Академический Документы
Профессиональный Документы
Культура Документы
Rev
Date
Description
1999
Checked
Approved
DL
GES D.04
Page 2 of 22
Rev 0 1999
INDEX
SECTION
TITLE
1.0
SCOPE OF SPECIFICATION
1.1
1.2
Introduction
Other NOC Specifications
4
4
2.0
DEFINITIONS
2.1
2.2
Technical
Contractual
5
6
3.0
DESIGN
3.1
3.2
6
7
4.0
MATERIALS
10
4.1
4.2
Materials of Construction
Chemical Composition
10
11
5.0
FABRICATION/ERECTION
11
5.1
5.2
Introduction
Procedures
11
12
6.0
TOLERANCES
14
6.1
6.2
6.3
Fabrication
Curvature
Roundness
14
14
14
7.0
INSPECTION
14
7.1
7.2
Procedures
Methods
14
15
8.0
TESTING
17
8.1
8.2
8.3
Statutory Testing
Test Procedures
Nameplates
17
17
19
SECTION
TITLE
PAGE
PAGE
GES D.04
Page 3 of 22
Rev 0 1999
9.0
DOCUMENTATION
19
9.1
9.2
9.3
9.4
9.5
9.6
Introduction
Schedules/Reports
Data and Calculations
Drawings
Other Documents
Manuals
19
19
19
20
20
21
10.0
PRIOR TO SHIPMENT
21
10.1
10.2
10.3
10.4
10.5
21
21
21
22
22
DATA SHEETS
Tank Data Sheet (4 sheets)
GES D.04
Page 4 of 22
Rev 0 1999
1.0
SCOPE OF SPECIFICATION
1.1
Introduction
1.1.1
This specification covers the minimum requirements for design, materials, fabrication and erection,
inspection and testing of large, welded, low pressure carbon steel above-ground storage tanks.
1.1.2
These storage tanks shall be designed, fabricated, erected, inspected and tested in accordance with API
620, plus the additional requirements of this specification.
1.1.3
The tanks covered by this specification are designed for metal temperatures not greater than 250F
(120C) and with pressure in the gas or vapour space up to 15 psig (103 kPag).
1.1.4
1.1.5
This specification applies to equipment for refineries, onshore oil and gas, installations and processing
facilities.
1.1.6
The Purchase Order/Contract will state that the tanks will be purchased either by:
(a) Owner buying tank materials and a local Contractor carrying out the erection, or
(b) local Contractor carrying out procurement and erection.
1.1.7
1.1.8
The Vendor/Contractor shall comply fully with the provisions laid down in this specification. Any
exception must be authorised in writing by the Owner.
1.1.9
In the event of any conflict between this specification and the applicable codes and standards, the
Vendor/Contractor shall inform the Owner in writing and receive written clarification before
proceeding with the work.
1.1.10
The tank foundations will be provided by the Vendor/Contractor responsible for the erection of the
tanks.
1.1.11
This General Engineering Specification will form part of the Purchase Order/Contract.
1.2
GES W.01
GES W.02
GES X.01
GES X.02
GES X.03
2.0
DEFINITIONS
2.1
Technical
GES D.04
Page 5 of 22
Rev 0 1999
GES D.04
Page 6 of 22
Rev 0 1999
Contractual
The commercial terms used in this specification are defined as follows:
2.2.1
Owner
The oil or gas company, an associate or subsidiary, who is the end user of the equipment and facilities.
2.2.2
Vendor
The company supplying the equipment and material.
2.2.3
Contractor
The main Contractor for a defined piece of work
2.2.4
Sub-Contractor
A company awarded a contract by the Contractor to do part of the work awarded to the Contractor.
2.2.5
Inspection Authority
The organisation representing the Owner or Vendor/Contractor that verifies that the equipment and
facilities have been designed, constructed, inspected and tested in accordance with the requirements of
this specification and the Purchase Order/Contract.
