Академический Документы
Профессиональный Документы
Культура Документы
Introduction
Planning & Scheduling
Principles
Techniques
Work breakdown structure
Gantt Chart & S-Curve
Critical Path Method
Successor/ predecessor relationship
Arrow Diagram Method and
Precedence Diagram Method
Traditional Projects Critical Components (time, cost, & quality); in relation with
sustainable construction concept
Introduction
Project planning
Process of identifying all the activities necessary
to successfully complete the project.
Provides map to guide where to go and focused
on how to get there
Planned in early stage of Project life Cycle or also
before site activities start.
Introduction
Importance of planning
Reduce mistake and rework
Avoid wastage
minimize unnecessary in time and cost scheduling
better quality control
Effective project progress control
Effective usage resources
Introduction
Project scheduling
Process of determining the sequential order of the
planned activities, assigning realistic durations to
each activity and determining the start and finish
dates for each activities.
it can be used to manage, coordinate, control and
report.
Depending on the sophistication of the user, the
schedule can take different forms.
Project Scheduling
Purpose of project scheduling
Claim
Project time and cost control
Allocate project resources more efficiently
As a monitoring tool
Material delivery at site
Storage all material cannot put in the site (confined space)
Avoid delay of the work and activity.
Minimize the cash flow as min as possible such as order material
stage by stage depend on the work needed.
Control human resources and machinery To improve the efficiency
of the operation through the efficient use of resources and cost
control.
Client Satisfaction
COST
TIME
QUALITY
20
18
16
14
12
10
8
6
4
2
0
RESOURCES
SCOPE
Time &
Resource
Management
Activity
Sequencing
Schedule
development
Create WBS
Scope
Activity
resource
planning
Cost Estimating
Activity
Duration
Estimation
Cost Budgeting
Management
Cost
Management
Level 2
Start Project
Preliminaries
Block A
Level 3
Performance
bond
Earthwork
Establish and
removal of site
office
Structure Work
Architecture
Work
M&E work
Testing &
Commissioning
Project
complete
Testing and
Commissioning
Project complete
Building
works
Structure
Architecture
External
works
M&E
Sewerage
Foundation
Wall
Wiring
Road and
drainage
Ground level
Floor
Fittings
installation
Landscape
Roof
2nd floor
level
Fittings
Level
4
Projects size
Complexity
Duration
Personnel
Owner requirements
Advantages
Disadvantages
Easy to interpret
Simplicity & ease of preparation and
understanding (Simple graphical).
No theory or complicated calculation
involved (Easy for general
comprehension).
Time-scaled (the length of the bar
representing certain activity is
proportional to the duration of that
activity.
Appeal to persons who do not have a
technical background
Wide spread used in industry
Mostly used in small project
Fairly broad planning and scheduling
tools, so they require less revision
and updating than more
sophisticated systems
Difficult to update
Very cumbersome as the
number of line activities, or bars
increases
Does not integrate costs or
resources with the schedule
Limited application for detail
construction work
Difficult to use it for forecasting
the effects that changes in a
particular activity will have on
the overall schedule
Description
Month
1
Mobilization
Foundation Excavation
Diversion Stage
Foundation Grouting
Dam Concrete
Prestress
Radial Gates
10
Spillway Bridge
11
Curtain Grout
12
10
Original Schedule
Actual progress
Month
1
Mobilization
Foundation Excavation
Diversion Stage
Foundation Grouting
Dam Concrete
Prestress
Radial Gates
10
Spillway Bridge
11
Curtain Grout
12
10
100
Original Schedule
Actual progress
No.
