Академический Документы
Профессиональный Документы
Культура Документы
Anatec
Address:
Tel:
Fax:
Email:
Prepared by:
Anatec Limited
Presented to:
EnQuest
Date:
Revision No.:
00
Ref.:
A3304-EQ-HAZOP-1
Aberdeen Office
10 Exchange Street, Aberdeen, AB11 6PH, UK
01224 253700
0709 2367306
aberdeen@anatec.com
Cambs Office
Braemoor, No.4 The Warren, Witchford, Ely, Cambs, CB6 2HN, UK
01353 661200
0709 2367306
cambs@anatec.com
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
TABLE OF CONTENTS
1.
INTRODUCTION............................................................................................................ 4
1.1
1.2
1.3
1.4
2.
3.
APPROACH ................................................................................................................ 15
HAZOP ACTIONS ..................................................................................................... 16
SIFS .......................................................................................................................... 16
RESPONDING TO HAZOP ACTIONS ........................................................................... 16
APPROVING ACTIONS ................................................................................................ 17
4.
5.
Date:
Doc:
Page:
- with P&IDs
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Glossary:
BLV
bpod
ESD
ESDV
F&G
FPSO
HAZOP
HP
HPU
ICSS
LP
OIM
P&ID
PSD
SIF
SIL
Date:
Doc:
Page:
- with P&IDs
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
1. Introduction
1.1 Knightsbridge Development
The Knightsbridge development will develop the remaining oil reserves in the Alma
(formerly Ardmore and Argyll) and Galia (formerly Duncan) fields. The Alma field lies in
Blocks 30/24 and 30/25, the Galia field lies in blocks 30/24 and 30/29, 310 km south-east of
Aberdeen in the UKCS North Sea.
EnQuest plan to redevelop the field with 7 subsea production wells tied back to a floating
production, storage and offloading (FPSO) vessel, through means of two 8 production risers.
As the wells are expected to have a 70%+ water cut, they will be produced with the aid of
electrical submersible pumps. Reservoir pressure will be maintained by produced water reinjection through means of two 8 risers, supplemented with treated seawater.
Doc:
Page:
- with P&IDs
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
for further dry dock inspection. The water depth at this location is approximately 78 m.
Crude oil production rate is predicted as 57,000 bopd.
1.2 Previous HAZOP Studies
The development is approaching the end of the design and construction phase and EnQuest
are preparing for commissioning and operations.
A number of HAZOPs have been carried out at various times during the design phase:
Dates
Description
EQ / AMEC Doc No
Boiler HAZOP #1
A2867-EQ-RP-1
Subsea HAZOP
THL-KN501-HS-505-REP-0001
Topsides HAZOP
THL-KN501-HS-505-REP-0002
Utility HAZOP #1
Not issued to EQ
Boiler HAZOP #2
ENQ-KN501-HS-000-REP-0005
Utility HAZOP #2
THL-KN501-HS-505-REP-0003
Marine HAZOP
ANA-KN501-HS-100-REP-0002
Utility HAZOP #3
TH-S-R-1119-01
Although it is considered that all relevant systems and packages have been subject to formal
HAZOP study, there may have been changes in key process characteristics, equipment
selection or interface issues that may not have been fully addressed, or change the way the
system is to be operated.
1.3 End to End HAZOP Purpose
The purpose of the End to End HAZOP Review was to review the entire process and utility
systems at a "high" level to identify any significant changes, interfaces or missed areas that
may require further HAZOP review.
This was not intended to be a conventional HAZOP study, however, if a gap was identified in
the original HAZOP study, or if the design or operating parameters have significantly
changed, a conventional HAZOP study of that particular item was adopted, or actioned for
later study.
The objective of the End-to-End HAZOP Review was to provide a formal review of the
design and operation of the Knightsbridge facilities from wells to export, including marine
systems, in order to address:
Completeness of original HAZOP studies and identify any gaps;
Date:
Doc:
Page:
- with P&IDs
"
&
'
"
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Interface issues (in particular any assumptions made in the HAZOP studies due to
incomplete design information, or any changes);
Overall design and operability;
Significant changes to design or operating parameters.
The existing HAZOP study reports, HAZOP Action Register and latest P&IDs will form the
basis of the End to End HAZOP Review.
This End to End HAZOP has been carried out in accordance with the EnQuest HAZOP
Terms of reference [ENQ- KN501-HS-100-TOR-0002 A2].
1.4 Scope of HAZOP
The scope of the HAZOP included the following systems:
+
Steam condensate (Marine System 315) return to topsides deaerator was not
completed because the pumping system and interface control system between topsides
and marine steam systems require further development;
HPU systems for subsea control / valve operation and for operation of the Riser
ESDVs have not been seen and so may not have been HAZOPed.
Actions have been raised to ensure these two items are assessed in due course.
Date:
Doc:
Page:
- with P&IDs
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
2. HAZOP Administration
Paul Caldwell
Steven Armstrong
Sandeep Ghotey
Review Chairman
Review Scribe
Knightsbridge Process
Engineer
Peter Benson
Operations Process Engineer
Michelle McRobbie Marine Systems Engineer
Matt Hastings
Process TA
Malcolm Robertson Production Supervisor
Doug McGregor
Instruments Engineer
Mike Webster
ESP Package Engineer
Mark Toshney
Subsea Engineer
Shaun Wilson
Umbilical Engineer
Bill Gracie
Subsea Controls Engineer
Donald Paterson
Steam Engineer
Iain MacLeod
MCO EnQuest Producer
John Chadwick
Mechanical Engineer
Geoff Black
Process Engineer
Ali Al-Khayat
Process Engineer
John Lennox
Process Engineer
Colin Greenlees
Process Engineer
Richard Auld
Controls & Instrumentation
Shah Ahmed
Controls & Instrumentation
Neil McMillan
Controls & Instrumentation
Peter Marchant
Safety Engineer
Paul Renwick
Safety Engineer
Neil Wise
Process Engineer
Anatec
Anatec
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
AMEC
AMEC
AMEC
AMEC
AMEC
AMEC
AMEC
AMEC
AMEC
Parsons
Brinckerhoff
Tues 29th
Mon 28th
Company:
Fri 25th
Title:
Wed 23rd
Name:
Thurs 24th
The HAZOP sessions were held at AMEC's City View offices, Aberdeen.
Date:
Doc:
Page:
- with P&IDs
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Date:
Doc:
Page:
- with P&IDs
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Doc:
Page:
- with P&IDs
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Swivel Drains:
0400-110-F100-PID-019-001 Rev C2 Swivel Drains Recuperation System
Boiler Drains:
0400-110-F100-PID-022-001 Rev C2 Boiler Package Hazardous Open Drain Collection System
Seawater:
0400-110-F120-PID-001-001 Rev C2 Seawater Distribution
0400-110-F120-PID-002-001 Rev C3 Seawater for Deck Modules
0400-110-F120-PID-003-001 Rev C3 Seawater for Deck Modules Coarse Filters
0400-110-F120-PID-005-001 Rev C3 Electrochlorination Package
0400-110-F120-PID-006-001 Rev C3 Seawater for Deck Modules Seawater Lift Pumps
0400-110-F120-PID-008-001 Rev C3 STU Deaerator and Vacuum Pumps
0400-110-F120-PID-010-001 Rev C3 STU Seawater to Deaerator
0400-110-F120-PID-014-001 Rev C2 Overboard Caisson Starboard Side Forward
Firewater:
0400-110-F120-PID-017-001 Rev C3 Firewater Distribution Accommodation Area
0400-110-F120-PID-018-001 Rev C2 Firewater Jockey Pumps 615-P-004 A&B
0400-110-F120-PID-019-001 Rev C2 Firewater Pumps 615-P-001/002
0400-110-F120-PID-020-001 Rev C3 Firewater Distribution Aft Area Ringmain
0400-110-F120-PID-021-001 Rev C3 Firefighting Pump & Foam System Forward
0400-110-F120-PID-023-001 Rev C2 Firewater Distribution Engine Room / Aft Area
0400-110-F120-PID-024-001 Rev C3 Firewater Distribution Fwd Area Ringmain
0400-110-F120-PID-025-001 Rev C3 Firewater Distribution Helideck & Aft Deck
0400-110-F120-PID-027-001 Rev C3 Fire Fighting Pumps System in Pump Room After and Foam
Del. On Pump Room Bottom:
0400-110-F120-PID-029-001 Rev C2 Helideck & Sterndeck Water/Foam Monitoring System
0400-110-F120-PID-030-001 Rev A2 Engine Rom High Expansion Foam System
Blaze Vendor Foam Skid P&IDs:
P0400-131-F120-006-CO3-001/2/3/4/5 Rev 04 P&ID: Deluge Skid A/B/C/D/E
HP Water Injection / Produced Water:
0400-110-F150-PID-001-001 Rev C3 P&ID Produced Water Degasser 510-V-002
0400-110-F150-PID-002-001 Rev C3 Skimmed Oil Pumps 510-P-005 A/B
0400-110-F150-PID-003-001 Rev C3 Seawater Treatment Unit LP Booster Pumps P-5660-A/B
0400-110-F150-PID-004-001 Rev C3 Water Injection Pumps 535-P-001 A/B
0400-110-F150-PID-005-001 Rev C3 Water Injection Pumps 535-P-002 A/B
0400-110-F150-PID-006-001 Rev C3 Produced Water Coolers E-5175 A/B
0400-110-F150-PID-009-001 Rev C3 Production Separator Hydrocyclone S-5111
0400-110-F150-PID-010-001 Rev C3 Pumps 510-P-009 A/B Dehydrator Produced Water Recycle
0400-110-F150-PID-011-001 Rev C3 Production Hydrocyclones S-5801
0400-110-F150-PID-013-001 Rev C3 Production Separator Hydrocyclone S-5112
0400-110-F150-PID-014-001 Rev C2 Produced Water Filter Package
Topsides Steam Systems:
PBL-KN501-PR-315-DRG-0001-001 Rev C4 P&ID: HP Steam Header, IP&LP De-Superheater
PBL-KN501-PR-315-DRG-0002-001 Rev C4 P&ID: 20 Bar Steam Distribution
PBL-KN501-PR-315-DRG-0003-001 Rev C4 P&ID: LP (8 Bar) Steam Distribution
PBL-KN501-PR-315-DRG-0004-001 Rev C4 P&ID: Turbine By-Pass
PBL-KN501-PR-315-DRG-0005-001 Rev C5 P&ID: Condensate Return System
PBL-KN501-PR-315-DRG-0006-001 Rev C4 P&ID: Boiler Feed Water
Date:
Doc:
Page:
- with P&IDs
10
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Doc:
Page:
- with P&IDs
11
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Doc:
Page:
- with P&IDs
12
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
The latest BLV drawings reviewed in the End to End HAZOP had some red line, hand
marked "as-built" and latest design change corrections and so are included in Appendix C.
