Вы находитесь на странице: 1из 146

CHAPTER 5

SCHEDULING AND TRACKING


WORK IN CONSTRUCTION
PROJECT MANAGEMENT

Introduction
Planning & Scheduling

Principles
Techniques
Work breakdown structure
Gantt Chart & S-Curve
Critical Path Method
Successor/ predecessor relationship
Arrow Diagram Method and
Precedence Diagram Method

THE INTEGRATION OF TIME &


SUSTAINABLE CONSTRUCTION
Our focus!!

Traditional Projects Critical Components (time, cost, & quality); in relation with
sustainable construction concept

Introduction
Project planning
Process of identifying all the activities necessary
to successfully complete the project.
Provides map to guide where to go and focused
on how to get there
Planned in early stage of Project life Cycle or also
before site activities start.

Introduction
Importance of planning
Reduce mistake and rework
Avoid wastage
minimize unnecessary in time and cost scheduling
better quality control
Effective project progress control
Effective usage resources

Introduction
Project scheduling
Process of determining the sequential order of the
planned activities, assigning realistic durations to
each activity and determining the start and finish
dates for each activities.
it can be used to manage, coordinate, control and
report.
Depending on the sophistication of the user, the
schedule can take different forms.

Project Scheduling
Purpose of project scheduling

Claim
Project time and cost control
Allocate project resources more efficiently
As a monitoring tool
Material delivery at site
Storage all material cannot put in the site (confined space)
Avoid delay of the work and activity.
Minimize the cash flow as min as possible such as order material
stage by stage depend on the work needed.
Control human resources and machinery To improve the efficiency
of the operation through the efficient use of resources and cost
control.

Project planning is prerequisite to project planning!

Desired results of planning and scheduling

Finish the project on time.


Continuous (uninterrupted) flow of work (no delays)
Reduced amount of rework (least amount of changes)
Minimized confusion on misunderstandings.
Increase knowledge of status of project by everyone.
Meaningful and timely reports to management.
You run the project instead the project running you.
Knowledge of scheduled times of key parts of the project.
Knowledge of the distributions of costs of the project
Accountability of people, define responsibility/authority.
Clear understanding of who does what, when & how much.
Integration of all work to ensure a quality project for the owner.

What are the different?


Planning is more difficult to accomplish than
scheduling.
The term planning and scheduling are often
used synonymously.
Planning is first step to project scheduling.
Tools used for planning and scheduling are
different!

Principles of planning and scheduling

Begin planning before starting work, rather than after starting


work.
Involve people who will actually do the work in the planning
and scheduling process.
Includes all aspects of the project: scope, budget, schedule &
quality.
Build flexibility into the plan, include allowance for changes and
time for reviews and approvals.
Remember the schedule is the plan for doing the work, and it
will never be precisely correct.
Keep the plan simple, eliminate irrelevant details that prevent
the plans from being readable.
Communicating the plan to all parties; any plan is worthless
unless it is known.

Client Satisfaction
COST

TIME

QUALITY

20
18
16
14
12
10
8
6
4
2
0

RESOURCES

SCOPE

The Collection of Projects Critical Components (should be in equilibrium)

Steps in planning and scheduling


Scope
definition

Time &
Resource
Management

Activity
Sequencing

Schedule
development
Create WBS

Scope

Activity
resource
planning

Cost Estimating

Activity
Duration
Estimation

Cost Budgeting

Management

Cost
Management

Steps in planning and scheduling


1.
2.
3.
4.

Develop a work breakdown structure (WBS)


Prepare a drawing (network diagram)
Determine the time, cost and resources required
Compute the schedule to determine start, finish
and float times
5. Analyze costs and resources for the project
6. Communicate the results of the plan and
schedule

Work breakdown structure (WBS)


Identifies the tasks and activities that must be
performed.
It divides the project into identifiable parts that can be
managed.
Concept of WBS: in order to manage a whole project,
one must manage and control each of its parts.
It defines:

The work to be performed


The need of expertise
Assist in selection of project team
Establish a base of project scheduling and control

Work breakdown structure (WBS)


WBS is display as a graphical or outline
method that shows the division of work in a
multi level system.
In developing WBS, we should consider:
Activities that require time
Activities that require cost
Activities that need to arrange
Activities that need to monitor

Work Breakdown Structure (Graphical)


Level 1

Construction of one block office building

Level 2
Start Project

Preliminaries

Block A

Level 3
Performance
bond

Earthwork

Establish and
removal of site
office

Structure Work

Architecture
Work

M&E work

Testing &
Commissioning

Project
complete

Work Breakdown Structure (Outline)


Construction of one
block office building
Start Project
Preliminaries
Performance bond
Establish and removal
of site office
Block A
Earthwork
Structure Work
Architecture Work
M&E work

Testing and
Commissioning
Project complete

Work breakdown structure (WBS)


Importance of WBS
Overall program can be explain in summary according to
each sub-element divided.
Planning could execute.
Cost and budget could estimate more accurately.
Time, Cost and Performance of each element could be
monitor from time to time.
Objective could be relate directly with the available
resources in the company.
Network diagram and control planning could be prepared
in early stages.
Responsibilities for each parties involve in every element
could be identify and assign.

Work breakdown structure (WBS)


Example:
You are the Project Manager for a Construction
of Proposed Construction and Completion of a
Double Storey Bungalow House And Related
Works For Messrs. Dato 'Kamal Jaafar. Develop
a preliminary graphical work breakdown
structure (up to level 4) for the project given.
Your WBS should complete with all works needs
in completing a one unit bungalow.

Example (WBS-Graphical Method)


Level
1
Level
2
Level
3

Proposed Construction and Completion of A Double Storey Bungalow House and


Related Works for Messrs. Dato 'Kamal Jaafar.
Preliminary
works
Performance
bond
Progress
Report

Building
works
Structure

Architecture

External
works
M&E

Sewerage

Foundation

Wall

Wiring

Road and
drainage

Ground level

Floor

Fittings
installation

Landscape

1st floor level

Roof

2nd floor
level

Fittings

Level
4

Exercise (Outline Method)


Proposed Construction and Completion of A Double Storey Bungalow House and
Related Works for Messrs. Dato 'Kamal Jaafar.

