Вы находитесь на странице: 1из 175

End to End HAZOP

EnQuest Producer FPSO

Anatec
Address:
Tel:
Fax:
Email:

Prepared by:

Anatec Limited

Presented to:

EnQuest

Date:

31st October 2013

Revision No.:

00

Ref.:

A3304-EQ-HAZOP-1

Aberdeen Office
10 Exchange Street, Aberdeen, AB11 6PH, UK
01224 253700
0709 2367306
aberdeen@anatec.com

Cambs Office
Braemoor, No.4 The Warren, Witchford, Ely, Cambs, CB6 2HN, UK
01353 661200
0709 2367306
cambs@anatec.com

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

TABLE OF CONTENTS
1.

INTRODUCTION............................................................................................................ 4
1.1
1.2
1.3
1.4

2.

KNIGHTSBRIDGE DEVELOPMENT ................................................................................ 4


PREVIOUS HAZOP STUDIES ....................................................................................... 5
END TO END HAZOP PURPOSE .................................................................................. 5
SCOPE OF HAZOP ...................................................................................................... 6

HAZOP ADMINISTRATION ........................................................................................ 7


2.1
2.2
2.3

3.

HAZOP ATTENDEES .................................................................................................. 7


REFERENCE DOCUMENTS ............................................................................................ 8
HAZOP NODES ........................................................................................................ 13

HAZOP METHODOLOGY ......................................................................................... 15


3.1
3.2
3.3
3.4
3.5

APPROACH ................................................................................................................ 15
HAZOP ACTIONS ..................................................................................................... 16
SIFS .......................................................................................................................... 16
RESPONDING TO HAZOP ACTIONS ........................................................................... 16
APPROVING ACTIONS ................................................................................................ 17

4.

HAZOP FINDINGS ....................................................................................................... 18

5.

HAZOP ACTIONS ........................................................................................................ 19

APPENDIX A - CONVENTIONAL HAZOP GUIDEWORDS


APPENDIX B - END TO END HAZOP WORKSHEETS
APPENDIX C - END TO END HAZOP P&IDS
APPENDIX D - ADDITIONAL HAZOP WORKSHEETS & HAZOP P&IDS

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Glossary:
BLV
bpod
ESD
ESDV
F&G
FPSO
HAZOP
HP
HPU
ICSS
LP
OIM
P&ID
PSD
SIF
SIL

Blohm and Voss


barrels oil per day
Emergency Shutdown
Emergency Shutdown Valve
Fire and Gas
Floating Production, Storage and Off-loading facility
Hazard and Operability (study)
High Pressure
Hydraulic Power Unit
Instrumented Control and Safety System
Low Pressure
Offshore Installation Manager
Process and Instrumentation Diagram
Process Shutdown
Safety Instrumented Function
Safety Integrity Level

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

1. Introduction
1.1 Knightsbridge Development
The Knightsbridge development will develop the remaining oil reserves in the Alma
(formerly Ardmore and Argyll) and Galia (formerly Duncan) fields. The Alma field lies in
Blocks 30/24 and 30/25, the Galia field lies in blocks 30/24 and 30/29, 310 km south-east of
Aberdeen in the UKCS North Sea.
EnQuest plan to redevelop the field with 7 subsea production wells tied back to a floating
production, storage and offloading (FPSO) vessel, through means of two 8 production risers.
As the wells are expected to have a 70%+ water cut, they will be produced with the aid of
electrical submersible pumps. Reservoir pressure will be maintained by produced water reinjection through means of two 8 risers, supplemented with treated seawater.

Figure 1.1: Alma & Galia Field Layout


The EnQuest Producer FPSO (the vessel formerly known as Uisge Gorm) is to be recertified
and classed as an FPSO to remain on station at the Alma/Galia field (approximately 25
nautical miles from its previous location on the Fife field) for 10 years without requirement
Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

for further dry dock inspection. The water depth at this location is approximately 78 m.
Crude oil production rate is predicted as 57,000 bopd.
1.2 Previous HAZOP Studies
The development is approaching the end of the design and construction phase and EnQuest
are preparing for commissioning and operations.
A number of HAZOPs have been carried out at various times during the design phase:


Dates

Description

EQ / AMEC Doc No

17 May - 18 May 2012

Boiler HAZOP #1

A2867-EQ-RP-1

16 July-18 July 2012

Subsea HAZOP

THL-KN501-HS-505-REP-0001

6 Aug - 16 Aug 2012

Topsides HAZOP

THL-KN501-HS-505-REP-0002

22 Oct - 1 Nov 2012

Utility HAZOP #1

Not issued to EQ

7 Nov-8 Nov 2012

Boiler HAZOP #2

ENQ-KN501-HS-000-REP-0005

4 Feb - 14 Feb 2013

Utility HAZOP #2

THL-KN501-HS-505-REP-0003

25 Feb - 8 March 2013

Marine HAZOP

ANA-KN501-HS-100-REP-0002

13 May-17 May 2013

Utility HAZOP #3

TH-S-R-1119-01

Although it is considered that all relevant systems and packages have been subject to formal
HAZOP study, there may have been changes in key process characteristics, equipment
selection or interface issues that may not have been fully addressed, or change the way the
system is to be operated.
1.3 End to End HAZOP Purpose
The purpose of the End to End HAZOP Review was to review the entire process and utility
systems at a "high" level to identify any significant changes, interfaces or missed areas that
may require further HAZOP review.
This was not intended to be a conventional HAZOP study, however, if a gap was identified in
the original HAZOP study, or if the design or operating parameters have significantly
changed, a conventional HAZOP study of that particular item was adopted, or actioned for
later study.
The objective of the End-to-End HAZOP Review was to provide a formal review of the
design and operation of the Knightsbridge facilities from wells to export, including marine
systems, in order to address:
Completeness of original HAZOP studies and identify any gaps;
Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

"

&

'

"

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Interface issues (in particular any assumptions made in the HAZOP studies due to
incomplete design information, or any changes);
Overall design and operability;
Significant changes to design or operating parameters.

The existing HAZOP study reports, HAZOP Action Register and latest P&IDs will form the
basis of the End to End HAZOP Review.
This End to End HAZOP has been carried out in accordance with the EnQuest HAZOP
Terms of reference [ENQ- KN501-HS-100-TOR-0002 A2].
1.4 Scope of HAZOP
The scope of the HAZOP included the following systems:
+

Subsea Production and Water Injection;


Topsides Production;
Topsides Utilities;
Steam System;
Marine Systems;
Any systems that have not previously been HAZOPed or are significantly changed.

The following systems were not covered:


+

Steam condensate (Marine System 315) return to topsides deaerator was not
completed because the pumping system and interface control system between topsides
and marine steam systems require further development;
HPU systems for subsea control / valve operation and for operation of the Riser
ESDVs have not been seen and so may not have been HAZOPed.

Actions have been raised to ensure these two items are assessed in due course.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

2. HAZOP Administration

Paul Caldwell
Steven Armstrong
Sandeep Ghotey

Review Chairman
Review Scribe
Knightsbridge Process
Engineer
Peter Benson
Operations Process Engineer
Michelle McRobbie Marine Systems Engineer
Matt Hastings
Process TA
Malcolm Robertson Production Supervisor
Doug McGregor
Instruments Engineer
Mike Webster
ESP Package Engineer
Mark Toshney
Subsea Engineer
Shaun Wilson
Umbilical Engineer
Bill Gracie
Subsea Controls Engineer
Donald Paterson
Steam Engineer
Iain MacLeod
MCO EnQuest Producer
John Chadwick
Mechanical Engineer
Geoff Black
Process Engineer
Ali Al-Khayat
Process Engineer
John Lennox
Process Engineer
Colin Greenlees
Process Engineer
Richard Auld
Controls & Instrumentation
Shah Ahmed
Controls & Instrumentation
Neil McMillan
Controls & Instrumentation
Peter Marchant
Safety Engineer
Paul Renwick
Safety Engineer
Neil Wise
Process Engineer

Anatec
Anatec
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
EnQuest
AMEC
AMEC
AMEC
AMEC
AMEC
AMEC
AMEC
AMEC
AMEC
Parsons
Brinckerhoff

Tues 29th

Mon 28th

Company:

Fri 25th

Title:

Wed 23rd

Name:

Thurs 24th

2.1 HAZOP Attendees


The HAZOP was held over five days in October 2013. The following personnel attended
some or all of the HAZOP sessions.

The HAZOP sessions were held at AMEC's City View offices, Aberdeen.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

2.2 Reference Documents


The HAZOP reviewed the following P&IDs:
Subsea:
MAX-KN501-PR-000-PID-0001-001 Rev A1 P&ID: Alma, Galia Production Tree
MAX-KN501-PR-000-PID-0002-001 Rev A1 P&ID: Alma Water Injection Tree
JPK-KN501-PR-844-PID-0001 Rev C2 P&ID: Alma Production Manifold
Topsides / Subsea Interface:
BLU-KN501-PR-840-PID-0010 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0001 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0002 Rev C1 P&ID: Swivel Stack
Topsides Process:
0400-110-F020-PID-019-001 Rev C1 Legend Sheet Piping Symbols
0400-110-F020-PID-019-002 Rev C1 Legend Sheet Instrument Symbols
0400-110-F020-PID-019-003 Rev C1 Valve Configuration Details
0400-110-F070-PID-014-001 Rev C1 Centralised Sample Collection
0400-110-F070-PID-016-001 Rev C1 P&ID Inlet Cooler
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
0400-110-F070-PID-028-001 Rev C3 CSU P&ID Produced Crude Oil Pumps P-5130 A/B/C
0400-110-F070-PID-029-001 Rev C3 First Stage Separator V-5100
0400-110-F070-PID-030-001 Rev C3 CSU P&ID Electrostatic Dehydrator V-5150
0400-110-F070-PID-031-001 Rev C3 P&ID Piperack Interface
0400-110-F070-PID-032-001 Rev C3 CSU P&ID Produced Crude Oil Coolers E-5135 A/B
0400-110-F070-PID-034-001 Rev C3 P&ID Swivel Stack
P0400-131-F070-001-01-C03-001-01 Rev 4 P&ID Inlet Heaters
P0400-131-F070-001-01-C03-002-01 Rev 12 First Stage Separator
P0400-131-F070-001-01-C03-003-01 Rev 11 Interstage Heater
P0400-131-F070-001-01-C03-004-01 Rev 11 Condensate Cooler
P0400-131-F070-001-01-C03-005-01 Rev 11 Topside Condensate Pumps / Drum
P0400-131-F070-001-01-C03-006-01 Rev 05 Drip Tray
BLV-KN501-MA-205-PID-0001-001 Rev C1 P&ID - Cargo Oil Piping in Tanks
Topsides Chemical Injection:
0400-110-F080-PID-013-001 Rev C3 Biocide Injection
0400-110-F080-PID-014-001 Rev C3 Oxygen Scavenger
0400-110-F080-PID-015-001 Rev C3 Demulsifier Injection
0400-110-F080-PID-017-001 Rev C3 Subsea Scale Inhibitor
0400-110-F080-PID-018-001 Rev C3 De-Oiler
0400-110-F080-PID-019-001 Rev C3 SWI Antifoam
0400-110-F080-PID-020-001 Rev C3 Vapour Phase Corrosion Inhibitor
0400-110-F080-PID-021-001 Rev C3 PWRI & SWI Scale Inhibitor
0400-110-F080-PID-022-001 Rev C3 Multi-phase Corrosion Inhibitor
0400-110-F080-PID-023-001 Rev C3 Oil Antifoam
Fuel Gas / Gas Handling:
0400-110-F080-PID-024-001 Rev C3 Fuel Gas Superheater
0400-110-F080-PID-026-001 Rev C2 Boiler & Steam Turbine - Interface with Topsides
0400-110-F080-PID-027-001 Rev C3 LP Condensate Return Pumps P-5355A/B

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

0400-110-F080-PID-028-001 Rev C3 HP Gas KO Drum V-5320


0400-110-F080-PID-029-001 Rev C3 LP Gas KO Drum V-5350
0400-110-F080-PID-030-001 Rev C3 LP Gas Coolers E-5335A/B
0400-110-F080-PID-031-001 Rev C3 HP Gas Cooler E-5305B
Nitrogen Generation, Storage & Distribution:
0400-110-F080-PID-032-001 Rev C3 Nitrogen Distribution
0400-110-F080-PID-033-001 Rev C3 Nitrogen Generation Package
0400-110-F080-PID-034-001 Rev C3 Nitrogen Storage Vessel
LP Fuel Gas Compressor:
0400-110-F080-PID-036-001 Rev C3 LP Fuel Gas Compressor
P0400-131-F080-PID-006-01-C03-001-01 Rev 06 LP Gas Recovery Compressor (OGS)
P0400-131-F080-PID-006-01-C03-001-02 Rev 06 LP Gas Recovery Compressor (OGS)
P0400-131-F080-PID-006-01-C03-001-03 Rev 06 LP Gas Recovery Compressor (OGS)
P0400-131-F080-PID-006-01-C03-001-04 Rev 06 LP Gas Recovery Compressor (OGS)
P0400-131-F080-PID-006-01-C03-001-05 Rev 05 LP Gas Recovery Compressor (OGS)
Topside Interface with Marine Systems:
0400-110-F080-PID-045-001 A1 Topside Interface with Marine Systems
Boiler Dosing:
0400-110-F080-PID-041-001 Rev C2 Chemical Injection Process System Boiler Crude Fuel Additive
Chemical
0400-110-F080-PID-046-001 Rev C1 Boiler HP Dosing Process System
0400-110-F080-PID-047-001 Rev C1 Boiler HP Dosing Process System - Oxygen Scavanger &
Condensate Polisher
Helifuel:
0400-110-F080-PID-048-001 Rev C2 Helifuel Decanting & Storage
Freshwater:
0400-110-F080-PID-050-001 Rev C1 Fresh Cooling Water System
0400-110-F080-PID-053-001 Rev C2 Topsides Freshwater Distribution
Cargo Offloading Metering and Sampling Facilities:
0400-110-F080-PID-052-001 Rev C2 Cargo Offloading Metering and Sampling Facilities
CSU Closed Drains:
0400-110-F100-PID-001-001 Rev C3 CSU P&ID Open & Closed Drains Collection 1 of 2
0400-110-F100-PID-001-002 Rev C3 P&ID Open & Closed Drains Collection 2 of 2
Flare:
0400-110-F100-PID-005-001Rev C3 P&ID Flare Header
0400-110-F100-PID-006-001 Rev C3 P&ID Flare KO Drum V-5370
0400-110-F100-PID-007-001 Rev C3 P&ID Flare Tip 515-X-001
Hazardous Open Drains Collection & Deluge Drains
0400-110-F100-PID-009-001 Rev C2 Drain Box Connections for Deluge Water and Hazardous Open
Drain
0400-110-F100-PID-010-001 Rev C3 P&ID Hazardous Open Drain System
0400-110-F100-PID-011-001 Rev C3 Hazardous Open Drain Collection System
Topsides Plant Air Distribution:
0400-110-F100-PID-012-001 Rev C2 Topside Plant Air on Deck
0400-110-F100-PID-013-001 Rev C2 Instrument Air in Power Module
0400-110-F100-PID-014-001 Rev C2 Starting & Compressed Air System in E.R.
0400-110-F100-PID-015-001 Rev C2 Topsides Instrument Air Distribution Sht 1 of 2
0400-110-F100-PID-015-002 Rev C2 Topsides Instrument Air Distribution Sht 2 of 2
Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Swivel Drains:
0400-110-F100-PID-019-001 Rev C2 Swivel Drains Recuperation System
Boiler Drains:
0400-110-F100-PID-022-001 Rev C2 Boiler Package Hazardous Open Drain Collection System
Seawater:
0400-110-F120-PID-001-001 Rev C2 Seawater Distribution
0400-110-F120-PID-002-001 Rev C3 Seawater for Deck Modules
0400-110-F120-PID-003-001 Rev C3 Seawater for Deck Modules Coarse Filters
0400-110-F120-PID-005-001 Rev C3 Electrochlorination Package
0400-110-F120-PID-006-001 Rev C3 Seawater for Deck Modules Seawater Lift Pumps
0400-110-F120-PID-008-001 Rev C3 STU Deaerator and Vacuum Pumps
0400-110-F120-PID-010-001 Rev C3 STU Seawater to Deaerator
0400-110-F120-PID-014-001 Rev C2 Overboard Caisson Starboard Side Forward
Firewater:
0400-110-F120-PID-017-001 Rev C3 Firewater Distribution Accommodation Area
0400-110-F120-PID-018-001 Rev C2 Firewater Jockey Pumps 615-P-004 A&B
0400-110-F120-PID-019-001 Rev C2 Firewater Pumps 615-P-001/002
0400-110-F120-PID-020-001 Rev C3 Firewater Distribution Aft Area Ringmain
0400-110-F120-PID-021-001 Rev C3 Firefighting Pump & Foam System Forward
0400-110-F120-PID-023-001 Rev C2 Firewater Distribution Engine Room / Aft Area
0400-110-F120-PID-024-001 Rev C3 Firewater Distribution Fwd Area Ringmain
0400-110-F120-PID-025-001 Rev C3 Firewater Distribution Helideck & Aft Deck
0400-110-F120-PID-027-001 Rev C3 Fire Fighting Pumps System in Pump Room After and Foam
Del. On Pump Room Bottom:
0400-110-F120-PID-029-001 Rev C2 Helideck & Sterndeck Water/Foam Monitoring System
0400-110-F120-PID-030-001 Rev A2 Engine Rom High Expansion Foam System
Blaze Vendor Foam Skid P&IDs:
P0400-131-F120-006-CO3-001/2/3/4/5 Rev 04 P&ID: Deluge Skid A/B/C/D/E
HP Water Injection / Produced Water:
0400-110-F150-PID-001-001 Rev C3 P&ID Produced Water Degasser 510-V-002
0400-110-F150-PID-002-001 Rev C3 Skimmed Oil Pumps 510-P-005 A/B
0400-110-F150-PID-003-001 Rev C3 Seawater Treatment Unit LP Booster Pumps P-5660-A/B
0400-110-F150-PID-004-001 Rev C3 Water Injection Pumps 535-P-001 A/B
0400-110-F150-PID-005-001 Rev C3 Water Injection Pumps 535-P-002 A/B
0400-110-F150-PID-006-001 Rev C3 Produced Water Coolers E-5175 A/B
0400-110-F150-PID-009-001 Rev C3 Production Separator Hydrocyclone S-5111
0400-110-F150-PID-010-001 Rev C3 Pumps 510-P-009 A/B Dehydrator Produced Water Recycle
0400-110-F150-PID-011-001 Rev C3 Production Hydrocyclones S-5801
0400-110-F150-PID-013-001 Rev C3 Production Separator Hydrocyclone S-5112
0400-110-F150-PID-014-001 Rev C2 Produced Water Filter Package
Topsides Steam Systems:
PBL-KN501-PR-315-DRG-0001-001 Rev C4 P&ID: HP Steam Header, IP&LP De-Superheater
PBL-KN501-PR-315-DRG-0002-001 Rev C4 P&ID: 20 Bar Steam Distribution
PBL-KN501-PR-315-DRG-0003-001 Rev C4 P&ID: LP (8 Bar) Steam Distribution
PBL-KN501-PR-315-DRG-0004-001 Rev C4 P&ID: Turbine By-Pass
PBL-KN501-PR-315-DRG-0005-001 Rev C5 P&ID: Condensate Return System
PBL-KN501-PR-315-DRG-0006-001 Rev C4 P&ID: Boiler Feed Water
Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

10

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

PBL-KN501-PR-315-DRG-0009-001 Rev C4 P&ID: Blowdown & Drains A


PBL-KN501-PR-315-DRG-0010-001 Rev C4 P&ID: Blowdown & Drains B
PBL-KN501-PR-315-DRG-0011-001 Rev C3 P&ID: Make-up Water & Miscellaneous Condensate
PBL-KN501-PR-315-DRG-0012-001 Rev C4 P&ID: Steam Turbine Drains
PBL-KN501-PR-315-DRG-0013-001 Rev C2 P&ID: Miscellaneous Fuels
PBL-KN501-PR-315-DRG-0014-001 Rev C3 P&ID: Sea Water Cooling
PBL-KN501-PR-315-DRG-0015-001 Rev C1 P&ID: Miscellaneous Utilities
PBL-KN501-PR-315-DRG-0016-001 Rev C1 P&ID Symbology Sheet
PBL-KN501-PR-315-DRG-0017-001 Rev C1 P&ID: Assorted Boiler Drains
PBL-KN501-PR-315-DRG-0018-001 Rev C3 P&ID: Miscellaneous Piping
PBL-KN501-PR-315-DRG-0019-001 Rev C3 P&ID: Instrument & Service Air
PBL-KN501-PR-315-DRG-0021-001 Rev C2 P&ID: Condenser A Piping - Piping Supplied by PBL
PBL-KN501-PR-315-DRG-0022-001 Rev C2 P&ID: Condenser B Piping - Piping Supplied by PBL
PBL-KN501-PR-315-DRG-0023-001 Rev C2 P&ID: Turbine A Piping - Piping Supplied by PBL
PBL-KN501-PR-315-DRG-0024-001 Rev C2 P&ID: Turbine B Piping - Piping Supplied by PBL
PBL-KN501-PR-315-DRG-0025-001 Rev C2 P&ID: STG Enclosure A Pressurisation System
PBL-KN501-PR-315-DRG-0026-001 Rev C2 P&ID: STG Enclosure B Pressurisation System
PBL-KN501-PR-315-DRG-0027-001 Rev C2 P&ID: Dirty and Oily Drains Piping Supplied by PBL
HCE-KN501-PR-315-PID-0001-001 Rev C3 P&ID: Economiser & Steam System - Boiler 'A'
(MB950011-001-01)
HCE-KN501-PR-315-PID-0002-001 Rev C2 P&ID: Fuel Gas & Oil Services - Boiler 'A'
HCE-KN501-PR-315-PID-0003-001 Rev C2 P&ID: Burner Fuel Systems - Boiler 'A'
HCE-KN501-PR-315-PID-0004-001 Rev C3 P&ID: Combustion Air + Soot Blowers Systems (Boiler
'A')
HCE-KN501-PR-315-PID-0005-001 Rev C4 P&ID: Economiser & Steam System - Boiler 'B'
HCE-KN501-PR-315-PID-0006-001 Rev C3 P&ID: Fuel Gas & Oil Services - Boiler 'B'
HCE-KN501-PR-315-PID-0007-001 Rev C3 P&ID: Burner Fuel Systems - Boiler 'B'
HCE-KN501-PR-315-PID-0008-001 Rev C4 P&ID: Combustion Air + Soot Blowers Systems (Boiler
'B')
HCE-KN501-PR-315-PID-0009-001 Rev C1 P&ID: Oil Supply System Diesel Oil Pump Skid
HCE-KN501-PR-315-PID-0010-001 Rev C1 P&ID: Oil Supply System Crude Oil Pump Skid
HCE-KN501-PR-315-PID-0012-001 Rev C4 P&ID: Condensate System Deaerator
HCE-KN501-PR-315-PID-0013-001 Rev C1 P&ID: Water Analysis Unit
HCE-KN501-PR-315-PID-0015-001 Rev C1 P&ID Diagram Symbols
HCE-KN501-PR-315-PID-0016-001 Rev C2 P&ID: Boiler Module - Cooling / Sealing Air Systems
(Boiler A)
HCE-KN501-PR-315-PID-0016-001 Rev C1 P&ID: Boiler Module - Cooling / Sealing Air Systems
(Boiler B)
HCE-KN501-PR-315-PID-0164-001 Rev A3 P&ID: Drains Schematic Boiler A
HCE-KN501-PR-315-PID-1164-001 Rev A3 P&ID: Drains Schematic Boiler B
DRC-KN501-PR-310-PID-0001-001 Rev C1 P&ID: Key
DRC-KN501-PR-310-PID-0002-001 P&ID: Turbine
DRC-KN501-PR-310-PID-0003-001 Rev C2 P&ID: Oil M'c A
DRC-KN501-PR-310-PID-0004-001 Rev C2 P&ID: Instrumentation M'c A
DRC-KN501-PR-310-PID-0005-001 Rev C1 P&ID: HP Desuperheater System M'c A (withdrawn)
DRC-KN501-PR-310-PID-0006-001 Rev C3 P&ID: Surface Condenser
DRC-KN501-PR-310-PID-0009-001 Rev C2 P&ID: Oil M'c B
DRC-KN501-PR-310-PID-0010-001 Rev C1 P&ID: Instrumentation M'c B
Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

11

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

DRC-KN501-PR-310-PID-0011-001 Rev C1 P&ID: HP Desuperheater System M'c B (withdrawn)


