Академический Документы
Профессиональный Документы
Культура Документы
Chapter One
INTRODUCTION
1.1
In the 17th century, architects were responsible for the design and supervise the erection
of buildings while the craftsmen did the measuring and estimating. Each craftsman will
employ his own method of measurement.
unsatisfactory due to the difficulty in reconciling the actual materials used and the
measured works carried out.
1.2
Listed below are outlines of certain conventions and define of terms, which apply to bill
preparation and measurement processes generally.
Quantities - It is the estimated amount of labour and the materials required to carry
out the project under the various items of works.
Bill of Quantities - The Bill of Quantities is a list of items giving the quantities and
brief descriptions of work to be carries out with its respective quantities and unit cost
crate) for carrying out each trade.
In conjunction with the other Contract Documents, it forms the basis on which tenders
are obtained. When priced it affords a means of comparing tenders. When the Contract
1/ 1
KJC326
has been entered into, the rates in the prices Bill of Quantities are applied to assess the
value of the actual quantities of work carried out.
prepared and measurements made in according with the procedure set out in the Civil
Engineering Standard Method of Measurement (CESMM), unless other methods of
measurement are preferred by the Promoter (Employer/Purchaser).
Standard Method of Measurement - SMM is a document stipulating guidelines on
the method of measurement of any particular trade. These guidelines give the different
components of an item to be measured (taking-off) and describe in a manner which is
easily understood so that all tenderers can price them on the same basis.
Trade - It is the works or practice of certain craft for example bricklayer, plumber etc.
Civil Engineering Works are classified under different trades and this will help the civil
engineer in pricing the different categories of works.
Taking Off - It is the process of measuring from drawings and recording all dimensions
in recognised form on a special ruled paper called Dimension Paper.
Squaring Dimensions - It is the process of multiplication and/or addition/subtraction
of recorded dimension for the purpose of obtaining the linear, square or cubic
measurements.
Abstracting or Working-up - It is process of collecting of measurements of identical
character and description, under different tracks and reducing them to units as required
by CESMM.
Billing - Writing the draft bill for the Abstract.
CESMM - The rules and provisions of the Civil Engineering Standard Method of
Measurement. (CESMM), are applicable to the preparation of Bill of Quantities for and
the measurement of civil engineering works such as earthworks, roads, bridges,
structures, culverts, sewage, etc and quantities are usually prepared by the civil
engineers.
They are not intended to apply to the preparation of bills of quantities for or the
measurement of mechanical engineering, electrical engineering or building work. The
CESMM is intended for use in conjunction with the I.C.E. Conditions of Contract.
1/ 2
KJC326
The CESMM document contains eight numbered Sections. The first seven sections are
each divided into Paragraph. Section 8, is divided into eighteen(18) main classifications.
Conditions of Contract - It defines the terms under which the work is to be carried
out, the relationship between the Promoter and the Contractor, the powers of the
Engineer and the terms of payment.
Specification - It describes in detail the work to be executed, the character and quality
of the materials and workmanship, any special responsibilities of the Contractor that are
not covered by the Conditions of Contract. It may also lay down the order in which
various portions of the work are to be executed, the methods to be adopted and
particular of any facilities to be afforded to other contractors.
Care should be exercised when drafting the specification to avoid conflict with any of the
provisions of the conditions of contracts.
Estimating - It is the process of costing the project of each item or trade after the
quantities has been measured and summing up the items to arrive at a total estimated
cost for the whole project.
Measurement - (1) Taking off
(2) The actual measurement of the work executed on the site.
Prime Cost Sum @ P.C.Sum - A sum provided for work or services to be executed by
nominated sub-contractor, for materials or goods to be obtained from a nominated
supplier. Such sum shall be deemed to be exclusive of any profit required by the general
contractor and provision shall be made for the addition thereof.
Provisional Sum - A sum provided for works or for the cost, which cannot be entirely
foreseen, defined or detailed at the time tendering documents, is issued.
1/ 3
KJC326
1.3
1.0
DESCRIPTION
No of items
Covers
CESMM
large variety
SMMM
of Covers more trade or work
different jobs.
section.
2.0
BQ
backfilling
trenches,
E.g.
backfilling
trenches,
levelling,
compacting
excavation rate.
3.0
Temporary
(Diversion)
works
contractors
must Temporary
diversion
works
etc.
works.
which
are
normally
are
and
classified
as
Concrete work
Measurement of concrete in
KJC326
specified.
Coding
numbering
items
1/ 5
No coding is required.
