Вы находитесь на странице: 1из 7

Federal Register / Vol. 70, No.

19 / Monday, January 31, 2005 / Proposed Rules 4791

Applicability in any category; as identified in Table 1 of


(c) This AD applies to Airbus Model A319, this AD.
A320, and A321 series airplanes, certificated

TABLE 1.—APPLICABILITY
But not hav-
Having the Or the following ing the fol-
following Airbus service lowing Air-
Airbus
Airbus Model- bulletin incor- bus modi-
modification porated in fication in-
installed in service- stalled in
production- production-

A319 series airplanes ....................................................................................................................... 24486 A320–21–1140 32616


A320 series airplanes ....................................................................................................................... 20084 A320–21–1048 32616
A321 series airplanes ....................................................................................................................... 22596 Not applicable ... 32616

Unsafe Condition DEPARTMENT OF ENERGY G. Patrick Rooney (Technical


(d) This AD was prompted by a report that, Information), Office of Markets,
during a test of the fire extinguishing system, Federal Energy Regulatory Tariffs and Rates, Federal Energy
air leakage around the temperature sensor for Commission Regulatory Commission, 888 First
the aft cargo compartment reduced the Street, NE., Washington, DC 20426.
concentration of fire extinguishing agent to 18 CFR Part 35 (202) 502–6205.
below the level required to suppress a fire. P. Kumar Agarwal (Technical
We are issuing this AD to prevent air leakage [Docket No. RM05–4–000] Information), Office of Markets,
around the temperature sensor for the aft Tariffs and Rates, Federal Energy
cargo compartment, which, in the event of a Interconnection for Wind Energy and Regulatory Commission, 888 First
fire in the aft cargo compartment, could Other Alternative Technologies Street, NE., Washington, DC 20426.
result in an insufficient concentration of fire (202) 502–8923.
extinguishing agent, and consequent inability January 24, 2005. Jeffery S. Dennis (Legal Information),
of the fire extinguishing system to suppress AGENCY: Federal Energy Regulatory Office of the General Counsel, Federal
the fire. Commission, DOE. Energy Regulatory Commission, 888
Compliance ACTION: Notice of proposed rulemaking. First Street, NE., Washington, DC
20426. (202) 502–6027.
(e) You are responsible for having the SUMMARY: The Federal Energy
SUPPLEMENTARY INFORMATION:
actions required by this AD performed within Regulatory Commission (Commission) is
the compliance times specified, unless the proposing to amend its regulations to Introduction
actions have already been done. require public utilities to append to the 1. In Order No. 2003,1 the
Relocation of Aft Cargo Compartment standard large generator interconnection Commission adopted standard
Temperature Sensor agreement in their open access procedures for the interconnection of
(f) Within 24 months after the effective
transmission tariffs (OATTs) specific large generation facilities and a standard
date of this AD: Replace the ventilation
technical requirements for the large generator interconnection
extraction duct with a new duct and relocate interconnection of large wind agreement. The Commission required
the aft cargo compartment temperature generation. public utilities that own, control, or
sensor by accomplishing all of the actions DATES: Comments are due March 2, operate facilities for transmitting
specified in the Accomplishment 2005. Reply comments will be due 30 electric energy in interstate commerce to
Instructions of Airbus Service Bulletin A320– days thereafter. file revised Open Access Transmission
21–1141, dated April 7, 2004. ADDRESSES: Comments may be filed Tariffs (OATTs) containing these
Alternative Methods of Compliance electronically via the eFiling link on the standard provisions, and use them to
(AMOCs) Commission’s Web site at http:// provide interconnection service to
www.ferc.gov. Commenters unable to generating facilities having a capacity of
(g) The Manager, International Branch,
file comments electronically must send more than 20 megawatts. In Order No.
ANM–116, Transport Airplane Directorate,
an original and 14 copies of their 2003–A, on rehearing, the Commission
FAA, has the authority to approve AMOCs
comments to Federal Energy Regulatory determined that the standard
for this AD, if requested in accordance with
Commission, Office of the Secretary, procedures and agreement were
the procedures found in 14 CFR 39.19.
888 First Street, NE., Washington, DC designed around the needs of traditional
Related Information synchronous generation facilities, and
20426. Refer to the Comment
(h) French airworthiness directive F–2004– Procedures section of the preamble for that generators relying on non-
123, dated July 21, 2004, also addresses the additional information on how to file 1 Standardization of Generator Interconnection
subject of this AD. comments. Agreements and Procedures, Order No. 2003, 68 FR
Issued in Renton, Washington, on January FOR FURTHER INFORMATION CONTACT: 49845 (Aug. 19, 2003), FERC Stats. & Regs.,
18, 2005. Regulations Preambles ¶ 31,146 (2003) (Order No.
Bruce A. Poole (Technical Information), 2003), order on reh’g, 69 FR 15932 (Mar. 24, 2004),
Ali Bahrami, Office of Markets, Tariffs and Rates, FERC Stats & Regs., Regulations Preambles ¶ 31,160
Manager, Transport Airplane Directorate, Federal Energy Regulatory (2004) (Order No. 2003–A), order on reh’g, 70 FR
Aircraft Certification Service. 265 (January 4, 2005), FERC Stats & Regs.,
Commission, 888 First Street, NE., Regulations Preambles ¶ 31,171 (2004) (Order No.
[FR Doc. 05–1725 Filed 1–28–05; 8:45 am] Washington, DC 20426. (202) 502– 2003–B), reh’g pending; see also Notice Clarifying
BILLING CODE 4910–13–P 8468. Compliance Procedures, 106 FERC ¶ 61,009 (2004).

