Академический Документы
Профессиональный Документы
Культура Документы
: P 10,000,000.00
: 120 Calendar Days
: September 15, 2014
: January 15, 2014
ANA SY
Owner
TABLE OF CONTENT
l
ll
lll
Project Details
IV
VI
VI
VII
VII
VIII
IX
Safety Procedures
XI
It is general policy of ANA SY to perform work in the safest Manner Possible consistent
with good construction practices. To achieve these objectives, we are committed to the following:
o Identification of potential hazards that may arise from the Programmed
Scheduled work activities
o Organizing the work activities so as to minimize the risk arising from them;
o Ensuring that all workers are given orientation/briefing regarding safety practices or
Induction prior to Deployment to the site;
o Establishing a site safety committee to act as policy making body of the project
On all issues pertaining to safety and health.
o Ensure the conduct of daily toolbox meetings.
PROJECT DETAILS
Name of Project
Address/Location
: ANY SY
Contact Number
: 09985391124/09306508460
Project In-charge
: BY ADMINISTRATION
Project Cost
: P 10,000,000.00
Estimated Workers
: 20 Workers
: MAY, 2014
Duration of Project
Site clearing
Layout/Staking and excavation works
Preparation of scaffoldings, and formworks
Fabrication and Installations of reinforcing steel bars for footing and wall footings
Fabrication and Installations of reinforcing steel bars for columns, Roof beams and slab
Pouring of concrete at footing, wall footing, columns, Roof Beams and slab
CHB Laying and plastering at the Exterior walls
CHB Laying and plastering at the Interior Partitions
Concrete topping for Ground floor
Installation of ceiling board
installation of Doors and windows
Electrical rough-in wiring And fixtures
Installation, plumbing rough-in and Fixtures installation
Tile works
Finishing works such as Cabinets, closets and wall mounted cabinets and drawers
Painting works
OwnerForeman
Worker
Secretary -
: ANA SY
: RICO VILLARON
: ALFIE ASTURIAS
: WILFREDO APANITAN JR.
: JOSE MODESTO
: MERLAMINA ARTATES
: RAMIL S. ARTATES
: JAYSON JOHN A. BASILONIA
Function of CSH committee shall include but are not limited to the following:
Plans, develops and oversees the prevention programs for the construction project;
Gather feedback, discuss, review, safety policies, procedures and Recommend improvements;
Conducts safety/toolbox meetings.
Communicate safety and health concerns and information to management and staff Personnel;
Reviews reports of accident investigation and implementation of program;
Solicit, evaluate and confirm implementation of safety and health Suggestions from employees.
Name of First-aider
: MERLAMINA ARTATES
c. Workers:
consistently observed work condition, operation, equipment and
tools for the purpose of accident prevention.
Complies with all the regulations as well as safe work practices and
Safety rules.
uses all necessary personnel protective safety equipment and other safe
Working practices.
Correct any unsafe practices within the scope of work operation and
Reports any unsafe conditions.
Attend all committee/toolbox meetings.
Accessible area.
Scaffoldings
A. General requirements:
Every Scaffolds shall be of good and sound construction materials and strength for its Intended Purpose
Timber, when used as Scaffolds shall be in good condition, the Bark completely stripped off And not painted
and treated in such manner that the defects cannot be easily seen.
B. Specific Requirements
Timber and bamboo Scaffolds when used shall be limited to a height on Six (6) meters from The ground or
base. For more than six (6) meter in height, steel scaffolds shall be used.
Structural steel when used as load bearing members of scaffolding shall be distressed at Welded or bent
joints.
All manufactured scaffolds and its accessories shall follow the manufacturers designs and Specifications.
Manufactured scaffolds exceeding six (6) meters in height shall be designed By structural engineer and
approved by appropriate authority.
All site fabricated/conventional supported scaffolds exceeding six (6) meters in height or a working load of
150kg/sq.m. Shall be designed by a structural engineer and approved by Appropriate authority.