KJC326
1.3.2
CESMM
SMMM
Lump Sum
Not covered
Number
Not covered
L.S/hectare/acre
m2
Number
(diameter specified)
Number
(diameter specified)
1.0
Site Investigations
(a)
(b)
Moving plant
2.0
Site Clearance
(a)
(b)
Big trees
3.0
Excavation
(a)
General excavation
m3
m3
(b)
i)
m3
m3
included in
excavated rate
m2
iii) Planking
included in
excavated rate
m2
included in
excavated rate
4.0
Mass Concrete
m3
m3
5.0
m3
m2
(with thickness of slab
specified)
6.0
Steel Reinforcement
Kg
Kg
7.0
m3
m (with diameter
specified)
1/ 6
KJC326
1.3.3
a) General Items
- CESMM Class: A
- CESMM Class: B
- CESMM Class: C
- CESMM Class: D
e) Earthworks
- CESMM Class: E
f)
- CESMM Class: F
Concrete work
g) Roadworks
- CESMM Class: G
h) Drainage Works
- CESMM Class: H
i)
Pipeworks
- CESMM Class: I
j)
Piling Works
- CESMM Class: J
- CESMM Class: K
l)
- CESMM Class: L
Timberworks
m) Metalworks
- CESMM Class: M
n) Painting Works
- CESMM Class: N
o) Rail Tracks
- CESMM Class: O
- CESMM Class: P
- CESMM Class: Q
r) Miscellaneous Works
- CESMM Class: R
1.4
TYPE OF TENDER
KJC326
1.4.1
(i)
Open Tender
(ii)
(iii)
Negotiated Tender
Open Tender
This type of tender is open to all qualified contractors registered under same class. The
invitation to tender is usually advertised through newspaper, journal, and etc.
Merit:
(i)
(ii)
(iii)
It offers chances to new and inexperience contractors to bid for the tender.
Demerit:
(i)
Tenders may be received from firms who neither have the necessary
financial resource nor technical knowledge and experience of the class of
work involved.
(ii)
(iii)
(iv)
1.4.2
This type of tender is only offer to contractors who are short-listed according to particular
criteria.
Merit:
(i)
(ii)
(iii)
KJC326
(iv)
Demerit:
(i)
(ii)
Tender sum may be not the lowest, as not all qualified tenderers are
invited.
(iii)
(iv)
1.4.3
Negotiated Tender
Negotiated tender is an alternative to open tender and close tender. The tender is
directly offered to contractor short-listed. It is usually proceeds and follows by discussion,
1/ 9
KJC326
and negotiation for ultimate contract sum, form of contract to be used, construction
programme and method of carrying out the work. It is usually advisable in special
circumstances, such as:
(i)
(ii)
Projects for armed forces, where the work site is of restricted area.
(iii)
(iv)
(v)
(vi)
Merit:
(i)
Since only one contractor is invited, negotiation can be easily dealt with;
and it saves a lot of time and money compares with other type of tenders.
(ii)
(iii)
(iv)
Demerit:
(i)
(ii)
Tender sum may be not the lowest, as all qualified tenderisers may not be
invited.
(iii)
1.5
TENDER DOCUMENTS
1/ 10
KJC326
Tender document for civil engineering projects normally comprises of form of contract,
general conditions of contract, specification, BQ, contract drawings, and form of tender.
Tender documents may consist of:
(i)
(ii)
(iii)
Specification
-
(iv)
Bill Of Quantities
-
(v)
Contract Drawings
-
ideal contract drawings should detail the entire contract work, which is
not practical in practice. However, they should be prepared sufficiently
detail to enable the tenderers satisfactorily understand what is the
project require.
(vi)
Form Of Tender
1/ 11
KJC326
for
performance
bond,
insurance,
Liquidated
and
1.6
The traditional method of preparation of a BQ can conveniently be broken down into two
main processes:
(i)
Taking off
(ii)
Abstracting / Working up
This traditional method was very lengthy and tedious. As such, The Direct Billing
System was developed. It is to bill direct, by transferring the items direct from the
dimensions paper to the BQ, thus eliminating the need for an abstract. The quantity takeoff is set down in the standard form of BQ, that by adding together the prices listed will
give the contract price or tender sum.
The functions of BQ are:
(i)
It prompts the client and design team to finalise most project particulars
before the bill is prepared, and ideally based on full production drawing
and project specification.
(ii)
(iii)
It set down the various items of work in logical sequence and recognised
manner, easily priced by the contractor.
(iv)
It limits the risk element borne by the contractor to the rates he enters in
the bill and thereby results in more realistic and competitive tenders.
(v)
(vi)
It provides a good basis for the preparation of cost analyses for cost
planning usage.
1/ 12
KJC326
A bill of quantities (BQ) is a document which lists all the items necessary for the
complete construction of works. Each item includes a description and a quantity.
1.6.1
A bill of quantities cannot be prepared directly from the drawings but must be built up in
three stages.
a)
Taking off is to calculate the quantity in each item of work. The taking off sheet, which is
sometimes called a dimension sheet, is ruled in the following way (See Appendix A1)
Table 1.6.1 : Taking Off Sheet / Dimension Sheet
1/ 13
KJC326
Column B
Column C
Column D
b)
It consists of transferring the description and quantity the description and quantity from
the taking-off sheet to the abstract sheet (as shown in Appendix A2) and collecting
together items, which can be, billed under one item. If the quantity has to be converted
from one unit to another unit this is done on the abstract sheet.
c)
There are certain principles, which should always be followed when writing a bill of
quantities. It should be concise, accurate and well written (as shown in Appendix A3).
i)
Descriptions
Each item should be described in enough detail to enable anyone reading the bill
of quantities to be able to locate the item in the works.
ii)
Order
Items should be entered in a logical order. It is suggested that the following order
be used.
1/ 14
KJC326
iii)
Accuracy
Numbering
Abbreviations
brickwork
C.I.
cast iron
Ddt
deduct
D.P.C
Ex.
excavation
M.S
mild steel
n.e.
not exceeding
P.C.
prime cost
R.C.
reinforced concrete
S.G.S.W.
W.I.
wrought iron
1/ 15