Check List (Piping) Project

Start/ Kick-Off Meeting Discussion


0

Sr.
No.

List

REVIEW/ QUERIES ON DOCUMENTS RECEIVED FROM


CLIENT/ PROCESS LICENSOR
1.
Basic/ Extended basic engineering package

Project design basis

Piping design basis

P & I D

Equipment data sheet

Piping material specification

Review the entire package requirement


and generate queries for missing information,
contradicting information, Ambiguous information,
and content of information.
2.
Site survey drawing and Site master plan
3.
Clients/ Process Licensors design standards
4.
Existing facility documentation
5.
Scope of work and Split of work
6.
Applicable codes and Standards
7.
Review requirement
8.
Project schedule
9.
Documentation requirement
10. Design basis for stress analysis and support
design
11. Design basis for 3D model / Usage of software
12. Local regulation and Statutory requirement
Sr.
List
No.
DESIGN
1.
Clients standard/ preference for locating
various facilities on the plot.
2.
Clients standard/ preference for equipment

3.
4.

5.

spacing.
Minimum foundation heights for equipment and
supports
Preference of piperack / Pipe sleepers design if
any,

Preference of elevated rack v/s pipe


sleepers v/s inside trench v/s buried pipes and
extent of the same

Concrete, steel or combination of both

Minimum piperack elevation in general


and at road/ rail crossing

Tier to tier distance

Spare space in each tier for future


expansion

Cable tray/ duct routing preference


combined pipes and cables tier or separate?

Walkways between cable trays for cable


pulling/ maintenance

Location of rack longitudinal beam at


tier elevation or in between tier elevation.

Conventional rack or modular rack. If


modular, philosophy of design, erection etc.

Incase of air fin cooler on top of the


rack, operating/ maintenance platform requirement
and access

Incase of equipment supported on top of


the rack, maintenance requirement, erection
methods etc.

Cable tray layout flat type of tree


type

Usage of Low friction rods, low friction


sliding plates etc.

Movement requirement below the racks


Preference on Building/ structure design

Concrete, steel, combination of both

Building sides closed or open. If


closed type of enclosure with doors windows,
cladding etc.

Minimum floor to floor height


requirement

Minimum ground floor plinth elevation


requirement

Roof configuration

Floor finishes Type of floor

6.

7.

Encasement of steel sections

Floor and wall cut out type precast


or at site, with or without sleeves, sealed or
unsealed etc.

Floor drainage philosophy

Need for foundation for small equipment


or can be supported off the floor

Extent of paving out side building

Architectural features if any

Expansion requirement/ future space/


provision to be made at present for any future
requirement.

Equipment erection philosophy within


building

Preference on equipment support and


mounting arrangement.
Layout consideration

Specific hazard consideration

Maintenance requirement such as crane,


monorail, lifting beams etc.

Road width, roads cross-section and


type of road etc.

Future expansion provision and


consideration

Operating access requirement for instrument valves


manways, handholes etc.

Storage warehouse sizes, no. of days


storage for raw material, intermediate, finished
product, waste, by products etc. and their
loading and unloading consideration

Non plant facilities requirement

Extent of paving, drainage requirements


and containment consideration.

Architectural consideration

Equipment erection consideration for


very heavy, very tall and fragile equipment.

Understanding operating and maintenance


requirement for the entire plant and individual
equipment
Stress analysis
Stress analysis design basis

Derivation procedure/ criteria for stress


critical line list

Design codes to be used

8.

Wind loading data and earthquake zone

Additional external loading


consideration such as snow load, solar effect
etc.

Fabricated equipment acceptable


nozzle
loads
for various sizes and pound
equipment
rating nozzles

Proprietary/ Rotary equipment


acceptable equipment external nozzle loading for
equipment such as pumps, turbines, compressors,
air fin coolers, fired heaters etc

Package equipment battery limit tie in


point acceptable nozzle loading
Relief valve force calculation

clients standard

Software to be used for stress


analysis.

Documentation requirement.

Review requirement by client


Pipe support design

Movement

Design criteria, guidelines, support


standard.

Up to what size it is supported on


design office document and below which size to be
field supported

Structural steel section type.

Specific requirement of using type of


support

Loading/ height criteria for


determining whether to be built by civil group or
piping group.

Probable vendor for spring

Usage of low friction slide plates in


supports near critical equipment, high expansion
area etc

Vessel supported pipes cleat,


standard, design

Documentation requirement :
Pipe support on model annotation or actual support Pipe
support on isometrics or on layout

Special pipe supports

Support MTO
Support design software