Вы находитесь на странице: 1из 18

Jalaur River Multi Purpose Project Stage II

Activity ID

Activity Name

Classic WBS_Jalaur
CODE

Quantity Unit

Jalaur River Multi Purpose Project Stage II


MOBILIZATION
MOBILIZAT
A100

Award of Contract

A103

Mobilization

Original
Duration

Start

1374d

2016.Feb.01

2019.Nov.05

243d

2016.Feb.01

2016.Sep.30

0d

TEMPORA
TEMPORARY
WORKS

Finish

2016.Feb.01

Jan
1

Feb
2

Mar
3

Apr
4

May
5

2016
Jun Jul
6
7

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

2015.Dec.14 07:59
2017
Jun Jul
18
19

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

Jan
25

Feb
26

Mar
27

Apr
28

May
29

2018
Jun Jul
30
31

Aug
32

Sep
33

Oct
34

Nov
35

Dec
36

Jan
37

Feb
38

Mar
39

Apr
40

May
41

2019
Jun Jul
42
43

Aug
44

Sep
45

Oct
46

2020
Nov Dec Jan Feb Mar Apr May
47
48
49
50
51
52 53
2019.Nov.05, Jalaur River Multi Purpose

2016.Sep.30, MOBILIZATION
Award of Contract

243d

2016.Feb.01

2016.Sep.30

516d

2016.Feb.01

2017.Jun.30

Mobilization

1d

2016.Aug.01

2016.Aug.01

Supply vehicle to be used by employer


Supply, motor cycles of 125cc power supply system

2017.Jun.30, TEMPORARY WORKS

A201

Supply vehicle to be used by employer

JA0201

252 /month

A202

Supply, motor cycles of 125cc power supply system

JA0202

336 /month

1d

2016.Aug.01

2016.Aug.01

A203

Supply construction equipment and vehicles

JA0203

LS

365d

2016.May.01

2017.Apr.30

A101

Land preparation for temporary construction yard

JA101

1 LS

90d

2016.Feb.01

2016.Apr.30

A102

Temporary building including construction and removal (


Breakdown of the name of buildings required )

JA102

1 LS

152d

2016.Mar.02

2016.Jul.31

A106

Cement bag unpacking facilities including installation (and JA106


removal)

1 LS

184d

2016.May.01

2016.Oct.31

A107

Water supply system including installation (and removal)

JA107

1 LS

486d

2016.Mar.02

2017.Jun.30

Water supply system including installation (and removal)

A108

Power supply system including installation (and removal)

JA108

1 LS

486d

2016.Mar.02

2017.Jun.30

Power supply system including installation (and removal)

A109

Operation and maintenace of power supply system

JA109

1 LS

334d

2016.Aug.01

2017.Jun.30

A110

Temporary construction access roads

JA110

1 LS

214d

2016.May.01

2016.Nov.30

A111

Testing Laboratory including maintenance and removal

JA111

1 LS

92d

2016.May.01

2016.Jul.31

Testing Laboratory including maintenance and removal

A112

Temporary communication system including installation


(and removal)

JA112

1 LS

61d

2016.May.01

2016.Jun.30

Temporary communication system including installation (and removal)

Supply construction equipment and vehicles


Land preparation for temporary construction yard
Temporary building including construction and removal ( Breakdown of the name of buildings required )
Cement bag unpacking facilities including installation (and removal)

Operation and maintenace of power supply system


Temporary construction access roads

1369d

2016.Feb.01

2019.Oct.31

B101

Excavation ( Soil )

JA1101

323962 cu.m.

121d

2016.Mar.02

2016.Jun.30

B102

Excavation ( Rock )

JA1102

465066 cu.m.

152d

2016.Mar.02

2016.Jul.31

B103

Embankment ( Subgrade )

JA1103

385144 cu.m.

153d

2016.Apr.01

2016.Aug.31

B104

Embankment ( Road bed )

JA1104

191163 cu.m.

184d

2016.May.01

2016.Oct.31

B105

Soil Conveyance Without Change

JA1105

55709 cu.m.

92d

2016.Mar.02

2016.Jun.01

B106

Dozer Conveyance

JA1106

14799 cu.m.

183d

2016.Mar.02

2016.Aug.31

B107

Dump Truck Conveyance

JA1107

231787 cu.m.

184d

2016.Mar.02

2016.Sep.01

B108

Spoil Soil

JA1108

310310 cu.m.

92d

2016.Mar.02

2016.Jun.01

Spoil Soil

B109

Clearing and Grubbing

JA1109

129125 sq.m.

120d

2016.Feb.01

2016.May.30

Clearing and Grubbing

B110

Lawning ( Excavation )

JA1110

119555 sq.m.

91d

2016.Jun.01

2016.Aug.30

B111

Lawning ( Embankment )

JA1111

28541 sq.m.

153d

2016.May.01

2016.Sep.30

B112

Preparation of Roadbed

JA1112

43836 sq.m.

184d

2016.May.01

2016.Oct.31

Preparation of Roadbed

B113

Ditchs

JA1113

169d

2016.May.16

2016.Oct.31

Ditchs

B114

Catch pit ( D=800mm )

JA1114

4 nos

7d

2016.May.01

2016.May.07

B115

Catch pit ( D=1000mm )

JA1115

8 nos

15d

2016.May.01

2016.May.15

B116

Drainage Pipe ( D=800mm )

JA1116

60 m

16d

2016.Apr.01

2016.Apr.16

B117

Drainage Pipe ( D=1000mm )

JA1117

88 m

30d

2016.Apr.01

2016.Apr.30

B118

Longitudinal Drainage Pipe ( D=800mm )

JA1118

200 m

61d

2016.Apr.01

2016.May.31

Longitudinal Drainage Pipe ( D=800mm )

B119

Box Culvert ( Single, 1.0Mx1.0M )

JA1119

112 m

61d

2016.May.01

2016.Jun.30

Box Culvert ( Single, 1.0Mx1.0M )

B120

Box Culvert ( Single, 1.5Mx1.5M )

JA1120

153 m

61d

2016.May.01

2016.Jun.30

Box Culvert ( Single, 1.5Mx1.5M )

B121

Box Type Underpass ( Single, 4.5Mx4.5M )

JA1121

47 m

61d

2016.May.01

2016.Jun.30

Box Type Underpass ( Single, 4.5Mx4.5M )

B122

Slope Protection Work ( Stone Masonry )

JA1122

22262 sq.m.

184d 1h

2016.Jun.30

2016.Dec.31

B123

Slope Protection Work ( Riprap Stone )

JA1123

53136 cu.m.

155d

2016.Sep.28

2017.Mar.01

B124

Reinforced Earth Retaining Wall

JA1124

3613 sq.m

126d 7h

2016.Dec.27

2017.May.02

B125

Tunnel Against Falling Stone

JA1125

250 m

96d

2017.Feb.25

2017.May.31

B126

Rock Bolt

JA1126

53136 nos

82d 4h

2017.Apr.26

2017.Jul.17

B127

Subbase Course ( T=20cm )

JA1127

11672 cu.m.

92d

2019.Jul.01*

2019.Sep.30

B128

PCC Pavement ( T=23cm )

JA1128

7454 sq.m.

78d

2019.Aug.15

2019.Oct.31

B129

Aggregate Coarse

JA1129

1453 cu.m.

92d

2019.Jul.16

2019.Oct.15

Aggregate Coarse

B130

Traffic Signs

JA1130

62 nos

48d

2019.Sep.14

2019.Oct.31

Traffic Signs

B131

Line Marking ( White )

JA1131

2514 sq.m.

33d

2019.Sep.29

2019.Oct.31

Line Marking ( White )

B132

Line Marking ( Yellow )

JA1132

613 sq.m.

33d

2019.Sep.29

2019.Oct.31

Line Marking ( Yellow )

B133

Chevron Alignment Signs ( Shoulder )

JA1133

114 nos

48d

2019.Sep.14

2019.Oct.31

Chevron Alignment Signs ( Shoulder )

ACCESS ROADS
R

5056 m

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

2019.Oct.31, ACCESS ROADS


Excavation ( Soil )
Excavation ( Rock )
Embankment ( Subgrade )
Embankment ( Road bed )
Soil Conveyance Without Change
Dozer Conveyance
Dump Truck Conveyance

Lawning ( Excavation )
Lawning ( Embankment )

Catch pit ( D=800mm )


Catch pit ( D=1000mm )
Drainage Pipe ( D=800mm )
Drainage Pipe ( D=1000mm )

Slope Protection Work ( Stone Masonry )


Slope Protection Work ( Riprap Stone )
Reinforced Earth Retaining Wall
Tunnel Against Falling Stone
Rock Bolt
Subbase Course ( T=20cm )
PCC Pavement ( T=23cm )

Page 1 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

B134

Guard Rail ( L=2.425M )

B135

2016
Jun Jul
6
7

2015.Dec.14 07:59
2017
Jun Jul
18
19

2018
Jun Jul
30
31

2019
Jun Jul
42
43

2020
Nov Dec Jan Feb Mar
47
48
49
50
51
Guard Rail ( L=2.425M )

Quantity Unit

Original
Duration

Start

Finish

JA1134

2938 nos

43d

2019.Sep.19

2019.Oct.31

Guard Rail ( L=4.0M ( 1 POLE )

JA1135

1486 nos

48d

2019.Sep.14

2019.Oct.31

B136

Guard Rail ( end point rail : round rail )

JA1136

34 nos

43d

2019.Sep.19

2019.Oct.31

Guard Rail ( end point rail : round rail )

B137

Rock Preventing Facility

JA1137

3552 m

75d

2019.Aug.15

2019.Oct.28

Rock Preventing Facility

426d

2016.May.01

2017.Jun.30

B203

Aggregate plant including installation (and removal),


(480t/hr)

JA103

184d

2016.May.01

2016.Oct.31

B204

Main batcher plant and cement silo including installation


(and removal), (2.25 m3 x 2)

JA104

426d

2016.May.01

2017.Jun.30

B205

Sub-batcher plant and cement silo including installation


(and removal) ,(1.5 m3)

JA105

184d

2016.May.01

2016.Oct.31

1289d

2016.Mar.02

2019.Sep.11

1289d

2016.Mar.02

2019.Sep.11

45d

2016.Mar.02

2016.Apr.15

CONSTRU
CONSTRUCTION
PLANT

HIGH DAM
Diversion W
Works
Portal Excavation
Exc

Jan
1

Feb
2

Mar
3

Apr
4

May
5

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

30d

2016.Mar.02

2016.Mar.31

40d

2016.Mar.07

2016.Apr.15

1259d

2016.Apr.01

2019.Sep.11

107d

2016.Apr.16

2016.Jul.31

Excavation, all classes for diversion

JC0110

1597 nos.

Furnishing, installing, operating, maintaining (and


removing) lighting and ventilation system

JC0111

C112

Drilling grout holes in diversion tunnel

JC0112

C113

Furnishing and installing cooling pipe embedded for


plugging

C114
C115

2016.Jul.31

Furnishing and installing rock bolt for diversion tunnel

2016.Apr.01

2016.Jul.31

Furnishing, installing, operating, maintaining (and removing) lighting and ventilation system

1770 m

62d

2016.Aug.31

2016.Oct.31

Drilling grout holes in diversion tunnel

JC0113

1015 m

16d

2016.Oct.16

2016.Oct.31

Furnishing and installing cooling pipe embedded for plugging

Re-drilling grout holes in diversion tunnel

JC0114

120 m

47d

2016.Sep.30

2016.Nov.15

Water pressure test for curtain grout in diversion tunnel

JC0115

51d

2016.Sep.30

2016.Nov.19

C116

Pressure grouting of curtain grout in diversion tunnel

JC0116

27180 kg

47d

2016.Oct.05

2016.Nov.20

C117

Grouting in cooling pipe

JC0117

870 kg

13d

2016.Nov.01

2016.Nov.13

C118

Furnishing and installing metal pipe fitting for pressure


grouting in diversion tunnel

JC0118

1332 kg

47d

2016.Oct.05

2016.Nov.20

C119

Pressure grouting of consilidation grouting in diversion


tunnel

JC0119

28800 kg

92d

2016.Aug.31

2016.Nov.30

C120

Handling and placing reinforcement bars for diversion


tunnel

JC0120

185856 kg

93d

2016.Jun.30

2016.Sep.30

C121

Lining concrete in diversion tunnel

JC0121

3389 cu.m.

76d

2016.Aug.01

2016.Oct.15

Lining concrete in diversion tunnel

C122

Form for Item No. C121

JC0122

5011 sq.m.

76d

2016.Aug.01

2016.Oct.15

Form for Item No. C121

C125

Plugging concrete in diversion tunnel

JC0125

793 cu.m.

45d

2019.Jun.29

2019.Aug.12

C126

Backfill with excavated material

JC0126

1077 cu.m.

30d

2019.Aug.13

2019.Sep.11

C127

Furnishing and placing 200 mm Plastic seal

JC0127

15d

2019.Jul.14

2019.Jul.28
2016.Dec.16, Portal Structure
Structure concrete in inlet and outlet portal of diversion tunnel

C124

Form for Item No. C123

JC0124

1042 sq.m.

62d

2016.Oct.16

2016.Dec.16

Form for Item No. C123

1d

2016.Dec.17

2016.Dec.17

2016.Dec.17, River Diversion


Diversion and care of Jalaur river for the high dam area

1d

2016.Dec.17

2016.Dec.17

135d

2016.Dec.18

2017.May.01

75d

2016.Dec.18

2017.Mar.02

3032 cu.m.

15d

2016.Dec.18

2017.Jan.01

Excavation, in common, in open-cut for upstream cofferdam


Excavation, in rock, in open-cut for upstream cofferdam

C103 Excavation, in rock, in open-cut for upstream cofferdam

JC0103

71 cu.m.

20d

2016.Dec.23

2017.Jan.11

C104 A1 Concrete in Upstream Cofferdam

JC0104

9366 cu.m.

30d

2017.Jan.12

2017.Feb.10

C105 C Concrete in Upstream Cofferdam

JC0105

5986 cu.m.

30d

2017.Feb.01

2017.Mar.02

C Concrete in Upstream Cofferdam

C106 Form for Item No. C105

JC0106

979 sq.m.

30d

2017.Feb.01

2017.Mar.02

Form for Item No. C105

60d

2017.Mar.03

2017.May.01

JC0128

1793 cu.m.

10d

2017.Mar.03

2017.Mar.12

Excavation, in common, in open-cut for downstream cofferdam

JC0129

162 cu.m.

10d

2017.Mar.13

2017.Mar.22

Excavation, in rock, in open-cut for downstream cofferdam

C130 A1 Concrete for downstream cofferdam

JC0130

1213 cu.m.

30d

2017.Mar.23

2017.Apr.21

C131 C Concrete for downstream cofferdam

JC0131

3558 cu.m.

30d

2017.Apr.02

2017.May.01

C Concrete for downstream cofferdam

C132 Form for Item No. C131

JC0132

352 sq.m.

Form for Item No. C131

DAM SURFACE
SUR
EXCAVATION

Actual Work

Critical Remaining Work

Remaining Work

Milestone

2017.May.01
2019.Aug.28

396d

2016.May.31

2017.Jun.30

Summary

Sep
45

Oct
46

Apr May
52 53

2017.May.01, D/S Cofferdam

C129 Excavation, in rock, in open-cut for downstream


cofferdam

2017.Apr.02

Aug
44

A1 Concrete in Upstream Cofferdam

C128 Excavation, in common, in open-cut for downstream


cofferdam

2016.May.31

May
41

2017.May.01, Cofferdams

JC0102

30d

Apr
40

2017.Mar.02, U/S Cofferdams

C102 Excavation, in common, in open-cut for upstream


cofferdam

1185d

Mar
39

Backfill with excavated material

2016.Dec.16

JALAUR HIHGH
HI
DAM

Feb
38

Furnishing and placing 200 mm Plastic seal

2016.Dec.16

D/S Cofferdam
Co

Jan
37

Plugging concrete in diversion tunnel

2016.Oct.16

U/S Cofferdams
Co

Dec
36

Pressure grouting of consilidation grouting in diversion tunnel

2016.Oct.16

1 LS

Nov
35

Handling and placing reinforcement bars for diversion tunnel

62d

JC0101

Oct
34

Furnishing and installing metal pipe fitting for pressure grouting in diversion tunnel

62d

Diversion and care of Jalaur river for the high dam area

Sep
33

Pressure grouting of curtain grout in diversion tunnel

1211 cu.m.

C101

Aug
32

Grouting in cooling pipe

JC0123

Cofferdams
Cofferdam

May
29

Water pressure test for curtain grout in diversion tunnel

Structure concrete in inlet and outlet portal of diversion


tunnel

River Diversion
Dive

Apr
28

Re-drilling grout holes in diversion tunnel

C123

Portal Structure
Stru

Mar
27

2019.Sep.11, Tunnel Work s

2016.May.01

129 m

Feb
26

Excavation, in rock, in open-cut for diversion tunnel

92d

24 time

Jan
25

Excavation, in common, in open-cut for diversion tunnel

122d

1 LS

Dec
24

2019.Sep.11, Diversion Works

4920 cu.m.

Furnishing and installing rock bolt for diversion tunnel

Nov
23

2016.Apr.15, Portal Excavation

10435 cu.m.

C111

Oct
22

2019.Sep.11, HIGH DAM

JC0108

C110

Sep
21

Main batcher plant and cement silo including installation (and removal), (2.25 m3 x 2)

JC0107

11234 cu.m.

Aug
20

Sub-batcher plant and cement silo including installation (and removal) ,(1.5 m3)

Excavation, in rock, in open-cut for diversion tunnel

JC0109

May
17

2017.Jun.30, CONSTRUCTION PLANT

Excavation, in common, in open-cut for diversion tunnel

Excavation, all classes for diversion

Apr
16

Aggregate plant including installation (and removal), (480t/hr)

C108

C109

Mar
15

Guard Rail ( L=4.0M ( 1 POLE )

C107

Tunnel Works
Wo

Feb
14

A1 Concrete for downstream cofferdam

2019.Aug.28, JALAUR HIHGH DAM


2017.Jun.30, DAM SURFACE EXCAVATION

Page 2 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

C201

Excavation, common in open-cut

JC0201

C202

Excavation, rock in open-cut

Quantity Unit

Original
Duration

Start

Finish

114092 cu.m.

304d

2016.May.31

2017.Mar.30

JC0202

37254 cu.m.

