:

Name

Name

Date

Date

Time

Time

Signature:

Signature:

Details of inspection :
1. Inspection completed, the contractor may proceed with the works.

Yes

No

2. Remedial works required as below but further inspection not required.

Yes

No

3. Remedial works required as below and re-inspection is required.

Yes

No

Remarks by LTMRHL:

FOR L&T
Distribution :

FOR LTMRHL / LBC


Original to Contractor ; Duplicate to LTMRHL

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Format No. LTMRHL / AF3

(Rev.01)

LEVEL FIELD BOOK


PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
B&F IC
: L&T Construction

Infra IC
Date:

Drawing Number:
Instrument and its number:

Date of next calibration:

SERIES OF LEVELS FROM................................... TO...............................


No. of
station

Offset

Back
Sight (m)

FOR L&T C

Intermedi
Heigth of
Fore Sight
ate Sight
collimation
(m)
(m)
(m)

Reduced
level (m)

Required
Level (m)

Difference

Remarks

FOR LTMRHL / LBC

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR

: Hyderabad Metro Rail

: Hyderabad Metro Rail Limited


: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
: L&T Construction
B&F IC
Infra IC

CHECK LIST FOR INJECTION /PRESSURE GROUTING & APPLICATION OF WATER PROOFING COMPOUND/Bitumen Emulsion

Structure

Floor Level

Location

Drg. Reference

Sl.no

Format No.: L&T C / B&F / TF67

Description
Check for

01
02
03
04
05
06
07

Date

Verified Signature
L&T

LTIL

Surface preparation by cleaning and removing


unwanted materials
Providing GI or PVC grouting nozzles of at 1.00m
c/c in construction joints or any defect /honey
comb area
Mixing of grout Materials
Injecting/Pressure grouting the cement slurry
admixed with non-shrink expanding grout by low
pressure grout pump till it fill
Cutting the projected portion of nozzle after
completing he grouting operation and setting of
grout materials
Water filling in tank/floor

08

Water ponding test(Water leakage shall be


observed two times in a day 9.00am & 9.00pm
and recorded for 3 days)
Application of Water Proofing Coat

Surface preparation

Mixing of water Proof coating Materials

Primer/First Coat application

Second coat/Final Coat application

Protective layer finishing

Cement Concrete on Floor

Plastering the flooring with CM 1:4 and 15mm


thick mixed with integral WP compound

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Remarks

Format No: LTMRHL / TF 8

CONCRETE BATCH SHEET


PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
B&F IC
: L&T Construction

Location of testing lab:


Corrridor No:

Stage No:
Source

DATE, TIME & Plant location:

Aggregate in the Design mix


20mm (%)
12.5mm (%)
River Sand (%)
Crusher Sand (%)
Admixture (%)

Portland Cement
Flyash
Micro Silica
Crushed Aggregate
River Sand
Admixture

Grade of Concrete:
Ingredients of Mix

Infra IC

Qunitity per
cum (as per
mix design)
(kG)
2

Free Moisture in
Water
Water absorption Free Moisture
ingredients (kG)
absorption (kG) (col.4 = clo.2 x in ingredients
(col.6 = col.2 x col.5
(%)
col.3 / 100)
(%)
/ 100)
3
4
5
6

Corrected weight of ingredients per


cum after moisture corrections (kG)

for
_______cum
(kG)

Ordinary Portland Cement (kG)

col.2 =

Flyash (kG)

col.2 =

Micro Silica (kG)

col.2 =

Coarse Aggregate Fraction 1 20mm (kG)


Coarse Aggregate Fraction 2 10mm (kG)
Fine Aggregate Fraction 3 River Sand (kG)
Fine Aggregate Fraction 4 Cruhser Sand (kG)

col.2 + col.6 =
col.2 + col.6 =
col.2 + col.6 =
col.2 + col.6 =

Free Water (kG)

col.2 + col.4 - col.6 =

Admixture (kG)

col.2 =

FOR L&T C

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

FOR LTMRHL / LBC

Format no: LTMRHL / CF2

CONCRETE POUR CARD


PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR

Drawing no.