All suspended scaffolds shall be designed and inspected by a structural engineer if site Fabricated.
No scaffold shall be erected, moved, dismantled or altered except under the supervision of A competent
person.
A fall protection equipment shall be used when working in a height of 2 meters and above. For work height
of 10 meters, workers are required to use fall arrest equipment.
All personnel involved in scaffolding activities shall have appropriate certification. Manufacturers training
Certification shall be limited to the erection of manufacturers Equipment only.
Each platform on all working levels of scaffolds shall be fully planked or decked between The front uprights
and the guardrail supports as follow.
Each platform unit (e.g., scaffold plank, fabricated plank, fabricated deck, or fabricated Platform) shall be
Installed so that the space between adjacent units and the space between the platform and the uprights is no
More than 1 inch (2.5 cm) wide,
Each scaffold platform and walkway shall be at least 18 inches (46 cm) wide.
Each end of a platform, unless cleated or otherwise restrained by hooks or equivalent means, Shall extend
over the centerline of its support at least 6 inches (15 cm).
Each end of a platform 10 feet or less in length shall not extend over its support more than12 inches (30 cm)
Unless the platform is designed and installed so that the cantilevered portion Of the platform is able to
support employees and/or materials without tipping, or has Guardrails which block employees access to the
Cantilevered end.
Each platform greater than 10 feet in length shall not extend over its support more than 18 Inches (46 cm),
unless it is designed and installed so that the cantilevered portion of the Platform is able to support
Employees without tipping, or has guardrails which block employee Access to the cantilevered end.
On scaffold where a scaffold planks are abutted to create a long platform, each abutted end shall rest on a
Separate support surface. The provision does not preclude the use of common support members, such as T
sections, to support abutting planks, or hook on platforms designed to rest on common supports.
On scaffolds where platforms are overlapped to create along platform, the overlap shall occur only over
supports, and shall not less than 12 inches (30 cm) unless the platforms are nailed together
or otherwise restrained to prevent movement.
At all points of a scaffold where the platform changes direction, such as turning a corner, any Platform that
rests on a bearer at an angle shall be laid first, and platforms which rest at right Angles over the same
bearer
shall be laid second, on top of the first platform.
maximum intended load without settling or displacement. Unstable objects such As barrels, boxes, loose
brick, or concrete blocks shall not be used to support scaffolds;
Scaffolds posts shall bear on a foundation of sufficient size and strength to spread the load From the posts
over a sufficient area to prevent settlement. All posts shall be set plumb;
Any damaged or weakened scaffold members from any cause shall be immediately repaired, Replaced or
discarded;
Scaffolds shall not be loaded excess of the working load for which they are intended;
Scaffolds shall be anchored or secured to permanent or rigid structures. In the absence of Permanent
structures, guys and sway bracing and/or outrigger shall be used;
Scaffold components produced by different manufacturers shall not be intermixed unless the Components fit
together without force and the scaffolds structural integrity is maintained by The user. It shall likewise not
be modified in order to intermix them unless designed by the Structural engineer; and
Front-end loaders similar types of equipment shall not be used to support platforms unless they have been
specifically designed by the manufacturer for such use. Forklifts shall not Be used to support scaffold
platforms.
G. Scaffold Erection
No work shall be undertaken without the direct supervision of a competent/qualified person As the case may
be.
All posts shall be maintained plumb regardless of connection.
All posts spacing and materials shall conform to the designers specification.
All runners shall be perpendicular to the posts in all situations. Spacing of the runners shall Conform to the
designed scaffold.
Diagonal brace shall extend from one connection to another. It shall be connected to the post Within 150
millimeters from the point connection.
Diagonal braces shall not exceed an angle of 60 degrees from horizontal.
Diagonal braces shall be installed immediately as the scaffold rises to maintain plumbness of the system
All posts shall be joined or connected by means of joint pin, spigot or any appropriate means Of
connections. No lap connection shall be allowed.
