POSTGRADUATE DIPLOMA IN
PROCUREMENT
AND SUPPLY MANAGEMENT
PGD6
TOPIC 1
1.1
LEARNING OBJECTIVES:
When you have completed this TOPIC you should be able to: Outline the objectives of the PPA and its Regulations
Identify and explain the general guidelines of Public Procurement
Identify Principles governing the Public Procurement.
Identify the contents and parts of the PPA and its regulations
The Procurement Act has the intention of regulating the relations between
natural person(s) and the state, and those against the Government interest.
The Procurement Act provides punishment for damages to those who have
inflicted some harm against the government or for damages against those who
have caused loss to another natural person.
Further from that the PPA 2004 Section 76 indicates clearly that the measures
provided by the Act shall not preclude the institution of criminal proceedings
pursuant to the Penal Code (Cap. 16) the Prevention of Corruption Act, 1971 or
any other written law against any person discharging functions or excising powers
under this Act or Regulations made under this Act.
The Minister may make regulations and rules for the better carrying out of
the provision of this Act and such Regulations shall include yearly review of
the limits of Authority for each procuring entity and approving entity.
All Regulations and directions made in connection with this Act shall be
published in the Government Gazette.
The Public Procurement (Selection and Employment of Consultants) Act No.
21 of 2004 also came into operation on 11th Feb 2005. However, Sect. 113 of
the Regulations empowers the Minister to make amendments where
applicable. Similarly the Procurement of goods and works Regulations were
also made under Sect. 88 (1-2) of the Public Procurement Act No. 21 of 2004.
Regulations 129 (1-2) have again given power of amendment of the same to
the respective Minister.
4
In this regard the Procurement Act shall not apply to any Parastatal
organisation except where a Parastatal organisation receives government
subsidiary or subversion and is specified in the Regulations as being
Government Department or Public body, and/or Public Authority for the
purpose of the Act (Section 2(2) of the Act).
Under Section 28 of the Act, there shall be established in every governing body
of a Public Authority a TENDER BOARD.
The Public Procurement Policies are based on the need to make the best
possible use of public funds while conducting all procurement with honesty
and fairness (Regulation 4(1)) for goods and work Government notice 97.
The need for economy and efficiency in the use of public funds and
in the implementation of projects including the provision of related
goods and services.
(b)
(c)
(d)
fairness
and
The need for economy and efficiency in the provision of works, goods,
and services.
(d) Procurement of all stock items require the prior authorization of the
Procurement Department or authorization by an appropriate person(s) directed
by the Department to exercise such authority on the Departments behalf.
(e) All overseas purchases shall require the approval of the Head of Procurement
Department, Chief Accountant and the Approving Authority or Chief Executive
(for parastatals tender).
(f) Procurement of all stock items requires an approval requisition to purchase.
(g) Optimum value for money will be obtained by a combination of comprehensive
specifications in line with industry and international norms, coupled with
effective procurement. The Technical, Commercial and user roles are fully
complementary and independent.
(h) Procurement and repair of assets required the prior approval of works order.
(i) Good Procurement management means the effective operation of an efficient
Procurement and Supply Chain Management from forecasting to procurement,
warehousing and distribution to end-user.
This
demand full
cooperation/coordination from all involved in the process, the Technical
Department for the technical specification, the Regions for accurate forecasting
of its user requirements and the Procurement Department for effective
procurement of the goods/services its stocking and distribution to the user in
the most efficient manner possible.
(j) Contractors and/or suppliers engaged by a public Procuring Entry (PPE) must
abide by the appropriate conditions of contract and in particular must have
Public and Employers liability insurance policies and the existence and verified
prior to commencement or work.
(k) Suppliers of goods, works and services to a public procuring entity must
comply with all Government Regulations requirements.
(l) In addition to ensuring that the PPE gets value for money in all its procurement
these procedures also provide the checks and balances necessary for security
and control purposes and comply with current Government Regulations.
(m) The accountable board or body is responsible for ensuring that all
procurement is full consistent with procedures and policies adopted by Public
Procuring Entity. In discharging that responsibility the accountable board or
OF
The PPA No. 21 of 2004 has the following parts and sections
PART 1:
Preliminary Provisions
Section 1-4: Include short title and commencement,
Applications, Interpretation and International Obligations.
PART II:
Section 5-27:
Include Establishment, Objectives,
Functions, Investigations Procedures, Powers, Disciplinary
Actions, Recommendations and appointment of Directors.
PART III:
Tender Boards
Methods of Procurement
Section 58 71: Include selection methods, Invitation to
Tender, Tender documents, Validity of Tenders, Evaluation
Criteria Receipt of Tenders and Opening,
Evaluation/Comparison of Tenders, Approval, Selection of
Consultants/Negotiation and Award.
PART VI:
Prohibitions
10
Principles
governing
the
Public
11
12
(ii)
(iii)
13
TRAINEE ACTIVITIES;
1. Read Section 3 of the PPA No. 21 of 2004 and suggest which of the
definitions is more likely to be frequently used by the procurement
specialist in performing his/her duties.
2. Section 2 and section 4 of the PPA No.21 of 2004 are both concerned
with the application of the Act. Discuss
PROGRESS CHECK;
1. All procurement falls under main categories of expenditure namely:
Works, Goods, Consultancy and Non-Consultancy Services. How would
you differentiate the individual category from each other?
2. Differentiate the term Pre-qualification from Post-qualification
14
Section 6:
(a)
(b)
(c)
(d)
Set standard for the public procurement systems in the united republic of
Tanzania.
(e)
(f)
15
TRAINEE ACTIVITIES;
1. Read part II of the PPA and identify sections that may not be used as
means to enforce compliance to the PPA and its Regulations
PROGRESS CHECK;
1. Identify functions and powers of the PPRA that may be used to enforce
compliance of the Procuring Entity to the PPA requirements.
16
17
(b)
(c)
(d)
(e)
(f)
(g)
(j)
(k)
(l)
(p)
(q)
Section 36 provides for the functions of the user department of the PE, which
include providing assistance to the PMU throughout the procurement or disposal
by tender process to the point of contract placement including input with
technical evaluation of tenders received as required by the PMU.
Section 37 provides that an evaluation committee, which shall report to the PMU,
the membership of which shall be recommended by the PMU and approved by the
accounting officer, shall conduct the all evaluations. The members may be
external to the PE where the required skills or experience are not available within
the PE.
TRAINEE ACTIVITIES;
1. Read part III of the PPA and explain the establishment and
scope of services of the PMU, Tender Board, PE, CEO, User
Department and the Evaluation Committee.
PROGRESS CHECK;
1.
19
for any failure unless s/he satisfies the PPRA that s/he had delegated her/his
functions in accordance with the law.
20
(b)
(c)
The methodology is specified in the regulations, and the PE shall include in the
records a statement of the grounds for its decision to justify the restriction.
Invitation procedures, issue of tender documents validity of tenders, contents of
tender documents, evaluation criteria, receipt of tenders and opening (Sections
61-66) are set out in the regulations.
Section 67 specifies the bases for evaluation and comparison of tenders. All
tenders for works shall be evaluated based on monetary terms and completion
period for goods and equipment other factors in addition to price may be
prescribed in the tendering documents.
Any Procedure under which tenders above or bellow a pre-determined assessment
of tender value are automatically disqualified is not acceptable.
Any additions to the value of a procurement contract shall be reviewed and agreed
by the approving and agreed by the approving authority and must be to the
benefit of the government or not disadvantageous to the government (section 69)
21
Subsection (2) specifies that, negotiations shall include discussions of the terms of
reference, the methodology, staffing, procuring entity's inputs and special
conditions of contract and the discussions shall not substantially alter the original
terms of reference or the terms of the contract.
Subsection (3) specifies that, where the negotiation under subsection (2), fail to
result in an acceptable contract, the procuring entity shall terminate the
negotiations and after consultation with the appropriate tender board, invite the
next ranked firm for negotiations.
Subsection (4) further specifies that, after negotiations are successfully completed,
the procuring entity shall within the time set out in the Regulations notify
PROGRESS CHECK;
1. Lack of competition shall not be determined solely on the basis of the
number of tenderers or persons who made proposals when
recommending for the rejection of all tenders. Discuss.
22
Prohibitions
Section 72 prohibits fraud and corruption and action against the defaulters shall
include institutions of criminal proceedings cap.16 act No. 3 of 1971; the Penal
Code, the Prevention of corruption Act, 1971 as provided under section 76 of the
PPA or any other written law against any person discharging functions or
exercising powers under the PPA or its regulations.
Any conduct influencing public officer is prohibited under sections 73 of the Act.
All payments made by way of commission must be declared in writing and
furnished to the Prevention of Corruption Bureau (PCB) and Tanzania Revenue
Authority (TRA) pursuant to section 74 of the Act.
23
The PE or approving authority shall deliver a written decision within 30 days after
submission of the complaint in case no mutual agreement and this decision shall
be final unless the aggrieved party institutes the procedures for administrative
review by the PPRA within 14 days of the PES decision (section 80 and 81). The
PPRA shall deliver decision within 30 days. Procedures for review by the PPAA are
stipulated under section (82 -84). If the ruling of the PPAA does not satisfy the
aggrieved party, that party shall have the right to institute judicial review
pursuant to section 85 of the Act.