-
Date:
Doc:
Page:
- with P&IDs
13
<
<
<
>
>
<
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Node:
10
20
Description:
Subsea Production to 1st Stage Separation (multi-phase flow)
Oil Stabilisation (Interstage Heater, 2nd Stage Separator & Electrostatic
Dehydrator) to Cargo Tanks
30
Produced Water Treatment (plus overboard disposal)
40
Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to
Flare, plus Hydrocarbon Condensate Return
50
Oil Water Recycle from 2nd Stage Separation and Hydrocyclones to 1st
Stage Separator
60
Flare & Vent System, including Return of Liquids to Process System and
Emergency Blowdown
70
Process Drains System, Closed Drains, Hazardous Open Drains, Deluge
Drains and Swivel Drains
80
Seawater Supply (Existing and New Lift Pumps, Coarse Filtration, Seawater
Users and Overboard Dump)
90
HP Water Injection (Produced Water and Seawater) to Subsea Wells
100
Chemical Injection and Helifuel, Swivel Recuperation System, Boiler Crude
Fuel Additive Chemical
110
Plant Air, Nitrogen, Hypochlorite, Freshwater Cooling System, other
Topsides Utilities
120
Steam Generation, Fuel Supply and Steam Distribution to Consumers
130
Steam Condensate Return (Topsides and Marine) and Boiler Water Make-Up
140
Cargo Storage, Handling, Pumping and Offloading, including Tank
Stripping, Washing, etc.
150
Inert Gas and Cargo Tank Venting, Purging, Gas Freeing
160
Seawater System, Firewater Pumping and Distribution
170
Potable Water, Freshwater Cooling System
180
Diesel Bunkering, Storage, Transfer and Purification
190
Bilge, Ballast, Sounding and Gauging, Drains & Sewage
200
New Marine Systems not Previously HAZOPed
Nodes for Systems not Previously HAZOPed, but Requiring HAZOP:
71
Closed Drains
121
ER Steam Heat Exchanger
122
Heating Water Loop for Engine Room
161
High Expansion Foam System for Engine Room
Date:
Doc:
Page:
- with P&IDs
14
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
3. HAZOP Methodology
3.1 Approach
The End to End HAZOP Review methodology was slightly different from a conventional
HAZOP (as described in Appendix A, which was used for three new systems (Nodes 71, 121
& 122 and 161) / P&IDs the team decided required new HAZOP).
The End to End HAZOP Review took the following approach:
The chairman / project process engineer introduced each node or session and provided a
summary of the extent of the previous HAZOP and any significant changes that have
occurred since - these may be as a direct result of actions raised in the previous HAZOP, or
due to design change or equipment procurement / construction change.
The independent Chairman then led the team through each of the following steps:
U
The HAZOP Review was recorded using the "HAZOP Manager" software.
By using the guidewords, the Chairman stimulated lateral thinking to identify potential
hazards and operability concerns. The End to End HAZOP Review guidewords are listed on
the next page.
The Chairman allowed scope for additional guidewords to be used for particular sub-systems
where deemed necessary by the Review team.
The Review team did not attempt to produce solutions by redesigning the plant during the
review sessions - any issues which could not be resolved promptly during the sessions were
resolved by formulating a suitable action.
Date:
Doc:
Page:
- with P&IDs
15
<
<
<
<
>
<
>
>
>
<
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Equipment Change
Interface Issues
Operability Issues
Maintainability Issues
Completeness of
Previous HAZOP(s)
or if they are:
Date:
Doc:
Page:
- with P&IDs
16
<
>
<
<
>
<
<
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
4. HAZOP Findings
The following key findings / issues arose out of the End to End HAZOP:
]
The majority of the systems and P&IDs have been covered in the earlier HAZOPs,
and the findings of those HAZOPs are still valid (note: all but a few of the earlier
HAZOP actions have been closed out);
Some equipment or design change has occurred, mainly in the marine systems. Some
drain lines have been re-routed and the oil export fiscal metering flushing line has
been modified;
Two new vendor packages have been added since the earlier HAZOPs (a new Blaze
foam package for the Engine Room, and a Heinen and Hopman Steam Heater and
closed loop heating medium and space heaters for the Engine Room). Both these
packages were subject to conventional HAZOP during the End to End HAZOP review
and are included in this report;
The Closed Drains Header and routing to the Residual Tank M-14 has been subject to
some modification and so was re-HAZOPed using conventional HAZOP guidewords,
and is presented in this report;
New hydraulic systems and interface pipework have been designed for marine
actuated valves and aft offloading winches. These were reviewed during the End to
End HAZOP but due to their simplicity, no adverse consequences were foreseen.
However, a formal review by a competent person should be made of the HPU
packages (vendor items) when the details are available. The same applies to the HPU
packages for riser ESDVs and subsea LP & HP supply to actuated valves;
Some minor interface issues were identified and actioned;
Some aspects were raised for clarification, but these are not expected to lead to further
design change;
The steam condensate return from marine consumers requires development of the
pumping system. In addition, the level control systems for the various marine and
topsides condensate collection vessels and boiler feedwater make-up requires HAZOP
as this has been deferred from the earlier HAZOPs.
Actions have been raised to address these issues / concerns, as summarised in Section 5.
Date:
Doc:
Page:
- with P&IDs
18
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
5. HAZOP Actions
The following End to End HAZOP Actions were raised:
No. Action:
Responsible
Person:
Due to the need to be able to deal with hydrates subsea during the
initial production phase, ensure that the topsides temporary
methanol injection facilities are HAZOPed as well as the usual risk
assessment for temporary equipment offshore.
Sandeep Ghotey,
EnQuest
Sandeep Ghotey,
EnQuest
Ensure outlet lines from PSVs 1133/1134 at the Inlet Coolers are
shown on P&IDs with a slope to the Flare Knock Out drum and no
pockets.
Geoff Black,
AMEC
Node 20 - Oil Stabilisation (Interstage Heater, 2nd Stage Separator & Electrostatic
Dehydrator) to Cargo Tanks
4
Change from AC11BS (17 barg) topsides pipe spec to marine MT2
spec (16 barg) should be identified on marine P&IDs.
Sandeep Ghotey,
EnQuest
Ensure that adequate pipe stress analysis has been carried out
across topsides and marine pipe interfaces and that existing and
new tie points as shown on AMEC P&IDs.
Sandeep Ghotey,
EnQuest
Geoff Black,
AMEC
Sandeep Ghotey,
EnQuest
Sandeep Ghotey,
EnQuest
Node 40 - Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to
Flare, plus Hydrocarbon Condensate Return
9
Date:
Doc:
Sandeep Ghotey,
EnQuest
Page:
- with P&IDs
19
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
No. Action:
Responsible
Person:
Node 50 - Oil Water Recycle from 2nd Stage Separation and Hydrocyclones to 1st Stage
Separator
10
John Lennox /
Shah Ahmed,
AMEC
Node 60 - Flare & Vent System, including Return of Liquids to Process System and
Emergency Blowdown
11
Sandeep Ghotey,
EnQuest
12
Ensure all lines into the Flare Header have a suitable slope and no
pockets
Geoff Black,
AMEC
13
Sandeep Ghotey,
EnQuest
14
Ali Al-Khayat,
AMEC
15
Ensure that TT-9013 and TT-9012 have suitable low range for
temperatures that could be created during flowline depressurising.