Always maintain the base width to height ratio of 1:4 during erection for stability. If the Height exceeds
what is allowed, refer to Section 3.2.7.
No scaffold activity shall be undertaken if the wind velocity exceeds 48kph.For erected Scaffold, additional
precaution shall be considered during typhoon.
No other work shall be allowed to commence below the scaffold during erection phase.
Working platform shall be provided per level during erection. This working platform shall not Be removed
J. Supported Scaffold
Mobile Scaffold:
In the use of mobile scaffolds, which are manually propelled, the following must be observed.
It should be of stable construction and weighted at the base to prevent overturning;
It shall be only be used on firm and even surface;
It shall be securely braced;
It shall not be moved when any worker is on scaffold and all tools and materials are secured;
When manual force is used to move the scaffold, it must be applied as close to the base as Practicable, but
not more than 1.2 m (4 feet) above the supporting surface;
When the free standing, the height of the mobile scaffold should not exceed four (4) times The base width
dimension;
When outrigger frames are used to increase base width dimension, it shall be installed on both sides of the
scaffold;
All casters must be secured to frame legs or screw jacks pins, bolt & nut, and other secured Means.
Weight of tower should not exceed the capacity of the casters and should be Designed to support four (4) times
the maximum intended load;
To prevent movement of the scaffold while it is being used in a stationary position, scaffold Casters and
wheels shall be locked either with positive wheel locks, wheel and swivel locks Or equivalent means; and
Platforms must not extend beyond the base supports of the scaffold, unless stability is Ensured by outrigger
frames or equivalent devices.
Couplers must be made of a structural metal, such as drop-forged steel, malleable iron, Or structural-grade
aluminum. Gray cast iron is prohibited.
Transverse bracing forming an X across the width of the scaffold must be installed ends, And at least at
every third set of posts horizontally (measured from one end only), and every Fourth runner vertically.
Bracing must extend upward diagonally to opposite sides of the scaffold, such as from the Inner posts or
runners, or vice versa.
Building ties should be installed at the bearer levels between the transverse bracing or as per
Recommendation of designer/structural engineer.
On straight run scaffolds, longitudinal bracing across the inner and the outer rows of posts Must be installed
diagonally in both directions, and extend upward from the base end posts To the top of the scaffold at
approximately a 45-degree angle but not more than 60 degree.
On scaffold whose length is greater than their height, longitudinal bracing must be repeated Beginning at
least at every fifth post.
On scaffolds whose length is less than their height, longitudinal bracing must be installed From the base of
the end posts, and then in alternating directions until reaching the top of the Scaffold.
Bracing must be installed as close as possible to the intersection of the bearer and posts or Runner and post.
Bearers must be installed transversely between posts.
When bearers are coupled to posts, the inboard coupler shall be bear directly on the runner Coupler, and be
as close to the posts as possible.
Bearers must extend beyond the posts and runners, and provide full contact with the coupler.
Runners must be installed along the length of the scaffold, located at level heights on both The inside and
outside posts. Runners shall be spaced vertically at 1.8m (6ft.) to 2m (7ft.) on Centers.
On outside posts of tube and coupler scaffold, guardrails and mid-rails may be used in lieu of Outside runner.
Runners on straight runs must be interlocked to form continuous lengths, and coupled to Each post.
M. Frame Scaffolds
When moving platforms to the next level, the existing platform shall be left undisturbed until The new end
frames have been set in place and braced prior to receiving the new platforms.
Frames shall be braced by a cross, horizontal, or diagonal braces, or combination thereof, Which secure
vertical members together laterally. The cross braces shall be of such length as
Will automatically square and align vertical members so that the erected scaffold is always Plumb, level,
and square. All brace connections shall be secured.
Frames shall be joined together vertically by coupling or stacking pins.
Where uplift can occur which would displace scaffold end frames, the frames shall be locked Together vertically
by pins or equivalent means.