Activity A
Activity B
Activity C
Activity D
Activity E
(1/6-7/6)
(8/6-21/6)
(15/6-5/7)
(22/6-5/7)
(29/6-12/7)
Duration
(week)
Week 1
1/6
Act. A
Act. B
Act. C
Act. D
Act. E
Week 2
8/6
Week 3
15/6
Week 4
22/6
Week 5
29/6
Week 6
6/7
Activity A
Activity B
Activity C
Activity D
Activity E
Activity
Duration
(week)
Week 1
1/6
Act. A
Act. B
Act. C
Act. D
Act. E
Week 2
8/6
Week 3
15/6
Week 5
29/6
Week 6
6/7
Activity
Duration
(days)
Start Date
Cost (RM)
Resources/
day
(person)
Work
progress
percentage
(%)
Activity A
4/5/2014
1,400.00
12
Activity B
7/5/2014
2,700.00
30
Activity C
10/5/2014
3,500.00
21
Activity D
15/5/2014
6,000.00
10
Activity E
17/5/2014
4,700.00
12
Activity F
19/5/2014
12,600.00
15
30,900.00
100
(4/5-6/5)
(7/5-11/5)
(10/5-16/5)
(15/5-19/5)
(17/5-20/5)
(19/5-24/5)
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
Act. F
16/5
15/5
Act. E
14/5
13/5
Act. D
12/5
11/5
Act. C
10/5
9/5
Act. B
8/5
7/5
Act. A
6/5
Duration
(days)
5/5
Activity
4/5
24/5
23/5
22/5
21/5
20/5
19/5
18/5
Act. F
17/5
16/5
Act. E
15/5
14/5
Act. D
: (4/5-6/5)
: (7/5-11/5)
: (10/5-16/5)
: (15/5-19/5)
: (17/5-20/5)
: (19/5-24/5)
13/5
12/5
Act. C
11/5
9/5
Act. B
8/5
7/5
Act. A
6/5
Duration
(days)
5/5
Activity
4/5
10/5
Activity A
Activity B
Activity C
Activity D
Activity E
Activity F
S-Curve
Type of S-Curve
Physical S-Curve
Financial S-Curve
S-Curve (Example)
Num
Activity
Duration
(days)
Start Date
Cost (RM)
Resources/
day
(person)
Work
progress
percentage
(%)
Activity A
4/5/2014
1,400.00
12
Activity B
7/5/2014
2,700.00
30
Activity C
10/5/2014
3,500.00
21
Activity D
15/5/2014
6,000.00
10
Activity E
17/5/2014
4,700.00
12
Activity F
19/5/2014
12,600.00
15
30,900.00
Based on bar chart in Example 2, construct S-curve (daily basis) for this project:
1. Financial S-Curve
2. Physical S-curve (resources vs time & work vs time)
100
Financial S-Curve
Financial S-Curve
12,600
Cost/day
Cumulative cost/day
24/5
23/5
Act. F
22/5
4,700
21/5
20/5
Act. E
19/5
6,000
18/5
17/5
Act. D
16/5
3,500
15/5
14/5
Act. C
13/5
2,700
12/5
11/5
Act. B
10/5
1,400
9/5
8/5
Act. A
Cost/day
(RM)
7/5
Cost
(RM)
6/5
Duration
(days)
5/5
Activity
4/5
STEP 1: DRAW BAR CHART (from Example 2), include Cost of each activity
Financial S-Curve
Act. A
Act. B
Act. C
Act. D
Act. E
Act. F
1,400
=1,400/3
467
5
2,700 =2,700/5
540
7
3,500 =3,500/7
500
5
6,000 =6,000/5
1200
4
4,700 =4,700/4
1175
6
12,600 =12,600/6
2100
Cost/day
Cumulative cost/day
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
12/5
11/5
10/5
9/5
8/5
Cost/day
(RM)
7/5
Cost
(RM)
6/5
Duration
(days)
5/5
Activity
4/5
Financial S-Curve
12,600
2100
Cumulative cost/day
24/5
Act. F
23/5
1175
22/5
4,700
21/5
20/5
Act. E
1200
19/5
6,000
18/5
17/5
Act. D
500
16/5
3,500
15/5
14/5
Act. C
540
13/5
2,700
12/5
11/5
Act. B
467
10/5
1,400
9/5
8/5
Act. A
Cost/day
Cost/day
(RM)
7/5
Cost
(RM)
6/5
Duration
(days)
5/5
Activity
4/5
Financial S-Curve
540
3,500
Act. D
6,000
Act. E
4,700
1175
Act. F
12,600
2100
Cumulative cost/day
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
467
Act. C
Cost/day
12/5
2,700
11/5
10/5
Act. B
9/5
1,400
8/5
7/5
Act. A
Cost/day
(RM)
6/5
Cost
(RM)
5/5
Duration
(days)
540 +500
500
1200
467
467
467
540
540
540
1040
1040
500
500
500
1700
1700
2375
2375
4475
3275
2100
2100
2100
2100
Activity
4/5
Financial S-Curve
Act. F
12,600
2100
24/5
1175
23/5
4,700
22/5
21/5
Act. E
20/5
6,000