Ali Al-Khayat,
AMEC
Node 70 - Process Drains System, Closed Drains, Hazardous Open Drains, Deluge
Drains and Swivel Drains
16
Ali Al-Khayat,
AMEC
17
Ali Al-Khayat,
AMEC
18
Ali Al-Khayat,
AMEC
Node 80 - Seawater Supply (Existing and New Lift Pumps, Coarse Filtration, Seawater
Users and Overboard Dump)
19
Date:
Doc:
Sandeep Ghotey,
EnQuest
Page:
- with P&IDs
20
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
No. Action:
Responsible
Person:
20
21
John Lennox,
AMEC
Sandeep Ghotey,
EnQuest
23
Sandeep Ghotey,
EnQuest
24
Sandeep Ghotey,
EnQuest
Node 100 - Chemical Injection and Helifuel, Swivel Recuperation System, Boiler Crude
Fuel Additive Chemical
25
Malcolm
Robertson,
EnQuest
Node 110 - Plant Air, Nitrogen, Hypochlorite, Freshwater Cooling System, other
Topsides Utilities
26
Peter Benson,
EnQuest
27
Only require single fill line connection to the Fresh Water Cooling
Medium Expansion Tank 355-V-001
John Lennox,
AMEC
28
John Lennox,
AMEC
Node 120 - Steam Generation, Fuel Supply and Steam Distribution to Consumers
29
Sandeep Ghotey,
EnQuest
30
Sandeep Ghotey,
EnQuest
Date:
Doc:
Page:
- with P&IDs
21
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
No. Action:
Responsible
Person:
Node 130 - Steam Condensate Return (Topsides and Marine) and Boiler Water MakeUp
31
Peter Benson,
EnQuest
32
Sandeep Ghotey,
EnQuest
Node 140 - Cargo Storage, Handling, Pumping and Offloading, including Tank
Stripping, Washing, etc.
33
Lock closed the double block and bleed valves 205-DBB-005 in the Colin Greenlees,
Cargo Oil Stripping Pump line used for flushing metering skid.
AMEC
34
Confirm at least one of the valves listed in note 18 on P&ID 0400110-F080-PID-052-001 is locked open at any one time.
Michelle
McRobbie,
EnQuest
35
Doug McGregor,
EnQuest
36
Sandeep Ghotey,
EnQuest
37
Michelle
McRobbie,
EnQuest
Node 150 - Inert Gas and Cargo Tank Venting, Purging, Gas Freeing
38
39
See Action 39: Ensure tank gas freeing procedure reflects finalised
operating philosophy
Date:
Doc:
Peter Benson,
EnQuest
Page:
- with P&IDs
22
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
No. Action:
Responsible
Person:
Colin Greenlees,
AMEC
41
Colin Greenlees,
AMEC
42
Colin Greenlees,
AMEC
43
Remove line details 1"-DF-615-9068-AC11BS and 1"-DF-6159069-AC11BS from AMEC drawing 0400-110-F120-PID-019-001
Colin Greenlees,
AMEC
44
Confirm that firewater pump test mode and procedure for using
615-PCV-1243 is clearly defined in operating procedures.
Peter Benson,
EnQuest
Michelle
McRobbie,
EnQuest
46
Sandeep Ghotey,
EnQuest
Node 190 - Bilge, Ballast, Sounding and Gauging, Drains & Sewage
47
Clarify (Class) requirement for flame screen/spark arrestor (X-35111/112/113 and X-17-131/132) in exhausts from Diesel
Generators and aft Firewater Pump Diesel Driver
Michelle
McRobbie,
EnQuest
48
Michelle
McRobbie,
EnQuest
49
Michelle
McRobbie,
EnQuest
Date:
Doc:
Page:
- with P&IDs
23
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
No. Action:
50
Responsible
Person:
Consider cross over line between port and starboard Sewage Tanks
M15 and M23.
Michelle
McRobbie,
EnQuest
Michelle
McRobbie,
EnQuest
52
Sandeep Ghotey,
EnQuest
53
Identify whether the HPU packages for riser ESDVs and LP & HP
hydraulic supply for subsea control (valves) have been subject to
HAZOP review, and if not carry out a HAZOP.
Sandeep Ghotey,
EnQuest
Responsible
Person:
Ensure all valves in main route to Residual Tank M14 are locked
open (ie. valves on P&ID BLV-KN501-MA-205-PID 0003-001).
Sandeep Ghotey,
EnQuest
55
Sandeep Ghotey,
EnQuest
56
Sandeep Ghotey,
EnQuest
57
Ali Al-Khayat,
AMEC
Date:
Doc:
Michelle
McRobbie,
EnQuest
Page:
- with P&IDs
24
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
No. Action:
59
Responsible
Person:
Either lock open valves 11 & 13 or provide thermal relief for Steam Michelle
Heat Exchanger tubes. Note: these valves may not be required.
McRobbie,
EnQuest
Michelle
McRobbie,
EnQuest
61
Confirm relief valve (item 10) capacity is suitable for thermal relief
requirements.
Michelle
McRobbie,
EnQuest
62
Michelle
McRobbie,
EnQuest
63
Michelle
McRobbie,
EnQuest
64
Michelle
McRobbie,
EnQuest
65
Michelle
McRobbie,
EnQuest
Ensure 3 way ball valve (Blaze Item 09) is routed to Engine Room
rather than foam test line.
Paul Renwick,
AMEC (for
Blaze)
67
Isolation valve (Blaze Item 08) between foam tank and foam
inductor should be locked open.
Paul Renwick,
AMEC (for
Blaze)
68
Paul Renwick,
AMEC (for
Blaze)
Date:
Doc:
Page:
- with P&IDs
25
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
No. Action:
Responsible
Person:
69
70
Paul Renwick,
AMEC (for
Blaze)
71
Confirm that a level gauge or local level indication for the Foam
Tank will be provided.
Paul Renwick,
AMEC (for
Blaze)
Date:
Doc:
Page:
- with P&IDs
26
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Date:
Doc:
Page:
- with P&IDs
27
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Guideword
no flow
less flow
more flow
reverse flow
misdirected
flow
varying flow
more pressure
less pressure
low temperature
high level
low level
erosion /
corrosion
composition
deposition
loss of services
equipment
isolation
drain, vent,
purge
draining, venting, purging, lifting, vessel entry, spares, bunds, drip trays
Date:
Doc:
Page:
- with P&IDs
28
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Guideword
maintenance
start-up
shutdown
operability
ergonomics, behaviour
inherent safety
fire and
explosion
release to
environment
general
documentation
For the new P&IDs considered in Appendix D, all of the above guidewords were considered.
The worksheets do not list each guideword if they did not raise a concern.
Date:
Doc:
Page:
- with P&IDs
29
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Date:
Doc:
Page:
- with P&IDs
30
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
EnQuest
PROJECT NO:
A3304
PROJECT:
DETAILS:
MEETING DATES: Wed 23rd, Thur 24th and Fri 25th October 2013
TEAM MEMBERS
Independent Chairman, Paul Caldwell (Anatec)
Scribe, Steven Armstrong (Anatec)
EnQuest Knightsbridge Process Engineer, Sandeep Ghotey
EnQuest Process TA, Matt Hastings
EnQuest Operations Process Engineer, Peter Benson
EnQuest Production Supervisor, Malcolm Robertson
EnQuest Instruments Engineer, Doug McGregor (part-time)
EnQuest ESP Package Engineer, Mike Webster (part time)
EnQuest Subsea Engineer, Mark Toshney (part time)
EnQuest Umbilical Engineer, Shaun Wilson (part time)
EnQuest Subsea Controls Engineer, Bill Gracie (part time)
AMEC Process Engineer, Geoff Black / Ali Al-Khayat / John Lennox (part time)
AMEC Controls & Instrumentation, Richard Auld / Shah Ahmed (part time)
AMEC Safety Engineer, Peter Marchant / Paul Renwick (part time)
ACTION RESPONSES TO: Paul Renwick, Technical Safety Engineer, AMEC
DOCUMENTS STUDIED
Subsea:
MAX-KN501-PR-000-PID-0001-001 Rev A1 P&ID: Alma, Galia Production Tree
MAX-KN501-PR-000-PID-0002-001 Rev A1 P&ID: Alma Water Injection Tree
JPK-KN501-PR-844-PID-0001 Rev C2 P&ID: Alma Production Manifold
Topsides / Subsea Interface:
BLU-KN501-PR-840-PID-0010 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0001 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0002 Rev C1 P&ID: Swivel Stack
Topsides Process:
0400-110-F070-PFD-001-001 Rev A2 EnQuest Producer Process Overall Flow Scheme
0400-110-F020-PID-019-001 Rev C1 Legend Sheet Piping Symbols
0400-110-F020-PID-019-002 Rev C1 Legend Sheet Instrument Symbols
0400-110-F020-PID-019-003 Rev C1 Valve Configuration Details
0400-110-F070-PID-014-001 Rev C1 Centralised Sample Collection
0400-110-F070-PID-016-001 Rev C1 P&ID Inlet Cooler
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
Date:
Doc:
Page:
- with P&IDs
31
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Date:
Doc:
Page:
- with P&IDs
32
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Produced Water:
DOCUMENTS STUDIED (continued)
0400-110-F150-PID-001-001 Rev C3 P&ID Produced Water Degasser 510-V-002
0400-110-F150-PID-002-001 Rev C3 Skimmed Oil Pumps 510-P-005 A/B
0400-110-F150-PID-003-001 Rev C3 Seawater Treatment Unit LP Booster Pumps P-5660-A/B
0400-110-F150-PID-004-001 Rev C3 Water Injection Pumps 535-P-001 A/B
0400-110-F150-PID-005-001 Rev C3 Water Injection Pumps 535-P-002 A/B
0400-110-F150-PID-006-001 Rev C3 Produced Water Coolers E-5175 A/B
0400-110-F150-PID-008-001 Rev A2 P&ID Production Hydrocyclone S-001 ??