Structure

Location

Segment

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
B&F IC
: L&T Construction

Date:

Grade of concrete

Quantity of concrete

Cement Required in MT

:_________________

Date & time of start

Expected time of completion

Method of transportation

Method of mixing

Method of pouring

Rate of pour achieved

Water- cement ratio

Admixture

Slump observed:
1

mm
No. Of cubes taken
ID Marks on cubes

APPROVED TO POUR

FOR L&T C

Infra IC

mm

cum/hour.

Retarder/ super plasticizer

mm

mm

mm

mm

:
:

: YES/ NO

FOR LTMRHL / LBC

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Format No.: LTMRHL / TF 9

WORKABILITY OF CONCRETE BY SLUMP CONE TEST


PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
B&F IC
: L&T Construction

Infra IC
Date :

Weather condition at concrete placing location :


Structure
Corridor

Stage

Location

Name

Part

Identification
number

FOR L&T C

Time of
Transit mixer
observation
number

Grade of
concrete

Slump
observed
(mm)

FOR LTMRHL / LBC

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Format No.: LTMRHL / TF 7

COMPRESSIVE STRENGTH OF CONCRETE CUBES


PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR

Location of testing lab:


Corrridor No:
S.No Date of casting

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
: L&T Construction

B&F IC

Infra IC

Date of testing:
Stage No:
Location / Identification mark

Grade of
concrete

W-C ratio

Age on
testing

FOR L&T C

Cube
number

Weight of
cube (gm)

Machine
load (kN)

Compressive strength
(N/mm2)
Individual
Ave

FOR LTMRHL / LBC

Page ____ of ____


Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Format no: LTMRHL / CF 3

POST-CONCRETE CHECKLIST
PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR
Drawing no.
Location
Structure
Segment
Quantity of concrete poured
Achieved pouring time
Date of pour
Date of side shutter stripped
Date of soffit shutter stripped

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
B&F IC
: L&T Construction
Date
:
:
:
:
:
:
:
:
:

Infra IC
:

POSITION/ DIMENSIONS
Alignment
Levels
Dimensions
Non-conformance report no.

: S / NS
: S / NS
: S / NS
:

dated

CURING
Method
Starting date
Finishing date
Checks
Date

:
:
:
:

Remarks
References: S-Satisfactory
SURFACE DEFECTS

NS-Not satisfactory.

No defects/ Minor defects/ Major defects


Non-conformance report no.

dated:

CRACKS
No cracks/ cracks

date observed:

Nature of cracks: Hairline/ <0.25mm/ >0.25mm


SPALLING
No spalling/ Spalling
dated

Non-conformance report no.


for cracking/ spalling

SKETCH( indicate position/ dimensions of crack/spalling)

Inspected by:

Date:

Signature:

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Format No.: LTMRHL / TF 3

CALIBRATION OF SAND POURING CYLINDER


[As per IS 2720, (Part - 28)]

Project
Client
Independent Engineer
Concessionaire
Contractor

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
: L&T Construction

B&F IC

Infra IC

Pouring Set No.

Tested By

Proposed Use

Source of Sand

Location of testing lab:


Corrridor No:
Weight of Sand in Cone

Date of testing:
Stage No:

Trials
2

Average

1 Weight of sand in pouring cylinder before pouring, A


(gm)
2 Weight of sand in pouring cylinder after filling in the Cone, B (gm)
3 Weight of sand in the cone C = (A-B)
(gm)
Bulk Density of Sand
1 Weight of sand in pouring cylinder before pouring, W 1
(gm)
2 Weight of sand in pouring cylinder after filling in the
(gm)
3 Weight of sand in the calibrating container and cone
(gm)
4 Weight of sand in the cone W c
(gm)
5 Weight of sand in the calibrating container, W 4 = (W 3-W c)
(gm)
6 Volume of calibrating container, W 5
(cc)
7 Bulk Density of Sand, W 2/W 5 (gm/cc)
Note : Sand to be used shall be clean, uniformly graded natural sand passing 1.00 mm sieve and retained on
600 micron sieve.
Results
=
gm/cc
1. Average Bulk density of sand
2. Weight of sand in Cone of the
=
gm
Pouring cylinder
Remarks :

FOR L&T C

FOR LTMRHL / LBC

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Format no: LTMRHL / CF 3

POST-CONCRETE CHECKLIST
PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd
: L&T Metro Rail (Hyderabad) Limited
B&F IC
: L&T Construction

Infra IC
Page 01 of 02

DEPUTED ENGINEERS EVALUATION(tick as applicable)


Not significant (use as it is)
Structural or indeterminable origin
NCR to be raised
Name:

Date:

Signature:

QUALITY FOLLOW-UP
Non-conformance report no.