19/5
18/5
Act. D
17/5
3,500
16/5
15/5
Act. C
14/5
2,700
13/5
12/5
Act. B
11/5
1,400
10/5
9/5
Act. A
8/5
Cost/day
(RM)
7/5
Cost
(RM)
6/5
Duration
(days)
5/5
Activity
4/5
467
540
500
Cost/day
467
467
467
540
540
540
1040
1040
500
500
500
1700
1700
2375
2375
4475
3275
2100
2100
2100
2100
Cumulative cost/day
467
934
1041
1941
2481
3021
4061
5101
5601
6101
6601
8301
1001
12376
14751
19226
22501
24601
26701
28801
30901
1200
Cumulative
cost cost
(previous)
+ current
cost/day
Cumulative
(previous)
+ current
cost/day
= 467= +934
467+ 467
Financial S-Curve
Total cumulative cost
Act. A
Act. B
Act. C
Act. D
5
7
1,400
2,700
3,500
12,600
Start from 0
Cost/day
Cumulative cost/day
24/5
23/5
20600
500
1175
15450
10300
467
1041
934
5150
2100
Start from 0
467
467
467
540
540
540
1040
1040
500
500
500
1700
1700
2375
2375
4475
3275
2100
2100
2100
2100
22/5
540
6,000
4,700
21/5
25750
467
934
1041
1941
2481
3021
4061
5101
5601
6101
6601
8301
10001
12376
14751
19226
22501
24601
26701
28801
30901
Act. F
30900
467
1200
Act. E
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
12/5
11/5
10/5
9/5
8/5
Cost/da y
(RM)
7/5
Cost
(RM)
6/5
Duration
(days)
5/5
Activity
4/5
Financial S-Curve
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
12/5
11/5
10/5
9/5
8/5
Cost/da y
(RM)
7/5
Cost
(RM)
6/5
Duration
(days)
5/5
Activity
4/5
30900
Act. A
Act. B
Act. C
Act. D
5
7
1,400
2,700
3,500
467
25750
540
20600
500
15450
6,000
1200
4,700
12,600
1175
5150
2100
0
Cost/day
467
467
467
540
540
540
1040
1040
500
500
500
1700
1700
2375
2375
4475
3275
2100
2100
2100
2100
Act. F
Cumulative cost/day
467
934
1041
1941
2481
3021
4061
5101
5601
6101
6601
8301
10001
12376
14751
19226
22501
24601
26701
28801
30901
Act. E
10300
Physical S-Curve
(resources VS time)
Num
Activity
Duration
(days)
Start Date
Cost (RM)
Resources/
day
(person)
Work
progress
percentage
(%)
Activity A
4/5/2014
1,400.00
12
Activity B
7/5/2014
2,700.00
30
Activity C
10/5/2014
3,500.00
21
Activity D
15/5/2014
6,000.00
10
Activity E
17/5/2014
4,700.00
12
Activity F
19/5/2014
12,600.00
15
30,900.00
100
Resource/day
Cumulative resource/day
24/5
23/5
22/5
21/5
20/5
Act. F
19/5
18/5
17/5
Act. E
16/5
15/5
14/5
Act. D
13/5
12/5
2
2
2
6
6
8
8
13
9
5
5
5
5
Act. C
11/5
10/5
Act. B
9/5
8/5
7/5
Act. A
6/5
Resource/
day
5/5
Duration
(days)
4/5
Activity
2
2
2
3
3
3
5
STEP 1: DRAW BAR CHART (from Example 2), include resource/day for each activity
23/5
22/5
21/5
Act. F
20/5
19/5
18/5
Act. E
17/5
16/5
15/5
Act. D
14/5
13/5
12/5
Act. C
11/5
10/5
9/5
Act. B
8/5
7/5
6/5
Act. A
5/5
Resource/
day
Resource/day
2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5
Duration
(days)
Cumulative resource/day
2
4
6
9
12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
101
Activity
4/5
23/5
22/5
21/5
Act. F
20/5
19/5
18/5
Act. E
17/5
16/5
15/5
Act. D
14/5
13/5
12/5
Act. C
11/5
10/5
9/5
Act. B
8/5
7/5
6/5
Act. A
5/5
Resource/
day
Resource/day
2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5
Duration
(days)
Cumulative resource/day
2
4
6
9
12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
101
Activity
4/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
12/5
11/5
10/5
9/5
8/5
7/5
Resource/
day
6/5
Duration
(days)
5/5
Activity
4/5
Act. B
Act. C
Act. D
Act. E
Act. F
5
7
5
4
6
102
85
68
51
4
102/6 x 2 = 34
34
102/6 = 17
17
4
5
Resource/day
2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5
