FOREWORD
CAMTECH Gwalior
09.5.2011
S.C. Singhal
Exe cutive Director
Page 3 of 173
PREFACE
Hitherto Mechanical Department has been managing their activities departmentally.
However due to increase in volume of transport services and rise in costumer
expectations, it has become very difficult to manage the services departmentally in cost
effective manner. Therefore outsourcing of following few non core activities is being
done.
At present, the supervisors and officers of Mechanical department are not well versed
with procedures of contract management, therefore a need was felt to summarise
various guidelines about contract management.
In this handbook various topics such as, steps during contract management, general
conditions of contract, eligibility criteria, execution of work, special condition/ model
tender document of standard contract being under taken by mechanical department,
have been included.
It is clarified that this handbook does not supersede any existing procedures and
practices laid down by the Railway Board and instructions issued by Zonal Railways.
Learning is a continuous process, hence feel free to write to us for any addition /
modification in this handbook or in case you have any suggestion to improve the
handbook, your contribution in this direction shall be highly appreciated.
CAMTECH Gwalior
Date: 09.5.2011
(K.P. Yadav)
Director/Mech.
Page 4 of 173
CONTENTS
Page No.
Front Page
Forward
Preface
Contents
4-5
PART-I
1.0
Introduction:
2.0
3.0
3.1
Tender system
3.2
Types of Tenders
3.3
Estimate
3.4
Tender Notice
10
10
11
Tender Processing:
11
4.1
11
4.2
12
4.3
Terms of Contract
13
4.4
13
4.5
13
4.6
13
4.0
5.0
6.0
7.0
Tender Box
15
5.1
15
14
6.1
18
19
Page 5 of 173
8.0
9.0
24
8.1
24
8.2
24
8.3
Validity of offer
25
Security Deposit (S D)
25
9.1
25
26
28-43
44
44
44
45
45
45
46
47
49
49
14.0 Negotiation
50
51
51
51
51
51
51
52
52
52
Page 6 of 173
17.6 Test check
52
52
53
53
53
54
54
56
56
56
56
57
57
58
59
59
60
60
60
61
61
63
63-66
67-68
Page 7 of 173
1.0
Introduction:
M ost of the organizations both in private and p ublic sectors are en gagin g other agencies for
doing various work/supp ly of materials and maintainin g assets. In Railways due to increase in
volume of transp ort services it became d ifficu lt to carry out all activities through d ep artmental
resources. Outsourcing the work to other agencies of high er technical qualifications havin g
better resources viz equip ment, machinery etc came in to force.
As such it is absolutely essential for all, to be aware of basic in gredients of contract so that they
do not commit mistake.
2.0
3.0
Page 8 of 173
3.1
Tender system
As p er Para 1210 of Engineerin g code, it is the p rimary duty of the executive to obtain the best
value p ossible for the money sp ent and the tender sy stem should be given a very carefu l and
serious consideration in all cases to secure comp etitive rates.
What is a Tender?
Tender is a sort of bid or offer mad e by a contractor for execution of certain work or supp ly of
materials for sp ecified work under specified conditions with p rescribed time limit.
Generally , when the value of the work exceeds Rs. 2 lakhs, it should be p rocessed through
tender p rocedure. First, estimated cost of work should be worked out. This can be arrived at on
the basis of last accepted rates (LAR) or budgetary quotations. A detailed justification should
be mad e and ad ministrative ap p roval for the work should be accorded by the authority
comp etent to do so after thorough examination of the necessity , utility and financial asp ects.
3.2
Types of Tenders
1. Open Tender:
It is a sy stem of invitation of tender by p ublic advertisements in most open p ublic manner. The
tender documents in the case of open Tenders, are to be issued to those p rospective tenderers
who dep osit the fee for tender documents irresp ective of whether an eligib ility clause is
p rescribed or not. In case, an eligib ility clause is p rescribed, it is for tender committee to
evaluate whether the tenderer satisfies the prescribed eligibility clauses.
Page 9 of 173
In this sy stem, the tenderer are advised to submit their offers in two sealed envelop s with one
cover containin g the Technical and Commercials Bid and other containing Financial Bid.
Technical Bid
The Technical and commercial conditions are read out before the tenderers and the tender
committee evaluates the same. The tenderers are adv ised to enclose EM D in the technical bid.
Financial Bid
If the technical bid is found accep table by the competent authority, the second p acket
(Financial bid) is op ened and the tenders p rocessed for accep tance in the normal manner.
However, if on the basis of the information of the first p acket, the tender committee needs
clarifications, regard in g the design and sp ecifications, discussions are held with each individu al
contractor after obtaining the ap p roval of the competent authority .
2. Single Tender:
This is resorted to in rare and emergent situations such as accidents, derailments, dislocation
to works etc. This should have the concurrence of FA & CAO and ap p roval of GM .
AMCs for the equip ments may be p laced on single tender basis on authorized dealers with
the app roval of GM .
Detailed justification should be sp elt out.
All the cases of single tender shall requ ire p rior finance concurren ce before the
administrative app roval.
Up to Rs. 20 Lakhs per case per PHOD subject to annual limit of Rs. 1 Crore (prior
finance concurrence a t the level of FA& C AO).
Up to Rs. 10 Lakhs per case per DRM subject to annual limit of Rs. 50 Lakhs (prior
finance concurrence a t the level of Sr. DFM).
All single tender cases (other than stores) will require GM s p ersonal sanction and FA &
CAOs concurrence.
TC & Accep ting authority should be one step higher.
3. Limite d tender:
Under this system, every railway unit is supp osed to have an approved list of
contractors/supp liers/manufacturers. Tenders are sent to only app roved parties. The contractors
are registered after screening by a committee available. There should be minimu m 10 firms
registered for limited tender.
Page 10 of 173
5. Bulletin Tender:
It floated for so many items to be p urchased or work to be executed. These are p rocessed
through Bulletin by Stores dep artment.
ANNUAL C EILING
S r. S cale
JAG
S AG
1,00,000
2,00,000
4,00,000
5.0 lakhs
20.0 lakhs
40.0 lakhs
Normally p owers to disp ense with callin g of tenders should b e excercised sp aringly and
Circumstances should be sp elt out.
Invited from at least 3 well exp erienced genuin e contractors, not necessarily borne on
app roved list.
Register showing the full details to be maintain ed and sent to Associate Finance while
seekin g concurrence.
Reasonability of rates to be gone through objectively and in detail by Accepting Authority
(AA).
Quotations: In gen eral, any works p rop osal Value up to Rs. 2 Lakh and below can be
p rocessed through work order by calling quotations. Work order should be op en to all
contractors and minimu m 3 quotations are required. Attempt should not be made to split the
works to bring the p rop osal under work order limit.
Tenders receive d by P ost:
Tenders received by p ost should be entered in the Tender Register and the time of receip t
should be recorded on the cover of the tender and dep osited before the closing time in the
tender box. (En gineerin g code, 1999 Para 1247)
3.3
Esti mate:
Page 11 of 173
3.4
Tender Notice:
After sanction of comp etent authority , a brief tender notice has to be p rep ared. Sufficient notice
should be given for submission of tender, which in case of large works should not be less than a
month. Further, it should be ensured that the tender notice is given maximu m p ublicity while
releasin g the adv ertisement for tenders dep ending up on the imp ortance of work. Care should also
be taken to have a judicious mix of lo cal, n ational and/or fin ancial d ailies in ord er to generate
adequate comp etition. The tender notice and tender documents should also be p osted on a
website and the name of website should be given in the tender notice.
Page 12 of 173
(viii) Website p articulars and notice board lo cation where co mplete details of tender can be
seen, etc.
The Railway s need to be cautious while issuing notices and corrigendum/ addendum which
should invariab ly be p ublished in all the concerned newspap ers besides p osting the same in the
Website/Notice Board of the Office, etc. where the original notice was p asted. The web-site
should also specify a date up to which the tenderers may note up dates/ corrigendu m/rev ised date
of op ening.
The Railway s may also arran ge to have all the notices includin g tender notices p ublished on a
fixed day in a week. For this, since the space requirements in newsp apers will be in bulk, the
railway may negotiate for considerable reduction in the advertisement charges with the
newspap ers concerned.
3.4.3 Advertisement of Tender
While p ublishin g tender in news pap er , CPRO/PRO must ensure that NIT has already been
up loaded on the website by taking certificate from Executive.
Any op en tender not having token of confirmation (in the form of internet download record) ,
it will be treated as inadequ ately advertised tender.
(Rly Bd letter No. 2008/RS(G)/779/2 Dated 7/11/2008)
4.0
Tender Processing:
The tender document should contain clear d etails of works, sp ecifications, scop e of work,
schedule of work, instructions to tenderers, general conditions, sp ecial conditions and contract
agreements. Eligibility criteria and similar n ature of works should be specifically mentioned in
Tender documents for op en tenders above Rs.50 lakhs.
The tender form supplied to tenderers ap art from other thing should contain Amount of Earnest M oney dep osit to accomp any the tender.
With whom or what authority , the acceptance of a tender will rest.
4.1
Page 13 of 173
Activity
Time Limit
(Approx.)
01
--
02
--
03
--
04
--
05
Vetting of estimate
--
06
Sanction to estimate
--
07
--
08
--
09
--
10
--
11
--
12
--
13
Op ening of tender
01 Day
14
02 Day s
15
07 Day s
16
01 Day
17
05 Day s
18
Nomination of TC members
01 Day
19
TC p rep aration
05 Day s
20
07 Day s
21
TC Finalization
07 Day s
22
01 Day
23
01 Day
24
30 Day s
25
02 Day s
26
Verification of BG by bank
05 Day s
Page 14 of 173
27
02 Day s
28
03 Day s
29
01 Day
30
Up dation of finalised tender on net for valu e more than 1.0 crores.
04 Day s
31
-TOTAL
4.3
85 DAYS
Terms of Contract:
The terms of contract must be p recise and definite and there should be no room for ambigu ity
or misconcep tion and should includ e the followin g:
The contractor is to do; what, when, where and to whose satisfaction.
What the railway administration is to do, on what terms?
What and when the p ay ment is to be made and the method and the basis for makin g it?
The resp onsibility of the contractor in resp ect of adequate supervision, care of government
p rop erty .
Measures to be adopted in the event of breach of the contract by either p arty .
The method of setting disp utes as p er GCC Para 1217 of Engineerin g Code.
(As far as p ossible, legal and finan cial advice should be taken in drafting contract before they
are finally entered into as p er Para 1217 of Engin eerin g Cod e).
4.4
4.5
The present cost of tende r form for various value s of works is as under:
4.6
Up to Rs. 5 lakhs
Above Rs. 5 lakhs and up to 20 lakhs
Above Rs. 20 lakhs and up to 50 lakhs
Above Rs. 50 lakhs and up to Rs. 2 cr.
Above Rs. 2 crores to 50 Crores
Above 50 Crores
Para 1251 of the Indian Railway s Code for the Engineerin g Dep artment (Revised Edition
1982) stip ulates that for dealing with Delay ed and Late tenders, sep arate instructions as
issued by the Railway Board from time to time should be followed.
In this regard Railway Boards letter no.71/RS(G)/777 dated 01.08.1981 and 19.04.1984 are
rep roduced below for gu idance.
(Copy of Railway Boards letter no.71/RS(G)/777 dated 01.08.1981)
Page 15 of 173
The tender opening should be done by tender op ening committee in p resence of all the
tenderers or their authorised rep resentatives.
All envelop s pertaining to a particular tender to be serially numbered like 1/5, 2 /5 .... 5/5 if
5 envelop s are there and initialled by all the tender op enin g officials
They are to be entered in the tender op ening register in the same order 1/5, 2/5 ----- with
name of the firm.
Then op en envelop one after another and record number app earing on the env elop on each
p age of the offer with initials of tender op ening officials
Better to indicate total number of p ages after carefu l countin g with initials so as to
eliminate p age subsequently .
Encircle all rates both figures and words as well conditions having financial implications
with initials without leavin g any sp ace around so as to eliminate p ossibility of any
insertions later on.
Page 16 of 173
Testify and indicate corrections and total number of corrections on each p age so as to
eliminate p ossibility of further manipulation by corrections.
Indicate ambigu ities in rates by recording rate also in words if not written by the tenderer
with remark rates not quoted in words.
Record whether sample has been supp lied and identify it with initials so as to eliminate
p ossibility of its subsequent rep lacement
Number of conditions quoted on each p age to be counted and indicated on each p age so
as to eliminate p ossibility of later additions.
Name and rates quoted by each tenderer to be read aloud.
No opp ortunity to be given to tenderers to repudiate , amend, exp lain the rate or
conditions
Valu e and form of EMD to be noted
A summary of rate p rep ared
In case of two p acket system p ackets containing technical b id are op ened first.
Care should be taken durin g tender op enings so that followin g p ost op ening
manipulations are avoid ed as these may chan ge the interse p osition of the tenderers.
Alteration/corrections in rates
Alteration/corrections in conditions
Insertion of additional offers
Insertion of additional duties/taxes
Alteration in discounts etc.
5.0
Tender Box
Tender box should be kep t in the office duly locked and sealed by the accounts
rep resentative at the nominated date.
Tenderers may be instructed to directly dep osit the sealed tenders in the tender bo x at the
nominated date within the stipulated time.
Tenders received by p ost within the time sp ecified may be received by the Office
Sup erintendent concerned who should immed iately drop the same in the tender box
without op ening the envelop e or breakin g the seal.
In case tenders are received well in adv ance or the size of packet of the tender document
is large so that it cannot b e drop p ed in the tender bo x, sp ecial p rocedure should be
followed.
Page 17 of 173
As p er Railway Boards letter No. CE-I/CT/1 dated 13.02.1991, it is desired that boxes
should be p rovided well in advance and in any case at least ten days before the last date of
receip t of the tenders so that tenderers feel free to dep osit the tenders at their convenience.
Tender box on ce sealed to be op ened at sp ecified time and the op enin g should under normal
circumstances not to be p ostp oned.[ CE/CRs L.No. W.187.R.VII OF 31.10.79, Para 10] annex . 56.]
It should be ensured that the sealed tender box not temp ered with and adequate
arran gements for its security are made to avoid comp laints from any of the tenderers.
[ CE/CRs L.No. W.187.R.VII OF 31.10.79, Para 10] annex ure 56. & Bds letter dated 13.02.1991 ]
g. Tender box should ind icate by a slip pasted on the box conspicuously , the name of the work
for which the tenders are to be dep osited therein and date & time up to which tenders can be
dropp ed in the box.
h. The key of this lock should be kep t in the custody of the Sup ervisory official.
i. For high value tenders, arran gements should be made for keep in g tender boxes at 2 to 3
different locations so as to give max. scop e for contractors residing in far off remote areas to
submit their offers.[ Boards letter No. 90/CE-I/CT/I of 28-10-98, annex.26].
The tenderers should be allowed to drop their offers in the tender bo x up to 15 minutes p rior
to the opening of the tenders where after the boxes may be sealed. This should be indicated
in the NIT.
j.
The tenderers should be allowed to drop their offers in the tender box up to the time sp ecified
in NIT, where after the boxes may be sealed.
k. At the specified time for closing of tenders, the hole in the box should be covered by a slip
p asted over it under the signature of the sup ervisory official holding the key of the tender
box and p referably in the p resence of the Section Officer (Accounts).
l.
Immediately after sealing of the tender box, the same should be kept in the chamber of the
Gazetted officer nomin ated for tender op ening.
Page 18 of 173
Time of Tender
Box placement
Time of tender
box taken in safe
custody by SS E
Signature of
key holding
supervisor
Tender No.
Estimated cost
: Rs.
Earnest Money
: Rs.
DME/S r DME
Page 19 of 173
6.0
Tender should be op ened at the sp ecified time, date and place by the officer nomin ated for the
p urp ose in the p resence of an accounts representative and intending tenderers. The p articulars
of the tenders should be recorded in the register as below:
(a) Serial No.
(b) Date of op ening
(c) Name of the work and tender number
(d) Name of the tenderer
(e) Description of work
(f) Rate quoted by the tenderer
(g) Whether EM D enclosed or not
After making the above entries, the register should be countersigned by the Officer op ening
the tender and Finance rep resentative.
Delayed tenders: Tenders received before the time of openin g but after due date and time of
receip t of tenders.
Late tenders: Tender received after the sp ecified time and date of op ening of tenders.
Delayed and late tenders should be dealt as per the latest guidelines of Railway Board
enumerated in p ara 4.6.
Page 20 of 173
7.0
Page 21 of 173
Page 22 of 173
otherwise of samp les, etc. the entire responsibility shall be of the memb ers of the Technical
Dep artment.
The proceeding of the Tender committee should be signed by all the memb ers of Tender
committee on each and ev ery p age.
Details of estimate:
M ode of tender:
Period of contract:
Tender op ened on :
Tender valid up to :
Remarks:
Scrutiny by Finance
Duty of SSO- Vetting by accounts
The original tenders along with the tabulation statement and briefin g note should b e sent to
Associate Finance for scrutiny and vetting.
The tabulation statement should clearly indicate the following as p er Para 1254 of
Engineering Code.
(a) Complete information in regard to contract rates.
(b) Any special cond itions attached to the rates.
(c) Any other relevant information.
Page 23 of 173
FORMAT OF B RIEFING NOTE FOR TENDERs
Description
1.
Name of Work
2.
Directorate/Division
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13
Master copy of the tender document sealed at tag & signed by Competent
Authority p laced at SI. No.
14.
Whether the offered tender document has been comp ared with master
copy
15.
16.
Tender Notice No. & date (also sp ecify date of p ublication, if different)
17.
Whether comp lete bid documents p ublished on website or not and date of
p ublication.
18.
Remarks
Page 24 of 173
- Whether a min imum criterion is fulfilled.
3. In case of Sp l. Ltd. Tender-Basis of short listed firms.
- Whether minimum criteria is fulfilled.
19.
Whether tender notice period has b een shortened.( App roval of competent
authority)
20.
21.
2.
3.
4.
Tenders op ened by
5.
6.
Validity of offer
7.
level of TC
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
From the p articip ating firms whether business has been banned with any
firm,
Page 25 of 173
Amt. of
tender
docume
nt
dep osite
d
Mode
of EM
(BGs
are not
valid)
No.
&
Date
of
instru
ments
Issuing
bank &
whether
is a
schedule
d bank.
Exe
mpti
ons,
if
any
Wal
val,
if
any
Validity,
if any
indicatin
g last
date of
validity
Whether
cross
checked
with
issuing
Bank
Remar
ks
EMD
8.1
8.2
Page 26 of 173
p erformance of the stip ulation to keep the offer op en for the period specified in the tender
documents or to the Earnest M oney while in their p ossession nor be liable to p ay interest
thereon.
(GCC2010 Annexure 1 Second Sheet, Item No. 6d)
9.0
The security dep osit is for the due fulfillment of the contractual obligations of the tender by the
tenderers. The Security Deposit that is to be recovered from the tenderer shall b e 5% of the
contract value. EMD should be adjusted against security Dep osit and balance shall be recov ered
from the p rogressive bills of the contractors @10% of each bill till it reaches 5% of the contract
value. Security dep osit will be recovered only from the runnin g bills of the contract and no other
mode of collectin g SD such as SD in the forms of instruments like B ank Guarantee, FD etc shall
be accep ted. In case of contracts of value Rs.50 crore and abov e, irrevo cable Bank Guarantee can
also be accep ted as a mode of obtainin g security dep osit. After the work is p hysically comp leted,
security dep osit recovered from the running bills of a contractor can be returned to him if he so
desires, in lieu of FDR/ irrevocable Bank guarantee for equ ivalent amount to be submitted by
him.
Based on completion rep orts, the security dep osit remitted by the contractor has to be
refunded with the app roval of the comp etent authority .
Refund of SD is the last act in any contract. After its refund, the contract is concluded.
In exceptional cases, it can be refunded ev en before the fin alization of the bill.
SD refund should be linked with the performance of the work and the cost incurred by the
dep artment on the rectification should be deducted from it.
Security Deposit shall be returned to the contractor after the exp iry of the maintenance p eriod
in all the cases other than Note (i) mentioned below and after p assing the final bill based on No
Claim C ertificate with the ap p roval of the Competent Authority . The Comp etent Authority
shall normally be the authority who is comp etent to sign the contract. If this Comp etent
Authority is of the rank lower than JA Grade, then a JA Grade Officer (concerned with the
work) should issue the certificate. The certificate, inter alia, should mention that the work has
been comp leted in all resp ects and that all the contractual obligations have been fu lfilled by the
contractor and that there is no due from the contractor to Railway s against the contract
concerned. Before releasin g the SD, an uncond itional and unequ ivocal no claim certificate
from the contractor concerned should be obtain ed.
i.
After the work is p hy sically comp leted, security dep osit recovered from the runnin g
bills of the contractor can b e returned to him if he so d esires, in lieu of FDR/
irrevocab le Bank Guarantee for equiv alent amount to be submitted by him.
ii.
In case of contracts of value Rs 50 crore and above, irrevocable Bank Guarantee
can also be accepted as a made of obtainin g security dep osit.
(Ref: Railway Boards letter no. 2007/CE-1/CT/18 dated 07.03.2008)
Page 27 of 173
b)
c)
The successful bidder shall have to submit a Performance Guarantee (PG) within 30
(thirty) day s from the date of issue of Letter Of Accep tance (LOA). Extension of time for
submission of PG beyond 30 (thirty) day s and upto 60 days from the date of issue of LOA
may be given by the Authority who is comp etent to sign the contract agreement.
However, a panel interest of 15% p er annum shall be charged for the delay bey ond
st
30(thirty ) days, i.e. from 31 d ay after the date of issue of LOA. In case the contractor
fails to submit the requisite PG ev en after 60 days from the d ate of issue of LOA, the
contract shall be terminated du ly forfeiting EM D and other dues if any , p ay able against
that contract. The failed contractor shall be debarred from p articip ating in re-tender for
that work.
The successful bidder shall submit the Performan ce Guarantee (PG) in any of the
followin g forms, amountin g to 5% of the contract value:
A dep osit of Cash.
Irrevocable Bank Guarantee.
Government Securities includ in g State Loan Bonds at 5% below the mark et value.
Dep osit Receipts, Pay Orders, Demand Drafts and Guarantee Bonds. These forms of
Performance Guarantee could be either of the State Bank of India or of any of the
Nationalized Banks.
Guarantee Bonds executed or Dep osit Receipts tendered by all Scheduled Banks.
A Dep osit in the Post Office Sav in g Bank.
A Dep osit in the National Sav in gs Certificates.
Twelve y ears National Defence Certificates.
Ten y ears Defence Deposits
National Defence Bonds and
Unit Trust Certificates at 5% below market value or at the face valu e whichev er is less.
Also, FDR in favour of FA&CAO (free from any encumbrance) may be accepted.
The p erformance gu arantee shall be submitted by the successful bidder after the letter of
Accep tance (LOA) has been issued, but before signin g of the contract agreement. This P.G.
Page 28 of 173
shall be initially valid up to the stip ulated date of comp letion p lus 60 day s bey ond that. In
case the time for comp letion of work gets extended, the contractor shall get the validity of
P.G. extended to cover such extended time for comp letion of work p lus 60 day s.
d) The value of P.G. to be submitted by the contractor will not change for variation upto 25 %
(either increase or decrease). In case during the course of execution, value of the contract
increases by more than 25% of the origin al contract value, an additional Performan ce
Guarantee amountin g to 5% (five p ercent) for the excess value over the original contract
value shall be deposited by the contractor.
e) The Performance Guarantee (PG) shall be released after p hy sical comp letion of the work
based on Completion Certificate issued by the comp etent authority stating that the
contractor has comp leted the work in all resp ects satisfactorily . The Security Dep osit shall,
however, be released only after exp iry of the maintenance p eriod and after p assing the final
bill based on No Claim Certificate from the contractor
f) Wherever the contract is rescinded, the security dep osit shall be forfeited and the
p erformance guarantee shall be encashed and the balance work shall be got done
indep endently without risk and cost of the failed contractor. The failed contractor shall be
debarred from particip ating in the tender for executin g the balance work. If the failed
contractor is a JV or a partnership firm, then every member/partner of such a firm shall be
debarred from p articip ating in the tender for the balance work either in his/her individu al
capacity or as a partner of any other JV/p artnership firm.
g) The engineer shall not make a claim under the Performance Guarantee except for amounts to
which the President of India is entitled under the contract (not withstanding and/or without
p rejudice to any other p rovisions in the contract agreement) in the event of:
i) Failure by the contractor to extend the validity of the Performance Guarantee as
described h erein abov e, in which event the En gineer may claim the fu ll amount of the
Performance Guarantee.
ii) Failure by the contractor to p ay President of India any amount due either as agreed by
the contractor or determined under any of the Clauses/ Conditions of the Agreement,
within 30 days of the service of notice to this effect by Engineer.
iii) The Contract being determined or rescinded und er p rovision of the GCC, the
Performance Guarantee shall b e forfeited in fu ll and shall be absolutely at the disp osal of
the President of India
Legal v etting
Page 29 of 173
11.0 Conditions of Contract: (Ref: Engineerin g Code, Re-Print 1999, Para 1220)
These are the gu idelines clearly definin g the roles, obligation and rights of both the parties i.e.
client & the contractor. These detailed statements reduce the area of clash or disp ute. These are
closely linked to the rates and sp ecifications for an item of the work. Factually drafted conditions
go a lon g way in the successful p erformance of the contract as the contract is between the two
p arties whose objectives are not fully concurrent.
Types of Conditions: The conditions are of two types: General conditions and Special
conditions of contract.
General Conditi ons of Contract: These are the basic conditions of the contract. These are
app licable to all the contracts and provided in the p rinted booklet form. These are revised and
up dated p eriodically by the exp erts. Necessary amendments issued by Railway board from time
to time may please be referred in future.
There are 64 clauses p rovided in GCC. Some of these clauses hav e been rev ised and circulated
by board vide their letter No 2007/CE-I/CT/18 pt.XII dated 31.12.2010.
Special Conditions of Contract: These cond itions are p eculiar to the p articular items of the
work of the contract, hence called the sp ecial cond ition of the contract. These cond itions
stip ulate date of comp letions, maintenance p eriod, guarantee, warranty , p rice variation clause,
the variation in quantity or method of measurement etc. The SCCs are framed by the experien ced
engineers, who know the detailed p rocedures of the various construction activities etc.
The GCC consists of 64 clauses, and deals with various issues, such as:
DEFINIT IONS AND INTERPRET AT ION
Clause1. (1) Definition:- In these General Conditions of Contract, the following terms shall h ave the
meanin g assigned here und er excep t where the context otherwise requires :(a) "Railway" shall mean the President of the Rep ublic of Ind ia or the Administrative Officers of the
Railway or of the Su ccessor Railway authorised to deal with any matters which these p resents are
concerned on his behalf.
(b)"General Manager" shall mean the Officer in-charge of the General Sup erintendence and
Control of the Railway and shall also include the General Manager of the successor Railway .
(c) "Chief Engineer" shall mean the Officer in-charge of the Dep artment of Railway successors of
the Successor Railway.
(d) "Divisional Railway Manager" shall mean the Officer in-ch arge of a Division of the Railway
and shall mean and includ e the Divisional R ailway Manager of the Su ccessor Railway .
Page 30 of 173
(e) "Engineer" shall mean the Divisional En gineer or the Executive En gineer, in executive charge of
the works.
(f) "Engineer's Representative" shall mean the Assistant Engineer, in d irect charge of the works
and shall in clude any Sr. Sec./Sec./Jr.En g.
(h) "Contractor" shall mean and include the Agreement of Work Order, the accep ted schedule of rates
of the Schedule or Rates of Railway .
(i) "Works" shall mean the works to be executed in accord ance with the contract "Sp ecifications"
shall mean the Standard specifications for materials and works of ---------------- Railway as
sp ecified .
(k) "Schedule of Rates of Railway shall mean the schedule of Rates issued under the authority time
to time.
(I) "Drawing" shall mean the map s, drawings, p lans and tracings or p rints there of annexed to the
contract .
(m) "Constructional Plant" shall mean all ap p liances or things of whatsoever nature required for the
execution, of the works
(n) "Temporary Works" shall mean all temp orary works of every kind of works.
(o) "Site" shall mean the lands and other p laces on, under, in or throu gh which the works are to be
carried out.
(p ) "Period of Maintenance" shall mean the sp ecified p eriod of maintenance from the d ate of
comp letion of the works as certified by the Engin eer.
