INDEX
Clause
Clause Description
1.0
SCOPE OF WORK
2.0
3.0
OPERATING STRATEGY
4.0
SEQUENCE OF ACTIVITIES
5.0
CONSTRUCTION METHODOLOGY
6.0
6.2
6.3
QUALITY FORMATS
7.0
8.0
Page No.
ENVIRONMENTAL TEST
7.02
HEALTH
7.03
SAFETY
ATTACHEMENTS/ANNEXURES
SCOPE OF WORK:
This Construction Work Procedure is applicable for execution of Typical Toilet Water Proofing works as per
approved drawing and technical specification, at Uppal Depot, Hyderabad Metro Rail Project.
This work procedure includes the following:
a.
b.
c.
d.
e.
2
2.2 DRAWINGS:
i)
S.No
Rev no
Description
OPERATING STRATEGY:
3.1
ORGANISATION CHART
XXXXXXXX
PROJECT MANAGER
XXXXXXX
PLANNING
xxxxxxxxxxxx
CONSTRUCTION
MANAGER
XXXXXXX
P&M
INCHARGE
XXXXXXX
SHE MANAGER
XXXXXX
QUALITY
xxxxxxxxxxx
Site Engineer
(Day & Night)
XXXXXX
P&M Engineer
Safety
Steward
Xxxxxxxx
Q/C Engineer
xxxxxxxx
Q/A Engineer
XXXXXXXX
Site Engineer
(Day & Night)
Organize & manage all resources and field activities to achieve an efficient and effective completion
of the contract, within the agreed time and cost, whilst paying due regard to safety and meeting
Quality requirements.
Ensure the construction activity as per approved construction & work methods.
Ensure completion of activities to meet the project time schedules
Organize & manage all resources and field activities to achieve an efficient and effective completion
of the contract, within the agreed time and cost, whilst paying due regard to safety and meeting
Quality requirements.
Implementation of Project Quality Plan, EHS Plan, Liaison with Customer, Regional, Head Office and
local authorities.
Negotiation with S/c and suppliers for fixing rates.
Improving Customer satisfaction including handling customer complaints
Co-ordinate with Water proofing agency on day to day activities to monitor work sequence &
progress.
Ensure the materials brought to site for work is approved one only.
To ensure the work shall be executed and inspected stage wise as per approved work procedure.
Interacts with the LTMRHL Representatives and generates RFIs for inspection activity as per Inspection
plan.
To ensure that the relevant project specification, approved working procedure and approved shop
drawings are available in coordination with construction manager and QC engineer.
Submits the requirement of materials and other resources for his work to Construction manager.
Liaison with internal departments like Planning cell, Quality control cell, Plant & Machinery
department, Safety department and Stores for synchronizing all activities in execution.
Ensures to implement all mandatory safety requirements within his work limits.
Ensure all works are carried out as per the working procedure.
Follows the Inspection plan, Test plans and submits records to LTMRHL for their reviews and approval
through EDMS.
Maintain all format and checklist
Responsible for Operational inspection and maintenance of P&M equipments on regular basis
Reporting of required data related for operation and maintaining records.
Responsible for co-ordination with site engineer for arranging dewatering pump.
Responsible for arranging power supply at workplace day to day basis by co-ordination with site
engineer.
Ensure continuous availability and proper functioning of P&M at site.
Ensure periodic preventive maintenance & timely breakdown repairs of all machinery & electrical
equipment as per their inspection manuals.
Check the quality of materials cement, Fine aggregate and Coarse aggregates etc.
Check and ensure the water proofing materials batch number, manufacturing date, MTC and expiry
date before opening the seal for usage.
Responsible for inspecting the stage wise work as per IPT and clearing for next stage activity after
getting clearance from LTMRHL.
Responsible for the compressive strength of the concrete, cement mortar batched at site or RMC
Identify material sources, and conduct material tests and ensure conformity with specifications &
standards
Conduct Routine Tests on materials as per ITP for conformance and maintain records.
Identify, Calibrate and maintain Master List of Testing and Measuring Equipment
Responsible for submission of all reports related to quality matters
Responsible for casting of concrete/Mortar cubes for every batch produced from the plant or site.
Responsible for the compressive strength of the concrete/Mortar batched at site.
Disseminate and Communicate HSE Policy, HSE Management System requirements to site personnel.
Provide necessary advice, information and support in the effective implementation of the HSE
Management System requirements and this HSE plan.
Updating the HSE Plan to the requirements of the activities being carried out when there is a revision.
Plan and conduct Internal HSE training programs, initiate drive to promote HSE awareness and
performance
Carry out HSE inspection of Work Area, Work Method, etc. as per the IMS requirement.
Advising line management in preparing HSE risk assessment for the new activities.
Creating HSE awareness through PEP talks.
Conduct investigation of all incidents / dangerous occurrences & recommend appropriate corrective
measures.
Advice & co-ordinate for implementation of Work Permit Systems.