DRC-KN501-PR-310-PID-0012-001 Rev C3 P&ID: Surface Condenser
Marine System P&IDs:
BLV-KN501-MA-205-PID-0001-001 Rev C1 P&ID - Cargo Oil Piping in Tanks
BLV-KN501-MA-205-PID-0002-001 Rev C2 P&ID - Cargo Oil Piping in Pump Room
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
BLV-KN501-MA-210-PID-0001-001 Rev C2 P&ID - Cargo Oil Tank Cleaning
BLV-KN501-MA-220-PID-0001-001 Rev C2 P&ID - Inert Gas Skid
BLV-KN501-MA-220-PID-0002-001 Rev C2 P&ID - Deck Seal - Inert Gas System
BLV-KN501-MA-220-PID-0003-001 Rev C2 P&ID - Deck Distribution - Cargo Tank Vent & Inert
Gas System
BLV-KN501-MA-225-PID-0001-001 Rev C2 P&ID - Ballast & Stability Control
BLV-KN501-MA-230-PID-0001-001 Rev C2 P&ID - Drain Arrangement Oil
BLV-KN501-MA-230-PID-0002-001 Rev C2 P&ID - Drain Arrangement Water
BLV-KN501-MA-230-PID-0003-001 Rev C2 P&ID - Drain Arrangement Oil Water
BLV-KN501-MA-230-PID-0004-001 Rev C2 P&ID - Sludge Oil Water Tank Arrangement
BLV-KN501-MA-230-PID-0005-001 Rev C1 P&ID - Heliplatform Scuppers and Drains
BLV-KN501-MA-235-PID-0001-001 Rev C2 P&ID - Sounding, Gauging & Draft
BLV-KN501-MA-235-PID-0002-001 Rev C2 P&ID - Sounding, Gauging & Draft
BLV-KN501-MA-240-PID-0001-001 Rev C2 P&ID - Bilge System in ER
BLV-KN501-MA-240-PID-0002-001 Rev C2 P&ID - Bilge System Forward
BLV-KN501-MA-240-PID-0003-001 Rev C2 P&ID - Bilge System in After Ship
BLV-KN501-MA-255-PID-0001-001 Rev C1 P&ID - LP Hydraulic System for Aft Offloading
Winches
BLV-KN501-MA-255-PID-0002-001 Rev C1 P&ID - LP Hydraulic System for Aft Offloading
Winches
BLV-KN501-MA-315-PID-0001-001 Rev C2 P&ID - E.R 20 Barg Steam System
BLV-KN501-MA-315-PID-0002-001 Rev C3 P&ID - E.R 8 Barg Steam System
BLV-KN501-MA-315-PID-0003-001 Rev C2 P&ID - E.R Steam Condensate System
BLV-KN501-MA-315-PID-0004-001 Rev C2 P&ID - E.R Steam Condensate Transfer Pump Skid
BLV-KN501-MA-315-PID-0005-001 Rev C2 P&ID - Steam & Condensate for Tank Heating
BLV-KN501-MA-325-PID-0001-001 Rev C1 P&ID - Hydraulics for Crude Oil Pump Skid
BLV-KN501-MA-325-PID-0002-001 Rev C1 P&ID - Hydraulics for Fire Pump Skid
BLV-KN501-MA-325-PID-0003-001 Rev C1 P&ID - Hydraulics for Cargo Stripping Pump
BLV-KN501-MA-330-PID-0001-001 Rev C2 P&ID - Lubricating Oil Fill & Drains for ER Diesel
Engines
BLV-KN501-MA-335-PID-0001-001 Rev C2 P&ID - ER Exhaust & Drains for Diesel Engines
BLV-KN501-MA-340-PID-0001-001 Rev C2 P&ID - E.R Diesel Filling & Transfer System
BLV-KN501-MA-340-PID-0002-002 Rev C2 P&ID - Diesel Fuel Separator System
BLV-KN501-MA-340-PID-0003-001 Rev C2 P&ID - Fuel Service System - D.G & Diesel for Cargo
Pump
BLV-KN501-MA-340-PID-0004-001 Rev C2 P&ID - Diesel Oil Fuel Tanks Quick Closing Valves
BLV-KN501-MA-340-PID-0005-001 Rev C2 P&ID - Diesel Fuel Transfer System Outside E.R
BLV-KN501-MA-345-PID-0001-001 Rev C2 P&ID - E.R Freshwater Generation
BLV-KN501-MA-345-PID-0002-001 Rev C2 P&ID - Boiler Feedwater Storage and Transfer
BLV-KN501-MA-345-PID-0003-001 Rev C2 P&ID - E.R Freshwater Storage and Transfer
BLV-KN501-MA-345-PID-0004-001 Rev C2 P&ID - E.R Freshwater System Distribution on Deck
BLV-KN501-MA-350-PID-0001-001 Rev C2 P&ID - E.R Seawater Circulation
Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

12

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

BLV-KN501-MA-350-PID-0002-001 Rev C2 P&ID - E.R L.P Seawater Service


BLV-KN501-MA-350-PID-0005-001 Rev C2 P&ID - Upper Deck Wash System
BLV-KN501-MA-350-PID-0006-001 Rev C2 P&ID - General Seawater System in ER
BLV-KN501-MA-351-PID-0001-001 Rev C2 P&ID - ER Chlorinator and Dosing System
BLV-KN501-MA-355-PID-0002-001 Rev C2 P&ID - E.R Diesel Generators Freshwater Cooling
BLV-KN501-MA-360-PID-0001-001 Rev C1 P&ID - Sewage System
BLV-KN501-MA-360-PID-0002-001 Rev C1 P&ID - Black and Grey Water System
BLV-KN501-MA-360-PID-0002-002 Rev C1 P&ID - Black and Grey Water System
BLV-KN501-MA-371-PID-0001-001 Rev C1 P&ID - Marine Plant Air Distribution System
BLV-KN501-MA-371-PID-0002-001 Rev C1 P&ID - Marine Plant Air Distribution System
BLV-KN501-MA-725-PID-0001-001 Rev C2 P&ID - Hydraulic Control System
BLV-KN501-MA-725-PID-0002-001 Rev C2 P&ID - Hydraulic Control System
BLV-KN501-MA-725-PID-0003-001 Rev C2 P&ID - Hydraulic Control System
Vendor Drawings:
ALC-KN501-PR-345-PID-0001-001 Rev A9 P&ID - Aqua 45 HW Offshore (Alfa Laval)
ALC-KN501-PR-345-PID-0001-002 Rev. A9 P&ID Softening, EDI & NaOH Softening (Alfa Laval)
AFL-KN501-PI-220-PID-0001-001 Rev C1 P&ID Flow Diagram Inert Gas System (Aalborg)
AFL-KN501-PI-220-PID-0001-002 Rev C1 P&ID Flow Diagram Delivery Line (Aalborg)
AFL-KN501-PI-220-LEG-0001 Rev A2 Symbols and Letter Code (Aalborg)
1307-M20/C01/001 P&ID: Proposed Inside Air High Expansion Foam System for Engine Room
(Blaze)
HHO-KN501-HV-375-DWG-0174-001 Rev A1 P&ID Heating System Engine Room (Heinen &
Hopman)

The latest BLV drawings reviewed in the End to End HAZOP had some red line, hand
marked "as-built" and latest design change corrections and so are included in Appendix C.
-

2.3 HAZOP Nodes


The HAZOP was broken into the following HAZOP nodes:

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

13

<

<

<

>

>

<

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Node:
10
20

Description:
Subsea Production to 1st Stage Separation (multi-phase flow)
Oil Stabilisation (Interstage Heater, 2nd Stage Separator & Electrostatic
Dehydrator) to Cargo Tanks
30
Produced Water Treatment (plus overboard disposal)
40
Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to
Flare, plus Hydrocarbon Condensate Return
50
Oil Water Recycle from 2nd Stage Separation and Hydrocyclones to 1st
Stage Separator
60
Flare & Vent System, including Return of Liquids to Process System and
Emergency Blowdown
70
Process Drains System, Closed Drains, Hazardous Open Drains, Deluge
Drains and Swivel Drains
80
Seawater Supply (Existing and New Lift Pumps, Coarse Filtration, Seawater
Users and Overboard Dump)
90
HP Water Injection (Produced Water and Seawater) to Subsea Wells
100
Chemical Injection and Helifuel, Swivel Recuperation System, Boiler Crude
Fuel Additive Chemical
110
Plant Air, Nitrogen, Hypochlorite, Freshwater Cooling System, other
Topsides Utilities
120
Steam Generation, Fuel Supply and Steam Distribution to Consumers
130
Steam Condensate Return (Topsides and Marine) and Boiler Water Make-Up
140
Cargo Storage, Handling, Pumping and Offloading, including Tank
Stripping, Washing, etc.
150
Inert Gas and Cargo Tank Venting, Purging, Gas Freeing
160
Seawater System, Firewater Pumping and Distribution
170
Potable Water, Freshwater Cooling System
180
Diesel Bunkering, Storage, Transfer and Purification
190
Bilge, Ballast, Sounding and Gauging, Drains & Sewage
200
New Marine Systems not Previously HAZOPed
Nodes for Systems not Previously HAZOPed, but Requiring HAZOP:
71
Closed Drains
121
ER Steam Heat Exchanger
122
Heating Water Loop for Engine Room
161
High Expansion Foam System for Engine Room

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

14

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

3. HAZOP Methodology
3.1 Approach
The End to End HAZOP Review methodology was slightly different from a conventional
HAZOP (as described in Appendix A, which was used for three new systems (Nodes 71, 121
& 122 and 161) / P&IDs the team decided required new HAZOP).
The End to End HAZOP Review took the following approach:
The chairman / project process engineer introduced each node or session and provided a
summary of the extent of the previous HAZOP and any significant changes that have
occurred since - these may be as a direct result of actions raised in the previous HAZOP, or
due to design change or equipment procurement / construction change.
The independent Chairman then led the team through each of the following steps:
U

Select the appropriate section of the plant (node);


Define the nodes design intent and process conditions - note the "sections" of plant
will be fairly large, eg. oil stabilisation or gas handling, so not all the design details
will be repeated and recorded in the design intent, just the main items;
Apply the first/next guide word /deviation;
Determine (by brainstorming) whether the deviation is significant in terms of
applicability of the previous HAZOP;
Assess the consequences and all the potential implications of each deviation;
Assess whether the existing / new design provides sufficient protection;
Evaluate the likelihood of the net effect of consequence and protection;
Agree a recommendation for action or further consideration of the problem, if
required;
Apply the next guide word / deviation until they have all been considered;
Move onto the next node of the system until the whole study has been examined.

The HAZOP Review was recorded using the "HAZOP Manager" software.
By using the guidewords, the Chairman stimulated lateral thinking to identify potential
hazards and operability concerns. The End to End HAZOP Review guidewords are listed on
the next page.
The Chairman allowed scope for additional guidewords to be used for particular sub-systems
where deemed necessary by the Review team.
The Review team did not attempt to produce solutions by redesigning the plant during the
review sessions - any issues which could not be resolved promptly during the sessions were
resolved by formulating a suitable action.
Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

15

<

<

<

<

>

<

>

>

>

<

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

End to End HAZOP Review Guidewords / Deviations:


Guideword:
Design Change

Equipment Change
Interface Issues
Operability Issues

Maintainability Issues
Completeness of
Previous HAZOP(s)

Possible Deviations / Causes:


Change of design basis or scope, revised well or process
conditions, offloading criteria, storage capacities, line sizing or
specs breaks, material specification
Change of equipment type during procurement, reuse of equipment
previously considered obsolete
Interfaces with vendor packages, marine & topsides, spec changes,
piping and material specifications
Previously unrecognised operability issues, conflict with
operability of other plant or equipment, location & accessibility,
manual intervention vs remote operation (automation), start-up /
shutdown, ESD
Previously unidentified maintainability issues, access, physical
handling, replacement / spares
Incomplete HAZOP, recommendation for further HAZOP, new
equipment or design, assumptions in previous HAZOP

3.2 HAZOP Actions


The HAZOP actions are summarised in Section 5. Action response sheets have been issued
to the relevant parties separately from this report, but the approved responses will be included
in a HAZOP Close-out report.
3.3 SIFs
The HAZOP team noted that there are a number of safety instrumented functions (SIFs)
throughout the topsides and marine systems. Some of these have been subject to SIL
Assessment to determine their Safety Integrity Level (SIL). However, it was uncertain
whether all marine SIFs have been subject to SIL assessment. An action (no. 36) was raised
to ensure that all critical SIFs are appropriately assessed.
3.4 Responding to HAZOP Actions
When a suitable response has been developed by the discipline responsible, the actionee
should send the response to the AMEC technical safety engineer using the AMEC project
action tracking system.
Responses to HAZOP actions will not be accepted if they fail to:
\

Address all parts or all aspects of the action adequately;


Address the relevant aspects of the cause, consequence or safeguard statements;
Reference key documents.

or if they are:
Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

16

<

>

<

<

>

<

<

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

4. HAZOP Findings
The following key findings / issues arose out of the End to End HAZOP:
]

The majority of the systems and P&IDs have been covered in the earlier HAZOPs,
and the findings of those HAZOPs are still valid (note: all but a few of the earlier
HAZOP actions have been closed out);
Some equipment or design change has occurred, mainly in the marine systems. Some
drain lines have been re-routed and the oil export fiscal metering flushing line has
been modified;
Two new vendor packages have been added since the earlier HAZOPs (a new Blaze
foam package for the Engine Room, and a Heinen and Hopman Steam Heater and
closed loop heating medium and space heaters for the Engine Room). Both these
packages were subject to conventional HAZOP during the End to End HAZOP review
and are included in this report;
The Closed Drains Header and routing to the Residual Tank M-14 has been subject to
some modification and so was re-HAZOPed using conventional HAZOP guidewords,
and is presented in this report;
New hydraulic systems and interface pipework have been designed for marine
actuated valves and aft offloading winches. These were reviewed during the End to
End HAZOP but due to their simplicity, no adverse consequences were foreseen.
However, a formal review by a competent person should be made of the HPU
packages (vendor items) when the details are available. The same applies to the HPU
packages for riser ESDVs and subsea LP & HP supply to actuated valves;
Some minor interface issues were identified and actioned;
Some aspects were raised for clarification, but these are not expected to lead to further
design change;
The steam condensate return from marine consumers requires development of the
pumping system. In addition, the level control systems for the various marine and
topsides condensate collection vessels and boiler feedwater make-up requires HAZOP
as this has been deferred from the earlier HAZOPs.

Actions have been raised to address these issues / concerns, as summarised in Section 5.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

18

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

5. HAZOP Actions
The following End to End HAZOP Actions were raised:
No. Action:

Responsible
Person:

Node: 10 - Subsea Production to 1st Stage Separation (multi-phase flow)


1

Due to the need to be able to deal with hydrates subsea during the
initial production phase, ensure that the topsides temporary
methanol injection facilities are HAZOPed as well as the usual risk
assessment for temporary equipment offshore.

Sandeep Ghotey,
EnQuest

Clarify whether the AMV should be normally closed or open on


production trees

Sandeep Ghotey,
EnQuest

Ensure outlet lines from PSVs 1133/1134 at the Inlet Coolers are
shown on P&IDs with a slope to the Flare Knock Out drum and no
pockets.

Geoff Black,
AMEC

Node 20 - Oil Stabilisation (Interstage Heater, 2nd Stage Separator & Electrostatic
Dehydrator) to Cargo Tanks
4

Change from AC11BS (17 barg) topsides pipe spec to marine MT2
spec (16 barg) should be identified on marine P&IDs.

Sandeep Ghotey,
EnQuest

Ensure that adequate pipe stress analysis has been carried out
across topsides and marine pipe interfaces and that existing and
new tie points as shown on AMEC P&IDs.

Sandeep Ghotey,
EnQuest

Node 30 - Produced Water Treatment (plus overboard disposal)


6

Update HP/LP interface report to include pipework with pipe spec


changes from AC11BS to MW1

Geoff Black,
AMEC

Update P&IDs to identify the HP/LP interfaces between AC11BS


and MW1 pipework.

Sandeep Ghotey,
EnQuest

Confirm set point of 510-TI-1066 TAHH trip downstream of


Produced Water Coolers E-5175 A/B to ensure suitable protection
of slops tanks (coating and anodes).

Sandeep Ghotey,
EnQuest

Node 40 - Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to
Flare, plus Hydrocarbon Condensate Return
9

Review outlet temperature of sea water return from HP gas cooler


E-5305B due to not plugging surplus tubes in cooler

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Sandeep Ghotey,
EnQuest

Page:

- with P&IDs

19

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

No. Action:

Responsible
Person:

Node 50 - Oil Water Recycle from 2nd Stage Separation and Hydrocyclones to 1st Stage
Separator
10

Review the response to HAZOP action #75 (Topsides HAZOP),


taking into account change in pump type from centrifugal to
reciprocating, and update the control philosophy and P&ID, as
appropriate.

John Lennox /
Shah Ahmed,
AMEC

Node 60 - Flare & Vent System, including Return of Liquids to Process System and
Emergency Blowdown
11

Consider requirement to HAZOP replacement Flare Gas KO


Pumps P5380A/B if procured to different specifications (and also
the replacement of the LP Condensate Return Pump)

Sandeep Ghotey,
EnQuest

12

Ensure all lines into the Flare Header have a suitable slope and no
pockets

Geoff Black,
AMEC

13

Consider requirement for heat tracing of 2" outlet pipework from


Flare Gas KO Pumps, particularly if A1 spec pipework is to be
replaced

Sandeep Ghotey,
EnQuest

14

Review minimum temperature during blow down of flow line and


topsides pipework after shut in on high pressure trip.

Ali Al-Khayat,
AMEC

15

Ensure that TT-9013 and TT-9012 have suitable low range for
temperatures that could be created during flowline depressurising.

Ali Al-Khayat,
AMEC

Node 70 - Process Drains System, Closed Drains, Hazardous Open Drains, Deluge
Drains and Swivel Drains
16

Consider new high level alarm function on 531-LZIT-1000.

Ali Al-Khayat,
AMEC

17

Confirm location of vent 2"-VA-531-9159-AC11BS onto open


deck is in a safe location.

Ali Al-Khayat,
AMEC

18

Reconsider Action #25 (Utility HAZOP #3 - requirement for


relocating 842-LAHH-0114 onto a separate bridal) depending on
consequence of failure to detect high high level (ie. the SIL
requirement for the LAHH trip function and ability to achieve that
SIL requirement with the current configuration).

Ali Al-Khayat,
AMEC

Node 80 - Seawater Supply (Existing and New Lift Pumps, Coarse Filtration, Seawater
Users and Overboard Dump)
19

Ensure vendor information for replacement of Vacuum Pump


P5640A/B is passed to AMEC to update P&IDs, as required.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Sandeep Ghotey,
EnQuest
Page:

- with P&IDs

20

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

No. Action:

Responsible
Person:

20

Ensure vendor information for replacement of Sea Water LP


Sandeep Ghotey,
Booster Pump P5660A/B is passed over to AMEC to update P&IDs EnQuest
if required

21

Ensure that there is sufficient protection at the HP/LP interface at


tie in point TP350-039 on P&ID 0400-110-F120-P&ID-002-001.

John Lennox,
AMEC

Node 90 - HP Water Injection (Produced Water and Seawater) to Subsea Wells


22

Review whether this scenario has been considered in hydraulic


analysis and whether suitable protection is provided for water
injection flowline (eg PALL at riser).

Sandeep Ghotey,
EnQuest

23

Confirm whether the potential hazard of a short section / volume of


hot water (up to 105C) in the water injection riser liner has been
addressed and satisfactorily resolved.

Sandeep Ghotey,
EnQuest

24

Review requirement for a low suction pressure override controller


for Sea Water and Produced Water Injection Pumps 535-P-001 &
002A/B on start up, and raise MOC as necessary.

Sandeep Ghotey,
EnQuest

Node 100 - Chemical Injection and Helifuel, Swivel Recuperation System, Boiler Crude
Fuel Additive Chemical
25

Consider closing Chemical Injection system topsides manual


isolation valve when backing off stroke adjustor on turret chemical
injection dosing pump as an additional barrier to the two check
valves.

Malcolm
Robertson,
EnQuest

Node 110 - Plant Air, Nitrogen, Hypochlorite, Freshwater Cooling System, other
Topsides Utilities
26

Confirm function / description of symbol for SP-220 and put on


P&ID legend sheet

Peter Benson,
EnQuest

27

Only require single fill line connection to the Fresh Water Cooling
Medium Expansion Tank 355-V-001

John Lennox,
AMEC

28

Ensure vent from Fresh Water Cooling Medium Expansion Tank


355-V-001 is in a safe and suitable location

John Lennox,
AMEC

Node 120 - Steam Generation, Fuel Supply and Steam Distribution to Consumers
29

Confirm that stress analysis of steam system bellows has been


reviewed by EnQuest Piping TA

Sandeep Ghotey,
EnQuest

30

Confirm suitability of boiler Diesel Oil Pumps 340-P-2000A/B


(Hamworthy supply) for use with low sulphur marine diesel

Sandeep Ghotey,
EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

21

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

No. Action:

Responsible
Person:

Node 130 - Steam Condensate Return (Topsides and Marine) and Boiler Water MakeUp
31

Ensure operating procedure for Cargo Pump Steam Turbines is


updated (previously the outlet isolation valves S56 & S61 were
used during warm up).

Peter Benson,
EnQuest

32

When control system is developed and Condensate Transfer Pumps


315-P-2013A/B design to handle two different pumping rates has
been resolved, then a HAZOP should be carried out (including
condensate return to Deaerator Vessel along with other topsides
steam condensate streams).

Sandeep Ghotey,
EnQuest

Node 140 - Cargo Storage, Handling, Pumping and Offloading, including Tank
Stripping, Washing, etc.
33

Lock closed the double block and bleed valves 205-DBB-005 in the Colin Greenlees,
Cargo Oil Stripping Pump line used for flushing metering skid.
AMEC

34

Confirm at least one of the valves listed in note 18 on P&ID 0400110-F080-PID-052-001 is locked open at any one time.

Michelle
McRobbie,
EnQuest

35

Clarify how cargo offloading valves 3CO02/03/04 are interlocked


as per Note 10 on P&ID BLV-KN501-MA-205-PID-0003-001.

Doug McGregor,
EnQuest

36

Confirm whether a SIL review should be carried out on critical


marine systems.

Sandeep Ghotey,
EnQuest

37

Check note 13 on P&ID PLV-KN501-MA-205-PID-0002-001 and


whether the Cargo Pumps have internal pressure relief and pressure
trip function.

Michelle
McRobbie,
EnQuest

Node 150 - Inert Gas and Cargo Tank Venting, Purging, Gas Freeing
38

It was agreed by the HAZOP team that the original operating


Sandeep Ghotey,
philosophy should be retained using the Purge Header for gas
EnQuest
freeing with the individual tank P/Vs isolated.
Confirm philosophy of isolating / bypassing P/Vs (220-PVV-006 to
021)on individual tanks during gas freeing operation.

39

See Action 39: Ensure tank gas freeing procedure reflects finalised
operating philosophy

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Peter Benson,
EnQuest

Page:

- with P&IDs

22

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

No. Action:

Responsible
Person:

Node 160 - Seawater System, Firewater Pumping and Distribution


40

Remove line 3/4"-ST-1728-MB1-HC connecting to forward pump


room sea chest on P&ID: 0400-110-F120-PID-021-001 (but leave
screw down check valve / isolation valve at sea chest connection)

Colin Greenlees,
AMEC

41

Isolation valves 615-BUT-077 and 615-BUT-078 should be locked


open

Colin Greenlees,
AMEC

42

Delete line 2"-FF-2758-MW2 from PID 0400-110-F120-PID-029001

Colin Greenlees,
AMEC

43

Remove line details 1"-DF-615-9068-AC11BS and 1"-DF-6159069-AC11BS from AMEC drawing 0400-110-F120-PID-019-001

Colin Greenlees,
AMEC

44

Confirm that firewater pump test mode and procedure for using
615-PCV-1243 is clearly defined in operating procedures.

Peter Benson,
EnQuest

Node 170 - Potable Water, Freshwater Cooling System


45

P&ID BLV-KN501-MA-345-0002-001 is under development and


requires HAZOP.

Michelle
McRobbie,
EnQuest

46

Clarify who will carry out design development of Boiler Feedwater


Storage Tanks and associated Boiler Make-up Water Pumps 345-P200A/B/C.

Sandeep Ghotey,
EnQuest

Node 180 - Diesel Bunkering, Storage, Transfer and Purification


No actions raised in this node

Node 190 - Bilge, Ballast, Sounding and Gauging, Drains & Sewage
47

Clarify (Class) requirement for flame screen/spark arrestor (X-35111/112/113 and X-17-131/132) in exhausts from Diesel
Generators and aft Firewater Pump Diesel Driver

Michelle
McRobbie,
EnQuest

48

Confirm location of Bilge Water Filter Separator unit S-15-121


relative to Bilge Holding Tank M-20 to ensure pump will operate
satisfactorily and confirm whether a low level switch is required on
240-LS-010 to stop the pump to prevent it running dry.

Michelle
McRobbie,
EnQuest

49

Confirm design pressure of Bilge Ejectors X-15-141/142 for use


with firewater as motive fluid.

Michelle
McRobbie,
EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

23

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

No. Action:
50

Responsible
Person:

Consider cross over line between port and starboard Sewage Tanks
M15 and M23.

Michelle
McRobbie,
EnQuest

Node 200 - New Marine Systems not Previously HAZOPed


51

Ensure that a review of the HP & LP hydraulic system for Aft


Offloading Winches is carried out by a competent person to ensure
it satisfies original operating philosophy and EnQuest
requirements.