Techniques for scheduling


Techniques used will vary depending on:

Projects size
Complexity
Duration
Personnel
Owner requirements

Two general methods commonly used :

Bar chart (Gantt chart)


Critical path method (CPM/ network analysis
system)

Develop by Henry L.Gantt


Is a graphical time-scale of the schedule,
length represent the duration of activity.

Advantages

Disadvantages

Easy to interpret
Simplicity & ease of preparation and
understanding (Simple graphical).
No theory or complicated calculation
involved (Easy for general
comprehension).
Time-scaled (the length of the bar
representing certain activity is
proportional to the duration of that
activity.
Appeal to persons who do not have a
technical background
Wide spread used in industry
Mostly used in small project
Fairly broad planning and scheduling
tools, so they require less revision
and updating than more
sophisticated systems

Difficult to update
Very cumbersome as the
number of line activities, or bars
increases
Does not integrate costs or
resources with the schedule
Limited application for detail
construction work
Difficult to use it for forecasting
the effects that changes in a
particular activity will have on
the overall schedule

Bar chart (Gantt Chart)


No.

Description

Month
1

Mobilization

Foundation Excavation

Diversion Stage

Foundation Grouting

Dam Concrete

Install Outlet Gates

Install Trash Racks

Prestress

Radial Gates

10

Spillway Bridge

11

Curtain Grout

12

Dismantle Plant, Clean Up

10

Original Schedule

Actual progress

Bar chart basically use x-axis only (to depict time).


The y-axis is use to show individual activities, to represent a variable across time

(e.g.: man-hours, budget, % complete and so forth.

Bar chart (Gantt Chart) + S curve


Description

Month
1

Mobilization

Foundation Excavation

Diversion Stage

Foundation Grouting

Dam Concrete

Install Outlet Gates

Install Trash Racks

Prestress

Radial Gates

10

Spillway Bridge

11

Curtain Grout

12

Dismantle Plant, Clean Up

10
100

Original Schedule

Actual progress

Cumulative progress (%)

No.

Bar chart basically use x-axis only (to depict time).


The y-axis is use to show individual activities, to represent a variable across time (e.g.: man-hours,
budget, % complete and so forth.
The variables usually shown as a curve superimposed on the bar chart.

Bar chart (Gantt Chart)


Tutorial No.2:
A project consist of five activities that should be
done in a period of time. Try to create a bar chart
to ease the project planning and scheduling.
* consider 1 week as 7 days

Activity A
Activity B
Activity C
Activity D
Activity E

: 1 week, starting from 1 Jun 2015


: 2 week, starting from 8 Jun 2015
: 3 week, starting from 15 Jun 2015
: 2 week, starting from 22 Jun 2015
: 2 week, starting from 29 Jun 2015

Bar chart (Gantt Chart)-Example 1


Step 1: identify start date and finish date for
each activity
Activity A
Activity B
Activity C
Activity D
Activity E

: 1 week, starting from 1 Jun 2014


: 2 week, starting from 8 Jun 2014
: 3 week, starting from 15 Jun 2014
: 2 week, starting from 22 Jun 2014
: 2 week, starting from 29 Jun 2014

(1/6-7/6)
(8/6-21/6)
(15/6-5/7)
(22/6-5/7)
(29/6-12/7)

Bar chart (Gantt Chart)-Example 1


Step 2: Draw outline of bar chart
Activity

Duration
(week)

Week 1
1/6

Act. A

Act. B

Act. C

Act. D

Act. E

Week 2
8/6

Week 3
15/6

Week 4
22/6

Week 5
29/6

Week 6
6/7

Bar chart (Gantt Chart)-Example 1


Step 3: Draw the
activity bars

Activity A

Activity B
Activity C
Activity D
Activity E

Activity

Duration
(week)

Week 1
1/6

Act. A

Act. B

Act. C

Act. D

Act. E

Week 2
8/6

Week 3
15/6

: 1 week, starting from 1 Jun 2014


(1/6-7/6)
: 2 week, starting from 8 Jun 2014
(8/6-21/6)
: 3 week, starting from 15 Jun 2014
(15/6-5/7)
: 2 week, starting from 22 Jun 2014
(22/6-5/7)
: 2 week, starting from 29 Jun 2014
(29/6-12/7)
Week 4
22/6

Week 5
29/6

Week 6
6/7

Bar chart (Gantt Chart)-Example 2


Num

Activity

Duration
(days)

Start Date

Cost (RM)

Resources/
day
(person)

Work
progress
percentage
(%)

Activity A

4/5/2014

1,400.00

12

Activity B

7/5/2014

2,700.00

30

Activity C

10/5/2014

3,500.00

21

Activity D

15/5/2014

6,000.00

10

Activity E

17/5/2014

4,700.00

12

Activity F

19/5/2014

12,600.00

15

30,900.00

100

Bar chart (Gantt Chart)-Example 2


Step 1: identify start date and finish date for
each activity
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F

: 3 days, starting from 4 May 2014


: 5 days, starting from 7 May 2014
: 7 days, starting from 10 May 2014
: 5 days, starting from 15 May 2014
: 4 days, starting from 17 May 2014
: 6 days, starting from 19 May 2014

(4/5-6/5)
(7/5-11/5)
(10/5-16/5)
(15/5-19/5)
(17/5-20/5)
(19/5-24/5)

Bar chart (Gantt Chart)-Example 2

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

Act. F

16/5

15/5

Act. E

14/5

13/5

Act. D

12/5

11/5

Act. C

10/5

9/5

Act. B

8/5

7/5

Act. A

6/5

Duration
(days)

5/5

Activity

4/5

Step 2: Draw outline of bar chart

Bar chart (Gantt Chart)-Example 2

24/5

23/5

22/5

21/5

20/5

19/5

18/5

Act. F

17/5

16/5

Act. E

15/5

14/5

Act. D

: (4/5-6/5)
: (7/5-11/5)
: (10/5-16/5)
: (15/5-19/5)
: (17/5-20/5)
: (19/5-24/5)
13/5

12/5

Act. C

11/5

9/5

Act. B

8/5

7/5

Act. A

6/5

Duration
(days)

5/5

Activity

4/5

Step 3: Draw the


activity bars

10/5

Activity A
Activity B
Activity C
Activity D
Activity E
Activity F

An S-curve is defined as:


"A display of cumulative costs, labor hours or
other quantities plotted against time. The name
derives from the S-like shape of the curve, flatter
at the beginning and end and steeper in the
middle, which is typical of most projects. The
beginning represents a slow, deliberate but
accelerating start, while the end represents a
deceleration as the work runs out."