Given by

Signature

TEST RESULTS SUMMARY


Test

No.

Mean

SD

Max

Min

Compliance

Slump (mm)

Yes/ No

Compressive strength7days (N/mm2)

Yes/ No

Compressive strength28days (N/mm2))

Yes/ No

Any non-compliance
: Yes/No
:
If yes- action taken
===============================================
===============================================
===============================================
=====......................................................................................................................................................
........................................................................................................................................................................
........................................................................................................................................................................
........................................................................................................................................................................
........................................................................................................................................................................
..................==========================================
===============================================
=================.....................................................................

DATA TRANSFER
Date passed to structure records
FOR L&T C

: Yes/ No
FOR LTMRHL / LBC

Page 02 of 02

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Format no: L&T C/B&F/ TF19

CHECK LIST FOR PLASTERING WORKS


PROJECT
CLIENT
INDEPENDENT ENGINEER

: Hyderabad Metro Rail


: Hyderabad Metro Rail Limited
: Louis Berger Consulting Pvt. Ltd

CONCESSIONNAIRE

: L&T Metro Rail (Hyderabad) Limited

CONTRACTOR

: L&T Construction

B&F IC

Corridor No:

Stage No:

Structure

Floor Level

Location

Drg. Reference
Sl.no
01

Infra IC

Type

Description
Check for
Clearance for plastering (like door or window frame

: External / Internal / Ceiling


Date

Date:

Verified Signature
L&T Site
L&T QA

fixing, electrical conduits, other embedments, etc)


02

Roughening the surface


If block work - racking out joints
If concrete surface hacking

03
04
05
06

Providing the chicken wire mesh at the junction of


block work and concrete surfaces
Cleaning and dampening the surfaces
Fixing of mortar gauges with line, level and plumb
Carrying out the plastering as per the drawing and
technical specification procedures by following the:
Thickness as _______mm
Cement mortar ratio as CM ______

07

Line, level and plumb


Adding water proofing compound for external
plastering, others if required as per drawing

08

Curing the surface

Guideline:
Type
Wall Plastering
Internal
External
1st coat
2nd coat
Ceiling plastering

Thk.

Ratio

12mm

1:6

12mm
6mm
6mm

1:6
1:4
1:3

FOR L&T C

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

FOR LTMRHL

Remarks

HOUSEKEEPING CHECK-LIST
Ref: HMRP-31 A Rev 00
__________________________________________________________________________________________
Project
: Hyderabad Metro Rail
Client
: Hyderabad Metro Rail Limited
Independent Engineer
: Louis Berger Consulting Pvt.Ltd
Concessionaire
: L&T Metro Rail Hyderabad Limited
Contractor
: L&T Construction
B&F IC
Infra IC
__________________________________________________________________________________________
Location:
Date:

S.NO

POINTS TO BE CHECKED

1.

Is the working place cleaned properly?

2.

Is the approach road to the workplace proper and clear of


obstruction

3.

Are the internal roads barricaded from pedestrian path

4.

Is the road maintained daily from removal of any spoil

5.

Periodical spraying of water for dust suppression

6.

Are all lights working properly in the night shift?

7.

Is there any loose & hanging temporary wiring?

8.

Is there any wastage/ leakage of water, oil in the work


place?

9.

Waste collecting drums are available

10.

Are the machines & equipment kept clean while working &
guarded properly?

11.

Are fire protection appliances kept un obstructed?

12.

Mud sediment cleaned from the wheel wash area

13.

Are all instruction charts, sign boards, notice boards etc. in


position and kept up to date?

14.

Goal post is installed under overhead LT / HT power lines?

