Академический Документы
Профессиональный Документы
Культура Документы
By
Sanjay K Chaudhary
A dissertation submitted to
The Faculty of Engineering, Science, and Medicine, Aalborg University
in partial fulfillment of the requirements for the degree of
Doctor of Philosophy
Acknowledgments
My deepest gratitude goes to my supervisors Prof. Remus Teodorescu and
Prof. Pedro Rodriguez for the valuable guidance, inspiration, support and
encouragement. I would like to thank Dr. Philip C. Kjer, Peter W.
Christensen and K. H. Sbrink from Vestas A/S for their valuable discussions
and feedbacks on my research. I would also like to thank the Technical
Reference Committee members, especially Dr. T. Jonsson, Prof. W L. Kling
and Prof. M. Aredes.
This research is a part of Vestas Power Program. I would acknowledge
Vestas Wind Systems A/S and Aalborg University for supporting my research.
I am grateful to Dr. A. M. Gole and Dr. U. Annakkage for the motivating
discussions during my stay at University of Manitoba. I am thankful to Udana
Gnanarathna, Dr. R. Gokaraju and Dr. Amit Jindal.
I would like to thank Dr. Dharshana Muthumuni, HVDC Research Center,
who introduced me the PSCAD/EMTDC and who has been very helpful in my
research. I am thankful to Mr. In Kwon Park from RTDS Technologies
teaching me the fundamentals of real time simulation. Jonas Hansen, ABB
Denmark, was very helpful in setting up the relay interface with the RTDS
systems.
My sincere thanks goes to Osman, Andrzej, Maciej, Ram, Rodrigo, Mufit
Omer, Yash, Tamas, Dezso, Lajos, Ionut, Pukar, Jai, Erhan, and all the
colleagues from the Vestas Power Program and the Department of Energy
Technology as a whole.
Lastly I would like to thank my parents, my sister, my wife and my sons
for their support and encouragement.
Sanjay K Chaudhary
Aalborg, Denmark,
September 2011
Abstract
Wind power plants are the fastest growing source of renewable energy.
European Union expects to generate 230 GW wind power, and offshore wind
power is expected to contribute 40GW. Offshore wind power plants have better
wind velocity profile leading to a higher energy yield. Europe has a huge
potential of offshore wind energy, thereby securing its energy supply in a green
and sustainable way. All these have led to the development of offshore wind
power plants.
However, overall cost of offshore installation, operation, and maintenance
are higher than those of onshore wind power plants. Therefore, the plant size
needs to be higher such that the cost of per unit energy can be lowered. An
overall increase in operating efficiency would further reduce the cost of energy,
thereby increasing the viability of the project. Multi-MW variable speed wind
turbine generators, of unit sizes between 5 -10 MW, have been developed so as
to take advantage of the lower cost per MW of installed wind power capacity.
The current trend is that these large units will comprise of multi-pole, lowspeed synchronous generators equipped with full scale converters.VSC-HVDC
cable transmission is a favorable option for large and remote offshore wind
power plants, which need long cable connection to the onshore power grid. It
has lower power losses and higher transmission efficiency, and fast control of
both the active and reactive power.
This dissertation presents an operation and control approach of a potential
wind power plant with VSC-HVDC connection the onshore grid. A layout of
an offshore wind power plant is modeled for electromagnetic simulation in the
PSCAD/EMTDC environment. The offshore terminal of VSC-HVDC is
controlled to establish the reference voltage waveform in the offshore grid. A
new controller has been proposed for the offshore VSC-HVDC terminal which
utilizes the measured active and reactive power to define the feed-forward
terms for the current references.
HVDC transmission decouples the offshore grid frequency from the
onshore grid frequency. A scheme has been evaluated to relay the onshore grid
frequency using the dc voltage of the VSC-HVDC for the purpose of enabling
the frequency control from the wind power plants. At the same time, the
placement of chopper controlled resistors in the full-scale converters has been
proposed and investigated for the dissipation of power in the event of onshore
grid disturbances.
The current control capability of the converters in the offshore wind power
plant grid can be utilized to enhance the fault time behavior of the whole
system. A novel approach has been proposed to allow a calculated amount of
negative current injection from the full scale converters in the wind turbine
generators and at the same time enabling the negative sequence current control
in the VSC-HVDC. The proposed approach is found to have lower power
oscillations and hence lower dc voltage overshoots in the VSC-HVDC system.
On the protection side, the coordination of over-current relays has been
analyzed in the new environment. A simple yet reliable scheme utilizing the
well-known over-current relay characteristics have been presented for the
detection of faults and determination of faulted section on the wind turbine
generator cable feeders. The intermediate high voltage cable feeders may
require under-voltage measurement signal or interlocking signal from the MV
feeder relays to avoid over-reach under certain conditions.
Contents
Contents.............................................................................................................. i
Abbreviations ................................................................................................... iv
1 Introduction ................................................................................................. 1
1.1 Background ....................................................................................................... 1
1.2 Wind Power Plants ............................................................................................ 2
1.3 State-of-the-Art ................................................................................................. 3
1.4 Motivation and Objectives ................................................................................ 6
1.4.1 Simulation Tools and Techniques ...................................................................................7
1.5 Limitations ........................................................................................................ 8
1.6 Outline of the Thesis ......................................................................................... 9
2 Grid Connection of Wind Power ............................................................. 11
2.1 Wind Turbine Generator (WTG) .................................................................... 11
2.1.1 Wind Turbine................................................................................................................11
2.1.2 Mechanical Control of Wind Turbines .........................................................................13
2.2 Wind Turbine Generators................................................................................ 14
2.2.1 Type A: Fixed Speed Wind Turbines ...........................................................................14
2.2.2 Type B: Limited Variable Speed ..................................................................................14
2.2.3 Type C: Variable Speed with Partial Scale Frequency Converter.................................15
2.2.4 Type D: Variable Speed with Full Scale Frequency Converter ....................................15
2.2.5 Permanent Magnet Synchronous Generator..................................................................15
2.3 Wind Turbine Generators with Full Scale Converters .................................... 16
2.3.1 Permanent Magnet Generator with Machine Side Converter (PMSG-MSC)................17
2.4 Grid Connection of Wind Power Plants .......................................................... 17
2.4.1 VSC- HVDC Transmission ..........................................................................................19
2.5 Modular Multi-level Converter (MMC) based HVDC ................................... 21
3 System Layout and Main Circuit Parameters ........................................ 24
3.1 Main circuit components and parameters........................................................ 24
3.2 Onshore Grid................................................................................................... 24
3.3 Converter Transformers .................................................................................. 27
3.4 Voltage Source Converters ............................................................................. 27
3.5 Tuned Filters ................................................................................................... 29
3.6 Phase Reactors ................................................................................................ 30
3.7 DC line Capacitors .......................................................................................... 31
3.8
3.9
3.10
3.11
3.12
3.13
ii
6.1
6.2
6.3
6.4
iii
Introduction ..................................................................................................... 81
Negative Sequence Controller for the VSC-HVDC ........................................ 82
Negative Sequence Controller for the WTG-GSC .......................................... 84
Simulation Results .......................................................................................... 86
6.5
6.6
Discussion ....................................................................................................... 99
Summary ....................................................................................................... 101
iv
Abbreviations
C2L
CB
DFIG
FRT
FSC
GCR
GOOSE
GSE
GTNET
GTAO
HAWT
HVAC
HVDC
IED
IGBT
IGCT
LVRT
MMC
PLL
PMSM
PMSG
PWM
RTDS
SOGI
VSC
WECS
WPP
WTG
1 Introduction
1.1 Background
Wind energy is the fastest growing source of renewable energy globally
the average annual growth rate of installed wind power capacity has been
around 30% in the last decade. The 2009 EU Renewable Energy Directive aims
to produce 20% of the overall energy mix from renewable energy sources. By
2020, EWEA targets to develop 230GW of wind power, with 40GW coming
from offshore wind power plants [1]. In 2010, global installed wind power
capacity increased by 24.1% and reached 197, out of which 86. 3GW was in
Europe. A vast majority of these are onshore wind turbines. However, the
offshore wind power plants are growing at even faster rate. In 2010, 883 MW
of offshore wind power was added, bringing the total installed offshore wind
power capacity to 2946 MW 2946 MW in Europe [2]. A total of 600 GW of
wind energy will be installed by the year 2050, of which 250GW will be
onshore and the remaining 350 GW offshore. Thereby it will be able to meet
50% of the European Union electricity demand [1].
400
Onshore
Offshore
350
300
250
200
150
100
50
0
1990
1995
2000
2005
2010
2015
2020
2025
2030
1200
Offshore
Onshore
1000
800
600
400
200
0
2000
2005
2010
2015
2020
2025
2030
Fig. 2 Power production from onshore and offshore wind in the EU (2000-2030) [1]
1.3 StateoftheArt
Wind power plants comprise of a large number of wind turbine generators
(WTG), each having a unit size of a few MW at the most. In the early 1990s,
the wind turbines mostly employed fixed speed squirrel cage induction
generators. These were followed by the induction generators with limited range
of speed control provided by the introduction of rotor resistance through slip
rings. These days doubly fed induction generators are the most popular
topologies. Recently permanent magnet synchronous generators (PMSG) with
full scale converters are gaining popularity for large WTG units.
Grid connection of the large wind power plant is necessary for the
transmission and distribution of the generated electric energy. Breseti et. al.[3]
present a comparison of ac and dc transmission options for the grid connection
of offshore wind power plants. It is concluded that VSC-HVDC is the cheapest
option for the grid connection when the plant size is larger than 100MW and
the distance is larger than 90 km. VSC-HVDC is the latest technology in
HVDC transmission. The first commercial VSC-HVDC transmission was
installed in Gotland, Sweden in the year 1997. Since then ABB has installed
around 12 VSC-HVDC transmission systems. Most of them are for
With the emergence of large wind power plants, the grid operators are
cautious about their impact upon the power system. Grid operators have come
up with Grid Code Requirements (GCR) to be complied with before the wind
power plants can be connected to the grid. GCR specifies the operational
conditions of voltage, frequency and power factor. In the beginning, the wind
power penetration in power system was small, and they could disconnect
during the grid disturbances. However, with increasing penetration of wind
power in power system and decreasing proportion of the conventional
synchronous generators, grid operators demand that the large wind power
plants remain connected to and assist the grid recovery. For instance, the
German grid code [11] requires that the WPP remain connected and supply
reactive current to the grid during low voltage faults in the power system grid.
It also specifies the power ramping rate after the fault has been cleared. Though
the grid code asks for 2% reserve be made available within 1 minute for 400
mHz change in frequency, the offshore grid code [12] over-rides this
requirement by asking for only downward regulation. In the Danish grid code
[13] both options have been specified.
Low voltage ride through capability is another challenging requirement for
the WPP. Ref [14] describes the different techniques available for fast power
reduction of the wind power plant or dissipating the excess power in braking
resistors. Feltes et al [15] describe the different ways of achieving the LVRT
capability and proposes the demagnetization of the doubly fed induction
generator such that the WPP grid voltage can be suppressed rapidly so that fast
voltage reduction can be achieved without producing the typical short circuit
currents and the related electrical and mechanical stresses.
Muyeen et al [16] have described the use of energy capacitor system (ECS)
composed of power electronic devices and electric double layer capacitor
(EDLC) to enhance the LVRT capability of fixed speed wind turbine generator
system during network disturbances. Use of ECS using EDLC to enhance the
transient stability of multi-machine power system including wind power plants
is presented in [17].
In power systems, the synchronous machines provide the inertial response
to sudden variations in frequency due to instantaneous load-generation
unbalance. The wind turbine generators with their power electronic converter
interface do not automatically respond to grid frequency variations. Therefore,
1.4.1
controllers for the VSC-HVDC and the wind turbine generators are not
available as standard modules and they have been modelled as a part of
modelling and simulation in this project.
Real Time Digital Simulation (RTDS) has been used as it facilitates the
hardware in loop simulation. An industrial overcurrent feeder protection relay,
REF615 from ABB was interfaced with the real time simulation model and the
relay coordination was experimentally verified as a part of validation exercise.
MATLAB/Simulink has been used for the numerical calculations and
frequency domain analysis of the controller and filters.
1.5 Limitations
Two level converters have been simulated and studied. Recent
development of multi-level converters has rendered the two level converters an
obsolete technology for the VSC-HVDC transmission. However, the concepts
and theories developed in this thesis regarding the offshore wind power plants
and its grid connection using VSC-HVDC transmission are expected to give
useful insights in the understanding and investigation of the new systems.
Only ac collector grid layout has been considered here for the wind power
plant. The turbine generators are assumed to be permanent magnet synchronous
generators equipped with full scale converters. Further, the specific details of
the turbine and the generator has not been used here, but a rather simplified
model whereby the turbine, generator and the converter is modelled as a power
source of the first order transfer function. The focus here is on the operation of
the grid side converter of the WTG-FSC, the collector grid network and the
VSC-HVDC transmission to the grid.
The onshore grid has been modelled here as Thvenins equivalent voltage
source.
WPP and VSC-HVDC have been considered here as a single system. This
implies that the VSC-HVDC control is used to facilitate the grid integration of
the wind power plant. For instance, in some of the approaches, the VSC-HVDC
relays the onshore grid frequency to the offshore grid. The onshore grid
terminal is assumed to be the point of common coupling where the grid code
10
Real time simulation of the whole test system in RTDS with interconnected industrial overcurrent relay for the detection of fault events and relay
trip characteristics have been presented in Chapter 9. It corroborates the
observation for the relay coordination settings in the MV WTG feeders.
11
Wind Turbine
12
1
2
. .
.
(2.1)
The volume of wind passing through area AR swept by the turbine blades
in a second is
. Therefore, the total mechanical power is,
1
2
1
2
(2.1)
(2.2)
0.593. Modern
3-blade wind turbines have an optimal C in the range of 0.52 to 0.55 when the
power is measured at the rotor hub. After deducting the losses in the drive train
and the generator, the optimal value of lies in the range of 0.46-0.48 [27].
and its
(2.3)
can be
(2.4)
13
Slootweg et. al. present a table of coefficients for the commercial constant
speed and variable speed wind turbines in [28]. The turbine characteristic for
, , (2.6), given in [31] is a special case of
the performance coefficient,
(2.5),
0.5
116
0.4
(2.5)
where,
1deg
0.5
0.4
2deg
5deg
0.3
10deg
0.2
15deg
0.1
25deg
Figure 2.1
2.1.2
6
8
10
Tipspeed ratio ( )
12
14
16
Equations 2.3-2.7 reveal that the power absorbed by the wind turbines
depends upon the operational speed of the turbine and the blade pitch angle. In
a variable speed wind turbines the turbine speed can be controlled to achieve an
optimal torque speed ratio ( and therefore maximum efficiency over a range
of wind speed. When the wind speed varies, the turbine rotor and generator
14
speed vary and hence the torque remains fairly constant, thereby reducing the
mechanical stress. Maximum power point tracking over a wide speed range
enables increased energy capture, improved power quality and reduced
mechanical stress on the wind turbine. Apart from this, the turbine speed
should be limited within safe design limits in presence of strong wind
conditions. Stall control have been used for this purpose. Nowadays, pitch
control mechanism is used to regulate the power. The blades can be turned out
or into the wind as the power output varies. Such a fast control provides good
power control, assisted start-up and emergency stop.
2.2.1
15
2.2.3
Double fed induction generator with partial scale converters allow speed
control -40% to +30% around the synchronous speed. The converters are of
approximately 30% of the nominal generator power. The partial scale converter
injects voltage in the rotor circuit at the slip frequency to vary the slip.
2.2.4
(2.6)
16
poles. In Multi-brid concept, a single stage gear box is used to bring down the
size and weight of the generator. Direct drive permanent magnet synchronous
generators have the losses 35% lower than the DFIG and approximately 32%
lower than the direct drive synchronous generators with wound rotors. If a
single stage gear-box is used, the losses increase but there is a 75% reduction in
weight as the machine synchronous speed is increased [26].
Figure 2.2 Wind Turbine, PMSG, FSC L-C-L output filter and unit transformer
where,
components of the wind speed in m/s. The wind turbine generator shaft
dynamics can be modeled in terms of a set of three coupled masses
representing the blade, hub and the generator Error! Reference source not
found.. Slootweg et. al.[30] [28] recommends using two mass representation of
the drive train to include the dynamics of the low speed shaft.
17
2.3.1
(2.8)
18
19
High voltage, high power two level or three level voltage source converters
(VSC) are used in HVDC applications are. It is possible to switch the insulated
gate bipolar transistor switches in the VSC at a frequency of a few kHz for
pulse width modulation to control the phase of the current with respect to the
voltage waveform. Both active and reactive power exchange can be
independently controlled. This enables the four quadrant operation of the
converter as shown in Figure 2.3. The advantages of VSC-HVDC over the
LCC-HVDC are listed below [37]:
I.
II.
20
1.5
Q
MVAmax
Vc=1.15pu
0.5
Vc=1.0pu
Vc=0.85pu
-0.5
-1
ConverterendQvsP
-1.5
-1.5
-1
-0.5
GridendQvsP
0
0.5
1.5
III.
IV.
V.
VI.
21
Figure 2.4 Location of Borkum 2 and other wind power plants in the North Sea [38].
22
from the fact that after the first VSC-HVDC connection to the Borkum-2 wind
power plant, all the later VSC-HVDCs, viz. BorWin-II, HelWin-I, DolWin-I,
SelWin-I connecting the in the North Sea are of the MMC-HVDC type.
A multi-level converter comprises of a number of unit sub-modules of a
low unit voltage ratings connected in series to attain a high voltage
requirements as shown in Figure 2.5. Each sub-module comprises of a pair of
complimentary IGBT switches connected in series across the sub-module
capacitor. When the switch T1 is ON, the capacitor voltage, the sub-module
is referred as turned ON and Vc appears across the sub-module terminals and
the capacitor gets charged or discharged depending upon the direction of the
sub-module current, Ism . When the switch T2 is turned ON, and the switch
T1 is OFF, the sub-module capacitor is by-passed and the sub-module
output voltage is 0. Thus by controlling the complimentary switches T1 and T2,
the sub-module voltage can be controlled. Since, there are a large number of
unit sub-modules connected in series, the output ac voltage can be controlled in
the multi-level, determined by the number of switches between the ac voltage
terminal and the dc pole. At any instant, the ac terminal voltage for phase A is
given by,
(2.9)
where,
lower multi-valves of the same phase. Similarly other phase voltages can be
obtained.
It is obvious from 2.9, that the total number of sub-modules in a phase is
related to the pole voltages by the relation,
(2.10)
Vdc
23
The multi-level output ac voltage has a lower harmonic content and hence
the tuned filters, which are mandatory in a two-level or three-level converters
are not required. The converter sub-modules are switched at a low frequency,
but the effective frequency turns out to be very high due to the number of submodules connected in series. Due to low frequency switching, the overall
losses are lower [41]. On the flip side, the number of IGBT switches required
for a given converter is doubled.
However, the two-level VSC-HVDC system has been considered in this
project as the objective is on the operation and control of the wind power plant
with VSC-HVDC connection to the grid. Most of the findings of this project
would be applicable to the MMC-HVDC systems as well with necessary
modifications. An application of MMC-HVDC for the connection of wind
power plants was studied in [39].
24
Onshore Grid
Converter Transformers
Tuned Filters
Phase reactors
Voltage source converters
HVDC Capacitors
HVDC Cables
150kV submarine cables
3-winding transformers
Zig-zag grounding transformers
Wind turbine generators with LCL filters
25
LCL
Filter
Chopper
Resistor
GSC
CB & CT
MV feeder #1
36 kV Coll.
Bus#1
WTG#1
GSC
MV feeder #2
WTG#2
36 kV Coll.
Bus#2
HV
feeder #1
MV feeder #3
36 kV Coll.
Bus#3
WTG#3
GSC
B1
150 kV
B2
HV
feeder #2
GSC
FB
150 kV Coll
Bus #2
MV feeder #4 A4
FA
WTG#4
OFFSHORE
ONSHORE
VSC1
VSC based HVDC Transmission
Vf2
170 kV
Vc2
Vdc1
Vc1
Xph1
Vdc2
170 kV
VSC2
Xph2
Xt2
Vg 400 kV
150 kV
150 kV Coll
Bus #1
P+ jQ
26
Figure 3.1 Single line diagram (SLD) of a 400MW offshore wind power plant with VSC-HVDC connection to the onshore grid.
27
cos
2
1
2
where,
sin
sin
cos
(2.2)
cos
28
Frequency Spectrum
0.9
Fundamental
Component
0.8
Component at
Switching Frequency
0.7
Magnitude (pu)
0.6
0.5
0.4
0.3
0.2
0.1
0
Figure 3.2
index=0.9).
1000
2000
3000
4000
5000
Frequency (Hz)
6000
7000
8000
29
Two such filters, tuned at the 39th and 78th harmonic frequencies are used in
this project. They have the quality factors of 25 and 6.They inject 0.06 pu and
0.03 pu reactive power respectively. Other parameters are calculated in
Appendix A. The admittances of the filters are shown in as a function of
frequency.