Cumulative resource/day
2
4
6
9
12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
101
Start from 0
Act. A
Act. B
Act. C
Act. D
Act. E
5
7
5
4
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
12/5
11/5
10/5
9/5
8/5
7/5
102
85
68
51
34
17
Resource/day
2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5
6/5
Resource/
day
Cumulative resource/day
2
4
6
9
12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
101
Act. F
Duration
(days)
5/5
Activity
4/5
Physical S-Curve
(work VS time)
Num
Activity
Duration
(days)
Start Date
Cost (RM)
Resources/
day
(person)
Work
progress
percentage
(%)
Activity A
4/5/2014
1,400.00
12
Activity B
7/5/2014
2,700.00
30
Activity C
10/5/2014
3,500.00
21
Activity D
15/5/2014
6,000.00
10
Activity E
17/5/2014
4,700.00
12
Activity F
19/5/2014
12,600.00
15
30,900.00
100
Physical
S-Curve
(work
VS
time)
STEP 1: DRAW BAR CHART (from Example 2), include work progress
15
Work progress/day
Cumulative work progress/day
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
Act. F
12
16/5
15/5
Act. E
10
14/5
13/5
Act. D
21
12/5
11/5
Act. C
30
10/5
9/5
Act. B
12
8/5
7/5
Act. A
Work
progress
percentage
(%)
6/5
Duration
(days)
5/5
Activity
4/5
15
Work progress/day
Cumulative work progress/day
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
Act. F
12
16/5
15/5
Act. E
10
14/5
13/5
Act. D
21
12/5
11/5
Act. C
30
10/5
4 4 4
9/5
Act. B
12
8/5
7/5
Act. A
Work
progress
percentage
(%)
6/5
Duration
(days)
5/5
Activity
4/5
Physical
S-Curve
(work
VS
time)
STEP 2: Calculate work progress percentage of each day for every activities
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
12
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
12/5
11/5
10/5
9/5
8/5
7/5
Act. A
Work
progress
percentage
(%)
6/5
Duration
(days)
5/5
Activity
4/5
4 4 4
6 +3
5
Act. C
Act. D
Act. E
Act. F
30
21
10
12
15
Work progress/day
Cumulative work progress/day
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5
Act. B
15
Work progress/day
Cumulative work progress/day
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
Act. F
12
15/5
14/5
Act. E
10
13/5
12/5
Act. D
21
11/5
10/5
Act. C
30
9/5
8/5
Act. B
12
7/5
6/5
Act. A
Work
progress
percentage
(%)
5/5
Duration
(days)
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5
Activity
4/5
15
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
Act. F
12
14/5
13/5
Act. E
10
12/5
11/5
Act. D
21
10/5
9/5
Act. C
30
8/5
7/5
Act. B
12
6/5
5/5
Act. A
Work
progress
percentage
(%)
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
Work progress/day
4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5
Duration
(days)
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100
Activity
4/5
15
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
Act. F
12
14/5
13/5
Act. E
10
12/5
11/5
Act. D
21
10/5
9/5
Act. C
30
8/5
7/5
Act. B
12
6/5
5/5
Act. A
Work
progress
percentage
(%)
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
Work progress/day
4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5
Duration
(days)
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100
Activity
4/5
Act. A
Act. B
Act. C
Act. E
Act. F
30
21
10
12
15
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
12/5
11/5
10/5
9/5
8/5
7/5
4 4 4
75
6 6 6 6 6
3 3 3 3 3 3 3
50
2 2 2 2 2
3 3 3 3
25
Work progress/day
4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5
12
100
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100
Act. D
Work
progress
percentage
(%)
6/5
Duration
(days)
5/5
Activity
4/5
Act. A
Act. B
Act. C
Act. E
Act. F
30
21
10
12
15
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
12/5
11/5
10/5
9/5
8/5
7/5
4 4 4
75
6 6 6 6 6
3 3 3 3 3 3 3
50
2 2 2 2 2
3 3 3 3
25
Work progress/day
4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5
12
100
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100
Act. D
Work
progress
percentage
(%)
6/5
Duration
(days)
5/5
Activity
4/5
Act. A
Act. B
Act. C
Act. E
Act. F
30
21
10
12
15
24/5
23/5
22/5
21/5
20/5
19/5
18/5
17/5
16/5
15/5
14/5
13/5
12/5
11/5
10/5
9/5
8/5
7/5
4 4 4
75
6 6 6 6 6
3 3 3 3 3 3 3
50
2 2 2 2 2
3 3 3 3
25
Work progress/day
4
4
4
6
6
6
9
9
3
3
3
5
5
5
5
7.5
5.5
2.5
2.5
2.5
2.5
12
100
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84.5
90
92.5
95
97.5
100
Act. D
Work
progress
percentage
(%)
6/5
Duration
(days)
5/5
Activity
4/5
Activity
Duration
(days)
Start Date
Actual Start
Date
Actual Finish
Date
Cost (RM)
Resources
(person)
Activity A
4/5/2014
4/5/2014
6/5/2014
1,400.00
Activity B
7/5/2014
7/5/2014
12/5/2014
2,700.00
Activity C
10/5/2014
11/5/2014
17/5/2014
3,500.00
Activity D
15/5/2014
17/5/2014
21/5/2014
6,000.00
Activity E
17/5/2014
18/5/2014
22/5/2014
4,700.00
Activity F
19/5/2014
21/5/2014
26/5/2014
12,600.00
30,900.00
Start
Date
Actual
Start
Date
Actual
Finish
Date
Act. A
4/5/14
4/5/14
6/5/14
Act. B
7/5/14
7/5/14
12/5/14
Act. C
10/5/14
11/5/14
17/5/14
Act. D
15/5/14
17/5/14
21/5/14
Act. E
17/5/14
18/5/14
22/5/14
Act. F
19/5/14
21/5/14
26/5/14
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
Planning
Actual
Start
Date
Actual
Start
Date
Actual
Finish
Date
Act. A
4/5/14
4/5/14
6/5/14
Act. B
7/5/14
7/5/14
12/5/14
Act. C
10/5/14
11/5/14
17/5/14
Act. D
15/5/14
17/5/14
21/5/14
Act. E
17/5/14
18/5/14
22/5/14
Act. F
19/5/14
21/5/14
26/5/14
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
Start
Date
Actual
Start
Date
Actual
Finish
Date
Act. A
4/5/14
4/5/14
6/5/14
Act. B
7/5/14
7/5/14
12/5/14
Act. C
10/5/14
11/5/14
17/5/14
Act. D
15/5/14
17/5/14
21/5/14
Act. E
17/5/14
18/5/14
22/5/14
Act. F
19/5/14
21/5/14
26/5/14
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30
1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32
Start
Date
Actual
Start
Date
Actual
Finish
Date
Act. A
4/5/14
4/5/14
6/5/14
Act. B
7/5/14
7/5/14
12/5/14
Act. C
10/5/14
11/5/14
17/5/14
Act. D
15/5/14
17/5/14
21/5/14
Act. E
17/5/14
18/5/14
22/5/14
Act. F
19/5/14
21/5/14
26/5/14
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30
1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32
Start
Date
Actual
Start
Date
Actual
Finish
Date
Act. A
4/5/14
4/5/14
6/5/14
Act. B
7/5/14
7/5/14
12/5/14
Act. C
10/5/14
Act. D
15/5/14
Act. E
Act. F
11/5/14
17/5/14
17/5/14
21/5/14
17/5/14
18/5/14
22/5/14
19/5/14
21/5/14
26/5/14
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
Planning
Actual
1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30
1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32
Network Diagram
Activity on Arrow (AOA)/ Arrow Diagram
Method (ADM)
In arrow diagram project task or activities are
represented by the arrow and connected by the node
to express their logical relationship
Node represents an event. An activity starts or ends at
a node.
