INDICES OF APPROVED TRANSMISSION STANDARDS AND SPECIFICATIONS

Standard No.

Title

Rev No.

Rev Approved Date

TMSS

TRANSMISSION MATERIAL STANDARDS AND SPECIFICATION (TMSS)


General Requirements
01-TMSS-01

General Requirements for All Equipment/Materials

Mar. 31, 2010

Total =

Conductors, Bare
10-TMSS-01

Conductors Bare

Apr. 29, 2009

10-TMSS-02

Guy Wire Strand, Galvanized

Mar. 13, 2006

10-TMSS-03

Overhead Ground Wire (OGW)

Mar. 13, 2006

10-TMSS-04

Optical Ground Wire (OPGW)

Mar. 13, 2006

10-TMSS-05

Bare, Copper-clad Steel Grounding Conductor and Ground Rod

Sep. 07, 2010

10-TMSS-06

Conductor, Bare, Overhead Line (Heat-Resistance, Aluminum Alloy


Conductor)

Feb. 14, 2007

Total =

Conductor, Insulated
11-TMSS-01

Power Cable , XLPE, Cu or Al, 1-Core, 69 kV

May. 30, 2006

11-TMSS-02

110kV, 115KV, 132KV, 230KV or 380kV, XLPE, Single Core, Copper


Power Cable

May. 30, 2006

11-TMSS-03

POWER CABLE, LPOF, CU, 1-CORE, 115kV, 132 kV, 230kV or 380kV

May. 30, 2006

11-TMSS-10

Power and/or Control Cable Cu or Al Conductor 600/1000 V Rating

Mar. 18, 2006

11-TMSS-11

Instrumentation Cables, Shielded

Sep. 07, 2010

Total =

Conductor Fittings
12-TMSS-01

Line Hardware

Mar. 31, 2010

12-TMSS-02

Compression Type Connectors For O/H T/L

Aug. 05, 2006

12-TMSS-03

Obstruction Markers And Conductor Lighting

May. 30, 2006

12-TMSS-10

Splice & Termination Kits For Power Cables 69 kV, 115 kV, 132 kV, 230
kV, and 380 kV

May. 30, 2006

12-TMSS-11

Link Boxes For Grounding Of U/G Power Cable

Dec. 15, 2007

Total =

Insulators
15-TMSS-01

Insulators, Station Post Type, Porcelain, Indoor/Outdoor, 69 kV through


380 kV

May. 30, 2006

15-TMSS-02

Insulators, Porcelain or Glass, Suspension Type

Mar. 31, 2010

15-TMSS-03

Insulators, Porcelain Horizontal Line Post Type

Apr. 09, 2006

15-TMSS-04

Insulators, Porcelain, Long Rod Type

Jun. 30, 2010

15-TMSS-05

Insulators, Composite, Horizontal Line Post, Suspension and Tension


Type

Sep. 08, 2010

15-TMSS-06

Composite Station Post Insulators, 69 kV through 230 kV

Feb. 14, 2007

15-TMSS-07

RTV Silicon Rubber Insulator Coating

Jun. 25, 2008

Total =

Poles, Towers, Structures and Line Supports


20-TMSS-01

Transmission Line And S/S Latticed Steel Structures

Aug. 20, 2006

20-TMSS-02

Poles, Steel, Tapered, Tubular For Transmission Lines

Aug. 20, 2006

20-TMSS-03

Wood Equivalent Steel Poles, Direct Embedded for Overhead


Transmission Lines.

Sep. 01, 2009

Total =

Conduits, Fittings & Accesssories

24-Jan-2011

Page 1 of 9

Standard No.

Title

Rev No.