(2) Sin gular and Plural:- Words imp orting the singular number shall also includ e the p lural and vice
versa where the context requires.
(3) Headings & margin al headings:- The headings and marginal headin gs in these gen eral cond ition
are solely for the p urpose of facilitating referen ce and shall not be deemed to be part thereof or be
taken into consideration in the interpretation or construction thereof or the contract. .
Page 31 of 173
GEN ERAL OB LIGAT IONS
Clause 2 (1) Execution Co-relation and intent of contract Documents:- The contract documents be
signed in trip licate by the Railway and the Contractor..
(2) If a work is transferred from the jurisdiction of one Railway to another Railway or to a Project
authority or vice versa while contract is in subsistence, the contract shall be bindin g on the Contractor.
(3) If for admin istrative or other reasons the contract is transferred to the Successor Railway the contract
shall not withstanding any things contained h erein contrary there to, be binding on the Contractor.
Clause 3: (1) Law go verning the contract:- The contract shall be govern ed by the law for the time
bein g in force in the Rep ublic of India.
(2) Compliance to regulations and bye-laws:- The Contractor shall conform to the provision of any
statute relating to the works and regu lations and by e-laws of any local authority and of any water and
lighting companies or undertakin gs.
Clause 4: Communications to be in writing:- All notices, communications, reference and comp laints
made by the Railway or the En gin eer or the En gin eer's R epresentative or the Contractor interse
concernin g the works shall be in writing.
Clause 5: Service of Notices on Contractors:- The Contractor shall furnish to the Engineer the name
designation and address of his authorized agent and all complaints, notices, co mmunications and
references shall be d eemed to have been duly given to the Contractor.
Clause 6: Occupation and use of land:- No land belon gin g to or in the p ossession of the Railway shall
be occup ied by the Contractor without the permission of the Railway . Whenever non-railway
bodies/p ersons are p ermitted to use railway p remises with comp etent authority s app roval, conservancy
charges as ap plicable from time to time may be levied.
Clause 7 Assignment or subletting of contract:- The Contractor shall not assign or sublet the contract
or any p art thereof or allow any p erson to become interested therein any manner whatsoever without the
sp ecial p ermission in writing of the Railway . Any breach of this condition shall entitle the Railway to
rescind the contract under clause 62 of these conditions.
Clause 8. Assistance by the Railway for the S tores to be obtained by the Contractor:- Owing to
difficulty in obtaining certain materials (includ in g Tools & Plant) in the market, the Railway may have
agreed without any liability therefore to endeavour to obtain or assist the Contractor in obtaining the
required quantities of such materials as may be sp ecified in the Tender.
Clause 9. Railway Passes:- No free Railway p asses shall be issued by the Rly . to the Contractor or any
of his emp loyee/worker.
Clause 10.Carriage of materials:- No forwarding orders shall be issued by the Railway for the
conveyance of Contractor's materials, tools and p lant by Rail which may be required for use in the works
and the contractor shall p ay full freight charges at public tariff rates therefore.
Clause 11. Use of ballast trains:Clause 12. Representation on Works:- The Contractor shall, when he is not personally p resent on the
site of the works place and keep a responsible agent at the works during workin g hours. Before
absenting h imself, the Contractor shall furnish the n ame and address of his agent for the p urp ose of this
clause and failure on the p art of the Contractor to comp ly with this p rovision at any time will entitle the
Railway to rescind the contract under clause 62 of these conditions.
Clause 13. Relics and Treasures:- All gold, silver, o il and other minerals of any descrip tion and all
p recious stones, coins, treasures relics antiquities and other similar things which shall be found in or
up on the site shall be the p rop erty of the Railway .
Clause 14. Excavated material:- The Contractor shall not sell or otherwise dispose of or remove except
for the p urp ose of this contract.
Page 32 of 173
Clause 15. Indemnity by Contractors: - The Contractor shall ind emnify and save h armless the
Railway from and against all actions, suit p roceedin gs losses, costs, damages, charges, claims and
demands of every nature and description brought or recovered against the Railway s by reason of any act
or omission of the Contractor
Clause 16. (1) Security Deposit: - The Earnest Money dep osited by the Contractor with his tender will
be retained by the Railway s as p art of security for the due and faithful fulfillment of the contract by the
contractor.
(2) Unless otherwise sp ecified in the sp ecial cond itions, if any , the Security Dep osit/rate of
recovery/mode of recovery shall be as under:
(a) Security Deposit for each work should be 5% of the contract value,
(b) The rate of recovery should be at the rate of 10% of the bill amount till the fu ll security dep osit
is recovered,
(c) Security Deposits will be recovered only from the running b ills of the contract.
(3) No interest will be p ay able up on the Earnest Money and Security Deposit or amounts p ay able to the
Contractor
(4) Performance Guarantee (P.G)
The procedure for obtaining Performance Guarantee is outlined below:
(a) The successful b idder may give Performance Guarantee amountin g to 5% of the contract value in
any of the following forms:(i) A dep osit of Cash. (ii) Irrevocab le Bank Guarantee. (iii) Government Securities including
State Loan Bonds at 5 percent below the market value, (iv) Dep osit Receip ts, Pay Orders, Demand
Drafts and Guarantee Bonds. These forms of Performance Guarantee could be either of the State
Bank of Ind ia or of any of the Nationalized Banks; (v)
Guarantee Bonds executed or Dep osits
Receip ts tendered by all Scheduled Banks; (vi) A Dep osit in the Post Office Saving Bank; (vii) A
Dep osit in the National Savin gs Certificates; (viii) Twelve y ears National Defence Certificates; (ix)
Ten y ears Defence Dep osits; (x) National Defen ce Bonds; and (xi) Unit Trust Certificates at 5 p er
cent below market value or at the face value whichev er is less. Also FDR in favour of FA&CAO/C,
(free from any encumbrance) may be accep ted.
Clause 17. Force Majeure Clause:- If at any time, durin g the continuance of this contract, the
p erformance in whole or in p art by either party of any obligation under this contract shall be prevented
or delay ed by reason of any war, hostility , acts of public enemy , civil co mmotion, sabotage, serious loss
or damage by fire, exp losions, epidemics, strikes, lockouts or acts of God (hereinafter, referred to
events) p rovided, notice of the happening of any such event is given by either party to the other within
30 days from the date of occurrence.
Clause 18.(1) Illegal Gratification:- Any bribe, commission, gift or adv antage given, p romised or
offered by or on behalf to the Contractor or his p artner, agent or serv ant or, any one on his behalf, to any
officer or employ ee of the Railway, or to any p erson on his behalf in relation to obtaining or execution
of this or any other contract with the Railway shall, in addition to any criminal liability which he may
incur, subject contractor to the rescission of the contract .
Page 33 of 173
EXECUT ION OF WORKS
Clause 19.(1) Contractor's understanding:- It is understood and agreed that the Contractor has, by
careful examination, satisfied himself as to the nature and location of the work.
(2) Commencement of works:- The Contractor shall commen ce the works within 15 day s after the
receipt by him of an order in writing to this effect from the Engineer and shall p roceed with the same
with due exp edition and without delay .
(3) Accepted programme of wo rk:- The Contractor who has been awarded the work shall p rovide
p rogramme as soon as p ossible but not later than 30 day s after the date of receip t of the accep tance letter
in respect of contracts with initial comp letion p eriod of two y ears or less or not later than 90 day s for
other contracts.
(4) Setting out of works: - The Contractor shall be resp onsible for the correct setting out of all works in
relation to original p oints.
Clause 20.(1) Compliance to Engineers Instructions:- The Engineer shall d irect the order in which the
several p arts of the works shall be executed and the Contractor shall execute without delay all orders
giv en by the En gineer fro m time to time but the Contractor shall not be reliev ed thereby from
resp onsibility for the due p erformance of the works in all resp ects.
(2) Alterations to be authorised:- No alterations in or additions to or omissions or abandon ment of any
p art of the works shall be deemed authorised.
(3) Extra works:- Should works over and above those in cluded in the contract requ ire to be executed at
the site, the contractor shall have no right to be entrusted with the execution of such works which may
be carried out by another contractor or contractors or by other means at the option of the Railway .
(4) S eparate contracts in connection with works:- The Railway shall have the right to let other
contracts in connection wit h the works. The Contractor shall afford other contractors reasonable
opp ortunity for the storage of their materials and the execution of their works.
Clause 21. Instruction of Engineer's Representative:- Any instructions or ap p roval given by the
Engineer's rep resentative to Contractor in connection with the works shall bind the Contractor as
through it had been giv en by the Engineer provided alway s as follows:(a) Failure of the Engineer's rep resentative to disapp rove any work or materials shall not p rejudice .the
power of the Engineer thereafter to disapp rove such work or material and to order the removal or
breakin g up thereof.
(b) If the Contractor shall be dissatisfied by reason of any decision of the Engineer's rep resentative, he
shall be entitled to refer the matter to the Engineer who shall there up on confirm or vary such
decision.
Clause 22 (1) Adherence to specifications and drawings:- The whole of the works shall be executed
in p erfect conformity with the sp ecifications and drawin gs of the contract.
(2) Drawings and specifications of the works:- The Contractor shall keep one copy of Drawings and
Sp ecifications at the site, in good order.
(3) Ownership of dra wings and specifications:- All Drawings and Specifications and cop ies thereof
furnished by the Railway to the Contractor are deemed to be the p roperty of the Railway .
(4) Compliance with Contractor's request for details:- The Engineer shall furnish with reasonable
promp tness, after receipt by him of the Contractor's request.
(5) Meaning and intent of specification and dra wings:- If any ambiguity arises as to the meanin g and
intent of any p ortion of the Sp ecifications and Drawings or as to execution or quality of any work or
material.
Page 34 of 173
Clause 23. Working during night:- The Contractor shall not carry out any work between sun-set and
sun-rise without the p revious permission of the Engineer.
Clause 24. Damage to Railway property or private life and property:-The contractor shall be
resp onsible for all risk to the work and for tresp ass and shall made good at his own expense all loss or
damage whether to the works themselves or to any other prop erty of the Railway or the lives, p ersons
or p rop erty of others on account of any negligence of contractor in connection with the works until they
are taken over by the Railway and in case the Railway shall be called up on to make good any costs,
loss or damages, or to p ay any comp ensation, includin g that p ay able under the provisions of the
Workmens Comp ensation Act or any statutory amendments.
Clause 25. Sheds, Stores houses and Yards:- The Contractor shall at his own exp ense p rovide himself
with sheds, storehouses and yards.
Clause 26. Provision of efficient and competent staff:- The Contractor shall place and keep on the
works at all times efficient and competent staff .
Clause 27. (1) Workmanship and testing:- The whole of the works and/or supply of materials
sp ecified and p rovided in the contract.
(2) Removal of Imp rop er work and materials:- The Engin eer or the En gineer's Representative shall
be entitled to order from time to time.
Clause 28. Facilities for Inspection:- The Contractor shall afford the En gineer and the Engineer's
Rep resentative every facility for entering in and up on every p ortion of the work at all hours for the
p urp ose of insp ection .
Clause 29.Examination of work before covering up:- The Contractor shall give 7 day s notice to the
Engineer or the En gineer's Rep resentative whenever any work or materials are intended to be covered.
Clause 30. Temporary Works:- All temporary works necessary for the p rop er execution of the works
shall be p rovided and maintain ed by the Contractor and subject to the consent of the Engineer shall be
removed by him at his exp enses.
Clause 31. (1) Contractor to supply water for works:- Unless otherwise p rovided in the Contract, the
Contractor shall be resp onsible for the arrangements to obtain supply of water.
(2) Water supply from Railway System:- The Railway may supp ly to the Contractor p art or whole of
the quantity of the water required for the execution of works from the, Railway 's.
(3) Water supply by Railway Transport:- In the ev ent of the Railway arran ging supp ly of water to the
Contractor at or near the site of works by travelling water tanks or other means, the freight and other
charges incurred thereby , including demurrage ch arges that may be levied, shall be p aid by the
Contractor.
(4)(a) Contractor to arrange supply of Electric power for works - Unless otherwise p rovided in the
contract, the Contractor shall be responsible for arran gements to obtain supp ly of Electric Power for the
works.
(b) Electric supply from the Railway system:- The Railway may supp ly to the Contractor p art or
whole of the electric p ower wherever availab le and p ossible, required for execution of works from the
Railway 's existin g electric sup p ly systems.
Clause 32. Property in materials and plant:- The materials and p lant brought by the Contractor up on
the site or on the land o ccupied by the Contractor in conn ection with the works and intended to b e used
for the execution thereof shall immediately , they are brought up on the site of the said land, be deemed to
be the p rop erty of the Railway .
Clause 33.(1) Tools, Plant and Materials Supplied by Railway:- The Contractor shall take all
reasonable care of all tools, p lant and materials or other p rop erty whether of a like descrip tion or not
belon gin g to the Railway and committed to his charge for the p urp ose of the works and shall be
resp onsible for all damage or loss caused by him.
Page 35 of 173
(2) Hire of Railway's Plant:- The Railway may hire to the Contractor such plant as concrete mixers,
comp ressors and p ortable en gin es for use durin g execution of the works on such terms as may be
sp ecified in the sp ecial conditions or in a separate agreement for Hire of Plant.
Clause 34. (1) Precaution during progress of works:- During the execution of works, unless otherwise
sp ecified, the Contractor shall at his own cost p rovide the materials for and execute all shorin g,
timberin g and strutting works .
(2) Roa ds and Water courses:- Existing roads or water courses shall not be b locked cut through,
altered, diverted or obstructed in any way by the Contractor.
(3) Provision of access to premises:- During progress of work in any street or thoroughfare, the
Contractor shall make adequate p rovision for the p assage of traffic, for securin g safe access to all
p remises.
(4) S afety of Public:- The Contractor shall b e responsible to take all p recautions to ensure the safety of
the p ublic.
Clause 35. Use of Explosives:- Exp losives shall not be used on the works or on the site by the
Contractor without the p ermission of the Engineer. and then only in the manner and to the extent to
which such permission is given. Where explosives are required for the works, they shall be stored in a
sp ecial magazine to be p rovided by and at the cost of the Contractor in accordance with the Exp losive
Rules.
Clause 36. Suspension of works:The Contractor shall on the order of the Engineer susp end the p rogress of the works or any p art thereof
for such time or times and in such manner as the Engin eer may consider necessary , if such susp ension
is:
Provided for in the contract, or
Necessary for the p rop er execution of the works.
Necessary for the safety of the work.
Clause 37. Rates for items of works:- The rates, entered in the accep ted Schedule of Rates of the
Contract are intended to p rovide for works duly and p rop erly comp leted in accordance with the general
and special (if any ) conditions of the contract.
Clause 38. Demurrage and wharfage dues:- Demurrage ch arges calculated in accord ance with the
scale in force for the time bein g on the Railway and incurred by the Contractor.
Clause 39 Rates for extra items of works:- Any item of work carried out by the Contractor on the
instructions of the Engineer or h is rep resentative which is not included in the accep ted schedules of rates
shall be executed at the rates agreed up on between the Engineer and the Contractor, before the execution
of such items of work.
Clause 40. (1) Handing over of works:- The Contractor shall be bound to hand over the works
executed under the contract to the Railway comp lete in all resp ects to the satisfaction of the Engineer.
(2) Clearance of site on completion:- On comp letion of the works, the Contractor shall clear away and
remove from the site all constructional p lant, surplus materials, rubbish and temp orary works of every
kind and leave the whole of the site.
VARIAT IONS IN EXT ENT OF CONTRACT
Clause 41. Modification to contract to be in writing:- In the event of any of the provisions of the
contract requirin g to be modified after the contract docu ments have b een sign ed, the mod ifications shall
be made in writing and sign ed by the Railway and the Contractor and no work shall p roceed und er such
modifications until this has been done.
Page 36 of 173
Clause 42. (1) Powers of modification to contract:- The Engineer on beh alf of the Railway shall be
entitled by order in writing to enlarge or extend, diminish or redu ce the works.
(2) (i) Unless otherwise sp ecified in the sp ecial conditions of the contract, the accep ted variation
in quantity of each individual item of the contract would be up to 25% of the quantity .
(ii) In case of earthwork, the variation limit of 25% shall app ly to the gross quantity of earth
work and variation in the quantities of individual classifications of soil shall not be subject to this
limit. .
(iii) In case of foundation work, no variation limit shall app ly and the work shall be carried out
by the contractor on agreed rates irresp ective of any variation.
(3) Valuation of variations:- The enlargements, extensions, diminution, reduction, alterations or
additions referred to in sub-clause (2) of this clause shall in no degree affect the validity of the
contract.
CLAIMS
Clause 43. (1) Monthly Statement of Claims:- The Contractor shall p repare and furnish to the
Engineer on ce in every month an account givin g full and detailed particulars of all claims.
(2) S igning of "No Claim" Certificate:- The Contractor shall not be entitled to make any claim
whatsoever against the Railway under or by virtue of or arising out of this contract after he shall have
signed a "No Claim" Certificate
Clause 44. Quantities in schedule annexed to Contract:- The quantities set out in the accep ted
schedule of rates with items of works quantified are the estimated qu antities of the works and they shall
not be taken as the actual and correct quantities of the work to be executed by the Contractor in
fulfillment of his obligations under the contract.
Clause 45 Measurement Book: The entire work will be insp ected and rep lacements made therein along
with measurements shall be recorded in a sep arate measurement book.
The Contractor will provide all the facilities to the Insp ecting Officer..
(a) It shall be op en to the Contractor to take specific objection to any recorded measurements or
Classification on any ground within seven d ay s of the date of such measurements. Any re
measurement taken by the Engineer or the En gineer's rep resentative in the presence of the
Contractor.
(b) (b) If an objection raised by the Contractor is found by the Engineer to be incorrect the Contractor
shall be liable to pay the actual exp enses incurred in measurements.
PAYMENT TERMS
Clause 46. (1) "On-Account " Payments:- The Contractor shall be entitled to be p aid from time, to
time by way of "On-Account" p ayment only for such works as in the op inion of the En gin eer h e has
executed in terms of the contract.
(2) Rounding off amounts:- The total amount due on each certificate shall be round ed off to the nearest
rup ee i.e. sum less than 50 paise shall be omitted and sums of 50 p aise and more up to Re.1 /- will be
reckoned as Re. 1 /(3) On Account Payments not prejudicial to final settlement:- "On-Account" p ay ments made to the
'Contractor shall be without p rejudice to the final makin g up of the accounts (except where
measurements are specifically noted in the Measurement Book as "Final Measurements".
(4) Manner of payment:- Unless otherwise sp ecified pay ments to the Contractor will be mad e by
cheque but no cheque will be issued for and amount less than Rs.100/-.
Clause 47. Maintenance of works:- The Contractor shall at all times during the p rogress and
continuance of the works and also for the period of maintenance sp ecified in the Tender Form after the
date of p assing of the certificate of comp letion by the Engineer .
Page 37 of 173
Clause 48. (1) Certificate of completion of works:- As soon as in the op inion of the Engineer, the
work has been comp leted satisfactorily , comp letion certificate shall be p rovided.
(2) Contractor not absolved by com pletion Certificate:- The Certificate of comp letion in resp ect of
the works referred to in sub-clause (1) of this clause shall not absolve the Contractor.
Clause 49. Appro val only by Maintenance Certificate:- No certificate other than maintenance
certificate referred to in Clause 50 of the cond itions shall be deemed to constitute app roval of any work.
Clause 50. (1) Maintenance Certificate:- The Contract shall not be consid ered as comp leted until a
M aintenance Certificate shall hav e been signed by the Engineer stating that the works have been
comp leted and maintain ed to his satisfaction.
(2) Cessation of Railways Liability: The Railway shall not be liable to the Contractor for any matter
arisin g out of or in connection with the contract of the execution of the works.
(3) Unfulfilled Obligations: Railway shall remain liable for the fulfillment of any obligation incurred
under the p rovision of the contract.
Clause 51.(1) Final Payment:- On the Engin eer's certificate of co mpletion in resp ect of the works
adjustment shall be made and the balance of account based on the En gineer or the Engineer's
rep resentative's certified measurements of the total quantity of work executed by the Contractor
(2) Post Payment Audit:- It is an agreed term of contract that the Railway reserves to itself the right to
carry out a p ost-p ay ment audit.
Clause 51-A. Production of vouchers etc. by the Contractor:- For a contract of more than one crore
of rupees, the contractor shall, whenever requ ired, produce or cause to be p roduced for examination.
Clause 52. Withholding and lien in respect of sums claimed:- Whenever any claim or claims for
p ay ment of a sum of money arises out of or under the contract against the contractor.
Clause 52-A Lien in respect of claims in Other Contracts:- Any sum of money due and pay able to
the contractor (includin g the security dep osit returnable to him) under the contract.
Clause 53. Signature on Receipts for Amounts:- Every receip t for money which may become p ay able
or for any security which may become transferable to the Contractors under these p resents.
LABOUR
Clause 54. Wages to Labour: - The Contractor shall be resp onsible to ensure comp liance with the
p rovision of the M inimum Wages Act, 1948 (hereinafter referred to as the "said Act" and the Rules
made there under in resp ect of any emp loy ees directly or through p etty contractors or subcontractors
emp loy ed by him on road construction or in building op erations or in stone breaking or stone crushing
for the p urp ose of carry ing out this contract.
Clause 54-A Apprentices Act: - The Contractor shall be resp onsible to ensure compliance with the
p rovisions of the Apprentices Act, 1961 and the Rules and Orders issued there under from time to time
in respect of app rentices directly or through p etty contractors or sub-contractors emp loy ed by him for
the p urp ose of carry ing out the Contract.
Clause 55. Provisions of payments of Wages Act: - The Contractor shall comp ly with the provisions
of the Pay ment of Wages Act, 1936 and the rules made there under in resp ect of all emp loy ees directly
or through p etty contractors or sub-contractors employ ed by him in the works.
Clause 55-A (1) Provisions of Contract labour (Regulation and Abolition) Act, 1970 - (1) The
Contractor shall comply with the p rovision of the contract labour (Regulation and Abolition) Act, 1970.
(2) The Contractor shall obtain a valid licence under the aforesaid Act.
(3) The Contractor shall p ay to the labour emp loy ed by him directly or through subcontractors the wages
as p er p rovision of the aforesaid Act and the Rules wherever ap p licable.
(4) In resp ect of all labour directly or indirectly employ ed in the work for p erformance of the
contractor's part of, the contract.
(5) In every case in which, by virtue of the p rovisions of the aforesaid Act or the Rules, the Railway is
obliged to p ay any amount of wages to a workman emp loyed by the Contractor.
Page 38 of 173
Clause 56. Reporting of Accidents to Labour:- The Contractor shall be resp onsible for the safety of
all emp loy ees directly or through p etty contractors or sub-contractor employ ed by him on the works and
shall rep ort serious accidents to any of them.
Clause 57. Provision of Workmens Compensation Act:- In every case in which by virtue of the
p rovisions of Section 12 Sub-section (1) of the Work men's Compensation Act 1923, Railway is obliged
to p ay comp ensation to a workman directly or through petty contractor or subcontractor employ ed by
the Contractor in executin g the work.
Clause 58. Railway not to pro vide quarters for Contractors: - No quarters shall normally be
p rovided by the Railway for the accommodation of the Contractor or any of his staff.
Clause 59. (1) Labour Camps:- The Contractor shall at his own exp ense make adequate arrangements
for the housing.
(2) Compliance to rules for employment of labour: - The Contractor(s) shall conform to all laws, by elaws rules and regulations.
(3) Preservation of peace: The Contractor shall take requisite precautions and use his best endeavours to prevent
any riotous or unlawful behaviour.
(4) S anitary arrangements: The Contractor shall obey all sanitary rules and carry out all sanitary measures that
may from time to time be prescribed by the Railway medical Authority
(5) Outbreak of infectious disease: The Contractor shall remove from his camp such labour and their families as
refuse protective inoculation and vaccination.
(6) Treatment of Contractor's staff in Railway Hospitals: T he Contractor and his staff, other than labourers
and their families requiring medical aid from the Railway Hospital and dispensaries will be treated as private patients.
(7) Medical facilities at site: - The Contractor shall p rovide medical facilities at the site.
(8) Use of intoxicants. The sale of ardent spirits or other intoxicating beverages upon the work or in any of the
buildings, encampmentsor tenements owned, occupied
(9) Non-employment of female labour: The Contractor shall see that the employment of female labour on in
Cantonment areas, particularly in the neighborhood of soldiers barracks, should be avoided as far aspossible.
(10) Restrictions on the employment of retired Engineers of Railway services within two years of
their retirement.
Clause 60. (1) Non-employment of labourers below the age of 15:- The Contractor shall not emp loy
children below the age of 15 as labourers directly or through p etty contractors or subcontractors for the
execution of work.
(2) Medical Certificate of fitness for labour:- It is agreed that the contractor shall not emp loy a p erson
above 15 and b elow 19 y ears of age for the p urp ose of execution of work under the contract unless a
medical certificate p roduced.
(3) Period of validity of medical fitness certificate: - A certificate of fitness granted or renewed for the
above said p urp oses shall be valid only for a p eriod of one y ear.
(4) Medical re-examination of labourer:
DET ERMINATION OF CONTRACT
Clause 61. (1) Right of Railway to determine the contract: - The Railway shall be entitled to
determine and terminate the contract at any time should, in the Railway s op inion, the cessation of work
becomes necessary owing to p aucity of funds or from any other clause whatever, in which case the value
of ap proved material at site and of work done to date by the Contractor will be paid for in fu ll at the rate
sp ecified in the contract.
(2) Payment on determination of contract: - Railway s shall admit and consider such claims as are
deemed reasonable and are supp orted by vouchers to the satisfaction of the Engineer.
(3) The Contractor shall have no claim to any p ay ment of compensation or otherwise, howsoever on
account of any p rofit or advantage which he might have derived from the execution of the work in full
but which he did not derive in consequ ence of d etermination of contract.
Clause 62, Determination of contract owing to default of contractor: - If the Contractor should:Becomes bankrup t or insolvent, or
Page 39 of 173
Bein g a company or corp oration, go into liquidation (other than a voluntary liquidation for the
p urp ose of amalgamation or reconstruction), or
Assigns the contract or any p art thereof otherwise than as provided in Clause 7 of these
conditions (GCC clause 7)or
Abandon the contract, or
Persistently disregard the instructions of the Engineer or contravene any provision of the
contract, or
Fails to adhere to the agreed p rogramme of work by a margin of 10 percent of the stip ulated
p eriod, or
Fails to remove materials from the site or to p ull down and rep lace work after receivin g the
Engineer notice to the effect that the said materials or works have been rejected and condemned
under clause 25 & 27 of GCC or
Fails to take step s to emp loy competent or additional staff and Labour as required under clause
26 of GCC of the conditions, or
Fails to afford the En gin eer or En gin eers rep resentative p rop er facilities for insp ecting of the
works or any p art there of as required under clause (28) of GCC or
Promise, offer or give any bribe, commission, gift or advantage either himself or through his
p artner, agent or servant to any officer or emp loy ee of the Railway or to any p erson on his or on
their behalf in relation to the execution of this or any other contract with the Railway .
S ETTLEMENT OF DIS PUTES INDIAN RAILWAY ARBITRATION RULES
Clause 63. Matters finally determined by the Railway All disp utes and differences of any kind
whatsoever arisin g out of or in connection with the contract, whether durin g the p rogress of the work or
after its completion and whether before or after the determination of the contract, shall be referred by the
contractor to the GM and the GM shall within 120 day s after receip t of the contractors rep resentation
make and notify decisions on all matters referred to by the contractor in writing provided that matters for
which p rovision has been made in clauses 8, 18, 22(5), 39, 43(2), 45(a), 55, 55-A(5), 57, 57A,61(1),
61(2) and 62(1) to (xiii) (B) of General Conditions of contract or in any clause of the special cond itions
of the contract shall be deemed as excepted matters (matters not arbitrable) and decisions of the
Railway authority , thereon shall be final and b indin g on the contractor; p rovided further that excep ted
matters shall stand sp ecifically excluded from the purview of the arbitration clause.