2.2.6
Inspector
A qualified individual representing the Owner, Vendor/Contractor or the assigned Inspection
Authority, who verifies that the equipment and facilities have been designed, constructed, inspected
and tested in accordance with the requirements of this specification and the Purchase Order/Contract.
3.0
DESIGN
3.1
3.1.1
The design and construction of storage tanks shall comply with this specification as well as with codes,
standards and provisions indicated on the data sheets provided by the Owner.
3.1.2
The following codes and standards shall be used in conjunction with this document, as specified by the
Owner.
ASME - American Society of Mechanical Engineers
ASME Boiler and Pressure Vessel Code
Section II
Section IIC
Section IID
Section V
Section VIII
Section IX
ASME B16.5 ASME B16.9 ASME B16.11
ASME B16.20
GES D.04
Page 7 of 22
Rev 0 1999
Safety Requirements for Floor and Wall Openings, Railings and Toe Boards
3.2.1
Corrosion Allowance
(a) Minimum corrosion allowance for tank components constructed from carbon steel shall be 1/16"
(1.5 mm) in sweet service and _" (3 mm) in sour and corrosive service.
(b) The design diameter of anchor bolts and the design thickness of holding down straps, shall be
increased in all cases by _" (3 mm) as corrosion allowance.
(c) Sacrificial anodes shall be provided to protect the inside wetted areas of the tank. The
composition of the anodes shall be compatible with the fluids and any corrosion inhibitor
proposed by the Owner.
3.2.2
Design Loads
(a) Design loading of the tank shall take into account cyclic operations, erection and test loadings.
(b) During erection, start-up or operation, all applicable loads shall be considered as acting
simultaneously.
(c) During hydrostatic testing, wind load (wind pressure) equivalent to a 35 mph (16 m/s) wind
velocity shall be considered acting simultaneously with the hydrostatic test load.
(d) Roof live load shall not be less than 25 lb/sq ft (1.2 kPa) applied over the projected roof area.
3.2.3
Design Stress
(a) The allowable design stress shall be in accordance with API 620.
3.2.4
> to _
> _ to 1
> 1
12.5
GES D.04
Page 8 of 22
Rev 0 1999
mm
in
mm
> 12.5-22
> 22-32
> 32
/16
_
7
/16
6
8
9.5
11
Bottom plates shall be a minimum nominal thickness of " (6 mm) and shall be square edged.
3.2.5
GES D.04
Page 9 of 22
Rev 0 1999
The type of end termination, elevation, orientation and location will be specified, where necessary, to
match the Owner's mating piping connections.
3.2.6
(d) Guard railings and toe plates shall enclose all product nozzle, pressure relief device and instrument
attachments located on the top of the tank.
(e) Platform flooring shall be steel grating.
(f) Any pipe used as handrailing shall be seal-welded to avoid internal corrosion.
(g) Railing and toe plates shall be carbon steel and per ANSI A12.1.
3.2.7
3.2.8
Instrumentation
(a) Where instruments are to be supplied by the Vendor/Contractor, the Vendor/Contractor shall
submit with the tender documents the manufacture and model type of all instruments for approval
by the Owner.
3.2.9
3.2.10
Fire-fighting Facilities
(a) For fire-fighting facilities refer to GES H.07.
GES D.04
Page 10 of 22
Rev 0 1999
(b) The tank Vendor/Contractor shall furnish and install firewater deluge system and components,
terminating at the laterals at the base of the tank.
3.2.11
4.0
MATERIALS
4.1
Materials of Construction
Materials shall be in accordance with API 620 and the additional requirements of this specification.
4.1.1
A complete material specification shall be submitted with the Vendor/Contractor's bid proposal.
4.1.2
Annular plates shall be of the same material specification and grade as the lowest shell course.
