Вы находитесь на странице: 1из 96

H E AT I N G A N D C O O L I N G

SOLUTIONS
TECHNICAL GUIDELINES

PkjijmPi_`mÙjjmC`\odib
Cjh`>jhajmoNtno`h
>jio`ion
Introduction
History of underßoor heating . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
The Uponor underßoor heating system. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Principle of heat ex-change by underßoor heating system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

BeneÞts of Uponor underßoor heating


Comfortable system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Clean and healthy environment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Complete design freedom . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Adaptable and easy to install . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Energy efÞcient with low maintenance costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Energy-saving and environmental friendly . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Range of applications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Thermal comfort and standard requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

Uponor underßoor heating system Ð Home Comfort


Modular approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Floor structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Uponor PE-Xa pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Uponor multi layer composite pipe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Pipe Þxation methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Decision table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Design and calculation


Floor construction components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Weights of Uponor underßoor heating system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
Loop conÞguration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
Screed expansion joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
Location of the manifolds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
Calculation basis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
Calculation criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
Practical calculation issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
Calculation of heating capacity according to EN 1264 and EN 15377-1 . . . . . . . . . . . . . . . . . . . 40
Pressure loss . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Expansion volumes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Calculation diagrams and tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Calculation spreadsheets. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
Uponor calculation software . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58

2 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation
Floor preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
Load bearing construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
Installation guide Home Comfort . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
Pipe loop connection and Þlling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
Pressure test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
Screeding and concreting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
Initial heating up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
Balancing of manifolds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
Fault tracing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
Troubleshooting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85

Controls
Water temperature control strategies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
Response time . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88
Self control effect . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89
Room temperature sensors - thermostats . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89
SpeciÞcation of Uponor radio and wired control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90
Uponor control stations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90

Terminology, symbols and units


Terminology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
Symbols and units . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93
Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Introduction

Diomj_p^odji
Cdnojmtjapi_`mÙjjmc`\odib
As early as 80 B.C. the Romans dis- Underßoor heating systems have Today Uponor PE-Xa made from
covered that the best way to heat gradually become more and more cross-linked polyethylene and MLC
an enclosed space was to introduce advanced. In the 1930Õs systems piping makes underßoor heating
heat below the surface and let it were constructed using steel piping. the perfect long-term solution
radiate upward through the struc- Later still, in the 1960Õs and 1970Õs, for heating requirements. Unlike
ture. The concept of a warm ßoor they were made of copper. These its predecessors and some of its
remains just as true today. The performed reasonably well but current competitors, Uponor pipe
Romans used a type of airborne proved unreliable in the long-term. products are designed to withstand
underßoor heating, the hypocaust, It was found that metal pipes were the stresses placed upon underßoor
a system where smoke from a fur- simply not designed to withstand heating applications. So much so
nace chamber (the fuel was either the stress forces imposed by a con- that the Uponor underßoor heating
charcoal or wood) was led through crete slab. Therefore systems using system is proving its effectiveness
chimneys under the building to heat plastic and composite piping were worldwide in residential, commercial
the structure. The Koreans used a developed. and industrial applications.
similar system.
Underßoor heating is mostly used
in residential buildings. However,
it is also applicable in commercial
and industrial applications. The
underßoor system may be used also
for cooling. This manual provides
the basic information required for
the design of underßoor heating
systems using Uponor PE-Xa and
MLCP pipes. The purpose is to
familiarise technicians, engineers
and other professionals with the
speciÞc advantages of the Uponor
underßoor heating system. The
material presented in this manual is
sufÞcient for the complete design
and calculation of underßoor heat-
ing systems. Installing guidance
for the Uponor underßoor heating
system is provided as well.
Hypocaust around 80 B.C.

Oc`Pkjijmpi_`mÙjjmc`\odibntno`h
Uponor system experience is the selected for optimum performance.
pioneer in branch of underßoor Uponor offers the system which
heating systems since many years. meets all requirements for different
Uponor offers a complete system needs.
for underßoor heating, a system
which includes a full range of pipes
(PE-Xa and Multi layer composite
pipe) and accessories carefully

4 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Introduction

Kmdi^dkg`jac`\o`s^c\ib`]tpi_`mÙjjmc`\odibntno`h
Important factors inßuencing the Heat exchange View and angle factor
heating capacity of water based
underßoor heating systems are Three physical mechanisms inßu- The value of the angle factor
the heat exchange coefÞcient ence heat transfer. The interaction between surface (e.g. ßoor) and
between the heat emitting surface among these three types deÞnes a person depends on the distance
and the indoor space (total heat the character of the heat transfer: between objects and the surface
exchange coefÞcient = convection area (size, shape) included into radi-
+ radiation), the acceptable maxi- Conduction Ð between the heat- ant heat exchange. It means that
mum surface temperature (based ing medium and the surfaces. the closer heating surface is to the
on standard comfort requirements), Convection Ð the transfer of person the higher inßuences has on
heat transfer between the pipes energy between air and surface perceived personÕs temperature. The
and the ßoor surface, emissivity of Radiation Ð the energy which is biggest inßuence on the thermal
the radiant surface and view angle transferred from one surface to sensation of people has a ßoor,
between the surfaces and angle another through electromagnetic because it is the largest and the
factors between the occupant and waves in a range of 0.8-400 µm. closest surface in the room respect
surfaces. to occupied zone of persons.
An underßoor heating system
consists of pipe loops embedded
in a ßoor construction, manifolds Example
and control equipment. The ßoor In comparison, one ¡C change of
surface temperature is clearly higher the ßoor temperature will have
than the temperature of other 2.5 times the effect on the mean
surfaces. The heat exchange on the radiant temperature (and opera-
surface occurs more than 50 % by tive temperature) than a change
radiation. of the ceiling temperature.
(Source: Olesen B. W 2002)

Thermal balance
model of a room
equipped with
surface heating.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 5
BeneÞts of Uponor underßoor heating

=`i`ØonjaPkjijmpi_`mÙjjmc`\odib
Demographic studies indicate More than 30 years of profes- sources like solar energy or heat
that nowadays people are spend- sional experience pumps
ing more time than ever before in Keeps the ßoors warm Can also be used to supply cool-
the home environment, whether Heat emitted mainly by radiation ing during hot periods of the
because of increased leisure time, for higher comfort year
or because of the greater scope Consistent room temperature Low maintenance and service
for working from home offered by Hygienic in operation Ð produces costs
technological development. Home no blown dust System is easy to lay and install
comfort is more important than ever Heating system suitable for There is no need for costly sys-
to both homeowner and building both new construction and the tem separation measures (e.g. by
constructor alike and heating the renovation of existing buildings means of heat exchangers) for
home in the best possible way is Can be combined easily with wall reasons of corrosion protection
given top priority. This is where heating Can be adapted to any type of
Uponor underßoor heating system No danger of burn injuries from architecture
comes in. hot radiators System is vandal-proof
Outstanding energy savings for Free room design
The main advantages of Uponor heating system
underßoor heating systems: Cost-efÞcient installation Some of the key advantages are
Can be used with condensing listed below more in detail.
heaters and renewable energy

>jhajmo\]g`ntno`h
Investigations show that the ideal The entire ßoor surface area radiator, convection, and ceiling
vertical room temperature distri- becomes a low temperature radia- heating systems do not deliver
bution allowing for the highest tor, which warms up the surfaces sufÞcient warmth at or near ßoor
comfort varies for different heating in a room, gives a horizontal even level, whilst in the case of forced
system as shown in Figure 1.1. The temperature distribution and sur- air systems, excess warmth at head
most acceptable indoor climate is rounds the body with warmth. Heat height is produced. In addition,
one in which the ßoor temperature loss, one of the primary causes of both radiator and convector heat-
ranges between 22 - 25 ¡C and physical discomfort, is reduced to a ing systems create uneven pools of
the head height temperature varies minimum. In particular, there is no warmth, which may cause discom-
from 19 - 20 ¡C. In other words loss of heat owing to a cold ßoor fort, whilst forced air heating often
people feel most comfortable with surface. Moreover air movement, leads to an uneven temperature
their feet a little warmer than their without the need for air circulation, distribution.
heads. Underßoor heating is the is also at a low level, which helps
heating method that comes closest prevent heat escape. Other forms of
to producing an ideal room tem- heating cannot match this perform-
perature distribution. ance. Figure 1.1 below show that

Figure 1.1
Ideal vertical
temperature proÞle

16 18 20 22 24 ¡C 16 18 20 22 24 ¡C 16 18 20 22 24 ¡C 16 18 20 22 24 ¡C 16 18 20 22 24 ¡C
Ideal heating Underfloor heating Radiant ceiling External-wall Internal-wall
heating radiator heating radiator heating

6 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
BeneÞts of Uponor underßoor heating

>g`\i\i_c`\goct`iqdmjih`io
Convector and forced air heat- injury, from scalding for example.
ing systems rely on air circulation Moreover the Uponor underßoor
for effect. The Uponor underßoor heating system runs quietly there
heating system, meanwhile, allows are no irritating or disturbing
natural air movement. Thus dust background noises. Furthermore
and other airborne particles such because the ßoor surface is warm,
as pollen are not spread so quickly cleaning and drying is made quick
through the home, making the and easy, quick-drying ßoors being
house a healthier and cleaner place of particular beneÞt in bathrooms
to live in. Meanwhile there are no and hallways.
radiators to gather dirt or cause

>jhkg`o`_`ndbiam``_jh
With the heating system out of Figure 1.2
Architectonically
sight under the ßoor (and thus free space
protected from external damage),
a room may be designed, decorated
and furnished to the architect or
homeownerÕs preference. There is
more usable ßoor and wall space,
and there are no ugly heating
grilles or bulky radiators to detract
from the appearance of the room.
The Uponor underßoor heating
system is ideal for advanced interior
design.

<_\ko\]g`\i_ @i`mbt`^d`iordocgjrh\dio`i\i^`
 `\ntojdino\gg  ^jnon
The Uponor underßoor heating Underßoor heating is the most there are few moving parts, the only
system is adaptable to a variety of efÞcient mode of heat delivery. items that will ever need service are
energy sources: geothermal, wood, It is designed to give comfort at simple and inexpensive to repair or
gas, oil, electricity or solar power. temperatures lower than those used replace.
As such it can be converted to in radiator and convector systems
more cost-effective fuel sources as because people and objects are
circumstances dictate. Furthermore warmed directly through the ßoor
it adapts to practically all kinds of (ßoor surface temperatures are
ßooring and can also be combined generally designed to remain at or
with other types of heating systems below 29 ¡C). Temperatures can be
should the need arise. It is also easy precisely controlled on a room-by-
to install. room basis. In addition, because

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 7
BeneÞts of Uponor underßoor heating

@i`mbt(n\qdib\i_`iqdmjih`io\gamd`i_gt
The thermal insulation Þtted to temperature, during the warm- Figure 1.3
Uponor underßoor
a building, the choice of room up phase, of just 30 - 40 ¡C. The heating is a
temperature and the type of heat- reduced operating temperatures of environmental
friendly system
ing system installed, all inßuence underßoor heating systems permit
the amount of the used energy for the use of low-temperature and
heating. The larger radiant-heat condensing boilers, along with Solar panels

surfaces used with underßoor renewable energy sources like heat


heating mean that a pleasant room pumps and solar power. Uponor
climate can be achieved with room underßoor heating is a future-
temperatures 1 - 2 K below those orientated system, designed to
that conventional radiator systems make an important contribution
use to produce the same heating to sustainable development, to
effect. And a drop of just 1 K in energy-saving and environmental
room temperature delivers energy protection.
savings of around 6 %. New resi-
dential and commercial buildings
are nowadays Þtted with highly
Low-temperature
efÞcient insulation, which Uponor Heat pump heating boiler,
oil-gas burner
condensing boilers
underßoor heating uses to produce
District heating
an ideal room climate with a supply

M\ib`ja\kkgd^\odjin
Uponor underßoor heating is a uni- House construction in general
versal systems which can be used OfÞce and administrative
in all kinds of private residential, buildings
public, commercial and industrial Industrial and commercial
buildings. Almost 50 % of all new buildings
detached and semi-detached hous- Assembly and maintenance
es in Germany are now equipped workshops
with an underßoor heating system. Hangars, warehouses, logistics
Uponor underßoor heating systems and distribution centres
are especially suitable for the fol- Hospitals, therapy centres, sen-
lowing applications: ior citizensÕ and nursing homes
Prisons and reformatories
Research facilities, laboratories,
food-industry plants
Schools and youth centres
Churches, museums
Bars and restaurants
Shopping malls, market halls and
exhibition centres
Indoor and outdoor swimming
pools
Open areas and green spaces
Garages, pavements, driveways

8 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
BeneÞts of Uponor underßoor heating

Oc`mh\g^jhajmo\i_no\i_\m_m`lpdm`h`ion
With pressure of international community on the indoor The indoor environment consists of four interacting
environmental certiÞcation into classes and environ- factors, which should be controlled within standard
mental auditing of buildings it is more and more impor- limits:
tant to deÞne the standard measures of a comfortable
environment for indoor human occupation. Thermal environment
Air quality
The aim of HVAC systems in buildings is to provide a Acoustics
healthy and comfortable indoor environment, which Lighting
enhances the performance of the occupants. The goal
is to provide this optimal indoor environment at low
energy consumption.

Thermal Environment Can the high ßoor surface temperature perform


harmfully on humans?
Thermal Environment represents the characteristics A clinical study was carried out by Dr. B. Scala from the
of the environment which affect the heat exchange European Association for Phlebology3) to examine the
between the human body and the environment. effect of underßoor heating systems on legs, veins and
vein diseases. This study showed that 69 % of tested
Operative temperature subjects reached stability of the clinical state, 7 % clini-
cal state got worse and the state of 25 % achieved an
Optimal temperature for winter: 22 ¡C ‡ 5 % PPD 1)
improvement in the clinical state during 6 month testing
Valid for: Typical winter clothing (1.0 clo): period.
Underwear with short sleeves and legs, shirt, trou-
sers, jacket, socks, shoes How often has the surface of underßoor heating
high temperature?
Sedentary activity level (1.2 met): OfÞce, dwelling,
Design maximum surface temperature of 29 ¡C may
school, laboratory ‡ a person produces 70 W/m2
be achieved just during a narrow time period when
Example of higher activity level (2.8 met): Walking on the design outdoor conditions occur. It means during
level ground 4 km/h ‡ a person produces 165 W/m2 a week with the lowest outdoor temperature. Else the
surface temperature will ßuctuate during the heating
Floor surface temperature season between 20 and 29 ¡C according to external
The ßoor temperature has a direct effect on comfort weather conditions and heat loss rate of space.
of the feet. The recommended ßoor temperatures will
however depend on ßoors which people occupy with Radiant temperature asymmetry
shoes and spaces with bare feet. There are seldom problems with radiant asymmetry from
cold windows in modern buildings. People are most
Recommended ßoor temperature range 19 Ð 29 ¡C, sensitive to radiant asymmetry caused by warm ceiling
for rooms with sedentary and/or standing occupants or cool walls Ð windows. Temperature asymmetry of 5 K
wearing normal shoes for warm ceiling and 10 K for walls.
Optimal ßoor temperature 24 ¡C ‡ 6 % PPD
Draught and Air velocity
Valid for: Typical winter clothing: Underwear with At air temperatures lower than 24¡C, up to 0.15 m/s air
short sleeves and legs, shirt, trousers, jacket, socks, velocity is accepted. If air velocity is higher than 0.15
normal indoor shoes m/s, this is due to incorrect adjustment of ventilation
Floor temperature max. just in peripheral area 35 ¡C 2) or to surface temperatures in the room being too high
or too low. With temperatures above 24¡C, higher air
velocities are acceptable.

1)
It is not possible to reach the satisfaction all of the building occupants. At least 5 % will be always complaining.
2)
The peripheral zone within 1 m from outside walls/windows.
3)
Phlebology is a medical branch that works on veins and vein diseases

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 9
BeneÞts of Uponor underßoor heating

Floor heating Vertical air temperature difference


Rooms with underßoor heating
Warm air heating
system have a uniform temperature
proÞle. The standard (EN ISO 7730)
requires the vertical temperature dif-
ference lower than 3 ¡C per meter;
preferably it stays below 2 ¡C. Bad
designed systems show gradients up
to 7 ¡C. In high ceiling spaces, such
as industrial workplaces, atria, and
hangars, increased stratiÞcation sig-
niÞcantly increases heat loss because
of the increase in average space
temperature. Floor heating is here a
perfect solution to keep warm just
Figure 1.4 Vertical air temperature difference in an airplane hangar equipped with ßoor heating
the in the occupied area and not to
and warm air heating heat the air under the ceiling.

Indoor air quality and allergies


Step against allergies
Surface radiant heating systems operate with less transportation of
Underßoor heating may also inßu-
dust compared to convective systems.
ence the indoor air quality in a
Underßoor heating avoid cleaning and maintenance of heat emitters
space.
Due to the higher surface temperatures, there is less chance for
condensation and mould growth. Floor heating also prevents cold
The German Allergy and Asthma
corners.
Association has conducted a study
Underßoor heating reduces the favourable living conditions for house
showing that ßoor heating reduces
dust mites compared to other heating systems.
the favourable living conditions
Higher temperatures in carpets and mattresses decrease the relative
for house dust mites compared to
humidity. Also, because mites seek the upper areas, they are more
other heating systems. Higher tem-
easily removed by vacuum cleaners.
peratures in carpets and mattresses
decrease the relative humidity. Also,
because mites seek the upper areas,
they are more easily removed by
vacuum cleaners.

Figure 1.5 Sample of creatures living in textile ßoor coverings and carpets

10 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Uponor underßoor heating system Ð Home Comfort

Pkjijmpi_`mÙjjmc`\odibntno`hÊCjh`>jhajmo
Home comfort is a complex and types, different pipe dimensions, apply with both pipe types. This
professional underßoor heating pipe distances, wide range of Þxa- complete system portfolio includes
system with a wide range of offered tion methods for different market also manifolds and wide range of
products. The use of the product needs and different construction controls, accessories, tools. The
range is very ßexible thanks to a types. A wet system is available offer of the Home Comfort system
modular approach, which allows for all common screeded installa- is supported by the designers train-
the interchangeable combination of tions and a lightweight system for ings at Uponor Academy and by a
products. Systems offer the heating reconstruction business. Most of design tool Ð HSE Software with
solutions with two different pipe the Þxation types are possible to Uponor product catalogue.

Hj_pg\m\kkmj\^c
Modular system ‡ means less items
Example
to be stored
one manifold for both pipe types (MLCP, PE-Xa)
basic kit + 4 extensions allow to create all necessary outlets
High ßexibility due to modular
max. 5 items to build at least 12 different manifolds
system ‡ Components are inter-
changeable

Agjjmnomp^opm`
The Uponor range of items for Uponor PE-Xa and MLC pipes Accessories
underßoor heating installation Different pipe Þxations Controls
includes the following system Insulation Tools
components: Manifold

Type A Type B Type G


Table 2.1
Chipboard or parquet Vapour barrier under Uponor heat Uponor PE-Xa pipe
ClassiÞcation of parquet emission plate 20 x 2.0 mm
Uponor underßoor
heating systems
according to
international 300 mm
standards; systems
with pipes in the
screed, pipes
outside the screed
(e.g. in thermal Insulation Battens minimum 22 x 95 mm with a Floor joist
pitch of 150 mm
insulation) and
system with pipes in
the wooden ßoor Uponor solution: Uponor solution: Uponor solution:
construction
clamp track lightweight panel heat emission plate
cable tie
pipe positioning panel
Comply to standard: Comply to standard: Comply to standards:
EN 1264 EN 1264 EN 15277-1
Legend: 1 Ð ßoor covering, 2 Ð heat diffusion layer, screed, 3 Ð heat emission plate, 4 Ð thermal insulation, 5 Ð building structure

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 11
Uponor underßoor heating system Ð Home Comfort

PkjijmK@(S\kdk`
Uponor PE-Xa pipes are made from
a plastic raw material, HD polyeth-
ylene, which has a high molecular
weight. At high pressure and high
temperatures, chemical bonds - also
called cross-links - are formed
between the long molecular chains Structure of pePEX
in the polyethylene using the cross- pipe with outer
diameter of 17 and
linking agent, peroxide. In this way 20 mm
a three-dimensional lattice is cre-
ated. Thanks to that Uponor PE-Xa
is extraordinarily strong. Uponor
underßoor heating PE-Xa pipes are
produced in accordance with prEN
15785.

Uponor eval and pePE-Xa Q&E PE outermost layer. This layer is


Basic PE-Xa pipe
pipes have an oxygen diffusion very ßexible and does not affect the Adhesive layer
barrier of EVOH (ethyl vinyl alco- ßexibility and pliability of the basic Diffusion barrier EVOH
hol). This barrier consists of a layer pipe. Uponor eval and pePE-Xa Adhesive layer
Scratch protection made of PE
of EVOH that is extruded on the Q&E pipes fulÞl the requirements
outside of the PE-Xa pipe. The for oxygen diffusion resistance as
pePE-Xa pipes have an additional per DIN 4726.