Miscellaneous Provisions
Offences, which are listed under section 87 of the Act include: (a)
(b)
(c)
(d)
(e)
(f)
Contravenes or fails to comply with a provision of the act and its regulations.
SCHEDULES
2nd Schedule
Composition:
-
3rd Schedule -
TRAINEES ACTIVITIES;
1. Read the sections under prohibitions and explains the key
areas of the prohibitions under the PPA 2004.
2. Read relevant sections under Part VI of the PPA and explain
the procedures for settlement of complaints or disputes by PE
and approving Authorities.
3. Read the relevant sections under the miscellaneous provision
of the Act and explain what circumstances may lead to the
recommendation by the Authority to have functions of
procurement of any PE transferred to a third party
Procurement Agency.
PROGRESS CHECK;
1. What are consequences of contradicting the procedures set
out in the PPA of 2004?
2. Explain the composition of:
a) PPRA.
b) PPAA.
25
26
department,
agency,
27
Goods means raw materials, products equipment and other physical objects of
every kind and description, whether in solid, liquid or gaseous form, electricity
intangible asset and intellectually property, as well as services incidental to the
supply
the good themselves.
Of the goods provided that the value of the
services does not exceed the value of goods themselves.
Works means:
(iv)
(v)
(vi)
28
entity to compete with each other in submitting priced tenders for goods,
works or services;
Goods means raw materials, products, equipment and other physical objects
of every kind and description, whether in solid, liquid or gaseous form, electricity,
intangible asset and intellectual property, as well as services incidental to the
supply of the goods provided that the value of the services does not exceed the
value of the goods themselves;
Lowest evaluated cost means the price offered by a supplier, contractor, or
consultant that is found to be the lowest after consideration of all relevant factors
and the calculation of
Minor Value means an amount of money up to a maximum limit for
the procurement of goods, works and services of a minor nature, to be determined
each year by the Minister;
29
(iii) Any company registered under the Companies Ordinance being a company in
which the Government or an agency of Government is in the position to
influence the policy of the company;
(iv) Any local government authority;
(v) Any parastatals organization.
General Provisions
Regulation 4 provides that the Public Procurement policies are based on the need
to make the best possible use of Public funds, whilst conducting all procurement
with honesty and fairness.
The basic considerations of the public procurement policy are:
(a)
The need for economy and efficiency in the use of public funds.
(b)
(c)
Encouragement
industries.
(d)
of
national
manufacturing,
contracting
and
service
a)
b)
c)
d)
That the firm possess the necessary professional and technical qualifications,
professional and technical competence, financial resources, equipment and
31
That they have legal capacity to enter into the procurement contract.
(c)
That they are not insolvent, in receivership, bankrupt or being wound up,
their officers are not being administered by a court or a judicial officer, their
business activities have not been suspended, and they are not the subject of
legal proceedings for any of the foregoing.
(d)
That they have fulfilled their obligations to pay taxes and social security
contributions in Tanzania where required.
(e)
That they have not been convicted of any criminal offences related to their
profession or have not been otherwise disqualified pursuant to administrative
suspension or disbarment proceedings.
The annulment of a tender may take place in the following cases (Regulation 20(2)
32
(a)
If no responsive tender
(b)
(c)
(d)
(e)
(f)
(g)
If no competition
TRAINEE ACTIVITIES
1. Read
33
PROGRESS CHECK
1. How Public Procurement Policies as laid down under
Regulation 4 of the Act can be achieved.
2. Outline the Objectives of PPR for goods and Works.
3. Define the following: Competitive tendering
Lowest evaluated Cost Tender.
Minor Value
Procurement expert or specialist
Procurement
Procurement proceedings
34
Approval of Procurement
Tender Boards.
Regulation 41 of the Act stipulates that, tenders may only be issued with the
approval of the appropriate tender board, which may examine the draft tender
document before approving the issue of the tender . Also the tender board may
make a decision of the tender board without a meeting by circular resolution by
circulation of the relevant papers among members of the tender board.
Emergency procurement.
Emergency procurement is allowed under Regulation 42 with due regard to
circumstances of urgency and without regard to the limits of the approving
authority.
The approving officer must promptly present the unauthorized
procurement to the paymaster general, treasury for retrospective approval. Lack
of foresight in not procuring at the right time authority is held personally liable to
the extra costs implications.
Under this chapter regulation 43-45 provides the details on the alteration and
amendments of a procurement contract, Conditions for additions to contract value
and validity of procurement authorization given by a tender board.
35
TRAINEE ACTIVITIES.
1. Read Part III of the Regulation and identify the powers of the
Accounting officer in comparison to that of the Tender Board.
PROGRESS CHECK.
1. Emergency procurement is generally prohibited but it is only allowed under
Regulation 32.Discuss
Planning
Regulation 46 stipulated the procedures for procurement planning; Planning for
implementation shall involve preparation of a project work plan describing the
various project tasks and activities, including how the tasks will be accomplished
and managed and identify the resources necessary to carry out the various project
activities.
Procurement planning shall begin at the design stage during the identification /
preparation stages of the project cycle.
The procuring entity shall take a strategy decision whether the most economic and
efficient procurement can best be achieved by separating contracts for each
component.
36
A procuring entity must forecast its requirements for goods and works as
accurately as is practicable, with particular reference to works already
programmed in the public authoritys annual work plan and included in the
annual estimates.
The forecasts shall include an estimate of the optimum time to the nearest month
for receipt of each consignment of goods or completion of required works.
The estimate shall be shown in the tender evaluation report and priorities for
procurement may be determined in accordance with available funds.
A procuring entity shall then draw up procurement plans for those requirements
for which sufficient funds are available in the current vote, sub-head or, if
payment will be due in a subsequent financial year, have been budget for that
year.
In compiling such plans, a procuring entity shall establish the appropriate method
of procurement, as set out in Part VI of these Regulations, to be employed for each
requirement.
The timescale for each procurement shall then be calculated on the basis of the
standard processing times at Fourth Schedule to these Regulations, allowing any
necessary margin for delays in transmission of documents or clarification of
tenders.
From this timescale, the start dated and critical points in the
procurement process shall be set out in the procurement plans.
Except for institutions, which have fully fledged engineering service departments
or such other similar professional service department, and those, that are in
position to use the services of such professional departments, all procuring
entities shall engage the services of consultants to prepare tender documents,
evaluate and make recommendations to tender boards.
Aggregating requirements.
37
Packaging of procurement.
38
In considering how a project may be carried out, account shall be taken of the
advantage, for economic and technical reasons, of dividing the project into
homogeneous lots or packages, which are as large as possible.
Where a project has been divided into packages, the size of the package should be
appropriate to foster maximum competition to obtain the most economic contract.
If similar items of equipment are to be procured for several subcomponents in a
project or for several projects, it may be convenient to combine them all into one
procurement package in
Where a project has been divided into lots or packages, the instructions to tenders
shall state: The number of lots or packages;
The nature, location and size of each lot; and
Where appropriate; the minimum and maximum number of lots
or packages for which a tender may tender.
The procedure for submitting a tender for package tenders shall be as follows:
a) Tender may submit a tender for each lot or package;
b) Unless the instructions to tenders provide otherwise, a tendered may include in
his tender the overall rebate he would grant in the event of amalgamation of
some or all of the lots or packages for which he has submitted individual
tenders;
c) Unless the instructions to tenders state that lots or packages apportioned on
the same tender shall form a single contract each lot shall form a separate
contract:
d) Where lots or packages are to be appointed to different tenders, the invitation
to tender document or the instructions to tenders may provide that the tender
for a particular lot or packages shall ensure the coordination of the execution
of all the lots or packages.
TRAINEE ACTIVITIES
1. Read Part V under regulations (46-50) of the Act and discuss
their importance to the procuring entity.
PROGRESS CHECK
1. How Procurement Planning can be used to achieve
Economy and Efficiency as stipulated under the
Public Procurement Policies?
4.O METHODS OF PROCUREMENT AND
THEIR CONDITIONS FOR USE
40
41
42
Subject to approval by the tender board a procuring entity may engage in a single
source procurement or direct contracting in accordance with Regulation 70 as
stipulated under Regulation 69 of this Act under the following circumstances: a) The goods are available only from a particular supplier or particular supplier
exclusive rights in respect of the goods and no reasonable alternative or
substitute exist.
b) There is an agent need for the goods and must be provided that the
circumstance giving rise to the urgency where neither foreseeable by the PE nor
the result of dilatory conduct on its part
c) Where NCB or ICB is carried out and PE determined that additional supplies of
the same type as those purchased under existing contract are required.
d) Where the PE seeks to enter into a contract with a supplier for the purpose of
research, experiment, study or development.
e) Procurement National Defense or National Security.
f) Where critical items need to be purchased from a specified supplier to ensure
that the contractor shall guarantee the output of a process plant responsible
for the process design.
g) Where standardization of equipment is essential for economic and technical
reason and it has been proved to the tender boards satisfaction that
compatibility of the existing equipment with another make of equipment cannot
be established and that there is no advantage in having an alternative supplier.
h) Where an on-going project, additional items need to be purchased for the
completion of implementation.