Brackets used to support cantilevered loads shall Be seated with side-brackets parallel to the frames and endbrackets at 90 degrees to the Frames;
Not be bent from these positions; and
Be used only to support personnel, unless the scaffold has been designed for other loads By a qualified
engineer and built to withstand the tipping forces caused by those other load Being placed on the bracketsupported section of the scaffold.
N.Timber Scaffolds
In single scaffold, the post shall be placed at 1.2 to 2.4 meters (4 to 8 ft.) apart at a distance of 1.0 m. (3 ft.)
from the wall, connected horizontally by runners shall be spaced vertically at 1.8m.(6 ft.) to 2 m. (7 ft.) on
Centers. Putlogs shall be placed in the holes left in the walls.
The size of the post shall not be less than 50 x 100 mm (2 x 4 in) and when it is necessary to Extend a post, the
Overlaps shall not be less than 60 cm. (24 in.)
In double scaffold, the bearer shall rest entirely on the runners. In addition to the diagonal Braces, inclined
supports shall be provided to prevent the scaffold from leaning away from the Wall. The support shall be
Strutted at intermediate heights against the posts.
The size of the posts for double scaffold shall not be less than 50 x 100 mm (2 x 4in) and When it is necessary to
extend a post the overlap shall not be less than 60cm(24in)
The distance between two consecutive bearers shall be designed with due regard to Anticipated load and the
nature of the platform flooring. As a minimum rule, the spacing Shall be as follows:
For 3.2 cm (1in) thick planks, spacing shall not exceed 1 m (3ft).
For 3.8 cm (1 in ) thick planks, spacing shall not exceed 1.5 m (5ft).
O.Bamboo Scaffold
Bamboo scaffold may used for painting or light construction work only and must observed the Following:
The material and construction shall be sufficient to carry at least forty (40) times the impose Load;
Only one worker shall be allowed in any one span;
The maximum span between poles shall be 2.4m. (8 ft.);
When the height or fall over 2m (6 ft. ), the use of fall protection shall be required; and
The maximum height allowed is 6 meters (20 ft.).
P.Trestle Scaffolds
Scaffold platforms must be placed no higher than the second highest rung or step of the ladder Supporting the
platform.
All step ladder used as a trestle scaffold shall conform to the manufacturers requirements and Shall be
prevented from slipping by fastening or tying to a permanent structure.
All trestle scaffolds must not be one to another.
Trestle scaffolds shall not be used if the working platform is more than 5 m. from the ground Or floor or other
surface upon which the scaffold is erected.
A trestle scaffold shall not be erected on a scaffold platform unless:
The platform is sufficiently wide for the transport of materials;
The posts are firmly attached to the platform and braced displacement; and
Designed by structural engineer and approved by the proper authority if erected on A scaffold 10 meters or
over in height.
No trestle scaffold shall be erected on suspended scaffold.
U.Suspended Scaffold
All suspended scaffold support devices, such as outrigger beams, cornice hooks, parapet Clamps, and similar
devices, shall rest on surfaces capable of supporting at least 4 times the Load imposed on them by the scaffold
Operating at the rated load of the hoist (or at least 1.5 times the load imposed on them by the scaffold at the
stall capacity of the hoist, whichever is greater).
Suspended scaffold outrigger beams, when used, shall be made of structural metal or Equivalent strength
material, and shall be restrained to prevent movement.
The inboard ends of suspended scaffold outrigger beams shall be stabilized by bolts or other Direct connections
to the floor or roof deck, or they shall have their inboard ends stabilized By counterweights, except masons
multi point adjustable suspended scaffold outrigger Beams shall not be stabilized by the counterweights.
Before the suspended scaffold is used, direct connections shall be evaluated by a competent Person who shall
confirm. Based on the evaluation, that the supporting surfaces are capable Of supporting loads to be imposed.
In addition, masons multi-point adjustable suspended Scaffold connections shall be designed by a structural
engineer experienced in such scaffold Design.
Counterweights shall be made of non-flowable material. Sand, gravel and similar materials That can be easily
dislocated shall not be used as counterweights.