VerDate jul<14>2003 16:55 Jan 28, 2005 Jkt 205001 PO 00000 Frm 00003 Fmt 4702 Sfmt 4702 E:\FR\FM\31JAP1.SGM 31JAP1
4792 Federal Register / Vol. 70, No. 19 / Monday, January 31, 2005 / Proposed Rules

synchronous technologies,2 such as Background 5. On May 20, 2004, in Docket No.


wind plants, may find that a specific RM02–1–005, AWEA submitted a
requirement is inapplicable or that a 3. In Order No. 2003, pursuant to its petition for rulemaking or, in the
different approach is needed.3 responsibility under sections 205 and alternative, request for clarification of
206 of the Federal Power Act (FPA) 6 to Order No. 2003–A, and a request for a
Accordingly, the Commission granted
remedy undue discrimination, the technical conference. AWEA asked the
certain clarifications, and also added a
Commission required all public utilities Commission to adopt in Appendix G
blank Appendix G (Requirements of
that own, control, or operate facilities certain standards for the
Generators Relying on Non- for transmitting electric energy in
Synchronous Technologies) to the interconnection of wind generation
interstate commerce to append to their plants. Specifically, AWEA submitted a
standard generator interconnection OATTs the pro forma Large Generator
agreement as a placeholder for the proposed Appendix G that it argues
Interconnection Procedures (LGIP) and addresses the concerns of both
inclusion of requirements specific to pro forma LGIA. To achieve greater
non-synchronous technologies.4 It Transmission Providers and the wind
standardization of interconnection generation industry. AWEA’s proposed
appears that the only relevant non- terms and conditions, Order No. 2003
synchronous generator in this Appendix G included a low voltage
required such public utilities to file ride-through capability standard, which
rulemaking is the wind generator, and revised OATTs containing the pro forma would allow the Transmission Provider
thus the proposed rule would apply LGIP and LGIA included in Order No. to require as a condition of
only to wind plants, although we 2003. interconnection that wind generation
request comments on whether there are 4. Order Nos. 2003–A and 2003–B, facilities have the ability to continue
other technologies that should also be issued on rehearing, made certain operating or ‘‘ride-through’’ certain low
subject to the rule. revisions to the pro forma LGIP and voltage conditions on the transmission
2. In this Notice of Proposed LGIA. In Order No. 2003–A, the system to which they are
Rulemaking (NOPR), the Commission is Commission clarified that certain interconnected. Additionally, AWEA
proposing standards applicable to the provisions of the LGIP and LGIA are not proposed that the power factor design
interconnection of large wind generating appropriately applied to wind criteria of up to 0.95 leading/lagging be
plants,5 to be included in Appendix G generators. The Commission stated that applied to wind generation plants, with
of the Large Generator Interconnection it ‘‘recognize[d] that the LGIA and LGIP certain flexibility regarding whether the
Agreement (LGIA). The Commission are designed around the needs of large location of the reactive support
proposes these standards in light of its synchronous generators and that many equipment would be at the common
findings in Order No. 2003–A, noted generators relying on newer point of interconnection of all the
above, and in response to a petition technologies may find that either a generators in the plant rather than at the
submitted by the American Wind specific requirement is inapplicable or individual turbine. Further, AWEA
Energy Association (AWEA) on May 20, that it calls for a slightly different proposed that we require Transmission
2004. Specifically, and as described approach.’’ 7 In light of this recognition, Providers and wind generator
more fully below, we propose to include the Commission clarified that LGIA manufacturers to participate in a formal
in Appendix G to the LGIA certain article 5.4 (Power System Stabilizers), process to develop, update, and improve
LGIA article 5.10.3 (Interconnection the engineering models and
technical requirements that
Customer’s Interconnection Facilities specifications used in modeling wind
Transmission Providers must apply to
Construction) and LGIA article 9.6.1 plant interconnections. Finally, AWEA
interconnection service for wind
(Power Factor Design Criteria) would proposed to include language in
generation plants that are different from not be applied to wind generators.8 Appendix G allowing the wind
that required of traditional synchronous Additionally, the Commission noted Interconnection Customer to ‘‘self-
generating plants or are now needed that ‘‘there may be other areas of the study’’ interconnection feasibility by
because of the increased presence of LGIP and LGIA that may call for a entering the interconnection queue
larger aggregated wind plants on the slightly different approach for a without providing certain power and
Transmission Provider’s systems. These generator relying on newer technology load flow data, receiving certain
requirements would be applied in because it may have unique electrical information from the Transmission
addition to the standard interconnection characteristics.’’ 9 As a result, the Provider, and conducting its own
procedures and requirements adopted Commission added to the LGIA a blank Feasibility Study.
by the Commission in Order No. 2003. new Appendix G as a placeholder for
Additionally, the Commission seeks 6. On September 24, 2004, the
requirements specific to newer Commission held a Technical
comments on certain issues, including technologies to be developed at a future
whether there are other non- Conference to discuss the issues raised
time.10 by AWEA’s petition. The goal was to
synchronous technologies, or other
discuss the technical requirements for
technologies in addition to wind, that 6 16
U.S.C. 824d–e (2000).
the interconnection of wind plants and
should also be covered by the proposed 7 OrderNo. 2003–A at P 407, n. 85.
8 Id. at P 278, 407, n. 85. other alternative technologies and the
Appendix G.
9 Id. at P 407, n. 85. need for specific requirements for their
2 A wind generator is considered non-
10 The Appendix G that was added to the LGIA interconnection. Additionally, the
synchronous because it does not run at the same
in Order No. 2003–A and that we propose in this Technical Conference considered how
NOPR should not be confused with the Appendix wind and other alternative generator
speed as a traditional generator. A non-synchronous G that the Commission originally proposed to
generator possesses significantly different include in the LGIA, which concerned technologies may respond differently to
characteristics and responds differently to network Interconnection Guidelines. The Commission did transmission grid disturbances and have
disturbances.
3 Order No. 2003–A at P 407, n. 86.
not include that Appendix in the Final Rule LGIA, different effects on the transmission
since its provisions were covered elsewhere in the grid. The Commission also solicited and
4 Id.
LGIP and LGIA. See Order No. 2003 at P 673. In
5 Large wind generating plants are those with an Order No. 2003–A, the Commission used the
output rated at 20 MW or higher at the point of Appendix G label for the requirements specific to synchronous technologies that we propose in this
interconnection. wind generation and perhaps other non- rulemaking.

