MONITORING OF EMBANKMENT
FOR MINIMAL SETTLEMENT
SCOPE OF PRESENTATION
Introduction
Design Criteria
Design Concept
Ground Condition
Design Parameters
Construction and Monitoring Records
Conclusion
INTRODUCTION
Introduction
PENANG ISLAND
(BATU MAUNG)
PULAU
JEREJAK
BATU KAWAN
EXPRESSSWAY
BATU KAWAN
TRUMPET
INTERCHANGE
0.
MAIN NAVIGATIONAL
SPAN
00
1+
P24-P27
00
+0
0
00
0.
PULAU
AMAN
3+
0
2+
0.
P0
PACKAGE 3C
0.
MAIN LAND
(BATU KAWAN)
5+
0
PACKAGE 3A
23
+0
2+
0
000
.
00
000
0.
+0
0.
0.
0.
19+00
18+00
17+00
0.
0.
16+00
15+00
00
0.
00
14
+
20+00
21+
13
P292
00
BATU MAUNG
INTERCHANGE
00
+0
0 00
11
10+
9+000
8+000
0.
7+00
0.
00
6+
00
22+
LAND PACKAGES
3 TIERS
DIRECTIONAL
RAMPS
6
CLOVERLEAF INTERCHANGE
AT MAINLAND
(BATU KAWAN)
LINKING NSE AT
KM154.8
2 TIERS
TRUMPET
INTERCHANGE
ADMINISTRATION
BUILDING
SECOND PENANG
BRIDGE TOLL
PLAZA
PROPOSED GROUND
TREATMENTS
LAND
BRIDGE
CLOVERLEAF
INTERCHANGE
SG. TENGAH
BRIDGE
PB2X TOLL
PLUS TOLL
BRIDGE OVER CANAL
AND ARCH CULVERT
11
LAND BRIDGE
12
PB2X TOLL
13
14
PLUS TOLL
15
16
17
DESIGN CRITERIA
DESIGN CRITERIA
DESIGN CHECK
Year
2007
2008
2009
2011
Stability (short-term
during construction)
1.25
1.25
1.25
1.25
Main Carriageway
100% consolidation
settlement during
construction (under the
permanent load)
Settlement
90% consolidation
settlement during
construction
90% consolidation
settlement during
construction
400mm postconstruction
settlement for the
first 7 years
250mm postconstruction
settlement for the
first 5 years
100% consolidation
settlement during
construction (under
the permanent load)
50mm postconstruction
settlement for the
first 2 years
100mm postconstruction
settlement for the
first 5 years
50mm post-construction
settlement for the first 20
years
Other areas
100% consolidation
settlement during
construction (under the
permanent load)
50mm post-construction
settlement for the first 2
years
100mm post-construction
settlement for the first 5
years
19
DESIGN CONCEPT
DESIGN CONCEPT
DESIGN CONCEPT
DESIGN CONCEPT
DESIGN CONCEPT
24
GROUND CONDITION
GROUND CONDITION
26
GROUND CONDITION
27
GROUND CONDITION
28
GROUND CONDITION
29
GROUND CONDITION
30
GROUND CONDITION
31
GROUND CONDITION
32
TYPICAL PIEZOCONE
RESULT
(NEAR PDC CLOVERLEAF
INTERCHANGE)
33
TYPICAL PIEZOCONE
RESULT
(NEAR LAND BRIDGE)
34
MOISTURE
CONTENT
35
ATTERBERG
LIMIT
36
PLASTICITY
INDEX
37
LIQUIDITY
INDEX
38
BULK DENSITY
39
PRECONSOLIDATION
PRESSURE
40
OVERCONSOLIDATION
RATIO
41
VOID RATIO
42
COMPRESSION
INDEX
43
COMPRESSION
RATIO
44
COEFFICIENT OF
CONSOLIDATION
(CV)
45
COEFFICIENT OF
CONSOLIDATION
(Ch)
46
47
48
49
Cu/v
50
Cu/Pc
51
DESIGN PARAMETERS
DESIGN PARAMETERS
53
Properties
Symbol
Unit
Upper CLAY
Lower CLAY
gb
kN/m3
15.0
16.0
Undrained shear
strength
Cu
kPa
5 + 1.5z *
24.5 + 0.4z*
Friction angle
degrees
2.5
2.5
Effective cohesion
kPa
21
23
Pre-overburden
pressure
Pc svo
kPa
20
20
eo
2.5
1.8
Compression index
Cc
1.0
0.6
Re-compression
index
Cr
0.10
0.06
Compression ratio
Cce = Cc/(1+eo)
0.286
0.214
Re-compression
ratio
Cre = Cr/(1+eo)
0.029
0.021
Coeff. of vertical
consolidation
Cv
m2/year
1.5
1.5
Coeff. of horizontal
consolidation
Ch
m2/year
Secondary
compression index
Ca
0.035
0.021
GEOTECHNICAL
DESIGN
GEOTECHNICAL DESIGN
Stage 1
Stage 2
Stage 3
Schem
e Ref.