Convene HSE Committee meeting & minute the proceedings for circulation & follow-up action.
Plan procurement of PPE & safety devices and inspect before use as per laid down norms.
Report to CHSEM on all matters pertaining to status of HSE and promotional programme at site level.
Facilitate screening of workmen and conduct HSE induction.
Monitoring administration of First Aid.
Conduct Fire Drill, Procure, inspect and arrange to maintain Fire Extinguishers.
Organise campaigns, competitions & other special emphasis programmes to promote HSE in the
workplace.
Record, analyse and cascade lateral learning points from First Aid Cases, Near Miss Cases & Accidents
to all project personnel and analyse the trends & effectiveness.
Maintain all HSE related documents & Update HSE training records
Identify potentially unsafe acts, areas and implement practice measures and educate staff &
workmen.
Investigate unsafe occurrences and initiate corrective steps.
Discuss near miss accidents with staff and workmen
Involves in regular safety pep talks, periodical demonstrations of safe practices in work.
Helps to provide necessary safety materials as per work requirements.
Implement EHS system at site; supervise for the safety lapse before commencement of work.
Organize training programs for safety awareness.
Coordinates with site administration, first-aid centre, doctors & hospitals during emergency.
Manpower
(other than in organization chart)
Nos. per
Day Shift
Nos For
Night Shift
1
2
3
Applicators
Helpers
Mason
02
04
02
02
04
02
4
5
Unskilled
Vendor Supervisor
10
01
10
01
Total Manpower
19
Remarks
19
Cement
Water
CEBEX 200
NITOBOND SBR Latex
HYDROPROOF
SILICA SAND
CONPLAST X 421 IC
3.2.2.1. Cement:
3.2.2.2. Water:
Water shall be conformed the IS: 3025 and IRS Concrete Bridge code
Water shall be potable and free from substances that may be deleterious to concrete or
steel. Water shall be fresh, clean and free from injurious amounts of oil, salts, acids, alkali,
other chemicals and organic matter.
Cebex 200 is a plasticising and hydrogen free expansion grout admixture is supplied as a powder.
Cebex 200 is a suitable pressure grouting admixture complying with ASTM C827
Nitobond SBR (latex) is modified styrene butadiene emulsion specially designed for use as a bonding aid and
gauging liquid for cementitious systems.
Nitobond SBR (Latex) shall be procured only after obtaining approval from LTMRHL.
Nitobond SBR (latex) materials shall be used and application done as per manufacturer specification and
recommendations.
3.2.2.5. HYDROPROOF:
Hydroproof is single component acrylic polymer from cement based water proof composite
coating membrane.
Hydroproof formulated to be mixed with cement on site or simply brush applied over
concrete or masonry surface to provide an effective waterproof membrane.
Hydroproof shall be used and application done as per manufacturer specification and
recommendations.
3.2.2.6. SILICA SAND or RIVER SAND:
Conplast X421IC is a dark brown liquid based on lignosulphonates which mixes readily with
water and therefore disperses evenly.
Conplast X421IC shall be conformed to IS 2645 2003.
3.2.3
EQUIPMENTS:
Sl.No.
Machinery
Remarks
Chipping Machine
One No
Marble/Cutting Machine
One No
Wooden Float
Brush
Rollers
10
Mason Trowel
Batching Plant
12
Chiller Plant
13
Loader
14
Tippers
15
16
Transit mixers
17
18
Air Compressor
Stone chiselers
19
from
5.
CONSTRUCTION METHODOLOGY:
The joint inspection shall be done prior to surface preparation along with LTMRHL.
If any defect identified, the same should be rectified with approved methodology by LTMRHL.
The concrete surface and construction joints location (Slab & Beam) has to be clean thoroughly by
removing the debris and mortar droppings, loose particles and any other foreign materials, which may
affect the adhesion the further treatments with the mother surface.
If any honeycombs/defects are identified in concrete surface, loose particles shall be removed from
that surface by and it should be finished with approved materials and approved CWP.
HYDROPROOF XTRA and packing the all honeycombed area either Conbextra GP2 / Renderoc RG of
FOSORC
Note: CWP for rectification works shall be submitted separately and obtained approval from LTMRHL.
5.02. Injection Grouting/Pressure Grouting:
The entire construction joint portion at every one meter c/c holes shall be drilled for fixing of nozzles
with drilling machine to the required depth as per annexure scheme drawing.( Annexure xx)
PVC/GI nozzles shall be fixed in to holes and gap shall be filled with quick setting cement only.
The nozzles shall be fixed from inside only. Outside the joint shall be filled with renderoc plug after
cleaning the in around joint.
The approved grout materials shall be procured and shifted to site grouting location.
The grout materials (CEBEX 200 plasticizing and hydrogen free expansion grout admixture) shall be
mixed with cement and water.
The grout materials one pocket (225 grams) shall be mixed with one bag of cement.