S-Curve
Type of S-Curve
Physical S-Curve
Financial S-Curve

Both S-curve can be in Baseline (planned) or


actual S-curve

S-Curve (Example)
Num

Activity

Duration
(days)

Start Date

Cost (RM)

Resources/
day
(person)

Work
progress
percentage
(%)

Activity A

4/5/2014

1,400.00

12

Activity B

7/5/2014

2,700.00

30

Activity C

10/5/2014

3,500.00

21

Activity D

15/5/2014

6,000.00

10

Activity E

17/5/2014

4,700.00

12

Activity F

19/5/2014

12,600.00

15

30,900.00
Based on bar chart in Example 2, construct S-curve (daily basis) for this project:
1. Financial S-Curve
2. Physical S-curve (resources vs time & work vs time)

100

Financial S-Curve

Financial S-Curve

12,600

Cost/day
Cumulative cost/day

24/5

23/5

Act. F

22/5

4,700

21/5

20/5

Act. E

19/5

6,000

18/5

17/5

Act. D

16/5

3,500

15/5

14/5

Act. C

13/5

2,700

12/5

11/5

Act. B

10/5

1,400

9/5

8/5

Act. A

Cost/day
(RM)

7/5

Cost
(RM)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 1: DRAW BAR CHART (from Example 2), include Cost of each activity

Financial S-Curve
Act. A

Act. B
Act. C

Act. D
Act. E
Act. F

1,400

=1,400/3

467
5
2,700 =2,700/5
540
7
3,500 =3,500/7
500
5
6,000 =6,000/5
1200
4
4,700 =4,700/4
1175
6
12,600 =12,600/6
2100
Cost/day
Cumulative cost/day

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

12/5

11/5

10/5

9/5

8/5

Cost/day
(RM)

7/5

Cost
(RM)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 2: Calculate COST/ DAY = Cost / duration

Financial S-Curve

12,600

2100

Cumulative cost/day

24/5

Act. F

23/5

1175

22/5

4,700

21/5

20/5

Act. E

1200

19/5

6,000

18/5

17/5

Act. D

500

16/5

3,500

15/5

14/5

Act. C

540

13/5

2,700

12/5

11/5

Act. B

467

10/5

1,400

9/5

8/5

Act. A

Cost/day

Cost/day
(RM)

7/5

Cost
(RM)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 2: Calculate COST/ DAY = Cost / duration

Financial S-Curve

540

3,500

Act. D

6,000

Act. E

4,700

1175

Act. F

12,600

2100

Cumulative cost/day

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

467

Act. C

Cost/day

12/5

2,700

11/5

10/5

Act. B

9/5

1,400

8/5

7/5

Act. A

Cost/day
(RM)

6/5

Cost
(RM)

5/5

Duration
(days)

540 +500

500
1200

467
467
467
540
540
540
1040
1040
500
500
500
1700
1700
2375
2375
4475
3275
2100
2100
2100
2100

Activity

4/5

STEP 3: Calculate the TOTAL COST of each DAY

Financial S-Curve

Act. F

12,600

2100

24/5

1175

23/5

4,700

22/5

21/5

Act. E

20/5

6,000

19/5

18/5

Act. D

17/5

3,500

16/5

15/5

Act. C

14/5

2,700

13/5

12/5

Act. B

11/5

1,400

10/5

9/5

Act. A

8/5

Cost/day
(RM)

7/5

Cost
(RM)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 4: Calculate the CUMULATIVE COST of each DAY

467
540
500

Cost/day

467
467
467
540
540
540
1040
1040
500
500
500
1700
1700
2375
2375
4475
3275
2100
2100
2100
2100

Cumulative cost/day

467
934
1041
1941
2481
3021
4061
5101
5601
6101
6601
8301
1001
12376
14751
19226
22501
24601
26701
28801
30901

1200

Cumulative
cost cost
(previous)
+ current
cost/day
Cumulative
(previous)
+ current
cost/day
= 467= +934
467+ 467

Financial S-Curve
Total cumulative cost
Act. A

Act. B
Act. C

Act. D

5
7

1,400

2,700
3,500

12,600
Start from 0
Cost/day

Cumulative cost/day

24/5

23/5

20600

500

Get the medium (30900 /2)

1175

15450

10300

467

1041
934
5150

2100

Start from 0
467
467
467
540
540
540
1040
1040
500
500
500
1700
1700
2375
2375
4475
3275
2100
2100
2100
2100

22/5

540

6,000
4,700

21/5

25750

467
934
1041
1941
2481
3021
4061
5101
5601
6101
6601
8301
10001
12376
14751
19226
22501
24601
26701
28801
30901

Act. F

30900

467

1200
Act. E

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

12/5

11/5

10/5

9/5

8/5

Cost/da y
(RM)

7/5

Cost
(RM)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 5: Plot graph base on cumulative cost

Financial S-Curve
24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

12/5

11/5

10/5

9/5

8/5

Cost/da y
(RM)

7/5

Cost
(RM)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 5: Plot graph base on cumulative cost

30900

Act. A

Act. B
Act. C

Act. D

5
7

1,400

2,700
3,500

467

25750

540

20600

500

15450

6,000
1200

4,700
12,600

1175
5150

2100
0

Cost/day

467
467
467
540
540
540
1040
1040
500
500
500
1700
1700
2375
2375
4475
3275
2100
2100
2100
2100

Act. F

Cumulative cost/day

467
934
1041
1941
2481
3021
4061
5101
5601
6101
6601
8301
10001
12376
14751
19226
22501
24601
26701
28801
30901

Act. E

10300

Physical S-Curve
(resources VS time)

Num

Activity

Duration
(days)

Start Date

Cost (RM)

Resources/
day
(person)

Work
progress
percentage
(%)

Activity A

4/5/2014

1,400.00

12

Activity B

7/5/2014

2,700.00

30

Activity C

10/5/2014

3,500.00

21

Activity D

15/5/2014

6,000.00

10

Activity E

17/5/2014

4,700.00

12

Activity F

19/5/2014

12,600.00

15

30,900.00

100

Physical S-Curve (resources VS time)

