Академический Документы
Профессиональный Документы
Культура Документы
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Thanks
W.P.S.K. Jayaweera
----- Original Message ----From: ramkumar
To: "Prof. Sam" <sam99@emirates.net.ae>
Date: Wed, 07 May 2008 11:03:25 +0400
Subject: clarifications
Dear Prof Sam,
We need some clarification from you for an ongoing project.
The original time for completion of the project is 240 days, which was on Sept 2007.In
that period we have carried out only the materials and shop drawing submissions. The
actual site works started by January 2008 and all the works are expected to be completed
by August 2008.In this scenario, pl advise us on the following.
1. whether we can submit new rates for all the works or the price escalation in material,
labour ,plant to be worked out and included in the EOT claims? If you can prove that the
Employer prevented you from procuring the material and Plant within the original Time
for Completion, you may have a good case. Regarding labour, your entitlement may be
limited to in-house wage increases and not to procuring labour from market at higher
prices.
2.For any new items, can we able to give rate analysis based on the present market rates
or contract rate schedule only to be used? If the new items you are referring to are
variations which are not necessary or not appropriate to complete the original scope of
work, then you can claim new rates provided that you served a timely notice pursuant to
Sub-Clause 52.2 (a).
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Regards
Ram kumar
-----Original Message----From: sathis jayaweera [mailto:sathisjayaweera@yahoo.com]
Sent: 04 May 2008 12:00
To: sam99@eim.ae
Subject: Re: Test Email to "Class of Spring 2008"
Prof. Sam
I, W.P.S.K. Jayaweera. The my second Question as follows.
1.) If CESMM3 is a method of measurements of a BOQ. Can we consider as CESMM3 is
a part of Contract documents ? Generally Contracts state what the Contract Documents
are. You have to study that provision in detail and verify whether there are adequate links
to consider that CESMM3 has been incorporated as a Contract Document. A mere
reference in the Preamble to say that the BOQ is prepared according to CESMM3 does
not make CESMM3 a Contract Document.
2.) Supposed, in a BoQ some items were not line with the CESMM3, if the Contractor
point out that. What action the Engineer needs to take and any consequences ( like
variations) The completed work should be measured according to CESMM3 and new
rates should be agreed/fixed for all items that the BOQ Compiler failed to measure
correctly or missed-out. It would not be a variation, but a correction of incorrect
measurements.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Thanks
W.P.S.K. Jayaweera
----- Original Message ----From: Basheer
To: sam99@eim.ae
Date: Tue, 06 May 2008 10:21:41 +0400
Subject: RE: Dear Class of Spring 2008 - Q&A 1
Dear Sir,
I attended your class of spring 2008, it was very much useful for a APC candidate like me, thank
you very much for your valuable time.
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Thanks
W.P.S.K. Jayaweera.
----- Original Message ----From: "Noufel K.Mohamed"
To: sam99@eim.ae
Date: Mon, 05 May 2008 15:15:24 +0400
Subject: Float in the Clause 14 Program
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
If he qualified his Tender regarding his assumption of 100-200m distance and the Employer accepted the
Tender unconditionally, then the new distance is a variation, irrespective of whether or not he visited the Site.
If there was no such qualification/acceptance and if all the documents are silent about the distance, then it is
at Contractors risk. This comment equally applies to the question of water table.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
regards
Ashlyn
----- Original Message ----From: sathis jayaweera
To: sam99@eim.ae
Date: Mon, 05 May 2008 05:37:25 -0700 (PDT)
Subject: Dear Class of Spring 2008 - Q&A 1
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Regards
W.P.S.K. Jayaweera
----- Original Message ----From: "arunachalam.murugan"
To: sam99@eim.ae
Date: Mon, 05 May 2008 15:43:38 +0400
Subject: RE: Dear Class of Spring 2008 - Q&A 1
Please accept my heartfelt thanks for your valuable continued service to the Industry
and to your Students, specially for your intention to extend your knowledge to us through
this Q & A.
I am most admired by your 30 hour Training which has really provided me a much high
confidence level in arguing/ discussing the contractual/ commercial matters with my
peers and Seniors in a much better way I have ever done before.
I could observe that my ability to understand the core of some of the contractual issues
has been tremendously improved and I feel myself proud and courage to face many
interesting issues in the future ( in my career as a QS).
Thank you so much again for the continued support.
With Best Regards
Arunachalam
Quantity Surveyor
DE LEEUW MIDDLE EAST
DUBAI
Dear Mr. Arunachalam,
Many thanks.
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Regards,
Ram Kumar
General Manager
Dear Mr. Ram Kumar,
You are welcome.
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668