Mixing of grout materials shall be done with mechanically powered slow speed drill machine fitted
with stirrer
The cement shall be slowly added to Cebex 200 grout mixture along with water (20 to 22 liters per
bag) and mixed with drill machine.
Mixing shall be continued for 5 minutes as per manufacturer recommendations, till it become smooth
even consistency obtained.
After nozzles set completely, the pressure grouting application shall be started.
The grouting machine pipe out let shall be fitted with existing nozzles.
The grout materials shall be grouted with pressure grouting machine (40 Psi capacity) in to nozzles till it
get filled and grout materials shall come out from the nozzle.
The mixed grout materials shall be consumed within 30 minutes of final mixing time.
After completion of grouting the nozzle shall be sealed with renderoc plug materials only.
The nozzles shall be removed after 24 hours or the grout is set, whichever is later.
The exposed portion of nozzles from concrete surface shall be cut and removed.
The depressions shall be filled with renderoc plug materials and finished to match wall surface.
5.03.
After completion of Injection/pressure grouting, water shall be filled in water tank up to a free board
level.
Water ponding test shall conform the section 10 of IS3370-Part 1.
The water shall be filled up to free board level.
The water level (initial level) shall be marked on wall surface at all corners.
The water level shall be monitored and recorded at subsequent intervals of 24 hours over a period of
seven days along with LTMRHL.
The water ponding test shall be continued for 7 days and level shall be recorded.
The continuous observation shall be done for outer wall surface for any leakage
The total drop in surface level over a period of seven days shall be taken as an indication of the water
tightness of the tank.
If the total drop in surface water level does not exceed 40 mm for a period of seven days, tank may
be deemed to be water-tight.
If the structure does not satisfy the condition of test, and the daily drop in water level decreasing, the
period of test may be extended for a further seven days and if specified limit is then reached, the
structure may be considered as satisfactory.
If any leakage found, it shall be rectified by pressure grouting as explained above in section 5.02.
5.04.
After completion of water pond test, water shall be drained out and allow to get dry
concrete surface.
The entire surface to be treated must be ensured thoroughly cleaned.
The surface must also be free from oil, grease, wax or any other foreign materials which might
affect adhesion.
5.04.2. Priming/First Coat:
The primer/first coat shall be prepared with the ratio of 1:2:4 (1 part of Hydroproof: 2 part of
Water: 4 parts of cement)
Mixing shall be done thoroughly with slow speed drilling machine attached with mixing
paddle till it get uniform colour and consistent slurry avoiding any lump formation.
Do not mix more than two minutes.
The mixing materials shall be consumed with in pot life(30 minutes).
Retempering the mix with water should not be done. Occasionally stir the materials till the
entire quantity is applied.
Before application of water proofing paint, the concrete surface shall be weted.
The application shall be done by using paint brush consistently and the application shall be
overlapped 300 mm minimum over the vertical and horizontal surface.
The same paint shall be be applied on wall surface for minimum height of 300 mm from
finished floor level(FFL).
The minimum thickness shall be 1 to 2 mm.
The priming/first coat should be allowed to dry for 5-6 hours.
Note: To control the thickness of coat, the area coverage shall be monitored as per
manufacturer specification, ie. 16 -17 sqm/ liter for Priming/First Coat
5.04.3. Second Coat/Final Coat Application:
After drying of first coat application, second coat application shall be applied.
The second/final coat shall be prepared with the ratio of 1:2 (1 part of Hydroproof: 2 parts of
cement)
The application shall be done same as explained above in section 5.04.2.
When the second coat is in green status, silica/coursed sand shall be sprinkled prior to ensure
bonding with water proof plaster.(grain size of coarse sand shall conform to table 1 of
IS1542)
After application of final coat, initial air drying shall be allowed for 2 to 6 hours. During this
period water should not be used for curing.
Moist curing should be done for the next 24 hours by spraying water on hydroproof coating.
Following moist curing, hydroproof should be allowed to dry for three days before subjecting
it to submersion in water.
Note: To control the thickness of coat, the area coverage shall be monitored as per
manufacturer specification, ie. 4.5 -5.0 sqm/ liter for / Coat
5.05.
The concrete portion of floor area shall be free from debris and other foreign materials.
Floor area shall be cleaned properly before starting of concrete activity.
40 mm thick level pads shall be fixed at every 6 0 intervals and slope shall be maintained as
per specification and drawings.
After obtaining the clearance and approval of level pads from LTMRHL,(Refer Pour Card)
place the concrete order to batching plant trough QA/QC dept.
Toilet slab/sunken slab area should be free from debris and any other foreign materials. Keep
the sufficient manpower, tools for placing and compaction of concrete.
Ensure the grade of concrete should be as per GFC drawing before unloading from transit
mixer.
The concrete workability & temperature should be checked and recorded at batching plant
and also at site before unloading of concrete from transit mixture.
The concrete should be placed from one end and Concrete shall be compacted
immediately after placing and leveled uniformly with using hammer/floats made of steel
channels (ISMC) and long handles for manual compaction.