Michelle
McRobbie,
EnQuest

52

Check red line change of Ship Service Diesel Generators tag


number from D to A on P&ID: BLV-KN501-MA-325-PID-0003001.

Sandeep Ghotey,
EnQuest

53

Identify whether the HPU packages for riser ESDVs and LP & HP
hydraulic supply for subsea control (valves) have been subject to
HAZOP review, and if not carry out a HAZOP.

Sandeep Ghotey,
EnQuest

Additional Actions Raised for New HAZOP Nodes:


No. Action:

Responsible
Person:

Node: 71 - Closed Drains


54

Ensure all valves in main route to Residual Tank M14 are locked
open (ie. valves on P&ID BLV-KN501-MA-205-PID 0003-001).

Sandeep Ghotey,
EnQuest

55

In the event Residual Tank M14 is unavailable and closed drains


are routed to Cargo Tank No. 7 port, the isolation valves in the
routing line to Cargo Tank no. 7 port should be locked open.

Sandeep Ghotey,
EnQuest

56

Review requirement for check valves in Closed Drain pipework on


upper deck to Residual Tank M14 (and No. 7 port), due to potential
for blocking relief from sea water system PSVs.

Sandeep Ghotey,
EnQuest

57

Provide suitable isolation on Closed Drain header for connecting


flushing hose

Ali Al-Khayat,
AMEC

Node 121 - ER Steam Heat Exchanger


58

Consider requirement for steam trap in condensate outlet from ER


Steam Heat Exchanger.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Michelle
McRobbie,
EnQuest

Page:

- with P&IDs

24

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

No. Action:
59

Responsible
Person:

Either lock open valves 11 & 13 or provide thermal relief for Steam Michelle
Heat Exchanger tubes. Note: these valves may not be required.
McRobbie,
EnQuest

Node 122 - Heating Water Loop for Engine Room


60

Confirm tubes in Steam Heat Exchanger are designed for 175C

Michelle
McRobbie,
EnQuest

61

Confirm relief valve (item 10) capacity is suitable for thermal relief
requirements.

Michelle
McRobbie,
EnQuest

62

Consider providing check valve in each Circulation pump


discharge.

Michelle
McRobbie,
EnQuest

63

Provide connection for filling Engine Room Steam Heating system.

Michelle
McRobbie,
EnQuest

64

Clarify overall Engine Room heating philosophy and identify any


alarm and trips.

Michelle
McRobbie,
EnQuest

65

Clarify source of air, air fan requirements and whether there is a


requirement for gas detector(s) in the fresh air intakes.

Michelle
McRobbie,
EnQuest

Node 161 - High Expansion Foam System for Engine Room


66

Ensure 3 way ball valve (Blaze Item 09) is routed to Engine Room
rather than foam test line.

Paul Renwick,
AMEC (for
Blaze)

67

Isolation valve (Blaze Item 08) between foam tank and foam
inductor should be locked open.

Paul Renwick,
AMEC (for
Blaze)

68

Isolation valve (Blaze Item 04) in bypass around deluge valve


should be locked closed.

Paul Renwick,
AMEC (for
Blaze)

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

25

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

No. Action:

Responsible
Person:

69

Due to hazards to personnel in the event of inadvertent release of


Peter Benson,
high expansion foam in Engine Room, consider making the fire and EnQuest
gas signal permissive only and manual activation of the foam
system on the approval of OIM. Note: a risk assessment balancing
the fire risk in the Engine Room with the potential risk to personnel
in the event of inadvertent release of the high expansion foam
system should be carried out to support any such manual override
of the automatic foam release (as currently configured).

70

615-PIT-XXX (Blaze Item 18) provides signal to fire and gas


system - this should also have a high pressure alarm function to
indicate when deluge valve is open.

Paul Renwick,
AMEC (for
Blaze)

71

Confirm that a level gauge or local level indication for the Foam
Tank will be provided.

Paul Renwick,
AMEC (for
Blaze)

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

26

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Appendix A - Conventional HAZOP Guidewords

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

27

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Guideword

Examples of Potential Concerns

no flow

valve closure, line/instrument tapping blockages, filter blockage

less flow

stagnant lines, high pressure

more flow

undesirable flow, leakage, high velocity/erosion, vents and overflows,


draining/sampling, seal/gasket failure, environmental emissions, inventory
minimization / isolation, well barrier failure/testing

reverse flow

utilities contamination/overpressure, reverse rotation, NRV failure

misdirected
flow

flow in a place it shouldnt be

varying flow

slugging, system change affecting flow

more pressure

HP/LP interfaces, hydraulic surge, gas breakthrough, liquid overfill,


compressor settle out, tube rupture, deadheaded pump, thermal expansion,
vent blockages

less pressure

air ingress, gravity discharge, vacuum failures

varying pressure surging, pressure cycling, system change affecting pressure


high
temperature

thermal expansion, location of temperature probes, decomposition, fire

low temperature

hydrates/freezing, flashing liquids, depressurisation, low ambient


temperatures

high level

vessel overfill, high static head

low level

line routing, deadlegs, liquid accumulation, cavitation, gas blowby, loss of


interface

erosion /
corrosion

localised failure, choked valves, straight tees, unbalanced flows; dissimilar


materials, stress corrosion cracking, under lagging cracking, pitting, crevice
corrosion

composition

contamination, slugging, chemical additives, sand, corrosion products,


foaming, phase change, density change, viscosity change

deposition

sand, scale, wax, asphaltenes, hydrates

loss of services

power, heating/cooling medium, instrument air, hydraulics, nitrogen/fuel gas


purge, HVAC, comms failure/low quality

equipment

specific equipment design issues, vibration, interfaces

isolation

access, layout, isolation, pressure / leak testing

drain, vent,
purge

draining, venting, purging, lifting, vessel entry, spares, bunds, drip trays

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

28

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Guideword

Examples of Potential Concerns

maintenance

function testing, spares, vendor support, shutdown requirements, lifting,


access, laydown, inspection

start-up

non-standard conditions, human errors

shutdown

emergency shutdown requirements, sequential operations

operability

modes of operation. turndown, recycle, procedures, operator intervention, use


of controls, noise

vibration/fatigue Failure due to vibration, repetitive stress


human factors

ergonomics, behaviour

inherent safety

elimination/reduction, simplification, substitution, reduce hazard effect

fire and
explosion

impact of pool or jet fire, impact of explosion

release to
environment

spills and emissions

general

an opportunity to raise any other concerns

documentation

drafting errors, specification breaks, line gradient, tag nos., insufficient


information, incorrect tag nos.

For the new P&IDs considered in Appendix D, all of the above guidewords were considered.
The worksheets do not list each guideword if they did not raise a concern.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

29

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Appendix B - End to End HAZOP Worksheets


Note: P&IDs have not been included due to the large number, with the exception of Marine
System P&IDs which contain some red line mark-ups. These are included in Appendix C.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

30

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

EnQuest Knightsbridge Project


CLIENT:

EnQuest

PROJECT NO:

A3304

PROJECT:

End to End HAZOP Review - Process, Flare, Drains

DETAILS:

Review of previous HAZOP studies of the Knightsbridge Project to identify any


omissions, changes to design or equipment, or interface issues that might make
the earlier HAZOPs obsolete, or require new HAZOP study.

MEETING DATES: Wed 23rd, Thur 24th and Fri 25th October 2013
TEAM MEMBERS
Independent Chairman, Paul Caldwell (Anatec)
Scribe, Steven Armstrong (Anatec)
EnQuest Knightsbridge Process Engineer, Sandeep Ghotey
EnQuest Process TA, Matt Hastings
EnQuest Operations Process Engineer, Peter Benson
EnQuest Production Supervisor, Malcolm Robertson
EnQuest Instruments Engineer, Doug McGregor (part-time)
EnQuest ESP Package Engineer, Mike Webster (part time)
EnQuest Subsea Engineer, Mark Toshney (part time)
EnQuest Umbilical Engineer, Shaun Wilson (part time)
EnQuest Subsea Controls Engineer, Bill Gracie (part time)
AMEC Process Engineer, Geoff Black / Ali Al-Khayat / John Lennox (part time)
AMEC Controls & Instrumentation, Richard Auld / Shah Ahmed (part time)
AMEC Safety Engineer, Peter Marchant / Paul Renwick (part time)
ACTION RESPONSES TO: Paul Renwick, Technical Safety Engineer, AMEC
DOCUMENTS STUDIED
Subsea:
MAX-KN501-PR-000-PID-0001-001 Rev A1 P&ID: Alma, Galia Production Tree
MAX-KN501-PR-000-PID-0002-001 Rev A1 P&ID: Alma Water Injection Tree
JPK-KN501-PR-844-PID-0001 Rev C2 P&ID: Alma Production Manifold
Topsides / Subsea Interface:
BLU-KN501-PR-840-PID-0010 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0001 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0002 Rev C1 P&ID: Swivel Stack
Topsides Process:
0400-110-F070-PFD-001-001 Rev A2 EnQuest Producer Process Overall Flow Scheme
0400-110-F020-PID-019-001 Rev C1 Legend Sheet Piping Symbols
0400-110-F020-PID-019-002 Rev C1 Legend Sheet Instrument Symbols
0400-110-F020-PID-019-003 Rev C1 Valve Configuration Details
0400-110-F070-PID-014-001 Rev C1 Centralised Sample Collection
0400-110-F070-PID-016-001 Rev C1 P&ID Inlet Cooler
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

31

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

DOCUMENTS STUDIED (continued)


0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
0400-110-F070-PID-028-001 Rev C3 CSU P&ID Produced Crude Oil Pumps P-5130 A/B/C
0400-110-F070-PID-029-001 Rev C3 First Stage Separator V-5100
0400-110-F070-PID-030-001 Rev C3 CSU P&ID Electrostatic Dehydrator V-5150
0400-110-F070-PID-031-001 Rev C3 P&ID Piperack Interface
0400-110-F070-PID-032-001 Rev C3 CSU P&ID Produced Crude Oil Coolers E-5135 A/B
0400-110-F070-PID-034-001 Rev C3 P&ID Swivel Stack
P0400-131-F070-001-01-C03-001-01 Rev 4 P&ID Inlet Heaters ??
P0400-131-F070-001-01-C03-002-01 Rev 12 First Stage Separator
P0400-131-F070-001-01-C03-003-01 Rev 11 Interstage Heater
P0400-131-F070-001-01-C03-004-01 Rev 11 Condensate Cooler
P0400-131-F070-001-01-C03-005-01 Rev 11 Topside Condensate Pumps / Drum
P0400-131-F070-001-01-C03-006-01 Rev 05 Drip Tray
BLV-KN501-MA-205-PID-0001-001 Rev C1 P&ID - Cargo Oil Piping in Tanks
Fuel Gas / Gas Handling:
0400-110-F080-PID-024-001 Rev C3 Fuel Gas Superheater
0400-110-F080-PID-026-001 Rev C1 Boiler & Steam Turbine - Interface with Topsides (not in Utilities
HAZOP #1)
0400-110-F080-PID-027-001 Rev C3 LP Condensate Return Pumps P-5355A/B
0400-110-F080-PID-028-001 Rev C3 HP Gas KO Drum V-5320
0400-110-F080-PID-029-001 Rev C3 LP Gas KO Drum V-5350
0400-110-F080-PID-030-001 Rev C3 LP Gas Coolers E-5335A/B
0400-110-F080-PID-031-001 Rev C3 HP Gas Cooler E-5305B
LP Fuel Gas Compressor:
0400-110-F080-PID-036-001 Rev C3 LP Fuel Gas Compressor
P0400-131-F080-PID-006-01-C03-001-01 Rev 06 LP Gas Recovery Compressor (OGS Vendor
P&ID)
P0400-131-F080-PID-006-01-C03-001-02 Rev 06 LP Gas Recovery Compressor (OGS Vendor
P&ID)
P0400-131-F080-PID-006-01-C03-001-03 Rev 06 LP Gas Recovery Compressor (OGS Vendor
P&ID)
P0400-131-F080-PID-006-01-C03-001-04 Rev 06 LP Gas Recovery Compressor (OGS Vendor
P&ID)
P0400-131-F080-PID-006-01-C03-001-05 Rev 05 LP Gas Recovery Compressor (OGS Vendor
P&ID)
C214-D02-001-002 Rev A LP Gas Recovery Compressor (OGS Vendor P&ID)
C214-D02-001-003 Rev A LP Gas Recovery Compressor (OGS Vendor P&ID)
C214-D02-001-004 Rev A LP Gas Recovery Compressor (OGS Vendor P&ID)
C214-D02-001-005 Rev A LP Gas Recovery Compressor (OGS Vendor P&ID)
0400-110-F080-PID-035-001 Rev A1 LP Gas K.O. Drum V-5350 (LP Compressor Installation) (Redlined)
0400-110-F080-PID-038-001 Rev A1 HP Gas Coolers E-5305A/B (LP Compressor Installation) (Redlined)
Marine Topsides Interface:
0400-110-F080-PID-036-001 Rev C2? Topsides Interface with Marine Systems - handmarked up
Cargo Loading, Offloading Metering & Sampling:
0400-110-F080-PID-045-001 A1 Topside Interface with Marine Systems
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
0400-110-F080-PID-052-001 Rev C1 Cargo Offloading Metering and Sampling Facilities
BLV-KN501-MA-205-PID-0001-001 Rev C1 P&ID - Cargo Oil Piping in Tanks
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

32

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Produced Water:
DOCUMENTS STUDIED (continued)
0400-110-F150-PID-001-001 Rev C3 P&ID Produced Water Degasser 510-V-002
0400-110-F150-PID-002-001 Rev C3 Skimmed Oil Pumps 510-P-005 A/B
0400-110-F150-PID-003-001 Rev C3 Seawater Treatment Unit LP Booster Pumps P-5660-A/B
0400-110-F150-PID-004-001 Rev C3 Water Injection Pumps 535-P-001 A/B
0400-110-F150-PID-005-001 Rev C3 Water Injection Pumps 535-P-002 A/B
0400-110-F150-PID-006-001 Rev C3 Produced Water Coolers E-5175 A/B
0400-110-F150-PID-008-001 Rev A2 P&ID Production Hydrocyclone S-001 ??
0400-110-F150-PID-009-001 Rev C3 Production Separator Hydrocyclone S-5111
0400-110-F150-PID-010-001 Rev C3 Pumps 510-P-009 A/B Dehydrator Produced Water Recycle
0400-110-F150-PID-011-001 Rev C3 Production Hydrocyclones S-5801
0400-110-F150-PID-013-001 Rev C3 Production Separator Hydrocyclone S-5112
0400-110-F150-PID-014-001 Rev C2 Produced Water Filter Package
Flare (previously F080 System?):
0400-110-F100-PID-005-001 Rev C2 P&ID Flare Header
0400-110-F100-PID-006-001 Rev C2 P&ID Flare KO Drum V-5370
0400-110-F100-PID-007-001 Rev A2 P&ID Flare Tip 515-X-001
0400-110-F080-PID-006-001 Rev A2 CSU P&ID Purging Flare Header - Obsolete?
Hazardous Open Drains Collection & Deluge Drains
0400-110-F100-PID-009-001 Rev C2 Drain Box Connections for Deluge Water and Hazardous Open
Drain
0400-110-F100-PID-010-001 Rev C2 P&ID Hazardous Open Drain System
0400-110-F100-PID-011-001 Rev C2 Hazardous Open Drain Collection System
0400-110-F100-PID-003-001 Rev A2 P&ID (Construct) Hazardous Open Drain Collection System
Swivel Drains:
0400-110-F100-PID-019-001 Rev C1 Swivel Drains Recuperation System
Boiler Drains:
0400-110-F100-PID-022-001 Rev C1 Boiler Package Hazardous Open Drain Collection System

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

33

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 10

DATE REVIEWED: Wednesday, 23 October 2013

ITEM: Subsea Production to 1st Stage Separation (multi-phase flow)


Well fluids from subsea wells via ESPs, through manifolds, subsea pipeline and flexible risers, turret / swivel through inlet cooler to 1st stage separators (2
parallel process trains).
HP 2500# (350 barg) / LP 150# (17 barg) interface downstream of swivel, with PAHH trips set at 40barg. Inlet coolers designed for 17barg and 1st stage
separators designed for 17barg.
Flow rate up to 57,000bpd oil and 70,000 bpd gross fluids through either train
DRAWINGS AND DOCUMENTS
MAX-KN501-PR-000-PID-0001-001 Rev A1 P&ID: Alma, Galia Production Tree
MAX-KN501-PR-000-PID-0002-001 Rev A1 P&ID: Alma Water Injection Tree
JPK-KN501-PR-844-PID-0001 Rev C2 P&ID: Alma Production Manifold
BLU-KN501-PR-840-PID-0010 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0001 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0002 Rev C1 P&ID: Swivel Stack
0400-110-F070-PID-034-001 Rev C3 P&ID Swivel Stack
0400-110-F070-PID-031-001 Rev C3 P&ID Piperack Interface
0400-110-F070-PID-016-001 Rev C1 P&ID Inlet Cooler
0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
0400-110-F070-PID-029-001 Rev C3 First Stage Separator V-5100
P0400-131-F070-001-01-C03-002-01 Rev 12 First Stage Separator
DEVIATION
1

Design
Change

CAUSE
Inlet heaters removed since first
HAZOP - deemed not required
due to infrequent cold fluids
(repositioning of FPSO closer to
wells means well fluid arrival
temperatures will be higher than
previously expected).

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

CONSEQUENCE

SAFEGUARDS

No heating on start up when cold


well fluids will arrive at the FPSO,
or initially in topsides pipework.
In efficient separation of oil, gas
and water, off-spec oil to cargo
tanks. Excess water can be
stripped from cargo tank bottoms
and recovered /

Process design has been


reHAZOPed in Utility #2 HAZOP
with the inlet heaters deleted.
Interstage heater is available.

ACTION

Page:

- with P&IDs

34

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

(continued on next page)

NODE: 10 (continued)
ITEM: Subsea Production to 1st Stage Separation (multi-phase flow)
DEVIATION

CAUSE

CONSEQUENCE

DATE REVIEWED: Wednesday, 23 October 2013


SAFEGUARDS

ACTION

(continued from previous page)


disposed overboard if of suitable
spec. Some venting of vapours
through cargo tank vent system
(has been considered in Marine
HAZOP).

Design
Change

HP / LP interface topsides HP / LP interface had to be


design of overpressure protection managed. Finalised solution is
system
for IOPPS with closure of inlet
ESDVs at riser.

Design
Change

New logic in the event an ESP


trips was identified as required
(not initiating cause but effect of
trip)

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Potential for reverse flow through


ESP if it stops, allowing the ESP
to rotate in reverse and
subsequent damage when it
restarts.

Design of IOPPS has been


reHAZOPed and LOPA studies
have been carried out to
determine the correct SIL rating
of the system (with subsequent
verification of with the SIL is
achieved by the proposed design
trip and valve closure
configuration).
XOV and PWV will be positively
closed when ESP trips to prevent
reverse flow (PWV will be
opened as part of start up
sequence prior to restarting
ESP).

Page:

- with P&IDs

35

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 10 (continued)
ITEM: Subsea Production to 1st Stage Separation (multi-phase flow)

DATE REVIEWED: Wednesday, 23 October 2013

DEVIATION

CAUSE

CONSEQUENCE

SAFEGUARDS

ACTION

Design
Change

Previously a permanent methanol


supply and pumping system was
available topsides for hydrate
separation, but this has been
deleted.

Potential for hydrates on cold


start up with gas cap - this is
primarily a concern during the
early phase of field life (first 6
months, after which very little gas
is expected).

During initial production period


(typically 6 months) there will be
a temporary methanol injection
facility topsides for cold well start
up.
Methanol injection flow path from
topsides to subsea remains in
place and is unchanged from the
system originally HAZOPed.
Umbilical core will be filled with
methanol as a contingency so as
to minimise amount of brine
injected into the subsea
production system in the event
methanol is to remove hydrates.

Due to the need to be able to


deal with hydrates subsea during
the initial production phase,
ensure that the topsides
temporary methanol injection
facilities are HAZOPed as well as
the usual risk assessment for
temporary equipment offshore.

ACTION NO: 1 ASSIGNED TO: Sandeep Ghotey, EnQuest


5

Equipment
Change

AMV is shown as normally closed Pressure transmitters APPT 1 &


2 with high pressure alarm are
physically isolated from the
annulus (normally the AMV would
be open on production wells).
Unable to continuous monitor
annulus pressure.

Clarify whether the AMV should


be normally closed or open on
production trees

ACTION NO: 2 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

36

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 10 (continued)
ITEM: Subsea Production to 1st Stage Separation (multi-phase flow)
DEVIATION

CAUSE

CONSEQUENCE

Equipment
Change

Improved metering of appropriate


Different types of meter at gas
fluid - no adverse impact
and oil outlets from 1st Stage
Separators to be used from those foreseen in terms of HAZOP.
HAZOPed

Interface
Issues

No slope shown on outlet line


from PSV 1133/1134 for Inlet
Coolers

Accumulation of liquid in tail


pipes creates back pressure,
potential for ice plug of icing of
pipework if gas is cold.

DATE REVIEWED: Wednesday, 23 October 2013


SAFEGUARDS

ACTION

Ensure outlet lines from PSVs


1133/1134 at the Inlet Coolers
are shown on P&IDs with a slope
to the Flare Knock Out drum and
no pockets.

ACTION NO: 3 ASSIGNED TO: Geoff Black, AMEC

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

37

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 20

DATE REVIEWED: Wednesday, 23 October 2013

ITEM: Oil Stabilisation (Interstage Heater, 2nd Stage Separator & Electrostatic Dehydrator) to Cargo Tanks
Stabilisation and separation of water from oil to export quality specification (RVP 10psi).
Design flow rate is 57000 bpd oil. System design pressure is 150 # (17 bar gauge) and MT2 marine spec for pipe work (16 barg). Operating pressure is 1 bar
gauge.
Design temperature is -20/118C for the pipe work and 228C for the heater. Operating temperature is up to 85C.
Stabilised crude oil drops into Cargo tank No. 4P or S and is distributed to the other tanks as per loading plan.
DRAWINGS AND DOCUMENTS
0400-110-F070-PID-029-001 Rev C3 First Stage Separator V-5100
0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
P0400-131-F070-001-01-C03-002-01 Rev 12 First Stage Separator
P0400-131-F070-001-01-C03-003-01 Rev 11 Interstage Heater
0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
0400-110-F070-PID-030-001 Rev C3 CSU P&ID Electrostatic Dehydrator V-5150
0400-110-F070-PID-028-001 Rev C3 CSU P&ID Produced Crude Oil Pumps P-5130 A/B/C
0400-110-F070-PID-032-001 Rev C3 CSU P&ID Produced Crude Oil Coolers E-5135 A/B
0400-110-F080-PID-045-001 A1 Topside Interface with Marine Systems
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
DEVIATION

CAUSE

CONSEQUENCE

Design
Change

None identified since the


last HAZOP

Design
Change

Line from Produced Crude


Start up preheating can be achieved,
Oil Pumps to 1st Stage
but will take longer using Interstage
Separator has been deleted Heater instead of Inlet Heaters as
previously supplied and recycling
warmed crude back to 1st Stage
Separator.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

SAFEGUARDS

ACTION

Either use Dehydrator Produced Water


Recycle Pumps to recycle water heated by
Interstage Heater, or block water outlet line
from Dehydrator and use Produced Crude
Oil Pump to recycle hot water back to 1st
Stage Separator.

Page:

- with P&IDs

38

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 20 (continued)
DATE REVIEWED: Wednesday, 23 October 2013
ITEM: Oil Stabilisation (Interstage Heater, 2nd Stage Separator & Electrostatic Dehydrator) to Cargo Tanks
DEVIATION

CAUSE

CONSEQUENCE

10 Equipment New Jet Mixer 505-U-1101


Change
downstream of Produced
Crude Coolers

Improved metering of water cut of oil


using air driven pump to recirculate
fluids across the oil-in-water analyser
to create homogeneous mixture.

11 Interface
Issues

All existing topsides pipework (A1


spec) has been replaced by new pipe
compliant with NORSOK spec
(AC11BS).
Slight change in design pressure
specification between new pipework
(AC11BS for 17barg) and existing
marine pipework (MT2 10barg).
Pipe stress calculations have only
been carried out for the new pipework
as far back as the first pipe support in
the existing marine spec pipework.

Reuse of existing pipework


(A1 spec) and interface with
existing marine spec (MT1 or
MT2) pipework

SAFEGUARDS

ACTION

Topsides (AMEC) P&IDs


will be updated to reflect
new spec pipework as part
of P&ID "as built" exercise.

[1] Change from AC11BS (17 barg)


topsides pipe spec to marine MT2
spec (16 barg) should be identified
on marine P&IDs.
[2] Ensure that adequate pipe stress
analysis has been carried out across
topsides and marine pipe interfaces
and that existing and new tie points
as shown on AMEC P&IDs.

ACTION NO: 4 ASSIGNED TO: Sandeep Ghotey, EnQuest REF: [1]


ACTION NO: 5 ASSIGNED TO: Sandeep Ghotey, EnQuest, for Scott Haley, EnQuest REF: [2]
12 Interface
Issues

Frames drawings do not have


EnQuest numbers and are not
available on ASSAI.
HH trip function missing from
505-LI-1117 (high level trip on
KSU Separator).