0400-110-F150-PID-009-001 Rev C3 Production Separator Hydrocyclone S-5111
0400-110-F150-PID-010-001 Rev C3 Pumps 510-P-009 A/B Dehydrator Produced Water Recycle
0400-110-F150-PID-011-001 Rev C3 Production Hydrocyclones S-5801
0400-110-F150-PID-013-001 Rev C3 Production Separator Hydrocyclone S-5112
0400-110-F150-PID-014-001 Rev C2 Produced Water Filter Package
Flare (previously F080 System?):
0400-110-F100-PID-005-001 Rev C2 P&ID Flare Header
0400-110-F100-PID-006-001 Rev C2 P&ID Flare KO Drum V-5370
0400-110-F100-PID-007-001 Rev A2 P&ID Flare Tip 515-X-001
0400-110-F080-PID-006-001 Rev A2 CSU P&ID Purging Flare Header - Obsolete?
Hazardous Open Drains Collection & Deluge Drains
0400-110-F100-PID-009-001 Rev C2 Drain Box Connections for Deluge Water and Hazardous Open
Drain
0400-110-F100-PID-010-001 Rev C2 P&ID Hazardous Open Drain System
0400-110-F100-PID-011-001 Rev C2 Hazardous Open Drain Collection System
0400-110-F100-PID-003-001 Rev A2 P&ID (Construct) Hazardous Open Drain Collection System
Swivel Drains:
0400-110-F100-PID-019-001 Rev C1 Swivel Drains Recuperation System
Boiler Drains:
0400-110-F100-PID-022-001 Rev C1 Boiler Package Hazardous Open Drain Collection System
Date:
Doc:
Page:
- with P&IDs
33
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 10
Design
Change
CAUSE
Inlet heaters removed since first
HAZOP - deemed not required
due to infrequent cold fluids
(repositioning of FPSO closer to
wells means well fluid arrival
temperatures will be higher than
previously expected).
Date:
Doc:
CONSEQUENCE
SAFEGUARDS
ACTION
Page:
- with P&IDs
34
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 10 (continued)
ITEM: Subsea Production to 1st Stage Separation (multi-phase flow)
DEVIATION
CAUSE
CONSEQUENCE
ACTION
Design
Change
Design
Change
Date:
Doc:
Page:
- with P&IDs
35
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 10 (continued)
ITEM: Subsea Production to 1st Stage Separation (multi-phase flow)
DEVIATION
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
Design
Change
Equipment
Change
Date:
Doc:
Page:
- with P&IDs
36
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 10 (continued)
ITEM: Subsea Production to 1st Stage Separation (multi-phase flow)
DEVIATION
CAUSE
CONSEQUENCE
Equipment
Change
Interface
Issues
ACTION
Date:
Doc:
Page:
- with P&IDs
37
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 20
ITEM: Oil Stabilisation (Interstage Heater, 2nd Stage Separator & Electrostatic Dehydrator) to Cargo Tanks
Stabilisation and separation of water from oil to export quality specification (RVP 10psi).
Design flow rate is 57000 bpd oil. System design pressure is 150 # (17 bar gauge) and MT2 marine spec for pipe work (16 barg). Operating pressure is 1 bar
gauge.
Design temperature is -20/118C for the pipe work and 228C for the heater. Operating temperature is up to 85C.
Stabilised crude oil drops into Cargo tank No. 4P or S and is distributed to the other tanks as per loading plan.
DRAWINGS AND DOCUMENTS
0400-110-F070-PID-029-001 Rev C3 First Stage Separator V-5100
0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
P0400-131-F070-001-01-C03-002-01 Rev 12 First Stage Separator
P0400-131-F070-001-01-C03-003-01 Rev 11 Interstage Heater
0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
0400-110-F070-PID-030-001 Rev C3 CSU P&ID Electrostatic Dehydrator V-5150
0400-110-F070-PID-028-001 Rev C3 CSU P&ID Produced Crude Oil Pumps P-5130 A/B/C
0400-110-F070-PID-032-001 Rev C3 CSU P&ID Produced Crude Oil Coolers E-5135 A/B
0400-110-F080-PID-045-001 A1 Topside Interface with Marine Systems
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
DEVIATION
CAUSE
CONSEQUENCE
Design
Change
Design
Change
Date:
Doc:
SAFEGUARDS
ACTION
Page:
- with P&IDs
38
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 20 (continued)
DATE REVIEWED: Wednesday, 23 October 2013
ITEM: Oil Stabilisation (Interstage Heater, 2nd Stage Separator & Electrostatic Dehydrator) to Cargo Tanks
DEVIATION
CAUSE
CONSEQUENCE
11 Interface
Issues
SAFEGUARDS
ACTION
Date:
Doc:
Page:
- with P&IDs
39
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 30
CAUSE
CONSEQUENCE
Date:
Doc:
SAFEGUARDS
ACTION
Page:
- with P&IDs
40
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 30 (continued)
ITEM: Produced Water Treatment (plus overboard disposal)
DEVIATION
CAUSE
SAFEGUARDS
ACTION
14 Design
Change
15 Equipment
Change
16 Interface
Issues
Date:
Doc:
Page:
- with P&IDs
41
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 40
ITEM: Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to Flare, plus Hydrocarbon Condensate Return
HP gas from 1st stage separators plus LP gas from 2nd stage separators through LP gas KO drum V-5320 and LP gas compressor 550-C-001, through HP
gas cooler E-5305A/B to HP KO drum and fuel gas electric superheater 550-E-001A and meter to Steam Boiler burners.
Return of hydrocarbon condensate from HP gas KO drum and LP gas KO drum and LP condensate return pumps P-5355A/B, to inlet of 2nd stage separator.
Design pressure: 17 barg, Operating pressure approx. 7barg.
Design temperature: -20 C to118 C, Operating temperature (in/out): 40C to 85 C.
DRAWINGS AND DOCUMENTS
0400-110-F070-PID-029-001 Rev C3 First Stage Separator V-5100
P0400-131-F070-001-01-C03-002-01 Rev 12 First Stage Separator
0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
0400-110-F080-PID-030-001 Rev C3 LP Gas Coolers E-5335A/B
0400-110-F080-PID-029-001 Rev C3 LP Gas KO Drum V-5350
0400-110-F080-PID-036-001 Rev C3 LP Fuel Gas Compressor
0400-110-F080-PID-031-001 Rev C3 HP Gas Cooler E-5305B
0400-110-F080-PID-028-001 Rev C3 HP Gas KO Drum V-5320
0400-110-F080-PID-024-001 Rev C3 Fuel Gas Superheater
0400-110-F080-PID-026-001 Rev C1 Boiler & Steam Turbine - Interface with Topsides
PBL-KN501-PR-315-DRG-0013-001 Rev C2 P&ID: Miscellaneous Fuels
HCE-KN501-PR-315-PID-0002-001 Rev C2 P&ID: Fuel Gas & Oil Services - Boiler 'A'
HCE-KN501-PR-315-PID-0003-001 Rev C2 P&ID: Burner Fuel Systems - Boiler 'A'
HCE-KN501-PR-315-PID-0006-001 Rev C3 P&ID: Fuel Gas & Oil Services - Boiler 'B'
HCE-KN501-PR-315-PID-0007-001 Rev C3 P&ID: Burner Fuel Systems - Boiler 'B'
0400-110-F080-PID-027-001 Rev C3 LP Condensate Return Pumps P-5355A/B
DEVIATION
18 Design
Change
CAUSE
Change of type of gas meter
Date:
Doc:
CONSEQUENCE
SAFEGUARDS
ACTION
Page:
- with P&IDs
42
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 40 (continued)
DATE REVIEWED: Thursday, 24 October 2013
ITEM: Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to Flare, plus Hydrocarbon Condensate Return
DEVIATION
CAUSE
CONSEQUENCE
SAFEGUARDS
19 Design
Change
20 Design
Change
21 Design
Change
22 Equipment
Change
ACTION
Date:
Doc:
Page:
- with P&IDs
43
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 40 (continued)
DATE REVIEWED: Thursday, 24 October 2013
ITEM: Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to Flare, plus Hydrocarbon Condensate Return
DEVIATION
24 Completeness
of Previous
HAZOP
CAUSE
Reverse flow from
downstream higher design
pressure system if
compressor stops with only a
single check valve in
compressor discharge.
Date:
Doc:
CONSEQUENCE
Potential to exceed package
design pressure of 13.8barg if
reverse flow from higher
downstream system (17barg
design pressure)
SAFEGUARDS
ACTION
Page:
- with P&IDs
44
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 50
ITEM: Oil Water Recycle from 2nd Stage Separation and Hydrocyclones to 1st Stage Separator
Oily water from PW Degasser 510-V-002 via skimmed oil pump 510-P-005A/B to 2nd Stage Separator.