YES

NO

REMARKS

SIGNATURE CHECKED BY

SIGNATURE WITNESSED BY

SITE-INCHARGE/ ENGINEER

EHSO/ SITE EHS PERSONNEL

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

EXCAVATION CLEARANCE PERMIT


Ref: HMRP-14-C Rev 00
___________________________________________________________________________
Project

: Hyderabad Metro Rail

Client

: Hyderabad Metro Rail Limited

Independent Engineer

: Louis Berger Consulting Pvt.Ltd

Concessionaire

: L&T Metro Rail Hyderabad Limited

Contractor

: L&T Construction

B&F IC

Infra IC

___________________________________________________________________
(In respect to (i) Existence of service lines and utilities (ii) In the proximity of existing structures,

buildings, foundations, installations like gas, electrical service stations etc. (iii) Any other conditions
which may result in serious hazardous consequences.)
Please permit the following excavation job as per sketch enclosed:

Details of excavation: Lengthm Width.m Depth.m


Location: Performing Agency:
Permit valid from (Date). to.....Execution In harge
Tel. No.:
Name:
Date:
Designation:
Signature:
Proj/Mfg/Maint/TS/ES
I ELECTRICAL:
1. Details of underground cable present in the area to be excavated..
2. Electrical isolation of the following required...
Date:
Name & Designation:
Signature:
II INSTRUMENTS:
1. Details of underground cable present in the area to be excavated....
2. Precautions to be observed for safe excavation job...
Date:
Name & Designation:
Signature:
III COMPUTER SERVICES:
1. Details of underground cable present in the area to be excavated....
2. Precaution to be observed for safe excavation job....
Date:
Name & Designation:
Signature:
IV ENGINEERING SERVICES:
1. Description of underground facilities existing at the proposed location....
2. Precaution to be observed for safe excavation job....
Date:
Name & Designation:
Signature:
V. FIRE & SAFETY:
1. Provide: Cross over....Barricades...
Road Blocks...Shoring....Others..
2. Use following safety equipment: Gas Masks...Eye Protection..
Wooden Handled Tools....Others..
3. Provide following: Approach for the Fire/Emergency Tenders/ Road closure boards/Other
Precautions...
Date:
Name & Designation:
Signature:
Remarks if any..
The Above Mention Job Can Commence.....
Date:
Name & Designation:
ISSUING AUTHORITY

Signature:

The above mentioned excavation work has been completed satisfactorily.


Date:

Name & Designation:

Signature:

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

ISSUING AUTHORITY
__________________________________________________________________________________
_
Note: The scope of this permit is limited to carrying out the excavation work safely. This permit is not
intended / applicable till closing of the excavated area.
FOR L&TC

FOR LTMRHL/LBC

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

VEHICLE & EARTH MOVING EQUIPMENT INSPECTION CHECKLIST


Ref: HMRP-09-A5 Rev 00
_____________________________________________________________________
Project

: Hyderabad Metro Rail

Client

: Hyderabad Metro Rail Limited

Independent Engineer

: Louis Berger Consulting Pvt.Ltd

Concessionaire

: L&T Metro Rail Hyderabad Limited

Contractor

: L&T Construction

B&F IC

Infra IC

______________________________________________________________
Make / Model
Job No.
Inspected By
Date

:
:
:
:

Sl. No.

Asset code (If applicable) :


Owned by
:
Points

Engine condition

Clutch / brake / Hand brake

Hydraulic System

Guards / Covers / Doors

Fastener lock pins / Keys

Horn / Reverse horn / Lights

Indicators / Wiper Blades

Operators fitness

Tyre pressure / Tyre Condition

10

Condition of Battery and Lamps

11

Operating levers / steering

12

Gauges & warning devices

13

Fire extinguisher provided

14

Rear Side Mirror

15

Seat Belt

16

Triangular Retro Reflectors 4 nos.


(Front side 02, Rear side 02)

17

Chock blocks (min 02 nos.)

18

Delay Start Mechanism

19

Validity of PUC Certificate

20

Validity of Fitness Certificate

FOR L&TC

Observation

Measures

FOR LTMRHL/LBC

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

EQUIPMENT FITNESS REPORT FOR VEHICLE & EARTH MOVING EQUIPMENT


Ref: HMRP-15-B Rev 00
___________________________________________________________________________
Project

: Hyderabad Metro Rail

Client

: Hyderabad Metro Rail Limited

Independent Engineer

: Louis Berger Consulting Pvt.Ltd

Concessionaire

: L&T Metro Rail Hyderabad Limited

Contractor

: L&T Construction

B&F IC

Infra IC

___________________________________________________________________
Make / Model
:
Asset code (If applicable)
Owned by
:

Identification/Reg No
Date :
Inspected Team :

Sl.
No.

