Академический Документы
Профессиональный Документы
Культура Документы
Project Overview
Background:
Technology
Status
Country
City
Lat/Long Location
Electricity Generation
Explanation
Company
Parabolic trough
Under Commissioning
Egypt
Al Kuraymat
2916 North, 3115 East
34,000 MWh/yr (Expected)
Expected generation is based on solar
fraction of anticipated total generation of
852,000 MWh/yr.
New and Renewable Energy Authority
(NREA)
Construction:
Break Ground
Start Production
Developer(s)
January 1, 2009
December 30, 2010
NREA
Plant Configuration :
Solar Field :
Solar-Field Aperture Area
131,000 m
Power Block :
Turbine Capacity (Gross)
Turbine Capacity (Net)
Output Type
150.0 MW
150.0 MW
Steam Rankine
Project data:
Project name
Plant location
Customer
End user
Year of operation
Gas Turbine:
Number of units
Type: GE
Fuel
1
Frame 6FA
Natural gas
1
Modular HRSG (hybrid)
2
Solar heat as energy source
Steam:
Steam flow (kg/s)
Steam pressure (bara)
Steam temperature (C)
69.4
95
500-560