Only those items specifically designed as counterweights shall be used to counterweights Scaffold systems.
Construction materials such as, but not limited to, masonry units and rolls Of roofing felt, shall not be used as
counterweights.
Counterweights shall not be removed from an outrigger beam until the scaffold is Disassembled.
Outrigger beams which are not stabilized by bolts or other direct connections to the floor or Roof deck shall be
secured by tiebacks.
Tiebacks shall be equivalent in strength to the suspended ropes.
Outrigger beams shall be placed perpendicular to its bearing support (usually the face of the Building or
structure). However, where the employer can demonstrate that it is not possible To place an outrigger beam
perpendicular to the face of the building or structure because of Obstruction that cannot be moved, the
outrigger beam may be placed at some other angle, Provided opposing angle tiebacks are used.
Tiebacks shall be secured to a structurally sound anchorage on the building or structure. Sound anchorages
include structural members, but do not include standpipes, vents, other Piping systems, or electrical conduit.
Tiebacks shall be installed perpendicular to the face of the building or structure, or opposing Angle tiebacks
shall be installed at an angle prohibited.
Suspended scaffold outrigger beams shall be:
Provided with stop bolts or shackles at both ends;
Securely fastened together with the flanges turned out when channel iron beams are used in Place of I-beams;
Installed with all bearing supports perpendicular to the beam center line;
Set and maintained with the web in a vertical position; and
When an outrigger beam is used, the shackle or clevis with which the rope is attached to The outrigger beam
shall be placed directly over the center line of the stirrup.
Suspended scaffold support devices such as cornice hooks, roof hooks, roof irons, parapet Clamps, or similar
devices shall be:
Made of steel, wrought iron, or materials of equivalent strength;
Supported by bearing blocks; and
Secured against movement by tiebacks installed at right angles to the face of the building or Structure, or
opposing angle tie backs shall be installed and secured to a structurally sound Point of anchorage on the
building or structure. Sound points of anchorage include Structural members, but do not include standpipes,
vents, other piping systems, or electrical Conduit.
Tiebacks shall be equivalent in strength to the hoisting rope.
When winding drum hoists are used on a suspended scaffold, they shall contain not less than Four wraps of the
suspended rope at the lowest point of scaffold travel. When other types Of hoists are used, the suspended ropes
shall be long enough to allow the scaffold to be Lowered to the level below without the rope end passing
through the hoist, or the rope end Shall be configured or provided with means to prevent the end from passing
through the Hoist.
The use of repaired wire rope as suspended rope as suspended rope is prohibited.
Wire suspended ropes shall not be joined together except through the use of eye splice Thimbles connected with
shackles or cover-plates and bolts.
The end of wire suspended ropes shall be equipped with proper size thimbles and secured By eye splicing or
equivalent means.
Ropes shall be inspected for defects by a competent person prior to each work shift and every occurrence which
could affect a ropes integrity. Ropes shall be replaced if any of The following conditions exist:
Any physical damage which impairs the function and strength of the rope, such as:
Kinks that might impair the tracking or wrapping of rope, around the drum(s) or Sheave(s).
Six randomly distributed broken wires in one rope lay or three broken wires in one Strand in one rope lay.
Abrasion, corrosion, scrubbing, flattening or penning causing loss of more than One-third of the original
V.Aerial Lift
A combination of any such devices. Aerial equipment may be made of metal, wood, fiberglass reinforced plastic
(FRP), or other material; may be powered or manually Operated; and are deemed to be aerial lifts whether or
not they are capable of rotating about a substantially vertical axis.
Aerial lifts may be field modified for uses other than those intended by the manufacturer provided the
modification has been certified in writing by any other equivalent entity.
Specific requirements for aerial lifts:
Ladder trucks and tower trucks.
Aerial ladder shall be secured in the lower travelling position by the locking device on top of the truck cab, and
the manually operated device at the base of the ladder before the truck is moved for highway travel.
Extensible and articulating boom platforms.
