STG-ECL-IOCL CONSORTIUM

PROJECT
OWNER
CONSULTANT
THIRD PARTY INSPECTION
JOB PROCEDURE

BARODA-AHMADABAD-KALOL PIPELINE PROJECT


GUJRAT STATE PETRONET LIMITED
TRACTEBEL ENGINEERS & CONSTRUCTORS PVT LTD
BVIS
SEIC-BAKPL-STC-JP-06

JOB PROCEDURE
FOR
CONCRETING

25.05.03

For Review &


Approval

REV

DATE

DESCRIPTION

CONCRETING

PREPARED
BY SEIC

CHECKED &
APPROVED
BY SEIC

REVIEWED
BY TPIA

DOCUMENT NO.
SEIC-BAKPL-STC-JP-06

REV.
1

APPROVED
BY TECPL

SHT.
1 of 7

STG-ECL-IOCL CONSORTIUM

1.

PURPOSE :
The purpose of this procedure is to summaries production of quality concrete As Per
Specifications.

2.

REFERENCE
1. IS 456: 2000, IS: 383, IS: 1786, IS: 10262.
2. Tender Specifications GTS/Z/02/004 Cl. No. 1.5

3.

SCOPE
This procedure covers materials for, and the batching, mixing, transporting placing,
compacting curing and protecting of, all concrete for use in the civil works.

4.

EQUIPMENT
1. Mixture M/C.
2. Vibrator.
3. Cube Mould.
4. Slump Cone.
5. Cube Testing M/C.
6. Weigh Batcher.

5.

MATERIALS
Approved Material Cement, Coarse aggregate, Fine aggregate, Water and admixtures.

6.

PROCEDURE
The following sequence will be adopted for producing quality concrete.

6.1

First of all sources of constructions materials will be identified.

6.1.1

Cement:
Cement shall be of approved source / Manufacturer from TECPL.
Conforming to IS: 269 MTC of each consignment shall be submitted to TECPL /
GSPL and one lot of cement shall be tested in approved lab during design mix.
Cement shall be tested in lab as per IS: 269 (if OPC)

6.1.2

Aggregates:

6.1.2(a) Coarse aggregate will be procured from quarries located at Sevalia from approved
sources only.
6.1.2(b) Fine Aggregate will be procured from Quarries located at Bhadarpur or any other
Suitable quarries approved by TECPL.
CONCRETING

DOCUMENT NO.
SEIC-BAKPL-STC-JP-06

REV.
1

SHT.
2 of 7

STG-ECL-IOCL CONSORTIUM

6.1.3

Water:
Water from Bore well near S.V. Stations will be used for mixing in concrete and
curing shall confirm to IS 456: 2000.

6.1.4

Admixtures:
Admixtures will be used in concrete if required as per requirement and will be
procured from renowned manufacturers like fosroc/ SIKA LAB / Structural water
proofing etc.

6.2

After identification of sources of material, Test reports will be submitted as per


GTS/Z/02/004 Clause no: 1.6.2 and 3.2.

6.3

Materials used in concrete production will be properly delivered, stored and handled
properly as per GTS/Z/02/0004 Clause No.1.7.

6.3.1

CEMENT:
Cement will be delivered in bags and stored on concrete/wood/steel/ Platform.
Cement shall be stacked inside the well ventilated shed & each consignment shall be
stacked separately.

6.3.2

AGGREGATES:
Aggregates will be stored on concrete/steel floors and will be separated with suitable
bins to avoid intermixing.

6.4

Full fledged laboratory will be established at site in due course. Till such time we
propose to do concrete Mix design and tests in recognized institutes such as GERI and
M.S. University Baroda. After the finilisation of Mix design and approval from
TECPL / GSPL we will start the actual Concreting work.

6.5

BATCHING
The aggregates and cement will be batched by means of suitable weigh batching
machines and materials will be handled in Steel Boxes of specified size. Temperature
of cement will be kept below 40C at the time of incorporation into the mix.
Convenient system of measuring water to the concrete Mixture will be installed.

6.6

MIXING CONCRETE
Suitable concrete mixers (10/7) of approved type will be used for Mixing concrete
materials including water. Water shall be mixed with the help of proper measuring
jars.

CONCRETING

DOCUMENT NO.
SEIC-BAKPL-STC-JP-06

REV.
1

SHT.
3 of 7

STG-ECL-IOCL CONSORTIUM
6.7

TRANSFER / PLACEMENT OF CONCRETE


Placement of concrete will start only after the owners representative has checked and
approved the positioning, fixing and condition of reinforcement and any other items
to be embedded and the cleanliness, alignment and suitability of the containing
surfaces or formwork.
The concrete will be discharged from the mixer to the receiving Platform. Mixers will
be placed near the pour area and placement will be done through Head load or
through chute. Chute height will be kept upto 2.0 mt, in case if it is necessary to
increase the height of chute, then owners representatives approval will be taken.
Concrete placement shall be as follows GTS / Z / 02 / 004 clause No 3.1.2 of
specification.

6.8

COMPACTING OF CONCRETE
Concrete will be compacted within 30 minutes of water being added to the Mix.
Approved internal vibrators of size varying 25/40mm diameter to 75 mm will be used
for compacting concrete.

6.9

CURING AND PROTECTION

6.9.1

For Horizontal Surfaces


The following procedure will be followed.
1.
2.
3.

Immediately after compacting and finishing, polythene sheeting will be


placed.
After final set, Polythene will be replaced by wet hessian, which will be
immediately covered with polythene; hessian will be kept always wet.
After 7 days hessian and polythene will be removed. After getting approval
from owners representative either area will be filled with water upto 7 days or
curing compound will be sprayed.

6.9.2 For Vertical Surfaces


1. After stripping of formwork, concrete surface will be wrapped with wet hessian
and then covered with polythene.
2. After 7 days curing compound of approved quality will be sprayed on concrete
surface.
6.10

FIELD QUALITY CONTROL

6.10.1 Testing Of Cement:


If desired by owners representative, cement will again be tested.
Test certificate of each batch shall be presented.
CONCRETING

DOCUMENT NO.
SEIC-BAKPL-STC-JP-06

REV.
1

SHT.
4 of 7

STG-ECL-IOCL CONSORTIUM
6.10.2 Testing Of Aggregates:
Weekly or at 50 cum intervals, grading of aggregrates will be tested.
Testing of Water: As per IS 456.
5.10.2 6.10.3 Testing Of Concrete:
Frequency of sampling of concrete will be as per IS 456 Page No. 29 Clause No. 15
and GTS/Z/02/004 Clause No. 3.2.4.and 3.2.5 steel cubes of size 150mm X 150mm X
150mm will be used.
6.10.4 Workability Of Concrete:
Slump test will be done in order to check workability of concrete.
7.

TOLERANCES

7.1

Accuracy Of Batching:
Cement 2 % of the weight of the cement in the batch.
Aggregate 2 % of the weight of each aggregate in the batch.
Water 2% of the weight of each water added to the batch.

8.

DOCUMENTATION
Inspection test plan
Concrete pour card

: SEIC-BAKPL-ITP-06
: SEIC-BAKPL-PC-06

Concrete mix design is to be estimated as per IS: 456 for each grade of concrete
taking into account type of cement, Min cement content, w/c ratio conforming to
exposed condition.
Design mix calculation to be submitted after testing of material for approval.
Batching of cement and aggregates shall be done by mass or it should be converted to
volume in consultation with TECPL / GSPL with specific request in writing.
No hand mixing is permitted.
Pour card shall be submitted to TECPL / GSPL before concreting and same should be
signed by TPI & GSPL / TECPL.
Cover to be provided as per Drawings and IS: 456.
All blemishes & small defects shall be rectified immediately after removal of
formwork.
Quality of cover block shall be same as grade of concrete.

CONCRETING

DOCUMENT NO.
SEIC-BAKPL-STC-JP-06

REV.
1

SHT.
5 of 7

STG-ECL-IOCL CONSORTIUM

Project
: BARODA AHEMDABAD KALOL PIPELINE PROJECT.
Client
: GUJARAT STATE PETRONET LIMITED
Consultant
: TRACTEBEL ENGINEERS & CONSTRUCTIONS PVT.LTD.
DOCUMENT NO : SEIC-BAKPL-PC-06
CONCRETE POUR CARD
Pour Card No:-

Drawing No:-

1.

Name of structure / Co-ordinates:

2.

Levels

3.

Grade of concrete/Mix Proportion :

4.

Proposed time of pouring :


a)

Location:-

Start

b) Complete

From :-

5.

Slump

6.

Temperature of Concrete:

7.

W/C ratio

8.

Quality of aggregates / Quantity of aggregates :

9.

Type of Cement used :


a)

Date:-

To:-

:
:
10mm :

20mm :

Sand :

Cement Level in Kgs/Cum

10. Quality and source of Water


11. Equipment mobilization:
a)

Mixer Machines :

b) Vibrators :
c)

Hoists :

12. Position of reinforcement / Cover block :


13. Correctness of anchor bolts :
14. Correctness of pockets / Openings / Bolts / Inserts :
15. Rigidity of shuttering / Form work :
16. Quantity of concrete
17. No. of cubes taken :
18. Cleaning of area where concrete is to be placed.
19. Extra reinforcement
Provided if any :
Extra bar
a) Laps
b) Separators
c) Chairs
d) any others

Dia

CONCRETING

No.

Length

Total length

DOCUMENT NO.
SEIC-BAKPL-STC-JP-06

REV.
1

SHT.
6 of 7

STG-ECL-IOCL CONSORTIUM
20. Post pour Inspection:

For STG-ECL-IOCL

For BVIS

For GSPL/TECPL

Name:

Name:

Name:

Date:

Date:

Date:

CONCRETING

DOCUMENT NO.
SEIC-BAKPL-STC-JP-06

REV.
1

SHT.
7 of 7