Direct contracting for works
A procuring entity may obtain a priced quotation from a single contractor and
negotiate and enter into a direct contract when:a) There is an agent need for the works such that there would be insufficient time
for a PE to engage in tendering or any other method of procurement provided
that the circumstances giving rise to the agency could not have been foreseen
by the PE and have not been caused by dilatory conduct on its part.
b) There is only one particular contractor, which a PE can reasonably expect to
undertake the required works.
c) There are advantages to a PE in using a particular contractor who has
undertaken or is undertaking similar work or who may have already been
mobilized with plant, equipment and staff in the vicinity.
d) Civil works are already satisfactorily under construction are to extended and
the prices on the extended contract are reasonable and competitive and there is
no advantage to further tendering.
e) The estimated value of the works does no exceed the limit specified in 3 rd
schedule to these regulations.
43
Procurement of Commodities
Regulation 76 of this Act provides the details on procurement of Commodities
such as grain, animal feed, cooking oil, fuel, fertilizer and metals, the market price
of which fluctuate depending upon the demand
44
and supply at any particular time, may involve multiple awards for partial
quantities to assure security and multiple purchases over a period of time to take
advantage of favorable market conditions and to keep inventories low. In any
procurement of such commodities a PE may: a) Draw up a list pre-qualified suppliers and issue periodic invitations for the
supply of commodities to quote price linked to the market price at that time of
or prior to, the shipment of such commodity and tender validities shall be as
short as possible.
b) Specify single currency in which a commodity is priced in the market to be
used in for tendering and payment,
Procurement agents
(A procuring entity may procure the services of a procurement agent to undertake any or
all of those procurement functions which would otherwise carried out by the entity
provided that all such procurement functions are carried out in conformity with the Act
and in accordance with these Regulations. This is stipulated under Regulation 77 of the
Act where a PE shall:-
Inspection agents
Regulation 78 stipulates the need for inspection agent to undertake preshipment inspection and certification of imports.
But where exemption by the Minister has no been granted, any inspection agents
fees are not to be included in the price tendered or considered in the evaluation of
a tender.
TRAINEE ACTIVITIES
Procedures for competitive tendering for goods and works are stipulated under
Regulation 79 and invitation to tender and advertising procedures are stipulated
under Regulation 80. Where:(i) A procuring entity wishing to commence competitive tendering proceedings shall
prepare a tender notice inviting suppliers or contractors to submit priced offers for
the supply of the required goods or works.
(ii) The approved tender notice shall be advertised by the procuring entity at least twice
in one or more newspaper of national circulation and in case of international
tendering, a similar notice may be published in appropriate foreign publication or
trade journals.
(iii)
Any tender notice shall be published in sufficient time, to enable the
prospective tenderers to obtain tender documents, prepare and submit their
responses before the deadline for receipt of tenders.
(iv)The time specified for the opening of the tenders submitted shall be the same as the
deadline for receipt of tenders or immediately thereafter, and shall be repeated,
together with the place for tender opening in the invitation to tender.
Tender Period
Time allowed for preparation of tenders shall depend on the magnitude and
complexity of the procurement sought, tender boards would require the following
minimum times as stipulated under Regulation 84
-
NCB = 30 days
ICB= 45 days
Submission of tenders.
Regulation 86 provides that the procuring entity shall indicate the specific
date and time for bid submissions and opening.
place,
Note That:
The time for the tender opening shall be the same as time for deadline for
the receipt of tenders
Period of effectiveness of tender, modification and withdrawal of tenders
The procuring entity shall require tenderers to make their tenders and tender securities
valid for periods specified in the tendering documents and such periods shall be sufficient
to enable the procuring entity to complete the comparison and evaluation of the tenders
and for the appropriate tender board to review the recommendations and give its approval
for the contract to be awarded while the tenders are still valid.
Tender securities.
If the procuring entity requires suppliers, contractors or consultants who are submitting
tenders to provide any form of tender security or any form of guarantee or bond against
satisfactory performance of the contract, such requirement shall apply equally to all
suppliers, contractors (regulation 88)
TRAINEE ACTIVITIES
1. Read Part VI of the regulation and identify main steps in
tender proceedings.
2. Read Part VI of the Regulation and identify how
encouragement of the national can be exercised and when it
should be applied?
PROGRESS CHECK
1. How does efficient tender proceedings enhance Economy and
Efficiency as required by the Act.
2. What is a tender security and when can it be issued during
the tendering process?
Prohibition
Regulation 100 stipulates that procuring entities and approving authorities as well
as consultants under public financed contracts shall proceed in a transparent and
accountable manner during the selection and execution of such contracts as
required by Section V of the Act
Regulation 101 of the Act prohibits improper inducement of procuring entities,
approving authorities and tenderers in soliciting contracts either direct or
indirectly.
Regulation102 & 103 concerns conflict of interest. Members of the procuring
entities, tender boards and approving authorities shall declare their personal
interest which can influence decisions in any procuring contracts.
Miscellaneous Provisions
Liquidated damages Regulation 119 & 120 concerns pre-estimated rates of 0.10.2% of undelivered values of goods or materials and 0.1-0.15% of the contract
value for delayed works, up to a sum equivalent to the amount of the performance
guarantee.
Regulation 121 refers to continuous monitoring and evaluation of performance of
the contract by the procuring entity.
Goods delivered shall be inspected sampled and tested by the receiving entity and
procedures for inspection of goods shall be carried out by PE through inspecting
and counting the goods in order to ascertain whether they are correct and
complete in accordance with the agreement and the accounting officer shall
appoint a works inspection committee which shall inspect, supervise and see to it
that the work(s) is progressing in accordance with the approved programme of
works and order variations to the contracted work(s), if considered expedient in
Schedules
1st Schedule Authorized limits for accounting officers and heads of departments
2nd Schedule methods of selection and limit of application.
-
ICB - No limit
NCB - goods 800m, -works 3000m
Restricted tendering
Goods 400 m
Works 800 m
Competitive quotations
Goods 80 m
Works 200 m
Single source
Goods No limit but must be justified
Works 800 m
3rd Schedule
4th Schedule
TRAINEES ACTIVITIES
1. Read Part VII of the regulation under prohibitions and
explain the key areas of the prohibitions under the PPR of
2005
2. Read the relevant regulations under the miscellaneous
provision of the Act and explain what circumstances may
lead to the omission of regulation 126-127.
PROGRESS CHECK
1. With reference to the prohibitions listed in the PPR explain
how transparency and accountability during the selection
and execution of contract can be achieved.
GENERAL OVERVIEW
COMPETITIVE SELECTION OF CONSULTANTS
A procuring entity wishing to commence competitive selection proceedings shall prepare
inviting consultants to submit expressions of interest for providing the services required,
and such a notice shall be submitted in good time before the planned issue of the request
for proposal to the Secretary of the tender board.
(i)
The notice for invitation of consultants shall be published in the Gazette and it shall
contain:
(a) The name and address of the procuring entity;
(b) A brief description of the services to be procured; and
(c) The deadline and place of the submission of the expressions of interests.
(ii)
SELECTION OF CONSULTANTS
A procuring entity when selecting consultants may use the following principal selection
methods:(a) Selection based on technical quality by evaluation of the firms competence, the staff
seconded to the assignment and the technical value or quality of the proposal, or
(b) Selection based on the technical quality with price consideration, or
(c) Selection based on the lowest price after establishing compatibility of technical
proposals and the service to be provided.
Application Regulation 2.
Interpretation Regulation. 3
Consultants are permitted to compete for consultancy job without regard to
nationality except in case where a Procuring entity decides otherwise;
Foreign consultants shall be eligible if: (a): They are are registered or if elected are capable of being registered by the
relevant professional registration board; and
(b):They have entered into a voluntary joint venture or association with a local
consultant or if selected are capable of forming or entering into voluntary
joint venture or association with a local consultant.
(a)
(b)
(a)
(b)
(c)
(d)
(e)
If every proposal received exceeds the financial resources earmarked for the
contract
If there has been no competition.
TRAINEE ACTIVITIES;
3.
4.
Read Section 3 of the PPA No. 23 of 2004 and suggest which of the
definitions is more likely to be frequently used by the procurement
specialist in performing his/her duties.
Section 2 and section 4 of the PPA No.23 of 2004 are both concerned
with the application of the Act. Discuss
PROGRESS CHECK;
3.
4.
A procuring entity may restrict the issue of RFP to a limited number of specified
consultants when:a)
There is an urgent need for the services.
b)
Pre-qualification have been carried out
c)
Service required are within the competence of a limited number of
specialized consultants
PROGRESS CHECK:
3. Outline the Objectives of Selecting different consultants
4. Identify the Guidelines and Principles governing the Selecion and
Employment of Consultancy
(f)
Selection based on the lowest price after establishing compatibility of technical
proposals and the service to be provided.
Based
Based
Based
Based
on
on
on
on
technical Quality
technical quality with price consideration
compatibility of technical proposal and least cost consideration
quality and fixed budget
Procedures for selection based on technical quality Regulation 37, stipulates that
the firm which has submitted the best technically acceptable proposal shall be the
first to be invited for negotiation with its financial proposal opened first. If
negotiation fails the second ranked firm is invited for negotiations.
Conditions for application are outlined under Regulation 38 selection based on
combined technical quality and price consideration (Regulation 38.).
Two envelopes are submitted for technical and financial proposals respectively.