366d

2016.Jun.30

2017.Jun.30

Jan
1

Feb
2

Mar
3

Apr
4

May
5

2016
Jun Jul
6
7

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

2015.Dec.14 07:59

2017
Apr May Jun Jul Aug Sep
16
17
18
19
20
21
Excavation, common in open-cut

Oct
22

Dec
24

Jan
25

Feb
26

Mar
27

Apr
28

May
29

2018
Jun Jul
30
31

Aug
32

Sep
33

Oct
34

Nov
35

Dec
36

Jan
37

Feb
38

Mar
39

Apr
40

May
41

2019
Jun Jul
42
43

Aug
44

Sep
45

Oct
46

Nov
47

Dec
48

112d

2017.Jun.11

2017.Sep.30

Drilling grout holes foundation in the stage between 0 m


and 15 m less inclined than 15

JC0301

20370 m

30d

2017.Jul.01

2017.Jul.30

C302

Drilling grout holes foundation in the stage between 0 m


and 15 m more inclined than 15

JC0302

1290 m

25d

2017.Jul.11

2017.Aug.04

C303

Drilling grout holes foundation in the stage between 15 m


and 40 m less inclined than 15

JC0303

9020 m

30d

2017.Jul.21

2017.Aug.19

C304

Drilling grout holes foundation in the stage between 15 m


and 40 m more inclined than 15

JC0304

1780 m

30d

2017.Jul.31

2017.Aug.29

C305

Drilling grout holes foundation in the stage between 40 m


and 100 m less inclined than 15

JC0305

6360 m

30d

2017.Aug.10

2017.Sep.08

C306

Drilling grout holes foundation in the stage between 40 m


and 100 m more inclined than 15

JC0306

70 m

30d

2017.Aug.20

2017.Sep.18

C307

Furnishing and installing casing in grout holes

JC0307

100 m

92d

2017.Jul.01

2017.Sep.30

C308

Re-drilling grout holes in foundation in the stage between


0 m and 15 m less inclined than 15

JC0308

4074 m

30d

2017.Jul.11

2017.Aug.09

C309

Re-drilling grout holes in foundation in the stage between


0 m and 15 m more inclined than 15

JC0309

258 m

25d

2017.Jul.21

2017.Aug.14

C310

Re-drilling grout holes in foundation in the stage between


15 m and 40 m less inclined than 15

JC0310

1804 m

30d

2017.Jul.31

2017.Aug.29

C311

Re-drilling grout holes in foundation in the stage between


15 m and 40 m more inclined than 15

JC0311

356 m

30d

2017.Aug.10

2017.Sep.08

C312

Re-drilling grout holes in foundation in the stage between


40 m and 100 m less inclined than 15

JC0312

1272 m

30d

2017.Aug.20

2017.Sep.18

C313

Re-drilling grout holes in foundation in the stage between


40 m and 100 m more inclined than 15

JC0313

14 m

30d

2017.Aug.30

2017.Sep.28

C314

Core Drilling NX

JC0314

100 m

30d

2017.Jun.11

2017.Jul.10

Core Drilling NX

C315

Core Drilling BX

JC0315

100 m

30d

2017.Jun.11

2017.Jul.10

Core Drilling BX

C316

Pressure grouting foundation

JC0316

1680696 kg

92d

2017.Jul.01

2017.Sep.30

C501

Dental concrete

JC0501

C502

Concrete type A1 in high dam and spillway

C503

Concrete type C in high dam and spillway

C504
C517

Drilling grout holes foundation in the stage between 15 m and 40 m less inclined than 15
Drilling grout holes foundation in the stage between 15 m and 40 m more inclined than 15
Drilling grout holes foundation in the stage between 40 m and 100 m less inclined than 15
Drilling grout holes foundation in the stage between 40 m and 100 m more inclined than 15
Furnishing and installing casing in grout holes
Re-drilling grout holes in foundation in the stage between 0 m and 15 m less inclined than 15
Re-drilling grout holes in foundation in the stage between 0 m and 15 m more inclined than 15
Re-drilling grout holes in foundation in the stage between 15 m and 40 m less inclined than 15
Re-drilling grout holes in foundation in the stage between 15 m and 40 m more inclined than 15
Re-drilling grout holes in foundation in the stage between 40 m and 100 m less inclined than 15
Re-drilling grout holes in foundation in the stage between 40 m and 100 m more inclined than 15

Pressure grouting foundation

2017.Oct.01

2019.Aug.28

2017.Oct.01

2017.Oct.06

JC0502

311703 cu.m.

481d

2017.Oct.07

2019.Jan.30

JC0503

179374 cu.m.

466d

2017.Nov.06

2019.Feb.14

Form works for item C503

JC0504

31788 sq.m.

466d

2017.Nov.06

2019.Feb.14

Concrete for minor structure in high dam site

JC0517

593 cu.m.

331d

2018.Mar.06

2019.Jan.30

Concrete for minor structure in high dam site

C518

Form works for item C517

JC0518

1379 sq.m.

331d

2018.Mar.06

2019.Jan.30

Form works for item C517

C519

Concrete blackouts larger than 600 cm

JC0519

4 cu.m.

481d

2017.Oct.07

2019.Jan.30

Concrete blackouts larger than 600 cm

C701

Furnishing and placing 300 mm in width plastic water


stop

JC0701

2399 m

478d

2017.Oct.10

2019.Jan.30

Furnishing and placing 300 mm in width plastic water stop

C702

Furnishing and placing metal water stop

JC0702

13160 kg

478d

2017.Oct.10

2019.Jan.30

Furnishing and placing metal water stop

C703

Furnishing and placing galvanized joint metal

JC0703

275623 kg

478d

2017.Oct.10

2019.Jan.30

Furnishing and placing galvanized joint metal

C907

Furnishing and installing perforated PVC pipe drain

JC0907

2054 m

481d

2017.Oct.07

2019.Jan.30

Furnishing and installing perforated PVC pipe drain

C908

Furnishing and installing miscellaneous steel pipe drains


and vent pipe

JC0908

1604 kg

481d

2017.Oct.07

2019.Jan.30

Furnishing and installing miscellaneous steel pipe drains and vent pipe

C910

Furnishing and installing PVC drain pipe 400mm inner


diameter

JC0910

158 m

481d

2017.Oct.07

2019.Jan.30

Furnishing and installing PVC drain pipe 400mm inner diameter

C1102

Furnishing and installing high dam crest handrail

JC1102

21392 kg

46d

2019.Jul.10

2019.Aug.24

C1103

Furnishing and installing pipe handrail

JC1103

6758 kg

30d

2019.Jul.30

2019.Aug.28

C1108

Furnishing and installing entrance gate

JC1108

462 kg

C1109

Furnishing and installing stone pitching

JC1109

405 sq.m.

2019.Jul.10

2019.Aug.24

2018.Dec.01

2019.Aug.15

Apr May
52 53

Drilling grout holes foundation in the stage between 0 m and 15 m more inclined than 15

6d

46d

2020
Mar
51

2017.Sep.30, DAM FOUNDATION TREATMENT

697d

258d

Feb
50

Drilling grout holes foundation in the stage between 0 m and 15 m less inclined than 15

100 cu.m.

DAM BODY
BOD

Jan
49

Excavation, rock in open-cut

C301

DAM FOUNDATION
FOU
TREATMENT

Nov
23

2019.Aug.28, DAM BODY


Dental concrete
Concrete type A1 in high dam and spillway
Concrete type C in high dam and spillway
Form works for item C503

Furnishing and installing high dam crest handrail


Furnishing and installing pipe handrail
Furnishing and installing entrance gate
Furnishing and installing stone pitching

192d

2019.Feb.15

2019.Aug.25

C401

Furnishing, handling and placing reinforcement for


spillway chute way and sidewall

JC0401

127321 kg

55d

2019.May.01

2019.Jun.24

C402

Furnishing, handling and placing reinforcement


surrounding of opening structure in dam body

JC0402

153343 kg

75d

2019.Feb.15

2019.Apr.30

C403

Furnishing, handling and placing reinforcement of dam


crest structure

JC0403

9560 kg

32d

2019.Jul.25

2019.Aug.25

Furnishing, handling and placing reinforcement of dam c

C404

Furnishing, handling and placing reinforcement for


spillway over bridge

JC0404

61964 kg

40d

2019.Jun.25

2019.Aug.03

Furnishing, handling and placing reinforcement for spillway ov

C407

Furnishing, handling and placing reinforcement for minor


structure in high dam site

JC0407

15177 kg

32d

2019.Jul.25

2019.Aug.25

C505

Concrete in spillway, chuteway and flip bucket

JC0505

12558 cu.m.

75d

2019.Feb.15

2019.Apr.30

Concrete in spillway, chuteway and flip bucket

C506

Form works for item C505

JC0506

1313 sq.m.

75d

2019.Feb.15

2019.Apr.30

Form works for item C505

C507

Concrete for spillway and chute way wall

JC0507

683 cu.m.

55d

2019.May.01

2019.Jun.24

Concrete for spillway and chute way wall

C508

Form works for item No. C507

JC0508

1519 sq.m.

55d

2019.May.01

2019.Jun.24

Form works for item No. C507

C509

Concrete spillway for over bridge

JC0509

747 cu.m.

45d

2019.Jun.25

2019.Aug.08

Concrete spillway for over bridge

C510

Form works for item No. C509

JC0510

1311 sq.m.

45d

2019.Jun.25

2019.Aug.08

Form works for item No. C509

C1104

Furnishing and installing steel miscellaneous embedded


metal works

JC1104

100 kg

21d

2019.Jul.25

2019.Aug.14

Furnishing and installing steel miscellaneous embedded me

C1105

Furnishing and installing miscellaneous non-embedded


metal works

JC1105

100 kg

21d

2019.Jul.25

2019.Aug.14

Furnishing and installing miscellaneous non-embedded me

SPILLWAY STRUCTURE

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

2019.Aug.25, SPILLWAY STRUCTURE


Furnishing, handling and placing reinforcement for spillway chute way
Furnishing, handling and placing reinforcement surrounding of opening structure in

Furnishing, handling and placing reinforcement for minor

Page 3 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Activity Name

Classic WBS_Jalaur
CODE

Quantity Unit

WATERWAY
WATERWA

Original
Duration

Start

Finish

441d

2018.Feb.14

2019.Apr.30

2018.Nov.21

2019.Jan.09

Jan
1

Feb
2

Mar
3

Apr
4

May
5

2016
Jun Jul
6
7

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

2015.Dec.14 07:59
2017
Jun Jul
18
19

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

Jan
25

Feb
26

Mar
27

Apr
28

May
29

2018
Jun Jul
30
31

Aug
32

Sep
33

Oct
34

Nov
35

Dec
36

Jan
37

Feb
38

Mar
39

Apr
40

2019
May Jun Jul
Aug Sep
41
42
43
44
45
2019.Apr.30, WATERWAY

Oct
46

Nov
47

Dec
48

Jan
49

Feb
50

2020
Mar
51

C405

Furnishing, handling and placing reinforcement for


retaining wall in gate house yard

JC0405

27735 kg

50d

C406

Furnishing, handling and placing reinforcement for gate


house

JC0406

38563 kg

47d

2019.Jan.10

2019.Feb.25

C511

Concrete for steel penstock encasement at outside of


dam body

JC0511

631 cu.m.

66d

2018.Sep.26

2018.Nov.30

C512

Form works for item C511

JC0512

319 sq,m.

40d

2018.Sep.26

2018.Nov.04

C513

Concrete for gate house sub structure

JC0513

310 cu.m.

50d

2018.Nov.21

2019.Jan.09

Concrete for gate house sub structure

C514

Form works for item C513

JC0514

924 sq.m.

50d

2018.Nov.21

2019.Jan.09

Form works for item C513

C515

Concrete for gate house super structure

JC0515

190 cu.m.

47d

2019.Jan.10

2019.Feb.25

C516

Form works for item C515

JC0516

775 sq.m.

47d

2019.Jan.10

2019.Feb.25

C520

2nd stage concrete for gate chamber and gate house

JC0520

416 cu.m.

7d

2018.Dec.05

2018.Dec.11

C1001

Furnishing and installing intake trash rack

JC1001

1 LS

15d

2018.Feb.14

2018.Feb.28

C1002

Furnishing and installing intake gate and hoist

JC1002

1 LS

5d

2018.Mar.16

2018.Mar.20

C1003.

Furnishing and installing monorail hoist in gate chamber

JC1003

1 LS

30d

2018.Feb.14

2018.Mar.15

C1004

Furnishing and installing waterway steel conduit

JC1004

43354 kg

132d

2018.Feb.14

2018.Jun.25

C1005

Furnishing and installing steel penstock

JC1005

54800 kg

152d

2018.Jun.26

2018.Nov.24

C1006

Furnishing and installing outlet guard gate hoist

JC1006

1 LS

5d

2018.Nov.25

2018.Nov.29

C1007

Furnishing and installing outlet jet flow gate

JC1007

1 LS

5d

2018.Nov.30

2018.Dec.04

C1008

Overhead crane in gate house

JC1008

1 LS

30d

2019.Mar.18

2019.Apr.16

C1101

Furnishing and installing mild steel anchor bolts

JC1101

200 nos

5d

2019.Mar.18

2019.Mar.22

C1106

Furnishing and installing chain wire fencing

JC1106

100 sq.m.

30d

2019.Feb.26

2019.Mar.27

Furnishing and installing chain wire fencing

C1107

Furnishing and installing rock fence

JC1107

238 m

30d

2019.Mar.28

2019.Apr.26

Furnishing and installing rock fence

C1301

Furnishing of materials and painting on the interior wall for JC1301


gate house

613 sq.m.

24d

2019.Apr.07

2019.Apr.30

Furnishing of materials and painting on the interior wall for gate house

C1302

Furnishing of materials and painting on the exterior wall of JC1302


gate house

291 sq.m.

24d

2019.Apr.07

2019.Apr.30

Furnishing of materials and painting on the exterior wall of gate house

C1303

Furnishing and installing doors louvered steel type for


gate house

JC1303

14 sq.m.

24d

2019.Apr.07

2019.Apr.30

Furnishing and installing doors louvered steel type for gate house

C1304

Furnishing and installing window louvered steel type for


gate house

JC1304

28 sq.m.

24d

2019.Apr.07

2019.Apr.30

C1305

Furnishing and installing long span rib type roofing sheets JC1305
for gate house

164 sq.m.

20d

2019.Apr.07

2019.Apr.26

C1306

Furnishing and installing steel trusses for gate house

JC1306

917 kg

20d

2019.Feb.26

2019.Mar.17

C1307

Furnishing and installing C Purlins

JC1307

887 kg

INST,, MECH'L.&
MEC
ELECTR'L

20d

2019.Mar.18

2019.Apr.06

577d

2017.Oct.01

2019.Apr.30

Apr May
52 53

Furnishing, handling and placing reinforcement for retaining wall in gate house yard
Furnishing, handling and placing reinforcement for gate house
Concrete for steel penstock encasement at outside of dam body
Form works for item C511

Concrete for gate house super structure


Form works for item C515
2nd stage concrete for gate chamber and gate house
Furnishing and installing intake trash rack
Furnishing and installing intake gate and hoist
Furnishing and installing monorail hoist in gate chamber
Furnishing and installing waterway steel conduit
Furnishing and installing steel penstock
Furnishing and installing outlet guard gate hoist
Furnishing and installing outlet jet flow gate
Overhead crane in gate house
Furnishing and installing mild steel anchor bolts

Furnishing and installing window louvered steel type for gate house
Furnishing and installing long span rib type roofing sheets for gate house
Furnishing and installing steel trusses for gate house
Furnishing and installing C Purlins
2019.Apr.30, INST,, MECH'L.& ELECTR'L

C801

Furnishing, installing and testing of instruments including


monitor system in high dam

JC0801

1 LS

502d

2017.Oct.01

2019.Feb.14

C802

Furnishing, installing water level gauge in upstream of


High dam

JC0802

1 LS

14d

2019.Feb.15

2019.Feb.28

C1201

Furnishing and Installation of Feeder line, Transfor mer


and Pole dressing

JC1201

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of Feeder line, Transfor mer and Pole dressing

C1202

Furnishing and Installation of 3 units 15KVA transformer

JC1202

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of 3 units 15KVA transformer

C1203

Furnishing and Installation of One Automatic Transfer


Switch

JC1203

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of One Automatic Transfer Switch

C1204

Furnishing and Installation of One Main Distribution Panel JC1204

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of One Main Distribution Panel

C1205

Furnishing and Installation of Four Distribution Panel

JC1205

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of Four Distribution Panel

C1206

Furnishing and Installation of one unit 150KVA Diesel


Generator w/ fuel stock w/ hand pump

JC1206

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of one unit 150KVA Diesel Generator w/ fuel stock w/ ha

C1207

Furnishing and Installation of Lighting fixtures in operation JC1207


/ Generator room area

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of Lighting fixtures in operation / Generator room area

C1208

Furnishing and Installation of Switches in operation /


Generator room area

JC1208

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of Switches in operation / Generator room area

C1209

Furnishing and Installation of Power outlet in operation /


Generator room area

JC1209

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of Power outlet in operation / Generator room area

C1210

Furnishing and Installation of Conduit, Raceway, and


Boxes

JC1210

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of Conduit, Raceway, and Boxes

C1211

Furnishing and Wiring installation and Feeder Line

JC1211

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Wiring installation and Feeder Line

C1212

Furnishing and Installation of Fire extinguisher at


operation / Generator room

JC1212

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of Fire extinguisher at operation / Generator room

C1213

Furnishing of Operation desk chair at Electrical


maintenance building

JC1213

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing of Operation desk chair at Electrical maintenance building

C1214

Furnishing and Installation of Grounding system and


Lighting system

JC1214

1 LS

24d

2019.Apr.07

2019.Apr.30

Furnishing and Installation of Grounding system and Lighting system

C1215

Others Miscellaneous and fixing materials

JC1215

1 set

24d

2019.Apr.07

2019.Apr.30

635d

2017.Jul.01

2019.Mar.27

2019.Jan.10

2019.Feb.08

OTHERS
C3401

Precast concrete cover

JC0601

45 cu.m.

30d

C3402

Miscellaneous precast concrete

JC0602

50 cu.m.

30d

2019.Jan.10

2019.Feb.08

C3408

Furnishing and installing 300mm diameter concrete pipe


culvert

JC0901

30 m

30d

2018.Dec.01

2018.Dec.30

C3409

Furnishing and installing 450mm diameter concrete pipe


culvert

JC0902

30 m

30d

2018.Dec.11

2019.Jan.09

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Furnishing, installing and testing of instruments including monitor system in high dam
Furnishing, installing water level gauge in upstream of High dam

Others Miscellaneous and fixing materials


2019.Mar.27, OTHERS
Precast concrete cover
Miscellaneous precast concrete
Furnishing and installing 300mm diameter concrete pipe culvert
Furnishing and installing 450mm diameter concrete pipe culvert

Page 4 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II

Classic WBS_Jalaur
Start

Finish

30 m

30d

2018.Dec.21

2019.Jan.19

2019
Feb Mar Apr May Jun Jul
Aug Sep Oct Nov
38
39
40
41
42
43
44
45
46
47
Furnishing and installing 600mm diameter concrete pipe culvert

JC0904

30 m

30d

2018.Dec.31

2019.Jan.29

Furnishing and installing 800mm diameter concrete pipe culvert

Furnishing and installing 1,000mm diameter concrete


pipe culvert

JC0905

30 m

30d

2019.Jan.10

2019.Feb.08

Furnishing and installing 1,200mm diameter concrete


pipe culvert

JC0906

30 m

30d

2019.Jan.20

2019.Feb.18

C3416

Drilling drainage hole into foundation

JC0909

743 m

92d

2017.Jul.01

2017.Sep.30

C3417

Furnishing and installing PVC drain pipe 400mm inner


diameter

JC0910

158 m

496d

2017.Oct.07

2019.Feb.14

Furnishing and installing PVC drain pipe 400mm inner diameter

C3418

Furnishing and installing PVC downspout and fittings

JC0911

20 m

496d

2017.Oct.07

2019.Feb.14

Furnishing and installing PVC downspout and fittings

C3458

Design, furnishing and Construction guard house

JC1308

2 nos

30d

2019.Feb.26

2019.Mar.27

Design, furnishing and Construction guard house

C3459

Monument, memorial and Others

JC1401

P.S.