VerDate jul<14>2003 16:55 Jan 28, 2005 Jkt 205001 PO 00000 Frm 00004 Fmt 4702 Sfmt 4702 E:\FR\FM\31JAP1.SGM 31JAP1
Federal Register / Vol. 70, No. 19 / Monday, January 31, 2005 / Proposed Rules 4793

received post-Technical Conference wind turbine manufacturers have Commission seeks comment on whether
comments from interested persons. turbines in their inventory that do not the voltage-time profile of the proposed
have low voltage ride-through capability Appendix G is appropriate or should be
Discussion
or adequate reactive power capability. modified.
7. Based on our review and Some participants argued that a
consideration of AWEA’s petition and Supervisory Control and Data
transition period would be appropriate
the comments received at and after the Acquisition (SCADA) Capability
to accommodate this inventory. This
Technical Conference, the Commission proposal is designed in part to allow the 14. Previously, Transmission
is proposing certain technical Transmission Provider to assure Providers generally did not require
requirements for the interconnection of transmission grid safety and reliability. wind generators to have remote
wind generating plants. The For this reason, deviations should not supervisory control and data acquisition
Commission proposes to include these be permitted unless approved by the (SCADA) capability because of their
technical requirements as Appendix G Transmission Provider on a comparable small size and minimal effects on the
to the LGIA, as contemplated in Order basis. The proposal grants the transmission system. Now that there are
No. 2003–A. The technical requirements Transmission Provider the flexibility to more large wind plants, Transmission
we propose here are similar in certain relax certain requirements if not needed Providers may need SCADA capability
respects and differ in other respects for safety and reliability, as explained in to ensure the safety and reliability of the
from the Appendix G proposed by more detail below. transmission system during normal,
AWEA in its petition for rulemaking. system emergency, and system
Low Voltage Ride-Through Standard contingency conditions, and to acquire
The Commission is also seeking
comments on certain issues, as 11. Prior to the advent of larger wind wind facility operating data.
discussed below. Our goal is to adopt plants generally consisting of multiple 15. The Commission proposes to
final technical requirements for the wind generation turbines, individual require that large wind plants seeking to
interconnection of wind plants (and wind turbines were designed to go interconnect to the transmission grid
other alternative technologies, if any) offline if there was a sudden change in possess SCADA capability. The
that recognize the special characteristics voltage on the transmission system. proposed Appendix G would require
of wind plants, their larger size and However, now there are larger that the wind plant install SCADA
increased penetration on the aggregated wind plants with a greater capability to transmit data and receive
transmission system (in terms of the penetration level on the Transmission instructions from the Transmission
wind generating capacity’s percentage Provider’s systems in certain areas, and Provider. Additionally, the proposed
contribution to total system generating significant stability problems can occur Appendix G states that the
capacity), and the effects they have on on the transmission system if such large Transmission Provider and wind plant
the transmission system. This proposal plants become unavailable during a low owner shall determine the SCADA
seeks to accommodate wind plants voltage excursion. As a result, information that is essential for the
while ensuring the continued reliability Transmission Providers need large wind proposed wind plant, taking into
of the nation’s electric transmission plants to remain online during low- account the size of the plant, its
system. voltage occurrences for reliability characteristics, location, and importance
8. The Appendix G technical reasons. in maintaining generation resource
requirements for the interconnection of 12. The Commission is proposing to adequacy and transmission system
wind generation plants that we propose require that large wind plants seeking to reliability in its area.13
interconnect to the grid demonstrate 16. The Commission seeks comments
in this NOPR are not intended to be the
low voltage ride-through capability, regarding the SCADA capability
sole interconnection requirements for
unless waived by the Transmission requirements proposed in this NOPR.
wind plants. Such plants will still be
Provider on a comparable and not Particularly, the Commission seeks
subject to the other standard
unduly discriminatory basis. comments on whether there is any basic
interconnection procedures and
Specifically, Appendix G would require essential SCADA information that large
requirements adopted by the
that ‘‘wind generating plants * * * wind plants should be required to
Commission in Order No. 2003, unless
demonstrate the ability to remain on- provide, and if so, what that information
wind plants have been otherwise should be (such as information needed
exempted from such procedures and line during voltage disturbances up to
the time periods and associated voltage to determine how the plant’s maximum
requirements. megawatt output and megawatt ramp
9. Recently, the Commission became levels set forth in Figure 1’’ of the
Appendix. The required voltage levels rate vary over time with changes in the
aware of the Alberta Electric System
would be measured at the high voltage wind speed, and/or information needed
Operator’s adoption of technical
side of the substation transformers.12 to forecast the megawatt output of the
standards for the interconnection of plant).
13. The Commission seeks comments
wind generation plants to its
on this proposed standard. Particularly, Power Factor Design Criteria (Reactive
transmission system.11 The standards
the Commission is interested in Power)
adopted by the AESO are similar to, but
comments addressing whether it should
more comprehensive than, the standards 17. Previously, Transmission
adopt a low voltage ride-through
we propose in the Appendix G in this Providers did not require wind
standard at all, whether this or another
NOPR. generators to have the capability to
10. The Commission is not proposing standard is more appropriate, and
a transition period before the technical whether this proposed standard is 13 Unlike synchronous generating plants, which