The approved water proofing admixture (conplast X421IC) should be mixed along with
concrete at batching plant as per manufacturer recommendations. The concrete shall be
stiff as possible ( 50 15 mm) at pour location.
The concrete surface shall be finished smoothly before final setting of concrete.
5.05.2. Water Proof Plastering:
Fix plaster buttons (50mm X 50mm size) at 2.0m intervals on the wall surface to a depth of 18mm.
The level pads shall be fixed line and plumb in order to maintain uniform thickness of plaster.
Plastering Mortar shall be prepared in proportion of 1:4, cement : sand
Volumetric boxes to be made and used for measurement.
Cement and sand to be mixed and blended together using a mechanical mixer machine or
manually. Water to be added to obtain required consistency. Water shall be added to such quantity
of dry mix prepared, which can be consumed within 30 minutes of mixing water. Unused Mortar shall
not be reworked with addition of water.
The approved water proofing compound should be added(for better results water proofing
compound shall be mixed with water, then it to be added to mortar) to the mix while mixing mortar,
125 ml of water proofing compound to 50 kg of cement bag.
The water proofing compound materials make and product approval should be obtained from
LTMRHL before using in plastering.
The surface to be plastered shall be dampened with water prior to applying the plaster mix.
The prepared Plaster Mix to be dashed against the wall with force.
Carryout plastering with reference of guide levels and finish to smooth using straight Edge, trowel and
spatula.
Polythene sheet can be laid at the floor surface, so that the fallen plaster mix can be collected and
reapplied within 30 minutes of mixing water.
Check the surface levels using straight edge and verticality with plumb and finish smooth without
undulations.
Plastering around the MEP Pipe fixtures to be trowelled to smoothness and squareness to be checked
prior to drying of mortar.
The flatness, right angle and plumb shall be checked whilst the mortar is green, so that the same shall
be rectified immediately.
The plastered surface shall be kept wet for a period of 7 days from the date of applying plaster.
Where ever the outlets of plumbing pipes are there, the gap between the pipe and concrete/wall
surface shall be filled with non-shrink grout (Conbextra GP2) materials.
Sunken portion of toilet shall be filled with brick bat coba or any other filling materials and level the
surface to the required level as per GFC drawing.
The brick bat coba materials grade shall be obtained approval from LTMRHL before using at site.
The brick bat of size 25 to 40 mm out of well burnt bricks shall be used for brick bat coba.
The brick bats coba shall be mixed in the ration of 1:4:8(1 cement/4 fine aggregate/8 brick bats) in
mechanical mixture and filled in sunken portion to the required level.
5.06.
Curing:
Exposed surfaces of concrete shall be kept continuously in a damp or wet condition by ponding or
covering with a layer of sacks, canvas, Hessian or by similar materials and shall be kept constantly wet
at least for a period of 14 days
Description of sub-activity
Fixing of temporary bench marks
Check
by
LTMRHL
MTC
QCP
QHP
10
2
3
4
5
6
11
Documentation
RFI, L F book, list of
TBMs
RFI, checklist
Format No
Remarks
LTMRHL/CMP011F01(Rev 01)
LTMRHL/AF3(Rev01)
L&TC/B&F/TF 67
L&TC/B&F/TF 67
LRMRHL/CMP011F01(Rev01)
LRMRHL/CMP011F01(Rev01)
LTMRHL/CF2
RFI, Pre-concrete
checklist and pour
cards
LRMRHL/CMP011F01(Rev01)
LTMRHL/CF2
LTMRHL/CF2
LTMRHL/TF9
Checklist
LTMRHL/TF7
LTMRHL/CF3
Production of concrete
Transportation of concrete
Temperature of concrete
10
11
12
2
3
4
5
W
W
W
W
R
R
R
R
6
7
W
W
R
R
LRMRHL/CMP011F01(Rev01)
L&T C/B&F/TF 19
LTMRHL/TF7
1
2
3
4
5
6
7
Others:
Housekeeping check list
Excavation Clearance permit
Pep talk report
Vehicle & earth moving equipment inspection
Equipment fitness report
Weekly environment inspection
Electrical safety check list
QCP
QHP
W
R
EDMS
QC
W
W
W
W
W
W
W
R
W
R
R
R
R
R
MTC
TBM
RFI
BBS
LF
PCC
Inspection
HMRP-31-A-rev 00
HMRP-14-C-Rev 00
HMRP-12-A-Rev 00
HMRP-09-AS-Rev00
HMRP-15-B Rev 00
HMRP-28-A3 Rev00
HMRP-09-A2 Rev00
Cement
IS 4031-Part1 to 6
Flyash
IS 3812-Part1
Water
IS 3025
Admixture
IS 9103
FREQUENCY OF TESTING
02 tests for every Consignment
MTC to be maintained for every batch
MTC to be maintained for every batch
IS 2386 Part-1
6
7
8
9
10
IS 2386 Part-4
IS 2386 Part-4
IS 2386 Part-1
IS 2386 3
IS 2386 Part-3
IS 2386 Part-5
IS 2386 Part-4
11
12
SPECIFICATION REQUIREMENT
Fe500 as per IS1786
Shall conform to BS 8110 part 1
Shall conform to BS 6319
14
15
16
17
18
19
IS 1199
BS1881 Part 6
BS1881 Part 6
BS 1881
MoRT&H
As per approved
Calibration of batching plant
method
Plastering For routine tests during permanent works
Cement
IS 12269
2
3
IS 1542
IS 3025
Other tests
S.No.