4.1.3
Pipe and formed plate used for nozzles, manhole necks and flush-type clean-out fitting assemblies shall
comply with the following table:
MATERIAL
LIMITATION
MATERIAL SPECIFICATION
SEAMLESS
Pipe
Formed Plate
4.1.4
WELDED
Attachment to steel
having a yield strength <
43,000 psi (296 MPa)
Not permitted
Attachment to steel
having a yield strength >
43,000 psi (296 MPa)
ASTM A 106
GrB or C
Not permitted
If impact testing is required by API 620, tests shall be conducted per ASTM E23 using the Charpy Vee
(Type A), specimens shall be taken per ASTM A370 for plate materials, and per ASTM A333 for pipe
materials.
GES D.04
Page 11 of 22
Rev 0 1999
Materials for permanent structural attachments, welded to the shell, shall be of the same nominal
composition.
4.1.6
4.2
Chemical Composition
4.2.1
The carbon equivalent of carbon steel plate used for the tank shell, shell nozzles, annular plates and
bottom plates, as defined by the equation below, shall meet the following limits:
Carbon Equivalent (CE) is:
CE = C + (Mn)/6 + (Cr+Mo+V)/5 + (Ni+Cu)/15 = 0.45%
C = 0.28% max
All elements shall be determined for each heat of material.
5.0
FABRICATION/ERECTION
5.1
Introduction
Fabrication and erection shall comply with the requirements of API 620 code, and the additional
requirements of this specification.
No fabrication shall commence until complete material certification has been received and written
approval of shop drawings, calculations, weld procedures plus welder performance qualifications
has been received by the Vendor/Contractor.
Approval of material certificates and welder qualification certificates are the responsibility of the
Owner's Inspector and/or the Inspection Authority.
Approval of the tank drawings, calculations and weld procedure are the responsibility of the Owner.
The Vendor/Contractor shall notify the Owner of the proposed starting date of actual fabrication.
Tank Vendor/Contractor shall provide erection tools for the Owner or his Contractor to erect and weld
the tank.
Procedures
5.2.1
GES D.04
Page 12 of 22
Rev 0 1999
Carbon and carbon manganese steels may be cut to size, and bevelled by thermal or mechanical
methods consistent with accepted practice.
5.2.2
impact tests shall be made on the weld metal and the HAZ;
impact tests shall be conducted at the design metal temperature;
impact specimens of the weld metal and HAZ shall be taken per API 620.
Welding procedure qualification test welds shall be carried out under conditions simulating the worst
access and environmental conditions expected during production welding.
5.2.3
5.2.4
5.2.5
GES D.04
Page 13 of 22
Rev 0 1999
5.2.7
Welding
(a) Holes shall not be made in shell plate for erection purposes.
(b) All shell joints shall be complete penetration and complete fusion welds.
(c) The shell to annular plate joint shall be a complete penetration complete fusion weld, or double
fillet `T'. If the `T' joint is used, the fillets shall be made with a minimum of 2passes, and the minimum size of fillet shall be equal to the annular plate thickness.
Tack welds for shell-to-bottom fillet welds, if used, shall be removed prior to
welding fillets.
(d) Annular plates shall be butt-welded with complete penetration and complete fusion.
(e) Bottom plates shall be 2-pass fillet welded to develop a minimum joint efficiency of 70%.
(f) The qualification procedure for bottom fillet weld shall be:
-
using the same type of electrode (same manufacturer's designation), plate (same material
and thickness) and weld procedures, as will be used for the bottom, two linear feet
(600 mm) of lap weld shall be made;
three 3" x 18" (75 x 450 mm) tensile test strips shall be cut from this weld and tested at
the design metal temperature. The maximum breaking load of the strips shall be at least
70% of the specified or guaranteed minimum tensile strength of the unwelded plate at test
temperature. Weld failure shall be at least 95% shear fracture;
three cross sections of the weldment shall be polished and etched sufficiently to show the
weld's penetration into the base material. Complete fusion shall exist throughout each
cross section. If the first pass destroys the vertical edge of the lap weld, a minimum of
3
/32" peak penetration into the bottom plate shall be shown.