30d

2019.Feb.26

2019.Mar.27

Monument, memorial and Others

1234d

2016.May.31

2019.Oct.16

2019.Oct.16, AFT ERBAY DAM

1203d

2016.Jul.01

2019.Oct.16

2019.Oct.16, Diversion Works

92d

2016.Jul.01

2016.Sep.30

89d

2016.Jul.01

2016.Sep.27

Activity Name

CODE

C3410

Furnishing and installing 600mm diameter concrete pipe


culvert

JC0903

C3411

Furnishing and installing 800mm diameter concrete pipe


culvert

C3412
C3413

Quantity Unit

AFTERBAY DAM
Diversion W
Works
Portal Excavation
Exc
D107

Excavation, in rock, in open-cut for diversion tunnel

JD0107

2819 cu.m.

D108

Excavation, in rock, in open-cut for diversion tunnel

JD0108

3188 cu.m.

Tunnel Works
Wo

87d

2016.Jul.06

2016.Sep.30

1141d

2016.Sep.01

2019.Oct.16

Jan
1

Feb
2

Mar
3

Apr
4

May
5

2016
Jun Jul
6
7

2015.Dec.14 07:59

Original
Duration

Activity ID

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

2017
Jun Jul
18
19

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

Jan
25

Feb
26

Mar
27

61d

2016.Oct.01

2016.Nov.30

772 nos

61d

2016.Oct.01

2016.Nov.30

D111

Furnishing, installing, operating, maintaining and removing JD0111


lighting and ventilation system

61d

2016.Sep.01

2016.Oct.31

D112

Drilling grout holes in diversion tunnel

JD0112

976 m

47d

2016.Dec.31

2017.Feb.15

Drilling grout holes in diversion tunnel

D113

Furnishing and installing cooling pipe embedded for


plugging

JD0113

531 m

15d

2017.Jan.30

2017.Feb.13

Furnishing and installing cooling pipe embedded for plugging

D114

Re-drilling grout holes in diversion tunnel

JD0114

120 m

45d

2017.Jan.15

2017.Feb.28

Re-drilling grout holes in diversion tunnel

D115

Water pressure test for curtain grout in diversion tunnel

JD0115

45d

2017.Jan.15

2017.Feb.28

Water pressure test for curtain grout in diversion tunnel

D116

Pressure grouting of curtain grout in diversion tunnel

JD0116

16380 kg

32d

2017.Jan.30

2017.Mar.02

Pressure grouting of curtain grout in diversion tunnel

D117

Grouting in cooling pipe

JD0117

456 kg

15d

2017.Feb.14

2017.Feb.28

Grouting in cooling pipe

D118

Furnishing and installing metal pipe fitting for pressure


grouting in diversion tunnel

JD0118

809 kg

45d

2017.Jan.15

2017.Feb.28

Furnishing and installing metal pipe fitting for pressure grouting in diversion tunnel

D119

Pressure grouting of consilidation grouting in diversion


tunnel

JD0119

16800 kg

40d

2017.Jan.20

2017.Feb.28

D120

Handling and placing reinforcement bars for diversion


tunnel

JD0120

89710 kg

60d

2016.Dec.01

2017.Jan.29

Handling and placing reinforcement bars for diversion tunnel

D121

Lining concrete in diversion tunnel

JD0121

1723 cu.m.

60d

2016.Dec.01

2017.Jan.29

Lining concrete in diversion tunnel

D122

Form for Item No. D121

JD0122

2246 sq.m.

60d

2016.Dec.01

2017.Jan.29

Form for Item No. D121

D123

Structure concrete in inlet and outlet portal of diversion


tunnel

JD0123

1651 cu.m.

61d

2017.Jan.30

2017.Mar.31

Structure concrete in inlet and outlet portal of diversion tunnel

D124

Form for Item No. D123

JD0124

1475 sq.m.

61d

2017.Jan.30

2017.Mar.31

Form for Item No. D123

D125

Plugging concrete in diversion tunnel

JD0125

528 cu.m.

45d

2019.Sep.02

2019.Oct.16

D126

Backfill with excavated material

JD0126

1938 cu.m.

30d

2019.Sep.02

2019.Oct.01

D127

Earthfill with excavated material

JD0127

6006 cu.m.

15d

2019.Oct.02

2019.Oct.16

D128

Furnishing and placing 200 mm Plastic seal

JD0128

15d

2019.Sep.12

2019.Sep.26

Earthfill with excavated material


Furnishing and placing 200 mm Plastic seal

2017.Apr.01

2017.Apr.20

2017.Apr.20, Portal Structur e

2017.Apr.01

2017.Apr.20

2nd Stage Concrete for inlet of diversion tunnel

D131

Formworks for Item No. D130

JD0131

59 sq.m.

20d

2017.Apr.01

2017.Apr.20

D132

Installation guide frame for diversion closing gate

JD0132

1 LS

15d

2017.Apr.01

2017.Apr.15

1d

2017.Apr.21

2017.Apr.21

2017.Apr.21, River Diversion

JD0101

1 LS

1d

2017.Apr.21

2017.Apr.21

Diversion and care of Jalaur river for the afterbay dam area

105d

2017.Apr.22

2017.Aug.04

75d

2017.Apr.22

2017.Jul.05

2590 cu.m.

15d

2017.Apr.22

2017.May.06

Excavation, in common, in open-cut for upstream cofferdam


Excavation, in rock, in open-cut for upstream cofferdam

Formworks for Item No. D130


Installation guide frame for diversion closing gate

2017.Aug.04, Cofferdams
2017.Jul.05, U/S Cofferdam

D102 Excavation, in common, in open-cut for upstream


cofferdam

JD0102

D103 Excavation, in rock, in open-cut for upstream cofferdam

JD0103

159 cu.m.

20d

2017.Apr.27

2017.May.16

D104 A2 Concrete in Upstream Cofferdam

JD0104

4879 cu.m.

30d

2017.May.17

2017.Jun.15

D105 C Concrete in Upstream Cofferdam

JD0105

4375 cu.m.

30d

2017.Jun.06

2017.Jul.05

C Concrete in Upstream Cofferdam

D106 Form for Item No. D105

JD0106

686 sq.m.

30d

2017.Jun.06

2017.Jul.05

Form for Item No. D105

30d

2017.Jul.06

2017.Aug.04

2017.Aug.04, D/S Cofferdam

JD0129

1 LS

30d

2017.Jul.06

2017.Aug.04

Constructing, maintenance and removal of downstream cofferdam

1211d

2016.May.31

2019.Sep.23

Critical Remaining Work

Remaining Work

Milestone

Summary

Apr May
52 53

Plugging concrete in diversion tunnel

20d

Actual Work

2020
Mar
51

Backfill with excavated material

20d

Dam Body (Afterbay)

Feb
50

Pressure grouting of consilidation grouting in diversion tunnel

20 cu.m.

D129 Constructing, maintenance and removal of downstream


cofferdam

Jan
49

Furnishing and installing rock bolt for diversion tunnel

JD0130

D/S Cofferdam
Co

Dec
48

Furnishing, installing, operating, maintaining and removing lighting and ventilation system

2nd Stage Concrete for inlet of diversion tunnel

U/S Cofferdam
Co

Jan
37

Excavation, all classes for diversion

D130

Cofferdams
Cofferdam

Dec
36

2019.Oct.16, Tunnel Works

5248 cu.m.

Diversion and care of Jalaur river for the afterbay dam


area

Nov
35

Excavation, in rock, in open-cut for diversion tunnel

JD0110

D101

Oct
34

2016.Sep.30, Portal Excavation

JD0109

River Diversion
Dive

Sep
33

Excavation, in rock, in open-cut for diversion tunnel

Furnishing and installing rock bolt for diversion tunnel

Portal Structure
Stru

Aug
32

Furnishing and installing 1,200mm diameter concrete pipe culvert

Excavation, all classes for diversion

129 m

2018
Jun Jul
30
31

Drilling drainage hole into foundation

D110

24 Time

May
29

Furnishing and installing 1,000mm diameter concrete pipe culvert

D109

1 LS

Apr
28

A2 Concrete in Upstream Cofferdam

2019.Sep.23, Dam Body (Afterbay)

Page 5 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Activity Name

Classic WBS_Jalaur
CODE

Quantity Unit

Excavation

Original
Duration

Start

Finish

396d

2016.May.31

2017.Jun.30

2016.May.31

2017.Jun.17

Jan
1

Feb
2

Mar
3

Apr
4

May
5

2016
Jun Jul
6
7

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

2015.Dec.14 07:59
2017
Jun Jul Aug Sep Oct Nov
18
19
20
21
22
23
2017.Jun.30, Excavation

Dec
24

Jan
25

D201

Excavation, common in open-cut for afterbay dam

JD0201

382d 4h

D202

Excavation, rock in open-cut for afterbay dam

JD0202

376d

2016.Jun.20

2017.Jun.30

Excavation, rock in open-cut for afterbay dam

D207

Clean-off of foundation for inspection

JD0207

285d

2016.Sep.18

2017.Jun.29

Clean-off of foundation for inspection

Feb
26

Mar
27

Apr
28

May
29

2018
Jun Jul
30
31

Aug
32

Sep
33

Oct
34

Nov
35

Dec
36

Jan
37

Feb
38

Mar
39

Apr
40

May
41

2019
Jun Jul
42
43

Aug
44

Sep
45

Oct
46

Nov
47

Dec
48

Jan
49

Feb
50

2020
Mar
51

Apr May
52 53

Excavation, common in open-cut for afterbay dam

75d

2017.Jul.01

2017.Sep.13

D301

Drilling grout holes foundation in the stage between 0 m


and 15 m less inclined than 15

JD0301

4949 m

25d

2017.Jul.01

2017.Jul.25

D302

Drilling grout holes foundation in the stage between 0 m


and 15 m more inclined than 15

JD0302

368 m

25d

2017.Jul.11

2017.Aug.04

D303

Drilling grout holes foundation in the stage between 15 m


and 40 m less inclined than 15

JD0303

894 m

25d

2017.Jul.21

2017.Aug.14

D304

Drilling grout holes foundation in the stage between 15 m


and 40 m more inclined than 15

JD0304

88 m

25d

2017.Jul.31

2017.Aug.24

D305

Drilling grout holes foundation in the stage between 40 m


and 100 m less inclined than 15

JD0305

9 m

25d

2017.Aug.10

2017.Sep.03

D306

Furnishing and installing casing in grout holes

JD0306

160 m

75d

2017.Jul.01

2017.Sep.13

D307

Drilling grout holes in foundation stage between 0 m and


15 m less inclined than 15

JD0307

990 m

25d

2017.Jul.11

2017.Aug.04

D308

Re-drilling grout holes in foundation stage between 0 m


and 15 m more inclined than 15

JD0308

74 m

25d

2017.Jul.21

2017.Aug.14

D309

Re-drilling grout holes in foundation stage between 15 m


and 40 m less inclined than 15

JD0309

179 m

25d

2017.Jul.31

2017.Aug.24

D310

Re-drilling grout holes in foundation stage between 15 m


and 40 m more inclined than 15

JD0310

18 m

25d

2017.Aug.10

2017.Sep.03

D311

Re-drilling grout holes in foundation in the stage between


40 m and 100 m less inclined than 15

JD0311

2 m

25d

2017.Aug.20

2017.Sep.13

D312

Core Drilling NX

JD0312

100 m

30d

2017.Jul.01

2017.Jul.30

Core Drilling NX

D313

Core Drilling BX

JD0313

100 m

30d

2017.Jul.01

2017.Jul.30

Core Drilling BX

D314

Pressure grouting foundation

JD0314

313298 kg

75d

2017.Jul.01

2017.Sep.13

740d

2017.Sep.14

2019.Sep.23

D402

Furnishing, handling and placing reinforcement for intake JD0402


structure for irrigation canal

25385 kg

60d

2017.Dec.19

2018.Feb.16

Furnishing, handling and placing reinforcement for intake structure for irrigation canal

D403

Furnishing, handling and placing reinforcement of dam


crest structure

JD0403

4106 kg

29d

2018.Jan.18

2018.Feb.15

Furnishing, handling and placing reinforcement of dam crest structure

D406

Furnishing, handling and placing reinforcement for minor


structure in afterbay dam site

JD0406

8812 kg

87d

2017.Dec.04

2018.Feb.28

D407

Furnishing, handling and placing reinforcement


surrounding of opening structure in dam body

JD0407

79428 kg

149d

2017.Sep.20

2018.Feb.15

D501

Dental concrete

JD0501

50 cu.m.

6d

2017.Sep.14

2017.Sep.19

D502

Concrete type A2 in afterbay dam spillway

JD0502

38002 cu.m.

150d

2017.Sep.20

2018.Feb.16

D503

Concrete type C in afterbay dam spillway

JD0503

34927 cu.m.

147d

2017.Oct.05

2018.Feb.28

Concrete type C in afterbay dam spillway

D504

Form works for item D503

JD0504

7619 sq.m.

147d

2017.Oct.05

2018.Feb.28

Form works for item D503

D511

Concrete for irrigation canal including intake structure

JD0511

587 cu.m.

72d

2017.Dec.19

2018.Feb.28

D512

Form works for item D511

JD0512

804 sq.m.

1d

2017.Dec.19

2017.Dec.19

D513

Concrete for minor structure in afterbay dam site

JD0513

344 cu.m.

87d

2017.Dec.04

2018.Feb.28

Concrete for minor structure in afterbay dam site

D514

Form works for item D513

JD0514

800 sq.m.

87d

2017.Dec.04

2018.Feb.28

Form works for item D513

D515

Concrete in blockouts larger than 600 cm

JD0515

4 cu.m.

147d

2017.Oct.05

2018.Feb.28

Concrete in blockouts larger than 600 cm

D516

Form works for item D515

JD0516

16 sq.m.

147d

2017.Oct.05

2018.Feb.28

Form works for item D515

D517

Concrete for gate chamber and gallery

JD0517

1548 cu.m.

119d

2017.Oct.05

2018.Jan.31

Concrete for gate chamber and gallery

D518

Form works for item D517

JD0518

2213 sq.m.

119d

2017.Oct.05

2018.Jan.31

Form works for item D517

D519

2nd stage concrete for gate chamber

JD0519

93 cu.m.

28d

2018.Feb.01

2018.Feb.28

2nd stage concrete for gate chamber

D601

Precast concrete cover

JD0601

42 cu.m.

87d

2017.Dec.04

2018.Feb.28

Precast concrete cover

D602

Miscellaneous precast concrete

JD0602

20 cu.m.

87d

2017.Dec.04

2018.Feb.28

Miscellaneous precast concrete

D701

Furnishing and placing 200 mm in width plastic water


stop

JD0701

758 m

150d

2017.Sep.20

2018.Feb.16

Furnishing and placing 200 mm in width plastic water stop

D702

Furnishing and placing 300 mm in width plastic stop

JD0702

663 m

150d

2017.Sep.20

2018.Feb.16

Furnishing and placing 300 mm in width plastic stop

D703

Furnishing and placing copper water stop

JD0703

2671 kg

150d

2017.Sep.20

2018.Feb.16

Furnishing and placing copper water stop

D704

Furnishing and placing galvanized joint metal

JD0704

50077 kg

150d

2017.Sep.20

2018.Feb.16

Furnishing and placing galvanized joint metal

D901

Furnishing and installing 300mm diameter perforated


PVC pipe with geotextile filter mat

JD0901

362 m

150d

2017.Sep.20

2018.Feb.16

Furnishing and installing 300mm diameter perforated PVC pipe with geotextile filter mat

D1102

Furnishing and installing afterbay dam crest handrail

JD1102

318 kg

40d

2019.Aug.15*

2019.Sep.23

D1103

Furnishing and installing pipe handrail

JD1103

1087 kg

30d

2019.Aug.15

2019.Sep.13

D1104

Furnishing and installing steel miscellaneous embedded


metal works

JD1104

50 kg

40d

2019.Aug.15

2019.Sep.23

Furnishing and installing steel miscellaneous embe

D1105

Furnishing and installing miscellaneous non-embedded


metal works

JD1105

50 kg

32d

2019.Aug.15

2019.Sep.15

Furnishing and installing miscellaneous non-embedd

D1109

Furnishing and installing stone pitching

JD1109

68 sq.m.

149d

2018.Jan.03

2018.May.31

413d

2017.Sep.14

2018.Oct.31

109d

2017.Sep.14

2017.Dec.31

Foundation
Foundatio

Structure

Spillway
D214

Pneumatically applied mortar

JD0214

2669 sq.m.

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

2017.Sep.13, Foundation
Drilling grout holes foundation in the stage between 0 m and 15 m less inclined than 15
Drilling grout holes foundation in the stage between 0 m and 15 m more inclined than 15
Drilling grout holes foundation in the stage between 15 m and 40 m less inclined than 15
Drilling grout holes foundation in the stage between 15 m and 40 m more inclined than 15
Drilling grout holes foundation in the stage between 40 m and 100 m less inclined than 15
Furnishing and installing casing in grout holes
Drilling grout holes in foundation stage between 0 m and 15 m less inclined than 15
Re-drilling grout holes in foundation stage between 0 m and 15 m more inclined than 15
Re-drilling grout holes in foundation stage between 15 m and 40 m less inclined than 15
Re-drilling grout holes in foundation stage between 15 m and 40 m more inclined than 15
Re-drilling grout holes in foundation in the stage between 40 m and 100 m less inclined than 15

Pressure grouting foundation


2019.Sep.23, Structure

Furnishing, handling and placing reinforcement for minor structure in afterbay dam site
Furnishing, handling and placing reinforcement surrounding of opening structure in dam body
Dental concrete
Concrete type A2 in afterbay dam spillway

Concrete for irrigation canal including intake structure


Form works for item D511

Furnishing and installing afterbay dam crest handr


Furnishing and installing pipe handrail

Furnishing and installing stone pitching


2018.Oct.31, Spillway
Pneumatically applied mortar

Page 6 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

D215

Furnishing and installing steel mesh reinforcement

JD0215

D216

Furnishing and installing rock anchors for steel mesh


reinforcement

JD0216

D217

Grouted reinforcement anchor bars

D401

Furnishing, handling and placing reinforcement for


spillway chute way and sidewall

D404

Quantity Unit

2016
Jun Jul
6
7

2015.Dec.14 07:59
2017
Jun Jul
18
19

2018
Jun Jul
30
31

2019
Jun Jul
42
43

Original
Duration

Start

Finish

7401 kg

64d

2018.Jul.28

2018.Sep.29

726 m

57d

2018.Jul.28

2018.Sep.22

JD0217

726 m

109d

2017.Sep.14

2017.Dec.31

JD0401

64021 kg

64d

2018.Jul.28

2018.Sep.29

Furnishing, handling and placing reinforcement for


spillway over bridge

JD0404

117724 kg

117d

2018.Jan.18

2018.May.14

D405

Furnishing, handling and placing reinforcement for


spillway stilling basin and side wall

JD0405

179577 kg

102d

2018.Apr.16

2018.Jul.26

Furnishing, handling and placing reinforcement for spillway stilling basin and side wall

D505

Concrete for spillway chute block and side wall

JD0505

6293 cu.m.