TEST TYPE
1
Calibration of auto level
2
Environment monitoring
3
4
Illumination monitoring
Noise levels monitoring
As per Manufacturer
specification
A.P State
Pollution Board
BOCW act
BOCW act
No of samples
1
2
3
4
4+1 for every 50cum or
part thereof
IS 2250-1981
CODE OF PRACTICE
Quantity
1-5 cum
6-15 cum
1630cum
31-50cum
51 above
IS 516
FREQUENCY OF TESTING
Once per 6 months
SPECIFICATION REQUIREMENT
<2mm per Km
Vehicle / machinery and equipment operation, maintenance and refuelling shall be carried out in such a
fashion that spillage of fuels and lubricants does not contaminate the ground.
Shall ensure that no trees / branches to be fell by labourer for fuel, warmth during winter. Enough provision of
fuel to be ensured.
General refuse shall be stored in enclosed bins or units and it should to be separated from construction and
chemical wastes.
7.2. HEALTH:
Section In-charge / Engineer shall ensure all workers are screened before engaging them for duties.
In-charge shall ensure availability of first aider with first aid kit.
Shed / shelter shall be provided for workers for weather protection along with drinking water.
7.3. SAFETY:
REFERENCE :
SAF 30
The following persons have been appointed to be our representatives on site for all site safety emergencies.
Position
Name of
Representative
RAJESH B KONDLE(RBK)
A G CHANDRA SEKHAR
S K JHA
K. SRINIVAS
P CHAITHANYA
Home
Tel.
-
Mobile No.
PM
7799699880
CM
9963027004
PROJECT HEAD
K. SRINIVAS REDDY
Dr. KARUNAKAR
Office
Tel.
-
ACM
9849949767
9912855721
EHSM
9666097111
DOCTOR
9985738741
886998920
IR
Project Manager
Signature
Hospital Location
Contact No:
YASHODA
HOSPITALS
+9140 24555555
IMAGE
HOSPITALS
APOLLO
HOSPITAL
JAGDAMBA
HOSPITAL
IMAGE
HOSPITALS
+9140 23750000
SWAPNA
NURSING HOME
KAMINENI
HOSPITALS
+9140 66924444
+9140 23244444
+9140 66563334
+9140 39879999
8. ATTACHEMENTS/ ANNEXURES:
1. Annexure 1 Risk Assessment
2. Annexure 2 Incident Flow
3. Annexure 3 - Formats
Contract:
Signature:
Date: 13.07.2013
KEY:
L = Likelihood
S = Severity
RISK RANKING:
Task/Element
Confine Space
Potential Hazards
Shifting of materials
Working Platform
Improper shifting of
materials
Fall of material, hitting,
slip & fall
Population at
Risk
Workmen
Employee &
Workmen
Employee &
Workmen
Employee &
Workmen
Risk Rating
Revised Rating
Control Measures/ Follow-up Checklist
Spillage of chemical
Employee &
Workmen
Nonuse of
PPEs
Employee &
Workmen
No approach/
No access
Employee &
Workmen
Contract:
Signature:
Date: 13.07.2013
KEY:
L = Likelihood
RISK RANKING:
Task/Element
L = Low priority to be
implemented when resources
allow.
Population
Risk Rating
Potential Hazards
at Risk
Confine Space
Shifting of
Materials
Working
Access /egress
/ Working
Platform
Mixing /
Placing / Grout
(Application)
Employees /
Workmen
Chemical
Injury to arms/
eyes
Employee &
Workmen
Improper shifting of
Materials
Employee &
Workmen
Falling of material,
hitting, slip & fall
Spillage of chemical
Employee &
Workmen
S = Severity
Employee &
Workmen
Revised Rating
L
S
R
Control Measures
No approach/
No access
Employee &
Workmen
Employee &
Workmen
RISK MATRIX
SEVERITY
PROBABILITY
Nonuse of
PPEs
4
5
L
M
M
M
M
H
H
H
H
H
Location
Topics discussed
Response of workmen
Signature:
-----------------------HSEO
---------------------Site Engineer
Sl.No
Land
Disposal of oils
Disposal of batteries
Disposal of waste
Wood waste
Concrete waste
Biological waste
10
Others
II
Water
Conservation measures
Sewage disposal
III
Air
Exhaust emissions
IV
Noise
Date:
Observation
Measures
Description
Sl.No
Site Engineer
Observation
EHS OFFICER
Measures
Client
Independent Engineer
Concessionaire
Contractor
: L&T Construction
B&F IC
Infra IC
___________________________________________________________________
To identify safe work practices related to working inside a confined space or a vessel or a plant / equipment.