(g) Attachment welds for tank anchors, shell stiffeners, insulation supports, stairway clips, pipe
supports and similar components shall be continuously fillet welded.
(h) Radial buttwelds between shell stiffener sections shall terminate approximately " (13 mm) from
the tank shell.
(i) Single pass buttwelds and multiple pass electrogas, or electroslag vertical buttwelds are not
permitted.
(j) Weld undercuts and excessive weld metal build-up which creates steep angles at corners of fillet
welds shall be repaired.
(k) Mechanical caulking shall not be permitted.
(l) The roof shall not have depressions that will permit accumulation of water.
(m) Hardness of hot formed sections and of weld metal, and the related heat affected zone (HAZ) of all
welds, shall not exceed 225 Brinell for P1 materials. ("P" numbers are defined in ASME Boiler
GES D.04
Page 14 of 22
Rev 0 1999
TOLERANCES
Tolerance shall be in accordance with the API 620 Standard and the following additional requirements.
6.1
Fabrication
Shell plates shall have dimensional tolerances as follows:
Dimension
Tolerance
Length
Width
Difference in Diagonals
6.2
in
mm
1/16
1/16
_
1.5
1.5
3.0
Curvature
The tolerance for peaking and banding of shell plates is " (6 mm).
6.3
Roundness
The radius of the shell measured at 12" (300 mm) above the bottom corner weld shall be within the
following tolerances which represent deviation from the average radius:
Tank Diameter
Tolerance on Radius
ft
in
mm
< 120
120 to 210
> 210
< 36
36 to 64
> 64
1
1
13
25
38
The circumference shall be no smaller than the theoretical circumference for the specified diameter.
The maximum permissible out-of-plumb of any single course, exclusive of banding effects, shall be "
(6 mm).
7.0
INSPECTION
7.1
Procedures
7.1.1
All items of plant and equipment referenced within this specification shall be subject to inspection by
the Owner or his nominated Inspection Authority.
GES D.04
Page 15 of 22
Rev 0 1999
7.1.2
Inspection shall be in accordance with API 620 code and this specification. All inspection activities,
including any special requirements, shall be agreed with the Owner and shall be incorporated within
the agreed Quality Control Plan provided by the Vendor/Contractor.
7.1.3
All operators of NDE equipment shall have thorough knowledge of the operation of the equipment to
be used and shall hold an appropriate certificate of competence which is to be approved by the Owner.
All NDE procedures and qualifications shall be subject to approved by the Owner.
Approval of all NDE records are the responsibility of the Owner's Inspector at the
Vendor's/Contractor's works or construction site.
7.1.4
Any approvals given by the Inspector does not relieve the Vendor/Contractor of any responsibility
regarding guarantees, workmanship or compliance with the code and this specification.
7.1.5
The Vendor/Contractor shall furnish the Inspector with all reasonable facilities to satisfy themselves
that the equipment is fabricated and tested in accordance with the relevant code and this specification.
The Vendor/Contractor shall afford the Inspector the opportunity to witness all or some of the
following quality control checks. The details shall be agreed mutually between the Inspector and the
Vendor/Contractor, prior to the commencement of fabrication.
(a) Welding procedure and operator qualification work,
(b) Examination of rolled and welded shells,
(c) Identification of materials against Mill Test Certificates and impact tests,
(d) Welding examination,
(e) Examination of radiographic film,
(f) Internal and external examination of tanks,
(g) Pressure tests,
(h) Final dimensional check (inc. peaking and banding),
(i) Examination after cleaning,
(j) Examination after painting, if specified,
(k) Verification of code nameplate details,
(l) Review and signature of Vendor's/Contractor's dossiers.
7.2
Methods
Inspection shall be in accordance with API 620 and the additional requirements of this specification.
7.2.1
Shop Inspection
Shop inspection shall be made of the following tankage and components.