Technical proposals and evaluated first and those passing the minimum technical
score shall have their financial proposals opened in Public.
Technical proposal weights are combined with financial proposal weights and the
highest ranked firm is invited for negotiation first.
Selection based on compatibility
consideration (Regulation 39).
of
technical
proposals
and
least
cost
The firms, which submitted the technical proposals with weights not less than
80%, shall have their financial proposal opened and the firm with the lowest offer
shall be invited for negations.
Selection under fixed budget (Regulation 40) is the procedure under which the
RFP shall indicate the available budget and request the consultants to submit
technical and financial proposals within the budget; The firm with highest rank in
technical proposal whose budget is within the limit shall be invited for
negotiations.
Selection based on consultants qualification (Regulation 41) is for very small
assignments for which the need for preparing and evaluating proposals is not
justified. Very small means minor value contracts. TOR is prepared and them
EOI whereby a shortlist is established and a firm with most appropriate
qualifications and references are selected. The firm small then be asked to submit
a combined technical and financial proposal and then be invited to negotiate the
contract.
TRAINEE ACTIVITIES;
PROGRESS CHECK;
Regulation 42 provides that proposals shall be invited from five to ten qualified
and experienced consultants:
Principal stages are as per Regulation 42 (2)
(a)
Preparation of TOR
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(m)
(b)
Clear description of the nature and scope of the services required and their
context as well as the time interval in which they shall be provided.
(c)
(d)
(e)
(f)
(g)
Advertisement (Regulation 49) must be made for EOIs and copy sent to PPRA for
values exceeding TSh 100m, and giving a minimum of 14 days to respond to the
EOI.
Preparation of short list (Regulation 50 requires that at least 3 firms must be from
Tanzania.
RFP regulation 52 must be in the standard document prepared by the PPRA.
Information to consultants (Regulation 54)
Receipt of proposals must be within 30-90 days (Regulation 56).
Evaluation of proposals shall be two stage; for the quality and then the cost
(Regulation.57)
Evaluation of technical proposal shall use merit point system (Regulation
58)
Evaluation committee shall comprise 5 or more specialists. Regulation 58
(2)
Relative merit points for individual criteria out of 100.
(a)
5%-15% for general experience, reputation and experience in previous
similar assignments
(b)
20% - 40% for under standing of the TOR, methodology and overall quality
of proposal
(c)
30% - 60% for qualification of key personnel
(d)
5% - 15 % for local firms participation
(e)
5% - 10% for local participation by national export
(f)
5% - 10% for knowledge of the country
Regulation (8) specifies the ratings of individual key staff to be based on the
following:
a) General qualification:
- General education & training
- Length of experience
- Positions held
- Time with the consulting firm
- Experience in developing countries etc.
b) Adequacy for the assignment
- education
- training and experience in the specific sector, field, subject, etc relevant
to the particular assignment.
c) Experience in regional countries knowledge of local
administration system & culture.
language
PROGRESS CHECK;
What are the basic considerations when preparing TOR?
of
of
of
of
TRAINEE ACTIVITIES;
For more reference Read Part VI of GN 98 of 2005(Selection and
Employment of Consultant Regulation0.
Preparation of TOR
Opening and evaluation of tenders for works, goods and proposals.
Preparation of the brief where architectural services are to be procured
Revision and updating of feasibility studies
Preliminary or Project engineering design
Technical assistance for planning
Training
Assistance with project implementation
Preparation of project completion report
All other necessary assistance decided by the PE.
(c)
(d)
(e)
(f)
(g)
Regulation 79 (2) stipulated that for short-term assignments of a few weeks to one
or two months, the PE may after approval by the tender board recruit a qualified
individual consultant directly on the basis of information available.
Criteria for evaluation:
(a) General qualification and suitability 45%
(b) Experience in specific assignment 40%
(c) Language 10%
(d) Knowledge of the country 5%
TRAINEE ACTIVITIES;
TRAINEE ACTIVITIES;
11.0 PROHIBITIONS
When you complete this chapter you should be able to: Identify different disputes settlement methods
Determine time limit of reviewing procurement decicions
Regulation
Regulation
Regulation
Regulation
Regulation
Regulation
Authority
104:
105:
106:
107:
108:
109:
PROGRESS CHECK;
Examine time limits for reviewing procurement decisions and appeal
13.0 MISCELANEOUS PROVISIONS
o Regulations111) Role of consultant
o Regulation (112) Action by the Tender Board
o Amendment of the regulations
Schedules 1-7
Limits of methods
ICS
NCS
Limited selection
Single source -
No limit
800 m
500m
300m
PROGRESS CHECK;
Study all the schedules and time limits of authorities for schedule 1-7
TOPIC-2
1.2
1.3
a
a
a
a
a
plan
ploy
pattern (of consistent behaviour)
position
perspective.
Factors to take into account when deciding how far ahead to plan objectives
The organisations time horizon
Strategic lead time
Resource stability
Estimated life of production or service facilities
Estimated life of products/services
Reliability of forecasts
BUYING STRATEGY
The roles, which distinguish the procurement entity in public sector from that of
industrial organisation, include those of:
A supplier of wide variety of goods and services to many departments and
agencies, which in turn, use those items to produce public service and
support internal operations
A decision maker, which must strike the balance between quality, total cost,
timeliness, control, accountability and politics.
A staff adviser, which assists management and line departments in
developing budgets, planning projects.
An implementer of socio-economic policy in the frontline of economic
development for local, small and the disadvantaged business.
For goods, the cycle ends when the organization has consumed or disposed
of the item.
For services, it ends when the final payment has been made.
Planning and scheduling, supplier selection and contract management are
the three principal phases in cycle.
PURCHASING REQUISITIONING
Requisitioning for goods and services has been a major source of inefficiency and
delay due to lack of understanding between the purchasing department and the
operating departments of their respective needs. There may be hundreds of
requisitions dispersed throughout a large Organization that may cause difficultly
in processing the requisitions by the buying department. Additionally, most
requisitioners are technical people such as doctors, engineers, field experts, etc.
Who have very low tolerance for the competitive procurement process
THE
After the preliminary annual work plan and budget has been developed for the
coming year, procurement plans are then developed for the same period. A
precise procurement plan should be structured for each major material or
category of materials.
There are three major steps in developing a precise procurement plan:
Demand analysis
As a general rule, the 80-20 phenomenon holds for most organizations, and for
obvious reasons, it is particularly important that plan for top 20% or 50% of the
materials be developed using careful detailed analyses. The 80% of the materials
that account for approximately 20% of the firms expenditures are grouped by
general classifications and a plan is made for each group of similar items.
Market analysis
Since the buyers major initial concerns are availability and price, the
anticipated supply and demand factors, along with their expected stability,
must be reviewed
Supplier analysis
PACKAGING OPTIONS.
For Goods and Works
Sub-categorize requirements according to similarities of items to procure;
size of each package should be appropriate to obtain maximum possible
competition from qualified bidders
Group requirements to get larger size of contract to facilitate international
competitive bidding (ICB) and to get economies of scale
Create Lots within a single procurement proposal
(a) To reduce the number of procurement proposals, and
(b) To facilitate procurement of grouped items as a Lot
PACKAGING OPTIONS.
For Consultancy services
OPTIONS
ON
METHODS
For Goods and Works
OF
PROCUREMENT
PROCEDURES
FOR
Learning Objectives:
When you have completed this topic you should be able to:
o Is the means that play important role in the search for the quality
and the right value
o Assist in resolving design conflicts between departments and
therefore this is the heart of resulting purchase order or contract.
o Is the method of describing requirements
o It is important to have written description of quality of goods and
their impact.
Objectives:
The Technical Specifications should require that all goods and materials to
be incorporated in the goods be new, unused, and of the most recent or
current models, and that they incorporate all recent improvements in design
and materials, unless provided for otherwise in the contract. Cautions in
Purchasing Used Equipment .It is difficult to determine the true condition of
a used machine and to estimate the type and length of service it will
provide. For this reason it is wise to have one buyer specialized in used
equipment. Moreover, it is virtually essential to enlist the cooperation of an
experienced production or maintenance specialist in appraising used
equipment. It is always sound practice to check the reputation of a used
equipment supplier and to shop around, inspecting several machines before
making a purchase. Whenever possible, a machine should be observed
under power through a complete operating cycle. Finally, a prospective
buyer should determine the age of a machine. If not available in the seller's
records, the age of a machine can be traced through the manufacturer
simply by serial number identification. The combined knowledge of age and
usage history is a key guide in predicting the future performance of a used
machine.
The Technical Specification should make use of best practices. Samples of
specifications from successful similar procurements in the same country or
sector may provide a sound basis for drafting the Technical Specification.
The use of metric units should be encouraged.
Trainee Activity:
Any specification intended for repeated use becomes a standard. The word
standard refer to anything we use as a measure; we speak for instance of a
standard of length, a standard of living, a standard of value. A builder who builds
every house to a different specification has not standardized his main product; but
he may well have standardized some part of it, for instance the kitchen. If he
supplies a standard kitchen in each house, this is to say that the kitchen in each
house is built to the same specification. The word also implies the notion of
measuring or comparison; if one of the kitchens does not comply with the
specification, we would say it is not up to standard. The organized process of
formulating standards and getting everyone concerned to adopt them is called
standardization.