Fill Height,
H (m)
PVD
Spacin
g (m
c/c)
H 2.5
1.4
1.5
2.0
0.5
4.0
0.5
HS Geotextile 200/50
1.2
2.0
3.5
1.25
4.5
1.0
5.5
0.5
HS Geotextile 200/50
1.2
2.2
3.5
1.25
4.5
1.0
6.7
0.5
HS Geotextile 400/50
Surcharge
Height (m)
Max.
Fill
Height
(m)
Filling
Rate
(m/wk)
Rest
Period
(mth)
Max.
Fill
Height
(m)
Filling
Rate
(m/wk)
Rest
Period
(mth)
Max.
Fill
Height
(m)
Filling
Rate
(m/wk)
Rest
Period
(mth)
Basal
Reinforcement (kN)
Fill Height,
H (m)
A
B
C
SC Spacing (m c/c)
Under
Under
Main
Side
Carriage
Slope
way
2.5
2.3
2.4
2.1
2.1
1.8
1.8
1.8
Stage 1
Surcharge
Height
(m)
1.5
2.0
2.0
Max.
Fill
Height
(m)
4.0
4.0
4.0
2.2
4.0
Stage 2
Filling
Rate
(m/wk)
Rest
Period
(mth)
1.0
1.0
1.0
Max.
Fill
Height
(m)
8.0
10.5
11.5
1.0
12.2
Filling
Rate
(m/wk)
Rest
Period
(mth)
0.5
0.5
0.5
3.0
2.5
2.5
HS Geotextile 400/50
HS Geotextile 400/50
Geogrid 400/100
0.5
2.5
Geogrid 400/100
CONSTRUCTION AND
MONITORING RESULTS
GEOTECHNICAL INSTRUMENTATION
Instruments
Approx. Spacing
Quantities
Remarks
57
100m intervals
131 nos.
100m to 150m
intervals
151 nos.
Inclinometers
200m intervals
47 nos.
Pneumatic Piezometers
200m intervals
39 nos.
3 nos.
Reference datum
5 nos.
58
59
PB2X TOLL
60
CLOVERLEAF INTERCHANGE
61
62
63
64
65
RSG-108 (PVD)
66
RSG-108 (PVD)
67
RSG-108 (PVD)
68
Asaoka Plot
RSG-108 (PVD)
69
RSG-110 (PVD)
70
RSG-110 (SC)
71
RSG-110 (SC)
72
Asaoka Plot
RSG-110 (SC)
73
RSG-114 (SC)
74
RSG-114 (SC)
75
RSG-114 (SC)
76
Asaoka Plot
RSG-114 (SC)
77
INCLINOMETER
NEARBY
RSG-114 (SC)
78
INCLINOMETER
NEARBY
RSG-114 (SC)
79
RSG-117 (SC)
80
RSG-117 (SC)
81
RSG-117 (SC)
82
Asaoka Plot
RSG-117 (SC)
83
CONCLUSION
CONCLUSION
In order to fulfill the minimum settlement design
criteria, the following steps were employed:1)
2)
3)
4)
5)
85
Higher surcharge
Longer surcharge period
Pumping from well points to remove trapped
water
Proper drainage to ensure that water can be freely
discharged from sand blanket
Sufficient testing and instrumentation
86