Shell plates may be inspected at the tank fabrications shop or the mill, or both, by the Owner's
Inspector. Inspection includes witnessing tests of physical properties.
GES D.04
Page 16 of 22
Rev 0 1999
Manholes, nozzles and flush-type clean-out fittings shop welded into a tank plate or reinforcing pad,
shall be inspected by the Owner's Inspector at the tank fabricator's shop.
7.2.2
Visual Inspection
Final inspection shall be carried out after the removal of all mill scale, dirt, grit, weld spatter, paint, oil
or other foreign matter from the tanks.
It is the Vendor's/Contractor's responsibility to offer the tanks in a suitable condition for the Inspector's
examinations, including the provision of scaffolding/ladders when required.
7.2.3
the gap between the bottom shell ring and the lap welded bottom plates at radial weld
location shall be a maximum of _" (3 mm).
(c) All bottom plate joints shall be vacuum tested using a vacuum box and soap suds solution.
7.2.4
for shell plates over _" (22 mm), vertical joints shall be fully radiographed;
for shell plates _" (22 mm) or less, one spot radiograph shall be taken for every 50 ft
(15.25 m) of weld, and at all junctions of vertical and horizontal joints at a location
selected by the Inspector;
if submerged arc machine welding is used, the first 3 ft (0.9m) of complete weld made by
each machine for each tank shall be 100% radiographed;
if electro-gas welding is used, the first 8 ft (2.4 m) of completed weld made by each
machine shall be fully radiographed, and all starts and stops in the welded joints shall be
radiographed;
quality control shall be done progressively throughout the job.
(b) For high strength tank steels, and for tanks with a product of specific gravity greater than 1.0
radiographic requirements shall be the same as for low strength tank steels, except that all vertical
seams shall be 100% radiographed.
(c) Reference markers, on each film, shall include the tank and seam numbers. Each film shall have at
least two reference markers indicating the correct location of the film on the weld.
(d) Radiograph film length shall be 10" (254 mm) minimum, or the full length of the weld if less than
10" (254mm).
7.2.5
GES D.04
Page 17 of 22
Rev 0 1999
8.0
TESTING
8.1
Statutory Testing
8.1.1
The Vendor/Contractor shall conduct the hydraulic test on the tank in accordance with API 620 and
this specification.
8.1.2
The tests shall be carried out in the presence of the Owner's Inspector.
8.1.3
Prior to testing the Vendor/Contractor shall submit his test procedure in writing to the Owner for
approval.
8.1.4
The hydrostatic test shall not produce a stress in the bottom shell course greater than 90% of the
specified yield stress at room temperature.
8.2
Test Procedures
8.2.1
Prior to carrying out the hydrostatic test, all backing and reinforcement plates shall be leak tested using
air via a tell-tale hole and soap and water.
8.2.2
No type of preservative or paint shall be allowed to cover any joint, mechanical or welded, before the
test is complete.
8.2.3
GES D.04
Page 18 of 22
Rev 0 1999
Filling
The water filling rate for testing shall not exceed the following:
BOTTOM COURSE
THICKNESS
in
mm
<_
22
8.2.5
TANK PORTION
FILLING RATE
in/hr
22
mm/hr
Top course
Below top course
12
18
300
450
Top third
Middle third
Below Third
9
12
18
225
300
450
Settlement Measurements
Shell and bottom settlement measurements shall be made by the Vendor/Contractor per
the following:
(a)
Shell settlement measurements shall be made after tank erection, prior to
hydrostatic testing and during water filling at the , and full levels corresponding to design
liquid height. Level readings shall be accurate to within 1/16" ( 1.5 mm). The minimum
number of measurement locations shall be given below:
Tank Diameter
ft
m
46
> 46
< 150
> 150 to 225
16
24
32
48
to 69
> 225 to 325
> 69
to 99
> 325
> 99
(b)
Bottom internal measurements shall be made after hydrostatic testing. Such
measurements shall be made at 10 ft (30 m) spacing from the centre on the radius, and the
following:
Tank Diameter
ft
150
> 150 to 225
> 225 to 325
> 325
m
46
> 46 to 69
> 69 to 99
> 99
Number of
Diameter
Axes
4
6
8
10
GES D.04
Page 19 of 22
Rev 0 1999
location and extent of depressions shall be indicated on the tank bottom plate layout drawing.