DESIGN ANALYSIS
When designing technical specification the application of Design analysis is
important.
Value analysis and value engineering are jointly used.
Value
engineering application, focuses on new specifications developed at the engineering
design stage. On the other hand, in most analysis applications, management
attempts to coordinate the talent of personnel in engineering, operations and
purchasing in conducting a meticulocis investigation, which usually leads to
improvement of existing rather than new specifications.
Design analysis entails a methodical step-by-step study of all phases of the design
of a given item in relation to the function it performs. The philosophy underlying
this approach is not concerned with appraisal of any given part per se. Rather, the
appraisal focuses on the function, which the part, or the larger assembly
containing the part, performs. This approach is designed to lead the analyst away
from a traditional perspective which views a part as having certain accepted
characteristics and configurations. Instead, it encourages the analyst to adopt a
broader point of view and to consider whether the part performs the required
function both as effectively and as efficiently as possible. Both quality and cost are
objects of the analysis.
One technique many firms use in analyzing component parts of a subassembly is
to dismantle, or explode the unit and then mount each part adjacent to its
mating part on a pegboard or a table. The idea is to demonstrate visually the
functional relationships of the various parts. Each component can thus be studied
as it relates to the performance of the complete unit, rather than as an isolated
element. Analysis of each component in this fashion attempts to answer four
specific questions:
1. Can any part be eliminated without impairing the operation of the complete
unit?
2. Can the design of the part be simplified to reduce its basic cost?
3. Can the design of the part be changed to permit the use of simplified and less
costly production methods?
4. Can less expensive but equally satisfactory materials be used in the part?
When viewed in this manner - from the standpoint of composite operation and
cost-possibilities for making component design simplifications are frequently more
apparent than is possible under the original design conditions. This in no way
reflects unfavorably on the work done by the design engineer. The discovery of
such potential improvements is simply the product of an analysis with a
substantially broader orientation than that possessed by the original designer. An
organized value analysis study usually utilizes a number of individuals with
different types of background, experience, and skill impossible to combine in the
person of a single designer. Resulting design changes often permit the substitution
of standardized production operations for more expensive operations required
special setup work. In some cases, considering the volume of parts to be produced,
an entirely different material or production process turns out to be more efficient
than the one originally specified.
TRAINEE ACTIVITY:
CHAPTER 3
TITLE: HOW BALANCED SPECIFICATIONS ARE
DEVELOPED
LEARNING UNIT 1: PREPARATION OF TECHNICAL
SPECIFICATIONS AND SCHEDULES OF REQUIREMENTS FOR
GOODS
3.l
General Outline
3.1.1
Learning Objectives:
When you have completed this chapter you should be able to:
Define and apply all the approaches for preparation of balanced technical
specifications.
3.1.2
3.1.3
General Outline.
Introduction.
Approaches to Develop Balanced Specifications.
Trainee Activity.
Progress Check.
3.1.4
APPROACHES
SPECIFICATIONS:
TO
DEVELOP
BALANCED
(b)
(c)
(d)
TRAINEE ACTIVITY:
CHAPTER 4
TITLE:
LEARNING UNIT 1: PREPARATION OF TECHNICAL
SPECIFICATIONS AND SCHEDULES OF REQUIREMENTS FOR
GOODS
4.l
General Outline
4.1.1
Learning Objectives:
When you have completed this chapter you should be able to:
4.1.2
Prepare specifications.
4.1.3
General Outline.
Needs in writing Specifications
Examples of Writing Specifications.
Trainee Activity.
Progress Check.
4.1.4
4.2
INTRODUCTION
WRITING SPECIFICATIONS
After a design of a product is determined, the next step is to translate the
individual part and material specifications into written form. The need for
clarity and precision of expression is important in all business
communication emanating from purchase contracts.
Optimal performance in all departments is contingent on good
specifications. To meet the needs of all departments, a specification must
satisfy the following requirements:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
Production controls
economically.
(vii)
requirement
to
schedule
the
material
No.0114
Date Issued: 15.08.02
Replaces
---------
Tomato Paste shall be the product resulting from concentration of the liquid
obtained from clean, sound, well ripened tomatoes of red varieties. Free from
skin, seed particles, black specks, foreign material, added salt or colouring
and harmful contaminants.
2. ORGANOLEPTIC REQUIREMENTS
a. Flavour and Aroma
Free from scorched, bitter, green tomato flavours or
objectionable flavours or objectionable odours of any kind.
b. Colour
Gardner Colour difference meter targets at 12 % total solids by
refractometer: L25 1, a 25 +, b + less than a.
double fuel filter, Rear differential Lock, power door lock/power windows
Anti-Theft immobiliser Security system, Electrical winch.
TRAINEE ACTIVITY
With example describe the process of writing specifications .
machining the pulleys from bar stock. The second decision would be to
select an industrial standard for the part, regardless of the method of
manufacture used. This decision leads directly to a consideration of
standardization.
Commercial Standards
Design specification (generally accompanied by engineering drawing)
Material and method-of-manufacture specification
(i)
(ii)
Samples
When samples are used, the buyer does not have to look for an equal brand,
pick a standard specification, or describe the performance wanted. Samples
Market grades
Grading is a method of determining the quality of commodities. A grade is
determining by comparing a specific commodity with standards previously
agreed on, e.g. on wheat, hides, cotton, etc. In buying graded commodities,
buyer often use personal inspection as part of their buying techniques. This
is done in the same way one selects a shoe in a shop.
Qualified Products
This method is applied when it is necessary to determine in advance of
purchase whether a product can meet specifications. For example:
(a)
when it takes too long to conduct the normal post purchase
inspection and test to ensure quality compliance.
(b)
When special tests are involved, and
(c)
When purchase involves safety equipment, life survival equipment,
research equipment, etc.
Combination of methods
A combination of more than one method may be used when a single method of
description cannot adequately describe an item, e.g. something like space vehicle.
Performance specifications could describe overall characteristics of the vehicle, i.e.
its ability to withstand certain temperatures; physical specification describes the
vehicles configuration, commercial standards or brand names used to describe
selected pieces of electrical hardware for its support systems.
TRAINEE ACTIVITY
(1)
(2)
But with the increase use of International Standard now we have three kinds of
materials standards.
If the designer or user cannot adopt a national standard for his/her purpose
the second choice is to use a company standard. But if the required part is
truly a non-repetitive special then use of standard is impossible. The
increase of international trade and by eliminating technical trade barriers
the need for international standards is fundamental.
The standards specifications, which are the specification for the items that
have been standardized, can be obtained from the organizations that have
developed them, such as Tanzania Bureau of Standards and many of
commercial trade associations, and testing associations. Some of the
standards used are adopted from international organizational standards like
BS ie, British Standards, American Bureau of Standards which share the
common standards like bolts and nuts sizes, electrical equipments and
spare parts. In 1979 the International Standard Code Multilateral Trade
Agreements was signed which involved thirty signatory nations including
United States, The European Economic Community, The Nordic countries,
Canada, New Zealand and Japan who current use the code.
The mechanism used to create international standards was relatively easy.
However, actually getting International Standards adopted will be a long and
difficult task. Consider just a few of existing difficulties. Many countries
includes United States are in the early stages of implementing metric
standards. Although metric standards are use din both Europe and Japan,
product dimension have not been standardized so parts from these
countries are not yet interchangeable.
Standardizing electric power
characteristics in a very difficult problem; for example voltage requirements
for electrical equipment vary significantly between the United States and
Europe. In short countries around the world currently have widely different
standards for virtually everything from safety to ecology.
Nevertheless, simply because there is no quick or easy way to get
international standards adopted does not mean that progress will not be
made.
The economic states associated with the development of
international standards are so high in terms of increased international trade
and prosperity that progress, albeit slow, is inevitable. Because private
organizations, national and regional governments and other international
organizations are all involved in the adoption process, political infighting is
inescapable. This of itself precludes fast action.
The value analysis process insist of six steps; identification, appraisal, solution
generation, solution evaluation, implementation planning and execution, and the
project follow-up.
Identification:
The identification step determines the functions of the item, the customers
requirements, the costs, the value of function and the service and
maintenance issues that are present. The value analysis team must identify
the facts that are known about the items under analysis, the assumptions
that are being made, and the information that is not known.
Appraisal:
Solution Generation:
Solution Evaluation:
Once a set of potential solutions is generated, the next stage in the process
is to evaluate the feasibility, appropriateness and cost of each potential
solution. The team must evaluate if each solution is technically feasible and
evaluate the suitability of a particular solution.
Implementation Planning and Execution:
Once a preferred solution is identified the team needs to develop a plan for
making the required changes in the product and/or process.
Project Follow-up:
Probable the most important stage of the process is to verify that the project
objectives were achieved. Has the items cost been reduced? Does the
consumer perceive an increase or maintenance of value?
TRAINEE ACTIVITY
Discuss the use of National and International Standards.
In absolute terms
Relative to perceived need
As conformance with stated requirements
In Absolute Terms
Quality is the function of excellence, intrinsic value, or grade as
determined before by society generally. Hence most people consider
gold to be a high quality precious metal. In a more utilitarian sense
MATERIAL SPECIFICATION
A sound material specification represents a blend of four different considerations:
1.
