Database Migration Methodology

Methodology for database migration is proven, time-tested and has been successfully
implemented in many projects across the globe for various clients. Blends this migration
methodology with Database Migration tool provided by Microsoft named SSMA SQL Server
Migration Assistant for executing this migration. The highlights of the methodology are as
follows:

The solution consists of two distinct stages namely, the preparation stage and the
implementation stage. This distinction provides greater control and hence better
management of a data migration project.

All the activities in the preparation stage are carried out based on the implementation stage
for data migration.

The constraints on implementation like the batch window for cut-over, data cleanliness,
national language conversion and other complexities are taken into account right from the
project start-up through the activities in the preparation stage.

Best practices and lessons learnt from earlier data migration assignments are embedded
into the approach.

The following figure shows the high-level view of database conversion methodology.

Database Conversion Methodology

understands, based on the RFP requirements and AIG investmentss response to queries, that
actual production implementation will be handled by AIG investments with support. Hence the

focus of the conversion strategy for will be on the Preparation stage only. The different steps of
the preparation stage are described in the table below:

Step

Strategy
Definition

Sub-Step

Description

Inventory

Consolidation of inventory on source and target databases, data


models, volumes of data available in the different data stores.
Migration Analyzer tool which is part of the Microsoft SSMA toolset
would be used for this purpose.

Mapping
Strategy

Finalization of mapping strategy. Target to source is the preferred


option. SSMA offers Schema & Data Migrator tool that

automatically maps most of the source Oracle database


objects to SQL Server objects. Strategy needs to be defined
for anything that does not map by the tool or that needs to be
handled differently.

Analysis

Design

Build

Tool Selection

proposes to use SQL Server Migration Assistant (SSMA) for the


migration.

Rollout
Options

Rollout or cut-over options for production data migration. The choice


of big-bang, incremental or long-bang option is decided based on
the Clients requirements and constraints

Data
Model
Analysis

Analysis of the source and target data models for cardinality and
optionality. Data stores with multiple layouts are analyzed for record
identifiers.

Data Analysis

Derivation of the domains, ranges and set of valid values for a set of
data items identified for profiling.

Data Quality
Assessment

Identification of unclean data in terms of business as well as domain


values. The detection rules are employed for this purpose.

Extraction,
Audit
and
Validation
Criteria

Derivation of extraction criteria based on the analysis results and


choice of implementation option. The audit and validation criteria are
derived based on the requirements for assessing completeness and
correctness of data migration.

Mapping

Derivation of the mapping rules and specifications based on the


source and target data structures, types and domain information.
Business logic present in stored procedures and functions also need
to be converted.

Migration
Script Design

Derivation of the sequence of execution of scripts based on the


dependencies (both technical and business). The batch window
available for cut-over is the guiding principle for the design.

Development
of Scripts

Development and Unit Testing of the database object migration


scripts, data extraction scripts, data transformation scripts (some of
the cleansing rules are accommodated as part of transformation
programs), additional data cleansing scripts, if required, audit and
data validation scripts. These scripts are also integration tested, if
required.
The Schema & Data Migrator and SQL Converter tool will be used
for actual data migration. The process steps to be executed using

Step

Sub-Step

Description

this tool for the migration would be listed down as part of the
development scripts along with any other custom scripts that are
needed.

The testing requirements as part of the build phase can vary based on the implementation
options and the business requirements. Business continuity factors, constraints in infrastructure
and availability of specialists are considered and the suitable testing methodology is
recommended. Performance management is a critical component in data migration due to the
batch window constraints on cut-over. This is addressed from the planning through the build
phases.

2.2

Database Migration Technical Approach

There are many benefits on moving to SQL Server from Oracle database. Key benefits are
listed below.