A full report of settlement measurements and tank bottom depressions shall be made
together with the results of the hydrostatic test including leakage rates.
8.3
Nameplates
8.3.1
8.3.2
The nameplate shall be of stainless steel stamped or engraved with the required information.
9.0
DOCUMENTATION
9.1
Introduction
9.1.1
9.2
9.2.1
9.2.2
9.2.3
9.3
9.3.1
This section covers the documentation requirements for the design, materials, fabrication,
inspection and testing.
Schedules/Reports
For each tank, the Vendor/Contractor shall supply with the tender, a schedule showing submission
of all documents for review and approval, proposed sub-contractors and material procurement and a
production/erection programme.
The Vendor/Contractor shall submit with the tender a Quality Control Plan for the contract.
After the Purchase Order/Contract award, monthly reports on design, material procurement and
production progress shall be submitted to the Owner.
Data and Calculations
For each tank, the manufacturer shall supply with the tender, a completed Tank Data Sheet
containing all the relevant information necessary for appraisal of the mechanical design by the Owner.
Also included shall be any additional drawings, specifications, etc and a list of any proposed
subcontractors.
The documents shall be submitted for approval/review to the Owner and to the Inspection
Authority within the periods agreed between the Owner and Vendor/Contractor. It shall be the
responsibility of the Vendor/Contractor to ensure that the production schedule of the tank takes into
account documentation submission periods, plus a three week approval review period by the Owner
and/or the Inspection Authority.
The Vendor/Contractor shall be responsible for obtaining approvals from the Inspection
Authority.
9.3.2
All calculations shall be carried out in a clear and logical manner. Where conditions involve the
use of formulae or methods not specified in the design code, the source of these formulae or methods
shall be clearly referenced.
Computer calculations will only be accepted if all input is shown, together with
calculated values of intermediate terms and factors and options chosen, as well as final calculated
dimensions, stresses or other values. The computer program shall be validated to the satisfaction of the
Owner.
GES D.04
Page 20 of 22
Rev 0 1999
Drawings
9.4.1
The following drawings listed in paragraph 9.4.2 to 9.4.5 shall be sent by the tank
Vendor/Contractor to the Owner and/or the Inspection Authority for review and approval.
9.4.2
The plating drawings, shall as a minimum, show the position of all through thickness welds,
together with material thicknesses and specifications. In addition, it shall clearly indicate the welding
procedure specification which is applicable to each weld. The plating drawing may be combined with
the general arrangement drawing, provided that this drawing clearly indicates the same information.
9.4.3
General arrangement drawings shall show the relative location and main dimensions of all
components including elevations and orientations of nozzles.
In addition, the following information shall be included on the assembly drawings:
-
nozzle schedule,
list of related drawings and procedures,
operating conditions,
design conditions,
corrosion allowance,
hydrotest,
NDE requirements,
design code and main standards/specifications,
weight, empty, operating, full of water,
painting requirements,
general notes covering specified requirements,
mechanical loading conditions (e.g. nozzle loads, wind, etc).
9.4.4
Detail drawings which may be included on the general arrangement shall include thicknesses and
dimensions of all components, weld details, machining and surface finish requirements, gasket and
nameplate details.
9.4.5
As-built drawings may be the general arrangement drawings marked-up with the actual as-built
dimensions.
9.4.6
Drawing sizes shall conform to ISO Standard A1 to A4. All drawings shall be suitable for
microfilming on 35 mm film mounted in aperture cards. Where drawings are CAD generated, two (2)
sets of copy disks shall be supplied.