Clause 64 (1) (i) - Demand for Arbitration-In the event of any disp ute or differen ce between the p arties
hereto as to the construction or op eration of this contract, or the resp ective rights and liabilities of the
p arties on any matter in question, disp ute or difference on any account or as to the withholding by the
Railway of any certificate to which the contractor may claim to be entitled to, or if the Railway fails to
make a decision within 120 day s, then and in any such case, but excep t in any of the excep ted matters
referred to in C lause 63 of these conditions, the contractor, after 120 d ay s but within 180 days of his
p resenting his final claim on disp uted matters shall demand in writin g that the disp ute or difference be
referred to arbitration.
64 (1) (ii) - The demand for arbitration shall sp ecify the matters which are in question, or subject of the
disp ute.
64 (1) (ii) - (a) The Arbitration proceedings shall be assumed to have co mmen ced from the day , a
written and valid demand for arbitration is received by the Railway.
(b) The claimant shall submit his claim stating the facts supp orting the claims alon g with all the relev ant
documents and the relief or remedy sought against each claim within a p eriod of 30 day s.
(c) The Railway shall submit its defence statement and counter claim(s), if any, within a p eriod of 60
day s.
(d) The p lace of arbitration would be within the geo graphical limits of the Division of the Railway
where the cause of action arose or the Headqu arters.
Page 40 of 173
64 (1) (iii) - No new claim shall be added durin g p roceedin gs by either p arty . However, a party may
amend or supp lement the original claim.
64 (1) (iv) - If the contractor(s) does/do not p refer his/their sp ecific and final claims in writing, within a
p eriod of 90 day s of receiving the intimation from the Railway s that the final bill is ready for p ay ment.
64 (2) - Obligation Durin g Pendancy of Arbitration - Work under the contract shall, unless otherwise
directed by the Engineer, continue durin g the arb itration p roceedings.
64 (3) (a) (i) - In cases where the total value of all claims in question added together does not exceed
Rs.10,00,000/- (Rupees ten lakhs only ), the Arbitral tribunal shall consist of a sole arbitrator who shall
be a gazetted officer of Railway .
64 (3) (a) (ii) - In cases not covered by the clause 64(3) (a)(i), the Arbitral Tribunal shall consist of a
Panel of three Gazetted Rly . Officers not below JA grade or 2 Railway Gazetted Officers not below JA
Grade and a retired Railway Officer, retired not below the rank of SAG Officer, as the arbitrators.
64 (3) (a) (iii) - If one or more of the arbitrators appointed as above refuses to act as arbitrator,
withdraws from his office as arbitrator, or vacates his/their office/offices or is/are unab le or unwillin g to
p erform his functions as arbitrator for any reason whatsoever or dies or in the op inion of the General
M anager fails to act without undue delay , the General M anager shall ap p oint new arbitrator/arbitrators.
64 (3) (a) (iv) - The arbitral Tribunal shall have p ower to call for such evidence by way of affidavits or
otherwise as the Arbitral Tribunal shall think p roper, and it shall be the duty of the p arties hereto to do
or cause to be done all such things as may be necessary to enable the Arbitral Tribunal to make the
award without any delay .
64 (3) (a) (v) - While ap p ointing arbitrator(s) under sub-clause (i), (ii) & (iii) above, due care shall be
taken that he/they is/are not the one/those who had an opportunity to deal with the matters to which the
contract relates or who in the course of his/their duties as Railway servant(s) exp ressed views on all or
any of the matters under dispute or differences.
64 (3) (b) (i) - The arbitral award shall state item wise, the sum and reasons up on which it is based. The
analy sis and reasons shall be detailed enou gh so that the award could be inferred there from.
64 (3) (b) (ii) - A party may app ly for corrections of any computational errors, any typ ographical or
clerical errors or any other error of similar n ature occurring in the award of a tribunal and interp retation
of a specific point of award to tribunal within 60 day s of receip t of the award.
64 (3) (b) (iii) - A p arty may app ly to tribunal within 60 day s of receip t of award to mak e an add itional
award as to claims p resented in the arbitral proceedin gs but omitted from the arbitral award.
64 (4) In case of the Tribunal, co mp rising of three M embers, any rulin g on award shall be mad e by a
majority of Members of Tribunal. In the absence of such a majority, the views of the Presiding
Arbitrator shall p revail.
64 (5) where the arbitral award is for the pay ment of money , no interest shall be p ay able on whole or
any p art of the money for any p eriod till the date on which the award is made.
64 (6) The cost of arbitration shall be borne by the resp ective p arties. The cost shall inter-alia include fee
of the arbitrator(s), as p er the rates fixed by the Railway Board from time to time and the fee shall be
borne equally by both the p arties.
64 (7): Sub ject to the p rovisions of the aforesaid Arbitration and Conciliation Act 1996 and the rules
there under and any statutory modifications thereof shall app ly to the arbitration p roceedin gs under this
clause.
Clause 65 to IR's General Conditions Of Contract (GCC)
{Ref : Railway Board's letter no. 2002/CE-I/CT/37, New Delh i, dated 07.09.2011}
Clause 65. Participation Of Joint Venture (JV) Firms In Works TenderThis Clause shall be ap p licable for works tenders of value as approved and communicated by Railway
Board from time to time.
65.1 Sep arate identity/name shall be given to the Joint Venture Firm.
Page 41 of 173
65.2 Number of members in a JV Firm shall not be more than three, if the work involves only one
dep artment (say Civil or S&T or electrical or M echanical) and shall not be more than five, if the work
involves more than one d ep artment.
65.3 A member of JV Firm shall not be permitted to p articip ate either in individual cap acity or as a
member of another JV Firm in the same tender.
65.4 The tender form shall be p urchased and submitted only in the name of the JV Firm and not in the
name of any constituent member.
65.5 Normally EM D shall b e submitted only in the name of the JV Firm and not in the name of
constituent member. However, in excep tional cases EM D in the name of Lead Member can b e accep ted
subject to submission of sp ecific requ est letter from Lead Member stating the reasons for not submitting
EM D in the name of JV Firm and givin g written confirmation from JV members to the effect that EMD
submitted by the Lead M ember may be deemed as EM D submitted by JV Firm.
65.6 One of the members of the JV Firm shall be its Lead Member who shall have a majority (at least
51%) share of interest in the JV Firm and also, must have satisfactorily comp leted in the last three
p revious financial y ears and the current financial y ear up to the date of op ening of the tender, one
similar sin gle work for a minimum value of 35% of advertised tender valu e. The other members shall
have a share of not less than 20% each in case of JV Firms with up to three members and not less than
20% each in case of JV Firms with more than three members. In case of JV Firm with foreign member
(s), the Lead Member has to be an Indian Firm with a M inimum share of 51%.
65.7 A cop y of M emorandum of Understanding (MOU) executed by the JV members shall be submitted
by the JV Firm alon gwith the tender. The comp lete details of the members of the JV Firm, their share
and resp onsibility in the JV Firm etc. p articularly with reference to financial, technical and other
obligations shall be furnished in the M OU. (The MOU format for this p urp ose shall be finalized by the
Railway in consultation with their Law Branch and shall b e enclosed alongwith the tender.)
65.8 Once the tender is submitted, the MOU shall not be modified / altered / terminated during the
validity of the tender. In case the tenderer fails to observe/comp ly with this stipulation, the full Earnest
M oney Dep osit (EM D) shall be liable to be forfeited.
65.9 App roval for change of constitution of JV Firm shall be at the sole discretion of the Emp loy er
(Railway s). The constitution of the JV Firm shall not be allowed to be modified after submission of the
tender bid by the JV Firm, excep t when modification b ecomes inevitable due to succession laws etc. and
in any case the minimum eligibility criteria should not get vitiated. However, the Lead M ember shall
continue to be the Lead M ember of the JV Firm. Failure to observe this requirement would render the
offer invalid.
65.10 Similarly , after the contract is awarded, the constitution of JV Firm shall not be allowed to be
altered durin g the currency of contract excep t when modification become inevitable due to succession
laws etc. and in any case the min imum eligib ility criteria should not get vitiated. Failure to observe this
stip ulation shall be deemed to be breach of contract with all consequential p enal action as p er contract
conditions.
65.11 On award of contract to a JV Firm, a single Performance Guarantee shall be submitted by the JV
Firm as p er tender conditions. All the Guarantees lik e Performan ce Guarantee, Bank Guarantee for
M obilization Advance, M achinery Advance etc. shall be accep ted only in the name of the JV Firm and
no sp litting of gu arantees amon gst the members of the JV Firm shall b e permitted.
65.12 On issue of LOA (Letter Of Acceptance), an agreement amon g the members of the JV Firm (to
whom the work has been awarded) shall be executed and got registered before the Registrar of the
Companies under Comp anies Act or before the Registrar/Sub-Registrar under the Registration Act,
1908. This JV A greement shall be submitted by the JV Firm to the Railway s before signin g the contract
Page 42 of 173
agreement for the work. In case the tenderer fails to observe/comp ly with this stipulation, the full
Earnest M oney Deposit (EMD) shall be forfeited and other p enal actions due shall be taken against
p artners of the JV and the JV. This Joint Venture Agreement shall hav e, inter-alia, followin g Clauses:
65.12.1 Joint And Several Liability - M embers of the JV Firm to which the contract is awarded, shall be
jointly and severally liable to the Emp loy er (Railway s) for execution of the p roject in accordance with
General and Sp ecial Conditions of Contract. The JV members shall also be liable jo intly and severally
for the loss, damages caused to the Railway s during the course of execution of the contract or due to
non-execution of the contract or p art thereof.
65.12.2 Duration of the Joint Venture A greement - It shall be valid durin g the entire currency of the
contract includin g the p eriod of extension, if any and the maintenance p eriod after the work is
comp leted.
65.12.3 Governin g Laws- The Joint Venture Agreement shall in all resp ect be gov erned by and
interpreted in accordance with Indian Laws.
65.13 Authorized M ember - Joint Venture memb ers shall authorize one of the memb er son behalf of the
Joint Venture Firm to deal with the tender, sign the agreement or enter into contract in resp ect of the said
tender, to receiv e p ayment, to witness joint measurement of work don e, to sign measurement books and
similar such action in resp ect of the said tender/contract. All notices/corresp ondences with resp ect to the
contract would be sent only to this authorised member of the JV Firm.
65.14 No member of the Joint Venture Firm shall hav e the right to assign or transfer the interest right or
liability in the contract without the written consent of the other member sand that of the emp loy er
(Railway s) in resp ect of the said tender/contract.
65.15 Documents to be enclosed by the JV Firm alon gwith the tender:
65.15.1 In case one or more of the members of the JV Firm is/are partnership firm (s), following
documents shall be submitted:
(a) Notary certified cop y of the Partnership Deed,
(b) Consent of all the partners to enter into the Joint Venture Agreement on a stamp p ap er of
app ropriate value (in original).
(c) Power of Attorney (duly registered as p er prevailing law) in favour of one of the p artners of the
p artnership firm to sign the JV Agreement on behalf of the p artner ship firm and create liab ility
against the firm.
65.15.2 In case one or more members is/are Prop rietary Firm or HUF, the followin g do cuments shall be
enclosed:
Affidavit on Stamp Pap er of app ropriate value declarin g that his/her Concern is a Proprietary Concern
and he/she is sole p rop rietor of the Concern OR he/she is in p osition of "KARTA" of Hindu Undivided
Family (HUF) and he/she has the authority, p ower and consent given by other partners to act on behalf
of HUF.
65.15.3 In case one or more members is/are limited comp anies, the following documents shall be
submitted:
(a) Notary certified copy of resolutions of the Directors of the Comp any , p ermitting the comp any to
enter into a JV agreement, authorizing M D or one of the Directors or M anagers of the Comp any to sign
JV A greement, such other do cuments required to be signed on beh alf of the Comp any and enter into
liability against the comp any and/or do any other act on behalf of the comp any .
(b) Copy of Memorandum and Articles of Association of the Comp any .
(c) Power of Attorney (duly registered as per p revailin g law) by the Comp any authorizing the person to
do/act mentioned in the p ara (a) above.
Page 43 of 173
65.15.4 All the M embers of JV shall certify that they are not black listed or debarred by Railways or any
other Ministry/Dep artment of the Govt. of India/State Govt. from p articipation in tenders/contract on the
date of op ening of bids either in their individu al cap acity as members of the JV or the JV Firm in which
they were/are members.
65.16 Credentials & Qualifyin g Criteria : Techn ical and finan cial eligibility of the JV Firm shall be
adjud ged based on satisfactory fulfillment of the following criteria:
65.16.1 Technical Eligibility Criteria Ca' or 'b' mentioned hereunder) :
(a) Either the JV Firm or Lead M ember of the JV Firm must have satisfactorily completed in the last
three previous financial y ears and the current financial y ear up to the date of opening of the tender, one
similar sin gle work for a minimu m of 35'10of advertised value of the tender.
OR
(b) (i) In case of comp osite works (e.g. works involvin g more than one distinct comp onent, such as Civil
Engineerin g works, S&T works, Electrical works, OHE works etc. and in the case of major brid ges substructure, sup erstructure etc.). for each component, at least 35'10of the value of any of such
comp onents individually for single similar nature of work should have been satisfactorily completed by
the JV Firm or by any member of the JV Firm in the previous three financial y ears and the current
financial y ear up to the date of op ening of tender. The member satisfy ing technical eligibility criteria for
the largest comp onent of the work shall be the Lead M ember and that Member shall h ave a majority (at
least 51'10) share of interest in the JV Firm.
(ii) In such cases, what constitutes a comp onent in a comp osite work shall be clearly p re-defined
with estimated tender cost of it, as part of the tender documents without any ambiguity . Any work or set
of works shall be considered to be a sep arate component, only when cost of the comp onent is more than
Rs.2 crore each.
(iii) However, as lon g as the JV Firm or any member of the JV Firm meets with the requirements, in
one or more co mp onents of the work, and has comp leted a min imum of 35'10 of the advertised valu e of
the tender for the same value of the comp onent, and resultantly , all the members of the JV collectively,
then meet the p rescribed technical eligib ility criteria, the JV shall stand technically qualified.
Note: Value of a co mp leted work done by a M ember in an earlier JV Firm shall b e reckoned only to the
extent of the concerned member's share in that JV Firm for the p urp ose of satisfying his/her comp lian ce
to the above mentioned technical eligibility criteria in the tender under consideration.
65.16.2 Financial Eligibility Criteria: The contractual p ay ments received by the JV Firm or the
arithmetic sum of contractual p ay ments received by all the memb ers of JV Firm in the p revious three
financial y ears and the current financial y ear up to the date of opening of tender shall be at least 150'10
of the estimated value of the work as mentioned in the tender.
Note: Contractual p ay ment received by a Member in an earlier JV Firm shall be reckoned only to the
extent of the concerned member's share in that JV Firm for the purp ose of satisfy ing comp liance of the
above mentioned financial eligibility criteria in tender under consideration.
The amount payable on account of Price variatio n shall be settled every quarter as per the following method:(i)
The amount paid during a quarter shall be divided as under: X % Labour
- T o be fixed by Railways
Y % Material
- DOZ % Fixed Component (this implies the cost of machines and fixed installations) DO(ii) No price variation shall be payable on the fixed component of the cost, if any.
Page 44 of 173
(iii) For calculation of PV on account of Labour, the Consumer Price Index Numbers for industrial workers
(Base 2001 = 100) published as Sh.35 in RBI Bulletins shall be used. T he base shall be taken as the index no.
(All India Average) as on date of opening of tender. For a particular quarter, the average index for that quarter
shall be worked out and variation with reference to the base index no. shall be taken into account for calculation
purpose.
(iv) For material portion, Statement 39 o f RBI Bulletin (All India Average) sh all be used. T he calcul ation o f Pri ce
Variation payable illustrated as under.
(v)
Illustration:Amount paid in the first quarter = Rs 10,00,000/- (say)
Price Index for Labour as on date of opening
(Lo)
= 450
Price Index for material as on date of opening (Mo)
= 160
st
Avg. Price index for Labour during I quarter (L1) = (452 + 456 + 455) / 3 = 454.3, where 452, 456 and
455 are the indices for the three months in the quarter under consideration.
st
Avg. Price index for material during I quarter (M1) = (165 + 164 + 168) / 3 = 165.7, where 165,164 and
168 are the indices for the three months in the quarter under consideration.
Bifurcation of amount paid is as under: -( assuming X=55 and Y=45)
Labour (W)
Rs. 5,50,000/Material (M)
Rs. 3,00,000/Fixed
Rs. 1,50,000/PV for Labour = (L1 Lo) x W/Lo= (454.3 - 450) x 5, 50,000 /450 =
PV for material = (M1 Mo) x M / Mo
i.e (165.7 - 160) x 3,00,000 /160
Rs 5,255/-
Rs 10,687/-
No Price Variation will be payable on Rs. 1,50,000/- (i.e. the fixed component)
The contract will be valid for a p eriod of 3 years with a p rovision for annual p rice variation as exp lained
in Price Variation clause.
Page 45 of 173
As p er extent instructions of Railway Board, issued vide letter no. 2008/ C E-I/ CT/ Con / 7
(PCE/GM ) dated 15.12.08, the eligibility criteria p rescribed by Sudhir Chandra Committee
would app ly only to tender of tenders of value more than Rs. 20 lakh. Since the limit was fixed
in the y ear 2008 and considerin g the need to increase this limit, Board have now decid ed that this
limit be enhanced to Rs. 50 lakh. Other conditions given in the letters referred above shall,
however, remain same.
Note: (A) However, the above eligibility criteria may be modified on case to case basis in resp ect of
urgent Project/Works and sp ecialised nature of work with concurrence of FA&CAO and
p ersonal approval of General M anager.
Note- The single similar work completed will be considered as under,
(1) Total value of similar nature of works comp leted durin g the qualify in g p eriod, and not the p ay ment
receiv ed within qualifyin g p eriod alone will be considered.
In case fin al b ill of similar n ature of work has not been p assed, paid amount includ in g statutory
deductions is to be considered if fin al measurements have not been recorded OR if fin al
measurements have been recorded and work has been comp leted with negative variation.
However, if final measurements have been record ed and work has b een comp leted with p ositive
variation but variation has not been sanctioned, origin al contractual valu e of work will be
considered for jud gin g eligibility .
(2)
In the case of comp osite works involving combin ation of different works, even separate PORTION
OF SIMILAR WORK comp leted works of required value i. e 35% of total tender v alue will be
considered while evaluatin g the eligibility criteria.
(B) The following documents should be specified for submission along with tender.
o
List of Personnel, Organisation av ailable on hand and p rop osed to be engaged for the subject
work.
o
List of Plant and M achinery available on hand (own) and p rop osed to be inducted (own and
hired to be given sep arately ) for the subject work.
o
List of Works comp leted in the last three financial y ears givin g descrip tion of work,
organ ization for whom executed, ap p roximate value of contract at the time of award, date of
award and date of scheduled co mp letion of work. Date of actual start, actual comp letion and
Page 46 of 173
final value of contract should also be given.
o
List of works on hand indicating d escrip tion of work, contract value, ap p roximate value of
balance work y et to be done and date of award.
Note: 1. In case of items (c) and (d) abov e, supp ortive documents/ certificates from the
organ izations with whom they worked/are workin g should be en closed.
2. Certificates fro m p rivate indiv iduals for whom such works are executed/ b ein g executed
should not be accep ted.
13.0 Tender Committee (Ref: En gineerin g Code, Re-Print 1999, Para 1255)
Tender Committee is to be formed for ev aluatin g the offers. The level of TC and numb er of
members in it, dep end on the value of the work. For works tenders of value upto Rs.20 lakh,
the tender committee shall hereafter be constituted with only two members out of which, one
should essentially be from the Accounts Deptt. and the other from the concerned Executive
Deptt. However, the existing p ractice of three memb er Tender Committee will continue to be
app licable for tenders of v alue more than Rs. 20 lakh each. Tender Committee should evaluate
the documents/credentials submitted by the tenderer and assess the eligibility . Tender
Committee/Tender Callin g authority should not enter into corresp ondence with the tenderer
after the tender is op ened. However, origin als of certificates, documents, testimonials etc.,
already submitted by the tenderer alon g with his/her tender may be called for and their
genu ineness verified by checkin g the originals or by verification from the concerned
dep artments, if needed. Any p ap er submitted by the tenderer after op ening of the tender, should
not be given any cognizance.
The TC will record the minutes and their recommendations. Recommendations will normally be
accep ted by the Tender Accepting Authority (TAA). After accep tance, letter of accep tance
(LOA) is issued to the contractor.
13.1 Constitution of Tender Committee is tabulated as under
Value
Accepting
Authority
Executive
Accounts
Other
deptt.
Sr.Scale
Jr.Scale
-----
JAG/SG
Sr.Scale
Jr.Scale
Sr.Scale
JAG/SG
Sr.Scale
Sr.Scale
Sr.Scale
JAG/SG
JAG/SG
JAG/SG
JAG/SG
SAG/ADRM
Tender is accep ted for and on behalf of the Presid ent of India by an Authority comp etent to
do so. This is stipulated in the schedule of p owers.
Tender Accep ting Authority accep ts the tender on the basis of p roceedings on the TC.
The level of TAA should be at the least one rank above the memb ers of TC.
In case of sin gle tender, committee will be one stage high er as mentioned above.
Page 47 of 173
TC members should give an undertaking at the appropriate time, that none of them has
any personal interest in the companies / agencies participating in tender process and that
any member having interest in any company should be refrained from participating in
TC.
(RB letter No 94/C-1/CT/4(Pt ii) dt19.11.05)
Financial capacity, capability and past performance of tenderer / contractor should be
investigated / examined in detail by TC before recommending for awarding a contract
duly considering existing work load with the tenderer (s).
Tender committee to be constituted as per SOP.
All the me mbers are collectively responsible for given recommendations.
Eligibility criteria of tenderers have to be exa mined in detail.
The Tender committee minutes should be self contained and self e xplanatory .
Rate reasonability of individual ite m to be exa mined.
TCM to be finalised within validity of tender.
No TC me mber to be related with any of the tenderer.
Each page of TCM to be signed with date.
TC to verify that:
Page 48 of 173
Page 49 of 173
All tenders are correctly filled and if there are corrections and overwriting then they have
been initialed by tender op ening officials.
Tender have been op ened correctly .
Earnest money is requisite and in accep table form.
All valid tender offers are serially p laced and put up in a comparative statement along with
a briefin g note, duly vetted.
All sp ecial conditions have b een mentioned and those having fin ancial imp lications are
evaluated.
The arithmetical accuracy of the offer.
A p rop er rate analy sis has been prep ared and p laced on record by the Convenor.
The funds p osition and if work is sanctioned or not.
The p artnership deed and any legal issue involved is examined.
All sp ecial conditions havin g financial rep ercussions have been examin ed.
Consistent app roach is taken in dealin g with tender for all similar cases, as he is a common
member for all tenders.
Responsibility of TC as a whole:
It is the collective resp onsibility of the TC to give a definite reco mmend ation with full facts
and reason brin gin g out all the known facts, back ground and v alid ap p rehensions, which
have formed the basis for its recommendation.
It must also clearly sp ecify the authority comp etent to consider recommend ations of the
TC.
Page 50 of 173
A current market survey with a prop er rate analy sis of at least those items, which constitute
above 75-80% of the total cost, i.e. by an ABC analysis.
The rate analy sis is p repared by the Convenor but TAA must examine whether the analy sis
is based on data / survey from the market.
Comp arison of last accepted rate for it ems, which are similar and comp arable. All such
rates may be brought out and not only those which are favorable.
If a lower offer is bein g overlooked, sufficient reasons have to be given for doin g so.
If some adv erse factors are cited for justifying high er rates, they must be explained
adequately to justify the action.
If high rates are justified on the basis of urgency, the fact should be available on record.
Rates reasonableness on the basis of quotations is debatable.
The first step is to examine all the basic facts about the tender.
Whether the recommendation of TC is unanimous or otherwise.
Even in case of unanimous recommendation, all the asp ects about reasonableness of the
rate must be examined. Any deficiency noticed may be referred to TC.
TAA can not function as a rubber stamp and must app ly his/ her mind indep endently and
such app reciation should be visible. The acceptance or otherwise must be recorded on the
body of TC p roceedin g itself.
In case of non-unanimous recommendations, if TAA wants to accept either single or
majority recommend ation, it should record detailed reasons for doin g so.
TC recommendations should normally be accep ted, but in case TAA rejects/ modifies the
same, grounds should be given for the same.
It is not correct to obtain additional details from a third person but if such details are
considered necessary , TC should be asked to obtain them and p ut up to TAA after p rop er
examin ation of the same by TC.
TAA should take the decision in a reasonab le period of time. Unavo idable delay s should be
explain ed.
Page 51 of 173
14.0 Negotiation:
There should normally be no negotiations strictly be an exception rather than rule and only
where rates received are unjustifiably high er and also in situation of cartel formation with
unreasonable rates.
2.
3.
There shall b e no compromise to transp arency , equity or fair treatment in accep tance of
tenders. Prescribed time frame of settling tenders is to be strictly adhered to.
(Rly. Bds letter no. 99/RS (G)/779/2 dated 15.10.2007 RBS No. 15/2007)
The negotiation should be with technically accep table L1 and to be resorted in following
excep tional cases: Where the lowest tender is consid ered to be unreasonably high, and it is felt that retendering would not secure better advantage to the Railway and / or
Where lowest tender is not accep table due to any reason and next higher offer is found
to be unreasonably high
Tender to be discharged if negotiations fail
(RB Letter no 2008/CEI/CT/1 D AT ED 12/09/08)
A tenderer during negotiations is required to giv e a declaration that in event of failure of
negotiation, h is original offer shall remain op en for accep tance and not allowed to increase
rates of any of items.
Board has modified existin g form of declaration.
Page 52 of 173
Sometimes, counter offer may be given to the contractor on the reduced rate or without
accep ting some conditions.
Page 53 of 173
Best way to communicate it through the observation in the site order book (it is very
imp ortant and useful in case of arbitration).
Do not delegate to lower official to do any corresp ondence with the contractor.
Do not leave any of the contractors letter unanswered. There should be no amb iguity in
reply . It should be in clear terms.
All the sp ecial conditions discussed in the TC should b e clearly brought out in the
agreement.
Watch should be kep t on the financial imp lications of various sp ecial cond itions. Finance
generally keep close scrutiny of all sp ecial conditions.
Watch should be kep t on variations.
Page 54 of 173
All p ay ments are made on the b asis of measurements made in the M . Book (M B).
Measurements must be recorded directly in the M Bs by authorized officials.
Prescribed ch ecks on measurements should be carried out by senior officers in M Bs and in
Bills.
Pay ment at full rate should not be made until the item has been comp leted to the required
specifications.
Measurements should be taken from time to time at the discretion of Engineer.
Contractor to witness measurements and sign the records.
Measurements taken in the absence of contractor are bindin g on him if h e fails to attend
after receiv in g communication.
Objections of Contractor on measurements - Any re-measurements taken by Engineer in
the p resence of contractor are final and bindin g and no claim on this will be entertained.
18.2
Pay ments for all work done by contractor should b e made on the basis of measurements
recorded in M easurement Books.
There should be no d elay in takin g measurements and prep aration of bills after the
measurements are taken.
Petty bills should be used for makin g p ay ments to contractors when a sin gle p ay ment is
made for a job or contract on its comp letion.
Page 55 of 173
The running or on account bill form is used in contract works only and where p ayment is
made in installments.
Final bill form should be used for making final p ay ments.
Before forwarding a contactors bill to the Accounts Office, the Executive Engin eer should
satisfy himself as to the correctness of the quantities billed, the rates and all recov eries.
All p articulars / columns in the bill form should be filled up . Quantities since last
certificate, quantities up to-date, units, rate, amount, total value for the bill, total value of
work done so far etc. are filled up .
Technical Ch eck of B ills to be done in the Drawing office und er the sup ervision of
Executive En gineer.
Contractor's accounts to be closed without any delay on completion of work. If contractor
delay s to receive final pay ment for more than one month, final bill to be p assed and kep t
under deposit.
Final M easurements to be recorded with in 21 day s of comp letion of work.
The time for the execution of the work or part of the works sp ecified in the contract
documents shall be deemed to be the essence of the contract.
If the contractor fails to comp lete the works within the time as sp ecified in the contract for
the reasons other than the reasons sp ecified in clause 17 and 17-A of GCC, the Railway
may , if satisfied that the works can be completed by the contractor within a reasonable
short time thereafter, allow the contractors further extension of time as the En gineer may
decide.
On such extension the Railway will be entitled without p rejudice to any other right and
remedy availab le on that behalf, to recover from the contractor as agreed damages and not
by way of p enalty a sum equivalent to of 1% of the contract value of the works for
each week or part of the week.