Resource/day
Cumulative resource/day

24/5

23/5

22/5

21/5

20/5

Act. F

19/5

18/5

17/5

Act. E

16/5

15/5

14/5

Act. D

13/5

12/5

2
2
2
6
6
8
8
13
9
5
5
5
5

Act. C

11/5

10/5

Act. B

9/5

8/5

7/5

Act. A

6/5

Resource/
day

5/5

Duration
(days)

4/5

Activity

2
2
2
3
3
3
5

STEP 1: DRAW BAR CHART (from Example 2), include resource/day for each activity

Physical S-Curve (resources VS time)


24/5

23/5

22/5

21/5

Act. F

20/5

19/5

18/5

Act. E

17/5

16/5

15/5

Act. D

14/5

13/5

12/5

Act. C

11/5

10/5

9/5

Act. B

8/5

7/5

6/5

Act. A

5/5

Resource/
day

Resource/day

2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5

Duration
(days)

Cumulative resource/day

2
4
6
9
12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
101

Activity

4/5

STEP 2: Calculate the CUMULATIVE resource of each DAY

Cumulative resource (previous) + current resource/day


=2+2

Physical S-Curve (resources VS time)


24/5

23/5

22/5

21/5

Act. F

20/5

19/5

18/5

Act. E

17/5

16/5

15/5

Act. D

14/5

13/5

12/5

Act. C

11/5

10/5

9/5

Act. B

8/5

7/5

6/5

Act. A

5/5

Resource/
day

Resource/day

2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5

Duration
(days)

Cumulative resource/day

2
4
6
9
12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
101

Activity

4/5

STEP 3: Plot graph base on cumulative resource

Physical S-Curve (resources VS time)


24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

12/5

11/5

10/5

9/5

8/5

7/5

Resource/
day

6/5

Duration
(days)

5/5

Activity

4/5

STEP 3: Plot graph base on cumulative resource

Total cumulative resource


Act. A

Act. B
Act. C

Act. D
Act. E
Act. F

5
7

5
4
6

102
85

68

51

4
102/6 x 2 = 34

34

102/6 = 17

17

4
5

Resource/day

2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5

Cumulative resource/day

2
4
6
9
12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
101

Start from 0

Physical S-Curve (resources VS time)

Act. A

Act. B
Act. C

Act. D
Act. E

5
7

5
4

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

12/5

11/5

10/5

9/5

8/5

7/5

102

85

68

51

34

17

Resource/day

2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5

6/5

Resource/
day

Cumulative resource/day

2
4
6
9
12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
101

Act. F

Duration
(days)

5/5

Activity

4/5

STEP 3: Plot graph base on cumulative resource

Physical S-Curve
(work VS time)

Num

Activity

Duration
(days)

Start Date

Cost (RM)

Resources/
day
(person)

Work
progress
percentage
(%)

Activity A

4/5/2014

1,400.00

12

Activity B

7/5/2014

2,700.00

30

Activity C

10/5/2014

3,500.00

21

Activity D

15/5/2014

6,000.00

10

Activity E

17/5/2014

4,700.00

12

Activity F

19/5/2014

12,600.00

15

30,900.00

100

Physical
S-Curve
(work
VS
time)
STEP 1: DRAW BAR CHART (from Example 2), include work progress

15

Work progress/day
Cumulative work progress/day

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

Act. F

12

16/5

15/5

Act. E

10

14/5

13/5

Act. D

21

12/5

11/5

Act. C

30

10/5

9/5

Act. B

12

8/5

7/5

Act. A

Work
progress
percentage
(%)

6/5

Duration
(days)

5/5

Activity

4/5

percentage/day for each activity

15

Work progress/day
Cumulative work progress/day

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

Act. F

12

16/5

15/5

Act. E

10

14/5

13/5

Act. D

21

12/5

11/5

Act. C

30

10/5

4 4 4

9/5

Act. B

12

8/5

7/5

Act. A

Work
progress
percentage
(%)

6/5

Duration
(days)

5/5

Activity

4/5

Physical
S-Curve
(work
VS
time)
STEP 2: Calculate work progress percentage of each day for every activities

12% / 3 days = 4%/ day


6 6 6 6 6

30% / 5days = 6%/ day

3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5

Physical S-Curve (work VS time)

12

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

12/5

11/5

10/5

9/5

8/5

7/5

Act. A

Work
progress
percentage
(%)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 2: Calculate work progress percentage of each day

4 4 4

6 +3
5

Act. C

Act. D

Act. E

Act. F

30

21
10

12
15

Work progress/day
Cumulative work progress/day

6 6 6 6 6

3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5

4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5

Act. B

Physical S-Curve (work VS time)

15

Work progress/day
Cumulative work progress/day

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

Act. F

12

15/5

14/5

Act. E

10

13/5

12/5

Act. D

21

11/5

10/5

Act. C

30

9/5

8/5

Act. B

12

7/5

6/5

Act. A

Work
progress
percentage
(%)

5/5

Duration
(days)

4 4 4
6 6 6 6 6

3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5

4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5

Activity

4/5

STEP 3: Calculate cumulative work progress percentage of each day

Physical S-Curve (work VS time)

15

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

Act. F

12

14/5

13/5

Act. E

10

12/5

11/5

Act. D

21

10/5

9/5

Act. C

30

8/5

7/5

Act. B

12

6/5

5/5

Act. A

Work
progress
percentage
(%)

4 4 4
6 6 6 6 6

3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5

Work progress/day

4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5

Duration
(days)

Cumulative work progress/day

4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100

Activity

4/5

STEP 3: Calculate cumulative work progress percentage of each day

Physical S-Curve (work VS time)

15

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

Act. F

12

14/5

13/5

Act. E

10

12/5

11/5

Act. D

21

10/5

9/5

Act. C

30

8/5

7/5

Act. B

12

6/5

5/5

Act. A

Work
progress
percentage
(%)

4 4 4
6 6 6 6 6

3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5

Work progress/day

4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5

Duration
(days)

Cumulative work progress/day

4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100

Activity

4/5

STEP 4: Plot S-curve

Physical S-Curve (work VS time)

Act. A

Act. B

Act. C

Act. E

Act. F

30

21
10

12
15

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

12/5

11/5

10/5

9/5

8/5

7/5

4 4 4
75

6 6 6 6 6

3 3 3 3 3 3 3

50

2 2 2 2 2
3 3 3 3

25

2.5 2.5 2.5 2.5 2.5 2.5


0

Work progress/day

4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5

12

100

Cumulative work progress/day

4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100

Act. D

Work
progress
percentage
(%)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 4: Plot S-curve