9.5
Other Documents
9.5.1
Previously qualified weld procedure may be proposed by the Vendor/Contractor, provided all
welding and testing was witnessed by an independent third party and are supported by evidence of
successful previous application. Evidence shall be in the form of quality records of previous
applications.
9.5.2
NDE procedures shall include the general procedure to be utilised for each type of NDE
employed, together with detailed technique sheets for each applicable joint configuration proposed for
each vessel.
9.5.3
Deviations from the requirements of the Owner's specification shall be technically justified and
have the written approval of the Owner.
Manuals
9.6.1
Data Book
GES D.04
Page 21 of 22
Rev 0 1999
On completion of fabrication, the Vendor/Contractor shall submit to the Owner, two (2)
copies of the Tank Data Book. They shall contain the following:
-
9.6.2
The Vendor/Contractor shall supply the Owner one set of reproducible original drawings.
10.0
PRIOR TO SHIPMENT
10.1
10.1.1
Surface preparation, painting and painting materials shall be in accordance with GES X.01, GES X.02
and GES X.03.
10.1.2
Shop prefabricated plates intended for site welding shall be left with a 2" (50 mm) margin, unprimed.
10.1.3
With the written agreement from the Owner, the unprimed margins may be protected for transport,
prior to site welding, by a special weld preparation coating or a weldable prefabrication primer.
10.2
Spares
The Vendor/Contractor shall submit with his proposal a priced list of recommended
spares for start-up and two years normal operation.
10.3
Packing/Storage
10.3.1
This section describes the minimum requirement for the preservation and protection of the equipment
during transportation and storage, prior to unpacking.
10.3.2
The probable storage period will be specified in the Purchase Order/Contract and shall extend from the
time of despatch to the time of unpacking at site. If the storage period is not stated, a minimum period
of 24 months shall be assumed. All packing shall be suitable for sea freight.
10.3.3
GES D.04
Page 22 of 22
Rev 0 1999
The Vendor/Contractor shall be responsible for loading and anchoring the items
to prevent damage during shipment.
10.3.4
Any additional preservation/protection requirements for sea transport shall be advised by the
Vendor/Contractor.
10.3.5
Equipment preservation and protection shall be adequate to enable the equipment to be delivered
without suffering damage or deterioration.
10.3.6
Adequate supports and bracing shall be fitted to prevent distortion of tanks and parts of tanks during
shipment.
10.4
Shipping
10.4.1
All detailed arrangements are to be covered by the Vendor/Contractor and the Purchase
Order/Contract.
10.4.2
All relevant equipment and materials shall not leave the Vendor/Contractor's works for shipment until
the release has been approved by the Owner's Inspector.
10.5
Warranty
10.5.1
The Vendor/Contractor shall warrant the tank, specified materials and services supplied against any
defect for a period of 12 months after commissioning or 24 months from the date of delivery to the site,
whichever is the shorter period, or for the period stipulated in the Purchase Order/Contract.
10.5.2
Should any item be found defective, the Vendor/Contractor shall be responsible for all costs associated
with restoring the tank and equipment to the standard specified by the Purchase Order/Contract.
S:\NOC9077\ADMIN\SPECIFICATIONS\D-SERIES\D-04\GESDO4RF
TANK
P.O. / CONTRACT No.