SQL Server provides Integrated Business Intelligence, Reporting and ETL features that
to improve the capabilities of the underlying solution
Reduces total cost of ownership: Lower licensing, people and administrative costs
Highly productive Microsoft tool. quickly build applications on SQL Server
SQL Server is relatively easy to install and administer

The following figure gives a high-level view of the steps for database platform migration from
source Oracle database to target SQL Server 2005 database.

Source/ Existing
Database
(Oracle)

Target Configuration Metadata


& Database Architecture
(Sql Server)

Source
Configuration
Metadata (Oracle

Database Mapping &


Translation

Target Object
Scripts & Modules

Deployment
Package for Oracle
Objects

Target Database
(Sql Server )

ORACLE to SQL Server 2005 Platform Migration Methodology

A brief overview of the different steps involved in the approach is described in this sub-section.
1. Acquire Source Metadata
In this step the detailed Metadata will be acquired for the existing Oracle database platform.
This will include (not limited to) gathering information about the following areas:

Current Hardware configuration and estimate for capacity

Current Operating System and specific configuration for the Oracle database

Oracle database configuration Parameters about Disk Storage, I/O, Cache (SQL and Data),
DB layout, Archival, Backup and so on.

Oracle database and Schema objects Partitions, Tables, Constraints, Indices, Views,
Triggers, Stored Procedures, Sequences, and so on.

OS Scripts for Oracle database administration, monitoring, alerts and so on.

Data Load, Extract SQLs, Validation SQLs and so on.

Job Scheduling Scripts

Database Security Configuration

Database Failover, High Availability, Replication configurations

The goal is to capture as much critical information as possible that is required for an equivalent
operation of the database in the target environment/platform.
These activities can be automated using a combination of:

SSMA - SQL Server 2005 Migration Analyzer tool

ORACLE 10G Administration tools

The following are some of the statistics computed by the Migration Analyzer over all database
objects in the source Oracle database. The statistics include:
Total number of database objects such as procedures, functions, triggers, tables, indexes, packages,
sequences, and views.
Total number of code lines, including per-object statistics.
Total number of SELECT, INSERT, DELETE, and UPDATE statements.
Total number of CURSORs, RECORDs, and EXCEPTIONs.
Total number and percentage of automatically convertible components.
Estimated complexity of conversion.

2. Prepare/Define Target Metadata


In this step the detailed Metadata is created for the target SQL Server 2005 platform. This will
include (not limited to) defining the appropriate information based on the requirements and
analysis of the source metadata such as:

Hardware configuration for the target SQL Server 2005 database

Operating System details relevant to SQL Server 2005 database

SQL Server 2005 Database configuration parameters

SQL Server 2005 Database and Schema objects based on analysis of existing Oracle 10G
database

Database Administration related scripts and modules

Data Load and extraction routines

Job Scheduling scripts

High Availability Configurations

Executing this step ensures that the target database platform will be in a position to support the
existing functionality without any disruption of services.