73d

2018.May.16

2018.Jul.27

Concrete for spillway chute block and side wall

D506

Form works for item D505

JD0506

1283 sq.m.

73d

2018.May.16

2018.Jul.27

D507

Concrete spillway over bridge

JD0507

910 cu.m.

88d

2018.Feb.17

2018.May.15

Concrete spillway over bridge

D508

Form works for item No. D507

JD0508

1337 sq.m.

88d

2018.Feb.17

2018.May.15

Form works for item No. D507

D509

Concrete spillway stilling basin and side wall

JD0509

8687 cu.m.

65d

2018.Jul.28

2018.Sep.30

Concrete spillway stilling basin and side wall

D510

Form works for item No. D509

JD0510

4378 sq.m.

65d

2018.Jul.28

2018.Sep.30

Form works for item No. D509

D902

Furnishing and installing 500mm diameter perforated


PVC pipe with geotextile filter mat

JD0902

122 m

31d

2018.Oct.01

2018.Oct.31

D1001

Furnishing and installing outlet steel conduit

JD1001

6023 kg

44d

2017.Oct.20

2017.Dec.02

Furnishing and installing outlet steel conduit

D1002

Furnishing and installing outlet gate and hoist

JD1002

1 LS

40d

2017.Oct.25

2017.Dec.03

Furnishing and installing outlet gate and hoist

D1003

Furnishing and installing intake gate for high canal

JD1003

1 LS

34d

2018.Jan.13

2018.Feb.15

Furnishing and installing intake gate for high canal

D1004

Furnishing and valve for MC-1

JD1004

1 LS

34d

2018.Jan.13

2018.Feb.15

Furnishing and valve for MC-1

D1005

Furnishing and installing steel conduit for MC-1

JD1005

2980 kg

34d

2018.Jan.13

2018.Feb.15

Furnishing and installing steel conduit for MC-1

D1101

Furnishing and installing mild steel anchor bolts

JD1101

50 nos

34d

2018.Jan.13

2018.Feb.15

Furnishing and installing mild steel anchor bolts

Jan
1

Feb
2

Mar
3

Apr
4

May
5

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

Jan
25

Feb
26

Mar
27

Apr
28

May
29

Aug
32

Sep
33

Oct Nov Dec Jan Feb Mar Apr May


34
35
36
37
38
39
40
41
Furnishing and installing steel mesh reinforcement

Aug
44

Sep
45

Oct
46

Nov
47

Dec
48

Jan
49

Furnishing, handling and placing reinforcement for spillway chute way and sidewall
Furnishing, handling and placing reinforcement for spillway over bridge

Form works for item D505

Furnishing and installing 500mm diameter perforated PVC pipe with geotextile filter mat

274d

2018.Mar.01

2018.Nov.29

JD0801

1 LS

20d

2018.Mar.01

2018.Mar.20

D1201

Furnishing and Installation of Feeder line, Transfor mer


and Pole dressing

JD1201

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of Feeder line, Transfor mer and Pole dressing

D1202

Furnishing and Installation of 3 units 15KVA transformer

JD1202

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of 3 units 15KVA transformer

D1203

Furnishing and Installation of One Automatic Transfer


Switch

JD1203

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of One Automatic Transfer Switch

D1204

Furnishing and Installation of One Main Distribution Panel JD1204

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of One Main Distribution Panel

D1205

Furnishing and Installation of Four Distribution Panel

JD1205

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of Four Distribution Panel

D1206

Furnishing and Installation of one unit 150KVA Diesel


Generator w/ fuel stock w/ hand pump

JD1206

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of one unit 150KVA Diesel Generator w/ fuel stock w/ hand pump

D1207

Furnishing and Installation of Lighting fixtures in operation JD1207


/ Generator room area

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of Lighting fixtures in operation / Generator room area

D1208

Furnishing and Installation of Switches in operation /


Generator room area

JD1208

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of Switches in operation / Generator room area

D1209

Furnishing and Installation of Power outlet in operation /


Generator room area

JD1209

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of Power outlet in operation / Generator room area

D1210

Furnishing and Installation of Conduit, Raceway, and


Boxes

JD1210

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of Conduit, Raceway, and Boxes

D1211

Furnishing and Wiring installation and Feeder Line


installation

JD1211

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Wiring installation and Feeder Line installation

D1212

Furnishing and Installation of Fire extinguisher at


operation / Generator room

JD1212

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of Fire extinguisher at operation / Generator room

D1213

Furnishing of Operation desk chair at Electrical


maintenance building

JD1213

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing of Operation desk chair at Electrical maintenance building

D1214

Furnishing and Installation of Grounding system and


Lighting system

JD1214

1 LS

60d

2018.Oct.01

2018.Nov.29

Furnishing and Installation of Grounding system and Lighting system

D1215

Other Miscellaneous and fixing materials

JD1215

1 LS

60d

2018.Oct.01

2018.Nov.29

Other Miscellaneous and fixing materials

D1403

Closed circuit watch system and remote control system


of gates

JD1403

PS

60d

2018.Oct.01

2018.Nov.29

Closed circuit watch system and remote control system of gates

140d

2018.Jul.28

2018.Dec.14

2018.Nov.29, Mech, Electrical, Architecture, Instrumentation

863 cu.m.

60d

2018.Oct.01

2018.Nov.29

Furnishing and installing PVC water level gauge at upstream and downstream face of Afterbay dam

2018.Dec.14, Others

D208

Free drainage backfill

JD0208

D209

Gravel bedding and gravel fill

JD0209

70 cu.m.

60d

2018.Oct.16

2018.Dec.14

Gravel bedding and gravel fill

D210

Riprap protection

JD0210

983 sq.m.

60d

2018.Oct.16

2018.Dec.14

Riprap protection

D282

Seeding with coconet

JD0213

1447 sq.m.

60d

2018.Oct.16

2018.Dec.14

D336

Furnishing and installing 300mm diameter concrete


culvert

JD0903

50 m

63d

2018.Jul.28

2018.Sep.28

Furnishing and installing 300mm diameter concrete culvert

D337

Furnishing and installing 450mm diameter concrete


culvert

JD0904

50 m

63d

2018.Jul.28

2018.Sep.28

Furnishing and installing 450mm diameter concrete culvert

D338

Furnishing and installing 600mm diameter concrete


culvert

JD0905

50 m

63d

2018.Jul.28

2018.Sep.28

Furnishing and installing 600mm diameter concrete culvert

D339

Drilling drainage hole into foundation

JD0906

401 m

63d

2018.Jul.28

2018.Sep.28

Drilling drainage hole into foundation

D340

Furnishing and installing PVC downspout and fittings

JD0907

20 m

63d

2018.Jul.28

2018.Sep.28

Furnishing and installing PVC downspout and fittings

D351

Furnishing and installing chain wire fencing

JD1106

100 sq.m.

63d

2018.Jul.28

2018.Sep.28

Furnishing and installing chain wire fencing

D352

Furnishing and installing rock fence

JD1107

122 m

63d

2018.Jul.28

2018.Sep.28

Furnishing and installing rock fence

D353

Furnishing and installing entrance gate

JD1108

792 kg

63d

2018.Jul.28

2018.Sep.28

Furnishing and installing entrance gate

D370

Design, furnishing and construction guard house

JD1301

63d

2018.Jul.28

2018.Sep.28

Design, furnishing and construction guard house

2 nos

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Apr May
52 53

Grouted reinforcement anchor bars

Furnishing and installing PVC water level gauge at


upstream and downstream face of Afterbay dam

Others

2020
Mar
51

Furnishing and installing rock anchors for steel mesh reinforcement

D0801

Mech, Elect
Electrical, Architecture, Instrumentation

Feb
50

Free drainage backfill

Seeding with coconet

Page 7 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur
Start

Finish

500 sq.m.

63d

2018.Jul.28

2018.Sep.28

2019
Oct Nov Dec Jan Feb Mar Apr May Jun Jul
34
35
36
37
38
39
40
41
42
43
Design, furnishing, construction and operation building

JD1401

2 LS

63d

2018.Jul.28

2018.Sep.28

Furnishing and installing trash fence

JD1402

PS

126d

2018.Jul.28

2018.Nov.30

757d

2016.Feb.01

2018.Feb.26

CODE

D371

Design, furnishing, construction and operation building

JD1302

D372

Furnishing and installing trash fence

D373

Special protection for excavated slope

Quantity Unit

ALIBUNAN CATCH DAM


E101

Diversion and care of Alibunan River

JE0101

1 LS

First Stage
Excavation
1 LS

Jan
1

Feb
2

Mar
3

Apr
4

May
5

2016
Jun Jul
6
7

2015.Dec.14 07:59

Original
Duration

Activity Name

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

2017
Jun Jul
18
19

1d

2016.Feb.01

2016.Feb.01

257d

2016.Oct.01

2017.Jun.14

107d

2016.Oct.01

2017.Jan.15

2017.Jan.15, Excavation

61d

2016.Oct.01

2016.Nov.30

Two stage coffering system (1st Stage Work)

Excavation, in common, in open-cut

JE0201

11871 cu.m.

46d

2016.Dec.01

2017.Jan.15

Excavation, in common, in open-cut

E202

Excavation, in rock, in open-cut

JE0202

35801 cu.m.

36d

2016.Dec.11

2017.Jan.15

Excavation, in rock, in open-cut

E203

Clean-off of foundation for inspection

JE0203

2000 cu.m.

46d

2016.Dec.01

2017.Jan.15

Clean-off of foundation for inspection

175 cu.m.

E208

Furnishing and installing rock anchor for steel mesh


reinforcement

JE0208

73 m

E209

Drilling holes for anchor bars and grout anchor bars

JE0209

800 m

E301

Drilling grout holes foundation between 0 mm and 15 mm JE0301


less inclined than 15

350 m

E302

Re-drilling grout hole foundation between 0 m and 15 m


less inclined than 15

JE0302

70 m

E401

Furnishing, handling and placing reinforcement bars

JE0401

62562 kg

E501

Dental concrete

JE0501

30 cu.m.

2016.Dec.11

2017.Mar.15

2016.Dec.16

2017.Feb.15

1d

2016.Dec.11

2016.Dec.11

Furnishing and installing rock anchor for steel mesh reinforcement

62d

2016.Dec.16

2017.Feb.15

Drilling holes for anchor bars and grout anchor bars

62d

2016.Dec.16

2017.Feb.15

Drilling grout holes foundation between 0 mm and 15 mm less inclined than 15

65d

2016.Dec.26

2017.Feb.28

59d

2017.Jan.16

2017.Mar.15

36d

2016.Dec.11

2017.Jan.15
2017.Mar.16

2017.Jan.16

2017.Feb.14

E503

Concrete type D, for gate structure and water passage


structure

JE0503

3093 cu.m.

30d

2017.Feb.15

2017.Mar.16

E504

Form works for item E502

JE0504

1230 sq.m.

32d

2017.Jan.16

2017.Feb.16

E505

Form works for item E503

JE0505

3185 sq.m.

27d

2017.Feb.15

2017.Mar.13

Form works for item E503

E506

Concrete blockout larger than 600m

JE0506

35 cu.m

32d

2017.Jan.16

2017.Feb.16

Concrete blockout larger than 600m

E507

Form works for item E506

JE0507

56 sq.m.

32d

2017.Jan.21

2017.Feb.21

E601

Furnishing, installing and placing 200mm in width plastic


water stop for stilling basin slab

JE0601

50 m

44d

2017.Jan.16

2017.Feb.28

27d

2017.Feb.15

2017.Mar.13

E204

Backfill with excavated material

JE0204

2128 cu.m.

15d

2017.Feb.15

2017.Mar.01

E205

RIPRAP Protection

JE0205

1326 sq.m.

12d

2017.Mar.02

2017.Mar.13

RIPRAP Protection

E206

Stone pitching

JE0206

407 sq.m.

12d

2017.Mar.02

2017.Mar.13

Stone pitching

120d

2017.Feb.15

2017.Jun.14

E801

Furnishing and installing intake gate

JE0801

1 LS

30d

2017.Mar.17

2017.Apr.15

E802

Furnishing and installing desilting gate

JE0802

1 LS

30d

2017.Apr.16

2017.May.15

E803

Furnishing and installing trashrack

JE0803

1 LS

30d

2017.May.16

2017.Jun.14

E901

Furnishing and installing mild steel anchor bolt diameter


32mm x 4m long spaced at 1.5m O.C. BW

JE0901

6137 kg

30d

2017.Feb.15

2017.Mar.16

75d

2017.Mar.17

2017.May.30

Oct
46

Nov
47

Dec
48

Jan
49

Feb
50

2020
Mar
51

Apr May
52 53

2017.May.30, Others
Furnishing and installing handrail

Concrete type D, for gate structure and water passage structure

Form works for item E506


Furnishing, installing and placing 200mm in width plastic water stop for stilling basin slab
2017.Mar.13, Bac kfilling
Backfill with excavated material

2017.Jun.14, Gates
Furnishing and installing intake gate
Furnishing and installing desilting gate
Furnishing and installing trashrack
Furnishing and installing mild steel anchor bolt diameter 32mm x 4m long spaced at 1.5m O.C. BW

1130 kg

20d

2017.Mar.17

2017.Apr.05

E903

Furnishing and installing miscellaneous non-embedded


metal works

JE0903

50 kg

20d

2017.Apr.11

2017.Apr.30

Furnishing and installing miscellaneous non-embedded metal works

E904

Furnishing and installing miscellaneous embedded metal


works

JE0904

50 kg

15d

2017.May.06

2017.May.20

Furnishing and installing miscellaneous embedded metal works

E905

Furnishing and installing chain wire fencing

JE0905

20d

2017.May.11

2017.May.30

Furnishing and installing chain wire fencing

72d

2017.Mar.17

2017.May.27

2017.May.27, Electrical

E1001

Furnishing and Installation of Feeder line, Transfor mer


and Pole dressing

JE1001

1 LS

25d

2017.Mar.17

2017.Apr.10

E1002

Furnishing and Installation of 3 units 15KVA transformer

JE1002

1 LS

25d

2017.Mar.22

2017.Apr.15

E1003

Furnishing and Installation of One Automatic Transfer


Switch

JE1003

1 LS

25d

2017.Mar.27

2017.Apr.20

E1004

Furnishing and Installation of One Main Distribution Panel JE1004

1 LS

25d

2017.Apr.01

2017.Apr.25

Furnishing and Installation of One Main Distribution Panel

E1005

Furnishing and Installation of Four Distribution Panel

JE1005

1 LS

25d

2017.Apr.04

2017.Apr.28

Furnishing and Installation of Four Distribution Panel

E1006

Furnishing and Installation of one unit 150KVA Diesel


Generator w/ fuel stock w/ hand pump

JE1006

1 LS

25d

2017.Apr.09

2017.May.03

E1007

Furnishing and Installation of Lighting fixtures in operation JE1007


/ Generator room area

1 LS

25d

2017.Apr.14

2017.May.08

Furnishing and Installation of Lighting fixtures in operation / Generator room area

E1008

Furnishing and Installation of Switches in operation /


Generator room area

JE1008

1 LS

25d

2017.Apr.17

2017.May.11

Furnishing and Installation of Switches in operation / Generator room area

E1009

Furnishing and Installation of Power outlet in operation /


Generator room area

JE1009

1 LS

25d

2017.Apr.17

2017.May.11

Furnishing and Installation of Power outlet in operation / Generator room area

Summary

Sep
45

Form works for item E502

JE0902

Milestone

Aug
44

2017.Mar.16, Weir & Walls

Furnishing and installing handrail

Critical Remaining Work

Sep
33

Concrete type C, for wier and retain of wall, stilling basin slab

E902

Remaining Work

Aug
32

Furnishing, handling and placing reinforcement bars

2017.Jan.16

Actual Work

2018
Jun Jul
30
31

Dental concrete

30d

Electrical

May
29

Re-drilling grout hole foundation between 0 m and 15 m less inclined than 15

60d

120 sq.m.

Apr
28

2017.Mar.15, Foundation Treatment

4295 cu.m.

Others

Mar
27

Pneumatically applied mortar

JE0502

Gates

Feb
26

62d

Concrete type C, for wier and retain of wall, stilling basin


slab

Backfilling

Jan
25

95d

E502

Weir & Walls


Wa

Dec
24

2017.Jun.14, First Stage

E201

JE0207

Nov
23

Diversion and care of Alibunan River

JE0102

Pneumatically applied mortar

Oct
22

Special protection for excavated slope

Two stage coffering system (1st Stage Work)

E207

Sep
21

2018.Feb.26, ALIBUNAN CATCH DAM

E102

Foundatio Treatment
Foundation

Aug
20

Furnishing and Installation of Feeder line, Transfor mer and Pole dressing
Furnishing and Installation of 3 units 15KVA transformer
Furnishing and Installation of One Automatic Transfer Switch

Furnishing and Installation of one unit 150KVA Diesel Generator w/ fuel stock w/ hand pump

Page 8 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

E1010

Furnishing and Installation of Conduit, Raceway, and


Boxes

JE1010

E1011

Furnishing and Wiring installation and Feeder Line

E1012
E1013

Quantity Unit

2016
Jun Jul
6
7

2015.Dec.14 07:59

2017
May Jun Jul Aug Sep Oct Nov Dec Jan Feb
17
18
19
20
21
22
23
24
25
26
Furnishing and Installation of Conduit, Raceway, and Boxes

Original
Duration

Start

Finish

1 LS

25d

2017.Apr.20

2017.May.14

JE1011

1 LS

25d

2017.Apr.23

2017.May.17

Furnishing and Installation of Fire extinguisher at


operation / Generator room

JE1012

1 LS

25d

2017.Apr.26

2017.May.20

Furnishing and Installation of Fire extinguisher at operation / Generator room

Furnishing of Operation desk chair at Electrical


maintenance building

JE1013

1 LS

25d

2017.Apr.29

2017.May.23

Furnishing of Operation desk chair at Electrical maintenance building

E1014

Furnishing and Installation of Grounding system and


Lighting system

JE1014

1 LS

25d

2017.May.01

2017.May.25

Furnishing and Installation of Grounding system and Lighting system

E1015

Other Miscellaneous and fixing materials

JE1015

1 LS

25d

2017.May.03

2017.May.27

Other Miscellaneous and fixing materials

257d

2017.Jun.15

2018.Feb.26

107d

2017.Jun.15

2017.Sep.29

2017.Sep.29, Excavation

Second Stage
Sta
Excavation
1 LS

Jan
1

Feb
2

Mar
3

Apr
4

May
5

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

Mar
27

2018
Jun Jul
30
31

Aug
32

Sep
33

Oct
34

Two stage coffering system (1st Stage Work)

JE0102

61d

2017.Jun.15

2017.Aug.14

Two stage coffering system (1st Stage Work)

Excavation, in common, in open-cut

JE0201

11871 cu.m.

