Вы находитесь на странице: 1из 72

Step

MIDAS IT Co., Ltd.

Construction Stage Analysis of Metro Station


midas GTS Tutorial

Step

00

Construction Stage Analysis of Metro Station


Over view

L1

In this tutorial the modeling


sequence for a 2D metro station has
been given.

MIDAS IT Co., Ltd.

The figure on the right shows the

Man Made Fill (1)


Upper Sand (2)
Upper Clay (3)
Middle Sand (4)
Lower Sand (5)

L2
L3
L4

cross section of the metro station.

The ground has 9 different layers of


soil

Upper Clay (6)

Lower Sand (7)


Lower Clay (8)

Four different stages of excavation


have been identified.

L1- Ground to Roof Slab

L2- Roof Slab to Ticket Slab

L3 Ticket Slab to Intermediate Slab

L4 Intermediate Slab to Raft Slab

The columns, barrets, slabs and D

Lower Sand (9)

wall have been modeled as


structural elements (beam elements).

On the next page a zoomed in view


of the D wall and columns can be
seen.

If you want to start this tutorial except definition of attributes and generation of all geometries, I
recommend that you need to see this tutorial from Step 6(page 35).

Construction Stage Analysis of a Metro Station

Step

00

Construction Stage Analysis of a Metro Station


Over view

20 kN/m2
+54.34

20 kN/m2

The closer look of the cross section

+52.59

+52.34

0.90

is shown here during the


construction phase.
2,5 kN/m2

0.70

+47.54

2,5 kN/m2

0.70

+42.89

0.80

0.80

0.80

20 kN/m2

MIDAS IT Co., Ltd.

+33.29

+32.69
EB +30.0
0.80
+26.85

+24.19

6.48

4.92

11.39

15.97

4.92

6.48

11.40

27.37

Construction Stage Analysis of a Metro Station

Step

01 Material Properties

MIDAS IT Co., Ltd.

Soil Material Properties

*MC- Mohr Coulomb

ID

Name

Man
Made Fill

Upper
Sand

Middle
Sand

Lower
Sand

Upper
Clay UD

Lower
Clay UD

Upper
Clay D

Lower
Clay D

Type

Ground

Ground

Ground

Ground

Ground

Ground

Ground

Ground

(E) [MPa]

40

100

140

60

80

54

72

Poissons Ratio ()

0.3

0.25

0.25

0.25

0.45

0.45

0.35

0.35

Unit Weight [kN/m3]

16.677

18.639

19.62

20.601

18.639

18.1485

18.639

18.1485

Unit Weight
(Saturated) [kN/m3]

16.677

18.639

19.62

20.601

18.639

18.1485

18.639

18.1485

Cohesion (c) [kPa]

160

170

Friction Angle ()

27

35

38

39

28

30

K0

0.52

0.43

0.38

0.36

0.56

0.62

0.56

0.62

Material Model

MC

MC

MC

MC

MC

MC

MC

MC

Drainage Parameter

Undrain
ed

Undrain
ed

Undrain
ed

Undrain
ed

Undrain
ed

Undrain
ed

Drained

Drained

Construction Stage Analysis of a Metro Station

Step

01 Material Properties

MIDAS IT Co., Ltd.

Structural Element Material Properties


ID

10

11

12

13

Material

D Wall
Concrete

D Wall
Concrete
(service)

Structural
Steel

Structural
Concrete

Structural
Concrete
(Service)

Type

Structural

Structural

Structural

Structural

Structural

(E) [MPa]

19,905

9,953

200,000

23,281

11,641

Poissons Ratio ()

0.2

0.2

0.3

0.2

0.2

Unit Weight
(Gamma) [kN/m3]

25

25

77

25

25

Material Model

Elastic

Elastic

Elastic

Elastic

Elastic

Note: 1. D Wall concrete is used in D Wall and Barrets


2. Structural Concrete is used in Slabs and Columns

GTS provides two types of materials, Ground and Structural. Ground is used to define material characteristics for t
hose elements which are used to represent soil/ground (like plane strain in 2D and solid elements in 3D).
Structural material is used to define the material characteristics of structural elements like beam/truss/plate etc,
Construction Stage Analysis of a Metro Station

Step

02 Properties

MIDAS IT Co., Ltd.

Property

Columns
Since the column is a composite section
we directly enter the properties of the sec
tion as shown.

Barrets
Property is used to define the geometrical d
etails of structural elements. For line elemen
ts cross section/spacing may be defined. Fo
r plane elements thickness may be defined

Construction Stage Analysis of a Metro Station

Step

02 Properties

MIDAS IT Co., Ltd.

Property

Roof Slab

Ticket/Intermediate Slab

Construction Stage Analysis of a Metro Station

Step

02 Properties

MIDAS IT Co., Ltd.

Property

Raft Slab

D Wall

Construction Stage Analysis of a Metro Station

Step

03

File >

MIDAS IT Co., Ltd.

Open

Procedure

1. Main Menu > File> New


2. In the Project Setting define the
details as shown.
3. Click [OK].

Construction Stage Analysis of a Metro Station

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure

1. Main Menu > Model >

Property > Attribute


2. Click on [Add] >Select [Plane].
3. ID 1, Name Man Made Fill.
4. Element Type > [Plane Strain].

5. Material > Click [Add].

6. ID 1, Name Man Made Fill,


3

Model Type [Mohr Coulomb].