Check Points

Engine condition

Clutch / brake

Hydraulic System

Guards / Covers / Doors

Fastener lock pins / Keys.

Horn / Reverse horn / Lights/

Indicators / Wiper Blades

Operators fitness

Tyre pressure

10

Condition of Battery and Lamps

11

Operating levers / steering

12

Gauges & warning devices

13

Fire extinguisher Provided

14

First Aid Box

15

Swing Alarm Provided

16

Validity of PUC Certificate

17

Validity of Fitness Certificate

18

Delay Start Mechanism

Observation

Remarks

This Vehicle/ Earth Moving Equipment has been checked for the above points and
Found FIT for deployment
_________________
(P&M Engineer)
FOR L&TC

Found UN FIT for deployment


___________________
(EHSO)
FOR LTMRHL/LBC

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Weekly Environmental Inspection Checklist


HMRP-28 A3 Rev 00
_______________________________________________________________________________________
Project

: Hyderabad Metro Rail

Client

: Hyderabad Metro Rail Limited

Independent Engineer

: Louis Berger Consulting Pvt.Ltd

Concessionaire

: L&T Metro Rail Hyderabad Limited

Contractor

: L&T Construction

B&F IC

Infra IC

________________________________________________________________________________________
A) SUMMARY SHEET
1.

Major issues of non-conformity in the past week are:


Issue

2.

Reason

(i)

Air (Specify)

(ii)

Water (Specify)

(iii)

Noise (Specify)

(iv)

Waste (Specify)

(v)

Storage (Specify)

(vi)

Housekeeping (Specify)

(vii)

Roads (Specify)

Over the last week have been able to implement environmental management requirements as per
contract
Yes

if not yes reasons are

No
(i)
(ii)

3.

Following issues have not been resolved for more than past two weeks
(i)
(ii)

4.

Support/Clarification from L&TMRHL and/or its representative required in the following:


(i)
(ii)

5.

Complaints received in the past week.


(i)

From

(ii)

Public

(iii)

Client

(iv)

Statutory Agency

Action Taken

Reasons for Delay

Auditor:

Project Manager

Contract Number:

Contractor

Environmental Manager

Project Manager

Document No.:

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

B) Weekly Environmental Inspection


Report No.:

Inspection Date:

Inspected by :

Inspection Area:

Participants:

Action
S. No.

Item

1.0

AIR POLLUTION

1.1

Dust
(approach
roads,
adjacent
roads,
working
area,
cement
handling etc.)

Site Satisfactory

Generators

Satisfactory

1.2

Observation

Remarks

Site Dusty
Sprinkling carried out as required
Excavate removal within 2 days

Black smoke
Leaking oil
Drip Pans not available
1.3

Vehicles

Satisfactory
PUC certificate available
Black smoke
Wheel Washed /Cleaned
Leaking oil
Side of vehicle clear of mud
Material transported in closed
manner

1.4

Air Monitoring

Carried out as per contract Results


reported as per contract Remedial
measures in place where
required

2.0

WATER POLLUTION

2.1

Site Drains

Drainage system functional

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

By date

By
whom

Action
S. No.

Item

Observation

Remarks

No Contamination
Not blocked by debris/ garbage No
indications of Oil spilled in drains
Storage of chemical waste not
nearby
2.1

Site Drains

Storage of refuse/ excavate muck not


near the drains

2.2

Adjacent Drains

Not damaged
No signs of pouring bentonite No
signs of pouring Chemicals
Signs of discharging Silt/ debris

2.3

Separator Tanks

Tank not full of silt


Tank regularly emptied

3.0

NOISE POLLUTION

3.1

Noise
control
measures

All powered mechanical equipments


are sound reduced
Acoustic / enclosures constructed in
areas of excessive noise
Equipment located and directed
away from noise receptors

3.2

3.3

Generators
provided
with
acoustic
enclosures

Effective

Noise
Monitoring

Carried out as per contract

Not effective
Not provided

Not exceeded baseline values


Remedial measures in place
Results evaluated statistically for
inclusion in Monthly repot

4.0

WASTE MANAGEMENT

4.1

Waste Identified

Chemical Flammable Corrosive


Construction related/ oil/ Filters/
Batteries
Hazardous
Other (Specify)

4.2

Storage
Containers

Adequate number and properly place


&

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

By date

By
whom

Action
S. No.

