Академический Документы
Профессиональный Документы
Культура Документы
construction
projects
bear
some
degree
of
confusion
and
uncertainty.
Blake Construction Co. v. C.J. Coakley Co., Inc. (D.C. Ct. App. 1981) 431
A.2d 569, 575.
65390.1 JDARLING
10/19/2004--3:59 PM
Page 1 of 21
delay or disrupt
These obligations
cooperating
with
the
contractor
when
difficulties
or
California.3
The Spearin
At
specifications
are
complete
and
that
an
experienced
general
The
siding with one party; either way increased costs are inevitable.
Public Contract Code Section 1104; City of Salinas v. Souza & McCue
(1967) 66 Cal.2d 217; Howard Contracting, Inc. v. G.A. McDonald Construction
(1998) 71 Cal.App. 138.
65390.1 JDARLING
10/19/2004--3:59 PM
Page 2 of 21
If
Subcontractors
who
not
being
timely
paid
are
in
the
delay
arena
and
of
disruption
proper
responsibilities
planning.
Proper
fall
planning,
65390.1 JDARLING
10/19/2004--3:59 PM
Page 3 of 21
Ship"
and
is
responsible
for
coherent
based
on
"critical
path"
and
logical
Schedules are
methodology.
If
the
subcontractors
as
possible.
To
maximize
profit,
as
possible.
If
the
prime
contractor
schedules
the
This
More
Page 4 of 21
are
inexcusable.
basically
two
types
of
delay:
excusable
and
contractor
excusable/compensable delay
must
establish
proof
of
an
Bigelow, Inc. ASBCA No. 24376, 81-2 BCA CCH No. 15, 30000.
65390.1 JDARLING
10/19/2004--3:59 PM
Page 5 of 21
per
diem
amount
for
every
calendar
day
of
delay.
on the project.
In order to
delay
is
also
typically
delay:
"If
period
of
litigated
in
claims
can
be
attributed
Id.
65390.1 JDARLING
10/19/2004--3:59 PM
Page 6 of 21
is partly the fault of the owner and partly the fault of the
contractor, courts will permit the parties to apportion delay
according to fault.11
Assuming a contractor can establish excusable/compensable
delay, the contractor typically only recovers delay damages if the
delay falls on the critical path.12
10
65390.1 JDARLING
10/19/2004--3:59 PM
Page 7 of 21
start/late
particular task.
start
and
early
finish/late
finish
for
any
In
delay litigation, owners and contractors each contend that they own
this float.
an
as-planned
schedule
together
with
an
analysis
demonstrating the delays that occurred on the project and how those
delays created a new critical path.
13
14
65390.1 JDARLING
10/19/2004--3:59 PM
Page 8 of 21
relationship
among
predecessor
and
successor
activities.
In
California,
courts
have
held
that
bar-chart
the
demonstrates
project's
". . . that
critical
the
delays
path
and
constitute
the
analysis
critical
path
delays."15
A contractor's delay damages typically consists of direct and
indirect expenses.
project
site
for
office
15
trailers,
fences,
65390.1 JDARLING
10/19/2004--3:59 PM
Page 9 of 21
fax
project
management,
and
administrative
support.
Once
This calculation is
Eichleay is based
through
construction projects.
revenue
stream
generated
65390.1 JDARLING
10/19/2004--3:59 PM
various
from
Page 10 of 21
Contractors'
project
is
delayed
and
the
contractor
does
not
If
receive
delay
period,
the
contractor
will
nevertheless
have
to
activities.
Under
this
scenario,
the
contractor
to
the
trier
of
fact
together
with
the
number
of
the trier of fact then calculates the total extended home office
overhead claim to be awarded to the contractor.
For
demonstrate
contractor
that
(1)
to
a
recover
compensable
under
delay
Eichleay,
occurred;
it
must
(2)
the
17
West v. Allstate Boiler, Inc. (1998) 146 F.3d 1368, 1373; Interstate
General Government Contracts, Inc. v. West (Fed. Cir. 1993) 12 F.3d 1053,
1056.
18
65390.1 JDARLING
10/19/2004--3:59 PM
Page 11 of 21
It
21
more
man-hours
contemplated.
to
complete
the
task
than
originally
19
20
21
65390.1 JDARLING
10/19/2004--3:59 PM
Page 12 of 21
also
contend
that
the
contractor's
assumptions
22
Cushman & Butler Construction Change Order Claims (1994) John Wiley
& Sons, Inc. 7.11.
24
65390.1 JDARLING
10/19/2004--3:59 PM
Page 13 of 21
25
Courts have
recognized that experts are needed to demonstrate a cause-andeffect relationship by some accepted method of proving causation
and quantification.
"Quantification of loss of efficiency or
impact claims is a particularly vexing and
complex problem. We have recognized that
maintaining cost records, identifying and
separating inefficiency costs to be both
impractical and essentially impossible."26
Another court addressed this quantification issue in a similar
fashion,
"[w]e, as most other courts and board,
recognize that quantifying the loss of labor
productivity is difficult and that the
determination of the dollar amount of damages
for labor inefficiency with exactitude is
essentially impossible. In recognizing this
fact, we expect that the measurement of the
amount of inefficiency would usually be
supported by expert testimony."27
To support a disruption damage calculation, contractors
typically site to Civil Code
25
Lewis Management & Service Co., ASBCA No. 24,389,85-2 B.C.A. (CCH)
18, 042 at 90,565 (1985).
26
The Clark Construction Group, Inc., VABCA No. 5674, 00-1 BCA 30,
27
P.J. Dick, Inc. VABCA No. 5597, et al., 01-2 BCA 31,647.
870.
65390.1 JDARLING
10/19/2004--3:59 PM
Page 14 of 21
"Measured
Mile"
approach
analyzes
the
contractor's
compared
disruption.
to
the
productivity
experienced
during
28
65390.1 JDARLING
10/19/2004--3:59 PM
Page 15 of 21
the
The
contractor's expert can use the MCAA factors and opine as to how
29
P.J. Dick, Inc. VABCA No. 5597, et al., 01-2 BCA 31,647
65390.1 JDARLING
10/19/2004--3:59 PM
Page 16 of 21
that
30
involves
(1)
demonstrating
the
impracticability
of
31
Huber Hunt & Nichols, Inc. v. Moore (1977) 67 Cal. App.3d 278,
Amelco Electric v. The City of Thousand Oaks, 27 Cal.4th 228 (2002).
65390.1 JDARLING
10/19/2004--3:59 PM
Page 17 of 21
On a
of the Total Cost and Modified Total Cost methods is that they can
be used by contractors to hide their self-imposed losses due to bid
errors or defective project management.
causation
between
what
the
owner's
actions
and
the
35
Servidone v. United States (1990) 19 Cl. Ct. 346, 348, aff'd (Fed.
Cir. 1990) 931 F.2d 860.
65390.1 JDARLING
10/19/2004--3:59 PM
Page 18 of 21
long
and
complex
construction
case
can,
in
short
or
the
trier
of
approximation of damages.36
resort.
fact
to
make
fair
and
reasonable
36
Tutor
Saliba
(1987).
65390.1 JDARLING
10/19/2004--3:59 PM
Page 19 of 21
of
delay
and
disruption
losses:
"no
damages
for
delay"
other,
all
bear
serious
consideration
before
use,
with
inception of a
4556
Page 20 of 21
65390.1 JDARLING
10/19/2004--3:59 PM
Page 21 of 21