The Architecture of the target Database Platform can be created using the SQL Server 2005
Database Management tools or a default database configuration can be achieved using the
SQL Server 2005 Migration Workbench.
3. Apply Mappings and Translations
The Schema & Data Migrator toll from (SSMA) will be used for mapping and translation of
Oracle schema to SQL Server database schema. The schema is the basis for defining the target
database. In migrating from Oracle to SQL Server, the new schema can be derived in a fairly
straightforward manner from the original schema. Because of feature differences between the
two platforms, the mapping between the schemas may not be one to one. An example of where
this arises is in dealing with long-valued attributes such as BLOBs.
Oracle supports multiple BLOB-valued attributes per table while SQL Server supports only one
per table. In this case, a single table in Oracle may map to multiple tables in SQL Server.
Because of such differences, migrating the data between databases may not be a simple table
copy, because the new table structures may be somewhat different from the old ones. The
Schema & Data Migrator (SSMA) automatically converts an Oracle database schema (tables,
constraints, indexes) to a Microsoft SQL Server schema and physically migrates the data to
populate the new database.
Both source (ORACLE 10G) and target (SQL Server 2005) metadata information is compared
and mapping is generated for similar objects and translation rules are identified/applied, if there
is no one-to-one direct mapping.
There are ORACLE 10G objects which may not be migrated directly and some manual
intervention or translation is required for their migration. ORACLE 10G objects like Stored
Procedures, Data Load Scripts, and Administration scripts and alerts, High availability and
replication, and Job Scheduling scripts and so on, need some extra attention to be migrated
successfully.
Executing this step ensures that there are no gaps between the source and target database
platforms and the new database does not cause any issues in the migrated environment.
The Mappings and Translations can be created using SQL Server 2005 SSMA tool and with the
help of ORACLE 10G and SQL Server 2005 Administration tools.
Business Logic Conversion
SQL, Stored Procedures, Functions, Triggers, Package, System functions, cursors, exception
handling and transaction management are some of the business logic components that need to
be converted from Oracle to equivalent SQL Server implementation. Schema & Data Migrator
and SQL Converter will offer functionality for business logic objects migration.
The complexity of a database from a migration perspective is a function of the number of
business logic objects it contains, the size of those objects, and the particular language features
used to implement them. Additional complexity derives from differences in the system function
libraries provided in the two platforms.
For example, Oracles stored procedure language, PL/SQL, has many features not supported in
Transact-SQL (T-SQL), the stored procedure language of SQL Server, and even where similar
features exist, the languages contain many syntactic and semantic differences. To migrate a
PL/SQL object that uses a feature that has no T-SQL counterpart requires that that capability be
emulated in T-SQL using the available features. Developing a good emulation can be quite
subtle and time consuming. In fact many subtleties need to be addressed in the migration

whether developing emulations for missing features or accounting for semantic differences in
corresponding features.
4. Generate Target Database Scripts/Modules
This step is carried out once the source (ORACLE 10G) and target (SQL Server 2005)
environments have been analyzed and mappings/translations have been created and verified.
In this step the actual database scripts and/or modules are developed or generated from tools
and a release build package is created for the target database (SQL Server 2005). This is in a
deployable form and is thoroughly tested and validated in a test environment.
This release package consists of scripts for all schema objects, configuration files, data load
scripts, administration scripts, user security profiles, archival and backup modules and so on.
The scripts and modules are created based on target Operating system, SQL Server 2005
Home directory and appropriate paths.
The goal of this step is to have a validated build script which can be used as a package for
deployment in the target database environment.
The scripts/modules can be built using SQL Server Migration Assistant - SSMA, SQL Server
2005 Administration tools depending on the type of objects.
5. Deploy Target Objects
In this step, the actual database environment is created from the Deployment Release package
built in previous stages. This step is carried out once the appropriate Hardware and Operating
system have been established and infrastructure is ready to support the target SQL Server 2005
database. The objects are created by executing the Scripts and Modules in the proper order to
maintain dependencies.
The deployment process is either centralized or distributed depending on the requirements and
the objects are propagated accordingly. Connectivity is established between various servers
and client machines. The High-availability and replication options are deployed based on
various sites and terms of usage. Once the deployment is complete, the database platform is
ready for use.
6. Verify Target Database Platform
This is the final step of the Database Platform Migration approach. Once all SQL Server 2005
objects are deployed into the target environment the instances are verified from an operational
point of view. Connectivity is tested and all components are validated.
The goal of this step is to ensure availability of target database platform for all consumer
applications and prepare for Data Migration.
The verification process can be automated using SQL Server 2005 Administration tools and
some test scripts can be executed to validate the deployment.
Migration Tester tool from SSMA provides automated validation of the migration process.