Oily water from Electrostatic Dehydrator V-5150 via Dehydrator Produced Water Recycle Pumps 510-P-009A/B to 1st Stage Separators.
Reject oily water from Hydrocylones (S-5111, S-5112 7 S-5801) to 2nd Stage Separator.
Design pressure is 17 bar gauge, Operating pressure is 3-4 bar gauge.
Design temperature is -20/118C for the pipework. Operating temperature is approx. 85degC.
DRAWINGS AND DOCUMENTS
0400-110-F070-PID-030-001 Rev C3 CSU P&ID Electrostatic Dehydrator V-5150
0400-110-F150-PID-010-001 Rev C3 Pumps 510-P-009 A/B Dehydrator Produced Water Recycle
0400-110-F150-PID-001-001 Rev C3 P&ID Produced Water Degasser 510-V-002
0400-110-F150-PID-002-001 Rev C3 Skimmed Oil Pumps 510-P-005 A/B
0400-110-F150-PID-009-001 Rev C3 Production Separator Hydrocyclone S-5111
0400-110-F150-PID-011-001 Rev C3 Production Hydrocyclones S-5801
0400-110-F150-PID-013-001 Rev C3 Production Separator Hydrocyclone S-5112
0400-110-F070-PID-016-001 Rev C1 P&ID Inlet Cooler
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
DEVIATION
25 Equipment
Change
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
Review the response to HAZOP
action #75 (Topsides HAZOP),
taking into account change in
pump type from centrifugal to
reciprocating, and update the
control philosophy and P&ID, as
appropriate.
Date:
Doc:
Page:
- with P&IDs
45
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 50 (continued)
ITEM: Oil Water Recycle from 2nd Stage Separation and Hydrocyclones to 1st Stage Separator
DEVIATION
CAUSE
26 Operability
Issues
27 Operability
Issues
Type of instrumentation on
produced water degasser vessel
allows either interface control or
bulk control
Date:
Doc:
CONSEQUENCE
ACTION
Page:
- with P&IDs
46
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 60
ITEM: Flare & Vent System, including Return of Liquids to Process System and Emergency Blowdown
Flare Collection Header, HP Gas KO Drum V-5320, flare and pilots & condensate return to 2nd Stage Separator.
Design flow rate 10 MMSCFD (continuous). Design pressure is 17 barg (upstream systems that feed into flare header) and 7barg (flare header and system).
Operating pressure is flare header pressure (less than 1 bar gauge). Design temperature is -20/118 degC for the pipe work. Operating temperature is
ambient. The HP Gas KO Drum pump out capacity is 5 cubic metres per hour (max 10 cubic metres per hour with both pumps running).
Supply of HP gas to pilot and flare purge from HP Fuel Gas KO Drum V-5320 (F080-PID-0028).
DRAWINGS AND DOCUMENTS
0400-110-F080-PID-028-001 Rev C3 HP Gas KO Drum V-5320
0400-110-F100-PID-005-001 Rev C2 P&ID Flare Header
0400-110-F100-PID-006-001 Rev C2 P&ID Flare KO Drum V-5370
0400-110-F100-PID-007-001 Rev A2 P&ID Flare Tip 515-X-001
0400-110-F080-PID-006-001 Rev A2 CSU P&ID Purging Flare Header - Obsolete?
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
DEVIATION
CAUSE
CONSEQUENCE
Improved level sensing and
control of pumps
28 Design
Change
29 Equipment
Change
SAFEGUARDS
ACTION
Date:
Doc:
Page:
- with P&IDs
47
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 60 (continued)
ITEM: Flare & Vent System, including Return of Liquids to Process System and Emergency Blowdown
DEVIATION
30 Interface
Issues
CAUSE
Slope is not shown on all lines
into the Flare Header
CONSEQUENCE
SAFEGUARDS
ACTION
Ensure all lines into the Flare
Header have a suitable slope and
no pockets
32 Operability
Issues
Date:
Doc:
Page:
- with P&IDs
48
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 60 (continued)
ITEM: Flare & Vent System, including Return of Liquids to Process System and Emergency Blowdown
DEVIATION
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
Date:
Doc:
Page:
- with P&IDs
49
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 70
ITEM: Process Drains System, Closed Drains, Hazardous Open Drains, Deluge Drains and Swivel Drains
Swivel Drains Recuperation Unit - Design pressure 7barg & return to Flare Gas KO Drum.
Centralised Sample Collection disposal to Closed Drains.
Process Closed Drains from vessels, etc., to Closed Drains Collection Header, then to Residue Tank No. 14 (in hull). - check interface drawing no. on marine
drawing BLV-KN501-MA-205-PID-0003-001 Rev C2.
Collection of hazardous drains (drip trays / tun dishes) from process areas, chemical storage & pumps, into Hazardous Open Drains Vessel 531-V-001 (local
vent) and transfer to Residue Tank No. 14 (in hull) via Hazardous Open Drain Pumps 531-P-001A/B (design pressure FV/18barg). New tie-in from Chemical
Injection Skid hazardous drains.
Boiler Package Hazardous Open Drains Collection System (drip trays) to Vessel 531-V-002 (design pressure FV/1bar) and transfer of liquids to Residue Tank
No. 14 (in hull) via Boiler Package Hazardous Open Drain Pump 531-P-002 (design pressure 7barg).
DRAWINGS AND DOCUMENTS
0400-110-F100-PID-006-001 Rev C2 P&ID Flare KO Drum V-5370
0400-110-F100-PID-019-001 Rev C1 Swivel Drains Recuperation System
0400-110-F070-PID-014-001 Rev C1 Centralised Sample Collection
0400-110-F100-PID-001-001 Rev C2 CSU P&ID Closed Drains Collection 1 of 2
0400-110-F100-PID-001-002 Rev C2 CSU P&ID Closed Drains Collection 2 of 2
0400-110-F080-PID-045-001 Rev A1 Topside Interface with Marine Systems
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
0400-110-F100-PID-009-001 Rev C2 Drain Box Connections for Deluge Water and Hazardous Open Drain
0400-110-F100-PID-010-001 Rev C2 P&ID Hazardous Open Drain System
0400-110-F100-PID-011-001 Rev C2 Hazardous Open Drain Collection System
DEVIATION
35 Design
Change
CAUSE
New connection to closed drain
header from offloading meters
Date:
Doc:
CONSEQUENCE
Used to initially drain offloading
meters and then flush offloading
hose to Residue Tank
SAFEGUARDS
ACTION
Page:
- with P&IDs
50
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 70 (continued)
ITEM: Process Drains System, Closed Drains, Hazardous Open Drains, Deluge Drains and Swivel Drains
DEVIATION
36 Operability
Issues
CAUSE
CONSEQUENCE
High level in drain vessel and
overflow of water, oil or
chemicals onto process deck to
atmospheric vent
SAFEGUARDS
This has been discussed in
previous HAZOPs
ACTION
[1] Consider new high level alarm
function on 531-LZIT-1000.
[2] Confirm location of vent 2"VA-531-9159-AC11BS onto open
deck is in a safe location.
38 Operability
Issues
Date:
Doc:
Page:
- with P&IDs
51
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 70 (continued)
ITEM: Process Drains System, Closed Drains, Hazardous Open Drains, Deluge Drains and Swivel Drains
DEVIATION
CAUSE
CONSEQUENCE
39 Completeness
of Previous
HAZOP
Date:
Doc:
SAFEGUARDS
ACTION
A new HAZOP of the Closed
Drains System has been carried
out (as part of the End to End
HAZOP - see separate
worksheets for Node 71)
Page:
- with P&IDs
52
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
EnQuest
PROJECT NO:
A3304
PROJECT:
DETAILS:
Date:
Doc:
Page:
- with P&IDs
53
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Date:
Doc:
Page:
- with P&IDs
54
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 80
ITEM: Seawater Supply (Existing and New Lift Pumps, Coarse Filtration, Seawater Users and Overboard Dump)
Seawater Supply for consumers and to suction of HP SW Injection Pumps.
Seawater Lift Pumps 350-P-001A/B and Seawater Feed Pumps P-4452A/B through Coarse Filters 350-F-001 and either to consumers or to Deaerator V5650 and Seawater Booster Pumps P-5660A/B, with overboard dump (if not injecting subsea - see Node 90).
The design flow rate is 70000 barrels of seawater a day. Design pressure is FV/7barg. Operating pressure is vacuum (in deaerator) up to 12.5barg. Design
temperature is -20/30C for the pipework. Operating temperature is ambient seawater temp.
DRAWINGS AND DOCUMENTS
0400-110-F120-PID-001-001 Rev C2 Seawater Distribution
0400-110-F120-PID-002-001 Rev C3 Seawater for Deck Modules
0400-110-F120-PID-003-001 Rev C3 Seawater for Deck Modules Coarse Filters
0400-110-F120-PID-004-001 A3 Seawater for Deck Modules New Seawater - missing??