Admittance of Filter #1 (Tuned at 1950 Hz)
Admittance (dB)
20
-20
-40
-60
Phase (deg)
90
45
0
-45
-90
2
10
10
10
Frequency (Hz)
30
Admittance (dB)
-10
-20
-30
-40
-50
-60
-70
Phase (deg)
90
45
0
-45
-90
2
10
10
10
Frequency (Hz)
(2.4)
31
Phase reactor (i) Terminal Voltages (ii) Voltage difference across the terminals
& (iii) Phase A current
kV
100
0
-100
0.1
0.102
0.104
0.106
0.108
0.11
0.112
0.114
0.116
0.118
0.12
0.102
0.104
0.106
0.108
0.11
kV
0.112
0.114
0.116
0.118
0.12
0.102
0.104
0.106
0.108
0.11 0.112
Time (s)
0.114
0.116
0.118
0.12
Vx (kV)
200
0
-200
0.1
Ia (kA)
1
0
-1
0.1
Figure 3.6 Phase reactor (i) Terminal voltages (ii) Voltage across the reactor and (iii)
current through the reactor
Figure 3.6 shows the ripple currents through a 19.3 mH phase reactor
driven by a VSC with 300kV dc link voltage at the switching frequency of
1950 Hz. A large phase reactor would mean better filtering and hence lower
current ripples. However, too high value would slow down the dynamics of the
converter. In this project a phase reactor of 0.12 pu size has been used.
32
In other words, is the time taken to charge the capacitors to the nominal
dc voltage levels, when it is charged by the rated current. For the VSC-HVDC
system, in this project a time constant of 2 ms has been used [43], [44]. This
gives the capacitor size of 35.5 F from each of the dc lines to the ground.
33
where,
(2.6)
Equation (3.5) is based upon the assumption that there are m number of
WTGs connected to the cable section m and each of them contribute the same
nominal current to the cable. The three feeders strings appear in parallel at the
34
, and susceptance,
(2.7)
,
35
36
Figure 3.9 Model of an aggregated wind turbine generator with its LCL filter and step-up
transformer.
37
(2.8)
, and
where,
, and
(2.9)
(2.10)
vwt
.
vwt .
vwt
.
vwt .
Figure 3.10 Proportional resonant current controllers for the WTG GSC.
38
1
2
3
2
1
2
3
2
(2.11)
The - axis is aligned with the axis of phase A while the -axis leads the
- axis by 90 For a set of balanced 3-phase positive sequence
, and
,
and
have the same magnitude as that of ,
voltages, ,
is in phase with
, and
lags
by 90. For a set of balanced 3-phase
, and
,
and
have the same
negative sequence voltages, ,
magnitude as that of
,
is in phase with
, and
leads
by 90.
A set of unbalanced voltages can be decomposed into balanced positive,
negative and zero sequence components. The zero sequence component is onethird of the sum of the three phase quantities. A method of separating the
positive and negative sequence components is described here.
The positive sequence components,
and
and the negative sequence
and
in the
axes are given by the transformations
components
(3.9) and (3.10) [51]
V
V
1 1
j V
2 j 1 V
1 1
1
2
(2.12)
(2.13)
39
40
2
0
Magnitude (dB)
3
-10
-20
3
1
-30
-40
-50
90
Phase (deg)
1& 3
0
2
-90
-180
0
10
10
10
10
Frequency (Hz)
2:
3: 0.5
2
2
(2.15)
2
(2.16)
2
At, the tuned frequency, , the gains are unity.
1 and
(2.17)
41
components can be calculated using (3.11) and (3.12). Then the filtered
positive sequence components can be applied to Parks transformation based
positive sequence phase locked loop (Figure 3.13).
(2.18)
42
converter
as expressed in,
(2.19)
(2.20)
43
(2.21)
(2.22)
The current references are given by the outer voltage control loop as follows,
(2.23)
44
Lim
Lim
45
46
Figure 3.16 Overall control structure of the WPP with VSC-HVDC connection
47
48
Table 4.1 Event list for the demonstration of the normal operating modes of the WPP with
VSC-HVDC connection
Time
0.00s
0.05s
0.20s
0.40s
0.50s
0.60s
1.40s
4.5s
5.40s
8.40s
9.60s
9.80s
10.40s
10.90s
4.1.2
Event
All CBs are open. All controllers are disabled
Onshore grid CB is closed. Pre-insertion resistance is 1k. By pass
resistance remains in circuit for 70ms.
The onshore VSC is de-blocked. Its controller is enabled.
The offshore VSC is de-blocked and its controller is enabled. The
offshore converter transformer is connected by the circuit breaker.
The WTG controllers are enabled.
The WTG1 CB is closed.
Power reference is set to 400MW. This power order gets divided to
the 4 aggregated WTG generators. Maximum rate of change of
power is 250MW/sec.
A single line to ground fault is applied at the point FA on the
feeder connecting WTG 4. (The fault is not a part of normal
operation. It is included here just to show that the complete control
system withstands a transient fault).
Power order is set to 0. Power order falls at the rate of 250MW/sec.
The WTG1 circuit breaker is opened.
The WTG voltages are set to 0. WPP circuit breaker is opened.
The offshore VSC is blocked.
Onshore VSC voltage reference is set to 0.
Onshore VSC is blocked and the onshore grid transformer is opened.
Energizing the Offshore Grid
After the VSC-HVDC voltage is stabilized, the offshore VSC is deblocked. Its controller ramps up the ac reference voltage and the offshore
voltage builds up gradually. When the nominal voltage levels have been
attained in the offshore-grid, the WTG cable strings are connected to the
collector bus sequentially to avoid oscillations. At this point of time the WPP is
fully energized, and the WTGs are ready for synchronization. Figure 4.2 shows
the voltage and current waveforms under these conditions. A small power
flows from the onshore grid to meet the no load losses.
49
4.1.3
The WTGs are running at rated voltage but with no load generation. The
WTG-GSC is controlled in stationary reference frame. The positive sequence
voltage is estimated from the terminal voltage using DSOGI filters and
synchronization is achieved using the frequency locked loop (FLL) [51],[52].
When the power generation picks up, the dc-link voltage regulation for the
WTG-FSC sets the power reference for the WTG-GSC. The actual power
control lies with the WTG and machine side converter controls. The reactive
power reference may be set by an auxiliary terminal voltage regulation loop or
it can be externally set. Positive sequence current references are generated from
the estimated positive sequence controllers and the active and reactive power
orders. Then they are implemented using the proportional resonant controllers
in the stationary reference frame.
1
0
Vac (pu)
-1
0
0.5
0.05
0.1
0.15
0.2
0.25
0.3
0.1
0.15
0.2
0.25
0.3
0.1
0.15
0.2
0.25
0.3
0.1
0.15
Time (s)
0.2
0.25
0.3
Iac (pu)
0
-0.5
0
1
0.05
Vdc (pu)
0.5
0
0
0.4
0.2
0
-0.2
0
0.05
Idc (pu)
0.05
Figure 4. 1 Energization of the VSC HVDC system. Vac is the filter bus voltage of the
onshore VSC-HVDC terminal, Iac is the current through the onshore phase reactors, Vdc is the
dc link voltage, and Idc is the dc line current.
50
1
Vac (pu)
0
-1
1.28
0.5
1.285
1.29
1.295
1.3
1.305
1.31
1.29
1.295
1.3
1.305
1.31
Iac (pu)
0
-0.5
1.28
1.01
1.285
Vdc (pu)
1
0.99
1.28
1.285
1.29
1.295
1.3
1.305
1.31
0
Idc (pu)
-0.05
1.28
1.285
1.29
1.295
Time (s)
1.3
1.305
1.31
0.05
Figure 4.2 Waveforms when the offshore collector grid is energized and the WTG units are
connected. Vac is the filter bus voltage of the onshore VSC-HVDC terminal, Iac is the current
through the onshore phase reactors, Vdc is the dc link voltage, and Idc is the dc line current.
1
0
-1
3.28
1
Vac (pu)
3.285
3.29
3.295
3.3
3.305
3.31
3.29
3.295
3.3
3.305
3.31
3.285
3.29
3.295
3.3
3.305
3.31
Idc (pu)
-1.1
3.28
3.285
3.29
3.295
Time (s)
3.305
3.31
0
Iac (pu)
-1
3.28
3.285
1.02
Vdc (pu)
1
0.98
3.28
-0.9
-1
Pg (pu)
3.3
Figure 4.3 Steady state operation at full load. Vac is the filter bus voltage of the onshore
VSC-HVDC terminal, Iac is the current through the onshore phase reactors, Vdc is the dc link
voltage, and Idc is the dc line current.
51
1
Pg (pu)
0.5
0
0
2
1
Pwtg1 (pu)
0.5
0
-0.5
0
2
1.5
1
0.5
Vdc (pu)
0
0
2
1.5
1
0.5 Idc (pu)
0
-0.5
0
2
10
10
10
10
Qwtg1 (pu)
4
Time (s)
Figure 4.4 Full operating range (with a single line to ground fault at 4.5 s).
4.1.4
Figure 4.3 shows the ac voltage and current waveform at the onshore VSCHVDC terminal when the WPP is generating nominal 1 pu power. The dc link
voltage ripple is less than 1%, while there is significant current ripple even at
nominal power ratings. Figure 4.4 shows that the WTGs have to absorb the
reactive power throughout the operating range as the collector grid is capacitive
in nature. It also shows the impact of a transient single line to ground fault of
150 ms duration at a 36 kV collector bus (for WTG#4). Power flow gets
disturbed for some time and power output from WTG #1 also gets affected.
High ripples are observed on the HVDC system during the fault, but they settle
down to nominal levels soon after the fault is cleared.
4.1.5
In this step the reference power to the WTGs are set to zero and the power
generation is ramped down. Then the whole plant is shut down in a controlled
way. First the WTGs are shut down, and then the offshore VSC-HVDC
terminal is blocked. Then the onshore VSC is blocked. The dc system has
52
trapped dc voltage which will take a long time to discharge by itself. Some
discharge resistors have to be connected to ensure a quick discharge.
53
active power available at the moment. The unit should be disconnected after 10
seconds if the frequency remains at or above 51.5 Hz.
Figure 4.6 Frequency regulation with and without previous downward regulation (Denmark
grid code [13])
4.2.2
54
55
56
1.005
Fgrid2
wn2
1
0.995
13
1.06
14
15
16
17
18
19
20
21
15
16
17
18
19
20
21
16
17
18
19
20
21
17
18
19
20
21
Vcc1est
1.03
1
13
1.005
14
FRMF
wn1
1
0.995
13
14
15
1.02
PMF
1
0.98
13
0.85
14
15
16
Ps1
Psg
0.8
0.75
13
14
15
16
17
18
19
20
21
Time (s)
Figure 4. 8 Frequency regulation through VSC-HVDC using the dc voltage and offshore
frequency for relaying change of dc voltage, offshore frequency and the power flows..
Figure 4. 8 and Figure 4.9 show the simulation results for this case. A
frequency change is simulated by introducing the step changes in the frequency
(Fgrid2) voltage source model for the onshore grid. The onshore grid PLL
measures the grid frequency (wn2). It is used to change the dc reference voltage
of the onshore VSC-terminal using a multiplication factor (DCVMF).
Consequently the HVDC voltage on the onshore terminal changes (Vdc2). The
offshore HVDC terminal voltage (Vdc1) changes as well. It is compared with
the nominal offshore voltage estimated (Vdc1est) for the measured load current
and the offshore frequency (wn1) is changed. The WTG-FSC then change the
power reference to the WTG-FSC as per the pre-set droop and frequency
regulation is achieved. The power generated and hence injected to the grid
changes as shown in the Figure 4. 8 It is represented by the curve FRC1 in
Figure 4. 10.
57
1.005
Fgrid2
wn2
0.995
13
1.02
14
15
16
17
18
19
20
21
15
16
17
18
19
20
21
DCVMF
1
0.98
13
14
1.05
1
Vdc2
0.95
13
14
Vdc1
15
16
17
18
19
20
21
15
16
17
18
19
20
21
1.06
Vdc1est
1.04
1.02
1
13
14
Figure 4.9 Frequency regulation through VSC-HVDC using the dc voltage and offshore
frequency for relaying change of dc voltage, and estimation of the voltage change.
58
0.8
FRC1
FRC2
FRC3
0.79
0.78
0.77
0.76
13
14
15
16
17
18
19
20
21
Figure 4. 10 Comparison of the power flow change as a result of frequency regulation using
the three methods.
(FRT)
Using
VSCHVDC
When there is a fault on the onshore ac grid, the AC grid voltage at the point
of common coupling (PCC) dips, thereby reducing the power transfer
capability from the onshore VSC-HVDC terminal. Power flow to the VSCHVDC can be rapidly controlled when it is connected to two strong power
system grids. However, when it is connected to a wind power plant, the rating
of the VSC-HVDC is the same as the wind power plant rating. The WPP power
generation cannot be brought down instantaneously. The excess power gets
accumulated in the VSC-HVDC system capacitance, thereby, leading to DC
over-voltage.
59
Chopper controlled resistor is used to dissipate the excess power and thus
limit DC voltage rise within safe levels, while the WTGs are signaled to
reduce their generation as quickly as possible [44]. It is installed in HVDC
Nord E.ON 1 (now referred as BorWin 1) to prevent DC over-voltages by
temporarily dissipating the excess power [53]. In variable frequency drives, it is
referred as braking resistor to dissipate the braking energy [54]. A similar
arrangement is provided in the WTG-FSC to limit the DC link over-voltages
[55]. In this section the performance of the chopper resistor in the FSC is
evaluated for controlling the HVDC system over-voltage during low voltage
faults in the onshore grid.
E.ON Grid Code requires that the WPP remain connected till the grid
voltage at the PCC drops down to 0% of the nominal levels for periods lasting
as long as 150ms, and inject reactive current to assist in the system recovery
[11]. As the fault is cleared and voltage starts building up, the WPP has to ramp
up active power supply.
Mathematically, the power transferred between the converter terminals and
the PCC bus is given by the power transfer relationship
where,
sin
(4.1)
is the
reactance between the converter and the grid. and indicate the voltage and
the voltage phase angle at the converter and grid terminals which are identified
by the subscripts c and g respectively. According to (4.1), the power transferred
from the converter to the grid will decrease to zero as the grid voltage
magnitude dips to zero due to the fault in the onshore grid. If Pwpp is the wind
power plant production being injected to the VSC-HVDC transmission and Ceq
is the equivalent capacitance of the dc lines and the capacitors in the VSCHVDC system, the dc voltage rise will be given by,
2
(4.2)
60
between 5 to 10% of the nominal value, the value of the chopper resistor is
given by,
1.1
(4.3)
The operation of chopper controlled resistor is similar in the case of the full
scale converters of the WTGs and the VSC-HVDC. Hence the equations 4.24.4 are applicable to all of them, with their respective ratings and limits.
Figure 4.11 Fault Ride Through (FRT) requirement of E.ON Netz Grid Code [11]
According to the E.ON Netz Grid Code [11], large generating stations of
sizes 100MW or larger must stay connected and provide voltage support to the
grid in the event of nearby faults for a period of up to 150ms as shown in
Figure 4.11. The generating unit must remain connected as long as the
operating point (voltage and duration) remains above the limit Line 2. A
conditional disconnection is allowed if it the operating point lies between Line
1 and Line 2. Further the generating plant should be capable of providing
voltage support during grid disturbances.
A reactive current of the order of 2 pu per pu voltage drop should be
injected when the voltage drops below the 10% dead-band [11] and absorbed
at the same slope for voltage rises as shown in Figure 4.12. As per the Grid
codes for the offshore generation plants, the dead-band is 5% at the point of
61
common connection which is considered the offshore point. In this project, the
VSC-HVDC is a dedicated transmission for the Wind power plant under study
and the point of common coupling is assumed at the onshore inverter station.
Figure 4.12 Reactive current injection requirement for voltage support during grid
disturbances.
62
Figure 4.13 FRT using fast communication to block the WTG-FSC when the onshore grid
voltage dips to 0.01 pu.
63
4.4 Discussion
Elimination of the chopper controlled resistors was proposed. However,
during the fault ride through, very large transient over-voltages were observed
even when the fast communication links of the order of 8 ms were used. It must
be noted here that the dc link capacitors were sized with a time constant of
2ms. In such a situation, elimination of the chopper resistors might prove to be
a more expensive solution. Having a chopper controlled resistors would limit
the over-voltage. However, by having a communication or relaying
mechanism, the size of the chopper resistors can be optimized.
4.5 Summary
This chapter described the different operating modes of the WPP with
VSC-HVDC connection. Enabling frequency control through the VSC-HVDC
link was demonstrated using the three methods described in literature. Since
frequency regulation is a slow phenomenon, all three methods were found to be
acceptable.
For fault ride through conditions, elimination of chopper resistors would
not be recommended as it leads to very high over-voltages. However, they
could be optimized for very short durations to take control of the transients.
When the chopper resistors are included, even the relaying methods using
frequency or voltage drop might be sufficient to tackle the fault ride through
conditions. However, these cases must be carefully analysed.
64
5.1 Introduction
Commercial wind turbine generators are of few MW unit size. Therefore, a
large wind power plant of a few hundred MW capacity deploys a few hundred
wind turbine generators. Large offshore wind power plants are spread over a
large area (e.g. 35 sq. km for the 300 MW Thanet Offshore Wind Farm in the
UK [57]). Since offshore maintenance work is expensive and time consuming
[26]; the protection system should be secure and reliable. Any fault in the
collector system will adversely affect power generation of the whole WPP.
Therefore, fault detection and isolation of the faulted sections to facilitate the
operation of the healthy sections is very important in offshore wind power
plants.
Protection of a radial feeder is a well-understood topic. In a conventional
radial feeder network, the coordination of over-current relays is conducted with
the knowledge of the rotating machines contributions to short circuit currents.
However, the offshore wind power plant collection grid is different as rotating
machines are connected to the grid through full-scale power electronic
converter interfaces. Such converters have limited short-circuit current
capability [58] in the range of 1.1 to 1.5 pu. Coordination of over-current relays
in such a radial collector system needs to be studied and validated. Further,
since an offshore grid is composed of a large number of closely laid short cable
sections, conventional distance protection logic is not applicable.
Most of the studies on WPP protection are focused on their response to grid
disturbances and low voltage fault ride through requirements imposed by the
grid operators [15], [58]-[60]. Several other studies address the impact of
distributed generation in distribution systems on the protection and relay
coordination in the distributed networks [61],[62]. Reference [63] describes a
65
III.
66
Relay co-ordination studies are done to set the pick-up current (Ipick-up) and
time dial setting such that proper discrimination is attained for the different
types and strengths of faults. As per, IEEE Std. C37-112 [66], the over-current
relay trip time, t(I), for the relay current transformer (CT) current I is given
by (5.1),
(5.1)
where,
19.61 ,
0.491 ,
2, for very inverse characteristics and
Ipick-up is the relay pick up current setting. The characteristic curve is shown in
Figure 5.1.
VeryInverseCharacteristicoftheOvercurrentRelay
PickupCurrentRatio(M)
4
3.5
3
2.5
2
1.5
1
0.5
0
0
0.1
0.2
0.3
0.4
0.5
RelayPickupTime(s)
Figure 5.1 Very inverse characteristics of the over-current relay (IEEE Std. C37-112) [67].
The trip time given by (5.1) is modified by the time dial setting to obtain
the actual trip time of the relay.
In a conventional relay coordination study the pick-up current is set-up on
the basis of short circuit analyses. High short circuit currents are observed in
conventional power systems and the relays are coordinated with other relays
such that they trip for the faults in their own zone. The trip time is adjusted by
using the time multiplier settings.
67
68
CaseI
CaseII
CaseIII
CaseIV
CaseV
CaseVI
Sources
I_HVDC
1.15
1.15
1.15
1.15
1.15
1.15
Iwtg#1
1.10
1.10
1.10
Iwtg#2
1.10
1.10
0.00
1.10
0.00
Iwtg#3
1.10
1.10
1.10
0.00
0.00
Iwtg#4
1.10
1.10
1.10
1.10
1.10
1.10
Faultcurrent
9.00
7.90
7.90
6.80
6.80
5.70
HV_CT
3.40
2.85
3.40
2.30
2.85
2.30
MV_CT
7.90
6.80
6.80
5.70
5.70
4.60
Faultcurrent
4.50
3.95
3.95
3.40
3.40
2.85
HV_CT
3.40
2.85
3.40
2.30
2.85
2.30
MV_CT
1.1
1.1
1.1
1.1
1.1
1.15
FaultatFA
FaultatFB
69
Fault
MV CT
HV CT
8
6
4
2
0
Figure 5.3 Estimated fault and CT currents for the short-circuit faults at FA and FB
Theoretically the HV feeder will carry the same fault currents for both the
fault locations. Though the fault currents are more than twice the nominal
currents, there is no discrimination for the faults on the MV feeder and the HV
feeder. Therefore, additional information like the voltage or sensing the pick-up
by the MV feeder relay might be used. In absence of such information, the HV
feeder may be set with higher time multiplier setting such that it trips in a
longer duration, with a margin long enough to ensure that the MV feeder relay
would have tripped its circuit breaker and the fault would have been isolated if
it were on the MV feeder. The HV feeder relay will also act as a back-up relay
for the MV feeder faults. It would be a slow relay for the faults on the HV
feeder.