Physical S-Curve (work VS time)

Act. A

Act. B

Act. C

Act. E

Act. F

30

21
10

12
15

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

12/5

11/5

10/5

9/5

8/5

7/5

4 4 4
75

6 6 6 6 6

3 3 3 3 3 3 3

50

2 2 2 2 2
3 3 3 3

25

2.5 2.5 2.5 2.5 2.5 2.5


0

Work progress/day

4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5

12

100

Cumulative work progress/day

4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100

Act. D

Work
progress
percentage
(%)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 4: Plot S-curve

Physical S-Curve (work VS time)

Act. A

Act. B

Act. C

Act. E

Act. F

30

21
10

12
15

24/5

23/5

22/5

21/5

20/5

19/5

18/5

17/5

16/5

15/5

14/5

13/5

12/5

11/5

10/5

9/5

8/5

7/5

4 4 4
75

6 6 6 6 6

3 3 3 3 3 3 3

50

2 2 2 2 2
3 3 3 3

25

2.5 2.5 2.5 2.5 2.5 2.5


0

Work progress/day

4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5

12

100

Cumulative work progress/day

4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100

Act. D

Work
progress
percentage
(%)

6/5

Duration
(days)

5/5

Activity

4/5

STEP 4: Plot S-curve

Planning VS Actual S-curve??


Before this, we just create a planning bar
chart.
What if, the real activities has started? How to
create actual S-curve?

Planning VS Actual S-curve (Example 2)


Physical S-Curve (work vs time)
Num.

Activity

Duration
(days)

Start Date

Actual Start
Date

Actual Finish
Date

Cost (RM)

Resources
(person)

Activity A

4/5/2014

4/5/2014

6/5/2014

1,400.00

Activity B

7/5/2014

7/5/2014

12/5/2014

2,700.00

Activity C

10/5/2014

11/5/2014

17/5/2014

3,500.00

Activity D

15/5/2014

17/5/2014

21/5/2014

6,000.00

Activity E

17/5/2014

18/5/2014

22/5/2014

4,700.00

Activity F

19/5/2014

21/5/2014

26/5/2014

12,600.00

30,900.00

Planning VS Actual S-curve


Activity Duration
(days)

Start
Date

Actual
Start
Date

Actual
Finish
Date

Act. A

4/5/14

4/5/14

6/5/14

Act. B

7/5/14

7/5/14

12/5/14

Act. C

10/5/14

11/5/14

17/5/14

Act. D

15/5/14

17/5/14

21/5/14

Act. E

17/5/14

18/5/14

22/5/14

Act. F

19/5/14

21/5/14

26/5/14

Planning cumulative work / day


Actual cumulative work/ day

4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5

STEP 1: DRAW BAR CHART (planning and actual)

Planning
Actual

Planning VS Actual S-curve


Activity Duration
(days)

Start
Date

Actual
Start
Date

Actual
Finish
Date

Act. A

4/5/14

4/5/14

6/5/14

Act. B

7/5/14

7/5/14

12/5/14

Act. C

10/5/14

11/5/14

17/5/14

Act. D

15/5/14

17/5/14

21/5/14

Act. E

17/5/14

18/5/14

22/5/14

Act. F

19/5/14

21/5/14

26/5/14

Planning cumulative work / day


Actual cumulative work/ day

4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5

STEP 2: Calculate cumulative for both planning & actual work/day

Planning VS Actual S-curve


Activity Duration
(days)

Start
Date

Actual
Start
Date

Actual
Finish
Date

Act. A

4/5/14

4/5/14

6/5/14

Act. B

7/5/14

7/5/14

12/5/14

Act. C

10/5/14

11/5/14

17/5/14

Act. D

15/5/14

17/5/14

21/5/14

Act. E

17/5/14

18/5/14

22/5/14

Act. F

19/5/14

21/5/14

26/5/14

Planning cumulative work / day


Actual cumulative work/ day

4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5

STEP 2: Calculate cumulative for both planning & actual work/day

1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30
1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32

Planning VS Actual S-curve


Activity Duration
(days)

Start
Date

Actual
Start
Date

Actual
Finish
Date

Act. A

4/5/14

4/5/14

6/5/14

Act. B

7/5/14

7/5/14

12/5/14

Act. C

10/5/14

11/5/14

17/5/14

Act. D

15/5/14

17/5/14

21/5/14

Act. E

17/5/14

18/5/14

22/5/14

Act. F

19/5/14

21/5/14

26/5/14

Planning cumulative work / day


Actual cumulative work/ day

4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5

STEP 3: Plot the S -curves

1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30
1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32

Planning VS Actual S-curve


Activity Duration
(days)

Start
Date

Actual
Start
Date

Actual
Finish
Date

Act. A

4/5/14

4/5/14

6/5/14

Act. B

7/5/14

7/5/14

12/5/14

Act. C

10/5/14

Act. D

15/5/14

Act. E

Act. F

11/5/14

17/5/14

17/5/14

21/5/14

17/5/14

18/5/14

22/5/14

19/5/14

21/5/14

26/5/14

Planning cumulative work / day


Actual cumulative work/ day

4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5

STEP 3: Plot the S -curves

Planning

Actual

1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30
1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32

Arrow Diagram Method (ADM)


-Activity-on-Arrow (AOA) Network

Precedence Diagram Method (PDM)


- Activity-on-Nodes (AON) Network

Network Diagram
Activity on Arrow (AOA)/ Arrow Diagram
Method (ADM)
In arrow diagram project task or activities are
represented by the arrow and connected by the node
to express their logical relationship
Node represents an event. An activity starts or ends at
a node.
Activity A
Node

Activity B
Node

Node

ADM
Diagram for construction of pad footing

Fabricated rebar

Excavate
trench

Fixed fwk

Fabricated formwork

Fixed rebar

Pour concrete

Network Diagram
Activity on Node (AON)/ Precedence Diagram
Method (PDM)
activity is place on the node
The arrow used to connect between project task
to show their logical relationship

Act. A

Node

Act. B

Node

Network Diagram
Diagram for construction of pad footing

Arrow
Node
Logical

- Logical
- Activity
Show the relationship
between activities
- Sequences of interrelated
activity

Basic definition in network diagram


Activity- the performance of a task required to
complete the project. An activity require time,
cost, or both.
Network- a diagram to represent the
relationship of activities to complete a project.
The network may be drawn as ADM or PDM.
Duration- the estimated time required to
perform an activity.

