Академический Документы
Профессиональный Документы
Культура Документы
to
Since signing the initial contract in July 2013, the project partners have
implemented an aggressive schedule to deliver the benefits of the propane
conversion to the Territory as soon as possible.
The project commenced with an initial estimated project budget before
the front end engineering and design (FEED) was complete.
Following the completion of the FEED, the project leadership anticipated
the needed adjustments to the budget from $87 million to $150 million,
which resulted from the improvements deemed necessary, refined design
specs, unknown obstacles like the pilings and regulatory
recommendations, etc.
Although the projects costs have increased, customer savings from the switch
to propane will not be impacted.
WAPA remains committed to maintaining savings for all customers, and
fuel costs will still be reduced to the anticipated 30% due to the conversion
from fuel oil to propane, along with the estimated 20% reduction in
greenhouse gas emissions
These fuel cost savings will be passed along directly to customers.
The increased cost of the project is being shared by the project partners,
WAPA and Vitol.
Vitol is still paying all upfront costs and WAPA will now repay Vitol
according to a new amortization schedule.
WAPA and Vitol had previously agreed to an amortization period of seven
years with the option to complete payment in five years.
The amortization period has been extended to ten years, with the option
to complete payment in seven years.
Control Room
Construction
Construction
Activity, St. Thomas
Construction Activity on
Control Room, St. Thomas
10
11
Vaporizer Construction,
St. Croix
12
13
Propane tanks
set sail from Container Port
15
16
10,400 m3
65, 500 bbls.
14,000 m3
88,000 bbls.
Effective Supply
19.2 days
18.3 days
17
18
19
20
21
22
Built and commissioned new propane delivery vessels (the Epic Curacao and Epic
Caledonia) specifically to deliver liquefied propane to WAPAs facilities.
23
Sealed Turbine
Compartment
Control System
Upgrade
Control Cabinet
24