46d

2017.Aug.15

2017.Sep.29

Excavation, in common, in open-cut

E1058

Excavation, in rock, in open-cut

JE0202

35801 cu.m.

36d

2017.Aug.25

2017.Sep.29

Excavation, in rock, in open-cut

E1059

Clean-off of foundation for inspection

JE0203

2000 cu.m.

46d

2017.Aug.15

2017.Sep.29

Clean-off of foundation for inspection

95d

2017.Aug.25

2017.Nov.27

62d

2017.Aug.30

2017.Oct.30

Pneumatically applied mortar

JE0207

E1050

Furnishing and installing rock anchor for steel mesh


reinforcement

JE0208

73 m

1d

2017.Aug.25

2017.Aug.25

Furnishing and installing rock anchor for steel mesh reinforcement

E1051

Drilling holes for anchor bars and grout anchor bars

JE0209

800 m

62d

2017.Aug.30

2017.Oct.30

Drilling holes for anchor bars and grout anchor bars

E1052

Drilling grout holes foundation between 0 mm and 15 mm JE0301


less inclined than 15

350 m

62d

2017.Aug.30

2017.Oct.30

Drilling grout holes foundation between 0 mm and 15 mm less inclined than 15

E1053

Re-drilling grout hole foundation between 0 m and 15 m


less inclined than 15

JE0302

70 m

65d

2017.Sep.09

2017.Nov.12

E1054

Furnishing, handling and placing reinforcement bars

JE0401

62562 kg

59d

2017.Sep.30

2017.Nov.27

E1055

Dental concrete

JE0501

36d

2017.Aug.25

2017.Sep.29

60d

2017.Sep.30

2017.Nov.28

30 cu.m.

2017.Sep.30

2017.Oct.29

E1040

Concrete type D, for gate structure and water passage


structure

JE0503

3093 cu.m.

30d

2017.Oct.30

2017.Nov.28

E1041

Form works for item E502

JE0504

1230 sq.m.

32d

2017.Sep.30

2017.Oct.31

E1042

Form works for item E503

JE0505

3185 sq.m.

27d

2017.Oct.30

2017.Nov.25

Form works for item E503

E1043

Concrete blockout larger than 600m

JE0506

35 cu.m

32d

2017.Sep.30

2017.Oct.31

Concrete blockout larger than 600m

E1044

Form works for item E506

JE0507

56 sq.m.

32d

2017.Oct.05

2017.Nov.05

E1045

Furnishing, installing and placing 200mm in width plastic


water stop for stilling basin slab

JE0601

50 m

44d

2017.Sep.30

2017.Nov.12

27d

2017.Oct.30

2017.Nov.25
2017.Nov.13

E1047

RIPRAP Protection

JE0205

1326 sq.m.

12d

2017.Nov.14

2017.Nov.25

RIPRAP Protection

E1048

Stone pitching

JE0206

407 sq.m.

Stone pitching

JE0801

1 LS

30d

2017.Nov.29

2017.Dec.28

E1017

Furnishing and installing desilting gate

JE0802

1 LS

30d

2017.Dec.29

2018.Jan.27

E1018

Furnishing and installing trashrack

JE0803

1 LS

30d

2018.Jan.28

2018.Feb.26

E1019

Furnishing and installing mild steel anchor bolt diameter


32mm x 4m long spaced at 1.5m O.C. BW

JE0901

6137 kg

30d

2017.Oct.30

2017.Nov.28

75d

2017.Nov.29

2018.Feb.11

2018.Feb.11, Others

E1020

Furnishing and installing handrail

JE0902

1130 kg

20d

2017.Nov.29

2017.Dec.18

Furnishing and installing handrail

E1021

Furnishing and installing miscellaneous non-embedded


metal works

JE0903

50 kg

20d

2017.Dec.24

2018.Jan.12

Furnishing and installing miscellaneous non-embedded metal works

E1022

Furnishing and installing miscellaneous embedded metal


works

JE0904

50 kg

15d

2018.Jan.18

2018.Feb.01

Furnishing and installing miscellaneous embedded metal works

E1023

Furnishing and installing chain wire fencing

JE0905

20d

2018.Jan.23

2018.Feb.11

Furnishing and installing chain wire fencing

72d

2017.Nov.29

2018.Feb.08

2018.Feb.08, Electrical

Furnishing and installing trashrack


Furnishing and installing mild steel anchor bolt diameter 32mm x 4m long spaced at 1.5m O.C. BW

JE1001

1 LS

25d

2017.Nov.29

2017.Dec.23

E1025

Furnishing and Installation of 3 units 15KVA transformer

JE1002

1 LS

25d

2017.Dec.04

2017.Dec.28

E1026

Furnishing and Installation of One Automatic Transfer


Switch

JE1003

1 LS

25d

2017.Dec.09

2018.Jan.02

Furnishing and Installation of One Automatic Transfer Switch

E1027

Furnishing and Installation of One Main Distribution Panel JE1004

1 LS

25d

2017.Dec.14

2018.Jan.07

Furnishing and Installation of One Main Distribution Panel

E1028

Furnishing and Installation of Four Distribution Panel

JE1005

1 LS

25d

2017.Dec.17

2018.Jan.10

Furnishing and Installation of Four Distribution Panel

E1029

Furnishing and Installation of one unit 150KVA Diesel


Generator w/ fuel stock w/ hand pump

JE1006

1 LS

25d

2017.Dec.22

2018.Jan.15

E1030

Furnishing and Installation of Lighting fixtures in operation JE1007


/ Generator room area

1 LS

25d

2017.Dec.27

2018.Jan.20

Furnishing and Installation of Lighting fixtures in operation / Generator room area

E1031

Furnishing and Installation of Switches in operation /


Generator room area

1 LS

25d

2017.Dec.30

2018.Jan.23

Furnishing and Installation of Switches in operation / Generator room area

Milestone

Summary

Apr May
52 53

Furnishing and installing desilting gate

Furnishing and Installation of Feeder line, Transfor mer


and Pole dressing

Critical Remaining Work

2020
Mar
51

Furnishing and installing intake gate

E1024

Remaining Work

Feb
50

2018.Feb.26, Gates

Furnishing and installing intake gate

Actual Work

Jan
49

Backfill with excavated material

E1016

JE1008

Dec
48

2017.Nov.25, Backfilling

2017.Oct.30

Electrical

Nov
47

Furnishing, installing and placing 200mm in width plastic water stop for stilling basin slab

15d

120 sq.m.

Oct
46

Form works for item E506

2128 cu.m.

Others

Sep
45

Form works for item E502

JE0204

2017.Nov.25

Aug
44

Concrete type D, for gate structure and water passage structure

Backfill with excavated material

2018.Feb.26

2019
Jun Jul
42
43

Concrete type C, for wier and retain of wall, stilling basin slab

E1046

2017.Oct.30

May
41

2017.Nov.28, Weir & Walls

30d

2017.Nov.14

Apr
40

Dental concrete

4295 cu.m.

12d

Mar
39

Furnishing, handling and placing reinforcement bars

JE0502

120d

Feb
38

Re-drilling grout hole foundation between 0 m and 15 m less inclined than 15

Concrete type C, for wier and retain of wall, stilling basin


slab

Gates

Jan
37

Pneumatically applied mortar

E1039

Backfilling

Dec
36

2017.Nov.27, Foundation Treatment

E1049

Weir & Walls


Wa

Nov
35

2018.Feb.26, Second Stage

E1057

175 cu.m.

May
29

Furnishing and Wiring installation and Feeder Line

E1056

Foundatio Treatment
Foundation

Apr
28

Furnishing and Installation of Feeder line, Transfor mer and Pole dressing
Furnishing and Installation of 3 units 15KVA transformer

Furnishing and Installation of one unit 150KVA Diesel Generator w/ fuel stock w/ hand pump

Page 9 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II

Classic WBS_Jalaur
Start

Finish

1 LS

25d

2017.Dec.30

2018.Jan.23

2018
Feb Mar Apr May Jun Jul
Aug Sep Oct Nov Dec Jan
26
27
28
29
30
31
32
33
34
35
36
37
Furnishing and Installation of Power outlet in operation / Generator room area

JE1010

1 LS

25d

2018.Jan.02

2018.Jan.26

Furnishing and Installation of Conduit, Raceway, and Boxes

Furnishing and Wiring installation and Feeder Line

JE1011

1 LS

25d

2018.Jan.05

2018.Jan.29

Furnishing and Wiring installation and Feeder Line

Furnishing and Installation of Fire extinguisher at


operation / Generator room

JE1012

1 LS

25d

2018.Jan.08

2018.Feb.01

Furnishing and Installation of Fire extinguisher at operation / Generator room

E1036

Furnishing of Operation desk chair at Electrical


maintenance building

JE1013

1 LS

25d

2018.Jan.11

2018.Feb.04

Furnishing of Operation desk chair at Electrical maintenance building

E1037

Furnishing and Installation of Grounding system and


Lighting system

JE1014

1 LS

25d

2018.Jan.13

2018.Feb.06

Furnishing and Installation of Grounding system and Lighting system

E1038

Other Miscellaneous and fixing materials

JE1015

1 LS

Other Miscellaneous and fixing materials

Activity Name

CODE

E1032

Furnishing and Installation of Power outlet in operation /


Generator room area

JE1009

E1033

Furnishing and Installation of Conduit, Raceway, and


Boxes

E1034
E1035

Quantity Unit

25d

2018.Jan.15

2018.Feb.08

HIGH CANAL
CANA

1027d

2016.Sep.01

2019.Jun.24

Excavation

791d

2016.Oct.01

2018.Nov.30

G101

Canal Excavation ( with Road )

JG0101

3494259 cu.m.

791d

2016.Oct.01

2018.Nov.30

G102

Stripping ( 10 cm minimum )

JG0102

68065 cu.m.

123d

2016.Oct.01

2017.Jan.31

Jan
1

Feb
2

Mar
3

Apr
4

May
5

2016
Jun Jul
6
7

2015.Dec.14 07:59

Original
Duration

Activity ID

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

2017
Jun Jul
18
19

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

Jan
25

Feb
38

Mar
39

Apr
40

May
41

2019
Jun Jul
42
43

762d

2016.Nov.30

2018.Dec.31

2018.Dec.31, Backfill and Embankment

762d

2016.Nov.30

2018.Dec.31

Embankment Construction and Compaction

G202

Hauling ( >60m, Backhoe+Dump Truck )

JG0202

931588 cu.m.

762d

2016.Nov.30

2018.Dec.31

Hauling ( >60m, Backhoe+Dump Truck )

G203

Borrow Pit

JG0203

132490 cu.m.

762d

2016.Nov.30

2018.Dec.31

Borrow Pit

G204

Disposal

JG0204

786983 cu.m.

762d

2016.Nov.30

2018.Dec.31

G205

Cofferdam Embankment

JG0205

86076 cu.m.

731d

2016.Nov.30

2018.Nov.30

G206a

Cofferdam Demolition

JG0206a

57550.2 sheet

446d

2017.Sep.26

2018.Dec.15

Cofferdam Demolition

G206b

Cofferdam P.P Burlap Filling

JG0206b

1752 cu.m.

731d

2016.Nov.30

2018.Nov.30

Cofferdam P.P Burlap Filling

G207

Cofferdam P.P Burlap Demolition

JG0207

1752 cu.m.

446d

2017.Sep.26

2018.Dec.15

G208

Cofferdam P.P Bag

JG0208

62856 sheet

1d

2016.Nov.30

2016.Nov.30

150d

2017.Feb.01

2017.Jun.30

2017.Jun.30, Service Road

Aggregate Base Coarse ( Gravel Surfacing )

JG0301

42512 cu.m.

150d

2017.Feb.01

2017.Jun.30

Aggregate Base Coarse ( Gravel Surfacing )

732d

2016.Dec.30

2018.Dec.31

G401

Lining ( Class "B" Concrete )

JG0401

43439 cu.m.

686d 4h

2017.Jan.29

2018.Dec.16

G402

PVC Pipe diameter 5 cm

JG0402

671d 1h

2017.Jan.29

2018.Dec.01

PVC Pipe diameter 5 cm

G403

Filter Drain ( Coarse Aggr egates )

JG0403

21851 cu.m.

701d 1h

2016.Dec.30

2018.Dec.01

Filter Drain ( Coarse Aggr egates )

G404

Plain Dowel Bar ( 12 mm x 400 mm)

JG0514

64687 ea

686d 4h

2017.Jan.29

2018.Dec.16

Plain Dowel Bar ( 12 mm x 400 mm)

G515.

Dowel Bar Cap

JG0515

64687 ea

686d 4h

2017.Jan.29

2018.Dec.16

Dowel Bar Cap

G517.

Sealant

JG0517

23807 m

612d

2017.Apr.29

2018.Dec.31

G518.

Asphalt Waterproof

JG0518

261460 sq.m.

686d 4h

2017.Jan.29

2018.Dec.16

701d

2016.Nov.30

2018.Oct.31

G501

Class "A" Concrete

JG0501

179070 cu.m.

240d 4h

2017.Feb.19

2017.Oct.17

G502

Lean Concrete

JG0502

20088 cu.m.

184d

2017.Jan.29

2017.Jul.31

G503

Preshunk Concrete

JG0503

45 sq.m.

240d 4h

2017.Feb.19

2017.Oct.17

Preshunk Concrete

G504

Plywood ( 3 times )

JG0504

479239 sq.m.

240d 4h

2017.Feb.19

2017.Oct.17

Plywood ( 3 times )

G505

Circular P.F ( 3 times )

JG0505

815 sq.m.

240d 4h

2017.Feb.19

2017.Oct.17

Circular P.F ( 3 times )

G506

Pipe Support

JG0506

235370 cu.m.

240d 4h

2017.Feb.19

2017.Oct.17

Pipe Support

G507

Horizontal member of Support

JG0507

746 sq.m.

240d 4h

2017.Feb.19

2017.Oct.17

Horizontal member of Support

G508

Steel Pipe Scaffolding

JG0508

107013 sq.m.

240d 4h

2017.Feb.19

2017.Oct.17

Steel Pipe Scaffolding

G509

Spacer ( Wall, vertical )

JG0509

825642 ea

166d

2017.Apr.30

2017.Oct.12

Spacer ( Wall, vertical )

G510

Spacer ( Slab, horizontal )

JG0510

1492188 ea

137d

2017.Jan.30

2017.Jun.15

G511

Construction Joint Surface Clearing

JG0511

240d

2017.Feb.19

2017.Oct.16

G512

Waterstop Sealer

JG0512

171458 m

239d

2017.Jan.30

2017.Sep.25

Waterstop Sealer

G513

Waterstop

JG0513

48514 m

239d

2017.Jan.30

2017.Sep.25

Waterstop

G516

Filler

JG0516

6184 sq.m.

244d

2017.Jan.30

2017.Sep.30

G519

Gravel Bedding

JG0519

5320 cu.m.

201d

2016.Dec.30

2017.Jul.18

G520

Ladder (ST pipe)

JG0520

325 m

75d 4h

2017.Oct.17

2017.Dec.31

G521

Hand rail (ST)

JG0521

361 m

75d 4h

2017.Nov.16

2018.Jan.30

G522

Polyethylene Sheet ( 400?-min. thickness )

JG0522

115778 sq.m.

426d

2016.Dec.30

2018.Feb.28

G523

Fence

JG0523

481 m

90d

2018.Jan.31

2018.Apr.30

172964 pc

Structures

59212 sq.m.

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Dec
48

Jan
49

Feb
50

2020
Mar
51

Apr May
52 53

Canal Excavation ( with Road )

2198331 cu.m.

Canal

Nov
47

Stripping ( 10 cm minimum )

JG0201

G301

Oct
46

2019.Jun.24, HIGH CANAL

Embankment Construction and Compaction

Service Road
Ro

Sep
45

2018.Nov.30, Excavation

G201

Backfill and Embankment

Aug
44

Disposal
Cofferdam Embankment

Cofferdam P.P Burlap Demolition


Cofferdam P.P Bag

2018.Dec.31, Canal
Lining ( Class "B" Concrete )

Sealant
Asphalt Waterproof
2018.Oct.31, Structures
Class "A" Concrete
Lean Concrete

Spacer ( Slab, horizontal )


Construction Joint Surface Clearing

Filler
Gravel Bedding
Ladder (ST pipe)
Hand rail (ST)
Polyethylene Sheet ( 400?-min. thickness )
Fence

Page 10 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

G524

Fabrication & Installation RC Pipe ( 61cm )

JG0524

G525

Bar schedule ( D12 )

G526
G527

Quantity Unit

2016
Jun Jul
6
7

2015.Dec.14 07:59
2017
Jun Jul
18
19

2018
Jun Jul
30
31

2019
Nov Dec Jan Feb Mar Apr May Jun Jul
35
36
37
38
39
40
41
42
43
Fabrication & Installation RC Pipe ( 61cm )

Original
Duration

Start

Finish

685 pc

701d

2016.Nov.30

2018.Oct.31

JG0525

3718 ton

244d

2017.Jan.30

2017.Sep.30

Bar schedule ( D12 )

Bar schedule ( D16 )

JG0526

4503 ton

244d

2017.Jan.30

2017.Sep.30

Bar schedule ( D16 )

Bar schedule ( D20 )

JG0527

7729 ton

244d

2017.Jan.30

2017.Sep.30

Bar schedule ( D20 )

G528

Bar schedule ( D25 )

JG0528

3 ton

244d

2017.Jan.30

2017.Sep.30

Bar schedule ( D25 )

G529

Precast flume (0.3 m x 0.3 m)

JG0529

255d

2017.Jun.19

2018.Feb.28

877d

2017.Jan.29

2019.Jun.24

G601

Steel Gate in Canal ( 1.0m x 0.8m )

JG0601

1 set

25d

2017.Jul.09

2017.Aug.02

G602

Steel Gate in Canal ( 1.2m x 0.8m )

JG0602

2 set

25d

2017.Aug.03

2017.Aug.27

G603

Steel Gate in Canal ( 1.2m x 0.9m )

JG0603

2 set

25d

2017.Aug.28

2017.Sep.21

G604

Steel Gate in Canal ( 1.2m x 1.0m )

JG0604

7 set

60d

2017.Sep.22

2017.Nov.20

G605

Steel Gate in Canal ( 1.4m x 1.0m )

JG0605

7 set

60d

2017.Nov.01

2017.Dec.30

G606

Steel Gate in Canal ( 1.4m x 1.2m )

JG0606

12 set

80d

2017.Dec.01

2018.Feb.18

G607

Steel Gate in Canal ( 1.6m x 1.0m )

JG0607

2 set

25d

2018.Feb.09

2018.Mar.05

G608

Steel Gate in Canal ( 1.6m x 1.4m )

JG0608

2 set

25d

2018.Mar.06

2018.Mar.30

G609

Steel Gate in Canal ( 1.8m x 1.5m )

JG0609

2 set

25d

2018.Mar.31

2018.Apr.24

G610

Steel Gate in Canal ( 1.8m x 1.6m )