0400-110-F120-PID-005-001 Rev C2 Electrochlorination Package
0400-110-F120-PID-006-001 Rev C3 Seawater for Deck Modules Seawater Lift Pumps
0400-110-F120-PID-007-001 A3 Seawater System in Power Module - missing??
0400-110-F120-PID-008-001 Rev C2 STU Deaerator and Vacuum Pumps
0400-110-F120-PID-010-001 Rev C3 STU Seawater to Deaerator
0400-110-F120-PID-014-001 Rev C2 Overboard Caisson Starboard Side Forward - in this Node??
0400-110-F150-PID-003-001 Rev C3 Seawater Treatment Unit LP Booster Pumps P-5660-A/B
DEVIATION
40 Equipment
Change
CAUSE
Replacement of Vacuum Pump
P5640A/B for Deaerator
CONSEQUENCE
May be slight variation in vacuum
pump characteristics, and hence
instrumentation / control.
No adverse consequence for
HAZOP foreseen.
SAFEGUARDS
ACTION
Ensure vendor information for
replacement of Vacuum Pump
P5640A/B is passed to AMEC to
update P&IDs, as required.
Date:
Doc:
Page:
- with P&IDs
55
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 80 (continued)
DATE REVIEWED: Friday, 25 October 2013
ITEM: Seawater Supply (Existing and New Lift Pumps, Coarse Filtration, Seawater Users and Overboard Dump)
DEVIATION
41 Equipment
Change
CAUSE
Replacement of Seawater LP
Booster Pump P5660A/B
CONSEQUENCE
SAFEGUARDS
ACTION
Ensure vendor information for
replacement of Sea Water LP
Booster Pump P5660A/B is
passed over to AMEC to update
P&IDs if required
Date:
Doc:
Page:
- with P&IDs
56
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 90
CAUSE
AMV on Water Injection well is
shown as normally closed
Date:
Doc:
CONSEQUENCE
SAFEGUARDS
ACTION
Page:
- with P&IDs
57
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 90 (continued)
ITEM: HP Water Injection (Produced Water and Seawater) to Subsea Wells
DEVIATION
44 Operability
Issues
CAUSE
HP Water Injection pumps stop
CONSEQUENCE
ACTION
Review whether this scenario has
been considered in hydraulic
analysis and whether suitable
protection is provided for water
injection flowline (eg PALL at
riser).
Start up of an additional HP
Water Injection pump or Booster
Pump trips
Date:
Doc:
Page:
- with P&IDs
58
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 90 (continued)
ITEM: HP Water Injection (Produced Water and Seawater) to Subsea Wells
DEVIATION
47 Operability
Issues
CAUSE
Scale forming in tail pipe from
PSV 1100 (if leaking) causing
blockage
Date:
Doc:
CONSEQUENCE
SAFEGUARDS
ACTION
Page:
- with P&IDs
59
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 100
ITEM: Chemical Injection and Helifuel, Swivel Recuperation System, Boiler Crude Fuel Additive Chemical
Use of chemicals for process condition & corrosion and scale control.
Atmospheric pressure storage tanks filled from tote tanks. Injection pumps design pressure 7barg, 14barg or 17barg depending on delivery location.
Helifuel supply in tote tanks, helifuel pumps 385-P-001A/B to Helifuel Dispensing Unit 385-U-002. Pump & dispensing unit design pressure 3.8barg.
Boiler Crude Fuel Additive Chemical: Atmospheric storage with dosing pump design pressure 100barg and delivery to Crude Oil Feed Pumps 205-P-2000A/B.
DRAWINGS AND DOCUMENTS
0400-110-F080-PID-013-001 Rev C2 Biocide Injection
0400-110-F080-PID-014-001 Rev C3 Oxygen Scavenger
0400-110-F080-PID-015-001 Rev C3 Demulsifier Injection
0400-110-F080-PID-016-001 Rev C3 Methanol - Has been deleted
0400-110-F080-PID-017-001 Rev C3 Subsea Scale Inhibitor
0400-110-F080-PID-018-001 Rev C3 De-Oiler
0400-110-F080-PID-019-001 Rev C3 SWI Antifoam
0400-110-F080-PID-020-001 Rev C3 Vapour Phase Corrosion Inhibitor
0400-110-F080-PID-021-001 Rev C3 PWRI & SWI Scale Inhibitor
0400-110-F080-PID-022-001 Rev C3 Multi-phase Corrosion Inhibitor
0400-110-F080-PID-023-001 Rev C3 Oil Antifoam
0400-110-F080-PID-048-001 Rev C2 Helifuel Decanting & Storage
BLU-KN501-PR-840-PID-0003 Rev C1 TMS P&ID: Turret Scale Inhibitor Dosing Pumps
BLU-KN501-PR-840-PID-0006 Rev C1 TMS P&ID: Turret CI Dosing Pumps
BLU-KN501-PR-840-PID-0008 Rev C1 TMS P&ID: Turret Scale Inhibitor Dosing Pumps
BLU-KN501-PR-840-PID-0009 Rev C1 TMS P&ID: Turret Scale Inhibitor Dosing Pumps
BLU-KN501-PR-842-PID-0002 Rev C1 TMS P&ID: Turret Swivel Drains Recovery Lines
0400-110-F080-PID-046/047-001 Rev C1 Boiler HP Dosing
0400-110-F080-PID-026-001
HCE-KN501-PR-315-PID-0001/5/10/12
Date:
Doc:
Page:
- with P&IDs
60
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
SAFEGUARDS
48 Design
Change
49 Operability
Issues
50 Operability
Issues
51 Operability
Issues
ACTION
Date:
Doc:
Page:
- with P&IDs
61
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 110
ITEM: Plant Air, Nitrogen, Hypochlorite, Freshwater Cooling System, other Topsides Utilities
General Topsides Utilities including distribution to consumers, as appropriate.
Plant Air & Instrument Air: Compression, drying & filtering, storage and supply of plant air at design pressure 12barg, operating pressure 8 to 10barg.
Nitrogen: Nitrogen Generator 372-U-001, 1805m3/hr, design pressure 13barg, design temp -20C/+60C.
Freshwater Cooling: Closed circuit cooling system with Freshwater Cooling Medium Expansion Tank 355-T-001, Central Freshwater Coolers E-4461A/B and
Cooling Water Circulation Pump 355-P-0001A/B
DRAWINGS AND DOCUMENTS
0400-110-F080-PID-032-001 Rev C3 Nitrogen Distribution
0400-110-F080-PID-033-001 Rev C3 Nitrogen Generation Package
0400-110-F080-PID-034-001 Rev C3 Nitrogen Storage Vessel
0400-110-F100-PID-012-001 Rev C2 Topside Plant Air on Deck
0400-110-F100-PID-013-001 Rev C2 Instrument Air in Power Module
0400-110-F100-PID-014-001 Rev C2 Starting & Compressed Air System in E.R.
0400-110-F100-PID-015-001 Rev C2 Topsides Instrument Air Distribution Sht 1 of 2
0400-110-F100-PID-015-002 Rev C2 Topsides Instrument Air Distribution Sht 2 of 2
0400-110-F080-PID-050-001 Rev C1 Fresh Cooling Water System
0400-110-F080-PID-053-001 Rev C2 Topsides Freshwater Distribution
DEVIATION
CAUSE
CONSEQUENCE
52 Completeness
of Previous
HAZOP
Date:
Doc:
SAFEGUARDS
ACTION
Page:
- with P&IDs
62
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
53 Completenes
s of Previous
HAZOP
54 Equipment
Change
The Instrument Air package that has May not be suitable for use on
been procured does not comply with FPSO.
Class requirements
55 Equipment
Change
ACTION
Date:
Doc:
Page:
- with P&IDs
63
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
Outlet from vent for Fresh Water
Cooling Medium Expansion Tank
CONSEQUENCE
SAFEGUARDS
ACTION
Date:
Doc:
Page:
- with P&IDs
64
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
EnQuest
PROJECT NO:
A3304
PROJECT:
DETAILS:
Doc:
Page:
- with P&IDs
65
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Date:
Doc:
Page:
- with P&IDs
66
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 120
CAUSE
CONSEQUENCE
SAFEGUARDS
Bellows are designed for 76barg
compared to 64.5barg design
pressure for rest of system.
Full stress analysis has been
carried out of pipework and
bellows and are Class approved
(Lloyds)
ACTION
Confirm that stress analysis of
steam system bellows has been
reviewed by EnQuest Piping TA
Date:
Doc:
Page:
- with P&IDs
67
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
60 Operability
Issues
61 Operability
Issues
62 Operability
Issues
ACTION
Date:
Doc:
Page:
- with P&IDs
68
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
Change over from diesel to crude Error in switch over and burning
oil for fuel at boiler burners
incorrect fuel could affect
combustion properties and
temperature within boiler
combustion chamber and
exhaust.
Steam Boiler HAZOP considered
this possibility and noted:
"Mixture of fuels for a short
period, should not affect burner
performance."
Date:
Doc:
ACTION
Page:
- with P&IDs
69
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 130
ITEM: Steam Condensate Return (Topsides and Marine) and Boiler Water Make-Up
Return of FPSO steam condensate to topsides, plus steam condensate from topsides boilers, and boiler feedwater make-up.
Chemicals.