A.
1.
2.
3.
DATE :
YES
6. HAVE ALL THE ELECTRICAL / AIR / HYDRAULIC EQUIPMENT / DRIVES BEEN DISCONNECTED
YES
7. HAVE THE PERSONS REQUIRED TO ENTER THE CONFINED SPACE BEEN TRAINED IN DEALING
WITH THE SPECIFIED HAZARDS
8. PPE PROVIDED
9. HAS A RESCUE TEAM EQUIPPED WITH EMERGENCY RESCUE DEVICES PUT ON STANDBY
YES
YES
YES
YES
YES
13. LIST OF AUTHORIZED PERSONS TO WORK INSIDE A CONFINED SPACE & THE RESCUE TEAM (LIST TO BE
ENCLOSED)
I have checked the above points and found conditions suitable to undertake the work.
_____________________
Name of the permittee
(Site Engineer)
__________________
Signature
______________________
Designation
FOR L&TC
________________________
Section In-charge
_______________
EHSO
FOR LTMRHL/LBC
Shifting of Materials /
Fixing & Placing
(Application)
1
Chemical
Spillage
AIR
WATER
Dust due to
the mixing /
Pollution /
Vapors
Air pollution
due to
emissions
from diesel
engines
Contamination Due to
flowing to nearby
drains
LAND
Contamination
RATINGS
OTHER
DURATION
IMPACT
PROBABILITY
ASPECT
SEVERITY
ACTIVITY
SCALE
S.No.
Note:
SCALES:
RATINGS
1
SCALE OF
IMPACT
Localized
SEVERITY OF
IMPACT
very low
PROBABILITY OF
OCCURANCE
Rare
Department
Low
Once a year
Factory
Moderate
Once a month
City
High
Once a week
Global
Very high
Intermittently/
when activity goes
on
DURATION
OF IMPACT
LAST
Momentary
Lasts for a
day
Lasts for a
month
As long as
aspect
continues
Permanent
MINOR INCIDENTS
(Such as Near miss, First-Aid, Property damage, Traffic zone
incidents etc.)
STEPS
L&T Construction
LTMRHL
Receive SMS
(by EHS Department)
Receive e-mail
(by EHS Department)
Inform
By SMS Immediately
Identify, Register and send
e-mail (register in .exl)
Complete correction
Investigate
1
2
MAJOR INCIDENTS
(such as Dangerous Occurrences, LTI, Fatal, Working zone incidents)
STEPS
1
2
L&T Construction
LTMRHL
Inform
By SMS Immediately
Identify, Register and send email (register in .exl)
Receive SMS
(by EHS Department)
Receive e-mail
(by EHS Department)
Complete Correction
Implement Corrective
Action
Inform By e-mail
Discuss in
weekly review meeting
Discuss in
weekly review meeting
10
11
12
Discuss in
weekly review meeting
Infra IC
Date:
Date:
ITEM LOCATION
Corridor No:
Stage No:.
Area name:
Drawing Number:
Details of item :
Reduced From:
level
To:
Requested by:
Quantity:
Inspected by:
Name
Name
Date
Date
Time
Time
Signature:
Signature:
Details of inspection :
1. Inspection completed, the contractor may proceed with the works.
Yes
No
Yes
No
Yes
No
Remarks by LTMRHL:
FOR L&T
Distribution :
(Rev.01)
Infra IC
Date:
Drawing Number:
Instrument and its number:
Offset
Back
Sight (m)
FOR L&T C
Intermedi
Heigth of
Fore Sight
ate Sight
collimation
(m)
(m)
(m)
Reduced
level (m)
Required
Level (m)
Difference
Remarks
PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR
CHECK LIST FOR INJECTION /PRESSURE GROUTING & APPLICATION OF WATER PROOFING COMPOUND/Bitumen Emulsion
Structure
Floor Level
Location
Drg. Reference
Sl.no
Description
Check for
01
02
03
04
05
06
07
Date
Verified Signature
L&T
LTIL
08
Surface preparation
Remarks
Stage No:
Source
Portland Cement
Flyash
Micro Silica
Crushed Aggregate
River Sand
Admixture
Grade of Concrete:
Ingredients of Mix
Infra IC
Qunitity per
cum (as per
mix design)
(kG)
2
Free Moisture in
Water
Water absorption Free Moisture
ingredients (kG)
absorption (kG) (col.4 = clo.2 x in ingredients
(col.6 = col.2 x col.5
(%)
col.3 / 100)
(%)
/ 100)
3
4
5
6
for
_______cum
(kG)
col.2 =
Flyash (kG)
col.2 =
col.2 =
col.2 + col.6 =
col.2 + col.6 =
col.2 + col.6 =
col.2 + col.6 =
Admixture (kG)
col.2 =
FOR L&T C
Drawing no.