Incomplete set of P&IDs recorded and


available

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

EnQuest numbers will be


provided during the "as
building" exercise and the
drawings put on ASSAI.

Page:

- with P&IDs

39

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 30

DATE REVIEWED: Wednesday, 23 October 2013

ITEM: Produced Water Treatment (plus overboard disposal)


Treatment of up to 94,000bpd oily water from production stream to less than 15ppm?? oil in water for re-injection (normal operation) or disposal overboard
(short-term, if subsea re-injection unavailable).
Design pressure of system is 7 bar gauge and full vacuum. Operating pressure is flare header pressure (less than 1 bar gauge). Design temperature is 20/118 degC for the pipe work. Operating temperature is up to 85degC.
Oily water from 1st stage separators through production hydrocyclones (S-5111, S-5112 & S-5801), degasser (510-V-002), produced water booster pumps
(510-P-003A/B), produced water filter (510-F-001A/B) and produced water cooler (E-5175A/B) to inlet of HP injection pumps (see Node 90) with alternative of
direct overboard dump, slops tank and then overboard dump or to cargo tanks.
DRAWINGS AND DOCUMENTS
0400-110-F070-PID-029-001 Rev C3 First Stage Separator V-5100
P0400-131-F070-001-01-C03-002-01 Rev 12 First Stage Separator
0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
0400-110-F150-PID-009-001 Rev C3 Production Separator Hydrocyclone S-5111
0400-110-F150-PID-011-001 Rev C3 Production Hydrocyclones S-5801
0400-110-F150-PID-013-001 Rev C3 Production Separator Hydrocyclone S-5112
0400-110-F150-PID-001-001 Rev C3 P&ID Produced Water Degasser 510-V-002
0400-110-F150-PID-014-001 Rev C2 Produced Water Filter Package
0400-110-F150-PID-006-001 Rev C3 Produced Water Coolers E-5175 A/B
BLV-KN501-MA-205-PID-0001-001 Rev C1 P&ID - Cargo Oil Piping in Tanks
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
DEVIATION
13 Design
Change

CAUSE

CONSEQUENCE

Addition of produced water filters Requirement for filters was


after topsides process HAZOP
specified by EnQuest.
was carried out.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

SAFEGUARDS

ACTION

Produced water filters and tie-ins


to existing produced water
system were HAZOPed in a
subsequent utilities HAZOP.

Page:

- with P&IDs

40

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 30 (continued)
ITEM: Produced Water Treatment (plus overboard disposal)
DEVIATION

CAUSE

DATE REVIEWED: Wednesday, 23 October 2013


CONSEQUENCE

SAFEGUARDS

ACTION

Potential to overpressure bellows 510-BUT-001 has been


if 510-BUT-001 isolation valve
designated as Locked Open
upstream is closed.

14 Design
Change

Flexible bellows at inlet to each


Produced Water Booster Pump
has been rated to 7barg instead
of 14barg

15 Equipment
Change

It was noted that the use of


butterfly valves may not be
suitable for isolation for on-line
maintenance purposes

These are standard items in the


produced water system

16 Interface
Issues

HP/LP interface between


Potential to overpressure marine
topsides pipework (AC11BS 17
pipework
barg) and marine (MW1 10 barg)

Maximum discharge pressure


[1] Update HP/LP interface report
from produced water pumps
to include pipework with pipe
(63m) is less MW1 spec (10barg) spec changes from AC11BS to
MW1.
[2] Update P&IDs to identify the
HP/LP interfaces between
AC11BS and MW1 pipework.

ACTION NO: 6 ASSIGNED TO: Geoff Black, AMEC REF: [1]


ACTION NO: 7 ASSIGNED TO: Sandeep Ghotey, EnQuest REF: [2]
17 Interface
Issues

Potential to send hot produced


water (>60C) to slops tank
because 510-TI-1066 is set at
70C

Potential damage to slops tank


lining and anodes (design
temperature specified as 60C).

TAH alarm set at 55C in cooler's


discharge

Confirm set point of 510-TI-1066


TAHH trip downstream of
Produced Water Coolers E-5175
A/B to ensure suitable protection
of slops tanks (coating and
anodes).

ACTION NO: 8 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

41

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 40

DATE REVIEWED: Thursday, 24 October 2013

ITEM: Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to Flare, plus Hydrocarbon Condensate Return
HP gas from 1st stage separators plus LP gas from 2nd stage separators through LP gas KO drum V-5320 and LP gas compressor 550-C-001, through HP
gas cooler E-5305A/B to HP KO drum and fuel gas electric superheater 550-E-001A and meter to Steam Boiler burners.
Return of hydrocarbon condensate from HP gas KO drum and LP gas KO drum and LP condensate return pumps P-5355A/B, to inlet of 2nd stage separator.
Design pressure: 17 barg, Operating pressure approx. 7barg.
Design temperature: -20 C to118 C, Operating temperature (in/out): 40C to 85 C.
DRAWINGS AND DOCUMENTS
0400-110-F070-PID-029-001 Rev C3 First Stage Separator V-5100
P0400-131-F070-001-01-C03-002-01 Rev 12 First Stage Separator
0400-110-F070-PID-023-001 Rev C3 P&ID Knightsbridge Separation Unit Interfaces
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
0400-110-F080-PID-030-001 Rev C3 LP Gas Coolers E-5335A/B
0400-110-F080-PID-029-001 Rev C3 LP Gas KO Drum V-5350
0400-110-F080-PID-036-001 Rev C3 LP Fuel Gas Compressor
0400-110-F080-PID-031-001 Rev C3 HP Gas Cooler E-5305B
0400-110-F080-PID-028-001 Rev C3 HP Gas KO Drum V-5320
0400-110-F080-PID-024-001 Rev C3 Fuel Gas Superheater
0400-110-F080-PID-026-001 Rev C1 Boiler & Steam Turbine - Interface with Topsides
PBL-KN501-PR-315-DRG-0013-001 Rev C2 P&ID: Miscellaneous Fuels
HCE-KN501-PR-315-PID-0002-001 Rev C2 P&ID: Fuel Gas & Oil Services - Boiler 'A'
HCE-KN501-PR-315-PID-0003-001 Rev C2 P&ID: Burner Fuel Systems - Boiler 'A'
HCE-KN501-PR-315-PID-0006-001 Rev C3 P&ID: Fuel Gas & Oil Services - Boiler 'B'
HCE-KN501-PR-315-PID-0007-001 Rev C3 P&ID: Burner Fuel Systems - Boiler 'B'
0400-110-F080-PID-027-001 Rev C3 LP Condensate Return Pumps P-5355A/B
DEVIATION
18 Design
Change

CAUSE
Change of type of gas meter

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

CONSEQUENCE

SAFEGUARDS

ACTION

Improved turn down capability of


new gas meters.
No adverse impact on HAZOP
foreseen.

Page:

- with P&IDs

42

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 40 (continued)
DATE REVIEWED: Thursday, 24 October 2013
ITEM: Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to Flare, plus Hydrocarbon Condensate Return
DEVIATION

CAUSE

CONSEQUENCE

SAFEGUARDS

19 Design
Change

Reduced power for ESPs and


process heating requirements

Reduced demand for fuel gas


and higher flaring rate during
initial production phase

Still within flare and gas handling


capacity.
Best estimate of flaring rates
during initial start up period will
be updated.

20 Design
Change

525-PIT-1101 has split range


control on 525-PCV-1101A/B

This is a change from selectable


PCV control originally provided
for well testing or full production
rates

No adverse impact for HAZOP


foreseen

21 Design
Change

New type of coriolis meter 550FIT-1012

Improve type of meter for this


duty

22 Equipment
Change

Previous plan was to plug some


of the tubes in the HP gas cooler
E-5305B this will not be done
now

Potential for over cooling but


TCV on sea water return should
be able to control cooling rate
appropriately.
Low flow rate through cooler.

Sea water is filtered. No adverse


impact on HAZOP foreseen.

ACTION

Review outlet temperature of sea


water return from HP gas cooler
E-5305B due to not plugging
surplus tubes in cooler

ACTION NO: 9 ASSIGNED TO: Geoff Black, AMEC


23 Equipment
Change

New pumps will be required for


Different pump characteristics,
the LP Condensate Return
may affect control or pump
Pumps P-5355A/B instead of
recycle requirements.
using existing refurbished pumps

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Same specification for the pumps


- do not foresee adverse impact
for HAZOP requirements

Page:

- with P&IDs

43

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 40 (continued)
DATE REVIEWED: Thursday, 24 October 2013
ITEM: Gas Handling (fuel gas), Compression and Supply to Boilers / Disposal to Flare, plus Hydrocarbon Condensate Return
DEVIATION
24 Completeness
of Previous
HAZOP

CAUSE
Reverse flow from
downstream higher design
pressure system if
compressor stops with only a
single check valve in
compressor discharge.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

CONSEQUENCE
Potential to exceed package
design pressure of 13.8barg if
reverse flow from higher
downstream system (17barg
design pressure)

SAFEGUARDS

ACTION

NRV and SDV in outlet of LP Gas


Compressor package.
PAHH-1066 and PAHH-1119
trips at 1st Stage Separators set
at 11.5barg. PAHHs are SIL2
rated to protect the flowlines, but
will also prevent high pressure in
downstream HP gas system and
hence the LP Gas Compression
package.

Action raised in previous HAZOP


for LP Gas Compression
package to increase design
pressure from 13.8barg to 17barg

Page:

- with P&IDs

44

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 50

DATE REVIEWED: Friday, 25 October 2013

ITEM: Oil Water Recycle from 2nd Stage Separation and Hydrocyclones to 1st Stage Separator
Oily water from PW Degasser 510-V-002 via skimmed oil pump 510-P-005A/B to 2nd Stage Separator.
Oily water from Electrostatic Dehydrator V-5150 via Dehydrator Produced Water Recycle Pumps 510-P-009A/B to 1st Stage Separators.
Reject oily water from Hydrocylones (S-5111, S-5112 7 S-5801) to 2nd Stage Separator.
Design pressure is 17 bar gauge, Operating pressure is 3-4 bar gauge.
Design temperature is -20/118C for the pipework. Operating temperature is approx. 85degC.
DRAWINGS AND DOCUMENTS
0400-110-F070-PID-030-001 Rev C3 CSU P&ID Electrostatic Dehydrator V-5150
0400-110-F150-PID-010-001 Rev C3 Pumps 510-P-009 A/B Dehydrator Produced Water Recycle
0400-110-F150-PID-001-001 Rev C3 P&ID Produced Water Degasser 510-V-002
0400-110-F150-PID-002-001 Rev C3 Skimmed Oil Pumps 510-P-005 A/B
0400-110-F150-PID-009-001 Rev C3 Production Separator Hydrocyclone S-5111
0400-110-F150-PID-011-001 Rev C3 Production Hydrocyclones S-5801
0400-110-F150-PID-013-001 Rev C3 Production Separator Hydrocyclone S-5112
0400-110-F070-PID-016-001 Rev C1 P&ID Inlet Cooler
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
DEVIATION
25 Equipment
Change

CAUSE

CONSEQUENCE

Previous HAZOP action #75


(Topsides HAZOP) to change
control of Dehydrator Produced
Water Pumps to start second
pump on high high interface level
in Electrostatic Dehydrator.
Use of reciprocating pump for
Dehydrator Produced Water
Recycle Pumps.

Action #75 response was to make this


change, but the P&ID and control
philosophy do not reflect the change.
Design was based on centrifugal
pumps (now reciprocating pumps), so
the flow controller 510-FIC-1080 used
for minimum flow protection for the
pumps will result in excess water
being returned to Second Stage
Separator.

SAFEGUARDS

ACTION
Review the response to HAZOP
action #75 (Topsides HAZOP),
taking into account change in
pump type from centrifugal to
reciprocating, and update the
control philosophy and P&ID, as
appropriate.

ACTION NO: 10 ASSIGNED TO: John Lennox / Shah Ahmed AMEC

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

45

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 50 (continued)
ITEM: Oil Water Recycle from 2nd Stage Separation and Hydrocyclones to 1st Stage Separator
DEVIATION

CAUSE

26 Operability
Issues

Note previous discussion about


butterfly valves for process
isolation (triple offset valves)

27 Operability
Issues

Type of instrumentation on
produced water degasser vessel
allows either interface control or
bulk control

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

CONSEQUENCE

Interface control requires more


sophisticated nucleonic level
detectors that may not measure
oil/water interface when it sees
oil/gas interface

DATE REVIEWED: Friday, 25 October 2013


SAFEGUARDS

ACTION

It is feasible to operate on bulk


control and if that is insufficient
could try interface control

Page:

- with P&IDs

46

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 60

DATE REVIEWED: Thursday, 24 October 2013

ITEM: Flare & Vent System, including Return of Liquids to Process System and Emergency Blowdown
Flare Collection Header, HP Gas KO Drum V-5320, flare and pilots & condensate return to 2nd Stage Separator.
Design flow rate 10 MMSCFD (continuous). Design pressure is 17 barg (upstream systems that feed into flare header) and 7barg (flare header and system).
Operating pressure is flare header pressure (less than 1 bar gauge). Design temperature is -20/118 degC for the pipe work. Operating temperature is
ambient. The HP Gas KO Drum pump out capacity is 5 cubic metres per hour (max 10 cubic metres per hour with both pumps running).
Supply of HP gas to pilot and flare purge from HP Fuel Gas KO Drum V-5320 (F080-PID-0028).
DRAWINGS AND DOCUMENTS
0400-110-F080-PID-028-001 Rev C3 HP Gas KO Drum V-5320
0400-110-F100-PID-005-001 Rev C2 P&ID Flare Header
0400-110-F100-PID-006-001 Rev C2 P&ID Flare KO Drum V-5370
0400-110-F100-PID-007-001 Rev A2 P&ID Flare Tip 515-X-001
0400-110-F080-PID-006-001 Rev A2 CSU P&ID Purging Flare Header - Obsolete?
0400-110-F070-PID-017-001 Rev C3 P&ID Second Stage Separator V-5120
DEVIATION

CAUSE

CONSEQUENCE
Improved level sensing and
control of pumps

28 Design
Change

Type of level instrumentation on


Flare Gas KO Drum used for
process control of Flare Gas KO
Drum Pumps will change

29 Equipment
Change

Flare Gas KO Pumps P-5380A/B Same specification for the new


will be replaced with new pumps pumps as the existing pumps, but
pump characteristics may change
resulting in slightly different
control requirements.

SAFEGUARDS

ACTION

No impact on HAZOP foreseen.


Note: nucleonic type detectors for
level trip function (LAHH / LALL)
will not change.
Consider requirement to HAZOP
replacement Flare Gas KO
Pumps P5380A/B if procured to
different specifications (and also
the replacement of the LP
Condensate Return Pump)

ACTION NO: 11 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

47

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 60 (continued)
ITEM: Flare & Vent System, including Return of Liquids to Process System and Emergency Blowdown
DEVIATION
30 Interface
Issues

CAUSE
Slope is not shown on all lines
into the Flare Header

CONSEQUENCE

DATE REVIEWED: Thursday, 24 October 2013

SAFEGUARDS

Accumulation of liquids, blockage


or hydrates

ACTION
Ensure all lines into the Flare
Header have a suitable slope and
no pockets

ACTION NO: 12 ASSIGNED TO: Geoff Black, AMEC


31 Interface
Issues

Potential high pressure / low


pressure interface between
propane bottles and supply of
pilot gas from HP gas to KO
drum

Storage pressure of propane


bottles is 8 to 10barg.

500-PSV-1019 set at 12barg is


suitable for fire relief and block
discharge

32 Operability
Issues

Cold ambient temperature and


requirement to heat trace pipe of
2" diameter or less

2" outlet from Flare Gas KO


Pumps will be replaced and so
should be given heat tracing due
to intermittent flows and
presence of water

Existing pipework without heat


tracing will not be changed, but
replaced pipe should have heat
tracing, as required by
winterisation philosophy.

Consider requirement for heat


tracing of 2" outlet pipework from
Flare Gas KO Pumps, particularly
if A1 spec pipework is to be
replaced

ACTION NO: 13 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

48

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 60 (continued)
ITEM: Flare & Vent System, including Return of Liquids to Process System and Emergency Blowdown
DEVIATION

CAUSE

CONSEQUENCE

Low temperature could cause


33 Operability Issues Low temperature in flow
lines or topsides production damage to flowline or pipework
pipework when
depressuring flowline with
gas present (JT cooling)
(eg Galia well)

DATE REVIEWED: Thursday, 24 October 2013

SAFEGUARDS

ACTION

TT-9013 and TT-9012 with low


temperature alarm upstream of
swivel by SDV and bypass valve

[1] Review minimum temperature


during blow down of flow line and
topsides pipework after shut in on
high pressure trip.
[2] Ensure that TT-9013 and TT9012 have suitable low range for
temperatures that could be
created during flowline
depressurising.

ACTION NO: 14 ASSIGNED TO: Ali Al-Khayat, AMEC REF: [1]


ACTION NO: 15 ASSIGNED TO: Ali Al-Khayat, AMEC REF: [2]
34 Completeness of
Previous HAZOP

Line from LP Fuel Gas


Compressor package to
Flare Gas KO Drum

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Line was not included in original


HAZOP but it has been
HAZOPed since then

Page:

- with P&IDs

49

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 70

DATE REVIEWED: Thursday, 24 October 2013

ITEM: Process Drains System, Closed Drains, Hazardous Open Drains, Deluge Drains and Swivel Drains
Swivel Drains Recuperation Unit - Design pressure 7barg & return to Flare Gas KO Drum.
Centralised Sample Collection disposal to Closed Drains.
Process Closed Drains from vessels, etc., to Closed Drains Collection Header, then to Residue Tank No. 14 (in hull). - check interface drawing no. on marine
drawing BLV-KN501-MA-205-PID-0003-001 Rev C2.
Collection of hazardous drains (drip trays / tun dishes) from process areas, chemical storage & pumps, into Hazardous Open Drains Vessel 531-V-001 (local
vent) and transfer to Residue Tank No. 14 (in hull) via Hazardous Open Drain Pumps 531-P-001A/B (design pressure FV/18barg). New tie-in from Chemical
Injection Skid hazardous drains.
Boiler Package Hazardous Open Drains Collection System (drip trays) to Vessel 531-V-002 (design pressure FV/1bar) and transfer of liquids to Residue Tank
No. 14 (in hull) via Boiler Package Hazardous Open Drain Pump 531-P-002 (design pressure 7barg).
DRAWINGS AND DOCUMENTS
0400-110-F100-PID-006-001 Rev C2 P&ID Flare KO Drum V-5370
0400-110-F100-PID-019-001 Rev C1 Swivel Drains Recuperation System
0400-110-F070-PID-014-001 Rev C1 Centralised Sample Collection
0400-110-F100-PID-001-001 Rev C2 CSU P&ID Closed Drains Collection 1 of 2
0400-110-F100-PID-001-002 Rev C2 CSU P&ID Closed Drains Collection 2 of 2
0400-110-F080-PID-045-001 Rev A1 Topside Interface with Marine Systems
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
0400-110-F100-PID-009-001 Rev C2 Drain Box Connections for Deluge Water and Hazardous Open Drain
0400-110-F100-PID-010-001 Rev C2 P&ID Hazardous Open Drain System
0400-110-F100-PID-011-001 Rev C2 Hazardous Open Drain Collection System
DEVIATION
35 Design
Change

CAUSE
New connection to closed drain
header from offloading meters

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

CONSEQUENCE
Used to initially drain offloading
meters and then flush offloading
hose to Residue Tank

SAFEGUARDS

ACTION

This has been considered in the


new Closed Drains system
HAZOP

Page:

- with P&IDs

50

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 70 (continued)
ITEM: Process Drains System, Closed Drains, Hazardous Open Drains, Deluge Drains and Swivel Drains
DEVIATION
36 Operability
Issues

CAUSE

CONSEQUENCE
High level in drain vessel and
overflow of water, oil or
chemicals onto process deck to
atmospheric vent

High level in Hazardous Open


Drain Vessel due to failure of
531-LIT-1001 or Hazardous
Open Drain Pumps to operate

DATE REVIEWED: Thursday, 24 October 2013

SAFEGUARDS
This has been discussed in
previous HAZOPs

ACTION
[1] Consider new high level alarm
function on 531-LZIT-1000.
[2] Confirm location of vent 2"VA-531-9159-AC11BS onto open
deck is in a safe location.

ACTION NO: 16 ASSIGNED TO: Ali Al-Khayat, AMEC REF: [1]


ACTION NO: 17 ASSIGNED TO: Ali Al-Khayat, AMEC REF: [2]
37 Operability
Issues

Isolation valves on Swivel Drain


Recuperation system are marked
as locked open, except for
needle valves

If needle valves are closed then


unable to monitor failure of swivel
seal and possible build-up of
pressure in swivel seals.

Considered in previous HAZOP


Action #20 (Utility HAZOP #3) Needle valves are normally open
as specified in Bluewater
operating procedures.

38 Operability
Issues

Use of control bridle for level


transmitter 842-LIT-1003 and for
842-LAHH-1004 trip function

Failure to detect primary seal


failure (high high level in vessel)

Action was raised in previous


HAZOP to consider relocating
842-LAHH-0114 onto separate
bridal, but this was rejected.

Reconsider Action #25 (Utility


HAZOP #3 - requirement for
relocating 842-LAHH-0114 onto a
separate bridal) depending on
consequence of failure to detect
high high level (ie. the SIL
requirement for the LAHH trip
function and ability to achieve
that SIL requirement with the
current configuration).

ACTION NO: 18 ASSIGNED TO: Ali Al-Khayat, AMEC

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

51

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 70 (continued)
ITEM: Process Drains System, Closed Drains, Hazardous Open Drains, Deluge Drains and Swivel Drains
DEVIATION

CAUSE

CONSEQUENCE

39 Completeness
of Previous
HAZOP

Closed Drain system does not


appear in any of the previous
HAZOPs as a discrete node

System not HAZOPed., although


the drains have been considered
in various parts of the HAZOPs
(eg. draining of an individual
vessel).

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

DATE REVIEWED: Thursday, 24 October 2013

SAFEGUARDS

ACTION
A new HAZOP of the Closed
Drains System has been carried
out (as part of the End to End
HAZOP - see separate
worksheets for Node 71)

Page:

- with P&IDs

52

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

EnQuest Knightsbridge Project


CLIENT:

EnQuest

PROJECT NO:

A3304

PROJECT:

End to End HAZOP Review - Topsides Utilities & Seawater

DETAILS:

Review of previous HAZOP studies of the Knightsbridge Project to dentify and


omissions, changes to design or equipment, or interface issues that might make
the earlier HAZOPs obsolete, or require new HAZOP study.