2.3

Data Migration Technical Approach

Based on our experience we have seen that majority of data can be migrated using an
automated tool like Schema & Data Migrator of SSMA. But from time to time we have
encountered complex situations where export/import or Load/Unload utilities from ORACLE 10G
and SQL Server 2005 have been utilized for data migration.
In some other situations where ongoing data migration is needed a third party ETL tool like SSIS
and DataStage are also considered. These tools can greatly reduce the development time
compared to PL/SQL and can handle heavy data loads and complex transformations.
The following figure gives a high-level view of the steps for data migration from source ORACLE
10G to target SQL Server 2005.

Source Data
Analysis &
Profiling

Target Data
Model Analysis
Data Mapping &
Transformation Rules

Source/ Existing
Database
(Oracle)

Data Migration
Routines

Target
Database
(SQL Server )

Data Validation &


Database tuning

Data Migration Methodology

As part of the Data Migration approach the following major steps are carried out.
1. Source Data Analysis
This step is for performing detailed analysis of the data sources involved in the data migration
process. This includes:

Study of existing ORACLE 10G data models to fully understand the entities, relationships,
constraints, rules, data types, data formats, and so on.

Understand source data for as part of migration analysis.

The goal of this step is to have a comprehensive understanding of the data that is in the scope
of migration and derive a complete strategy for migration.
2. Target Database/Schema Analysis

This step is to analyze the Target Database/Schemas where the data will be migrated to. This
includes:

Understanding of the entities, relationships, data types, data formats and so on, of the target
data model in SQL Server 2005

Analyzing the database platform and reviewing differences from the source ORACLE 10G
platform, which might create issues during data migration

Understanding if there are any changes to the data model due to change in platforms such
as data types, data formats, partitions and so on.

The goal of this step is have a good understanding of the target SQL Server 2005 database and
schemas involved in data migration and assist in developing the migration strategy.
The Database/Schemas Analysis can be automated using SQL Server 2005 Administration tools
and reports can be published for review.
3. Data Mapping and Transformation definition
This step is for defining the data mapping between the source ORACLE 10G and target SQL
Server 2005 database/schemas. This includes:

Defining Data Element mapping between ORACLE 10G and SQL Server 2005
database/schemas

Defining the transformation rules based on requirements. The rule can be stored in
repository with details of their usage

Verifying the constraints and ensuring they are taken care of either by the database or by
the data migration routines

The goal of this step is to fully understand the source and target data elements and mapping
between them. This understanding is used to define the migration routines to avoid any gaps in
data in the migrated environment. The Schema & Data Migrator tool will be used for generating
data mapping and transformation definition.
4. Data Migration Routines (Extract, Validate, Transform, and Load)
This step is for defining and building the Data Migration routines that will actually move the data
from source to target database/schemas. This includes:

Building Data Extraction routines based on source Data analysis and data mapping
documents

Applying Data Quality rules (if applicable) and build modules accordingly

Building Data Transformation routines based on data mapping and transformation rules
document

Building Data Load routines based on target analysis and data mapping documents

Developing Batch Schedules based on dependencies and on going need (if applicable)

Building migration audit and notification routines to track, monitor and verify the data
migration processes

Building Error handling and Re-start routines to handle exceptions during the data
migrations process

The goal of this step is build the data migration routines based on the analysis and mapping
work done in previous steps. This is critical to ensure the success of the overall data migration
effort. Schema & Data Migrator tool from SSMA will help with the data migration.
5. Data Validation
This step is to perform the validation of the migrated data to ensure that correct data is available
to the applications and reports. This includes:

Performing Data Validation checks on data that has been loaded

Running Application process on the migrated data to ensure validity of data

Running reports over the migrated data and matching with existing reports to ensure
accuracy of data

Verifying the data load logs and audits to make sure nothing was dropped during the
migration

The goal of this step is to ensure successful data migration for all databases/schemas in scope.
The Zebra Visualization Tool from SSMA extends the GUI to address the need for testing as well
as to enable the user to follow the automated migration process. After the PL/SQL code has
been converted, this tool allows the user to easily browse through the code and to find the
corresponding code structures.