The total amount of liquidated damages under this condition, shall not exceed the under
noted p ercentage value or of the total value of the item or groups of items of work for
which a sep arate distinct comp letion p eriod is sp ecified in the contract.
For contract value up to Rs.2 lakhs
For contracts valued abo ve Rs. 2 lakhs: 10% of the first Rs. 2 lakhs and the 5% of the
balance.
Page 56 of 173
Similarly in cases where the workmen emp loy ed by the contractor p erform the same or similar
kind of work as the workmen directly employ ed by the princip al emp loyer of the establishment,
the wage rates, holiday s, hours of work and other conditions of service of the workmen, of the
contractor shall be the same as app licable to the workmen directly emp loy ed by the p rincipal
emp loy er of the establishment on the same or similar kind of work.
You may be aware that Government has enacted the Contract labour (Regu lation and Abolition
Act- 1970) and central rules made there under which p rovide regulation of contract labour in
the establishments. The Act also p rovides for prohibition of emp loy ment of contract labour
where a notification is issued und er Section 10. So far, 82 Notifications have been issued. This
Act casts obligation on emp loy ing dep artments to register their establishments under the Act
before the authority notified by the Central Government, the contractors have also to obtain
license b efore en gagement of contract labour in the establishments. The Act & Rules p rovide
for certain facilities to be provided to the contract workers engaged in the establishments and
also to maintain registers and records, to issue wages slip s and emp loy ment cards to the
contract workers by the emp loy ing dep artment and contractor.
The Act also p rovides for penal action against the d efaulters. The relevant Sections a re as
under:
Section 23. Contravention of pro visions regarding employment of contract labour.Whoever contravenes any p rovision of this Act or of any rules made there under p rohibiting,
restricting or regulating the emp loy ment of contract labour, or contravenes any condition of a
license granted under this Act, shall b e punishable with imp risonment for a term which may
extend to 03 months, or with fine which may extend to Rs. 1000/-, or with both, and
in the case of continuing contravention with an additional fine which may extend to Rs. 100/for every day during which such contravention continues after conviction for the first such
contravention. Provide p enalty for Contravention of p rovisions regardin g emp loyment of
contract labour shall be punishable with imp risonment for a term which may extend to 03
months, or with fine which may extend to Rs. 1000/- or with both and in the case of a
continuing contravention with an additional fine which may extend to Rs. 100/- for every day
during which such contravention continues after conviction for the first such contravention.
Section 24. Other offences.- If any p erson contravenes any of the p rovisions of this Act or any
rules made there under for which no other p enalty is elsewhere provided, he shall be p unishable
with imp risonment for a term which may extend to 03 months, or with fine which may extend
to Rs. 1000/- or with both. Provide p enalty for contravention of other offences shall be
p unishable with imp risonment for a term which may extend to 03 months, or with fine which
may extend to Rs. 1000/- or with both.
It is also noticed that some establishments are engagin g contract workers in the employ ments
which have been p rohibited under section 10 of the Contract Labour (Regulation and Abolition)
Act 1970. Some p rincip al emp loyers and contractors are violatin g the p rovisions of Act &
Rules.
In view of above; the employ ing dep artments are hereby notified to ensure the compliance of
the provisions of the Act & Rules in all establishments includ in g PSU's under them.
Page 57 of 173
19.3 Provisions of Contract labour (Regulation and Abolition) Act, 1970 - (1)
The Contractor shall comply with the provision of the contract labour (Regulation and
Abolition) Act, 1970 and the Contract labour (Regulation and Abolition) Central Rules 1971 as
modified fro m time to time.
(GCC 2010, Labour , Item No 55A(1))
Page 58 of 173
Whether the funds av ailability has been certified and has been allocated to prop er heads of
accounts.
Whether all d eductions have been mad e and the bill is arithmetically accurate.
Whether penalties, if any, to be recovered from the bill have b een made.
Once the bill is checked, the bill is p assed for pay ment.
n on account bill
1. Name of work
:
2. Name of contractor
:
3. Situation of work
:
4. Contract agreement no. and date
:
5. Date of commencement
:
6. Date of comp letion
:
7. Total working p eriod
:
8. Total value of work
:
9. Date of measurement
:
10. Period of bill
:
11. Last reference
: Page noto of M B no..
Measurement of on account bill
A typ ical examp le of an on account bill is as under:
NS-1 : Provision of ..
Qty . executed 03 nos (p erson) p er month @ Rs.p .m.
Since work done
- 02 months ( unit)
Total work done
- 14 months
Prep aid (Ref. M B page no)
12 months
Now to p ay
- 02 months
@ Rs. 2100/- x 2
- Rs.4200/Total absents during the month
- Nil
Total p enalties during the month
- Nil
Gross amount Rs..
Deductions
1.
2.
3.
4.
Income tax @ 2%
:
Surcharge on IT @12%
:
E.Cess on IT @ 3%
:
Conservancy cess @ 128/- p.m.
( upto 10 p ersons)
Total deductions
---------Net p ay able
----------
Page 59 of 173
Certified that the p ay ment made through this bill is actually for the work done by the
contractor during the period fromto.
Certified that the work has been carried out as p er items, terms and conditions of the
contract agreement.
Certified that no p lants and machinery hired by the contractor.
100 % measurement check has been exercised by me.
The p enalties of Rs. /- as calculated on p age no. .. to of MB no.
.. has been deducted for the absents during the period from .. to.
Signature of Supervisor
Certificate of Contractor
Certified that the labour engaged by us have been p aid minimu m wages as p er p rescribed by
Labour Commissioner and also mandatory commencement in ESI/PF.
Certified that the measurements as recorded at p age no. ..to ..R of the measurement
book no. for the period . to . are correct and accep ted without any
p rotest.
The bills are correct and accep ted without any p rotest by us and have no claim against any item
of C.A. No. .
dated .
Signature of the Contractor
Certificate of Officer In charge
Certified for Gross amount Rs. . (Rup ees .. only ).
Certified for Net p ayable amount Rs. (Rup ees only ).
Certified that the pay ment made through this bill is actually for the work done by the
contractor from .. to .
Certified that no p lants and machinery hired by the contractor.
Certified that the work has been carried out as p er items, terms and conditions of the contract
agreement.
Certified that the measurements have b een recorded by Shri .., JE/SSE on M easurement
Book p age no. to R.
Certified that the 20% test check has been carried out and found correct.
Certified that there is no any audit/account/vigilance p ara is pending against the Contract
Agreement.
Funds are available for the year .
Gross amount of the Bill
Rs.
Total deductions
Rs. .
Net Pay able amount
Rs. .
(Rup ees only)
Signature of officer in charge
Page 60 of 173
Pay ment of bills in time is mandatory in terms of Para 1484 of Engineerin g Code.
Income Tax at the sp ecified rates of government, Cess and Surch arge on In come Tax at the
rates app licable from time to time will be recovered from the contractors bill.
Delay in pay ment of final bills is one of the root cause for arb itration.
If final bill is not p assed in time, the following problems can occur
(a) M aterial outstanding with the contractor can not be taken back.
(b) Provision of the maintenance clause can not be invoked.
(c) Over pay ment can not be detected.
(d) Quality can not be ascertained.
Page 61 of 173
II.
III.
Whether the work has been satisfactorily completed by the contractor within the stipulated
time frame.
Certificate that no recoveries are outstanding against the contractor.
Certificate that Railway s has suffered no loss due to late completion of work.
Page 62 of 173
Activity
Prep aring office note for ap p roval
Callin g for bud getary quotation from Firm
Concurrence to prop osal
Prep aration of estimate/ Est. cost
Vetting of estimate
Sanction to estimate
Tender booklet prep aration with Terms and Conditions, Scop e of work etc.
EMD (2% of the estimated tender value up to 1.0crores), above this, 2 lakhs
+ 0.5% of the excess of estimated cost
Ensure Unit of Advertised Tender
Prep aration of tender notice for op en tenders/OEM
Loadin g of Tender Notice on Net before 35 days of opening of tender
Issuing of tender booklet before 25 d ay s
Opening of tender
Submission of tender cost of down loaded tender form to Associated finance
(Same day / next working day )
Verification of EMD submitted by Tenderer
Prep aration of brief note & Tender tabulation statement
Verification of brief note SO (Wks A/cs) .
Nomination of TC members
TC p rep aration
Verification of eligib ility criteria
TC Finalization
Accep tance of TC recommendations
Issuance of Letter of Accep tance ( LOA)
(Vetting of LOA from associated finance before issue of LOA if required.)
Submission of PG by the firm within 30 Day s [ 5% of contract value ]
Verification of PG by law officer
Verification of BG by bank
Prep aration of Contract Agreement
Page 63 of 173
28
29
30
31
32
33
34
35
Page 64 of 173
Publishing of advertisement in the newsp ap ers at far off p laces rather than the area of
demand.
Non finalization of tenders within the validity p eriod.
Defective Tender schedule, lacunae in the technical descrip tion requirin g clarifications
/negotiations after op ening of the tenders.
Play ing with the technical asp ects for rejecting inconvenient bids on the grounds of
technical unsuitability .
Resorting to the negotiations to create opp ortunities for a firm to be favoured.
Incorrect evalu ation of the bids, sp ecial conditions offered by the tenderers were not
prop erly assessed.
Accep tance of an unsolicited offer from other than the lowest tenderer and awarding of
the contract without givin g an equ al opp ortunities to others.
Consideration of a tender based on the data materially different from that giv en in the
gen eral and sp ecial cond itions of contract without the knowledge of tenderers.
Placement of orders at higher rates on flimsy ground, technical or otherwise, shorter
comp letion p eriod/delivery schedule but the period is extended later and the excuse that
the lower tenders do not belong to a develop ed source.
File held up after the accep tance of tender before the order are issued.
Waival of the insp ection or change in the inspecting authority or relaxation of technically
rigid requirements or relaxation in the commercial terms
Sp litting of the demands to bring the tender value within the p owers of lower level
sanctioning authority .
Inclusion of dummy firms to inflate the number and ultimately consider the favoured
firms in case of the limited tenders.
Accep tance of high er rates on the p lea that the accep ted offer is lowest without
adequately justify ing the reasonableness.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
x.
xi.
xii.
xiii.
xiv.
25.1
CVC guidelines:
CVC has also issued gu idelines from time to time. For easy understanding the tendering
p rocess can be divided into four stages. The guid elin es issued and the checklist for each
stage is summarized below.
i)
Preparation of tender documents:
Allow adequate and reasonable minimum time (as p rescribed) for op enin g of all tenders
to encourage p roper response.
Ensure timely supp ly of cop ies of app roved p lans for tenders where sp ecial items rates
have to be quoted for the p articular details of the ap p roved p lans.
Ensure the comp arative statement and briefin g note hav e b een p rep ared and du ly sign ed
by the concerned officials on each p age.
Only consider offers accomp anied by requisite earnest money in p roper term.
Page 65 of 173
Attempt identification of sister concerns to detect cartel formations esp ecially in the case
of limited tenders.
The tender after acceptance and signin g beco mes the contract a legal docu ment. An
ambiguous agreement leads to p oor contract p erformance and litigations. It also giv es an
opp ortunity to a contractor to make p rofit out of ambiguous conditions. It has been
observed that the tender documents are p repared in a hurried manner without check in g the
conformity among the schedule of items, drawin gs, sp ecifications, and contract conditions
etc. This generally hap p ens due to the reason that different p arts of the tender document
such as schedule of quantities, sp ecifications, drawin gs, and general conditions p rep ared
by different peop le are compiled without correlatin g them. So metimes they are cop ied
from old tenders without givin g a thought to the app licability of the conditions to the
p resent work.
Checklist :
Page 66 of 173
In the various book lets issued by the CTE Organization of the Commission, the need to
maintain transp arency in receip t and op ening of tenders has been emp hasized and it has been
suggested therein that suitable arran gements for receip t of sealed tenders at the scheduled date
and time through consp icuously located tender boxes n eeds to be ensured. The Commission
vide their Circular No. 05-04-1-CTE-8 dt. 8.6.2004 has further instructed that in case of bu lky
tender documents the p rovision for submission of bids to designated officials by hand should
be made in the tender document itself.
To maintain transp arency in the op ening of tenders, the Commission in its circular dated 8.6.04
has instructed to op en the bids in the p resence of bidders. Despite the reiteration from the
Commission regarding maintainin g transparency in inv iting & op ening of the tenders, a
number of cases ind icatin g lack of transp arency , openness and fairness have come to light.
- Checklist :
Prefer op en tendering as far as p ossible
In case limited tenders are resorted to, p rep are & up date p anel of contractors/ vendors in a
transp arent way .
Ensure adequate & wide p ublicity . (Web p ublicity is necessary even in case of limited
tenders)
Ensure adequ ate time for submission of offers.
Up load NIT & tender document on web site, even in case of limited tenders (cvcs circular
dated 11.2.2004).
Notify complete address of p lace of tender submission (cvcs circular dated 8.6.2004).
Op en the bids in p resence of bidders.
Attest and account for corrections, omissions, insertions, overwriting
Prepare on the sp ot summary in tender op ening register
iii) Pre-qualification
The success of a p roject largely dep ends on the cap ability of the contractor/vendor. Prequalification is a p rocess to select competent contractors having techn ical and finan cial
cap ability commensurate with the requirements of the p articular procurement (Project / supp ly
of goods/ hiring of services).
The pre-requisites of p re-qualification p rocess are-Transp arency
-Fairness
-M aintenance of comp etition
The Commission has issued gu idelines vid e circular No12-02-1-CTE-6 dated: 12.12.2002 and
07.05.2004 advisin g the organizations to frame the p re-qualification criteria in such a way that
it is neither too stringent nor too lax to ach ieve the purp ose of fair comp etition.
Checklist:
Keep the PQ criteria neither too stringent nor too lax.
Prepare the PQ criteria sp ecific to the requirement of the work in clear terms.
Notify the evaluation criteria in the PQ document.
Verify PQ credentials.
Evaluate the bids exactly as p er the notified criteria
Retender if relaxation in PQ criteria is necessary .
Page 67 of 173
Page 68 of 173
Dos:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
Allow adequate and reasonable minimum time (as prescribed) for op ening of all tenders
to encourage p rop er resp onse.
Ensure timely supp ly of cop ies of app roved p lans for tenders where sp ecial items rates
have to be quoted for the p articular details of the ap proved plans.
Ensure the comp arative statement and briefing note have been p repared and duly signed
by the concerned officials on each p age.
Only consider offers accomp anied by requisite earnest money in p rop er term.
Attempt identification of sister concerns to detect cartel formations esp ecially in the case
of limited tenders.
Ensure consideration of reasonableness of rates in the tender committee minutes. This
should not be with reference to p resumably accep ted rates, but also after taking in to
accounts market rates and analy sis of rates. Reasonableness has to be exp lain in detail.
Obtain views of the Comp etent Authority to deal with the lowest acceptable offer of
contractors with adverse rep orts.
Treat the Tender Committee recommendations with dissenting notes carefully . Dissent
should be p art of running minutes with views of other members also on it.
Negotiation should be an exception and not the rule in acceptance of tenders. These are to
be held with lowest valid tenders only.
Record relevant reasons for overlooking the lowest offer if it is not accep table. Speaking
decision is a must.
Order callin g for fresh tenders if items are to be rev ised or their value is to be enhanced.
Ensure that sp ecial conditions do not give avo idable scop e for accep tance of high rates
(like mentioning steel to be supp lied by the tenderers and later includin g p ay ment for
such supp ly , which has a tendency to boost the p ercentage rates quoted by the tenderers).
Ensure that the tender committee minutes contain the relevant information as the date,
venue of the meetin g and d ated sign atures of the members.
Record the accep tance or otherwise on the body of the tender committee minutes only &
not on the noting side of the file.
Ensure that the rating of the offers received is done p rop erly after evaluating the sp ecial
conditions and vetting by finance.
Ensure that the reasonableness of rates is examin ed critically , logically and sp ecifically
both in resp ect of total cost and rates of imp ortant individuals items.
Beware that the low offers are in facts so in reality and p rice, differential for similar but
different items of schedule is reasonable.
Ensure that the tender committee is duly constituted of comp etent level of officers
sp ecified.
Ensure p rior sanction of comp etent authority before executin g additional quantities
(bey ond 25%) in such items (overall for earthwork) so that the contracts are not vitiated.
Page 69 of 173
Donts:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Do not change the Tender Committee members once constituted without p rior app roval
of competent authority.
Do not consider delay ed/ late tenders excep t under specified excep tional circumstances &
that too only by following p rescribed procedure.
Do not treat the Tender Committees recommendations with dissenting notes from on e or
more members of the Tender Committee as unanimous recommendations.
Do not order negotiation on the repeated advice of tender committee to invite fresh
tenders, p articularly where response to the call for negotiations is p oor.
Do not exercise the p ower of accep ting authority in case y ou have been a member of the
Tender Committee. Let it go to higher authority .
Do not hold negotiation with those who had either not tendered originally or whose
tender was rejected because of unsatisfactory credentials, inadequ acy of cap acity or
where tenders were unaccompanied with adequate earn est money or any other invalid
tenders.
Do not accep t op en quotations from contractors during negotiations.
Do not entertain letter/ rep resentations of tenders subsequent to opening / negotiations/
consideration of tenders.
Do not accep t modified offers, not considered by the Tender Committee.
Do not allow subsequent revision of the minutes unless the reconsidered minutes are p ut
up in addition.
Do not advise the tender committee p rior to their deliberations on the suitability or
otherwise of any p articular offer.
Do not allow anomalies in ev aluation of sp ecial conditions to affect the accep tance of the
offer recommended.
Do not op erate non-schedule items without sanction of co mp etent authority . In
excep tional cases where it has to be done, maintain necessary site records.
Do not op erate non-schedule items where it possible to do work as p er schedu le items or
a combination there of.
Do not award works on quotations in a routine mann er and strictly follow annual
financials limits laid down.
Page 70 of 173
Department
REMARKS
status
a
b
c
7 Is the DOC reas onable? Has the work plan been m ade?
8
a
b
c
d
Page 71 of 173
REMARKS
Page 72 of 173
d
19
a
b
c
d
e
20
a
b
c
d
e
21
22
23
DATE:
REMARKS
Page 73 of 173
8
Is tender docum ent s tam ped and num bered before selling
and the address of the party m entioned on the tender
document s old ?
DATE:
ITEM
While publishing tender in News paper, CPRO/PRO has
ens ured that NIT has already been uploaded on the website
by taking certificate from executive.
Has the token of confirm ation in the form of internet download
record for open tender ensured (non confirm ation will be
treated as in adequately advertized tender (Rly. Bd. Letter
NO. 2008/RS(G)/779/2 dated 07.11.2008
REMARKS
REMARKS
Page 74 of 173
10 Has the cover, front co ver page and every page on which
rates , counter offer, EMD, and tender doc payment details of
each tender document initia lled with date by executi ve and
accounts m ember?
11 Have all over-writings , corrections encircled, num bered
s eparately and initialed and total numbers also mentioned?
REMARKS
Page 75 of 173
12 Is there any ambiguity/des crepancy in rates quoted in words
and figures . If s o has it been m entioned?
ITEM
Has the following check s heets fill ed properly
Pre notice check s heet
Check-s heet for tender notice
Check-s heet for tender docum ent
Check-s heet for tender s ale
Check-s heet for tender opening
Are News paper cuttings of tender notice available on tender
file ?
8 Is internet uploading evidence available on tender file ?
9 Is MIC (m aterial intens ive contract) approval available in file ,
if applicable?
10 Has briefing note been prepared and vetted?
11 Has com parative s tatem ent been prepared and vetted and
all LAR references available in file?
12 Is detail es timate been vetted and Valid?
13
14
15
16
17
18
19
20
REMARKS
Page 76 of 173
a Technical eligibility
b Financial eligibility
21 Has it been checked that no uns crupulous effort been made
to m eet eligibility criteria by:
a Form ing partners hip firm after date of tender notice
b Claiming to have Assets /M&P's without actually poss ess ing it
c Giving incorrect experience certificate
22 Is firm complying with the special conditions which are
essential as per tender notice ?.
23 Has fair com petition been ensured
a By ensuring wide publicity
b By adequate notice period
c By non-participation of firms having different names but sam e
m anagem ent.
24 Has it been exam ined that firm does 'nt have excess ive
workload w.r.t. its capacity and capable of perform ing the
tas k within the DOC?
25
a
b
c
d
e
f
g
h
I
j
k
l
Page 77 of 173
28 Has the tender been finalised within validity period ?. If not,
reas ons to be given
29 Does LOA cos t exceed work sanctioning lim it of concerned
Authority (MLW/LW/PB)?
DATE:
Sheets
for
Page 78 of 173
PART-II
Page 79 of 173
Special Conditions
(Model tender document)
Page 80 of 173
GOVERNMENT OF INDIA
MINIS TRY OF RAILWAYS
(RAILWAY BOARD)
No.2000/M (C)/141/7/IV
Page 81 of 173
TENDER NOTICE NO. DRM.Mech._file no. ___________________dated_________________
Divisional Railway Manager (Mechanical), Railway, address for and on behalf of The President of
India, inv ites op en tenders (Two packet system comp risin g Technical and Financial Bids) in sealed
covers from the rep uted contractors on p rescribed form up to 15.00 hrs on op ening day as p er details
mentioned below:
Name of W ork
Approximat
e cost of
work
EMD
Cost of the
Te nde r
form
Date
Validity
of
Validity
Contract
Period
App roximat
e total cost
for 3 years
Rs._____/-
Rs.__
_/-
Rs.___/-
__________
(Date)
at
______ hrs.
90 day s
3 y ears
AND
Rodent control in
coaching d ep ot
y ards and
p remises
Prescribed tender forms can be obtained from the office of the undersigned on all working days up to
17.00 hrs on cash p ay ment of the cost of tender form (non-refundable). If the tender form is obtained
from the office of the undersign ed, the cost of the tender form should be p aid in cash with Chief
Cashier, Railway , (Address) or Divisional Pay M aster, __ Railway, (Address) or with Station Manager
I Station M aster of any station of ___ Railway .
The tender form shall also b e d isplay ed on website at www.tenders.gov.in. If the tender form is
downloaded from the website, the pay ment towards cost of tender form must be made in the form of
DEMAND DRAFT issued by any Nationalized Bank in favour of Sr. Divisional Finance Manager/
Railway / (Division). The Demand draft should be enclosed alon g with the tender documents submitted
by the tenderer(s).
The Earnest Money Dep osit (EM D) should be in cash or in the form of dep osit receip ts, p ay orders or
demand drafts executed by State Bank of India or any of the Nationalized Banks or by the Scheduled
bank. Sale of tender forms will be closed at 17.00 hrs. one day before the tender op ening date.
Tenderer(s), who want to be p resent at the time of op ening of tenders, may do so.
(a) Total Contract amount received durin g the last three y ears and in the current financial y ear up to the
date of tender op ening, should be min imum 150% of the advertised tender value of work. Tenderer(s)
shall submit docu ments to this effect, in the form of attested certificates from emp loy er client, audited
balance sheet duly certified by Chartered Accountant
Page 82 of 173
(b) The tenderer should have, in the last three y ears and the current financial y ear upto the date of
tender op ening, completed at least one similar sin gle work for a minimum v alue of 35% of the annu al
value of this advertised tender.
The tenderer should have, in the last three y ears and the current financial y ear upto the date of tender
op ening, received pay ment of at least 35% of the annual value of this advertised tender against
uninterrupted and satisfactory execution of an on goin g similar p est and rodent control contract.
Similar work implies' "pest and roden t control work executed in Ra ilway coa ches/Station premises,
registered housing societies, warehouses, godowns & reputed ho tels etc. "
(c) Total p enalty imposed for unsatisfactory p erformance in the similar qualify ing contract should not
exceed more than 7% of the contract value. Confirmation and documentary evidence must be
submitted by the tenderer duly verified by the Agency that had awarded the contract.
Tenderer(s) should submit the following documents along with the tender document: (a) List of
works of similar nature ongo in g/co mp leted in the qualify in g p eriod (Le. current year and three
p revious financial y ears) givin g descrip tion of work, organization for whom executed, app roximate
value of contract at the time of award, p ayment received in the qualify in g p eriod, date of award and
date of scheduled comp letion of work. Date of actual start, actual comp letion and final value of
contract should also be giv en. In case of ongo in g contracts, date of commencement of contract and the
date the contract p eriod will be comp leted should be mentioned with. Supp orting do cuments /
certificates from the organizations for which the tenderer(s) have worked should be enclosed. The
authorized signatory of the organization should sign the certificates submitted by the tenderer(s).
Certificates from p rivate individuals for whom such works were executed will not be accep ted. (b) As
p roof of the total contract amount receiv ed durin g the qualify ing p eriod (Le. current year and three
p revious financial y ears), tenderer(s) shall submit documents in the form of attested certificates from
emp loy er/client or, audited balance sheet duly certified by Chartered Accountant (c) List of works on
hand indicating descrip tion of work, contract value, ap p roximate value of balance work y et to be done
and date of award. (d) List of p ersonnel organ ization available on h and and p rop osed to be engaged
for the subject work (e) Details of Infrastructure, Plant and Machinery , agreements with rep uted
p esticide manufacturers to indicate cap ability of supp ly ing quality p esticides.
Further details are given in tender schedu le which can be p urchased from the office of Sr.DM E __
/Sr.CDO or downloaded from website.
Divisional Railway Manager (Mechanical)__________________ DIVIS ION
INDEX
S rNo
Contents
1
2
3
4
5
6
7
Pages
From
8
9
10
11
to
Page 83 of 173
S tar of tender document
Impo rtant notes for intending tenderer(s)
Please ensure that:
1. You have sign ed the offer p age with full name, address and witness fillin g all the blanks.
2. You have filled in the required colu mn's.
3. You have accep ted the validity p eriod of 90 days.
4. You have not quoted sp ecial conditions of y our own, as they are likely to vitiate y our
tender and make it p rone to rejection.
5. You have sign ed all p ages, correction neatly scored out and initialed wherever requ ired.
6. Please do not leave any blanks, which may lead to declaration of y our offer as INVALID.
7. Tenders must be enclosed in a sealed cover sup er-scribed with the sp ecified Tender number and
must be dep osited in the sp ecial bo x allotted for the p urp ose at the office of
Sr.DME (division) (Address). Alternatively, the tenders can be sent by registered p ost to the above
addres.s so as to reach not later than the specified time of sealin g the tender box on the day of tender
op ening.
8. The tender box shall be sealed and op ened at the sp ecified timings on the day of op ening as detailed
in the tender notice and corrigendum, if any, thereof.
9. Precaution to be observed for downloading of Tender Document from Internet Website/Additional
Sp ecial Cond itions:
i. These additional special cond itions are app licable to tender document and considered as p art
of it, which is downloaded from Internet I website.
ii. Tenderer(s) may note that p ermitting of downloadin g of tender document is an added facility
for the convenien ce of Tenderer(s). In case of download failure I delay or, if incomp lete tender
document is downlo aded, whatsoever, R ailway s shall not be responsible in any way . Railway s
shall not be resp onsible for any direct I indirect loss of business I p rofit resulting from inability
to use this facility .
iii. Tenderer(s) shall download & print the Tender document solely for the p urpose of bidding
for the above work and downloaded document shall not be used, cop ied or rep roduced for any
other purp ose.
iv. The end of tender document is indicated by "END OF TENDER DOCUMENT marker.
Tenderer(s) should carefully see that above marker ap p ears on the last p age of downloaded
tender document so as to, ensure that downloaded document is complete. Tenderer(s) are
suggested to check the integrity and comp leteness of document before submission.
v. The tender document downloaded from website though does not bear signature of Railway
authority , shall have same authority as the tender document directly p urchased from the office
of Sr.DM E (division). Tenderer(s) while submitting their offer must sign all p ages of the tender
document.
vi. The downloaded and p rinted tender document along with the various other documents
should be submitted as p er details mentioned in the tender document. The tenderer(s) should
clearly write on the main tender cover and also on the top of the sealed cover "Tender
documents downloaded from website".
vii. Tenderer(s) are required to pay non-refundable cost of tender document in the form
p rescribed in the tender notice white submitting their offer. In case they fail to furnish the
requisite cost of tender document in p rescribed form, their offer shall be rejected. The cost of
EM D shall not be merged with cost of tender form and shall be separately furnished.
viii. Tenderer(s) shall maintain the integrity of downloaded tender document and shall not
make any chan ge addition/d eletion/tamp ering, whatsoever, in the downloaded docu ments. The
tenderer(s) offer shall be rejected and full earnest money shall be forfeited, in case it is detected
after submission of offer, that they have made any modification in the downloaded document.
In case such modification is noticed even after award of contract, Railways is liable to
Page 84 of 173
terminate the contract on contractor's default. In addition Railway s reserves the right to take
other action against the contractor as deemed fit, which may include banning of business
dealings with the firm and the firm is also liable to be p rosecuted as. p er the law. After award
of work, agreement will be prep ared based on the master cop y of tender document av ailable in
the office of Sr.DME (division). In case, any discrep ancy is noted in the tender document
submitted by the tenderer(s), the Master document kept with Railway s shall prevail and the
decision of Railway s thereon shall be final and bindin g on Tenderer/Contractor.
ix. Tenderer(s) shall p rint the tender document on good quality A4 size p ap er of thickness 75
GSM or above and the p rinted document shall be clearly legible. The document shall be
p rop erly bound and p age numbers shall be in serial order as mentioned in the downloaded
documents. Tenderer(s) shall not be reimbursed with the cost of stationery, p rinting and
binding, etc. Offer of Tenderer(s) is liab le to be rejected by Railway s, if the tender document is
not p rinted or bound as p er above instructions. Further, Tenderer(s) shall bear exp enses of
internet connection and telephone charges. if any , for downloading of the tender docu ment.
x. All offers in the prescribed form should be submitted in Two-Packet sy stem. One p acket
shall be called "Technical Bid" and the other p acket be called "Financial Bid". These shall be
sep arately sealed in individual envelop e distinctly marked as Technical Bid and Financial Bid
in Bold letters. The two envelop es shall be p ut in one common envelop e duly sealed and sup er
scribed on top Tender No & Due date. Tenders not comply ing with these instructions shall be
summarily rejected.
xi. The tender do cuments duly comp leted in all resp ects shall be submitted in a sealed cover
addressed to Senior Div isional M echanical En gin eer (Division, Address). The tender shall be
dropped in the Tender Box kep t for the p urp ose in said office before the date and time
indicated above.
xii. All offers shall be submitted before the time and date fixed for the receipt of the offers
as.~et forth in the tender p apers. Offers received after the stip ulated time and date are liable to
be rejected.
xiii. Tenderer(s) shall k eep themselves up dated about any modification in the tender notice and
tender document, issued by Railways through newsp ap ers, website or email or any other means
and shall act accordingly . It is the resp onsibility of the Tenderer(s) to check if any corrections
or modifications are p ublished subsequently on the Website and the same shall be taken into
account while submitting the
tender. The offer of the Tenderer(s) is liable to be rejected if they do not enclose all the
corrections / corrigendum alon g with the downloaded tender documents.
xiv. The "Additional Conditions for Tender Document downloaded from Website" must be
signed by the Tenderer(s) and enclosed alon g with the Tender document failin g which the
tender is liable to be rejected.
Note:
i. Tenderer(s) may carefu lly note that his/their Contract. Agreement for this work is liable to be
terminated at any time later, in case any of the information furnished by them is found to be
untrue or any adverse p oints come to light subsequently . The decision of Railway in this regard
shall be fin al and b indin g.
ii. The tender documents are not transferable and the cost of the tender document is also not
refundable.
iii. Railway reserves the right to reject conditional tenders summarily without assigning any
reasons whatsoever.
iv. Non-compliance with any of the conditions set forth herein above is liab le to result in the
tender bein g rejected.
v. The tender forms not accomp anied with prop er Earnest Money will be summarily rejected.
Page 85 of 173
vi. Tender documents duly comp leted in all resp ects shall be dropp ed in the Tender Box kep t
for the p urp ose in the office of Sen ior Divisional M echanical En gineer (Division, Address)
before the date and time ind icated abov e.
vii. Decision of the Senior Divisional M echanical En gin eer (Division, Address) regardin g the
accep tability of the scheme shall be final and b indin g. However, within the framework of the
scheme as submitted by the tenderer & accep table to Railway s, the Railway can effect suitable
modifications to details as necessitated by the p rovision of various codes, manuals, referen ce
etc. viii. Any other information required by the tenderer can be obtained from the office of
Senior Div isional M echanical En gineer (Division) durin g the working hours.
ix. Contractors who download tender document from website shall mak e following d eclaration:
I/We hav e downloaded the tender docu ment from the website and l!We have not
tamp ered/modified the tender forms in any manner. In case the document is found to be
tamp ered/ modified, I/We understand that my /our tender is liable to be rejected and fu ll earnest
money dep osit will be forfeited and I/We am/are liab le to be banned from doin g business with
Railway s and/or p rosecuted.
Signature of tenderer
Two packet system of tendering shall be adop ted for this work and the renderers shall submit
their bids in following two parts: (A) Technical bid & (8) Fin ancial bid
A. Technical Bid: shall consist of
i. EM D
ii. Documents in support of fulfilment of the laid down ELIGIBILIT Y CRIT ERION as under:
(a) Total Contract amount received durin g the last three y ears and in the current financial y ear up to the
date of tender op ening, should be min imum 150% of the advertised tender value of work. Tenderer(s)
shall submit docu ments to this effect, in the form of attested certificates from emp loy er/client, audited
balance sheet duly certified by Chartered Accountant
(b) The tenderer should have, in the last three y ears and the current financial y ear upto the date of
tender op ening, completed at least one similar sin gle work for a minimum v alue of 35% of the annu al
value of this advertised tender.
OR
The tenderer should have, in the last three y ears and the current financial y ear upto the date of tender
op ening, received p ay ment of at least 35% of the annual value of this advertised tender against
uninterrupted and satisfactory execution of an on goin g similar p est and rodent control contract.
Similar work implies "pest and rodent control work executed in Railway coach es/Station premises,
registered housing societies, warehouses, godowns & reputed ho tels etc."
(c) Total p enalty imposed for unsatisfactory p erformance in the similar qualify ing contract should not
exceed more than 7% of the contract value. Confirmation and documentary evidence must be
submitted by the tenderer duly verified by the Agency that had awarded the contract.
iii. As p roof of the total contract amount received durin g the qualify in g p eriod (Le. current y ear and
three previous financial y ears), tenderer(s) shall submit documents in the form of attested certificates
from emp loy er/client, audited balance sheet duly certified by Chartered Accountant, TDS certificates
or annual income tax returns filed with Income Tax Dep artment. Tenderer shall submit bills and other
verifiab le documents from organizations for which they have executed p est and rodent control
contracts for establishing that they fulfill the technical eligibility criteria. Railway s reserve the right to
seek indep endent confirmation from these organizations or from any other source. iv. List of works
comp leted in the qualify ing p eriod (Le. current y ear and three previous fin ancial y ears, Annexure ~
giv in g description of work, organization for whom executed, ap p roximate valu e of contract at the time
Page 86 of 173
of award, p ayme!1t received in the qualify ing p eriod, date of award and date of scheduled co mp letion
of work. Date of actual start, actual completion and final value of contract should also be given.
Sup p orting documents / certificates from the organizations for which the tenderer(s) hav e worked
should be enclosed. The authorized signatory of the organization should sign the certificates submitted
by the tenderer(s). Certificates from p rivate individuals for whom such works were executed will not
be accep ted.
v. List of works on hand indicating d escrip tion of work, contract value, and ap p roximate value of
balance work y et to be done till date of tender op ening.
vi. List of p ersonnel and the organization p rop osed to be engaged for the subject work alon g with their
qualifications.
vii. List of various machines / equipment prop osed to be supp lied and commissioned by the tenderer.
Detailed sp ecifications of these machines / equ ip ment, OEM's catalogues, etc. are to be en closed.
viii. List of manp ower and site sup ervisor trained by recognized institutes like CFTRI My sore, Indian
Grain Storage Institute, National Plant Protection Training Institute etc. should be supp lied along with
the technical b id. The p roof of site sup ervisor being a life science or agriculture graduate should be
submitted. ix. The clause by clause accep tance and deviation schedu le as per Annexure B.
x. The tenderer must establish that he follows all Labour Laws and makes p ay ment to his staff in
accordan ce with relevant Acts through do cumentary eviden ce like cop y of returns filed for PF, ESI
code no. etc.
xi. The Contractor should p rovide satisfactory evidence, accep table to the Railway s, to establish that:
a. He is a reputed firm / contractor who regularly undertakes the works similar to the subject tender
and has adequate technical knowledge and exp erience.
b. He has an established p rop er supervisory control organ ization to ensure that there shall be adequate
control at all stages of execution of the contract.
xii. The Contractor shall be industry leader p ossessing comp lete technical know-how of p est control
treatment including but not limited to anti-cockroach treatment, anti bedbugs, anti rodent treatment
and other disinfestations/ p est control treatments. Proof to substantiate this shall be enclosed alon g
with tender.
Note:
This work is for comp rehensive pest/rodent control treatment in the coaches homed in various
coachin g dep ots and also rodent control in the identified area of the coachin g dep ots. Contractor may
therefore visit the co achin g dep ot (s) to familiarise himself with the sy stem of op erations and
maintenance of coaches, levels of infestation of p est and rodents in coaches/y ards etc. and the primary
maintenance schedules in the p it lines/lie-over (id lin g Time) of emp ty rakes during which the
p est/rodent control treatment is to be carried out in the coach es/rakes, and p lan the treatments
accordin gly . The contractor shall ensure that at no stage because of the treatment, any harm is caused
to the p assengers/ Railway staff. B. Financial bid : shall consist of schedule of rates as p er p rescribed
formats given in Annexure '0'. Contractor shall quote rates against every item. Only those contractors
shall qualify to p articip ate in Financial Bid op ening, whose Techn ical Bids h ave b een accep ted and
have met all conditions p rescribed in eligib ility criteria of the tender.
PART -II: CONDITIONS OF CONTRACT
1. The SCC and the GCC: These Sp ecial cond itions of contract (SCC) (alon g with Specifications of
work and other conditions as contained in this Tender Document) shall b e read together with the terms
and conditions in corporated in this tender document and the General Conditions of Contract (GCC) of
Railway s. Should there be any conflict between the p rovisions of the SCC (along with Sp ecifications
of work and other conditions as contained in this tender document) hereof and that of the GCC I the
imp ort of the former shall p revail over the latter.
2. The coaches can be offered for p est / rodent control at coaching dep ots / p it lines of Division,
Railway . The app roximate number of coach es based in different coachin g depots is as indicated in
Annexure C.
Page 87 of 173
4, The quantity of coaches as mentioned in the tender is only app roximate and can v ary (increase /
decrease) du e to op erational and other unforeseen circumstances.
5. The p est control treatment shall include cockroaches, bedbu gs, mosquitoes etc. while the rodent
control shall include mice & other rodents etc., which cause discomfort to the traveling passengers.
S . No. T e of coach
1. AC Coaches & Pant Cars
2. Reserved Non-AC coaches
The Pest Control Operators/Contractors shall be required to use only those chemicals / p esticides that
have been app roved for the household purp ose by "Central Insecticides Board and R egistration
Committee" under the p rovision of Insecticides Rules 1971 framed under Insecticides Act 1968.They
must however undertake chan ges in the chemicals quarterly so that insects do not acquire immun ity
for a particular typ e of chemical. They shall also submit detailed p lan and methodolo gy towards this
end.
(i) The chemicals (also with brand names) prop osed for the p est control treatment.
(ii) Concentration of the solution (dilution ratio etc.).
(iii) Dose (quantity )/coach/treatment for different categories of coaches. Arising out of the experience
in this tender, the most effective comb ination of chemicals/treatment shall on ly be stipulated for the
subsequent tenders. Bidders are accordin gly exp ected to offer the most effective treatment solution.
The contractor must also ensure the following and submit documents in supp ort,
wherever ap plicable:
(i) The p est control op eration should at no time violate the p rovisions of the Insecticides Act, 1968 and
Insecticides Rules 1971 and lor any other relevant Law and Rules as framed by Government of India,
State Government or Local Bod ies.
(ii) The p est control op erations shall be done only by agencies, which h ave been ap p roved by the Plant
Protection Officers of the concerned state's agriculture dep artment or Central Insecticides Board and
Registration Committee (CIB&RC), Faridabad. The PPOs are available at the district/division level
(iii)The p est control op erators/agencies should p rovide an attested copy of their license in the
p rescribed form with clear endorsement for p ermission to carry out commercial and domestic p est
control. The license should not be only for sellin g, exhibitin g and stockin g insecticid es. Their license
should be valid for the entire duration of their contract with Railway s.
S. No. T e of coach
1. AC Coaches & Pant Cars
2. Reserved Non-AC coaches
i) For the rodent control treatment as p er the above-noted frequency, food based attractant Glue
Boards of reputed make shall be p rovided in the coach es durin g their p rimary maintenance schedu le as
under:
Coach Typ e
I AC Coach
No. of Glue Boards to be laced
One in each cabin, coup e, attendant cubicle and electrical control Panel
4 Nos. in p assenger co mp artment and 1 in Electrical control Panel
6 Nos.
4 Nos. in assen
Pant Cars
Reserved non-AC coach es
ii) The Glue Boards shall be taken off fro m the coaches at the end of primary maintenance schedu le
and it shall be ensured that rats/rodents trapp ed in the Glue Boards are removed before the dep arture of
the train. The disp osal of such dead/llive rats/rodents must not cause any health /environmental hazard.
iii) Two Nos. of glue boards shall continue to remain in each of the I AC/AC-2Tier coach and p antry
car for the entire leg of the onward /return journey for requirements enroute/ at the other end terminals.
Page 88 of 173
iv) The contractor shall also p rovide 2 Glue Boards p er train rake to the escorting staff/Executive
Housekeep er of the agency p roviding on Board housekeep ing/ co ach attendant to attend to sp ecific
requirements/comp laints enroute.
The glu e Boards must be rep laced whenever they become unusab le/ineffective for trap p ing rodents.
Other devices/imp lements as deemed fit by the contractor, such as rat trap s, guards on cables goin g
from underneath of coach floorin g to inside of the coach, ultrasonic devices etc. may also be used in
addition in order to eliminate rodents/rats from the coaches.
i) The identified area of the coachin g depot(s) for rodent control Le., p it lines, stabling lines and
adjoinin g y ard etc. is indicated in Annexure C-1. The rodent control p rogramme in the identified area
of the coaching dep ot y ard, p it lines and premises will require integrating several control methods to
be implemented in a p lanned manner by high ly trained and exp erienced technical personnel. The
treatment should commence with strategic p lacement of baits to bring the infestation under control. A
constant vigil on p opulation of rodents would be necessary.
ii) The followin g methodology and gu idelines should generally be followed for rodent control in p it
lines/ co aching d ep ot y ard:
a) On commencement of the contract, on the 1st day , rep resentative of the contractor and Railway
shall jointly survey the entire area to lo cate p ockets of high, medium and low density burrows and the
Contractor shall simultaneously p lug all the burrows with soil and stone. The objective of this exercise
is to identify and distinguish active burrows from the dormant ones so as to p revent the use of
chemicals in excess. Sp ecial monitorin g and treatment should be carried out for the high density
areas/zones.
b) On next day the burrows which are found op en by rodents shall be termed as active bul'IDJ\lSand
these burrows shall be treated with aluminum p hosp hide (or equivalent) fumigant tablets and laced
food attractant baits.
c) During the 1st month, burrow fumigation treatment should be done on weekly basis and baiting
shall be done on d aily basis.
d) From 2nd month onwards, baiting should be done on fortnightly basis or as and when required.
Burrow fumigation treatment should also be done on monthly basis or as & when required.
e) All dead rats / rodents found shall be disp osed off suitably on the same day by the contractor. The
disp osal of such dead/live rats/rodents must not cause any health /environmental hazard.
7. (a) A maximum tolerance of + 7 days shall be p rovided in the frequency of p est/rodent control
treatment in coaches to take care of op erational exigencies and disturbance of coaches in the rake links
etc. In case, for some reasons the coach does not return to the p rimary coachin g dep ot by the
designated due time for treatment includin g the tolerance (in cludin g bookin g of the co ach to the
Workshop s for maintenance schedules etc.), no p enalty shall be imp osed on the contractor.
However, the coach shall be treated immed iately on arrival, before bein g permitted in the train
services from the p rimary dep ot/station.
(b)The contractor must adhere to the sp ecified frequ ency of treatment for rodent control in coachin g
dep ot y ards/pit lines and no tolerance shall be p rovided for the same.
(c) Rates shall be quoted by the Tenderer on a per treatment basis for each of the category of the
coaches as in Annexure-D, and the p ay ments shall be made accordin gly through monthly bills for the
total No. of treatments in each of the category of coach es.
For the rodent control in coachin g dep ot p remises identified for the p urpose, the rates shall be quoted
by the tenderer on a per month basis as in the format in Annexure'D '.
For every attention done by contractor, the same shall be certified by Railway Sup ervisor nominated/
dep uted for this p urpose by Sr.DM E/ Sr.CDD of the division.
The Measurement book for this p urp ose shall be maintained in every dep ot on the basis of which
p ay ments shall be made to the contractor.
(d) The frequency of treatments laid down as above is the minimum requirement. The contractor may
be required to increase the frequency , for a better and effective p est/rodent control and in order to
achieve the desired end results as in Annexure 'A'.
Page 89 of 173
Pay ments shall however be made only for the No. of treatments carried out p er month in coaches in
accordan ce with the minimum frequency sp ecified in the tender and on a monthly basis for rodent
control in the coaching d ep ot p remises.
(e) Contractor shall ensure that only those personnel who are trained in the field of p est/rodent control
by certified trainin g institutes are dep loy ed for this treatment. The contractor shall giv e details of such
p ersonnel alon g with bid documents. The technical b id should clearly brin g out the y ardstick for
dep loyment of manp ower for effective execution of the contract.
(f) The strategy to eliminate p ests/rodents while including all the measures stip ulated in this tender
schedule should not be limited/restricted by these. The contractor is exp ected to take all measures,
whether mentioned in tender schedule or not, required for co mp lete elimination of p ests/rodents etc.
9. Tenderer(s) should quote the rate inclusive of all ap plicable taxes and levies, etc. levied by the
Government or Local bodies. Railway s shall not be liable for any increase in the taxes or duties lev ied
by the Government or Local bodies which shall h ave to be borne by the contractor.
10. Any overwriting / correction have to be attested / countersigned by the tenderer(s).
The rate quoted in words shall be considered as fin al rate in case of ambiguity .
a. All offers shall b e written/typ ed neatly without correction and over writings.
b. Any individual(s) signin g the tender or other documents connected therewith shall specify whether
he is sign in g.
i. As sole p roprietor of the concern.
ii. As a p artner or p artners of the firm.
iii. As a Director, M anager or Secretary of a Limited company duly authorized by a resolution p assed
by the board of Director or in p ursuance of the authority
c. All p rices and other information like docu ment sets having a bearin g on the p rice shall be written
both in figures and words in the p rescribed offer form and duly signed and stamped.
d. Offer in the p rescribed form should be addressed to Sen ior Division al Mechanical Engin eer
(Coachin g), (Address). The tender should be submitted in a sealed cover sup er scribed with the name
of work.
e. Tenderers shall submit their offers made as per the General Conditions of Contract in force as
amended from time to time as well as these Sp ecial conditions of contract and Sp ecifications of the
work as mentioned in this tender.
f. In case of any deviation from the requirements of tender sp ecifications, instructions to tenderer(s) or
General & Sp ecial Conditions of Contract, the same should be brought out by the tenderer in
Annexure B.
g. All p ages of the tender document duly serialized and enclosed should be du ly filled in by the
tenderer wherever app licable and submitted alon g with the tender du ly signed and stamp ed on each
p age.
h. The tenderer should avoid ambiguity in his offer e.g. his offer is to his standard
sizes/lengths/dimensions. He should sp ecifically state them in details without any ambiguity. Brief
descriptions such as "Standard lengths" etc. should be avoided in the offer.
11. The contractor shall ensure that his staff while carry in g out the said work, are in uniform and carry
an identity card on their p erson, at all times. They shall beh ave in a d isciplined courteous manner, and
in no way , indulge in activities in Railway p remises, which could cause loss to p rop erty or reputation
of Railway s.
12. Issue of Identity cards by Contractor: Contractor should issue Identity badges (as p er app roved
format) to all his labour being en gaged to carry out the Work, includin g the Sup ervisor. These identity
badges should be so carried that Railway Security can identify them. The Identity cards should be
worn by the contractors' labour on left side on the chest every time, during their p resence on Railway
Premises.
a. Security Dep osit for each work should be 5% of the contract value.
b. The rate of recovery should be at the rate of 10% of the bill amount till the full security deposit is
recovered.
Page 90 of 173
c. Security Dep osit will be recov ered on ly from the running b ills of the contract and no other mod e of
collecting SO such as BG, FD etc. shall be accep ted. In case of contracts of value RS.50 Crores and
above, irrevo cable bank guarantee can also be accepted as a mode of obtainin g security dep osit.
d. After the work is p hy sically comp leted, security deposit recovered from the runnin g b ills of a
contractor can be returned to him if he so desires, in lieu of FOR/irrevo cable Bank Guarantee for
equivalent amount to be submitted by him.
e. No interest will be p aid on the said security in terms of Clause 16 (3) of General Conditions of
Contract.
a. The successful bidder shall submit a Performance Guarantee (PG) in the form of an irrevocable
bank gu arantee amounting to 5% of the contract value.
b. A Performance Guarantee shall be submitted by the successful bidder after the letter of accep tance
has been issued, but before sign in g of the agreement. The agreement should normally be signed within
07 days after the issue of LOA and the Performance Guarantee shall also be submitted within this time
limit. This guarantee shall be initially valid up to the stip ulated date of comp letion p lus 60 day s bey ond
that. In case the time for comp letion of work gets extended, the contractor shall get the validity of
Performance Guarantee extended to cover such extended time for comp letion of work p lus 60 days.
c. The Performance Guarantee (PG) shall be released after the p hysical comp letion of the work based
on the 'Completion Certificate' issued by the comp etent authority stating that the contractor has
comp leted the work in all resp ects satisfactorily . The security deposit, however, shall b e released only
after the expiry of the maintenance p eriod and after passing the final bill based on "No Claim
Certificate".
d. Wherever the contract is rescinded, the security dep osit shall be forfeited and the Performan ce
Guarantee shall b e encashed and the balance work shall be got done indep endently without risk and
cost of the failed contractor. The failed contractor shall be debarred from p articipating in the tender for
executin g the b alan ce work. If the failed contractor is a J V or a partnership firm, then every
member/p artner of such a firm shall be debarred from p articip ating in the tender for the balance work
either in his/her individu al cap acity or as a partner of any other JV/p artnership firm.
e. The En gineer shall not make a claim under the Performance Guarantee excep t for amounts to which
the President of India is entitled under the contractor (not withstanding and /or without prejudice to any
other provisions in the contract agreement) in the event of:
i) Failure by the contractor to extend the validity of the Performance Guarantee as describ ed herein
above, in which event the Engineer may claim the full amount of the Performance Guarantee.
ii) Failure by the contractor to p ay President of India any amount due, either as agreed by the
contractor or determined under any of the Clause/Conditions of the agreement, within 30 day s of the
service of notice to this effect by Engineer.
iii) The contract bein g determined or rescinded under p rovision of the GCC the Performance
Guarantee shall be forfeited in full and shall be absolutely at the disp osal of the President of India.
f. The successful bidder shall submit a Performance Guarantee (PG) in any of the following forms
amounting to 5% of the contract value.
i. A dep osit of cash
ii. Irrevocable B ank Guarantee
iii. Government Securities includ in g State Loan Bonds at 5% below market value
iv. Dep osit Receip ts, Pay Orders, Demand Drafts and Guarantee Bonds. These forms of Performance
Guarantee could be either of the State Bank of India or of any of the Nationalized Banks
v. Guarantee Bonds executed or Deposit Receip ts tendered by all Scheduled Banks
vi. A dep osit in the Post Office Savin g B ank
vii. A dep osit in the National Sav in g Certificates
viii. Twelve years National Defence Certificates
ix. Ten y ears Defence d ep osits
x. National Defence Bonds
xi. Unit Trust Certificate at 5% below market value or at the face value whichever is less.
Page 91 of 173
xii. Also FOR in favour of FA&CAO (free from any encumbrance) may be accepted
15. The coaches can b e offered for p est / rodent control at coachin g depots / maintenance sidin gs of
Division, Railway or at any other location as decided by Sr.DME (Cog) / Sr.CDO. The app roximate
number of coaches based at the above co achin g d epots is as indicated in Annexure C.
16. Tenderer(s) should quote the rate inclusive of all ap plicable taxes and levies, etc. levied by the
Government or Local bodies. Railway s shall not be liable for any increase in the taxes or duties lev ied
by the Government or Local bodies which shall h ave to be borne by the contractor.
17.Any overwriting / correction have to be attested / countersigned by the tenderer(s). The rate quoted
in words shall be considered as final rate in case of amb iguity .
18.The above work will be subject to the General conditions of contract in force on Railway in
addition to the Sp ecial terms and conditions as laid down below.
I / We hereby agree to carry out the work at the rates quoted by me/us duly accep ted by (i)
Comprehensive control of cockroaches, rodents, bedbugs, mosquitoes, etc. in all co aches maintained at
coachin g d ep ots of Division, Railway .
Note:
a. It must be ensured that treatment/disinfestation is carried out in thoroughly cleaned coaches. Prop er
I.iaison must be made by the contractor with the Coachin g Dep ot officials in this regard.
b Whenever a coach is detached from the rakes for IOH/POH in the sick lines/workshop s,
fumigation/misting treatment shall be carried out in the coach usin g rep uted brands of foggin g tin
(CANNON or equivalent) to cover all corners/crevices, includ in g inaccessible areas such as
underneath seats and berths, including toilets and dustbins etc. The tin shall be lighted and once it
starts p roducing smok e the coach es shall be sealed. The fumigated co ach must be kept in the sealed
condition for about 6 hours.
The contactor shall quote the rate/coa ch for this activity separately (As in Annexure 0) and monthly
payments shall be made according ly for the No. of coaches where such fumigation has been carried
out.
c. Pest/rodent control treatment should invariably be carried out in the coach before p utting it back in
service after IOH/POH in the workshop s.
The work shall be carried out at coach ing dep ots of Division, Railway . In case of any chan ge in
location, same needs to be jointly agreed to by authorized rep resentative of contractor and
Sr.DME/CDO.
a. In order to get maximum time for the chemicals to act, the contractor may , if so desired, start the
p est control treatment immediately on arrival of the terminating train on the p latform after detraining
of the p assengers. The coaches shall be opened as soon as the rake is taken up for maintenance in p it
line. Contractor shall have no claim to the effect that less than adequate time was availab le" for the
chemicals to act. The contractor supervisor shall maintain close liaison with authorized rep resentative
of respective coaching dep ots towards an overall effective objective of p est/rodent control.
b. In order to p revent cross infestation, the contractor may make efforts to treat all the AC coaches &
all the Non-AC coaches of a p articular rake together.
c. Besides maintain in g written records, the d ate of the treatment and next due d ate shall also be
indicated by the contractor through ap p rop riate stickers inside the coach in the doorway /toilet area. No
additional p ayment shall be made for said activity .
d. Sp are coaches ly ing in y ards, etc. shall also be required to be treated for p est/rodent control as p er
the laid down frequency .
e. Railway s shall make efforts to detach p antry cars from rakes once a month (within reasonab le
tolerance) to facilitate complete vacation & intensive clean in g for thorough p est / rodent control
treatment & give adequ ate time for the ch emicals to act. However, due to exigen cies of train
op erations, the same may not always be possible & the pantry cars may have to run for a p eriod of
more than one month before detach ment. The contractor shall not have any claim in this regard.
f. The contractor shall carry out surp rise insp ections with regard to the work carried out by their staff
& submit rep ort of the said insp ection whenever called for the p erusal of comp etent Railway authority .