MEETING DATES: Fri 25th October 2013


TEAM MEMBERS
Independent Chairman, Paul Caldwell (Anatec)
Scribe, Steven Armstrong (Anatec)
EnQuest Knightsbridge Process Engineer, Sandeep Ghotey
EnQuest Operations Process Engineer, Peter Benson
EnQuest Production Supervisor, Malcolm Robertson
AMEC Process Engineer, John Lennox
AMEC Controls & Instrumentation, Shah Ahmed
ACTION RESPONSES TO: Paul Renwick, Technical Safety Engineer, AMEC
DOCUMENTS STUDIED
Topsides Chemical Injection:
0400-110-F080-PID-013-001 Rev C2 Biocide Injection
0400-110-F080-PID-014-001 Rev C3 Oxygen Scavenger
0400-110-F080-PID-015-001 Rev C3 Demulsifier Injection
0400-110-F080-PID-017-001 Rev C3 Subsea Scale Inhibitor
0400-110-F080-PID-018-001 Rev C3 De-Oiler
0400-110-F080-PID-019-001 Rev C3 SWI Antifoam
0400-110-F080-PID-020-001 Rev C3 Vapour Phase Corrosion Inhibitor
0400-110-F080-PID-021-001 Rev C3 PWRI & SWI Scale Inhibitor
0400-110-F080-PID-022-001 Rev C3 Multi-phase Corrosion Inhibitor
0400-110-F080-PID-023-001 Rev C3 Oil Antifoam
Nitrogen Generation, Storage & Distribution:
0400-110-F080-PID-032-001 Rev C3 Nitrogen Distribution
0400-110-F080-PID-033-001 Rev C3 Nitrogen Generation Package
0400-110-F080-PID-034-001 Rev C3 Nitrogen Storage Vessel
Boiler Dosing:
0400-110-F080-PID-046-001 Rev C1 Boiler HP Dosing Process System
0400-110-F080-PID-047-001 Rev C1 Boiler HP Dosing Process System - Oxygen Scavanger &
Condensate Polisher
Helifuel:
0400-110-F080-PID-048-001 Rev C2 Helifuel Decanting & Storage
Swire Vendor Package for Helifuel storage and pumping.
Freshwater:
0400-110-F080-PID-050-001 Rev C1 Fresh Cooling Water System
0400-110-F080-PID-053-001 Rev C2 Topsides Freshwater Distribution

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

53

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

DOCUMENTS STUDIED (continued)


Topsides Plant Air Distribution (changed P&ID no.s):
0400-110-F100-PID-012-001 Rev C2 Topside Plant Air on Deck
0400-110-F100-PID-013-001 Rev C2 Instrument Air in Power Module
0400-110-F100-PID-014-001 Rev C2 Starting & Compressed Air System in E.R.
0400-110-F100-PID-015-001 Rev C2 Topsides Instrument Air Distribution Sht 1 of 2
0400-110-F100-PID-015-002 Rev C2 Topsides Instrument Air Distribution Sht 2 of 2
Swivel Chemicals:
BLU-KN501-PR-840-PID-0003 Rev C1 TMS P&ID: Turret Scale Inhibitor Dosing Pumps
BLU-KN501-PR-840-PID-0006 Rev C1 TMS P&ID: Turret CI Dosing Pumps
BLU-KN501-PR-840-PID-0008 Rev C1 TMS P&ID: Turret Scale Inhibitor Dosing Pumps
BLU-KN501-PR-840-PID-0009 Rev C1 TMS P&ID: Turret Scale Inhibitor Dosing Pumps
BLU-KN501-PR-842-PID-0002 Rev C1 TMS P&ID: Turret Swivel Drains Recovery Lines
Seawater:
0400-110-F120-PID-001-001 Rev C2 Seawater Distribution
0400-110-F120-PID-002-001 Rev C3 Seawater for Deck Modules
0400-110-F120-PID-003-001 Rev C3 Seawater for Deck Modules Coarse Filters
0400-110-F120-PID-005-001 Rev C2 Electrochlorination Package
0400-110-F120-PID-006-001 Rev C3 Seawater for Deck Modules Seawater Lift Pumps
0400-110-F120-PID-008-001 Rev C2 STU Deaerator and Vacuum Pumps
0400-110-F120-PID-010-001 Rev C3 STU Seawater to Deaerator
0400-110-F120-PID-014-001 Rev C2 Overboard Caisson Starboard Side Forward
HP Water Injection / Produced Water:
0400-110-F150-PID-001-001 Rev C3 P&ID Produced Water Degasser 510-V-002
0400-110-F150-PID-002-001 Rev C3 Skimmed Oil Pumps 510-P-005 A/B
0400-110-F150-PID-003-001 Rev C3 Seawater Treatment Unit LP Booster Pumps P-5660-A/B
0400-110-F150-PID-004-001 Rev C3 Water Injection Pumps 535-P-001 A/B
0400-110-F150-PID-005-001 Rev C3 Water Injection Pumps 535-P-002 A/B
0400-110-F150-PID-006-001 Rev C3 Produced Water Coolers E-5175 A/B
0400-110-F150-PID-009-001 Rev C3 Production Separator Hydrocyclone S-5111
0400-110-F150-PID-010-001 Rev C3 Pumps 510-P-009 A/B Dehydrator Produced Water Recycle
0400-110-F150-PID-011-001 Rev C3 Production Hydrocyclones S-5801
0400-110-F150-PID-013-001 Rev C3 Production Separator Hydrocyclone S-5112
0400-110-F150-PID-014-001 Rev C2 Produced Water Filter Package
Topsides / Subsea Interface:
0400-110-F070-PID-034-001 Rev C3 P&ID Swivel Stack
BLU-KN501-PR-840-PID-0010 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0001 Rev C1 P&ID: Turntable
BLU-KN501-PR-840-PID-0002 Rev C1 P&ID: Swivel Stack
Subsea:
MAX-KN501-PR-000-PID-0002-001 Rev A1 P&ID: Alma Water Injection Tree
JPK-KN501-PR-844-PID-0001 Rev C2 P&ID: Alma Production Manifold

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

54

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 80

DATE REVIEWED: Friday, 25 October 2013

ITEM: Seawater Supply (Existing and New Lift Pumps, Coarse Filtration, Seawater Users and Overboard Dump)
Seawater Supply for consumers and to suction of HP SW Injection Pumps.
Seawater Lift Pumps 350-P-001A/B and Seawater Feed Pumps P-4452A/B through Coarse Filters 350-F-001 and either to consumers or to Deaerator V5650 and Seawater Booster Pumps P-5660A/B, with overboard dump (if not injecting subsea - see Node 90).
The design flow rate is 70000 barrels of seawater a day. Design pressure is FV/7barg. Operating pressure is vacuum (in deaerator) up to 12.5barg. Design
temperature is -20/30C for the pipework. Operating temperature is ambient seawater temp.
DRAWINGS AND DOCUMENTS
0400-110-F120-PID-001-001 Rev C2 Seawater Distribution
0400-110-F120-PID-002-001 Rev C3 Seawater for Deck Modules
0400-110-F120-PID-003-001 Rev C3 Seawater for Deck Modules Coarse Filters
0400-110-F120-PID-004-001 A3 Seawater for Deck Modules New Seawater - missing??
0400-110-F120-PID-005-001 Rev C2 Electrochlorination Package
0400-110-F120-PID-006-001 Rev C3 Seawater for Deck Modules Seawater Lift Pumps
0400-110-F120-PID-007-001 A3 Seawater System in Power Module - missing??
0400-110-F120-PID-008-001 Rev C2 STU Deaerator and Vacuum Pumps
0400-110-F120-PID-010-001 Rev C3 STU Seawater to Deaerator
0400-110-F120-PID-014-001 Rev C2 Overboard Caisson Starboard Side Forward - in this Node??
0400-110-F150-PID-003-001 Rev C3 Seawater Treatment Unit LP Booster Pumps P-5660-A/B
DEVIATION
40 Equipment
Change

CAUSE
Replacement of Vacuum Pump
P5640A/B for Deaerator

CONSEQUENCE
May be slight variation in vacuum
pump characteristics, and hence
instrumentation / control.
No adverse consequence for
HAZOP foreseen.

SAFEGUARDS

ACTION
Ensure vendor information for
replacement of Vacuum Pump
P5640A/B is passed to AMEC to
update P&IDs, as required.

ACTION NO: 19 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

55

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 80 (continued)
DATE REVIEWED: Friday, 25 October 2013
ITEM: Seawater Supply (Existing and New Lift Pumps, Coarse Filtration, Seawater Users and Overboard Dump)
DEVIATION
41 Equipment
Change

CAUSE
Replacement of Seawater LP
Booster Pump P5660A/B

CONSEQUENCE

SAFEGUARDS

ACTION
Ensure vendor information for
replacement of Sea Water LP
Booster Pump P5660A/B is
passed over to AMEC to update
P&IDs if required

May be slight variation in booster


pump characteristics, and hence
instrumentation / control.
No adverse consequence for
HAZOP foreseen.

ACTION NO: 20 ASSIGNED TO: Sandeep Ghotey, EnQuest


42 Operability
Issues

High pressure / low pressure


interface between new and
existing pumps

Potential to exceed MW1 pipe


spec due to maximum discharge
pressure of new pumps.

Previous HAZOP action to install


two check valves, but only one
has been provided in high
pressure system.
350-PAHH-1082 will protect low
pressure existing system from
overpressure.

Ensure that there is sufficient


protection at the HP/LP interface
at tie in point TP350-039 on P&ID
0400-110-F120-P&ID-002-001.

ACTION NO: 21 ASSIGNED TO: John Lennox, AMEC

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

56

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 90

DATE REVIEWED: Wednesday, 23 October 2013

ITEM: HP Water Injection (Produced Water and Seawater) to Subsea Wells


Produced Water and deaerated and filtered seawater, pumped form approx. 5 barg to 40 to 180barg for disposal subsea through two pairs of HP Water
Injection Pumps 535-P-001A/B and 535-P-001A/B, with common discharge to WI riser to subsea wells (Alma & Galia).
Design flow rate is 90000 barrels of injection water a day. Design pressure is 235 bar gauge, nominal operating pressure is 40 to 180 barg. Design
temperature is -20/118C for the pipework. Operating temperature is from ambient to 55C.
DRAWINGS AND DOCUMENTS
0400-110-F150-PID-003-001 Rev C3 Seawater Treatment Unit LP Booster Pumps P-5660-A/B
0400-110-F150-PID-004-001 Rev C3 Water Injection Pumps 535-P-001 A/B
0400-110-F150-PID-005-001 Rev C3 Water Injection Pumps 535-P-002 A/B
0400-110-F150-PID-006-001 Rev C3 Produced Water Coolers E-5175 A/B
0400-110-F070-PID-034-001 Rev C3 P&ID Swivel Stack
BLU-KN501-PR-840-PID-0002 Rev C1 P&ID: Swivel Stack
BLU-KN501-PR-840-PID-0001 Rev C1 P&ID: Turntable
JPK-KN501-PR-844-PID-0001 Rev C2 P&ID: Alma Production Manifold
MAX-KN501-PR-000-PID-0002-001 Rev A1 P&ID: Alma Water Injection Tree
DEVIATION
43 Interface
Issues

CAUSE
AMV on Water Injection well is
shown as normally closed

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

CONSEQUENCE

SAFEGUARDS

ACTION

Pressure transmitters APT 1 & 2


with high pressure alarm are
physically isolated from the
annulus (normally the AMV would
be open on injection wells).
Unable to continuous monitor
annulus pressure.

Page:

- with P&IDs

57

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 90 (continued)
ITEM: HP Water Injection (Produced Water and Seawater) to Subsea Wells
DEVIATION
44 Operability
Issues

CAUSE
HP Water Injection pumps stop

CONSEQUENCE

DATE REVIEWED: Wednesday, 23 October 2013


SAFEGUARDS

ACTION
Review whether this scenario has
been considered in hydraulic
analysis and whether suitable
protection is provided for water
injection flowline (eg PALL at
riser).

Low pressure in water injection


well causes negative pressure in
water injection flow line and
damage

ACTION NO: 22 ASSIGNED TO: Sandeep Ghotey, EnQuest


45 Operability
Issues

Water injection shut down (no


flow through swivel) but
production continues

Confirm whether the potential


hazard of a short section /
volume of hot water (up to 105C)
in the water injection riser liner
has been addressed and
satisfactorily resolved.

Heat from production lines


transfers through swivel into
short section of water injection
line increasing temperature
above 80C (up to 105C) with
potential damage to flowline riser
liner when restart water injection.

ACTION NO: 23 ASSIGNED TO: Sandeep Ghotey, EnQuest


46 Operability
Issues

Start up of an additional HP
Water Injection pump or Booster
Pump trips

Low suction pressure at Hp


Water Injection pump, cavitation
and pump damage.
Discharge of produced water
overboard and possible shut
down of production.

PALL trips water injection pump


trips on low suction pressure.
Overall control philosophy for
Sea Water and Produced Water
HP Injection Pumps is being
developed and will consider this
issue.

Review requirement for a low


suction pressure override
controller for Sea Water and
Produced Water Injection Pumps
535-P-001 & 002A/B on start up,
and raise MOC as necessary.

ACTION NO: 24 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

58

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 90 (continued)
ITEM: HP Water Injection (Produced Water and Seawater) to Subsea Wells
DEVIATION
47 Operability
Issues

CAUSE
Scale forming in tail pipe from
PSV 1100 (if leaking) causing
blockage

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

DATE REVIEWED: Wednesday, 23 October 2013

CONSEQUENCE

SAFEGUARDS

Over pressure of 150lb pipework


to Closed Drain system

Action #120 (Topsides HAZOP)


to review this issue was raised in
original HAZOP.
Dosing of sea water system with
scale inhibitor.
Normally no flow through this
(PSV) line and line is sloped to
Closed Drain header.
Operators would be aware that
PSV is leaking due to high
upstream pressure and noise.
Could use drain double block and
bleed connection downstream of
PSV for flushing the line.

ACTION

Page:

- with P&IDs

59

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 100

DATE REVIEWED: Friday, 25 October 2013

ITEM: Chemical Injection and Helifuel, Swivel Recuperation System, Boiler Crude Fuel Additive Chemical
Use of chemicals for process condition & corrosion and scale control.
Atmospheric pressure storage tanks filled from tote tanks. Injection pumps design pressure 7barg, 14barg or 17barg depending on delivery location.
Helifuel supply in tote tanks, helifuel pumps 385-P-001A/B to Helifuel Dispensing Unit 385-U-002. Pump & dispensing unit design pressure 3.8barg.
Boiler Crude Fuel Additive Chemical: Atmospheric storage with dosing pump design pressure 100barg and delivery to Crude Oil Feed Pumps 205-P-2000A/B.
DRAWINGS AND DOCUMENTS
0400-110-F080-PID-013-001 Rev C2 Biocide Injection
0400-110-F080-PID-014-001 Rev C3 Oxygen Scavenger
0400-110-F080-PID-015-001 Rev C3 Demulsifier Injection
0400-110-F080-PID-016-001 Rev C3 Methanol - Has been deleted
0400-110-F080-PID-017-001 Rev C3 Subsea Scale Inhibitor
0400-110-F080-PID-018-001 Rev C3 De-Oiler
0400-110-F080-PID-019-001 Rev C3 SWI Antifoam
0400-110-F080-PID-020-001 Rev C3 Vapour Phase Corrosion Inhibitor
0400-110-F080-PID-021-001 Rev C3 PWRI & SWI Scale Inhibitor
0400-110-F080-PID-022-001 Rev C3 Multi-phase Corrosion Inhibitor
0400-110-F080-PID-023-001 Rev C3 Oil Antifoam
0400-110-F080-PID-048-001 Rev C2 Helifuel Decanting & Storage
BLU-KN501-PR-840-PID-0003 Rev C1 TMS P&ID: Turret Scale Inhibitor Dosing Pumps
BLU-KN501-PR-840-PID-0006 Rev C1 TMS P&ID: Turret CI Dosing Pumps
BLU-KN501-PR-840-PID-0008 Rev C1 TMS P&ID: Turret Scale Inhibitor Dosing Pumps
BLU-KN501-PR-840-PID-0009 Rev C1 TMS P&ID: Turret Scale Inhibitor Dosing Pumps
BLU-KN501-PR-842-PID-0002 Rev C1 TMS P&ID: Turret Swivel Drains Recovery Lines
0400-110-F080-PID-046/047-001 Rev C1 Boiler HP Dosing
0400-110-F080-PID-026-001
HCE-KN501-PR-315-PID-0001/5/10/12

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

60

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 100 (continued)


ITEM: Chemical Injection and Helifuel, Swivel Recuperation System, Boiler Crude Fuel Additive Chemical
DEVIATION

CAUSE

CONSEQUENCE

DATE REVIEWED: Friday, 25 October 2013

SAFEGUARDS

48 Design
Change

Some minor FCN changes to the No adverse consequence for


Chemical Injection systems were HAZOP foreseen
reviewed in the End to End
HAZOP.

49 Operability
Issues

Final selection of chemicals to be Potential incompatibility.


completed

50 Operability
Issues

No impact on safety as Chemical


Design of Water Injection system Some of the Chemical Injection
PSVs have been left set at 7barg Injection system is designed for
Chemical Injection system is
to avoid design change
14barg
14barg (eg. scale inhibitor into
discharge of Sea Water Booster
Pumps.

51 Operability
Issues

Dosing pumps in turret. In the


event production from a single
well is stopped, the appropriate
chemical injection pump head
would be manually stopped.

Potential for reverse flow from


production manifold and adjacent
wells into Chemical Injection
system

ACTION

Chemicals compatibility review


has been / will be carried out.

Two check valves to prevent


reverse flow from the well (one at
injection point, one in pump
discharge).

Consider closing Chemical


Injection system topsides manual
isolation valve when backing off
stroke adjustor on turret chemical
injection dosing pump as an
additional barrier to the two
check valves.

ACTION NO: 25 ASSIGNED TO: Malcolm Robertson, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

61

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 110

DATE REVIEWED: Friday, 25 October 2013

ITEM: Plant Air, Nitrogen, Hypochlorite, Freshwater Cooling System, other Topsides Utilities
General Topsides Utilities including distribution to consumers, as appropriate.
Plant Air & Instrument Air: Compression, drying & filtering, storage and supply of plant air at design pressure 12barg, operating pressure 8 to 10barg.
Nitrogen: Nitrogen Generator 372-U-001, 1805m3/hr, design pressure 13barg, design temp -20C/+60C.
Freshwater Cooling: Closed circuit cooling system with Freshwater Cooling Medium Expansion Tank 355-T-001, Central Freshwater Coolers E-4461A/B and
Cooling Water Circulation Pump 355-P-0001A/B
DRAWINGS AND DOCUMENTS
0400-110-F080-PID-032-001 Rev C3 Nitrogen Distribution
0400-110-F080-PID-033-001 Rev C3 Nitrogen Generation Package
0400-110-F080-PID-034-001 Rev C3 Nitrogen Storage Vessel
0400-110-F100-PID-012-001 Rev C2 Topside Plant Air on Deck
0400-110-F100-PID-013-001 Rev C2 Instrument Air in Power Module
0400-110-F100-PID-014-001 Rev C2 Starting & Compressed Air System in E.R.
0400-110-F100-PID-015-001 Rev C2 Topsides Instrument Air Distribution Sht 1 of 2
0400-110-F100-PID-015-002 Rev C2 Topsides Instrument Air Distribution Sht 2 of 2
0400-110-F080-PID-050-001 Rev C1 Fresh Cooling Water System
0400-110-F080-PID-053-001 Rev C2 Topsides Freshwater Distribution
DEVIATION

CAUSE

CONSEQUENCE

52 Completeness
of Previous
HAZOP

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

SAFEGUARDS

ACTION

AMEC design for nitrogen system


has not changed since HAZOP.
The vendor package for nitrogen
generation is a standard unit
which has been HAZOPed (Utility
HAZOP #1 & #2).

Page:

- with P&IDs

62

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 110 (continued)


ITEM: Plant Air, Nitrogen, Hypochlorite, Freshwater Cooling System, other Topsides Utilities
DEVIATION

CAUSE

CONSEQUENCE

53 Completenes
s of Previous
HAZOP

Fresh water cooling system is new


but has been HAZOPed (Utility
HAZOP #3 & #4) except for the
replacement fresh water cooling
medium expansion tank.

54 Equipment
Change

The Instrument Air package that has May not be suitable for use on
been procured does not comply with FPSO.
Class requirements

55 Equipment
Change

Symbol for SP-220 (in grid C2 on


Unclear what the function is of
P&ID 0400-110-F080-PID-0505-001) this symbol - probably for
disengagement of gas if present
in cooling water return stream
from Coolers.

DATE REVIEWED: Friday, 25 October 2013


SAFEGUARDS

ACTION

No adverse consequence for


HAZOP foreseen.

Package is being reviewed and


updated, as required, to satisfy
Class requirements
Confirm function / description of
symbol for SP-220 and put on
P&ID legend sheet

ACTION NO: 26 ASSIGNED TO: Pete Benson, EnQuest


56 Operability
Issues

Fresh Water Cooling Medium


Expansion Tank has two inlet
connections for top up water

Unnecessary piping probably


copied over from original design
which used ball valve for auto
top-up of tank

Only manual top up required (no


ball valve in replacement tank)

Only require single fill line


connection to the Fresh Water
Cooling Medium Expansion Tank
355-V-001

ACTION NO: 27 ASSIGNED TO: John Lennox, AMEC

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

63

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 110 (continued)


ITEM: Plant Air, Nitrogen, Hypochlorite, Freshwater Cooling System, other Topsides Utilities
DEVIATION
57 Operability
Issues

CAUSE
Outlet from vent for Fresh Water
Cooling Medium Expansion Tank

DATE REVIEWED: Friday, 25 October 2013

CONSEQUENCE

SAFEGUARDS

ACTION

Potential venting of hydrocarbons


due to leak from LP Gas Cooler
or from LP Fuel Gas Compressor
and hazard to personnel

Note P3 on P&ID 0400-110F080-PID-050-001 is to provide a


gas detector local to vent
discharge

Ensure vent from Fresh Water


Cooling Medium Expansion Tank
355-V-001 is in a safe and
suitable location

ACTION NO: 28 ASSIGNED TO: John Lennox, AMEC

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

64

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

EnQuest Knightsbridge Project


CLIENT:

EnQuest

PROJECT NO:

A3304

PROJECT:

End to End HAZOP Review - Steam Systems

DETAILS:

Review of previous HAZOP studies of the Knightsbridge Project to identify any


omissions, changes to design or equipment, or interface issues that might make
the earlier HAZOPs obsolete, or require new HAZOP study.

MEETING DATES: Mon 28th October 2013


TEAM MEMBERS
Independent Chairman, Paul Caldwell (Anatec)
Scribe, Steven Armstrong (Anatec)
EnQuest Knightsbridge Process Engineer, Sandeep Ghotey
EnQuest Operations Process Engineer, Peter Benson
EnQuest Marine Systems Engineer, Michelle McRobbie
EnQuest Process TA, Matt Hastings
EnQuest Instruments Engineer, Doug McGregor
EnQuest Steam Engineer, Donald Paterson
EnQuest Mechanical Engineer, John Chadwick
Parsons Process Engineer, Neil Wise
AMEC Process Engineer, Colin Greenlees
ACTION RESPONSES TO: Paul Renwick, Technical Safety Engineer, AMEC
DOCUMENTS STUDIED
Parsons Brinkerhoff:
PBL-KN501-PR-315-DRG-0001-001 Rev C4 P&ID: HP Steam Header, IP&LP De-Superheater
PBL-KN501-PR-315-DRG-0002-001 Rev C4 P&ID: 20 Bar Steam Distribution
PBL-KN501-PR-315-DRG-0003-001 Rev C4 P&ID: LP (8 Bar) Steam Distribution
PBL-KN501-PR-315-DRG-0004-001 Rev C4 P&ID: Turbine By-Pass
PBL-KN501-PR-315-DRG-0005-001 Rev C5 P&ID: Condensate Return System
PBL-KN501-PR-315-DRG-0006-001 Rev C4 P&ID: Boiler Feed Water
PBL-KN501-PR-315-DRG-0009-001 Rev C4 P&ID: Blowdown & Drains A
PBL-KN501-PR-315-DRG-0010-001 Rev C4 P&ID: Blowdown & Drains B
PBL-KN501-PR-315-DRG-0011-001 Rev C3 P&ID: Make-up Water & Miscellaneous Condensate
PBL-KN501-PR-315-DRG-0012-001 Rev C4 P&ID: Steam Turbine Drains
PBL-KN501-PR-315-DRG-0013-001 Rev C2 P&ID: Miscellaneous Fuels
PBL-KN501-PR-315-DRG-0014-001 Rev C3 P&ID: Sea Water Cooling
PBL-KN501-PR-315-DRG-0015-001 Rev C1 P&ID: Miscellaneous Utilities
PBL-KN501-PR-315-DRG-0016-001 Rev C1 P&ID Symbology Sheet
PBL-KN501-PR-315-DRG-0017-001 Rev C1 P&ID: Assorted Boiler Drains
PBL-KN501-PR-315-DRG-0018-001 Rev C3 P&ID: Miscellaneous Piping
PBL-KN501-PR-315-DRG-0019-001 Rev C3 P&ID: Instrument & Service Air
PBL-KN501-PR-315-DRG-0021-001 Rev C2 P&ID: Condenser A Piping - Piping Supplied by PBL
PBL-KN501-PR-315-DRG-0022-001 Rev C2 P&ID: Condenser B Piping - Piping Supplied by PBL
PBL-KN501-PR-315-DRG-0023-001 Rev C2 P&ID: Turbine A Piping - Piping Supplied by PBL
PBL-KN501-PR-315-DRG-0024-001 Rev C2 P&ID: Turbine B Piping - Piping Supplied by PBL
PBL-KN501-PR-315-DRG-0025-001 Rev C2 P&ID: STG Enclosure A Pressurisation System
PBL-KN501-PR-315-DRG-0026-001 Rev C2 P&ID: STG Enclosure B Pressurisation System
PBL-KN501-PR-315-DRG-0027-001 Rev C2 P&ID: Dirty and Oily Drains Piping Supplied by PBL
Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

65

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

DOCUMENTS STUDIED (continued)