2.
3.
4.
Design requirements
Production factors
Commercial purchasing considerations, and
Frequently marketing factors.
Prediction
Time
Size
Fig. 2 and 3:
process
Buyers acceptance
range of quality
Natural range of process
quality capability
0.996
0.995
1.004
1.005
Fig. 2
Buyers acceptable
range of capability
0.997
0.996
1.003
1.004
Fig. 3
No operations activity can produce identical results time after time. This is true
even for machine-based production processes. Every process possesses some
natural variability due to such things as machine part tolerances or clearances,
bearing wear, lubrication, variations in operator technique, and so on. These are
common causes, which produce random variations in the output. Overtime, this
natural variability in the output of a process will produce a distribution of outputs
around the mean quality level. In many cases this distribution approximates the
normal bell-shaped curve. The difference between the two extremes of the curve,
the high and low values are defined as the natural tolerance range of the process.
As long as the process is properly adjusted and is not affected by any outside nonrandom forces as long as the process is in control the distribution it produces
is predictable (shown in Fig. 1).
If a buyers desired range of quality for a given purchased part is compatible with
the natural tolerance range of a potential suppliers production process, the
supplier should have a little difficult in providing the buyer with parts that meet
specifications. On the other hand, when the buyers required quality range is
narrower than the natural capability range of the process, the supplier is bound to
produce some unacceptable parts.
Alert buyers recognize the direct economic relationship between their specified
quality requirements and the produces ability to perform consistently at the
specified level. In the case of a non-standard item, the capable buyer before
selecting a supplier, must determine:
1. Whether the potential supplier in-fact knows what the natural capability
range for its production process is;
2. If so, whether the buyers desired range of quality is compatible with the
suppliers natural capability range; and
3. If so, how the supplier plans to monitor the process to ensure that it
stays in control so that it will consistently produce satisfactory output.
The following examples should clarify this concept.
In figure 2(a) assume that a buyer want to purchase 100,000 metal shafts 1
inch in diameter, with a tolerance of + 0.005 inch. Assume further that the
supplier has studied his process, stabilized it, and knows its natural
capability for this type of job to be 1 inch + 0.004. Examining Figure 2, the
buyer sees that as long as the suppliers process operates normally and
remains centered on 1:0 inch, every piece produced will fall within his/her
acceptable range of quality. In this example, then if the supplier is able to
keep the process in control, this situation appears to represent a sound
purchase for the buyer from a quality point view
Assume now that the buyer wants to purchase 100,000 shafts 1 inch in
diameter, with a tolerance of + 0.003 inch. Examination of Figure 3 reveal
that, dealing with the same supplier, under normal operating conditions,
the production process cannot entirely satisfy the buyers requirement.
Some shafts will be produced with diameters less than 0.997 inch and some
with diameters larger than 1.003 inches. It is important for the buyer to
understand this type of situation. Unusable shafts, whether re-worked or
scrapped, must be paid for. In the long run it will be the buyer who pays.
Assuming that the buyers requirements cannot be compromised, he or she
is faced with two alternatives:
Negotiate with the supplier to determine whether the natural range of
process capability can be narrowed economically to a point nearer the
buyers requirements.
Seek another supplier whose process can meet the requirements more
economically.
0.01 = 1.25
0.008
Example
S/N DESCRIPTION (S)
UNIT
QTY
DELIVERY PERIOD
FROM CONTRACT
SIGNATURE
(ii)
At EXW premises
(ii)
(iii)
In order to determine the correct date of delivery hereafter specified, the purchaser
has taken into account the additional time that will be needed for international or
national transit to the Project site or to another commonplace.
CLASS ACTIVITY
Prepare a schedule of requirements for a photocopying papers need by your company for annual
use.
Reference Materials:
ii)
iii)
iv)
v)
vi)
vii)
viii)
Plastering of 25mm will be used with the mortar ratio of 1:3 cement sand.
Tairolean (putching) of mixture of cement, lime and sand will be applied for
finishing.
Example 1
Top concrete
slab
100mm
Block
walls
225mm
3000mm
Block
walls
Bottom
round
concrete
base
150mm
1500mm
2.
3.
The Technical Specification should make use of the best practices. Samples
of specification from successful similar procurements in the same country
or sector may provide a sound basis for drafting the TS.
4.
5.
Standardizing
technical
specifications
under
General
Technical
Specifications may be advantageous, depending on the complexity of the
construction and the repetitiveness of the type of procurement. Technical
Specifications should be broad enough to avoid restrictions on
workmanship, materials, and equipment commonly involved in
manufacturing similar kinds materials even if these may not necessarily
apply to a particular procurement. Particular technical requirements for a
particular procurement would be in each case specified through deletions or
addenda to the Technical Specification.
6.
When the purchaser requests that the bidder provides in its bid a part of all
the technical specifications technical schedules or other technical
information, the purchaser shall specify in detail the nature and extent of
the required information and the manner in which it has to be presented by
the Bidder in its Bid.
DRAWINGS
This is the major part of specification in the procurement of works. The
purpose of drawings it to specify locations, dimension, materials to be used,
stages of construction, details of hidden parts, and other characteristics of
work or construction.
The purchaser should prepared appropriate drawings as needed this is
normally prepared by Architects and later bill of quantities which are
prepared by Quantity Surveyors. This is done through procurement of
consultancy services.
The purchaser includes the drawings in the Bidding documents. Such
drawing which are part of schedule of supply are contract documents and
therefore shall be part of contract. Similarly the purchaser may request the
contractor to provide drawings either with its bid or for approval during
contract execution.
Bills of Quantities are the statements, which state the quantities of materials and
labour for the various sections of works. They state the general condition of
works, workmanship required and quantity of materials.
3.1.1 Function of Bills of Quantities
1.
Helps bidders to quote in a uniform manner
2.
3.
Assists and act as the base for valuation during work progress or
construction (interim valuation)
4.
5.
6.
Decide on unit of measure and dimensions i.e. linear (Running meters), Area
(M2) (volume) (M3) and weights (kg), Pcs, etc.
2.
3.
(ii)
The contractor shall provide and maintain for his workers latrine
facilities, washing and drinking water, first aid equipment, first aid
equipment and shelter equipped with tables, benches and cooking
facilities all to the reasonable satisfaction of Project Manager and the
Health Authorities.
(iii)
The contractor shall provide and maintain any temporary storage shed
or building which in his opinion are necessary for execution of the
works.
(iv)
Telephone:
Allow for the installation, paying bills and later removal of the telephone for the
sole use of the Project Manager at site if the service is available.
Water for Works
The contractor shall allow for all necessary clean fresh water for the works,
including that required by subcontractors and for any temporary plumbing meter
and storage facilities and pay all the changes in connection therewith and clear
away on completion and make good all works disturbed.
Lighting and Power for the Works
The contractor shall allow for providing and maintaining a temporary electricity
supply for the works including that required by subcontractors and for any meters
and fittings to give artificial lighting and power necessary for the execution of the
works and pay all charges in connection therewith and clean away on completion
and make good all works disturbed.
Watching and lighting
The contractor shall allow for providing and maintaining any barrier, loading,
watching and lighting which must comply with the bylaw or requirements of the
local Authority and Police Regulation and the contractor must give all requisite
notices to these authorities and provide everything necessary to protect the
general public, workmen, plant, materials and the whole of the works from injury
or damage.
Signboard
The contractor shall provide and exact a signboard on the site showing the little of
the contract, the name and address of Employer, Project financier, Project
Manager, Nominated subcontractors and such information as may be required by
the Project Manager.
Protection
The contractor is required to protect the works in all sections until practical
completion.
Removing rubbish and cleaning
The contractor shall remove all rubbish and superfluous materials from the site of
the works with all reasonable speed from time to time and at completion.
Disturbance or Nuisance
The contractor shall allow for taking all necessary precaution in the cause of
execution of the works as to avoid causing disturbance or nuisance to the
occupants of the existing building and those adjacent to the works and complying
with the Project Managers instructions in this respect.
Trespass, Damage and care of works
The contractor shall prevent any trespass on the adjoining property, and he shall
take reasonable precautions during the progress of the contract to prevent any
damage to the adjoining property or public or private read ways and to prevent
materials, plant; rubbish, debris etc.
The contractor will be reasonable for protection of adjoining buildings, boundary
walls, fences, services either overhead or underground and for the making good of
or paying for all damage there to should such be caused in the course of building
or civil operations.
The contractor shall be required to take all reasonable care during alternations as
not to damage the existing structure.
The collection of the above priced items are added and taken as the total
Preliminary Items which be carried to General Summary.
Part two of Bill of Quantities after the Preliminary items which are quoted in lump
sum is that part which is normally divided into Elements and are Quoted
according to the provided units.
The costing is done according to Work
Breakdown Structure (WBS). Starting from the first activity to the required last
finishing activity.