requirements in Appendix G would take specific enough. Additionally, the generally possess SCADA capability, can respond to
effect. At the Technical Conference, automatic generation control signals from the
12 While low voltage ride-through capability is control center and are often staffed, wind generating
however, several participants noted that needed for wind plants, it is not a concern for large plants are often remote, unmanned, and
synchronous generating facilities because most of characterized by an unpredictable rate of change of
11 Those standards, titled Wind Power Facility these facilities are equipped with automatic voltage output, thus making it difficult for the Transmission
Technical Requirements, are at http:// control devices to increase output during low Provider to limit the output of the wind plant when
www.aeso.com. voltage excursions. necessary for system reliability.

VerDate jul<14>2003 16:55 Jan 28, 2005 Jkt 205001 PO 00000 Frm 00005 Fmt 4702 Sfmt 4702 E:\FR\FM\31JAP1.SGM 31JAP1
4794 Federal Register / Vol. 70, No. 19 / Monday, January 31, 2005 / Proposed Rules

provide reactive power because the seeks input as to whether any dynamic 22. With regard to AWEA’s self-study
facilities were generally small and had (i.e., controllable) reactive capability proposal, Order No. 2003 currently
minimal impact on the transmission should be required of wind plants as a requires that a valid and complete
grid. Because of the larger size of many condition of interconnection, and if so, Interconnection Request be on file with
of the wind plants currently operating what level of dynamic capability should the Transmission Provider before the
and the increased penetration of wind be required. Further, the Commission Interconnection Customer may receive
energy on the transmission system, seeks comments on the proposed waiver Base Case data.15 Section 2.3 did not
Transmission Providers may need to provisions for the power factor address situations where the
require wind plants to operate within a requirement discussed above. Interconnection Customer might need
specified power factor range to help access to the Base Case data before it
balance the reactive power needs of the Models and Self-Study of Feasibility could complete its Interconnection
transmission system. 20. In its petition, AWEA proposed Request. Therefore we seek comments
18. The Commission is proposing to that certain variations in the on how to balance the need of wind
require that wind plants maintain a Interconnection Study process be generators to self-study prior to filing a
power factor within the range of 0.95 applied to the interconnection of wind completed Interconnection Request with
leading to 0.95 lagging (as required by plants. Specifically, AWEA proposed the need to protect this critical energy
Order No. 2003), to be measured at the that Transmission Providers be required infrastructure information and
high voltage side of the substation to ‘‘participate in a formal process for commercially sensitive data against
transformer. The proposed Appendix G updating, improving, and validating the unwarranted disclosure.
permits wind plants flexibility in how engineering models used for modeling 23. Additionally, in Order No. 2003
they meet the power factor requirement the interconnection impacts of wind the Commission addressed requests that
(for example, using either power turbines.’’ 14 Additionally, AWEA additional time be provided after the
electronics designed to supply this level proposed that wind Interconnection Interconnection Request is made to
of reactive capability or fixed and Customers be permitted to enter the submit final design specifications.16
switched capacitors if agreed to by the interconnection queue and ‘‘self-study’’ There, we stated that ‘‘[t]he
Transmission Provider, or a the feasibility of interconnection after Interconnection Customer should have
combination of the two.) Additionally, submitting an Interconnection Request its design substantially completed prior
the Commission proposes to allow the that does not include power and load to submitting its Interconnection
Transmission Provider to waive the flow data and paying the applicable Request so that it does not block or
power factor requirement for wind deposit. These wind Interconnection disrupt the queue process.’’ 17 We also
plants where such capability is not Customers should be entitled to have noted that Transmission Providers
needed at that location or for a the scoping meeting with the would not be able to act on an
generating facility of that size, provided Transmission Provider and receive from incomplete Interconnection Request,
that such waiver is not unduly the Transmission Provider the base case and that giving ‘‘one class of
discriminatory and is offered on a data, according to AWEA. Following its Interconnection Customers extra time to
comparable basis to similarly situated self-study, the wind Interconnection submit design specifications would be
wind plants. Should the power factor Customer would submit an electrical unfair to other Interconnection