Activity A
Node
Activity B
Node
Node
ADM
Diagram for construction of pad footing
Fabricated rebar
Excavate
trench
Fixed fwk
Fabricated formwork
Fixed rebar
Pour concrete
Network Diagram
Activity on Node (AON)/ Precedence Diagram
Method (PDM)
activity is place on the node
The arrow used to connect between project task
to show their logical relationship
Act. A
Node
Act. B
Node
Network Diagram
Diagram for construction of pad footing
Arrow
Node
Logical
- Logical
- Activity
Show the relationship
between activities
- Sequences of interrelated
activity
Activity Sequencing
Understand the order of how the job to be
accomplished in the field.
The planner must understand how various
activities of the project related to each other
in term of their logical sequence.
Example preparing formwork before
reinforcement could be place & than pouring
concrete.
Activity Sequencing
Predecessor
A task whose start or finish date determines the
start or finish date of its successor task.
Successor
A task whose start or finish date is driven by its
predecessor task.
ADM
PDM
ES
LS
Activity
ES
1
LS
Event/ Node
2 events / nodes
D
A
TF
EF
LF
ES
EF
2
LF
LS
D
A
TF
1 event
EF
LF
ES
LS
D
B
TF
EF
LF
PDM
Early Start (ES) is the earliest possible time an activity can start.
Early Finish (EF) is the earliest possible time an activity can finish if it
is start on Early Start Time (ES) and finish within the planned duration.
EF = ES + D
*D = duration
or
TF = LS ES
or
TF = LF EF
PDM
Activity Nodes
ES
LS
D
A
TF
EF
LF
Predecessor
Activity
ES
LS
D
B
TF
EF
LF
Current
Activity
ES
LS
D
B
TF
EF
LF
Successor
Activity
ADM
F S
Relationshi
p
Critical
path
PDM
F
F
S
S
S
F
S
F
Critical Path
A series of interconnected activities through the network
diagram, with each activity having zero total float time. The
critical path determines the minimum time to complete the
project.
1.
2.
3.
ESX = LSX, or
LFX = EFX, or
Total Float (TF) = 0
ADM
PDM
Definition
Dummy
Activity
D
or
An activity that
If there is a situation
in Precedence Diagram
Method (PDM)
ADM
Item
ADM
Activity A & B have the same
ID
A: 1-2
B: 1-2
False
Dummy
Activity
D
or
True
A
1
2
If C is to follow A & B,
but D is to follow only B.
(not fulfill)
If C is to follow A & B,
but D is to follow only B.
(use dummy)
Item
ADM
If P, Q and R follow A, and B follows P, Q and R. The following diagram is not the
correct representation of the same.
False
Dummy
Activity
R
Reason: Activities P, Q and R have the same ID (2-3).
True
P
or
1
5
Q
2
R
Item
ADM
1.
2.
3.