Activity Sequencing
Understand the order of how the job to be
accomplished in the field.
The planner must understand how various
activities of the project related to each other
in term of their logical sequence.
Example preparing formwork before
reinforcement could be place & than pouring
concrete.

Activity Sequencing
Predecessor
A task whose start or finish date determines the
start or finish date of its successor task.

Successor
A task whose start or finish date is driven by its
predecessor task.

ADM vs. PDM


Item

ADM

PDM
ES

LS

Activity

Activities shown as an arrow or


sometimes as a line.

ES
1
LS

Event/ Node

2 events / nodes

D
A
TF

EF
LF

ES: Early Start LS: Late Start


EF: Early Finish LF: Late Finish
D : Duration
TF: Total Float

Activities shown on node.

ES

EF
2
LF

LS

D
A
TF

1 event

EF

LF

ES

LS

D
B
TF

EF

LF

ADM vs. PDM


ADM

PDM

Early Start (ES) is the earliest possible time an activity can start.
Early Finish (EF) is the earliest possible time an activity can finish if it
is start on Early Start Time (ES) and finish within the planned duration.
EF = ES + D

*D = duration

Late Finish (LF) is the latest possible time an activity can


finish without extending the completion date of the project.
Late Start (LS) is the latest possible time an activity can
start without extending the completing date of the project.
LS = LF - D

Total float (TF)- the amount of time an activity may be


delayed without delaying the completion date of the project.
TF = LF ES D

or

TF = LS ES

or

TF = LF EF

Free float (FF)- the amount of time an activity may be


delayed without delaying the early start time of the
immediately following activity.
FF(i) = ES(j) EF(i) ; i-preceding activity, j-following activity

ADM vs. PDM


ADM
-A and B are activities. 1, 2 and 3 are events
-Activity A has ID or label 1-2 ; Activity B has ID or label 2-3
-Activity A precedes activity B

PDM
Activity Nodes
ES
LS

D
A
TF

EF
LF

Predecessor
Activity

ES
LS

D
B
TF

EF
LF

Current
Activity

ES
LS

D
B
TF

EF
LF

Successor
Activity

ADM vs. PDM


Item

ADM
F S

Relationshi
p

ADM only shows finish-to-

start relationships, meaning


that each activity is
completed before the
successor activity starts.

Critical
path

PDM
F
F
S
S

S
F
S
F

Critical Path
A series of interconnected activities through the network
diagram, with each activity having zero total float time. The
critical path determines the minimum time to complete the
project.
1.
2.
3.

ESX = LSX, or
LFX = EFX, or
Total Float (TF) = 0

Possible to have more than one critical path


- Activities which lay on critical path cannot suffer any delay
-

ADM vs. PDM


Item

ADM

PDM

Definition

Dummy
Activity
D

or

An activity that

indicates any activity


following the dummy
cannot be started until
the activity(ies)
preceding the dummy are
completed.
Activity which has not
duration. It is only used
to show any relationship
between activities.
Function

If there is a situation

where one event is used


to show relationship more
than one activity.
To show a complicated
relationship clearly

Dummy activity is not used

in Precedence Diagram
Method (PDM)

ADM

Item

ADM
Activity A & B have the same
ID
A: 1-2
B: 1-2

False

Dummy
Activity
D

or

ID for Activity A & B are not


same.
A: 1-2
B: 1-3

True
A

1
2

If C is to follow A & B,
but D is to follow only B.
(not fulfill)

If C is to follow A & B,
but D is to follow only B.
(use dummy)

Item

ADM
If P, Q and R follow A, and B follows P, Q and R. The following diagram is not the
correct representation of the same.

False
Dummy
Activity

R
Reason: Activities P, Q and R have the same ID (2-3).

True
P

or
1

5
Q

2
R

Activities P has the ID (2-5), Q (2-3) and R (2-6).

Item

ADM
1.
2.
3.

D is preceded by A only
E is preceded by A and B
F is preceded by B and C

Dummy
Activity

False

True

or

Statement 3 not fulfill


where F is preceded by
A, B and C.

E
F

ADM vs. PDM


Item

ADM
-

PDM

FORWARD PASS

: To establish the earliest expected start and finish


times for each activity in the network.

Estimating
duration

BACKWARD PASS

: To establish the latest allowable start and finish


times for each activity in the network.

FORWARD PASS

Early
Start

Early
Finish

Late
Start

Late
Finish

BACKWARD
92 PASS

Arrow Diagram Method

93

Note

Forward pass
c = a + X
a
1 b

c
2 d

e = c + Y
B
Y

e
3
f

a
b
c
d
e
f
X
Y

:
:
:
:
:
:
:
:

Early Start (ES)A


Late Start (LS)A
Early Finish (EF)A = (ES)B
Late Finish (LF)A = (EF)B
Early Finish (EF)B
Late Finish (LF)B
Duration of activity A
Duration of activity B

d = f Y

Backward pass

Forward pass
a = 0
c = a + X
e = c + Y

Backward pass
f = e
d = f Y
b = d - X

ACTIVITY

DURATION(DAY)

PREDECESSOR

10

E,D

C,F

2
A

C
5

D
4

F
10

ACTIVITY

DURATION
(DAY)

PREDECESSOR

10

E,D

C,F

0+3=3

Early Finish Box

Early Start Box


Early
Start at
node 1
is zero

A
1

B
5

C
5

D
4

F
10

Make forward pass through the


network by adding duration times.

Early Start Box

2 3
A
1

3+5=8

C
5

D
4

Early Finish Box

F
10

Make forward pass through the


network by adding duration times.

2
A
1

3 8

D
4

3+4=7

F
10

Larger=7
0+4=4

If two or more activities terminate at a junction


node, place the larger sum at ES box.

2
A
1

3 8

D
4

F
10

17

26

2
A
1

3 8

D
4

F
10

17

Early finish of activity G in the node 6 =26 days. Thats means


it will take 26 days to complete the project. Therefore, 26 days
represents Late Finish of the project.
Enter 26 into Late Finish box at the node 6, and make a backward
pass to establish LF for each activity by deducting the durations.