Rev Approved Date

23-TMSS-01

PVC Conduits & Fittings for Underground Cables

Oct. 09, 2007

23-TMSS-02

Duct Sealing Units

Aug. 05, 2006

Total =

Line Switches and Disconnecting Devices


30-TMSS-01

Air Break Disconnect Switches and Grounding Switches, 33Kv Through


380Kv

Feb. 22, 2006

Total =

Substation Panels
31-TMSS-01

Relay and Control Panels

Feb. 22, 2006

31-TMSS-02

Auxiliary AC/DC Panels

May. 30, 2006

31-TMSS-06

Terminal Blocks

Aug. 31, 2009

Total =

Switchgear
32-TMSS-01

Metal Clad Switchgear 11kV, 13.8kV, 33kV or 34.5kV

Jun. 30, 2010

32-TMSS-02

SF6 Gas Insulated Switchgear, 69kV through 380kV

Jun. 30, 2010

32-TMSS-03

Metal Clad Gas Insulated Medium Voltage Switchgear


(11kV,13.8kV.33kV or 34.5kV)

Dec. 24, 2008

32-TMSS-07

SF6 Non-Extensible Ring Main Unit, 13.8 kV

Jan. 07, 2007

Total =

Lightning & Surge Protection Devices


35-TMSS-01

Surge Arrester

Oct. 10, 2007

Total =

Circuit Breakers
37-TMSS-01

Circuit Breaker, SF6, Dead Tank, 69 kV Through 380 kV

Aug. 20, 2006

37-TMSS-02

Circuit Breaker, SF6, Live Tank, 69 kV Through 380 kV

May. 07, 2007

37-TMSS-03

LV Circuit Breakers

Mar. 31, 2010

Total =

Power Line Carrier, Supervisory Control


38-TMSS-01

Line Trap

Feb. 14, 2007

38-TMSS-02

Line Tuner

Oct. 10, 2007

38-TMSS-03

Remote Terminal Unit

Aug. 31, 2009

38-TMSS-04

Sequence of Events Recorder System

Mar. 25, 2007

38-TMSS-05

Annunciator Systems

Aug. 06, 2006

38-TMSS-06

DYNAMIC SYSTEM MONITOR

Dec. 24, 2008

38-TMSS-07

On-Line Partial Discharge Monitoring System

Jun. 30, 2010

38-TMSS-08

Coupling Capacitor Voltage Transformer for 69kV Thru 380kV System


Voltage

Dec. 15, 2007

Total =

Meters
40-TMSS-02

Metering Devices

Mar. 25, 2007

40-TMSS-03

AUTOMATIC METER READING (AMR) SYSTEM

Dec. 03, 2007

Total =

Batteries and Power Supplies


46-TMSS-01

Vented Type Lead Acid Stationary Battery

Mar. 18, 2006

46-TMSS-02

Battery Chargers

Mar. 13, 2006

46-TMSS-03

UPS 5 kVA thru 100 kVA

Dec. 16, 2006

46-TMSS-04

Valve Regulated Lead Acid (VRLA) Stationary Battery Bank

Jan. 07, 2007

24-Jan-2011

Page 2 of 9

Standard No.

Title

Rev No.

Rev Approved Date

46-TMSS-05

48 V Communication Battery Charger

Mar. 25, 2007

46-TMSS-06

Vented Nickel - Cadmium Stationary Battery Bank

Jan. 07, 2007

46-TMSS-07

DC-DC CONVERTORS

Apr. 29, 2009

Total =

Communications & Fiber Optic Equipment


48-TMSS-01

Pilot Wire Cables

Aug. 21, 2006

48-TMSS-02

Non Metallic Fiber Optic Cables

Aug. 21, 2006

48-TMSS-03

Pilot Cable Termination Box

Sep. 27, 2006

48-TMSS-04

Pilot Cable Termination Equipment

Aug. 21, 2006

48-TMSS-05

Pilot Cable Termination Equipment With Cabinet

Aug. 21, 2006

48-TMSS-06

Medium Density Fiber Optics Terminal Equipment

Aug. 21, 2006

Total =

Transformers, Current and Potential


50-TMSS-01

Current Transformer, 11 kV through 380 kV

May. 30, 2006

50-TMSS-02

Capacitor Voltage Transformers (CVT), 110 kV through 380 kV

Aug. 06, 2006

50-TMSS-03

Potential Transformer, 33 kV through 380 kV

Aug. 28, 2006

Total =

Transformers, Station Service, up to 2MVA


51-TMSS-01

Pad Mounted Station Service Transformer up to 2 MVA

Mar. 18, 2006

Total =

Transformer, Specialty
52-TMSS-01

Grounding Transformer, 13.8kV, 33kV or 34.5kV

May. 30, 2006

52-TMSS-02

Air Core Neutral Grounding Reactor for 11 kV through 132 kV System

Jan. 08, 2007

Total =

Power Transformer, Rated Above 2MVA


53-TMSS-03

Online Gas Analyzer

Aug. 31, 2009

Total =

Electrical Insulating oil


54-TMSS-01

Mineral Insulating Oil for Electrical Apparatus

Sep. 01, 2009

Total =

Resistor
57-TMSS-01

Neutral Grounding Resistor, 11 kV through 34.5 kV

Jan. 08, 2007

Total =

CONSTRUCTION MATERIALS AND SUPPLIES


70-TMSS-01

Shop Applied Internal Cement Mortar Lining Of Steel Pipes

Oct. 10, 2007

70-TMSS-02

Chainlink Fence

Apr. 09, 2006

70-TMSS-03

Normal Weight Ready Mixed Cement Concrete

Apr. 10, 2006

Total =

CONSTRUCTION MATERIAL II
71-TMSS-02

Prefabricated portable bldg

Dec. 16, 2007

71-TMSS-03

Pre-Engineered Metal Building

Jun. 23, 2008

Total =

AIR CONDITIONING EQUIPMENT


73-TMSS-01

Air Conditioning Unit, Packaged

May. 30, 2006

73-TMSS-02

Packaged Air Cooled Water Chiller with Screw-Type Compressor

Aug. 06, 2006

24-Jan-2011

Page 3 of 9

Standard No.

Title

Rev No.

Rev Approved Date

73-TMSS-03

Air handling Units, Chilled Water Type

Dec. 16, 2007

73-TMSS-04

HVAC Pumps

Jul. 17, 2007

73-TMSS-05

Centrifugal Exhaust Fans

Jul. 17, 2007

Total =

PIPES, HOSES, TUBINGS AND FITTINGS


75-TMSS-01

Plastic piping for plumbing systems

Dec. 03, 2008

75-TMSS-03

Enameled Cast Iron Plumbing Fixtures

Jul. 17, 2007

Total =

BOLTS; NUTS; WASHERS


76-TMSS-02

Irrigation Controllers And Valves

Jul. 15, 2007

Total =

ABRASIVES; PAINT; PROTECTIVE COATING, OTHER


78-TMSS-01

Catalytically Cured Epoxy Phenolic Coating For Atmospheric Service

Oct. 10, 2007

78-TMSS-02

Catalytically Cured Epoxies & Epoxy Phenolics For Immersion And Damp
Services

Oct. 10, 2007

78-TMSS-03

Primers: Zinc Chromate

Mar. 29, 2008

78-TMSS-04

Paints: Enamel, Emulsion, Varnish And Laquers

Jun. 23, 2008

78-TMSS-05

Paints: Chlorinated Rubber Systems

Jun. 23, 2008

78-TMSS-06

Paints: Aluminum And Steel

Jun. 23, 2008

78-TMSS-07

Non-Skid Deck Paint

Jun. 23, 2008

78-TMSS-08

Miscellaneous Materials For Paints and Repairs

Jun. 23, 2008

78-TMSS-09

Primers-Others

Dec. 03, 2008

78-TMSS-10

Paints for Interiors

Dec. 03, 2008

78-TMSS-11

Coating and Water Proofing

Dec. 03, 2008

78-TMSS-12

Floor Systems For Substations

Mar. 11, 2009

Total =

12

WATER TREATMENT & STORAGE EQUIPMENT


80-TMSS-01

Shop Assembled Storage Tank

Jul. 15, 2007

Total =

GENERATOR; PORTABLE; PUMPS; ENGINES; MOTOR


83-TMSS-01

Submersible Sump Pumps

Oct. 10, 2007

Total =

SAFETY AND SECURITY EQUIPMENT


90-TMSS-01

Fire Protective Signaling Panel

Mar. 25, 2007

90-TMSS-02

Fire Water Pumps

Mar. 29, 2008

90-TMSS-03

Portable Fire Extinguishers

Jun. 24, 2008

90-TMSS-04

Carbon Steel Pipes For Fire Protection Systems

Dec. 03, 2008

90-TMSS-08

Emergency shower and eye (and face) wash equipment.

Apr. 29, 2009

90-TMSS-09

Valve Inspection And Testing Requirements

Jun. 23, 2008

90-TMSS-10

Fire Water Sprinklers

Dec. 16, 2007

Total =

FURNISHINGS, MISCELLANEOUS APPLIANCES


94-TMSS-01

Automatic Electric Water Heaters

Jun. 23, 2008

94-TMSS-02

Drinking Water Coolers

Jun. 23, 2008

Total =

TES

TRANSMISSION ENGINEERING SPECIFICATION (TES)


24-Jan-2011

Page 4 of 9

Standard No.

Title

Rev No.

Rev Approved Date

FIRE PROTECTION SYSTEM


TES-B-106.01

Fire Detection And Alarm Systems

Dec. 17, 2007

TES-B-106.03

CO2 Total Flooding System

Dec. 03, 2008

TES-B-106.04

Deluge System

Apr. 29, 2009

TES-B-106.05

HFC-227ea Clean Agent Extinguishing Systems

Dec. 03, 2008

TES-B-106.06

FK 5-1-12 Fixed Installation Total Flooding Clean-agent Fire


Extinguishing System

Nov. 11, 2009

Total =

PAINT AND COATINGS


TES-H-107.01

Painting

Dec. 03, 2008

TES-H-107.02

Paint Color Codes and Standards

Dec. 03, 2008

Total =

AIR CONDITIONING , HEATING


TES-K-100.01

Heating, Ventilating and Air Conditioning System Design

Aug. 20, 2006

Total =

BATTERIES AND UPS STANDARDS


TES-P-103.01

Introduction to Batteries and UPS Standards.

Oct. 09, 2007

TES-P-103.02

Storage Battery Selection and Capacity Determination

Jul. 15, 2007

TES-P-103.03

Battery Charger Sizing

Mar. 25, 2007

TES-P-103.04

Storage Battery Installation

Jan. 08, 2007

TES-P-103.05

Uninterruptible Power System

Jul. 15, 2007

TES-P-103.06

Communication DC Power Systems

Oct. 09, 2007

Total =

UNDERGROUND CABLE ENGINEERING STANDARDS


TES-P-104.01

General Engineering Requirements For U/G Cables

Dec. 16, 2006

TES-P-104.02

Cable Construction

Dec. 16, 2006

TES-P-104.03

Cable Sizing & Selection

Dec. 16, 2006

TES-P-104.04

Splice & Termination

Dec. 16, 2006

TES-P-104.05

Cable Installations, Engineering Requirements

Feb. 18, 2007

TES-P-104.08

Bonding & Grounding of Insulated Metallic Sheath of Power Cables

Aug. 04, 2007

Total =

Substation Design Standards


TES-P-119.01

Introduction to Substation Design Standards

Jan. 30, 2007

TES-P-119.05

Insulation Coordination

Oct. 17, 2006

TES-P-119.06

Surge Protection

Oct. 16, 2006

TES-P-119.07

Shielding

Oct. 16, 2006

TES-P-119.08

Clearances

Aug. 04, 2007

TES-P-119.09

Busbars and Supporting Structures

Nov. 29, 2010

TES-P-119.10

Grounding

Oct. 16, 2006

TES-P-119.11

Substation Insulators

Jan. 30, 2007

TES-P-119.12

Application Criteria for Electrical Equipment

Feb. 19, 2007

TES-P-119.18

Outdoor Equipment Foundation

Dec. 17, 2007

TES-P-119.19

Substation Building and Site Developement

Dec. 17, 2007

TES-P-119.20

LV Cable Raceways & Cable Installation Practices

Dec. 16, 2006

TES-P-119.26

Control Schemes for Substation Equipments

Nov. 29, 2010

TES-P-119.27

Supervisory Control and Data Acquisition (SCADA)

Jun. 30, 2010

24-Jan-2011

Page 5 of 9

Standard No.

Title

Rev No.

Rev Approved Date

TES-P-119.28

Protection and Metering Instrument Transformers CT & PT Sizing


Calculation

Sep. 08, 2010

TES-P-119.29

LV Cable Selection and Sizing (600 V & Below)

Oct. 09, 2007

TES-P-119.30

Auxiliary Power Systems (AC/DC)

Mar. 25, 2007

TES-P-119.31

Metering

Dec. 16, 2006

TES-P-119.33

Substation Electrical Diagrams

Dec. 16, 2006

TES-P-119.34

Application Of System Grounding

Dec. 15, 2007

Total =

20

TRANSMISSION LINE DESIGN STANDARDS


TES-P-122.01

Basic Design Requirements

Oct. 17, 2006

TES-P-122.03

Conductors And Overhead Ground Wires

Oct. 17, 2006

TES-P-122.04

Line Hardware and Fittings for Conductors and Overhead Ground Wires

Sep. 07, 2010

TES-P-122.05-PI

Transmission Line Structures Part I: Latticed Steel Towers

May. 07, 2007

TES-P-122.05-PII

Transmission Line Structure Part II: Steel Poles

Oct. 17, 2006

TES-P-122.06

Transmission Structure Foundations

Sep. 08, 2008

TES-P-122.07

Transmission Structure Spotting

Oct. 18, 2006

TES-P-122.08

Survey Guidlines

Feb. 18, 2007

TES-P-122.09

Clearance & ROW Requirments

Dec. 12, 2007

TES-P-122.10

Transmission Line Grounding

Feb. 18, 2007

TES-P-122.11

Access Roads and Structure Pads

Mar. 29, 2008

TES-P-122.12

Upgrading Of Overhead Transmission Lines

Jun. 25, 2008

Total =

12

SAFETY AND SECURITY


TES-S-101.01

Safety and Security - Introduction

Dec. 15, 2007

TES-S-101.02

Safety & Security - Security Fence

Dec. 15, 2007

TES-S-101.03

Safety & Security - Category II Fence

Dec. 15, 2007

TES-S-101.04

Safety & Security - Catergory III Fence

Dec. 15, 2007

TES-S-101.05

Safety & Security - Category III Fence (Alternative)

Dec. 15, 2007

TES-S-101.06

Safety & Security - Gates in Perimeter Fences

Dec. 15, 2007

TES-S-101.07

Safety & Security - Gates in Woven Wire Fabric Fences

Dec. 15, 2007

TES-S-101.08

Safety & Security - Barbed "S" Wire Concertina

Dec. 15, 2007

TES-S-101.09

Safety & Security - Security and Emergency Exit Doors

Dec. 15, 2007

TES-S-101.10

Safety & Security - Locks Used on Security Doors, Perimeter Fences and
Emergency Exits

Dec. 15, 2007

TES-S-101.11

Safety & Security - Building Housing Vital Equipment

Dec. 15, 2007

TES-S-101.12

Safety & Security - Protection Of Vital Equipments

Dec. 15, 2007

TES-S-101.13

Safety & Security - Power Supplies

Dec. 15, 2007

TES-S-101.14

Safety & Security - Communications

Dec. 15, 2007

TES-S-101.15

Safety & Security - Security Lighting Systems

Dec. 15, 2007

TES-S-101.16

Safety & Security - Check Point Lighting

Dec. 15, 2007

TES-S-101.17

Safety & Security - Intruder Detection Systems

Dec. 15, 2007

TES-S-101.18

Safety & Security - Automatic Control of Entry

Dec. 15, 2007

TES-S-101.19

Safety & Security - Gate House and Vehicle Lock

Dec. 15, 2007

TES-S-101.20

Safety & Security - Fire Fighting Equipments

Dec. 15, 2007

TES-S-101.21

Safety & Security - Work Permit Procedures

Dec. 15, 2007

TES-S-101.22

Safety & Security - Expanded Metal Mesh

Dec. 15, 2007

TES-S-101.23

Safety & Security - Protection of Diesel Engines

Dec. 15, 2007

24-Jan-2011

Page 6 of 9

Standard No.

Title

Rev No.

Rev Approved Date

TES-S-101.24

Safety & Security - Gasoline Filling Stations

Dec. 15, 2007

TES-S-101.25

Safety & Security - Automatic Control of Entry

Dec. 15, 2007

TES-S-101.26

Safety & Security - Turn Isles for Entry Control

Dec. 15, 2007

TES-S-101.27

Safety & Security - Internal Tank Cleaning

Dec. 15, 2007

TES-S-101.28

Safety & Security - Blast Resistant Control Building

Dec. 15, 2007

TES-S-101.29

Safety & Security - Tank Spacing-Dikes And Drainage

Dec. 15, 2007

TES-S-101.30

Safety & Security - The safe design, Construction, Operation and MTCC
of On-Shore Pipelines for the Conveyance of Petrol

Dec. 15, 2007

TES-S-101.31

General Procedures / Safety Standards For Blasting Near SEC Facilities.

Dec. 15, 2007

Total =

31

COMMUNICATIONS
TES-T-111.02

Communication Facility Grounding

Mar. 29, 2008

TES-T-111.03

Communications Facility Lightning and Electrical Protection

Mar. 31, 2010

TES-T-111.05

General And VF Level Circuit Performance

Feb. 14, 2007

TES-T-111.06

Fiber Optic and PCM Circuit Performance

Dec. 03, 2008

TES-T-111.07

PLC/SSB Circuit Performance

Dec. 03, 2008

TES-T-111.08

ACC/FDM Circuit Performance

Dec. 03, 2008

TES-T-111.10

Communications Feeder Cables

Dec. 03, 2008

TES-T-111.12

Outside Plant (Communications) Standards and Practices for Facility


Area Plan Design and Remote Distribution Area Plan Design

Nov. 11, 2009

TES-T-111.17

Fire Protection Of Communication Facilities

Jun. 25, 2008

TES-T-111.18

Environmental Considerations For Communications Sites And Remote


Communications Terminals

Jan. 30, 2007

TES-T-111.19

Design Criteria For Communication Tower

Jul. 15, 2007

Total =

11

TCS

TRANSMISSION CONSTRUCTION SPECIFICATION (TCS)


AIR CONDITIONING, HEATING
TCS-K-100.01

HVAC Systems and Equipment Installation

Dec. 03, 2008

Total =

BUILDING CODE
TCS-M-112.01

General Purpose Fencing

Dec. 03, 2008

Total =

UNDERGROUND CABLE CONSTRUCTION STANDARDS


TCS-P-104.01

General Requirments

Aug. 04, 2007

TCS-P-104.02

Cable Reels Handling & Storage

Oct. 09, 2007

TCS-P-104.03

Trenches and Ducts

Jun. 25, 2008

TCS-P-104.06

Cable Installation, Field Handling Procedures

Feb. 14, 2007

TCS-P-104.08

Field Testing of Power Cables Rated 110kV, 115kV, 132kV, 230kV or


380kV

Dec. 16, 2007

Total =

COMMISSIONING TESTS AND CHECKS OF POWER


TRANSMISSION NETWORK EQUIPMENT
TCS-P-105

Precommissioning Tests/Procedures for SEC Transmission Electrical


Installations

Sep. 21, 2004

Total =

TRANSMISSION LINE CONSTRUCTION STANDARDS


TCS-P-122.01

Safety in Construction of Transmission Lines

Oct. 10, 2007

TCS-P-122.02

Material Handling

Oct. 17, 2006

TCS-P-122.03

Structure Staking

Jun. 23, 2008

24-Jan-2011

Page 7 of 9

Standard No.

Title

Rev No.

Rev Approved Date

TCS-P-122.05

Installation Of Steel Structure Foundations

Dec. 16, 2006

TCS-P-122.06

Assembly And Erection Of Steel Structure

Dec. 16, 2006

TCS-P-122.07

Installation of Overhead Line Conductors & Ground Wires

Dec. 16, 2006

TCS-P-122.08

Composite OPGW Strand Installation

Jan. 09, 2007

TCS-P-122.09

Storage, Handling & Installation of Composite Insulators

Aug. 04, 2007

TCS-P-122.21

Transmission Line Structure Details for 69kV to 380kV.

Aug. 18, 2009

TCS-P-122.22

Application of Silicon Rubber Protective Coating on Ceramic Insulators

Sep. 01, 2009

Total =

10

CONCRETE FOUNDATIONS
TCS-Q-113.01

Asphalt Concrete Paving

Apr. 10, 2006

TCS-Q-113.02

Earthworks

Apr. 10, 2006

TCS-Q-113.03

Cast - In - Place Concrete

Apr. 10, 2006

TCS-Q-113.04

Precast Concrete works

Dec. 17, 2007

Total =

COMMUNICATIONS/UNDERGROUND COMMUNICATION
(TELEPHONE/OPTICAL FIBER/PILOT) CABLE INSTALLATION
TCS-T-111.01

Acceptance/Commissioning, Test and Inspection of Communications


Network Equipment

Feb. 14, 2007

TCS-T-111.02

Conduit Sealing For Underground Communication Cable

Dec. 03, 2008

TCS-T-111.03

Communication Cable Splicing

Nov. 29, 2010

TCS-T-111.04

Underground Telephone Cable Installation

Mar. 31, 2010

TCS-T-111.05

Long Pulls And Reel Length Limitations Of Underground Telephone


Cables

Mar. 29, 2008

TCS-T-111.06

Optical Fiber Cables Splicing

Dec. 03, 2008

TCS-T-111.08

Installation of Underground Non Metallic Fiber Cable

Mar. 29, 2008

TCS-T-111.10

Underground Installation, Splicing and Testing / Acceptance of Pilot


Cables

Dec. 03, 2008

TCS-T-111.11

Design And Installation Of Underground Communications Conduit And


Manhole System

Mar. 29, 2008

Total =

TSD

TRANSMISSION DEVELOPMENT SPECIFICATION (TSD)


TRANSMISSION STANDARD DRAWINGS
TA-800001

110 /115 KV High/Low Bus Support & Disconnect Switch Structures

Mar. 25, 2007

TA-800002

Plan, Elevation, Section And Details Of Standard Switch Operating


Platform

Mar. 25, 2007

TA-800004

Lighting/Lightning Steel Monopoles

Mar. 25, 2007

TA-800005

110 kV to 115 kV "A" Frame Take Off Structure

Oct. 09, 2007

TA-800006

110/115 kV Take Off Structure Lattice Gantry Structure

Jul. 15, 2007

TA-800012

Precast Concrete Boundary Wall (Plan, Elevation & Details)

Apr. 29, 2009

TA-800013

Boundary Wall for Substation Location in Urban Areas

Aug. 31, 2009

TA-800022

Gate in Woven Wire Fabric Fence (SAG SSD/5A:TES-S-101.07)

Oct. 12, 2009

TA-800023

Door Schedule & Details

Apr. 29, 2009

TA-800024

Finish Schedule / Miscellaneous Details

Apr. 29, 2009

TA-800039

Plans, Elevations & Sections for Gatehouse

Jun. 30, 2010

TA-800040

Foundation, Roof Plan & Details for Gatehouse

Jun. 30, 2010

TA-800041

Miscellaneous Details for Gatehouse

Jun. 30, 2010

TA-800042

Miscellaneous Details, Security Mesh & Bar Bending Schedule for


Gatehouse

Jun. 30, 2010

TA-800062

Typical Duct Bank Sections, Concrete Duct Bank 69kV to 380kV

Mar. 11, 2009

TA-800063

Highway Crossings for 69kV to 380kV Cables

Mar. 11, 2009

24-Jan-2011

Page 8 of 9

Standard No.

Title

Rev No.

Rev Approved Date

TA-800068

Highway Under Crossing for 110kV to 380kV U/G Power Cables by


Directional Drilling

Nov. 23, 2009

TA-800078

Typical Detail of Conduit Mounting on the Gantry Structure for


Non-Metallic Fiber Optic Cables

Nov. 11, 2009

TA-800098

Manhole/Handhole Accessories for Communications

Nov. 29, 2010

TA-800100

132 kV Steel Take Off Structure and Details

Jun. 23, 2008

TA-800101

132kV "A Frame Take-Off Structure

Nov. 23, 2009

TA-800102

132 kV High/Low Bus Support & Disconnect Switch Structures.

Jun. 23, 2008

TA-800106

Fire Protection System, Miscellaneous Details

Mar. 29, 2008

TA-800111

Substation Signboard at Gate House

Mar. 29, 2008

TA-800112

Decorative Steel Fence

Apr. 29, 2009

TA-800113

Chain Link Boundary Fence

Apr. 29, 2009

TA-800133

Removable Crash Barrier, Location Plan and Detail in Substation

Sep. 08, 2010

TA-800134

Septic Tank Installation Details for Non-Traffic Area

Sep. 08, 2010

TA-800135

Disposal System Layout & Seepage Pit Installation Details

Sep. 08, 2010

TA-800136

Miscellaneous Field Installation Details for Sanitary Works

Sep. 08, 2010

TA-800137

Sanitary Sewer Manhole Precast Concrete Plan, Section & Details

Sep. 08, 2010

TA-800138

Drainage Sump, Drainage Channel and Sewer Manhole Cover Details

Sep. 08, 2010

TA-800139

Counter Weight for Vehicle Entry Gate

Nov. 29, 2010

TA-800140

Water Proofing for Duct Banks, Manhole/Handhole and Alternate Roof


Drainage Details

Nov. 29, 2010

TB-800014

Pipe Line Crossing for SEC Access Roads

Sep. 08, 2010

TB-800067

Direct Buried Cable Trench Details in Rocky Area (Communications).

Aug. 31, 2009

TB-800069

Standard Trench detail Joint Communication & Power Cables

Aug. 31, 2009

TB-800076

Standard Precast Handhole for Communication in Non Traffic Areas


(1.20m x 1.20m x 1.20m)

Nov. 11, 2009

TB-800077

Standard Precast Hand-Hole for Communication in Traffic Areas (1.20m


x 1.20m x 1.20m)

Mar. 31, 2010

TB-800079

PVC Conduit Installation Concrete Encased (Vital Communications)

Sep. 08, 2010

TB-800090

PVC Conduit Installation Concrete Encased (Non-Vital Communications)

Sep. 08, 2010

TB-800091

Concrete Encased Duct Detail for Rocky Areas (Vital Communications)

Nov. 11, 2009

TC-800003

Signboard on Substation Building

Jul. 15, 2007

TC-800115

Transformer-Medium Voltage Switchgear Connection: Cable


Arrangement

Jun. 30, 2010

TD-800007

Standard Sign Danger High Voltage Keep Away

Oct. 09, 2007

TD-800008

Standard Sign Danger High Voltage-Bone Skull

Jul. 15, 2007

TD-800061

Typical Tower Structure Configuration 380kV, 230kV, 132kV, 115kV &


110kV

Aug. 19, 2009

TE-800110

SEC Monogram for equipment Mounting

Dec. 03, 2008

Total =

48

SEEDS

SAUDI ELECTRICITY COMPANY ENGINEERING DRAWINGS STANDARD(SEEDS)


ENGINEERING DRAWINGS STANDARD
SEEDS-I

PREPARING, PROCESSING & MANAGING TRANSMISSION


DRAWINGS/DOCUMENTS

Apr. 29, 2009

Total =

ENGINEERING DRAWINGS STANDARD FOR CONTRACTORS


SEEDS-II

PREPARING, PROCESSING & MANAGING TRANSMISSION FOR


CONTRACTORS

Oct. 19, 2004

Total =
TMSS

115

24-Jan-2011

TES

97

TCS

31

TSD

48

SEEDS

TOTAL

293

Page 9 of 9