Structure
Location
Segment
Date:
Grade of concrete
Quantity of concrete
Cement Required in MT
:_________________
Method of transportation
Method of mixing
Method of pouring
Admixture
Slump observed:
1
mm
No. Of cubes taken
ID Marks on cubes
APPROVED TO POUR
FOR L&T C
Infra IC
mm
cum/hour.
mm
mm
mm
mm
:
:
: YES/ NO
Infra IC
Date :
Stage
Location
Name
Part
Identification
number
FOR L&T C
Time of
Transit mixer
observation
number
Grade of
concrete
Slump
observed
(mm)
B&F IC
Infra IC
Date of testing:
Stage No:
Location / Identification mark
Grade of
concrete
W-C ratio
Age on
testing
FOR L&T C
Cube
number
Weight of
cube (gm)
Machine
load (kN)
Compressive strength
(N/mm2)
Individual
Ave
POST-CONCRETE CHECKLIST
PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR
Drawing no.
Location
Structure
Segment
Quantity of concrete poured
Achieved pouring time
Date of pour
Date of side shutter stripped
Date of soffit shutter stripped
Infra IC
:
POSITION/ DIMENSIONS
Alignment
Levels
Dimensions
Non-conformance report no.
: S / NS
: S / NS
: S / NS
:
dated
CURING
Method
Starting date
Finishing date
Checks
Date
:
:
:
:
Remarks
References: S-Satisfactory
SURFACE DEFECTS
NS-Not satisfactory.
dated:
CRACKS
No cracks/ cracks
date observed:
Inspected by:
Date:
Signature:
Project
Client
Independent Engineer
Concessionaire
Contractor
B&F IC
Infra IC
Tested By
Proposed Use
Source of Sand
Date of testing:
Stage No:
Trials
2
Average
FOR L&T C
POST-CONCRETE CHECKLIST
PROJECT
CLIENT
INDEPENDENT ENGINEER
CONCESSIONNAIRE
CONTRACTOR
Infra IC
Page 01 of 02
Date:
Signature:
QUALITY FOLLOW-UP
Non-conformance report no.
Given by
Signature
No.
Mean
SD
Max
Min
Compliance
Slump (mm)
Yes/ No
Yes/ No
Yes/ No
Any non-compliance
: Yes/No
:
If yes- action taken
===============================================
===============================================
===============================================
=====......................................................................................................................................................
........................................................................................................................................................................
........................................................................................................................................................................
........................................................................................................................................................................
........................................................................................................................................................................
..................==========================================
===============================================
=================.....................................................................
DATA TRANSFER
Date passed to structure records
FOR L&T C
: Yes/ No
FOR LTMRHL / LBC
Page 02 of 02
CONCESSIONNAIRE
CONTRACTOR
: L&T Construction
B&F IC
Corridor No:
Stage No:
Structure
Floor Level
Location
Drg. Reference
Sl.no
01
Infra IC
Type
Description
Check for
Clearance for plastering (like door or window frame
Date:
Verified Signature
L&T Site
L&T QA
03
04
05
06
07
08
Guideline:
Type
Wall Plastering
Internal
External
1st coat
2nd coat
Ceiling plastering
Thk.
Ratio
12mm
1:6
12mm
6mm
6mm
1:6
1:4
1:3
FOR L&T C
FOR LTMRHL
Remarks
HOUSEKEEPING CHECK-LIST
Ref: HMRP-31 A Rev 00
__________________________________________________________________________________________
Project
: Hyderabad Metro Rail
Client
: Hyderabad Metro Rail Limited
Independent Engineer
: Louis Berger Consulting Pvt.Ltd
Concessionaire
: L&T Metro Rail Hyderabad Limited
Contractor
: L&T Construction
B&F IC
Infra IC
__________________________________________________________________________________________
Location:
Date:
S.NO
POINTS TO BE CHECKED
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Are the machines & equipment kept clean while working &
guarded properly?
11.
12.
13.
14.
YES
NO
REMARKS
SIGNATURE CHECKED BY
SIGNATURE WITNESSED BY
SITE-INCHARGE/ ENGINEER
Client
Independent Engineer
Concessionaire
Contractor
: L&T Construction
B&F IC
Infra IC
___________________________________________________________________
(In respect to (i) Existence of service lines and utilities (ii) In the proximity of existing structures,
buildings, foundations, installations like gas, electrical service stations etc. (iii) Any other conditions
which may result in serious hazardous consequences.)
Please permit the following excavation job as per sketch enclosed:
Signature:
Signature:
ISSUING AUTHORITY
__________________________________________________________________________________
_
Note: The scope of this permit is limited to carrying out the excavation work safely. This permit is not
intended / applicable till closing of the excavated area.