requirement be waived, however, the design and turbine models sufficient to Customers in the queue.’’ 18 The
interconnection agreement would be allow the Transmission Provider to Commission is not persuaded to
considered a non-conforming agreement propose deviations from these
conduct a System Impact Study under
under section 11.3 of the LGIP, conclusions in this rulemaking.
AWEA’s proposal. AWEA stated that
requiring that it be filed with the
these provisions were necessary because Other Generating Technologies
Commission. The Commission believes
requiring power system and load flow 24. The Commission seeks comments
that it is appropriate to permit the
data to be submitted with the regarding whether there are other
Transmission Provider to waive the
Interconnection Request is impractical generating technologies that should be
power factor requirement for a wind
for wind plants, since the turbine required to comply with the specific
plant if the Transmission Provider does
selection and electrical design of the technical requirements included in
not need reactive power for reliability at
wind plant may be based on the Appendix G.
that plant’s location because, unlike a
non-wind generator which always has outcome of the Feasibility Study and
grid conditions at the point of Variations From Appendix G
some reactive power capability, a wind
plant must incur an additional capital interconnection. 25. The Commission is proposing to
cost to provide this reactive power. 21. The Commission is not proposing permit Transmission Providers to justify
Finally, we propose to require that wind these provisions for several reasons. variations from the terms of the final
plants have the capability to provide With regard to the proposal to require Appendix G using the approach taken in
sufficient dynamic voltage support in Transmission Providers to participate in Order No. 2003. In Order No. 2003, the
order to interconnect to the a formal process to update and improve Commission modified the approach
transmission system, instead of the wind turbine modeling, we believe that taken in Order No. 888,19 which
power system stabilizer and automatic such a formal process should take place
voltage support at the generator outside the Commission, through 15 See LGIP, section 2.3; see also Order No. 2003

industry technical groups or perhaps at P 77–84.


excitation system, if the System Impact 16 See Order No. 2003 at P 99.
Study shows that such dynamic through the regional reliability councils. 17 Id. at P 103.
capability is necessary for system The Commission recognizes, however, 18 Id.

reliability. that improvements in the way that wind 19 Promoting Wholesale Competition Through

19. The Commission seeks comments interconnections are modeled would be Open Access Non-Discriminatory Transmission
regarding whether the proposed power beneficial, and we encourage the Services by Public Utilities; Recovery of Stranded
industry to address this issue. Costs by Public Utilities and Transmitting Utilities,
factor range proposed should be Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996)
increased or decreased for wind at 31,760–61 (Order No. 888), order on reh’g, Order
generation plants. Also, the Commission 14 AWEA Proposed Appendix G at 5. No. 888–A, FERC Stats. & Regs. ¶ 31,048 (1997),

VerDate jul<14>2003 16:55 Jan 28, 2005 Jkt 205001 PO 00000 Frm 00006 Fmt 4702 Sfmt 4702 E:\FR\FM\31JAP1.SGM 31JAP1
Federal Register / Vol. 70, No. 19 / Monday, January 31, 2005 / Proposed Rules 4795

allowed two types of variations. First, variation’’ from the pricing and non- requirements imposed by agency rule.23
public utilities may seek variations to pricing provisions of the pro forma LGIP Comments are solicited on the
the LGIP and LGIA based on regional and LGIA.22 The Commission intends to Commission’s need for this information,
reliability requirements.20 Second, apply all three of these variation whether the information will have
public utilities may argue that proposed standards to proposed variations from practical utility, the accuracy of
changes to any OATT provision are the Appendix G the Commission finally provided burden estimates, ways to
‘‘consistent with or superior to’’ the adopts in this proceeding. enhance the quality, utility and clarity
terms of the pro forma OATT.21 of the information to be collected, and
Information Collection Statement
Additionally, Order No. 2003 allows any suggested methods for minimizing
RTOs and ISOs greater flexibility in 26. Office of Management and Budget respondents’ burden, including the use
complying with its provisions. They (OMB) regulations require OMB to of automated information techniques.
may seek an ‘‘independent entity approve certain information collection 27. Public Reporting Burden:

Number of Number of Hours per Total annual


Data collection respondents responses response hours

FERC–516 ....................................................................................................... 238 1 18 4,284