70
In case of a fault on the MV feeder the fault, current from the HV side has to
pass through the three-winding transformer, which has high impedance on the
system MVA base. Therefore, the magnitude of the HV feeder voltage would
provide the necessary discrimination between the faults on the MV and HV
feeder sections. Assuming that the fault is on a MV feeder, and the transformer
impedance is 0.48 pu a 1.1pu current from the VSC-HVDC converter to the
fault on MV circuit would imply that the voltage on the transformer primary
remains around 0.53 pu. Relatively lower voltage is expected for a fault on the
HV cable section. The HV feeder voltage information may be used to
distinguish the MV feeder faults from the faults on the HV feeder.
On the basis of this analysis, the over-current relay pick-up current is
heuristically set at 1.25 pu levels for both the MV and HV feeder sections .The
trip time is multiplied by 8 ms for the MV feeder relay and it is multiplied by
16ms for the HV feeder relay.
The studies were carried out with fault resistance of 0.01 pu (1%) and 0.20
pu (20%).
Two separate faults were applied at the points FA on the MV WTG #4
and FB on the HV feeder #2 at the instants of 4 s and 5 s respectively. In this
study, the simulated faults were of transient nature, and they got cleared by
themselves in 150 ms. In some cases, when the relay took longer time to trip,
the fault duration was extended to 250 ms. Since the objective was to
demonstrate the relay performance, breaker tripping operation was not
simulated.
71
5.4.1
Figure 5.4 shows the output responses of the two over-current relays for the
two faults for case-I with 1% fault resistance. The MV relays tripped within
100 ms for a fault at FA. The maximum trip time for the HV relay was 139
ms for an LL fault at FB. The HV feeder relay tripped in 154 ms exhibiting
over-reach for a SLG fault on the MV feeder. In this case, the MV realy had
already tripped within 12ms and it could have been used to block the the HV
relay trip.
Figure 5.4 Outputs of over-current relays for the faults - (i) SLG, (ii) LLG, (iii) LLLG, and
(iv) LL applied at FA at the instant 4s; and at FB at the instant 5s. Fault resistance is 1%.
Figure 5.5 shows that relay trip time is longer when the fault impedance is
20%. The average trip time is 21 ms for the different faults at FA with fault
resistance of 1%; and it is 44 ms when the fault impedance is 20%. Similarly,
72
the relay trip time for the different faults at FB is 99 ms when the fault
impedance is 1%, and it is 146 ms when the fault resistance is 20%. The relay
trip times for different cases, different fault types and fault resistances of 1%
and 20% are shown in Tables 5.2 and 5.3 respectively.
Figure 5.5 Outputs of over-current relays for the faults - (i) SLG, (ii) LLG, (iii) LLLG, and
(iv) LL applied at FA at the instant 4s; and at FB at the instant 5s. Fault resistance is 20%.
The peak fault current T was 12.8 pu peak and 9.3 pu maximum RMS
(computed over 10 ms moving window) for the SLG fault at FA (Figure 5.6).
The MV feeder CT#4 recorded a fault current of 11.95 pu peak and 10.3 pu
RMS. For a fault at FB, the values were 1.90 pu peak and 1.36 pu RMS.
Similarly, the HV feeder CT#2 recorded a fault current of 3.52 pu peak and
2.98 pu RMS for a fault at FA. For a fault at FB, it recorded 7.65 pu peak and
4.76 pu RMS fault current.
73
Table 5.2 Max. Time (in ms) Taken By Over-Current Relays for Different Faults in
Different Cases
Fault
SLG
LLG
LLLG
LL
Relay
Case#1
Case#2
Case#3
Case#4
Case#5
Case#6
HV2
64
53
66
57
59
58
MV
12
12
12
13
13
14
HV2
71
90
64
92
82
95
MV4
12
12
12
13
13
17
HV2
113
140
115
129
128
129
MV4
26
26
28
27
27
32
HV2
139
136
112
131
125
129
MV4
37
26
26
26
25
32
HV2OverreachCases
SLG
HV2
154
149
130
LL
HV2
157
142
165
Table 5.3 Over-current relay trip time for different faults (Fault resistance = 0.20 pu)
Fault
SLG
LLG
LLLG
LL
Relay
HV2
Case#1
Case#2
Case#3
Case#4
Case#5
Case#6
114
115
90
121
93
100
MV4
48
47
21
46
47
47
HV2
99
111
83
186
123
175
MV4
40
40
20
41
41
45
HV2
135
142
99
250
159
293
MV4
55
59
37
65
67
76
HV2
146
179
151
185
175
191
MV4
36
35
31
34
34
35
155
HV2OverreachCases
SLG
LL
In the pu notation adopted here, the both the peak and the RMS values
should have been the same for sinusoidal current data. However, the RMS
values were found to be lower than the peak ones as the fault currents were not
sinusoidal. Comparing these results with the estimated results given in Table
5.4, it is found that the peak fault currents are higher than both the estimated
and simulated values for the three phase fault.
74
75
(FaultatFAon
MVFeeder)
(FaultatFBon
HVFeeder)
FaultCurrent
Base
(kA,rms)
Estimated
(pu)
Simulated
peak(pu)
Simulated
rms(pu)
Error%
Total
1.711
8.4
4.34
7%
MVCT#4
1.711
6.8
7.1
5.6
4%
HVCT#2
0.855
2.85
3.3
2.31
14%
27%
Total
0.855
4.5
6.1
3.1
MVCT#4
1.711
1.1
1.7
1.5
35%
HVCT#2
0.855
3.4
5.0
3.3
32%
76
The current waveforms are shown in Figure 5.8 and Figure 5.9. The active
current limit action of the VSC-HVDC is distinctly visible in both the figures.
The current waveforms show a very high content of harmonics during the
faulted condition.
77
5.4.2
Tables 5.2 and 5.3 reveal some of the cases when the relays on both the
MV feeder#4 and the HV feeder #2 tripped for the fault events on the MV
78
feeder #4. Figure 5.10 shows plots of an SLG fault in case-I with 0.01 pu fault
resistance.
The first subplot shows that the MV feeder relay tripped after 12 ms as
desired. The relay on the HV feeder also tripped after 154 ms in response to the
fault on MV feeder #4. While there was a time delay of 132 ms, this was not
the desired operation.
Such over-reach of the HV feeder relay can be avoided by changing the
relay pick-up current settings or time multiplier settings. However, the relay
79
characteristic will change for all the fault instances. Its sensitivity will decrease
if the pick-up current level is increased while the speed of operation will be
slower if the time multiplier setting is increased. For instance, if the time
multiplier setting is increased, the relay trip time will increase for all the fault
cases. Similarly, if the pick-up current setting is raised, the relay will lose
sensitivity to high fault impedance faults, as well as the trip will be delayed.
Considering the high impedance (0.12 pu on 112.5 MVA base appears as
0.24 pu on 225MVA base and 0.48 pu on 445MVA base) of the 3-winding
transformer interconnecting the MV and the HV feeders, faults on the MV
feeder are bound to result in a higher RMS voltage on the HV feeder as the
VSC-HVDC feeds the fault. Figure 5.10 also shows the RMS voltage at the HV
feeder terminal for the two fault conditions. It remained above 0.8 pu for the
fault at FA. It dropped down to a level of approximately 0.20 pu when the
fault was at FB on the HV feeder. Thus, RMS under-voltage level at the HV
bus can be used as a discriminator for the faults on the MV and HV feeders.
80
for numerical calculation. Another reason was the fact that the instantaneous
over-current limit control in the VSC-HVDC converter was achieved by
blocking the converters for one time period of the switching frequency as an
active current protection limit. On the other hand, the WTG converters were
blocked when their AC terminal voltage was lower than a predefined threshold
of low voltage limit (10% of the nominal was used here).
Synchronous machines are typically characterized by the sub-transient and
transient time constants, which indicate their response to short circuit
conditions. Simulation results emphasize that conventional fault analysis
techniques would not be applicable as the converter current response is
different from the rotating machines. Therefore, detailed EMT simulation
analysis with proper representation of the converter PLL and controller
dynamics is necessary for the thorough analysis of fault currents and relay coordination.
5.6 Summary
This chapter investigates the over-current relay coordination in offshore
WPP grid, which is connected to power electronic converters at all the
terminals. A simplified numerical approach to estimate the symmetrical fault
currents by using the current source representation of the WTG-FSC has been
proposed. Although, the EMT simulations showed had an error of upto 35% in
the estimated values, they trend was identical. Therefore, the numerical method
can be considered as preliminary evaluation of the fault currents and relay
coordination. EMT simulation with detailed model of the power electronic
converter controllers is necessary to obtain the actual fault currents under
different operating conditions and for different faults necessary for the precise
relay coordination.
The simulation results show that with proper parameter settings the
conventional over-current relays can be used for the detection and
discrimination of faults in the converter connected offshore grids. Limited fault
current capability of the converters can be exploited to estimate with the short
circuit current levels and determine the relay settings.
81
6.1 Introduction
There are plenty of power electronic voltage source converters (VSCs) in a
WPP right from the FSCs in the WTGs to the VSC-HVDC. The current
control capability of these converters can be utilized to control the negative
sequence current injection in the offshore WPP grid during unbalanced
operating conditions arising out of asymmetric faults.
Ref [68] presents the control of WTG-GSC during unbalanced grid
conditions. Rotating reference frame has been used for the implementation of
the current controller. This requires two separate controllers. The need for
power reduction during unbalanced grid conditions has been highlighted. Four
different control alternatives for the control of control of grid connected
converters under unbalanced voltage conditions have been described in [69]. A
three phase voltage source has been considered as the grid model which
produces sinusoidal waveforms even under unbalanced voltage conditions.
Control of the grid side converter (GSC) of a WTG-FSC using the sequence
components of currents is presented in [70],[71].
Analysis and control of VSC-HVDC system connecting two power system
grids was presented in [43], [72]. Negative sequence currents were injected to
achieve the predetermined power flow under the given unbalanced terminal
voltage conditions. Both these methods assumed that the power flow was
known in advance. However, in a VSC-HVDC connection to the wind power
plant, the power level depends upon the prevalent wind conditions, and it is not
known precisely. The VSC-HVDC terminal is controlled to maintain the
82
voltage reference like an infinite bus, such that the generated power can be
collected [73].
An offshore grid with WTG-FSC units and VSC-HVDC transmission is
different from the cases when at least one terminal is connected to the
conventional grid. Here all the terminals are connected to VSCs. The VSCHVDC converter sets up the reference voltage. During faults and unbalanced
operating conditions, they themselves may go in current limiting mode. Any
injection of the negative sequence current will also affect the offshore grid
voltage profile. This chapter presents a novel method of estimating the negative
sequence current injections by the VSC-HVDC to eliminate the power
oscillations. Prior information of active power flow is not required in this
method. Though the control approach have been described here with reference
to the VSC-HVDC with two level converters, it is also applicable to the multilevel converters as their interaction with the grid remains similar as far as
current injection control is concerned [39].
(6.1)
where,
, , , and are the components of the fundamental frequency
voltage (V) and current (I) along the
axes in the stationary reference
frame.
It can be expanded and written in the matrix form as shown in (6.2) after
separation of real and imaginary parts.
(6.2)
and
are the average real and reactive power. The terms for
where,
are just the real and imaginary parts of the terms involving both the
and
positive and negative sequence components in the power expression. These
terms do not explicitly imply the oscillations in active or reactive power, but
merely their combination. These are different from those given in [70], [71].
83
(6.4)
(6.5)
84
current references are generated and added to the positive sequence current
references. The positive and negative sequence voltage references for the
converter cannot be added directly as they are the reference frames are rotating
in opposite directions. Hence, the two sets of voltage references are converted
into the phase variables by using inverse Parks transformation and then added
together as shown in Figure 6.1(c)
(6.6)
(6.7)
where, , ,
are the positive and negative sequence current
references. The overall current references are given by (6.8) and (6.9),
(6.8)
(6.9)
When the NSCC is not enabled for the WTG-GSC, the current references
are given by (6.10) and (6.11),
(6.10)
(6.11)
85
Lim
Lim
+
-
86
Figure 6.1. Offshore VSC-HVDC controller with negative sequence current controller.
87
to ground fault was studied in detail. Then other types of faults at FA and
FB were studied.
Since the negative sequence controllers can be applied in the WTG-GSCs
and the offshore VSC-HVDC controllers, four combinations arise as given
below:
1.
Figure 6.2 shows the effect of the negative sequence current controllers on
the dc over voltage in the VSC-HVDC transmission system. The peak DC line
voltage overshoot was 1.25 pu for the case W1H1 while it was 1.42 pu, 1.46
pu, and 1.52 pu for the cases W1H0, W0H1, and W0H0 respectively.
88
Figure 6.2 DC link voltage over-shoot in the VSC-HVDC system for SLG fault at FA.
The effect of these controllers on power flow to the HVDC system is shown
in Figure 6.3. The power flow was less oscillatory when the NSCC was
enabled, although the average power. It was found that the WTG-GSC went
into current limit control mode, and the current references given by NSCC were
scaled down, thereby limiting the output power during the fault. This was the
price for the reduction in peak voltage oscillations observed in Figure 6.2. The
excess power which could not be evacuated to the VSC-HVDC would have to
be dissipated in the WTG-FSC chopper resistors. Power and voltage
oscillations were higher and the damping was poor when the NSCC in the
WTG-GSC was disabled.
89
Figure 6.3. Power flow to the offshore VSC-HVDC terminal during the SLG fault at FA
(i) W1H1 (ii) W0H0. (iii)W1H0 (iv) W0H1
Figure 6.4 shows the three phase voltage waveforms at the filter bus of the
offshore VSC-HVDC for the four cases. A comparison of the cases W1H1 and
W0H1 against W1H0 and W0H0 reveals that negative sequence controllers on
the VSC-HVDC are more effective in eliminating the high frequency
oscillations from the voltage waveforms. Enabling the NSC on the WTG-GSC
has a small impact in reducing these oscillations. The transient peak ac voltage
is reduced to 1.32 pu for the case W1H1 from 2.49 pu for the case W0H0. A
comprehensive summary of the peak dc voltage overshoot, minimum power
flow and the ac voltage transient peaks is presented in Table 6.1.
90
Figure 6.4. Grid voltage at the offshore VSC-HVDC terminal during the SLG fault at FA
(i) W1H1 (ii) W1H0. (iii) W0H1 and (iv) W0H0
91
Table 6.1 Effect of NSCC on the peak values of voltages, currents and power flow during SLG fault at FA
W1H1
p.u.Max
p.u.Min
Case
DClinevoltageVDC
PowerflowtoVSCHVDC
ACvoltage(atHVDCfilters),Ph.A
ACvoltage(atHVDCfilters),Ph.B
ACvoltage(atHVDCfilters),Ph.C
Neg.Seq.daxiscurrent
Neg.Seq.qaxiscurrent
1.25
0.97
1.31
1.17
1.22
0.57
0.21
0.70
0.39
1.32
1.18
1.21
0.18
0.31
W1H0
p.u.Max
p.u.Min
1.42
0.97
2.36
1.63
2.47
0.73
0.21
0.67
0.28
2.20
2.00
2.19
0.08
0.37
W0H1
p.u.Max
p.u.Min
1.46
1.11
1.97
1.46
2.06
0.75
0.21
W0H0
p.u.Max
p.u.Min
0.77
0.57
1.87
1.68
2.11
0.00
0.40
1.52
0.99
2.37
1.46
2.40
0.83
0.21
0.59
0.34
2.49
1.61
2.40
0.00
0.48
Table 6.2 Effect of NSCC on the peak values of DC voltage overshoot and power flow during different faults.
Fault
Location
Case
DClinevoltageVDC
PowerflowtoVSCHVDC
DClinevoltageVDC
PowerflowtoVSCHVDC
W1H1
W0H0
W1H1
W0H0
W1H1
W0H0
W1H1
W0H0
FA
FB
SLG
p.u.Max p.u.Min
1.25
1.52
0.97
0.99
1.39
1.34
1.00
0.95
0.70
0.59
0.39
0.34
0.71
0.62
0.46
0.17
LLG
p.u.Max p.u.Min
1.18
0.75
1.12
0.66
0.96
0.05
0.96
0.03
1.09
0.67
1.10
0.75
0.96
0.08
0.95
0.18
LLLG
p.u.Max p.u.Min
1.21
0.58
1.22
0.67
0.96
0.1
0.96
0.01
1.07
0.67
1.07
0.70
0.96
0.09
0.95
0.11
LL
p.u.Max p.u.Min
1.31
0.59
1.30
0.72
0.96
0.26
0.96
0.08
1.24
0.73
1.25
0.75
0.99
0.53
0.95
0.26
92
Figure 6.5. Negative sequence d and q axes currents during the SLG fault at FA
Though the same positive sequence controllers were used in both cases,
enabling the negative sequence components led to a reduced level of current
oscillations in the positive sequence current (Figure 6.6). This signifies an
overall improvement in the system performance.
93
Figure 6.6. Positive sequence d and q axes currents during the SLG fault at FA
When the NSCC were enabled, positive and negative sequence components
of the filter bus voltages were less oscillatory, though the magnitude of the
negative sequence voltage components increased (Figure 6.7). The positive
sequence voltage on the d-axis reaches a minimum of 0.82 pu in case of W1H1
while it falls down to 0.52 pu in W0H0. The positive sequence q-axis voltage is
limited within -0.15 pu and 0.17 pu in the case of W1H1 while it varies
between -0.37 and 0.48 pu in the case of W0H0.
94
Figure 6.7. Positive and negative sequence d- and q axes voltage components for the SLG
fault at FA
6.4.2
The dc voltage overshoot for the different fault cases, namely. LLG, LLLG
and LL faults at the point FA are shown in Figure 6.8. For all these cases,
there was no improvement in minimizing the dc over-voltage. The overvoltages were observed to be lower than the one which appeared in the case of
SLG fault described earlier.
95
Figure 6.8. DC voltage overshoots in the VSC-HVDC lines for different faults at FA
Figure 6.9 shows the power flow to the offshore VSC-terminal during the
different faults in the offshore collector grid at point FA. The power transfer
96
to the VSC-HVDC system was higher during the fault and the post fault
recovery in the case of LL fault. For other faults, the difference in power
transfer was small.
The LLLG fault is a symmetrical fault. The negative sequence current
control was not expected to have any contribution in such faults. It was
included here to show that the results did not deteriorate. Table 6.2 gives a
summary of the extremes of the dc voltage and power flow to the VSC-HVDC
during the fault at FA and FB.
Figure 6.9. Power flow to the offshore VSC-HVDC terminal during different faults at 'FA'.
6.4.3
Faults at FB
The effect of the NSCCs was studied for the different faults at the ac
terminals of the converter transformers (FB). Soon after the fault event, the
NSCC in WTG-GSC got blocked as the denominator of (6.6, 6.7) came close to
0 and hence only positive sequence current were injected in this case (similar to
W0H1). Figure 6.10 shows that the dc voltage overshoot was rather higher in
the case W1H1 than in W0H0. The case W1H1 was more oscillatory during the
97
faulted period. However, the post fault oscillations were lower in the case
W1H1 than in the case W0H0. The power flow to the VSC-HVDC terminal
during the SLG and LL faults was improved by the NSCC control (Figure
6.11).
Figure 6.12 shows the ac voltage waveforms at the VSC-HVDC filter bus
and the ac current waveforms of the converter. By allowing the negative
sequence current control, the converter generated the unbalanced ac voltage
waveform with a low harmonic content. The ac current was unbalanced, but it
allowed the flow of power transfer. When the NSCC was disabled, a lot of
hamronics were generated as the converter attempted to maintain a balanced
sinusoidal voltage profile in the network with asymmetrical fault.
98
Figure 6.10. DC link voltage over-shoot in the VSC-HVDC system for SLG and LL faults
at FB.
99
Figure 6.11. Power flow to the offshore VSC-HVDC terminal for SLG (i) W1H1, (ii)
W0H0 and LL faults (iii) W1H1 and (iv) W0H0 at FB.
6.5 Discussion
The simulation results in the previous section show that the NSCC was
effective in reducing the dc voltage oscillation in the case when the fault was at
FA. When the fault was at FB, there was an enhancement in the power flow,
though there was no improvement in reducing the maximum dc voltage
overshoot. Rather, it increased to 1.39 pu from 1.34 pu in the case of an SLG
fault at FB. However, this should be viewed together with the significant
increase in the power flow to the VSC-HVDC terminal during the fault.
Further, better damping of oscillation was observed after the fault had been
cleared.
100
Figure 6.12. Filter bus voltage and the converter ac currents of the offshore VSC-HVDC
terminal during the LL faults for the two cases W1H1 and W0H0.
On the other hand for the MV feeder faults at FA, enabling the NSCC in
WTG-GSC decreased the average power flow as observed in the comparison of
power flow in the cases W1H1 and W1H0 against W0H1 and W0H0 (Figure
6.3). This was due to the fact that the overall current references demanded by
NSCC as per (6.6, 6.7) exceed the limit and therefore they went into current
limit mode. For the SLG and LL faults at FB, the NSCC got blocked soon
after the fault inception, thereby resulting in the higher power transfer. When
the fault was cleared the NSCC in the WTG became active again and assisted
in damping the oscillations.
Although NSCC affected the overall negative sequence current
components, there was a persistent error between the negative sequence current
references and the actual negative sequence current flow. The fundamental
101
reason for such a persistent error is a topic for further research. Perhaps the
unbalanced grid network during the asymmetrical faults was more crucial in
determining the negative sequence current flow. When the NSCC acted to
restrain the negative sequence current components, both the positive and
negative sequence components of the voltage as well as the positive sequence
current components got modified. The negative sequence voltage increased
when the NSCCs were enabled. The average power flow balance was the result
of all these voltage and current components.
6.6 Summary
Negative sequence current injection control strategy has been formulated
here for the peculiar case when the power reference for the VSC-HVDC
converter is not known. The strategy has been implemented in the simulation
model of an offshore wind power plant grid. Simultaneously the WTG
converters have been provided with the negative sequence current control
scheme to eliminate the oscillations in the active power.
The simulation results prove that even though the converter controller had
a persistent error in tracking the computed negative sequence current
references, the negative sequence current control was effective enough to
reduce the peak of the dc voltage oscillations during asymmetric faults. Post
fault oscillations decayed fast when the NSCCs were enabled It was found that
the NSCC on the VSC-HVDC converters were more effective in minimizing
the dc voltage overshoots from 1.52 pu peak to 1.25 pu peak in the case of SLG
fault. They were also effective in the reduction of high frequency component in
the filter bus voltage. Negative sequence current control in the WTG-GSC
converter assisted in decreasing the dc voltage and power oscillations.
However, the average power transfer level also decreased as the current levels
were hitting the limits.
102
7.1 Introduction
Computer simulation provides a lot of insight into the real world
phenomena. However, the simulation models are idealized to some level as all
physical details cannot be modelled and simulated. For instance, the
communication time lag, inherent filtering and delay present in data acquisition
or even stray parameters and noises may affect the interaction between the
physical equipments in a power system. Transient network analyzers (TNA)
were developed to build an analog equivalent model of the power system such
that the switching phenomena on the transmission lines could be studied.
Multiple pi-sections using inductors and capacitors were used to model the
transmission lines, and circuit breakers were modelled by switches to simulate
the electromagnetic characteristics in the scaled analog equivalent. Attempts
were made to use digital computers to facilitate the simulation [76].
With the development of computer technology the simulation programs
have become more detailed and very large system can be handled. Even then, it
is of prime importance to test a physical piece of hardware and its numerous
interactions with the power system under different operating conditions.
Real Time Digital Simulator (RTDS) allows digital EMT simulation of
power system in real time with a typical time step of 50 s. [77]. Power
electronic converters can be simulated with a small time step of around 2-3 s.
Physical hardware devices like relays or controllers can be interfaced with the
simulation and their performance can be simulated as demonstrated.
103
This chapter describes the use of RTDS connected with a physical relay to
assess the performance of the relay protection coordination. In chapter 5, a
coordination method based on estimated nominal current and fault current
levels were proposed and simulated in PSCAD/EMTDC. The RMS values of
the relay CT currents were calculated and applied to over-current relay models.
This chapter presents a realistic approach as the relay current transformer have
been modelled in the simulation and the actual current waves obtained from the
amplifier were applied to an industrial ABB overcurrent relay for feeder
protection (REF615).
The IED supports the IEC 61850 standard for GOOSE communication.
The relay settings can be programmed using the PCM600 relay interface
104
software. The relay pick-up (start) and trip (operate) signals can be
communicated to the RTDS simulation using the GTNET-GSE cards from the
RTDS. Similarly, the relay trip functions can be selectively programmed and
blocked by communicating GOOSE signal bits from the RTDS.
7.2.1
In this study the grid side inverters in the WTG were modeled as PWM
switching inverters. The positive sequence terminal voltage was extracted using
second order generalized integrator (SOGI) filters and then a positive sequence
phase locked loop (PLL) is used as shown in Figure 3.13 [51]. Vector control
in rotating reference frame is used to control the inverter for the specified
active power. The reactive power is controlled so as to maintain the nominal
voltage across the capacitor of the LCL filter.
7.2.2
Active current limits are imposed by blocking the converter gate pulses
during when the measured RMS currents exceed the pre-defined converter
current limits and the blocking is continued as long as the limit is violated.
105
(Figure 7.3). Their respective PI controller is disabled during the period when
the converter is blocked.
Inverse
Parks
Transform
7.2.4
106
112.5
3. 36
1804
1: 400
5 /100
5 /1
1600: 1
1 ,
1804
1.1275
1.1275
1600
1.25
1.41
0.05
40 .
225
3. 150
866
1: 200
5 /100
5 /1
800: 1
1 ,
866
1.0825
1.0825
800
1.25
1.353
0.05
40 .
107
PHIPTOC1.Str
PHIPTOC1.Op
PHLPTOC1.Str
PHLPTOC1.Op
EFHPTOC1.Str
EFHPTOC1.Op
DEFHPTOC1.Str
DEFHPTOC1.Op
108
7.4.1
Figure 7.4 shows the dc voltage, power and current waveforms during the
steady state operation of the wind power plant and VSC-HVDC. While the
total harmonic distortion for the dc voltage was 6.5%, the peak to peak ripple
was within 3% of the nominal. The 4 aggregated WTG were generating 0.85,
0.86, 0.87 and 0.88 pu active power (on 100 MW base).
VDC1
kV
310
305
300
295
VDC2
310
kV
305
300
295
290
PG1 PG2 PG3 PG4
-82
MW
-84
-86
-88
-90
PHVDC1
MW
342
340
338
336
PHVDC2
-318
-320
MW
-322
-324
-326
-328
0
0.06667
0.13333
0.2
0.26667
0.33333
0.4
Figure 7.4. Steady state results (in pu) (i)HVDC voltage at offshore terminal (ii) HVDC
voltage at the onshore terminal (iii) Power generated by the 4 WTGs (v) Power transmitted to the
offshore VSC-HVDC terminal (vi) Power transmitted by the onshore VSC-HVDC terminal
109
Figure 7.5 Voltage signal at the GTAO output and the overlapping current signal output of
the Amplifier
110
Figure 7.6 DC voltage and power flow during SLG fault on MV feeder. Corresponding
curves from PSCAD simulation is included for comparison.
111
Figure 7.7 Comparison of the RTDS and PSCAD current waveorms during SLG fault at
FA.
112
FaultNumber:38/TimeandDate:29.9.201101:34:58.141
Start duration.................100.....%
Setting group....................1......
Max current IL1..............6.968...xIn15.76kA,pk
Max current IL2..............0.998...xIn 2.26kA,pk
Max current IL3..............0.999...xIn 2.26kA,pk
Current IL1...................6.45...xIn14.59kA,pk
Current IL2..................0.739...xIn 1.67kA,pk
Current IL3..................0.879...xIn 1.99kA,pk
Current Io.......................0...xIn
Current Io-Calc..............7.398...xIn16.74kA,pk
Current Ps-Seq...............2.258...xIn 5.11kA,pk
Current Ng-Seq...............1.769...xIn 4
kA,pk
113
Trip
Pick-up
114
7.4.3
A line-to-line (LL) fault was simulated on the MV feeder. The fault current
and the input currents to the relays (i.e. the secondary current of the
corresponding CT) for the LL fault on the MV feeder are shown in Figure 7.9.
The relay pick-up and trip timings for different faults on the MV feeder are
shown in Figure 7.10.
Trip
Pick-up
Figure 7.9. LLG Fault on MV Feeder at 'FA' (i) Fault current (Ph. A & B) (ii) Relay trip
signal.(iii) Secondary current (in A) of the CT on the faulted MV feeder. (iv) Secondary current
(in A) of the CT on the HV feeder.
115
MVFeederRelayTime
Trip
Pick-up
Start
Trip
SLG
0.011
0.076
LLG
0.013
0.085
LLLG
0.012
0.169
LL
0.016
0.121
LLLG
0.015
0.112
Figure 7.10 Trip times for the different faults on the MV feeder.
7.5 Discussion
This chapter presents the experimental set-up for the validation of the overcurrent relays in the collector grid networks of a large wind power plant with
VSC-HVDC connection to the grid. The results have been compared with the
simulated results in PSCAD and those recorded in the relay IED. The purpose
was to validate and extend the simulated results observed in Chapter 5.
Though experiments have been successful for the detection of faults in the
MV cable feeders using the low stage three phase non-directional over-current
relays, the relay trip times are considerably longer than the very fast detection
times observed in Chapter 5. One reason that the relay has some minimum
settings, like the operate delay time of 40ms, which cannot be
modified. Even the time multiplier cannot be smaller than 0.05, whereas in
simulation 0.008 and 0.016 were used as time multipliers. Another difference
was the attenuation of the RMS current signal in the relay and its high
frequency components as it had to pass through several stages like the GTAO
card, amplifier and the relay interface. This shows some of the realities of the
physical world.
The performance and discrimination can be further enhanced using the other
available protective functions like the high stage over-current relays, the
116
instantaneous overcurrent relay and the earth fault over-current relay. The
communication capability of the relays can be exploited and tested to avoid the
over-reach conditions as seen in Chapter 5. The experimental set up is ready
and the study will be extended to come out with a more comprehensive
protective solution.
Some problems were observed in the setting of the over-current relay for the
HV feeders in the wind farm. There was no problem in detecting the SLG
faults, but the other faults did not produce a trip in the 150ms fault duration. It
was therefore concluded that the relay settings need be fine-tuned further
exploiting other protective functions. Moreover, in certain instances, the HV
feeder relay would be tripping for the fault in the MV feeder. The blocking
signal generated by the start of the MV feeder relay was used to disable the HV
feeder relay. However, these studies have not been included here as they need
further analysis and investigation. The experimental set-up provides a platform
to program the relay functions and test them using real time simulation.
7.6 Summary
The experimental set-up for the testing of the offshore grid relay
coordination has been described in this chapter. The results are compared
against the PSCAD simulation results and the relay IED as well. The relay
tripping behaviour for the faults on the MV feeder has been recorded and that
corroborates the proposed settings.
117
8.1 Conclusions
A new controller algorithm for the offshore VSC-HVDC converter has
been proposed. It is an adaptation of the standard vector control structure for
establishing the sinusoidal balanced voltage at controllable frequency in the
offshore wind power grid. The power flow order to the VSC-HVDC is not
available beforehand and this controller is applicable to the wind power
generation system where the power generation is not explicitly known
beforehand. The vector control scheme is adapted for the purpose of
establishing the desired voltage profile in the offshore grid such that a kind of
infinite voltage bus is created for the wind turbine generators to get
synchronized to. The robustness of the controller is apparent from the
numerous fault studies done on the test system.
Faults in the offshore wind power collection grid have been investigated
through electromagnetic transient simulations in PSCAD/EMTDC. A detailed
layout of the test wind power plant system with collector grid and VSC-HVDC
connection the onshore grid is developed in Chapters 3 and 4. Faults are
simulated in the collector grid and an approximate fault current estimation
method on the basis of scalar current sources has been proposed. An offshore
grid protection scheme using over-current relays has been proposed and
demonstrated through PSCAD/EMTDC simulations in Chapter 5. The results
are further corroborated through a real time simulation in RTDS with an
industrial relay from ABB. The RTDS simulation model and hardware in loop
configuration with IEC 61850 process bus communication set-up can be used
to investigate the different control and protective features of modern numerical
relays.
The system is designed for three phase balanced positive sequence
operation. However, asymmetric faults may lead to unbalanced voltage
conditions and current flows. In Chapter 6, the unbalanced voltage and currents
118
are separated into the positive and negative sequence components and an
expression for the power oscillation has been derived. Negative sequence
current controller for the offshore VSC-HVDC system has been formulated
using the estimated positive sequence current, and both positive and negative
sequence voltage. The controller performance in minimizing the dc voltage
oscillations is demonstrated through EMT simulations. The controller can
remain active all the time, but its affects the system only when there is negative
sequence voltages in the system.
119
120
121
122
References
[1] European Wind Energy Association, Pure Power Wind Energy Targets for
2020 and 2030, 2009 update. Available at: http://www.ewea.org
[2] Global Wind Energy Council, Global Wind Report Annual market
update 2010,, April 2010. Available at: http://www.gwec.net
[3] P. Bresesti, W. L. Kling, R. L. Hendriks, and R. Vailati, HVDC
Connection of Offshore Wind Farms to the Transmission System, IEEE
Transactions on Energy Conversion, vol. 22, no. 1, pp. 37-43, Mar. 2007.
[4] S. K. Chaudhary, R. Teodorescu and P. Rodriguez, "Wind Farm Grid
Integration Using VSC Based HVDC Transmission - An Overview,"
Energy 2030 Conference, 2008. ENERGY 2008. IEEE, pp. 1-7, 2008.
[5] N. Flourentzou, V. G. Agelidis and G. D. Demetriades, "VSC-Based
HVDC Power Transmission Systems: An Overview," Power Electronics,
IEEE Transactions on, vol. 24; 24, pp. 592-602, 2009.
[6] K. Eriksson, C. Liljegren and K. Sobrink, "HVDC light experiences
applicable for power transmission from offshore wind power parks," in
42nd AIAA Aerospace Sciences Meeting and Exihibit, Reno, Nevada. 2004.
[7] L. Harnefors, "Control of VSC-HVDC transmission," in Tutorial Presented
at the IEEE PESC, Rhodos, Greece, Jun 15-19, 2008. 2008.
[8] F. Iov, P. Sorensen, A. -. Hansen and F. Blaabjerg, "Grid connection of
active stall wind farms using a VSC based DC transmission system,"
Power Electronics and Applications, 2005 European Conference on, pp. 10
pp., 2005.
[9] C. Feltes and I. Erlich, "Variable Frequency Operation of DFIG based
Wind Farms connected to the Grid through VSC-HVDC Link," Power
Engineering Society General Meeting, 2007. IEEE, pp. 1-7, 2007.
[10]
L. Xu, B.W. Williams, and L. Yao, Multi-terminal DC transmission
systems for connecting large offshore wind farms, 2008 IEEE PES
General Meeting - Conversion and Del. of Electrical Energy in the 21st
Century, IEEE, 2008, pp. 1-7.
[11]
Grid Code for High and Extra High Voltage, E.ON Netz GmbH
Bayreuth,April 1, 2006.
[12]
Requirements for Offshore Grid Connections in the E.ON Netz
Network, E.ON Netz GmbH Bayreuth, April 1, 2008.
[13]
Wind Turbines Connected to Grids with Voltages above 100kV
Technical regulation for the properties and the regulation of wind turbines,
123
124
125
[35]
T. Ackermann, Transmission Systems for Offshore Wind Farms, in
Wind Power in Power Systems, Ed. T. Ackermann, Chicester, U.K. Wiley,
2006.
[36]
http://www.tennettso.de/pages/tennettso_en/Tasks/Offshore/Our_proje
cts/index.htm
[37]
B. Normark and E. K. Nielsen, Advanced power electronics for cable
connection of offshore wind, presented at the Copenhagen OffshoreWind
Conf., Copenhagen, Denmark, Oct. 2628, 2005
[38]
T. Ahndorf, R. Witzmann, and S. Bopp, The German offshore gridA
successful integration of offshore wind power, in European Offshore
Wind Conference, 2007, December, pp. 4-6.
[39]
U. N. Gnanarathna, S. K. Chaudhary, A. M. Gole and R. Teodorescu,
Modular Multi-level converter based HVDC System for Grid Connection
of Offshore Wind Power Plant, in Proc. of the 9th International
Conference on AC and DC Power Transmission 2010.
[40]
U. N. Gnanarathna, S. K. Chaudhary and A. M. Gole, Multilevel
Modular Converter for VSC-HVDC Transmission Applications: Control
and Operational Aspects, in Proc. of the 16th National Power Systems
Conference, NPSC 2010. Osmania University, 2010. pg. 405-410
[41]
U. N. Gnanarathna, A. M. Gole, A. D. Rajapakse, and S. K.
Chaudhary, Loss Estimation of Modular Multi-Level Converters using
Electro-Magnetic Transients Simulation IPST 2011, Delft, The
Netherlands.
[42]
D. G. Holmes and T. A. Lipo, Pulse Width Modulation for Power
Converters: Principles and Practice, John Wiley & Sons, Inc., 2003.
[43]
C. Du, VSC-HVDC for Industrial Power Systems, Ph.D Thesis,
Chalmers University of Technology, Gteborg, Sweden 2007.
[44]
P. Sandeberg and L. Stendius, Large scale offshore wind power
energy evacuation by hvdc light, European Wind Energy Conference &
Exhibition, 2008.
[45]
IEEE PES wind plant collector system design working group Wind
power plant collector system design considerations, IEEE, 2009.
[46]
E. Muljadi, C.P. Butterfield, a Ellis, J. Mechenbier, J. Hochheimer, R.
Young, N. Miller, R. Delmerico, R. Zavadil, and J.C. Smith,
Equivalencing the collector system of a large wind power plant, 2006
IEEE Power Engineering Society General Meeting, 2006, p. 9 pp.
126
[47]
R. van de Sandt, J. Lowen, J. Paetzold, and I. Erlich, Neutral earthing
in off-shore wind farm grids, 2009 IEEE Bucharest PowerTech, pp. 1-8,
Jun. 2009.
[48]
C. Feltes, R. van de Sandt, F. Koch, F. Shewarega, and I. Erlich,
Neutral grounding in wind farm medium voltage collector grids, in 2011
IEEE/PES Power Systems Conference and Exposition, 2011, pp. 1-7.
[49]
A. S. Locker and M. S. Scarborogh, Safer and Smarter Systems,
IEEE Industry Applications Magazine,Vol. 16, No. 5, Sep-Oct 2010.
[50]
E.R. Detjen and K.R. Shah, Grounding transformer applications and
associated protection schemes, IEEE Transactions on Industry
Applications, vol. 28, 1992, pp. 788-796.
[51]
P. Rodriguez, A. Luna, M. Ciobotaru, R. Teodorescu, and F. Blaabjerg,
Advanced Grid Synchronization System for Power Converters under
Unbalanced and Distorted Operating Conditions, in IECON 2006 - 32nd
Annual Conf. on IEEE Ind. Electron., 2006, no. 2, pp. 5173-5178.
[52]
P. Rodriguez, A. Luna, I. Candela, R. Mujal, R. Teodorescu, and F.
Blaabjerg, Multiresonant Frequency-Locked Loop for Grid
Synchronization of Power Converters Under Distorted Grid Conditions,
IEEE Transactions on Industrial Electronics, vol. 58, no. 1, pp. 127-138,
Jan. 2011.
[53]
ABB review 4/2008: The future is now (on the offshore HVDC light
link NordE.ON 1, germany). Available: http://www.abb.com/
[54]
N.. Mohan, T. M. Undeland and W. P. Robbins, Power
ElectronicsConverters, Applications, and Design;,3rd ed., NJ: John Wiley
& Sons, 2003.
[55]
J. Conroy and R. Watson, "Aggregate modelling of wind farms
containing full-converter wind turbine generators with permanent magnet
synchronous machines: transient stability studies," Renewable Power
Generation, IET, vol. 3, pp. 39-52, 2009.
[56]
A. A. van der Meer, R. L. Hendriks, and W. L. Kling, A survey of fast
power reduction methods for VSC connected wind power plants consisting
of different turbine types, in 2nd EPE Wind Energy Chapter Seminar,
KTH, Stockholm, 23-24 April, 2009.
[57]
S. Patel, GLOBAL MONITER, Power;, Vol. 154 Issue 11, pp. 8-15,
Nov. 2010.
[58]
D. Turcotte and F. Katiraei, Fault contribution of grid-connected
inverters, in 2009 IEEE Electrical Power & Energy Conference (EPEC),
2009, pp. 1-5.
127
[59]
G. Ramtharan, a Arulampalam, J. B. Ekanayake, F. M. Hughes, and N.
Jenkins, Fault ride through of fully rated converter wind turbines with AC
and DC transmission systems, IET Renewable Power Generation, vol. 3,
no. 4, p. 426, 2009.
[60]
A. D. Hansen and G. Michalke, Multi-pole permanent magnet
synchronous generator wind turbines grid support capability in
uninterrupted operation during grid faults, IET Renewable Power
Generation, vol. 3, no. 3, p. 333, 2009.
[61]
E. J. Coster, J. M. A. Myrzik, B. Kruimer, and W. L. Kling,
Integration Issues of Distributed Generation in Distribution Grids,
Proceedings of the IEEE, vol. 99, no. 1, pp. 28-39, Jan-2011.
[62]
S. M. Brahma and A. A. Girgis, Development of Adaptive Protection
Scheme for Distribution Systems With High Penetration of Distributed
Generation, IEEE Transactions on Power Delivery, vol. 19, no. 1, pp. 5663, Jan. 2004.
[63]
H. J. Laaksonen, Protection Principles for Future Microgrids, Power
Electronics, IEEE Transactions on, vol. 25, no. 12, pp. 2910-2918, 2010.
[64]
J. Cardenas, V. Muthukrishnan, D. McGinn, and R. Hunt, Wind farm
protection using an IEC 61850 process bus architecture, in 10th IET
International Conference on Developments in Power System Protection
(DPSP 2010). Managing the Change, 2010, p. P10-P10.
[65]
P. Christiansen, K. Jrgensen, and A. Srensen, Grid connection and
remote control for the Horns Rev 150 MW offshore wind farm in
Denmark, in Proceedings of the 2nd International Workshop on
Transmission Networks for Offshore Wind Farms, 2008, pp. 2930.
Available: http://www.hornsrev.dk/engelsk/nyheder/nyh_aug_02/grid_control.pdf
[66]
IEEE Standard Inverse-Time Characteristic Equations for OverCurrent Relays, IEEE Std C37.112-1996, Sep. 1996.
[67]
IEEE PES Wind Plant Collector System Design Working Group,
"Wind plant collector system fault protection and coordination," IEEE PES
Trans. and Dist. Conf. and Exposition 2010, , Apr. 2010
[68]
C.H. Ng, L. Ran, and J. Bumby, Unbalanced-Grid-Fault RideThrough Control for a Wind Turbine Inverter, IEEE Trans. on Ind. Appl.,
vol. 44, 2008, pp. 845-856.
[69]
R. Teodorescu, I. Liserre, Marco, and P. Rodriguez, Control of Grid
Converters under Grid Faults, Grid Converters for Photovoltaic and Wind
Power Systems, IEEE-Wiley, 2011.
128
[70]
S. Alepuz, S. Busquets-Monge, J. Bordonau, J. a Martinez-Velasco, C.
a Silva, J. Pontt, and J. Rodriguez, Control Strategies Based on
Symmetrical Components for Grid-Connected Converters Under Voltage
Dips, IEEE Trans. Ind. Electron., vol. 56, Jun. 2009, pp. 2162-2173.
[71]
D. Roiu, R.I. Bojoi, L.R. Limongi, and a Tenconi, New Stationary
Frame Control Scheme for Three-Phase PWM Rectifiers Under
Unbalanced Voltage Dips Conditions, IEEE Trans. Ind. Appl., vol. 46,
2010, pp. 268-277.
[72]
L. Xu, B.R. Andersen, and P. Cartwright, VSC Transmission
Operating Under Unbalanced AC ConditionsAnalysis and Control
Design, IEEE Trans. on Power Del., vol. 20, Jan. 2005, pp. 427-434.
[73]
L. Xu, L. Yao, and C. Sasse, Grid Integration of Large DFIG-Based
Wind Farms Using VSC Transmission, IEEE Trans. on Power Syst., vol.
22, pp. 976-984, Aug. 2007.
[74]
P. Rodriguez, A. Luna, M. Ciobotaru, R. Teodorescu, and F. Blaabjerg,
Advanced Grid Synchronization System for Power Converters under
Unbalanced and Distorted Operating Conditions,in Proc. of IECON, Nov.
2006, pp. 5173-5178.
[75]
P. Rodriguez, A.V. Timbus, R. Teodorescu, M. Liserre, and F.
Blaabjerg, Flexible Active Power Control of Distributed Power
Generation Systems During Grid Faults, IEEE Trans Ind. Electron., vol.
54, pp. 2583-2592, Oct. 2007.
[76]
M. Hirakami and W. Neugebauer, Transient Network Analyzer
Operation with Digital Computer Control and Analysis, IEEE
Transactions on Power Apparatus and Systems, vol. 100, no. 4, pp. 15971607, Apr. 1981.
[77]
P. Forsyth, T. Maguire, and R. Kuffel, Real time digital simulation for
control and protection system testing, in 2004 IEEE 35th Annual Power
Electronics Specialists Conference (IEEE Cat. No.04CH37551), 2004, pp.
329-335.
[78]
ABB Oy, Distribution Automation, Feeder Protection and Control
REF615 Product Guide. Available at: www.abb.com/substationautomation
[79]
H. Kirrmann, Sampling Redundancy, in ABB Review -Special Report
IEC 61850, ABB Group R & D and Technology, Switzerland 2010. ISSN:
1013-3119. Available at: www.abb.com/abbreview.
[80]
A. Hakala-Ranta, O. Rintamaki, and J. Starck, Utilizing possibilities
of IEC 61850 and GOOSE, in Electricity Distribution-Part 1, 2009.
CIRED 2009.
A-1
10
400
Assuming a power factor of 0.9 gives system MVA of 444.44 MVA. System base
is taken as 450MVA
84.3
Angular Frequency,
2 50
314.16
Grid Impedance,
3.57
35.78
35.96 84.3
113.9
400
0.9
400
170
150
170
0.14
444.44 ~ 450
,
25
,
,
12,353
0.06
27
2.97
686.1
,
,
2 1950
1950
2.24
,
1.097 ,
2.2
A-2
A.3.2.
Filter#2 parameters
,
6
24504
0.03
,
,
2 3900
13.5
1.91
128.2
0.872
Table A.1 Filter Impedance at the fundamental, 3rd harmonic and resonance
Impedance
at 50 Hz
Impedance
at 150 Hz
Impedance
at Resonance
1069.7, -90
354.7 , -90
1.1 , -2.3
th
2140.4 , -90
712.5 , -90
4.5 , -9.4
Filter#1 Admittance
20
Admittance (dB)
0
-20
-40
-60
-80
Phase (deg)
90
45
0
-45
-90
1
10
10
10
10
Frequency (Hz)
A-3
Filter #2 Admittance
0
Admittance (dB)
-20
-40
-60
-80
90
Phase (deg)
45
0
-45
-90
1
10
10
10
10
Frequency (Hz)
,
,
0.12
50
2
170
450
50
24.5
1950
300
,
,
400
,
1.333
,
2
2
17.78
A-4
1.2 .
1334
,
1112
1.2
18.8
12
1.68 10 . m
,
200
,
3.09
2
0.315
ln
0.1
0.384
76.85
0.7788 0.0188
Considering shielding by sheath at a radius of 30.8mm, the inductance is given by,
0.0308
0.2 ln
0.2 ln
0.1487
29.74
,
. 7788 0.0188
,
0.2 ln
0.2 ln
222
225
855.4
Single core copper cable with 1200 sq. mm cross section has been selected from
Table 4 of ABB XLPE cables data sheet. Cross bonded cable layout in flat formation
gives a maximum current carrying capacity of of 850 A and 1050 A for a temperature
rise of 65C and 90C respectively. As per table 21, the maximum dc resistance is
0.0151 /km at 20C. In flat formation, the cable inductance is 0.5mH/km- Cable
capacitance is 0.26uF/km.
A-5
: 0.24
0.12
36
36
170
1
2
0.093
0.05
5.238
0.18
0.13
It has been scaled to an equivalent LCL filter for a 111MVA WTG-FSC operating
at the 3.3 kV RMS ac line-line voltage. This change will effectively decrease the
impedances by a factor of
1
2
111
3.3
28.6
15.46
6256
55.65
40.19
0.093
0.05
5.238
0.18
0.13
A-6
111
3.3/36
.
15.46
0.005
0.005
_
_
_
95
240
400
, 270
, 475
, 625
0.193 /
0.0754 /
0.047 /
0.69
0.60
0.57
/
/
/
0.17
0.23
0.28
/
/
/
For the equivalent cable string shown in Fig. A 1 b , the cable parameters are given
by,
A-7
.
0.161
1.308
1.08
The parameters of the aggregated WTG feeder can be calculated by the parallel
combination of these strings, which gives the parameters of the aggregated cable feeder
as follows,
0.0537
0.436
3.24
References:
[A.1]
A-8
B-1
Fig. B. 1 Three phases, and space vectors in stationary and rotating reference frames.
(B.1)
(B.2)
(B.3)
(B.4)
B-2
2
3
1
2
1
2
2
3
2
3
1
2
4
3
4
3
(B.5)
or,
cos
cos
cos
2
3
2
3
sin
sin
sin
2
3
4
3
1
1
(B.6)
(B.7)
(B.8)
(B.9)
The coefficient 2/3 ensures that the magnitudes of
and
remain the same as
the peak magnitude of , for a balanced three phase system. This transformation is not
power invariant. The instantaneous power is given by,
Or,
Or,
3
2
3
2
3
2
(B.10)
B-3
1
2
3 0
1
2
1
2
3
2
1
2
1
2
3
2
1
2
(B.11)
B.3 Relationship
between
Transformations
0
1
3
1
2
3
1
2
Parks
(B.12)
and
Clarkes
Or,
Or,
sin
sin
sin
cos
sin
cos
(B.13)
(B.14)
C-1
C.1.
The plant comprises of a VSC connected to the filter bus through a phase reactor with the inductance
(Lpr) and resistance (Rpr) as given below,
0.02453 ,
0.060
0.4088
0.4088
After the open loop poles get cancelled, the remaining open loop transfer function is
(C.1)
. In this
implementation, the controller gain, G, is considered as unity. This means the VSC output is same as
the controller reference. The closed loop transfer function becomes,
1
1
1
1
(C.2)
C-2
Switching frequency is 1950 Hz, The bandwidth is selected as half decade lower than the
switching frequency, i.e. 390 Hz (or 780 rad/sec). Hence,
1
1
1
0.4088,
(1.2)
780
1,
0.06
780
60.11,
(1.3)
C.2.
0.4088
30.05
60.11, T
0.0068
(1.4)
0.00041 s.
achieved by setting,
39
2
3
39
0.00942
Hence, we get
0.00942 and
In PSCAD implementation,
C.3.
0.04332
78
The
C-3
C.4.
Neglecting the current injection from the WPP, the filter bus voltage and the current are related by the
phase equation,
If the cross coupling terms are ignored, and the current is considered constant for a switching cycle, the
current to voltage gain is
78
.
0.000858
78
0.4756
Table C. 1 PI controller parameters : Calculated values, and Values used in PSCAD simulation.
ControlLoop
CurrentControl
NegativeSequenceCurrentcontroller
Dcvoltagecontroller
Reactivepowercontroller
ACvoltagecontroller
CalculatedParameters
Kp
Ti
60.1
0.0068
60.1
0.0068
0.0094
0.0433
0.0005
0.850
0.001
0.476
Parametersused
Kp
Ti
47.3
0.0068
60
3
0.0056
0.0721
0.0005
0.850
0.001
0.349
Publications
P.1
IEEE Energy2030
Atlanta, GA USA
17-18 November, 2008
Wind Farm Grid Integration Using VSC Based HVDC Transmission An Overview
S. K. Chaudhary
R. Teodorescu
P. Rodriguez
Department of Energy
Technology, Aalborg University,
Denmark
skc@iet.aau.dk
Department of Energy
Technology, Aalborg University,
Denmark
ret@iet.aau.dk
Department of Energy
Technology, Aalborg University,
Denmark
pro@iet.aau.dk
I. INTRODUCTION
Wind power generation has received a major
impetus due to ever increasing demand for
energy and depleting fossil fuel reserves. Energy
is the critical resource for development, without
which the world will come to standstill. Fossil
fuels like coal, oil and gas have been the chief
energy source till now. However, fossil fuels are
limited in supply and the reserves are
concentrated in a few countries; thereby raising
energy security concerns. Therefore, significant
research and development has been directed
towards harnessing renewable energy sources
world-wide for sustainable development. Wind
energy is an abundant renewable energy
resource. In the last couple of decades, there has
been a lot of research and development in the
field of electricity generation from wind power.
While the development is still going on, now
wind turbine technology has matured enough to
generate electrical energy from wind on a
massive scale (see Fig. 1).
Another attractive factor for wind energy is its
cleanliness. It does not use water for its operation
and the greenhouse gases emission (GHG) from
300
Onshore
250
Power (GW)
120
75
200
35
150
12
100
50
4
1
56
77
2007
2010
146
113
165
180
2025
2030
0
2015
2020
Year
commutation failure when compared with LCCbased HVDC. It is not referred in this paper.
The paper is divided into five sections. A
brief description of HVAC and LCC-based
HVDC transmission system for wind farms is
given in section II Prevalent grid codes are
briefly discussed in Section III. Section IV
describes the VSC-based HVDC system. In the
end, section V concludes the paper.
II. HVAC AND HVDC OPTIONS FOR
WIND FARM INTEGRATION
A vast majority of generation, transmission,
distribution and consumption of electric power is
in the form of AC. Hence, HVAC transmission is
the obvious choice for the grid connection of
wind farm. Most of the operational wind farms
are connected using HVAC connection. Horns
Rev Wind farm uses 21 km of submarine cable
and 36km of onshore cable for the HVAC
transmission of. 160MW at 150kV
VSC-based HVDC
150 1500 MW
50 550 MW
Convertor/Semiconductor technology
Relative volume
Type of cable
XLPE
4 6 times
Mass Impregnated Paper
Oil/Paper
Yes
Voltage control
Limited
Extensive
Fault ride-through
No
Yes
No
Yes
10
No requirement
11
No
Yes
12
Yes
No requirement
13
No minimum DC power
14
0.8%
1.6%
15
Operating experience
> 20 years
8 years
16
No
Yes
yes
A. Gotland
10kV
Enge
10kV
Tjreborg
2MW
GB
2MW
8MVA
9kV DC
7MW
8MVA
GB
GB
1.5M
W
1MW
GB
70 kV
HVDC to
M ainland
HEM SE
65 M VA
BCKS
80 kV
50 M W
65 M VA
NS
30 kV
N S 2
70 kV
NS
10kV
B. Tjreborg
The 7.2MW, 9kV, 4.4km long HVDC Light
at Tjreborg was commissioned in 2000 to
demonstrate the VSC-based HVDC technology
on a small scale. The farm consists of 4 wind
turbines of different types and makes, with a
total generation of 6.5 MW. The DC cable is laid
in parallel with the existing AC cable, thus
enabling three different operation modes: AC
mode via the AC cable only, the DC mode via
the DC cable only or the AC/DC mode via the
DC and the AC cable in parallel. The offshore
P.2
I. INTRODUCTION
400 kV AC Grid
150 kV
Filter Bus
Vdc2
150 kV
Filter Bus
Vdc1
HVDC Chopper
Resistors
33 kV Collector Bus
Fig. 1 VSC-HVDC Connection for Wind Power Plant comprising of Wind Turbines with Full Scale Converters
Fig. 2 Wind Turbine Generator with Full Scale AC-DC-AC Converter, Chopper resistor in the DC link and its transformer
Pcg
Vc * Vg
X ph
sin(G c G g )
(1)
Where,
Pcg Power transfer from the converter to the grid
VcGc Converter terminal voltage (Magnitude and Phase
of the fundamental component)
VgGg Grid terminal voltage (Magnitude and Phase at the
filter bus),
Xph Reactance of the phase reactor
2
( Pwpp Pcg ) dt
Ceq
Vdc
(2)
Rchop
2
Vrated
Prated
(3)
I chop
1.05 Vrated
Rchop
1.05 Prated
Vrated
1.05 I rated
(4)
RWTG ,chop
IWTG ,chop
2
VWTG
, rated
PWTG ,rated
(7)
(8)
Vc
Vg
Vdc2
400kV
Idc2
Rchop
HVDC
Chopper
Resistor
Vdc1
Idc1
150kV
33kV Collector
Bus
Wind Turbine
generator
RWTG , chop
-3 kV, DC bus
Wind Turbine Generator with its Full Scale Converter and DC chopper
resistor
Fig. 5 Power at Collector Bus and Power Transmitted to the Grid when the
PCC voltage dips to 42 kV in Case A.
Fig. 6 HVDC Over-voltage and chopper resistor current when the PCC
voltage dips to 42 kV in Case A
HVDC voltage at the grid side VSC rises to 309 kV while the
power flow into the grid drops to 128 MW. The peak current
through the chopper resistor is 0.8 kA. Table 1 summarizes
the power flow, observed DC over-voltage and peak current
through the chopper resistor for the different voltage dips
simulated.
5
TABLE 1 DC OVERVOLTAGE FOR IN CASES A AND B DURING VOLTAGE DIPS OF
DIFFERENT LEVELS AT THE PCC
Fig. 8 Power at Collector Bus and Power Transmitted to the Grid when the
PCC voltage dips to 42kV in Case B.
Fig. 7 Generation of Reduction Factor for Active Power input to the WPP-side
VSC
Fig. 9 : Over-voltages in the HVDC system, the WTG-FSC DC link and the
FSC chopper resistor current when the PCC voltage dips to 42 kV in Case B.
Fig. 10 i)Power at the Collector bus and the power transmitted to the grid ii)
HVDC Voltage fluctuation
Fig. 11 i) Chopper Resistor Current in the DC link of the Full Scale Converter
and ii) DC link over-voltage of the Full Scale converter during Voltage dip to
42 kV at the Collector Bus
Fig. 12 DC link over-voltage in the Full Scale converter during voltage dip to
42 kV at the Collector Bus in absence of the chopper resistor.
V. CONCLUSIONS
Similar levels of over-voltages in HVDC system have been
observed in the two sets of simulated cases when the chopper
resistors are placed in the HVDC system and when they are
placed in the DC links of the full scale converters. Through
this simplified simulation results, the two methods appear to
perform in a similar way to check the HVDC system overvoltage.
However, using the chopper resistors in the DC link of the
full-scale converters has merit as the resistor size and ratings
is greatly reduced when compared to a large resistor bank
required when it is placed on the HVDC line. Putting the
chopper controlled resistors in the DC link of full scale
converters will be an attractive option as these will have to
face a lower DC voltage and power ratings. Further, the
chopper resistor on each of the full-scale converter provides
them DC-link over voltage protection against faults between
the full scale converter and the HVDC converter, for example
a fault on the collector bus.
Therefore the WTG-FSCs should be equipped with the
chopper controlled resistors while the chopper resistor in the
HVDC may be eliminated.
The study assumes that the WPP does not ramp down the
power generation. However, modern WTGs are capable of
cutting down power generation by pitch regulation. Though it
is a slow control when compared to electrical control systems,
it would still help in optimizing the chopper resistors.
7
[5] C. Feltes and I. Erlich, "Variable Frequency Operation of DFIG based
Wind Farms connected to the Grid through VSC-HVDC Link," Power
Engineering Society General Meeting, 2007. IEEE, pp. 1-7, 2007.
VI. APPENDIX
Table 2 : System Parameters used in the simulation
Onshore Grid
1 Base MVA
500 MVA
400 kV
25 pu
80 degree
500 MVA
400/150 kV
150/33 kV
Leakage Reactance
0.07 pu
Cu-loss
0.01 pu
Fe-loss
0.01 pu
Phase reactors
5 Inductance
17 mH
6 resistance
10 mOhm
HVDC System
Pole to pole DC boltage
300 kV DC
Power rating
400 MW
HVDC Cable
Cable length
200 km
resistance
2.797 Ohm
Inductance
22.31 mH
Shunt Capacitance
28.15 uF
35.5 uF
2 km
0.248 Ohm
Inductance
0.72 mH
WTG-FSC DC Voltage
150 sq. mm
resistance
Shunt Capacitance
[6] P. Sandeberg and L. Stendius, "Large scale offshore wind power energy
evacuation by hvdc light," presented at European Wind Energy Conference
& Exhibition 2008. Available: http://library.abb.com/global/scot/scot221.nsf/
veritydisplay/ba91daab7c7f5f8dc125747a0051a5dc/$File/Large%20scale%20
Offshore%20Wind%20Power%20Energy%20evacuation%20by%20HVDC%
20Light.pdf
0.4 uF
6 kV
VII. ACKNOWLEDGMENT
This work is a part of the research being carried out for the
Vestas Power program. The program is funded by Vestas
Wind Systems A/S, Denmark and Aalborg University,
Denmark. The authors gratefully acknowledge the financial
and technical support of Vestas Wind Systems A/S.
VIII. REFERENCES
[1] Global wind report 2008. Global Wind Energy Council (GWEC),
Available:
http://www.gwec.net/fileadmin/documents/Publications/Report_2008/Global_
Wind_2008_Report.pdf
[2] S. K. Chaudhary, R. Teodorescu and P. Rodriguez, "Wind Farm Grid
Integration Using VSC Based HVDC Transmission - An Overview," IEnergy
2030 Conference, 2008. ENERGY 2008. IEEE, pp. 1-7, 2008.
[3] J. Machowski, J. W. Bialek and J. R. Bumby, Power System Dynamics :
Stability and Control. ,2nd ed.Chichester, U.K.: Wiley, 2008, pp. 629.
[4] T. Ackermann, Wind Power in Power Systems; Wind Power in Power
Systems. ,Elektronisk udgave ed.Chichester: John Wiley, 2005, pp. xlvii, 691.
IX. BIOGRAPHIES
Sanjay Kumar Chaudhary(S02-M05-SM08) was
born in Nepal in Dec 1976. He received his B. Tech.
degree from Aligarh Muslim University, India in
2000 and M. Tech degree from Indian Institute of
Technology, Kanpur, India in 2002, all in electrical
engineering.
From 2002 to 2005 he worked as engineer with ABB
Ltd (BU: HVDC and FACTS), India. In 2005 he
joined Honeywell Technology Solutions (HTS),
Bangalore, India. Since 2008, he is on sabbatical leave from HTS to pursue
his Ph.D. at Aalborg University, Denmark. His research interests are in Power
system analysis and simulation, HVDC and FACTS and wind power
technology.
Remus Teodorescu received the Dipl.Ing. degree in
electrical engineering from Polytechnical University
of Bucharest, Romania in 1989, and PhD. degree in
power electronics from University of Galati,
Romania, in 1994. In 1998, he joined Aalborg
University, Department of Energy Technology,
power electronics section where he currently works
as full professor. He is the co-recipient of the
Technical Committee Prize Paper Awards at IEEE
lAS Annual Meeting 1998, and Third-ABB Prize
Paper Award at IEEE Optim 2002. He is a Senior
Member of IEEE, Associate Editor for IEEE Power Electronics Letters and
chair of IEEE Danish joint IES/PELS/IAS chapter. His areas of interests are:
design and control of power converters used in renewable energy systems,
distributed generation mainly wind power and photo-voltaics, computer
simulations, digital control implementation.
Remus Teodorescu is the founder and coordinator of the Green Power
Laboratory at Aalborg University focusing on the development and testing of
grid converters for renewable energy systems and the coordinator of the
Vestas Power Program.