CLIENT
PLANT
LOCATION
SERVICE
SHEET
ITEM No.
of
No. of UNITS
psig/F
6 SG of Liquid
7 Design Liquid Head
ft
8 Design Code
9 Internal Design Pressure
Tank
in wg
Coil
psig
Tank
in wg
Coil
psig
Tank
Coil
F
13 Tank Dia
ft
14 Pumping Rate
In / Out
15 Breathing Rate
In / Out
ft
Out
ft/h
16 Corrosion Allowance
17 Inert Blanket
Tank Height
In
at
usgpm
bar
and
in
Yes/No
18 Hazard Considerations
19
20 Uniform Live Load
lb/ft
21 Foundation Type
22 Wind Design Code
23 Earthquake Design Code/ Zone
/Zone 2
lb/ft
Maximum Rainfall
in/hr
Wind Velocity
mph
Earthquake Factor
24
25
MATERIALS
26
27 Shell
Roof
28 Bottom
Reinforcement
29 Nozzle Flanges
Nozzle Necks
30 Fittings
31 Structurals
32 Fixed Internals
Removable Internals
33 External Attachments
34 Internal Bolting / Nuts
External Bolting/Nuts
35 Gaskets
36 Floating Roof Seal
37 Internal Lining/Coating
38 Heating Coil & Nozzles
39
PAINTING
40
41
42
43
44
45
Revision No./Date
Prepared by/Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
K:\nocspecs\SPECIFICATIONS\d-series\d-04\Dd0401r0.xls Sheet1
TANK
P.O. / CONTRACT No.
CLIENT
PLANT
LOCATION
SERVICE
SHEET
ITEM No.
of
No. of UNITS
CONSTRUCTION
1 Vendor / Contractor
2
3 Roof Type
Supported
Self Supported
Floating
Covered Floating
Butt
8 Anchor Bolts:
Yes
No
9 Insulation:
Yes/No
mm
10 Weight Empty:
lb
lb
lb
13 Nominal Capacity
ft
lb.ft
lb
Yes/No
Density
lb/ft
16
17 Hydrostatic Test
Full of Water
18 Weld Examination
Radiography
19
Supplementary Ultrasonic
20
Sectioning
21 Leak Testing
Bottom
22
Shell
23
Roof
25
TANK ATTACHMENTS
26
27
28 Stairway Type:
Circular
Straight
Ladder
Landings
Handrailing
30 Walkway Width:
31 Draw Off Sump:
ft
Standard
Yes/No
Scaffold Hitch
Yes/No
Special
Yes/No
32 Internal Pipe
Swingline
Suction Nozzle
33 Heating Coil
Yes/No
Surface Area
ft
34 Roof Drain
Hose
Jointed
Syphon
35
36 Breather Valve:
Yes/No
Type:
37 Flame Arrestor
Yes/No
Type:
By:
By:
38 Level Indicator
Yes/No
Type:
By:
39 Dip Hatch
Yes/No
Type:
By:
40 Insulation Supports
Yes/No
Type:
Supplied By:
41 E STANDARDS
42
43
44
45
Revision No./Date
Prepared by/Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
K:\nocspecs\SPECIFICATIONS\d-series\d-04\Dd0401r0.xls Sheet2
TANK
P.O. / CONTRACT No.
CLIENT
PLANT
SERVICE
LOCATION
ITEM No.
SHEET
of
No. of UNITS
SKETCH
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
Revision No./Date
Prepared by/Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
K:\nocspecs\SPECIFICATIONS\d-series\d-04\Dd0401r0.xls Sheet3
TANK
P.O. / CONTRACT No.
CLIENT
PLANT
LOCATION
SERVICE
SIZE
No.
CLASS
ANSI B16.5
NOZZ
STAND
from
API 605
SCH
OUT
REF. T.L.
(L)
(E)
TYPE
FACE
RAD
ANGLE
of
No. of UNITS
DISTANCE
FLANGES
REF
SHEET
ITEM No.
SERVICE
NOZZLE
REINFORCING
ATTACH
PADS
-MENTS
(R)
(A)
O/D
THK
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Revision No./Date
Prepared by/Date
Authorised by/Date
Purpose
(C) 1999 NATIONAL OIL CORPORATION. The information on this sheet may be used only for the purpose for which it is supplied by NOC.
K:\nocspecs\SPECIFICATIONS\d-series\d-04\Dd0401r0.xls Sheet4