Академический Документы
Профессиональный Документы
Культура Документы
PGP-CM-MODULE-01
ASSIGNMENT NO: 03
COURSE TITLE:
MATERIALS
AND EQUIPMENT
MANAGEMENT
COURSE CODE NCP 24/25
DATE OF DISPATCH: 25/11/2015
LAST DATE OF RECEIPT: 30/11/2015
INTRODUCTION
It is a common fact that we find a wide variety of construction
machines on every construction sites, which makes the
construction jobs easy, safe and quicker. Good project
management in construction must vigorously pursue the
efficient utilization of labour, material and equipment.
The use of new equipment and innovative methods has made
possible wholesale changes in construction technologies in
recent decades. The selection of the appropriate type and size
of construction equipment often affects the required amount of
time and effort and thus the job site productivity of a project.
These act as the backbone in the case of huge construction
projects. Proper use of the appropriate equipment contributes
to economy, quality, safety, speed and timely completion of a
project. Equipments are use for highway projects, irrigation,
buildings, power projects etc. Almost 15-30% of total project
cost has been accounted towards equipment and machinery.
It is therefore important for site managers and construction
planners to be familiar with the characteristics of the major
types of equipment most commonly used in construction.
Scope of work:
100m width of Road construction for international airport 30 Km
away from city.
Assumptions:
(a)
Type of equipment:
Excavator for excavation and cutting
Dozer for dozing
Grader for spreading of material
Dumper for shifting and hauling of material
Roller and water tanker for compaction.
(b)
Working hours: 10 hours per day and maximum of 60 per
week.
(c)
Maintenance: 10 hours per week per plant ( one day per
week)
(d)
Induction period: three working days (dismantling,
transport, reassembling and testing) for a lead of 100km.
(e)
Break down period considered : four days per equipment
in a month
(f) Adequate spares and sub assemblies are available with trained
maintenance
staff.
(g)
Mass diagram of the area has been prepared and the plant
operators are familiar with the task at hand.
(h)
Work is executed as per the mass diagram.
(i) Plant operators are experienced and are capable of achieving
the planned output.
(j) No disruptions have been considered for reasons of inclement
weather and other factors.
(k)
Plant / equipment as planned will be made available.
Cost analysis:
1 Excavation of 100000 cum soil.
Consider 3number of excavators 0.9 cum bucket capacity @ 60
cum per hour
Output 3 excavators = 1800 cum/day
Total duration required to excavate 100000 cum soil = 56 days
Assume cost of operation of excavator @ Rs 2200 per Hour
Total cost for excavation of 100000 cum soil = Rs 36.67 L
2 dozing of excavated material
Consider 3 numbers of dozer, 80HP @ 30cum per Hour
Output 3 dozers (10 Hrs working)
900 cum/day
= Rs 41.7 L
10 cum/Trip
15min
10min
5min
10min
40min
= 15 numbers
1200 cum
17 working days
= Rs 3.60 L
4 Shifting of 20000 cum sand from 20Km away
Consider 8 numbers of dumpers to execute this work
Capacity
10 cum
15 min
=
=
5min
30 min
560 cum
= 36 working days
50 working
Rs 17.00 L
6 Compaction
Consider 2 nos. Vibratory road roller 8-10 tonnes capacity,
100cum per hour and 2 nos. Water tanker 6KL capacity.
Output of 2 rollers ( 10hrs working)
Total duration required
= 50 working days
= Rs. 11.70
L
SUMMARY OF EQUIPMENTS REQUIRED AND COST
ESTIMATE
Sl.n
o
Activity
Equipment
planned
Unit cost
of
operation
Total
estimated
cost
Excavation of 100000
cum soil
Rs.36.67L
Dozer, 80 hp
3 nos.
Rs.2500
per hour
Rs.41.67L
Dumper
8nos.
Rs 6 per
cum per
km
Rs. 3.60L
Dumper
8nos.
Rs 6 per
cum per
km
Rs 24.00L
Spreading of 80000
cum soil and 20000
cum sand
Motor grader
2nos.
Rs. 1700
per hour
Rs. 17.00L
Compaction of 100000
cum material
a) Vibratory
roller, 810 T
capacity
b) Water
tanker 2
nos. 6KL
cap.
a) Rs.
1000
per
hour
b) Rs.
1700
per
day
Total
estimated
cost
Rs. 11.70L
Rs.
134.64L
Favourable
Average
Unfavourable
25 % of fuel cost
33 % of fuel cost
50% of fuel cost
Day
from
beginni
ng
15
25
35
60
69
70
79
80
89
Openin
g stock
Order
placed
order
0
0
0
0
5000
0
5000
0
5000
50000
50000
50000
-
50000
50000
50000
-
Total
Consum Closing
ed
Stock
50000
5000
5000
5000
50000
5000
5000
5000
50000
5000
5000
5000
Work Complete
45000
45000
45000
-
(b) Safety level: The above case was planned considering ideal
conditions where there were no delays anticipated. However in
case of any delays in the supply chain, the work would suffer,
hence certain safety levels are maintained to cater for
emergencies. In the above case a safety level can be
incorporated by decreasing the order quantity and increasing
the number of orders. Consider the above case with changed
order levels;
i. bitumen required from 60th day after work commencement
ii. lead time 45 days
iii. total requirement 1,50,000 litres
iv. storage capacity 50,000 litres
v. no.of orders being placed - four
vi. first order to be placed on 15th day of work for 50,000
litres
Biblography / Readings:
As recommended in assignment and material from internet.