FOR L&TC
FOR LTMRHL/LBC
Client
Independent Engineer
Concessionaire
Contractor
: L&T Construction
B&F IC
Infra IC
______________________________________________________________
Make / Model
Job No.
Inspected By
Date
:
:
:
:
Sl. No.
Engine condition
Hydraulic System
Operators fitness
10
11
12
13
14
15
Seat Belt
16
17
18
19
20
FOR L&TC
Observation
Measures
FOR LTMRHL/LBC
Client
Independent Engineer
Concessionaire
Contractor
: L&T Construction
B&F IC
Infra IC
___________________________________________________________________
Make / Model
:
Asset code (If applicable)
Owned by
:
Identification/Reg No
Date :
Inspected Team :
Sl.
No.
Check Points
Engine condition
Clutch / brake
Hydraulic System
Operators fitness
Tyre pressure
10
11
12
13
14
15
16
17
18
Observation
Remarks
This Vehicle/ Earth Moving Equipment has been checked for the above points and
Found FIT for deployment
_________________
(P&M Engineer)
FOR L&TC
Client
Independent Engineer
Concessionaire
Contractor
: L&T Construction
B&F IC
Infra IC
________________________________________________________________________________________
A) SUMMARY SHEET
1.
2.
Reason
(i)
Air (Specify)
(ii)
Water (Specify)
(iii)
Noise (Specify)
(iv)
Waste (Specify)
(v)
Storage (Specify)
(vi)
Housekeeping (Specify)
(vii)
Roads (Specify)
Over the last week have been able to implement environmental management requirements as per
contract
Yes
No
(i)
(ii)
3.
Following issues have not been resolved for more than past two weeks
(i)
(ii)
4.
5.
From
(ii)
Public
(iii)
Client
(iv)
Statutory Agency
Action Taken
Auditor:
Project Manager
Contract Number:
Contractor
Environmental Manager
Project Manager
Document No.:
Inspection Date:
Inspected by :
Inspection Area:
Participants:
Action
S. No.
Item
1.0
AIR POLLUTION
1.1
Dust
(approach
roads,
adjacent
roads,
working
area,
cement
handling etc.)
Site Satisfactory
Generators
Satisfactory
1.2
Observation
Remarks
Site Dusty
Sprinkling carried out as required
Excavate removal within 2 days
Black smoke
Leaking oil
Drip Pans not available
1.3
Vehicles
Satisfactory
PUC certificate available
Black smoke
Wheel Washed /Cleaned
Leaking oil
Side of vehicle clear of mud
Material transported in closed
manner
1.4
Air Monitoring
2.0
WATER POLLUTION
2.1
Site Drains
By date
By
whom
Action
S. No.
Item
Observation
Remarks
No Contamination
Not blocked by debris/ garbage No
indications of Oil spilled in drains
Storage of chemical waste not
nearby
2.1
Site Drains
2.2
Adjacent Drains
Not damaged
No signs of pouring bentonite No
signs of pouring Chemicals
Signs of discharging Silt/ debris
2.3
Separator Tanks
3.0
NOISE POLLUTION
3.1
Noise
control
measures
3.2
3.3
Generators
provided
with
acoustic
enclosures
Effective
Noise
Monitoring
Not effective
Not provided
4.0
WASTE MANAGEMENT
4.1
Waste Identified
4.2
Storage
Containers
By date
By
whom
Action
S. No.
Item
Observation
Remarks
Proper quality
Bins
Emptied regularly
Labeling proper
No spillage on container surface
noticed
Pollutants (e.g. waste chemical), not
dumped in bins
Recyclable (e.g. metal) not dumped
in garbage bins
4.3
Oil Waste
4.4
Excavate/Muck
5.0
STORAGE
5.1
Diesel Storage
6.
6.1
Housekeeping &
Hygiene
By date
By
whom
Action
S. No.
Item
Observation
Remarks
ROADS
7.1
Access Roads
Satisfactory Maintenance
In urgent need of Maintenance
7.2
Public
Roads
used
by
Contractor
Satisfactory maintenance
Repair not carried out
By date
By
whom
AUDIT No. :
WEEK ENDING :
Environmental Manager
FOR L&TC
Project Manager
Document No.:
FOR LTMRHL/LBC
Client
Independent Engineer
Concessionaire
Contractor
: L&T Construction
B&F IC
Infra IC
______________________________________________________________
Inspected By
Date
Sl.
No.
:
:
Points
Observation
Measures
CABLES
1
2
Are
welding
overlapping?
&
taken
electrical
either
Cables
DBs / SDBs
1
Page 1 of 3
Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM
Sl.
No.
Points
Observation
Measures
Page 2 of 3
Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM
Sl.
No.
Points
Observation
RCBO / RCCB
1
Page 3 of 3
Downloaded from EDMS by Pradeep Kumar Karne () on 26-Sep-2013 09:03:13 AM
Measures