Item

Observation

Remarks

Proper quality

Bins

Emptied regularly
Labeling proper
No spillage on container surface
noticed
Pollutants (e.g. waste chemical), not
dumped in bins
Recyclable (e.g. metal) not dumped
in garbage bins
4.3

Oil Waste

Drip pans available


No oil stains on ground
Spill absorption material available
Waste oil poured in to designated
waste drums
Used oil filters not dumped in
garbage bins

4.4

Excavate/Muck

Storage satisfactory/ properly


secured
Dumping in authorized areas
No interference with nearby drainage

5.0

STORAGE

5.1

Diesel Storage

Extensive diesel spillage on ground


not visible
Drip pans used when pumping diesel
Pipes / connectors/ pumps not
leaking
Not located close to storm water
drains
transfer arrangement satisfactory

6.

AESTHETICS & CLEANLINESS

6.1

Housekeeping &
Hygiene

Designated storage area for


materials
Scraps/brickbats/rubbish scattered at
site
Proper space for handling waste
Area Clean and dry
Stagnant water treated weekly

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

By date

By
whom

Action
S. No.

Item

Observation

Remarks

Proper stacking of drums


Barricades are clean, in line, firmly
secured and proper earthling
Water not allowed to accumulate in
work area for any reason
7.0

ROADS

7.1

Access Roads

Satisfactory Maintenance
In urgent need of Maintenance

7.2

Public
Roads
used
by
Contractor

Satisfactory maintenance
Repair not carried out

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

By date

By
whom

WEEKLY ENVIRONMENTAL AUDIT

AUDIT No. :

WEEK ENDING :

POGRESS IN THE LAST WEEK:

PLANNING /GOALS FOR THE NEXT WEEK:

Environmental Manager

FOR L&TC

Project Manager

Document No.:

FOR LTMRHL/LBC

Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

ELECTRICAL SAFETY INSPECTION CHECKLIST


Ref: HMRP-09-A2 Rev 00
_____________________________________________________________________
Project

: Hyderabad Metro Rail

Client

: Hyderabad Metro Rail Limited

Independent Engineer

: Louis Berger Consulting Pvt.Ltd

Concessionaire

: L&T Metro Rail Hyderabad Limited

Contractor

: L&T Construction

B&F IC

Infra IC

______________________________________________________________
Inspected By
Date
Sl.
No.

:
:
Points

Observation

Measures

CABLES
1
2

Whether the condition of Cable is


checked?
Are Cables received from other site
checked for Insulation Resistance before
putting them into use?

Are all main Cables,


underground / Overhead?

Are welding Cables routed properly above


the Ground?

Are
welding
overlapping?

Is any improper jointing of Cables wires


prevailing at Site?

&

taken

electrical

either

Cables

DBs / SDBs
1

Is earth conductor continued upto DB /


SDB?

Whether DBs & extension boards are


protected from rain / water?

Is there any overloading of DBs / SDBs?

Are correct / proper fuses & CBs provided


at main boards & sub- boards?

Is energised wiring in junction boxes, CB


panels & similar places covered all times?

Page 1 of 3
Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Sl.
No.

Points

Is periodical maintenance done and loose


connections are avoided?

Observation

Measures

Page 2 of 3
Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM

Sl.
No.

Points

Observation

RCBO / RCCB
1

Whether the connections are routed through


RCBO / RCCB?

Is RCBO/RCCB sensitivity maintained at 30


mA?

Are the RCBO/RCCB numbered & tested


periodically & test results recorded in a
logbook countersigned by competent person?
EARTHING

Is neutral earthing ensured at the source of


power (Main DB at Gen. or Transformer)?

Whether the continuity & tightness of earth


conductor are checked?

Mention the SWG of earth conductor used

Mention the value of Earth Resistance


ELECTRICALLY OPERATED MACHINES /
ACCESSORIES

Whether the plug top provided for all electrical


connections?

Are all metal parts of electrical equipments &


light fittings / accessories grounded?

Is there any shed / cover for welding


machines?

Are light fittings fixed at proper places?

Are Portable power tools maintained as per


norms?

Any other Information

Page 3 of 3
Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM