Вы находитесь на странице: 1из 92

Institute of Petroleum Engineering

Production Technology

This manual and its content is copyright of Heriot Watt University 2013
Any redistribution or reproduction of part or all of the contents in any form is prohibited.
All rights reserved. You may not, except with our express written permission, distribute or
commercially exploit the content. Nor may you reproduce, store in a retrieval system or transmit
in any form or by any means, electronic, mechanical, photocopying, recording or otherwise
without the prior permission of the Copyright owner.

1
2
3
4
5
6
7
8
9
10
11
12
13

CONVENTIONAL COMPLETIONS
ADVANCED WELLS AND COMPLETIONS
RESERVOIR AND TUBING PERFORMANCE
SELECTION AND DESIGN OF ARTIFICIAL LIFT
GAS LIFT
PERFORATING
FORMATION DAMAGE
MATRIX ACIDISING
HYDRAULIC FRACTURING
UNSTABLE FORMATIONS AND SAND CONTROL
FIELD DEVELOPMENT CONCEPTS AND FLUID PROCESSING
RESERVOIR AND TUBING PERFORMANCE TUTORIAL
EXAMINATION AND MODEL SOLUTIONS

Production Technology

Petroleum Engineering

Conventional Completions O N E

Initiate Design

Selection of
Production
Conduit

Bottom Hole
Completion
Technique

Completion
String
Facilities

Conceptual Design

Casing
String
Design

Detailed
Completion
String Design

Well
Productivity

Objective of
this chapter

Well
Performance
Optimisation

Final Design(s)

Production Technology

Petroleum Engineering

Conventional Completions O N E

C O N T E N T S
INTRODUCTION
1 BOTTOM HOLE COMPLETION TECHNIQUES
1.1 Open Hole Completion
1.2 Screen or Pre-slotted Liner Completions
1.3 Cemented and Perforated Casing / Liner
2 SELECTION OF FLOW CONDUIT BETWEEN
RESERVOIR AND SURFACE
2.1 Tubingless Casing Flow
2.2 Casing and Tubing Flow
2.3 Tubing Flow Without Annulus Isolation
2.4 Tubing Flow With Annular Isolation
3 COMPLETION STRING FACILITIES
3.1 Basic Completion String Functions and
Facilities
3.2 Additional Completion String Functions
3.3 Composite Completion String
4 COMPLETION STRING COMPONENTS
4.1 Wellhead / Xmas Tree
4.2 Production Tubing
4.2.1 Tubing Diameter
4.2.2 Tensile Strength
4.2.3 Internal Pressure
4.2.4 External Pressure
4.2.5 Corrosion
4.2.6 Coupling Types
  

  
4.3 Annular Pressure Seal
4.3.1 Ease of Retrieval
4.3.2 Setting Mechanism
4.3.3 Ability to Withstand Differential Pressure
4.3.4 Number of Packer Bores
4.4 Seal Between Tubing and Packer
4.5 Sub-Surface Safety Valves
4.6 Side Pocket Mandrel (SPM)
4.7 Sliding Side Door (SSD)
4.8 Landing Nipples
4.9 Perforated Flow Tube
4.10 Flow Coupling

Production Technology
26/06/14

5 MULTIPLE COMPLETIONS
      
5.2
Multiple Zone Depletion Concepts
5.2.1 Co-mingled Flow
5.2.2 Segregated - Multiple Zone Depletion
5.2.3 Alternate Zone Well Completion Stratege
5.2.4 Selection of Development Strategy
          !
5.3.1 Dual Zone Completion
5.3.2 Completions for Three or More Zones
5.4
Multiple Completion Equipment
5.4.1 Tubing Hanger Systems
5.4.2 Multiple Tubing Packer Systems
5.4.3 Blast Joint
6. WIRELINE SERVICING OF COMPLETION
ACCESSORIES
6.1
The Wire
6.2
Surface Monitoring Equipment
7 TUTORIALS
7.1
Well Completion Designs
7.2
Completion Tutorials: Spot The Errors

Petroleum Engineering

Petroleum Engineering

LEARNING OBJECTIVES:
Having worked through this chapter the Student will be able to:
" #$     $  ! $ !
  % % 
   ! &
make a recommendation based on well integrity and reservoir management
requirements.
" '!! !! &
 &  

   !&  &*  !%
production and injection applications.
" +&  ,; $    &
 &
  
   ,
  ! !
for a variety of situations.
"  !
   %  !  &   
      
 !   <
  
equipment components.
" +&  ,    * 
  !
%  
& ! ! &    
mechanisms/operational problems with equipment.
" '!! !!* !  , =   ! &
    ! %   * & ! 
"  !
  %  !; &%  %  
! !> &$   !;&

multiple reservoir units.
" ?!    
  !
%  
 !&
*;%  
zones simultaneously.
"   %  =   =   !  !
@ !; %  ! &K !
trees for multiple completion strings.
"  !
  %  =  ! &*    ! $

  
 !

Production Technology

Conventional Completions O N E

INTRODUCTION
The development of a hydrocarbon reservoir requires a large number of wells to be
drilled and completed to allow the structure to be depleted. The drilling and completion
   !  

%  $   ,% *     !!
&
objectives. The design and completion of both production and injection wells must:
" ?$ &  &
 > <
   

" #! !  ,Y% !!  &[ &
  !\
"  ]  ! %    , &    ,% 
  $ %  $ !  &  
of the completed well
"    ! %  
!!  $ [ &&
& <
 &;     ! 
%  
!!   
  ;   &
  &  &  ! !
" ^% 
    
! &&
 &  & %  
  ! $ 
characteristics or development constraints.
% 
  & !  $$ ! 
 &
!   !;%  % $ & 
a conceptual design (Figure 1):
" 

 % % 
  
% =
"  
 % &
 
& 
" '!! !! 
  ! 
  !
" #$   *   
>&
 $ ,_ <
 $ ,
This conceptual design process is initiated on the basis of data from exploration wells.
Considerable uncertainty may exist as to the validity and accuracy of that data. Thus
a number of alternative designs for well completions will normally be selected and
contingency designs may be developed. The detailed design evaluation and costing
of the selected completion concept will then be undertaken to:
" 
,  =   &   !
" ^  ! 
    

" ^  ! *   

It is essential that an interactive approach is adopted at both the conceptual and detailed
& ! !  !% ! !
!! ,& % & $ ! ,& ! &  ;  ! $ 
@
&[ &  !;&
 
! !; 
 &%   & !
  !*%
%% $ 
! % &
!  @ 
!!; &     !; ! $    !
and production technologists.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

Petroleum Engineering

Production Technology

Initiate Design

Selection of
Production
Conduit

Bottom Hole
Completion
Technique

Well
Productivity

Completion
String
Facilities

Objective of
this chapter

Conceptual Design

Casing
String
Design

Detailed
Completion
String Design

Well
Performance
Optimisation

Final Design(s)

Figure 1 Completion design strategy.

Well Integrity is the process that sets the Standards and Policies which the completed
* !%& &%  % * !%&, 
!
 &; !   & &
maintained to these (company) standards and policies. These standards and policies
 ,    , 
 ; , !   &

& %   % 


& &%     $  
Well integrity encompasses:
" ` !
 +  ,{
Wellhead & X-mass tree
Casing & Cement Integrity
Shoe bond & window cement bond tests
CBLs
Casing Corrosion Logs
Zonal Isolation
Well bore integrity
Etc.
"   +  ,'!! 
{
Wellhead & X-mass tree integrity management
  *} < *  ,   , !! 
Y*}   ,~ $ ;  !;
  &   &  ; `     #,  & ;       ?
@  % 
 ?     $  ; 
\
Accessibility assurance (i.e. no obstruction)
Annulus Management

Conventional Completions O N E

Gas Lift & Gas Injection


Pump Integrity Assurance
Etc.
" *'!! 
{
Scale Management
Asphaltene Management
Corrosion Management
Etc.
" `   ,
     
Examples of well integration failure are presented in Table 1.
FAILURE EVENT

OPERATIONAL
CONSEQUENCES

CONCERN
IF NOT REPAIRED

Tubing failure in wall leak


or coupling

Tubing Annulus communication

Well safety

Packer failure

Annulus reservoir
communication

Well safety

Seal failure

Annulus reservoir
communication

Well safety

Tubing hanger leak

Tubing - annulus
communication

Well safety

Xmas tree seal leakage

External leak

Well safety

Wellhead leakage

External or annulus
leak

Well safety

Circulation sleeve seal failure

Annulus communication

Well safety

Sub Surface Safety Valve


failure

Inability to isolate well


Inability to land flow
control devices

Well safety and loss


of flow

Gas lift valve leak

Tubing annulus
communication

Well control limitation

Gas lift valve closure

Inability to lift well at


valve depth

No or limited
production

Downhole pump failure

Failure to lift well

No production

Table 1 The nature and consequence of completion failure.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

Petroleum Engineering

Production Technology

BOTTOM HOLE COMPLETION TECHNIQUES

The three alternative approaches for the completion of the reservoir zones are:
" ^ % 
  
" ? _&  &> _! &  !
 
  Y
  &\
"  !   * %  
    &!! =    

1.1

Open Hole Completion

The simplest approach to bottom hole completion is to leave the entire drilled reservoir
section open after drilling (Figure 2). Such completions are sometimes referred to
as barefoot completions and the technique is widely applied. Since no equipment
requires to be installed there are savings in both costs and time. However this type of
completion does mean that the entire interval is open to production and hence does
$ & ! 
 $ 
$ [ &&
  <
 + !%   
recommended for production or injection wells where distinctive variations in layer
    ,* &    , % !*  

, !& *  [&
 ! <
 + !& 
 !  *  > ! @%%    % 
wellbore unless the entry pour is at the base of the well where isolation with a cement
 , !

!!% !!   ,   


!![* 
@ !! 
dictating multizone depletion cannot be corrected with this type of completion.
This lack of zonal control for production or injection is the major limitation on the
application of this technique.

OPEN HOLE

Figure 2 Open hole completion.

Open hole completions can only be applied in consolidated formations as the borehole
 ,
 !  
 & *&*   & &
% * [*+!
%
cases either total collapse of the formation or the production of sand may occur.
6

Conventional Completions O N E

The above characteristics of open hole completions explains why they are used in:
" *
!& $  !
"  ;
! &  & ! $ ! &
&,&   & $  ! !&
contact between fracture and well
"   ,
 & ! $ !
"  %   &    * !* %% %&   
!!

1.2

Screen or Pre-slotted Liner Completions

'*  _*  &!


 ;! &!       $ ! &
!
  ! !  &
(Figure 3) once the drilling through completed reservoir section has been completed.
The screen or liner is installed to prevent sand production into the wellbore and tubing.
The success of the completion in controlling sand production is dependent upon the
screen or slot sizes and the sand particle sizes. The screen will only become 100%
effective if it totally restrains sand production which requires that the slot size be equal
% ! % !  ! 
 !}* $ ; !
%
! !% !! ,=
@,

  & &  & [*; !   !! * &
 $ ,
This system is also used in high angle angle wells to prevent major borehole collapse
or facilitate the passage of logging tools.

PRE SLOTTED LINER


( or Alternative)

Figure 3 Well completed with wire wrapped screen or slotted liner.

This technique shares the inability for zonal control of production or injection with
open hole completion. It may also only effectively control sand production over a
   &  
&  !}* $ ;  ! Y   $ ,\*
!
% = ! 
conventional sand screens restricts the technique's application to reservoir rock that
consists of relatively large and homogenous sand grains. The introduction of woven
mesh screens and in particular expanding sand screens has greatly extended its range
of applicability.
26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

Petroleum Engineering

1.3

Production Technology

Cemented and Perforated Casing/Liner

%     ! !  %  


  &
! ! *%
% ] &!
@
surface or a cemented liner which extends back into the shoe of the previous casing
! Y  \?   !! = ,$ & ! %![ &[*>
the wellbore and formation.

CEMENTED AND
PERFORATED
LINER OR CASING

Figure 4 Cemented and perforated production casing or liner.

The integrity and selectivity of the completion depends on an effective hydraulic


seal being provided in the casing-formation annulus by the cement placed during
%   ,
 <%  ! 
  % 
 
 & % [ &
    % &% 
! !
;  %      !
which it was assumed to be isolated. It may be possible to regain annular isolation or
close off unwanted perforations by a remedial cement squeeze operation.
This type of completion involves considerably greater costs and time than the previous
options. The cost of a full length of casing from the surface to the base of the well

 
! &   ;*%
%!  && &% 
!   ;
   &
the additional rig time. The use of a liner helps to reduce the required length (and

!\ 
!  }* $  %    , 
 %  &     & $ &   !;
!  %  [*& !   &
&[ &! &
%  <
 [ &!
into zones are essential to a large number of developments. This has resulted in the
cemented and perforated liner or casing being the most widely applied bottom hole
completion technique.

Conventional Completions O N E

SELECTION OF THE FLOW CONDUIT BETWEEN THE


RESERVOIR AND SURFACE

%       ![ &[*!


  &
 * ;% 
     <
 * ! &   !*%
% , [ 
% 
%
 
& 

!;[*!   ,;   ,


[* & ! * !  , &   ,
the well by minimising corrosion or erosion.
The following alternatives exist for a single zone completion:
"
"
"
"

  !!


! [*
 !  & [*
 [** %   !  
 [** %   !  

These options are depicted in Figure 5


(a)

(b)

(c)

TUBINGLESS
COMPLETION

TUBING COMPLETION
WITHOUT PACKER
(with optional
annulus production)

TUBING COMPLETION
WITH ANNULUS PACKER

Figure 5 Alternative production conduits for a single zone.

2.1

Tubingless Casing Flow (Figure 5a)

Once the well has been drilled and the bottom hole completion technique implemented
Y %    &
! \% *  ! &
&[*& & *&* &[ &
is produced up the inside of the casing. This technique is very simple and minimises

!!}* $  & !% $  !& ! &$   ! !,;% &


 
!  , !
   &   % % [ &! 
$ 
 !  * %% ! !    
&! 

; !  !  [* & 


 ! &[*  !! !! 
% 
! % &
&[ & ! ! & 


* %% 
! ;  ,
 !  
! 
! ; }2S or CO2   !  &
&[ &!
! 
! ; ! & ! &
& &
 ! % 
!    ,&  % 
the above can result in potential burst of the casing at the wellhead if the well changes
from oil to gas production.
26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

Petroleum Engineering

%  !  =      *@$  ! %  %  *  ! %,& 


, @  & % 
 !      %,& 
 % &  [ & *%
% $ & !   %   !! 
greater than reservoir pressure in this type of completion can only be accomplished by
either squeezing% *  
 !
@ %   ;

  
!!
the wellhead using the Volumetric Technique=   $ ![ &!

@ %    !& !     ,
! !! 
 ,!;!
 % 
particulates will be carried in the perforation or the formation matrix. Thus killing
such wells will result in a compromise between safety and subsequent productivity. In
&&  ; !!=    !;%  =  & <
  !! !*& 
 !  !
[ &!   <
 & &% ! ,
! 

$ 
! !    !% 
  &   
! ;% & ! @ [ & , %%%  % %,&
;
inhibiting the squeeze process.
% !
   !  ,! && % ! & *
@!%   !!
  ; 
$  % ! 
%; !!   !  &   !}  %  %  !
drilled passed all the zones and individual tubing strings located opposite each zone.
The entire borehole is then cemented and each tubing string perforated with orientated
guns. This is not a simple multi-zone completion but its design precludes workovers
if problems subsequently arise.

2.2

Casing and Tubing Flow (Figure 5b)

'    $   !!


! [*% %,&
 $ * !*%     

!!!
    [* !& !   ; ! !  &
   & *
[*

%   &%  _


!  !% !, 
  
has the very important advantage of providing a circulation capability deep in the
* *%   ! $ [ &!
 & !
&!
,  <
 &@ [ &% 
required density to provide hydraulic overbalance on the reservoir. This capability


  Y_ \@ [ & * %  ! &%   $ !% 
necessity for reinjection into the reservoir. It also does not require the high pressures
!!
 &* %!=    !% !
   !$ ,! % %[*  
* !$ & & ! $ 
! $ 
&!   !  % [*! 

2.3

Tubing Flow Without Annulus Isolation (Figure 5b)

+!   !*%    [*  


! _! 
   !!  ]
!! $ 
% ! !   * %
! =  
 ! &[*  !! !! &[* !   ,;
consideration should be given to closing the annulus at surface and preventing annular
[*+% [* %  !!  !  *%   ; !;* 
   * &!& , 
,
! ! [*!%   %  
tailpipe. Some gas will accumulate in the annulus resulting in an increased casing head
 !!  !
 ! & %  !* 
    !
  , !
the annulus when it off-loads as a gas slug into the base of the tubing and is produced.
This production instability will be cyclical and is referred to as annulus heading.
In this type of completion the casing is exposed continuously to the potentially corrosive
&
&[ &% !;
 &* %%     % & ;
  $ & &
when the annulus is not left open to production.

10

Production Technology

Conventional Completions O N E

2.4

Tubing Flow with Annular Isolation

'  !

! 

 !; !& !
!! &  $ %   ;% 
! ! , !  &,%  !    
@  &% &
&[ &
[*!% !
$ %  % 
@ % !     *%
%;*% 

 !! & [  &;*  ] & %  ! * %   &% 
casing. The packer is normally located as close to the top of the reservoir as possible
to minimise the trapped annular volume beneath the packer. Hence the volume of gas
which can accumulate there is minimised; simplifying downhole pressure management
*% % 
@  !  ! &,% &   & 
$ ,   !}* $ ;

@  !    $ !%    ,_ 

  @ [ & * % 
  & !% 

  
   ,
  ! &$  

!!,;
such as a sliding side door which allows annulus communication. Alternatively one can
   %  ;*%
%*& & 
  % 
 
  
&
 +%
! !;% 

    ! , !&  % *  !
!!  ; $ % 
@ 
This completion system is by far the most widely used and offers maximum well
security and control.

COMPLETION STRING FACILITIES

There are many capabilities which can be included in the string design. Some of these

    !   !!  ;!
% !%! $ &     !
 ,!  ,;*% !
% !$ &  $ &  
[ ]   ,}* $ ;  
 ! &&  
[ ]   ,$ & &,% 
   , !!  
 ]
  
design with a large number of components. Such inbuilt complexity compromises the
reliability of the completion string. The design process should thus initially identify
the minimum functional requirements. Any additional options are then assessed on
%  ! ! 
   
 ] ,$ !! 
     

3.1

Basic Completion String Functions and Facilities

The basic facilities provided by a completion string must allow it to continue the
&
  <
 [ &!$  !   & !!!  * %% 
!! ,
  <  $  
&
*   !% ;% & ! ! ! % 
safe operation of the well at all times and also reliably allow for its shutdown in a
$  ,!   !% 
  ! ;&
 
!  &* % &!
act as a composite high pressure system which prevents the unintended escape of
  [ &! & !!    [* !% &
   &% K !
Tree into the surface processing facilities.
The following (see also Figure 6) are considered to be the essential for the majority
of completion string installations to allow the well to be produced in a safe and
controlled manner:
Y \%    , 
  %  ]
 & [*   !!  ! *  ! %  % % !
%,& 
 !! *%
% ,  , & *    ! &!%&[*
!
Y&
 \%  ! $ Y <
 * !\* %   [* 
 !! !! &  [*!   ,

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

11

Petroleum Engineering

Production Technology

Y\    ! $  [ &



 * % %  &
 
!  , !   % 
annulus between the production casing and the tubing.
(c) The ability to affect downhole shut-in either by remote control or by automatically

 $  &,% 
%  * [* 
&  !
(d) A means to establish circulation between the annulus and the tubing.
(e) The ability to block the tubing by the installation of a plug. This allows pressure
testing of the tubing etc.
Surface Isolation
(wellhead / Xmas tree)

Tubing Isolation (SSV)

Circulation between
Annulus & Tubing (SSD)

Annulular Isolation (packer)


Tubing Isolation (nipple)

Figure 6 Basic well completion schematic.

%  $  *!% 
  ! &
  !  ;
    
Consider each of the functions in turn:

Pressure and Flow Containment


%  ! $  !!  !
  &* % % &
 
! ;% &
  ;
% * % & &% !
$ $ 
! !,! @* !% K ! % ;
the casing and tubing annulus is protected from the reservoir or injection pressure if a
packer is installed at the bottom of the production tubing. The tubing size is selected
!
%% * &
   !    ! & &% [* !!  
%!;%% 
!  & !%& & !  &* %! &%  ]  !! 
]
 & % *  % &
 
! ;
@  &* % &
 ! 
@

 [ &! & !! ! %  $    @   ,;% * % &;
from which each casing string is suspended will be rated for maximum anticipated
!
 !! !^$  
[ &&
 ; <
  ;% * 
12

Conventional Completions O N E

is provided by the valve system located on top of the wellhead. This Xmas tree usually
comprises an in-line valve with a backup valve to shut in the well and side outlets
with valves for both choke and kill line attachment during well killing procedures.

Annulus Isolation
Annulus isolation is required in the majority of production wells for reasons of tubing
[*!   , &
 % &
 
! 
! + ! = ,
necessary to isolate the annulus to prevent surface injection pressures being exerted
on the wellhead and possibly giving rise to burst of the production casing. This occurs
in injection wells and during well stimulation operations.
This annular isolation is normally achieved by installing a packer at the bottom of the
completion string which is lowered into the wellbore with an elastomeric element
%  
 &!  '%  !
  && %;%     !! , ]! 
[   %   !
 * %   &%  !   ! % 
$  *% 
@  &%  %
!  ]! &* [ &!;% 
@ 
is normally set quite deep in the well.

Downhole Closure of the Flow String


+ ! &$ !  ; & !
! ! & ,;% $  !
& , !
! 
* !
    [*!
'

!!% K ! 


! % K !
tree valve is not possible. The installation of a sub-surface safety valve (SSSV) will
provide this emergency closure capability. The valve can be either remotely operated
from the surface {a surface controlled sub-surface safety valve (SCSSSV)} or will

!   
,*%   &    &[*
&  Y ]
!! $ [*  
low bottom hole pressure) occurs in the well.

Circulation Capability
^ %  <    !!  &
 
!  !% [*
& Y  
without a production tubing) is the inability to kill the well by circulation. A coiled
tubing unit or snubbing unit could be used but is unlikely to be available at short notice
to carry out the well killing operation. Hence the majority of completions include
one of the following devices to provide circulation between the annulus and tubing:
"  & ! & &Y\! & ! $ Y\
"  & 
@  & Y?\
" ? & 
They can all be opened when required and subsequently closed. An alternative is to
use a tubing punch or a perforation gun with a low power tubing perforator charge.
}* $ ;% ! !,! &  *@$ ! 
%  ! %  !   

Tubing Isolation
A further means of physical isolation of the reservoir is installed at one or more places
%  %!% $ !  !   !& * % % *  ; % <!
above and/or just below the packer. The isolation is normally provided by lowering
a plug on wireline down the inside of the tubing string until it lands and locks into
a wireline nipple which was incorporated into the design of the tubing string at an
appropriate depth.
26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

13

Petroleum Engineering

3.2

Additional Completion String Functions

A range of other tubing functions may be necessary as a future contingency. Some of


the more prevalent are discussed below.

Downhole Tubing Detachment


Failure of a tubing string component often results in the necessity to pull the completion
% *  
 ! 
 }* $ ;  !!    ! %  
of equipment to be pulled from the completion while making this replacement. Thus
a point of easy detachment and reconnection would be useful. This is obtained by
installing a removable locator device that seals in the remainder of the tubing string
left in the well during the repair operation. A means of hydraulic isolation of the
tubing below the point of detachment is also required. Examples of such systems are

@ ! !,! ;*%
% *!%   $ % 
@  & !

 &
and retrieved; or a downhole hanger system which suspends the tubing in the well
beneath the wellhead. Completion components that are more prone to failure and
 =   =  
 ; ~;*  
 & $ !
%& $
!

Tubing stresses
Temperature and pressure changes during normal well operations results in the tubing
string can expand or contract in length. The resulting changes in the tubing stress can
 !
,! $   ! $  ! &   % 
@ ;* % &%  
!  %   ! ] &
!  & % !
, &  % * % &
and downhole in the packer.
These stresses can be avoided by installing a moving seal system which allows expansion
and/or contraction of the tubing without mechanical failure or disengagement from
the packer or seal bore. Various systems are available. They all feature a concentric
! $  
%*%  ! !  
 &  


 !; !
*%
%
moves while the other is stationary.

Ability to Suspend Pressure and Temperature Monitoring Equipment


It is frequently required to monitor the bottomhole pressure during production tests by
!    !!         !


  %  '*    
  ; !  & !&  % *  !!!   % 
  ! $ & !% !

 ,'   &   ! !  & $ % !  $ &      $ [*
entry point when the packer tail pipe is blocked by installation of the gauge.

Controlled Fluid Injection from the Annulus into Tubing


?&
&[ &!

 
! $ 
 !;!
% !^;% $ % %
 !* %  & [*  !! !! !% 
!Y
!  %  !
 &  !! !; 
\
  <
 &+ , 
!! , &

% 
!
% [*!   
 & * % % * $ &  ]    &
counteract the impact of these characteristics. Examples of this may be the injection
 
!  %   &  !! ^   ! <
% ! [ &!
into the casing-tubing annulus and include in the tubing string a side pocket mandrel
* % $ $ *%
%*  &  !
  & !! 
&  !%   [ &
* % [*%  ! %   % 
 !,    ,
'%  ]   ! !  !   !*%   !  <
 & % &
&[ &!
to lighten the hydrostatic head and maintain production at economic levels.
14

Production Technology

Conventional Completions O N E


 
The selection of an electrical or hydraulically powered downhole pumping system or
of gas lift will require the inclusion of the pump or of multiple side pocket mandrels
in the completion string design. Important design issues will be:
" %  %& !    &  $ %   
" ! !

!!%  *    %% 


" +!   & %% ! & 
@  & ! &  &&
% 
well.

Wireline Entry Guide


+*  
!! ,; !* !;
&
*    
  &    !
 *% %  ! ; 
!!%    &  $ `    #,
Guide (WEG) aids retreval of the wireline tool string from the casing into the lower
end of the tail pipe of the tubing string.

3.3

Composite Completion String

% 
  ! & !  ! [ 
&,    ! $  &%     !
 ,&   & ! ! ] ! &
%!

!   ;  & ! !

be considered. Figure 7 summaries the general completion components and their
functions.
COMPONENT

FUNCTIONALITY

XMAS TREE

Flow Control and


Surface Isolation

WELLHEAD

Tubing & Casing


Suspension

(SC) S.S.S.V.

Safety Isolation
Downhole

SIDE POCKET
MANDREL(S)

SLIDING SIDE
DOOR

SEAL ASSEMBLY

Circulation or
Fluid Injection

Tubing / Annulus
Circulation
Accomodate
Tubing Stress

PACKER

Annular
Isolation

NIPPLE

Tubing
Isolation

PERFORATED
JOINT

Alternative
Entry for Flow

NIPPLE

Landing T and P
Guages

W.E.G.

Wireline
Re-Entry

Figure 7 General well completion string schematic.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

15

Petroleum Engineering

COMPLETION STRING COMPONENTS

% &   && ! % 


  !  $$ !% ! 
  &!

 
  !
  !%     ,  
 ! $   ;
% 
has numerous variants and each equipment supplier has their own particular designs.
In practice most companies use one supplier or have considerable experience with
!

, !
 !'!;%  =   !!
& ! 
 !  &
with a certain type of threaded coupling. Hence tubing completion equipment is of
necessity fairly standard and comparable between the different suppliers.
Equipment selection should be done on the basis that the component will provide a
!


 ,
!! ,% !

!!  
 &   % * 
under a range of operating scenarios. Each component adds undesirable complexity
to the completion. This must be compensated for by the fact that it is necessary or

 
 . One approach to discussing whether a particular
* 
   ! __!  ! $   % 
  !% 
%
 
$ & !% & !  !%!<! &  &! ! ! &%   ![ ]   ,
can be assessed against the drawback of incremental complexity.
Each component in Figure 7 will now be discussed below in relation to its purpose in
production operations. It should be remembered at all times that the purpose of well
design is to minimise the wells "total life time cost" (i.e. the sum of the well construction
capital costs and the subsequent operating costs. Thus a range of reservoir depletion
scenarios should be considered during the above evaluation.

4.1

Wellhead/Xmas Tree

The wellhead provides the basis for the mechanical construction of the well at surface
or the sea-bed. It provides:
" ! !   & $ & 
! ! & !;


, % * 
" '  ,  !   !

! >[*
 & $
    %  * 
This is ether a blow out preventer stack whilst drilling or the Xmas tree for
production or injection
" },& 


!!%    * 
!  *
 
  &
between the production casing and tubing for well circulation
% K ! $ $ $ & [*
% [ &!&
& <
 &
into the well. The Xmas tree is normally installed on the wellhead after installation
of the production tubing has been completed. The wellhead provides the facility for
all the casing strings and the production tubing are suspended from the well head
*%
% ! ! ! &,% 
&
;% &  % * %     
  !
K ! & ! !   +% !** $ $  !; 
&
  &% %  <
 ; * @  '&&   ,;% % &
outlet (swab value) provides vertical access into the tubing for insertion of wireline
or coiled tubing tools into the well. The lower valve is the master valve. It controls
all hydraulic and mechanical access to the well. Well safety may require it to be
duplicated. All outlets have valves which may be manually operated or are remotely
controlled valves operated from a control room.
16

Production Technology

Conventional Completions O N E

GAUGE VALVE

XMAS TREE

TOP CONNECTION
SWAB VALVE
FLOW FITTING

CHOKE
WING VALVE
MASTER VALVE

TUBING HEAD ADAPTOR


TUBING HANGER
TUBING HEAD

WELLHEAD

TUBING
CASING HANGER
CASING HAED
INNER CASING
INTERMEDIATE CASING
SEALING MEDIUM
CASING HANGER
CASING HEAD
OUTER CASING

Figure 8 Simple wellhead assembly including casing spools and Christmas tree.

4.2

Production Tubing

The bulk of the completion string comprises threaded joints of tubing which are coupled
together. The integrity of the tubing is vital to the safe operation of a production or
<
 * % !

  &
  ! 
 & ! &
% 
% 
 &%,& 
   
&  ! $ !  &;% ! &   
$   &  * 
! &   !%  ! !
&$ & 
the following capabilities:
Y\%  ! &  &     %    ! $ &   &
& [ & $ 
, 
minimise the total pressure loss (the tubing performance relationship).
(2) The tensile strength of the string (both tubing and coupling) must be high enough
to allow suspension of the complete string without tensile failure.
(3) The completion string must be able to withstand the maximum conceivable
internal (or burst) pressure.
(4) The completion string must be able to withstand the maximum concievable
external differential pressures between the annulus and the tubing (the collapse
pressure).
(5) The tubing must be resistant to chemical corrosion which may arise because of
[ &

 % *  ; & %   ,

   !   ,


one of the loads and stresses mentioned above (2)-(4).

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

17

Petroleum Engineering

Each of the above facets of tubing selection are discussed below.

4.2.1 Tubing Diameter


$   ,% ! & &   %   !!
&%  ! & &   
!&  &,% * %
@ !!! $ %  !* %  Y!>\ 
^ !>% * %
@ !!*  [ 
%  !  ! %% 
steel as well as its resistance to failure with high internal (burst) or (collapse) external
 !! &    !%   !%!!
& !  
 ! & &   
& !

* %>*%
%%!!
!% * %
@ !!

4.2.2 Tensile Strength


The maximum allowable tensile load of a joint of tubing is determined by the tensile
! %% ! ;% * %
@ !!%  Y &% 
%   &  \
and the tensile strength of the threaded coupling.
%    ! $  ! & & & !! }_;_;_;_;_ &?_
The numbers after the letter grading signify the minimum yield strength in units of
a thousand psi. The letter grades indicate the manufacturing process or subsequent
  % ! & , !  !; %  & & !  %   &
 $   ! 
! !+   ;% % % % , &! %
  &,*@ 
% ! ;%  !!
    !     &  ,}2S.
%   , &! %&  !%    !  ! % ! %  !  
 & !
 &,%   &  * !
   %   ;% 
% * %>
foot of the pipe also affects the tensile load. The joints nearest surface are under the
greatest tensile load due to weight of the suspended pipe since each joint suspends
the joint immediately beneath it.
% % & &
 % !$ & * !

 ! !, !  !  
load up the tubing string and secondly to produce a connection which provides a seal
to retain internal pressure within the tubing.
The design of a completion string to withstand a given tensile load will obviously be
dependent upon the depth to which the completion string will be run but the following
aspects will also be considered.
(a) The minimum tensile strength of the pipe utilised for the design will be based
%  
 !&  % !

 +*   &
&,% 
application of a safety factor with a typical value of 1.6 to 2.0.
(b) The tensile load of a suspended string will cause it to become longer leading to
a reduction in the tubing's wall thickness. This will have to be taken into failure
conditions due to high external pressures by derating the nominal collapse resistance.

4.2.3 Internal Pressure


+ !%   & %  !    !! %  !  ; % 
the differential pressure between the internal and the external pressures. The "highest"
burst condition is usually encountered at the surface where the external pressure is at
its minimum. The maximum design burst pressure is normally the pressure when the

18

Production Technology

Conventional Completions O N E

!  ! !  &  %  % & !!  = !%  ! $  !!  !
the hydrostatic head of gas in the well.
A safety factor which varies from 1.0 to 1.33 is normally used to reduce the tubing
manufactures test data.




The collapse condition occurs when the external pressure exceeds the internal pressure.
This condition is normally greatest at the bottom of the well when the annulus is full
[ & &  ! $
  &
The published minimum tubing collapse data are derated by a safety factor of 1.0 to
1.125.

4.2.5 Corrosion
There are two principal types of corrosion encountered in oil and gas production
wells namely:
(1) Acidic Corrosion due to the presence of carbonic acid (from CO2) dissolved
% &
&*  %  

&
 % %,&
[ &
(2) Sulphide Stress Cracking/Hydrogen Embrittlement due to the presence of
H2 % [* * [ &!%  ! $ }2S can also be generated by
% *% &

   !  [ &!;  % 
! _  !
or in the reservoir.
Most corrosion is selective (pitting) rather than an even reduction in wall thickness.
Corrosion inhibitor treatments will assist in minimising corrosion damage but must
be continiously applied. The alternative approach is to select a steel that is naturally
 % &
&[ &! ]  ;* & !  !
 & &! }2S
 
 !! !! 
% !    !!!!
      ; _
Figure 9 is an example of a completion metallurgy selection chart illustrating how
more complex and expensive alloys are required as the partial pressure of hydrogen
sulphide and carbon dioxide increases. Increasing reservoir temperature will further
complicate the selection process.
(3) Corrosion/erosion is also encountered due to the presence of produced solids
% *  !&
&  % % [*$ 
,

4.2.6 Coupling Types


There are two general classes of threaded coupling:
(1) Connections which require internal pressure to produce a pressure tight seal.
This type of coupling includes the API round thread and buttress connection whereby
a thread compound applied to the threads must be compressed by external pressure

 % 
 
!    ,$ &!
!* % % 
 
(2) Metal to metal or elastomeric seal connection - Premium threads.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

19

Petroleum Engineering

Production Technology

This class of coupling includes the Extreme Line as well as a range of specialised

 !!


 
& ! ; },& ~'& ! !% 
 !
do not always utilise the threads to give the pressure seal but allow torque to be applied
to bring together seal shoulders or a tapered surface within the coupling.
^% !
 ! &
 !;!
% ! !  !  !;   !! &$ &  
additional seal system.
    ! 
 !! & ! Integral or  couplings:
" ' ]  
 !
% !% ~'
 Y   \ =  !%    
thread be cut on each end of the tubing joints and while the coupling has two
female connection.
" ' ]  
 % !    
 $ * %
@ !! % 
 !
 
(Dc > D) giving it higher load capacity compared to an integral coupling. The
integral coupling (Figure 9b) has a male and female thread cut on opposite ends
of the pipe.
" ' ]  ! 
 ! !  
 ! &* %
@ !!     &
%    *     % & 
* %!


%
the tensile load carrying capacity.
" '[!%<  !  *%
%%   !  +     Y&&
\%%
the make up connection (Figure 9a).
" '   ! 
  !  *%
%%   ! ! !
 &
 ! &
Internal Diameter (d > dc) in the area of the coupling (Figure 9b).
1.0E+06

1.0E+05

DUPLEX STAINLESS
22 Cr- 5 NI - 3Mo
COLD WORKED 2205

15 Cr - 60 NI - 16 Mo
21 Cr - 61 NI - 16 Mo
25 Cr - 50 NI - 16 Mo

1.0E+04

QUENCH
ANNEALED

1.0E+03
27 Cr - 31 NI - 3.5 Mo
22 Cr - 42 NI - 3 Mo
1.0E+02

13 Cr
20 Cr - 25 NI - 4 Mo

1.0E+01

1.0E+00

1.0E-01

API J-55
N-80
NACE

API-80
C-75-2

85 SS
90 SS

1.0E-02

1.0E-03
1.00E-03

1.00E-02

1.00E-01

1.00E+00

1.00E+01

1.00E+02

1.00E+03

1.00E+04

1.00E+05

Partial Pressure of H2S, psia

Figure 9 An example of a Completion Metallurgy Selection Chart

20

1.00E+06

Conventional Completions O N E

a)

b)
D
d

D
d

dc

dc

Dc

Dc

Figure 9  \~'{'   ,[!%


 \'   ;   ,! 
 


 

!"
% !  !&  &   ,,% * &
 $ ,  ,! !*%
% &  !% 
optimum tubing internal diameter based upon the available sizes. Frequently the
completion string will contain tubings of different diameter with the diameter decreasing
towards the bottom of the well. The use of larger diameter tubing higher up the well


 %  
 ! [*$ 
 ! !% [ & ] &! & ! !    &
from solution as pressure declines up the tubing. The reduction in tubing size in the
lower sections of the well may be necessary because of limited equipment availability
&
% 
    ; &
    ! & &   
% &   && !  ! &% % 
% 

&  !Y ! ;! &

 ! \
 
  &
% !  !!
&%  ! !

 
the tubing is summarised as:

26/06/14

Length
of tubing

tubing
OD

e.g.7000'

51/2

tubing
wt/ft

23 lb/ft

grade coupling
of steel
type
C-75

Institute of Petroleum Engineering, Heriot-Watt University

joint
length

Hydril Range 3
Super EU

21

Petroleum Engineering

4.3

Production Technology

Annular Pressure Seal

An annular seal or pack-off in production wells is necessary for:


" +$ &[*!   , &&
 

" ?
 %   !! 
  !,! Y% &
 
!  &
the wellhead).
" +!  $  ! !& !   &
    !; 
!  *&
 !% $ &   [ &  !;^; !! 
permeability or for stimulation or pressure maintenance.
The most common method to provide an annular seal is the packer (Figure 10a). The
packer is anchored in position by pushing the steel teeth of the slips into the casing
wall while the pack-off is accomplished by expanding or extending the elastomer
element outwards from the packer body until it seals against the casing wall (Figure 10b).
a)

b)

Compression force moves


cone downwards moving
slips against casing well
and compressing sealing
element.
The greater the compression, the
greater the sealing force and the
resulting resistance to packer movement.

Drag Springs

Slips
Upper
Cone

Lower Cone
Cone
Lower

Sealing Elements

Lower Slips

Slips

Figure 10 a) Permanent packer. b) Schematic of setting a compression set packer.

The characteristics that determine which type of packer is most appropriate for a
particular application are:

4.3.1 Ease of Retrieval


This refers to how easy it is to release the packer for retrieval to the surface. This
&    !% &  & 
, *@ $  *  & , ! &

limitations in of the differential pressure that the packer can withstand:
22

Conventional Completions O N E

" A Retrievable Packer The packer can be run as an integral part of the tubing
string. It is run to the setting depth where the setting mechanism is actuated.
It can be easily retrieved after installation by pulling tension on the tubing and
shearing a set of (weak) screws. This reverses the setting process.
" A Permanent Packer (Figure 10a) cannot be so easily retrieved. It is usually
 &! !    ,; % * %* %%    %  !  !
subsequently run and the packer engage to achieve a pressure seal within the
central bore of the packer. Packer retrieval involves milling away the packer's
internal sleeves to allow the rubber element to collapse.

Packer Retrieval
" '  $  
@  !
$  &,  ! %  % ! ! 
shears a series of (weak) brass screws at a predetermined value that depends
on the number and strength of the screws. The packer setting action can now
be reversed. The slips disengage from the casing wall and the sealing element
collapses and the packer is released from the casing wall and can be pulled to
the surface.
"  $     
@  =  !   * ,%    ! $ ;*%
%
%&!% ! ! 
% !  ! !% 
@ ;*%
% !*  &

be pulled from the well. The milling operation normally takes between 3-6 hours.
%  % & ! & &% 
@  &   & 
,  & &;
*%
% !! !%%;% 
@  Y  \%    ! !  &
with a retrieval tool and catch sleeve which collects the remains of the packer
*% %       !
  ; &%    $ &

Packer
Mill
Packer

Milling
Shoe

Catch sleeve prevents


packer falling into well,
allowing immediate
retrieval

Catch
Sleeve

Figure 11 Packer milling tool illustrating one trip milling and retrieval.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

23

Petroleum Engineering

4.3.2 Setting Mechanism


The compression and extrusion of the rubber element during the setting of packers
can be accomplished by a number of mechanisms.
" Mechanically set e.g. by rotation of the tubing string.
" Compression or Tension using the suspended weight of the tubing. A cone
mechanism transfers the string weight to be transferred to the packer to compresses
the rubber element (Figure 10b). This setting mechanism is simple but is
unidirectional in terms of the setting force and ability to withstand a differential
pressure. This drawback can be avoided by installing an upper cone (see Figure
10a) which acts in the opposite direction and will withstand tensile forces.
" Hydraulic set utilises hydraulic pressure inside the completion string. The tubing
string must be isolated or plugged below the packer to prevent pressure being
exerted on the formation or the annulus during setting.
" Electrical The packer (plus tailpipe) assembly is lowered into the casing on an
electrical conductor cable. A small explosive charge is detonated at the required
!  & %;
  % !  
%  !

4.3.3 Ability to Withstand Differential Pressure


" Compression PackersY * %! \+% 
!  &
* !;
higher pressure below the packer compared to above counteracts the setting
mechanism. This type of packer is suitable for injection wells where the differential
pressure supports the setting mechanism.
" Tension Packer This is the opposite to the compression packer.
" Compression and Tension Set Packers Packers that can withstand pressure
from either direction.

4.3.4 Number of Packer Bores


+ !
!! ,% $   %%% 
@ 
% !   ;& 
or triple bore packers are available for multiple tubing string completions.

4.4

Seal between Tubing and Packer

Some completion designs anchor the tubing string mechanically to the production
casing at both the packer and the tubing hanger that was landed in the wellhead.
% ;
%  ! % [*      &  !! 

!    
or contraction of the tubing string. This may result in buckling or tensile failure of
%    ! *%    *  %  
@  & * % &  !
 $ , %!; ! 
!!  !
 
 !! &

& *% % % , * $  


compensate for thermal expansion and contraction of the tubing i.e. dynamic or static
seal assemblies respectively (Figure 12).

24

Production Technology

Conventional Completions O N E

(a)

(b)

(c)
Locator

Anchor seal
assembly

(d)

Locator with seal


assembly inside
polished bore
of packer

(e)

Locator seal assembly


with seal bore extension

(f)
Polished Bore Receptacle (PBR)
Packer seals liner annulus
Cemented production liner

Extra Long
Tubing Seal
Receptacle
(ELTSR)

Travel joint

Figure 12 Schematic views of various tubing seal assemblies.

" Static or Anchor Seal Assembly (no tubing movement). An external elastomer
elements seal at the bottom of the tubing. Tubing movements is prevented by
installing a mechanical latch assembly inside the seal bore (Figure 12a).
" Dynamic Seal Assemblies accommodate tubing movement.
" Locator Seal Assembly (Figure 12b) This consists of a series of standard elastomer
seal elements which are run inside the smooth (polished) bore of the packer. The
 %% ! ! !!
% % ,  * % % 
@ *% %  
experiences the maximum expected amount of expansion or contraction. A greater
seal contact area is provided by a seal bore extension run below the packer (Figure
12c). A locator (or shoulder) is included at the top of the seal assembly. It has an
outside diameter that is greater than that of the packer base. The point at which the
!      !% 
@  ! &  &,! $   &
  % 
string weight when the locator "hangs-up" on the packer.
" 
"
!"

#   (ELTSR Figure 12d) This device consists of
two concentric cylinders with elastomer seals between them. The outer cylinder
is attached to the tubing string by a threaded coupling. The inner cylinder is
latched into the packer with an anchor seal assembly as described above. The
typical ELTSR is 10 30 ft long.
" Travel Joint (Figure 12e) This device is very similar to an inverted ELTSR.
" Polished Bore Receptacle (PBR) This completion component simultaneously
provides both an annular pressure seal and a locator seal which permits tubing
movement. The PBR consists of a receptacle with a polished internal bore (Figure
12f) which is run on top of a production liner with packer. A seal assembly can
then be run on tubing and located inside the PBR.
26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

25

Petroleum Engineering

4.5

Sub-Surface Safety Valves (SSSV)

The Christmas Tree's production wing valve and master valves are used for well
isolation or closure under normal operating conditions. The advantage of these valves
!% % ,
    & 
&* %  & 
,% ! $ $ !  % 
primary closure system for the well. Well security is endangered in the absence of
an effective surface closure system. This can occur during:
(1) Xmas tree removal during workover preparations to pull tubing
(2) Removal of valves or valve components for servicing
(3) Accidental damage to Xmas tree
Y\ @   % * % &_K ! [  ! !
'$ $ !%[* !
 &  %% * % & ! %  !,! 
This Sub-Surface Safety Valve or SSSV is required when the Christmas trees valves
are not operational. These valves are based upon two different control philosophies:
(1) Direct Controlled SSSV which are designed to close when downhole well

&  ! !! >[*  $ , ! & ! $  !% ! $ $ !  


often refered to as "storm chokes".
(2) Remotely or Surface Controlled SSSV (SCSSSV) whereby closure and
opening of the valve is actuated using a surface control system which feeds
hydraulic pressure directly to the downhole valve assembly.
Both valve systems provide a failsafe shutdown system for remote sub-surface isolation
e.g. in the event of a catastrophic failure of the Xmas tree.
" Remotely Controlled SSSV This is the more widely employed and more
    %&% $ $ ! , ,%,& 
 !! ;! &
the downhole valve by a small 1/4" monel control line run in the annulus and
!  &%  ;@ % $ $  % $ $  !  ! , % 
  [  , Y  ! &\& $
* !   $   
deploying and retrieving the valve:
" Tubing retrievable The valve is run as an integral part of the tubing string. It

,   $ &, %  % [* %


% $ % !  
&    !%  '!  [*&   *      $  $ $ 
 
!  & % % $ $ % ! *!* &
 
  ;%%
!! ,  *   ; %    $  $   !
" Wireline retrievable The valve nipple is run as an integral part of the tubing
the internal valve assembly being subsequently run and retrieved on wireline

 % [* %% $ $ * % $  !    % % &


 
tubing. It should always be evaluated if this will restrict production at some time
in the wells life. (This is especially important for gas wells).

26

Production Technology

Conventional Completions O N E

Pressurised
control line
Landing
nipple
Sheer pin

Depressurised
control line

Snap ring
Shifting sleeve up

Shifting sleeve
down

Spring
extended

Spring
compressed

Ball

Spring
extended

Spring
compressed

OPEN

CLOSED

Figure 13 Ball type Surface Controlled Sub Surface Safety Valve.

Open

Pressurised
control line

Depressurised
control line

Shifting
sleeve down
Spring
compressed

Shifting sleeve up

Flapper
open

Flapper
closed

Spring
extended

Closed

Figure 14 Flapper type Surface Controlled Sub Surface Safety Valve.

Annular safety values are installed at shallow depth for cases where it is required to
minimise the volume of annular gas released if wellhead assembly is damaged. This
is typically installed in offshore wells where gas lift is installed or where a downhole
packer has not been installed. An example completion is illustrated in Figure 28.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

27

Petroleum Engineering

4.6

Production Technology

Side Pocket Mandrel

The side pocket mandrel (Figure 15a and 15b) contains an off-centre pocket with ports
%  !'$ $ ;*%
%
!% [ &[* *   & !;

  !  & % 


@ %  *![ &[* *   & !
" Gas lift valves  !  ;!%% %  ![* * %  !
and the tubing at a preset pressure at valve depth. They can either respond to
the pressure of gas injected into the annulus or to the tubing pressure {see also
%  ;Y ! \% ?&
 
%,& 
" Chemical Injection Valves *%  <
 &
 
% 
!;!
% !

!  %  !; &  !! !; 


; %  % $ $  !
opened when the annular pressure exceeds a preset value.
" Circulation [ &!%  ! %   !
% $ &, !  
a valve with a bursting disc which can be sheared. Communication between the
annulus and the tubing can only be stopped by replacing the shear valve by wireline.
The installation and recovery of the valves from the side pocket mandrel is also
described in Chapter 5 (Gas Lift) of the Production Technology module.
(a)

(b)
Orienting Sleeve

Cross section of Side Pocket Mandrel


with gas lift valve installed in pocket

Seal Element
Polished bore
Tool Discriminator

No restriction
to tubing
access

Valve Body

Polish Bore

Valve body
Pocket Assembly

Figure 15a and 15b Side Pocket Mandrel with valve installed.

28

Conventional Completions O N E

4.7

Sliding Side Door (SSD)

The sliding side door (Figure 16) permits communication between tubing and annulus.
+
! !!*


! $ !;
  !!% !;* %  ! 
! !
between them. The inner sleeve can move up or down by wireline or coiled tubing.
This movement aligns the inner and outer openings. Its main application is to provide

!!%   !   


  ! &
 [ &! % 
tubing or annulus by circulation (often for well killing).
The SSD's design features external ports through the tubing wall within which is
located an inner mandrel with slots and seal rings above or below the slots (Figure
\`% 
! &;%    & ! $  !
 &!
%% % ! % 
outer tubing wall are isolated by seals above and below on the inner mandrel (Figure
16b). Movement of the inner sleeve upwards (Figure 16a) allows circulation between
the tubing and annulus by aligning the slots in the inner mandrel with the ports in the
outer tubing. Moving the inner sleeve in the reverse direction returns the circulation
device to its closed position after completion of the circulation operation.
Movement of the inner sleeve requires the running of a shifting tool to open and
close the sleeve. The shifting tool lands in the top or bottom of the inner sleeve and
,<  ;% ! $ 
 $ &&* ,$  % ! $ 
cannot be accomplished if a extremely high differential pressure exists across the
sleeve. Any number of sleeves of the same size can be run in the same completion.
 &!  %  !     %  
  *  & $   & %   !   

jarring can cause failure to close the sleeve. A separation sleeve can be run which will
land inside the sliding sleeve and seal in the seal bores above and below the slotted
section of the inner sleeve when it proves impossible to close the sliding side door
as described above.

Sliding (inner)
Sleeve
Seals
Ports on SSD body

Circulation
permitted

Circulation
prevented

Seals
Inner ports

a) Open

b) Closed

Figure 16 Wireline Operated Sliding Side Door.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

29

Petroleum Engineering

4.8

Production Technology

Landing Nipples

' &   Y  \ ! !%; 

!,* %      *%


%
can accommode and secure a mandrel run into its bore on wireline or coiled tubing.
It provides a:
"
!!
% 
,
@%  &  
!  !  ] &  @ ,!
" ? !! !  * %     %    &%  !
% 
mandrel.
%   %    !  & >
@    & !   *%
%% 
mandrel (a plug or other equipment) may be selectively installed.

Selective Landing Nipple

Mandrel with correct profile


locked in place

Pressure Equalising
Sub allows retrieval
of mandrel

Subsurface
Flow Control
valve

Figure 17!
[*
 &  ! 
 $  &   

Nipples are installed at various points in the string to allow:


Y\+!       %    !   *  !% ; *@$   
hydraulically setting packers.
(2) A ported device which allows communication between the tubing and the annulus.
Y\#  
,
! %    [*
& ,  & 

control.
Y\*%    % % [*

30

Conventional Completions O N E

(5) The installation of downhole pressure and temperature recording gauges.


The landing nipple maybe selective or non-selective. A selective nipple will only allow
the corresponding mandrel to lock into place e.g. seven or more different mandrels
of the same size can be selectively landed in the correct nipple installed in tubing.
There are three methods of obtaining selectivity in a landing nipple system:
Y \ 
 $ , ! & $        
(b) Selectivity associated with the setting tool.
(c) Selectivity based upon pre-spaced magnets.

4.9

Perforated Flow Tube

%    &< Y   \ *![*  % !  $  %  ! 


% 
@     ! &,;! ,; !!   !

4.10 Flow Coupling


 ,%  

!! !;  &   !; !  &* %   ! ;
* 
!   !
 [*% 
$  
 && $  
 
! !!
 &
with entry to and exit from the nipple system will cause increased turbulence. This
turbulence can lead to substantial abrasive erosion of the tubing wall and nipple
system. Flow couplings (Figure 18b) are installed above and below the nipple to

 ![*! %  & $
!% ,% $   
 ! &* %
@ !! !  ] 
allowance for erosion.
(a)

(b)

Flow Coupling
with increased
wall thickness

Turbulence
generated
by landing
nipples profile.

Landing Nipple

Flow Coupling
with increased
wall thickness

Figure 18 \?   &[* \*


 

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

31

Petroleum Engineering

MULTIPLE ZONE COMPLETIONS

$%
&
Multiple zone completions are employed for reservoirs where more than one distinct
 ! $   ,  !  !
 & ,  !   *  & %   ! %    ;    
 =   ;&
 <
 % !  , !!    ,#
% ! $ 
% !;,&   ; !* !!     &;  ! ;% * !_^ _

and Water-Oil-Contact.
% 

 %  ! ! $   , ] !!   ,}* $ ;&

  !
  
! &  &!  &; &% &
  ,&  &!
%  ] *%
%$ 
[*

!  & ! $ !  


  &,
%  !
in depositional conditions resulting in layers having a variable degree of vertical
permeability. Each of the producing layers has to be treated as a separate reservoir if
a very low vertical permeability exists between the separate the layers.

5.2

Multiple-Zone Depletion Concepts

"   % *$  ! ! *%


%[ & % 
 ! $  !   !, [*!   !     !   *  !
producing up a single tubing string.
" Segregated, Multi Zone Depletion: multiple production conduits are installed
within the same wellbore. Each tubing controls the production of one reservoir.
" Alternate Zone Well Completion Strategy: each well is completed on more
%   ! $ }* $ ;,  ! $  !&
&  ! 
at any particular time. The advantages and disadvantages of each of the above
techniques is discussed below.

5.2.1 Co-mingled Flow


Advantages
" %   * ! &% 
   $ ! ; !   ! &! 

%
well provides a drainage point in every reservoir
" %  &
    ] 
%  ! $  !%&   
% & =
@, ! 

the amount of drilling is minimised and so is the number of wells and the time
required to execute the drilling programme. i.e. production should be accelerated
compared to the other optional strategies

Disadvantages
" %  ] &
&[ &! % *  
 & ! &$   ! [ &!
from one or more of the reservoirs have any of the following characteristics:
1 Corrosive or potentially corrosive materials 
&!;}2;^2.
2 Produced sand has an erosive effect. The implementation of sand control
procedures may be more complicated.
3  
  
 compositions and hence differing economic
value.
32

Production Technology

Conventional Completions O N E

4 
       
  % !*  [ 
% $ 

lift performance of the total well system.
" Variation in individual zone pressures and permeability can lead to a back pressure
effect on the less productive or lower pressure reservoirs.
"   ! 
   " 
#  
$  %
 
 " 
Only the total well production rate can be effected by choke control.
" &
$ "#
  
'
 !   [ &!
 ! ,
be diverted into individual layers without temporary isolation using sealants
(diverters) or bridge plugs.
" A change in the production characteristics of one zone e.g. water coning and the

! =  
 !  `^*  [ 
%  &
 % * 
+ , & 
  &,* %
!  % * 

5.2.2 Segregated Multiple Zone Depletion


Advantages
" % &
    &&  [*
% 
  &  & ,
controlled.
" %  !  %  &
 
% 
  !
!      *   [ 
 % 
others.
"   , !    &  *@  & $ &   !
  

 !% &
* % * ,! 
 % &
 %  !; 
 != ;
    ; 

"  
 $    
%  !!!  
"  !&     
%  !!!  % ! !! !!    
balance or reservoir simulation studies for reservoir management.

Disadvantages
" #
%  =  ! !* !  
 ! %  %&
 
tubing and other completion equipment required. This requires an increase in
% 
   ] &  ;%  & $ & *  !      &  
 !  
the total time required to complete the drilling programme.
" %  
% 

 ] ,  % 
   ! 
 ! &    = 
equipment malfunction can be expected during installation and in the future.
" %  &
& ! !
% 
  !
 _ 
  ! , &

%  [*

,% * 

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

33

Petroleum Engineering

5.2.3 Alternate Zone Well Completion Strategy


Advantages
" #
 $ 
  !
! ! $ &    &* 
 !$ & &
" ` 
    ! ! ,
%  &  %  &    !  , !   &; 
changing a well from production to injection.
" ? ! 
  & * &
!!  , [ 
% 
  ,
% &
 [ &%  ! &* !
" #
%*  !
% 
,   $ ,!     ! %  !@  & 
to complexity.

Disadvantages
" '   * !% $  &  & &
  &
% $ % !  
degree of depletion control and reservoir management. The same reservoir drainage


,* , 
% $ &, !!  , 
 ! & && $  
cost.
" %  &!     &%!%  &
 
!!;*   
 ! & !!
the number of wells is increased.

5.2.4 Selection of Development Strategy


" Offshore or Onshore Development
Offshore developments have a higher well cost and a reduced number of wells
compared to comparable onshore developments
'


*

+;

#
<
The installation of complex multiple completions is problematic in high angle
* ! &
 &! 
& 
 ! & 
 ! ! % &  
!
excessive lost time while these problems are corrected.
'

=

>
#
#?

@ 
K>
 %     
!   !  , %  &
& [ &! *  [ 

% , 
  + &&  ;% &  *%
%% & *&* 
  %! !!&
 %  ! , [ 
% 
%

completion:


34

+ &&  ;% [*  


%  %    & !  
 ! % !  !  &;
! 
@!
* % % *  
a multiple tubing completion.

Production Technology

Conventional Completions O N E

$Q
U  
<
K; 
K"
` !
 
 ; 
  & ,  !* % % !  * 
bore by simply increasing the amount of completion equipment installed to provide
!   & [*

   ,%    !  !  %  !   *   
  &
   ! 

The inherent advantage of the single wellbore completion are lost as the number
 !% % 
 ] ,; &% 
%    
 ; 
 ! !
The optimum number of zones to be produced into any wellbore will depend on the
 ! $  Y  %  &
    \; %  *  & !  Y  %  & $    \ &
the expected problems (e.g. completion component failure and expected operational
problems throughout the well's life).

5.3.1 Dual Zone Completion


There are a number of ways in which completions can be designed to produce two zones
Y  \ ! & !
_  &[* & & $ & * > 
  %    {

Casing/Tubing Flow
In this case a single tubing string is run with a single packer installed to provide isolation
between zones. The lower zone will produce up the tubing whilst the upper zone will
&
% 
! _  !% & 
,* %% !, 
   !
% &   [*
&  ! * % $   $  ! % !
!!   
  !  ,$ $ '!% &
&[ & ! 

* %% 
!  & 
 ,%!
! &   ,
!   ! + &&  ; !!     !
the annulus with respect to casing burst may preclude stimulation of the zone which
produces via the annulus. These issues can be addressed by:
" ("" %
 

   &*%  %   [ & !_
! $ ;
non-abrasive and where casing pressure limitations do not preclude stimulation.
" ) %
 

  this design can be considered in situations where the


  *& !     [*% *    [*
system requires one long and one very short tubing and two packers and a crossover
% !& ! %* $ ;  !

!!% ! ;    




26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

35

Petroleum Engineering

Production Technology

(a) Upper Zone Annular Flow

(b) Lower Zone Annular Flow

Nipple

Sliding side door for


upper zone production

Sliding side door for


upper zone production

Nipple

(c) Single String Selective

(d) Dual Tubing

Figure 19^ !!   && ! ;* 


  * %
  

'
&
!"
 % !
  % ! !     ! 
% + =  !*
@ !;
one to isolate between zones and the other to isolate the upper zone from the
upper casing annulus. The depletion of each zone can be accurately monitored
&
 &+ &&  ;%  <
 [ &! 
%  !   &,
,%  & ! 
   % 
   ! ! !  &%  

&
  * [ &!%   , 


 % % % 
   
   !%*   &'


  *!   
 [*% &
&[ &!Y  $ 
! ! \ =  !  
complex running procedure.
" Single String Selective
 % *  !
  &* !;* %  ! % % ! & !  &
to selectively allow the production of either zone or to commingle both zones.
% 
   =  !*
@ !;  !   *  ! &% % 
 !  %  !+ &&  ;  ,  ! =  &[ &% 
upper zone to enter the ! % !
   & &
! & !& !  &;  
sliding side door (SSD). Finally producing the upper zone into the tubing closure
of the lower zone may be accomplished by setting a plug in a nipple at the base
of the tailpipe.

36

Conventional Completions O N E

5.3.2 Completions for Three or More Zones


The options discussed for dual completions can be extended for wells to be completed
with or without some degree of zonal co-mingling on three or more zones.
Thus for Triple Zone Completions this can be accomplished with either:
" %  ! 
    ! !     [* &% $ % 
packers for isolation.
" *! 
  ;*%  ,[** ! !
_  &  
the tubing strings.
"      [* &* ! !&
!    ,*
zones.
" *! 
  *%   % %% ! !  
  & *
selectively production from two of the zones. This requires two tubing strings
and three packers.
"   ! ;   ! 
 $ 
  

5.4

Multiple Completion Equipment

+      !; =    =   !    


  !     ,
based upon the equipment available for single string completions with the following
exceptions:
"  %  !,! !
"  
@ !,! !
" 
 ! & !    =  
Obviously the number of tubing strings will affect the completion procedure. The size
of the tubing and ancillary equipment will be dictated by the limitations imposed by
% 
!  ! & &   ; !   & &= 
    !*  ,  
! 
  
   

5.4.1 Tubing Hanger Systems


The simplest way of landing multiple tubings in the tubing head spool is to use a
segmented hanger (Figure 20). Each tubing string requires a hanger segment. Upon
 &  %  ! !;% %  !!%& 
!  

 %  
which also seals the annular space in the landing seat within the tubing head spool.
Normally each hanger segment is made up with a short (or pup) tubing joint above
and below which is attached to the rest of the string. The tubing strings can either be
run independently or simultaneously.
Provision must also be made for the control lines for each tubing string and valve
system when using a surface controlled sub-surface safety valve.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

37

Petroleum Engineering

Figures 20 Split dual tubing hanger

5.4.2 Multiple Tubing Packer Systems


   !,! !*  , =  % ;%  
@ ! = !% 
  ! &
&*
@ !*   =  & &  ;& 
tubing completion. The lower one is a single packer whilst the upper will be a dual

@    ,;% 
@ !*   =  &;
 !  !  ;&  &   

@  %  ;   
  
Similar types of multiple string packers are available as these described for single string

@ !;  % ,
  %      $  + &&  ;% ,
 ! 
!  %,& 
 
% 
!  
& % *    !  
& ;
! = ,! &! % * ;!  ! 
@ 
Although in most cases it is preferable to run retrievable multi-string packers since it
 &! !   $     &, 
 ]*@$    ;   
packers are available and may be required in high pressure wells or wells where
! 
   $   & ! !! ! 
  & %  !   
&  
the packers must be such to allow pressure testing of all tubing to be carried out
independently before initiating the packer setting procedure.
All multiple string packers must offer a means of connecting tubing both above and
below the packer for each string. In some cases mechanical attachment exists e.g.
 !
 * &%  ! % 
@ *% !; % 
! !;% 
@  !
a seal bore.
The tubing strings will have different lengths in multiple string completions in
,
   $$   ! !% ,  &  & !% ! ;% 
intermediate string and the short string. This terminology is crucial to the running
procedures for the completion e.g. a packer may be run into the well on the long
! *%
% ! & &; & , ! ! %,& 
 !!  % ,% 
! ,% !%!    % ! ;
 & % 
@ !   &
landed off in the tubing hanger.

5.4.3 Blast Joints


The long string in a multiple completion is located in the casing opposite the perforated
!
 ! &
 !% & 
 [ &[*%%%    !
% *   ! ,  &
 % *  ] ! &% [ &[*! 
!=
@,
%  %%[*%  % [ &   % *  
38

Production Technology

Conventional Completions O N E

Y % %$ 
, ![*\ ,% $  ! 
 

%  * 
% ! ; & %,& 
 ! %  !   * & !
, 
 ! 
! &% ! &  !   &
&
'%
@*  & !
 @* !  !< ; ! , 
& & % 
string opposite the perforated intervals of the upper production zones to compensate
for the increased rate of erosion.

WIRELINE SERVICING OF COMPLETION ACCESSORIES

The majority of well completions with "dry" wellheads and deviation angles < 65
use wireline techniques either to operate equipment in the well or eliminate the need
to pull the completion string and replace components which have failed. Typical
wireline applications are the:
" +!    
   =        %  &
   
e.g. a packer and a tailpipe assembly.
" +!       $   =   * %  %    !   $ $ !;
 !!   !; 

" ^   &*%  =   % & $ !%[ &[*  
a sliding side door or install a bridge plug
" $    !;*%
%% $   %  ! ;!
% !* ]
sand.
" '&<! % 
    $     
`     $$ !*    %    !


 % 
!  ! !! & & %  !  ! &*  ;  & &

     % ! ; % , ! *  ;*    
jarring effect on the tool and activate the setting or retrieval mechanism that will carry
%  =  &
 '   $ ,; 
 * %  


&
    
an electric signal can be used to initiate the required action.
!   *     * ;   ,
! !;    =
@ ;  

    $ 
to mobilising a drilling or workover rig to pull the tubing string to replace faulty
=  }* $ ;% *       % !
 !%,!
,$ ,  
from the downhole location where the tool must operate. This remoteness coupled
with the uncertainty of cable stretch (especially important in deviated wells) and the
small scale of the tools makes wireline a technique which requires highly skilled
 !   
 $ }* $ ; 
  *       & =   
% 
  ! & ! $ & !  
 ! &&  [ ]   ,  !
well operations and servicing capability. Electric line allows real time information and
measurements to be conveyed to the surface operator. This means that the equipment is

%  ] ! $  &%   !! % %,  &}* $ ;%  ! 
!

 
% $ !%   =  &,%    
$  ;!
@;
wireline unit.
26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

39

Petroleum Engineering

Production Technology

Wireline's greatest asset is the ability to conduct operations on a "live" well i.e. one
*%  

  ] !! * %  ! $ ;% *   &% % 
tubing. Hence pressure is present at the xmas tree during a wireline intervention and
the surface wireline equipment must allow:" *  % ! % Y&*% \*@
  & !!! = 
retrieval.
"   % !   &% 
  ! 
" } &  &    ,!!% % 
 &% ! 
 
positioned vertically above the well prior for lowering through the Xmas tree
and into the tubing string.
" %    , ! % !  %  $ *  & $  !! ! &
* [ & !
  %  $  
" '* $ *%
%* ! %  ! &% 
  &; 
 =  &;
% *    
The components of a conventional wireline system are shown in Figure 21.
Pulley
Stuffing Box
(Pressure Seal Around Wireline)

Lubricator
determines
maximum length
of toolstring
that can be inserted
into well

Lubricator (or Pressure Containment System)


consists of one or more tubing joints
Lifting Clamp

Portable Hoist
Wire
Lubricator Pressure Release

Blow-Out Preventor
Connection to Xmas Tree

Odometer
measures length
of wire inserted
into well
to Wireline Drum

Load Cell Measures Wireline Tension


Xmas Tree

Figure 21 Wireline Surface Equipment mounted on Xmas Tree

40

Conventional Completions O N E

6.1

The Wire

$   *    ;!


@*    ;  ! ! !  ! &*  % *  
is normally made from high tensile steel so that the ratio of breaking strength (lbs)
to wire diameter (inches) is maximised. The minimum cable diameter is normally
used to reduce the weight of wire while still achieving the required breaking strength.
The wireline is normally wound onto a reel on a self contained skid which has its own
power supply for drum rotation and measurement of cable length and tension (Figure 22).

Work Platform
Wireline Unit

Portable Hoist

BOP Control
SC-SSV Control

Hydraulic Power Unit

Figure 22 Wireline Surface Equipment

6.2

Surface Monitoring Equipment

The important parameters that the wireline operator must be aware of at all times
during well operations are the tool string location (depth in the well) and the tension
on the cable. The length of cable in the well gives an approximate depth for the tool
string. It is measured by holding the cable without slippage against an odometer (a
wheel with a device that counts the number of rotations) as the tool string is lowered
into the well (Figure 21).
The cable tension is continuously monitored to ensure that the breaking strength of
the cable is not exceeded. The cable tension will:
" &
 !% !  !*  &%% !
  %  ! & 
 [ &  !!  } 

   ! 
 

  ,  $   ]   
indication of tool position.
26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

41

Petroleum Engineering

" +
 !  !% !  !*  & % * & %  
 ! * %
the wire. Hence it will also decrease during recovery of the wire and tool string.
" +
 ! Y  &,\ % ! % !_ !
%, &*% 
restriction during recovery of the wireline.
" $ ! ,; &  !    %   !   %  * ; %   !  * 
reduce when it does not fall easily down the well due to increasing friction or a
downhole restriction.
The maximum well deviation angle for conventional wireline operations is 65 due
to the increasing friction of the wire and tool string against the tubing and production
casing or liner. Wireline servicing of such wells requires use of an electrically driven
tractor that pulls the tool string into the well. Tractors allow servicing of wells with
deviation angles greater than 90; but they require substitution of the slick (solid) wire
by a (more expensive) electrical cable as well as hire of the tractor itself.

TUTORIALS

7.1

Well Completion Designs

%     !* 


  & ! !; !  ]
 &% * &   
     ! &*  $  !% $  ,& ! ! [
{
"





Well characteristics such as:


" ? !! 
" ?&
 $ , <
 $ , & ]
"  &  !
" 
@  ! & 
&  

"





Geographical factors:
" 
 
" `  & %Y !% \
" ` % 
&  !
" '

!!   ,

" Operational design constraints:


 " #$      !
 "   , !
!
" The number of producing zones.
A number of typical completion types are presented below. These designs have
been chosen to illustrate functional similarities and differences in a range of well
environments. They are all based on the concepts discussed in this chapter.

42

Production Technology

Conventional Completions O N E

COMPLETION NO. 1 (Figure 23)


This completion features VAM tubing with an anchor seal assembly latched into a
permanent packer. The VAM tubing is required due to the production or injection of
gas with relatively high closed in surface tubing pressures. The permanent packer
would have been made up with its tailpipe and run in and set on drillpipe or with an
electric wireline cable. The absence of a moving seal assembly indicates that little
expansion or contraction will occur or that the need for good differential pressure
sealing integrity is paramount.

Hydraulic Control Line


Surface Controlled Sub Surface
Safety Valve
7" Production Casing
3 1/2" VAM Tubing
Wireline Operated Sliding Side Door

31/2 in 'X' Nipple

Anchor
Permanent Packer Seal Assembly
Millout Extension (Required for packer retrieval)
Crossover 51/2 in x 31/2 in
31/2 Hydril EU Tubing Tailpipe
31/2 in 'X' Nipple
Perforated Flow Tube
31/2 in 'X' Landing Nipple
Wireline Entry Guide

Figure 23 Single zone completion with no provision for tubing movement.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

43

Petroleum Engineering

Production Technology

COMPLETION NO. 2 (Figure 24)


This design allows production through a tubing string with a moving seal assembly
located inside a permanent packer. Additional features include two nipples located in
%    ;%    !!  !   %  !  !  $ & &
the lower one for landing bottom hole pressure survey gauges.
Production Casing
Hydraulic Control Line
Surface Controlled
Sub Surface Safety Valve

Production Tubing

Nipple
Wireline Operated Sliding
Slide Door

Locator
Seal Assembly
Permanent Packer
Seal Bore Protector

Packer Millout Extension


Cross Over to Smaller Tubing
Nipple

Perforated Flow Tube


Nipple
Wireline Entry Guide
Production Liner

Figure 24 Single zone completion utilising a locator seal assembly.

44

Conventional Completions O N E

COMPLETION NO. 3 (Figure 25)


This design allows high production rates since the large bore tubing minimises the
frictional pressure drop in the tubing. The packer and tailpipe can be set on electric
cable or coiled tubing and the tubing string subsequently latched into the packer with
an anchor seal assembly at the base of an extra long tubing seal receptacle. The range
 $   !,
,?&
   !;;>&
or more are typical for this type of completion.

9 5/8" Production Casing


Hydraulic Control Line
Surface Controlled Sub Surface
Safety Valve

7" Hydril Production Tubing

Wireline Operated
Sliding Side Door
Extra Long Tubing Seal
Receptacle with Nipple and
Anchor Seals on the Slick Joint

Permanent Packer Wireline Set


Mill-out Extension

4 Hydril Tailpipe
Nipple

Perforated Tube
Landing Nipple

7" Production Liner

Figure 25} %[*   


  
with an extra long tubing seal receptacle for greater tubing movement.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

45

Petroleum Engineering

Production Technology

COMPLETION NO. 4 (Figure 26)


% !
   & !   % % [*   &
   <
  !     $ 
to Figure 23. It is referred to as a Monobore ! % !   ;   $ ,
! 
diameter from surface to the reservoir. This consistent diameter facilitates concentric
access and intervention. It utilises a polished bore receptacle at the top of the 7" liner
which seals against a seal assembly installed at the base of the tubing string. The seal
assembly provides a moving seal area to accommodate expansion and/or contraction
%  % !& ! %! ! 
 !^
& [*% 
* % &%    !'!!%*%  ;%   !
 , !   *
the PBR. This can be achieved by installing a packer and small tailpipe containing
a wireline nipple below the PBR. Circulation to kill the well is provided by a shear
valve in a side pocket mandrel instead of a sliding side door.
9 5/8" Production Casing
Hydraulic Control Line
Surface Controlled Subsurface
Safety Valve
7" Production Tubing
Side Pocket Mandrel Permits
Circulation After Instalation of a
Chemical Injection or
Shear Valve
Nipple
Seal Assembly
Polished Bore Receptacle
Liner Packer and Hanger

7" Production Liner

Figure 26    


  % %[*   <
 >
production using a polished bore receptacle.

46

Conventional Completions O N E

COMPLETION NO. 5 (Figure 27)


This completion provides gas lift to allow production to occur or to increase the
production rate. The string contains several side pocket mandrels containing gas injection
$ $ ! $  !& %!% & !   ! !   $  
@ ;     
%

if it is suspected that a completion will require mechanical repair at frequent intervals.

9 5/8" Production Casing


Hydraulic Control Line
Surface Controlled Subsurface
Safety Valve
7" Production Tubing
Nipple
Side Pocket Mandrels Provide
Subsequent Gas Lift Once Suitable
Valves are Installed
Nipple
Retrievable Packer

Nipple
4 Tail pipe
Perforated flow Tube

Nipple

7" Production Liner

Figure 27 Single zone completion with gas lift.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

47

Petroleum Engineering

Production Technology

COMPLETION NO. 6 (Figure 28)


% !
 ] & !  &
! [ ]   ,  % 
   ! 
  *! 
commingled production of both zones or for selective production from either of the
zones. Continuous gas lift using gas injected down a separate string. Gas injection
using the 2 7/8" tubing avoids excessive gas pressures being exerted on the production
casing (which mitigates a casing burst if the casing has deteriorated). The small gas
injection string and dual packer are also used in offshore situations when annular gas
pressure is not allowed. In this case the dual packer is normally set at a shallow depth.

4 1/2" Production Tubing


(x2) Surface Controlled Subsurface
Safety Valve
2 7/8" Tubing
Hydraulic Set Retrievable
Dual Packer
Nipple
9 5/8" Production Tubing
Gas Lift Mandrels

31/2" Production Tubing


Travel Joint
Locator Seal Assembly
Wireline Set Permanent Packer

Upper Zone
Perforations

Blast Joint

Sliding Side Door


Permanent Packer
Nipple
Wireline Entry Guide
Lower Zone
Perforations

9 5/8" Casing

Figure 28  ! ;! 


 $ ;&  &
!* % ! 

48

Conventional Completions O N E

COMPLETION NO. 7 (Figure 29)


This design features a downhole ESP installed parallel to a bypass tubing which allows

!!% &
  *% #? &
  !$ ,!; 

 %    $  %,& 
! 
@  !! &% ! &
!Y_\% & 
 !
in pulling the string should the pump need replacing regularly. The run life for a
large capacity ESP can be as long as several years but this depends upon installation


, &% 
     $    !%  Y'
 \
of the Production Technology module.
Junction
Box

Surface
Power
Cable

Production
Wellhead Incorporating
Cable Penetrator

Retrievable Hydraulic Set Packer

Production Tubing
(3 1/2")

Downhole Cable
Clamped to Outside
of Tubing
Y-Tool

Selective Nipple
Bypass Tubing (2 3/8")

Pothead Connection

Pump (5.44" OD)


Pump Inlet
ESP / Bypass Tubing Clamps
Motor (5.44" OD)
Pressure Sensors

Bypass Tubing (3 1/2")

9 5/8" Casing

Figure 29 Single zone completion with Electric Submersible Pump (ESP)

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

49

Petroleum Engineering

Production Technology

COMPLETION NO. 8 (Figure 30)


% !
     ! ! *   ! !; *  !    & &
  

% * % ! 
&   ! $     % * 
@  ! 
permanent packer and the longer tubing string is connected to it using a seal assembly.
%  
@  !   $  ;& 
@ ' =   !&
 &; *
!_!
!  ,$ $ !;*

  & $
!; 
%
@*  &< !@* !
Blast Joints are used to combat erosion on the longer string at the point of entry of
[ &%    % *  
9 5/8" Production Casing
2 x 1/2" EU Tubing
2 x Surface Controlled Subsurface
Safety Valves
Crossover 3 1/2" x 2 7/8"

2 7/8" EU Tubing

Nipple
3 1/2" Sliding Side Door
Nipple

2 7/8" Sliding Side Door


Tubing Latch and Seal

2 7/8" Nipple
2 7/8" Tubing
2 7/8" Nipple
2 7/8" Wireline Entry Guide

Upper Zone
Perforations

3 1/2" Blast Joint


Nipple
Sliding Side Door
3 1/2" Locator Tubing Seal Assembly
Permanent Packer
Crossover 3 1/2" x 2 7/8"
Perforated Tubing
2 7/8" Tubing
2 7/8" Nipple

Figure 30 Dual completion with segregated production.

50

Conventional Completions O N E

COMPLETION NO. 9 ( Figure 31)


% ! ,  
   ! % !   &    $ ,
%  }* $ ;  ! !
%  !
    !& !
!! &  +% !   & !   !; 
%  && # ! &% '*%   !  ;&  &  
  !% $  
!  &  !%  Y'
 \ % ?&
 
%,& 

Production Casing

Nipple
Direct Controled Surface
Controlled Subsurface Safe
Upper Zone Perforations
Wireline Isolating Nipple
Borehole Wall
Direct Controled S.S.S.V
Lower Zone Perforations
Cement Sheath

Figure 31 A "Tubingless" dual completion.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

51

Petroleum Engineering

7.2

Production Technology

Completion Tutorials: Spot The Errors.

Indicate the correct position of the accessories shown on the completion below (Figure
\  
 !% !    $ & &!% ,
& *% !  
and then compare it with a solution on the next page (Figure 33).
Depth
0
100

Tubing hanger

Sliding Side Door


Blast Joints

600
758

Landing Nipple

1055

Landing Nipple
Control Line

9 58 Casing

3 2 Production tubing
Surface controlled
sub-surface safety valve

2000
2550

20 Locator seal assembly

2562

Permanent packer

2610

7 Liner hanger
2632
2774

SPM

Side pocket mandrel

Sliding side door

Landing Nipple

2784

Wire line entry guide


2992

HUD (Hold Up Depth)

Figure 32 A completion with several errors.

52

Conventional Completions O N E

Depth
0
100

Tubing hanger

Sliding Side Door


Blast Joints

600
758

Landing Nipple

1055

Landing Nipple
Control Line

9 58 Casing

3 2 Production tubing
Surface controlled
sub-surface safety valve

2000
2550

20 Locator seal assembly

2562

Permanent packer

2610

7 Liner hanger
2632
2774

SPM

Side pocket mandrel

Sliding side door

Landing Nipple

2784

Wire line entry guide


2992

HUD (Hold Up Depth)

Figure 32 A completion with several errors.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

53

Petroleum Engineering

Production Technology

Depth
0
100

Tubing hanger

Sliding Side Door


Blast Joints

600
758

Landing Nipple

1055

Landing Nipple
Control Line

9 58 Casing

3 2 Production tubing
Surface controlled
sub-surface safety valve

2000
2550

20 Locator seal assembly

2562

Permanent packer

2610

7 Liner hanger
2632
2774

SPM

Side pocket mandrel

Sliding side door

Landing Nipple

2784

Wire line entry guide


2992

HUD (Hold Up Depth)

Figure 32 A completion with several errors.

54

Conventional Completions O N E

Depth
Tubing hanger

Surface controlled
sub-surface safety valve

500

3 2 Tubing
2400

SPM

2488

Side pocket mandrel


Sliding Side Door
Retrievable packer

2520
9 58 Casing
2550

Blast Joints

2562

2570

2580

Sliding side door


Landing Nipple
Permanent packer

2610

20 Locator seal assembly

2632

Cross over 5 x 32
2650

Landing Nipple

7 Liner
perforated flow tube
2665

Landing Nipple
Wire line entry guide

2774
2784
2992

HUD (Hold Up Depth)

Figure 33 A solution.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

55

Petroleum Engineering

FURTHER READING
 ?  ` !
 ,#
 & !;;`  !; &_
 ;  ? !% & , % `  ,  ! &  ,   !! 
TN871.2P487 1988 and ISBN 0 471 96938 9
 `      !  ,  ,;  ~     $  ! 
Petroleum Science. First Edition published by Elsevier in 2009. ISBN 978-044-53210-7 and ISSN 0376-7361

56

Production Technology

True Vertical Depth

Advanced Wells and Completions T W O

9000

10000

11000

12000

13000

41/2 Inch
7 Inch

14000

1500

TD 15.925 ft. MD
1000
1000
1500

500
2000

Ea

st

(ft)

t)

2500

500

(f

rt

3000

1000

3500 1500

Production Technology
26/06/14

Petroleum Engineering

Advanced Wells and Completions T W O

C O N T E N T S
1 INTRODUCTION
2 HORIZONTAL WELLS
2.1 Horizontal Well Trajectory and Build Radii
2.2 Extended Reach Wells
2.3 Geosteering
2.4 Horizontal Well Completion
2.4.1 Smart/Intelligent Wells
2.5 Well and Reservoir Performance
2.5.1 Flow Regimes
2.5.2 Reservoir Drainage Area
2.5.3 The Well Productivity Improvement Factor
   !}  ` !
2.6.1 Increased Exposure to the Reservoir
2.6.2 Connection of Laterally Discontinuous Features
2.6.3 Changing the Drainage Geometry
2.6.4 Extending Field Appraisal Laterally
2.6 Disadvantages of Horizontal Wells
2.8 The Economics of Horizontal Wells
2.8.1 Costs
  ?    ,+&
!
3 MULTI-LATERAL WELLS
  +&
    !
 
!+[ 
% ?  '
 
Multi-Laterals
3.2.1 Multi-Lateral Interference in the Reservoir
   _   +   
 % ` 
3.3 Impact on Recovery and Rate
3.4 Initiation Methods for Laterals
3.5 Principal Multi-Lateral Geometries
   ! _   ` !#


Technical
3.6.1 Application of Multi-Lateral Wells
3.6.2 A Multi-Lateral Well Example

Production Technology
26/06/14

Petroleum Engineering

Petroleum Engineering

LEARNING OBJECTIVES:
Having worked through this chapter the Student will be able to:
"  !
  % 
%, =  &&  ;!   &
  %  
wells.
"  !
  %  
 %  * !
" & ! &%  !
! _   
%, & !%  
 !

Production Technology

Advanced Wells and Completions T W O

INTRODUCTION

#]   &&


   & !% $   ! &$ %  ! , !
, ] ! $ & $  ! * !,! ! &
%,   &
  

%, % !  &  !!    * *  !%  ! %  % $  
 ! & %  

,
 &
 % &    &$ 
&
  ! 
 !! ! , *

% !%  ,   & & $ & , 
   {
"
"
"
"

}  * !


#] & &
% & & * !
 _   * !
+   Y! \* !

True Vertical Depth

This chapter discusses the application of advanced wells to enhance the exploitation
  & ! ! $ !
%* !   !@* !
$   * !; 
% 
! 
 ] <
 !;%  & !  *  !!   !! &Y  \
% , ,%  $ &&  
%,% % !
  $    %  !
, !%  
  *!  
 ! &    , &  $ ! & % 
* %  && $  <
$ {

9000

10000

11000

12000

13000

41/2 Inch
7 Inch

14000

1500

TD 15.925 ft. MD
1000
1000
1500

500
2000

Ea

st

(ft)

t)

2500

500

h
rt

(f

3000

1000

3500 1500

Figure 1 A "Designer" well


26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

Petroleum Engineering

" '

!! % * !  

!!   ! $ !
" +
 ! % 
$ ,
>!*  

,
" +
 ! &* [*  !

% &$ 
&* !  
% 
  ! &, 
 ! &&  &! 
&% 
 !

 &      & !
  !% , =    ] ! $ !&,
Y & & \%  ! =  & &   * !! 
% {
" ` 
    ! 
 ]; =   

   ! $ & !
  
* % & =  &  
" !  !@!* %
! = 
  
,   ! !!  
" !!% $  * & !& &% 

  ! &

 , 
 !@!  !
,&  &
"    
,
 
!! * % !!   
  !; *@$ ! & !   
!  
& & % !

  ,! !
'&$ 
&
  ! 
 
  %%{
" &
& 
%
!
   ] &      &
&
" &
&    ] &      &
&
" '

   &    &&
  &_ & ! $ 
$ ,
"  *%  &  
% = ! $   %  ! $   ! %  &!
lateral limits.
#] & 
 ! &
%   !  ! *% !  &$ 
&
  ! 
& {
" +
 ! &
 ] , =  !   ! $  &    % 
%!  * 
design since the potential risks are greater.
"  *
! !   &
&*%    % ! * !
" * ;% %  * ! !!   
 ! &
 
 
  * % !
  @ &
 
%  ]    &$ 
&
  
%, &!  !  

!!%  ! % %     $ @* &  & ]  
* %
%   !  !       ' & &   ! 
    ! $  &
well details in the area around the proposed well is the foundation of this planning

!!%  !%&,
!&  ;
   & ,&
 
!%&
$ %   
,
 % * %%  & %  
!^* !% !%&    ! &, && !!  !  
  
!
%%% * !  
4

Production Technology

Advanced Wells and Completions T W O

HORIZONTAL WELLS

Introduction
}  * !% $ 
   ]  , & $   Y  \
% !
%   &
!%  !
!& !   &
   %  * ` 
 <
,; !  ; ! $ [*   ! &&     !  & !
!! &!
%  * !!   &  & ! &!
  % % % !% & !

% = % , *! !%    % &    &
  
% = 

Drilling and completion of horizontal wells

5,000

50,000

4,000

40,000

3,000

30,000

2,000

20,000

1,000

10,000

Cumulative Wells

Annual Well Count

% &
 
! Y 5/8 \ %  *  !! ,!   % %  Y
70\<! $ <!* % %  ! $  & Y1/2 \ % Y  \&  &
%%%  ! $ ' % 
  , &*% %   !   & 

 ! $ @* & %  
 ! &
!%  %  * % &  !
%   
!%  
 &%  !@!*%
%*      &
% 
 % % ! , $   &%  %  ! & &  & &  
$   ; %  *   & %   & %  ] & & %%  ! $   % 
  & % &  ,% * 
   ! !  &

0
1985

1986

1988

1990

1992

1994

Annual

1996

1998

2000

2002

Cumulative

Figure 2+
 !  %  *  !

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

Petroleum Engineering

Production Technology

Long Radius
Profile

Medium Radius
Profile
Formation Top
Pilot Hole
abandoned after evaluation

Target Reservoir

Figure 3 A horizontal well with pilot hole.

2.1 Horizontal Well Trajectory and Build Radii


The trajectory from surface to an entry point close to the reservoir is drilled using

$   &  


%,* %  & !Y-6> \ &_!
 
 $ % 

!    &*  %!% &  !& 
 &% * 
  !
&,%  ! $    %  &_ %  ! $ !
  

 ! ! &  & !Y-20> \Y  \%  ,  %  ! $ 
!
 &% %  &%   &% *  * , !
 &%  Y  \

Build Radius

Heel

Toe

Standoff

Figure 4 Horizontal well nomenclature

Hole Type
Build Radius for 90 turn (ft/m)
Long Radius
1,000-2,000 / 300-600
Medium Radius
300-800 / 100-250
Short Radius
30-200 / 10-60
Ultrashort Radius
1 6 / 0.3 - 2

Table 1 Build radii.


6

Oil
Water

Advanced Wells and Completions T W O

% *  ! = ,&  &    [ &



 ! $ >_ ! $ 

@
 !% $ 
& ! 
% 

 !
 &% ! & 
  


   % $ 
& 
 ,!  _*%  _&  

% = !%  ! % & ! 
 * %  &% [ &

% 
 ,
 !% %  !
 
   ]
!!%    !
! ,! , ! $  =   !;
  * 

!!
! &   !
! ,&  & 
 !}  !
 !% $  ]
& &@ ! 
&!%  % * 
  % @%  ,% !
* 

  % %  !
  !
  &* %#] & &
%
%, 
the upper section of the well.

2.2

Extended Reach Wells

#] & &


%* !% $  %  & !
 Y \~ 
& %  
  !{% 
  ] Y  \%  ] $  
% !  &  &!% {
" Vertical Depth. The highest ratios are achieved in shallow reservoirs.
" Drilling conditions    ! $ ! * % & 
 &  
&  !; % %
= *       !
% !  
" Equipment%  !% $   & =  & $  && *_*@!% & 
%  
 ! &! * % &= & 
" Technology capabilities%  <
,% * ! 
 ,
 &
#] & &
%* ! *   
%   ! $  

!! & 
&  
  ]  ;%  %  &!  & !
&
% $  & $  &* % !    % % % 
 , !  & 
] & &
%
%,% &  $    % !%      

! ! !!


 &* % ] & &
%* !{
" 
  & !@& %  
 ! & % &
 ] ,
%* 
" } %  $ !  * 
"    !%  $   &   
"       !
! &,% '} & ! 
%  ! $  &
the completion length with in the reservoir.
" *   &  $  
  !
 &,% *   , !!
"Smart Wells" are installed.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

Petroleum Engineering

Production Technology

0
5,000

TVD, ft

10,000
15,000

Extended Reach
Drilling Envelope

20,000
25,000
Horizontal Reach
= 0.25
True Vertical Depth

30,000
35,000
0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

Departure, ft

Figure 5 Examples of Extended Reach Drilling.

#] & &


%  % !
     , &!& !  % !     !+
has allowed economic development with very large "step-outs" in shallow reservoirs.

2.3

Geosteering

The successful drilling and completion of a horizontal well at the target location
depends on placing the well at the correct depth within the reservoir. The lateral
%    ,%  ! $  =  !% % *  <
, !
 $ , &<! &
!  _       !! 
%  ! % * !
 * % !

 %     [ & ,
 !Y  \% !!  
!! !
known as geosteering.
Shale

Sand
Water

Figure 6 Geosteering on a shale zone.

%  _     



 {
" Cuttings analysis &  !&    @  % ! ]  &   
!   %
% !* %   !! $ 
   ! $ 
  &  &,
examination of the microfossils. The cuttings will also differentiate reservoir
_ ! $ !  ! & !%*! &  ,[ &

!

Advanced Wells and Completions T W O

" "Logging-While-Drilling" (LWD) !  & ! ,;  ! ! $ , & %  ! 
&  ,
! & %,
%  ! !*  !& ! 
[ &

!
Example applications include
'
"




}  * !    ! $   !<

to severe gas cresting if any part of the well is close to the gas-oil contact.
^ 
 % * 
 =  %   !!   & !
&
& ! 
 $ %  _*  

% !
  
% $ &* % ! ! $ ,
tools.
'
"
 


> 

+ ! & !   ! % * <!& 
% !%  % ! !%  ! $  ! ! $ ,;   ,! ,!

  , &% 
%! &  & % !


&  !
'
"


>">
; 
 } %    ,! &!% $  * 
*  !   % *    ,! &!& 
  ,
!% !

  !  ! ! $ ,
 ! * % ! ! &! * % *  
 !  &%%% % %    ,! &

2.4

Horizontal Well Completion

Horizontal Well Completions are one or two orders of magnitudes longer than
conventional completions.
%  , 
 ! &
!% %  * !
  % ! 
! &  & 
* %%  
 ! &
 ] , &% % ?&
 
%, =   !; 
 &;  !  ;! 
 $ ,*   !!%_ &!   
   !*%
%  
 !& ,
 ]

%, !* $   
 $ 
      
 ! 
  *     &
  &  

!! 
!  *  %  * !^  

!! _   * !!  ! !


 
%  *  &
 

, &  &!  %   ! $ ! [*   
 % 
completion design and the wells production casing or liner diameter. The relationship
 * % ! 
! !!  ! &   
Well Capacity

Completion Design

Wellbore length
orientation etc.

Production Casing or Liner

Lift considerations

Reservoir

Mechanical
problems

Flow capacity
(diameters)

Excessive
water/gas
production

Sand
production

Completion type

Open hole

Perforation
productivity

Reservoir inflow
performance
greatly increased
by horizontal well

Natural

Formation
damage

Figure 7 Well Production Capacity.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

Petroleum Engineering

Production Technology

Sketches of three type generic horizontal well completions are shown Figure 8.
  !  ! !%  &$   ! && ! &$   !
System

Advantages

Disadvantages

Open Hole
barefoot completions
(Figure 8a)

- low cost
- large internal diameter

- risk of hole collapse


- difficult to abandon
- no sand control

Open-hole liner
completions
(Figure 8b)

- liner provides access for


wireline or coiled tubing
- maintains access if hole
collapses
- provides sand control if
wire wrapped screen installed

- isolation and
selectivity
problematic
- difficult to abandon

Cemented and cased


completion
(Figure 8c)

- provides zonal isolation


- allows multiple hydraulic
fracturing treatments
- can be completed as
a smart well

- higher cost
- achieving a
good cement bond
requires good
practices

Table 2 Horizontal well completion options.

Production casing shoe set in the reservoir


above the heel of the well
Open hole
section

Figure 8(a) Open hole completion.

Tubing tail pipe installed


partially along lateral moves the
point of maximum drawdown to the
centre of the lateral

Slotted or drilled liner or


wirewrapped screen

Figure 8(b) ^ %   


  * %Y  \ ] & &    

10

Advanced Wells and Completions T W O

Total flow rate measured by Multi-phase Flow Meter


installed near the Christmas Tree

Cemented liner with internal


tubuling along lateral

Interval control valve


adjusts zonal inflow rate
into the tubing

Packer separates zones

Figure 8(c) Selective completion divides the lateral into three zones.

2.4.1 "Smart" or "Intelligent" Wells


 * !   ,;
!!  ,;%  * ! =  &* %&*% 
   &

 &%  &*%  !  !Y 
    ; !! \ !  $    &
  &* %%  * [*  
 ! &,  _% ! *   !  & % 
% ! ! % &   !
 ,! & &%    ! & &<!%  [*
& $
!% !
&
 , 
 &% !
, *    >
  &   $  !% 
! $  % * % &*%    
& ! && 
,  

&*% [*
% !! % !,   @ 
%  & $  & ! * !% ! %   ! $     
 %   * ! ! $       % ! %  <
 $   !  %  % 
 ! $ !
%[*    
, ]
 &* %   *  &[ &!
Y *  \% ! =  !%    ,
!    &  $ ! &> 
 *   &  $ !%  %&!    &!   & ! &
!
  ! 
  &
! ! & 
$   $ 
* !   & 

%  * !  
 ! $     
& 

& % 
* *  & $ & &   !  !;
%*%
%
&   & &
controlled separately. It would also reduce the operating and processing costs as well
! &
% *@$  = 
, $ & %  
 ! & !@! &
!! !!
 &
* %
$   *@$  %&!{
'
!;"

Waiting for $    , =  ;


 *!;&    


'
K



',
! &&  !  Y 
%  \
 @ & ,! 
  !&   & '!!   !  *@$ 
  
  !  ] ! $ %   <

'
#?

^ !& $  & % *@$ 

'
K     %  *      
    =  ! &   
plugs etc.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

11

Petroleum Engineering

Production Technology

! Y!! ,& *  \ && $  !* % _       
[*     ?^Y! !
 % !& \% , 
  &
 
 , !* = ,
 ! &

2.5

Well and Reservoir Performance

2.5.1 Reservoir Flow Regimes


~ 
* !%   ,   &
!!%     ! $ !
 !%*  & 
[*   * %$ 
[** % %  ! $ Y   \%  * !
 ! !!  % [ &[*!$ 
,%  $ % %  * Y  \% 
well would drain oil from a horizontal layer whose thickness is the well diameter if
$ 
[** !!!  Y  @v\'%  * 
  &   & ;
homogenous reservoir whose width is shorter than the length of the well will show

!
 $ , & ;  ;! & &  &  ,%  !% 
[*   !

Top View

Top View

Side View

Side View
Vertical Well

Horizontal Well

Figure 9 Flow regimes for vertical and horizontal wells in a homogeneous reservoir.

2.5.2 Reservoir Drainage Area


%  %%  * % 
 &  & !
   % * !

 *  $ 
 * !' %   * 
 %    &  %  !     
$  !! $  $ 
* !;,
, 
 * * &$ 
* !
Y  \% ! ]
   &! 
  &, &
  ]  

  $  &; ! &  &!%  ! $ !
  &
  ,+
,
 &   $ ,@* %    &  & ; !* %   !

 
%  &!    ! $ !

(a)

Field Development with


5 vertical or deviated wells

(b) Field Development with


2 Horizontal Well

Figure 10 Horizontal and vertical well drainage areas compared.

12

Advanced Wells and Completions T W O

2.5.3 The Well Productivity Improvement Factor


% !   ! &;* &
 $ , & ]J !&  & !{

J=

Qhc
( P Pwf )

Where
Qhc  },&
?&
     & &&  !
_
P
= Average reservoir pressure in drainage volume of well
 % [*  !!  ! & !  &  $  ! P

Pwf

?&
 $ ,+$  
Y?+\ !&  & !%   % %  * 
&
 $ , & ]YJH\$ 
* &
 $ , & ]YJV\{

PIF 

JH
JV

Figure 11 shows the PIF value of a 500 m long well placed in a 15 m thick reservoir
as a function of the kv/kh ratio. At low k~/kh values the horizontal well performs more
poorly than a vertical well; while for k~/kh = 1 the horizontal well productivity is 4.3
times that of a vertical well.

5
4

PIF

3
2
Centrally placed
500 m horizontal
well in 15 m thick
reservoir

1
0
0.001

0.01

0.1

kv/kh

Figure 11% ?&


 +$  
Y?+\ %  * 
! 
 % $ 
 &%      ,  Y@$>@%\

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

13

Petroleum Engineering

Production Technology

[
\

]*
^ 
Horizontal well applications are summarised in Figure 12.
Increased Formation Exposure

Lateral Connectivity

Low permeabilty reservoirs

Layered reservoirs

Modified Drainage Geometry

High permeability sands

Reduced sand
production

Natural fractures

Hydraulic fractures

Viscous Oil

Fault blocks /
compartments

Enhanced gravity drainage

Vugular reservoirs

Oil rim coning

Reduce surface footprint

Reduce number of wells

Figure 12 Horizontal well applications.

2.6.1 Increased Exposure to the Reservoir


%  
 !    ! $  ]!   !   !  * * ,! + %  !%  
the production rate is higher and in the long term the cumulative production from a
%  *  !   $   ! $ ! * %!;%  * !
 =  &
% $   $   &
    &
$ ,
*   !!
  !  $ %   & 
&
 &  $ * % ;%  
* !
   %  &
    
   , $ 
 * ! %  ?+
Y  \* !&!%*  & !  {
"  ,% %  * !  !%* & 
 !  &
 
% & ;! @ ,?+;* !*%  %  ; $   ;?+* !'
minority of wells showed a PIF greater than 20.
" % % % !?+!*  ! $ &%  * !&
$ !
!Y% $,\
    $ ,% %    ,! &! &* ! *    ,
&!* %   
 

14

Advanced Wells and Completions T W O

300

Mode

203 Fields
1,305 Wells

250
200
Number of Wells

Log normal distribution


Mean

150
100
50
0
0

10

12

14

16

18

PIF

20

22

adapted from SPE 30745

Figure 13?&
 +$  
& !  %  * !

"  !% *   


 & $ & * !&  &  % 
&% !

!! 
!   & $ & * !  
* !Y,
&
!&
&* % % 
!  
\& !  
% $   &&
  &
 &   ,,% 
!
 %  &  %  !! *  &* +

5,000

Forecast

Oil Production b/d

4,000

Actual

3,000

2,000

1,000

0
A

Well Number
Adapted from SPE 30745

Figure 14 Performance of horizontal wells in one North Sea Field.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

15

Petroleum Engineering

Production Technology

Production Rate bbls/day

1000
A typical horizontal well initially
produces at 150 - 200 bbls/d and
recovers 150,000 - 200,000 bbls
100

10
A typical vertical well initially
produces at 40 - 60 bbls/d and
recovers 50,000 - 70,000 bbls
1
Year 1

Year 2

Year 3
Horizontal Well

Year 4

Year 5

Vertical Well

Figure 15 ; 


 ! &&
   %  * !&  $ ! 
 ! &
reserves in a North American Field.

" '!   ! %     &


     ! % 
  $  
$ ,; 
 ! $ !; *  ! $ !    &%  ,*  !! ! ! 

 !   ! $ !
  & $ 
* _  ! *  
 &
  %  * ! =  &^ 
! *%  %  
 ! &
early well production resulted in an increasing recovery is shown in Figure 15.
  ,;% ! $   ! ! * ,!! $ & 

+#% 
  ;% %*   & ! !    
 ! & ! $ !! 
  =  !
%    ,   Y ]
 &\ ]
!! $  [] !*   !  !
% *   !* % * % ! 
 &; =  %  

& ! $ & ! 



2.6.2 Connection of Laterally Discontinuous Features


  , 
 &  ! $ !
     $ !  %,&
!%    ]
    , !    * 
 
 &
    ! }* $ ; * !
 !
  ;  
 !
&
 % %  !& %     
 [*% ! 
 !   ,
! $ 
 &   ! $ !'
horizontal well aligned normal to the stress direction at the time of fracture creation
% ! 
%  
% 
  !
 % 
 !Y   \
% @ ,     !% 
 & ! ,+% 
 & ! , !!
,! ! 
it is unlikely that a vertical or deviated well will intersect a fracture. The horizontal
* 
  ] & &    !
! !
 
 ! $ % 
 =  &* &
   

16

Advanced Wells and Completions T W O

Figure 16(a)~ 
 &%  * !

   
 !

Fault
Reservoir 1
Reservoir 2

Figure 16(b) ! $ !!    &, !   

 &
&, !  %  * 

% %  * 


 !

 ! $ ! &    
@!% `
response while drilling the horizontal section may suddenly indicate a change from
 ! $ _ ! $ Y  \% * !*;&  & % , 
 ; & 
 &* &!&** &!  ! 
%%  ! $ &=  ,
! !
 & & ! & %  &!!
 % !,   =  &%  % 
 ! $ ! % * 
@! ,% $ ! 
,&       !! !
%  !! ! ,& $  &  ]       %  [*% 
!    
@!!      *  ,  
%  

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

17

Petroleum Engineering

Production Technology

2.6.3 Changing the Drainage Geometry


'}  * ! ,% !   ?&
 $ ,+& ]%  $ 
* } 
;
  $ &
 !  ;% & *&**  * ;&  , %  

% 
*  &[ &!!
% !*   !% !%   !   & !
 
vertical wells and cresting for horizontal wells. Figure 17a shows that the drawdown
!$ 
 % , 
,
& % &   & !  !  &*  
% & ! &*  _ 


%% % * !   &  $ 
 ,;%   % & ! 
% %  *  $ % `  _^ _

%   % & *&*
 * %*  &
 

Water
Oil

Oil

New oil water contact


Original oil-water contact

Figure 17(a) Water "coning" phenomena.

'!   %  *


 &
! & *!%  !&** &!% 
%    &  $ Y  \
Gas

Gas

Original gas oil contact


New Gas oil contact

Oil

Gas

Oil

Original oil - water contact

Water

Water

Figure 17(b) Gas "cusping" phenomena.

%    !< !&
& *% % !& ! 
!%& % !&
! 
 

 
   _  ! $  % 
!   $    ,  ;!
% !
  ] !! % $,  ! $ !'% ! _  =  !% % %  
*  
&   % [ &

!   !  * % !
% 
&   ! $ & $ 
%  !Y !
 ] !  =   []\  
  &
 !!%   , *  
  & *  
 !  $ 
 &
horizontal well respectively.

18

Advanced Wells and Completions T W O

Producing Wellbore

Water Crest

Water Cone

(a) Vertical Well

(b) Horizontal Well

Figure 18?&
  &
&*  
 Y$ 
* !\ &
 ! Y%  * !\

2.6.4 Extending Field Appraisal Laterally


%  &    
% &  ! % ! & Y  \$ 
* !
&;,  & ! % ; &  
 & ! $ & 
!  %  && $    % !
!!
  ] & &   ,! 
%  * !+
  !
,*  &    !   %
 !*%  
 ! $ =  , ,&  & $   *@   !#]  !*%    ! 
,%  * ! ! &$   !  % {
" +& 
 
  *@!* % 

 &  ,
"      !  && $  <
 $ !  * 
" ' !  , 
@!* % * 
" '  ,     ! $  *% ! ! 
 ,! *% 
%  ! $  !& 
 ,! !


2.7

Disadvantages of Horizontal Wells

 %  % ! !% ! % !  $  !


!%  * !'! ]
 &;
%     !& ! &$   !{
" '% % !

 &    &&   !! , ! =  &!

!!,
drill the horizontal well.
" %  !  , &!%& ! % %,  &% !  ! !
,
to the directional drilling specialist.
" }  * !% $  * & *&* &! &
[ & [*$ 
,
% $ 
* !;% 

  
  !* & 
% !% !
  && !! &,& $  & _ [ &! =   *& *&*
for removal of the mudcake.
" %  !*   ;
 &  $      ] ! $ 
in a horizontal well.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

19

Petroleum Engineering

" % 
!>&  & %  *  &
! !  %  *  ]  

! _   
  &
%  $ & ! &$   !
      &,&  

2.8

The Economics of Horizontal Wells

2.8.1 Costs
Horizontal wells normally take longer to drill than vertical wells in the same reservoir.
% , =  % %!

  =   &!
 ! ! #]  
!%*!
% %  ! ** !  %  &  
   $ , ] ! $ ;
 

! &  ,


%   ! * !  &  &% 
!% _% !
 !%&
have operating costs similar to a vertical well. The horizontal section will have additional

!!   $   ! =  &&


  ;!    !  ! 

  & &  !   % &%  & !% !


 & =  

_
 
`
% ! & &  &    , &
!  ! &* 

!% !   
 ? ! ~  Y?~\;? __+$ !   Y?+\;? ,
@   &% 
  
![* ! & &&  & !*!Y!  _ ]

  !! 
,\{
" Net Present Value (NPV)
%     & !& $ & &      &! &%  *
!%[*&    &

%  & %   !%*Y\  & Y \ !&  & !% 
$  !%   &
NCFi},&
  ,?
   !^   !
The sum of the NCF for the period of the project is commonly referred to as Cumulative
Cash Surplus or Ultimate Cash Surplus. The discount factor
%  &Y& \
!  &_, & !
   & !
  &   !{

dfi =

1
(1 + d / 100)i 1/ 2

 !
 &?~Y&\ !% &  & !{

NPV(d ) =

NCF1 NCF2 NCF3


+
+
+
df1
df2
df3

= 1N

NCFi
dfi

`% ! ?~  !  = %% & !


   &%    
&  
Y%    ,  %  $  ]  \

20

Production Technology

Advanced Wells and Completions T W O

NPV is the most direct and robust measure of value.


" ||`;
#
}`#~

% ?+ !&  & !{Ultimate Cash Surplus


Total Capital Expenditure
+ !   ,   ! & !
 &=   !{

PIR(d ) 

NPV(d )
Capex(d )

`%    ]Y&\ !%     #] &  & !


 & &   % 
!     !% ?~ $ 
 

 
 





 

" Payback Time
% ! !%    *%
%% 
  $ Y& !
 &\ !    $ 
 !  $ 


 
  



!


" Unit Cost of Production

Unit Cost-per-Barrel=

Capex(d)+Opex(d)
Producttion(d)

Where Opex is the Operating Expenditure



    
  

!

 ! 
 
"

 ! & !   
 % ! 

    !%  
* !  !%*!%  
 ! &` ?&
 $ ,+& ] !  ! $ 



% $ &, $  %   & _   * !  !%*!
%*% ! *!  &
  %  
! =  && $    &
 
capacity.

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

21

Petroleum Engineering

Production Technology

140

14
PI,
PI, STBD/Psi
STBD/Psi
Rate,
Rate, MBOD
MBOD

12

100

10

80

60

40

20

Production Rate MBOD

PI, bbl/day/psi

120

0
1.0

2.0

3.0
5.8
Reservoir Contact, Km

8.5

12.3

Figure 19 Well Productivity Index and Production Rate increases


, ] & & ! $ 

   && # !  &

Normalized Unit Cost


($/bbl/day of Initial Production)

1.2
1.0
0.8
0.6
0.4
0.2
0.0
1

10

11

12

13

Reservoir Contact, Km

Figure 20
 ! & & $  
!$! ! $ 

   && # !  &

MULTI-LATERAL WELLS

Q%
`

&
' _ 
%*  !&  & ! * *%
%% ! %  $ 
; 
  &
%  % &  & !  !   &

 &
@ !  % 
*  % !!
 
! ! _   !*%
%%  
% !  %  
or close to horizontal in the reservoir.
The main reason for drilling a multi-lateral well is to increase the return
on investment through improved reservoir drainage even though the initial
well cost is higher. For example the reported reserves per multi-lateral
 %  '!  % @ Y ] !; '\ % $      &       ! % 
reserves per single lateral while the cost was 1.4 times that of a single lateral.
%  % !
,    & 
 !  % !  _   !% ! 
 ! % !
 & $ , ! 
  
 ! &% * !% $ % &$  !
22

Advanced Wells and Completions T W O

 $ !!% !
  % & ! ;!   % ! & 
@!* !
*%  %  
% !
&  _   & !  &! 
 $ ,% !  =   !
have encouraged the service companies to invest in new methods of drilling and
completing multi-laterals. This particularly applied to the construction of the multilateral junction to achieve zonal isolation and allow re-entry.
The most common multi-lateral well has two or three laterals per well. They are often
 &  &!*%  %  * !*  !

!! &% 
!! $ !
&
  & ,% $  * *  !!
       ! 
one multi-lateral well thus made sense.

Q
@
`"
>

 

U |  
There are many constraints in multi-lateral well design related to the operation of
! & 
@ %   ,*   &% !%  %    ! $ Y!\
]  ;%   ,*   , 1/2 % * %    &  *%  % 
! & 
@ ,  % * %=   ! $   &  & % ! $ 

& ! 
 * % <
  &%  ! $ %    ! ,% $ &    %!
&&   
  ! !  !!
%  

! !+%   ,*  
!% %,& $  &% %  % !     * %    !*   !
 &
% 
!! _   * & !   $$ !    ! * Y& 
  \
&  !;  !! & ! $    !   !  !
,!  !&
 , 
! [ 
 %  &
!   *% %   & ,   _    % ,

 ! &  * ] !  &!  % % $ !  ]  

%  * ! %   +! 
! !;    
 &  &   *& 
 

=   ]  >  ! &   &&  &  !!

!!; %     &


&
 > <
   & &

Q%
U | 
` 

!>
#
+%    !   &  & % !   ! $  

  ! $ !;
% &     !*  $  ,$  %  !  &     *  
 !!% *
% &      !  %     Y  \}* $ ;
 *     ,  ! $ ! %   !    &  ,  !       &
! 


     &


  *   
% $ &       
 
!
reduce production.

No F
l
Bou ow
ndar
y

Production Time Increasing


Figure 21+   
 * &     % *   !
26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

23

Petroleum Engineering

Production Technology

Q
U | 
` 

!>
^ 
% !   !! !  !   $ 
*  _

  ! $ !Y   
! = 
!
@ & ! $ !\+   
*  @ 
 % *   !!
& 
   !! &Y   \+ !
 & &!  
  
&
 
   % * ! $ !  &    !! Y
!![*\
reservoirs at the same pressure regime commingled production when producing dry
 
! !  !!! $  &    &    @ !
Y  \
%  &$ *  
  , 
! ! 
@ !!   ]  
&  , 
& % % % & ! ,% [ & %   $  , 
(a)

(b)

OWC

Water

Figure 22(a) _       
 
! % *  
Figure 22(b) `   @%% 
!%   

% !   _   * 

3.3

Impact on Recovery and Rate

   _   !! ,

   %  &
   &  
 !     

$ ,% !
  
   !*%  
!! & !@!  % %*% % 
production rate from a single lateral is non-economic. Both acceleration and improved

$ ,Y  \ =   & ! & %   !%    &
$ 
[*% !   %    ! %  ! $ *  
 
 &  ,
 
!! ,$ &   $  !!    !
    ! $     
Increased recovery
Multilateral

Production Rate

Single lateral

Multilateral
with early decline
Time

Cumulative Production
or Reserves

Multilateral

Single lateral
or multilateral
showing early
decline

Time

Figure 23#

  ! _   !

24

Advanced Wells and Completions T W O

Q
`
U>

 
  !
     &,{
" ^ % ! & 
@!&  &* %* %*% !
@
"   ! & 
@! 
! &*  !* %  *% !
@
"   ! & 
@!%%%  * % ! &   *% !
@
%  ! %& !! &
!
  *
!%% ;! & 
@ 
 % %  !   Y  \'&    ! =  &! 
% !

   &, 
  & &   
Low Permeability
High Oil Saturation
High Permeability
Low Oil Saturation

Figure 24   & & $   ,  & ! $ !

Q$
 
U | 
;

(a) Stacked trilateral


in a multiple
layered reservoir(s)

(b) Planar trilateral in


a single reservoir

(c) Planar opposed dual


lateral in a naturally
fractured formation

Figure 25 Multi-lateral well designs.

% %  !
   ! _   !  {
" Stacked
   Y   \ !! && $   _

 ;
 ,  & ! $ + ! !!   !   !! $ ;*    , ! $ 
*%  %   !   & ! &
       
 * 
%    !
 !! 


26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

25

Petroleum Engineering

" Planar
   Y  \ !! &   ,
 & ! $ !*%  
%   !! 
 , 
    %    !    
 !!  !
   !
 % 
 !   !    
%    * ; !!% !  & !  
 ! !$ ,
!  &
" & | 
   Y  
\% !%  &$    $ %   !
&       $  %*  * %       
 % 
heel of the well.

Q[
\

U | 
^ 

;

!>
Technical advantages of multi-laterals centre on greater reservoir exposure at a lower

!% 

  ! _   * !  ! % 
% % 
& 
!
%  ! $ ,% ! &  & &
! &
 _   !

% $   < 
!% , 
 ! % &
  & ,!
  ]! 

%! $     ] & !!     _   ! &
% 

  
!! 
% 
! ! &   ! !   &%  !!
*     &!  ! & 

,$  & $  !
% !   

  !% & $  !, &
%  &! % 
&  
 & % $  * * !  &!!*   &
&! ,
%%% $  !   !
 &%  $  *   & 
to the reduced impact of this smaller surface presence.
%    

& ! &$   !%  & 
 ! & %   !  
!@ !* 

  &  !   * !+%   
%    ,   &&       
!! &   
  !  %   ! $  &

% 
  
^ %  
% ! , ]  
   *  
 ! @%% & =   & 
!%_   
 _   !   ,     !@`   $  *   & 

& ! $    &    %  =  !!
%  $   !
 ,
   & !
    &
   _   ! &
! *& 
 !
* 
 & !     &
  & $ &  
% !

Q[%
 

U | 
^ 
%     ! 
 ! _   * !?  ]  ! 
& {
" Viscous oil reservoirs% $  &
 $ ,%  !;    ;
!  &, 
  ,  ;  Y?    ,>~ !
! ,@>\ !*% ! !
  &;
* %%  !!
 &% %& *&*!, ]    ]! 
'
% $ 

[*  ! =  ! %    ]! ;  Y\
 % %   
 ! & % &   
" Layered reservoirs
  
, ]  &! % !
@ & _   

      Y \    !    @   $    %  &   


 
 %    ! % 
  +%  !!    !  ! 
,
&   %   , 
!! , ! !     ! ! 
  
* %&*% [*
$  !  Y
\

26

Production Technology

Advanced Wells and Completions T W O

'
+ 
@


; 
#
  %Y*    ,\ &  ,
 & ! $ !
  ]  &! 
  
   !* %*    ! ! &  !Y\ &
Y\
 %;
 & ! $ !   
% ! $  !  !
*      
 ! %  ! $  ]! 
! 
 $ ,% 
naturally fractured case it depends on how well the natural fracture orientation is
known. If this orientation is relatively poorly known one could place laterals at
&     !; ! % &
    
%   &    *%
% !
% ! $     % 
!! !%  ]  
 !
'
@  and compartmentalised reservoirs are good candidates for multi-lateral

 ; !
, ! % 
  !% $  ! $ ! *%  $ 
*%
%  & $ & * 
& <! &+&  !
%* !;@* & 
%  
 ! & ]  
&   %   *    
Y  \'% %_ ! ;! !
!$ ,* %&* 
* 
make well placement easier.
" Depleted or mature reservoirs  
& &  ! _   * !; 
 
especially when the pace of development in the various zones is different. Figure
!%*!* !; * %&    ,;* !   *%  % 
% % ! *     , &    !   % % %    ,
 , 
&
=  * %% $ 
*  % *    ,
!  !  & %  *  %   !&

    
rates from each two lateral.

Q[

U | 
^
; 
'   !  $    %   !

 % !   $ & & , %   % &  !
&Y  ! &\% !*    , ! &&
!&, !% 
   & !! &! %    Y$ 
\*  % ! &* !!

% 
 ** & ! @ &$   %  ! $  , !*!{
" % % ;%  ;*  * !
& % % %     ,! &
<! $ %  !_`  _
Y  \% !

 ! ]
 &
$ &  ! $ &   & % ! ! %  =  
" %    
% *    ,;;# &! &!*
$  !!%  &

   % !* 


   * !
%! 
! 

! 
% $ 
    ,
" '!  <
  * % *   !* %  !  
& ! &
! * !
&* % %  ! $ Y  ! &\
" % ?+%  _   * !
  &% $ 
& !
$ ,* 

26/06/14

Institute of Petroleum Engineering, Heriot-Watt University

27

Petroleum Engineering

Production Technology

-9,100

-9,200

Lateral

Zone F
Zone E

-9,400

Zone D
Horizontal Wellbore

-9,500
GWC

Zone C

-9,585

Zone B
-9,700

-9,800

Rotligendes Formation

Depth (SSTVD)

-9,300

Top Carboniferous

-9,900

Figure 26  % & & _   


 

41/2" Tubing

Gauge Mandrel 7150


Casing Window 7560
Openhole juncton high in reservoir
7" Liner Window 9703

41/2" Slotted Liner

TD 13975

Openhole completion
41/2" Liner Top 9800

abandoned
pilot hole

7" Liner Shoe 9900

7" Liner
TD 13743
41/2" Slotted Liner

Figure 27  % & _   


  

28

Вам также может понравиться