Page 92 of 173
g. The desired end result in redu ction / elimination of the infestation in co aches and broad
methodology for measurin g the lev el of infestation and the exp ected reduction at various stages of the
contract agreement is as at Annexure A. Contactor must aim to achieve the prescribed results. The
measurement of infestation levels at various stages shall b e jointly recorded by contractor/his
rep resentative and the Railway staff nominated by the COO.
h. S torage Sp ace: Railways shall p rovide storage sp ace free of cost for stocking of ch emicals,
maintainin g of records, etc. The space may not necessarily be a sep arate room; some sp ace may be
earmark ed within existing roo m. About one month's inventory of the chemicals shall b e maintained in
the storage space. The security of chemicals / records will be the resp onsibility of the contractor and
the allotted sp ace shall under no circumstances be used for any other p urpose. Contractor shall
maintain records of consump tion of various chemicals consumed by him and shall make the same
available to insp ecting Railway officials Le. Sr OME/Sr COO or the supervisors nominated by them
for this p urp ose.
L The p est control operator shall give an undertaking of followin g all safe workin g p ractices. The p est
control. op erations should not result in any discomfort to the p assengers (including ch ildren) / Railway
staff in vicinity at the time of op erations or during normal service and maintenance of the coach es. The
p rocesses utilized for rodent I p est control should be safe for the traveling p ublic.
j. Railway s reserve the right to randomly draw samp les of the insecticid es utilized by the contactor for
p est control, for tests in any Government app roved laboratory , in case of doubts or comp laints. The
cost of such tests will however be borne by the contractor.
4. Penalty:
Railway administration may at its sole discretion, imp ose the following p enalties for unsatisfactory
p erformance:
i. Penalty of Rs. 500/- (Rs. Five hundred only ) per coach (besides immediate free attention to the
coach) when the contractor does not adhere to the sp ecified frequ ency of treatment.
ii. Penalty of Rs. 1,000/- (Rs. One thousand only ) p er comp laint (besides immediate free attention to
the coach) for written p assenger comp laints regard in g presence of cockro aches, rod ents, bedbugs,
mosquitoes etc. in coaches cov ered under the contract.
The coachin g d ep ot incharges shall maintain a p rop er log of all such comp laints and ensure that the
bills are p aid on ly after accountin g for all the complaints. However, the dep ot incharges may consider
the exemp tion of p enalty on account of rodents in case it is established that 9utside yard (secondary
examination/terminal attention/stabling
p remises) nominated for the rake are infested to extraordinary dimensions. To exercise this discretion,
dep ot incharges should get an acknowled gement from Div isional authority that the concerned
outstation y ard/p remises is infested for which corrective measures are programmed by the Division
concerned.
iii. Penalty of RS.1000/- (Rs. One thousand only) whenever it is found by Rly Officer/Authorized
Sup ervisor that the number of p ersonnel deploy ed for the contract execution or their qualifications are
not as p er the y ardsticks of the bid.
iv. Penalty of RS.1500/- (Rs. One thousand and Five hundred only ) whenever it is noticed that
contractor is using chemicals/imp lements not p ermitted under this contract. Besides, no p ay ment shall
be made for such Pest/Rodent Control treatments carried out by the contractor.
v. A lump sum p enalty @ RS.100/coach holdin g covered under the contract whenever the contractor
does not achieve reduction in infestation levels of cockroaches as prescribed in ann exure -A.
vi. A lump sum p enalty @ RS.50/coach holdin g cov ered under the contract whenever the contractor
does not achieve reduction in infestation levels of rodents as p rescribed in annexure -A.
vii. Penalty of RS.10000 for not achiev in g desired level of infestation of rodents in the coachin g d ep ot
p remises during the monthly checks as p rescribed in Annexure-A. Bills for work done under this
contract shall be p repared in dup licate by the Contractor on or before ih day of each month in resp ect
of the work done durin g the p reced in g month. Such bills shall be submitted to the Divisional Railway
Page 93 of 173
M anager (Mechanical) (Division) and when p assed for p ay ment by the Sr. Divisional Finance
M anager, p ayment of amount due will be made through EFT / NEFT. M andate form of EFT / NEFT is
enclosed as Annexure E.
Pay ment shall be made for total number of treatments given to coach es durin g the month based on the
sp ecified frequency of treatment. No p ay ment shall be made for any treatment which is to be carried
out in addition to what has been sp ecified by the tender schedule for any reason whatsoever.
The contract will be valid for a p eriod of 3 years with a p rovision of a clause for price variation.
Price Variation Clause (PVC) shall howev er be ap plicable only for tenders of v alue more than Rup ees
fifty lakhs.
The amount pay able on account of Price variation shall be settled every quarter as p er the following
method:(i) The amount p aid during a qu arter shall constitute of the following elements: X % - Labour
Y % - M aterial (Consumables i.e. chemicals/p esticides, rodents trap s etc.)
Z % - Fixed Comp onent (this implies the cost of mach ines, implements, fixed installations and other
overheads) (X, Y and Z are to be quoted by the contractor in the Price Bid in "Annexure-D")
(iii) For calculation of PV on account of Labour, the Consumer Price Index Numbers for industrial
workers (Base 1982 = 100) published as Sh.36 in RBI Bulletins shall be used. The base shall b e taken
as the index no. (All India Average) ,as on date of op ening of tender. For a particular quarter, the
average index for that quarter shall be worked out and variation with reference to the base index no.
shall be taken into account for calculation purp ose.
(iv) For material p ortion, Statement 40 of RBI Bulletin (All India Average) shall be used. The
calcu lation of Price Variation p ay able illustrated as under. Price Index for material as on date of
op ening (M o) = 160 Avg. Price index for Labour durin g 1st quarter (L1) = (452 + 456 + 455) /3 =
454.3, where 452, 456 and 455 are the ind ices for the three months in the quarter under consideration.
Avg. Price index for material durin g 1st quarter (M1) = (165 + 164 + 168) /3 = 165.7, where 165,164
and 168 are the indices for the three months in the quarter under consideration.
Assuming the bifurcation of the amount of Rs. 10,00,000/- as under: - Labour 01'1) Rs. 5, 50,000/M aterial (M ) Rs. 3, 00,000/Fixed Rs. 1, 50,000/PV for material = (M1 - M o) x M /Mo = (165.7 - 160) x 3, 00,000/160 = Rs 10,687/No Price Variation will b e p ay able on Rs. 1, 50,000/- (i.e. the fixed co mponent)
7. Variation in Quantity: The variation in quantity shall be governed by the General Cond itions of
Contract.
8. Cancellations or S uspension of Contract: The Railway Administration shall be at lib erty at any
time without giv in g any reason to susp end temporarily or terminate permanently this contract on
giv in g 7 day s notice in writing to the contractor and the contractor shall not be entitled to any claim or
comp ensation by reason thereof.
l/We hereby agree to carry out the work at the rate quoted by me/us in financial bid submitted
sep arately in a sealed envelop e, duly accepted by Railway & abide by the terms & conditions laid
down here in above.
1. Broad methodology of measuring the lev el of infestation of cockroaches and ratsl rodents in
coaches and exp ected reduction in infestation with time Within these broad guidelines, before
commen cement of the contract, Sr OM E/ Sr COO or h is authorized rep resentative and contractor shall
lay down a specific methodolo gy for measurement of the lev els of infestation in samp le co aches at
various stages of the contract.
Pantry cars & AC coaches- 10% of the holdin g of the Depot Non AC coaches (Sleep er Class) - 5% of
the holding of the depot
Samp le coaches chosen should be rep resentative and include trains p ly ing in different
directions/destinations. The measurement of levels of infestation as p rescribed above should b e carried
Page 94 of 173
out in the samp le coach es, subject to these hav in g b een treated for p est control at least 5 d ay s prior to
this exercise.
(a) Cockroaches in coaches:
Flushing agents (ROACHEX/SOLFAC 050EW/OEVIKOL Solution in water in the ratio 100 ml
insecticide: 4.5 litres of water) will b e sp ray ed in cracks and crev ices and other vuln erable locations
like linen storage area; b erth folds; toilets etc., in the followin g doses to force cockro aches to come out
in op en:
Pantry cars
AC coaches
Non AC coaches
13.8 liters of solution/coach
9.2 liters of solution/coach
4.6 liters of solution/coach
After the above noted doses are sp ray ed, each sample p antry car and AC co ach shall also be subjected
to intensive foggin g usin g 125 gm CANON/equivalent rep uted make foggin g tin. The tin shall be
lighted and once it starts p roducing smoke the coaches shall be sealed for about an hour. Food based
attractant traps (5 Nos.) shall also be p laced in each p antry car/AC coach before sealin g.
Thereafter, the number of cockro aches trapp ed and their life stage (ny mp h / adult) will b e recorded
and used as a ben chmark for measurin g the lev els of infestation in the beginnin g as also at various
stages of the contract. Reduction to be achieved over the period of time shall be:
At the end of one month of commencement of work - 50%
At the end of six months of commencement of work - 90% (80% for p antry cars)
The levels to be achieved after six months should be sustained and checked/monitored every six
months thereafter.
No p enalty shall, however, be imp osed if number of cockroaches (Dead or aliv e) detected during these
checks is less than 2/coach.
Quarterly monitoring of levels of infestation of rodents shall b e done in the sample coaches. 6 Nos. of
Glue boards shall be p laced in each samp le co ach at p redetermined lo cations and rat/rodent catch, if
any , will be record ed. Acceptable levels durin g such checks shall not be more than one catch (dead or
alive) p er five coach es or a part thereof.
Note: Cost towards such p erformance monitorin g checks for control of cockroaches and rodents shall
be borne by the contractor and no extra p ayment shall be mad e by the Railway s.
Pit line /y ard area p rop osed to be covered und er the contract for rodent treatment is given in Annexure
C-1. The Contractor will be resp onsible for disinfestations of the earmarked area and shall ensure to
make passive the borou ghs, holes which p rovide shelter to rat / mon goose / bandicoots etc. by the end
of one month of co mmen cement of the contract and none of these are further permitted to come up
during the currency of the contract.
The monthly joint evaluation of the earmarked area will be conducted by contractor and Sr. DM E or
his authorized rep resentative, and a penalty shall be imp osed for not achievin g the desired results.
Contractor will bring out in his schedule as to how he p rop oses to show the effect of Rodent control
treatment in Pit lines/y ard of the coaching d ep ots, subject to approval of the scheme by Sr. DM E. If
the contractor fails to submit any acceptable methodology in this regard, the decision of Sr.DME will
be final.
Clause # Accep ted (Yes/No) If No list Deviation(s)
Sp ecial terms and Cond itions of contract:
S pecifications of work:
Sr. Dep ot Non AC Coaches AC No. Reserved Unreserved Coaches Pantry Cars
1
2
3
4
Page 95 of 173
5
Total no of
coaches
SKETCH/LAYOUT INDICATING THE AREAS OF THE COACHING DEPOT(S) IDENTIFIED
FOR RODENT CONTROL TREATM ENT, ALSO DENOTING THE TOTAL AREA IN SQUARE
M ETERS.
Typ e of coach No. of coaches Frequency Total number of Rate p er Total cost for (holding) of
treatments during treatment THREE y ears treatment the contract for 3 y ears
AC
Fortnightly
Pantry Cars Fortnightly
Non-AC (Reserved) Fortnightly in first three months & thereafter monthly
Non-AC Bi-monthly
(unreserved)
TOTAL COST (I)
Typ e of coach Rate per treatment (Rs.
Labour Component Material comp onent Fixed co mp onent
AC
Pantry Cars
Non -AC
(reserved)
Non -AC
(Unreserved)
Anticip ated No. of coaches to be Rate/treatment/coach Total cost for the contract
booked for IOH/POH during the (3years)
contract p eriod
Total Cost (II) ------------Typ e of coach No. of Frequency of Total number of Rate per Total cost for
coaches treatment treatments treatment THREE y ears
(holdin g) durin g the
contract for 3
y ears
AC During every
Primary
M aintenance
Pantry Cars During every
Primary
M aintenance
Non-AC (Reserved) Weekly
.
TOTAL COST (III) ---------Typ e of coach Rate per treatment (Rs.
Labour Component Material comp onent Fixed co mp onent
AC
Pantry Cars
Non-AC
(reserved)
N.S . Contractors shall note that above rates are inclusive of all the sp ecial treatments which
are p rop osed to be given at various stages of work and no pay ments other than the above
shall be made.
Page 96 of 173
1. PARTICULARS OF THE PARTY
i) NAME: _
ii) ADDRESS: _
iii) PHONE NO: M OBILE FAX NO. _
iv) INCOM E TAX PAN NO. EMAIL 10. _
2. PARTICULARS OF BANK ACCOUNT
i) CITY: _
ii) BANK NAM E: _
iii) BRANCH: _
iv) BANKADDRESS: _
v) BANK TEL NO. FAX NO. _
vi) BANK MICR CODE (9 DIGIT): _
vii) BANK IFS code: _
viii)BANK ACCOUNT NO: _
(Please enclose a cancelled blank cheque)
ix) ACCOUNT TYPE: (SAVUBGS/CURRENT/CASH CREDIT): _
3. Certified that the particulars furnished with reference to Bank Account are correct and the
bank gu arantees to honor all EFT/NEFT advices/reports as p er RBI Regulations.
i) I hereby declare that the p articulars giv en in this mandate form are correct and comp lete. If
the transaction is delay ed or not effected at all for reasons of incomp lete or incorrect information, the
User institution Le., FA & CAO/ Railway , (Division) will not be held responsible.
Page 97 of 173
CONTRACT
FOR
RAKE MECHANIZED
CLEANING & WATERING
OF COACHES
IN COACHING DEPOTS
INCLUDING CLEANING
OF DEPOT PREMISE
Page 98 of 173
SPECIAL TERMS & CONDITIONS OF CONTRACT FOR RAKE M ECHANIZED
CLEANING & WATERING OF COACHES IN COACHING DEPOTS
INCLUDING CLEANING OF DEPOT PREMIS E
The work pert ains to round the clock 24 x 7 days Intensive Mec hanized Cleaning of coaches on the pits
situated in depot. The rakes will be Attended at as per t he Pit Occupation Chart as giv en in ANNEXUREA3.
1.
The Contractor will utilize compact and portable Cleaning mac hines covering all the safety precautions as
specified in the Annexur e A-6.
2.
For every pit line there shall be a set of machines as listed out in Machine specifications a set of standby
machine shall be provided at site for any breakdown.
3.
The details and composition of the likely rakes and the time and days on whic h they will be maintained in
depot on different washing lines are plac ed as Annexure A3. This may howev er change depending on t he
decision of the depot officer due to occasional late arriv al of train or as a planned meas ure.
4.
The Contractor will nominate a representative/s upervisor-in-charge who will maintain liaison wit h the
Sr.Section Engineer (C&W) / CDO or his nominated represent ative regardin g carrying out cleaning
activities of rakes, liaison with Railways etc.
5.
The Rakes on terminatin g station will be handed over t o the Contractor after due inspection & it will be t he
Contractors responsibility to lock all t he coaches before t aking it to the washing/ pit line. After the
completion of cleaning activities & inspection by Railway authorities, t he c oaches s hall be duly lock ed
again and handed over to the Railways nominated authority.
6.
Nominated represent atives of Railway s hall ins pect the c oaches after cleaning activities have been
performed. The quality & quantity of work will be ins pected daily for each rak e. An objective and clear-cut
system of checking quality of cleanliness for each item of work with a score card s hall be filled while
inspecting and assessment of daily total score for each rake is defined and placed at Annexure A2.
7.
The Contractor should take utmost care to ensure that no damage to the rake/c oaches/Railway property
takes plac e due to any act of workmen, while carrying out the work under this Contract.
8.
The contract is for round the clock maintenance. The Contract or will have to employ his resources
according to the Pit Occupation Chart & offer servic es on multiple shifts bas is if required. In case of late
running of trains the contractor in liaison with t he CDO will resc hedule and arrange his resourc es to ensure
the coac hes are attended ev en if trains arriving late at Puri.
9.
The work will be carried out without affecting the Railway working and in consultation wit h CDO / Sr.Section
Engineer (C&W) or his authoriz ed representative.
10.
The Contractor s hall furnish complet e details of the personnel to be deploy ed with s upervisor(s) giving t he
working timings. The name/list of all t he employees along with supervisor should be submitted to
Sr.DME/CDO or his authorized repres entativ e bef ore starting the actual work.
11.
The Contractor s hould issue Identity badges to all his Labour engaged to c arry out t he work, including t he
supervisor. These identity badges should be so carried that they can be identified by Railway
Security/Carriage & Wagon Staff and Supervis ors. The Identity badge s hould be worn by contractor Labour
on left on the chest at the plac e of work.
Page 99 of 173
12.
The Contractor shall instruct the Labourers engaged to close the c oach toilet taps & Hydrant taps during
non-use and after us e to avoid wastage of water.
13.
The Contractor should ens ure that the dirt, litter and other filth collect ed after the cleaning shall not be off
loaded to nearby Pit/Was hing lines and will be dumped only at nominated place as advised by Sr.Section
Engineer(C&W)/CDO. The entire Pit/washing Line shall be cleaned after the rake has been cleaned.
14.
The Contractor shall mak e nec essary Electrical Plug & Socket with Cabling arrangement along the
catwalk/pit line t o draw electric ity as per Annex ure A-8. Railways will supply required load & Electricity free
of cost. However, the Contractor will have to give total load det ails / consumption /day. The electric al
installation is by the side of washing line and may come in c ontact with water. Contractor will be
responsible for providin g necessary training to its men for proper upkeepment of installation as per
specifications detailed in Annexure-A6 and all safety gadgets and materials to protect its men/Machines
from electric shock/short circuit/ accident. Railway shall not be responsible for any suc h mishap.
15.
All the mechaniz ed systems & implements /accessories as required in this project shall hav e to be to be
owned by contractor. The Contractor shall be responsible f or round t he clock av ailability, serviceability and
maint enance of t hese mechanized systems. Thes e Mechanized systems s hould be dedicated to this
contract and cannot be taken out for any ot her job.
16.
Railways shall provide adequate free of cost water supply through hydrant taps on the pit lines f or was hing
of coaches.
17.
The Railways shall prov ide free office accommodation and a storage space (Machine Room) with
independent lock & key for keeping the machines within the depot premises. Contractor s hall be
responsible for the safe cust ody of the machine and stores.
18.
The Contract will be awarded the work on turn key basis for daily cleaning of rak es from ins ide/outside
during its primary or sec ondary maintenance in depot as per sc hedule of work giv en in Annexure-A1.
However, Contractor shall be geared to tak e any additional no. in seas ons.
19.
All direct or indirect costs and obligations pertaining to employment of specialized manpower will be borne
by contract or under the turnkey scope of work.
20.
The resources shall be mobiliz ed and made functional within a period of 45 days from t he date of intimation
of the acceptanc e of tender which the contract shall be terminated & EMD/SD forfeited.
21.
The Contract or and Railway administration shall independently at their own costs arrange for passenger
opinion s urvey (Annexure-A7) regularly regarding cleanliness of t he coac hes. The Railways will give
required permission to conduct such surv ey at station.
22.
The Contractor is expected to maint ain entire dat abas e of coac hes/rakes attended by him for analytical
purpose at the end of every month & at the end of each year. The Contractor is also ex pected to make
available this database to Railway whenever desired.
23.
The Mec hanized Cleaning Contract is on turnkey basis. The turnkey serv ice contract will cover the
following:
a. All fixed installations,
b. Mechaniz ed systems as per giv en specifications
c. Hand implements, tools & tackles,
24.
On completion of work as specified in Annex ure-A1(-Schedule of Work), all t he window glass shutters shall
be closed and the doors lock ed from inside except one door which shall be locked from out side. The rakes
will be attended at as per the Pit occupation chart as given in Annexure-A as amended from time to time.
25.
Some pit lines will hav e catwalks on both sides; some pit lines on one side only and s ome pit lines do not
have catwalks. The contractor s hould be prepared t o clean the coac h on all t he pit lines irrespective of
whether c atwalk is available or not. The coaches are to be cleaned on rake during the pit occupation.
However the coaches av ailable in the yard, sick line and IOH may also be taken up f or cleaning based on
the necessity of the Rail way Administration.
26.
The contractor has to attend the intensive cleaning of coac hes and the rak e has to be c ompleted in 3 hours
maximum or as per the occupied time of rake in the washing line.
27.
The contractor should utiliz e trained manpower and supervis ory personnel from House keeping field. The
contractor should show doc umentary evidenc e in support of this. Trained personnel in House k eeping field
will be pref erred.
28.
Payment will be made on monthly basis for no. of coaches attended by the contractor by in the previous
month. The Paying authority will be the Sr. DFM- of the Division. The contractor shall submit his bills to t he
Sr.DME- of the Division every month for certification duly support ed by the daily score card duly verified
and s igned by CDO / Sr. Section Engineer in charge of the depot .Sr DME will forward the same to SrDFM
for payment.
29.
WORK EVALUATION :
The effectiveness of cleaning will be ev aluated on a scale of 10 as per the following grading and sc ores will be
assigned for eac h item in the score card:
Surface condition
Clean, no dirt or no stains
Clean, very slight stains with visible cleaning effort
Very light dirt or stains visible
Minor dirt/stains visible
Fair dirt and stains visible
Severe dirt and stains visible
Extremely dirt/stained
Rating
10
9
8
6
4
2
0
OVERALL RATING
80- 90%
PENALTY IF ANY
10% of the accepted rate/c oach will be recov ered
from the bills for no. of coaches in that rake.
(i)
70-80%
(ii)
The Railway Administration will terminate the contract..for 10days in more than 10% of the coac hes
offered during the period. If the work ex ecuted by the contractor is c onsist ently uns atisfactory (below 6
rating) for 10 days, at the risk and cost of the contractor.
The Labour engaged by the contract or should alw ays be in prescribed unif orm and identity badges & if they
are found without these, Railways may impose penalty not more than Rs. 100/- per case.
Railway Officials of different ranks will be ins pecting the quality of cleanliness of coaches from time to time.
Adverse remarks of any inspecting official or public complaints received on cleanliness of coac hes, t he
contractor will be liable for a penalty of Rs.500/-(Rupees Five hundred only) or the compensation awarded
to complainant in any court of law and in cons umer or both.
31.
Inventory of Materi als & Inspection:
The contractor shall make arrangements to present to the Senior Section Engineer/CDO, Coac h Maintenance
Depot at the commencement of the work ev ery day t he stock of v arious cleaning materials/ agents/ compounds to
record the adequacy of mat erials to be us ed for the day. The Senior Section Engineer shall exercise supervision to
ensure that the cleaning materials are actually used as per the scales for which the contractor shall co-operate. The
scal e (quantity)/brand/Specification and use of the chemicals/ cleaning solvents shall be specified along
with the tender document for the above purpose as a separate annexure on per coach basis for coach
cleaning chemicals and for depot premise cleaning every day..
32.
Quality of the works carried out should be jointly certified by Senior Section Engineer/CDO or his
nominated representative, Coach Maintenance depot along with repres entativ e of contractors and record to this
effect has to be maint ain ed by the contractor to prefer the bill for the c ompleted mont h.
WORK DIARY
The depot will open a Work Diary for the above contract for whic h the Contractor will indic ate the details of the
works carried out daily and it should be jointly certified by bot h SSE or his nominated repres entativ e and
contractors repres entativ e daily. The extracts of this Work book will form part of t he monthly bill f or v erification.
Additional records/registers if any should also be maintained and the details recorded as per the directions of CDO.
34.
GUARANTEE IN CLEANLINESS
Coaches should be free from dust, grime, muck and stain and there should not be room for any complaint from t he
traveling passengers.
(a) The quality of cleaning should not affect the glossiness of the parent material or the paint whichev er applicable.
No stains, spots, marks, pasted labels and any other substance should be left inside the c oach.
(b)
During the exec ution of work, it is the responsibility of the c ontractor to see that chemic al cleaning solution
should not affect the glossiness of surf ace on the exterior of c oac h. Whatever c hemic als f all on the exterior of
coach should be wip ed thoroughly.
(c) The quality of cleaning for the LP Sheet panels, varnished areas/ painted areas including partition frames,
pillars and s eats/berths support brackets wherever provided should be to the standard i.e., when any area
inside the coach is wiped with white clot h should not show traces of any sli ghtest change in the color of the
cloth. The windowsill areas also should satisfy the above c ondition.
(d) The Rexene surfaces s hould be free from stains, spots, marks, and accumulation of dirt and change of its
original colour t o dark. There should not be any difference of colour in the s ame seats/berths. Wiping with
white clot h, it should not show traces of any slight est change in the colour of the clot h. No drying marks should
be visible on any glass surf ace.
(e) The glass shutters inside/outside of the c oach and mirrors should be crystal clear i.e., when any area on the
surface of the glasses/mirrors wiped with white cloth should not show traces of any slightest change in t he
colo ur of the clot h. In cas e of AC coaches naphthalene balls should be provided between the glasses where
ever provision ex ists.
(f) The flooring surf aces should be free from stains, spots, marks, and accumulation of dirt and there should not be
any differenc e of colour in the same piece of PVC sheets including toilets.
(g) The inside roof portion of the coac h also should be free from dust, dirt, cobwebs etc. When wiped with white
cloth, it should not show traces of any slightest change in the colour of the cloth.
(h) The Aluminum c heckered plat es should be free from all types of muck and other s ubstances.
(i)
(j)
(k) The pantry c ars, storeroom racks, walls, kitchen room, partition mes hes, grills, gas room etc should be
thoroughly cleaned.
35.
INSPECTION CLAUSE
The Sr.DME/DME/AME/CDO/SSE, Coach Maintenance depot or his repres entativ es on his behalf will conduct
inspecti on of the coac hes after completion of work.
INTERIORS OF COACH:
Cleaning of dirt and muck from the fo llowing locations, disinfec tion and dry ing
2.1 All ceiling panels should be wiped with a duster and all permanent stains/head greas e, dirty spots of all
interior paneling/rexine/upholstry, met al beading, wall protectors, lavatory pans, wash basins, shutters,
seats/bert hs, racks etc, should be cleaned with a duster dipped in soap solution, wiped clean and dry.
2.2 Aluminum chequered plate in doorway; corridors between lavatories and vestibule area should be cleaned
detergent with scrubbing machine, disinfected and dried.
2.3 All grease should be removed and all windows, windowsil ls, shutters, etc, should be cleaned with wet
duster. Muck and dirt, which gets collected in the corners should also be scrapped and cleaned. The window
glasses s hould be cleaned with detergent solution and wiped dry with a Squeegee in such a manner that the
glass should be clear and trans parent after cleaning.
2.4 To remove dirt, stains due to coffee/tea, betel spittoon etc and clean the ceiling and floor of the coac h.
2.5 In the kitchen area of pantry cars, all dirt, greas e and oil stains on floor, window shutters near stove,
storage racks etc are to be removed and cleaned with suit able cleaning solvent and scrubbing mechanism,
disinfect ed and dried.
TOILETS:
Cleaning of dirt and muck from the fo llowing locations, disinfec tion and dry ing.
With a suitable HP Jet action & Detergents & manually following shall be cleaned:
3.1
3.2
3.3
Dirt formed on the side panel on which the lavatory door ov erlaps.
3.4
3.5
3.6
3.7
3.8
3.9
3.10 Door and side walls above waist level should not be hosed with wat er, but should
be t horoughly cleaned with cloth dipped in detergent s olution taking c are that no water goes int o the mirrors. The
sidewalls below waist level and the banjo s hutters should be thoroughly cleaned with soft soap / cleaning solution
and cleaned with water by hand or portable s prayer. All dirty s pots s hould be remov ed with the us e of detergent.
The ceiling and sidewalls s hould thereafter be wiped dry. There should be minimum usage of water.
3.11 The mirror should be wiped with a dry duster and if nec essary, cleaned with detergent solution and again
wiped dry. There should be no scratch mark on the mirror. Porcelain wash basins should be cleaned with det ergent
powder and wiped dry wit h duster and stainless steel wash basins should be cleaned with detergent. The porc elain
and stainless steel wash basins and lav atory pans should be sparkling clean.
3.12 The lavatory floor should be first scrubbed with hand brush & detergent and then
jet washed with HP Jet machine and vacuum dried.
3.13 The European style commode should also be washed with suitable detergent & brushed. The plastic
commode lid & seat and covers should be washed wit h detergent & hand brush and wiped dry.