Information Collection Costs: The plants. The proposed rule would require Environmental Analysis
Commission seeks comments on the that each public utility that owns,
28. The Commission is required to
costs to comply with these operates, or controls transmission prepare an Environmental Assessment
requirements. It has projected the facilities participate in one-time filings or an Environmental Impact Statement
annualized cost for all respondents to incorporating the technical for any action that may have a
be: Annualized Capital/Startup Costs- requirements into their own open access significant adverse effect on the human
Staffing requirements to review and transmission tariffs. Internal Review: the environment.25 The Commission has
prepare an interconnection agreement = Commission has assured itself, by categorically excluded certain actions
$642,600. (238 respondents × $150 means of internal review, that there is from this requirement as not having a
hourly rate × 18 hours per respondent.) specific, objective support for the
The OMB regulations require OMB to significant effect on the human
burden estimates associated with the environment. Included in the exclusion
approve certain information collection
information collection requirements. are rules that are clarifying, corrective,
requirements imposed by agency rule.24
The Commission’s Office of Market, or procedural, or that do not
Accordingly, pursuant to OMB
regulations, the Commission is Tariffs and Rates will use the data substantially change the effect of the
providing notice of its proposed included in filings under Section 203 regulations being amended.26 The
information collections to OMB. and 205 of the Federal Power to exclusion also includes information
Title: FERC–516, Electric Rate evaluate efforts for interconnection and gathering, analysis, and
Schedule Filings. coordination of the U.S. electric dissemination.27 The rules proposed in
Action: Proposed Information transmission as well as for general this NOPR would update and clarify the
Collection. industry oversight. These information application of the Commission’s
OMB Control No.: 1902–0096. requirements conform to the standard interconnection requirements
The applicant shall not be penalized Commission’s plan for efficient to wind generation plants. Further, this
for failure to respond to this collection information collection, communication, NOPR involves information gathering,
of information unless the collection of and management within the electric analysis, and dissemination regarding
information displays a valid OMB the interconnection of wind generators.
power industry. Interested persons may
control number. Therefore, this NOPR falls within the
obtain information on the reporting
Respondents: Business or other for categorical exemptions provided in the
requirements by contacting: Federal Commission’s Regulations, and as a
profit.
Energy Regulatory Commission, 888 result neither an environmental impact
Frequency of Responses: One-time
implementation. First Street, NE., Washington, DC 20426, statement nor an environmental
Necessity of Information: The Attention: Michael Miller, Office of the assessment is required. Additionally, we
proposed rule would revise the Executive Director, phone: (202) 502– note that this proposed rule will help
requirements contained in 18 CFR part 8415, fax: (202) 273–0873, e-mail: the development and interconnection of
35. The Commission is seeking to revise michael.miller@ferc.gov. Comments on wind plants, eliminating the airborne
its standardized interconnection the proposed requirements of the and other emissions that would result
procedures and agreements to include subject rule may also be sent to the from constructing fossil fuel generating
wind generation plants. In particular, Office of Information and Regulatory plants instead.
the Commission will propose that Affairs, Office of Management and
Budget, Washington, DC 20503, Regulatory Flexibility Act Certification
public utilities add to their standard
interconnection agreements the Attention: Desk Officer for the Federal 29. The Regulatory Flexibility Act of
technical requirements for the Energy Regulatory Commission, phone: 1980 (RFA) 28 generally requires a
interconnection of wind generation (202) 395–4650. description and analysis of final rules

order on reh’g, Order No. 888–B, 81 FERC ¶ 61,248 20 See Order No. 2003 at P 823–24. 25 Order No. 486, Regulations Implementing the

(1997), order on reh’g, Order No. 888–C, 82 FERC 21 See id. at P 816. National Environmental Policy Act, 52 FR 47897
¶ 61,046 (1997), aff’d in relevant part sub nom. 22 Id. at P 822–827; see also Order No. 2003–A at (Dec. 17, 1987), FERC Stats. & Regs. Preambles
Transmission Access Policy Study Group v. FERC, 1986–1990 ¶ 30,783 (Dec. 10, 1987).
P 48. 26 18 CFR 380.4(a)(2)(ii) (2004).
225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New 23 5 CFR 1320.11 (2004).
27 18 CFR 380.4(a)(5) (2004).
York v. FERC, 535 U.S. 1 (2002). 24 Id.
28 5 U.S.C. 601–612 (2000).

VerDate jul<14>2003 16:55 Jan 28, 2005 Jkt 205001 PO 00000 Frm 00007 Fmt 4702 Sfmt 4702 E:\FR\FM\31JAP1.SGM 31JAP1
4796 Federal Register / Vol. 70, No. 19 / Monday, January 31, 2005 / Proposed Rules