JG0610

3 set

25d

2018.Apr.25

2018.May.19

G611

Steel Gate in Canal ( 2.0m x 1.6m )

JG0611

2 set

25d

2018.May.20

2018.Jun.13

G612

Steel Gate in Canal ( 2.2m x 1.8m )

JG0612

3 set

25d

2018.Jun.14

2018.Jul.08

G613

Steel Gate in Canal ( 2.2m x 2.0m )

JG0613

6 set

60d

2018.Jul.09

2018.Sep.06

G614

Steel Gate in Canal ( 2.5m x 2.0m )

JG0614

6 set

60d

2018.Aug.18

2018.Oct.16

G615

Steel Gate in Canal ( 2.5m x 2.2m )

JG0615

12 set

80d

2018.Sep.17

2018.Dec.05

Steel Gate in Canal ( 2.5m x 2.2m )

G616

Trash Rack ( 1.10m x 1.40m )

JG0616

5 pc

50d

2018.Nov.06

2018.Dec.25

Trash Rack ( 1.10m x 1.40m )

G617

Trash Rack ( 3.55m x 2.30m )

JG0617

1 pc

25d

2018.Dec.26

2019.Jan.19

G618

Trash Rack (4.00m x 2.60m )

JG0618

7 pc

50d

2019.Jan.20

2019.Mar.10

G619

Trash Rack ( 4.40m x 2.80m )

JG0619

2 pc

25d

2019.Mar.11

2019.Apr.04

G620

Trash Rack ( 5.40m x 2.90m )

JG0620

15 pc

90d

2019.Mar.26

2019.Jun.23

G621

Testing & Inspection

JG0621

1 LS

691d

2017.Aug.03

2019.Jun.24

G622

Delivery

JG0622

1 LS

368d

2017.Jan.29

2018.Jan.31

61d

2016.Sep.01

2016.Oct.31

2016.Oct.31, Electrical

G701

Power Supply System included Main Panel ( panel board


)

JG0701

1 LS

61d

2016.Sep.01

2016.Oct.31

Power Supply System included Main Panel ( panel board )

G702

Incoming Power Line

JG0702

1 LS

61d

2016.Sep.01

2016.Oct.31

Incoming Power Line

G703

Transportation

JG0703

1 LS

61d

2016.Sep.01

2016.Oct.31

Transportation

G704

Spare parts and Tools

JG0704

1 LS

61d

2016.Sep.01

2016.Oct.31

Spare parts and Tools

814d

2017.Aug.14

2019.Nov.05

1000 m

Mechanical

Electrical

NEW IRRIGATION
IRRIG
AREA

Jan
1

Feb
2

Mar
3

Apr
4

May
5

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

Jan
25

Feb
26

Mar
27

Apr
28

May
29

Aug
32

Jan
49

Feb
50

2020
Mar
51

Apr May
52 53

Steel Gate in Canal ( 1.4m x 1.0m )


Steel Gate in Canal ( 1.4m x 1.2m )
Steel Gate in Canal ( 1.6m x 1.0m )
Steel Gate in Canal ( 1.6m x 1.4m )
Steel Gate in Canal ( 1.8m x 1.5m )
Steel Gate in Canal ( 1.8m x 1.6m )
Steel Gate in Canal ( 2.0m x 1.6m )
Steel Gate in Canal ( 2.2m x 1.8m )
Steel Gate in Canal ( 2.2m x 2.0m )
Steel Gate in Canal ( 2.5m x 2.0m )

Trash Rack ( 3.55m x 2.30m )


Trash Rack (4.00m x 2.60m )
Trash Rack ( 4.40m x 2.80m )
Trash Rack ( 5.40m x 2.90m )
Testing & Inspection
Delivery

2019.Nov.05, NEW IRRIGATION AREA

2017.Aug.14

2018.Apr.05

2017.Aug.14

2018.Jan.25

I102

Canal Excavation ( with Road )

JI0102

1037208 cu.m.

230d

2017.Aug.14

2018.Mar.31

Canal Excavation ( with Road )

I103

Canal Excavation ( Rock )

JI0103

18317 cu.m.

200d

2017.Sep.13

2018.Mar.31

Canal Excavation ( Rock )

I104

Stripping ( 10cm minimum )

JI0104

49494 cu.m.

204d 3h

2017.Sep.13

2018.Apr.05

256d

2017.Aug.14

2018.Apr.26

2018.Apr.05, Excavation
Structure Excavation ( Common )

Stripping ( 10cm minimum )


2018.Apr.26, Backfill & Embankment

I201

Structure Backfill

JI0201

4503 cu.m.

165d

2017.Sep.13

2018.Feb.24

I202

Embankment Construction and Compaction

JI0202

370101 cu.m.

200d

2017.Sep.13

2018.Mar.31

I203

Hauling ( >60m, Dozer )

JI0203

184312 cu.m.

235d

2017.Aug.14

2018.Apr.05

Hauling ( >60m, Dozer )

I204

Hauling ( >60m, Backhoe+Dump Truck )

JI0204

845242 cu.m.

235d

2017.Aug.14

2018.Apr.05

Hauling ( >60m, Backhoe+Dump Truck )

I205

Borrow Pit

JI0205

21827 cu.m.

235d

2017.Aug.14

2018.Apr.05

Borrow Pit

I206

Disposal

JI0206

67950 cu.m.

235d

2017.Aug.14

2018.Apr.05

Disposal

I207

Cofferdam Embankment

JI0207

35553 cu.m.

175d

2017.Oct.13

2018.Apr.05

Cofferdam Embankment

I208

Cofferdam Demolition

JI0208

28442 sheet

76d

2018.Feb.10

2018.Apr.26

I209

Cofferdam P.P Burlap Filling

JI0209

783 cu.m.

175d

2017.Oct.13

2018.Apr.05

I210

Cofferdam P.P Burlap Demolition

JI0210

783 cu.m.

76d

2018.Feb.10

2018.Apr.26

Summary

Dec
48

Steel Gate in Canal ( 1.2m x 1.0m )

165d

Milestone

Nov
47

Steel Gate in Canal ( 1.2m x 0.9m )

234d 3h

Critical Remaining Work

Oct
46

Steel Gate in Canal ( 1.2m x 0.8m )

33093 cu.m.

Remaining Work

Sep
45

2019.Jun.24, Mechanical

JI0101

Actual Work

Aug
44

Steel Gate in Canal ( 1.0m x 0.8m )

Structure Excavation ( Common )

Backfill & E
Embankment

Oct
34

Precast flume (0.3 m x 0.3 m)

I101

Excavation

Sep
33

Structure Backfill
Embankment Construction and Compaction

Cofferdam Demolition
Cofferdam P.P Burlap Filling
Cofferdam P.P Burlap Demolition

Page 11 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

I211

Cofferdam P.P Bag

JI0211

I301

Aggregate Base Coarse ( Gravel Surfacing )

I401

Quantity Unit

2016
Jun Jul
6
7

2015.Dec.14 07:59
2017
Jun Jul
18
19

2018
Jun Jul
30
31

Original
Duration

Start

Finish

32609 sheet

1d

2017.Oct.13

2017.Oct.13

JI0301

57531 cu.m.

147d

2017.Nov.12

2018.Apr.07

166d

2017.Nov.12

2018.Apr.26

2018.Apr.26, Canal

Lining ( Class "B" Concrete )

JI0401

27639 cu.m.

151d

2017.Nov.27

2018.Apr.26

Lining ( Class "B" Concrete )

I402

PVC Pipe diameter 5cm, L=8m

JI0402

66336 pc

151d

2017.Nov.27

2018.Apr.26

I403

Filter Drain ( Coarse Aggr egates )

JI0403

8638 cu.m.

147d

2017.Nov.12

2018.Apr.07

431d

2017.Sep.13

2018.Nov.17

I501

Class "A" Concrete

JI0501

12288 cu.m.

130d

2017.Dec.30

2018.May.08

I502

Lean Concrete

JI0502

3395 cu.m.

130d

2017.Dec.27

2018.May.05

Lean Concrete

I503

Preshunk Concrete

JI0503

26 cu.m.

128d

2017.Dec.30

2018.May.06

Preshunk Concrete

I504

Plywood ( 3 times )

JI0504

50341 sq.m.

128d

2017.Dec.30

2018.May.06

Plywood ( 3 times )

I505

Circular P.F ( 3 times )

JI0505

12 sq.m.

128d

2017.Dec.30

2018.May.06

Circular P.F ( 3 times )

I506

Pipe Support

JI0506

7062 cu.m

128d

2017.Dec.30

2018.May.06

Pipe Support

I507

Horizontal member of Support

JI0507

212 sq.m.

128d

2017.Dec.30

2018.May.06

Horizontal member of Support

I508

Steel Pipe Scaffolding

JI0508

6743 sq.m.

128d

2017.Dec.30

2018.May.06

Steel Pipe Scaffolding

I509

Spacer ( Wall, vertical )

JI0509

13014 ea

114d

2018.Jan.02

2018.Apr.25

I510

Spacer ( Slab, horizontal )

JI0510

53466 ea

114d

2018.Jan.02

2018.Apr.25

I511

Construction Joint Surface Clearing

JI0511

1621 sq.m.

110d 4h

2017.Dec.28

2018.Apr.17

I512

Waterstop Sealer

JI0512

2100 m

122d

2017.Dec.28

2018.Apr.28

Waterstop Sealer

I513

Gravel Bedding

JI0513

905 cu.m.

136d

2017.Dec.12

2018.Apr.26

Gravel Bedding

I514

Ladder ( ST pipe )

JI0514

512 m

90d

2018.May.09

2018.Aug.06

Ladder ( ST pipe )

I515

Hand rail ( ST )

JI0515

17 m

70d

2018.Jun.08

2018.Aug.16

Hand rail ( ST )

I516

Fence

JI0516

801 m

93d

2018.Aug.17

2018.Nov.17

I517

Fabrication & Installation RC Pipe ( 46cm )

JI0517

250 pc

208d

2017.Sep.13

2018.Apr.08

Fabrication & Installation RC Pipe ( 46cm )

I518

Fabrication & Installation RC Pipe ( 61cm )

JI0518

2819 pc

208d

2017.Sep.13

2018.Apr.08

Fabrication & Installation RC Pipe ( 61cm )

I519

P.E Pipe ( 110cm, L=8m )

JI0519

138 pc

208d

2017.Sep.13

2018.Apr.08

P.E Pipe ( 110cm, L=8m )

I520

Bar schedule ( D12 )

JI0520

20 ton

129d

2017.Dec.28

2018.May.05

Bar schedule ( D12 )

I521

Bar schedule ( D16 )

JI0521

1278 ton

129d

2017.Dec.28

2018.May.05

Bar schedule ( D16 )

676d

2017.Dec.30

2019.Nov.05

Canal

Structure

Mechanical

Jan
1

Feb
2

Mar
3

Apr
4

May
5

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

Aug
20

Sep
21

Oct Nov Dec Jan


22
23
24
25
Cofferdam P.P Bag

Feb
26

Mar
27

Apr
28

May
29

Aug
32

Sep
33

Oct
34

Nov
35

Dec
36

Jan
37

Feb
38

Mar
39

Apr
40

May
41

2019
Jun Jul
42
43

Aug
44

Sep
45

Oct
46

Nov
47

Dec
48

2018.Nov.17, Structure
Class "A" Concrete

Spacer ( Wall, vertical )


Spacer ( Slab, horizontal )
Construction Joint Surface Clearing

Fence

2019.Nov.05, Mechanical

8 set

15d

2018.Feb.28

2018.Mar.14

I602

Steel Gate in Canal ( 0.4m x 0.4m )

JI0602

5 set

10d

2018.Mar.15

2018.Mar.24

I603

Steel Gate in Canal ( 0.6m x 0.6m )

JI0603

33 set

40d

2018.Mar.15

2018.Apr.23

I604

Steel Gate in Canal ( 0.7m x 0.7m )

JI0604

39 set

50d

2018.Apr.24

2018.Jun.12

I605

Steel Gate in Canal ( 0.8m x 0.6m )

JI0605

2 set

20d

2018.Jun.13

2018.Jul.02

I606

Steel Gate in Canal ( 0.8m x 0.7m )

JI0606

7 set

30d

2018.Jul.03

2018.Aug.01

I607

Steel Gate in Canal ( 0.9m x 0.7m )

JI0607

4 set

25d

2018.Aug.02

2018.Aug.26

I608

Steel Gate in Canal ( 0.9m x 0.8m )

JI0608

4 set

25d

2018.Aug.27

2018.Sep.20

I609

Steel Gate in Canal ( 0.9m x 0.9m )

JI0609

2 set

25d

2018.Sep.21

2018.Oct.15

I610

Steel Gate in Canal ( 1.0m x 0.7m )

JI0610

5 set

30d

2018.Oct.16

2018.Nov.14

I611

Steel Gate in Canal ( 1.0m x 0.8m )

JI0611

8 set

40d

2018.Nov.15

2018.Dec.24

I612

Steel Gate in Canal ( 1.0m x 1.0m )

JI0612

4 set

30d

2018.Dec.25

2019.Jan.23

I613

Steel Gate in Canal ( 1.2m x 0.7m )

JI0613

1 set

20d

2019.Jan.24

2019.Feb.12

I614

Steel Gate in Canal ( 1.2m x 0.8m )

JI0614

3 set

35d

2019.Feb.13

2019.Mar.19

I615

Steel Gate in Canal ( 1.2m x 0.9m )

JI0615

4 set

35d

2019.Mar.20

2019.Apr.23

I616

Steel Gate in Canal ( 1.2m x 1.2m )

JI0616

2 set

35d

2019.Apr.24

2019.May.28

I617

Steel Gate in Canal ( 1.4m x 1.0m )

JI0617

1 set

20d

2019.May.29

2019.Jun.17

I618

Steel Gate in Canal ( 1.6m x 1.0m )

JI0618

1 set

25d

2019.Jun.18

2019.Jul.12

Steel Gate in Canal ( 1.6m x 1.0m )

I619

Trash Rack(0.5m x 0.67 m)

JI0619

1 set

15d

2019.Jul.13

2019.Jul.27

Trash Rack(0.5m x 0.67 m)

I620

Trash Rack(0.7m x 1.03 m)

JI0620

1 set

15d

2019.Jul.28

2019.Aug.11

I621

Trash Rack(0.7m x 1.17m)

JI0621

4 LS

25d

2019.Aug.12

2019.Sep.05

I622

Trash Rack(0.8m x 0.81m)

JI0622

2 set

20d

2019.Sep.06

2019.Sep.25

Milestone

Summary

Apr May
52 53

PVC Pipe diameter 5cm, L=8m

JI0601

Critical Remaining Work

2020
Mar
51

Filter Drain ( Coarse Aggr egates )

Steel Gate in Canal ( 0.3m x 0.3m )

Remaining Work

Feb
50

Aggregate Base Coarse ( Gravel Surfacing )

I601

Actual Work

Jan
49

Steel Gate in Canal ( 0.3m x 0.3m )


Steel Gate in Canal ( 0.4m x 0.4m )
Steel Gate in Canal ( 0.6m x 0.6m )
Steel Gate in Canal ( 0.7m x 0.7m )
Steel Gate in Canal ( 0.8m x 0.6m )
Steel Gate in Canal ( 0.8m x 0.7m )
Steel Gate in Canal ( 0.9m x 0.7m )
Steel Gate in Canal ( 0.9m x 0.8m )
Steel Gate in Canal ( 0.9m x 0.9m )
Steel Gate in Canal ( 1.0m x 0.7m )
Steel Gate in Canal ( 1.0m x 0.8m )
Steel Gate in Canal ( 1.0m x 1.0m )
Steel Gate in Canal ( 1.2m x 0.7m )
Steel Gate in Canal ( 1.2m x 0.8m )
Steel Gate in Canal ( 1.2m x 0.9m )
Steel Gate in Canal ( 1.2m x 1.2m )
Steel Gate in Canal ( 1.4m x 1.0m )

Trash Rack(0.7m x 1.03 m)


Trash Rack(0.7m x 1.17m)
Trash Rack(0.8m x 0.81m)

Page 12 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

I623

Trash Rack(0.8m x 0.94m)

JI0623

I624

Trash Rack(0.8m x 1.03m)

I625
I626

Quantity Unit

Original
Duration

Start

Finish

7 set

20d

2019.Sep.26

2019.Oct.15

JI0624

2 set

20d

2019.Oct.16

2019.Nov.04

Testing and Inspection

JI0625

1 LS

601d

2018.Mar.15

2019.Nov.05

Delivery

JI0626

1 LS

210d

2017.Dec.30

2018.Jul.27

1172d

2016.Feb.01

2019.Apr.17

442d

2016.Feb.01

2017.Apr.17

EXISTING IRRIGATION
Existing Irrigation
Irri
- PART 1

Jan
1

Feb
2

Mar
3

Apr
4

May
5

2016
Jun Jul
6
7

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

2017.Jan.02
2016.Dec.02

JJ0102

7162 cu.m.

46d

2016.Oct.31

2016.Dec.15

Structure Excavation ( Rock )

JJ0103

411746 cu.m.

71d

2016.Oct.01

2016.Dec.10

Canal Excavation ( with Road )

JJ0104

84300 cu.m.

63d 1h

2016.Oct.31

2017.Jan.02

Structure Excavation ( Rock )

J863

Canal Excavation ( with Road )

J864

Stripping ( 10cm minimum )

147d

2016.Oct.31

2017.Mar.26

12580 cu.m.

62d

2016.Oct.31

2016.Dec.31

J850

Embankment Construction and Compaction

JJ0202

304430 cu.m.

73d 2h

2016.Oct.31

2017.Jan.12

Embankment Construction and Compaction

J851

Hauling ( >60m, Dozer )

JJ0203

172504 cu.m.

73d 2h

2016.Oct.31

2017.Jan.12

Hauling ( >60m, Dozer )

J852

Hauling ( >60m, Backhoe+Dump Truck )

JJ0204

187777 cu.m.

73d 2h

2016.Oct.31

2017.Jan.12

Hauling ( >60m, Backhoe+Dump Truck )

J853

Borrow Pit

JJ0205

105462 cu.m.

73d 2h

2016.Oct.31

2017.Jan.12

Borrow Pit

J854

Disposal

JJ0206

84469 cu.m.

54d 4h

2016.Nov.30

2017.Jan.23

J855

Grouted Riprap

JJ0207

305 cu.m.

30d 6h

2017.Jan.12

2017.Feb.11

J856

Cofferdam Embankment

JJ0208

24198 cu.m.

90d

2016.Dec.11

2017.Mar.10

J857

Cofferdam Demolition

JJ0209

19358 cu.m.

45d 4h

2017.Feb.09

2017.Mar.26

Cofferdam Demolition

J858

Cofferdam P.P Burlap Filling

JJ0210

617 cu.m.

90d

2016.Dec.11

2017.Mar.10

Cofferdam P.P Burlap Filling

J859

Cofferdam P.P Burlap Demolition

JJ0211

617 cu.m.

