Академический Документы
Профессиональный Документы
Культура Документы
M. Arch 01
M. Arch 01
M. Arch 01
1. Step-down Transformer
2. Step-up Transformer
Step-down transformers are employed at the point of transmitting load into the facilities to the users. They are usually Pole
Mounted or Pad mounted
Transformers
Transformers that are generally employed in the built environment are Step-down Transformers. The step-up transformers
are used mostly by the power supply company in the transmission of power.
Step-down Transformer
The step down transformer is used to reduce the voltage from the high voltage used for transmission to the lower
voltage that is employed in the built environment
130000 volts
24000 volts
440/240/220/110 etc
M. Arch 01
Panel Box
ONE LINE DIAGRAM OF ELECTRICAL SYSTEM
TP 1
LIGHT
TP 2
PLUGS
TP 3
PLANTS
TP 4
AC
TP 4
TP 5
Construction Services Structure Integration (CSSI)
LIGHTS
PUMPS
4
`
3 1: Distribution Panel
2: Main 3 Phase Breaker
3: Conduits installed before
concrete placement
4: Main to Sub breaker
5: Main Breaker with above Main
6: Breaker with connecting cables
M. Arch 01
METERING
Metering is done through a single meter or through a meter centre
In single metering the main comes from a pothead directly to the individual meter
In the meter centre the mains comes to a control switch and then each meter feeds from that point
Meter centres are mostly used for buildings or structures where the clients needs individual electrical billing, while single metering is when the client
need only one billing
The rules regulating meter centres is found in JS-21 , but some of the most common BUT regulation are:
The base of the meter centre must have a minimum thickness of eighteen inches (18)
First metre socket must be one foot {1-0) from the finish floor level
Load on the rooms cannot be more than 400 AMPS with special permits need to go above
The room can be open front
The room must be ventilated
M. Arch 01
Circuits
Each circuit is govern by a breaker that is located in a panel box mounted on a wall of the structure
Circuits are rated by the resistance of the control breaker. The amperage is usually marked on the breakers in the panels and this is the indicator for the
load rating of the circuit
The typical plug circuits are either 110 or 220 volts
Five plugs are allowed 120 volts/20amps circuits. In the kitchen it is reduced to three per circuits
Light circuits are 15 amps with a maximum 12 lights permitted per circuits
Switches are placed 4-6 from the finish floor level (FFL)
Plugs are Placed 0-18 from the finish floor level
110 plugs are vertical while 220 are tandem
M. Arch 01
GEI
The GEI is the government electrical inspectors that gives certification on
behalf of the government for the purpose of the utility company to
conduct any form of termination.
No electrical connection can be made by the utility company without the
certification of the GEI.
M. Arch 01
8+
M. Arch 01
M. Arch 01
Introduction
Solar Photovoltaic (PV) power generation has recently emerged from its long hibernation; a technology
only used in satellites and special remote applications is now available to everyman
This is due to a convergence of:
THE SUN
SOURCE OF
ENERGY
Governments looking for alternative energy forms to replace the unsustainable ones we
depend on today
Modern manufacturing capability
The energy needs of modern society
World-wide abundance of free solar energy
TYPICAL
APPLICATION
OF PANES
FACING 18
DEGREES
SOUTH
M. Arch 01
Slide 13
Caribbean Background
M. Arch 01
Shortly after the silicon PV cell was invented the first commercial applications
of PV were in rural telephone systems and radio transmitters
images courtesy of
DOE/NREL: (M. & W. Rhodes,
Byron Stafford), LORENTZ
M. Arch 01
Slide 15
M. Arch 01
Slide 16
If consumers are connected to the utility grid, excess power not used at
the moment can be sold to the grid
COMBINATION
M. Arch 01
Slide 17
Portable PV systems
IMAGE:
1 PV USE FOR REMOTE CELL SITE
2 BOAT USING PV SYSTEM
3 REMOTE TENT IN THE HIGH MOUNTAINS
M. Arch 01
Slide 18
M. Arch 01
Slide 19
Domestic Application
Residential PV has two unique advantages over all forms of energy; solar modules fit on rooftops,
close to the load
By bringing energy production and consumption together - something fossil fuel power plants and
other renewable energy can't do suburban PV is distributed generation (DG) without the
transmission losses incurred with grid power
Being distributed, PV actually competes with retail power delivered by the utility not wholesale
(enforced by law: net metering)
Imagine a world with solar on every possible rooftop - and electric vehicles in every garage
M. Arch 01
Slide 20
Consideration
The cost to bring power from a utility may in some cases be prohibitive
Water pumping
Navigation beacon
Images: Courtesy of
DOE/NREL: (University
of Wyoming, Stennis
Young, Dave Parsons,
LarryAhasteen, John
Masson, United Solar
Ovonic), Sun Xtender
Remote cabin
Navaho homestead
Communications
Traffic signs
Lighting
M. Arch 01
Slide 21
Considerations
M. Arch 01
Slide 22
Considerations
Fossil Fuels
Peak-oil production has occurred twice now (USA ~1976, global ~2010)
Replacing oil and coal will be monumental undertakings and will take decades of
concerted effort
The longer we wait the more difficult, risky, and expensive it will become
The USA has 2% of the worlds reserves and requires 25% of the oil produced no amount of drilling will fix this
M. Arch 01
Slide 23
PV Growth
Not all countries are developing PV at the same rate; Germany has been the steady and strong growth center thanks to a solid
PV policy and a strong desire to replace nuclear energy with renewables
Spains attempt to develop PV was rapid and sporadic (2008) due to poorly developed incentives and commitments
USA and China are just awakening to PVs potential to provide a significant part of the energy demands, with enormous
potential growth due to the large energy needs
M. Arch 01
Slide 24
Considerations
Solar consideration for building
Construction Services
Structure Integration (CSSI)
Image: creative commons Ed Uthman
M. Arch 01
Slide 25
Area of Design
ELECTRICAL LINE
transformer
distribution
Panel
DIAGRAM
ELECTRICAL
No 2 or 2/0
Estimated distance from supply main =50 feet
Electrical cable runs underground From electrical poles to utilities room
250KVA
Equipment
ITEMS
safety factor
General electrics
DESCRIPTION
LOCATION
VOLTS
EQUIPTMENT
AMPS
QUANTITY
15
20
60
60
150
40
40
20
10
1
2
1
TYPE
HP
PHASE
1.5
Outlets
110/120-volts
220/450-volts
Main Panels
3phase
15 tonne
Offices
offices
Elevator
Air-condition
ROOF
EQUIPTMENT
FIRE PROTECTION
fire detection
Audio
SERVERS
SPRINKLER
HEATERS
domestic Water
IRRIGATION PUMPS
SERVERS
110v
220v
415v
415v
415
220v
Elevator
AHU
Chiller
PUMPS
110v
70
220v
110v
220v
40
20
20
Double Pole
Double Pole
Triple Pole
Triple Pole
Triple Pole
Triple Pole
Triple Pole
1
2
3
3
3
25
3
2
2
3
10000
PUMPS
PUMPS
Triple Pole
5
5
3
1
3
mf
Uf
# of lamps
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.4
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
1.420087787
4.219493395
2.485153628
1.710560289
8.855896334
27.54574461
4.244126001
5.244642396
4.570100697
1
1
535
Items
Safety Factor
Lighting
Generators
Description
type
Location
lux
LIGHTING
Lumens
Offices 1
office 2
Services
Vault
Passage
lobby
Conference
upper lobby
bathroom
500
500
500
500
500
500
500
500
300
10000
10000
10000
10000
10000
10000
10000
10000
10000
Area sq,ft
Room Height
2'x2 Troffers
"
"
"
"
"
"
"
"
Kva
8.520526723
25.31696037
14.91092177
10.26336174
53.135378
165.2744677
25.464756
31.46785438
45.70100697
15'
15'
15'
15'
15'
15'
15'
15'
15'
output
60.29580514
CIRCUITS
Items
Safety Factor 1.5
General electrics
Description
type
Location
volts
Breakers(AMPS)
110
220
220
20
15
15
Outlets
lighting
110/220v
110/220v
110/220v
Offices
offices
Ceiling
Generators
100kva
Floors
QUANTITY
TYPE
20
10
7
Single pole
Double Pole
Double Pole
1.5
"
Electrical System
spacing
1.5
3*100 amps
250kva
220/110
10'
10'
10'
10'
10'
10'
10'
10'
10'
PHOTOVOLTAIC
A utility-connected Photovoltaic (PV) system is becoming the most common system
configuration
Solar power-plant components can be arranged in many ways to design PV
systems for different situations, but the most common configuration is a utilityconnected system, a.k.a grid-tied
In most cases energy is not stored at the home (batteries) instead the power is fed
to the loads and the excess is sold to the grid it is a power generator
Ground Floor
ELECTRICAL ROOM
ELECTRICAL WIRING
Attached to roof
ELECTRICAL WIRING
In walls
ELECTRICAL WIRING
from panels
Section A-A
PV PANELS
BATTERIES
ELECTRICAL PV
Calculation of the solar PV energy output of a photovoltaic system
Yellow cell = enter your own data
Green cell = result (do not change the value)
White cell = calculated value (do not change the value)
Global formula :
E = A * r * H * PR
E = Energy (kWh)
A = Total solar panel Area (m)
r = solar panel yield (%)
H = Annual average irradiation on tilted panels (shadings not included)*
PR = Performance ratio, coefficient for losses (range between 0.9 and 0.5, default value = 0.75)
You have to find the global annual irradiation incident on your PV panels with your specific inclination (slope, tilt)
and orientation (azimuth).
More info
Source : www.photovoltaic-software.com
75329kWh/an
335m
15%
2000kWh/m.an
0.75
50.3kWp
8%
8%
2%
2%
3%
3%
2%
0%
ORIENTATION
:
1 8 DEGREES
DUE SOUTH
PV PANELS
PANELS
INVERTER
MAIN ELEC, PANEL
BATTERIES
BATTERIES
No Batteries
ITEMS ROOF AREA
1
479
UNITS
% USE
MSQ
PANEL SIZE
70
1.953697372
# PANELS
172
KW
STORAGE
42905.82625
40%
STORAGE
No Batteries
17162.3305
2
3
4
KWH/DAY
PEAK SUN HOURS (Consumption)
6
257.43
AH/DAY
5363.125
Batteries :
Alignment : Series
6 volts
Type Solar
# of 168
WH/day
(Consumption)
257430
8581
Battery Ah
Capacity
420
Total Batteries
BATTERY VOLTAGE BATTERIES IN PARALLEL BATTERIES IN SERIES Required
6
20.43095238
163.45
TYPICAL BATTERIES IN
SERIES