4

7. Enter the properties as shown.

8. Click [OK] in Add/Modify


Ground Material.
9. Click [Apply] in Add/ Modify
Plane Attribute.
9

10. Similarly create the Attributes


for Upper Sand, Middle Sand,
Lower Sand, Upper Clay UD

and Lower Clay UD using the


material properties defined in

the table before.


Construction Stage Analysis of a Metro Station

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure
1. ID 7, Name Upper Clay D.
2. Element Type > [Plane Strain].
3. Material > Click [Add].
4. ID 7, Name Upper Clay D,
Model Type [Mohr Coulomb].

5. Enter the properties as shown

5
4

in the table before.


6. Make sure that the Drainage
Parameter is changed to

1
2
3

Drained
7. Click [OK] in Add/Modify
Ground Material.
8. Click [Apply] in Add/ Modify
Plane Attribute.

9. Similarly create the Attributes


for Lower Clay D using the

material properties given in


table before.

Construction Stage Analysis of a Metro Station

10

Step

04

Model > Property >

Attribute

MIDAS IT Co., Ltd.

Procedure
1. The table on the right shows all
the Attributes created for
different soils.
2. Upper Clay Drained and Lower

Clay Drained have been defined


separately because their
properties are different during
drained and undrained behavior.
3. So the Drained behavior of Clay
will be simulated later on as a
boundary condition during the
modeling process.
4. In the next step we create the
Attributes for the Structural
Elements.

Construction Stage Analysis of a Metro Station

11

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure

1
2

1. Main Menu > Model > Property >


Attribute
2. Click [Add] > Select [Line].
3. ID 9, Name D Wall
4. Element Type > [Beam].

5. Material > Click [Add].

6. Enter the material properties for

D Wall Concrete and click [OK].


7. Property > Click [Add].
8

8. ID `1, Name `D Wall.

9. Type > [Beam/Nonlinear Beam],


10

Click [Sectional Library].


10. Enter the properties as shown.
11. Click[OK] in Sectional Library,
Click [OK] in Add/Modify
Property Box.
9

12. Click [Apply] in Add/Modify Line


Attribute.

11

11

Construction Stage Analysis of a Metro Station

12

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure

1. Attribute ID 10, Name D Wall


Service
2. Element Type > [Beam].
3. Material > Click [Add].
4. Enter the material properties for
D Wall Conc. Service as shown

2
4
3

and click [OK] in Add/Modify


5

Structural Material box.


5. Property > Select D Wall.
6. Click [Apply] in Add/Modify Line
Attribute.

Construction Stage Analysis of a Metro Station

13

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure

1. ID 11, Name Barret


1

2. Element Type > [Beam].

2
3

3. Material > Select D Wall


Concrete.

4. Property > Click [Add].


5. ID `2, Name `Barret.
10

6. Type > [Beam]


7. Click [Sectional Library].
8. Enter the properties as shown.
5

9. Click[OK] in Sectional Library,

Click [OK] in Property Dialogue


8

Box.
10. Click [Apply] in Add/Modify Line
Attribute.

7
9
9

Construction Stage Analysis of a Metro Station

14

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure

1. ID 12, Name Barret Service


2. Element Type > [Beam].
3. Material > Select D Wall Conc.
Service.
4. Property > Select Barret.

1
2
3

5. Click [Apply] in Add/Modify Line

Attribute.

Construction Stage Analysis of a Metro Station

15

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure
1. ID 13, Name Column
2. Element Type > [Beam].

2
3

3. Material > Click [Add].

4. Enter the material properties for


Structural Steel as shown and
click [OK] in Add/Modify
Structural Material box.
10

5. Property > Click [Add].

6. ID `3, Name `Column.


6

Since the column is a composite section as


shown the properties of the composite
s
ection have been calculated and then
entered

7. Type > [Beam/Nonlinear Beam]


7

8. Enter the properties as shown.

9. Click [OK] in Add/Modify


Property Dialogue Box.
10. Click [Apply] in Add/Modify Line
Attribute.

Construction Stage Analysis of a Metro Station

16

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure
1. ID 14, Name Roof Slab

2. Element Type > [Beam].

3. Material > Click [Add].

4. Enter the material properties for


Structural Concrete as shown
and click [OK] in Add/Modify
Structural Material box.

11

5. Property > Click [Add].


6. ID `4, Name `Roof Slab.
6

7. Type > [Beam]

7
8

8. Click [Sectional Library]


9. Enter the properties as shown.
10. Click [OK] in Add/Modify
Property Dialogue Box.
11. Click [Apply] in Add/Modify Line
Attribute.

8
10
10

Construction Stage Analysis of a Metro Station

17

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure
1. ID 15,
Name Roof Slab Service

2
3

2. Element Type > [Beam].


6

3. Material > Click [Add].


4. Enter the material properties for
ID-13, Name Structural Conc.
Service as shown.

5. Click [OK] in Add/Modify


Structural Material box.

6. Property > Select Roof Slab.


7. Click [Apply] in Add/Modify Line
Attribute.

Construction Stage Analysis of a Metro Station

18

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure
1. ID 16, Name Ticket/Inmdt Slab

2. Element Type > [Beam].

3. Material > Select

12 : Structural Concrete
4. Property > Click [Add].
5. ID `5, Name `Ticket/Inmdt Slab.
10

6. Type > [Beam/Nonlinear Beam]


7. Click [Sectional Library]
8. Enter the properties as shown.
5

9. Click [OK] in Add/Modify

6
8

Property Dialogue Box.


10. Click [Apply] in Add/Modify Line
Attribute.
Note : Since the Ticket and
Intermediate Slab have the same
thickness and same material so
the Attribute for them is also
same.

9
7

Construction Stage Analysis of a Metro Station

19

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute

Procedure
1. ID 17, Name Ticket/Inmdt Slab
Service
2. Element Type > [Beam].
3. Material > Select

13 : Structural Conc. Service


2

4. Property > Select


5 : Ticket/Inmdt Slab

3
4

5. Click [Apply] in Add/Modify Line


Attribute.

Construction Stage Analysis of a Metro Station

20

Step

04

Model > Property >

MIDAS IT Co., Ltd.

Attribute
11

Procedure
1. ID 18, Name Raft Slab

2. Element Type > [Beam].

2
3

3. Material > Select


4

12 : Structural Concrete
4. Property > Click [Add].
5. ID `6, Name `Raft Slab.

10

6. Type > [Beam]


7. Click [Sectional Library]
8. Enter the properties as shown.

9. Click [OK] in Add/Modify

Property Dialogue Box.


8

10. Click [Apply] in Add/Modify Line


Attribute.
11. Create the Attribute for Raft
Slab Service by selecting
material 13:Structural Concrete
and Property 6:Raft.

7
9
9

Construction Stage Analysis of a Metro Station

21

Step

04

Model > Property >

Attribute

MIDAS IT Co., Ltd.

Procedure
1. All the Attributes that have been
created are shown here.

Construction Stage Analysis of a Metro Station

22

Step

05

Geometry > Curve> Create on WP > Rectangle


Procedure

MIDAS IT Co., Ltd.

(Wire)

1. Main Menu > Geometry > Curve >


Create on WP > Rectangle(Wire)
2. Make sure that the Method is set
to ABS x, y
3. Enter coordinates -100,-100 and
click [Apply].

4. The Method now changes to REL


dx, dy.

5. Enter the coordinates of the


diagonally opposite corner as
200,100.
6. On the execution of this command
we get a wire whose dimensions

are X=200 m and Y=100 m as


shown in the figure.
7. Click [Cancel] to close the
Rectangle dialogue box.

Construction Stage Analysis of a Metro Station

23

Step

05

MIDAS IT Co., Ltd.

Geometry > Curve> Create on WP > Line


1

Procedure
1. Main Menu > Geometry >

Curve > Create on WP > Line


2. Make sure that the Method is set
to ABS x, y. Enter coordinates
-11.4, 0 and click [Apply].
4

3. The Method now changes to


REL dx, dy. Enter the
coordinates of the end point as
0,-27.49.
4. Similarly repeat the above
procedure with the initial

coordinates as 11.4 ,0 and the


(next) relative coordinates as
0, -27.49.
5. Create two more lines whose
respective ABS & REL
coordinates are given below

6. 1st line (-6.48,-1.75) (0,-28.4)


7. 2nd line (6.48,-1.75) (0,-28.4)

Construction Stage Analysis of a Metro Station

24

Step

05

Geometry > Curve> Create on WP > Line


Procedure

MIDAS IT Co., Ltd.

1. In the previous steps the


geometry of D Wall and Columns
was created. In this step the
geometry of the Slabs will be
created.
3

2.

1st line

(-11.4,-1.75) (22.8,0)

3. 2nd line (-11.4,-6.8) (22.8,0)


4. 3rd line (-11.4,-11.45) (22.8,0)
5. 4th line (-11.4,-21.05) (22.8,0)
Note : The first set of
coordinates are ABS (x, y) and

the next are REL (dx, dy) as can


be seen in the figure.

Construction Stage Analysis of a Metro Station

25

Step

06

MIDAS IT Co., Ltd.

Geometry > Curve> Intersect


Procedure

1. Main Menu > Geometry >


Curve > Intersect

2. Select all the curves that have


2

been created till this step by


using (Ctrl+A) or drag the
mouse around the created
edges to select all.
3. The selected edges will be
displayed by pink color
4. Click [Apply].
5. To ensure proper nodal
connectivity it is necessary to
intersect those edges which are
in contact (like Wall and slab
are in contact so the edges
representing them need to be
intersected)

Construction Stage Analysis of a Metro Station

26

Step

07

Geometry > New Geometry Set >

MIDAS IT Co., Ltd.

Incl./Excl. Items

Procedure
1. The edges now intersected will
be split up into smaller edges.
2. So in order to organize the
7

edges, Geometry Set will be


3

used.

Check-off to hide Slabs

3. Geometry > Geometry Set >


Context Menu > New Geometry
5

Set
4. Rename the new Geometry set
to Slabs by using F2. Right
click on this Geometry set and
select Incl./Excl. Items.
5. Select the 12 edges as
highlighted and click [OK].
6. Now when the Geometry Set
Slabs is selected, the
highlighted edges will be
selected.

7. Hide Slabs Geometry Set by


checking it off as shown.
Construction Stage Analysis of a Metro Station

27

Step

08

Geometry > Curve> Create on WP > Line

MIDAS IT Co., Ltd.

Procedure
1. Geometry > Curve > Create on
WP > Line
2. To create the edges representing
the different soil profiles, lines
will be created with co-ordinates
11

mentioned.
3. 1st line (-100,-3) (200,0)
4. 2nd line (-100,-9.05) (200,0)
5. 3rd line (-100,-11.55) (200,0)
6. 4th line (-100,-16.55) (200,0)
7. 5th line (-100,-20.55) (200,0)

12

8. 6th line (-100,-22.05) (200,0)


9. 7th line (-100,-30.55) (200,0)
10. 8th line (-100,-36.0) (200,0)
11. When all the edges are created
they are shown in the figure.
12. The distance at any time can be
checked by pressing F3 and
invoking the Measure
command.
Construction Stage Analysis of a Metro Station

28

Step

09

MIDAS IT Co., Ltd.

Geometry > Curve> Intersect


Procedure

1. Main Menu > Geometry >


Curve > Intersect

2. Select all the curves by using


(Ctrl+A) and click [Apply].
2

Construction Stage Analysis of a Metro Station

29

Step

10

Geometry > New Geometry Set >

MIDAS IT Co., Ltd.

Incl/Excl Items

Procedure
1. Geometry > Geometry Set >
Context Menu > New Geometry
Set
4

2. Rename the new Geometry set


1

to Soils by using F2. Right

Check-off to hide Soils

click on this Geometry set and


select Incl./Excl. Items.
3. Select the 32 edges as
highlighted and click [OK].
4. Hide Soils Geometry Set by
checking it off as shown.
3

Construction Stage Analysis of a Metro Station

30

Step

10

Geometry > New Geometry Set >

Incl/Excl Items

MIDAS IT Co., Ltd.

Procedure
1. Similarly create two new
Geometry Sets and rename
them to D Wall and
Columns.
2. Include the edges as shown in
the D Wall Geometry Set.

3. Include the edges as shown in


the Columns Geometry Set.
4. Hide the Columns Geometry
Set and show only D Wall
Geometry Set.

Construction Stage Analysis of a Metro Station

31

Step

11

MIDAS IT Co., Ltd.

Geometry > Transform> Translate


Procedure

1. Show only the D Wall


Geometry Set and hide the rest
3

as shown.
4

2. Main Menu > Geometry >


Transform > Translate.
5

3. Select the highlighted edge.


4. Direction > Select Global-X
5. Enter the details as shown and
click [Apply].
6. Similarly repeat the procedure

for the other edge as shown in


the figure below

Construction Stage Analysis of a Metro Station

32

Step

12

MIDAS IT Co., Ltd.

Geometry > Curve> Intersect


Procedure

1. Hide the D Wall Geometry Set.


2. Main Menu > Geometry >

3
3

Curve > Intersect


3. Select all the curves by using
(Ctrl+A) and click [Apply].
4. Select the two edges as shown
5. Invoke the context menu and
select Delete to delete these
edges.
6. When the Delete dialogue box
appears, click [OK].
4

Construction Stage Analysis of a Metro Station

33

Step

13

Geometry > Curve> Create on WP > Line


Procedure

1. Two more lines will be created

MIDAS IT Co., Ltd.

which would define the location


of building loads
2. Main Menu > Geometry >
Curve > Create on WP > Line
3. 1st line (-27.37,-2) (-10,0)
4. 2nd line (27.37,-2) (10,0).
5. The geometry now is complete
and the next step is creating the
mesh sets.
4

Construction Stage Analysis of a Metro Station

34

Step

14

Mesh > Size Control> Along

MIDAS IT Co., Ltd.

Edge

Procedure

1. Show all the Geometry Sets.


4

2. Main Menu > Mesh > Size

Control > Along Edge


3. Select the edges as shown.
4. Seeding Method > Select
Interval Length, Interval
Length > Enter 1.
5. Click [Preview ] ] to see the

seeding. Click [Apply].


6. Change the Seeding Method to
Linear Grading (Length).

7. Select the edge and reversed


6

edge as shown.

8. Enter Slen as 5 and Elen


as 1.
9. Click [Preview

] to see the

seeding. Click [Apply].

Construction Stage Analysis of a Metro Station

35

Step

14

Mesh > Size Control> Along

MIDAS IT Co., Ltd.

Edge

Procedure
1. Select the 6 edges on the left of
D Wall and 6 reversed edge to
1

the right of D Wall as shown.


2. Enter Slen as 5 and Elen
as 1.
3. Click [Preview

] to see the

seeding. Click [Apply].


4. Select the 2 edges as shown.

5. Let the Seeding Method and


other parameters be same.
6. Check on Symmetric Seeding
7. Click [Preview

] to see the
4

seeding. Click [OK].


5

Construction Stage Analysis of a Metro Station

36

Step

14

Mesh > Display >

MIDAS IT Co., Ltd.

Mesh Seed

Procedure
1. To see the seeds that have
been assigned to all the edges,
select all the edges, right click
to invoke the Context Menu and
select Display Mesh Seed
2. When the Display Mesh Seed
1

dialogue box appears select

Show Mesh Seed and click


2

[OK].
3. To hide the seeds, select all the
edges, right click to invoke the
Context Menu and select
Display Mesh Seed
4. Select Hide Mesh Seed in the
Display Mesh Seed dialogue
box and click [OK].

Construction Stage Analysis of a Metro Station

37

Step

15

Mesh > Auto-Mesh >

MIDAS IT Co., Ltd.

Planar Area

Procedure
1. Main Menu > Auto-Mesh >
Planar Area...
2. Select the 23 edges as shown
which define the first layer of

1
6

soil.
3

3. Enter Element Size 5.


4. Select Attribute 1 : Man Made

Fill.
5. Click on Advanced Option.
6. Select Element type as

Triangle
7. Check-off Register Each Area

Independently and click [OK].


8. Click [Apply] in Auto-Mesh
Planar Area dialogue box.
Note : If anytime the meshing step
is undone the features in
Advanced Option are again
set to default values.
Construction Stage Analysis of a Metro Station

38

Step

15

Mesh > Auto-Mesh >

MIDAS IT Co., Ltd.

Planar Area

Procedure
1. Check-off the Man Made Fill
Mesh set previously created so

that the selected edges can be


seen clearly.
2. Select the edges as shown for
the second layer.
3. Select Attribute 2 : Upper Sand

and enter Name Upper Sand 2


4. Click [Advanced Option] to check
if the options selected are still
updated.

5. Click [Preview] to see the seeds.


Click [Apply] to create the mesh
4

set.
Note : The edges which have Green

seeds imply those edges have


been previously used for
meshing and when the seeds are
Red the edges have not been
used for meshing.
Construction Stage Analysis of a Metro Station

39

Step

15

Mesh > Auto-Mesh >

MIDAS IT Co., Ltd.

Planar Area

Procedure
1. Check-off the Upper Sand 2
Mesh set previously created.

2. Select the 23 edges as shown for


the third layer.
3

3. Select Attribute 5 : Upper Clay


UD and enter Name Upper Clay
3
4. Click [Preview] to see the seeds.

Click [Apply] to create the mesh


set.
5. Check-off the Upper Clay 3
Mesh set.
6. Select the edges for the 4th layer

as shown.
7. Select Attribute 3 : Middle Sand
7

and enter Name Middle Sand 4


8. Click [Preview] to see the seeds.
Click [Apply] to create the mesh
set.

Construction Stage Analysis of a Metro Station

40

Step

15

Mesh > Auto-Mesh >

MIDAS IT Co., Ltd.

Planar Area

Procedure
1. Check-off the Middle Sand 4
Mesh set previously created.
2. Select the edges as shown for

the 5th layer.


3. Select Attribute 4 : Lower Sand

and enter Name Lower Sand 5


4. Click [Preview] to see the seeds.
Click [Apply] to create the mesh
set.

5. Check-off the Lower Sand 5


Mesh set.
6. Select the edges for the 6th layer
as shown.

7. Select Attribute 5 : Upper Clay


UD and enter Name Upper Clay

6
8. Click [Preview] to see the seeds.
Click [Apply] to create the mesh
8

set.
Construction Stage Analysis of a Metro Station

41

Step

15

Mesh > Auto-Mesh >

MIDAS IT Co., Ltd.

Planar Area

Procedure
1. Check-off the Upper Clay 6
Mesh set previously created.
2. Select the edges as shown for
the 7th

layer.

3. Select Attribute 4 : Lower Sand

and enter Name Lower Sand 7


4. Click [Preview] to see the seeds.
Click [Apply] to create the mesh
4

set.
5. Check-off the Lower Sand 7
Mesh set.
6. Select the edges for the 8th layer
as shown.

7. Select Attribute 6 : Lower Clay


UD and enter Name Lower Clay
7

8
8. Click [Preview] to see the seeds.
Click [Apply] to create the mesh
8

set.
Construction Stage Analysis of a Metro Station

42

Step

15

Mesh > Auto-Mesh >

MIDAS IT Co., Ltd.

Planar Area

Procedure
1. Check-off the Lower Clay 8

Mesh set previously created.


2. Select the edges as shown for
the 9th layer.

3. Select Attribute 4 : Lower Sand


and enter Name Lower Sand 9
4. Click [Preview] to see the seeds.
Click [OK] to create the mesh set

and close the dialogue box.


5. Check-on all the Mesh sets.
6. The mesh sets are shown in the
figure below.
5

Construction Stage Analysis of a Metro Station

43

Step

16

Model> Display

Material/Property

MIDAS IT Co., Ltd.

Procedure
1. To check that the mesh sets have
been assigned the Attributes
correctly, show all the mesh sets
2. Main Menu > Model >

Display

Material/Property.
3. The Attributes that have been
assigned to the mesh set can
now be cross-checked by the
color code and confirmed.
2

4. In the next step, the mesh sets


would be divided into mesh sets
based on stages of
construction/excavation.

Construction Stage Analysis of a Metro Station

44

Step

17

Mesh> Mesh Set >

MIDAS IT Co., Ltd.

New Mesh Set

Procedure
1. In the Works-Tree go to Mesh >
Mesh Set > Context Menu > New
Mesh Set.
2. Rename this New Mesh Set to
L1 by clicking F2 on it.
1

3. Right click on L1 mesh set >


Context Menu > Mesh Set >
Incl./Excl. Items.
4. Select the 94 elements to be
included in the L1 mesh set.
4

5. Click [OK].

6. Hide the L1 mesh set.

Construction Stage Analysis of a Metro Station

45

Step

17

Mesh> Mesh Set >

MIDAS IT Co., Ltd.

New Mesh Set

Procedure
1. Similarly create a New Mesh Set
and rename it to L2 by clicking
F2 on it.
2. Right click on L2 mesh set >
Context Menu > Mesh Set >
1

Incl./Excl. Items.
3. Select the highlighted elements
1

to be included in the L2 mesh


set.
4. Click [OK].
5. Hide the mesh set L2
6. Create two more New Mesh Set.
7. Rename them to L3 and L4
3

respectively.

Construction Stage Analysis of a Metro Station

46

Step

17

Mesh> Mesh Set >

MIDAS IT Co., Ltd.

New Mesh Set

Procedure
1. Right click on L3 mesh set >
Context Menu > Mesh Set >
Incl./Excl. Items.
2. Select the highlighted elements
2

to be included in the L3 mesh


set.
3. Click [OK] and hide this mesh set.

4. Right click on L4 mesh set >


Context Menu > Mesh Set >
Incl./Excl. Items.
5. Select the highlighted elements

to be included in the L4 mesh


6

set.
6. Click [OK].

Construction Stage Analysis of a Metro Station

47

Step

18

Model> Element >

MIDAS IT Co., Ltd.

Extract Element

Procedure
1. Model Works Tree > Mesh > Mesh

Set > Context Menu > Hide All.

2. Geometry > Curve > Context


3

Menu > Show All.


3. Check-on/Show all the
Geometry Sets except the Soil
Geometry Set.

4
5

4. Main Menu > Model >Element >


6

Extract Element
5. From Shape > Edge.
6. Select Edge(s) > Select the D
Wall Geometry Set.
7. Attribute 9 : D Wall.

8. Name D Wall.
8

9. Click [Apply].
10. Hide the D Wall Geometry Set.
9

Construction Stage Analysis of a Metro Station

48

Step

18

Model> Element >

MIDAS IT Co., Ltd.

Extract Element

Procedure
1. Select Edge(s) > Select the edges
as shown for the Roof Slab.
2. Attribute 14 : Roof Slab.
3. Name Roof Slab. Click [Apply].
4. Select Edge(s) > Select the edges
as shown for the Ticket Slab.
5. Attribute 16 : Ticket/Inmdt Slab.
1

10

6. Name Ticket Slab. Click [Apply].


7. Select the edges as shown for the
Intermediate Slab.
8. Attribute 16 : Ticket/Inmdt Slab.
9. Name Intermediate Slab. Click

11

12

[Apply].
10. Select Edge(s) > Select the edges
as shown for the Raft Slab.
11. Attribute 18 : Raft Slab.
12. Name Raft Slab. Click [Apply].

Construction Stage Analysis of a Metro Station

12

49

Step

18

Model> Element >

MIDAS IT Co., Ltd.

Extract Element

Procedure
1. Select Edge(s) > Select the edges
as shown for the L2 Columns.
2. Attribute 13 : Column.
3. Name L2 Columns.Click [Apply].
4. Select Edge(s) > Select the edges
as shown for the L3 Columns.
5. Attribute 13 : Column.
6. Name L3 Columns.Click [Apply].

10

7. Select Edge(s) > Select the edges


as shown for the L4 Columns.
8. Attribute 13 : Column.
9. Name L4 Columns. Click
[Apply].

11

12

10. Select Edge(s) > Select the edges


as shown for the Barrets.
11. Attribute 11 : Barret .
12. Name Barret.

13

13. Click [OK].


Construction Stage Analysis of a Metro Station

50

Step

19

Model> Element >

MIDAS IT Co., Ltd.

Align Csys

Procedure

1. Show D Wall,L2 Columns,L3


Columns,L4 Columns and
Barret mesh sets only.
2. Select the above mentioned mesh
sets. Context Menu > Display >
Click Element Csys.

2
4

3. The coordinate system of the 1D


elements are not aligned in the

same direction.
3

4. To align the elements go to


Model > Element > Change

Parameter
5. Select base element as the element
whose Z-axis (blue) is aligned in
same direction as Global X-axis
(red).
6. Select all the displayed elements as
elements to be aligned & [Apply].
7. Hide Element Csys by following

Step 2.
Construction Stage Analysis of a Metro Station

51

Step

19

Model> Element >

MIDAS IT Co., Ltd.

Align Csys

Procedure

1. Show Roof Slab, Ticket Slab,


Intermediate Slab and Raft
Slab mesh sets only.
2. Select the above mentioned mesh
sets. Context Menu > Display >
2

Click Element Csys.


3. Select base element as the

element whose X-axis (red) is


aligned in same direction as
Global X-axis (red).
4. Select all the displayed elements

3
4

of the slab mesh sets as elements


to be aligned & click [OK].
5. Hide Element Csys by following
Step 2.

Construction Stage Analysis of a Metro Station

52

Step

20

Model > Load >

MIDAS IT Co., Ltd.

Self Weight and Line Beam Load


1

Procedure

1. Main Menu >Model > Load >


3

Self Weight
2. Load Set >Self Weight .
3. Self Weight Factor> Y : -1.

5
6

4. Click [OK].

5. Model > Load > Line Beam

Load
7

6. Load Set Roof Slab Load.


7. Select the nodes at the two end
of the Roof Slab.
8. Direction> Global Y
8

9. Projection> No.
9

10. Enter the values of x1, x2, w1

10

and w2 as shown.
11. Click [Apply].
11

Construction Stage Analysis of a Metro Station

53

Step

21

Model > Load >

MIDAS IT Co., Ltd.

Line Beam Load

Procedure
1. Load Set Ticket Slab.

2. Select the nodes at the two end


of the Ticket Slab.
3. Direction> Global Y
4. Projection> No.
5. Enter the values of x1, x2, w1
7

and w2 as shown.
6. Click [Apply].
7. Load Set Ticket Slab Service.

8. Select the nodes at the two end


of the Ticket Slab.
9. Direction> Global Y
10. Projection> No.

10

11

11. Enter the values of x1, x2, w1


and w2 as shown.
12. Click [Apply].
6

12

Construction Stage Analysis of a Metro Station

54

Step

21

Model > Load >

MIDAS IT Co., Ltd.

Line Beam Load

Procedure
1. Load Set Intermediate Slab.

2. Select the nodes at the two end


of the Intermediate Slab.
3. Direction> Global Y
4. Projection> No.
5. Enter the values of x1, x2, w1
7

and w2 as shown.
6. Click [Apply].
7. Load Set Intermediate Slab

Service.
8. Select the nodes at the two end
of the Intermediate Slab.
9. Direction> Global Y

10

11

10. Projection> No.


11. Enter the values of x1, x2, w1
and w2 as shown.
12. Click [OK].

12

Construction Stage Analysis of a Metro Station

55

Step

22

Model > Load >

MIDAS IT Co., Ltd.

Pressure Load

Procedure
1. Model Works Tree > Geometry >
Curve > Context Menu > Show All.
2. Main Menu > Model > Load >

8
4

Pressure Load
3. Load Set CS Traffic Load.
4. Object Type > [Curve] . Select the

2
3

2 edges as shown.
5. Enter the values as shown in the
dialogue box
6. Click [Preview] to see the loads
and click [Apply].
7. Load Set Service Traffic Load.
8. Object Type > [Curve] . Select the
3 edges as shown.
9. Enter the values as shown in the
dialogue box

10. Click [Preview] to see the loads


and click [Apply].
6

10

Construction Stage Analysis of a Metro Station

56

Step

22

Model > Load >

MIDAS IT Co., Ltd.

Pressure Load

Procedure
1. Load Set Building Load 1.
2. Object Type > [Curve] . Select the

edges as shown.
3. Enter the values as shown in the
dialogue box
4. Click [Preview] to see the load

and click [Apply].


5. Load Set Building Load 2.
6. Object Type > [Curve] . Select the
edge as shown.
7. Enter the values as shown in the
dialogue box
8. Click [Preview] to see the load
and click [Apply].

Construction Stage Analysis of a Metro Station

57

Step

23

Model > Boundary > Ground

MIDAS IT Co., Ltd.

Support

Procedure
1. Analysis Works Tree > Load >

Context Menu > Hide All.


2. Model Works Tree > Mesh > Mesh
Set Context Menu > Show All.

3
4

3. Main Menu > Model > Boundary >


Ground Support

4. BC Set > Ground Support


5. Click [OK].

Construction Stage Analysis of a Metro Station

58

Step

24

Model > Boundary > Change

MIDAS IT Co., Ltd.

Element Attribute
3

Procedure
1. Main Menu > Model > Boundary >
4

Change Element Attribute


2. BC Set > Upper Clay Drained.
1

3. Change the selection filter to Mesh

(M)
4. Select the Upper Clay 3 and Upper
Clay 6 mesh sets. From the Model
Works Tree.

5. Select Attribute 7:Upper Clay D

6. Click [Apply].
7. BC Set > Lower Clay Drained.
8. Change the selection filter to Mesh

(M)
7

9. Select the Lower Clay 8 mesh set.


From the Model Works Tree.
10. Select Attribute 8:Lower Clay D
11. Click [Apply].

10

11

Construction Stage Analysis of a Metro Station

59

Step

24

Model > Boundary > Change


Procedure

MIDAS IT Co., Ltd.

Element Attribute
2

1. BC Set > D Wall Service.


3

2. Change the selection filter to Mesh


(M)
3. Select the D Wall mesh set from the
Model Works Tree.

4. Select Attribute 10:D Wall Service


5. Click [Apply].
6. BC Set > Barret Service.

4
5

7. Change the selection filter to Mesh


(M)
8. Select the Barret mesh set from the
Model Works Tree.
9. Select Attribute 12:Barret Service

10. Click [Apply].

9
10

Construction Stage Analysis of a Metro Station

60

Step

24

Model > Boundary > Change


Procedure

1. BC Set > Roof Slab Service.

MIDAS IT Co., Ltd.

Element Attribute
2

2. Change the selection filter to Mesh


(M)
1

3. Select the Roof Slab mesh set from


the Model Works Tree.
4. Select Attribute 15:Roof Slab
Service
4

5. Click [Apply].

6. BC Set > Ticket Slab Service.


7. Change the selection filter to Mesh
8

(M)
8. Select the Ticket Slab mesh set
from the Model Works Tree.

9. Select Attribute 17:Ticket/Inmdt


Slab Service
10. Click [Apply].
9
10

Construction Stage Analysis of a Metro Station

61

Step

24

Model > Boundary > Change

MIDAS IT Co., Ltd.

Element Attribute
2

Procedure
1. BC Set > Inmdt Slab Service.
3

2. Change the selection filter to Mesh


(M)
3. Select the Intermediate Slab mesh
1

set from the Model Works Tree.


4. Select Attribute 17:Ticket/Inmdt
Slab Service
5. Click [Apply].

4
5

6. BC Set > Raft Slab Service.


7. Change the selection filter to Mesh
(M)
8

8. Select the Raft Slab mesh set from


the Model Works Tree.
6

9. Select Attribute 19:Raft Slab


Service
10. Click [OK].
9
10

Construction Stage Analysis of a Metro Station

62

Step

25

Model > Construction Stage > Define

Construction Stage

Procedure

MIDAS IT Co., Ltd.

1
2

1. Main Menu > Model >


Construction Stage > Define
Construction Stage
3

2. Click [New], Stage Name Initial.


3. Drag & Drop from Set Data to
Activated Data the mesh sets,
load and boundary condition as
shown.

4
5

4. Define Water level as -24.34.


6

5. Check-on [Clear Displacement].

6. Click [Save].
7. Click [New], Stage Name
Loading.

8. Activate the loads as shown.


9. Click [Save].

Construction Stage Analysis of a Metro Station

63

Step

25

Model > Construction Stage> Define


Procedure

Construction Stage

MIDAS IT Co., Ltd.

1
1

1. Click [New], Stage Name D Wall


+Columns.
2. Drag & Drop from Set Data to
2

Activated Data the mesh sets,


shown.
3. Check on Undrained.
4. Click [Save].
5. Click [New], Stage Name
Excavation to Roof (L1).

4
5
5

6. Drag & Drop from Set Data to


Deactivated Data the L1

mesh set.
7. Check on Undrained.
8. Click [Save].

Construction Stage Analysis of a Metro Station

64

Step

25

Model > Construction Stage> Define


Procedure

1. Click [New], Stage Name Roof

MIDAS IT Co., Ltd.

Construction Stage
5

1
1

Slab + L2 Excv.

2. Drag & Drop from Set Data to


Activated Data the Roof Slab
mesh set, Roof Slab Load load
and into Deactivated Data the
L2 mesh set.
3. Check on Undrained.
4. Click [Save].
5. Click [New], Stage Name Ticket
Slab + L3 Excv.

5
5

6. Drag & Drop from Set Data to


Activated Data the Ticket Slab
mesh set, Ticket Slab load and
into Deactivated Data the L3
mesh set.
7. Check on Undrained.
7

8. Click [Save].
8

Construction Stage Analysis of a Metro Station

65

Step

25

Model > Construction Stage> Define


Procedure

1. Click [New], Stage Name Inmdt


Slab + L4 Excv.

MIDAS IT Co., Ltd.

Construction Stage
5

1
1

2. Drag & Drop from Set Data to


Activated Data the
Intermediate Slab mesh set,
Intermediate Slab load and
into Deactivated Data the L4
mesh set.
3

3. Check on Undrained.
4

4. Click [Save].
5. Click [New], Stage Name Raft

5
5

Slab.
6. Drag & Drop from Set Data to
Activated Data the Raft Slab
mesh set.
7. Check on Undrained.
8. Click [Save].

Construction Stage Analysis of a Metro Station

66

Step

25

Model > Construction Stage> Define


Procedure

1. Click [New], Stage Name EWL

Construction Stage

MIDAS IT Co., Ltd.

1
1

Service.
2

2. Activate/Deactivate the mesh


sets/Boundary Condition and
loads as shown in the figure .
3. Check-on Define Water Level
for Global and enter a value of 18.34 m.

4. Click [Save].
4

Construction Stage Analysis of a Metro Station

67

Step

26

Analysis >

MIDAS IT Co., Ltd.

Analysis Case

Procedure

1
2

1. Main Menu > Analysis >


Analysis Case
2. Click [Add]
3. Name > CSA of Metro.

3
5

4. Analysis Type > Select

[Construction Stage].
5. Click on [Analysis Control] .
6. Analysis Control > Select
Construction Stage tab.
Check-on Initial Stage For

6
7

Stress Analysis and select


[Initial].
7. Check on [K0 Condition].
8. Non-linear tab. Load Steps >
Check-on Arc Length Method.

9. Click [OK] in Analysis Control.


10. Click [OK] in Analysis Case.
9

Construction Stage Analysis of a Metro Station

68

Step

27

Analysis >

MIDAS IT Co., Ltd.

Solve
1

Procedure
1. Main Menu > Analysis > Solve

The Warning shown is not an error but a re


minder that the cross section has not been d
efined. This comes as Columns have been c
onsidered as composite sections.

2. Check on CSA of Metro.


3. Click [OK].

All the messages during the

analysis will be shown in the


Output Window. Especially, one
needs to be very cautious
about warning messages,
because these messages
indicate that the analysis
results may not be correct. The
model is automatically saved
before the analysis. The result
is saved as binary file(*.TA*) in
the same folder as the model.
The detail analysis information
is also saved in a text
file(*.OUT).

Construction Stage Analysis of a Metro Station

69

Step

28

Post Works Tree> Raft Slab -Step 001(1) > DY(V),

Soil SYY

MIDAS IT Co., Ltd.

Procedure
1. Post Works Tree > Raft Slab Step 001(1)> Displacement >
DY(V). Shows the displacement
contour in Y direction (vertical
for this problem).
2. Post Works Tree > Raft Slab Step 001(1)> 2D Element

Stresses > Soil SYY. Check the


effective vertical stresses in
soil as shown during the Raft
Slab stage.

Construction Stage Analysis of a Metro Station

70

Step

29

Post Works Tree> Excavation 3-Step 001(1) > 1D Element Forces >

Beam My

MIDAS IT Co., Ltd.

Procedure
1. Post Works Tree > Raft Slab Step 001(1)> 1D Element
Forces > Beam My. Shows the
moment in element Y direction.
2. Tabbed Toolbar > Post Data
Tab > Click the arrow next to
the Output Set as shown.
3. As the user scrolls through this
1

with Sensitive checked-on


the results are updated
simultaneously for each stage
and the results for each stage
can be checked by directly
scrolling to the stage.
2

Tabbed Toolbar
3

Construction Stage Analysis of a Metro Station

71