46d

2017.Feb.09

2017.Mar.26

J860

Cofferdam P.P Bag

JJ0212

25724 sheet

Lining ( Class "B" Concrete )

JJ0401

J847

PVC Pipe (5 cm)

JJ0402

J848

Filter Drain ( Coarse Aggr egates )

JJ0403

67926 cu.m.
118270 pc
14736 cu.m.

Structural

37d

2017.Jan.08

2017.Feb.13

3d

2017.Jan.08

2017.Jan.10

PVC Pipe (5 cm)


Filter Drain ( Coarse Aggr egates )

15d

2017.Feb.17

2017.Mar.03

J821

Lean Concrete

JJ0502

431 sq.m.

5d

2016.Dec.16

2016.Dec.20

J822

Preshunk Concrete

JJ0503

108 sq.m.

1d

2017.Feb.16

2017.Feb.16

J823

Plywood ( 3 times )

JJ0504

16213 sq.m.

15d

2017.Jan.17

2017.Jan.31

J824

Circular P.F ( 3 times )

JJ0505

256 sq.m.

15d

2017.Feb.01

2017.Feb.15

J825

Pipe Support

JJ0506

3454 cu.m.

15d

2017.Jan.17

2017.Jan.31

J826

Horizontal member of Support

JJ0507

197 sq.m.

15d

2017.Feb.01

2017.Feb.15

J827

Steel Pipe Scaffolding

JJ0508

5199 sq.m.

30d

2017.Jan.17

2017.Feb.15

J828

Spacer ( Wall, vertical )

JJ0509

6239 ea

3d

2017.Jan.15

2017.Jan.18

Spacer ( Wall, vertical )

J829

Spacer ( Slab, horizontal )

JJ0510

24663 ea

3d

2017.Jan.15

2017.Jan.18

Spacer ( Slab, horizontal )

J830

Construction Joint Surface Clearing

JJ0511

5d

2017.Jan.15

2017.Jan.20

Construction Joint Surface Clearing

J831

Waterstop Sealer

JJ0512

2666 m

5d

2017.Jan.15

2017.Jan.20

Waterstop Sealer

J832

Waterstop

JJ0513

282 m

3d

2017.Jan.15

2017.Jan.18

Waterstop

J833

Dowel Bar

JJ0514

371 ea

3d

2017.Jan.15

2017.Jan.18

Dowel Bar

J834

Dowel Bar Cap

JJ0515

371 ea

3d

2017.Jan.15

2017.Jan.18

Dowel Bar Cap

J835

Filler

JJ0516

3d

2017.Jan.15

2017.Jan.18

Filler

J836

Sealant

JJ0517

5d

2017.Mar.09

2017.Mar.13

J837

Asphalt Waterproof

JJ0518

5d

2017.Mar.04

2017.Mar.08

J838

Ladder ( ST pipe )

JJ0519

188 m

15d

2017.Mar.04

2017.Mar.18

J839

Hand rail ( ST )

JJ0520

327 m

15d

2017.Mar.19

2017.Apr.02

J840

Polyethylene Sheet ( 400?-min. thickness )

JJ0521

1d

2016.Feb.01

2016.Feb.01

J841

Fence

JJ0522

15d

2017.Apr.03

2017.Apr.17

1050 sq.m.
647 m

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Feb
38

Mar
39

Apr
40

May
41

2019
Jun Jul
42
43

Aug
44

Sep
45

Oct
46

2020
Nov Dec Jan Feb Mar
47
48
49
50
51
Trash Rack(0.8m x 0.94m)

Apr May
52 53

2017.Apr.17, Struc tural

3605 cu.m.

1819 sq.m.

Jan
37

Lining ( Class "B" Concrete )

JJ0501

26 sq.m.

Dec
36

2017.Feb.13, Canal

Class "A" Concrete

156 m

Nov
35

Cofferdam P.P Bag

J820

659 sq.m.

Oct
34

Cofferdam P.P Burlap Demolition

2017.Feb.13

2017.Apr.17

Sep
33

Cofferdam Embankment

2016.Dec.11

2017.Jan.09

Aug
32

Grouted Riprap

2016.Dec.11

2016.Feb.01

2018
Jun Jul
30
31

Disposal

2016.Dec.11

2016.Dec.11

May
29

2017.Mar.26, Bac kfill & Embankment

1d

30d

Apr
28

Structure Backfill

65d

442d

Mar
27

Stripping ( 10cm minimum )

JJ0201

J846

Feb
26

2017.Jan.02, Excavation

Structure Backfill

Canal

Jan
25

Structure Excavation ( Common )

J849

Backfill & Embankment

Dec
24

2019.Apr.17, EXIST ING IRRIGATION

2016.Oct.01

J862

Nov
23

2017.Apr.17, Exis ting Irrigation - PART 1

2016.Oct.01

JJ0101

Oct
22

Testing and Inspection

62d 1h

Structure Excavation ( Common )

Sep
21

Delivery

93d 1h

J861

Aug
20

Trash Rack(0.8m x 1.03m)

4653 cu.m.

Excavation

2015.Dec.14 07:59
2017
Jun Jul
18
19

Class "A" Concrete


Lean Concrete
Preshunk Concrete
Plywood ( 3 times )
Circular P.F ( 3 times )
Pipe Support
Horizontal member of Support
Steel Pipe Scaffolding

Sealant
Asphalt Waterproof
Ladder ( ST pipe )
Hand rail ( ST )
Polyethylene Sheet ( 400?-min. thickness )
Fence

Page 13 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

J842

Bar schedule ( D12 )

JJ0523

J843

Bar schedule ( D16 )

JJ0524

J844

Demonlition of Old Concrete (existing)

J845

Desilting Siphon

Quantity Unit

Original
Duration

Start

Finish

42 ton

24d 4h

2016.Dec.22

2017.Jan.15

267 ton

26d

2016.Dec.22

2017.Jan.16

JJ0525

318 cu.m.

15d

2017.Mar.04

2017.Mar.18

JJ0526

1443 cu.m.

30d

2017.Mar.04

2017.Apr.02

1d

2016.Feb.01

2016.Feb.01

2016.Feb.01, Mechanical

Mechanical
Mechanic

Jan
1

Feb
2

Mar
3

Apr
4

May
5

2016
Jun Jul
6
7

Sep
9

Oct
10

Nov
11

Dec
12

Jan Feb Mar Apr May


13
14
15
16
17
Bar schedule ( D12 )

2015.Dec.14 07:59
2017
Jun Jul
18
19

Oct
22

Nov
23

Dec
24

Jan
25

Feb
26

Mar
27

Apr
28

May
29

2 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 0.7m x 0.7m )

J790

Steel Gate in Canal ( 0.8m x 0.8m )

JJ0602

3 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 0.8m x 0.8m )

J791

Steel Gate in Canal ( 0.9m x 0.9m )

JJ0603

1 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 0.9m x 0.9m )

J792

Steel Gate in Canal ( 1.0m x 1.0m )

JJ0604

10 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.0m x 1.0m )

J793

Steel Gate in Canal ( 1.1m x 1.1m )

JJ0605

4 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.1m x 1.1m )

J794

Steel Gate in Canal ( 1.2m x 1.2m )

JJ0606

7 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.2m x 1.2m )

J795

Steel Gate in Canal ( 1.3m x 1.3m )

JJ0607

4 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.3m x 1.3m )

J796

Steel Gate in Canal ( 1.4m x 1.4m )

JJ0608

5 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.4m x 1.4m )

J797

Steel Gate in Canal ( 1.5m x 1.5m )

JJ0609

10 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.5m x 1.5m )

J798

Steel Gate in Canal ( 1.6m x 1.6m )

JJ0610

7 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.6m x 1.6m )

J799

Steel Gate in Canal ( 1.7m x 1.7m )

JJ0611

14 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.7m x 1.7m )

J800

Steel Gate in Canal ( 1.8m x 1.8m )

JJ0612

5 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.8m x 1.8m )

J801

Steel Gate in Canal ( 1.9m x 1.9m )

JJ0613

1 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.9m x 1.9m )

J802

Steel Gate in Canal ( 2.0m x 2.0m )

JJ0614

23 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 2.0m x 2.0m )

J803

Steel Gate in Canal ( 2.1m x 2.1m )

JJ0615

2 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 2.1m x 2.1m )

J804

Trash Rack ( 1.48m x 1.30m )

JJ0616

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 1.48m x 1.30m )

J805

Trash Rack ( 1.98m x 1.70m )

JJ0617

4 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 1.98m x 1.70m )

J806

Trash Rack ( 1.98m x 1.75m )

JJ0618

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 1.98m x 1.75m )

J807

Trash Rack ( 2.08m x 1.65m )

JJ0619

8 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.08m x 1.65m )

J808

Trash Rack ( 2.08m x 2.20m )

JJ0620

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.08m x 2.20m )

J809

Trash Rack ( 2.18m x 1.30m )

JJ0621

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.18m x 1.30m )

J810

Trash Rack ( 2.38m x 2.90m )

JJ0622

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.38m x 2.90m )

J811

Trash Rack ( 2.48m x 1.65m )

JJ0623

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.48m x 1.65m )

J812

Trash Rack ( 2.78m x 1.75m )

JJ0624

8 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.78m x 1.75m )

J813

Trash Rack ( 3.48m x 1.30m )

JJ0625

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 3.48m x 1.30m )

J814

Trash Rack ( 3.58m x 1.60m )

JJ0626

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 3.58m x 1.60m )

J815

Trash Rack ( 3.68m x 1.30m )

JJ0627

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 3.68m x 1.30m )

J816

Trash Rack ( 4.08m x 1.60m )

JJ0628

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 4.08m x 1.60m )

J817

Trash Rack ( 5.28m x 2.30m )

JJ0629

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 5.28m x 2.30m )

J818

Testing & Inspection

JJ0630

1 LS

1d

2016.Feb.01

2016.Feb.01

Testing & Inspection

J819

Delivery

JJ0631

1 LS

Delivery

1d

2016.Feb.01

2016.Feb.01

20d

2016.Oct.01

2016.Oct.20

2016.Oct.20, Electrical

J785

Power Supply System included Main Panel ( panel board


)

JJ0701

1 LS

20d

2016.Oct.01

2016.Oct.20

Power Supply System included Main Panel ( panel board )

J786

Incoming Power Line

JJ0702

1 LS

20d

2016.Oct.01

2016.Oct.20

Incoming Power Line

J787

Transportation

JJ0703

1 LS

20d

2016.Oct.01

2016.Oct.20

Transportation

J788

Spare parts and Tools

JJ0704

1 LS

20d

2016.Oct.01

2016.Oct.20

Spare parts and Tools

807d

2016.Feb.01

2018.Apr.17

93d 1h

2017.Oct.01

2018.Jan.02

Aug
32

4653 cu.m.

62d 1h

2017.Oct.01

2017.Dec.02

JJ0101

J782

Structure Excavation ( Rock )

JJ0102

7162 cu.m.

46d

2017.Oct.31

2017.Dec.15

Structure Excavation ( Rock )

J783

Canal Excavation ( with Road )

JJ0103

411746 cu.m.

71d

2017.Oct.01

2017.Dec.10

Canal Excavation ( with Road )

J784

Stripping ( 10cm minimum )

JJ0104

84300 cu.m.

63d 1h

2017.Oct.31

2018.Jan.02

147d

2017.Oct.31

2018.Mar.26

JJ0201

12580 cu.m.

62d

2017.Oct.31

2017.Dec.31

Embankment Construction and Compaction

JJ0202

304430 cu.m.

73d 2h

2017.Oct.31

2018.Jan.12

Embankment Construction and Compaction

J771

Hauling ( >60m, Dozer )

JJ0203

172504 cu.m.

73d 2h

2017.Oct.31

2018.Jan.12

Hauling ( >60m, Dozer )

Summary

Jan
37

Feb
38

Mar
39

Apr
40

May
41

2019
Jun Jul
42
43

Aug
44

Sep
45

Oct
46

Nov
47

Dec
48

Jan
49

Feb
50

2020
Mar
51

Apr May
52 53

2018.Mar.26, Bac kfill & Embankment

Structure Backfill

Milestone

Dec
36

Stripping ( 10cm minimum )

J770

Critical Remaining Work

Nov
35

Structure Excavation ( Common )

J769

Remaining Work

Oct
34

2018.Apr.17, Exis ting Irrigation - PART 2

Structure Excavation ( Common )

Actual Work

Sep
33

2018.Jan.02, Excavation

J781

Backfill & Embankment

2018
Jun Jul
30
31

Desilting Siphon

JJ0601

Excavation

Sep
21

Demonlition of Old Concrete (existing)

Steel Gate in Canal ( 0.7m x 0.7m )

Existing Irrigation
Irri
- PART 2

Aug
20

Bar schedule ( D16 )

J789

Electrical

Aug
8

Structure Backfill

Page 14 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

Quantity Unit

J772

Hauling ( >60m, Backhoe+Dump Truck )

JJ0204

J773

Borrow Pit

J774
J775

2016
Jun Jul
6
7

2015.Dec.14 07:59
2017
Jun Jul
18
19

2018
Jan Feb Mar Apr May Jun Jul
25
26
27
28
29
30
31
Hauling ( >60m, Backhoe+Dump Truck )

Original
Duration

Start

Finish

187777 cu.m.

73d 2h

2017.Oct.31

2018.Jan.12

JJ0205

105462 cu.m.

73d 2h

2017.Oct.31

2018.Jan.12

Disposal

JJ0206

84469 cu.m.

54d 4h

2017.Nov.30

2018.Jan.23

Grouted Riprap

JJ0207

305 cu.m.

30d 6h

2018.Jan.12

2018.Feb.11

J776

Cofferdam Embankment

JJ0208

24198 cu.m.

90d

2017.Dec.11

2018.Mar.10

Cofferdam Embankment

J777

Cofferdam Demolition

JJ0209

19358 cu.m.

45d 4h

2018.Feb.09

2018.Mar.26

Cofferdam Demolition

J778

Cofferdam P.P Burlap Filling

JJ0210

617 cu.m.

90d

2017.Dec.11

2018.Mar.10

Cofferdam P.P Burlap Filling

J779

Cofferdam P.P Burlap Demolition

JJ0211

617 cu.m.

46d

2018.Feb.09

2018.Mar.26

J780

Cofferdam P.P Bag

JJ0212

25724 sheet

1d

2017.Dec.11

2017.Dec.11

65d

2017.Dec.11

2018.Feb.13

2018.Feb.13, Canal

J766

Lining ( Class "B" Concrete )

JJ0401

67926 cu.m.

37d

2018.Jan.08

2018.Feb.13

Lining ( Class "B" Concrete )

J767

PVC Pipe (5 cm)

JJ0402

J768

Filter Drain ( Coarse Aggr egates )

JJ0403

14736 cu.m.

J740

Class "A" Concrete

JJ0501

3605 cu.m.

J741

Lean Concrete

JJ0502

J742

Preshunk Concrete

JJ0503

J743

Plywood ( 3 times )

J744

Canal

118270 pc

Jan
1

Feb
2

Mar
3

Apr
4

May
5

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

PVC Pipe (5 cm)

2018.Jan.09

Filter Drain ( Coarse Aggr egates )

807d

2016.Feb.01

2018.Apr.17

15d

2018.Feb.17

2018.Mar.03

431 sq.m.

5d

2017.Dec.16

2017.Dec.20

108 sq.m.

1d

2018.Feb.16

2018.Feb.16

JJ0504

16213 sq.m.

15d

2018.Jan.17

2018.Jan.31

Circular P.F ( 3 times )

JJ0505

256 sq.m.

15d

2018.Feb.01

2018.Feb.15

J745

Pipe Support

JJ0506

3454 cu.m.

15d

2018.Jan.17

2018.Jan.31

J746

Horizontal member of Support

JJ0507

197 sq.m.

15d

2018.Feb.01

2018.Feb.15

J747

Steel Pipe Scaffolding

JJ0508

5199 sq.m.

30d

2018.Jan.17

2018.Feb.15

J748

Spacer ( Wall, vertical )

JJ0509

6239 ea

3d

2018.Jan.15

2018.Jan.18

Spacer ( Wall, vertical )

J749

Spacer ( Slab, horizontal )

JJ0510

24663 ea

3d

2018.Jan.15

2018.Jan.18

Spacer ( Slab, horizontal )

J750

Construction Joint Surface Clearing

JJ0511

5d

2018.Jan.15

2018.Jan.20

Construction Joint Surface Clearing

J751

Waterstop Sealer

JJ0512

2666 m

5d

2018.Jan.15

2018.Jan.20

Waterstop Sealer

J752

Waterstop

JJ0513

282 m

3d

2018.Jan.15

2018.Jan.18

Waterstop

J753

Dowel Bar

JJ0514

371 ea

3d

2018.Jan.15

2018.Jan.18

Dowel Bar

J754

Dowel Bar Cap

JJ0515

371 ea

3d

2018.Jan.15

2018.Jan.18

Dowel Bar Cap

J755

Filler

JJ0516

3d

2018.Jan.15

2018.Jan.18

Filler

J756

Sealant

JJ0517

5d

2018.Mar.09

2018.Mar.13

J757

Asphalt Waterproof

JJ0518

5d

2018.Mar.04

2018.Mar.08

J758

Ladder ( ST pipe )

JJ0519

188 m

15d

2018.Mar.04

2018.Mar.18

J759

Hand rail ( ST )

JJ0520

327 m

15d

2018.Mar.19

2018.Apr.02

J760

Polyethylene Sheet ( 400?-min. thickness )

JJ0521

1d

2016.Feb.01

2016.Feb.01

J761

Fence

JJ0522

15d

2018.Apr.03

2018.Apr.17

J762

Bar schedule ( D12 )

JJ0523

42 ton

24d 4h

2017.Dec.22

2018.Jan.15

Bar schedule ( D12 )

J763

Bar schedule ( D16 )

JJ0524

267 ton

26d

2017.Dec.22

2018.Jan.16

Bar schedule ( D16 )

J764

Demonlition of Old Concrete (existing)

JJ0525

318 cu.m.

15d

2018.Mar.04

2018.Mar.18

J765

Desilting Siphon

JJ0526

1443 cu.m.