26
26

14-5=9
2
Smaller=3

3
3

B
5

3
1

7-4=3

0
0

3 8
14

D
4

F
10

17

17

26-9=17

In the case of junction nodes (with two or more activities), place the
smaller value in the LF box of that node.

26

26

3
3

3 8
14

3
1

0
0

D
4

F
10

17

17

26

26

TFB=6

TFA = LF-D-ES
=3-3-0
=0
TFA=0
1

TFB = LF-D-ES
=14-5-3
=6

3
3

3 8
14

E TFE=0

D
4
TFD=3

TFC=6

F
10
TFF=0

Total Float (TF) =LF-D-ES

17

17

9
TFG=0

26

26

TFB=6

2
TFA=0
1

3
3

3 8
14

E TFE=0

TFC=6

D
4
TFD=3

F
10
TFF=0

Activities on critical path : A,E,F and G.

17

17

9
TFG=0

26

26

ACTIVITY

DURATION(DAY)

ES

EF

LS

LF

TF

0*

14

17

14

17

0*

10

17

17

0*

17

26

17

26

0*

* Critical Activity
Total Float (TF)

=LF-D-ES

14

17

14

17

0*

10

17

17

0*

17

26

17

26

0*

10

Duration
(days)

Activity

BAR CHART

26

25

24

23

22

0*

21

20

19

18

17

16

15

TF

14

LF

13

LS

12

EF

11

ES

10

DURATION
(DAY)

ACTIVITY

Example 2 (ADM)
Activity

Duration (day)

Predecessor (s)

Act. A

Act. B

Act. C

Act. D

Act. E

C,D

Act. F

C,D

Act. G

Act. H

1. Develop an arrow diagram for the project.


2. Identify critical activity and critical path for the project.

2
A

Activity

Duration (day)

Predecessor (s)

Act. A

Act. B

Act. C

Act. D

Act. E

C,D

Act. F

C,D

Act. G

Act. H

C
3

1
B
3

D
4

E
3

G
4
7

F
2

H
6

Forward pass

2
C

4 7

B
3

5 10

D
4

E
3

G
4
7

F
2

H
3

14

Backward pass

2
A

0
0

2
4

2
B
3

3
3
3

D
4

4 7
7

E
3

5 10
10

G
4
7

F
2

9
11

H
3

14
14

Total Float
Activity

Duration
(day)

ES

EF

LS

LF

TF

Act. A

Act. B

0*

Act. C

Act. D

0*

Act. E

10

10

0*

Act. F

11

Act. G

10

14

10

14

0*

Act. H

14

11

14

* Critical Activity

Total Float (TF)

=LF-D-ES

Critical Path

2
A

0
0

2
4

2
B
3

3
3
3

D
4

4 7
7

E
3

5 10
10

G
4
7

F
2

9
11

H
3

Activities on critical path : B,D,E and G.

Critical path

14
14

Exercise 3 (ADM)
Activity

Duration (day)

Predecessor (s)

Act. A

Act. B

Act. C

Act. D

Act. E

B,C

Act. F

Act. G

C,D

Act. H

E,F,G

Prepare a arrow diagram for the project.


Identify critical path for the project.

Exercise 3 Forward pass


B
3

5,7

9,10,11

A
2
2

F
3

6,7

D
4

11

H
2

13

Exercise 3 Backward pass


B
3

0
0

A
2
2

2
2

C
5

7
9

F
3

9,8,7

6,2,3

D
4

11

11

13
13

Exercise 3 (ADM-Solution)
B
3

0
0

A
2

2
2

C
5

7
9

F
3

D
4
Activities on critical path : A,C,G and H.

11
11

7
Critical path

H
2

13
13

Link (Relationship)
Finish to Start (FS)
Activity B cannot start until
Act. A
Activity A finish

Start to Start (SS)


Activity B cannot start until
Activity A start

Act. B

Act. A

Act. B

Link (Relationship)
Finish to Finish (FF)
Activity B cannot finish until
Activity A finish.

Act. A
Act. B

Start to Finish (SF)


Activity B cannot finish until
Activity A start.

Act. A

Act. B

Lead time & lag time


Lead time
Overlap between
dependent activity
Eg : FS 5d

Act. A

Act. B
5d

Lag time
Delay between
dependent activity
Eg: FS + 2 d

Act. A

Act. B
2d

ACTIVITY

DURATION(DAY)

PREDECESSOR

START

D,E

C(+2),F

ES

LS

Activity
LS

EXAMPLE 1

2
A

6
B

TF

LF

6
C

ACTIVITY

DURATION
(DAY)

