Академический Документы
Профессиональный Документы
Культура Документы
Topic:
______________Planning PG________________
Batch Number:
_________________________________________
Date of Exam:
_________________________________________
Candidates Name:
_________________________________________
Total Questions: 30
Choose one of the best choices available for each question. All questions are mandatory.
1. The Project team has just completed the initial project schedule and budget. The next thing to
do is:
a. Identify Risks
c. Determine Communication requirements
b. Begin iterations
d. Create a Bar (Gantt) chart
2. You are a new Project Manager who has never managed a project before. You have been
asked to plan a new project. It would be best in this situation to rely on_________ during
planning to improve your chance of success.
a. Configuration Management
c. Stake Holder Analysis
b. Historical Information
d. Your intuition and training
3. Based on the network diagram, you complete the initial schedule and find out the scheduled
completion date for activity G is after an imposed delivery date. In order to shorten the project
length and meet the milestone, what should you do?
a. Fast track activity H & J
c. Decrease the work of activity E
b. Outsource activity I
d. Move more resources to activity B
10
St
art
11
I
4. Which of the following best describes a project management plan?
a. A printout from the project management software
E
n
d
b. A bar chart
c. Risk, staffing, process improvement and other management plans
d. The project scope
5. All of the following are inputs to the Determine budget process EXCEPT:
a. Activity cost estimates
c. Project Scope Statement
6. All of the following are inputs to the plan Quality process EXCEPT:
a. Enterprise environmental factors
c. The schedule baseline
b. Estimate costs
d. Control costs
9. A ranking of risks and a list of risks for additional analysis are all outputs of which process of
risk management?
a. Identify Risks
c. Perform Quantitative Risk Analysis
10. How many types of relationships between activities can be found on a precedence (AON)
diagram?
a. 3
b. 4
c. 1
d. 2
11. A project manager has increased project cost by US $100,000, but completed the project four
weeks earlier than planned. What activity is best described here?
a. Resource leveling
c. Critical Chain
b. Schedule compression
d. Adjusting leads and lags
b. Team
c. Network Diagram
d. Scope verification
14. An activity has an early start of day 3, a late start of day 13, an early finish of day 9, and a late
finish of day 19. The activity:
a. Has a lag
c. Is not on the critical path
b. Is progressing well
d. Is on the critical path
b. Accept
c. Share
d. Avoid
16. Which of the following is not part of the Define scope process?
a. Facilitated workshop
c. Product analysis
b. Identifying alternatives
d. Inspection
18. In which of the contract types does the buyer have the most cost risk?
a. CPPC
b. CPFF
c. CPAF
d. CPIF
19. In managing project communications, what should the project manager keep in mind?
a.
b.
c.
d.
20. Which estimating method tends to be most costly for creating project cost estimate?
a. Bottom-up
c. Parametric
b. Analogous
d. 50/50 Rule
21. A team member does not have the required skills or knowledge and was assigned to a project
team by his functional manager. Who is responsible for ensuring that he receives the proper
training?
a. The sponsor
c. The project manager
22. If a project has a 60% chance of a US $100,000 profit and a 40% chance of a US $100,000 loss,
the expected monetary value of the project is:
a. $100,000 profit
b. $60,000 loss
c. $20,000 profit
b. 20
c. 70
d. 25
d. $40,000 loss
a.
b.
c.
d.
b. Project Team
d. Project Stakeholders
26. Which of the following includes all of the relationships represented on an activity-on-node
diagram?
a.
b.
c.
d.
Finish-to-Start
Finish-to-Finish
Finish-to-Start, Start-to-Finish, Finish-to-Finish, Start-to-Start
Start-to-Start, Start-to-Finish
28. Based on the chart, what is the duration of the critical path?
a. 19
b. 13
c. 15
Activity
d. 14
Preceding Activity
Estimate
Start
Start
C, D
E, F
End
Start
30. You are trying to decide whether to lease or buy an item for your project. The daily lease cost
is $ 150. The investment cost to purchase the item is $ 2000, and the daily cost is $ 50. In how
many days will the lease cost be the same as the purchase cost?
a. 10
b. 15
c. 20
d. 25