that will have significant economic Availability section below. Commenters tariff under this section must amend
impact on a substantial number of small on this proposal are not required to such tariff by adding the standard
entities.29 The Commission is not serve copies of their comments on other interconnection procedures and
required to make such analyses if a rule commenters. agreement contained in Order No. 2003,
would not have such an effect. FERC Stats. & Regs. ¶ 31,146 (Final Rule
30. The Commission does not believe Document Availability
on Generator Interconnection), as
that this proposed rule would have such 34. In addition to publishing the full amended by the Commission in Order
an impact on small entities. Most filing text of this document in the Federal No. ll, FERC Stats. & Regs. ¶ ll
companies subject to the Commission’s Register, the Commission provides all (Final Rule on Interconnection for Wind
jurisdiction do not fall within the RFA’s interested persons an opportunity to Energy and Other Alternative
definition of a small entity. Further, the view and/or print the contents of this Technologies), or such other
filing requirements contain standard document via the Internet through interconnection procedures and
generator interconnection procedures FERC’s home page (http://www.ferc.gov) agreement as may be approved by the
and agreement for interconnecting and in FERC’s Public Reference Room Commission consistent with the Final
generators larger than 20 MW, which during normal business hours (8:30 a.m. Rule on Generator Interconnection.
exceeds the threshold of the Small to 5 p.m. eastern time) at 888 First (i) The amendment to implement the
Business Size Standard of NAICS. Street, NE., Room 2A, Washington, DC Final Rule on Generator Interconnection
Therefore, the Commission certifies that 20426. required by the preceding subsection
this rule will not have a significant 35. From FERC’s home page on the must be filed no later than January 20,
economic impact on a substantial Internet, this information is available in 2004.
number of small entities. the Commission’s document (ii) The amendment to implement the
management system, eLibrary. The full Final Rule on Interconnection for Wind
Comment Procedures
text of this document is available on Energy and other Alternative
31. The Commission invites eLibrary in PDF and Microsoft Word Technologies required by the preceding
comments on the matters and proposals format for viewing, printing, and/or subsection must be filed no later than
in this notice, including any related downloading. To access this document [60 days after publication of final rule].
matters or alternative proposals that in eLibrary, type the docket number (iii) Any public utility that seeks a
commenters may wish to discuss. excluding the last three digits of this deviation from the standard
Comments are due March 2, 2005. Reply document in the docket number field. interconnection procedures and
comments will be due 30 days 36. User assistance is available for agreement contained in Order No. 2003,
thereafter. Comments must refer to eLibrary and the FERC’s Web site during FERC Stats. & Regs. ¶ 31,146 (Final Rule
Docket No. RM05–4–000, and must normal business hours. For assistance, on Generator Interconnection), as
include the commenters’ name, the please contact FERC Online Support at amended by the Commission in Order
organization represented, if applicable, 1–866–208–3676 (toll free) or 202–502– No. ll, FERC Stats. & Regs. ¶ ll
and address. 6652 (e-mail at (Final Rule on Interconnection for Wind
32. Comments may be filed FERCOnlineSupport@FERC.gov), or the Energy and Other Alternative
electronically via the eFiling link on the Public Reference Room at 202–502– Technologies), must demonstrate that
Commission’s Web site at http:// 8371, TTY 202–502–8659 (e-mail at the deviation is consistent with the
www.ferc.gov. The Commission accepts public.referenceroom@ferc.gov). principles of the Final Rule on
most standard word processing formats Generator Interconnection.
and commenters may attach additional List of Subjects in 18 CFR Part 35
files with supporting information in * * * * *
Electric power rates, Electric utilities. [Note: The attachments will not be published
certain other file formats. Commenters By direction of the Commission. in the Code of Federal Regulations]
filing electronically do not need to make
Linda Mitry, Appendix G—Interconnection
a paper filing. Commenters that are not
Deputy Secretary. Requirements for Wind Generators
able to file comments electronically
must send an original and 14 copies of In consideration of the foregoing, the
Commission proposes to revise part 35, Appendix G sets forth additional
their comments to Federal Energy requirements and provisions specific to wind
Regulatory Commission, Office of the Chapter I, Title 18 of the Code of generating plants.
Secretary, 888 First Street, NE., Federal Regulations, as follows.
A. Standards Applicable to Wind Generators
Washington, DC 20426. PART 35—FILING OF RATE
33. All comments will be placed in i. Low Voltage Ride-Through (LVRT)
SCHEDULES Standard
the Commission’s public files and may
be viewed, printed, or downloaded 1. The authority citation for part 35 Wind generating plants shall demonstrate
remotely as described in the Document continues to read as follows: the ability to remain online during voltage
disturbances up to the time periods and
Authority: 16 U.S.C. 791a–825r, 2601– associated voltage levels set forth in Figure
29 The RFA definition of ‘‘small entity’’ refers to 2645; 31 U.S.C. 9701; 42 U.S.C. 7101–7352. 1, below. The requirements apply to voltage
the definition provided in the Small Business Act,
which defines a ‘‘small business concern’’ as a 2. In § 35.28, paragraph (f)(1) is measured at the high voltage side of the wind
business that is independently owned and operated revised to read as follows: plant substation transformer(s). The figure
and that is not dominant in its field of operation. shows the ratio of actual to nominal voltage
15 U.S.C. 632 (2000). The Small Business Size § 35.28 Non-discriminatory open access (on the vertical axis) over time (on the
Standards component of the North American transmission tariff. horizontal axis). Before time 0.0, the voltage
Industry Classification System defines a small at the transformer is the nominal voltage. At
electric utility as one that, including its affiliates, * * * * *
time 0.0, the voltage drops. If the voltage
is primarily engaged in the generation, (f) Standard generator
remains at a level greater than 15 percent of
transmission, and/or distribution of electric energy interconnection procedures and the nominal voltage for a period that does not
for sale and whose total electric output for the agreements.
preceding fiscal years did not exceed 4 million exceed 0.625 seconds, the plant must stay
MWh. 13 CFR 121.201 (Section 22, Utilities, North
(1) Every public utility that is online. Further, if the voltage returns to 90
American Industry Classification System, NAICS) required to have on file a non- percent of the nominal voltage within 3
(2004)). discriminatory open access transmission seconds of the beginning of the voltage drop