PREDECESSOR

START

D,E

C(+2),F

FS +2

G
1
D

3
F
3
E

EXAMPLE 1
FORWARD PASS
0

2
A

6
B

6
C

14

16,12
16 2 18
G

FS +2
8

1
D

9
5,9
9

3
E

3
F

12

EXAMPLE 1
BACKWARD PASS
0

2
A

6
B

6
C

14

16,12
16 2 18
G

FS +2
8

1
D

16
5,9
9

3
E

3
F

12

16

18

EXAMPLE 1
BACKWARD PASS
0

2
A

2
2,10

6
B

6
C

14

16,12

14

8,12

16 2 18
G

FS +2
8

1
D

12

9
13

16
5,9
9

2
10

3
E

5
13

13

3
F

12

16

18

EXAMPLE 1
BACKWARD PASS
0

2
A

2
2,10

6
B

6
C

14

16,12

14

8,12

16 2 18
G

FS +2
8

1
D

12

9
13

16
5,9
9

2
10

3
E

5
13

13

3
F

12

16

18

EXAMPLE 1
COMPLETED
0
0

2
A

2,10

6
B

6
C

14
16,12

14

8,12

16 2

FS +2

18

G
8

1
D

12

9
13

16

5,9
9

2
10

3
E

5
13

13

3
F

12
16

18

EXAMPLE 1
127

TOTAL FLOAT

TFC

2
A

6
B

6
C

14

14

= LF-EF
=14-14
=0

TFG
=0

16 2

FS +2
TFB

TFA

= LF-EF
=2-2
=0

= LF-EF
=8-8
=0

1
D

12

13

TFD = LF-EF
=13-9
=4

2
10

3
E

8 13

16

3
F

13

TFE = LF-EF

=13-5
=8

= LF-EF
=18-18

12
16

18

G
0 18

TFF = LF-EF
=16-12
=4

EXAMPLE 1
128

FREE FLOAT
0
0

2
A

2
2

6
B

8
8

6
C

14

14

FFC
Lag

= ESSUCC-EF=16-14-2
=0

16 2

FS +2
FFA = ESSUCC-EFLag
=2-2-0
=0

FFB
Lag

= ESSUCC-EF=8-8-0
=0

FFD
Lag

1
D

12

13

FFF = ESSUCC-EFLag
=16-12-0
=4

= ESSUCC-EF=9-9-0
=0

2
10

3
E

8 13

13

3
F
4

16

18

G
0 18

12
FFA

16

= ESSUCCEF- Lag
=18-18-

0
=0

EXAMPLE 1
CRITICAL PATH
0

2
A

6
B

6
C

14

14

2,10

16,12

8,12

16 2

FS +2
8

1
D

12

13

2
10

3
E

8 13

16

5,9
9

3
F

13

12
16

18

G
0 18

Example 2 (PDM)
Activity

Duration (day)

Predecessor (s)

Act. A

10

Act. B

11

Act. C

Act. D

Act. E

12

Act. F

C,D

Act. G

Act. H

11

Act. I

G,H

1. Develop a precedence diagram for the project.


2. Identify critical activity and critical path for the project.

Example 2 (PDM)
5

11

D
10

12

11

H
ES

LS

Activity
LS

TF

LF

Example 2 (PDM-forward pass)


21
10

11

26

21

26

29

36

F
21

29

25

D
0

10

10

36

10

12

22

22

11

33

H
ES

LS

Activity
LS

TF

LF

40

Example 2 (PDM-backward pass)


21
10

11

26

21

21

B
10

21
21

26
26

29

29

36

F
26

25

29

29

36

D
0

10

10

22

36

26

A
0

40

I
10

36

10

12

22

22

33

E
13

11

40

25

25

36
ES

LS

Activity
LS

TF

LF

Example 2 (PDM-Total float)


21
10

11

26

21

21

B
10

21
21

26
26

29

29

26

36

25

29

29

36

D
0

10

10

22

36

26

A
0

40

I
10

10

12

22

22

or

LS

33

25

25

36
ES

TF = LF ES D

E
13

11

36

TF = LS ES

or

TF = LF EF
Critical path

Activity
LS

TF

LF

40

Example 3 (PDM)
Activity

Duration (week)

Predecessor (s)

Act. A

Act. B

A (FS+2),
C (FF+1),
D(FF)

Act. C

Act. D

C (SS)

1. Develop a precedence diagram for the project.


2. Identify critical activity and critical path for the project.

Example 3 (PDM-forward pass)


4

+2
0

A
2

+1

Example 3 (PDM-backward pass)


4

+2
2

B
4

A
0

C
4

+1

Total Float = LF ES D
TF(A) = 2-0-2 = 0
TF(B) = 7-4-3 = 0
TF(C) = 6-2-2 = 2
TF(D) = 7-2-1 = 4

D
6

Critical path

Exercise 4(PDM)
Activity

Duration (day)

Predecessor (s)

Act. A

Act. B

Act. C

Act. D

Act. E

B,C

Act. F

Act. G

C,D

Act. H

E,F,G

Prepare a precedence diagram for the project.


Identify critical path for the project.

Exercise (PDM-Solution)
3

B
6

A
0

11

10

11

11

13

D
3

11

C
2

11

11

13

BUT WAIT!!
Are there any other type of Scheduling
method??
How if the Gantt Chart and CPM did not
actually work/represent well with the
nature/requirement of the particular
construction project??

So, actually we have LINEAR SCHEDULING


METHOD (LSM) / LINE OF BALANCE (LOB)

This method is actually appropriate for a


project that:
Progress linearly (straight without major
fluctuation of activities),
Highly repetitive works,
Have fixed starting point and end,
Such as; highways, airfields, pipelines, multiple
housing units, high-rise buildings, etc.

LINEAR SCHEDULING METHOD (LSM) (cont.)


Take for example; a highway construction
project:

LINEAR SCHEDULING METHOD (LSM)


(cont.)

Kilometer (km)

We have 5 linear
activities:
1.
Clear & strip
2.
Drainage
3.
Subgrade
4.
Base course
5.
Pave
Width of B:
At 40km, the subgrade
works will starts at week
4.4 until week 5.
Height of A:
At week 3, subgrade
works from 13km to
21km.

LSM Diagram for highway project (adopted from Nunnally, 2014)

Distance of C:
It is a time lag / time
float for 10km; between
subgrade works and base
course works.
1.4 weeks to be exact.

ACTIVITY
A
B
C
D
E
F
G
H
I
J
K
L
M

PREDECESSOR
A
B
C
D
D,E
D,E,F
G
H
I
J,K,L

DURATION (WEEK)
3
1
2
3
1
4
2
1
2
3
2
1
2

QUESTION 2
A project have a detail as below:
1. Draw the precedence diagram for the schedule shown next.
2. Determine the duration of project required.
3. Determine the Total Float for each activities and give the critical path for this project.
4. Draw a bar chart.

ACTIVITY
A
B
C
D
E
F

SUCESSOR
A-B (S-S),L=5
A-C (F-S),L=2
B-E (F-S),L=3
C-E (F-S),L=0
D-E (F-S),L=0
E-F (F-S),L=0

DURATION
(WEEK)
3
1
2
2
3
2

1. Draw the precedence diagram for the schedule shown next.


2. Determine the duration of project required.
3. Determine the Total Float for each activities and give the critical path for
this project.
4. Draw a bar chart.

Duration
(week)
5

2
3

B
C

4
3

E
F, G

4
5

D
E

2
7

H
F, G

6
7
8
9

F
G
H
I

2
5
3
6

I
I
I
-

No. Activity

Successor

Relationship

B, C, D

AB (SS)
AC (FS)
AD (FS)
BE (FS)
CF (FS)
CG (FS)
DH (FS)
EF (FS)
EG (FS)
FI (FS)
GI (FS)
HI (FS)
-

1. Estimate the total project duration.


2. Calculate the total float for each activity in the project.
3. State the critical path.

Lag
(week)
1
2
0
0
0
0
0
0
0
0
0
3
-

Вам также может понравиться