Pkjijmhpgodg\t`m^jhkjndo`kdk`
Uponor MLC pipe consists of a lap be adapted to speciÞc handling
welded aluminium pipe with an requirements. Smaller dimensions
inner and outer polyethylene layer. of MLC pipes are designed so that
All layers are permanently bonded the aluminium layer neutralises
together by means of an intermedi- the snap-back forces of the plastic
ate adhesive layer. The PE material material, enabling easier pipe instal-
PE-RT Adhesive Adhesive PE-RT is noncross-linked polyethylene lation with minimal effort.
Structure of Longitudinally welded of raised temperature resistance
MLC pipe with aluminium according to DIN 16833. Owing to The aluminium layer is important
outer diameter
of 16 and 18 mm
the speciÞc form of the octane side for heat expansion. Owing to the
chains in the molecular structure permanent bond between plastic
of the material, a similar effect and aluminium, thermal expansion
is achieved when polyethylene is is determined by the expansion
The Uponor multi-layer composite cross-linked. factor of the aluminium and roughly
pipe (MLCP) is a pipe genera- corresponds to that of a metal pipe,
tion that unites the advantages of Lap welding of the aluminium i.e. just approximately 1/7th of the
a plastic and a metal pipe and pipe produces a highly reliable and expansion of a pure plastic pipe.
therefore offers a high degree of lasting connection on account of
ßexibility and toughness, coupled the wider joint. The thickness of
with high pressure and temperature the aluminium layer is therefore
resistance. not decisive for welding and so can

12 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Uponor underßoor heating system Ð Home Comfort

Technical speciÞcation of pipes


Uponor PE-Xa pipe Uponor MLC pipe
Pipe type Uponor PE-Xa Q&E Uponor MLC UFH pipe
Pipe dimensions 9.9 x 1.1, 14 x 2.0, 17 x 2.0, 16 x 2.0, 18 x 2.0 mm
20 x 2.0 mm
Basic material PE-Xa PE-RT / aluminium / PE-RT
Pipe structure pe PE-Xa: basic PEXa pipe / PE-RT / adhesive / longitudinally
adhesive / diffusion barrier EVOH / overlapped welded aluminium /
adhesive / scratch protective PE adhesive / PE-RT)
eval PE-Xa: basic PEXa pipe /
adhesive / diffusion barrier EVOH
Production according to DIN 16892/4729
Oxygen tightness according to DIN 4726 according to DIN 4726
Density 0.938 g/cm3 -
Thermal conductivity 0.35 W/mK 0.35 W/mK
Building material class B2 B2
Pipe roughness 0.007 mm 0.0004
Operating common range for heating 50 ¡C / 1.5 bar 50 ¡C / 1.5 bar
Operating max. range for heating 70 ¡C / 6 bar 60 ¡C / 6 bar
Malfunction temperature 95 ¡C 95 ¡C
Crystallite melting point 133¡C -
Optimum installation temperature ³ 0 ¡C ³ 0 ¡C
UV protection, storage opaque carton opaque carton
(leave unused pipe in carton) (leave unused pipe in carton)
Properties Diffusion tightness, scratch resist- Diffusion tightness, form stability,
ant envelope, 35 years tested scratch resistant envelope
durability, recyclable material

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 13
Uponor underßoor heating system Ð Home Comfort

Kdk`Øs\odjih`ocj_n
Uponor offers different Þxation
methods which can be combined
with both Uponor pipes. This make
the Uponor underßoor heating sys-
tem suitable for various applications
(see decision table).

Overview on pipe Þxation methods


Pipe Type Pipe dimension Fixation
Uponor MLC 16 mm clamp track 16
clamp track

PE-Xa 14, 17, 20 mm clamp track 14 - 20

MLC 16, 18 mm +

Uponor PE-Xa 14, 17, 20 mm


cable tie /
tying wire
MLC 16, 18 mm

Uponor pipe PE-Xa 14 mm


positioning
panel
MLC 16 mm

Uponor PE-Xa 14 mm heat emission plate 14 mm


lightweight
panel
+

Uponor heat PE-Xa 20 mm heat emission plate 20 mm


emission plate

Uponor high PE-Xa 9.9 mm clamp track 9.9


performance
panel

14 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Uponor underßoor heating system Ð Home Comfort

?`^dndjio\]g`
Decision table for choosing the right Uponor underßoor heating
Uponor underßoor heating systems Uponor Uponor Uponor Uponor Uponor Uponor
Home Comfort: clamp Cale tie pipe posi- light- heat emis- high per-
track tying wire tioning weight sion plate* formance
panel panel panel
House age Newly built Ð
Reconstruction Ð Ð Ð Ð
Ceiling / ßoor construction Concrete heavy Ð
Wooden joist Ð Ð Ð Ð
Room shape Square shaped
DifÞcult shape Ð Ð
Room net height is sufÞcient Yes
No Ð Ð Ð Ð
Installation time for UFH Yes
(Þxation & feeds) is sufÞcient? No Ð
Total installation time incl. Yes**
screed drying is sufÞcient? No Ð Ð Ð Ð
Wet screed construction Yes Ð
No Ð Ð Ð Ð
One man installation Yes Ð
No
Thermal insulation supplied Yes Ð Ð***
locally No Ð Ð Ð Ð
* for wooden joist ßoors
** drying time differs according to screeding material
*** thermal insulation is included in reconstructed ßoor

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 15
Design and calculation

?`ndbi\i_^\g^pg\odji
Correct design and installation are such as water temperature and tional ISO standards, European EN
crucial to the satisfactory operation required ßow rate. Finally a correct standards and if not available the
of the system. Design features such installation and a balancing of the German DIN standards. In all cases
as loop conÞguration, pipe size, pipe loops will ensure an efÞcient check also national regulations and
spacing and depth are fundamen- performance. codes. The production requirements
tal, whilst other important aspects are included, as well.
which affect the systemÕs perform- Following design and calculation
ance are the calculated values, procedures are based on interna-

Agjjm^jinomp^odji^jhkji`ion
Gj\_]`\mdib The load bearing building construc- line 4. See the installation guides. Load capacity
^jinomp^odji tion must meet the static speciÞca- The load bearing building construc-
tions with respect to the working- tion must be sufÞciently dry. Table 3.1 stipulates different ßoor-
load capacity of ßoor constructions. structure characteristics, depending
The height and evenness of the Pipe conduits, electrical wiring, on ceiling loads and type of use
surface of the load bearing building etc. that run across the load bear- according to DIN 1055-3 ÒAction on
construction must conform, in terms ing building construction must be structures - densities and weights
of maximum/minimum dimensions securely laid. The top surface should of building materialsÒ.
and evenness tolerances, to the then be levelled once more for, sufÞ-
speciÞcations of DIN 18202 ÒDimen- ciently at least for attachment of the
sional tolerances in building con- sound insulation layer. Do not level
structionÓ, table 2 and table 3, line 2 with loose Þlling material consisting
and (for Uponor lightweight panel) of natural or reÞned sand.

Type of application SpeciÞed vertical working load


for ceilings conforming to DIN
1055 (kN/m2)
Dwelling areas, 1-2 family houses 2.0
Areas designed for ofÞce use 2.0
Lecture rooms, classrooms, treatment rooms, hotels 3.0
Large rooms in public buildings, e.g. churches, cinemas, gymnasiums, show- 5.0
rooms and shopping centres, shops and department stores, bookshops,
public-record ofÞces, catering establishments, commercial kitchens, bakeries,
factories and workshops with easy operation also for driveways and ramps in
underground garages and multi-storey car parks for passenger cars and other
vehicles with gross weights of up to 2.5 tons

16 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

All loops are to be maintained at the weight of the cement is 0.8 % Floor construction Uponor Otk`njar`o
normal operating pressure while the up to 0.12 %. Screed additive for clamp track and cable tie or n^m``_`_Ùjjmn
screed is being laid. Heating screed minor pipe coverage is suitable for tying wire
should be laid in conformity with cement-based screed ZE 30. The
DIN 18560-2 ÒScreeds in building use of this screed additive improves Uponor underßoor heating with
construction; ßoating screeds on heat conductivity, while increas- clamp track or cable tie/tying wire
insulation materialÒ. Cement-based ing the bending tensile strength conforms to building classiÞcation
screed should normally be used and crush resistance of the screed. B1 and is suitable for use with both
with Uponor screed additive. The The cement screed covering over cement based screed (ZE), and
use of screed additive improves pipes can be reduced to 30 mm anhydrite liquid screed (AE). The
heat conductivity, while increasing when Uponor screed additive is insulation roll with pipe Þxing foil
bending tensile strength and crush used; applicable for moving load up can be used with moving loads of
resistance. In case of cement-based to 2.0 kN/m2. With a total screed up to 5 KN/m2 (kPa). The available
screed with strength-grade cement height of 50 mm, approx. 1.3 kg of type of installation is a pipe Þxing
ZE 20 and/or anhydrite screed AE screed additive is required per m2. foil and/or insulation roll with pipe
20, normally screed pipe coverings The proportion with respect to the Þxing foil, with pipes secured by
of 45 mm are required for use in weight of the cement is 7.0 % up to means of clamp track.
residential buildings. When using 15 %. Experience suggests a recom-
anhydrite screed, the height of the mended average level of 12 %. Pipe Þxing foil and Insulation
covering may be reduced to 35 roll with pipe Þxing foil
mm. The manufacturerÕs instruc- The amount of additive required The pipe Þxing foil, used in con-
tions must be observed at all times. depends on the speciÞcations junction with the clamp track, is a
Thicker screed is normally required involved. The supplierÕs instructions key element of the Uponor under-
in case of higher speciÞcations. should be taken into account when ßoor heating system. It reßects the
Observe the instructions of the laying liquid or anhydrite screed. heat emitted by the Uponor pipes.
screed supplier. The screed should only be laid at There is an air-pocket layer on top
room temperatures of over 5 ¡C. of the aluminium Þlm, containing
Note: Use of Uponor screed addi- The system should be protected more than 8,000 tiny air chambers
tives with anhydrite liquid screed is from frost. Take suitable steps to per m2, which provides the required
not allowed. prevent the action of frost, and reßection clearance between the
avoid draughts during the drying aluminium layer and the screed.
The screed additive is suitable for stage. Screed heating should be The use of pipe Þxing foil increases
cement-based screed ZE 20 improve carried out according to the techni- the amount of heat radiated
heat conductivity by homogenisa- cal standards EN 1264. upwards, thereby reducing the
tion and quality-improvement of amount wasted by being radi-
the material. With a pipe cover- ated downwards. In comparison
ing of 45 mm and/or total screed to Uponor underßoor heating
height of 65 mm, about 0.16 kg of without pipe Þxing foil, lower hot
screed additive is required for each water temperatures are required to
m2. The proportion with respect to achieve a given heat output level.

Insulation without Insulation with


pipe fix. foil pipe fix. foil

Figure 3.1
Conventional insulation pipe fix. foil Floor
Screed Screed construction
Uponor clamp
Heating pipe Heating pipe track

Insulation PST 33/30 pipe Þx. foil


Insulation PST 33/30

Concrete Concrete

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 17
Design and calculation

A main characteristic of Uponor entry of damp into the insulation of a polystyrene thermal and sound
underßoor heating with pipe Þxing material lying below it. The printed- insulating layer EPS of 27 mm, plus
foil is the waviness of the ßoor on grid pattern is suitable for any a laminated-on pipe Þxing foil layer.
surface temperature. The heat- type of laying, and helps with pipe The combination of pipe Þxing
reßecting properties of pipe Þxing alignment during installation. foil insulation roll with PS insula-
foil reduce warm-up times, allowing tion boards and/or PUR insulation
the ßoor heating surface to react Insulation roll with pipe Þxing foil is boards, or with other standard
more quickly to changing condi- a ready-to-lay thermal and sound insulation material supplied locally
tions. Pipe Þxing foil can also be insulation supplied in rolls, which by the customer, can cover virtually
used with appropriate additional is designed to fulÞl the require- any type of situation.
heat insulation supplied locally by ments of EN 1264-4 with respect
the customer. It is impervious to to ßoors shared by rooms with
water vapour, thus preventing the similar heating systems. It consists

Figure 3.2 Thermal


functionality of the Floor surface temperature
pipe Þxing foil

Uponor heating pipes


Pipe Þxing foil
Thermal insulation

Insulation roll with pipe Þxing foil is Advantages:


Note
suitable for use with moving loads Ready-to-lay thermal and sound
In case of combination of more
of up to 5 kN/m2, making it not insulation supplied in rolls
sound and thermal insulation
only ideal for use in the construc- Fast and simple laying
layers, the material with lower
tion of residential properties, but Can be laid on standard insula-
compressibility should lay on the
also in the commercial and business tion in conjunction with pipe
top. The reason is to redistribute
sector and for public buildings etc. Þxing foil
the concentrated pressure to
The use of pipe Þxing foil along Can be installed with Uponor
larger area.
with additional insulation material MLC pipe 16, 18 mm and
supplied onsite and/or insulation Uponor PE-Xa pipes dim 14, 17
roll with pipe Þxing foil can further and 20 mm
optimise sound insulation. Printed-on grid pattern to act as
laying guide
Uponor MLC pipe 16, 18 mm and Suitable for both biÞlar and
Uponor PE-Xa pipes dim 14, 17, 20 meandering installation
mm are Þxed to the pipe Þxing foil Can be laid by a single person
and/or insulation roll with pipe Þx- Insulation roll with pipe Þxing
ing foil by means of clamp track 16 foil suitable for moving loads of
or clamp track 14 - 20 and fasten- up to 5 kN/m2
ing nails. Pipe Þxing foil increases the
amount of heat radiated
upwards

18 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Example of the ßoor construction onto similarly-heated rooms:


Uponor clamp track and insulation roll with pipe Þxing foil
Uponor clamp track and pipe Þxing foil + standard thermal and sound insulation

Note
For improved ease and quality of insulation, we recommend the use of insulation roll with
pipe Þxing foil. The classiÞcation of thermal insulation requirements is listed in Table 3.2.

Figure 3.3 Uponor


clamp track and
insulation roll with
pipe Þxing foil Legend
1 1 Upper ßoor covering
3 2 Screed
Pipe-
covering 3 Edging strip
2
4 Uponor pipe

95 mm
4 45 mm*
5 Clamp track
5
20 mm 6 Insulation roll with pipe Þxing foil
7 Load-bearing construction
6 30 mm**

* Heating screed conforming to DIN 18560-2, table 2, screed-types AE 20 and ZE 20, building classiÞcation B1, 65 mm
screed thickness, 45 mm pipe covering. In case of anhydrite screed (AE), a screed thickness of 55 mm, and/or a pipe
covering of 35 mm are possible. Please observe the manufacturerÕs instructions. Screed additive: See system components
Consult the person responsible for laying the screed if the surface is to be subjected to moving loads higher than those
speciÞed.
** An increase of 10 mm in the height of the insulating layer EPS will increases thermal resistance by Rλ = 0.25 (m2 x K)/W.

Example of the ßoor construction with higher insulation requirements:


Uponor clamp track and insulation roll with pipe fixing foil + standard thermal and sound
insulation
Uponor clamp track and pipe fixing foil + standard thermal and sound insulation

Figure 3.4 Uponor


clamp track and
insulation roll with Legend
pipe Þxing foil and 1 1 Upper ßoor covering
PS insulation board 2 Screed
3 2 Pipe-
covering 3 Edging strip
45 mm* 4 Uponor pipe
4
115 mm

5 Clamp track
20 mm
5 6 Insulation roll with pipe Þxing foil
6 7 Load-bearing construction
50 mm 10 Standard thermal insulation
10 choose locally

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 19
Design and calculation

Floor construction Uponor pipe The simple push-in principle allows Advantages:
positioning panel sections of Uponor pipe positioning Can be laid on top of standard
panel to be joined together in any insulation
Uponor underßoor heating with location. The panels are trimmed to No multiple handling of insula-
pipe positioning panel conforms Þt the shape of the ßoor using an tion materials
to building classiÞcation B1 and is easily-available blade cutter, which Floor can be conÞgured individ-
suitable for use with both cement- virtually eliminates rest material. ually according to local condi-
based screed (ZE) and anhydrite Special connection elements tions
liquid screed (AE). When used with located between the Þxing protru- Compatible with Uponor PE-Xa
suitable standard insulation materi- sions raise the Uponor pipe 4 mm pipe 14 x 2 mm and MLC pipe
als and load-distribution layers, above the height of the base plate. 16 x 2 mm
the Uponor pipe positioning panel As these protrusions have no direct Less waste
can bear moving loads of up to 20 contact with the installed pipes, the Simple snap-on connection of
kN/m2. It is thus also possible to Uponor pipe is completely sur- one section of panel to another
conÞgure commercial and indus- rounded by heating screed - which Can be laid by a single person
trial installation with load-bearing optimises heat distribution. High weight-bearing capacity for
underßoor heating with the Uponor moving loads of up to 20 kN/m2
pipe positioning panel. BiÞlar (coiled) and meandering The few system elements
(snaking) installation of Uponor required are all short-weight and
The pipe positioning panel is pipes are both fully compatible with clean to handle
made of a moulded-polystyrene the use of Uponor pipe position-
foil material designed to permit ing panels. The use of clips for
fast and simple installation on top diagonal installation 14-16 also
of standard heating and sound allows Uponor PE-Xa pipe 14 x 2
insulation. The robust construction mm and MLC pipe 16 x 2 mm to be
of the Uponor pipe positioning laid across Uponor pipe positioning
panel allows architects, planning panels at an angle of 45¡. Attach-
engineers, plumbers and building ment of the Þxing clip 14-16 is
owners to adapt thermal and sound carried out by simple insertion into
insulation precisely to individual the free space between the protru-
onsite conditions. When combined sions in the Uponor pipe position-
with different types of insulation ing panel, at the points marked for
materials approved for use in ßoors, the purpose.
different conÞgurations can be cre-
ated according to the type of ßoor
required.

Uponor pipe positioning panel is


used for securing Uponor PE-Xa
pipe 14 x 2 mm and Uponor MLC
pipe 16 x 2 mm, and also in order
to prevent screed and liquid cement
from seeping through to the
insulating layer below. The spe-
cially-designed shape of the Þxing
protrusions supplies each Uponor
pipe positioning panel with great
strength.

20 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Example of the ßoor construction onto similarly-heated rooms:


Uponor pipe positioning panel with standard thermal and sound insulation

Figure 3.5 Uponor


pipe positioning
panel with standard
thermal and sound
insulation Legend
1
3 1 Upper ßoor covering
Pipe-
2 covering 2 Screed
3 Edging strip

100 mm
4 45 mm* 4 Uponor pipe
5
20 mm 5 Uponor pipe positioning panel
7 6 Load-bearing bottom layer
35 mm
7 Standard insulation
6

Example of the ßoor construction with higher insulation requirements:


Uponor pipe positioning panel with more layers of standard thermal and sound insulation

Note
Refer to the site planner for details of the speciÞed U-value for newly-built constructions
with normal inside temperatures pursuant to ¤ 3 of EnEV. The value must not drop below the
minimum requirements for insulation conforming to EN 1264-4 (see Table 3.2 for thermal
resistance Rλ [(m2 x K)/W]).

Figure 3.6 Uponor


pipe positioning
panel with higher
insulation
requirements
1 Legend
3 Pipe- 1 Upper ßoor covering
2 covering 2 Screed
4 45 mm* 3 Edging strip
5 20 mm 4 Uponor pipe
150 mm

5 Uponor pipe positioning panel


7 6 Load-bearing bottom layer
7 Standard insulations, PS insulation
85 mm** board on top and other standard
insulation
7

* Heating screed conforming to DIN 18560-2, table 2, screed-types AE 20 and ZE 20, building classiÞcation B1, 65 mm
screed thickness, 45 mm pipe covering. In case of anhydrite screed (AE), a screed thickness of 55 mm, and/or a pipe
covering of 35 mm are possible. Please observe the manufacturerÕs instructions. Screed additive: See system components
Consult the person responsible for laying the screed if the surface is to be subjected to moving loads higher than those
speciÞed.
** An increase of 10 mm in the height of the insulating layer increases thermal conduction resistance by Rλ = 0.25 (m2 x K)/W.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 21
Design and calculation

Otk`njaÙjjmn Dry screeding boards are used with Advantages:


rdoc_mtn^m``_ Uponor lightweight panel. Those Floor structures are less thick in
boards are supplied locally. comparison to wet-screed sys-
tems, means also lower structure
Floor construction Uponor weight
lightweight panel The system elements of low-
weight and clean to handle
The Uponor lightweight panel is a Installation of the Uponor
special underßoor heating system lightweight panel system without
developed for use in a dry instal- waste
lation manner that ensures a quick The entire system can be installed
installation and application in by one person working alone
reconstruction business. Insulation and pipe assembly
installed at same height, leaving
The Uponor lightweight panel sys- ßoor at same level as unheated
tem is the ideal complement to the ßoors (e.g. underßoor heating in
Uponor underßoor heating system bathroom only)
with wet screed. It is equally suit- Omega-shaped pipe conduit
able for the modernization of exist- ensures good contact between
ing buildings and for use in new Uponor PE-Xa pipes 14 x 2 mm
constructions. Special applications and heat emission platesÕ bend
(e.g. underßoor heating for large area
indoor sports facilities) can also The use of dry-screed elements
be catered for. Uponor lightweight (commonly 25 mm thick) means
panel underßoor heating can be no drying time of heat screed
combined with standard dry-screed No onsite delays - operatives can
elements. The 25 mm-thick light- walk on top of underßoor heating
weight panel basic element, which immediately after installation
is made of polystyrene foam EPS, No damp-penetration of the
permits installation over entire room buildingÕs structure (an important
surfaces. It acts both as heat insula- point where old buildings, pre-
tion and as a weight-bearing base fabricated houses and wooden-
for installation of heat emission frame houses are concerned)
plate of the lightweight panel. The Ceilings can be plastered just
all-round stepped rebate with built- one day after installation of the
in tenons and indentations permits dry-screed elements. As there is
the secure interconnected attach- hardly any vibration, the occur-
ment of basic-elements to edge of rence of cracking in ceramic
the plate. The conÞguration of the coverings, if correctly laid, can
slots in the basic-element permits virtually be ruled out.
meandering conÞguration of the
Uponor PE-Xa pipe 14 x 2 mm.

The 0.5 mm thick heat emission


plate of the lightweight panel
(made of aluminium sheet, λ =
200 W/mK) provides optimum
transmission of heat to the dry-
screed elements. Two integrated
pre-cuts ensure easy shortening
and installation.

22 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Example of the ßoor construction onto similarly-heated rooms:


Uponor lightweight panel
Uponor lightweight panel with thin standard thermal and sound insulation

Figure 3.7 Uponor


lightweight panel
Suggested solution Legend
for modernising . 1 Upper ßoor covering
Existing insulation
may be taken into 2 Edging strip
account. 3 Screed element 25 mm (please
consult supplier)
7 Uponor pipe
1 8 Uponor lightweight panel
3 25 mm

45 mm
2 9 Load-bearing bottom layer with
10 existing insulation
25 mm
8
10 Heat emission plate
9

Figure 3.8 Uponor


lightweight panel
with a thin standard Legend
thermal and sound
insulation
1 Upper ßoor covering
Suggested solution 2 Edging strip
for modernising 3 Screed element 25 mm (please
Existing insulation consult supplier)
may be taken into
7 Uponor pipe
account. 25 mm
8 Uponor lightweight panel
55 mm

25 mm 9 Load-bearing bottom layer


10 mm 10 Heat emission plate
12 EPS insulation board of 10 mm

Example of the ßoor construction with higher insulation requirements:


Uponor lightweight panel with layers of standard thermal and sound insulation of higher requirements

Figure 3.9 Uponor


lightweight panel
with layers of Legend
standard thermal 1 Upper ßoor covering
and sound 2 Edging strip
insulation of higher 3 Screed element 25 mm (please
requirements
25 mm consult supplier)
7 Uponor pipe
25 mm
105 mm

8 Uponor lightweight panel


9 Load-bearing bottom layer
55 mm* 10 Heat emission plate
13 EPS high-resistance foam* of
55 mm

* An increase of 10 mm in the height of the insulating layer increases thermal conduction resistance by Rλ = 0.285 (m2 x K)/W.
Note: In order to prevent any spring-bending of the structure, you are recommended to stick the additional insulation onto a Þrm and even base
using a solvent-free dispersion adhesive

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 23
Design and calculation

Floor construction Uponor Remarks on the Uponor light- The thinner screed layer ensures
lightweight panel with liquid weight-construction system faster warm-up times and
screed with wet screed shorter delays for the underßoor
The pipe lies within the thermal heating system, in comparison to
The Uponor lightweight panel insulation, thus reducing the conventional wet-screed systems
is a standard dry system for a construction height relative to Lower supply temperatures
quick installation and recon- conventional wet-screed systems Separation between heating level
struction business. However, it is Approx. 2 cm less heat screed, and load-distribution layer (and
optionally also used with anhydrite thus permitting faster drying of so fewer problems with joints)
liquid screed. This will decrease the the screed used Clear separation between the
thickness of the system in compari- Lower weight due to thinner works of underßoor heating
son to other wet screeded types of screed layer (with cost savings of system and screed/natural-stone
system heat screed) Þnishes

Example of the ßoor construction onto similarly-heated rooms:


Uponor lightweight panel
Uponor lightweight panel with thin standard thermal and sound insulation

Figure 3.10 Uponor


lightweight panel
Legend
1 Upper ßoor covering
2 Edging strip
4 Liquid screed 35 mm
6 PE-foil
1 7 Uponor pipe
4 35 mm 8 Uponor lightweight panel
60 mm

2 9 Load-bearing bottom layer with


6
10 existing insulation
8
25 mm
10 Heat emission plate
9

Example of the ßoor construction with higher insulation requirements:


Uponor lightweight panel with layers of standard thermal and sound insulation of higher requirements

Figure 3.11 Uponor


lightweight panel
with standard Legend
thermal and sound
1 Upper ßoor covering
insulation
2 Edging strip
35 mm 4 Liquid screed 35 mm
6 PE-foil
120 mm

25 mm 7 Uponor pipe
8 Uponor lightweight panel
9 Load-bearing bottom layer
60 mm1)
10 Heat emission plate
14 EPS insulation board* of 60 mm

* An increase of 10 mm in the height of the insulating layer increases thermal conduction resistance by Rλ = 0.25 (m2 x K)/W

24 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Floor construction Uponor to 50 mm when applied to a wood


heat emission plate for wooden subßoor. Gypsum products spe-
ßoors ciÞcally designed for ßoor heating
can generally be installed 25 to 40
The piping with Uponor heat emis- mm thick because they are more
sion plate may be applied also on or ßexible and crack resistant than
under suspended wood ßoors (walls concrete. When concrete is used,
or ceilings) using several methods it should be of structural quality to
of construction. Piping may be reduce cracking due to movement
attached to the surface of the ßoor of the wood frame or shrinkage.
or may be embedded in a layer of Embedding material must provide a
concrete or gypsum, mounted in hard, ßat, smooth surface that can
or below the sub ßoor, or attached accommodate a variety of surface
directly to the underside of the coverings.
subßoor with aluminium panels
to improve heat transfer from the For the information on the ßoor
piping. structure see the installation guide-
line in Chapter 4.
The heat improves the tempera-
ture spread, and the heat can be
evenly distributed throughout the
ßoor. Pipes are generally installed
on 300 mm spacing. The thickness
of the embedding material (con-
crete or gypsum) is generally 25

Figure 3.12a Uponor heat emission plate for wooden ßoors

Figure 3.12b
Uponor heat
Chipboard or parquet Vapour barrier under Uponor heat Uponor PE-Xa pipe emission plate for
wooden ßoors in
parquet emission plate 20 x 2.0 mm cross-section

300 mm

Insulation Battens minimum 22 x 95 mm with a Floor joist


pitch of 150 mm

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 25
Design and calculation

Floor covering materials noted that the greater structural Plastic coverings
height resulting from use of the The typical heat-expansion prop-
The versatility of modern construc- thick mortar bed technique gives erties of plastic products, when
tion materials makes available a rise to considerably longer warm-up they are subjected to temperature
wide range of different products and reaction times where underßoor changes, tends to make them
and types of covering for the heating is concerned. unsuitable for full-surface bonding
ßoors of living areas Þtted with with adhesive.
integrated underßoor heating. Carpet coverings
The typical characteristics of each Textile coverings are normally Wood coverings
material should be established at suitable for use on ßoors Þtted Floors can be Þtted with parquet
the project-design stage in order to with underßoor heating. Cover- blocks or other wooden coverings.
prevent problems arising at a later ings of this type must be stuck The thermal conduction resist-
time. Special attention should be to the entire surface, and their ance of the covering should not be
paid to the subsequent Rλ,B value correspondingly lower thermal increased using additional Þttings
of the ßoor covering eventually conduction resistance taken into materials such as corrugated card-
chosen (see EN 1264-3). The ßoor account. Certain types of covering board. When prefabricated panels
covering should not exceed a value possess very high insulation proper- consisting of plain and mosaic-
of Rλ,B = 0.15 (m2 x K)/W. The lower ties, which can reduce the emission pattern parquet blocks are used,
is the Rλ,B value the more efÞcient is capacity of the heating system. Þttings can be carried out without
the Uponor system Suitable carpet coverings carry the problem using a suitable heat-
corresponding seal of approval, resistant bonding product, while
Ceramic, natural and cast stone consisting of an underßoor heating taking into account the required
These Þnishes can be laid using layout diagram with three arrows at expansion joints.
either the thin or thick mortar-bed the top.
technique. It should however be

Figure 3.13 Rλ,B = 0.1 is applied, when the real


Approximated levels
of thermal Carpeting property of surface covering is not
conduction known.
resistance Rλ,B for Parquet block
details ask the
supplier. Note: See thermal resistances of
Plastic
various ßoor coverings in section
max. 0.15

Ceramic Calculation diagrams.

0 0.05 0.10 0.15


Levels of thermal resistance RMB [(m2 x K)/W]

Ocd^fi`nnjaoc` The depth of the pipe is directly


Note
g\t`mjq`mkdk`n related to the water temperature
In installations where the
(heating capacity). In a system
material above the pipe has
where the pipe is installed deeper
lower thermal conductivity
as standard position, the water tem-
(wood), the pipe can be posi-
perature must be set higher in order
tioned closer to the surface.
to achieve the same heating capac-
When setting pipes in screed
ity. However, in a deeper installa-
it is important to prevent air
tion the ßoor temperature will be
pockets, which can impair the
more even. Standard thickness of
transfer of heat to the screed,
the cement screed over pipes is su =
from forming around the
45 mm, an anhydride screed can be
pipes.
reduced to 35 mm.

26 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Pipe spacing between 120-300 mm See the capacity diagrams for avail- demand is of course the determin- Kdk`
is suitable for Uponor underßoor able pipe spacing for each of the ing variable. In order to simplify the nk\^dib
heating, however in some special construction system type. design hand-calculations, either
cases can be applied also range water temperature or pipe spacing
between 100-400 mm. There are three main variables for can be kept constant. The design
One important factor determining the design of underßoor heat- using Uponor HSE software is more
the pipe spacing is the temperature ing; heat demand in W/m2, water ßexible and comfortable.
variation on the ßoor surface. temperature and pipe spacing. Heat

Energy saving is world wide impor- Thermal insulation requirements Dinpg\odji


tant task. European Union and m`lpdm`h`ion
also in many other countries there The insulation Þtted beneath
is a strong energy-saving restric- underßoor heating systems is sub-
tions proposed by governments. ject to the following regulations:
Related to this topic come also new
Green building standards. See also EN 1264-4 (introduced in 2001)
topic downward heat loss. Thermal ÒUnderßoor heating systems
insulation includes also property of and componentsÒ establishes
an acoustic insulation, therefore the the minimum levels of thermal
acoustic requirements will not be conduction resistance for insula-
dealt separately since the thermal tion layers installed beneath
insulation is always present in ßoor underßoor heating systems.
structure of the system. There are however some addi-
tional local standards for both
existing and newly-constructed
buildings with respect to insula-
tion and heating (e.g. German
EnEV).

Table 3.2 Minimum


Thermal Heated room Unheated or External air temperature below thermal resistance
condition intermittent of insulating layers
below the
under ßoor heated room External design External design External design underßoor heating
structure or directly on temperature temperature temperature system (EN 1264-4)
the ground1)2)3) θe,d ³ 0 ¡C 0 ¡C > θe,d ³ -5 ¡C -5 ¡C > θe,d ³ -15 ¡C
Resistance 0.75 1.25 1.25 1.50 2.00
(m x K/W)
1)
With ground water level ² 5m, the value should be increased.
2)
EnEV Directive: Ceilings neighbouring onto cellars and unheated rooms. The Minimum requirements of ceiling pursuant to EnEV ¤ 3, ¤ 7 and
¤ 8, plus appendix 3, table 1 no. 5a, c, d and f.
Rλ = 2.00 (m2  K)/W and/ or UMax = 0.50 W/(m2  K) (Rλ,Ceiling = 0.07 (m2  K)/W (concrete ceiling 15 - 16 cm) and contact resistance
Ra = 0.17 (m2 x K)/W could be taken into account.)
3)
Directive EnEV ¤ 3, ¤ 7 and ¤ 8, plus appendix 3, table 1 no. 5a, c, d and f: Ceilings neighbouring onto soil.
Rλ = 2.00 (m2  K)/W and/ or UMax = 0.50 W/(m2  K), (Rλ,Ceiling = 0.07 (m2  K)/W (concrete ceiling 15 - 16 cm) and contact resistance,
Ra = 0.17 (m2 x K)/W could be taken into account.)

For further details on see section Floor constructions.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 27
Design and calculation

Determining additional transmission heat-loss to the ground


This additional transmission heat-loss from an underßoor heating system into the soil is especially very low with the
insulation thickness of 8 cm and more (heat conductivity λ = 0.04 W/m x K). It means less than 2 % of the annual
primary energy requirements Qp.

Table 3.3
SpeciÞcation of
Insulating elements Available with Uponor system Height Rλ
Uponor insulation [mm] [(m2  K)/W]
materials
Uponor insulation roll with pipe Uponor clamp track 16, 27 0.75
Þxing foil consisting or Uponor pipe Uponor clamp track 14-20
Þxing foil with polystyrene1)
Uponor pipe Þxing foil 4 0.09
Uponor lightweight panel2) Uponor lightweight panel 25 0.62
1)
Rated thickness 27 mm, compressibility 2 mm, material is expanded polystyrene, thermal conductivity λ = 0.035 Ð 0.040 W/(m  K), internal
insulation under screed with acoustic protection requirement, with low compressibility.
2)
Expanded polystyrene, thermal conductivity λ = 0.030 Ð 0.035 W/(m  K), internal insulation under screed without acoustic protection requirement

The layers of insulation are laid in a lattice pattern and pushed tightly together. The different layers should be laid at
an angle to one another. The joints between the sections of one layer must not coincide with those of the next layer.
Only standardized and/or ofÞcially approved insulation materials should normally be used. The insulation layers must
comply to the standardsÕ laid down by EN 13162 to EN 13171.

Determining the insulation-layer thickness


At the planning stage, the Uponor underßoor heating system offers a wide range of possible variations with respect
to insulation conÞguration. In the design stage it is important to fulÞl the requirement of the min. Rλ, which depends
on the ßoor construction.

Table 3.4 The


following table gives Panel Thermal conductivity
an overview of thickness λ ² 0.025 λ ² 0.030 λ ² 0.035 λ ² 0.040 λ ² 0.045
various insulation
materials, indicating W/(m  K) W/(m  K) W/(m  K) W/(m  K) W/(m  K)
their different mm Rλ (m2  K)/W Rλ (m2  K)/W Rλ (m2  K)/W Rλ (m2  K)/W Rλ (m2  K)/W
thermal resistance
depend on thermal 10 0,4 0,333 0,285 0,25 0,222
conductivity and
thickness.
15 0,6 0,5 0,428 0,375 0,333
20 0,8 0,666 0,571 0,5 0,444
25 1.000 0,833 0,714 0,625 0,555
30 1.200 1.000 0,857 0,75 0,666
35 1.400 1.166 1.000 0,875 0,777
40 1.600 1.333 1.142 1.000 0,888
45 1.800 1.500 1.285 1.125 1.000
50 2.000 1.666 1.428 1.250 1.111
55 2.200 1.833 1.571 1.375 1.222
60 2.400 2.000 1.714 1.500 1.333
65 2.600 2.166 1.857 1.625 1.444
70 2.800 2.333 2.000 1.750 1.555
75 3.000 2.500 2.142 1.875 1.666
80 3.200 2.666 2.285 2.000 1.777
85 3.400 2.833 2.428 2.125 1.888
90 3.600 3.000 2.571 2.250 2.000
95 3.800 3.166 2.714 2.375 2.111
100 4.000 3.333 2.857 2.500 2.222

28 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Constructions adjacent to soil prevented by a PE foil (0.2 mm).


have to be permanently protected Please consult the manufacturersÕ N`\gdib
against moisture penetration into instruction for dry ßooring ele-
ßoors and walls. In case solid ßoors ments.
(e. g. concrete ßoors in new build-
ings) contain residual moisture,
the rising of moisture into the dry
original ßoor structure has to be

The term Òedging stripÓ refers to Uponor edging strip conforms to @_bdib
any point where the screed meets the speciÞcation of EN 1264. The nomdk
the side of an installed structural edging strip is 10 mm thick and
component. A sound-insulation thus conforms to the requirements
edging strip must be applied to all of the leading suppliers of liquid
joins shared with walls and other screed. It consists of PE foam and
vertically-oriented items (such as can be compressed by at least 5
doorways) before the screed is mm. The rear and skirt-side of the
laid. The edging strip, which must strip are both self-adhesive to per-
conform to EN 1264 ÒScreeds in mit easy and simple installation.
building constructionÒ, must be
laid from the load-bearing building
construction to the upper surface
of the Þnish, and must (in case of
heating screed) permit movement
of at least 5 mm.

In case of multi-layer insulation, the


edging strip must be laid before the
Þnal top-layer of insulation mate-
rial. The edging strip must be Þxed
Þrmly to prevent any shifting of
position when the screed is being
laid.

The surplus section of edging strip


and pulled-up covering material
must not be trimmed off prior to
laying the ßoor-covering has been
laid, or (in case of textile and other
elastic coverings) until the Þller has
hardened completely.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 29
Design and calculation

R`dbconjaPkjijmpi_`mÙjjmc`\odibntno`h
Figure 3.14
Weights of Uponor Uponor underßoor heating with clamp track or cable
underßoor heating tie/tying wire, Pipe covering 45 mm cement screed.

Pipe-
Weight including water Þlling of Uponor pipe
covering approx. 132 kg/m2 without top layer.
45 mm

95 mm
20 mm

30 mm

Uponor underßoor heating with pipe positioning


panel, Pipe covering 45 mm cement screed.

Pipe- Weight including water Þlling of Uponor pipe


covering approx. 130 kg/m2 without top layer.
100 mm

45 mm

20 mm
35 mm

Uponor underßoor heating with lightweight panel


and aluminium heat emission plates, Pipe covering
25 mm screed elements.
45 mm

25 mm Weight including water Þlling of Uponor pipe


25 mm
approx. 31 kg/m2 without top layer.

Uponor underßoor heating with lightweight panel


and aluminium heat emission plates, Pipe covering
25 mm 25 mm screed elements.
105 mm

25 mm
55 mm Weight including water Þlling of Uponor pipe
approx. 36 kg/m2 without top layer.

Uponor underßoor heating with lightweight panel


and aluminium heat emission plates, Pipe covering
35 mm liquid anhydrite screed AE 20 or AE 30.

35 mm
60 mm

Weight including water Þlling of Uponor pipe


25 mm
approx. 76 kg/m2 without top layer.

30 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Gjjk^jiØbpm\odji
Uponor pipes can be laid out in The temperature drop in the
any standard way. There are three pipe loops should be kept low,
main types of loop conÞguration for at approximately 5¡C, in order to
underßoor heating. The choice of avoid uneven ßoor temperature.
conÞguration depends on the con-
struction techniques, room shape In order to maintain as uniform as
and practices in different countries. possible the ßoor surface tempera-
In general when pipe layout plans ture, in the case of pipes in series
are being formulated, attention the biÞlar shape is preferred. The
should be paid to Þrst routing the supply is generally close to the
supply ßow to the external walls or external surfaces.
other potentially cold areas.
Note: According to EN 1264-4,
Note: A distance of 5 cm between section 4.2.6.2, stipulates that
the pipe and the wall must be main- Uponor installation must be at least
tained for all types of layout. 50 mm from vertical structural com-
ponents and at least 200 mm from
Note that at this stage also, consid- chimneys, open Þreplaces, open or
eration should be given to ensuring bricked-up shafts, and lift shafts
that the pipes do not run through
the expansion joints (see Figure
3.21 below) incorporated in the slab
design.

The peripheral area, with an area shall be selected, so that the Kdk`ndi
increased surface temperature (up supply differential temperature, cal- k`mdkc`m\g\m`\
to a maximum of 35 ¡C) is generally culated from the lower limit curve,
situated along the outer walls of a is not exceeded by entry of the
room with a maximum width of 1 m. heating medium from the peripheral
Design of peripheral areas is based area into the occupied area.
on a higher limit curve. In case a
series circuit is formed with a heat-
ing circuit in the occupied area, the
temperature drop in the peripheral

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 31
Design and calculation

ConÞguration A is easy to install and Figure 3.15


H`\i_`mdib Meandering layout
g\tjpo#<$ gives a more even distribution of heat with temperature
over the ßoor surface. Temperature distribution across
the room
variations within small areas are kept
to a minimum.The main advantage of
conÞguration A is that it adapts to all
kinds of ßoor structures. It can also
be easily modiÞed for different ener-
gy requirements by altering the pipe
pitch. ConÞguration A is suitable for
most underßoor heating installations
in the home. In view of the relatively
narrow bend radii, the use of a more
ßexible pipe is recommended.

Examples External wall External wall

Lightweight panel layout, just


meandering layout is possible

Meandering layout Meandering layout with periph-


In a meandering (snaking) layout, eral areas
the loops normally run inward from The use of smaller laying intervals
an external wall. This provides the in the peripheral areas produces
highest surface temperature and higher surface temperatures and
thus the greatest heat output, for thus greater heat output from
this area. The water then cools the underßoor heating along the
down as it runs into the room, caus- external wall.
ing the surface temperature and
consequent heat output to drop.

Characteristic for this conÞgura- Figure 3.16


?jp]g`(h`\i_`mdib Double-meandering
g\tjpo#=$ tion is that the supply and return layout with
pipes in the loop layout run paral- temperature
distribution across
lel to each other. ConÞguration B the room
provides an even mean temperature
but higher temperature variation
within small areas. It is suitable for
heating larger areas with a higher
heat demand, such as churches and
hangars.

32 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

This conÞguration is basically a =dØg\mjm^jdg`_


variation of conÞguration B, but is g\tjpo#>$
shaped as a spiral.
ConÞguration C is suitable for
housing with a higher heat demand.
It is less suitable for installation in
wooden ßoor structures.
This conÞguration overcomes the Figure 3.17
rigidity problem encountered in BiÞlar layout with
temperature
some pipes since there are no sharp distribution across
bends. It also allows the pipe to be the room

laid at a small pitch.

Examples
External wall External wall

BiÞlar or coiled layout BiÞlar layout with peripheral


In a biÞlar (coiled) layout, the sup- area
ply and return points lie adjacent to The use of smaller laying intervals
each other. This provides the ßoor in the peripheral areas along exter-
with a relatively consistent surface nal walls produces higher surface
temperature. temperatures and thus greater heat
output in these zones.

Entire room is connected as a loop Separate loops in peripheral and occupied A loop with combined zone layout
zone

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 33
Design and calculation

N^m``_`sk\indjiejdion
Figure 3.18 Joints in the structure and also in surface becomes wider or narrower.
Dividing of a room
to joint areas the insulation layer must be in the These expansion joints which divide
form of screed expansion joints. the screed as far as the insulation
³8m

In order to prevent damage to the layer, are to be based on a 10 mm-


screed and ßoor coverings that thick joint proÞle. The top surfaces
may result from the thermal expan- of the expansion joints between the
sion of the heating screed, screed screed Þelds should be treated with
³8m
sections measuring more than a a suitable sealant.
maximum of 40 m2 are likewise to
be divided with expansion joints. Note: As far as possible, the plac-
Screed surfaces measuring less ing of settlement joints should
than 40 m2 must also be Þtted with
³8m

begin from nooks (e.g. on pilasters


expansion joints if one of their lat- and Þreplaces), i.e. at points where
³8m

eral lengths exceeds 8 m. L-, T- and an expansion or narrowing of the


Z-shaped screed surfaces should screed surface has occurred. Dum-
be divided into areas that are as my or settlement joints are placed
³8m near as possible to being square or in door reveals and passageways.
rectangular.

The length-to-width ratio should


not exceed approx. 1:2. When
deciding on the position of expan-
sion joints re-entering angles
should be used wherever possible,
i.e. in those places where the screed

Figure 3.19
Expansion joint Legend
1 Floor covering
2 Screed
1 3 Gap
4 Pipe conduit
5 Uponor pipe
3 6 Splitting layer
2
7 Building damp
8 Penetration layer
4
5

6
7
8

34 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Dummy shrinking joints more than one third of the screed poured-in plastic resin. The heating
thickness, and care should be taken conduits at the crossover points of
Dummy joints (trowel cuts) can be to avoid damage to underlying expansion and dummy joints must
made in cement-based screed to heating conduits when cutting. be Þtted with a ßexible, 400 mm-
provide further division of screed Once the screed has hardened and long joint protection tube.
surfaces already Þtted with expan- dried out, dummy joints should be
sion joints. They may penetrate no sealed by Þlling with (for example)

Legend
2 1 Floor covering
3
2 Filling
1 3 Moos-gum
4 Screed
10 5 Uponor pipe
4 6 Splitting layer
7 Building damp
9 8 Penetration layer
9 Fine crack
5 10 Shrinking crack

6
7

8 Figure 3.20
Shrinking joint

Design of heating coils layout underßoor heating only, and only


with respect to expansion joints at one level. The heating pipes at
The loops should be arranged in the crossover points of these joints
such a way that the expansion must be Þtted with a ßexible,
and edging joints are cross-beam 400 mm-long joint protection tube.
by the connecting conduits of the

Figure 3.21
wrong right Right position of
expansion joint

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 35
Design and calculation

Gj^\odjijaoc`h\idajg_n
Careful consideration should be giv- tem and improve the temperature robe or a box-room, below a sink or
en to the location of the manifolds control of the individual rooms. recessed in a wall with a cupboard
at the initial stage of the project. They should also be positioned cover. In public buildings a lockable
Manifolds should be located as so that maintenance can be easily steel plate cabinet can be used.
near to the centre of the building carried out thus helping to minimize
as circumstances allow, so that the any water damage during mainte- Control system
length of the pipe running between nance. The aesthetics are a minor
the manifolds and the individual issue since the manifolds should be Uponor offers different control
heating zones is kept to a minimum. concealed, for example within walls. systems suitable for all applications
This will help to balance the sys- Manifolds can be located in a ward- (see Chapter Controls)

>\g^pg\odji]\ndn
Planning principles Components Floor coverings

The requirement for the correct Details of the construction materials Details of the intended type of
project design of an underßoor and components to be used includ- ßoor covering and its levels of
heating is the drawing-up of precise ing thermal insulation measures (U- thermal conduction resistance Rλ,B.
plans containing the correspond- values from relevant standards and If this information is missing, work
ing data. The planning engineer is EnEV calculation method). ConÞgu- should proceed according to
to receive them from the customer, ration of windows, doors, rollerblind EN 1264 for living areas, with a
countersigned whenever possible. housings and skylights, etc. thermal conduction resistance of
Rλ,B = 0.10 (m2 x K)/W, for bath-
Building plans and drawings Fixed ßoor spaces rooms: Rλ,B = 0.00 (m2 x K)/W.
Other values, up to a maximum of
Precise ground plans and cross- IdentiÞcation in ground plan of 0.15 (m2 x K)/W, are to be agreed
sectional drawings, in a scale of ßoor spaces areas, such as Þtted on a case-by-case basis.
1:50 if possible, with details of site kitchens, wall units, tiled stoves or
location, position, etc. The plan- open Þreplaces, etc. along with the The following forms can be used for
ning documents must show all Þxing method and type of plumbing quick and clear entering of basic
dimensions, especially of windows facilities. calculations and data.
and doors, along with details of
intended room use and the desired
inside temperature for each room. If
the latter details are not available,
room temperatures are to conform
to EN 12831.

36 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

General details for calculations


Building owner Date
Place of residence Tel.:
Street
Site address
Street
Planning engineer Tel.:
Heating installation Tel.:

Attached documents: Floor plans, cross-sectional drawings and elevations in 1:100 or 1:50 scale

Determining of room temperatures


Room temperatures as per EN 12831: Yes No

Desired room temperature (¡C) deviating from EN 12831 ÒRules for calculating the heat requirement of buildingsÓ

Room Temperature Screed height in mm Floor covering Type/height in mm


Living room ¡C
Study ¡C
Kitchen ¡C
Shower ¡C
Vestibule ¡C
Bedroom ¡C
Utility room ¡C
Bathroom ¡C
Entrance hall ¡C
ChildrenÕs room ¡C
Storeroom ¡C
WC ¡C
Hall ¡C
¡C
¡C
¡C

Building type: Terraced house Detached house Exposed to strong winds


Basement ßoor: Heated* Unheated* Not exposed to strong winds
Attic ßoor: Heated* Unheated*
* Please indicate in building plan

Place, Date CustomerÕs signature

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 37
Design and calculation

Building-material details for calculating heat requirements

2 1
3
SH
4
5
6
7
9 8 SH

10
1 11
12 SH

13 14

Building-material details for calculating heat requirements

No. Building component U-value W/(m2 x K) Material Details


1 Ceiling
2 Skylight
3 Roof pitch
4 Gable
5 Jamb wall
6 Outer jamb wall
7 Ceiling neighbouring onto attic
ßoor (or ßat roof)
8 Internal wall
9 Window
10 External wall
11 Basement ceiling
12 Basement window
13 External basement wall
14 Basement ßoor
15
16

Storey-height SH:_m

Place, Date CustomerÕs signature

38 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

>\g^pg\odji^mdo`md\
A room operative temperature of Available standard pipe spacing
20 ¡C (bathrooms 24 ¡C) according to system between
A heat requirement is estimated 120-300 mm (in some cases also
based on local standards and between 100-400 mm)
climatic conditions Pipe loops consisting of pePEX,
A heat requirement for the evalPEX and MLC pipes (various
house <100 W/m2, excluding dimensions)
downward heat loss (to limit the pePEX, evalPEX and MLC pipes
ßoor temperature to 29 ¡C) as supply pipes.
A temperature drop across the
pipe loop of approx. 5-10 ¡C
Three loop conÞgurations of
type A, B and C (section Loop
conÞguration)

Km\^od^\g^\g^pg\odjidnnp`n
A complete underßoor heating The location of the manifolds
installation design includes: should be given Þrst priority, (see
previous section). Manifolds can be
SpeciÞcation of the material located in a wardrobe or a box-
required room, below a sink or recessed in
A pipe layout drawing a wall with a cupboard cover. In
Technical information regarding public buildings a lockable steel
pressure drop, water tempera- plate cabinet can be used. The
ture and settings for balancing principle is to assign one pipe loop
the pipe loops. to each room. Larger rooms might
require 2 or more loops. In normal-
The design can be done manually size houses manifolds can serve 6-8
according to equation provided in loops (max. 10-12).
relevant standards. The design can be
accomplished by means of software With regard to the ßoor structure,
HSE. The Þrst step before beginning applicable national regulations
on the design and calculations is to and standards regarding drain-
check that all necessary information age, vapour barriers etc. must be
is at hand. There should be: observed. In houses built on a
concrete slab the insulation should
A legible, simpliÞed plan of the be increased by 80 mm in order to
building, indicating the scale. reduce the downward heat loss. The
Details of the heat demand in thickness of the insulation must be
(W/m2). homogeneous over the whole area.
An indication as to where the Suspended ßoor structures should
boiler is placed in the building also be insulated (for further details
and of the location of risers or see section Floor constructions
branches within the construction. - Insulation requirements). In all
Practical items such as a measur- cases instructions supplied by the
ing wheel, a device to measure manufacturer of the ßoor covering
distances in drawings, and a material should be followed.
template to draw the pipe loops.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 39
Design and calculation

>\g^pg\odjijac`\odib^\k\^dot\^^jm_dib
 oj@I,-1/\i_@I,0.22(,
Limitations of ßoor surface temperature and heat- The relationship between heat ßow density and mean
ing capacity differential surface temperature so called characteristic
curve (see also Calculation diagrams and three Equa-
Maximum ßoor surface temperature is based on the tions below) depends on the type of heat emitting
physiological reasons limited and consequently also surface (ßoor, wall, ceiling) and if the temperature of
limits the maximum heating capacity from the surface: the surface is lower (cooling) or higher (heating) than
the space temperature. Heat exchange coefÞcient is the
occupied zone θF,max = 29 ¡C parameter that affects the amount of heat transferred
peripheral zone θF,max = 35 ¡C between surface and the space related depends on the
bathrooms θF,max = θi + 9 ¡C = 24 ¡C + 9 ¡C = 33 ¡C position of the surface and the surface temperature in
relation to the room temperature (heating or cooling).
Due to a limited surface temperature, is needed in some
cases the additional heat emitter.

300
Figure 3.22 Floor Heating q = 8,92 (θi Ð θF,m)1,1
Basic characteristic
curve for ßoor 200
heating θi Nominal indoor operative temperature
θF,m Average surface temperature
Heat ßow density q (W/m2)

100
For other types of situations the following equations
should be used:
50 Wall heating: q = 8 (| θi Ð θF,m |)
40 Ceiling Heating: q = 6 (| θi Ð θF,m |)
30

20

10
1 2 3 4 5 10 20 30

Mean differential surface temperature (θF,m - θi) in K

Table 3.5
Total heat exchange
Total heat exchange Acceptable surface Maximum capacity
coefÞcient (combined coefÞcient [W/mK] temperature [¡C] [W/m]
convection + radiation)
between surface and Heating Maximum Heating Heating
space for heating and Floor occupied zone 11 29 99
cooling, acceptable
surface temperatures Floor perimeter zone 11 35 165
and capacity by 20¡C Wall 8 ~ 401) 160
room temperature for
heating and 26¡C Ceiling 6 ~ 272) 42
room temperature for
cooling (EN 15377-1).
1)
The risk of hand burning at the temperature of 42 ¡C should be avoided. In the spaces with for more sensitive persons like children or elderly and
where the occupants may easily get contact with the surface 35 ¡C should not be exceeded.
2)
The radiant asymmetry should be lower than 5 K (EN ISO 7730).

40 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Note to estimated heating The heat ßow density is propor- The design supplement is x = 0
capacity tional to ΔθH: whenever an increase in heating
capacity can be brought about by
It must be mentioned here that q = KH . ΔθH raising the temperature of the heat-
the system capacity is always ing medium. This applies in case
restricted in a manner to not exceed Where the heating medium differ- of the Uponor underßoor heating
the hygienic and comfort criteria ential temperature (ΔθH) is: system. A short-term peak in excess
for surface temperature listed in of the maximum allowable surface
relevant standards (see Table 3.5). temperature is possible. Calculated
RV  R R
For instance the maximum allowed %R H  heat demand QH should thus be
R Ri
heating ßoor surface temperature ln V equated with the corrected heat
in occupied zone is deÞned 29 ¡C. RR Ri demand estimate QBer in case of
In the room with room temperature and KH is the equivalent heat underßoor heating.
of 20¡C (winter) is the capacity transmission coefÞcient between
limited to 100 W/m. In peripheral the temperature of heating medium The heat gain from through-going
area with surface temperature of and room temperature determined connection conduits can be deduct-
allowed to swing up to 35 ¡C the by one of the following depending ed if equal usage applies. In case of
system could achieve the capacities on the type of system: certain rooms (e.g. entrance halls),
of 165 W/m. In case if the room m where the manifold is located, the
K H  B – ” ( ai i )
temperature would increase to 22 ¡C i entire system heating capacity can
the maximum allowed surface tem- in accordance with EN 1264-2 valid be covered by connecting conduits.
perature would limit the capacity for underßoor heating system; In certain cases, the upper faces
to approximately 77 W/m and by of connecting conduits must be
K H  1 / R HC R i
19 ¡C to approximately 140 W/m. covered with insulation material to
The room temperature of 26 ¡C is in accordance with EN 15377-1 prevent the maximum surface tem-
assumed for summer. In any case valid for heating system with a heat perature from being exceeded.
during the summer; the tempera- emission plate in wooden ßoor.
ture difference between room and Back-side thermal insulation
outside temperature should not In the case of the use of Uponor
exceed 8 K. underßoor heating systems in a In order to limit the heat ßow
special manner of application and towards the outside (not exceed
Heat emission from underßoor special ßoor construction; the KH 10 % of total heat ßow) or to
heating may also be determined by Finite adjacent spaces, a minimum ther-
Element Method or Finite Differ- mal resistance of the insulating
The heat ßow density q at a surface ence Method calculations according layer, Rλ,ins, shall be speciÞed in
is determined and inßuenced by the to EN 15377-1. the design. EnEV and EN 1264-4
following parameters: establish certain requirements for
Pipe spacing T In case of multi-storey buildings the minimum thermal conduction
Thickness su and thermal con- with underßoor heating, heat gain resistance of the insulating layer
ductivity λE of the layer inward from the rooms located above can Rλ,ins or ceilings Rλ,ceiling in order to
of the pipe (screed). only be taken into account if unlim- limit the downward ßow of heat
Thermal conduction resistance ited operation is in force. through the ceiling. Please refer
Rλ,B of surface covering. also to the planning instructions in
Pipe external diameter D = da, System heating capacity QH is section Thermal insulation require-
and the thermal conductivity of obtained from the corrected heat- ments.
the pipe λR demand estimate QBer multiplied by
Heat conducting devices, char- design supplement x determined by All types of application can be cov-
acterised by the value KWL in DIN 4701-3. ered using Uponor system compo-
accordance with EN 15377-1, A 3 nents insulation roll with pipe Þxing
QH  (1 x) s Q Ber
Contact between the pipes and foil, or suitable additional insulation
the heat conducting devices or locally supplied (See also Types of
screed, characterised by the fac- Screeded and dry ßoors). It is also
tor aK. possible to construct the ßoor by
using pipe positioning panels or
pipe Þxing foil and standard insula-
tion.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 41
Design and calculation

For underßoor heating systems with Note: The capacity diagrams show When carrying out the calculation,
clamp track, cable tie, pipe position- the output value for various room it is assumed that a uniform level
ing panel and lightweight panel, temperatures, along with average of thermal conduction resistance
the back-side thermal resistance is heating medium excess temperature applies to the ßoor coverings in all
calculated by following equation, for different types of ßoor covering. the rooms to be heated. For living
where sins means effective thickness With the help of these tables, it is areas has a uniform value of RλB =
and λins thermal conductivity of the also possible to quickly ascertain 0.10 (m2 K)/W. In case of bath-
insulation: the average heating medium excess rooms, the value is RλB = 0.00
sins temperature at which the underßoor (m2 K)/W. The temperature differ-
R M ,ins  heating should be operated, in order ence σ between supply and return
Mins
to obtain a speciÞc output. The heat may come to a maximum of 5 K
The effective thickness of the densities are distributed, proportion- (3 K in peripheral areas) on applica-
insulating layer, sins, depends on ally to surface, across the peripheral tion of the limit heat density, other-
the construction of the underßoor and living areas. wise wider differences are permitted.
heating. For Uponor system with
ßat thermal insulating panels, the See also section Floor construction System heating medium ßow
effective thickness is identical to the and Insulation requirements. rate
physical thickness of the thermal
insulating panel. For the system with Design heat ßow density When determining the heating
proÞled thermal insulating panels medium ßow rate for a room, both
(lightweight panel), a surface-related Design heat density qs,des in W/m2 is the desired upward heat densities
weighted calculation is made for calculated according to EN 1264: and downward heat loss should be
determining the effective thick- QF taken into account. Downward heat
qs , des =
ness of the insulating layer, where AF density qu is independent of the
sh means distance from founding to The heat output of the underßoor temperature difference between the
heat emission plate and sI distance heating system totals: rooms in question, while depend-
from founding to lowest part of the ing on the thermal conduction and
Q F = q x AF
pipe surface. contact resistance of the individual
The heat transfer of the entire layers of the ßoor structure.
s h – (T  D ) s I – D surface Þtted with heating proÞles,
sins 
T QF, is proportional to the length of The design medium ßow rate mH of
The standard recommended values pipe laid: a surface heating circuit is calculated
from thermal insulations are given in QF = q x T x L R as follows:
Table 3.2, depending on the thermal
conditions under the ßoor structure. Whereby q is distributed proportion-
ally to area across peripheral zone AR
Note: The factor that most inßu- (max. 1 m wide) and living area AA: Note: When using this numeri-
ences the performance of an under- AR A cal value, q in W/m2 is used in this
ßoor heating system is the operating q= x qR + A x q A equation; mH is then produced in
AF AF
water temperature. The supply kg/s.
temperature of the heating water is Required length of the heating
normally the same for the various circuit: The required length of the For further details see standard EN
rooms served by the system. The heating or cooling circuit, with no 15377-2.
selection of suitable heating-pipe particular consideration given to the
laying intervals and adjustment of pipe bends, is estimated by: The mass ßow rate mH is expressed
the ßow rate can be used to adapt A to by conversion to volume ßow rate
LR = F
the level of heat output for each T VH in m3/h.
room. This produces different return mH
temperatures for each loop. An Design supply water temperature VH =
r
average can be taken for the heating
medium excess temperature in the The design supply temperature is The density ρ of the water totals
event of a small difference between determined as per EN 1264 for the 0.998 kg/dm3 or 0.998 kg/l.
supply and return in order to simplify room with the highest design heat
the calculation. density qmax (bathrooms excepted).

42 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Km`nnpm`gjnn
The calculation of the lift of a cir- The pressure loss in the Uponor Estimation of the manifold set-
culation pump depends on the loop manifold ÆpVert is obtained from the tings for balancing of loops
with the largest amount of pressure technical diagram and include this
loss. The pressure loss in the pipe to the calculation. Two manifolds are available:
and the pressure loss in the mani- Uponor modular plastic manifold
%pHK  R s L HK %pVert
fold with feed valve and top-meter with balancing screw
give the pressure loss of the loop. Given that individual loops possess Uponor modular plastic manifold
different lengths and spread vari- with ßow meter
The total pressure drop can be ations, they bring about different
obtained by adding the pressure pressure drops. A pressure com- An installation with different
drop across: pensating procedure must be used pipe loop lengths and water ßow
1. The underßoor heating pipe to ensure that all loops are also requirements will have different
loop(s) supplied with the desired amounts pressure drops for the different
2. The manifold(s); including shut of water. This pressure compensa- loops. In order to achieve an even
off valves and the mixer tion is carried out at the manifold heat distribution between the
3. The supply and return pipes arrangement, by adjustment of the rooms at the installation stage the
4. The boiler, valves etc. ßow-rate per minute. pressure drop in the different loops
must be calculated, the setting of
In order to able to calculate pres- Limit values each balancing valve must be esti-
sure loss, the total pipe length The maximum supply tempera- mated by using a table or diagram
of the loop LHK (m) must Þrst be ture must not exceed 55 ¡C. provided by Uponor and later on
determined, including the supply Total pressure loss for all com- during installation balanced.
and return pipe from the manifold ponents forming part of the
to the loop. circulation pump system must In the Uponor underßoor heating
not exceed 300 mbar. system this can be done by means
Using the pressure loss diagram for of the lockshield valves in the
PE-Xa and MLC pipe and the vol- The water capacity of the entire return manifold. For further infor-
ume ßow rate per loop VHK (l/h) it system determines the conÞgura- mation on the manifold installation
is possible to calculate the pressure tion of the expansion tank. and valve setting see balancing of
loss due to pipe friction R (Pa/m). the manifold in the section instal-
In order to determine overall loop Manifold and manifold cabinets lation.
pressure loss, this value is multiplied
by the total number of loops. Uponor produces and offers mani- See pressure loss diagram for set-
folds and cabinets suitable for all ting the lockshield valves in this
underßoor heating applications and chapter.
Uponor systems

@sk\indjiqjgph`n
In underßoor heating systems, the spacing the water volume in 1 m of Note: The water volume per meter
demands on expansion vessels do pipe (Vpipe) will be approx. 0.2 l/m length for all other Uponor pipes
not differ from other systems. The and total pipe length (L) will be should be calculated.
water volume in the Uponor under- 6.67 m/m2. The water volume per
ßoor heating system can be calcu- m2 according to the above Þgures
lated as follows: will be approx. 1.3 l/m2. The water
volume in supply pipes and boiler
V = Vpipe x L must be included when selecting
the expansion vessel. The expansion
Example: For Uponor pePEX coefÞcient of water is 1.8 x 10-4/K
20 x 2.0 mm with 150 mm pipe at 20 ¡C.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 43
Design and calculation

>\g^pg\odji_d\bm\hn\i_o\]g`n
The use of calculation diagram Floor surface differential Thermal resistance of various
temperature ßoor coverings
The diagrams provide a complex
overview on the inßuence of The physiological limit for maxi- Carpet ca. 0,10 - 0,15 m2K/W
following parameters and joint mum ßoor surface temperature Parquet ca. 0,04 - 0,11 m2K/W
interaction: must be taken into account. The PVC ca. 0,025 m2K/W
amount of heating capacity on the Tiles, marble ca. 0,01 - 0,02 m2K/W
1. Heat ßow density at the ßoor ßoor surface is calculated by con-
q in [W/m2] sidering the difference between
2. Thermal resistance of surface mean ßoor surface temperature and
covering Rλ,B in [m2K/W] indoor temperature in relation to
3. Pipe spacing T in [cm] the basic characteristic curve of the
4. Heating medium differential UFH system. Maximum ßoor sur-
temperature ΔθH = θH Ð θi in [K] face temperature corresponds to
5. Limit heat ßow density following the limit heat ßow density which is
limit curve determined according to EN 1264.
6. Floor surface differential tem- This limit is shown in the calcula-
perature θF,m Ð θi in [K] tion diagram as a theoretical calcu-
lation limit.
Calculation heating capacity of
Uponor UFH included in diagrams is Max. surface temperatures
carried out in accordance with Euro- according to EN 1264:
pean Standards for embedded water 29 ¡C in the occupied zone
based surface heating systems. 35 ¡C in the peripheral zone
Calculation approach can be adapt- 33 ¡C in bathrooms
ed (adjusted) locally according to
national codes and standards. Heating medium differential
temperature
Three input parameters are sufÞ-
cient estimating all the remaining Heating medium differential tem-
UFH system parameters by using perature ΔθH is calculated as a
just one diagram. A quick estimation logarithmic average of supply,
of heat ßow density for the UFH return and standard indoor opera-
system with various ßoor coverings tive temperature in accordance with
and heating medium differential EN 1264.
temperatures is provided as well.
According to EN 1264 Part 3:

44 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Calculation diagram for Uponor clamp track 14 Ð 20, cable tie or tying wire with 14 x 2 PE-Xa pipe and
cement screed

(su = 45 mm with λu = 1,2 W/mK, various pipe spacing (T) and heating medium differential temperature (ΔθH))
180
15
Limit curve
peripheral zone T 2) K

K
10 25

K
40

K
35

30
14
160

13

140
Floor surface differential temperature (θF,m Ð θi) in [K]

12 K
20

11
120
Heat ßow density q in [W/m2]

10

100 Limit curve occupied zone T 101) K


9 15
T 15
8 T 20

80
7 T 30

6
10 K
60

4 40

K
3 - θi = 5
Δθ H = θ H

2 20

0 0

0
T1
5 T 10
30

T2
Thermal resistance of surface

T
covering Rλ,B [m2 K/W]

0,05

T qúN ΔθH
0,10
cm W/m2 K
10 98 15,4
15 95 17,5
20 91 19,4
30 78 22,0

0,15

1)
Limit curve is valid for θi 20 ¡C Note: According to EN 1264 the perature cannot be assumed higher
and θF, max 29 ¡C as well as for θi bathrooms, showers, WC etc. should as following:
24 ¡C and θF, max 33 ¡C be excluded from this estimation of θV, des = ΔθH, g + θi + 2,5 K.
2)
Limit curve is valid for θi 20 ¡C design supply water temperature. ΔθH, g will from limit curve accord-
and θF, max 35¡C The limit curves cannot be exceed- ingly result in smaller pipe spacing
ed. The design supply water tem- in the occupied zone.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 45
Design and calculation

Calculation diagram for Uponor clamp track 16, clamp track 14-20, cable tie or tying wire with 16 x 2 mm
MLC pipe and cement screed

(su = 45 mm with λu = 1,2 W/mK, various pipe spacing (T) and heating medium differential temperature (ΔθH))
180
15
Limit curve
peripheral zone T 2)
10 K

K
25

K
40

35
14

30
160

13

140
Floor surface differential temperature (θF,m Ð θi) in [K]

12
K
20
11
120
Heat ßow density q in [W/m2]

10

9 100 Limit curve occupied zone T 101) K


15
T 15
T 20
8

80
7 T 30

6 10 K
60

4 40

K
3 - θi = 5
Δθ H = θ H

2 20

0 0

T2
0
T1
5 T 10
30
Thermal resistance of surface

T
covering Rλ,B [m2 K/W]

0,05

0,10 T qúN ΔθH


cm W/m2 K
10 98 15,2
15 95 17,1
20 91 18,9
30 77 21,3
0,15

1)
Limit curve is valid for θi 20 ¡C Note: According to EN 1264 the perature cannot be assumed higher
and θF, max 29 ¡C as well as for θi bathrooms, showers, WC etc. should as following:
24 ¡C and θF, max 33 ¡C be excluded from this estimation of θV, des = ΔθH, g + θi + 2,5 K.
2)
Limit curve is valid for θi 20 ¡C design supply water temperature. ΔθH, g will from limit curve accord-
and θF, max 35¡C The limit curves cannot be exceed- ingly result in smaller pipe spacing
ed. The design supply water tem- in the occupied zone.

46 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Calculation diagram for Uponor clamp track 14-20, cable tie or tying wire with 17 x 2 mm PE-Xa pipe and
cement screed

(su = 45 mm with λu = 1,2 W/mK, various pipe spacing (T) and heating medium differential temperature (ΔθH))
180
15
Limit curve
peripheral zone T 2)
10 K

K
25

K
40

35
14

30
160

13

140
Floor surface differential temperature (θF,m Ð θi) in [K]

12
K
20
11
120
Heat ßow density q in [W/m2]

10

9 100 Limit curve occupied zone T 101) K


15
T 15
8 T 20

80
7 T 30

6 10 K
60

4 40

K
3 - θi = 5
Δθ H = θ H

2 20

0 0

0
T2 T1
5 T 10
30
Thermal resistance of surface

T
covering Rλ,B [m2 K/W]

0,05

T qúN ΔθH
0,10 cm W/m2 K
10 98 15,1
15 95 16,9
20 90 18,6
30 78 21,4

0,15

1)
Limit curve is valid for θi 20 ¡C Note: According to EN 1264 the perature cannot be assumed higher
and θF, max 29 ¡C as well as for θi bathrooms, showers, WC etc. should as following:
24 ¡C and θF, max 33 ¡C be excluded from this estimation of θV, des = ΔθH, g + θi + 2,5 K.
2)
Limit curve is valid for θi 20 ¡C design supply water temperature. ΔθH, g will from limit curve accord-
and θF, max 35¡C The limit curves cannot be exceed- ingly result in smaller pipe spacing
ed. The design supply water tem- in the occupied zone.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 47
Design and calculation

Calculation diagram for Uponor clamp track 14-20, cable tie or tying wire with 18 x 2 mm MLCP and
cement screed

(su = 45 mm with λu = 1,2 W/mK, various pipe spacing (T) and heating medium differential temperature (ΔθH))
180
15
Limit curve
peripheral zone T 2)
10 K

K
25

K
40

35
14

30
160

13

140
Floor surface differential temperature (θF,m Ð θi) in [K]

12
K
20
11
120
Heat ßow density q in [W/m2]

10

9 100 Limit curve occupied zone T 101) K


15
T 15
8 T 20

80
7 T 30

6 10 K
60

4 40

K
3 - θi = 5
Δθ H = θ H

2 20

0 0

0
T2 T1
5 T 10
30
Thermal resistance of surface

T
covering Rλ,B [m2 K/W]

0,05

T qúN ΔθH
0,10 cm W/m2 K
10 98 15,0
15 95 16,7
20 90 18,4
30 76 20,6

0,15

1)
Limit curve is valid for θi 20 ¡C Note: According to EN 1264 the perature cannot be assumed higher
and θF, max 29 ¡C as well as for θi bathrooms, showers, WC etc. should as following:
24 ¡C and θF, max 33 ¡C be excluded from this estimation of θV, des = ΔθH, g + θi + 2,5 K.
2)
Limit curve is valid for θi 20 ¡C design supply water temperature. ΔθH, g will from limit curve accord-
and θF, max 35¡C The limit curves cannot be exceed- ingly result in smaller pipe spacing
ed. The design supply water tem- in the occupied zone.

48 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Calculation diagram for Uponor clamp track 14-20, cable tie or tying wire with 20 x 2 mm PE-Xa pipe and
cement screed

(su = 45 mm with λu = 1,20 W/mK, various pipe spacing (T) and heating medium differential temperature (ΔθH))

180
15 Limit curve peripheral zone T 10 2)

K
K

K
35
40
14

30
160
K
25
13

140
Floor surface differential temperature (θF,m Ð θi) in [K]

12

11 K
120 20
Heat ßow density q in [W/m2]

10

Limit curve occupied zone T 101)


9 100

T 15 K
T 20 15
8

80
7 T 30

6
60 T4 10 K
0
5

4 40

3 K
- θi = 5
Δθ H = θ H
2 20

0 0

30 5 T 10
0

0 T1
T2
T4
Thermal resistance of surface

T
covering Rλ,B [m2 K/W]

0,05

T qúN ΔθH
0,10 cm W/m2 K
10 98 14,9
15 94 16,6
20 90 18,3
30 76 19,8
40 56 20,4
0,15

1)
Limit curve is valid for θi 20 ¡C Note: According to EN 1264 the perature cannot be assumed higher
and θF, max 29 ¡C as well as for θi bathrooms, showers, WC etc. should as following:
24 ¡C and θF, max 33 ¡C be excluded from this estimation of θV, des = ΔθH, g + θi + 2,5 K.
2)
Limit curve is valid for θi 20 ¡C design supply water temperature. ΔθH, g will from limit curve accord-
and θF, max 35¡C The limit curves cannot be exceed- ingly result in smaller pipe spacing
ed. The design supply water tem- in the occupied zone.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 49
Design and calculation

Calculation diagram for Uponor pipe positioning panel with 14 x 2 mm PE-Xa pipe and cement screed

(su = 45 mm with λu = 1,2 W/mK, various pipe spacing (T) and heating medium differential temperature (ΔθH))

180
15
Limit curv
peripheralezo
ne T 122)

K
K

40
14 25

K
160

35

30
13

140
Floor surface differential temperature (θF,m Ð θi) in [K]

12
K
20
11
120
Heat ßow density q in [W/m2]

10

9 100 Limit curve occupied zone T 121)


K
15
T 18
8
T 24
80 T 30
7

6 10 K
60

4 40

3 K
- θi = 5
Δθ H = θ H
2 20

0 0

30 4 T1
8
T T2 T 12
Thermal resistance of surface
covering Rλ,B [m2 K/W]

0,05

0,10 T qúN ΔθH


cm W/m2 K
12 97 16,3
18 93 18,7
24 86 20,7
30 81 23,1
0,15

1)
Limit curve is valid for θi 20 ¡C Note: According to EN 1264 the perature cannot be assumed higher
and θF, max 29 ¡C as well as for θi bathrooms, showers, WC etc. should as following:
24 ¡C and θF, max 33 ¡C be excluded from this estimation of θV, des = ΔθH, g + θi + 2,5 K.
2)
Limit curve is valid for θi 20 ¡C design supply water temperature. ΔθH, g will from limit curve accord-
and θF, max 35¡C The limit curves cannot be exceed- ingly result in smaller pipe spacing
ed. The design supply water tem- in the occupied zone.

50 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Calculation diagram for Uponor pipe positioning panel with 16 x 2 mm MLC pipe and cement screed

(su = 45 mm with λu = 1,2 W/mK, various pipe spacing (T) and heating medium differential temperature (ΔθH))

180
15
Limit curve
peripheral zo
ne T 122)

K
K

K
14 25

40

35

30
160

13
Floor surface differential temperature (θF,m Ð θi) in [K]

140
12
K
20
11
Heat ßow density q in [W/m2]

120

10

9 100 Limit curve occupied zone T 121)


K
15
T 18
8
T 24
80 T 30
7

6 10 K
60

4 40

3 K
- θi = 5
Δθ H = θ H
2 20

0 0

30 4
T1
8 T 12
T T2
Thermal resistance of surface
covering Rλ,B [m2 K/W]

0,05

T qúN ΔθH
0,10
cm W/m2 K
12 96 15,7
18 92 17,9
24 85 19,5
30 80 21,6

0,15

1)
Limit curve is valid for θi 20 ¡C Note: According to EN 1264 the perature cannot be assumed higher
and θF, max 29 ¡C as well as for θi bathrooms, showers, WC etc. should as following:
24 ¡C and θF, max 33 ¡C be excluded from this estimation of θV, des = ΔθH, g + θi + 2,5 K.
2)
Limit curve is valid for θi 20 ¡C design supply water temperature. ΔθH, g will from limit curve accord-
and θF, max 35¡C The limit curves cannot be exceed- ingly result in smaller pipe spacing
ed. The design supply water tem- in the occupied zone.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 51
Design and calculation

Calculation diagram for Uponor lightweight panel with 14 x 2 mm PE-Xa pipe and dry screed boards

(su = 25 mm with λu = 0,28 W/mK, various pipe spacing (T) and heating medium differential temperature (ΔθH))

180
15

K
K

30
40

35
14
160 Limit curve
peripheral zo
ne T 15 2)
13 K
25
Floor surface differential temperature (θF,m Ð θi) in [K]

140
12

11
120
Heat ßow density q in [W/m2]

K
20
10

9 100
Limit curve occupied zone T 151)
8 K
15
T 22,5
80
7
T 30

6
60
10 K
5

4 40

3
K
- θi = 5
Δθ H = θ H
2 20

0 0
0
Thermal resistance of surface

,5

15
T3

22

T
T
covering Rλ,B [m2 K/W]

0,05

0,10 T qúN ΔθH


cm W/m2 K
15 90,8 21,7
22,5 81,1 25,0
30 70,1 30,9

0,15

1)
Limit curve is valid for θi 20 ¡C Note: According to EN 1264 the as following:
and θF, max 29 ¡C as well as for bathrooms, showers, WC etc. should θV, des = ΔθH, g + θi + 2,5 K.
θi 24 ¡C and θF, max 33 ¡C be excluded from this estimation of ΔθH, g will from limit curve accord-
2)
Limit curve is valid for θi 20 ¡C design supply water temperature. ingly result in smaller pipe spacing
and θF, max 35 ¡C The limit curves cannot be exceed- in the occupied zone. Max. tem-
ed. The design supply water tem- perature load should respect the dry
perature cannot be assumed higher screeding plates.

52 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Calculation diagram for Uponor heat emission plate with 20 x 2 mm PE-Xa pipe and wooden joist ßoor

(su = 25 mm with λu = 0.13 W/mK, pipe spacing 300 mm (T) and heating medium differential temperature (ΔθH))

90

K
K

30
40

35
80

K
25
70

60
Heat ßow density q in [W/m2]

K
20

50

K
15
40

30
10 K

20

K
- θi = 5
Δθ H = θ H
10

0
0
Thermal resistance of surface

T3
covering Rλ,B [m2 K/W]

0,05

0,10

0,15

Note: This diagram is valid just for For a room with 20¡C design
one typical case with wooden ßoor internal temperature and 5 K water
boards of 25 mm over the pipes. In temperature drop, the maximum
normal case the RλB = 0.0 m2 K/W. corresponding heating capacity will
Maximum permissible water tem- be limited to approx. 60 W/m2.
perature in pipes embedded into
the wooded construction is 55 ¡C.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 53
Design and calculation

Calculation diagram for Uponor high performance panel with 9.9 x 1.1 mm PE-Xa and 15 mm screed

180
15
K K

K
30 25

35
14 Limit curve peripheral zone T 52)
160

K
13
Vz
T 100 20
Floor surface differential temperature (θF,m Ð θi) in [K]

140
12

11
120
Heat ßow density q in [W/m2]

10 K
15
9 100 Grenzkurve
Limit curveAufenthalt
occupiedszone T 552)1)
zoneVz

8 Vz
T 10
10
80
7 Vz
10 K
T 15
15

6
60

4 40
K
Ð Ri = 5
%RH = RH
3

2 20

0 0
5 0
T1 T1 T5
Thermal resistance of surface
covering Rλ,B [m2 K/W]

0,05

T qú N %RN
cm W/m2 K
0,10 5 94,4 11,59
10 82,6 12,33
15 71,8 12,91

0,15

1)
Limit curve is valid for θi 20 ¡C Note: According to EN 1264 the as following:
and θF, max 29 ¡C as well as for bathrooms, showers, WC etc. should θV, des = ΔθH, g + θi + 2,5 K.
θi 24 ¡C and θF, max 33 ¡C be excluded from this estimation of ΔθH, g will from limit curve accord-
2)
Limit curve is valid for θi 20 ¡C design supply water temperature. ingly result in smaller pipe spacing
and θF, max 35 ¡C The limit curves cannot be exceed- in the occupied zone. Max. tem-
ed. The design supply water tem- perature load should respect the dry
perature cannot be assumed higher screeding plates.

54 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

Pressure loss diagram for Uponor MLC pipe

1000
18 x 2
800 0,2 m/s 0,3 m/s 0,4 m/s 0,5 m/s 0,6 m/s 0,7 m/s

600 16 x 2
500
400

300
Mass flow m in [kg/h]

200

100
80

60
50
40

30

20

10
0,1 0,2 0,3 0,5 1 2 3 4 5 10 20 30
0,01 0,02 0,03 0,05 0,1 0,2 0,3 0,4 0,5 1 2 3
[mbar/m]
Pressure loss R [kPa/m]

Pressure loss diagram for Uponor PE-Xa pipes

400

300

200 mm
x2
20
Mass flow m in [kg/h]

0,6

mm
0,5

x2
m/

17
s
m/

100
0,4

m
m/

80
2m
0,3

x
14
m/

60
s

50
0,2
m/

40
0,1

s
5m

30
/s
0,1
m/

20
s

Medium: water
10
0,1 0,2 0,3 0,5 1 2 3 4 5 6 7 8 9
0,01 0,02 0,03 0,05 0,1 0,2 0,3 0,4 0,5
[mbar/m]
Pressure loss R [kPa/m]

Note:
Recommended maximum pressure loss of 250 mbar (25 kPa) per loop should not be exceeded.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 55
Design and calculation

Pressure loss 400


diagram for PE-Xa 300
pipe
200

0,7
100

0,6

m/
80

0,5

m/

s
s
m/
0,4
60
mm

s
m/
50
,1
Mass flow in [kg/h]

0,3

s
40
9, 9x

m/
s
0,2
30

m/
0,1

s
20 5m
/s
0,
1
m/

Medium: Water
s

10
0,1 0,2 0,3 0,5 1 2 3 4 5 6 7 8 9 [mbar/m]
0,01 0,02 0,03 0,05 0,1 0,2 0,3 0,4 0,5
[kPa/m]
Pressure loss R

Pressure loss
diagram for Uponor
plastic manifold
connection valve

500 50
Uponor plastic manifold connection
400 40
valve set will be used for hydronic
300 30


balancing and/or shut out of




200 20 supply/return of the Uponor


manifold. Can be used for zone


temperature control. Diagrams show





100 10
the valve setting.

8
$ 

80

60 6

50 5

40 4

30 3
 "

20 2
 

" !
10 1
100 200 300 500 1000 2000 3000

 #

Pressure loss for


Uponor plastic
manifolds - setting
of the lockshield
valves
Pressure loss (kPa)

56 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Design and calculation

>\g^pg\odjinkm`\_nc``on
Clamp tracks

Laying of 16 - 18 mm MLC pipes and 14 Ð 20 mm PE-Xa pipes with Uponor pipe Þxing foil material with and without insu-
lation, pipes Þxed with Uponor clamp track
Spacing (cm) Pipe length Edging strip (m) Pipe Þxing foil with/without Tape (m) Clamp track (m)
(m/m2) insulation (m2)
10 10 1 1 1 1
15 6.7 1 1 1 1
20 5 1 1 1 1
25 4 1 1 1 1
30 3.4 1 1 1 1
If cement-based screed is used instead of its anhydrite equivalent, add a further 0.16 kg of screed additive per m of underßoor heat-
ing surface. When using screed additive for minor pipe coverage add a further 1.3 kg/m screed additive.

Pipe positioning panel

Laying of 16 mm MLC pipes and 14 mm PE-Xa pipes with Uponor pipe positioning panel
Spacing (cm) Pipe length (m/m2) Edging strip (m) Pipe panel type 1 (m2) Fastening nail (pcs)
6 16.7 1 1.15 1
12 8.4 1 1.15 1
18 5.6 1 1.15 1
24 4.2 1 1.15 1
30 3.4 1 1.15 1
If cement-based screed is used instead of its anhydrite equivalent, add a further 0.16 kg of screed additive per m of underßoor heating
surface. When using screed additive for minor pipe coverage add a further 1.3 kg/m screed additive. The required quantity of polyethylene
foil should be determined onsite, as individual room geometry makes it impossible to carry out an advance estimate.

Lightweight panel

Meandering laying of 14 mm PE-Xa pipe with Uponor lightweight panel


Spacing Pipe length Edging strip Lightweight panel Heat emission plate
(cm) (m/m2) (m) (m2) (pcs/m2)
15 6.6 1 1 5.6
22.5 4.4 1 1 3.7
30 3.3 1 1 2.8

Heat emission plate for wooden ßoors

Meandering laying of 20 mm PE-Xa pipe with Uponor heat emission plate 20


Spacing Pipe length Heat emission plate
(cm) (m/m2) (pcs/m2)
30 3.3 2.5

When making your estimates, ensure that you also take into account such required accessories as manifolds, room thermostats and actu-
ators, etc. All data should be checked for correctness, BEFORE the system is placed into use, by the engineer/plumber responsible for
installation. Uponor will accept no liability whatsoever for any loss or damage resulting from a failure to check the guideline values for
correctness with respect to the installation in question. Such liability may only be assigned in the event of gross or wilful negligence on
the part of Uponor or its representatives or agents.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 57
Design and calculation

Pkjijm^\g^pg\odjinjaor\m`
Uponor HSE software Uponor Quicky software

Impressive in terms of its capabili- The Uponor software programme


ties and superbly quick and easy to Quicky offers you the option of car-
use. The software Uponor HSE is rying out calculation processes for
the optimal tool for the planning, Uponor underßoor heating systems.
drawing and calculation of sanita- All the necessary input information
tion and heating pipe networks and are available at a glance in menu,
under ßoor heating systems. In fact and the material requirements for
no additional CAD programme is the project will be calculated in an
required when working with HSE. instant. The bill of materials as an
output in generated in PDF format.
Simple drawing functions are avail-
able - whilst one can also import The provision of accompanying
external drawings, a facility which data with images and programme
enables the drawing of installations ãHelpÒ facility all serve to make the
on underlying plans. design work easier. The wide range
of options available in the selection
The complete tabular inputting of or replace of system components
ßoor plans and building structures allows for the individual conÞgura-
is not needed any more. The export tion of materials, and the calcula-
process can take place with or with- tion of a unique quote.
out the plan documents. The opti-
misation of planning using the HSE
software can be targeted towards
either the operational or investment
costs. Any wiring diagrams required
can be automatically generated
using the ground plans.

The software package also comes


with the heating load calculation
amendments deÞned in EN 12831
with change A1 to supplementary
sheet 1. The logging and evalua-
tion of data is thus possible in both
tabular and in graphic modes.

Updates for the new planning soft-


ware are quick and easy to access
and download from the software
menu via the internet, 24 hours per
day. This provides the engineer the
possibility to work with the latest
technical status of the software
development all the time.

The software with English menu


includes the catalogues of Uponor
underßoor heating systems. More
information are listed in the HSE
handbook which includes detailed
description of calculation examples.

58 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

Dino\gg\odji
Agjjmkm`k\m\odji
Before the installation, all the plas-
ter must be Þnished, and openings
closed to avoid draught.

Load bearing foundation is prepared


to create a clean and ßat plane that
will be covered by thermal insula-
tion and screed with pipes. The
constructive ßoor height must be
considered.

Gj\_]`\mdib^jinomp^odji
The load bearing construction dimensions and evenness toler-
should be without cracks and dry ances, to the speciÞcations of
before installation. The height and DIN 18202, table 2 and table 3,
evenness of the surface of the load- line 2 and (for Uponor lightweight
bearing bottom layer must conform, system) line 4.
in terms of maximum/minimum

Table 4.1
Maximum angle
Section Covering Nominal measurement between two walls located
tolerances opposite one another, in m:
up to 1 1-3 3-6 6 - 15 15 - 30 over 30
1 Vertical, horizontal and inclined 6 8 12 16 20 30
surfaces
Max. deviation from horizontal, gauged in mm

Table 4.2
Maximum evenness
Section Covering Distance between measuring points, in m:
tolerances 0.1 1.0 4.0 10.0 15.0
2 UnÞnished upper surfaces of ceil- 5 8 12 15 20
ings, under concrete and founda-
tion ßoors with high speciÞcations,
e.g. for the laying of ßoating screed
industrial ßoors, tiled and panelled
surfaces, composite-screed prefab-
ricated surfaces for underground
areas such as basement storerooms
and cellars
3 Finished-surface ßoors with higher 1 3 9 12 15
speciÞcations, e.g. with self-level-
ling Þller products (distributed-load
layer: dry-screed elements)
Max. evenness tolerances, in mm

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 59
Installation

Dino\gg\odjibpd_`Cjh`>jhajmo
Installation of Uponor clamp Sticking the joints of the insula- Uponor clamp tracks
>g\hkom\^f track system tion roll/pipe Þxing foil At a max. 1.50 m (for pipe dimension
Sticking all joined insulating lengths 16 - 20 mm) or a max. 1.0 m (with
The edging strip is to be Þtted be- (together with the glued-on perime- pipe dimension 14 mm) spacing, the
fore the Uponor insulation board is ter strip apron) creates a seal-tight Uponor clamp tracks are afÞxed par-
laid. trough for taking up the heating allel to each other onto the Uponor
screed. Precise bonding stops both pipe Þxing foil or the Uponor insula-
Laying the Uponor insulation any screed or screed water from tion roll with texture foil. The reverse
roll/pipe Þxing foil penetrating the insulation and also loop is not to be less than 50 cm
The Uponor insulation roll is to be stops acoustical bridges from being from the wall. An extra fastening
laid in preferably continuous lengths formed. point at a 50 cm spacing is recom-
in the longitudinal direction of the mended should the track length be
room. For an easier division of the over 1 m. Depending on spatial ge-
heating loops the marking frame is ometry, 0.75 -1.00 m of clamp track
to concur with the side-by-side in- is needed for a 1 m2 ßoor area. To
sulating lengths. Left-over surfaces produce expansion joints, the
in recesses, at the door passages Uponor joint proÞles are glued at
and strips remaining on the walls are the required positions.
to be subsequently Þlled in with
left-over pieces. Pipe laying
Always place ãfree-handÒ cut sides The Uponor clamp track is to be used
of the boards up against the peri- to fasten the heating pipes on the
meter strip to stop gaps appearing boards at the calculated spacing. In
in the board laminate. Sealing the perimeter strip so doing the permitted minimum
The perimeter strip foil apron must bending radii are to be kept to. The
be bonded with the insulation pipes must be pressed in at right an-
boards to the exclusion of any gaps gles into the clamp track. Laying can
or cavities. This is to stop the foil be of the meander or biÞlar method.
ripping and the resultant ingress of It could be helpful to mark supply and
screed or screed water. return of the heating loops to ensure
the correct manifold connection.

Additional insulation
An additional heat insulation may be
needed in keeping with the DIN EN
1264-4, EnEV or local requirements.

50 cm max. 1.50 m max. 1.50 m 50 cm


for for
16 x 2 mm 18 x 2 mm
17 x 2 mm 20 x 2 mm

max. 1.0 m max. 1.0 m


for for
14 x 2 mm 14 x 2 mm

60 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

Insulation and perimeter strip Kdk`kjndodjidib


k\i`g
Heat and sound impact
insulation
A suitable insulation which meets
the requirements for heat and
impact sound insulation has to
be installed. Only such insulation
materials are to be used which
meet the standards as well as the
specific construction and quality
assurance regulations. When using
conventional insulation materials,
one has to pay attention that with
multi-layer insulations a maximum
of two layers consists of impact
sound insulation materials. The
compressibility of all insulation
materials must not exceed 5 mm.
When combining heat and impact
sound insulation boards, the insu-
lation with the lesser compressibi-
lity must be installed on top.

1 2 3

Edging strip The PE foil of the edging strip is In case of multi-layered insulation,
Fix the edging strip with the self- laid on top of the insulation. the edging strip has to be installed
adhesive strip on the backside so prior to the topmost insulation
that the integrated breaking points layer.
show upwards. The edging strip
is continuously fixed on the wall
and reaches from the concrete
floor up along the complete floor
structure. The strip must be unbro-
kenly installed along the walls, door
frames, pillars or steps.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 61
Installation

Areas without pipe


positioning panel

4 5 6

Transition to areas without pipe Attention: The pipe positioning panel is laid
positioning panel In an ambient temperature below on top of the PE foil (overlapping
In areas without pipe positioning 0 ¡C or above 35 ¡C it is recom- approx. 250 mm).
panel, e. g. in front of the heating mended to cover the complete At the transition, the pipe position-
manifold, in doorways and in areas insulation with the 0.2 mm thick PE ing panel have to be fixed on the
with expansion joints, the insulation foil. At the joints, the foil should be insulation using the fastening nail.
has to be covered with the 0.2 mm overlapped by 80 mm.
thick PE foil. In the transition areas,
the pipe positioning panel laid on clear areas, where no pipe
top has to overlap the PE foil by at positioning panel is installed
least 250 mm. The PE foil can be fixation of the foil with the foil
fixed on the insulation using the nail
Uponor foil nail. area to be covered with the
pipe positioning panel

62 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

Installation of the pipe posi-


tioning panel

The pipe positioning panel provides


for positioning and fixation of pipes
dimension 14 up to 16 mm, as well
as for a barrier against penetra-
tion of screed and laitance into the
insulation underneath. Start laying
out the pipe positioning panel in
the corner of the room, whereas at
the wall edges the panels have to
be laid on top of the PE-foil of the
edging strip (approx. 10 cm over-
lapping). Due to the ãpress-studÒ
function, the panels can be joined
by pressing one row of studs on
top of another one, e. g. by step-
ping on the joint row. The punch-
out of one stud at the edge of the
panel prevents a multiple overlap-
ping when joining the panels. Cut if required for the joint. In order to on the insulation using the fasten-
the panels to size at the edges of prevent the panels from lifting from ing clip. For fixing the panels on
the room. The offcut can be used the insulation in the room corners the insulation, the pipe positioning
to start with the next row, whereas when the pipe is installed, the pipe panel shows special markings.
the panel can be turned by 180¡ positioning panel have to be fixed

7 8 9

Joining of the pipe positioning In case of 45¡ angled walls, the Offcuts can be integrated anywhere
panel pipe positioning panel can also be in the installation.
The pipe positioning panel can cut diagonally.
easily be joined due to the ãpress-
studÒ function.

Cutting the panels to size


Using a conventional blade knife
the pipe positioning panel can
be notched and then broken off.
The pipe positioning panel can be
joined at any point.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 63
Installation

Pipe installation with pipe


positioning panel

With the pipe positioning panel,


pipes 14 x 2 mm up to 16 x 2 mm
can be installed. For an easier
installation, we recommend to use
the pipe uncoiler. The length of
pipe in a heating circuit should not
exceed 120 m. Install the heating
circuits according to the design
layout. The pipe can simply be
uncoiled by hand or using the pipe
uncoiler. Simply press the pipes
between the stud rows with your
foot. Necessary pipe bends can be
made by hand. The smallest admis-
sible bending radius must be kept.
This bending radius corresponds to
a 180¡ bend over 3 stud rows. The
6 cm installation pattern of the
pipe positioning panel provides for that piece has to be replaced by a rosion. The heating circuits have
pipe distances of 6, 12, 18, 24, permanently tight press or screw/ to be designed in a way that no
30 cm and larger. compression coupling immediately. expansion joints are crossed.
In the same manner, the pipe can
Attention: In case the pipe gets be extended. The metal fittings
snapped or damaged otherwise, have to be protected from cor-

10 11 12

Diagonal installation Connection of pipes to the Expansion joints


With the Uponor clip 14/16, the manifold In case expansion joints are
pipes can also be installed in a The pipe end on the outside of the required, e. g. in doorways, the
diagonal way on the pipe position- coil is led under the pipe guiding supply pipes crossing the expansion
ing panel. The Uponor clip 14/16 track of the manifold cabinet. The joints have to be covered with the
is simply pushed into the clear pipe has to be pre-bent carefully longitudinally slit Uponor joint pro-
area between the studs of the pipe before guiding it into the manifold tection tube. Then the expansion
positioning panel where a special cabinet in order to avoid damaging. joint is produced by pressing the
marking is shown. Shorter pipe The adjustable screed shield can be 10 mm thick and 100 mm high PE
lengths like e. g. in doorways or in removed for that and put back on foam joint strip into the joint pro-
front of the manifold do not have after all pipes have been inserted. file which has been taped onto the
to be fixed. Cut, centre and bevel the pipe as PE foil covering the area without
described in the fitting instructions. pipe positioning panel.
Then connect the pipe to the heat-
ing manifold using the Uponor
compression adapters.

64 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

The Uponor MLCP and PE-Xa pipes The top layer of the insulation has Otdibrdm`n*
can be also fixed to a reinforcement to be covered with a separation ^\]g`od`n
mesh by using tying wires or cable layer of PE-foil to prevent penetra-
ties. tion of moisture from the screed
under the insulation.
The installation of the required heat
and sound impact insulation and The pipe will be fixed to the rein-
the edging strip is according to the forcement mesh with 2 tying wires
installation guide for pipe position- or cable ties per m of pipe.
ing panel.

Concrete Uponor MLCP or PE-Xa pipe fixed with tying wires


or cable ties to the reinforcement mesh

Insulation Reinforcement mesh PE-foil

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 65
Installation

Gdbcor`dbco On-site conditions 1 Insulation


k\i`g
Floor construction Thermal insulation / additional
It is very important that the exist- insulation
ing floor is clean and level. Smaller The 25 mm thick basic component
bumps can be levelled out with has a thermal insulation resistance
conventional filler. In case of larger of RhS = 0.62 m2 K/W. If the local
bumps, a levelling compound (e. g. standards require other thermal re-
Fermacell¨ or Perlite¨) should be sistance this value can be achieved
used. Between the levelling com- Before laying out the basic compo- by laying an additional polystyrene
pound and the lightweight panel, nents, the underground surface has insulation board (thermal con-
pressure resistant load distribution to be clean and level. Height varia- ductivity rating 040) underneath
panels have to be laid. It is impor- tions have to be levelled out. the basic element. In renovations,
tant that the panels used are suit- already existing insulations in the
able and certified for this purpose. floor structure can be considered
2
Please consult the manufacturersÕ for the layout.
instructions for dry flooring ele-
ments. In connection with dry flooring
panels, only insulation materials
Sealing of the building with high density must be used
Constructions adjacent to soil have (e. g. polystyrene PS 30, wood fibre
to be permanently protected against insulation panels make Pavatex,
moisture penetration into floors and type Pavapor or extruded PUR).
walls. In case solid floors (e. g. con- Fix the edging strip with the self-
crete floors in new buildings) con- adhesive strip on the backside so Impact sound insulation
tain residual moisture, the rising of that the integrated breaking points With the lightweight panel e. g. in
moisture into the dry original floor show upwards. The edging strip connection with dry flooring panels
structure has to be prevented by a is continuously fixed on the wall on solid floors, the impact sound
PE foil (0.2 mm). Please consult the and reaches from the concrete transmission can be reduced by up
manufacturersÕ instructions for dry floor up along the complete floor to 22 dB. Further impact sound in-
flooring elements. structure. The strip must be unbro- sulation, which might be addition-
kenly installed along the walls, door ally required, has to be adapted to
Expansion joints frames, pillars or steps. the existing floor structure. Please
Above construction joints, expan- consult the manufacturersÕ instruc-
sion joints have to be integrated in In case of multi-layered insulation, tions for dry flooring elements (e. g.
the dry flooring layer. Furthermore, the edging strip has to be installed Fermacell¨ or Perlite Perlcon¨-TE).
only edge joints (edging strip) are prior to the basic elements. In connection with Fermacell¨ also
required when installing the light- wood fibre panels 17/16 (make:
weight panel in connection with dry Pavatex Pavapor with a weight of
flooring panels (e. g. Fermacell¨ or 150 kg/m3) can be used.
Perlite Perlcon¨-TE) in rooms up
to 20 m length. Please consult the When using cement or self-levelling
manufacturersÕ instructions for dry screed, the required impact sound
flooring elements. insulation can be achieved by add-
ing a layer of suitable thermal and
impact sound insulation material
underneath the lightweight panel.
The thermal and impact sound in-
sulation panels are laid in a stag-
gered way to the basic elements
on top.

66 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

Installation of basic elements

Lightweight panels along the walls have The lightweight panels have to be laid on the complete surface of the room.
to be pushed underneath the foil of the
edging strip.

If necessary the lightweight panel can be cut by using a blade The lightweight panels in different rows have to be laid without
knife. any shift between the grooves for the pipe.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 67
Installation

Installation of heat emission plates

The heat emission plates are pushed into the grooves of the The heat emission plates have 2 predetermined breaking points.
lightweight panel. In places where a pipe bend has to be realised They can be separated into different lengths by repeated bend-
a distance of 9 cm between the heat emission plate and the ing at these points.
angular point of the pipe bend has to be kept.

Installation of the pipe

Push the 14 mm PE-xa pipe into the


grooves of the heat emission plates with
your foots.
Note: Please wear sturdy shoes

Connection to the manifold

In front of the manifold additional


grooves can be cut into the lightweight
panel using a polystyrene cutter.

Note: The manifold should be installed in


a central location. Thus heating loops can
be connected from different directions

Screed / Dry flooring panels

When using screed (cement or self-levelling screed), the lightweight panel has to be completely covered with a 0.2 mm thick PE-foil.
This foil serves as separation layer. The individual foil webs have to overlap by at least 5 cm. When using self-levelling screed, the joints
of the foil have to be taped. In order to prevent the penetration of screed or screed water at the edges, the PE-foil of the edging strip
also has to be taped on the separation foil.

In case dry flooring panels (e. g. Fermacell¨ or Perlite Perlcon¨-TE) are installed as load distribution layer, the separation foil is not nec-
essary. When using screeds, the system has to be heated up according to DIN 4725. Please see heating report.

68 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

Wooden suspended floors do not Ensure that the wood is properly to centre distances of less than C`\o`hdnndjikg\o`
conduct heat as efficiently as dried (maximum humidity content 600 mm). ajmrjj_`iÙjjmn
concrete. Therefore in this type of 10 %). The following guidelines
installation heat emission plates are general and are based on a
are required in order to achieve an centre distance between joists of
even floor temperature. 600 mm (they are also applicable

Chipboard or parquet Vapour barrier under Uponor heat Uponor PE-Xa pipe
parquet emission plate 20 x 2.0 mm

300 mm

Insulation Battens minimum 22 x 95 mm with a Floor joist


pitch of 150 mm

Nail battens measuring at least can be divided and adapted to When laminated parquet is laid
22 x 95 mm using two nails to each room length. The gap between the directly without chipboard beneath,
joist (use hot zinc coated nails plates should be at least 10 mm but the following should be observed:
preferably). The first batten should not more than 100 mm.
be nailed approx. 50 mm from the The structure must be reinforced.
outer wall so that the aluminium Pin the plates onto the battens The battens must be at least 28 x
plate can be positioned correctly. ensuring that the pipe grooves are 70 mm. They should be laid allow-
in alignment. ing for a gap of 25 - 30 mm to the
Leave half the distance between wall and should be nailed to all the
the two last joists free of battens. Position the pipes according to the joists except for the last one. Then
Another batten is then laid along layout pattern. the ends of the battens should be
the last joist by the cross wall. lifted whilst the pipe loops are slot-
Ensure that there is enough room Lay a vapour barrier as required. ted round and underneath them
left to allow for the positioning of before the nailing process is com-
the pipe loops . Mark the routing of the pipes in pleted, the laminated parquet is
order to prevent accidental perfora- laid across the battened area.
Lay the heat diffusion plates start- tion with screws.
ing from the outer wall. Leave Note that the battens should be
300 mm free from the cross wall The chipboard (minimum thickness nailed with hot zinc coated nails
in order to allow the pipe to loop of 22 mm) is then laid across the and that every fourth batten only
around. Cover as much as possible battens in 600 mm sections and need be nailed.
of the area with the diffusion plates fixed with screws. Tongues and
(70 - 90 %). The diffusion plates grooves are glued.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 69
Installation

Cdbck`majm( Load-bearing subsoil


h\i^`k\i`g The subsoil must be solid, load-
Coordination through discussion bearing, clean, skid-proof, free
between the heating specialists and from parting substances and dry.
the other trades is required. If the The load distribution layer must
subsoil does not meet the require- be checked and any cracks must
ments of DIN 18202 for approved be repaired. Wax and similar layers
subsoils, it has to be levelled using should be removed mechanically,
an appropriate Þlling compound. ßoor boards must be mounted
The existing load distribution layer properly and old ßoor coverings
and the newly applied Þlling com- such as linoleum, carpet or laminate
pound must allow linear expansion should be completely removed
(Edge insulation strips). The insula- without leaving a residue.
tion regulations must be followed
(see DIN 18560 and EN 1264). For
further details see Uponor mount-
ing instruction.

l [m] 0.1 1 4 10 15
2

t [mm] 2 4 10 12 15
1 2
1
1
1
1
1
1
1
1
1
9
8
7
6
5

t
4
3
2
1

70 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

Edging stripe High performance panel

1 2

1
3 4

3 2 1

6 5 4

16 9 8 7

17 12 11 10

18 15 14 13

Expansion joint profile

DIN 4726
x1,1
B 9,9
0W
X 11
PE
elta
V
or
on
Up
T

2
xT
r

r ³ 50 mm

Possible pipe spacing Optimum installation tem- Application temperature for Application temperature for
perature high performance panel pipe/pipe coupling
5 cm | 10 cm | 15 cm Å 15 ¡C 5 Ð 40 ¡C 0 Ð 40 ¡C

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 71
Installation

EN 1264-4
Minimum distance from vertical components Minimum distance from chimneys and open Þreplaces, open or
walled shafts as well as elevator shafts
> 50 mm > 200 mm

Mounting/operating instructions for Uponor modular


plastic manifold and Uponor push 12

Heat up according to EN 1264-4. Set the automatic regula-


tion connected in series on manual mode, for instance at 60 ¡C
constant

Pipe couplings and pipe repairing

b
max. 136°C

EN 1264-4
?m
Revision draft

?m

In case of any coupling is used, a revision drawing has


to be listed in project documentation.

72 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

1 2 3 4

3–5x

Leakage test after


qi 0 – 5° C qi 0 ≥ 5° C
2h 0,5 h

1 2 3 4
3–5x

Note: mount the pipe


on the support body
up to the end stop
5

1 2 3 4

Existing expansion joint

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 73
Installation

Commissioning/heat up/ be kept under working pressure. The system is introduced into opera-
functional test/operation The system should be kept safe tion in from of heat up steps from
from frost. max 25 to max 53¡C, in 5 K steps
Proceed to commissioning accord- Follow the manufacturerÔs which takes in total 1 day. The notes
ing to suitable installation instruc- instructions for the levelling are recorded into protocol for initial
tions (Þlling, washing, ventilating, compound. heat up. This is accomplished in a
pressure test, fan preadjustment). Levelling compound: Initial heat up manual hand mode operation. The
Provide a Þlter minimum 3 days after feeding the after is tested functionally of entire
compound. system (including controls) under
Feeding the levelling compound Thin screed: Initial heat up minimum real operating conditions and the
Vacuum clean the surface before 7 days after feeding the compound. test is documented. ProoÞng of the
feeding the compound. During temperature range 15 Ð 53 ¡C, and
the feeding of the levelling com- The use of only special screed is pressure test to 6 bar.
pound, all heating circuits should allowed, please contact Uponor.

Kdk`gjjk^jii`^odji\i_Øggdib
Manifolds, pipes loops and Filling With by-pass: A. Close the Þll-
Þttings ing valves. Remove the aeration
Fill the installation according to the valve from the end cap of the
Fix the manifold wall bracket on following instructions: return manifold using the tool
to the wall. Close all valves on the manifolds, from the basic kit. B. Remove the
Assemble the manifold onto wall both supply and return, as well as outlet hose and protective cover.
bracket and clamp it into position. shut-off valves. Ensure that the Connect the by-pass. C. Connect
Mount a bend support by Uponor aeration valves, on the manifoldÕs the venting hose to the aeration
PE-Xa pipe on the supply pipe end caps are closed (screwed in) valve on the supply manifold.
at the base of the wall beneath and the valves for Þlling are open Open both the shut-off valves
the manifold leaving sufÞcient (unscrewed). and vent via the aeration valve.
pipe length for connection to the Connect hoses to the two end Switch off the tap water, close
manifold. caps on the manifolds. Connect the return lineÕs charging valve,
Connect the pipe to the mani- one of the hoses to the water remove the hose and hose nipple
fold and set out the pipe loop tap. Run the other hose to a suit- and replace the protective cover.
in accordance with the layout able drain. Open all the valves and carry out
drawing. Pipe loops should be Turn on the water from the tap. pressure testing (3-4 bar; 0.3-
laid in an orderly manner for Open the end cap valves for the 0.4 MPa). The pressure will drop
neat installation. Mount a bend Þlling and draining of the system. during the Þrst hours but will
support on the return pipe in the Open the supply and return then remain steady, as long as
same way as for the supply pipe. valves for one loop. Let the water there are no leaks and provided
Cut the pipe and connect it to ßow through the loop until all the that the ambient temperature has
the manifold. air has been expelled. If the water been constant.
Mark the loop number for identi- does not ßow through the loop The ßoor can be Þnished (con-
Þcation purposes. check to see that the pipe is not creting, covering with chipboard,
Note the precise length of each buckled. parquet etc.) after a Þnal inspec-
loop using the metre markings on Close both valves and repeat the tion has been carried out to
the pipe and compare with the cycle for the other loops, one by ensure that the system is water-
layout drawing. A major deviation one, until all the loops have been tight.
in length may require an adjust- Þlled and bled of air.
ment of the loop balance set- Without by-pass: A. Close the Note: There is a risk of frost damage
tings. Þlling valves, switch off the mains to the system when temperatures are
water, undo the hose nipples and below freezing.
hoses and replace the covers.
B. Open the loopsÕ valves and For further information see also
check, using the aeration valves, Initial heating up
that there is no remaining air.

74 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

System Þlling and ßushing / venting

1 2 3
open max.open
close
open
close

close close close


open
open max.open
close min.open
close

open
close close close

max. 5 bar max. 5 bar

open open open

Repeat filling and flushing (steps 1-3) for all


additional heating circuits

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 75
Installation

Km`nnpm`o`no
Pressure testing of underßoor ing loops at a minimum of 4 bar is needed. The test pressure must
heating-loop conduits in accord- and a maximum of 6 bar (0,6 MPa) be recovered as required after the
ance with EN 1264-4. The loops, for 2 hours (in special cases longer, waiting period.
once Þtted, are to be leak-tested 24 hours). Do a visually inspect the
using pressurized water or air before joints. Ensure when doing so that All pressure-measuring instruments
applying the screed. the shutoff devices immediately used must be reliably accurate to
upstream and downstream of the 0.1 bar (10 kPa). The test pressure
The loops must be completely Þlled underßoor heating system manifold must not drop by more than 0.2 bar
and purged of air before pressurized are closed, in order to limit the test (20 kPa), and there should be no
water-testing takes place. Leak- pressure to the zone being exam- leaks. When the screed is being laid,
testing should be carried out both ined. The balance between ambi- the test pressure must be main-
immediately before and during the ent temperature and Þlling-water tained at the systemÕs maximum
screed-laying operation. temperature should be taken into permitted operating temperature.
account by a corresponding waiting Take appropriate measures if there
The test pressure must be at least period after achievement of test is any danger of pipes freezing up
1.3 times maximum operating pres- pressure. By the air test the suf- heating the building, etc.
sure. We recommend testing the Þcient time for the relaxation of the
Uponor system in underßoor heat- pressed air temperature and volume

In pressure test the whole system


Max. 0.6 bar drop period
is subjected to the test pressure Preliminary test
by pumping for 30 minutes, after
Max. 0.2 bar drop period
which the pressure is noted and the Main test
Pumping stops
test continues for 30 + 120 minutes
without further pumping. Test is
passed if the drop in pressure is less Test
pressure
than 0.6 bar (60 kPa) after the fol-
lowing 30 minutes (preliminary test,
System
system relaxation and temperature pressure
equalising), and 0.2 bar (20 kPa)
after the further 120 minutes (main
test), and there is no visible leak-
age throughout the test. It means
an allowed pressure drop of 0.2
bar (20 kPa) during the 2-hours 0
0 10 20 30 60 mins. 120 180
main test.

76 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

Pressure / Functional test

1 2

2x

open 2x

2h max. 6 bar

2x

Operating pressure
After 2 hrs., check
for leakage

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 77
Installation

Pressure test report

Pressure test for underfloor heating system in accordance with DIN EN 1264-4

Project:

Project phase:

Person responsible for inspection:

Max. allowable operating pressure: = _____________ bar


(with reference to lowermost point of system)

The balance between ambient temperature and filling water temperature should be taken into account by a corresponding waiting
period after achievement of test pressure. The test pressure must be recovered as required after the waiting period.

Note: By the air test the sufficient time for the relaxation of the pressed air temperature and volume is needed.

Preliminary test

Test start: _____________ , _______________ Test pressure: _____________ bar


Date Time (max. 6 bar)

Test end: , Test pressure: bar


Date, Time (max. drop in pressure 0.6 bar)

Main test

Test start: _____________ , _______________ Test pressure: _____________ bar


Date Time

Test end: , Test pressure: bar


Date, Time

Pressure loss during the main test : bar (max. 0.2 bar)

It was determined, at the end of the test period, that there were no leaks in the above-mentioned system.

Confirmation

Building owner/Customer: Site management/Architect: Heating company:


Stamp/Signature Stamp/Signature Stamp/Signature

Place, Date Place, Date Place, Date

78 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

N^m``_dib\i_^ji^m`odib
The construction of the screed layer case 45 mm. The maximum temper- be lower than 5¡C for at least 3
differs for Uponor systems and is ature around the heating elements days. Hardening screed should be
depended from Þxation method. (plastic pipes) in the screed shall protected from draught, fast drying
The thickness should be calculated not exceed 55 ¡C. The Òefßores- and harmful effects.
according to carrying capacity cenceÓ should be taken off.
speciÞed in national codes. The Max. Working load over the 30 mm
screed thickness above pipes must The temperature of the liquid screed is 1.5. kN/ m2 resp. for
be at least 30 mm, and in standard screed and the room should not 45 mm screed 5.0 kN/m2

The work over the screed can be


carried out only with a permit by
the resident engineer:

Uponor screed additive VD 450 Uponor screed additive VD 550 Uponor marking set

Is dedicated for use with cement- Is dedicated for use with cement- Is dedicated for controlling the mois-
based screed, homogenises and based screed, improves heat con- ture of the screed. The consultant
improves quality of screeding mate- ductivity, bending strength and must enter the approximate arrange-
rial in order to increase level of heat crush resistance. Consumption by ment of the measuring point(s) in
conductivity and crush resistance. 70 mm screed thickness is approxi- the room centre in the drawing. The
Consumption by 70 mm screed mately 0.2 l/m. Water curing takes measuring points must be marked
thickness is approx. 0.2 l/m for ca. 8 days. according to the drawing speciÞca-
screed with thickness of 30-45 mm. tion by the screed layer. Underßoor
Water curing takes approximately Note: Use of Uponor additives with heating pipes must be distant at
21 days. anhydrite and cement liquid screed least 10 cm from the measuring
is not allowed. point, and the most suitable point is
inside the pipe bending.

When using Uponor screed addi-


tives VD 450 and VD 550, thickness
of the screed over the pipes can
be reduced from 45 to 30 mm for
working load up to 2,0 kN/m2.

≥ 100

The resident engineer must be advised of suitable measuring points for measuring the humidity
(1 point per room – with a minimum of 3 points per 200 m2 or dwelling)

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 79
Installation

Didod\gc`\odibpk
Heating report

Heating report for Uponor underfloor heating systems (functional heating) for anhydrite and/or calcium sulphate screed and cement
screed, used with radiant heating as per EN 1264-4

Person responsible/Project:
Section/Floor/Room:

Anhydrite and/or calcium sulphate and cement screed, should be heated up before the floor covering is laid. Procedures require that the
heated floor structure should not be heat tested for correct functioning for the first 21 days after laying, in case of cement-based screed,
or 7 days for anhydrite and/or calcium sulphate screed (or as per supplierÕs instructions).

Testing involves maintaining the supply temperature at 25 ¡C for three days, followed by four days at maximum supply temperature. The
leak resistance of the loop should be determined, by means of water-pressure testing, both immediately before and during the screed
laying process. Any supplier data that differ from those contained in this report and/or EN 1264-4 (e.g. for liquid screed) must be taken
into account.

1. Type of screed, manufacturer:


Binding agent used:
2. End of work on heating screed:
3. Start of heating procedure (functional heating) at constant supply
temperature of 25 ¡C (manually regulated):
4. Start of heating procedure (functional heating) at max. supply
temperature (system temperature) of _____¡C. (as per DIN 18560
max. 60 ¡C. With laying of anhydrite or calcium-sulphate screed
max. 55 ¡C, or as per supplierÕs indications):
5. End of heating procedure (functional heating) (not earlier than four
days after no. 4):
6. Heating procedure (functional heating) was interrupted. Yes No
If ÒYesÓ: from to
7. The heated floor surface was free of building materials and other
covering items: Yes No
8. The rooms were ventilated (but draught-free) and, once the radiant
heating system was switched off, all windows and outside doors were
closed. Yes No
The system was approved for further installations at an outside The system was shut down at this stage.
temperature of _____¡C. The floor was heated at a temperature of ______ ¡C.

Please confirm the above details with signature and company stamp.

Heating procedure (functional heating) was not able to determine whether the screed has reached the moisture-content level specified
for further laying operations. Further heating may be needed in order to achieve the required level of preparation (see also technical
regulations on functional heating and drying of screed). When the radiant heating system is switched off at the end of the heating
procedure, the screed should be protected from cold draughts in order to prevent rapid cooling down.

Confirmation

Building owner/Customer: Site management/Architect: Heating company:


Stamp/Signature Stamp/Signature Stamp/Signature

Place, Date Place, Date Place, Date

80 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

=\g\i^dibjah\idajg_n
Since the loop length is not always To obtain the correct setting:
equal, the balancing of loops is Remove the red wheel. Close the
required. The calculation of pres- valve without using excessive force
sure loss per loop and estimation (torque approx. 3 Nm). Mount the
of the valve setting is accomplished setting ring with the Ô5Õ digit in the
according to a table or a diagram. centre of the indicator line. Replace
the red wheel with the wheelÕs stop
To balance each individual under- lug against the ringÕs stop lug (by
ßoor heating loop, close the valve the Ô5Õ digit).
on the supply manifold (clock-
wise) and lift and turn a setting Adjust the balancing screw:
ring, graduated 0.5 Ð 5. Once the
required setting value appears in Close the hand wheel on the
the centre of the black indicator supply manifold
line on the manifold neck, press the Lift the setting ring and turn it
ring down. The valve will then open CLOCKWISE until the desired
as far as the stop lug on the limiting setting value is in the centre of
ring. To prevent the balancing valve the marker point
from clogging, setting values below Push the setting ring down
1.5 should not be used. Open the hand wheel to the
stop lug
If the supply valves have been
replaced with ßow meters, adjust
these instead until all ßows cor- Hand red wheel
respond to those calculated. The
setting ring can subsequently be Stop lug
used to prevent any loop opening
Indicator line
too far.
Setting ring
The ßow through the by-pass can
be reduced or shut off using the
supply lineÕs Þlling valve.

If the red wheel has been removed,


it can end up in the wrong position
so that the adjustment values no
longer apply.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 81
Installation

Adjustment of the inlet valves/Adjustment of the manifold lead valve

1 2 3

close
Uponor Fußbodenheizungsberechnung
Uponor floor heating calculations
Uponor vloerverwarmingsberekening
Calculation du chauffage par le sol Uponor
Calcolo riscaldamento a pannelli radianti Uponor
Raum-Heizkreis-Daten
Room heating circuit data
Ruimte- en verwarminggroepsgegevens
Données des pièces - circuits de chauffage
Dati circuito riscaldamento locale

B Raum-Nr
Room No.
Heizkreis-Nr
Heating circuit No.
Wassermenge
Quantity of water
Ventileinstellung
Valve adjustment
Ruimte-Nr Verwarmingsgroep nr Hoeveelheid water Ventielvoorinstelling
N° de la pièce N° du circuits de Quantité d’eau Réglage de la vanne
Num. locale chauffage Quantità di acqua Tartura della valvola
Num. circuito
riscaldamento locale l/min

1 1 4 1
1 2 10 4
2 3 5 2
3 4 11 5
4 5 1,5 1,5

1 2

close
Uponor Fußbodenheizungsberechnung
Uponor floor heating calculations
Uponor vloerverwarmingsberekening
Calculation du chauffage par le sol Uponor
Calcolo riscaldamento a pannelli radianti Uponor
Raum-Heizkreis-Daten
Room heating circuit data
Ruimte- en verwarminggroepsgegevens
Données des pièces - circuits de chauffage

B
Dati circuito riscaldamento locale

Raum-Nr Heizkreis-Nr Wassermenge Ventileinstellung


Room No. Heating circuit No. Quantity of water Valve adjustment
Ruimte-Nr Verwarmingsgroep nr Hoeveelheid water Ventielvoorinstelling
N° de la pièce N° du circuits de Quantité d’eau Réglage de la vanne
Num. locale chauffage Quantità di acqua Tartura della valvola
Num. circuito
riscaldamento locale l/min

1 1 4 4
1 2 10 8
2 3 5 5
3 4 11 11
4 5 1,5 4,5

1 2 3
5

Rohrnetzberechnung
Pipe system calculations
Leidingnetberekening
Calculation des circuits de tuyau

Strang 1 Ventileinstellun
Riser pipe 1
Strang 1
g
Valve adjustment
Conduit principal 1
Ventielvoorinstelling

Verteiler 1
Distributor 1 8
Verdeler 1
Collecteur 1

Verteiler 2
Distributor 2
Verdeler 2
Collecteur 2
5
Strang 2 Ventileinstellun
Riser pipe 2
Strang 2
g
Valve adjustment
Conduit principal 2
Ventielvoorinstelling

Verteiler 1
Distributor 1 8
Verdeler 1
Collecteur 1

Verteiler 2
Distributor 2 5
Verdeler 2
Collecteur 2

max open 500 50


40
400

max close 300 30


2

2,5

200 20
3
5

4
5
6

100 10
8
Druckverlust Dp in [mbar]

80 8

36mm
mm 5x 60 6
7

50 5

40 4

30 3

20 2
[kPa]

Medium: Wasser
10 1
100 200 300 500 1000 2000 3000

Massenstrom m in [kg/h]

82 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

>jhhdnndjidib
Follow these instructions when Allen key. If this procedure is Comments
starting up the system: not done thoroughly, the entire
heat demand of the house may A. Concrete slab
1. Once all the pipe loops have be covered by just one or two When the underßoor heating
been Þlled, deaerated and pres- loops. installation has been completed
sure tested, close all the loop 6. In the case of manual control and provided that the heat source
valves and open the shut-off valves, the water temperature is already installed, it is possible to
valves instead. from the boiler must be control- run the whole system at the time
2. Fill the supply pipes and boiler led in order to avoid excessive the concrete slab is poured. Howev-
with water and deaerate. Deaer- temperatures. This can be done er note that until the concrete has
ation can be carried out at the by an outdoor temperature cured (this takes about 17 days in
end caps of the manifolds (sup- sensor or by a centrally-located a one-family house), the maximum
ply and return). In houses with indoor sensor and the relevant water temperature should be 25 ¡C.
several storeys begin by deaerat- control equipment. After this period the underßoor
ing the manifolds located in the Since underßoor heating is a heating system can be run at the
basement. low-temperature system, the designed temperature.
3. Open all the loops and check maximum water temperature in
once more to ensure that they wooden suspended ßoor struc- B. Wooden suspended ßoor
are bled of air as described tures need not be more than structure
above. If there is still air in the about 55¡C. This should be even In timber-built houses, local regula-
loops repeat the Þlling opera- lower in concrete. tions or recommendations regarding
tion. Where the supply water temper- the moisture content of the timber
4. The system is normally put ature is controlled by a central should be observed. ManufacturerÕs
under a pressure of 0.5-1.5 unit, sensing for instance the instructions on moisture content
bar (50-150 kPa). Start up the outdoor temperature, set a ßat in parquet ßooring should also be
pump and boiler. Open one loop response curve on the panel in followed. An underßoor heating
in the manifold. The temperature order to let the system operate installation will help maintain the
should now increase slowly. In within the required range of the prescribed moisture level.
a while you should be able to heating system. According to SS-27 23 44 (Swed-
feel the hot water reentering the 7. When controlling room tem- ish Standard) the moisture content
manifold. Repeat the procedure peratures with room thermostats should not exceed 10% either in
with all the loops. and actuators, the supply water the ßoor structure as a whole or in
In large installations it is conven- temperature can be kept at a the parquet. See ÒFloor construc-
ient to open one manifold and constant level all year round. tion Uponor heat emission plate for
then one loop in the manifold at The heat is sent out in pulses of wooden ßoorsÓ and ÒFloor covering
a time. Normally every manifold 5-6 minutes only until the room materialsÓ.
should be equipped with a shut- temperature setting has been
off valve. reached.
5. Set the calculated throttling 8. It is important that the control
values on the lockshield valves equipment at the heat source
(return valves) for each loop. and the room thermostats work
Count the number of turns from properly and are correctly set,
a closed valve (see also ÒBalanc- particularly so when the ßoor
ing of manifoldsÓ). This opera- covering material is parquet.
tion is done by means of a 4 mm

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 83
Installation

H\dio`i\i^` A\pgoom\^dib
Uponor underßoor heating system 1. Check that the installation has 4. Ensure that the installation
is in principle maintenance-free and been carried out in accordance has been Þlled with water and
designed to work for many years. with UponorÕs instructions. deaerated according to UponorÕs
In particular the loops should instructions.
There are however some aspects to have been laid according to Air in the loops is the most
consider: the drawing. The heat demand common cause of poor perform-
and the type of ßooring should ance in a system. That is why
1. The pressure in the heating also correspond to the drawing the Þlling instructions should be
system should be checked now speciÞcations. closely observed.
and again. If the pressure in the 2. Make sure that the installation Note: It is almost impossible to
system is incorrect, check by has been properly marked. The deaerate the loops without shut-
means of the deaeration valves loops should have been clearly off valves on the manifolds.
that the system has been bled of marked and should indicate 5. Make sure that the installation is
air. A large air bubble can disturb which room they serve, the correctly balanced.
the circulation. better to prevent loops from 6. Check once more that the heat
2. If the system still malfunctions, becoming cross-connected to demand, the loop length, the
check for leakage. It may be the manifolds. Ensure that all dimensions and the layout of the
necessary to tighten couplings. loops are correctly connected. supply pipes correspond with the
3. If necessary, the system may 3. Check that the hot water tem- drawing. If this is not the case,
need reÞlling. If the pressure perature to the manifold is new calculations should be made
cannot be maintained despite correct. with corresponding balancing
these measures, you must carry If not, check the following: adjustments.
out more careful fault tracing ¥ The boiler has sufÞcient
and if necessary call in experts capacity
to go through the entire system. ¥ All valves are opened
¥ The correct circulation pump
When tracing a fault follow the has been selected and has
procedures indicated below. been set for the right curve
¥ The control equipment for the
supply water temperature is
correctly adjusted.

Note 1: In the event of long


supply pipes running from the
boiler to the manifolds, it may
be necessary to bypass the
manifold so that water circulates
in the supply pipes.
Note 2: Concrete ßoors and
walls consume a considerable
amount of heat whilst drying
(evaporation heat). Concrete
ßoors should be allowed to cure
before heat is applied. Alterna-
tively, the procedure outlined in
the section on commissioning
above can be followed.
Note 3: When checking large
installations, it is easier to deal
with one section at the time.

84 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Installation

Omjp]g`ncjjodib
One of the rooms is cold The ßoor temperature in the
room is too high
All the loops work satisfactorily.
However one of the rooms is cold When the ßoor temperature in a
and the return water temperature room is too high, it means that the
drop is too high. water temperature in the loop is
too high. One probable reason is
If this is the case, the heat demand that the valve spindle on the supply
for this room is higher than calcu- manifold is not watertight.
lated. Check to see if the ventila-
tion supply temperature is too high Shut off the ßow through the loop
and if the insulation of the room at the manifold. This can be done
is sufÞcient. If neither is the case, by means of the manual valve
and yet the problem remains, open handle or if the manifold is provided
the return valve approx. 1/2 turn with an actuator by disconnecting
at a time. the auxiliary voltage to the actuator.
Shut off the return valve as well.
If necessary increase the supply
water temperature and rebalance Disconnect the return pipe of the
the loops. Also close the return loop. If the supply valve is water-
valves for the rooms that are too tight no water should come out of
warm, approx. 1/2 turn at a time. the pipe.

The ßoors are cold Note: When valve spindle failure


occurs the whole supply manifold
The ßoors are cold although the should be replaced.
room temperature is correct. This
means that there is another source
of heating in the house. If for
example, the heating system is a
combination of underßoor heating
and ventilation, check the tempera-
ture of the air inßow. It should be
2-3¡C lower than the desired room
temperature.

If the room is heated by other


heat sources (for example ofÞce
machines, lamps etc.) the room
thermostat and actuator should be
replaced by a manual valve handle
on the manifold, to give a constant
ßow through the loop.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 85
Controls

>jiomjgn
An effective temperature control due to the beneÞts of a high degree important control for comfort and
system needs to supply heat at the of Òself-controlÓ a ßoor heating and savings of energy.
same rate, at which the building cooling system is capable of com-
loses heat under dynamic condi- pensating for variation in external The heating systems with auto-
tions, thereby maintaining a stable and internal loads. For the optimal matically operated elements must
and comfortable indoor tempera- performance it is recommended to be equipped with room-by-room
ture. The air temperature of a room use a combination of central and thermostatic control. Uponor offers
takes the value that balances all individual room control. The central both radio and wired control sys-
heat supplies and losses. control shall control the mean or tems for this purpose, and Uponor
supply water temperature accord- control system is suitable for all
The results of real testing show that ing to the outside weather. The kinds of underßoor heating systems
with the right control concept and individual room control is the most and solutions.

Individual room temperature Zone control


Generally the best is a combined
control concept:
ÒLocal (individual) control is applied ÒZone control is applied when the
when the heat supplied to heated heat supplied to a zone normally
The central control in the heat
space is controlledÓ. The main idea consisting of several spaces (rooms)
source will control the supply
of individual control is to improve is controlledÓ. Zone control is
water temperature to the ßoor
the local thermal comfort in cer- applied for a certain group of rooms
system according to the external
tain room and save the energy by or open-plan spaces.
climate. The individual room
means of setting the expected room
control will then control the
temperature set-point directly from Central control
water ßow rate or water temper-
a person.
ature (mean water temperature
Central control is applied when the
as the best) individually for each
Room temperature control is heat supplied to the whole build-
room, according to the set-point
required to achieve the best indoor ing or manifold is controlled by a
selected by the user.
climate comfort. Different heat central system in control station or
requirements exist within a building boiler room.
depending on external factors (ori-
entation of the building, wind etc.)
or internal factors (lights, open Þre,
time of occupancy etc.). Underßoor
heating can cope with all these
requirements. Every room can be
controlled accurately by means of
a room thermostat. However, in
open-plan design, the different
ÓroomsÓ can be considered as one
(zone control). Here Uponor recom-
mends the use of only one room
thermostat to control the whole
open space, the thermostat being
installed in the ÓroomÓ with the
highest heating demand. Normally
this is the room with the highest
number of outer walls or windows.

86 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Controls

R\o`mo`hk`m\opm`^jiomjgnom\o`bd`n
There are different principles for change in the indoor temperature.
controlling the water temperature in It may take several days before the
underßoor heating. indoor temperature changes. In
other words an indoor temperature
Constant supply water tempera- control will harmonize with the ther-
ture at constant ßow mal inertia of the house. In using
this control technique, the risks for Boiler UFH
This technique is to be used only above and below temperature peaks
if the heated ßoor is used as a in the indoor climate are minimized.
secondary heating source. It will
satisfy only the minimum basic Outdoor temperature compen-
heating demand. Another heating sation of supply water tempera-
Figure 5.1 Principle diagram for constant sup-
system will have to control the room ture at constant ßow ply water temperature at constant ßow
temperature. Under these condi-
tions a constant supply tempera- Contrary to the above an outdoor
ture will give a near constant ßoor temperature control is regarded
surface temperature. If the room is by some experts as the best tech-
designed for a certain temperature nique. The reason for this is that
the supply water temperature must it is possible then to work with a
be set 2-3 K below this level. Oth- pre-set supply water temperature
erwise the ßoor temperature can, in curve as a function of the outdoor
some situations, override the room temperature. The major advantage
temperature control system. here is that when an increase in
the outdoor temperature occurs
Constant return water tempera- the control system will immediately
ture at constant ßow lower the supply water temperature,
thus minimizing unwanted heat
To be used as above. If the room is loss. On the other hand a decrease
designed for a certain temperature in the outdoor temperature will
the return water temperature must always create an above temperature Figure 5.2 Heating curve example
be set 8-10 K below this. peak in the indoor climate.

Indoor temperature compensa- Supply water temperature is com-


tion of supply water tempera- pensated according to the external
ture at constant ßow temperature. The adjustment of
the control is made by choosing
Some experts on indoor climate the right slope according to the
control are of the opinion that an premises, internal or external loads.
indoor temperature control tech- The adjustment device is the 3-way
nique is the best technique to use. valve of the central control.
The reason for this is the fact that
most buildings have a very high
thermal inertia. This means that a
quick change in the outdoor tem-
perature will start only a very slow

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 87
Controls

Variable ßow at constant supply is essential, such as in swimming absolute heat requirement com-
water temperature baths, shower rooms etc. The use pared to no night set-back will be
of a constant ßoor temperature is lower. The energy savings by night
Some experts consider that the to be seen only as part of an indoor set-back in residential buildings
techniques of indoor climate control climate control system. Room tem- are, however, relative low nowadays
using a variable supply water ßow perature control will be regulated by due to the high thermal insula-
at a constant temperature, are the another heating system. Whatever tion standard in new houses. The
Þrst modern temperature control the case, if the ßoor surface tem- advantageous here is also a boost
techniques. Generally the heat perature is higher than the pre-set heating, i.e. the water temperature
output can be estimated by meas- room temperature, the heated ßoor is increased above the temperature
uring the difference between the will in some instances override the corresponding to the heating curve
supply and return temperatures indoor temperature control system. during the beginning of the re-heat
of the heating installation. A large period in the morning. This reduces
temperature difference would then Night temperature set-back and the re-heat time and a longer set-
mean a low heating output and a boost up period in the morning back period is possible. The Boost
small temperature difference conse- re-heating improves the energy
quently would mean a high heating Night setback is a technique which performance with around 8 %.
output. aims to save the energy cost in
the time with decreased need for
Constant ßoor surface heating (decreased room tem-
temperature perature e.g. during nights by 2 K
is accepted). The additional heat
The technique using a constant requirement compared to an ÒidealÓ
ßoor temperature is often used night set-back (no thermal mass of
in places where ßoor temperature system ) is 10-15 %. Of course the

M`nkjin`odh`
Different interrelated factors to do Climatic conditions The ßoor structure will also affect
with climatic conditions and building the response time. In houses with
design, affect the response time of Response times vary in accord- concrete screeded ßoors, the
an underßoor heating installation. ance with the outside temperature. screed will store energy, initially
Heating systems are designed to slowing response time. In public
cope with temperatures during the buildings this storage effect can
coldest months of the year. How- be used to save energy at night or
ever, they are not designed to work at weekends, a temperature drop
properly only during that period, being acceptable when the build-
because in the months before and ings are not occupied. The system
after the cold season, there is a can, for example, be controlled by
capacity reserve which will speed up a seven-day timer programmed to
the response time. allow for system response. Houses
with wooden suspended ßoors or
Building design ßoating ßoors will, conversely, have
a faster response time, since wood
The insulation in a building, the has low thermal mass.
U-value, will complement the
Figure 5.3 Typical response time diagram. performance of the underßoor
heating system. If the structure is
poorly insulated, resulting in energy
wastage, the response time will be
affected by the heat loss.

88 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Controls

N`ga^jiomjg``^o
Due to the high impact the fast between room and the average Table 5.1 shows the percentage
varying heat gains (sunshine temperature in the layer, where decrease of the heat emitted from
through windows) may have on the the pipes are embedded. It means the ßoor by a 1 K increase of the
room temperature, it is necessary that fast change of room operative room temperature. A well insulated
that the heating system can control temperature will equally change of house has on average for the heat-
for that, i.e. reduce or increase the heat exchange and result in great ing season a heat load of 10 to
heating output. For a low tempera- inßuence of total heat exchange. 20 W/m. For these types of houses
ture heating system like ßoor heat- The self control is applicable only for the Òself control-effectÓ corresponds
ing a important effect is so called water-based surface systems, not for to 30 - 90 %.
Óself controlÓ. The Òself controlÓ electric heating. The self regulation
depends partly on the temperature effect will automatically control the
difference between room and ßoor heat supplied to the room accord-
surface and partly on the difference ingly to thermal needs.

Table 5.1 Percentage decrease in the heat exchange from the ßoor by a 1 K increases in θi.
(Source: Olesen B. W. 2001)

Average Floor Average temperature Percentage decrease of heat output by


Heating temperature of heating medium 1 K increase of room temperature
requirement (20 ¡C room
temperature) Reference temperature
Tile Carpet Floor surface Water
0.02 mK/W 0.1 mK/W Tile carpet
W/m ¡C ¡C ¡C % % %
40 23.9 26.2 29.4 26 16 11
20 22.1 23.3 24.9 48 30 20
10 21.1 21.7 22.5 91 59 40

Mjjho`hk`m\opm`n`injmn(oc`mhjno\on
Air temperature sensors The Uponor room temperature sen- The operative temperature in room
Operative temperature sensors sor will integrate the inßuence of air will be controlled exactly according
and mean radiant temperature in the to the desired temperature setting in
same ratio as a person exchanges the room location where a person is
the energy with room environment, located. This is enabled by wireless
and will show the temperature which date transfer.
a person feels. This is result of an
accurate design of size, shape and
colour of the temperature sensor.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 89
Controls

Nk`^dØ^\odjijaPkjijmm\_dj\i_rdm`_^jiomjg
Uponor radio control Uponor wired control (24 V) plished by a standard installer,
because no electrical connection is
The Uponor control system is a The Uponor control system is the needed.
complete management for under- complete management for under-
ßoor heating systems. Comfort, ßoor heating systems. The tem- The ßoor sensor can be used for
user-friendly handling and tem- perature control for each individual maximum or minimum limitation of
perature control for each room can room can be combined through the ßoor temperature, regardless of
be combined through the different the use of room thermostats wired the room temperature. For exam-
components like the remote room to the base control unit or ßoor ple, the maximum limitation can
thermostat wireless connected to temperature sensors, in the same protect a sensitive ßoor covering
the radio control unit, actuators manner like with radio controls. An from exposure to too high tempera-
wired to the base control unit and Uponor interface can be used in ture (wooden max. 55 ¡C) when
optional interface. An ergonomic order to facilitate the setting and there is a high heat demand. The
interface can be added in order to optimise the management. minimum limitation can keep a tiled
facilitate the setting and optimise ßoor warm even when there is a no
the management. Note: Installation of the wired con- general demand for heat supply to
trol system (24 V) can be accom- the room.

Pkjijm^jiomjgno\odjin
Uponor control stations are avail- Pump and shunt groups are normal- gives a possibility to be connected
able for: ly required to provide the correct to a high temperature heat source
water temperature and pressure as primary circle. The Uponor
Constant supply water tempera- in the underßoor heating system. underßoor heating system can be
ture Underßoor heating systems oper- provided with pump and shunt
Electronically controlled weather ate with a low temperature drop groups.
compensated water supply tem- and need to be adapted to different
perature heat sources and the Uponor push

1. Primary ßow connection with


thermo-electrical valve
2. Primary return connection with
return valve
3. Built-in balancing valve with
check valve
4. Outer handle for balancing valve
5. Circulation pump
6. Secondary ßow connection
7. Secondary return connection
8. Underßoor heating manifold
9. Primary pump

Available for type Ð electronically


controlled:
10. Central control unit
11. Outdoor sensor
12. Supply line sensor

Figure 5.4 Circuit diagram for Uponor Push

90 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Terminology, symbols and units

O`mhdijgjbt'nth]jgn\i_pidon
O`mhdijgjbt
Term DeÞnition
Area, heating surface Area of surface (ßoor, wall, ce iling) covered by the system between the
pipes at the outer edges of the system with the addition of a strip at each
edge of width equal to half the pipe spacing but not exceeding 0.15 m.
Characteristic curve, basic Curve or formula reßecting the relationship between the heat ßow density
and the mean differential surface temperature. This is depending on
heating and surface (ßoor/wall/ceiling) but not of the type of embedded
system.
Loop Section of system connected to a distributor which can be independently
switched and controlled.
Metabolic rate (met) Rate of energy production of the body. Note: The metabolic rate varies with
the activity. It is expressed in the met unit or in W/m; 1 met = 58.2 W/m.
One met is the energy produced per unit surface area of a sedentary person
at rest. The surface area of an average person is about 1.8 m.
Manifold Common connection point for several circuits.
Energy source Source from which useful energy can be extracted or recovered either
directly or by means of a conversion or transformation process.
Energy source, renewable Energy from a source that is not depleted by extraction, such as solar
energy (thermal and photovoltaic), wind, water power, renewed biomass.
Energy use for space heating Energy input to the heating system to satisfy the energy need for heating.
Heating medium Substance or ßuid that can be used to produce or transport heat or to
operate physical processes.
Heat ßow density Heat ßow between the space and surface divided by the heated/cooled
surface.
Heat ßow density, design Heat ßow divided by the heating surface taking into account the surface
temperature, required to reach the design thermal capacity of a surface
heated space less the thermal capacity of any supplementary heating
equipment if applicable.
Heat exchange coefÞcient The combined convective and radiant heat transfer coefÞcient between
the heated/cooled surface and the space operative temperature (design
indoor temperature).
Heating capacity, design Thermal output at design conditions of a surface heated/cooled room.
Heating medium ßow rate, design Mass ßow rate in a heating circuit which is needed to achieve the design
heat ßow density.
Insulation, clothing (clo) Resistance to sensible heat transfer provided by a clothing ensemble (i.e.
more than one garment) Note: It is described as the intrinsic insulation
from the skin to the clothing surface, not including the resistance provided
by the air layer around the clothed body and is expressed in the clo unit or
in m.K/W; 1 clo = 0.155 m.K/W.
Predicted percentage of Index that predicts the percentage of a large group of people likely to feel
dissatisÞed (PPD) thermally dissatisÞed for the body as a whole, i.e. either too warm or too
cool.
Set-back temperature Minimum internal temperature to be maintained during reduced heating
periods.
Set-point temperature of a Internal (minimum) temperature, as Þxed by the control system in normal
conditioned zone heating mode.

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 91
Terminology, symbols and units

Term DeÞnition
Temperature, average surface Average value of all surface temperatures in the occupied or peripheral
area.
Temperature, design indoor Operative temperature at the centre of the conditioned space used for
calculation of the design load and capacity.
Temperature, external Temperature of external air.
Temperature, mean radiant Uniform surface temperature of an enclosure in which an occupant would
exchange the same amount of radiant heat as in the actual non-uniform
enclosure.
Temperature, maximum surface Maximum temperature permissible for physiological reasons or building
physical , for calculation of the limit curves, which may occur at a point
on the surface (ßoor, wall, ceiling) in the occupied or peripheral area
depending on the particular usage at a temperature drop σ of heating
medium equal to 0.
Temperature, operative Uniform temperature of an enclosure in which an occupant would
exchange the same amount of heat by radiation plus convection as in the
actual non-uniform environment.
Temperature asymmetry, Difference between the plane radiant temperature of the two opposite
radiant sides of a small plane element.
Temperature difference, Logarithmically-determined average difference between the temperatures
heating medium of the heating medium and the design indoor temperature.
Temperature difference, Difference between the average surface temperature and the design
mean surface indoor temperature. It determines the heat ßow density.
Temperature difference, Air temperature difference between head and ankles of a person.
vertical air Note: 0.1 and 1.1 m for sedentary and 0.1 and 1.7 m above ßoor for
standing.
Temperature drop Difference between the supply and return temperatures of the heating
medium in a circuit.
Temperature of the Average temperature between the supply and the return temperature.
heating medium
Thermal comfort That condition of mind, which expresses satisfaction with the thermal
environment.
Thermal environment Characteristics of the environment which affect the exchange between the
human body and the environment.
Underßoor heating system, Floor (wall, ceiling) system where pipes carrying water with or without
water based additives as a medium are laid in the ßoor (wall, ceiling).
Zone, occupied That part of space designed for human occupancy and where the design
criteria are required to be met.
Zone, peripheral Surface area which is heated or cooled to a higher or lower temperature.
It is generÂally an area of 1 m maximum in width along exterior walls. It is
not an occupied area.

92 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
Terminology, symbols and units

Nth]jgn\i_pidon
Symbol Quantity Unit
AA Surface area of occupied zone m2
AF Heated area m2
AR Surface area of peripheral zone m2
B System-dependent coefÞcient W/(m2 x K)
cW speciÞc heat capacity of the water (4190 J/kg.K) J/kg x K
D, da Pipe external diameter m
ht, α Total heat exchange coefÞcient W/(m2 x K)
KH Equivalent heat transmission coefÞcient W/(m2 x K)
LHK total pipe length of the loop m
LR Calculated pipe length m
mH,sp SpeciÞc design heating ßuid mass ßow (related to the pipe covered area) kg/s
q Heat ßow density at the surface W/m2
qA Heat ßow density of occupied area W/m2
qN Nominal heat ßow density W/m2
qR Heat ßow density of peripheral area W/m2
qs,des Design heat ßow density at the surface W/m2
QBer Corrected heat demand W
QF Heat ßow of the heating system W
QH Calculated heat demand W
Æp Pressure loss, total kPa
ÆpHK Pressure loss per loop kPa
ÆpVert Pressure loss in the manifold kPa
R Pressure loos per meter kPa/m
RHC Thermal resistance from the heating medium to the heat-conducting layer m2 x K/W
Ro Partial inwards heat transmission resistance of the structure m2 x K/W
Ru Partial outwards heat transmission resistance of the structure m2 x K/W
Rλ Thermal resistance of the material m2 x K/W
Rλ,B Thermal resistance of surface covering m2 x K/W
Rλ,ins Thermal resistance of thermal insulation m2 x K/W
sh Distance from founding to the heat emission plate m
SI Distance from founding to the lowest part of the surface m
sins Thickness of the insulation m
sR Pipe wall thickness m
su Thickness of the layer above pipes m
T Pipe spacing m
U Thermal transmittance W/(m2 x K)
Uins Thermal transmittance of thermal insulation W/(m2 x K)
V Water volume in the underßoor heating pipes l
VH Volume ßow rate m3/h

U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 93
Terminology, symbols and units

Symbol Quantity Unit


Vpipe water volume in 1 m of pipe l/m
x Design supplement -
ÆθH Heating medium differential temperature K
ÆθH,g Limit of the heating medium differential temperature K
ÆθN Nominal heating medium differential temperature K
θH Heating medium temperature ¡C
θi Temperature, nominal indoor operative ¡C
θR Return temperature of heating medium ¡C
θF Temperature, ßoor heating surface ¡C
θF,max Temperature, maximum surface ¡C
θF,m Temperature, average surface ¡C
θV Supply temperature of heating medium ¡C
λ Thermal conductivity W/(m x K)
λE, λu Thermal conductivity of the screed W/(m x K)
λins Thermal conductivity of thermal insulation W/(m x K)
ρ Density kg/m3
σ Temperature drop θV - θR K
mi
Пai Power product -

<]]m`qd\odjin
Abbreviation DeÞnition
DIN German institute for standardisation
EnEV German directive for energy saving
EN European standard
EPS Expanded polystyrene
EVOH Ethyl vinyl alcohol
HD High density
HVAC Heating, ventilation and air-conditioning
ISO International organization for standardization
MLCP Multi layer composite pipe
PE-RT Polyethylene with raised temperature resistance
PE-Xa Polyethylene, cross-linked, type a
PPD Predicted percentage of dissatisÞed
PUR Polyurethane, abbreviation acc. to DIN
Q&E Quick & Easy
UFH Underßoor heating

94 U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M
U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M 95
Uponor Ð partnering with professionals

Uponor is a leading supplier of plumbing and heating systems for the


residential and commercial building markets across Europe and North
America, and a prominent supplier of municipal infrastructure pipe systems
in Europe. UponorÕs key applications are radiant heating, tap water systems
and infrastructure solutions. The Group employs 4,500 people globally. In
2007, UponorÕs net sales totalled 1.2 billion euros. Uponor Corporation is
listed on the Nordic Exchange in Helsinki, Finland.

Uponor International Sales takes care of all business activities in Western


Asia, Far East, Africa and Latin America.

Uponor. Simply more.


????? Ð 09/2008 Ð Subject to modiÞcations

Uponor Europe Ð East and International International Sales


P.O. Box 1641
97433 Hassfurt
Germany
T +49-(0)9521 690 0
F +49-(0)9521 690 750
E export@uponor-europe.com
W www.uponor.com/international
U P O N O R U N D E R F LO O R H E AT I N G H O M E C O M F O R T S Y S T E M

Вам также может понравиться