Lift control shall be tested each day prior to use to determine such controls are in Safe working condition.
Only authorized persons shall operate an aerial lift.
Belting off to an adjacent pole, structure, or equipment while working from an aerial Lift shall not be permitted.
Personnel shall always stand firmly on the floor of the basket, and shall not sit or climb On the edge of the
basket or use planks, ladders, or other devices for a work position.
A safety belt shall be worn and attached to the boom or basket when working from an Aerial lift.Boom and
basket load limits specified by the manufacturer shall not be exceeded.
The brakes shall be set and when outriggers are used, they shall be positioned on pads Or a solid surface.
Wheel chocks shall be installed before using an aerial lift on an incline provided they can be safely installed.
An aerial lift truck shall not be moved when the boom is elevated in a working position With men in the basket,
except for equipment which is specifically designed for this Type of operation.
Articulating boom and extensible boom platforms, primarily designed as personnel Carriers, shall have both
platform with upper and lower controls. Upper controls shall be in or beside the platform within easy reach of
the operator. Lower controls shall provide for overriding the upper controls. Controls shall be plainly marked
as to their function. Lower level controls shall not be operated unless permission has been obtained from the
personnel in the lift, except in case of emergency.
Climbers shall not be worn while performing work from an aerial lift.
The insulated portion of an aerial lift shall not be altered in any manner that might reduce its insulating value.
Before moving an aerial lift for travel, the boom(s) shall be inspected to see that it is properly cradled and
Outrigger s is in stowed position.
W.Modifications
All modifications to existing scaffolds should be carried out in such a way that the stability of The scaffold is
not
impaired. As a general rule, supplementary components should be added Before those, which have to removed,
are uncoupled and taken away.
Adding sheeting or debris netting to an existing unsheeted scaffold should only be carried out with approval.
The increased wind loads will change the design and may require additional ties and/or bracing.
Z. Scaffold Dismantling
During dismantling, no component, which endangers stability of the remaining structure, should be removed.
If dismantling has reached the stage at which a critical member has to be removed, (e.g. a tie or a brace) the
stability of the structure should be assured by fixing a similar or otherwise adequate member in place before
the member to be taken out is removed.
If changes are made in the scaffold structure during its working life, it is not safe to assume That dismantling
can be carried out in the reverse order to the erection, hence, ties And braces shall be inspected prior to
dismantling.
Materials should be lowered to the ground and not stored on the scaffold. Components Should not be thrown on
the ground; they should be lowered hand-to-hand in an orderly Manner or brought down by crane, pulley or
other suitable means.
Progressive Dismantling
Scaffolds, which are to be progressively dismantled during the demolition of a building,Should not be left
projecting above the residual height of the walls more than is necessary.Stabilizing ties should be maintained,
especially with sheeted scaffolds.
Scaffolds, which are to remain in use while partly dismantled, should be fitted with end Of the portion in use.
If access is possible on to a partly dismantled scaffold, warning notices should be fixed.
Maintenance and Storage
All scaffolds shall be properly maintained and shall be kept, clean, and free of damage.
Scaffolds accessories requiring lubrication shall be oiled prior to storage in a covered or
Closed container, or as per manufacturers recommendation.
Loading/Unloading and Transport
All loading and unloading operations, including transport of scaffolds, shall be properly planned by a
competent person, appropriately supervised and carried out in a safe manner.
Planning
During loading/unloading and transport of scaffolds, the following shall be considered:
Information on scaffolds to be handled as provided by manufacturers, e.g. weight, Shape and center of gravity
of material components/bundles of materials;
Selection of most appropriate vehicle and certified driver as applicable;
Loading/unloading operation
Location
Methodology
Provision of spacer during loading of scaffolds
Safe loading and unloading sequence
Provision of safe access to the vehicle
Any manual handling, including required PPE
Hazards for the stock yard workers, slingers/riggers and driver
All loose parts shall be strapped or secured prior to transport. Small parts shall be Placed on a box or bag
indicating the total weight before loading.
