HBK-AFCONS JV

NPP0032 COMMERCIAL TERMINALS


INFRASTRUCTURE & BUILDINGS

Method Statement

Project: New Port Project

Method Statement For The Installation of UPS System.


NPP/0032 COMMERCIAL TERMINALS INFRASTRUCTURE & BUILDINGS

NPP0032
---------------------------------------------------------Doc. No: NPP0032-ELC-MS-0099_0

Re
v

Date

Modifications Content

22-02-15

First issue

Prepared by
Designation
(full name)
Vipin KP

Sr. Project Er.


(ELC)
Trans Gulf

C
D

Prepared by

Checked by

Reviewed by

Approved by

Vipin KP.

Rakesh

Bala Subramanian
(HBK-AFCONS)

Amer Sahwneh
(HBK-AFCONS)

Sr. Project Er.


(Trans Gulf)

QC (HBK)

QA/QC Manager

Project Manager

Full Name:
Designation:
Date:
Signature

NDP00100-ACM-PRO-1201-MS
15
Revision 0 24 March 2014

1/

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

CONTENT
CONTENT............................................................................................................................................................... 2
1

INTRODUCTION............................................................................................................................................ 3
1.1
1.2
1.3

ROLES AND RESPONSIBILITIES.............................................................................................................. 4


2.1
2.2

DEFINITIONS................................................................................................................................................. 6
ABBREVIATIONS............................................................................................................................................ 6
REFERENCES................................................................................................................................................ 6

RESOURCES................................................................................................................................................... 7
4.1
4.2
4.3

MAIN CONTRACTOR...................................................................................................................................... 4
SUB-CONTRACTOR........................................................................................................................................ 4

DEFINITIONS / ABBREVIATION / REFERENCES..................................................................................6


3.1
3.2
3.3

PURPOSE...................................................................................................................................................... 3
SCOPE OF WORK.......................................................................................................................................... 3
REQUIRED PERMITS....................................................................................................................................... 3

MANPOWER.................................................................................................................................................. 7
PLANT AND EQUIPMENT................................................................................................................................ 7
MATERIALS................................................................................................................................................... 8

HEALTH / SAFETY / ENVIRONMENTAL PROVISIONS........................................................................9


5.1 HEALTH AND SAFETY.................................................................................................................................... 9
5.1.1 Emergency response...................................................................................................................... 9
5.2 ENVIRONMENTAL ISSUES............................................................................................................................. 10
5.2.1 Impacts............................................................................................................................................ 11
5.2.2 Mitigation measures...................................................................................................................... 11

SEQUENCE OF WORKS............................................................................................................................ 12
6.1
6.2
6.3
6.4
6.5

AREA OF THE WORKS.................................................................................................................................. 12


PROGRAMME / TIMELINE OF THE WORKS..................................................................................................... 12
PRE-INSTALLATION CHECK:......................................................................................................................... 12
INSTALLATION:............................................................................................................................................ 13
INSPECTION:............................................................................................................................................... 13

APPENDICES............................................................................................................................................... 14

NDP00100-ACM-PRO-1201-MS
15
Revision 0 24 March 2014

2/

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

INTRODUCTION

1.1 Purpose
This method statement covers the detailed procedure for the Installation of UPS System. This
procedure defines the method used to ensure that the Installation of UPS System have been carried
out as per the contract specification requirements.

1.2

Scope of work

This method statement describes:

The procedure for Installation of UPS System at New Port Project (NPP/0032)
This method statement is subject to the requirements as stated in the following regulatory &
statutory documents, applicable standards / specifications / building codes:

Project Specifications: Section 21: Clause 23, Point 23.1-23.10


QCS-2010: Section 18 Part 18
Approved Shop Drawings
Approved Material
Latest IFC Drawings

1.3 Required permits


Permit to work system will be implemented as required from H&S department before commencing
relevant
work
on
site.
The following permits are required for the execution of this method statement:

Lifting Plan

NDP00100-ACM-PRO-1201-MS
15
Revision 0 24 March 2014

3/

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

ROLES AND RESPONSIBILITIES

2.1 Main Contractor


Designation
Project Manager (MEP)
Coordinating with sub-contractor and the Client Representative.
Delegating tasks to the Co-Ordinater (MEP) and responsibilities, coordination of the work
planning activities.

Organizing the team and coordinating with Sub-Contractor (PM).


Setting the work objectives in view
Co-Ordinater (MEP)
Coordinating with sub-contractor and the Client Representative.
Delegating tasks to the Sub Contractor Construction Manager, coordination of the work planning
activities

Setting the work objectives in view.


QA/QC Engineer
Site quality control monitoring.
Investigate the cause if NCR (non-conformity report) if any received.
Conduct surveillance and inspection duties at various stretches.
SH&E Manager
To carry out in conjunction with the Project Manager a safe work methods for all activities
involving this works

To review the actual working activities to ensure compliance with the risk assessment and
contents of this method statement

To inspect and where necessary advise Project Management and Sub-contractors on


improvements required on the condition of emergency preparedness

To organize / inspect regularly the work place to ensure that activities are being carried out in
accordance with the approved Method statement and risk assessment.

HSE Officer
Implementing project safety procedure as per approved HSE plan.
Ensuring that workforce are aware and comply with health safety & Environmental requirements

on site at all times and that all personal have been brief on safety, environment and emergency
procedures.
Ensuring that activities on site meet with the project approved H&S plan.
Identifying accidents and near misses and advising on preventive measures.
Conducting tool box talk about the work to be performing in site.
Ensuring that all equipment on site have valid third party certificates.
Responsible for implementation of project colour coding for all equipment.

2.2

Sub-Contractor

Designation
Project Manager
Coordinating with Main-contractor and the Client Representative.
NDP00100-ACM-PRO-1201-MS
15
Revision 0 24 March 2014

4/

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

Delegating tasks to the site engineers and responsibilities, coordination of the work planning
activities.
Organizing the team and coordinating with site engineer.

Setting the work objectives in view.

Construction Manager
Organizing the team.
Coordinate with the Project Engineer / Site Engineer / Safety Engineer / Foremen and Surveyor for
a safe and proper execution to accomplish the works on time as planned and with respect to
the quality of the finished works.

Project Engineer
Coordinate with Site Engineer / Site Supervisor and Foremen will ensure that the works are
carried out according to the Specifications / Drawings and this Method Statement.

QA/QC Engineer
Reports directly to Project manager.
Coordinate with site personnel, will ensure that the works are carried out as per the project
requirements. He is also responsible for the implementation of QA/QC related to works as
detailed in this procedure and for completing Quality documents for all related works.
Preparation of WIR and carrying material inspection.

Site quality control monitoring.

Site Engineer
Reporting directly to the Project Engineer.
Delegating tasks and responsibilities to the supervisory staffs.
Following up on expediting materials deliveries.
Co-ordination of the reporting activities.
Assisting the site for technical matters.
HSE Officer
Implementing project safety procedure as per approved HSE plan.
Ensuring that activities on site meet with the project approved HSE plan.
Identifying accidents and near misses and advising on preventive measures.
Conducting tool box talk about the work to be performing in site.
Ensuring that all equipment on site have valid third party certificates.
Responsible for implementation of project colour coding for all equipment.

NDP00100-ACM-PRO-1201-MS
15
Revision 0 24 March 2014

5/

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

DEFINITIONS / ABBREVIATION / REFERENCES

3.1 Definitions
An uninterruptible
power
supply,
also uninterruptible
power
source, UPS or battery/flywheel backup, is an electrical apparatus that
provides emergency power to a load when the input power source,
typically mains power, fails. A UPS is typically used to protect hardware such
as computers, data centres, telecommunication equipment or other electrical
equipment where an unexpected power disruption could cause injuries,
fatalities, serious business disruption or data loss.

UPS System

3.2 Abbreviations
New Port Project Steering Committee Client

NPPSC
PMC

Program Management Consultant

EDC

Engineering Design Consultant

HBK

Hamad Bin Khalid Co. W.L.L

PM

Project Manager

CM

Construction Manager

IFC

Issued for Construction

PQP

Project Quality plan

QA

Quality Assurance

QC

Quality Control

IR

Inspection Request

ITP

Inspection and testing plan

PPE

Personal Protection Equipment

QCS

Qatar Construction Specification

3.3 References
Document
Reference
QCS-2010
Project
Specifications
General Cargo
Terminal IFC
Drawings

Off Shore
Terminal IFC
Drawings

Document title

Project Specifications: Section 21: Clause 23, Point 23.1-23.10


QCS-2010: Section 18 Part 18

NDP00100-ACM-PRO-1201-MS
15
Revision 0 24 March 2014

9224-05-PS-EL-DRG-2090
9224-05-PS-EL-DRG-2093 to 2095
9224-05-PS-EL-DRG-2157
9224-05-PS-EL-DRG-2160 to 2162
9224-05-AL-EL-DRG-2174
9224-05-AL-EL-DRG-2901
9224-05-PS-EL-DRG-2490
9224-05-PS-EL-DRG-2493 to 2495
9224-05-PS-EL-DRG-2557
9224-05-PS-EL-DRG-2560 to 2562
9224-05-AL-EL-DRG-2850 & 2851
9224-05-AL-EL-DRG-2911
9224-05-AL-EL-DRG-2912
9224-05-AL-EL-DRG-2913
6/

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project


Multi Use
Terminal IFC
Drawings

NDP00100-ACM-PRO-1201-MS
15
Revision 0 24 March 2014

9224-05-AL-EL-DRG-2480
9224-05-PS-EL-DRG-2870
9224-05-PS-EL-DRG-2873 to 2875
9224-05-AL-EL-DRG-2920

7/

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

RESOURCES

4.1 Manpower
Item

Description

Number

Site engineer

Safety Officer

Foreman/Supervisor

QA/QC Engineer

Electrician

Labour

Remarks

Plant and equipment

4.2

The following equipments and materials will be used for the works:
Item

Key equipment

No.

Electrician tool box

Portable Hand Tools

As
require
d

Measuring Tape

Insulation Tester

Ladder

Pallet Trolley

Note:

The availability and validity of registration, insurances and 3rd Party fitness certificates of
plant, operator and equipment and its physical condition should be checked by Safety officer.
Mechanical maintenance team should inspect thoroughly the plant or equipment before its
use on site that all are operational as per manufacturers specification and standards.
In case Step ladder required it will using only for the short duration 5-10 minutes.

4.3 Materials
Item

Material

No.

UPS with all accessories ,


enclosure , mounting bracket
etc.f

As per
B.O.Q

Danger Boards

Note: All Material estimated quantities are subject to design. It may change during actual
installation.

NDP00100-ACM-PRO-1201-MS
15
Revision 0 24 March 2014

8/

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

HEALTH / SAFETY / ENVIRONMENTAL PROVISIONS

5.1 Health and Safety


The health and safety activities are to be in accordance with the relevant Health, Safety and
Environmental requirements as described, but not limited to, within the guidelines for Method
Statement.
Ensure that every one Use the Mandatory and appropriate PPEs for performing the each type
of work.
First-Aid kit must be available in the work area. Minimum Personnel in the area while
operations are been carried out. At the start of each work shift for any relevant activity on
hand, the Daily pre start talks and Safe working instructions 1- 2 times per week will be done
on site. Please refer the Approved Health and Safety plan.

*Please refer to the separate document NPP0032-ELC-RA-0072 for the Risk Assessment for this
method statement.

5.1.1 Emergency response


In case any accident causing injury to personnel, the male nurse will be immediately notified
and he will come to the spot with necessary medicines & equipments, to administer
treatment. The Safety Supervisor or any other supervisor or foreman, who is certified in first
aid, will give first aid treatment till the arrival of the nurse. If the injury is of serious nature,
the injured person will be transferred to hospital in ambulance on call.
For further details refer NPP/0032 Project Health and Safety Plan Doc. No: NPP0032-HSHSP-0001
Summer Plan

The following arrangements will be taken as precautions for hot weather in the work area. The
precautionary measured includes,
Comply with Qatar Regulation regarding Summer Working Hours.
All people to attend heat stress training (to identify symptoms to look out for, urine test, safe
work practices, emergency procedures)
STARRT conducted and/or RAMS discussed to all persons involved in the task prior to works
commencing.
Ensure to regularly check the heat/humidity index, measure of humidity levels and adjust the
work/rest cycles accordingly.
Provision of insulated flasks to all operatives to be filled with cool water.
Provision of adequate and regular supply of cool drinking water. Also, encourage operatives
to drink a cup of water (200ml) every 10 to 15 minutes subject to the heat/humidity index
chart
Job rotation among operative to reduced exposure time.
No lone working is allowed.
If possible, work area to be shade.
Gas bottles to be shaded at all times.
Provision of shaded rest areas with suitable seating arrangements.
Provision of periodic rest breaks and rest facilities in cool conditions.
Use of PPE and light clothing that permits the evaporation of sweat should be wear (e.g.,
cotton clothing). Use sunscreen and cover your head when working outside.
Adoption of heat/humidity flag system across the site.
Flammable chemicals that react in high temperatures must be used under strict controls and
used during the cooler part of the days only

NDP00100-ACM-PRO-1201-MS
15
Revision 0 24 March 2014

9/

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

Close monitoring all staff working outside or in tanks/structures where temperature rise
could be significant.
Conduct regular workers physical assessment.
Trained, Competent and Authorized Supervision present at all times to monitor and guide
employees.

Use of power tools


Trained, Competent and Authorized operatives are allowed to use power tools
Qualified, Competent and Authorized electricians to test all portable electrical equipment at
recommended regular intervals
Employee conducts daily inspections of power tools (including electrical cords) before
operation and where faults are identified that require immediate maintenance the tool is put
out of service until maintenance is conducted by a Trained, Competent and Authorized
person
All power feeds, electrical, pneumatic or hydraulic, to comply with Qatar National Standards
and maintained in good condition
Ensure that the power tool has the correct guard, shield or other attachment that the
manufacturer recommends. Ensure all electrical distribution boards are fitted with ELCB and
this is regularly tested to evaluate if it is working safely or not with immediate rectification of
all faults
STARRT and/or RAMS discussed to all persons involved in the task prior to works
commencing
Ensure power tools have appropriate earthling.

Night shift Activity.

The following arrangements will be taken as precautions for Night shift activity in the work
area. The precautionary measured includes,
Proper and sufficient lightings to be provided in all areas of work and access and egress
areas (as a minimum 150 lux).
Stroboscopic effects to be avoided while providing lightings.
All work areas must be well lit, without shadow reflecting vest must be worn. No lone
working to be permitted, prior approval must be obtained before working at night.
Lighting for vehicles must be in good order& all Access must be well lit and free from
obstructions.
Regular inspections of lights by qualified, competent and authorized electricians and tags or
inspection stickers /color code provided on each fixture.
Do not use halide or halogen lighting inside Confined Spaces or Restricted Areas where
employees could come into contact with them or fires may occur.

First aid Provision


Suitable arrangements must be made at site for First-Aid in emergency conditions. There must
be an approved first aid kit available at site. All the personnel will be made aware of
emergency condition by conducting suitable mock-drills at the site. First Aid box should be
kept at site.

5.2 Environmental issues


The activities for environmental preservation through mitigation are to be in accordance with
the CEMP.
Environmental aspects during the UPS Installation are as follows
a) Air Emissions and Dust Generation
b) Noise

NDP00100-ACM-PRO-1201-MS
10/ 15
Revision 0 24 March 2014

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project


Specific management plan have been detailed in the MoE approved Construction
Environment Management Plan (CEMP) for above referred Environmental Aspects.
However, to ensure the environmental management requirements are considered and
controls implemented such as at the present case the following specific Environmental
Management Plan (EMP) will be implemented.

5.2.1 Impacts
The possible impacts are as follows,
a.
b.

Air Emissions and Dust Generation Pollute the atmospheric air


Noise major hearing problems to the workers

5.2.2 Mitigation measures


The mitigation measures are to specifically address the identified environmental impacts, in
addition to and not limited to, the items as described within the guidelines for method statement.
EMP for Air Emissions & Dust Generation:

Minimize vehicular movements and implement speed control.

Periodic water sprinkling for dust suppression at and around work area to minimize
airborne dust.
EMP for Noise:

Ensure field equipment maintenance team undertakes schedule preventive maintenance


and replacement of worm out components to minimize noise pollution.

NDP00100-ACM-PRO-1201-MS
11/ 15
Revision 0 24 March 2014

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

SEQUENCE OF WORKS

6.1 Area of the works


Works will be carried out at General Cargo Terminal / Off Shore Terminal / Multi Use Terminal.

6.2

Programme / Timeline of the works

Pre-Installation Check.
Installation
Inspection

6.3 Pre-Installation Check:


All safety requirements are in place in accordance with project safety plan.
It will be ensured that the correct revision of the approved shop drawing is being used. The
latest drawing will be issued to the concerned Engineer and the superseded drawing will be
surrendered to the Quality Dept. Note that any areas on the drawing are subject to revision;
work will not proceed in these areas until an updated drawing has been issued. Any
deviation from IFC drawings will be intimated to the engineer for approval.
Ensure that all materials used have passed receiving inspection in accordance with QA
procedures and are not damaged or defective. Any non-conforming materials will be labeled
by store keeper and returned to quarantine area in accordance with procedure.
Ensure that competent & trained electricians will do the installation/jointing/ termination to
ensure best quality of workmanship. Tool box talk & Training will be provided by Site Engineer
as and when required. Electrician certificate will be provided before any works start at site.
Ensure the works are carried out in accordance with manufacturers installation
recommendations/Guidance and in the presence of manufacturer / vendor/ experienced
engineer or representative.
Do not place the equipment in the presence of flammable gases or fumes. Operation of any
electrical equipment in such an environment constitutes a safety hazard. Do not place the
UPS in an airtight room. The UPS system must be installed according to the instructions in
the manual. Installation may be performed by qualified personnel only. Failure to recognise
the electrical hazards could prove fatal.
Because of the high energy stored within the batteries, the UPS equipment must be handled
with care. The UPS must always be kept in the position marked on the package and must not
be dropped.
If the UPS is not immediately installed the following must be remembered:
The UPS should be stored in the original packing and shipping carton.
The recommended storing temperature is between +15C ... +25C.
The equipment must always be protected from moisture and weather.
Unpack the equipment and remove all the packing materials and shipping cartons. The
equipment must be inspected for damage during shipment. If damage has occurred during
transit, all the shipping cartons and packing materials should be stored for further
investigation.

NDP00100-ACM-PRO-1201-MS
12/ 15
Revision 0 24 March 2014

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

6.4 Installation:
Note the following points when setting up the UPS system and its external battery units
(special accessories):
The contact surface must be smooth and in level. It must also be sufficiently strong and
sturdy to avoid vibration
and shock loads.
Make sure the mounting is able to support the weight: This is particularly important in
conjunction with external
Battery units.
Set up the units so that adequate air circulation is assured. There must be at least 100 mm
clearance at the
Back for ventilation purposes. Do not block the intake openings on the front and, if present,
on the side of the
Unit. There must be a gap of at least 50 mm here.
Set up external battery units on the side of the UPS system. To ensure the greatest possible
Mechanical stability, User should not set up the external battery unit(s) above or below the
UPS system.
Protect the units against external effects (in particular moisture and dust).
If you transport the unit from a cold room into a warm one, or if the room temperature
suddenly drops then condensation may form inside the unit. To avoid any damage due to
condensation, leave the unit to acclimatize for 2 hours before you switch it on.
If optional external battery cabinets will be connected to the UPS, take out the spacers
shipped with the battery cabinet.
Adjust the direction of the operation and display panel.
Please refer user manual for Cable Selection. Choice of the diameter and cross section of
conductors depend on the rated power of UPS, the installation and local regulations.
Steps to be follow:
Choose appropriate cables for input and output.
Remove the terminal block cover in the rear panel.
Connect the load to the output of the terminal block.
Connect the input power cable to the input of the terminal block. On selected models
connect the external battery cables. Secure the cables to the cable clamps.
Put the cover board back to the UPS and tighten the screws.
Before the input protection switch is being set in the ON position, supply power source to
the UPS.
Connecting to the Computer interface Computer interface: standard RS232 communication
port, use a RS232 cable to connect the UPS with the computer.
Raise Inspection after Installation of UPS for Client/ Consultant Approval.

NDP00100-ACM-PRO-1201-MS
13/ 15
Revision 0 24 March 2014

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

6.5 Inspection:
The IR will be submitted for the installation of UPS System as per the inspection and test plan
for various aspects described to be checked. The concerned Project Engineer and Site
Engineer will be responsible to ensure stage wise compliance for the above operations and site
QA/QC Engineer/Inspectors of M/s HBK & M/s TGIEM will carry out the internal inspections prior
to forwarding inspection request to consultant. Please refer the inspection and test plan no.
NPP0032-ELC-ITP-099_0 for this method statement.

NDP00100-ACM-PRO-1201-MS
14/ 15
Revision 0 24 March 2014

HBK-AFCONS JV

COMMERCIAL TERMINALS
Method
INFRASTRUCTURE & BUILDINGS

Statement

Project: New Port Project

APPENDICES

Appendix Title

Reference

Inspection & Test Plan (ITP)

NPP0032-ELC-ITP0099_0

Check List

NPP0032-ELC-QCC0099_0

Risk Assessment

NPP0032-ELC-RA0099_0

D
E
F
G
H
etc

NDP00100-ACM-PRO-1201-MS
15/ 15
Revision 0 24 March 2014