Вы находитесь на странице: 1из 15

Radiation Loss

Steam Output

Heat Input is Pulverised Coal, Heat Output is Superheated Steam


Efficiency Calculations:
Standard Applied

:- ASME Standard PTC 4.1

Calculation Method :- Loss Method


Losses calculated as percentage of INPUT as 100%
1) Loss due to dry flue gas = 4.928%
2) Loss due to Unburnt Carbon

= 0.331%

3) Due to Sen. Heat of Bottom Ash

= 0.071%

4) Due to Sen. Heat of Fly Ash

= 0.102%

5) Radiation Losses

= 0.200%

6) Loss due to moisture in Fuel

= 1.263%

7) Loss due to Hydrogen in Fuel

= 5.537%

8) Loss due to Moisture in Air


9) Unaccounted Losses
Total Losses

= 0.074%
= 1.327%

= 13.83%

CONTROLLABLE LOSSES 1:
1. LOSS DUE TO DRY FLUE GAS : CONTROLLED BY PROPER CLEANING OF THE
FURNACE
2. LOSS DUE TO UNBURNT IN BOTTOM ASH : CHECK THE FINENESS OF
PULVERISED COAL. CHECK THE % RETENTION ON 50 MESH. IT SHALL NOT
EXCEED 1%.
3. LOSS DUE TO UNBURNT IN FLY ASH : IF UNBURNT IN FLY ASH EXCEEDS 0.8%
IT INDICATES INCOMPLETE COMBUSTION DUE TO LESS AMOUNT OF AIR.
CHECK FOR O2 % AT THE APH FG INLET FOR 2.8%, INCREASE IF NECESSORY
TO 3.2%. AGAIN CHECK FOR UNBURNTS IN FLY ASH. SIMULTANIOUSLY CHECK
FOR AIR LEAKAGES/INGRESS IN THE SECOND PASS.
4. GCV Calculations for Coal :
1) Useful Heat Value
= 8900 138(A%+M%) kcal/kg
2) Gross Calorific Value (Air Dry Basis)
= (UHV + 3645 75.4 M
%)/1.466 kcal/kg
3) Ash % (As fired basis)
= [A %] (100 - TM%)/(100 M%)
%
4) Gross Calorific Value (As fired Basis)
= [GCVAD] (100 - TM%)/
(100 M%) kcal/kg
5) Net Calorific Value
=[GCV] 10.02M% Kcal/kg
Heaters:
For 0.56C increase in TTD on Top/other heaters, 0.016/0.013% increase in HR.
For 0.56C increase in DCA 0.005% increase in HR.
PURPOSE OF FEED WATER HEATERS:
1. They provide efficiency gains in the steam cycle by increasing the initial
water temperature to the boiler, so there is less sensible heat addition
which must occur in the boiler.
2. They provide efficiency gains by reducing the heat rejected in the
condenser, and they minimize the thermal effects in the boiler.
C) Pump Performance Assessment
i. Hydraulic Power
Hydraulic power of a pump is gives by:
Ph(kW)= QX (hd-hs) XX g/1000
Q= Volume Flow rate (m3/s)
=Density of fluid(kg/m3)
g= Acceleration due to gravity (m/s2)
(hd-hs)= Total Head in meters
ii. Motor Input Power
Input Power can be calculated using Power Analyzer.
iii. Pump Shaft Power
It is calculated by multiplying the motor input power by motor
efficiency.
Ps= Pm X motor
motor=Synchronous speedXRated SpeedX100/
Synchronous Speed
iv. Pump Efficiency
It is calculated by dividing the hydraulic power by pump shaft

power.
pump= Ph/Ps[11]
v. Specific Energy Consumption(SEC)
SEC= Pm/Q

Reliance Page : 40,43,44.

22 Tips - How to reduce Auxiliary Power Consumption of


500/600/660/800 MW Sets ?
Auxiliary Power Consumption (electrical energy needed to run the Unit at variable loads)
1.

Conduct Energy Audit of the Units/Plant every year by an efficient Energy


Auditor

2.

Implement all the recommendations of the said Energy Auditor for the
Units/Plant

3.

Identify and plug all energy loss points of the Units/Plant to the extent
possible

4.

Improve Unit overall efficiency (36% for sub-critical & 42% for super-critical)

5.

Improve Unit Heat Rate (close to 2300/2000 kCal/kWh for sub-critical/supercritical)

6.

Maintain Unit PLF close to 90% (for 330 days in a year/nearly 8000 running
hours)

7. Reduce Specific Coal Consumption (0.5 - 0.6 kg/kWh) by sustained


optimization of combustion in the boiler using suitably blended coal (60% F
Grade + 40% D Grade)
8. Reduce Specific Oil Consumption in the steaming Boiler (close to 1.0
ml/kWh)
9. Reduce DM Make-up Water Consumption in the steaming Boiler (close to
1.0%)
10. Carry out routine/preventive/annual/capital maintenance of all load bearing
equipments including their prime movers of the Unit as per
recommendations of respective OEMs
11. Maintain desired voltage/frequency level for the auxiliaries when the Unit is
in Bus
12. Keep Unit Transformers in service when the Unit is in Bus beyond 10% rated
load
13. Use combination of Steam Turbine Driven (2x50% running at 100% rated
load) & Electric Motor Driven (1x50% kept as standby) Boiler Feed Pumps for
running Unit
14. Or use Motor Driven Boiler Feed Pumps with Multi-Stage Variable
Speed Drive (with planetary gears) Vorecon (3 x 50% E-motor + Vorecon) for
running Unit
15. Use VFD for the prime movers of all other load bearing equipmentsfor the
running Unit
16. Keep all standby load bearing equipments of the Unit in switched
off/standby mode
17. Maintain desired Condenser Vacuum (around 76 - 80 mm of Hg) inthe
running Unit

18. Maintain optimum back end temperature (around 130 0C - 1400C) in the
steaming boiler
19. Maintain unburnt carbon in fly/bottom ash of the steaming boiler on lower
side (~1%)
20. Run the Unit at Base Load (100% Rated Load) on 24x7 basis
21. Maintain ash evacuation/disposal of the steaming boiler in dry mode except
exigency
22. Maintain optimum illumination level in the Plant (use energy efficient lamps)

Вам также может понравиться