30d

2018.Mar.04

2018.Apr.02

1d

2016.Feb.01

2016.Feb.01

2016.Feb.01, Mechanical

1050 sq.m.
647 m

Mechanical
Mechanic

2019
Jun Jul
42
43

Aug
44

Sep
45

Oct
46

Nov
47

Dec
48

Jan
49

Feb
50

2020
Mar
51

Apr May
52 53

Preshunk Concrete

Circular P.F ( 3 times )


Pipe Support
Horizontal member of Support
Steel Pipe Scaffolding

Sealant
Asphalt Waterproof
Ladder ( ST pipe )
Hand rail ( ST )
Polyethylene Sheet ( 400?-min. thickness )
Fence

Demonlition of Old Concrete (existing)


Desilting Siphon

JJ0601

2 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 0.7m x 0.7m )

JJ0602

3 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 0.8m x 0.8m )

J711

Steel Gate in Canal ( 0.9m x 0.9m )

JJ0603

1 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 0.9m x 0.9m )

J712

Steel Gate in Canal ( 1.0m x 1.0m )

JJ0604

10 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.0m x 1.0m )

J713

Steel Gate in Canal ( 1.1m x 1.1m )

JJ0605

4 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.1m x 1.1m )

J714

Steel Gate in Canal ( 1.2m x 1.2m )

JJ0606

7 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.2m x 1.2m )

J715

Steel Gate in Canal ( 1.3m x 1.3m )

JJ0607

4 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.3m x 1.3m )

J716

Steel Gate in Canal ( 1.4m x 1.4m )

JJ0608

5 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.4m x 1.4m )

J717

Steel Gate in Canal ( 1.5m x 1.5m )

JJ0609

10 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.5m x 1.5m )

J718

Steel Gate in Canal ( 1.6m x 1.6m )

JJ0610

7 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.6m x 1.6m )

Summary

May
41

Plywood ( 3 times )

Steel Gate in Canal ( 0.8m x 0.8m )

Milestone

Apr
40

Lean Concrete

Steel Gate in Canal ( 0.7m x 0.7m )

Critical Remaining Work

Mar
39

2018.Apr.17, Struc tural

J710

Remaining Work

Feb
38

Class "A" Concrete

J709

Actual Work

Jan
37

Cofferdam P.P Burlap Demolition

2018.Jan.10

1819 sq.m.

Dec
36

Cofferdam P.P Bag

2018.Jan.08

156 m

Nov
35

Grouted Riprap

2017.Dec.11

26 sq.m.

Oct
34

Disposal

3d

659 sq.m.

Sep
33

Borrow Pit

30d

Structural

Aug
32

Page 15 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II

Classic WBS_Jalaur

2015.Dec.14 07:59

Original
Duration

Start

Finish

14 set

1d

2016.Feb.01

2016.Feb.01

2016
Feb Mar Apr May Jun Jul
2
3
4
5
6
7
Steel Gate in Canal ( 1.7m x 1.7m )

5 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.8m x 1.8m )

JJ0613

1 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.9m x 1.9m )

JJ0614

23 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 2.0m x 2.0m )

Steel Gate in Canal ( 2.1m x 2.1m )

JJ0615

2 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 2.1m x 2.1m )

J724

Trash Rack ( 1.48m x 1.30m )

JJ0616

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 1.48m x 1.30m )

J725

Trash Rack ( 1.98m x 1.70m )

JJ0617

4 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 1.98m x 1.70m )

J726

Trash Rack ( 1.98m x 1.75m )

JJ0618

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 1.98m x 1.75m )

J727

Trash Rack ( 2.08m x 1.65m )

JJ0619

8 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.08m x 1.65m )

J728

Trash Rack ( 2.08m x 2.20m )

JJ0620

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.08m x 2.20m )

J729

Trash Rack ( 2.18m x 1.30m )

JJ0621

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.18m x 1.30m )

J730

Trash Rack ( 2.38m x 2.90m )

JJ0622

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.38m x 2.90m )

J731

Trash Rack ( 2.48m x 1.65m )

JJ0623

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.48m x 1.65m )

J732

Trash Rack ( 2.78m x 1.75m )

JJ0624

8 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.78m x 1.75m )

J733

Trash Rack ( 3.48m x 1.30m )

JJ0625

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 3.48m x 1.30m )

J734

Trash Rack ( 3.58m x 1.60m )

JJ0626

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 3.58m x 1.60m )

J735

Trash Rack ( 3.68m x 1.30m )

JJ0627

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 3.68m x 1.30m )

J736

Trash Rack ( 4.08m x 1.60m )

JJ0628

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 4.08m x 1.60m )

J737

Trash Rack ( 5.28m x 2.30m )

JJ0629

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 5.28m x 2.30m )

J738

Testing & Inspection

JJ0630

1 LS

1d

2016.Feb.01

2016.Feb.01

Testing & Inspection

J739

Delivery

JJ0631

1 LS

1d

2016.Feb.01

2016.Feb.01

Delivery

20d

2017.Oct.01

2017.Oct.20

2017.Oct.20, Electrical

Activity ID

Activity Name

CODE

J719

Steel Gate in Canal ( 1.7m x 1.7m )

JJ0611

J720

Steel Gate in Canal ( 1.8m x 1.8m )

JJ0612

J721

Steel Gate in Canal ( 1.9m x 1.9m )

J722

Steel Gate in Canal ( 2.0m x 2.0m )

J723

Quantity Unit

Electrical

Jan
1

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

2017
Jun Jul
18
19

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

Jan
25

Feb
26

Mar
27

Apr
28

May
29

2018
Jun Jul
30
31

J705

Power Supply System included Main Panel ( panel board


)

JJ0701

1 LS

20d

2017.Oct.01

2017.Oct.20

Power Supply System included Main Panel ( panel board )

J706

Incoming Power Line

JJ0702

1 LS

20d

2017.Oct.01

2017.Oct.20

Incoming Power Line

J707

Transportation

JJ0703

1 LS

20d

2017.Oct.01

2017.Oct.20

Transportation

J708

Spare parts and Tools

JJ0704

1 LS

20d

2017.Oct.01

2017.Oct.20

Spare parts and Tools

1172d

2016.Feb.01

2019.Apr.17

Existing Irrigation
Irri
- PART 3

Aug
32

Sep
33

Oct
34

Nov
35

Dec
36

Jan
37

Feb
38

Mar
39

Apr
40

May
41

93d 1h

2018.Oct.01

2019.Jan.02

62d 1h

2018.Oct.01

2018.Dec.02

JJ0102

7162 cu.m.

46d

2018.Oct.31

2018.Dec.15

Structure Excavation ( Rock )

JJ0103

411746 cu.m.

71d

2018.Oct.01

2018.Dec.10

Canal Excavation ( with Road )

JJ0104

84300 cu.m.

63d 1h

2018.Oct.31

2019.Jan.02

147d

2018.Oct.31

2019.Mar.26

J101

Structure Excavation ( Common )

JJ0101

J102

Structure Excavation ( Rock )

J103

Canal Excavation ( with Road )

J104

Stripping ( 10cm minimum )

Backfill & Embankment

Aug
44

62d

2018.Oct.31

2018.Dec.31

J202

Embankment Construction and Compaction

JJ0202

304430 cu.m.

73d 2h

2018.Oct.31

2019.Jan.12

Embankment Construction and Compaction

J203

Hauling ( >60m, Dozer )

JJ0203

172504 cu.m.

73d 2h

2018.Oct.31

2019.Jan.12

Hauling ( >60m, Dozer )

J204

Hauling ( >60m, Backhoe+Dump Truck )

JJ0204

187777 cu.m.

73d 2h

2018.Oct.31

2019.Jan.12

Hauling ( >60m, Backhoe+Dump Truck )

J205

Borrow Pit

JJ0205

105462 cu.m.

73d 2h

2018.Oct.31

2019.Jan.12

Borrow Pit

J206

Disposal

JJ0206

84469 cu.m.

54d 4h

2018.Nov.30

2019.Jan.23

J207

Grouted Riprap

JJ0207

305 cu.m.

30d 6h

2019.Jan.12

2019.Feb.11

J208

Cofferdam Embankment

JJ0208

24198 cu.m.

90d

2018.Dec.11

2019.Mar.10

J209

Cofferdam Demolition

JJ0209

19358 cu.m.

45d 4h

2019.Feb.09

2019.Mar.26

Cofferdam Demolition

J210

Cofferdam P.P Burlap Filling

JJ0210

617 cu.m.

90d

2018.Dec.11

2019.Mar.10

Cofferdam P.P Burlap Filling

J211

Cofferdam P.P Burlap Demolition

JJ0211

617 cu.m.

46d

2019.Feb.09

2019.Mar.26

J212

Cofferdam P.P Bag

JJ0212

25724 sheet

J402

PVC Pipe (5 cm)

JJ0402

J403

Filter Drain ( Coarse Aggr egates )

JJ0403

67926 cu.m.
118270 pc
14736 cu.m.

Structural
J501

Class "A" Concrete

JJ0501

3605 cu.m.

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Cofferdam Embankment

Cofferdam P.P Burlap Demolition

2018.Dec.11

2018.Dec.11

2019.Feb.13

37d

2019.Jan.08

2019.Feb.13

3d

2019.Jan.08

2019.Jan.10

PVC Pipe (5 cm)


Filter Drain ( Coarse Aggr egates )

2019.Jan.09

2016.Feb.01

2019.Apr.17

15d

2019.Feb.17

2019.Mar.03

Summary

Apr May
52 53

Grouted Riprap

2018.Dec.11

2018.Dec.11

2020
Mar
51

Disposal

1d

30d

Feb
50

Structure Backfill

65d

1172d

Jan
49

2019.Mar.26, Bac kfill & Embankment

12580 cu.m.

JJ0401

Dec
48

Stripping ( 10cm minimum )

JJ0201

Lining ( Class "B" Concrete )

Nov
47

2019.Jan.02, Excavation

Structure Backfill

J401

Oct
46

Structure Excavation ( Common )

J201

Canal

Sep
45

2019.Apr.17, Exis ting Irrigation - PART 3

4653 cu.m.

Excavation

2019
Jun Jul
42
43

Cofferdam P.P Bag


2019.Feb.13, Canal
Lining ( Class "B" Concrete )

2019.Apr.17, Struc tural


Class "A" Concrete

Page 16 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

J502

Lean Concrete

JJ0502

J503

Preshunk Concrete

J504
J505

Quantity Unit

2016
Jun Jul
6
7

2015.Dec.14 07:59
2017
Jun Jul
18
19

2018
Jun Jul
30
31

2019
Jun Jul
42
43

Original
Duration

Start

Finish

431 sq.m.

5d

2018.Dec.16

2018.Dec.20

JJ0503

108 sq.m.

1d

2019.Feb.16

2019.Feb.16

Plywood ( 3 times )

JJ0504

16213 sq.m.

15d

2019.Jan.17

2019.Jan.31

Circular P.F ( 3 times )

JJ0505

256 sq.m.

15d

2019.Feb.01

2019.Feb.15

J506

Pipe Support

JJ0506

3454 cu.m.

15d

2019.Jan.17

2019.Jan.31

J507

Horizontal member of Support

JJ0507

197 sq.m.

15d

2019.Feb.01

2019.Feb.15

J508

Steel Pipe Scaffolding

JJ0508

5199 sq.m.

30d

2019.Jan.17

2019.Feb.15

J509

Spacer ( Wall, vertical )

JJ0509

6239 ea

3d

2019.Jan.15

2019.Jan.18

Spacer ( Wall, vertical )

J510

Spacer ( Slab, horizontal )

JJ0510

24663 ea

3d

2019.Jan.15

2019.Jan.18

Spacer ( Slab, horizontal )

J511

Construction Joint Surface Clearing

JJ0511

5d

2019.Jan.15

2019.Jan.20

Construction Joint Surface Clearing

J512

Waterstop Sealer

JJ0512

2666 m

5d

2019.Jan.15

2019.Jan.20

Waterstop Sealer

J513

Waterstop

JJ0513

282 m

3d

2019.Jan.15

2019.Jan.18

Waterstop

J514

Dowel Bar

JJ0514

371 ea

3d

2019.Jan.15

2019.Jan.18

Dowel Bar

J515

Dowel Bar Cap

JJ0515

371 ea

3d

2019.Jan.15

2019.Jan.18

Dowel Bar Cap

J516

Filler

JJ0516

3d

2019.Jan.15

2019.Jan.18

Filler

J517

Sealant

JJ0517

5d

2019.Mar.09

2019.Mar.13

J518

Asphalt Waterproof

JJ0518

5d

2019.Mar.04

2019.Mar.08

J519

Ladder ( ST pipe )

JJ0519

188 m

15d

2019.Mar.04

2019.Mar.18

Ladder ( ST pipe )

J520

Hand rail ( ST )

JJ0520

327 m

15d

2019.Mar.19

2019.Apr.02

Hand rail ( ST )

J521

Polyethylene Sheet ( 400?-min. thickness )

JJ0521

J522

Fence

JJ0522

J523

Bar schedule ( D12 )

JJ0523

J524

Bar schedule ( D16 )

JJ0524

J525

Demonlition of Old Concrete (existing)

J526

Desilting Siphon

659 sq.m.

26 sq.m.
156 m
1819 sq.m.

1050 sq.m.

Jan
1

Feb
2

Mar
3

Apr
4

May
5

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

Jan
25

Feb
26

Mar
27

Apr
28

May
29

Aug
32

Sep
33

Oct
34

Nov
35

Dec
36

Jan Feb Mar


37
38
39
Lean Concrete

Apr
40

May
41

2020
Mar
51

Apr May
52 53

Sealant
Asphalt Waterproof

42 ton

24d 4h

2018.Dec.22

2019.Jan.15

Bar schedule ( D12 )

267 ton

26d

2018.Dec.22

2019.Jan.16

Bar schedule ( D16 )

JJ0525

318 cu.m.

15d

2019.Mar.04

2019.Mar.18

JJ0526

1443 cu.m.

30d

2019.Mar.04

2019.Apr.02

1d

2016.Feb.01

2016.Feb.01

2016.Feb.01, Mechanical

Polyethylene Sheet ( 400?-min. thickness )


Fence

Demonlition of Old Concrete (existing)


Desilting Siphon

J601

Steel Gate in Canal ( 0.7m x 0.7m )

JJ0601

2 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 0.7m x 0.7m )

J602

Steel Gate in Canal ( 0.8m x 0.8m )

JJ0602

3 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 0.8m x 0.8m )

J603

Steel Gate in Canal ( 0.9m x 0.9m )

JJ0603

1 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 0.9m x 0.9m )

J604

Steel Gate in Canal ( 1.0m x 1.0m )

JJ0604

10 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.0m x 1.0m )

J605

Steel Gate in Canal ( 1.1m x 1.1m )

JJ0605

4 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.1m x 1.1m )

J606

Steel Gate in Canal ( 1.2m x 1.2m )

JJ0606

7 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.2m x 1.2m )

J607

Steel Gate in Canal ( 1.3m x 1.3m )

JJ0607

4 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.3m x 1.3m )

J608

Steel Gate in Canal ( 1.4m x 1.4m )

JJ0608

5 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.4m x 1.4m )

J609

Steel Gate in Canal ( 1.5m x 1.5m )

JJ0609

10 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.5m x 1.5m )

J610

Steel Gate in Canal ( 1.6m x 1.6m )

JJ0610

7 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.6m x 1.6m )

J611

Steel Gate in Canal ( 1.7m x 1.7m )

JJ0611

14 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.7m x 1.7m )

J612

Steel Gate in Canal ( 1.8m x 1.8m )

JJ0612

5 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.8m x 1.8m )

J613

Steel Gate in Canal ( 1.9m x 1.9m )

JJ0613

1 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 1.9m x 1.9m )

J614

Steel Gate in Canal ( 2.0m x 2.0m )

JJ0614

23 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 2.0m x 2.0m )

J615

Steel Gate in Canal ( 2.1m x 2.1m )

JJ0615

2 set

1d

2016.Feb.01

2016.Feb.01

Steel Gate in Canal ( 2.1m x 2.1m )

J616

Trash Rack ( 1.48m x 1.30m )

JJ0616

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 1.48m x 1.30m )

J617

Trash Rack ( 1.98m x 1.70m )

JJ0617

4 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 1.98m x 1.70m )

J618

Trash Rack ( 1.98m x 1.75m )

JJ0618

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 1.98m x 1.75m )

J619

Trash Rack ( 2.08m x 1.65m )

JJ0619

8 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.08m x 1.65m )

J620

Trash Rack ( 2.08m x 2.20m )

JJ0620

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.08m x 2.20m )

J621

Trash Rack ( 2.18m x 1.30m )

JJ0621

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.18m x 1.30m )

J622

Trash Rack ( 2.38m x 2.90m )

JJ0622

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.38m x 2.90m )

J623

Trash Rack ( 2.48m x 1.65m )

JJ0623

6 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.48m x 1.65m )

J624

Trash Rack ( 2.78m x 1.75m )

JJ0624

8 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 2.78m x 1.75m )

J625

Trash Rack ( 3.48m x 1.30m )

JJ0625

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 3.48m x 1.30m )

Summary

Feb
50

Steel Pipe Scaffolding

2019.Apr.17

Milestone

Jan
49

Horizontal member of Support

2016.Feb.01

Critical Remaining Work

Dec
48

Circular P.F ( 3 times )

2019.Apr.03

Remaining Work

Nov
47

Pipe Support

2016.Feb.01

Actual Work

Oct
46

Plywood ( 3 times )

1d

Mechanical
Mechanic

Sep
45

Preshunk Concrete

15d

647 m

Aug
44

Page 17 of 18

TASK filter: All Activities


?Primavera Systems, Inc.

Jalaur River Multi Purpose Project Stage II


Activity ID

Classic WBS_Jalaur

Activity Name

CODE

J626

Trash Rack ( 3.58m x 1.60m )

JJ0626

J627

Trash Rack ( 3.68m x 1.30m )

J628
J629

Quantity Unit

2016
Feb Mar Apr May Jun Jul
2
3
4
5
6
7
Trash Rack ( 3.58m x 1.60m )

2015.Dec.14 07:59
2017
Jun Jul
18
19

2018
Jun Jul
30
31

2019
Jun Jul
42
43

Original
Duration

Start

Finish

1 set

1d

2016.Feb.01

2016.Feb.01

JJ0627

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 3.68m x 1.30m )

Trash Rack ( 4.08m x 1.60m )

JJ0628

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 4.08m x 1.60m )

Trash Rack ( 5.28m x 2.30m )

JJ0629

1 set

1d

2016.Feb.01

2016.Feb.01

Trash Rack ( 5.28m x 2.30m )

J630

Testing & Inspection

JJ0630

1 LS

1d

2016.Feb.01

2016.Feb.01

Testing & Inspection

J631

Delivery

JJ0631

1 LS

1d

2016.Feb.01

2016.Feb.01

Delivery

20d

2018.Oct.01

2018.Oct.20

2018.Oct.20, Electrical

J701

Power Supply System included Main Panel ( panel board


)

JJ0701

1 LS

20d

2018.Oct.01

2018.Oct.20

Power Supply System included Main Panel ( panel board )

J702

Incoming Power Line

JJ0702

1 LS

20d

2018.Oct.01

2018.Oct.20

Incoming Power Line

J703

Transportation

JJ0703

1 LS

20d

2018.Oct.01

2018.Oct.20

Transportation

J704

Spare parts and Tools

JJ0704

1 LS

20d

2018.Oct.01

2018.Oct.20

Spare parts and Tools

Electrical

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Jan
1

Aug
8

Sep
9

Oct
10

Nov
11

Dec
12

Jan
13

Feb
14

Mar
15

Apr
16

May
17

Page 18 of 18

Aug
20

Sep
21

Oct
22

Nov
23

Dec
24

Jan
25

Feb
26

Mar
27

Apr
28

May
29

Aug
32

Sep
33

Oct
34

Nov
35

Dec
36

Jan
37

Feb
38

Mar
39

Apr
40

May
41

Aug
44

Sep
45

Oct
46

Nov
47

Dec
48

Jan
49

Feb
50

2020
Mar
51

Apr May
52 53

TASK filter: All Activities


?Primavera Systems, Inc.

Вам также может понравиться