3.14 The commode chutes should be cleaned with a HP Jet or with circ ular brush throughout its length.
4. DOOR WAYS:
Cleaning of dirt and muck fr om the following locations, disinfection and dry ing
4.1 Dirt on ceiling above main door.
4.2 Dirt on ins pection cov er.
4.3 Muck formed on the backside and front side of the main door.
4.4 Dirt formed on the main door glass shutters and windowsills.
4.5 Dirt and muck formed near the hall basin panel
Annexure- A2/1
Logo
Name of Contractor
Name of Contractor -------------- ----- ----- ------ ----- ------ ----- ------ ----- ------ --
Name of Supervisor-------- ----- ------ ----- ------ ----- ----- ------ ----- ------ -Train No. ----------- ----- ------ ----- ------ ----- ----- ------ ----- ------ ----- --- Time Work Started----------- ----- ----T ime Work Comple ted-------------- ----- ------ ----- -No. Of Caches nI the rake-------------- ----- ------ ----- ------ ----- ------ ----- ----- ----No. of Coaches attended ----------- ----- ----- ------ ----- ------ ----- ------ ----- ------ -SNo.
1.
2.
3.
4.
5.
6.
7.
Coach Srl No
Itemized of work
Coach
Description
Type ->
Garbage Collection & Sweeping of
Internal Coach
Toilet Cleaning All Toilet Fittings,
Walls & F loor area and ceilling
10.
11.
12.
12.
16.
16
8.
9.
Note:
10
11
12
13
14
15
16
17
18
19
20
Rating
->
L1
L2
L3
L4
(Instruction-Items not applicable for a any coach shall be marked as NA and shall not be taken in assessment of Rating)
21
22
23
24
A
B
C
Signature of Contractors Supervisor
Annex A2/2
On the Back side of Score Sheet:
Surface condition
Clean, no dirt or stains
Clean, very slight stains with visible cleaning effort
Very light dirt or stains visible
Minor dirt/stains visible
Fair dirt and stains visible
Severe dirt and stains visible
Extremely dirt/stained
Sl.No.
OVERALL RATING
80- 90%
(i)
70-80%
(ii)
Rating
10
9
8
6
4
2
0
PENALTY IF ANY
10% of the accepted rate/coach will be recovered from the bills for no. of coaches in
that rake.
20% of the accepted rate/coach will be recovered from the bills for no. of coaches in
that rake.
No payment will be allow ed for the that rake for the day.
Annexure-3
Pit occupation chart
Repair line
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Weekly Berthing
Route-12A
2KP
Route-12B
Route-14
Contd.
2815/8475
4KP
8477
2802
8439,8449,8401,8403,8405(Weekly)
(I/PIT)
214
Route-16
5639/5640 (Sat)
8410
8452
210
(PIT)
Washing Line
210
Route-18
Route-19
2002+212
5639/40
2KP
8452
8008
8410
4KP
Washing and cleaning activities are done in Route no 18,19,14 &16(T otal 4 nos lines)
214
202+212
Contd.
Annexure-A4
Dear Passenger,
As valued passenger your view s & feedback on Cleanliness and Passenger Amenities , are very
important to us. East Coast Railway endeavor s to provide you the best cleaning and hygienic
services . Your valuable feedback would help us further improve the cleanliness standards.
Kindly spare your few minutes in Rating the areas as given in table below :
5= Excellent, 4 = Very Good, 3=Good, 2=Average & 1=Poor
5
Areas of Cleaning/Services
Please mark ( Tick ) in space
T oilet Washing & Cleaning
T oilet Drying
T oilet Mirror Cleaning
Wash Basin Cleaning
Cleaning of Coach Floor Area
Cleaning of Door Area
Cleaning of Vestibule Area
Cleaning of Window Glasse s
Cleaning of Dust Bins
Cleaning of Berths/Seats/Side Panels/Roofs
Cleaning Fittings & fixtures & Fans & Electrical
Cleaning of coach exterior
Availability of water
Passenger Name:
Berth/ Seat # :
Rake #
Date of Journey:
Signature of Passenger
Annexure A5
S core on
First Check
S core on 2
Check
nd
Average Score
Item(s)
Type of Operator required
Age Group
Specification(s)
Semi-Skilled/Unskilled
18 - 35
Item(s)
Qualification of Supervisors
Qualification of Project Supervisor
cum Service Engineer
Specification(s)
Graduate
Diploma in Electrical/
Mechanical + 3 to 4 years of
experience
25 - 35
Age Group
Particulars
Approximate
M ake
Qty.
LT panel Board ( 800 X 600 X 400 mm)
consisting of 1 X 100 A,416 Volt,4 pole
MCCB,200A copper bus bar and 63A,416V,4
Pole MCCB 3 Nos
50 sq.mm. x 3.5 core PVC,Aluminum unArmoured cable
80 Nos
40 Nos.
40 Nos.
MDS/L&T/Siemens/DATAR or any
other reputed make
Metal clad Plug and Socket: MDS
/BCH or any other reputed make
1500 Meters
MS Angle Support 25 x 5 mm
40 nos.
Machines: (Equipments)
The Contractor/ Agency is advised to utilize following types & no. of cleaning machines of state
of the art technology using least possible of Water & Electricity to control expenditure to
exchequer. The types of machines to be used are:
Portable Type High Pressure Jet Machine.
Portable Type Single Disc Mini Scrubber & scrubber drier
3. Portable Type Wet & Dry Vacuum Cleaner.
1.
2.
Some of the important specifications/ features required in the machines are as follows:
1.
It should be a rugged and reliable w et, dry & carpet extractor single phase vacuum cleaner
having accessories for effective cleaning in wet, dry & Carpet extractor conditions. This machine
should be supplied with accessories such T nozzle, Flexible intake tube, Carpet/Floor brush,
The suction cleaner shall be multi purpose industrial type, durable having steel tank for anticorrosion, portable, rugged in design w ith durable steel reinforced rubber hose.
It should have the facility to lift the motor separately for maintenance purposes.
The suction cleaner shall have an Air flow of 30 40 ltrs. /sec. with hose
The suction cleaner shall have a Container Volume 10-12 ltrs for dry and 5-7 for w et.
The suction cleaner shall have a minimum of 8-10 mtrs cable length.
The suction cleaner shall be equipped with lightweight plastic extension tubes for overhead
cleaning.
NB:
has
Machines: (Accessories/Tools):
(i)
All the machines used for cleaning job shall have sufficient length of Pow er Cable so that it can
take care of the coach length while tapping electrical pow er from DG pow er supply generation &
distribution system. The Power cable shall be of class-I insulation material and shall be duly
protected mechanically so that w ear & tear while daily handling shall not cause any leakage of
current resulting into fatal consequences. It shall be double insulated for extra protection.
(ii)
Floor Mopper:
Specially fabricated for Railway coaches to meet the width of Coach Aisle area (approximately 24
inches). The mop rubber shall be made of special type of sponge material (PVA) so as to absorb
& retain at least 1 litre of water. The length of the handle shall be at least 1 meter & made of mild
steel or aluminum.
(iii)
It shall be made of Stainless Steel handle of preferably 10 inches length w ith highly durable
rubber blade of size 45 cms having a locking arrangement for easier & faster removal for cleaning
or replacement.
(iv)
It shall be made of 100% cotton jute with a size at least 45 cms x 45 cms.
(vi)
Disposable bag is required for collection of waste & litter from Coaches & Dustbin of AC coaches
& after collecting the same the bag shall be disposed off to nominated municipal bin. This bag
shall be made of Milky w hite colour Polyethylene of a size 20 x 30 minimum & minimu m 80
micron gauge. Anything less than this micron size w ill not be acceptable for environmental
reasons. The polythene bag shall be printed with the name of scheme Clean Rake Station,
name of the contractor & the name of station necessarily.
The cleaning agents should preferably have near neutral PH value in used dilution.
Should have soothing fragrance & smell.
2.
A full-bodied apron covering both the upper & low er half in light green /blue colour of any
standard tricot cloth shall be provided to the worker minimu m 2 pairs a year.The uniform should
be neat,clean and tidy.
Cap:
Hand Gloves:
Workers shall wear good durable quality rubber gloves all the time w hile working on Coaches. It
shall be orange Coloured upto palm size i.e. 18 long.
Gumboot (Shoes):
Good durable quality gumboot shall be given to all workers @ 2 pairs per worker per annum.
They shall be knee length & comfortable w earing so that no obstacles are caused to workers
w hile operating on workstations.
1.
S.No.
1
Item(s)
Trouser
Shirt
4
5
6
Cap
Shoes
Torch
Qty.
2set
s
2set
s
2
2
1
2.
2
2a
2b
3
4
5
Area(s)
Behaviour:
With Railw ay Staff
With Coworker
With Supervisors
Productivity:
Quality:
Quality of Washing
Quality of Drying
Quality of Waste Collection
Quality of Waste Disposal
Quantity:
Sequence of Operations
Handling of Machines
Safety:
Electrical Safety
Team Work:
Coordination with Co-w orkers
Supervisors Training
No. of
Days
1
1
1
1
3.
a) Code of Conduct :
Dress code:
Every personnel w orking for Intensive Rake Cleaning in Depot should always be specified uniform
at all times.
Timings;
All personnel to report to work on the assigned time and be present till the assigned
time for leaving.
Behav iors;
Arguments with Railw ay staffs and RO (Railway officials) should be avoided at all
costs.
All w ork related issues or objections should be directed handled by the Site
Supervisors.
Language:
While communicating w ith Railway Staff all the Contractors men will use language
understood by them. The language used shall be preferably local language.
Annexure-II
Acceptance/deviation Schedule
(Tenderer may add more sheets if space is not adequate)
Clause #
General Conditions:
Accep ted(yes/No)
123
If No list Deviation(s)
03.
Name/s of Tender/s
Whether Individual/firm/
Company/Co-operativ e
Society (duly registered)
Permanent (i) Business address:
_________________________________________
_________________________________________
_________________________________________
_________________________________________
_________________________________________
_________________________________________
_________________________________________
If a firm:(a)
(b)
Date
and
No.
of
Registration
under
Indian
partnership
Act:_________________________________________________________________
___ ___________________________________
NOTE: TRUE COPOY, DULY ATTESTED OR registered Partnership Deed is to be enclosed in case of
partnership firm and copy of Certificate of Registration, under Indian Par tnership Act, should also be
enclosed.
05
06.
NOTE:- A certified copy of 1) Certificate of Registration, 2) Memorandum of Articles of the Society , 3) Last audited
Balance Sheet and Profit and Loss Accounts should be enclosed w ith this tender.
124
3
4
5
6
7
8
10
10
12
08.
TENDERERS SEAL
Signature/s of________________________
The tenderer/s________________________
Place:________________________
Dated:______________________
125
Railw ay,
126
1.
SCOPE OF WORK: The Contract is for Quarterly and Annual Maintenance an d testing of 5 Kg
capacity DCP type Fire Extinguishers of ______________ Division.
2.
3.
b.
c.
d.
e.
Nos.
Clean the exterior of the extinguisher, polish the painted portion with wax polish, the
brass/gun metal parts with metal polish, chromium plated parts with silver polish and
plastic components to be thoroughly washed with soap solution and sun dried.
Check the n ozzle outlet and vent holes as well as the threa ded portion of the cap for
clogging and check that plunger is clean and moving freely.
Ensure that the cap washer is intact and also grease the threads of the cap, plunger,
etc and wipe clean.
Make sure that the extinguisher is in proper condition and is not accidentally
discharged. In case of stored pressure extinguisher pressure gauge is to be checked for
correct pressure.
Check all the c omponents of the extinguisher as per the maintenance check list given
below:
The dry power extinguishers should be opened in a dry r oom and for a minimum possible time to
avoid effect to atmospheric moisture on power.
1.
2.
3.
4.
5.
6.
7.
8.
4.
Dry power extinguisher, where discharge control is fitted on the n ozzles, should be
operated before opening the extinguisher to ensure that there is no pressure in the
extinguisher.
Weigh the extinguisher to check the correct mass of power filled in it which should be
marked on the b ody of extinguisher and recor d book wh en it was first put into service.
Open the extinguisher and remove gas cartridge and see that sealing disc is intact.
Weigh and compare its mass with full mass of cartridge marked on it. In case, loss is
more than 10 perc ent, it should be replaced by n ew cartridge.
Check the operating mechanism, dis-charge controls for free movement an d closing.
Examine nozzles, hose, an d vent holes, piercing mechanism of cap cartridge holder,
grease and wipe clean.
Remove the inner shell (if any) and clean porthol es.
Empty the dry powder in a dry container and examine for caking, lumps an d foreign
matter, in which case replace it with new dry powder charge.
Examine the extinguisher using dry air.
Return the original charge to the extinguisher and fi the cartridge and other fittings.
In the first instance, by rotation if the extinguisher is due for discharge test, after
ensuring that the cap and compon ents are fully tightened nozzles an d vent holes are
free of any dust or dirt, operate the extinguisher for testing the performance.
In case the extinguisher is not falling due for discharge test as per the schedule of
records, empty the contents of the extinguishers in clean buckets and remove all the
components. In case it is failing in discharge test, procedure given in this standard is to
be followed.
127
6
7
8
9
10
5.
Examine the inside surface of the cylinder as well as the surface of the containers for
the condition of plating, for any rust formation, etc.
If there are visible rust marks, wash the cylinder thoroughly with clean water, sun dry
it and fill it with water for 24 h and observe the surface again. If there are still signs of
rust formation and plating thickness is not adequate, the plating thickness is not freshly
plated or phosphated as the case may be.
Examine the external surface of the fire extinguishers in respect of painting and if there
is damage to the painting, the surface should be re- painted with one coat of primer and
at least one coat of fire red paints as per the requirements of Indian Standard
specification.
Check up the condition of the label an d if it is not in order ensure to replace with correct
label.
Examine the cylinder an d its components in detail apart from functional point of view for
any physical damage, cracks, dents, etc. In case of any doubt, such components if
those are pressure parts should be subjected to hydraulic pressure test. If the damage
by a repair, the part should be replaced by a corr ect component.
The ann ual inspection should b e combined with the testing requirements for operational
test and hydraulic pressure test.
The extinguishers after inspection should b e refilled immediately and the date of
inspection and refilling should be indelibly marked on the extinguishers and recorded in
the register of fire extinguishers.
Painting with two coats of Red paint and re-labeling of the fire extinguishers has to be
carried out as mentioned b elow:
SSE/C&W/AQ/No.
Maintained by:
6.
128
8.
MAINTENANCE OF RECORDS
Maintenance of records should be as per IS 2190: 1992 Clause 13. The records of
maintenance, inspection and testing of all fire extinguishers including their
operational history shall be m aintained in a register as per the form at given in Annex
F of IS 2190: 1992.
9.
CERTIFICATE: -
10.
Special conditions: -
129
3. In case of dam age to the fire extinguisher due to negligence of the contractor, the
Contractor shall be required to attend to the sam e free of cost, Further, in case the
fire extinguisher is rendered un-serviceable due to such damage, the cost of the
same shall be recovered from the Contractor. Railways assessm ent of the cost of
the fire extinguisher shall be taken as final.
11.
Guarantee period: -
The guarantee period for the fire extinguishers is same as the duration between two
consecutive maintenance schedules plus 15 days. If any leakage/defect is noticed
within this period, contractor has to m ake good the leakage/defects, free of cost
and an additional penalty of Rs. 100/- per fire extinguisher shall be imposed.
12.
Payment: -
Lump sum paym ent on m onthly basis shall be m ade to contractor on the basis of
work attended and as certified by Railways representative. Service tax / V AT shall
be payable by the Contractor as per extant rules.
130
14.
a)
b)
c)
d)
Following documents & credentials should be submitted along with this offer.
A.
Requisite Earnest Money Deposit Receipt.
B.
Permanent SSI registration certificate.
C.
Declaration by tenderers of having infrastructural facilities, tools and plant,
etc, for carrying out various testing and m aintenance schedules of DCP type of
fire extinguishers.
D.
Contractor should have testing approval from Explosive departm ent for
Hydraulic pressure testing of fire extinguishers.
E.
Latest professional tax and sales tax clearance certificates.
F.
List of technical persons to be engaged for the work.
G.
All risk insurance policy for m an & m aterial.
H.
Own facility of re-filling of CO 2 gas cartridge along with documentary
evidence.
I.
Railways will have full rights to inspect the infrastructure to verify the
documents given by contractor.
J.
Past experience of similar works.
K.
The tenderers will subm it with the tender a list of required m achines/ plant
and tools for carrying out various testing and m aintenance schedules of DCP
type of fire extinguishers along with necessary documents to establish the
ownership / hiring.
OTHER CONDITIONS:
A No claim Certificate shall be furnished by the contractor with regards to any demand by
the worker for regular absorption in the Railways at any point of time.
The contractor shall ensure that his staff while carrying out the said work is in uniform and
carry an identity card on their person at all times. They shall be disciplined and courteous,
and in no way indulge in activities on Railway premises that could cause loss to property or
reputation of Railways.
The contract shall be responsible for provision of adult labour and payment to labour as per
Minimum Wages Act. He shall also be responsible for safety of the contract labour and shall
provide to tools/equipments necessary for their safety. Railway shall in no way be
responsible for injury of any kind.
Tender received after the du e date time of submission will not be accepted. Railway does n ot
take any responsibility for any postal delay or receipt of tender.
15.
16.
The rates quoted shall include all taxes, royalties, over h ead ch arges etc. & no separate
charges shall be payable.
17.
The Railway reserves of the rights of not to invite tenders for any Right of Railway work or
works or to in vite op en or limited tenders and when tenders to deal with tender ar e called to
accept a tender in wh ole or in part of reject any ten der or all tenders without assigning
reasons for any such action.
18.
It shall not be obligatory on the said authority to accept the lowest tender and n o tenderer /
tenderers shall demand any explanation for the cause or rejection of his /their tender.
19.
The authority for the acceptance of the tender will rest with the Central Railway, which does
not bind itself to accept the lowest or any other tender, nor does it undertakes to assign
reasons for declining to consider any particular tender or tenders.
20.
The successful tenderer shall be required to submit the lincence for executing this work from
Maharshatra Labour Commissioner or Central Labour Commissioner within seven days from
the receipt of Acceptance Letter.
131
The successful Contractor shall have only execute the work after submission of license within
stipulated time failing which Acceptance Letter shall be revoked without any notice.
The above work will be subject to the gen eral conditions of the contract up to correction slip in
force on C entral Railway in a ddition to these special terms & conditions as laid down her e in
above
132
ANNEXURE VI
CENT RAL RAILWAY
PROFORMA - 1
MECHANICAL DEPARTMENT
S TRUCTURE OF ORGANIZATION
1
Name of the Company
Address
2
Descrip tion of the major field of activities of the comp any
3
Number of y ears of exp erien ce in the field of execution of
works of similar Nature
4
Name and address of p artners of associated comp anies, if
any p rop osed to be involved in the p roject.
5
Name and address of the collaborators / consultants, if any ,
who will be involved in the p roject
6
Name and address of Bankers
7
Attach an organization Chart showing the structure of the
comp any including n ames and p osition of Directors and key
p ersonnel
133
CENTRAL RAILWAY
Category
No. of
personnel
a) On p ermanent roll
b) Temp orary
c) Likely to be
made av ailable
on works
134
Name
Qualification
CENTRAL
RAILWAY
PROFORMA III
MCHANICAL
DEPARTMENT
Particulars of No./
equip ments
Unit
Kind
/
M ake
Capacity
Age
and
Condit
ion
Details
of work
where
machin e
ry is in
use
at
p resent
Details of Remarks
machin ery
is
hyp othecate
d to any
bank
or
institution
Sr.No
135
R em a r ks
CENTRAL RAILWAY
FINANCIAL STATUS
1
2
4
5
6
7
8
8.1
8.2
8.3
8.4
8.5
9
Form of Business
Proprietary
Partnership Comp any
Whether the business p artnership is registered
Whether registered with RAILWAYS or other GOVT or
PUBLIC Sector undertakin gs (p rovide latest cop ies of
registration, validity)
Date and commen cement of Business
Authorized and p aid up capital (a cop y of the articles
of association to be enclosed)
Financial Position
Cash
Current Assets
Council Liabilities
Workin g Capital
Net Worth
CENTRAL RAILWAY
PROFORMA - V
Descrip tion
of work
Total
value
of
work
Date of
Award
of work
Stip ulated
comp letion
date
Date of
Actual
comp letion
Remarks
Performance for relev ant works in p rogress by the Tenderers from different organizations
Sr.
No.
Name of the
Govt.
Deptt/Client
with address
Descrip tion
of work
Total
value
of
work
Date of
Award
of work
Stip ulated
comp letion
date
137
%age
p rogress
on date
Remarks
Work of setting up of a
mechanized laundry (of capacity
of 1 ton of linen per shift, as per
detailed specifications at Clause
V of tender document) at
Wadibunder, Mumbai Division
on turn key basis
138
S r.
No
Name of Work
Work of setting up of a
mechan ized laundry (of
capacity of 1 ton of linen
p er shift, as p er detailed
sp ecifications at Clause V
of tender document) at
Wadibunder,
M umbai
Division on turn key basis
Approxima
te
Cost of the
Work
Rs.
96,94,800/-
EMD
Rs.
1,93,900/-
Cost of
Tender
form
Rs.
5,000/-
Completio
n
Period
Date of
Opening
Validity
15.06.09
at 15:30
hrs
Six
months,
besides
Warranty
180 day s supp ort as
p er Clause
no. VIII of
the tender
document
Prescribed tender forms can b e obtained from the office of the undersigned on all workin g days up to
17.00 hrs. on cash p ay ment of the cost of tender form (non-refundable). If the tender form is
obtained from the office of the undersigned, the cost of the tender form should be p aid in cash with
Chief Cashier, Central R ailway , Chhatrapati Shivaji Terminus M umbai (CSTM ) or Divisional Pay
M aster, Central Railway , CSTM or with Station M anager / Station M aster of any station of Central
Railway .
The tender form shall also be disp lay ed on website at www.t enders.gov.in If the tender form is
downloaded from the website, the p ay ment towards cost of tender form must be mad e in the form of
DEMAND DRAFT issued by any Nationalized Bank in favour of Sr. Division al Finan ce
M anager/Central Railway /M umbai CST. The Demand draft should be enclosed alon g with the
tender documents submitted by the tenderer (s).
Railway Administration shall not be responsible for any delay / d ifficu lties / in accessibility of the
down loading facility for any reason whatsoever. In case of any discrep ancy between the tender
documents down loaded from Internet and the master cop y available in Sr. DM E (Coaching) BBs
office, the latter shall p revail and will be binding on the tenderer (s). No claim on this account shall
be entertained.
Sale of tender forms will be closed at 17.00 hrs. one day before the tender opening date. Tenderer
(s), who want to be p resent at the time of op ening of tenders, may do so.
The EARNEST MONEY should be deposited in any of the following forms, in the name of Sr.
Divisional Finance M anager, Central Railway , M umbai CST: (i) Dep osit Receip ts, Pay Orders,
Demand Drafts issued by The State Bank of India or any of the Nationalized Banks (ii) Dep osit
139
ii.
iii.
Total Contract amount received durin g the last three y ears and in the current financial y ear
should be min imum 150% of the adv ertised tender value of work. Tenderer(s) shall submit
documents to this effect, in the form of attested certificates from emp loy er/client, or audited
balance sheet duly certified by Chartered Accountant
As proof of technical exp erien ce/comp etence, the tenderer(s) themselves or the OEM s of the
machin es / equ ip ment to be supplied and installed by them, should have in their individu al
cap acities comp leted at least one similar work for minimum valu e of 35% of the advertised
tender value of work in the qualify ing period i.e. current y ear and three p revious financial
y ears (even though the work might have commenced before the qualify ing p eriod). Total
value of similar nature of work comp leted durin g qualify ing p eriod and not the pay ment
receiv ed within the qualifying p eriod alone shall b e consid ered for the purp ose. Similar work
imp lies, manufacture, supply & commissioning of major laundry equipment of
significant capacity in five star hotels, major hospitals or industries of national /
international repute, in India, by the tenderer(s) or OEMs of the machines /
equipment, in their individual capacities. Railways interp retation as to whether the
tenderer(s) fulfill the criteria for hav in g done similar work of ad equate valu e shall b e final.
The tenderer should be OEM or an authorized agent / authorized dealer of OEM whose
equip ment / machine h e is p rop osing to supp ly . Said authorization should be valid at least up
to a p eriod of three y ears after expiry of the warranty p eriod as per Clause VIII. The scop e of
said authorization should include p rovision of after sales services, warranty supp ort, AM C,
supply and fitment of sp are p arts / machine consumables, etc. Moreover, the tenderers shall
have to submit attested certificates from OEMs that in the event of withdrawal of their
authorization by them during the warranty p eriod for any reason whatsoever, the OEM s
shall themselv es be liable for ensurin g warranty maintenance of their machin es / equipments
as per the same terms and conditions of contract. However, the Security dep osit of the
140
iv.
IV.
x.
xi.
xii.
xiii.
xiv.
xv.
2.
3.
4.
5.
b. Price Bid (Annexure E): Price (Financial) bid shall consists of schedule of rates i.e.
total cost offered by the tenderer for setting up the mechanized laundry on turn key
basis, breakup of cost of individu al mach ines, terms of AM C and cost of sp are p arts /
machin e consumables. Railway s reserve the right to award AMC to the tenderer, for
all or any of the machines supp lied and commissioned by him as p art of the turn key
contract, after exp iry of the warranty p eriod, as p er the terms quoted by him and
accep table to Railway s. Railway s further reserve the right to procure any of the the
sp are p arts / consumables normally required for maintenan ce of the machin es from
the tenderer as p er rates quoted by him and accep table by Railway s. However, said
AMC or p rocurement of sp are p arts / consumables shall be outside the scop e of this
contract which shall be awarded only for the supp ly and installation of the
mechan ized laundry equipment and commissionin g of the mech anized laundry on
turn key basis, besides p rovision of warranty support, training, etc.
Only those contractors shall qualify for Price (Financial) Bid op enin g, whose Technical
Bids have been accepted and have met all eligibility criteria of the tender
All offers shall b e submitted before the time and date fixed for the receipt of the offers
as set forth in the tender p apers. Offers received after the stip ulated time and date are
liable to be rejected.
In case of joint bidding, the tenderer must submit Affidavit that they will be
executin g the contract jointly throughout the p eriod of contract. The gu idelines for
p articip ation of joint venture firms in works tender are enclosed at Annexure D.
All offers in the p rescribed form should be submitted in Two-Packet system. One
p acket shall called Technical Bid and the other p acket be called Price (Financial)
Bid. These shall be sep arately sealed in individual envelop e distinctly marked as
142
6.
Note:
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
V.
Sr
No
1
2
3
Tenderer(s) may carefully note that their Contract Agreement for this work is liable to be
terminated at any time later, in case any of the information furnished by them is found to be
untrue or any adverse p oints come to light subsequently . The decision of Railway in this
regard shall b e final and bind in g.
The tender documents are not transferable and the cost of the tender document is also not
refundable.
Conditional tenders are liable to be rejected straight away Railway reserves the right to reject
such tenders summarily without assignin g any reasons whatsoever.
Non-comp liance with any of the conditions set forth herein abov e is liable to result in the
tender bein g rejected.
The tender forms not accomp anied with Earnest Money will be summarily rejected.
Any other information required by the tenderer can be obtained from the office of Sr. DM E
(Coachin g), Central R ailway , M umbai during workin g hours.
Pre bid meetin g shall b e held on 28 /05/2009 at 15/30 hrs in the office of Sr. DM E (Cog),
DRMs office, Central Railway , Chattrapati Shivaji Terminus, Mumbai.
This tender is bein g invited for setting up of the mechanized laundry of 1 T p er shift cap acity
as a p ilot p roject.
S pecifications of work for setting up of mechanized laundry at Wa di Bunder, Mumbai
Division on turn key basis
i.
The mechanized laundry should be able to handle a designed load of at least 1 ton of
linen p er shift of 8 hours (actual working time of 7 hrs).
ii.
The mechanized laundry is to be commissioned on turn key basis within a p eriod of six
months from the date of Letter of Acceptance.
iii.
The major p ortion of work would be washing of bed sheets, hand towels and p illow
covers. The current specifications and ap p roximate break-up of these items in terms of
quantity to be washed per shift is as mentioned below:
Sp ecification
st
143
Approx. Quantity to be
washed p er shift
1800
900
900
v.
vi.
vii.
viii.
ix.
x.
xi.
xii.
The equip ment / machines supp lied by the tenderer should be techno lo gically sup erior,
maintenance and op eration friendly , state of the art, of robust design and comp arable to
best availab le world wid e. The machines should operate on normal voltage and typ e of
electric sup p ly available at Wadibund er dep ot.