The elements, which form part of similar materials, are collected in one Bill of the
PACKAGE EXAMPLE: BILL NO. ------------------------- ACCOMODATION UNIT
ITEM DESCRIPTION
ELEMENT NO.1
substructure
Element No. 2
Frame
Element No. 4
Walling
Element No.5 Doors
Element no.6
UNIT
QUANTIT
Y
RATE
AMOUNT
(TSHS
windows
Element no. 7
Roofing
Element no. 8
Finishing
Element no.9
Decorations
Element no.10
Fitting & fixtures
Element no. 11
Plumbing and
Engineering
Installation
Element No. 12
Drainage
TOTAL ACCOMODATION
GENERAL SUMMARY
UNIT
CARRIED
TO
PREPARATION OF BOQs
Normally the Bill of Quantities shall be read in conjunction with the Instruction to
Bidders, General Conditions of Contracts, Technical specification and Drawing.
A rate or price shall be entered against each item in the priced Bill of Quantities.
The cost of items against which contractor has failed to be fill, shall be deemed to
be covered by other rates or prices entered in the bill of Quantities.
The detailed drawings, which are used for preparation of Bill of Quantities, are
normally attached with BOQ for the proper quotation.
In the preparation of BOQ the description of the site location is necessary. The
Bidder is advised to visit the site and acquaint himself with the nature and terrain
of the sites.
The reason of visiting the sites is to make the contractor to satisfy himself as to:
The nature of the sites
The amount of bush, rubbish or debris to be cleared away before
commencement of work
The nature and size of any adjoining buildings and property
Sources of electricity water etc.
After the description of site the BOQ has also to describe the works to be done
whether it is Building works or Civil Works. It is also to describe whether there is
an external works like construction of rainwater harvesting system, which may
include supply and installation of rainwater roof gutters and pipes for building
works and Excavation and construction of Catch Water drainage and Mitter for
Civil Works.
DESCRIPTION
ELEMENT No. 1: SUBSTRUCTURE (All Provisional)
EXCAVATION AND EARTHWORK
QTY
UNIT
RATE
AMOUNT
(TSHS)
CM
1,000.00 4,000.00
33
CM
1,000.00 33,000.00
33
CM
2,000.00 66,000.00
CM
5,000.00 5,000.00
CM
2,000.00 14,000.00
18
CM
600.00 10,800.00
SM
2,000.00 10,000.00
53
CM
1,500.00 79,500.00
the like
ITEM
ITEM
bed
(measured separately).
21
SM
3,500.00 73,500.00
bed
SM
3,500.00 7,000.00
SM
3,500.00 3,500.00
LM
1,000.00 2,000.00
To collection
308,300.00
ITE
DESCRIPTION
QTY
UNIT
RATE
AMOUNT
(TSHS)
Soil sterilisation
A
SM
600.00 3,000.00
22
LM
500.00 11,000.00
CM
80,000.00 80,000.00
22
SM
264,000.0
12,000.00 0
SM
12,000.00 24,000.00
LM
4,000.00 4,000.00
LM
4,000.00 4,000.00
17
SM
204,000.0
12,000.00 0
150mm Bed
150mm Ramp
NO
4,800.00 19,200.00
NO
2,000.00 4,000.00
17
SM
3,500.00 59,500.00
13
SM
2,500.00 32,500.00
24
LM
600.00 14,400.00
To collection
723,600.0
0
ITE
DESCRIPTION
A
QTY
UNIT
RATE
AMOUNT
(TSHS)
17
LM
600.00 10,200.00
LM
600.00 1,200.00
SM
2,500.00 2,500.00
54
SM
No
1,000.00 2,000.00
to concrete blockwall
12
SM
1,500.00 18,000.00
12
SM
1,000.00 12,000.00
WALLING
Solid concrete blocks to BS 2028 type "A" bedded
and jointed in cement mortar (1:3)
230mm Wall
______________
Build end of 100mm PVC pipe through 230mm
blockwall and make good sorrounds
12,000.00 648,000.00
Finishes
F
To collection
693,900.00
COLLECTION
308,300.00
723,600.00
693,900.00
1,725,800.
00
ITE
DESCRIPTION
QTY
UNIT
RATE
AMOUNT
(TSHS)
CM
90,000.00 90,000.00
119
Kg
600.00 71,400.00
28
Kg
600.00 16,800.00
10
SM
2,500.00 25,000.00
62
SM
10,000.00 620,000.00
10
LM
2,000.00 20,000.00
Reinforcement
Mild steel bar round bar reinforcement to BS
4449:1969
16mm Bar
8mm Bar
Sawn formwork to
150mm Wall
Raking cutting
SM
10,000.00 50,000.00
893,200.00
ITE
DESCRIPTION
QTY
UNIT
RATE
AMOUNT
(TSHS)
NO
70,000.00 140,000.00
NO
60,000.00 120,000.00
20
LM
3,750.00 75,000.00
19
LM
600.00 11,400.00
20
LM
1,000.00 20,000.00
Ironmongery
Supply and fixed the following ironmongery as
manufactured by "UNION" or other equal and
approved fixed to hardwood with matching screws
PRS
3,500.00 21,000.00
NO
1,000.00 4,000.00
391,400.00
ITE
DESCRIPTION
QTY
UNIT
RATE
AMOUNT
(TSHS)
24
SM
14,000.00 336,000.00
No
2,000.00 4,000.00
10
LM
1,800.00 8,000.00
50 x 150mm Rafters
20
LM
1,800.00
36,0
00.00
900.00
20,7
00.00
4,000.00
32,0
00.00
50 x 75mm Purlins
23
LM
Vent pipe
Unplasticised PVC pipes and fittings to BS 4514
G
H
Bend
Copper wire balloon set on top of 100mm pipe and
covered with mosquito gauze
LM
NO
2,000.00
4,000.
00
NO
2,000.00
4,0
00.00
TOTAL, ROOFING CARRIED TO SUMMARY OF BILL
No. 8/11/8
454,700.00
ITE
DESCRIPTION
QTY
UNIT
RATE
AMOUNT
(TSHS)
12
SM
4,000.00 48,000.00
SM
4,000.00 32,000.00
LM
1,300.00 2,600.00
LM
600.00 2,400.00
NO
3,000.00 12,000.00
NO
2,000.00 4,000.00
64
SM
1,800.00 115,200.00
28
SM
1,800.00 50,400.00
15mm To walls
External cement and sand (1:4) rendering with
approved plasticizer in two coats, steel trowelled
to a smooth finish
15mm To walls
External Tyrolean render in three coats
22mm To walls
39
SM
2,200.00 85,800.00
352,400.00
ITE
DESCRIPTION
QTY
UNIT
RATE
AMOUNT
(TSHS)
Plastered walls
41
SM
1,000.00 41,000.00
SM
1,000.00 5,000.00
23
SM
1,200.00 7,600.00
20
LM
240.00 4,800.00
SM
1,200.00 7,200.00
40
LM
240.00 9,600.00
28
SM
1,000.00 28,000.00
Plastered walls
Prepare and prime only wood surfaces before fixing
General surfaces
Rendered walls
SM
1,000.00 5,000.00
LM
120.00 960.00
129,160.0
0
ITE
DESCRIPTION
QTY
UNIT
RATE
AMOUNT
(TSHS)
1,725,800.0
0
893,200.00
391,400.00
454,700.00
352,400.00
129,160.00
3,946,660.0
CASE STUDY
A Special Procurement Audit conducted by a consultant for the Chanika
consulting agency revealed that the cost for constructing a conference hall was
higher than the budget by TShs. 7.0m. The auditors observed that the higher
costs were due to unnecessary steel reinforcement, which were used in the
construction of floors. The Specifications for the floor work indicated that
1000kgs of round bars were used to reinforce the floors. When asked, the
engineer said that this was because he wanted a floor, which could not deteriorate
easily.
Furthermore, the bricks used were made of concrete to support a heavy roof made
of 4x 6 timber traces placed 20cm apart.
The Engineer justified the
specifications by saying that the conference hall shall be used by students whom
he thought are normally shouting and he would not like to disturb passers-by.
TASK
Explain how Procurement Specialist could assist in the preparation of BOQ to help
reduce the costs.
(a) For reaching agreement among the responsible agencies within the
country or sector concerned, and between the executing agency and
the prospective financing agency, on the objectives and scope of the
proposed assignments
(b) To inform prospective consultants of the objectives and detailed
intended scope of work when they are invited to submit proposals (The
TOR is normally enclosed with the Request for proposals or in special
circumstances at the stage of the Expression of Interests) and
(c) To define the Consultancy services in the contract to be negotiated
after selection
(ii) Normally the TOR shall include and provide:
(a) A precise definition or statement of the assignment, objectives and goal
set
(b) A clear description of the nature and detailed scope of services required
as well as the context
(c) Qualification and experience of the consultants and counterparts staff
(d) Training of the required services (the time interval in which they shall
be provided)
(e) Location or place of the assignments to be carried out
(f) Specific description of the outputs, duties responsibilities of the
consultants
(g) Specific description of the inputs, duties and responsibilities to be
provided or undertaken by the client or procurement entity
(h) Background information of the problem areas, available data, reference
to all previous studies related to the assignment. This should provided
by the procurement
(i) Information on any counterpart staff and its role
(j) Information on training and the transfer of technology where necessary
(k) Summary of facilities and services which the procurement entity will
provide to the consultants
(l) Fees to be paid and the relevant payment modality
(m) The reporting requirements either
i. Draft report to be presented
ii. Final report
(n) Furthermore the TOR should
Scope of Service
The scope of service for consultants work is to be defined in a detailed engineering
designs following successful feasibility study since on the one hand the basic
characteristics of the project and the related problem areas are known and on the other,
the technical specifications and other important criteria may be determined on the basis
of study.