DRAWINGS AND DOCUMENTS
All topsides steam drawings (PBL, HC & DR) - see list in main text.
FPSO Steam Systems:
BLV-KN501-MA-315-PID-0001-001 Rev C2 P&ID - E.R 20 Barg Steam System
BLV-KN501-MA-315-PID-0002-001 Rev C3 P&ID - E.R 8 Barg Steam System
BLV-KN501-MA-315-PID-0003-001 Rev C2 P&ID - E.R Steam Condensate System
BLV-KN501-MA-315-PID-0004-001 Rev C2 P&ID - E.R Steam Condensate Transfer Pump Skid
BLV-KN501-MA-315-PID-0005-001 Rev C2 P&ID - Steam & Condensate for Tank Heating
DEVIATION
64 Design
Change
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
Isolation valves S56 and S61 will Ensure operating procedure for
be locked open.
Cargo Pump Steam Turbines is
updated (previously the outlet
isolation valves S56 & S61 were
used during warm up).
Date:
Doc:
Page:
- with P&IDs
70
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
Intended design of ER
Condensate Transfer Pumps
315-P-2013A/B was to have
two speeds of operation due
to the need to transfer
"normal" condensate returns
flow of approx 4 to 5m3/hr
and "cargo pump offloading"
condensate flows of approx.
40m3/hr. However, P&ID
details do not indicate how
pumps can be operated for
the two speeds / modes.
ACTION
Date:
Doc:
Page:
- with P&IDs
71
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
EnQuest
PROJECT NO:
A3304
PROJECT:
DETAILS:
Date:
Doc:
Page:
- with P&IDs
72
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Date:
Doc:
Page:
- with P&IDs
73
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 140
ITEM: Cargo Storage, Handling, Pumping and Offloading, including Tank Stripping, Washing, etc.
Receipt of stabilised crude oil (spec of 10.5 psi at 60 F - to be confirmed) at 2barg and 43 deg C from topsides process system at up to 57,000 bpd of oil.
Design temperature of marine systems (pipework, valves) is 60C, but tank themselves is less at 55C.
Distributed to cargo tanks by manual selection of double block valves.
Level alarms set at 95% and 98% in each cargo tank.
Pumping of crude oil via Cargo Pumps P-17-111/112/113 to Offloading Hose and Shuttle Tanker.
Transfer of up to 1800m3/hr by each pump and a maximum of two Cargo Pumps (limited by Inert Gas capacity).
Pump head 170mlc (approx. 14 barg) through 300# (PN25) system.
Flushing of off-loading hose from cargo or stripping pump to Slops Tank.
Using stripping pump to suck out oil from cargo pump P-17-111/112/113 suction and discharge lines, and from strainers S-17-211/212/213, to slops tank /
residual tank M-14.
Removal of bilge water from Cargo Pump Room through new hydraulically driven Stripping Pump or Stripping Ejectors No. 1 and 2.
Removal of water or oil from Slops Tank using Stripping Ejectors.
Pumping of produced water from topsides process plant produced water booster pump (max 6 barg) into Slops Tanks (if required).
Drains from Process Plant (closed drains and hazardous open drains from tank & pump) into Residual Tank M14.
Water from Cargo Seachest to suction of Cargo pumps for emergency filling of cargo tanks.
Slops Tank Overboard Discharge Monitoring system and gravity discharge line.
Supply of Inert Gas to Crude Pumps Cargo Oil Discharge Manifold.
Transfer of sludge from Sludge Tank M-16 to cargo tank 7P using sludge transfer pump P-4646.
Use of clean oil from one Cargo Pump P-17-111/112/113 for washing cargo tanks including Slops Tanks.
DRAWINGS AND DOCUMENTS
BLV-KN501-MA-205-PID-0001-001 Rev C1 P&ID - Cargo Oil Piping in Tanks
BLV-KN501-MA-205-PID-0002-001 Rev C2 P&ID - Cargo Oil Piping in Pump Room
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
BLV-KN501-MA-210-PID-0001-001 Rev C2 P&ID - Cargo Oil Tank Cleaning
Date:
Doc:
Page:
- with P&IDs
74
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
66 Design
Change
.
67 Design
Change
No adverse consequence
foreseen for HAZOP.
68 Design
Change
ACTION
Date:
Doc:
Page:
- with P&IDs
75
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
Cargo offloading valves
3CO02/03/04 are required to be
interlocked to restrict offloading
rate to less than 125% of the
Inert Gas supply capacity
CONSEQUENCE
If interlock is overridden, potential
to offload crude faster than inert
gas can balance pressure in
cargo tanks, cause vacuum in
cargo tanks and damage.
ACTION
Date:
Doc:
Page:
- with P&IDs
76
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 150
ITEM: Inert Gas and Cargo Tank Venting, Purging, Gas Freeing
Use of Boiler flue gases (at approx 190C and 90,000kg/hr) to generate clean, cool inert gas at up to 5500m3/hr at 2040mmwc (max) and <5% oxygen.
Seawater from topsides (87m3/hr) from AMEC with back-up supply from ?? (seawater system only shutdown on ESD1 because it is required for the boilers).
Inert gas scrubber with quench cooler, scrubber section and water spray into upper section. Two 100% blowers for distribution to Deck Seal and cargo tanks
via on-line oxygen analyser and purge and excess vent valve.
Water from inert gas scrubber and rinsing water from blowers discharged overboard minimum 2.5m below waterline (due to water acidity from washing flue
gases).
Steam to boiler flue inlet gases for soot cleaning of boiler flue gas valves (short duration steam blowing only) - 8 barg steam supply from AMEC (outstanding
TQ to cover provision of all utilities).
Design pressure of inert gas scrubber and pipework 2barg / 0.2bar vacuum. Design temperature 450 inlet pipework and 65C downstream of scrubber.
Distribution of clean, cool and <5% oxygen inert gas to cargo tanks via deck seal (set at 2500mmWC with water seal and steam heating) to prevent reverse
flow of inert gas and hydrocarbon vapours back to inert gas system and P/V breaker (set at 1800mmWC & -700mmWC with water / glycol mix) and capacity
of 7670m3/hr (max fill rate from topsides 84,000bpd (560m3/hr) total fluids or 5500m3/hr from inert gas generator).
Purging: Tank has been washed, and isolated from inert gas header. Previously, inert gas was routed to bottom lines (via cargo pump manifold connection),
but now send inert gas direct into tank top via purge header until hydrocarbon content <2% (verified by manual gas sampling).
Gas Freeing: Purge header isolation valves open and cross over to inert gas header closed. Purge to vent line until air composition is breathable. Purge
header has to be displaced with inert gas at end of gas freeing.
DRAWINGS AND DOCUMENTS
BLV-KN501-MA-220-PID-0001-001 Rev C2 P&ID - Inert Gas Skid
BLV-KN501-MA-220-PID-0002-001 Rev C2 P&ID - Deck Seal - Inert Gas System
BLV-KN501-MA-220-PID-0003-001 Rev C2 P&ID - Deck Distribution - Cargo Tank Vent & Inert Gas System
Plus Vendor Diagrams:
AFL-KN501-PI-220-PID-0001-001 Rev C1 P&ID Flow Diagram Inert Gas System (Aalborg)
AFL-KN501-PI-220-PID-0001-002 Rev C1 P&ID Flow Diagram Delivery Line (Aalborg)
AFL-KN501-PI-220-LEG-0001 Rev A2 Symbols and Letter Code (Aalborg)
Date:
Doc:
Page:
- with P&IDs
77
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
It was agreed by the HAZOP
team that the original operating
philosophy should be retained
using the Purge Header for gas
freeing with the individual tank
P/Vs isolated.
[1] Confirm philosophy of
isolating / bypassing P/Vs (220PVV-006 to 021) on individual
tanks during gas freeing
operation.
[2] Ensure tank gas freeing
procedure reflects finalised
operating philosophy.
Date:
Doc:
Page:
- with P&IDs
78
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 160
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
Marine electrochlorination
No adverse consequence for
package has been deleted and
HAZOP foreseen.
hypochlorite will be supplied from
topsides package through new
PVC pipework.
Date:
Doc:
Page:
- with P&IDs
79
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
SAFEGUARDS
74 Design
Change
General Service Pump discharge Previous pipework unsuitable for MW2 is suitable for 16barg
General Service Pump deadhead
/ distribution pipework to upper
deck has changed from MW1 (10 pressure of 12barg.
barg) to MW2 (16barg) spec
75 Design
Change
76 Design
Change
Drawing error
Line 3/4"-ST-1728-MB1-HC
connecting to forward pump room
sea chest on P&ID: 0400-110F120-PID-021-001 does not
exist.
ACTION
Date:
Doc:
Page:
- with P&IDs
80
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
SAFEGUARDS
ACTION
Isolation valves 615-BUT-077
and 615-BUT-078 should be
locked open
79 Design
Change
Date:
Doc:
Page:
- with P&IDs
81
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
SAFEGUARDS
Other firewater pumps can still
operate in the event of a fire (eg.
low pressure in ringmain).
ACTION
Confirm that firewater pump test
mode and procedure for using
615-PCV-1243 is clearly defined
in operating procedures.