Hamworthy Combustion:
HCE-KN501-PR-315-PID-0001-001 Rev C3 P&ID: Economiser & Steam System - Boiler 'A'
(MB950011-001-01)
HCE-KN501-PR-315-PID-0002-001 Rev C2 P&ID: Fuel Gas & Oil Services - Boiler 'A' (MB950011001-02)
HCE-KN501-PR-315-PID-0003-001 Rev C2 P&ID: Burner Fuel Systems - Boiler 'A' (MB950011-00103)
HCE-KN501-PR-315-PID-0004-001 Rev C3 P&ID: Combustion Air + Soot Blowers Systems (Boiler
'A') (MB950011-001-04)
HCE-KN501-PR-315-PID-0005-001 Rev C4 P&ID: Economiser & Steam System - Boiler 'B'
(MB950011-002-01)
HCE-KN501-PR-315-PID-0006-001 Rev C3 P&ID: Fuel Gas & Oil Services - Boiler 'B' (MB950011002-02)
HCE-KN501-PR-315-PID-0007-001 Rev C3 P&ID: Burner Fuel Systems - Boiler 'B' (MB950011-00203)
HCE-KN501-PR-315-PID-0008-001 Rev C4 P&ID: Combustion Air + Soot Blowers Systems (Boiler
'B') (MB950011-002-04)
HCE-KN501-PR-315-PID-0009-001 Rev C1 P&ID: Oil Supply System Diesel Oil Pump Skid
(MB950011-003-01)
HCE-KN501-PR-315-PID-0010-001 Rev C1 P&ID: Oil Supply System Crude Oil Pump Skid
(MB950011-003-02)
HCE-KN501-PR-315-PID-0012-001 Rev C4 P&ID: Condensate System Deaerator (MB950011-22001)
HCE-KN501-PR-315-PID-0013-001 Rev C1 P&ID: Water Analysis Unit (MB950011-220-02)
HCE-KN501-PR-315-PID-0015-001 Rev C1 P&ID Diagram Symbols
HCE-KN501-PR-315-PID-0016-001 Rev C2 P&ID: Boiler Module - Cooling / Sealing Air Systems
(Boiler A) (MB950011-001-05)
HCE-KN501-PR-315-PID-0016-001 Rev C1 P&ID: Boiler Module - Cooling / Sealing Air Systems
(Boiler B) (MB950011-002-05)
HCE-KN501-PR-315-PID-0164-001 Rev A3 P&ID: Drains Schematic Boiler A (MB950011-164-01)
HCE-KN501-PR-315-PID-1164-001 Rev A3 P&ID: Drains Schematic Boiler B (MB950011-164-02)
Dresser Rand:
DRC-KN501-PR-310-PID-0001-001 Rev C1 P&ID: Key
DRC-KN501-PR-310-PID-0002-001 P&ID: Turbine
DRC-KN501-PR-310-PID-0003-001 Rev C2 P&ID: Oil M'c A
DRC-KN501-PR-310-PID-0004-001 Rev C2 P&ID: Instrumentation M'c A
DRC-KN501-PR-310-PID-0005-001 Rev C1 P&ID: HP Desuperheater System M'c A (withdrawn)
DRC-KN501-PR-310-PID-0006-001 Rev C3 P&ID: Surface Condenser
DRC-KN501-PR-310-PID-0007-001 Rev C3 P&ID: Enclosure A (not in HAZOP Scope)
DRC-KN501-PR-310-PID-0007-002 Rev C3 P&ID: Enclosure A (not in HAZOP Scope)
DRC-KN501-PR-310-PID-0007-003 Rev A1 P&ID: Enclosure (not in HAZOP Scope)
DRC-KN501-PR-310-PID-0009-001 Rev C2 P&ID: Oil M'c B
DRC-KN501-PR-310-PID-0010-001 Rev C1 P&ID: Instrumentation M'c B
DRC-KN501-PR-310-PID-0011-001 Rev C1 P&ID: HP Desuperheater System M'c B (withdrawn)
DRC-KN501-PR-310-PID-0012-001 Rev C3 P&ID: Surface Condenser
DRC-KN501-PR-310-PID-0013-001 Rev C2 P&ID: Enclosure B (not in HAZOP Scope)
DRC-KN501-PR-310-PID-0013-002 Rev C1 P&ID: Enclosure B (not in HAZOP Scope)
Marine Steam Systems:
BLV-KN501-MA-315-PID-0001-001 Rev C2 P&ID - E.R 20 Barg Steam System
BLV-KN501-MA-315-PID-0002-001 Rev C3 P&ID - E.R 8 Barg Steam System
BLV-KN501-MA-315-PID-0003-001 Rev C2 P&ID - E.R Steam Condensate System
BLV-KN501-MA-315-PID-0004-001 Rev C2 P&ID - E.R Steam Condensate Transfer Pump Skid
BLV-KN501-MA-315-PID-0005-001 Rev C2 P&ID - Steam & Condensate for Tank Heating

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

66

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 120

DATE REVIEWED: Monday, 28 October 2013

ITEM: Steam Generation, Fuel Supply and Steam Distribution to Consumers


Steam Boiler and Turbine Power Generation package on the main deck to provide power for electrical submersible pumps, heating for process and topsides
utility requirements and general FPSO use (cargo tank heating, cargo pumps, freshwater generation).
Hamworthy Combustion (HC) have design the steam boilers, feedwater and fuel supply systems. Dresser Rand (DR) have designed the steam turbines /
gearboxes / generators, their lube systems, the turbine condenser and vacuum system. Parsons Brinckerhoff (PB) have designed the interconnection piping
between the above equipment, including some pressure reducing stations, desuperheaters, drain systems etc.
FPSO steam boilers removed. Steam condensate from FPSO returned to topsides boilers.
DRAWINGS AND DOCUMENTS
All topsides steam drawings (PBL, HC & DR) - see list in main text
DEVIATION
58 Design
Change

CAUSE

CONSEQUENCE

Bellows added in interconnecting Allows for movement of ship and


pipework
thermal expansion.
No adverse impact for HAZOP
foreseen.

SAFEGUARDS
Bellows are designed for 76barg
compared to 64.5barg design
pressure for rest of system.
Full stress analysis has been
carried out of pipework and
bellows and are Class approved
(Lloyds)

ACTION
Confirm that stress analysis of
steam system bellows has been
reviewed by EnQuest Piping TA

ACTION NO: 29 ASSIGNED TO: Sandeep Ghotey, EnQuest


59 Design
Change

New engine room space heater


provided in response to marine
HAZOP

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Steam supply and condensate


return from the heater have not
been HAZOPed

A HAZOP of steam heat


exchanger in engine room has
been carried out as part of this
End to End HAZOP - see Node
121

Page:

- with P&IDs

67

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 120 (continued)


ITEM: Steam Generation, Fuel Supply and Steam Distribution to Consumers
DEVIATION

CAUSE

CONSEQUENCE

DATE REVIEWED: Monday, 28 October 2013


SAFEGUARDS

60 Operability
Issues

Steam requirements have


reduced since original
specification due to reduced
power requirements for ESPs
and reduced process heating
(Inlet Heater has been deleted).

May only require one boiler


operating at 100% load.
No adverse impact for HAZOP
foreseen.

61 Operability
Issues

Use of Amergize boiler chemical


additive due to high salt content
in crude oil fuel for boilers

Reduces deposition of metal from Amergize chemical injection


salts on boiler tubes and allows
system has been designed by
easier removal with soot blowers. AMEC as part of topsides scope
and has been HAZOPed in
Topsides Utilities HAZOP.

62 Operability
Issues

Use of low sulphur marine diesel

Reduced lubricity in diesel pumps


used for fuel supply, possible
overheating and damage to
pumps.

ACTION

Second boiler will be maintained


on hot to stand by if it is not also
on duty (will probably operate
both boilers on about 50 - 60%
duty).

Confirm suitability of boiler Diesel


Oil Pumps 340-P-2000A/B
(Hamworthy supply) for use with
low sulphur marine diesel

ACTION NO: 30 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

68

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 120 (continued)


ITEM: Steam Generation, Fuel Supply and Steam Distribution to Consumers
DEVIATION
63 Operability
Issues

CAUSE

CONSEQUENCE

Change over from diesel to crude Error in switch over and burning
oil for fuel at boiler burners
incorrect fuel could affect
combustion properties and
temperature within boiler
combustion chamber and
exhaust.
Steam Boiler HAZOP considered
this possibility and noted:
"Mixture of fuels for a short
period, should not affect burner
performance."

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

DATE REVIEWED: Monday, 28 October 2013


SAFEGUARDS

ACTION

Steam Boiler HAZOP noted:


"XVs will be lined up so that
cannot operate with both fuels at
the same time (after the
switchover)", ie. Boiler
Management System will identify
XV in wrong position and
shutdown the boiler.

Page:

- with P&IDs

69

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 130

DATE REVIEWED: Monday, 28 October 2013

ITEM: Steam Condensate Return (Topsides and Marine) and Boiler Water Make-Up
Return of FPSO steam condensate to topsides, plus steam condensate from topsides boilers, and boiler feedwater make-up.
Chemicals.
DRAWINGS AND DOCUMENTS
All topsides steam drawings (PBL, HC & DR) - see list in main text.
FPSO Steam Systems:
BLV-KN501-MA-315-PID-0001-001 Rev C2 P&ID - E.R 20 Barg Steam System
BLV-KN501-MA-315-PID-0002-001 Rev C3 P&ID - E.R 8 Barg Steam System
BLV-KN501-MA-315-PID-0003-001 Rev C2 P&ID - E.R Steam Condensate System
BLV-KN501-MA-315-PID-0004-001 Rev C2 P&ID - E.R Steam Condensate Transfer Pump Skid
BLV-KN501-MA-315-PID-0005-001 Rev C2 P&ID - Steam & Condensate for Tank Heating
DEVIATION
64 Design
Change

CAUSE

CONSEQUENCE

Discharge pipework from Cargo


Pump Steam Turbines has been
uprated to MS3 (suitable for 20
barg), but the discharge flange
on the turbine is M10 (only
suitable for 10 barg).

If manual isolation valve (S56 or


S610) in outlet pipework is
closed, potential to overpressure
flange on turbine (note: valves
S56 & S61 are required to allow
maintenance of an individual
turbine whilst operating the other
one).
It is understood that the manual
isolation valves S56 & S61 were
used (closed) during initial
turbine warm up (Bluewater
procedure).

SAFEGUARDS

ACTION

Isolation valves S56 and S61 will Ensure operating procedure for
be locked open.
Cargo Pump Steam Turbines is
updated (previously the outlet
isolation valves S56 & S61 were
used during warm up).

ACTION NO: 31 ASSIGNED TO: Peter Benson, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

70

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 130 (continued)


ITEM: Steam Condensate Return (Topsides and Marine) and Boiler Water Make-Up
DEVIATION
65 Completeness
of Previous
HAZOP

CAUSE

CONSEQUENCE

Intended design of ER
Condensate Transfer Pumps
315-P-2013A/B was to have
two speeds of operation due
to the need to transfer
"normal" condensate returns
flow of approx 4 to 5m3/hr
and "cargo pump offloading"
condensate flows of approx.
40m3/hr. However, P&ID
details do not indicate how
pumps can be operated for
the two speeds / modes.

Unable to achieve turn down


required for "normal" operation
and when Cargo Pumps are
operating. Loss of boiler
condensate due to dumping
excess from marine system.
Note: Condensate return from
marine system and mixing with
topsides condensate return from
topsides users and the power
turbines has not been fully
HAZOPed.

DATE REVIEWED: Monday, 28 October 2013


SAFEGUARDS

ACTION

Blohm & Voss control philosophy When control system is


and P&IDs are now being
developed and Condensate
developed by AMEC.
Transfer Pumps 315-P-2013A/B
design to handle two different
pumping rates has been
resolved, then a HAZOP should
be carried out (including
condensate return to Deaerator
Vessel along with other topsides
steam condensate streams).

ACTION NO: 32 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

71

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

EnQuest Knightsbridge Project


CLIENT:

EnQuest

PROJECT NO:

A3304

PROJECT:

End to End HAZOP Review - Marine Systems

DETAILS:

Review of previous HAZOP studies of the Knightsbridge Project to identify any


omissions, changes to design or equipment, or interface issues that might make
the earlier HAZOPs obsolete, or require new HAZOP study.

MEETING DATES: Mon 28th and Tues 29th October 2013


TEAM MEMBERS
Independent Chairman, Paul Caldwell (Anatec)
Scribe, Steven Armstrong (Anatec)
EnQuest Knightsbridge Process Engineer, Sandeep Ghotey
EnQuest Operations Process Engineer, Peter Benson
EnQuest Marine Systems Engineer, Michelle McRobbie
EnQuest Process TA, Matt Hastings
EnQuest MCO EnQuest Producer, Iain MacLeod
AMEC Process Engineer, Colin Greenlees
AMEC Controls & Instrumentation, Neil McMillan
ACTION RESPONSES TO: Paul Renwick, Technical Safety Engineer, AMEC
DOCUMENTS STUDIED
Marine System P&IDs:
BLV-KN501-MA-205-PID-0001-001 Rev C1 P&ID - Cargo Oil Piping in Tanks
BLV-KN501-MA-205-PID-0002-001 Rev C2 P&ID - Cargo Oil Piping in Pump Room
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
BLV-KN501-MA-210-PID-0001-001 Rev C2 P&ID - Cargo Oil Tank Cleaning
BLV-KN501-MA-220-PID-0001-001 Rev C2 P&ID - Inert Gas Skid
BLV-KN501-MA-220-PID-0002-001 Rev C2 P&ID - Deck Seal - Inert Gas System
BLV-KN501-MA-220-PID-0003-001 Rev C2 P&ID - Deck Distribution - Cargo Tank Vent & Inert Gas
System
BLV-KN501-MA-225-PID-0001-001 Rev C2 P&ID - Ballast & Stability Control
BLV-KN501-MA-230-PID-0001-001 Rev C2 P&ID - Drain Arrangement Oil
BLV-KN501-MA-230-PID-0002-001 Rev C2 P&ID - Drain Arrangement Water
BLV-KN501-MA-230-PID-0003-001 Rev C2 P&ID - Drain Arrangement Oil Water
BLV-KN501-MA-230-PID-0004-001 Rev C2 P&ID - Sludge Oil Water Tank Arrangement
BLV-KN501-MA-230-PID-0005-001 Rev C1 P&ID - Heliplatform Scuppers and Drains
BLV-KN501-MA-235-PID-0001-001 Rev C2 P&ID - Sounding, Gauging & Draft
BLV-KN501-MA-235-PID-0002-001 Rev C2 P&ID - Sounding, Gauging & Draft
BLV-KN501-MA-240-PID-0001-001 Rev C2 P&ID - Bilge System in ER
BLV-KN501-MA-240-PID-0002-001 Rev C2 P&ID - Bilge System Forward
BLV-KN501-MA-240-PID-0003-001 Rev C2 P&ID - Bilge System in After Ship
BLV-KN501-MA-255-PID-0001-001 Rev C1 P&ID - LP Hydraulic System for Aft Offloading Winches
BLV-KN501-MA-255-PID-0002-001 Rev C1 P&ID - LP Hydraulic System for Aft Offloading Winches
BLV-KN501-MA-325-PID-0001-001 Rev C1 P&ID - Hydraulics for Crude Oil Pump Skid
BLV-KN501-MA-325-PID-0002-001 Rev C1 P&ID - Hydraulics for Fire Pump Skid
BLV-KN501-MA-325-PID-0003-001 Rev C1 P&ID - Hydraulics for Cargo Stripping Pump
BLV-KN501-MA-330-PID-0001-001 Rev C2 P&ID - Lubricating Oil Fill & Drains for ER Diesel Engines

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

72

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

DOCUMENTS STUDIED (continued)


BLV-KN501-MA-335-PID-0001-001 Rev C2 P&ID - ER Exhaust & Drains for Diesel Engines
BLV-KN501-MA-340-PID-0001-001 Rev C2 P&ID - E.R Diesel Filling & Transfer System
BLV-KN501-MA-340-PID-0002-002 Rev C2 P&ID - Diesel Fuel Separator System
BLV-KN501-MA-340-PID-0003-001 Rev C2 P&ID - Fuel Service System - D.G & Diesel for Cargo
Pump
BLV-KN501-MA-340-PID-0004-001 Rev C2 P&ID - Diesel Oil Fuel Tanks Quick Closing Valves
BLV-KN501-MA-340-PID-0005-001 Rev C2 P&ID - Diesel Fuel Transfer System Outside E.R
BLV-KN501-MA-345-PID-0001-001 Rev C2 P&ID - E.R Freshwater Generation
BLV-KN501-MA-345-PID-0002-001 Rev C2 P&ID - Boiler Feedwater Storage and Transfer
BLV-KN501-MA-345-PID-0003-001 Rev C2 P&ID - E.R Freshwater Storage and Transfer
BLV-KN501-MA-345-PID-0004-001 Rev C2 P&ID - E.R Freshwater System Distribution on Deck
BLV-KN501-MA-350-PID-0001-001 Rev C2 P&ID - E.R Seawater Circulation
BLV-KN501-MA-350-PID-0002-001 Rev C2 P&ID - E.R L.P Seawater Service
BLV-KN501-MA-350-PID-0005-001 Rev C2 P&ID - Upper Deck Wash System
BLV-KN501-MA-350-PID-0006-001 Rev C2 P&ID - General Seawater System in ER
BLV-KN501-MA-351-PID-0001-001 Rev C2 P&ID - ER Chlorinator and Dosing System
BLV-KN501-MA-355-PID-0002-001 Rev C2 P&ID - E.R Diesel Generators Freshwater Cooling
BLV-KN501-MA-360-PID-0001-001 Rev C1 P&ID - Sewage System
BLV-KN501-MA-360-PID-0002-001 Rev C1 P&ID - Black and Grey Water System
BLV-KN501-MA-360-PID-0002-002 Rev C1 P&ID - Black and Grey Water System
BLV-KN501-MA-371-PID-0001-001 Rev C1 P&ID - Marine Plant Air Distribution System
BLV-KN501-MA-371-PID-0002-001 Rev C1 P&ID - Marine Plant Air Distribution System
BLV-KN501-MA-725-PID-0001-001 Rev C2 P&ID - Hydraulic Control System
BLV-KN501-MA-725-PID-0002-001 Rev C2 P&ID - Hydraulic Control System
BLV-KN501-MA-725-PID-0003-001 Rev C2 P&ID - Hydraulic Control System
Firewater:
0400-110-F120-PID-016-001 Rev R1 Firefighting Distribution Main in Foam Room
0400-110-F120-PID-017-001 Rev C3 Firewater Distribution Accommodation Area
0400-110-F120-PID-018-001 Rev C2 Firewater Jockey Pumps 615-P-004 A&B
0400-110-F120-PID-019-001 Rev C2 Firewater Pumps 615-P-001/002
0400-110-F120-PID-020-001 Rev C3 Firewater Distribution Aft Area Ringmain
0400-110-F120-PID-021-001 Rev C2 Firefighting Pump & Foam System Forward
0400-110-F120-PID-023-001 Rev C2 Firewater Distribution Engine Room / Aft Area
0400-110-F120-PID-024-001 Rev C3 Firewater Distribution Fwd Area Ringmain
0400-110-F120-PID-025-001 Rev C3 Firewater Distribution Helideck & Aft Deck
0400-110-F120-PID-027-001 Rev C3 Fire Fighting Pumps System in Pump Room After and Foam
Del. On Pump Room Bottom:
0400-110-F120-PID-029-001 Rev C2 Helideck & Sterndeck Water/Foam Monitoring System
0400-110-F120-PID-030-001 Rev A2 Engine Rom High Expansion Foam System
Vendor Drawings:
ALC-KN501-PR-345-PID-0001-001 Rev A9 P&ID - Aqua 45 HW Offshore (Alfa Laval)
ALC-KN501-PR-345-PID-0001-002 Rev. A9 P&ID Softening, EDI & NaOH Softening (Alfa Laval)
AFL-KN501-PI-220-PID-0001-001 Rev C1 P&ID Flow Diagram Inert Gas System (Aalborg)
AFL-KN501-PI-220-PID-0001-002 Rev C1 P&ID Flow Diagram Delivery Line (Aalborg)
AFL-KN501-PI-220-LEG-0001 Rev A2 Symbols and Letter Code (Aalborg)

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

73

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 140

DATE REVIEWED: Tuesday, 29 October 2013

ITEM: Cargo Storage, Handling, Pumping and Offloading, including Tank Stripping, Washing, etc.
Receipt of stabilised crude oil (spec of 10.5 psi at 60 F - to be confirmed) at 2barg and 43 deg C from topsides process system at up to 57,000 bpd of oil.
Design temperature of marine systems (pipework, valves) is 60C, but tank themselves is less at 55C.
Distributed to cargo tanks by manual selection of double block valves.
Level alarms set at 95% and 98% in each cargo tank.
Pumping of crude oil via Cargo Pumps P-17-111/112/113 to Offloading Hose and Shuttle Tanker.
Transfer of up to 1800m3/hr by each pump and a maximum of two Cargo Pumps (limited by Inert Gas capacity).
Pump head 170mlc (approx. 14 barg) through 300# (PN25) system.
Flushing of off-loading hose from cargo or stripping pump to Slops Tank.
Using stripping pump to suck out oil from cargo pump P-17-111/112/113 suction and discharge lines, and from strainers S-17-211/212/213, to slops tank /
residual tank M-14.
Removal of bilge water from Cargo Pump Room through new hydraulically driven Stripping Pump or Stripping Ejectors No. 1 and 2.
Removal of water or oil from Slops Tank using Stripping Ejectors.
Pumping of produced water from topsides process plant produced water booster pump (max 6 barg) into Slops Tanks (if required).
Drains from Process Plant (closed drains and hazardous open drains from tank & pump) into Residual Tank M14.
Water from Cargo Seachest to suction of Cargo pumps for emergency filling of cargo tanks.
Slops Tank Overboard Discharge Monitoring system and gravity discharge line.
Supply of Inert Gas to Crude Pumps Cargo Oil Discharge Manifold.
Transfer of sludge from Sludge Tank M-16 to cargo tank 7P using sludge transfer pump P-4646.
Use of clean oil from one Cargo Pump P-17-111/112/113 for washing cargo tanks including Slops Tanks.
DRAWINGS AND DOCUMENTS
BLV-KN501-MA-205-PID-0001-001 Rev C1 P&ID - Cargo Oil Piping in Tanks
BLV-KN501-MA-205-PID-0002-001 Rev C2 P&ID - Cargo Oil Piping in Pump Room
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
BLV-KN501-MA-210-PID-0001-001 Rev C2 P&ID - Cargo Oil Tank Cleaning

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

74

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 140 (continued)


ITEM: Cargo Storage, Handling, Pumping and Offloading, including Tank Stripping, Washing, etc.
DEVIATION

CAUSE

CONSEQUENCE

66 Design
Change
.

Isolation valves in Cargo Oil Tank


No. 1 port and No. 1 starboard
are butterfly valves (shown as
gate valves on P&ID)

Update of as built drawing, now


consistent with isolation in other
cargo oil tanks.
No adverse impact for HAZOP
foreseen.

67 Design
Change

Isolation valve V-2000-8 in Slops


Tank overboard line is manually
operated.

No adverse consequence
foreseen for HAZOP.

68 Design
Change

Relocation of Cargo Oil Stripping


Pump line used for flushing
metering skid to downstream of
meters.

Reverse flow when flushing


through meters - No adverse
HAZOP impact foreseen (no
moving parts in meters).
Potential for reverse flow into
Cargo Oil Stripping Pumps if
double block and bleed in
flushing line is open.

DATE REVIEWED: Tuesday, 29 October 2013


SAFEGUARDS

ACTION

Tank inspection carried out in


pairs due to only a single butterfly
isolation valve in cargo tank
suction lines.

No hazard foreseen as it requires


multiple isolation valves to be in
incorrect position and would only
use this line for flushing the
meters every 3 months or more.

Lock closed the double block and


bleed valves 205-DBB-005 in the
Cargo Oil Stripping Pump line
used for flushing metering skid.

Note 18 on P&ID 0400-110F080-PID-052-001 defines


certain (combination of) marine
valves that need to be open.

Confirm at least one of the valves


listed in note 18 on P&ID 0400110-F080-PID-052-001 is locked
open at any one time.

ACTION NO: 33 ASSIGNED TO: Colin Greenlees, AMEC


69 Design
Change

Outlet line from sampling system


PSV requires certain marine
isolation valves to be open to
ensure clear flow path to tank,
and hence provision of pressure
relief.

Marine valves are not locked


open and could be closed
inadvertently, over pressure of
sampling system.

ACTION NO: 34 ASSIGNED TO: Michelle McRobbie, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

75

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 140 (continued)


ITEM: Cargo Storage, Handling, Pumping and Offloading, including Tank Stripping, Washing, etc.
DEVIATION
70 Operability
Issues

CAUSE
Cargo offloading valves
3CO02/03/04 are required to be
interlocked to restrict offloading
rate to less than 125% of the
Inert Gas supply capacity

CONSEQUENCE
If interlock is overridden, potential
to offload crude faster than inert
gas can balance pressure in
cargo tanks, cause vacuum in
cargo tanks and damage.

DATE REVIEWED: Tuesday, 29 October 2013


SAFEGUARDS

ACTION

Note 10 on P&ID 205-0003


states that valves 3CO02/03/04
are interlocked 2 out of 3.
Low pressure in cargo tank will
trip Cargo Pumps.

Clarify how cargo offloading


valves 3CO02/03/04 are
interlocked as per Note 10 on
P&ID BLV-KN501-MA-205-PID0003-001.

Cargo Pumps have been


mechanically restricted to
1500rpm so as not to exceed
downstream pipework design
pressure, and a PAHH trip has
been installed in each Cargo
Pump discharge (it is not clear
whether this PAHH trip has been
subject to SIL review).

[1] Confirm whether a SIL review


should be carried out on critical
marine systems.
[2] Check note 13 on P&ID PLVKN501-MA-205-PID-0002-001
and whether the Cargo Pumps
have internal pressure relief and
pressure trip function.

ACTION NO: 35 ASSIGNED TO: Doug McGregor, EnQuest


71 High
Pressure

Cargo Pumps discharge pressure Produced water spill into Engine


Room or Upper Deck.
can exceed downstream
pipework design pressure when
pumping produced water.