Projects for which there are no or insufficient pre-investment studies shall be given
particular attention regarding technical design parameters.
For very large projects or where the nature of the work requires major inputs from
diverse disciplines, it may be deemed necessary to retain more than one consultant. In
such cases, the terms of reference will include specific provision for coordination of
various consultants work.
For the preparation of final detailed designs and tender documents, the
procurement entity requires the consultant to be made solely responsible for the
accuracy and the suitability of its work. The terms of reference will provide,
therefore, that while the buyer shall supervise and review the consultants work,
no modifications shall be made in the final documents prepared by the consultant
without his consent. As appropriate the consultant may be appointed to act as
adviser to the buyer on all technical problems related to the project, with
authority to make final decisions within such limits as may be prescribed by the
buyer.
For works supervision and inspection services, the definition of the consultants
tasks is in general fairly simple. There may be instances; however, where the
buyer may consider that an additional consultant is necessary because of the
complexity of the project or the highly specialized nature of the inputs from
diverse disciplines.
In such case, the terms of reference will provide for coordination of the work and specify
the responsibilities of the different consultants.
Counterpart Staff
The Government insists that, during the acquisition of consultancy services,
qualified counterpart employed by the procuring entity or its executing
agency be involved in the assignment. Ideally, in some types of assignments
such as feasibility studies, would be desirable to assign to each key experts
of the consultants team and the counterpart from the executing agency, if
possible temporarily released from his function.
In view of the staffing constraints of the executing agencies the members of
counterparts shall be determined on a individual basis depending on the
importance of the assignment and the requirement of the executing agency
or procuring entity.
The role of counterpart varies from assignment to assignment and includes
the following responsibilities and elements:
a) Through a day-to-day contact with a consultants experts, benefit from
a transfer of skills and thus receive on the job training.
b) Liase between the organs of the procuring entity and the consultants
and assist the latter with data collection providing it will all available
information, documentation and studies of assignment.
Prior to any decision regarding the level, qualifications, number and
responsibilities of each counterpart, discussions shall be held during the
negotiation to determine:
a) The number and responsibilities of the counterpart staff cooperating
with the consulting team.
b) The extent to which counterpart staffs are released from their normal
duties.
c) The extent to which counterpart can fit into the consultants proposed
work schedule.
d) The arrangement made to cover field and travel expenses of the
counterpart staff.
e) The arrangements for Training replacements of unsuitable counterpart
staff.
1.6.2
Training
The strengthening of national capability `of agencies or agent in the
procuring entities through a transfer of knowledge and skills to local
professionals, is of key concerned to the government.
It is based on programmes which falls within the frame work or assignment
whose principle objective may not necessarily be training and transfer of
technology, but which meet requirements related to the principal project or
its sector and the programmes may provide an opportunity for strengthening
the capacity of the counterpart staff involved in the assignments to that of
the national staff participating in a joint venture between foreign
consultants.
For the successful implementation of this programme, the procuring entity
must be convinced of its necessity, and consequently, sele1ct the necessary
qualified professionals to participate in it, and release these professionals
for the duration of the programme. The consultant shall accept the training
function and its inclusions an obligation which is separate and distinct from
the other services and propose corresponding costs and an implementation
time frame.
The objective of the programme shall be define and included in the TOR sent to
the consultants invited to submit proposals; it will be defined during the
negotiations both with regard to trainers, trainees, the skills to be transferred
both with regard to trainers, trainees, the skills to be transferred and the timeframe.
1.6.3
The cost estimate and budget for key staffs shall be based on the Terms of
Reference. The budget shall be as detailed and as accurate as possible.
Although assignments often vary in importance, type, duration and complexity, the
buyer shall be able to prepare a detailed estimate by breaking down each
assignment into activities to be undertaken in time, in a given order and
subsequently determine the duration and cost of each.
An estimate of the level of key staff inputs (in staff month) require of the
consultants, and indication of minimum expense, academic achievement
and so forth, expected of key staff of the total budget, if a given figure
cannot be exceeded.
Therefore the principal cost categories and characteristics on which the cost
estimate based are the following:
(a)
(b)
(c)
(d)
(e)
(f)
An amount shall always be allocated, over and above the basic costs,
to cover physical and price contingencies.
Some items of the cost estimate in foreign exchange or in local currency may be
reimbursable and, as such, shall be clearly identified. These could be cost
covering, travel, and vehicles equipment purchased especially for the assignment,
some surveys and special investigations.
Any taxes and customs duties component of the cost estimate shall also be
identified and appropriately handled by the buyer.
Trainee Activities
This section deals with the definition of the assignment goals and objectives.
The objective should be clear and straightforward. Ambiguous statements
should be avoided as far as possible. Here are just a few of the objectives of
the project, to illustrate.
(a) Objectives:
(a) To present a program that will enable a learner to put together a
plan, schedule, and control system by the end of the class.
(a) To develop a course that is highly practical, rather than theoretical.
(No date is needed for this objective.)
(a) To have the course reviewed by at least two experienced project
managers by December 30,1995.
(b) A list of deliverables would include the following:
i.
ii.
iii.
iv.
The first step is to develop a problem statement. Here is the one written for
this project:
Problem Statement: New project managers usually have no formal training
in the tools and techniques of project management. They do not know how
to plan, schedule, and control a project and therefore try to manage by the
"seat of the pants."
Based on this problem statement, an overall statement of the goal of the project
can be written. Following is the goal of the training program project:
Project Goal: To develop a training program for new project managers that
will teach how to develop a project plan, a schedule with resources allocated
realistically, and a control system. The program should be completed by
November 30,2002.
It is a good idea at this point to list the assumptions that will govern the project
plan and have those agreed upon before going further. Some of the assumptions
that might govern this project include:
Project Scope: The training program will include the essential tools of
project management, including how to plan, how to schedule using either
CPM or PERT methods, how to allocate resources in scheduling, and how to
do variance or earned-value analysis. It will not include training in
supervisory skills, as these are already available in another course. The
course is also not aimed at experienced project managers, and so no
advanced concepts will be presented.
A mission statement for this project follows:
This step involves the breaking down of the major activities to be carried out
by the consultant showing the expected duration of each activity. Under
this section it is important to indicate the key staff
Key qualification required for the consultant and the key staff:
Under this section, the procuring entity should state the required skills and
knowledge to accomplish the above duties; the experience and minimum
level of education as well, as areas
This entails writing down the training requirements and the asking the
consultant on the skills transfer methodology requirement.
Reporting Requirements:
The program manager has the delegated authority from general management to
direct all program activities. He or she represents the company in contacts with the
customer and all internal and external negotiations. Project personnel have the
typical dual- reporting relationship: to functional management for technical
performance and to the program manager for contractual performance in
accordance with specifications, schedules, and budgets. The program manager
approves all project personnel assignments and influences their salary and
promotional status via formal performance reports to their functional managers.
Travel and customer contact activities must be coordinated and approved by the
program manager.
Any conflict with functional management or company policy shall be resolved by
the general manager or his or her staff.
Responsibility
The program manager's responsibilities are to the general manager for
overall program direction according to established business objectives and
contractual requirements regarding technical specifications, schedules, and
budgets.
More specifically, the program manager is responsible for
If the project manager's responsibilities are divided among several persons (such as one man for engineering, another for scheduling, a third
for cost, a fourth for contract administration, etc.) such division is the
most common cause of projects not achieving their objectives. Unless
one person integrates the efforts of the project engineer, the project
contract administrator, and so on, it is not possible to evaluate the
project effectively to identify current or future problems and initiate
corrective action in time to assure that the project objectives will be
met.
The project manager cannot actually perform all the planning,
controlling and evaluation activities needed, any more than he can
perform all the technical specialty activities required. Project
management support services must be provided to him, and he must
direct and control these support activities. The hazard is that the
support activities may exist, but in the absence of an assigned project
manager, they are not properly used.
Some companies are very explicit about their project manager's
responsibilities. For example, within the Fluor Corporation, a major
engineering/construction company, project managers have "...total
responsibility for the execution of the project from its earliest stages right
through to completion.
What is Accountability?
Accountability is the state of assuming liability for something of value,
whether through a contract or because of one's position of responsibility. A
professional is held accountable for excellence in the quality of the service
rendered to the organization. Project managers have dual accountability:
They are held answerable for their own performances and for the
performance of people who comprise the project team. One of the basic
characteristics of managers is that they are held accountable for the
effectiveness and efficiency of the people who report to them.
Authority, responsibility, and accountability can rest with a single person or with a
group of people. An example of pluralism in this sense is found in the use of a
plural executive at the top-management level of organizations such as a
Summary
In this chapter we addressed the de jure and de facto elements of authority. A
project manager can never be granted all the authority
Board
Role definition:
authority
responsibility
accountability
of
Directors
---------------CEO and
staff
------------------------Manager of
projects
--------------------------------Project
managers
----------------------------------------Functional
managers
--------------------------------------------------Work package
managers
------------------------------------------------------------
Cost objective
Schedule objective
Project
management
organizational
design
Project
professionals
Trainee Activities
What is the
accountability?
difference
between
authority,
responsibility,
and
What role does power play in project management? List and discuss
some power sources.