Date:
Doc:
Page:
- with P&IDs
82
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 170
Date:
Doc:
Page:
- with P&IDs
83
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
[1] P&ID BLV-KN501-MA-3450002-001 is under development
and requires HAZOP.
[2] Clarify who will carry out
design development of Boiler
Feedwater Storage Tanks and
associated Boiler Make-up Water
Pumps 345-P-200A/B/C.
84 Design
Change
85 Design
Change
Date:
Doc:
Page:
- with P&IDs
84
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 180
Date:
Doc:
Page:
- with P&IDs
85
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 190
Date:
Doc:
Page:
- with P&IDs
86
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
ACTION
Clarify (Class) requirement for
flame screen/spark arrestor (X35-111/112/113 and X-17131/132) in exhausts from Diesel
Generators and aft Firewater
Pump Diesel Driver
New P&ID Black and Grey Water Drawing shows source of black
and grey water into sewage
system on P&ID: BLV-KN501MA-360-PID-0002-001
tanks.
Although the previous HAZOP
only reviewed a "red-line markup" drawing, no adverse
consequences were foreseen
with the new arrangement.
88 Design
Change
Date:
Doc:
Page:
- with P&IDs
87
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
89 Design
Change
90 Equipment
Change
SAFEGUARDS
ACTION
Date:
Doc:
Page:
- with P&IDs
88
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
Removal of one Sewage Tank
(port or starboard) from service
for repair or inspection.
CONSEQUENCE
Approx. half of (starboard or port
side) cabins and hospital may be
out of use.
ACTION
Consider cross over line between
port and starboard Sewage
Tanks M15 and M23.
Date:
Doc:
Page:
- with P&IDs
89
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 200
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
Ensure that a review of the HP &
LP hydraulic system for Aft
Offloading Winches is carried out
by a competent person to ensure
it satisfies original operating
philosophy and EnQuest
requirements.
Date:
Doc:
Page:
- with P&IDs
90
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
94 Design
Change
95 Design
Change
SAFEGUARDS
ACTION
Date:
Doc:
Page:
- with P&IDs
91
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
SAFEGUARDS
ACTION
Identify whether the HPU
packages for riser ESDVs and LP
& HP hydraulic supply for subsea
control (valves) have been
subject to HAZOP review, and if
not carry out a HAZOP.
Date:
Doc:
Page:
- with P&IDs
92
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Date:
Doc:
Page:
- with P&IDs
93
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
94
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
95
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
96
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
97
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
98
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
99
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
100
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
101
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
102
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
103
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
104
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
105
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
106
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
107
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
108
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
109
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
110
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
111
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
112
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
113
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
114
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
115
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
116
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
117
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
118
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
119
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
120
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
121
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
122
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
123
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
124
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
125
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
126
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
127
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
128
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
129
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
130
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
131
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
132
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
133
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
134
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
135
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
136
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
137
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
138
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
139
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
140
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
141
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
142
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
143
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
144
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
145
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
146
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Closed Drains Systems (with new tie-ins from Crude Oil Metering and Sampling
Facilities and Steam Boiler Package Hazardous Open Drains);
Engine Room Steam Heating System;
High Expansion Foam System for Engine Room.
Date:
Doc:
Page:
- with P&IDs
147
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
EnQuest
PROJECT NO:
A3304
PROJECT:
DETAILS:
Date:
Doc:
Page:
- with P&IDs
148
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 71
Flow
No
CAUSE
Normal case no draining of
liquids
Date:
Doc:
CONSEQUENCE
SAFEGUARDS
ACTION
Page:
- with P&IDs
149
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 71 (continued)
ITEM: Closed Drains
DEVIATION
99
Flow
No
CONSEQUENCE
SAFEGUARDS
ACTION
[1] Ensure all valves in main
route to Residual Tank M14 are
locked open (ie. valves on P&ID
BLV-KN501-MA-205-PID 0003001).
[2] In the event Residual Tank
M14 is unavailable and closed
drains are routed to Cargo Tank
No. 7 port, the isolation valves in
the routing line to Cargo Tank
no. 7 port should be locked
open.
Date:
Doc:
Page:
- with P&IDs
150
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 71 (continued)
ITEM: Closed Drains
DEVIATION
CONSEQUENCE
SAFEGUARDS
101 Flow
No
102 Flow
More/High
103 Flow
Reverse
Inert gas in Residue Tank 14 (or Inert gas or oily water back into
Closed Drain header
Cargo Tank No. 7 port) or
reverse flow from offloading hose
flushing operation
104 Pressure
More/High
105 Pressure
More/High
Date:
Doc:
ACTION
Page:
- with P&IDs
151
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 71 (continued)
ITEM: Closed Drains
DEVIATION
CAUSE
CONSEQUENCE
SAFEGUARDS
106 Temperature
More/High
107 Level
More/High
108 Composition
General
No adverse consequence
foreseen for MT2 pipework.
109 Maintenance
General
ACTION
Date:
Doc:
Page:
- with P&IDs
152
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
153
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
154
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
155
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
156
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
EnQuest
PROJECT NO:
A3304
PROJECT:
DETAILS:
Date:
Doc:
Page:
- with P&IDs
157
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 121
CAUSE
CONSEQUENCE
110 Flow
No
111 Flow
No
112 Flow
No
SAFEGUARDS
ACTION
Date:
Doc:
Page:
- with P&IDs
158
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
SAFEGUARDS
113 Flow
Less/Low
114 Flow
More/High
115 Flow
More/High
116 Flow
Reverse
Leak in tube
Temperature monitoring of
system.
PSV on Expansion Vessel set at
3barg.
117 Pressure
More/High
ACTION
Date:
Doc:
Page:
- with P&IDs
159
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
Maintenance of Steam Heat
Exchanger
Date:
Doc:
CONSEQUENCE
Single isolation valve provided
SAFEGUARDS
ACTION
Page:
- with P&IDs
160
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 122
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
121 Flow
More/High
122 Flow
Reverse
Date:
Doc:
Page:
- with P&IDs
161
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
Leak from system
CONSEQUENCE
Loss of heating medium, reduced
heating of Engine Room.
SAFEGUARDS
ACTION
Temperature and
pressure instrumentation.
125 Temperature
More/High
Date:
Doc:
Page:
- with P&IDs
162
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
163
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
164
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
EnQuest
PROJECT NO:
A3304
PROJECT:
DETAILS:
Date:
Doc:
Page:
- with P&IDs
165
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
NODE: 161
CAUSE
Loss of fire water supply,
isolation valve closed or 3 way
ball valve in incorrect position
and foam sent to test
line/connection.
CONSEQUENCE
No foam to engine room when
required, escalation of fire.
SAFEGUARDS
ACTION
Date:
Doc:
Page:
- with P&IDs
166
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
SAFEGUARDS
129 Flow
Less/Low
130 Flow
Misdirected
Inadvertent opening of
isolation valve in bypass
around deluge valve.
Inadvertent opening of deluge
valve eg. spurious signal from
fire and gas system.
ACTION
ACTION NO: 68 ASSIGNED TO: Paul Renwick, AMEC (for Blaze) REF: [1]
ACTION NO: 69 ASSIGNED TO: Peter Benson, EnQuest REF: [2]
Date:
Doc:
Page:
- with P&IDs
167
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
CAUSE
CONSEQUENCE
SAFEGUARDS
ACTION
615-PIT-XXX (Blaze Item 18)
provides signal to fire and gas
system - this should also have a
high pressure alarm function to
indicate when deluge valve is
open.
Date:
Doc:
Page:
- with P&IDs
168
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
169
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
170
Project:
A3304
Client:
EnQuest
Title:
Date:
Doc:
www.anatec.com
Page:
- with P&IDs
171
Project:
A3304
Client:
EnQuest
Title:
www.anatec.com
Ambiguous;
Unsupported by evidence;
Technically unsound;
Based on actions to be made in the future;
Based on conclusions by unnamed persons;
Based on assumptions that are not stated in the response;
Based entirely on standard APR RP 14C safety analysis.
or if they propose work for other persons to do or otherwise leave the action open or
unresolved.
Attachments should be used where they make the response clearer. References should be
given in full for any reports, standards, calculations or drawings used in the response.
Responses should use equipment tag numbers, document reference numbers and document
revision numbers, if possible, to avoid confusion.
However, responses to actions regarding procedures to be developed in the future can be
closed out if the actionee has demonstrated how the procedure will be developed to
incorporate the HAZOP action and where he has identified the document reference for the
procedure.
3.5 Approving Actions
The AMEC Knightsbridge technical safety engineer will co-ordinate the close-out of all
HAZOP Review actions using the PiSYS action tracking management system. This is a webbased system, to which all nominated action parties have access. The PiSYS system is set up
to meet project and AMEC requirements for the workflow and approval chain.
Responses to actions will require approval by:
_
The chairman - to confirm that the response meets the intent of the Review team when
they raised the action;
The project engineer - to confirm that the project will adopt the activity proposed by
the response as part of the project workscope; and
Knightsbridge project manager to confirm EnQuest approval.
Where there is not agreement that the response should be approved, the Engineering Manager
will determine approval for adoption by the project, or will appoint a suitable technical
authority to resolve any disputed issue.
Date:
Doc:
Page:
- with P&IDs
17