ACTION NO: 36 ASSIGNED TO: Sandeep Ghotey, EnQuest REF: [1]


ACTION NO: 37 ASSIGNED TO: Michelle McRobbie, EnQuest REF: [2]

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

76

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 150

DATE REVIEWED: Tuesday, 29 October 2013

ITEM: Inert Gas and Cargo Tank Venting, Purging, Gas Freeing
Use of Boiler flue gases (at approx 190C and 90,000kg/hr) to generate clean, cool inert gas at up to 5500m3/hr at 2040mmwc (max) and <5% oxygen.
Seawater from topsides (87m3/hr) from AMEC with back-up supply from ?? (seawater system only shutdown on ESD1 because it is required for the boilers).
Inert gas scrubber with quench cooler, scrubber section and water spray into upper section. Two 100% blowers for distribution to Deck Seal and cargo tanks
via on-line oxygen analyser and purge and excess vent valve.
Water from inert gas scrubber and rinsing water from blowers discharged overboard minimum 2.5m below waterline (due to water acidity from washing flue
gases).
Steam to boiler flue inlet gases for soot cleaning of boiler flue gas valves (short duration steam blowing only) - 8 barg steam supply from AMEC (outstanding
TQ to cover provision of all utilities).
Design pressure of inert gas scrubber and pipework 2barg / 0.2bar vacuum. Design temperature 450 inlet pipework and 65C downstream of scrubber.
Distribution of clean, cool and <5% oxygen inert gas to cargo tanks via deck seal (set at 2500mmWC with water seal and steam heating) to prevent reverse
flow of inert gas and hydrocarbon vapours back to inert gas system and P/V breaker (set at 1800mmWC & -700mmWC with water / glycol mix) and capacity
of 7670m3/hr (max fill rate from topsides 84,000bpd (560m3/hr) total fluids or 5500m3/hr from inert gas generator).
Purging: Tank has been washed, and isolated from inert gas header. Previously, inert gas was routed to bottom lines (via cargo pump manifold connection),
but now send inert gas direct into tank top via purge header until hydrocarbon content <2% (verified by manual gas sampling).
Gas Freeing: Purge header isolation valves open and cross over to inert gas header closed. Purge to vent line until air composition is breathable. Purge
header has to be displaced with inert gas at end of gas freeing.
DRAWINGS AND DOCUMENTS
BLV-KN501-MA-220-PID-0001-001 Rev C2 P&ID - Inert Gas Skid
BLV-KN501-MA-220-PID-0002-001 Rev C2 P&ID - Deck Seal - Inert Gas System
BLV-KN501-MA-220-PID-0003-001 Rev C2 P&ID - Deck Distribution - Cargo Tank Vent & Inert Gas System
Plus Vendor Diagrams:
AFL-KN501-PI-220-PID-0001-001 Rev C1 P&ID Flow Diagram Inert Gas System (Aalborg)
AFL-KN501-PI-220-PID-0001-002 Rev C1 P&ID Flow Diagram Delivery Line (Aalborg)
AFL-KN501-PI-220-LEG-0001 Rev A2 Symbols and Letter Code (Aalborg)

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

77

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 150 (continued)


ITEM: Inert Gas and Cargo Tank Venting, Purging, Gas Freeing
DEVIATION
72 Equipment
Change

DATE REVIEWED: Tuesday, 29 October 2013

CAUSE

CONSEQUENCE

SAFEGUARDS

Vent Header 300-IG-220-2140MW1 has been slightly


undersized when it was replaced
in the shipyard.

Creates small back pressure of


PV valves during tank purging
operation, so would isolate the
P/Vs and open the bypass line to
allow venting. This has
operational restraints that cannot
offload or empty slop tanks at
same time.
Blohm & Voss proposal is to
operate the system differently
from original operating
philosophy by using portable air
blowers to gas free an individual
tank rather than using the Inert
Gas header. However this
creates local hydrocarbon hazard
above the tank when the tank is
initially opened, beneath the
process deck, and also to
personnel carrying out the
operation.

The deck P/V valve in the Inert


Gas Header is always available
to protect the tanks and there is
pressure monitoring in tanks with
alarm.
P/V breaker on vent header.
Operational risk assessment prior
to gas freeing tanks and isolating
/ bypassing individual tank P/Vs
in the vent lines.

ACTION
It was agreed by the HAZOP
team that the original operating
philosophy should be retained
using the Purge Header for gas
freeing with the individual tank
P/Vs isolated.
[1] Confirm philosophy of
isolating / bypassing P/Vs (220PVV-006 to 021) on individual
tanks during gas freeing
operation.
[2] Ensure tank gas freeing
procedure reflects finalised
operating philosophy.

ACTION NO: 38 ASSIGNED TO: Sandeep Ghotey, EnQuest REF: [1]


ACTION NO: 39 ASSIGNED TO: Peter Benson, EnQuest REF: [2]

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

78

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 160

DATE REVIEWED: Monday, 28 October 2013

ITEM: Seawater System, Firewater Pumping and Distribution


Aux SW Circulation Pump P-23-311 and SW Cooling to Overboard.
SW Cooling for Diesel Generators and Steam Condensate and FW Coolers Diesel Generators
Pipe spec MW1 (10barg).
SW Cooling for Air Conditioning Plant E-4652A/B.
Engine Room Emergency Bilge Suction. General Service Pump and supply of motive water to Bilge Eductors.
ER Chlorination and Dosing System.
Firewater Jockey Pumps 615-P-004A/B. Firewater Lift / Booster Pump 615-P-001/002. Firewater Lift / Booster Pump P-6411 / P-6140. Firewater Lift /
Booster Pump P-6413 / P-6412. Supply of Firewater to Accommodation Hydrants and Sprinklers.
Firewater Ringmain aft / forward and hydrants. Helideck and Aft Firewater Ringmain.
Supply of Firewater to Deluge & Foam Skids, Deluge Valve plus foam proportioner and foam tank.
Freshwater Sprinklers for Accommodation plus Firewater Supply for Follow-on Coverage.
Deluge and Foam System Delivery from Deluge and Foam Skids.
DRAWINGS AND DOCUMENTS
BLV-KN501-MA-350-PID-0001-001 Rev C2 P&ID - E.R Seawater Circulation
BLV-KN501-MA-350-PID-0002-001 Rev C2 P&ID - E.R L.P Seawater Service
BLV-KN501-MA-350-PID-0005-001 Rev C2 P&ID - Upper Deck Wash System
BLV-KN501-MA-350-PID-0006-001 Rev C2 P&ID - General Seawater System in ER
BLV-KN501-MA-351-PID-0001-001 Rev C2 P&ID - ER Chlorinator and Dosing System
Firewater System - see main text for list of drawings.
DEVIATION
73 Design
Change

CAUSE

CONSEQUENCE

SAFEGUARDS

ACTION

Marine electrochlorination
No adverse consequence for
package has been deleted and
HAZOP foreseen.
hypochlorite will be supplied from
topsides package through new
PVC pipework.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

79

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 160 (continued)


ITEM: Seawater System, Firewater Pumping and Distribution
DEVIATION

CAUSE

DATE REVIEWED: Monday, 28 October 2013


CONSEQUENCE

SAFEGUARDS

74 Design
Change

General Service Pump discharge Previous pipework unsuitable for MW2 is suitable for 16barg
General Service Pump deadhead
/ distribution pipework to upper
deck has changed from MW1 (10 pressure of 12barg.
barg) to MW2 (16barg) spec

75 Design
Change

Several isolation valves


previously not locked open are
now marked locked open.
Isolation valves at LP/HP
interface at new Sprinkler Vessel
615-V-001 have been locked
open (by the Elastomeric Valve
615-SV-1238)

76 Design
Change

Drawing error
Line 3/4"-ST-1728-MB1-HC
connecting to forward pump room
sea chest on P&ID: 0400-110F120-PID-021-001 does not
exist.

ACTION

Previously could have


LP/HP interface at new Sprinkler
inadvertently isolated fire
Vessel 615-V-001 is now
protection systems from firewater protected.
supply.
Previous potential to
overpressure 12barg system
from 14barg system.
Remove line 3/4"-ST-1728-MB1HC connecting to forward pump
room sea chest on P&ID: 0400110-F120-PID-021-001 (but
leave screw down check valve /
isolation valve at sea chest
connection)

ACTION NO: 40 ASSIGNED TO: Colin Greenlees, AMEC

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

80

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 160 (continued)


ITEM: Seawater System, Firewater Pumping and Distribution
DEVIATION
77 Design
Change

CAUSE

DATE REVIEWED: Monday, 28 October 2013


CONSEQUENCE

SAFEGUARDS

Loss of fire fighting systems


Isolation valves 615-BUT-077
and 615-BUT-078 could be
closed by mistake isolating fire
protection systems from firewater
supply

ACTION
Isolation valves 615-BUT-077
and 615-BUT-078 should be
locked open

ACTION NO: 41 ASSIGNED TO: Colin Greenlees, AMEC


78 Design
Change

Vendor details for engine room


high expansion foam system are
now available 616-U-002

79 Design
Change

TP-615-018 and line 2"-FF-2758- This line is actually used in


MW2 on P&ID: 0400-110-F120- general sea water system and so
PID-029-001 shown to bilge
should not appear on this P&ID.
ejectors in after ship

System has not been HAZOPed.

HAZOP of engine room high


expansion foam system 616-U002 has now been carried out by
the End to End HAZOP team and
is recorded in Node 161.
Delete line 2"-FF-2758-MW2
from PID 0400-110-F120-PID029-001

ACTION NO: 42 ASSIGNED TO: Colin Greenlees, AMEC


80 Interface
Issues

Duplication of line information for Lines are shown (duplicated) on


AMEC drawing 0400-110-F120fuel supply and return to diesel
day tank 340-T-2100
PID-019-001 and BLV-KN501MA-340-PID-0005-001

Remove line details 1"-DF-6159068-AC11BS and 1"-DF-6159069-AC11BS from AMEC


drawing 0400-110-F120-PID019-001

ACTION NO: 43 ASSIGNED TO: Colin Greenlees, AMEC

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

81

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 160 (continued)


ITEM: Seawater System, Firewater Pumping and Distribution
DEVIATION
81 Operability
Issues

CAUSE

DATE REVIEWED: Monday, 28 October 2013


CONSEQUENCE

Common test line for firewater


Can only operate one firewater
pumps on forward area ring main pump during the test and jockey
pumps may have to be isolated.
using 615-PCV-1243.

SAFEGUARDS
Other firewater pumps can still
operate in the event of a fire (eg.
low pressure in ringmain).

ACTION
Confirm that firewater pump test
mode and procedure for using
615-PCV-1243 is clearly defined
in operating procedures.

ACTION NO: 44 ASSIGNED TO: Peter Benson, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

82

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 170

DATE REVIEWED: Monday, 28 October 2013

ITEM: Potable Water, Freshwater Cooling System


Generation of fresh water for boiler feedwater (higher quality than drinking water), so continuous generation of FW, but capability to bunker fresh water to
Fresh Water Tanks M-12 and M-13.
Transfer of freshwater to Tanks M-12 & M-13 forward and aft in engine room via Sterilizer U-11-151 and Neutralizer U-11-141.
Storage of fresh water (potable quality) for consumers in M-12 165m3 plus M-13 128m3, sufficient for approx 10 days.
Transfer of FW from Tanks M-12 & M-13 using Transfer Pumps P-11-131/132 at 8m3/hr each and discharge pressure of 7.4barg.
Hydrophore Tank 2m3 to provide accumulator (pressurised by control and working air supply at approx 6-7 barg) to avoid transfer pumps having to run
continuously. UV Sterilizer 345-U-2499 to treat any bacteria in water supply to drinking water quality.
Closed loop freshwater circulation through 2 x 100% Freshwater Cooling Pump Small Coolers P-24-311/312 (Aux FW pumps) at 84m3/hr each and 21mwc.
2 x 100% DG FW Coolers are cooled with SW with bypass of coolers (TCV-4).
Use of Jacket Water (heat from the diesel engines) to Freshwater Evaporator U-4461 for generating freshwater (because steam from topsides not available).
Cooling of Diesel Generator engines, lube oil.
Deaerator allows any vapour generated by high water temperature from engine cooling to vent off from pump suction.
DRAWINGS AND DOCUMENTS
BLV-KN501-MA-345-PID-0001-001 Rev C2 P&ID - E.R Freshwater Generation
BLV-KN501-MA-345-PID-0002-001 Rev C2 P&ID - Boiler Feedwater Storage and Transfer
BLV-KN501-MA-345-PID-0003-001 Rev C2 P&ID - E.R Freshwater Storage and Transfer
BLV-KN501-MA-345-PID-0004-001 Rev C2 P&ID - E.R Freshwater System Distribution on Deck
BLV-KN501-MA-355-PID-0002-001 Rev C2 P&ID - E.R Diesel Generators Freshwater Cooling
BLV-KN501-MA-355-PID-0003-001 Rev A1 P&ID - E.R. Freshwater Generator Heating

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

83

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 170 (continued)


ITEM: Potable Water, Freshwater Cooling System
DEVIATION
82 Design
Change

DATE REVIEWED: Monday, 28 October 2013

CAUSE

CONSEQUENCE

SAFEGUARDS

ACTION
[1] P&ID BLV-KN501-MA-3450002-001 is under development
and requires HAZOP.
[2] Clarify who will carry out
design development of Boiler
Feedwater Storage Tanks and
associated Boiler Make-up Water
Pumps 345-P-200A/B/C.

Boiler Feed Water Storage and


Transfer P&ID BLV-KN501-NA-3450002-001 is under development and
requires HAZOP

ACTION NO: 45 ASSIGNED TO: Michelle McRobbie, EnQuest REF: [1]


ACTION NO: 46 ASSIGNED TO: Sandeep Ghotey, EnQuest REF: [2]
83 Design
Change

Addition of 20mm top up line to ER


Heating Expansion Tank

84 Design
Change

Two lines supplying fresh water to


No adverse impact on HAZOP
CCTV screen washers on
foreseen.
accommodation on P&ID BLV-KN501-MA-345-PID-0004-001 have been
removed because CCTV no longer
required

85 Design
Change

Isolation valve added to fresh water


supply to Inert Gas skid and check
valves added to potable water supply
to pump room (this is a Class
requirement).

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Intermittent use for top up only.


No adverse consequence
foreseen for HAZOP.

No adverse impact on HAZOP


foreseen.

Page:

- with P&IDs

84

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 180

DATE REVIEWED: Tuesday, 29 October 2013

ITEM: Diesel Bunkering, Storage, Transfer and Purification


Receipt of diesel from supply boat, bulk storage, transfer, purification for firewater pump diesel drivers and emergency power generators, supply to
consumers, including steam boilers (if required).
DRAWINGS AND DOCUMENTS
BLV-KN501-MA-340-PID-0001-001 Rev C2 P&ID - E.R Diesel Filling & Transfer System
BLV-KN501-MA-340-PID-0002-002 Rev C2 P&ID - Diesel Fuel Separator System
BLV-KN501-MA-340-PID-0003-001 Rev C2 P&ID - Fuel Service System - D.G & Diesel for Cargo Pump
BLV-KN501-MA-340-PID-0004-001 Rev C2 P&ID - Diesel Oil Fuel Tanks Quick Closing Valves
BLV-KN501-MA-340-PID-0005-001 Rev C2 P&ID - Diesel Fuel Transfer System Outside E.R
No significant deviations identified for this Item

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

85

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 190

DATE REVIEWED: Tuesday, 29 October 2013

ITEM: Bilge, Ballast, Sounding and Gauging, Drains & Sewage


Removal of bilge liquids from Bilge Wells in Engine Room using Aux Bilge Pump P-15-111 through Bilge Water Filter Separator S-15-121 to Sludge Tank Oil
Section M-16. Separation of oil to less than 15ppm from bilge water prior to dumping overboard by Bilge Water Filter Separator S-15-121.
Level sensing for sounding, gauging and draft, and associated control system.
Ballast system required for vessel stability during different operating conditions and sea states in order to keep the vessel's hull within it's safe operating
envelope.
Drains collection for oil sources, eg. diesel, crude oil, fuel and lube oil filters, drains, etc. routed to Sludge Tank Oil / Water compartment M-17.
Exhausts & ducting for: Diesel Generators A-35-111/112/113; Fire Pump Diesel Engine 615-D-2002; Diesel Engine for Cargo Pump D-17-131; Observation
Tank T-30-161; and Vent from Atmospheric Drain Tank and Atmospheric Condenser.
Storage of sewage, pumping through new macerator unit to overboard discharge.
DRAWINGS AND DOCUMENTS
BLV-KN501-MA-225-PID-0001-001 Rev C2 P&ID - Ballast & Stability Control
BLV-KN501-MA-230-PID-0001-001 Rev C2 P&ID - Drain Arrangement Oil
BLV-KN501-MA-230-PID-0002-001 Rev C2 P&ID - Drain Arrangement Water
BLV-KN501-MA-230-PID-0003-001 Rev C2 P&ID - Drain Arrangement Oil Water
BLV-KN501-MA-230-PID-0004-001 Rev C2 P&ID - Sludge Oil Water Tank Arrangement
BLV-KN501-MA-230-PID-0005-001 Rev C1 P&ID - Heliplatform Scuppers and Drains
BLV-KN501-MA-235-PID-0001-001 Rev C2 P&ID - Sounding, Gauging & Draft
BLV-KN501-MA-235-PID-0002-001 Rev C2 P&ID - Sounding, Gauging & Draft
BLV-KN501-MA-240-PID-0001-001 Rev C2 P&ID - Bilge System in ER
BLV-KN501-MA-240-PID-0002-001 Rev C2 P&ID - Bilge System Forward
BLV-KN501-MA-240-PID-0003-001 Rev C2 P&ID - Bilge System in After Ship
BLV-KN501-MA-335-PID-0001-001 Rev C2 P&ID - ER Exhaust & Drains for Diesel Engines
BLV-KN501-MA-360-PID-0001-001 Rev C1 P&ID - Sewage System

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

86

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 190 (continued)


ITEM: Bilge, Ballast, Sounding and Gauging, Drains & Sewage
DEVIATION
86 Design
Change

CAUSE

CONSEQUENCE

DATE REVIEWED: Tuesday, 29 October 2013


SAFEGUARDS

Flame arrestors shown in


Potential for sparks / flame / hot
exhausts from Diesel Generators shoot particles out of exhaust
and aft Firewater Pump Diesel
create ignition source.
Driver on P&ID BLV-KN-501-MA335-PID-0001-001 are not
installed.

ACTION
Clarify (Class) requirement for
flame screen/spark arrestor (X35-111/112/113 and X-17131/132) in exhausts from Diesel
Generators and aft Firewater
Pump Diesel Driver

ACTION NO: 47 ASSIGNED TO: Michelle McRobbie, EnQuest


87 Design
Change

New P&ID Black and Grey Water Drawing shows source of black
and grey water into sewage
system on P&ID: BLV-KN501MA-360-PID-0002-001
tanks.
Although the previous HAZOP
only reviewed a "red-line markup" drawing, no adverse
consequences were foreseen
with the new arrangement.

Lines are sloped and segregated


to avoid reverse flow. Headers
have vent.

88 Design
Change

Sewage Pump P-11-211 is not


installed.

Sewage Ejector with supply from


General Service Pumps can be
used as alternative to Sewage
Macerator Pump (although
sewage would not be
macerated).
Sewage Tanks can also be
drained directly overboard (when
offshore).

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Reduced redundancy but


Sewage Macerator Pump 360-U2000 considered to be sufficiently
robust / reliable.

Page:

- with P&IDs

87

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 190 (continued)


ITEM: Bilge, Ballast, Sounding and Gauging, Drains & Sewage
DEVIATION

CAUSE

DATE REVIEWED: Tuesday, 29 October 2013


CONSEQUENCE

89 Design
Change

System 725 hydraulic control


system.

Some valves have been removed and


hydraulic systems upgraded. No
adverse consequence for HAZOP
foreseen.

90 Equipment
Change

Bilge Water Filter Separator vendor details have been added


to P&ID: BLV-KN501-MA-240PID-0001-001 (in the HAZOP
only an outline schematic was
provided). In addition, bilge water
has been redirected via Bilge
Holding Tank.

The Aux Bilge Pump transfers bilge


fluids into the Bilge Holding Tank and
suction taken from Bilge Holding Tank
to Bilge Water Filter Separator using
pump supplied with separator
package.
Separator package is standard Class
approved unit and complies with
MARPOL.
Location of separator unit may creates
low suction pressure for package
pump due to elevation and so may be
unable to pump out Bilge Holding
Tank.

SAFEGUARDS

ACTION

Confirm location of Bilge Water


Filter Separator unit S-15-121
relative to Bilge Holding Tank M20 to ensure pump will operate
satisfactorily and confirm whether
a low level switch is required on
240-LS-010 to stop the pump to
prevent it running dry.

ACTION NO: 48 ASSIGNED TO: Michelle McRobbie, EnQuest


91 Interface
Issues

Operation of bilge ejectors using


firewater as motive fluid.

Firewater system pressure is 10barg at


ring main on process deck, therefore
pressure could exceed 12 barg at
ejectors.

Confirm design pressure of Bilge


Ejectors X-15-141/142 for use
with firewater as motive fluid.

ACTION NO: 49 ASSIGNED TO: Michelle McRobbie, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

88

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 190 (continued)


ITEM: Bilge, Ballast, Sounding and Gauging, Drains & Sewage
DEVIATION
92 Operability
Issues

CAUSE
Removal of one Sewage Tank
(port or starboard) from service
for repair or inspection.

CONSEQUENCE
Approx. half of (starboard or port
side) cabins and hospital may be
out of use.

DATE REVIEWED: Tuesday, 29 October 2013


SAFEGUARDS

ACTION
Consider cross over line between
port and starboard Sewage
Tanks M15 and M23.

ACTION NO: 50 ASSIGNED TO: Michelle McRobbie, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

89

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 200

DATE REVIEWED: Tuesday, 29 October 2013

ITEM: New Marine Systems not Previously HAZOPed


System 255-325-355-360-371 have new P&IDs: for HP & LP hydraulic system for Aft Offloading Winches; Hydraulics for pump skids (interconnecting
pipework between vendor supplied packages); ER Freshwater Cooling; Grey & Black Water; and Marine Plant Air distribution.
DRAWINGS AND DOCUMENTS
BLV-KN501-MA-255-PID-0001-001 Rev C1 P&ID - HP Hydraulic System for Aft Offloading Winches
BLV-KN501-MA-255-PID-0002-001 Rev C1 P&ID - LP Hydraulic System for Aft Offloading Winches
BLV-KN501-MA-325-PID-0001-001 Rev C1 P&ID - Hydraulics for Crude Oil Pump Skid
BLV-KN501-MA-325-PID-0002-001 Rev C1 P&ID - Hydraulics for Fire Pump Skid
BLV-KN501-MA-325-PID-0003-001 Rev C1 P&ID - Hydraulics for Cargo Stripping Pump
BLV-KN501-MA-355-PID-0002-001 Rev C2 P&ID - E.R Diesel Generators Freshwater Cooling
BLV-KN501-MA-360-PID-0002-001 Rev C1 P&ID - Black and Grey Water System
BLV-KN501-MA-360-PID-0002-002 Rev C1 P&ID - Black and Grey Water System
BLV-KN501-MA-371-PID-0001-001 Rev C1 P&ID - Marine Plant Air Distribution System
BLV-KN501-MA-371-PID-0002-001 Rev C1 P&ID - Marine Plant Air Distribution System
DEVIATION
93 Design
Change

CAUSE

CONSEQUENCE

System 255 HP and LP hydraulic System was not HAZOPed (P&ID


system for aft offloading winches does not provided details of
hydraulic pumping or winch drive
/ control), but should be subject
to review by competent person to
ensure it satisfies original
operating philosophy.

SAFEGUARDS

ACTION
Ensure that a review of the HP &
LP hydraulic system for Aft
Offloading Winches is carried out
by a competent person to ensure
it satisfies original operating
philosophy and EnQuest
requirements.

ACTION NO: 51 ASSIGNED TO: Michelle McRobbie, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

90

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 200 (continued)


ITEM: New Marine Systems not Previously HAZOPed
DEVIATION

CAUSE

DATE REVIEWED: Tuesday, 29 October 2013


CONSEQUENCE

94 Design
Change

System 325: hydraulics for crude New P&IDs showing interface


oil pump skid, fire pump skid and piping between hydraulic power
cargo stripping pump.
units and hydraulic tanks and
equipment.
The overall systems were
HAZOPed in the Marine HAZOP,
this new drawing shows the
interface pipework.

95 Design
Change

Tag numbers for Ship Service


Diesel Generators has been
changed from D to A in red line
mark up on P&ID: BLV-KN501MA-325-PID-0003-001.

SAFEGUARDS

Potential confusion that lube oil is


gong to alternator rather than
diesel engine.

ACTION

Check red line change of Ship


Service Diesel Generators tag
number from D to A on P&ID:
BLV-KN501-MA-325-PID-0003001.