Safety Procedures:
1. HOUSEKEEPING
The practice of proper housekeeping and cleanliness is highly enforced Poor
Housekeeping is a major factor in many accidents. A cluttered area is both unsafe and inefficient. Every
worker is responsible for keeping a clean area and ensures that all areas remain clean and orderly.
Worksite must be clean and orderly. Work surfaces must be kept dry or appropriate means taken to
assure the surface are slip resistant. Spills must be cleaned up immediately. All combustible scrap, debris,
and waste must be stored and safely removed promptly. Combustible dust must be cleaned up. The
accumulated combustible dust must be removed routinely. Covered metal waste cans are provided for oily
and paint-soaked waste. Make sure all pits or excavation and floor openings are either covered or
otherwise guarded.
2. TEMPORARY FACILITIES ELECTRICAL SUPPLY
All temporary electrical installation will be inspected and certified as safe by an
Electrical Engineer which will be based on the following requirement:
Conduit system whether PVC or galvanized iron shall be used whichever is appropriate.
Circuits are to be provided with rated MCB for protection.
Circuit panel board must have an earth leakage circuit breaker of 30Ma Tripping current.
Lighting fixture (fluorescent, etc.) must be installed with insulated Separator against wooden
Ceiling at the point of support in order to avoid Heat buildup on the surface of the wood due
To ballast operation.
Electrical conduits in the kitchen shall be galvanized iron and all Accessories shall be
Metal clad. Installation shall be exposed and electrical Accessories shall be located a distance
Substantial and sufficient light and properly braced or tied together by the used of G.I. wire and common
nail. All unused form, waste materials shall be removed as rapidly possible.
9. CONCRETING
Formwork and shoring will be properly braced or tied together so as to maintain position and
shape. The formwork including the shores, braces and other support will be inspected by the designated
persons during erection, during and after concreting work, and after any event likely to have affected their
stability, for example after heavy rain or following strong wind. Workers involved in the mixing and the
pouring of concrete are required to wear proper PPE and specialized PPE for the workers in contact with
the fresh concrete.
10.
CHB LAYING
Laying of concrete hollow blocks should be provide with platforms or staging on a higher level.
11. CARPENTRY
Electric plainer, electric drill will be used for carpentry and joinery works. All sharp and pointed tools
shall be always placed in safe area and kept it when no longer in use.
12. ELECTRICAL
Pipe layout, rough-in shall be embedded on walls using electrical grinder and concrete chisel. Wiring shall
be done by electrician. Workers must wear goggles and gloves.
13.
SANITARY
Water line and sanitary pipe layout must be done using plumbing tools, grinder and chisel. Workers must
wear goggles.
14. CEILING
Installation of ceiling frame and ceiling board shall be done by using electrical drill. Exact height
of platform, scaffold shall be provided conveniently for the workers.
15. WINDOWS
All windows shall be pre-assembled by the supplier and deliver at the construction site for
installation by the supplier.
16. TILES
Wearing eye goggles and rubber gloves when cutting and installing tiles.
17. PAINTING
Ensuring good ventilation during painting application. Avoid breathing vapor and spray mist. Avoid
contact with skin and eyes. Wear eye protection and gloves during painting application. Wash hand
afterwards.
PENALTIES/SANCTION - as a matter of policy and to ensure that the safety and health rules
specified are complied with, the following sanction/penalties in connection to any violations
committed shall be imposed:
First offense
Second offense
Third offense
Fourth offense
ANA SY
Name of Project Owner
Signature over Printed Name
RAMIL S. ARTATES
Supervising Civil Engineer
Signature over Printed Name
-warning (written)
-penalty-(one day salary deduction)
-penalty-(three days salary deduction)
-dismissal
CONSTRUCTION
SAFETY
AND HEALTH PROGRAM
OF FOUR-STOREY COMMERCIAL BLDG.
WITH ROOFDECK
LOCATION: SAN ROQUE STREET, ROXAS CITY