P.3
skc@iet.aau.dk
ret@iet.aau.dk
prodriguez@ee.upc.edu
pck@vestas.dk
pewch@vestas.dk
I. INTRODUCTION
Wind power plants (WPP) have come a long way from
isolated wind turbines to clusters of large wind turbines of a
few MW power sizes. Now WPP is regarded as a viable and
competitive source of renewable energy. By the end of 2008,
total installed capacity of WPP reached above 120.8 GW in
the world; out of this nearly 66 GW has been installed in
Europe, mostly onshore WPPs[1]. Due to scarcity of onshore
sites, developments in offshore technologies and availability
of a better aerodynamic profile, the trend in Europe is to
develop large offshore WPP. By 2030, Europe expects to have
300GW of wind energy, out of which 120GW is expected
from Offshore WPP[2].
A WPP comprises of a large number of wind turbine
generators (WTGs) connected together at the collector bus.
Each WTG has a wind turbine with drive train assembly for
driving the generator. The generator may be directly
150 kV
Xph2
Xt2
P + jQ
Vf2
Vdc2
Chopper
Resistor
Xf
Vf1
Vdc1
Xph1
Vc1
Xt1
Vwpp
Vcb
Vwppa
150 kV
ONSHORE
kV, 1400A,
150km DC Cable
Xf
Vg 400 kV
OFFSHORE
150 kV
Vc2
150 kV
33 kV
3 Aggregated
WTG groups
VSC1
VSC2
Xf
Xf
33 kV
150 kV
2x200MW WPP
6 x 6MW FCWTG units connected in a string.
Remaining aggregated WTG model
Vwppb
VSC-HVDC
Vcb
vdm
vd*
idm
*
d
vdm
*
vabc
vq*
i q*
vqm
vqm
iqm
VDCm
*
VDC
Q*
*
Vrms
idm
i d*
PI
Qm
vdm
PI
- +
PI
--+
DQ
ABC
(Limits
Imposed)
i q*
+-
+-
PI
*
vabc
vqm
iqm
wQ
wV
+-
Vrms , m
iabc
vabc
P*
Q*
ia
i
b
ic
va
vc vb i a*
1 Q
P < vb
< vb va *
2
i
3
vabc
b
v
v
v
c
a
c
*
where, vabc
(v v v )
2
a
2
b
2
c
ic
va*
vb*
vc*
3 3
Vm
i.
HVDC
ii.
iii.
iv.
(1)
Fig. 5 WPP Power generation and injection into the onshore grid
f fn
(2)
(3)
f off _ ref
(4)
500
400
25
80
500
400/150
150/33
0.12
0.01
0.01
MVA
kV
pu
degree
MVA
kV/kV
kV/kV
pu
pu
pu
0.105 pu
2.E-04 pu
300 kV DC
400 MW
200
2.797
22.31
28.15
35.5
km
:
mH
uF
uF
REFERENCES
[1] Global wind report 2008, Global Wind Energy Council (GWEC),
Available:
http://www.gwec.net/fileadmin/documents/Publications/
Report_2008/Global_Wind_2008_Report.pdf
[2]
S. K. Chaudhary, R. Teodorescu and P. Rodriguez, "Wind Farm Grid
Integration Using VSC Based HVDC Transmission - An Overview,"
Energy 2030 Conference, 2008. ENERGY 2008. IEEE, pp. 1-7, 2008.
[3]
[4]
[5]
[6]
[7]
P.4
8th International Workshop on Large-Scale Integration of Wind Power into Power Systems as well as on Transmission Networks for
Offshore Wind Farms, 14-15 October 2009, Bremen, Germany
Simulation Study of Wind Power Plant, VSCHVDC and Grid Integrated System
S. K. Chaudhary R. Teodorescu R. N. Mukerjee P Rodriguez P.C. Kjr and P. W. Christensen
AbstractA number of large offshore wind power plants
(WPP) are planned in the seas around Europe. VSC-HVDC is
a suitable means of integrating such large and distant offshore
WPP which need long submarine cable transmission to the
onshore grid. Both VSC-HVDC and Offshore WPP are new
technologies and a detailed study of their interaction, control
and coordination is required. Development and simulation of
an offshore WPP connected to the onshore grid by VSC-HVDC
has been described in this paper.
A sequence of operations for start-up of HVDC, energizing
the offshore grid and connection of the wind turbine generators
(WTG) followed by active power ramp up and ramp down has
been studied. A case of fault ride through has been simulated
for onshore grid faults. The model forms a means of
understanding the system and its operation as a whole from
power system perspective.
Index TermsOffshore Wind Power Plant, VSC-HVDC,
grid integration, modes of operation and fault ride through
(FRT)
I. INTRODUCTION
This work was supported in part by the Vestas Wind Systems A/S under
the Vestas Power Program.
S. K. Chaudhary, R. Teodorescu and R. N. Mukerjee are with the
Department of Energy Technology, Aalborg University, Aalborg, Denmark
(skc@iet.aau.dk, ret@iet.aau.dk and rnm@iet.aau.dk ).
P. Rodrigues is with the Dept. of Electrical Engineering, Technical
University of Catalonia Spain and a visiting faculty at the Department of
Energy Technology, Aalborg University, Aalborg, Denmark ( prodriguez
@ee.upc.edu )
P. C. Kjr and P. W. Christensen are with Vestas Wind Systems A/S
(pck@vestas.com , pewch@vestas.com )
400 kV
Vg
Vcb
Filters
Filters
Vf2
Vc2
Vdc2
Chopper Resistor
Vdc1
Vf1
Vc1
150 kV
150 kV
33 kV
8th International Workshop on Large-Scale Integration of Wind Power into Power Systems as well as on Transmission Networks for
Offshore Wind Farms, 14-15 October 2009, Bremen, Germany
vdm
vd*
*
d
*
q
idm
vdm
*
vabc
*
q
vqm
vqm
iqm
VDCm
*
DC
Q*
*
Vrms
i
PI
Qm
vdm
PI
- +
PI
--+
DQ
ABC
(Limits
Imposed)
i q*
+-
PI
+-
*
vabc
vqm
iqm
wQ
wV
+-
idm
*
d
Vrms , m
Fig. 3 Block Diagram of Onshore VSC Controller
iabc
vabc
P*
Q*
ia
i
b
ic
1
vabc
va
vc vb i a*
Q
P < vb 3 < vb va i *
va vc b
vc
*
where, vabc
ic
va*
vb*
vc*
8th International Workshop on Large-Scale Integration of Wind Power into Power Systems as well as on Transmission Networks for
Offshore Wind Farms, 14-15 October 2009, Bremen, Germany
Fig. 5 Power generation and transmission and HVDC Voltage curves for a whole range of operation from start-up to shut-down.
A. Charging of VSC-HVDC
In the beginning, the VSC-HVDC as well as the offshore
WPP grid is not energized. When the circuit breaker is
closed to connect the converter to the grid through the
converter transformer, the anti-parallel diodes in VSC2 does
the rectifying action and a large inrush current flows in to
charge the HVDC capacitors and the HVDC line to the DC
voltage level of uncontrolled rectifiers, given by,
Vdc 0
3 3
Vm
(1)
8th International Workshop on Large-Scale Integration of Wind Power into Power Systems as well as on Transmission Networks for
Offshore Wind Farms, 14-15 October 2009, Bremen, Germany
8th International Workshop on Large-Scale Integration of Wind Power into Power Systems as well as on Transmission Networks for
Offshore Wind Farms, 14-15 October 2009, Bremen, Germany
IV. DISCUSSION
A model of WPP with VSC-HVDC connection to the
onshore grid has been developed and the different operating
conditions have been simulated. Operational sequence of
starting up the VSC-HVDC, and energizing the offshore
grid, sequential synchronization and connection of a number
of aggregated WTG followed by power generation ramping
up to full power level and then ramping down to 0
generation levels have been demonstrated. The simulation
gives an overview of the overall system and its operation.
The low voltage fault ride through study shows that
VSC-HVDC is capable of supporting the grid by injecting
reactive current while dissipating the excess power in the
chopper controlled resistors. The WPP does not experience
the fault impact and hence the recovery after the fault is
cleared is fast and stable.
8th International Workshop on Large-Scale Integration of Wind Power into Power Systems as well as on Transmission Networks for
Offshore Wind Farms, 14-15 October 2009, Bremen, Germany
500
400
25
80
500
400/150
150/33
0.12
0.01
0.01
MVA
kV
pu
degree
MVA
kV/kV
kV/kV
pu
pu
pu
17 mH
10 m:
300 kV DC
400 MW
200
2.797
22.31
28.15
35.5
km
:
mH
uF
uF
150
2
9
0.44
0.295
sq. mm
km
m:
mH
uF
VI. REFERENCES
[1] "Seas of Change: Offshore Wind Energy," The European Wind Energy
Association (EWEA), 2009.
[2] "Pure Power Wind Energy Scenarios upto 2030," The European Wind
Energy Association (EWEA), Available: http://www.ewea.org/fileadmin
/ewea_documents/documents/00_POLICY_document/PP.pdf
[3] T. Ackermann, Wind Power in Power Systems; Wind Power in Power
Systems, John Wiley, 2005.
[4] S. K. Chaudhary, R. Teodorescu and P. Rodriguez, "Wind Farm Grid
Integration Using VSC Based HVDC Transmission - An Overview,"
Energy 2030 Conference, 2008. ENERGY 2008. IEEE, 2008.
[5] J. Conroy and R. Watson, "Aggregate modelling of wind farms
containing full-converter wind turbine generators with permanent magnet
synchronous machines: transient stability studies," Renewable Power
Generation, IET, vol. 3, pp. 39-52, 2009.
[6] Lie Xu, B. W. Williams and Liangzhong Yao, "Multi-terminal DC
transmission systems for connecting large offshore wind farms," Power and
Energy Society General Meeting - Conversion and Delivery of Electrical
Energy in the 21st Century, 2008 IEEE, pp. 1-7, 2008.
[7] A. A. Meer, R. L. Hendriks and W. L. Kling, "A survey of fast power
reduction methods for VSC connected wind power plant consisting of
different turbine types" presented at the 2nd EPE Wind Chapter Seminar,
KTH, Stockholm, Sweden, 23-24 April, 2009.
P.5
I. INTRODUCTION
This work was supported in part by Vestas Wind Systems A/S under the
Vestas Power Program.
S. K. Chaudhary and R. Teodorescu are with the Department of Energy
Technology, Aalborg University Denmark (e-mails: skc@iet.aau.dk and
ret@iet.aau.dk ).
P. Rodriguez is with the Technical University of Catalonia, Spain. He is a
visiting professor at Aalborg University, Denmark (e-mail: pro@iet.aau.dk ).
P.C. Kjr and P. W. Christensen are with the Vestas Wind Energy
Systems A/S, Denmark (e-mails: pck@vestas.com and pewch@vestas.com ).
Paper submitted to the PhD Seminar on Detailed Modelling and
Validation of Electrical Components and Systems 2010 in Fredericia,
Denmark, February 8th, 2010
Xt2
P + jQ
Vf2
Xph2
Vg 400 kV
150 kV
Chopper
Resistor
Vdc1
Vc1
Vf1
Vwpp
Xph1
Vdc2
150 kV
150 kV
Vwppa
Xt1
ONSHORE
Xf
Vc2
150 kV
33 kV
Vcb1A
Vcb1B
150 kV
33 kV
Vcb2A
OFFSHORE
r
kV, 1400A,
200km DC Cable
Xf
VSC1
VSC2
400MW, 150kV DC
& 150kV 3ph. ac AC rms.
Vwppb
Vcb2B
Xf
Xf
VSC based HVDC Connection
Iwa
Idcl2
Vwb
LCL Filter
Iwb
Vwc
Iwc
LCL Filter
+
-
Pm_in
Pcon_m
1
uy
1 sT
Vdcl
Vdcl
yu
Pconv2
Pconv 2
WTG
Terminal
LCL Filter
+
-
Chopper
Resistor
+
-
Vdcl
Idcl1
vwi iwi
i a ,b, c
Fig. 2 Simplified model of a wind turbine generator with full scale converter (WTG-FSC)
*
dcl
D. Grounding Transformer
Four zigzag transformers, as shown in Fig. 6, are used to
ground the 33kV collector busses in the offshore WPP buses.
The primary windings are connected in star and the secondary
windings are connected in the auto-transformer connection,
with the phase connections as shown in the phasor diagram.
The resultant configuration provides 0-impedance path for the
0-sequence components while it offers high impedance to the
positive and negative sequence components of the voltage.
An ungrounded system is simulated by disconnecting this
transformer.
Vd*
PI
Qm
Q*
*
Vrms
i d*
vdm
PI
-+
PI
--+
DQ
ABC
( Limits
Imposed)
i q*
+-
+-
idm R iqm X
idm
Vdm
+-
PI
wQ
wV
v*abc
vqm
iqm
iqm R idm X
Vrmsm,
N-A
a1
a0
Aln
b0
a0-a1
-b1
N-
c0
B
N-
b1
b0
c1
c0
Bln
-c1
Cln
N-A
-b0
b1
Bln
N
N-
a1-a0
-c0
N-
c1
Cln
55
P-WPP
P-ON-grid
0.5
0
0
3
4
Reactive Power (MVAr) Flow
0.5
Q - WPP
Q -ON-grid
0
-0.5
0
0
3
4
Onshore VSC HVDC Voltage(dc)
-2
5.95
6.05
6.1
6.15
33kV Bus Current from WTG side
6.2
6.25
6.05
6.1
6.15
33kV Bus Current from CB side
6.2
6.25
6.05
6.2
6.25
2
1
0.5
0
-2
5.95
Time(s)
10
Fig. 7 (i) Active power flow from WPP to VSC-HVDC (P-WPP) and from
VSC-HVDC to the onshore grid (P-ON-grid) (ii) Reactive power flow to the
offshore grid (Q-WPP) and to the onshore grid (Q-ON-grid) (iii) VSC-HVDC
operating voltage in p.u.
0
-10
5.95
6.1
Time(s)
6.15
Fig. 10 Voltage at the 33kV faulted bus, and currents observed on the both
sides of the L-G fault in a grounded offshore grid
-2
5.95
6.05
6.1
6.15
33kV Bus Current (pu) from WTG side
6.2
2
1
0
-1
-2
5.95
6.25
1
0
-1
5.95
6.05
6.1
6.15
33kV Bus Current (pu) from CB side
6.2
6.25
6.05
6.1
Time (s)
6.15
6.2
6.25
Fig. 8 Voltage at the 33kV faulted bus, and currents observed on the both
sides of the L-G fault in an ungrounded offshore grid
6.15
6.2
6.25
0.35
5.95
6.15
6.05
6.1
Onshore VSC HVDC Voltage(dc)
6.2
6.25
1.2
1.1
1
0.9
0.8
5.95
6.05
6.2
6.25
P-WPP
P-ONGrid
6.1
Time (s)
6.15
Fig. 11 150kV bus voltage waveform, HVDC power flows and the HVDC
voltage during the L-G fault in the ungrounded system.
6.05
6.1
Power flow (pu)
6.15
6.2
6.25
+ve
-ve
0
0.5
0.95
P-WPP
P-ONGrid
0.9
0.85
5.95
6.1
Power flow
0.6
2
1
0
-1
-2
5.95
6.05
0.85
-1
5.95
1.1
0
5.95
6
6.05
6.1
6.15
Onshore VSC HVDC Voltage(dc, pu))
6.2
6.05
6.1
6.15
6.2
6.25
6.25
1.05
1
1
0.95
5.95
+ve
-ve
0.5
6
6.05
6.1
Time (s)
6.15
6.2
6.25
Fig. 9 150kV bus voltage waveform, HVDC power flows and the HVDC
voltage during the L-G fault in the ungrounded system.
5.95
6.05
6.1
Time(s)
6.15
6.2
6.25
Fig. 12 Sequence components of the voltages in the 33kV and 150 kV grid
during the L-G fault.
Power (MW) flow from the WTG Collector bus to WPP terminal (in pu)
1
healthy ckt
Faulty ckt
0.5
5.95
6.05
6.1
6.15
6.2
Var flow from the WTG Collector bus to WPP terminal (in pu)
6.25
0
-1
-2
5.95
6.05
6.1
6.15
Grounding Transformer Neutral Current (pu)
6.2
6.25
6.2
6.25
10
0
-10
5.95
6.05
6.1
Time (s)
6.15
Fig. 13 Active and reactive power flows from the WTGs with healthy
collector bus and the WTG with a fault on the collector bus.
IV. DISCUSSION
The simulation results show that the simulation model is
robust enough to investigate the normal operating modes as
well as faults in the offshore grid. Onshore grid has not been
modelled in detail, but if need be the model can be plugged
into a more detailed grid model and the impact of grid
disturbances can be studied.
Simulation of the asymmetrical faults demonstrates the
importance of system grounding in the offshore grid network.
Even though an ungrounded system presents an advantage as a
single line-to-ground fault does not necessitate the service
interruption, the situation is dangerous as the healthy phases
can attain unsafe voltage levels. Persistent higher voltage
stress may lead to a second fault which has to be isolated.
Simulation of the grounded system gives an idea of the
fault current levels in the offshore grid and this information
will be useful in the design of the protection system for the
offshore grid.
REFERENCES
[1] "Seas of Change: Offshore Wind Energy," The European
Wind Energy Association (EWEA), 2009.
[2] "Pure power wind energy scenarios upto 2030," The
European Wind Energy Association (EWEA), Available:
http://www.ewea.org/fileadmin/ewea_documents/documents/0
0_POLICY_document/PP.pdf
[3] T. Ackermann, Wind Power in Power Systems; Wind
Power in Power Systems. , John Wiley, 2005.
[4] S. K. Chaudhary, R. Teodorescu and P. Rodriguez, "Wind
Farm Grid Integration Using VSC Based HVDC Transmission
- An Overview," Energy 2030 Conference, 2008. ENERGY
2008. IEEE, pp. 1-7, 2008.
[5] J. Conroy and R. Watson, "Aggregate modelling of wind
farms containing full-converter wind turbine generators with
permanent magnet synchronous machines: transient stability
studies," Renewable Power Generation, IET, vol. 3, pp. 39-52,
2009.
57
P.6
I. INTRODUCTION
Chopper
Resistor
GSC
LCL
Filter
CB & CT
33 kV dc
33kV Coll.
Bus#1
150 kV Coll
Bus #1
WTG#1
GSC
150 kV
WTG#2
150 kV
Xt1
Xph1
Vdc1
33kV Coll.
Bus#2
GSC
33kV Coll.
Bus#3
WTG#3
150 kV Coll
Bus #2
VSC1
GSC
Feeder circuit breaker (CB)
WTG#4
33kV Coll.
Bus#4
T Zt
iqp R idp X
(1)
(2)
VpD
VD
qVE
Fig. 3Model of an aggregated wind turbine generator with its LCL filter and
step-up transformer.
qVD
VE'
VpE
VE
qVD
qVE
(3)
(4)
The most important advantage of this method is its nondependence upon the measurement/estimation of phase angle.
Moreover, the resonant frequency can be set around the
nominal value of frequency set by the VSC-HVDC controller.
B. Determination of the positive sequence current references
DC-link voltage regulator of the WTG-GSC determines the
reference active power to be evacuated (Fig. 6). The reactive
power reference can be specified externally or it may be
generated by some reactive power control logic. In the present
case, reactive power reference has been arbitrarily set to 0.
The positive sequence current references for the WTGGSC are given by the power relationship in the stationary
reference frame (5).
(5)
iD
vwt
.D
iD
vwt .D
iE
vwt
.E
iE
vwt .E
(6)
(7)
(8)
where,
subscripts for the axes components
Controller output references
LCL filter capacitor bus voltage of the WTG
D. Over-current Relay
An over-current relay with very inverse time characteristics
can be used to detect and discriminate faults in the cable
feeders connected to the collector bus. Since several WTGs
are connected to a common cable feeder, they may be
provided with a common circuit breaker, like in Horns Rev I
[16]. When there is a short circuit fault in the feeder, the overcurrent relay should detect it and discriminate it against the
healthy feeders. The relay should then trip the circuit breaker
top isolate the fault. The following characteristics are
particularly helpful in the process
1. Each WTG-GSC is protected by its own current limit
controllers.
2. VSC-HVDC is the largest in the wind power plant
grid in terms of absolute ratings Therefore; it has the
maximum contribution to the fault currents. Other
WTG-GSCs also contribute to the fault current.
Therefore high fault current contributions are
where, A, B and P are the constants defining the relay trip time
characteristics, Ipick-up is the relay pick up current setting. The
trip time given by (8) is scaled by the time dial setting to
obtain the actual trip time of the relay.
IV. SIMULATION OF FAULTS
VSC-HVDC system energizes the offshore wind power
plant grid. The wind turbine generators get synchronized to
this grid through their WTG-GSC. When the wind power plant
is operating at its rated power generation, short circuit faults
are simulated on the WTG cable feeder connected to the 33kV
collector bus 4 (Fig. 1). Both symmetrical and asymmetrical
faults have been simulated with two different fault resistance
levels of (Rf) of 0.005pu and 0.25pu respectively. The fault
duration is 150ms in all the cases..
The over-current relay has been tightly set with the pick-up
current as 1.2pu and the time dial as 5ms. Eq. (8) gives the trip
time of 225ms when the ratio, M is 1.2. The relay current
transformers (CT) are placed at the 33kV collector bus end of
the WTG feeders as shown in Fig 1. The faults are simulated
on the feeder #4.
A delay of 50ms has been provided to simulate the opening
time of the circuit breaker after the trip command has been
received. The opening of the cable string circuit breaker also
opens the WTG load break switches.
A. Single line to ground fault at a 33 kV collector bus, with Rf
=0.005pu
Fig. 7 shows the current measured by the relay CT and the
phase A at the time when the single line to ground (SLG) fault
takes place. Grounding transformers enables the flow of fault
current. The curves for power injected by different WTGGSCs are shown in Fig. 8. The circuit breaker, which isolates
the fault within 71 ms of the occurrence of the fault, is shown.
It is reclosed at 4.35 s, after which the load switch of WTG
gets closed with a delay of 50 ms. The GSC of WTG#4 then
starts injecting power into the offshore grid. The plot shows
that other WTG-GSCs get disturbed during the incidence of
the fault, but as soon as the fault is cleared by the circuit
breaker opening they resume operation.
4.2
4.4
4.6
1
0.8
0.6
0.4
0.2
4.4
4.6
1
0.5
0
4
4.2
4.4
4.6
4.2
4.2
4.4
4.6
4.2
4.4
4.6
4.2
4.4
4.6
Time (sec)
Fig. 8 Output power (in pu) of the WTG converters and the circuit breaker
state for the SLG-fault with Rf =0.005 pu [CB opens at 4.071s, recloses at
4.348s]
Voltage at 33kV Collector Bus#1, Ph A
1
0
-1
4
4.1
4.2
4.3
4.4
4.5
4.6
4.5
4.6
4.5
4.6
4.1
4.2
4.3
4.4
4.1
4.2
4.3
4.4
Time (sec)
Fig. 9 Phase A voltage waveforms (in pu)at the collector bus #1 and #4 for
the SLG-fault with Rf =0.005 pu. [CB opens at 4.071s, recloses at 4.348s]
10
WTG#1 Voltages, Ph A
1
0
-1
0
-5
-10
3.95
4.05
4.1
4.15
4.2
4.1
4.2
4.3
4.4
WTG#1 Currents, Ph A
4.5
4.6
4.1
4.2
4.3
4.4
WTG#4 Voltages, Ph A
4.5
4.6
4.1
4.2
4.3
4.4
WTG#4 Currents, Ph A
4.5
4.6
4.1
4.5
4.6
1
0
-1
pu
0
-1
3.95
4
1
0
-1
4.05
4.1
4.15
Time (sec)
4.2
Fig. 7 Fault Current and voltage (in pu) at the 33kV faulted collector bus for
SLG-fault with Rf =0.005 pu. [CB opens at 4.071s]
1
0
-1
4.2
4.3
4.4
Time (sec)
Fig. 10 Phase A currents and voltages (in pu) of WTG#1 and WTG#4 for
the SLG fault with Rf =0.005 pu. [CB opens at 4.071s, recloses at 4.348s]]
6
Fault Currents
Fault Currents
10
10
-5
-5
-10
3.95
4.05
4.1
4.15
4.2
-10
3.95
1
0
0
-1
3.95
4.05
4.1
4.15
Time (sec)
4.2
4.2
0.5
0.5
4.2
4.4
4.6
4.2
4.4
4.6
0
4.4
4.6
4.2
4.4
4.6
0.5
0
4.2
4.4
4.6
4.2
4.4
4.1
4.15
4.2
4.2
4.4
4.6
1
0.8
0.6
0.4
0.2
1.2
1
0.8
0.6
0.4
0.2
4.6
1
0.8
0.6
0.4
0.2
Time (sec)
Fig. 12 Output power (in pu) of the WTG converters and the circuit breaker
state for the LLL-fault with Rf =0.005 pu [CB opens at 4.087s, recloses at
4.336 s]
4.2
4.4
4.6
4.2
4.4
4.6
0.5
1
0.8
0.6
0.4
0.2
4.05
0.5
Fig. 14 Fault Current and voltage (in pu) at the 33kV faulted collector bus for
SLG-fault with Rf =0.25 pu. [CB opens at 4.134s]
0.5
4.2
3.95
1.5
pu
4.15
Time (sec)
Fig. 11 Fault Current and voltage (in pu) at the 33kV faulted collector bus for
LLL-fault with Rf =0.005 pu. [CB opens at 4.087s]
4.1
-1
4.05
4.2
4.4
4.6
4.2
4.4
4.6
4.2
4.4
4.6
Fig. 15 Output power (in pu) of the WTG converters and the circuit breaker
state for the SLG-fault with Rf =0.25 pu [CB opens at 4.134s, recloses at
4.382 s]
Fault Currents
WTG#1 Voltages, Ph A
10
1
0
-1
5
4
4.1
4.2
4.3
4.4
WTG#1 Currents, Ph A
4.5
4.6
0
-5
1
0
-1
-10
3.95
4
4.1
4.2
4.3
4.4
WTG#4 Voltages, Ph A
4.5
4.2
4.3
4.4
WTG#4 Currents, Ph A
4.5
4.05
4.1
4.15
4.2
4.6
Phase A Voltage at the Faulted Collector Bus
1
0
-1
1
4
4.1
4.6
1
0
-1
0
-1
4.1
4.2
4.3
4.4
4.5
4.6
Time (sec)
Fig. 13 Phase A currents and voltages (in pu) of WTG#1 and WTG#4 for
the LLL-fault with Rf =0.005 pu. [CB opens at 4.087s, recloses at 4.336 s]
3.95
4.05
4.1
4.15
4.2
Time (sec)
Fig. 16 Fault Current and voltage (in pu) at the 33kV faulted collector bus for
LLL-fault with Rf =0.25 pu. [CB opens at 4.106s]
4.2
4.4
4.6
1
0.8
0.6
0.4
0.2
4.2
4.4
4.6
4.2
4.4
4.6
4.2
4.4
4.6
0.5
0.5
0
4
4.2
4.4
4.6
4.2
4.4
4.6
Time (sec)
Fig. 17 Output power (in pu) of the WTG converters and the circuit breaker
state for the LLL-fault with Rf =0.25 pu [CB opens at 4.106s, recloses at
4.386 s]
VII. REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
8
AC and DC transmission," Renewable Power Generation, IET , vol.3,
no.4, pp.426-438, December 2009
[8] A.D. Hansen and G. Michalke, "Multi-pole permanent magnet
synchronous generator wind turbines' grid support capability in
uninterrupted operation during grid faults," Renewable Power
Generation, IET , vol.3, no.3, pp.333-348, Sept. 2009
[9] IEEE PES Wind Plant Collector System Design Working Group, "Wind
power plant grounding, overvoltage protection, and insulation
coordination:," Power & Energy Society General Meeting, 2009. PES
'09. IEEE , vol., no., pp.1-8, 26-30 July 2009
[10] IEEE PES Wind Plant Collector System Design Working Group, "Wind
plant collector system fault protection and coordination," IEEE PES
Transmission and Distribution Conference and Exposition 2010, , vol.,
no., pp.1-5, 19-22 April 2010
[11] R. Van de Sandt, J. Lowen, J. Paetzold, and I. Erlich, "Neutral earthing
in off-shore wind farm grids," PowerTech, 2009 IEEE Bucharest , vol.,
no., pp.1-8, June 28 2009-July 2 2009.
[12] L. Xu, B. W. Williams and L. Yao, "Multi-terminal DC transmission
systems for connecting large offshore wind farms," Power and Energy
[13]
[14]
[15]
[16]
[17]
P.7
I. INTRODUCTION
Chopper
Resistor
GSC
CB & CT
MV feeder #1
36 kV Coll.
Bus#1
WTG#1
GSC
MV feeder #2
WTG#2
36 kV Coll.
Bus#2
HV
feeder #1
MV feeder #3
36 kV Coll.
Bus#3
WTG#3
GSC
B1
150 kV
B2
HV
feeder #2
GSC
FB
150 kV Coll
Bus #2
MV feeder #4 A4
FA
WTG#4
OFFSHORE
ONSHORE
VSC1
Vf2
170 kV
Vc2
Vdc1
Vc1
Xph1
Vdc2
170 kV
VSC2
Fig. 1. Single line diagram of a wind power plant with VSC-HVDC connection
Xph2
Xt2
Vg 400 kV
150 kV
150 kV Coll
Bus #1
P+ jQ
Inverse
Parks
Transformation
(1)
4
3.5
3
2.5
2
1.5
1
0.5
0
0
0.1
0.2
0.3
0.4
0.5
Ia
Ib
RMS
Irms
Calculation
Block
VSC
Ic
Imax
Fig. 3. Limiting overcurrent by blocking the VSC.
(2)
kA
A
A
A
1.1
(i)
A
0.9
0.08
0.09
0.1
0.11
0.12
0.13
0.14
0.15
0.16
0.17
0.08
0.09
0.1
0.11
0.12
0.13
0.14
0.15
0.16
0.17
0.08
0.09
0.1
0.11
0.12
0.13
0.14
0.15
0.16
0.17
0.08
0.09
0.1
0.11
0.12
0.13
Time (s)
0.14
0.15
0.16
0.17
( ii ) 0.95
0.9
kA
0.85
A
1
( iii )
A
A
0.95
1
( iv )
0
-1
Fig. 6. Steady state results (in pu) (i)HVDC voltage (ii) Power transferred
to the VSC-HVDC system and to the onshore grid. (iii) Power generated by
the wind turbine generators (iv) Offshore VSC-HVDC current waveform.
2
1.5
(i)
(i)
1
0.5
0
0.05
0.1
0.15
0.05
0.1
0.15
1
( ii ) 0.5
0
1
( iii ) 0.5
0
0
0.05
0.1
0.15
10
5
0
-5
-10
50
25
( ii )
0
-25
-50
10
5
0
( iii )
-5
-10
20
10
0
( iv )
-10
-20
1
( iv )
0.05
0.1
0.15
Time (s)
Fig. 7. SLG Fault on MV Feeder at 'FA' (i) HVDC voltage (ii) Power
transferred to the VSC-HVDC system and to the onshore grid. (iii) Power
generated by the Wind turbine generators. (iv) AC current waveform in the
offshore VSC-HVDC.
20
0
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.02
0.04
0.06
0.08
0.1
Time (s)
0.12
0.14
0.16
0.18
0.2
50
0
10
0
-10
20
( iv )
0
-20
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.02
0.04
0.06
0.08
0.1
Time (s)
0.12
0.14
0.16
0.18
0.2
-20
( iii )
0.06
0
0
-50
0.04
( v ) 0.5
-1
( ii )
0.02
(i)
1
( v ) 0.5
0
Fig. 8. SLG Fault on MV Feeder at 'FA' (i) Fault current (ii) Secondary
current (in A) in the faulted MV feeder CT. (iii) Secondary current (in A) in
the adjacent MV feeder CT. (iv) Secondary current (in A) in the HV feeder
CT. (v) Relay trip signal.
VII. REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
[13]
[14]
[15]
[16]
[17]
[18]
[19]
[20]
[21] IEEE PES Wind Plant Collector System Design Working Group,
"Wind plant collector system fault protection and coordination," IEEE
PES Trans. and Dist. Conf. and Exposition 2010, , Apr. 2010
[22] R. Van de Sandt, J. Lowen, J. Paetzold, and I. Erlich, "Neutral
earthing in off-shore wind farm grids," PowerTech, 2009 Bucharest.
[23] P. Rodriguez, A. Luna, M. Ciobotaru, R. Teodorescu, and F.
Blaabjerg, Advanced Grid Synchronization System for Power
Converters under Unbalanced and Distorted Operating Conditions,
in IECON 2006, pp. 5173-5178.
[24] S. K. Chaudhary, R. Teodorescu, P. Rodriguez, P.C. Kjr and P. W.
Christensen, Control and Operation of Wind Turbine Converters
during Faults in an Offshore Wind Power Plant Grid with VSCHVDC Connection, IEEE-PES General Meeting, 24-28 July 2011
[25] P. Christiansen, K. Jorgensen, and A.G. Sorensen, "Grid Connection
and Remote Control for the Horns Rev 150 MW Offshore Wind Farm
in Denmark," Available at http://www.hornsrev.dk
[26] IEEE Standard Inverse-Time Characteristic Equations for Overcurrent Relays, IEEE Std C37.112-1996, Sep. 1996.
[27] H. Kirrmann, Sampling Redundancy,ABB Review -Special Report
IEC 61850, ABB Group R & D and Technology, Switzerland 2010.
ISSN: 1013-3119. Available at: www.abb.com/abbreview.
[28] P. Forsyth, T. Maguire, and R. Kuffel, Real time digital simulation
for control and protection system testing, in . PESC., 2004.
BIOGRAPHIES
Sanjay K. Chaudhary (S02-M05-S08) obtained B. Tech. degree
from A.M.U., India in 2000 and M. Tech degree from IIT-Kanpur, India in
2002, all in electrical engineering. From 2002 to 2005 he worked as
engineer with ABB Ltd, India. In 2005 he joined Honeywell Technology
Solutions, India. Since 2008, he has been pursuing for his Ph.D. at Aalborg
University, Denmark. His research interests are in power system analysis
and simulation, HVDC and FACTS and wind power.
Remus Teodorescu (S'94-M'99-SM'02) received the Dipl.Ing. degree from
the Polytechnical University of Bucharest, Romania, in 1989, and the Ph.D.
degree from the University of Galati, Romania, in 1994. In 1998, he joined
Aalborg University, where he currently works as full professor.
He is the recipient of Nordjysk University Foundation Innovation Prize,
2011. His areas of interests are: design and control of power converters
used in grid connected renewable energy systems.
Pedro Rodriguez (S'99-M'04-SM'10) received the M.Sc. and Ph.D.
degrees in electrical engineering from the Technical University of
Catalonia, Spain, in 1994 and 2004, respectively. He is currently an
Associate Professor in the Department of Electrical Engineering UPC, and
the Head of the Research Center on Renewable Electrical Energy Systems
(SEER). His research interest is focused on applying power electronics to
improve grid integration of renewable energy systems.
Dr. Rodriguez is a member of the IEEE IES Technical Committee on
Renewable Energy Systems. and the chair of the IEEE Industrial
Electronics Student Forum.
Philip Carne Kjr received the M.Sc. degree from Aalborg University,
Denmark, in 1993, and the Ph.D. degree from the University of Glasgow,
U.K., in 1997. From 1993 to 1998, he was a Research Assistant at the
University of Glasgow, working with advanced control of switched
reluctance machines and drives. From 1998 to 2003, he was with ABB
Corporate Research, Vasteras, Sweden. Since October 2003, he has been
with Vestas Wind Systems as Chief Specialist for power plants. His
research covers control and application of electrical machines and power
electronic converters.
Dr. Kjaer is a Chartered Engineer in the U.K., a Member of the Institution
of Electrical Engineers, U.K., and the recipient of the 2004 Richard M.
Bass Outstanding Young Power Electronics Engineer Award.
P.8
Abstract
This paper explores the application of modular multi-level
converters (MMC) as a means for harnessing the power from
off-shore wind power plants. The MMC consists of a large
number of simple voltage sourced converter (VSC) submodules that can be easily assembled into a converter for
high-voltage and high power. The paper shows that the MMC
converter has a fast response and low harmonic content in
comparison with a two-level VSC option. The paper discusses
the modeling approach used, including a solution to the
modeling challenge imposed by the very large number of
switching devices in the MMC.
Introduction
C
G FSC Y
A
G FSC Y
Collector
Bus
DC Cable
LP1
AC Cable
LP2
Bus2
Zs2
TF2
YY
TF1
M1
MMC1
Offshore
WPP
DC Cable
MMC2
Onshore
AC2
VC ; it is
SM1
SM1
SM1
SM2
SM2
SM2
SMNP
SMNP
SMNP
Phase
reactor
Vd
SM1
SM1
SM1
SM2
SM2
SM2
SMNP
SMNP
SMNP
Power
Sub-module
0.
(pu)
1
IC
T1
-1
0
ISM
C Vc
VSM
T2
10
20
Time (ms)
30
IC
IC
R1
T1
ISM
ISM
VSM
Rc
The agrregated wind generator FSC model for the WPP and
the computationally efficient MMC converter model were
connected together to represent the system of Fig. 1. The
converter transformers, DC cables and the remaining ac
network were modelled in detail for electro-magnetic
transient simulation.
Vc
T2
VSM
VcEQ
R2
VMV
IMV
REQ
[VC]NP*1
VEEQQ
[FP]NP*2
Wind Turbine
Generator (WTG)
33kV Cables
Y
WTG
Transformer
Wind Turbine Generator (WTG) with Full Scale Converter (FSC)
sinRef
dis Ref
0
-1
0
10
15
20
25
30
15
20
Time (ms)
25
30
(b)
12
6
0
0
10
vs1(dq)*
is1(abc)
vconv1(abc)*
abc/dq
dq/abc
1
vs1(dq)
is1(dq)
Current
controller
vconv1(dq)*
400
200
0
6
(MVar)
is1
vs1(abc)
1
(MW)
vs1
f0*
MMC1
50
0
6
P wtg1
P ref
P ac2
(kV)
(kV)
MMC2
Bus2
vdc2
vs2(abc)
is2(abc)
C
abc/dq
PLL
Current
controller
PI
vconv2(abc)*
2
vs2(dq)
is2(dq)
2
dq/abc
vconv2(dq)*
(abc)
vs2
vdc2
vdc2*
10
Qref
8
(c)
10
8
(d)
10
300
0
6
120
0
6
Vd
Vq
8
Time (s)
10
Q2
- Q2*
+
PI
Qac2
8
(b)
*
+ vs2
vs2
(a)
(c)
30
(MW)
(kA)
400
0
-30
0
50
0.0
350
(kV)
(kV)
100
0
300
-100
0
250
0
5 Conclusion
A typical application of MMC based HVDC transmission
system was presented. The wind power plant was modelled as
an aggregated system connected to the offshore grid. An
accurate Thvenin equivalent model for the converter was
used to simulate the MMC on an electro-magnetic transient
simulation program. Several simulations were carried out to
demonstrate the behaviour of the MMC based HVDC system
in WPP connections. The MMC topology can be effectively
used to transmit power generated by the offshore wind
turbine-generators. The ability to operate the converter
without filters is a distinct advantage in WPP systems to
accomplish the compact design requirement.
Appendix I
TABLE A1
PARAMETERS OF MMC-BASED HVDC SIMULATION SYSTEM
Offshore grid
VBUS1(L-L) = 230 kV
LP1 = 0.0193 H
Transformer 1
S = 445 MVA
Ratio = 150/150 kV
XTF1 = 12 %
DC filter
DC rated voltage
DC cable
Onshore grid
VBUS2(L-L) = 150 kV
LP2 = 0.0193 H
SCR = 25
Transformer 2
S = 445 MVA
Ratio = 150/400 kV
XTF2 = 12 %
DC System
C = 35.5F
Vdc = 150 kV
Rdc = 14m/km
Ldc = 0.112mH/km
Cdc = 0.28F/km
Length = 200km
References
[1] World Wind Energy Report 2009, World Wind Energy
Association (WWEA), Available at: www.wwindea.org.
[2] S. V. Bozhko, R. Blasco-Gimenez, R. Li, J. C. Clare, and
G. M. Asher, Control of offshore DFIG-based wind
farm grid with line-commutated HVDC connection,
IEEE Trans. on Energy Convers., vol. 22, no. 1, pp. 71
78, Mar. 2007.
[3] W. L. Kling, R. L. Hendriks, and J. H. den Boon,
Advanced transmission solutions for offshore wind
farms, IEEE-PES General Meeting-Conversion and
Delivery of Electrical Energy in the 21st Century, 2008.
[4] N. M. Kirby, L. Xu, M. Luckett, and W. Siepmann,
HVDC transmission for large offshore wind farms,
Power Eng. J., vol. 16, no. 3, pp. 135141, 2002.
[5] R. Marquardt and A. Lesnicar, A new modular voltage
source inverter topology, EPE'03, Toulouse, 2003.
[6] P. Boonchiam and N. Mithulananthan, Diode-clamped
multilevel voltage source converter for medium voltage
dynamic voltage restorer, ESD2006 conf., Phuket,
Thailand, 2006.
[7] J. Rodrguez, J. S. Lai, and F. Z. Peng, Multilevel
inverters: A survey of topologies, controls, and
applications, IEEE Trans. on Industrial Electronics, vol.
49, no. 4, pp. 724-738, Aug. 2002.
[8] D. Retzmann and K. Uecker, Benefits of HVDC &
FACTS for Sustainability and Security of Power
Supply, Powerafrica Conference and Exposition,
Johannesburg, Jul. 2007.
[9] S. P. Teeuwsen, Simplified Dynamic Model of a
Voltage-Sourced Converter with Modular Multilevel
Converter design, IEEE/PES Power Systems
Conference and Exposition, Mar. 2009.
[10] U. N. Gnanarathna, A. M. Gole, and R. P. Jayasinghe,
Efficient Modeling of Modular Multi-Level HVDC
Converters (MMC) on Electromagnetic Transient
Simulation Programs, accepted (July 2010) for
publication in the IEEE Trans. on Power Delivery
[11] K. Strunz and E. Carlson, Nested Fast and Simultaneous
Solution for Time-Domain Simulation of Integrative
Power-Electric and Electronic Systems, IEEE Trans. on
Power Delivery, vol. 22, pp. 277287, Jan. 2007.
[12] Users Guide: Comprehensive Resource for EMTDCTransient Analysis for PSCAD Power System
Simulation, Manitoba HVDC Research Centre,
Winnipeg, Canada, Apr. 2005.
[13] H.W. Dommel, Digital computation of Electromagnetic
Transients in Single and Multi-phase Networks, IEEE
Trans. PAS, vol. PAS-88, no. 4, pp. 388-399, Apr. 1969.
[14] H.Ouquelle, L. A. Dessaint, S. Casoria, "An average
value model-based design of a deadbeat controller for
VSC-HVDC transmission link," PES General Meeting,
2009. IEEE, vol., no., pp.1-6, 26-30 July 2009.
[15] L. Xu, B. W. Williams and L. Yao, "Multi-terminal
P.9
Sanjay K. Chaudhary
I.
INTRODUCTION
VC T1 -ON, T2 -OFF
T1 -OFF, T2 -ON
0
(1)
T1
IOUT
C
VOUT
T2
Vc
Multi-valve
SM1
VC,T1
SM2
VC,T2
SMN
VC,TN
IMV,T
IMV,B
Vd
Vd/2
SM1
VC,B1
SM2
VC,B2
SMN
VC,BN
VA0
Vd/2
( pu )
Vref
VA0
0.5
0
45
0.5
90
135
180
225
270
315
NU
N NL
(2)
Vc
Vd
360
Zt (deg)
1
NL
(3)
Consider the upper multi-valve which requires NU submodules to be ON. If the current IOUT is positive (see Fig. 1),
then turning on a sub-module will result in capacitor voltage
increase. In that case, the NU sub-modules ranked lowest in
voltage are turned on, so that they can be re-charged. If IOUT is
negative, then the highest-voltage sub-modules are turned on,
so that their voltages may discharge. The same is done for the
lower multi-valve.
The capacitor voltages of sub-modules can be controlled in
a narrow band by applying this methodology for all three
phases [10]. The overall control structure for the converter,
including the waveform quantizer and the capacitor balancing
controller is shown schematically in Fig. 4.
III.
-1
Vref
Quantizer
Capacitor
voltages
C. Redundant Sub-modules
Redundant sub-modules are provided in each multi-valve.
If a sub-module fails during operation, it is quickly removed
from the circuit by operating the high-speed bypass switch [11]
shown in Fig. 1. Normal operation can continue with the
remaining sub-modules in the multi-valve. The waveform
synthesis algorithm discussed in the previous sub-section is
informed of the failure and now only controls the remaining
Vc1
Vc2
VcN
NU,NL
Capacitor voltage
balancing
Firing
pulses
FP1
FP2
IMV
0
Direction check
Fig. 4. Firing pulse control algorithm of MMC
FPN
Dnmx (%)
THD (%)
12
16
20
24
20
24
1
28
10
5
2
4
12
16
28
Fig 6. Max. individual harmonic and THD variations with no. of levels
(a)
40
20
0
0
0.5
(i)
(b)
100
0
-100
1
Time (s)
1.5
(ii)
100
Vout (kV)
Vc (kV)
10
20
30
40
50
Time (ms)
Fig. 5. a) Sinusoidal reference waveform and converter output
voltage waveforms when number of sub-modules per multi-valve is;
b) 2, c) 6, d) 12, e) 24, f) 48, and g) 96
10
Vout (kV)
(a)
(b)
(c)
(d)
(e)
(f)
(g)
120
-120
120
-120
120
-120
120
-120
120
-120
120
-120
120
-120
0
-100
2.2
800ms
400ms
200ms
100ms
40ms
(pu)
1.02
1.00
0.98
0.96
0
20
30
40
50
Time (ms)
Fig. 8. Average capacitor voltage fluctuation for different capacitance
values of 6-level MMC
C pu
10
(0.5CVc 2 )(6 N )
2
Pc Qc
(4)
(g)
(f)
(e)
(d)
(c)
(b)
(a)
10
20
30
Time (ms)
40
50
IV.
Rdc
Ldc
C
Rdc
Ldc
C
Cdc
L1 Bus1 Bus1A
Bus2 L2
Y
R1
Y
TF1
R1'
AC1
SCR=2.5
TF2
MMC1
(Rectifier)
Cdc
C
Ldc
Rdc
Rdc
R2
R2'
AC2
SCR = 1.0
MMC2
(Inverter)
Ldc
MMC1
Bus1
vs1
vs1*
vdc1*
+
+-
vdc1
MMC2
Bus2
P2
vdc1
vref1(abc)*
PI
Sinusoidal
M1
reference
generator
PI
1
1
PLL
vs1(abc)
vref2(abc)*
CONCLUSION
-+
P2
vs2*
P2*
(MW, MVar)
(a)
400
Pac2Ref
P2
Q2
200
0
0
0.4
0.8
(b)
1.2
1.5
0.4
0.8
(c)
1.2
1.5
(kV)
116
115
114
0
100
(kV)
PI
Sinusoidal
M2
reference
generator
PI
2
2
PLL
vs2(abc)
VI.
vs2
0
-100
0.38
0.4
0.42
0.44 0.46
Time (s)
0.48
0.5
REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
[13]
[14]
[15]
[16]
P.10
I. INTRODUCTION
HE newer voltage-sourced converter based HVDC (VSCHVDC) technology is becoming more competitive for
intermediate power levels up to a few hundred MW [1]. In
comparison with conventional line commutated thyristor
based converters (LCC), VSC-HVDC transmission systems
exhibit enhanced technical features that can cope with the
requirements of modern power transmission systems. The
VSC converter can operate in weak or even passive ac systems
and does not require reactive power support from the ac grid.
And also, VSC-HVDC system can independently control
active and reactive power exchange with the ac system [2].
Till recently, VSC-HVDC systems have been based on
two- or three-level technology which enables two or three
different voltage levels to the ac terminal of the converter. As
a result, high and steep level changes are applied at the
converter ac terminal hence extensive filtering measures are
required [3]. In order to lower harmonic distortion, pulsewidth modulation (PWM) techniques are used in voltage
synthesis whereas, most of these methods require a very high
switching frequency to obtain the very advantage of improved
harmonic performance. This causes considerable power losses
and eventually, reduces the total efficiency and substantially
increases the total cost of the VSC-HVDC project [4].
Instead of two- or three-level technique, the use of multilevel converters can significantly reduce the switching losses
[3]. These converters synthesize a stepped ac waveform
resembling a sine wave, by stacking fixed magnitude voltage
steps on top of each other. A newly introduced multi-level
converter for high voltage application is the modular multilevel converter (MMC). The VSC based MMC was initially
developed using H-bridge modules for STATCOM
applications [5].
The MMC topology has been recently emerged as a
promising technique for VSC based high voltage, high power
transmission systems after the introduction of AC/DC
conversion with half IGBT/diode bridges [6]. This topology is
designed to avoid connecting the devices in series that has
been a problem of most of other multi-level topologies. The
MMC consists of a stack of identical sub-modules, each with
two IGBT switches and a dc capacitor as shown in Fig. 1(a).
By suitably controlling the two switches in the sub-modules, a
multi-level ac voltage waveform can be synthesized as shown
Fig. 1(b). As the multi-level converter output voltage can
assume several discrete levels, the harmonic content is low
hence, the filters are not required. An inclusion of more submodules increases the voltage and power ratings of the
converter. The topology is designed to make low voltage
stresses on each switching devices. Therefore, MMC can
conceptually exploit the potential of conventional (two- or
three-level) VSC-HVDC schemes to the best.
Each sub-module capacitor voltage provides one step in the
resulting multi-level ac waveform. Therefore, it is required to
maintain the capacitor voltages at a constant value using an
internal control unit. The function of this capacitor voltage
balancing controller is to generate firing pulses for each submodule to maintain the sub-modules capacitor voltage at a
constant value. Therefore, the number of IGBT switching
operations required in a power cycle is mainly determined by
the capacitor voltage balancing algorithm. Hence, the IGBT
switching loss, which is a major contributor to the converter
power loss, depends heavily on the voltage balancing
algorithm.
An accurate estimation of converter losses is an important
step in the thermal management system design [7]. One of the
SM1
SM2
IC
T1
C
SMN
van
Vd
SM1
SM2
Power sub-module
van
Vd/2
t
SMN
Multi-valve
(a)
VC
VSM T2
-Vd/2
(b)
Fig. 1. (a) Schematic diagram of an MMC phase unit and (b) MMC
output waveform for 10 sub-modules per multi-valve (N=10).
V SM ( t )
V C ............... if T1 = O N and T2 = O FF
0 .................. if T1 = O FF and T 2 = O N
(1)
> n ( t ) 1@ * V C
Vd
2
w h ere N U
N U * VC
Vd
2
N L * VC
N NL
With this method, the full dc bus voltage can be seen across
the total number N N U N L of ON sub-modules. Thus,
since all capacitor voltages are required to be the same, each
must be equal to:
VC
Vd
(3)
SM1
Firing pulse
generator
NU
Sub-module
selector
(2)
TL
SM2
SM3
VC
SMN
LMV
I MV
NL
Upper multivalve
I MV
Quantizer
Sub-module
selector
Firing pulse
generator
TU
van
VC
TL
Lower multivalve
TU
of
in
lth
in
1
0
(b)
0.167
0
(c)
-1
0
0.167
0
(d)
0
1
0.01
0.02
0.03
0.01
0.02
0.03
III.
0.01
0.02
Electrical
network
0.01
0.02
Parameter
calculation
0.03
0
-1
0
0.03
Switch
model
Operating
conditions
Model
parameters
Loss
estimation
Device
temperature
Ambient
Thermal conditions
path model
Power loss
+
Tj
-
Cth1
Rthm
Cth2
PLc
Heat
Sink
+
TC
-
Cthm
Ta
Rdc
Bus 2
L2
Cdc
Ldc
Rdc
Rdc
C
Ldc
TF2
Inverter
R2'
25
15
0
0
20
R2
AC2
0.01
0.02
-20
0
0.03
P(MW)
Vrms(kV)
0.01
0.02
0.03
Vout(kV)
0
0.01
0.02
0.03
VC1(kV)
2.3
0
0
Y
VDC
0
0
Ldc
Cdc
VDC
PLOSS(MW)
0.23
(d)
Ldc
PLj
Rth2
(b)
Rth1
IGBT
(c)
0.01
0.02
Time (s)
0.03
PLOSS(MW)
(a)
0.45
PLOSS(MW)
0.22
0
0
0.01
25
15
0
0
20
(c)
(b)
(a)
0.02
P(MW)
Vrms(kV)
0.01
0.02
0.03
Vout(kV)
0
-20
0
(d)
0.03
0.01
0.02
0.03
2.3
VC1(kV)
0
0
0.01
0.02
Time (s)
0.03
(b)
0.005
0.01
0.015
0.02
25
15
0
0
20
S2
T1
T3
T5
VA
VB
VC
0.005
0.01
0.015
0.02
T6
-20
0
0.03
0.005
0.01
0.015 0.02
Time (s)
0.025
0.03
Fig. 10. Two-level VSC waveforms (a) Inverter side power loss, (b)
Power and rms voltage at inverter side Bus 2, and (c) Inverter output
voltage.
Converter
Type
MMC
(Capacitor
ranking)
MMC
(PWM)
T2
0.025
S8
T4
0.03
P(MW)
Vrms(kV)
Total
Power
(MW)
HVDC
system
power
loss
(%)
THD
(%)
/phase
Power
Loss/
Converter
(MW)
24
0.23
25
1.84
6.06
48
0.20
25
1.60
5.00
24
0.22
25
1.76
5.42
48
0.20
25
1.60
3.84
N/A
0.45
25
3.60
111
No. of
Submodules
S1
Vdc
0.025
Vout(kV)
(c)
2-VSC
(SPWM)
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
VI. REFERENCES
[1]
[2]
[13]
[14]
P.11
1HJDWLYH6HTXHQFH&XUUHQW&RQWUROLQ:LQG3RZHU3ODQWV
ZLWK96&+9'&&RQQHFWLRQ
-RXUQDO ,(((7UDQVDFWLRQVRQ6XVWDLQDEOH(QHUJ\
0DQXVFULSW,' 767(
0DQXVFULSW7\SH 6SHFLDO,VVXH:LQG(QHUJ\
'DWH6XEPLWWHGE\WKH
-XQ
$XWKRU
&RPSOHWH/LVWRI$XWKRUV &KDXGKDU\6DQMD\'HSWRI(QHUJ\7HFKQRORJ\$DOERUJ8QLYHUVLW\
7HRGRUHVFX5HPXV$DOERUJ8QLYHUVLW\,QVWLWXWHRI(QHUJ\7HFKQRORJ\
5RGULJXH]3HGUR7HFKQLFDO8QLYHUVLW\RI&DWDORQLD(OHFWULFDO(QJLQHHULQJ
.MU3KLOLS9(67$6:,1'6<67(07HFKQRORJ\5 '
*ROH$QL8QLYHUVLW\RI0DQLWRED
*ULGLQWHUDFWLRQRIVXVWDLQDEOHHQHUJ\VRXUFHV7UDQVDFWLRQVRQ
7HFKQLFDO7RSLF$UHD 6XVWDLQDEOH(QHUJ\:LQGWXUELQHJHQHUDWRUV7UDQVDFWLRQVRQ
6XVWDLQDEOH(QHUJ\
$&'&SRZHUFRQYHUVLRQ3RZHUV\VWHPIDXOWV&XUUHQWFRQWURO'&SRZHU
.H\:RUGV WUDQVPLVVLRQ)DXOWFXUUHQWV3RZHUV\VWHPPRGHOLQJ&RQYHUWHUV3RZHU
V\VWHPFRQWURO3RZHUV\VWHPWUDQVLHQWV3RZHUV\VWHPVLPXODWLRQ
Page 1 of 10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
<
" "
"
!" " >"
&$%
'&+%
#$%
" "
<
!" " >" "
" " ?
<
!" " "
"
" @" &$%'&+%
"
<
{
{`{
!
{!^\
{^`{
^\?
|^\?
Page 2 of 10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
>D
>D
%>D
> E
>E
%>E
?!!}^!!
|}|!^
Page 3 of 10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
||!\^}^
|!| |^ } ^ \ | ^
^ } | !
_$" %<
? |}`}
?|\!\
|\!\|!|^
|\ |\|}^
^|^||^^
| }^ \^ ^\
^^ ^^ !\^ |
^^^^|
?!~^\^}|^
| ^\ !\
|
^}^|\^
!\
{
{
?
| | ^ | |
^!\
_$" %<
? >`{>@
^
|^^|
||^^
^!^
||!\|^
^|\!\^^
{~
|^!|!\^}
| |\!\
^! | \^ | {
| ^ | ^ | `{ | |^ \^!
! ^ | ^ \\! | | ^\ ^! ^ ~
?!
!\^}^|^^|^ ^|^| ^|~~|
^ | ^^ \ ^|!{`{^^^
\ | |^
^|\^}\\!^^^
|^!\
^|^|!|{`{^
|^|{`{^|\ |^|\^|^\
^^ \ \ | ^^ |^ ^ ^ ^
! ~ |^ \ ^ `{ ^| \ ^ ^
| ^\ ^} \! | \ | { ^| ^^ |!| {
^
| | { ^ ^ {
^^\|~
}!|^^\\ ^|!|!{^
|{^^\^|^||^
|!\^}^^\
^ | ^} ^ | \! | ! | ^ |
^^|\!~||
^\^}^^!\
^!!|^}^|
\! ^^ | |!| \! ^ |
\!^^|\!!
! ^ | ^| ! |!!^^^!|{
\! ^ |\ !\ ^} \! ^^^|^|~~!
Page 4 of 10
UU
*!"
!"
'
$%
$
$
%
%
)%
$
$
)$
|**`|~
|}`|~
$%
"
$%
%
Z
\Z
J^;:
{
%
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
D
D
T Z
"
D
" D
E
"
E
E
T Z
" E
?!~^^|
T Z
Page 5 of 10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
|^!|\! |{
`{^^^|^|^|\
| ! | ~ ^ ! ^|
| | ! \! ^ ! | ^ |
^|^ ! |
^ ! | \
| | \! }^
|\|!||!^!\
||^^^|}^
!\^}^|
^| {`{ ^ ! ^
^
`?
> <
| ^ | ^| { ^
| ^| ! \! } ?!
|}^^|^
\ ~ ^ } |
|^|^!|
} !\ | ~^ ^ ~ ^
^ |^ ^ `\ ^ ^
}|^\!\^}^
| } ^ ^
||!\!^|
^^|}^^|
^^!\
| \ \!
| ^ !\ | \!
| ! \! | ^ { |
^^
!
Page 6 of 10
`
`
`
<!=
$%<=
$%<=
<!!=
!J<=
`
`
<!=
$%<=
$%<=
`
!J<=
`
!J<=
`
!J<=
`
<!=
<=
<=
<!!=
`
`
!J<=
`
!J<=
`
<!!!=
<!=
<=
{
?^^|
| !\ ^} ! | ^
\! \^| | `{ ^ ^ ^\ ?^
^!!^^||^^
^||^^?
| !\ ^} ^
| ^ | ^| {`{ ^
^^^!\
!\ ^} ^ |
| | ^| {`{
|{
!\ ^} ^ |
|{
|!\^}^
|{`{|{
|!\^}^^
|{
$ Z }
<=
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
?!^||||^\!\^|
^ | ^| {`{ | ^^
`
^|^^|{|{!^|{
`
|{\^|!\^}^|{
`{ \ ! | |!| }
!J<=
!J<=
^^|\!\^
!|
| |^ ^ ! |^
?!~|^|{`{!|
^^ | ^ \! ^
|{|{|{\|{
|^|{|^|{
|^\ ^ | \!
||^\!\^}\!^
!\\||^^ \^| | \! ^
||^!^^^|?! ^ ^ ^ !\ ^}
|{`{^||
!\^}^
Page 7 of 10
??
?`
~
{
?{
~
??
t,
D
D
s
Ws^,s
,s
,s
,s
E^
E^
t,
D
D
t,
D
D
t,
D
D
??
?`
~
{
?{
{
`
~
???
?
W
s^,s
s
W
s^,s
t,
t,
t,
t,
t,
t,
t,
t,
`
<=
>>>'
D D
!$@
`
<=
!$
`
!J<=
`
`
`
!@
!J<=
!@
!@
!J<=
`
`
`
>>
D D
`
`
<=
>>'
D D
$@<=
s
&
>
&
&
&
&
&
&
&
&
@<=
!J<=
`
<=
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
?!!\^}}^^!|
!J<=
Page 8 of 10
`UU
<!!=
!J<=
`
!J<=
!J<=
$Z<=
<!=
`
!J<=
Z@<=
$@
`
!J<=
!J<=
!J<=
`
UU
!J<=
`
UUU
!J<=
`
UU
`UUU
!J<= `UU
`
!J<=
`UU
`
UUU
$@
!J<=
<!=
<=
<!!!=
`UU
`
UU
`
`
`UUU
`
`
UU
<!!=
$
!J<=
`
UU
`UU
<=
$Z<=
`
!J<=
<=
`
$
`UU
`
UUU
?!~^\^}}^^!|
!J<=
`
UUU
!J<= `UU
<!=
$%<=
`
Z!
<=
<=
`Z!
`
<!!!=
$%<=
$%<=
<=
!J<=
!J<= `UUU
`UUU
`
Z!$
$%<=
`Z!$
!J<=
<=
`
UU
<=
$<=
$<=
`
UU
`UU
$%<=
<!=
`
$%<=
`
Z@<=
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
`
UU
!J<=
?! ~ | ^| {`{ !
^
\ | ^ | \! \^| ^
^ |!| | ! | !\ ^}
\! ^ ^ ?! | ^ |^|{|{
^\^}\!|^|^ |^^||^
^ |{ | ^ |\ ^ |
^| | | ^^ !\^
|{
Page 9 of 10
^|^|\!
|{`{!|
`U
<=
`UU
`
UU
!J<=
`UU
!J<=
$%<=
<!=
`U
!J<=
`
U
<=
`U
!J<=
`
U
`UU
<=
!J<=
`UU
!J<=
`
UU
`
UU
`UU
!J<=
!J<=
`
UU
$%<=
`
U
<=
<!!=
`U
<!!!=
<=
$%<=
$%<=
<!=
`
U
`
U
`U
<=
||^^^|^
|^|\^^
||!
^ | ^ |
^\^}|^^^
|{ ?! ^|^ | | \! \^| ^
| | ^^ |{ |{ | |
^ |{ ^ ^ ! |
`\ | ^ ^^ | ^
|{ | | ^ |{ | | {
`{!|^^\
|?!|\!\^?!
^| | | ^ \ ! | |!|
}|^|\!\!|
<=
<=
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
`
UU
!J<=
{
| ^ ^^ | \^ ^ ^|^ |
|^\!|\!^
|^||^||^
| ^ | | |!| |
\!\^||^
||\
Page 10 of 10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
!
? | |~|^ ~ ^
{!^^
!!\
{
^
|!?
^}^ ! {^
\ ~ ! !^ ^
^ \^
{!^
<
\
~
~^^!!
!! \\! ^
K }
$
^ ^^^
^^^ ! ! ^| ^ K
}
$ ` "
@ <
<
$ ?