ACTION NO: 52 ASSIGNED TO: Sandeep Ghotey, EnQuest


96 Design
Change

System 371 Marine Plant Air


Distribution system.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Some dead legs appear to have


been left and possibility of liquid
condensing in pipework.
Potential for corrosion.

Plant Air is dried so corrosion in


dead legs not considered to be a
significant concern.
Any condensation would be
blown out when initially opening
isolation valve.

Page:

- with P&IDs

91

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 200 (continued)


ITEM: New Marine Systems not Previously HAZOPed
DEVIATION
97 Design
Change
.

CAUSE

DATE REVIEWED: Tuesday, 29 October 2013


CONSEQUENCE

HPU packages for riser ESDVs


P&IDs have not been viewed for
and LP & HP hydraulic supply for these systems but may be
subsea control (valves).
available.

SAFEGUARDS

ACTION
Identify whether the HPU
packages for riser ESDVs and LP
& HP hydraulic supply for subsea
control (valves) have been
subject to HAZOP review, and if
not carry out a HAZOP.

ACTION NO: 53 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

92

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Appendix C - End to End HAZOP P&IDs


Note: All P&IDs have not been included due to the large number, with the exception of
Marine System P&IDs which contain some red line mark-ups.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

93

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

94

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

95

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

96

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

97

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

98

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

99

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

100

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

101

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

102

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

103

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

104

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

105

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

106

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

107

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

108

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

109

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

110

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

111

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

112

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

113

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

114

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

115

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

116

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

117

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

118

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

119

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

120

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

121

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

122

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

123

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

124

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

125

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

126

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

127

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

128

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

129

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

130

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

131

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

132

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

133

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

134

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

135

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

136

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

137

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

138

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

139

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

140

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

141

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

142

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

143

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

144

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

145

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

146

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Appendix D - Additional HAZOP Worksheets & HAZOP P&IDs


Conventional HAZOP was carried out on three new systems that had not previously been
HAZOPed:
^

Closed Drains Systems (with new tie-ins from Crude Oil Metering and Sampling
Facilities and Steam Boiler Package Hazardous Open Drains);
Engine Room Steam Heating System;
High Expansion Foam System for Engine Room.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

147

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

EnQuest Knightsbridge Project


CLIENT:

EnQuest

PROJECT NO:

A3304

PROJECT:

EnQuest Producer FPSO

DETAILS:

Closed Drains System

MEETING DATES: Thursday 24th Oct 2013


TEAM MEMBERS
Independent Chairman, Paul Caldwell (Anatec)
Scribe, Steven Armstrong (Anatec)
EnQuest Knightsbridge Process Engineer, Sandeep Ghotey
EnQuest Process TA, Matt Hastings
EnQuest Operations Process Engineer, Peter Benson
EnQuest Production Supervisor, Malcolm Robertson
AMEC Process Engineer, Ali Al-Khayat
AMEC Controls & Instrumentation, Richard Auld
ACTION RESPONSES TO: Paul Renwick, Technical Safety Engineer, AMEC
DOCUMENTS STUDIED
0400-110-F100-PID-006-001 Rev C2 P&ID Flare KO Drum V-5370
0400-110-F100-PID-019-001 Rev C1 Swivel Drains Recuperation System
0400-110-F070-PID-014-001 Rev C1 Centralised Sample Collection
0400-110-F100-PID-001-001 Rev C3 CSU P&ID Closed Drains Collection 1 of 2
0400-110-F100-PID-001-002 Rev C3 CSU P&ID Closed Drains Collection 2 of 2
0400-110-F080-PID-045-001 Rev C2 Topside Interface with Marine Systems
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

148

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 71

DATE REVIEWED: Thursday, 24 October 2013

ITEM: Closed Drains


Process Closed Drains from vessels, etc., to Closed Drains Collection Header, then to Residue Tank No. 14 (in hull).
Transfer of liquids from Hazardous Open Drains Vessel 531-V-001 to Residue Tank No. 14 (in hull) via Hazardous Open Drain Pumps 531-P-001A/B (design
pressure FV/18barg) and Closed Drains header.
New line from Boiler Package Hazardous Open Drains Pumps and new line from metering and sampling facilities connecting into piping on upper deck.
Oily water condensate design pressure of 150# (7barg) and temperature -20/118C.
DRAWINGS AND DOCUMENTS
0400-110-F100-PID-001-001 Rev C3 CSU P&ID Closed Drains Collection 1 of 2
0400-110-F100-PID-001-002 Rev C3 CSU P&ID Closed Drains Collection 2 of 2
0400-110-F080-PID-045-001 Rev C2 Topside Interface with Marine Systems
BLV-KN501-MA-205-PID-0001-001 Rev C2 P&ID - Cargo Oil Piping in Tanks
BLV-KN501-MA-205-PID-0003-001 Rev C2 P&ID - Cargo Oil Piping on Upper Deck
DEVIATION
98

Flow
No

CAUSE
Normal case no draining of
liquids

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

CONSEQUENCE

SAFEGUARDS

ACTION

Closed Drain header will drain to


cargo deck piping and should
self drain from there into Residue
tank (depending on trim of
vessel).
Potential for liquids to lie in
pipework, but unlikely to remain
for long period of time due to
fairly regular flow of liquids.
No adverse consequence
foreseen.

Page:

- with P&IDs

149

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 71 (continued)
ITEM: Closed Drains
DEVIATION
99

Flow
No

DATE REVIEWED: Thursday, 24 October 2013


CAUSE

CONSEQUENCE

Marine valve closed

SAFEGUARDS

Unable to drain production


vessels prior to maintenance.
PSVs on sea water system
unable to vent pressure and
potential burst of topsides
vessels.
Potential to overpressure marine
pipework (MT2 spec).

ACTION
[1] Ensure all valves in main
route to Residual Tank M14 are
locked open (ie. valves on P&ID
BLV-KN501-MA-205-PID 0003001).
[2] In the event Residual Tank
M14 is unavailable and closed
drains are routed to Cargo Tank
No. 7 port, the isolation valves in
the routing line to Cargo Tank
no. 7 port should be locked
open.

ACTION NO: 54 ASSIGNED TO: Sandeep Ghotey, EnQuest REF: [1]


ACTION NO: 55 ASSIGNED TO: Sandeep Ghotey, EnQuest REF: [2]
100 Flow
No

Check valve in Closed Drain


lines (on P&ID BLV-KN501-MA205-PID 0003-001) stuck closed

As previous entry, potential for


overpressure of topsides
equipment protected by PSVs or
of MT2 pipework.

Note: check valves may be


required to prevent reverse flow
from Residual and No.7 port
tanks (inert gas).

Review requirement for check


valves in Closed Drain pipework
on upper deck to Residual Tank
M14 (and No. 7 port), due to
potential for blocking relief from
sea water system PSVs.

ACTION NO: 56 ASSIGNED TO: Sandeep Ghotey, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

150

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 71 (continued)
ITEM: Closed Drains
DEVIATION

DATE REVIEWED: Thursday, 24 October 2013


CAUSE

CONSEQUENCE

SAFEGUARDS

101 Flow
No

Blockage from debris coming


down the drain system (eg sand
from production system or
construction / maintenance
materials left in vessels).

Unable to drain vessels or


provide PSV overpressure relief
in seawater system.

It is a closed system so gloves, etc. will


not enter through tun dishes or drip
trays (but could be left in vessels after
maintenance).
Nominal sand from the wells (specified
in the basis of design).
Rodding points provided.

102 Flow
More/High

Several PSVs opening, Boiler


Hazardous Drain Pump
operating, vessels being drained
for maintenance.

Large flow of liquid through


drains, possible backing up in
drain vessels

Sizing of pipework considered to be


adequate.

103 Flow
Reverse

Inert gas in Residue Tank 14 (or Inert gas or oily water back into
Closed Drain header
Cargo Tank No. 7 port) or
reverse flow from offloading hose
flushing operation

104 Pressure
More/High

PSVs in seawater system open

High pressure / flow into drains


system, see previous Flow More,
above.

105 Pressure
More/High

Maintenance drains opened on


pressurised vessel by mistake

Process system open to Closed


Drain header

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

ACTION

Closed Drain system is a closed


system, self-draining to the tanks, and
is designed for 7 barg.

Maintenance drain is isolated by a


spectacle blind (except on level bridles
due to low operating pressures), so
cannot swing spectacle blind before
system is depressurised.

Page:

- with P&IDs

151

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 71 (continued)
ITEM: Closed Drains

DATE REVIEWED: Thursday, 24 October 2013

DEVIATION

CAUSE

CONSEQUENCE

SAFEGUARDS

106 Temperature
More/High

Process fluids at 80C (possibly


up to 105C) from well fluids into
Residue Tank or Cargo Tank
No. 7 port

Potential damage to tank lining


and anodes if temperature >60C.
510-PSV-1098/1099 providing
blocked outlet protection for
Dehydrator Produced Water
Recycle Pumps currently have a
duty of 85C max.

Unlikely to be manually draining


vessels that are hot.
Some cooling provided in Closed
Drain header and piping on
upper deck due to ambient
temperature and heat sink of
volume of liquids in Residue
Tank.

107 Level
More/High

High level in Residue tank M14

Overflow of drains liquids to


Slops Tank or other cargo tanks
via inert gas line.
If unable to empty Residue Tank
then eventually production would
have to be stopped.

High level alarm (at 95% and


98%) in Residue Tank (and other
marine cargo tanks). Alarms are
displayed on cargo control panel
in control room.

108 Composition
General

Oil, water and production


chemicals

No adverse consequence
foreseen for MT2 pipework.

109 Maintenance
General

Blockage of drain lines requires Rodding points provided, but


clearing
potential for high pressure in
drains system if PSV opens (see
Flow No, previous entry) hazard to personnel when
opening rodding point.

ACTION

Provide suitable isolation on


Closed Drain header for
connecting flushing hose

ACTION NO: 57 ASSIGNED TO: Ali Al-Khayat, AMEC

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

152

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

153

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

154

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

155

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

156

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

EnQuest Knightsbridge Project


CLIENT:

EnQuest

PROJECT NO:

A3304

PROJECT:

EnQuest Producer FPSO

DETAILS:

Engine Room Steam Heating

MEETING DATES: Monday 28th October 2013


TEAM MEMBERS
Independent Chairman, Paul Caldwell (Anatec)
Scribe, Steven Armstrong (Anatec)
EnQuest Knightsbridge Process Engineer, Sandeep Ghotey
EnQuest Operations Process Engineer, Peter Benson
EnQuest Marine Systems Engineer, Michelle McRobbie
EnQuest Process TA, Matt Hastings
EnQuest Instruments Engineer, Doug McGregor
EnQuest Steam Engineer, Donald Paterson
EnQuest Mechanical Engineer, John Chadwick
Parsons Process Engineer, Neil Wise
AMEC Process Engineer, Colin Greenlees
ACTION RESPONSES TO: Paul Renwick, AMEC Technical Safety
DOCUMENTS STUDIED
HHO-KN501-HV-375-DWG-0174-001 Rev A1 P&ID Heating System Engine Room
BLV-KN501-MA-315-PID-0002-001 Rev C2 P&ID ER 8barg Steam System

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

157

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 121

DATE REVIEWED: Monday, 28 October 2013

ITEM: ER Steam Heat Exchanger


Space heating in engine room.
Supply of steam at 8 barg to deliver 360kW to closed loop water heating circuit heat exchanger.
Condensate return to ER Observation Tank.
Design pressure 8barg, design temperature 175C.
Steam flow up to 595kg/h.
DRAWINGS AND DOCUMENTS
HHO-KN501-HV-375-DWG-0174-001 Rev A1 P&ID Heating System Engine Room
BLV-KN501-MA-315-PID-0002-001 Rev C2 P&ID ER 8barg Steam System
DEVIATION

CAUSE

CONSEQUENCE

110 Flow
No

Upstream isolation valve or inlet No heating in engine room


temperature control valve closed, affects personnel working in the
space, condensation in
or loss of steam supply.
equipment and possible freezing
in extremely cold weather.

111 Flow
No

Outlet valve closed, steam trap


blocked.

Heat exchanger becomes


flooded.
No heating, as above.

112 Flow
No

No water circulating through


tubes

No heat demand and steam


does not condense.
Steam into condensate system
downstream.

SAFEGUARDS

ACTION

May be an alarm (low


temperature) if local control
panel is linked to ICSS.
Frequently manned area so
personnel will observe that the
heating system is not working.

Consider requirement for steam


trap in condensate outlet from
ER Steam Heat Exchanger.

ACTION NO: 58 ASSIGNED TO: Michelle McRobbie, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

158

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 121 (continued)


ITEM: ER Steam Heat Exchanger
DEVIATION

DATE REVIEWED: Monday, 28 October 2013

CAUSE

CONSEQUENCE

SAFEGUARDS

113 Flow
Less/Low

Less steam due to other


consumers

Less space heating.

Local control system will try to


maintain room temperature by
opening steam inlet valve.

114 Flow
More/High

Steam trap fails.

High flow rate of steam through


heat exchanger, steam into ER
Observation Tank.

Inlet control valve will open to


maintain steady temperature in
water circuit.
80mm vent on ER Observation
Tank and 65mm steam inlet line.

115 Flow
More/High

Inlet control valve goes fully


open.

Feed water temperature would


increase up to saturation
temperature of the steam
(approx 175C). Potential for
closed loop circulation pressure
to increase to 3barg.

PSV on Expansion Vessel set at


3barg.

116 Flow
Reverse

Leak in tube

Steam into closed cooling water


loop. Water into exchanger shell
side.

Temperature monitoring of
system.
PSV on Expansion Vessel set at
3barg.

117 Pressure
More/High

Water inlet valves 11 & 13


closed.

Blocked in section of Steam Heat


Exchanger tubes. If steam
passing through exchanger then
thermal expansion and failure of
pipework or tubes.

ACTION

Either lock open valves 11 & 13


or provide thermal relief for
Steam Heat Exchanger tubes.
Note: these valves may not be
required.

ACTION NO: 59 ASSIGNED TO: Michelle McRobbie, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

159

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 121 (continued)


ITEM: ER Steam Heat Exchanger
DEVIATION
118 Isolation
General

DATE REVIEWED: Monday, 28 October 2013

CAUSE
Maintenance of Steam Heat
Exchanger

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

CONSEQUENCE
Single isolation valve provided

SAFEGUARDS

ACTION

Single isolation valve is normally


considered sufficient for 10barg
steam systems

Page:

- with P&IDs

160

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 122

DATE REVIEWED: Monday, 28 October 2013

ITEM: Heating Water Loop for Engine Room


Closed loop hot water circulation from Steam Heat Exchanger to two Water Heaters.
Expansion vessel and PSV set at 3barg.
Dual circulation pumps.
Inlet temperature to heat exchanger is 70C outlet temperature 90C. Design pressure 3barg.
DRAWINGS AND DOCUMENTS
HHO-KN501-HV-375-DWG-0174-001 Rev A1 P&ID Heating System Engine Room
DEVIATION
119 Flow
No

CAUSE

CONSEQUENCE

Circulation pump tripped or


isolation valve closed

No heating of engine room.


Possible boiling in tubes,
increase in system pressure.

SAFEGUARDS

ACTION

Standby Circulation pump is [1] Confirm tubes in Steam Heat


available.
Exchanger are designed for 175C.
PSV set at 3 barg.
[2] Confirm relief valve (item 10)
capacity is suitable for thermal relief
requirements.

ACTION NO: 60 ASSIGNED TO: Michelle McRobbie, EnQuest REF: [1]


ACTION NO: 61 ASSIGNED TO: Michelle McRobbie, EnQuest REF: [2]
120 Flow
Less/Low

Water Heater tubes become


blocked

Less heating to engine room,


reduced water circulation.

121 Flow
More/High

Both Circulation pumps


operating

Higher circulation through closed


loop.

122 Flow
Reverse

One Circulation pump operating,


the other pump on standby

Reverse flow through standby


pump.

Consider providing check valve in


each Circulation pump discharge.

ACTION NO: 62 ASSIGNED TO: Michelle McRobbie, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

161

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 122 (continued)


ITEM: Heating Water Loop for Engine room
DEVIATION
123 Pressure
Less/Low

DATE REVIEWED: Monday, 28 October 2013

CAUSE
Leak from system

CONSEQUENCE
Loss of heating medium, reduced
heating of Engine Room.

SAFEGUARDS

ACTION

Temperature and
pressure instrumentation.

Provide connection for filling


Engine Room Steam Heating
system.

PSV set at 3barg.

See action #61

ACTION NO: 63 ASSIGNED TO: Michelle McRobbie, EnQuest


124 Pressure
More/High

Tube failure and steam control 8barg into 3barg system


valve failure, exposure of
exchanger and heating water
circulation loop to 8barg from
upstream steam system
(double jeopardy scenario).

125 Temperature
More/High

Bypassing Water Heaters


through 3 way valve

Temperature in closed loop system


increases and temperature controller
closes Steam Heat Exchanger steam
inlet valve.
Reduced heating of Engine Room.

Clarify overall Engine Room


heating philosophy and identify
any alarm and trips.

ACTION NO: 64 ASSIGNED TO: Michelle McRobbie, EnQuest


126 Loss of
Services
General

Air supply to Water Heaters from within Engine Room, or


new or existing ducting from
outside?

Source of air is not identified.


Potential to draw air from outside the
Engine Room with hydrocarbons.

Clarify source of air, air fan


requirements and whether there
is a requirement for gas
detector(s) in the fresh air
intakes.

ACTION NO: 65 ASSIGNED TO: Michelle McRobbie, EnQuest

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

162

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

163

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

164

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

EnQuest Knightsbridge Project


CLIENT:

EnQuest

PROJECT NO:

A3304

PROJECT:

EnQuest Producer FPSO

DETAILS:

High Expansion Foam System for Engine Room

MEETING DATES: Monday 28th October 2013


TEAM MEMBERS
Independent Chairman, Paul Caldwell (Anatec)
Scribe, Steven Armstrong (Anatec)
EnQuest Knightsbridge Process Engineer, Sandeep Ghotey
EnQuest Operations Process Engineer, Peter Benson
EnQuest Marine Systems Engineer, Michelle McRobbie
EnQuest Process TA, Matt Hastings
EnQuest Instruments Engineer, Doug McGregor
EnQuest Steam Engineer, Donald Paterson
EnQuest Mechanical Engineer, John Chadwick
Parsons Process Engineer, Neil Wise
AMEC Process Engineer, Colin Greenlees
AMEC Technical Safety Engineer, Paul Renwick
ACTION RESPONSES TO: Paul Renwick, AMEC Technical Safety
DOCUMENTS STUDIED
0400-110-F120-PID-027-001 Rev C3 Fire Fighting Pumps System in Pump Room After and Foam
Del. On Pump Room Bottom
1307-M20/C01/001 P&ID: Proposed Inside Air High Expansion Foam System for Engine Room

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

165

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 161

DATE REVIEWED: Monday, 28 October 2013

ITEM: High Expansion Foam System for Engine Room


Storage of 3000L to supply 2484m3/minute of 1% concentrate foam to Engine Room deluge nozzles.
Design pressure 14barg Design temperature -7C/40C
DRAWINGS AND DOCUMENTS
0400-110-F120-PID-027-001 Rev C3 Fire Fighting Pumps System in Pump Room After and Foam Del. On Pump Room Bottom
1307-M20/C01/001 P&ID: Proposed Inside Air High Expansion Foam System for Engine Room
DEVIATION
127 Flow
No

CAUSE
Loss of fire water supply,
isolation valve closed or 3 way
ball valve in incorrect position
and foam sent to test
line/connection.

CONSEQUENCE
No foam to engine room when
required, escalation of fire.

SAFEGUARDS

ACTION

Firewater supply isolation valves


are locked open.
Two sources of supply from fire
water system.

Ensure 3 way ball valve (Blaze


Item 09) is routed to Engine
Room rather than foam test line.

ACTION NO: 66 ASSIGNED TO: Paul Renwick, AMEC (for Blaze)


128 Flow
No

Isolation valve to foam tank is


closed.

No foam to in-line foam inductor,


fail to fill engine room with high
expansion foam and quench fire.

Isolation valve (Blaze Item 08)


between foam tank and foam
inductor should be locked open.

Potential for escalation.


ACTION NO: 67 ASSIGNED TO: Paul Renwick, AMEC (for Blaze)

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

166

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 161 (continued)


ITEM: High Expansion Foam System for Engine Room
DEVIATION

CAUSE

DATE REVIEWED: Monday, 28 October 2013


CONSEQUENCE

SAFEGUARDS

129 Flow
Less/Low

Isolation valve in drain line


open.

Isolation valve (Blaze Item


Less flow of firewater to in-line
foam inductor and hence foam to 03) is locked closed.
Engine Room.

130 Flow
Misdirected

Inadvertent opening of
isolation valve in bypass
around deluge valve.
Inadvertent opening of deluge
valve eg. spurious signal from
fire and gas system.

Fill engine room with high


expansion foam, with potential
hazard to personnel and
possible damage to equipment.
Difficulty for personnel to escape
from Engine Room (use of
vertical ladders, stairways).
The fire risk in the Engine Room
may be perceived to be low, but
was not assessed in the HAZOP.

Personnel would be able


to breathe if immersed in
high expansion foam, but
visibility would be reduced
and surfaces may be
slippery.
Isolation valve (Blaze Item
04) is CSC.

ACTION

[1] Isolation valve (Blaze Item 04) in


bypass around deluge valve should be
locked closed.
[2] Due to hazards to personnel in the
event of inadvertent release of high
expansion foam in Engine Room, consider
making the fire and gas signal permissive
only and manual activation of the foam
system on the approval of OIM. Note: a
risk assessment balancing the fire risk in
the Engine Room with the potential risk to
personnel in the event of inadvertent
release of the high expansion foam
system should be carried out to support
any such manual override of the automatic
foam release (as currently configured).

ACTION NO: 68 ASSIGNED TO: Paul Renwick, AMEC (for Blaze) REF: [1]
ACTION NO: 69 ASSIGNED TO: Peter Benson, EnQuest REF: [2]

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

167

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

NODE: 161 (continued)


ITEM: High Expansion Foam System for Engine Room
DEVIATION
131 Pressure
More/High

DATE REVIEWED: Monday, 28 October 2013

CAUSE

CONSEQUENCE

Deluge valve open

SAFEGUARDS

ACTION
615-PIT-XXX (Blaze Item 18)
provides signal to fire and gas
system - this should also have a
high pressure alarm function to
indicate when deluge valve is
open.

Pressure increases downstream


of deluge valve. This could be
used to confirm (inadvertent)
opening of the deluge valve to
warn operators.

ACTION NO: 70 ASSIGNED TO: Paul Renwick, AMEC (for Blaze)


132 Level
Less/Low

Loss of foam from Foam Tank,


or not filled correctly. No means
of visually checking Foam Tank
contents (other than removing
hatch and taking sample).

No foam to Engine Room when


615-LS-XXX (Blaze Item 20) is
required. Potential for escalation expected to have a low alarm.
of fire.
Regular sampling of Foam Tank
contents.
Foam Tank to be filled by
vendor.

Confirm that a level gauge or


local level indication for the
Foam Tank will be provided.

ACTION NO: 71 ASSIGNED TO: Paul Renwick, AMEC (for Blaze)


Engine Room not filled with high
133 Composition Degradation of foam in Foam
General
Tank, or filled with incorrect foam expansion foam, potential
escalation of fire.
type (eg AFFF instead of high
expansion foam).

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Regular sampling of Foam Tank


contents.

Page:

- with P&IDs

168

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

169

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

170

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

www.anatec.com

Page:

- with P&IDs

171

Project:

A3304

Client:

EnQuest

Title:

End to End HAZOP EnQuest Producer FPSO

www.anatec.com

Ambiguous;
Unsupported by evidence;
Technically unsound;
Based on actions to be made in the future;
Based on conclusions by unnamed persons;
Based on assumptions that are not stated in the response;
Based entirely on standard APR RP 14C safety analysis.

or if they propose work for other persons to do or otherwise leave the action open or
unresolved.
Attachments should be used where they make the response clearer. References should be
given in full for any reports, standards, calculations or drawings used in the response.
Responses should use equipment tag numbers, document reference numbers and document
revision numbers, if possible, to avoid confusion.
However, responses to actions regarding procedures to be developed in the future can be
closed out if the actionee has demonstrated how the procedure will be developed to
incorporate the HAZOP action and where he has identified the document reference for the
procedure.
3.5 Approving Actions
The AMEC Knightsbridge technical safety engineer will co-ordinate the close-out of all
HAZOP Review actions using the PiSYS action tracking management system. This is a webbased system, to which all nominated action parties have access. The PiSYS system is set up
to meet project and AMEC requirements for the workflow and approval chain.
Responses to actions will require approval by:
_

The chairman - to confirm that the response meets the intent of the Review team when
they raised the action;
The project engineer - to confirm that the project will adopt the activity proposed by
the response as part of the project workscope; and
Knightsbridge project manager to confirm EnQuest approval.

Where there is not agreement that the response should be approved, the Engineering Manager
will determine approval for adoption by the project, or will appoint a suitable technical
authority to resolve any disputed issue.

Date:

31st October 2013

Doc:

EnQuest Producer FPSO End to End HAZOP Rev 00

Page:

- with P&IDs

17

Вам также может понравиться