For the guid ance of the tenderer(s), the basic sp ecifications of the mach ines / equipments
are as indicated in Annexure A. The tenderer(s) are requ ired to supply and install
machin es of p roven technolo gy having these or ev en sup erior sp ecifications capable of
tacklin g the designed workload up to the desired quality .
The equip ment / machin es should hav e minimu m requ irement of labour, water, p ower
and other raw materials for op erational efficiency
The equip ment / machine should incorp orate all required safety features
The laundry equip ment / machin es shall be of suitable matchin g capacity for tacklin g the
design ed workload of 1 ton of linen p er shift of 8 hrs (actual working time of 7 hrs).
The mechan ized laundry is bein g set up as a p ilot p roject and provision of sep arate
plants/equip ment for water softening, water recy clin g, etc are not env isaged as p art of the
mechan ized laundry equip ment to be supp lied and commissioned by the tenderer.
However, there could be machines av ailable in the market where there are in-built
additional features to take of these and other requirements. While these add-on features
are desirab le, the same are not mandatory . The tenderer is advised to clearly mention
these additional features as are av ailable in the machines / equ ip ment offered by him in
his technical b id.
The contractor shall furnish detailed sp ecifications of the various machines / equip ment
which he is p rop osing to supp ly and install as p art of the turn key contract. Also, the
requirement of p ower / comp ressed air / steam / chemicals / labour / other raw materials
for the mech anized laundry while deliverin g the deigned out p ut up to the desired quality
is to be furnished as p er Annexure B5 to be en closed alon g with the technical bid. These
details shall b e used by Railway s for guidan ce while ev aluatin g the various b ids received.
Wherever ap p licable said requirement of raw material is to be supp orted by certificates
from OEM s, rep uted supp lier of chemicals, or other documentary p roof, etc. The
tenderer shall be required to furnish clarification, as required by Railway s at any stage, as
to how he has arrived at the requirement of raw materials as p er Annexure B5 of the
technical b id.
Railways will make effort to supp ly municip al water for op eration of the p lant. The
tenderer may mention the quality of inp ut water required for op eration of the mechanized
laundry in his technical b id.
The tenderer, along with the technical bid, shall be requ ired to submit comp rehensive
project rep ort including detailed specification of various machin es, their operating
procedures, requirement of labour, electricity , steam, comp ressed air and other raw
materials, d etailed layout p lan of the mech anized laundry , foundation drawin gs, drawin g
of p ower supp ly arrangement, steam lin es, comp ressed air p ip ing, etc. The authorized
service en gin eer of the tenderer shall have to p hy sically p resent at the time of execution
of work which are in Railway s scop e as p er Clause VII.
144
xiii.
xiv.
xv.
xvi.
xvii.
xviii.
xix.
xx.
xxi.
xxii.
xxiii.
xxiv.
xxv.
xxvi.
i.
ii.
iii.
i.
ii.
VI.
Training / Technical Literature:
The tenderer shall h ave to give trainin g to at least 15 Railway or non Railway staff in
op eration / maintenance of the various machines / equ ip ment for a min imum duration of 6
hours p er day for a minimum period of 15 working days as p er the training p rogram /
schedule mutually decided well in advance by the tenderer and authorized Railway
rep resentative. The training could co mp rise of on the job training, v isit to p remises of rep uted
mechan ized laundries / manufacturers of laundry equip ment, class room training, p ower
p oint p resentations, etc. The tenderer may also p rovide virtual training module, CDs, etc.
Class room, LCD projector, etc can b e arran ged at Basic Trainin g Center, Wadibund er by
Railway s free of cost. After comp letion of training, the nomin ated staff should become
conversant with op erating p rocedures of the individual machin es and the mechanized
laundry . They should be in a p osition to understand the machine details and b e able to
op erate the same and also carry out minor maintenance related works, failin g which the
duration of the trainin g may be extended, as per requirement, solely at the discretion of
Railway s.
No additional cost shall be p ay able by Railway s for said training
At least 5 hard and 5 soft cop ies of the comp lete sp ecifications, and maintenance / operating
manuals of each machin e / equ ip ment shall be supp lied by the tenderer
VII. Railways S cope of S upply
Land / shed at the location of the p lant, water supp ly, civil engineerin g works related to
installation of the mach ines. The tenderer(s) are advised to visit Wadibunder dep ot prior to
submitting their offers. The location of the mechanized laundry within Wadibunder dep ot, if
so required can be altered, if so requ ired, at the time of actual execution of work, however
availability of ample sp ace shall be ensured by Railway s
Power supply up to mains of each equip ment / machine.
147
iii.
iv.
v.
vi.
VIII. Warranty:
Warranty and maintenan ce of each of the mechanized equip ment supp lied and commissioned by the
contractor for a p eriod of one y ear from the date of commissioning of the laundry or as per the
warranty p eriod of individual mach ines / equip ment specified by their OEMs, whichever is later
shall be within the scop e of the contract. The mach ine consumables (such as various lubrication oils,
filters, belts, etc. which are p art of the machin e) required for p reventive maintenance are includ ed in
the scop e of work and no additional p ay ment shall be made by Railway s for the same. The security
dep osit of the firm shall be released after exp iry of warranty p eriod as p er Railway s codal
p rovisions.
IX.
Pay ment:
The p ay ment shall be made to the contractor on the following terms:
i. 75% of the total contract value on receipt of all the mechanized equipment at Wadi Bunder
dep ot after their insp ection and acceptance of the same by the authorized Railway
rep resentative
ii.
15% of the total contract value after commissioning of the mechanized laundry and
successful op eration for a period of at least one month.
iii.
10% after satisfactory p erformance of the mechanized laundry for a period of at least four
months from the date of commissionin g.
iv. Security deposit shall be released after comp letion of the warranty p eriod as p er Railway s
codal p rovisions.
X.
Penalty
Railway administration may at its discretion imp ose the following p enalties on the Contractor:
i.
ii.
The mechanized laundry is to be commissioned on turn key basis within a p eriod of six
months from the date of Letter of Accep tance, failin g which a penalty of Rs. 1000/- (Rup ees
one thousand only ) shall be imp osed on the tenderer for each additional day , in case delay in
commissionin g of the p lant is on their account. The decision of the Railway Administration
as to whether such delay is on account of tenderer shall be fin al and b indin g and the
contractor would have no claim in this regard.
Rs.500/- (Rup ees Five hundred only ) p er day or p art thereof for each day (after two calendar
day s, excludin g the day on which the comp laint is communicated to the contractor) that any
of the mechanized equip ment supp lied and installed by the tenderer are not functioning at
their full efficiency resulting in sub op timal outp ut from the mechanized laundry . Service
engineer shall be exp ected to be available at the earliest for attending to any problem bein g
encountered in op eration of the mechan ized laundry or for any other reason what so ever.
148
XI.
Bills: Bills for work done under this contract shall be p rep ared in dup licate by the Contractor
or his authorized agent / authorized dealer after comp letion of each stage of pay ment as p er
Clause (IX) above. Su ch bills shall be submitted to the Divisional Railway Manager
(M echanical), M umbai and when p assed for pay ment by the Senior Division al Finan ce
M anager, p ay ment of amount due will be mad e by cheque or through the Chief Cashier at the
direction of the Railway Administration.
XII.
XIII.
Conditions of Contract: In addition to these Special terms & conditions as laid down
abo ve, the above work will be subject to the General conditions of the contract up to
latest correction slip in force on Central Railway. Tenderer(s) can obtain a copy of the
General Conditions of Contract from the office of S r. DME (Cog.) BB on payment of a
nominal fees of Rs. 100/- (Rupees One hundred only).
I/We here by agree to carry out the work at the rate quoted by me/us duly accepted by Railway &
abide by the terms & conditions laid down here in above.
__________________________
Signature & Seal of Tenderer.
149
150
(Tenderers may p eruse Clause IV of Sp ecial Terms and Conditions p rior to filling up of their
Technical bids)
01.
02.
03.
04.
(c)
(d)
Name/s of T ender/s
_________________________________________
_________________________________________
Whether Individual/firm/ _________________________________________
Company/Co-operative _________________________________________
Society (duly registered)
__________________________________________
Permanent (i) Business address: _____________________________________
_____________________________________
______________________________________
(ii) Residential Address:_______________________________
______________________________
______________________________
If a Firm :Whether registered or unregistered, Partnership or Proprietorship: _____
__________________________________________________________________
Date and No. of Registration under Indian partnership Act:_____________________________
NOTE: T rue copy, duly attested OR registered Partnership Deed is to be enclosed in case of partnership firm and copy o f
Certifi cate o f Registration, under Indian Partnership Act, should also be enclosed.
05
If a Company:
(a) Whether incorporated in India: _______________________________________________
(c) Names and addresses of Directors:____________________________________________
__________________________________________________________________
______________________________
NOTE:- A certi fied copy o f the (i) Certificate o f In corporation (ii) Memorandum and Articles o f Association, and (iii)
last audited Balance Sheet and Profit & loss Accounts is to be enclosed.
06.
151
Sr.
No.
Machine
/equipment
Manu facturer
/ Model
Warranty
period
(as
speci fied
by
OEM)
Capacity
in terms
of kg of
linen
Cycle time
in hrs
(including
setting up
time,
loading,
unloading,
etc)
7 = (5
6)
Output
per
hour
(in kg
of
linen)
8 = (7 X
7 hours)
10
Output
per shift
of 8
hours
(actual
working
time of 7
hours)
T ype of
linen
dealt
with
(i.e.
bed
sheets /
hand
towels /
pillow
covers)
Remarks
NOTE :
1.
Details of each ind ividual machine / equipment to be filled in separate row
2.
Detailed specifications of these machin es / equip ment, OEMs catalogues, etc. are to be
enclosed
3.
Tenderer(s) may p eruse Clause V (Sp ecifications of work) and Clause VII (Railway s scop e
of supp ly ) of Sp ecial Terms and Conditions
152
Quality /
m axim um
perm itted
m oisture
content /
any other
requirement
Quantity
(per
tonne of
linen)
Quality /
m aximum
perm issible
m oisture
content / any
other
requirement)
Chemi cal
Quality /
Hardness
, etc
Quantity
(per
tonne of
linen)
Pressure
Quantit
y (kl
per
tonne of
linen)
Discharge r ate
Requiremen
t of
Electricity
(no. of units
per tonne of
linen)
Requirement of steam
Pressure
Requirement of
water
Discharge r ate
Total
Machine /
Equipm en
t required
Supervisors
Laundry
Operatio
n
Sr
N
o
Unskilled
Suggested
m anufacturers/Brand
s
Quantit
y per
tonne of
linen
Note:
1.
Wherever break up o f individual inputs is not possible, the same may be given for the entire mechanized laundry while washing one tonne of linen per shift o f 8 hours (actual
working time 7 hours)
2.
Whereveer applicable abov e info rmation should be supported by certificat es from OEM's, reputed suppliers of chemicals, etc
3.
T enderers are advis ed to contact Sr. DME (Cog.) BB or visit Linen room near Plat form No. 14 of CST M in order to see the g eneral condition of linen and extent o f soiling
before submitting their offer
4.
T he above requirement o f labour and other raw materi al should be calculated fo r achieving the desired quality as per Clause V (xvii) of Speci fication o f work.
5. T he tenderer may be required to furnish methodology adopted for above calculation, at any stage.
153
Annexure C
ACCEPTANCE/DEVIAT ION SCHEDULE
(Tenderer may add more sheets if space is not adequate)
Clause #
Accepted (Yes/No)
Sp ecial Cond itions of contract:
Sp ecifications of work:
154
If No list Deviation(s)
Annexure D
GUIDELIN ES FOR PART ICIPAT ION OF JOINT VENTURE FIRMS IN
WORKS TENDER
1.
Sep arate identity /name shall be given to the Joint Venture firm.
2.
3.
A member of JV firm shall not be p ermitted to particip ate either in indiv idual cap acity or
as a memb er of another JV firm in the same tender.
4.
The tender form shall be purchased and submitted only in the name of JV firm and not in
the name of any constituent member.
5.
Normally EM D shall be submitted only in the name of the J V and not in the name of
constituent member. However, in excep tional cases EMD in the name of lead partner can
be accep ted subject to submission of sp ecific request letter from lead partner stating the
reasons for not submitting the EMD in the name of JV and givin g written confirmation
from the JV p artners to the effect that the EM D submitted by the lead p artner may be
deemed as EM D submitted by JV firm.
6.
One of the members of the J V firm shall b e the lead member of the JV firm who shall
have a majority (at least 51%) share of interest in the JV firm. The other members shall
have a share of not less than 20% In case of J V firm with foreign memb er (s), the lead
member h as to be an Indian firm with a minimum share of 51%.
7.
8.
Once the tender is submitted, the M OU shall not be modified/altered / terminated durin g
the validity of the tender. In case the tenderer fails to observe / comp ly with this
stip ulation, the full Earnest M oney Dep osit (EM D) shall be forfeited. In case of
successful tenderer, the validity of this MOU shall be extended till the curren cy of the
contract expires.
9.
Approval for change of constitution of JV firm shall b e at the sole d iscretion of the
Railway s. The constitution of the JV firm shall not be allowed to be modified after
submission of the tender bid by the JV firm except when modification beco mes inev itable
due to succession laws etc. and in any case the minimum eligib ility criteria should not get
vitiated. In any case the Lead M ember should continue to be the Lead Member of the JV
firm. Failure to observe this requirement would render the offer invalid.
155
Similarly , after the contract is awarded, the constitution of JV firm shall not be allowed to
be altered durin g the currency of contract except when modification become inev itable
due to succession laws etc. and in any case the minimum eligib ility criteria should not get
vitiated. Failure to observe this stip ulation shall b e deemed to be breach of contract with
all consequ ential p enal action as per contract conditions.
11.
12.
On issue of LOA, an agreement among the members of the JV firm (to whom the work
has been awarded) h as to be executed and got registered b efore the Registrar of the
Comp anies under Comp anies Act or before the Registrar/Sub-Registrar under the
Registration Act, 1908. This agreement shall b e submitted by the JV firm to the
Railway s before signin g the contract agreement for the work. In case the tenderer fails to
observe/comp ly with this stip ulation, the full Earnest Money Dep osit (EM D) shall be
forfeited and other p enal actions due shall b e taken against p artners of the JV and the JV.
This joint venture agreement shall hav e, inter-alia, followin g clauses:
12.1
Joint and several liability The members of the JV firm to which the contract is
awarded, shall b e jointly and severally liab le to the R ailway s for execution of the p roject
in accord ance with General and Sp ecial cond itions of the contract. The JV members
shall also be liable jo intly and severally for the loss, damages caused to the Railway s
during the course of execution of the contract or due to non-execution of the contract or
p art thereof.
12.2 Duration of the joint Venture Agreement- It shall be valid durin g the entire curren cy of
the contract includin g the period of extension if any and the maintenance p eriod after the
work is comp leted.
12.3 Go verning Laws- The joint Venture Agreement shall in all resp ect be gov erned by and
interp reted in accordance with Indian laws.
13.
Authorized Member- Joint venture members shall authorize one of the members on
behalf of the Joint Venture firm to deal with the tender, sign the agreement or enter into
contract in resp ect of the said tender, to receive pay ment, to witness joint measurement of
work done, to sign measurement books and similar such action in resp ect of the said
tender/contract. All notices/corresp ondences with resp ect to the contract would be sent
only to this authorized member of the JV firm.
14.
No member of the Joint Venture firm shall have the right to assign to transfer the interest
right or liab ility in the contract without the written consent of the other members and that
of the Railways in resp ect of the said tender/contract.
15.
156
15.1
In case one or more of the members of the JV firm is/are p artnership firm(s), following
documents shall be submitted:
(a) Notary certified cop y of the Partnership Deed.
(b) Consent of all the p artners to enter into the Joint Venture Agreement on a stamp
p ap er of app rop riate value (in origin al)
(c) Power of Attorney (duly registered as p er p revailin g law) in favour of on e of the
p artners to sign the MOU and JV Agreement on behalf of the partners and create
liability against the firm.
15.2
In case one or more members is/are Proprietary Firm or HUF, the following docu ments
shall be en closed:
Affidavit on Stamp Pap er of ap p rop riate value declarin g that his Concern is a Prop rietary
Concern and h e is sole p rop rietor of the Concern OR he is in p osition of KARTA or
Hindu Undivided Family and he has the authority , p ower and consent given by other
p artners to act on behalf of HUF.
15.3
In case on e or more members is/are limited companies, the fo llowin g do cuments shall be
submitted:
(a) Notary certified cop y of resolution of the Directors of the Comp any , p ermitting the
comp any to enter into a JV agreement, authorizing M D or one of the Directors or
M anagers of the Comp any to sign M OU, JV Agreement, such other documents
required to be sign ed on behalf of the Co mp any and enter into liability against the
comp any and/or do any other act on behalf of the comp any .
(b) Copy of M emorandum and articles of Association of the Comp any.
(c) Power of Attorney (duly registered as p er p revailing law) by the Company
authorizing the p erson to do/act mentioned in the p ara (a) above.
15.4
All the members of the JV shall certify that they have not been black listed or debarred
by Railways or any other M inistry /Dep artment of the Govt. of India/State Govt. from
p articip ation in tenders/contract in the p ast either in their ind ividual cap acity or the JV
firm or p artnership firm in which they were members/p artners.
16.
16.1
157
158
CENTRAL RAILWAY
MECHANIC AL BRANCH
MUMB AI CS T
TENDER SCHEDULE
Sr.
no.
Item
1
2
3
4
5
6
7
8
9
10
7 (= 5
6)
8 (7 X 7
hours)
Capacity in t erms of kg
of linen
Cycle time in h rs
(including setting up
time, loading, unloading
etc)
10
11
12
Terms of comprehensive
st nd rd
AMC for 1 /2 /3 year
after the expiry of
warranty period (mention
validity period)
Manufacturer / Model
Sr. no.
Machine / Equipment
B.
Note : 1. Details of each indiv idual mach ine / equip ment to be filled in sep arate row
2. Tenderers may peruse Clause V (Sp ecifications of work) and Clause VII (Railway s
scope of supp ly ) of Sp ecial Terms and Conditions
159
Sr
No
Machine /
Equipment
fo r which
spare part /
consumable
required
Name o f the
Spare Part /
Speci fication
consumable
/ drawing
normally
etc.
required for
maintenance
OEM's
part
no.
No. of years o f
operation o f the
machine/equipment
(working in two
shifts every day )
after which Spare
part / consumable
required (to be
fu rnished only in
case the life o f the
spare part /
consumable is
approximately
predictable)
Cost of the
spare part /
consumable
(inclusive
of all taxes
duties, etc.)
valid for
the first
year aft er
expiry of
warranty
period
Source o f
supply of
spare part /
consumable
Remarks
if any
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Tenderer(s) Seal
Note:
i. The above rates as quoted by the tenderer(s) shall be inclusive of all taxes and other
duties leviable by the Government or Local bodies. Railway s shall not be liable for any
increase in the taxes or duties levied by the Government or Local bodies which shall h ave
to be borne by the contractor.
ii. Railway s may at their discretion go in for comp rehensive or non-comp rehensive AM C or
for no AM C at all after the exp iry of the warranty p eriod. Railway s reserve the right to
award AM C to the tenderer, for all or any of the machin es supp lied and commissioned by
him as p art of the turn key contract, after exp iry of the warranty p eriod, as p er the terms
quoted by him and accep table to Railways. Railway s further reserve the right to p rocure
any of the sp are p arts / consumables normally required for maintenan ce of the machines
from the tenderer as p er rates quoted by him and accep table by Railway s. However, said
AMC or p rocurement of sp are parts / consumables shall be outside the scop e of this
contract which shall b e awarded only for the supp ly and installation of the mechanized
160
161
162
163
chan ges
hav e
DRM (Mech) BB
164
Open Tender Notice no. mentioned in the Notice Inviting Tender (page 4 of tender
document) may be read as:
Clause no. I mentioned in the S pecial Terms and Conditions of contract (page 9 of
tender document) may be read as:
The scop e of work involves setting up of a mechanized laundry on turn key basis suitable for
tacklin g a designed workload of 1 ton of linen per shift of 8 hrs (actual working time of 7 hrs).
The location of the mechanized laundry shall be at Wadi Bunder d ep ot of Mumbai division of
Central Railway . The mechan ized laundry should be cap able of washin g, drying and ironin g
(calend arin g) of at least 1 ton of linen p er shift of 8 hrs (actual working time of 7 hrs) as p er para
V below.
4.
Clause no. VIII mentioned in the S pecial Terms and Conditions of contract (page 19
of tender document) may be read as:
Warranty and maintenan ce of each of the mechanized equip ment supp lied and commissioned by
the contractor for a p eriod of one y ear from the date of commissioning of the laundry or as p er
the warranty p eriod of individual mach ines / equip ment sp ecified by their OEMs, whichever is
later shall be within the scop e of the contract. The warranty support / repairs shall have to be
provided / carried out by the tenderer on site of the mechanized laundry i.e. Wadi Bunder,
Mumbai Division. The machine consumables (such as various lubrication oils, filters, belts, etc.
which are part of the machine) required for p reventive maintenance are in cluded in the scop e of
work and no additional p ayment shall be made by Railway s for the same. The security dep osit of
the firm shall be released after expiry of warranty p eriod as p er Railways codal p rovisions.
5.
Clause no. V (xix) mentioned in the S pecial Terms and Conditions of contract (page
16 of tender document) may be read as:
The tenderer in their Fin ancial b id (Annexure E) shall submit terms for both Comp rehensive and
st
nd
rd
Non-comp rehensive AM C for the 1 , 2 , 3 y ears after exp iry of the warranty p eriod for the
various machin es / equipment. Comp rehensive AM C imp lies regular visits of the Service
165
Financial bid (Annexure E), (Page 33 to 35) of the tender document may be read as:
CENTR AL RAILWAY
MECHANIC AL BRANCH
MUMB AI CS T
TENDER SCHEDULE
Sr.
no.
Item
166
3
4
5
6
7 (= 5
6)
8 (7 X 7
hours)
Note : 1.
167
Terms of comprehensive
st nd rd
AMC for 1 /2 /3 year
after the expiry of
warranty period (m ention
validity period)
10
Terms of Noncomprehensiv e AMC for
st nd rd
1 /2 /3 year after the
expiry of w arranty period
(mention validity period )
9
Cost of machin e in Rs.
(including cost o f
installation and
commissioning)
B.
Manufacturer / Model
Machine / Equipment
Sr. no.
10
C.
Sr
No
Machine /
Equipment
fo r which
spare part /
consumable
required
Name of the
Spare Part /
consumable
normally
required for
maintenance
Speci fication
/ drawing etc.
OEM's
part
no.
No. of years o f
operation o f the
machine/equipment
(working in two
shifts every day )
after which Spare
part / consumable
required (to be
fu rnished only in
case the life o f the
spare part /
consumable is
approximately
predictable)
10
168
Rate of the
spare part /
consumable
(inclusive of
all taxes
duties, etc.)
st
valid for 1 /
nd
rd
th
2 / 3 /4 /
th
5 years
after expiry
of warranty
period
Source o f
supply of
spare part /
consumable
Remarks
if any
Complete add ress of the nea rest service centre where maintenance suppo rt and other
help can be obtained a s required by Railways after expiry of the warranty period:
____________________________________________________
__________________________________________________________________
Tenderer(s) Seal
Note:
i. The above rates as quoted by the tenderer(s) shall be inclusive of all taxes and other
duties leviable by the Government or Local bodies. Railway s shall not be liable for any
increase in the taxes or duties levied by the Government or Local bodies which shall h ave
to be borne by the contractor.
ii.
Railway s may at their discretion go in for comp rehensive or non-comp rehensive AM C or
for no AM C at all after the exp iry of the warranty p eriod. Railway s reserve the right to
award AM C to the tenderer, for all or any of the machin es supp lied and commissioned by
him as p art of the turn key contract, after exp iry of the warranty p eriod, as p er the terms
quoted by him and accep table to Railways. Railway s further reserve the right to p rocure
any of the sp are p arts / consumables normally required for maintenan ce of the machines
from the tenderer as p er rates quoted by him and acceptable to Railway s for up to five
years after expiry of the warranty period. Tenderer(s) shall be bound to supply such
spare pa rts / consumables as per the yea r wise ra tes quoted b y them in the tender
schedule above. However, said AM C or p rocurement of sp are p arts / consumables shall
be outside the scop e of this contract which shall be awarded only for the supp ly and
installation of the mechanized laundry equip ment and commissioning of the mechanized
laundry on turn key basis, besides p rovision of warranty supp ort, training, etc.
iii.
Tenderer(s) ma y atta ch additional sheet for making their offer in case necessary.
However the fo rmat for offering the rates against item nos. A, B & C of the tender
schedule shall be as mentioned above. Any overwriting / correction has to be attested /
countersigned by the tenderer(s). The rate quoted in words shall be considered as fin al
rate in case of ambiguity .
iv. The above work will be subject to the General conditions of contract in force on Central
Railway in addition to the Sp ecial terms and conditions as laid down below.
I / We hereby agree to carry out the work at the rates quoted by me/us duly accep ted by Railway
and abide by the special terms and conditions as laid down here in above.
169
The total onward/return journey of the Mail/Exp ress train identified under the
scheme must not be less than 16 hours (including a mandatory day time journey
from 0500 hrs to 0900 hrs.)
(ii) Only reserved class coaches with vestibules shall be covered und er the scheme.
(iii) Arrangements for on Board cleaning must be made by the p rimary maintenance
dep ot for the round trip of identified train rakes.
(iv) Notwit hstanding (i) above, all Rajdhani and Shatabdi trains must be in cluded for On
Board House Keep ing Services in light of their p remier status.
(v) While on Bo ard cleanin g attention should be p rovided wherever desired/d emand ed
for by the passengers, the toilets, doorways, gan gway s and vestibules must
necessarily be clean ed frequently from 0500 hrs. to 0900 hrs. and from 1600 hrs to
2000 hrs., wherever ap p licable. The p assenger comp artments and the aisle must also
be cleaned and mop ped 2 times in a day at suitable intervals. In case any deviations
are need ed due to local conditions the same may be p ermitted with the p ersonal
app roval of CM E.
(vi) CDO concerned will issue a certificate to identified p ersonnel authorizing them to
travel on p rimary Trains of his coachin g dep ot for p roviding On Board
Housekeep ing Services. No reserved accommod ation will however b e provided to
these personnel.
vii) It has further been decided that OBHS shall be mandated in all the Duronto Express
trains as in the case of Rajdhan i/Shatabdi trains.
viii) Co mp liance of Bo ards guidelines for test check p rotocol for OBHS and other coach
clean ing contracts issued vide letter no. 95/M (C)141/1 Vol. II dt.21.05.2010 must be
ensured.
170
171
(vii) Carpet Brush: For cleaning of carp et in 1 AC co aches, esp ecially designed
p olyp ropy lene bristled brush shall be p rovided @ 1 p er train and shall be rep laced as and
when the bristles are worn out.
(viii) Upholstery cleaning brush: The carp et brush should not be allowed to be used for
seat/ berth up holstery cleanin g, for which a sep arate p olyp ropy lene bristled brush shall be
used.
(ix) Bucket: A smart looking, easy to carry , low height, app rox. 6 gallons cap acity
bucket made of heavy duty p olyp ropy lene for washing of mop s etc. shall be used. It shall
p referably have castor wheels for ergonomic handlin g. This shall be provided @ 1 p er
work station.
(x) Window Glass S queezee: Stainless Steel handle of p referably 10 inches length with
durable rubber b lade of size 45 cms hav ing a lo ckin g arran gement for faster and effective
cleanin g of window glasses shall be p rovided @ at least 1 p er 3 AC coaches and rubber
blades shall b e rep laced once in 15 d ay s.
(xi) Micro Fiber cloth for mirror cleaning
(xii) S ponge Duster for wash basin cleaning
(xiii) Disposable bags for garbage collection: Green coloured Disp osable bags shall be
required for collection of waste & litter from all coaches & also from dustbins of AC
coaches.
(xiv) Tool Kit: A light weight tool kit made of FRP containing all typ es of tools for
minor p lumbing / carpentry related rep airs shall be available with Executive
Housekeep er.
(xv) Foot mats: At every toilet entrance, a foot mat made of rubber h avin g bristles to
soak water shall be p rovided and shall b e rep laced as & when required to be.
172
173