VerDate jul<14>2003 16:55 Jan 28, 2005 Jkt 205001 PO 00000 Frm 00008 Fmt 4702 Sfmt 4700 E:\FR\FM\31JAP1.SGM 31JAP1
Federal Register / Vol. 70, No. 19 / Monday, January 31, 2005 / Proposed Rules 4797

(with the voltage at any given time never 1. A wind generating plant must have parameters of this regulation, and the
falling below the minimum voltage indicated LVRT capability down to 15 percent of the Transmission Provider may agree to such a
by the solid line in Figure 1), the plant must rated line voltage for 0.625 seconds; variation provided it does so on a comparable
stay online. The Interconnection Customer 2. A wind generating plant must be able to and not unduly discriminatory basis among
operate continuously at 90 percent of the
may not disable low voltage ride-through wind generators. The Transmission Provider
rated line voltage, measured at the high
equipment while the wind plant is in voltage side of the wind plant substation may waive the low voltage ride-through
operation. transformer(s). requirement on a comparable and not unduly
Two key features of this proposed The wind generating plant may ask the discriminatory basis for all wind plants.
regulation are: Transmission Provider for a variation of the

ii. Supervisory Control and Data Acquisition The Transmission Provider may agree to We designate viticultural areas to allow
(SCADA) Capability waive or defer compliance with the reactive vintners to better describe the origin of
The wind plant shall provide SCADA power standard. However, any such waiver their wines and to allow consumers to
capability to transmit data and receive or exemption must be considered a non-
better identify wines they may
instructions from the Transmission Provider. conforming agreement pursuant to section
11.3 of the LGIP. purchase. We invite comments on this
The Transmission Provider and the wind proposed amendment to our regulations.
plant Interconnection Customer shall [FR Doc. 05–1693 Filed 1–28–05; 8:45 am] DATES: We must receive written
determine what SCADA information is BILLING CODE 6717–01–P
essential for the proposed wind plant, taking comments on or before April 1, 2005.
into account the size of the plant, its ADDRESSES: You may send comments to
characteristics, location, and importance in any of the following addresses:
maintaining generation resource adequacy DEPARTMENT OF THE TREASURY • Chief, Regulations and Procedures
and transmission system reliability in its Division, Alcohol and Tobacco Tax and
area. Alcohol and Tobacco Tax and Trade Trade Bureau, Attn: Notice No. 30, P.O.
Bureau Box 14412, Washington, DC 20044–
iii. Power Factor Design Criteria (Reactive
Power) 4412.
27 CFR Part 9 • 202–927–8525 (facsimile).
A wind plant shall maintain a power factor
within the range of 0.95 leading to 0.95 [Notice No. 30] • nprm@ttb.gov (e-mail).
lagging, measured at the high voltage side of
• http://www.ttb.gov/alcohol/rules/
RIN 1513–AA67 index.htm. An online comment form is
the wind plant substation transformer(s). The
power factor range requirement can be met posted with this notice on our Web site.
Proposed Expansion of the Russian • http://www.regulations.gov (Federal
by using, for example, power electronics River Valley Viticultural Area (2003R–
designed to supply this level of reactive e-rulemaking portal; follow instructions
144T) for submitting comments).
capability (taking into account any
limitations due to voltage level, real power AGENCY: Alcohol and Tobacco Tax and You may view copies of this notice,
output, etc.) or fixed and switched capacitors Trade Bureau, Treasury. the petition, the appropriate maps, and
if agreed to by the Transmission Provider, or any comments we receive about this
ACTION: Notice of proposed rulemaking.
a combination of the two. The proposal by appointment at the TTB
Interconnection Customer shall not disable SUMMARY: The Alcohol and Tobacco Tax Library, 1310 G Street, NW.,
power factor equipment while the wind plant and Trade Bureau has received a Washington, DC 20220. To make an
is in operation. Wind plants shall also be able
petition proposing the expansion of the appointment, call 202–927–2400. You
to provide sufficient dynamic voltage support
in lieu of the power system stabilizer and existing Russian River Valley may also access copies of the notice and
automatic voltage regulation at the generator viticultural area in Sonoma County, comments online at http://www.ttb.gov/
excitation system if the Interconnection California. The proposed 30,200-acre alcohol/rules/index.htm.
System Impact Study shows this to be expansion would increase the size of See the Public Participation section of
this viticultural area to 126,200 acres. this notice for specific instructions and
EP31JA05.006</GPH>

required for system reliability.

VerDate jul<14>2003 16:55 Jan 28, 2005 Jkt 205001 PO 00000 Frm 00009 Fmt 4702 Sfmt 4702 E:\FR\FM\31JAP1.SGM 31JAP1

Вам также может понравиться