D is preceded by A only
E is preceded by A and B
F is preceded by B and C
Dummy
Activity
False
True
or
E
F
ADM
-
PDM
FORWARD PASS
Estimating
duration
BACKWARD PASS
FORWARD PASS
Early
Start
Early
Finish
Late
Start
Late
Finish
BACKWARD
92 PASS
93
Note
Forward pass
c = a + X
a
1 b
c
2 d
e = c + Y
B
Y
e
3
f
a
b
c
d
e
f
X
Y
:
:
:
:
:
:
:
:
d = f Y
Backward pass
Forward pass
a = 0
c = a + X
e = c + Y
Backward pass
f = e
d = f Y
b = d - X
ACTIVITY
DURATION(DAY)
PREDECESSOR
10
E,D
C,F
2
A
C
5
D
4
F
10
ACTIVITY
DURATION
(DAY)
PREDECESSOR
10
E,D
C,F
0+3=3
A
1
B
5
C
5
D
4
F
10
2 3
A
1
3+5=8
C
5
D
4
F
10
2
A
1
3 8
D
4
3+4=7
F
10
Larger=7
0+4=4
2
A
1
3 8
D
4
F
10
17
26
2
A
1
3 8
D
4
F
10
17
26
26
14-5=9
2
Smaller=3
3
3
B
5
3
1
7-4=3
0
0
3 8
14
D
4
F
10
17
17
26-9=17
In the case of junction nodes (with two or more activities), place the
smaller value in the LF box of that node.
26
26
3
3
3 8
14
3
1
0
0
D
4
F
10
17
17
26
26
TFB=6
TFA = LF-D-ES
=3-3-0
=0
TFA=0
1
TFB = LF-D-ES
=14-5-3
=6
3
3
3 8
14
E TFE=0
D
4
TFD=3
TFC=6
F
10
TFF=0
17
17
9
TFG=0
26
26
TFB=6
2
TFA=0
1
3
3
3 8
14
E TFE=0
TFC=6
D
4
TFD=3
F
10
TFF=0
17
17
9
TFG=0
26
26
ACTIVITY
DURATION(DAY)
ES
EF
LS
LF
TF
0*
14
17
14
17
0*
10
17
17
0*
17
26
17
26
0*
* Critical Activity
Total Float (TF)
=LF-D-ES
14
17
14
17
0*
10
17
17
0*
17
26
17
26
0*
10
Duration
(days)
Activity
BAR CHART
26
25
24
23
22
0*
21
20
19
18
17
16
15
TF
14
LF
13
LS
12
EF
11
ES
10
DURATION
(DAY)
ACTIVITY
Example 2 (ADM)
Activity
Duration (day)
Predecessor (s)
Act. A
Act. B
Act. C
Act. D
Act. E
C,D
Act. F
C,D
Act. G
Act. H
2
A
Activity
Duration (day)
Predecessor (s)
Act. A
Act. B
Act. C
Act. D
Act. E
C,D
Act. F
C,D
Act. G
Act. H
C
3
1
B
3
D
4
E
3
G
4
7
F
2
H
6
Forward pass
2
C
4 7
B
3
5 10
D
4
E
3
G
4
7
F
2
H
3
14
Backward pass
2
A
0
0
2
4
2
B
3
3
3
3
D
4
4 7
7
E
3
5 10
10
G
4
7
F
2
9
11
H
3
14
14
Total Float
Activity
Duration
(day)
ES
EF
LS
LF
TF
Act. A
Act. B
0*
Act. C
Act. D
0*
Act. E
10
10
0*
Act. F
11
Act. G
10
14
10
14
0*
Act. H
14
11
14
* Critical Activity
=LF-D-ES
Critical Path
2
A
0
0
2
4
2
B
3
3
3
3
D
4
4 7
7
E
3
5 10
10
G
4
7
F
2
9
11
H
3
Critical path
14
14
Exercise 3 (ADM)
Activity
Duration (day)
Predecessor (s)
Act. A
Act. B
Act. C
Act. D
Act. E
B,C
Act. F
Act. G
C,D
Act. H
E,F,G
5,7
9,10,11
A
2
2
F
3
6,7
D
4
11
H
2
13
0
0
A
2
2
2
2
C
5
7
9
F
3
9,8,7
6,2,3
D
4
11
11
13
13
Exercise 3 (ADM-Solution)
B
3
0
0
A
2
2
2
C
5
7
9
F
3
D
4
Activities on critical path : A,C,G and H.
11
11
7
Critical path
H
2
13
13
Link (Relationship)
Finish to Start (FS)
Activity B cannot start until
Act. A
Activity A finish
Act. B
Act. A
Act. B
Link (Relationship)
Finish to Finish (FF)
Activity B cannot finish until
Activity A finish.
Act. A
Act. B
Act. A
Act. B
Act. A
Act. B
5d
Lag time
Delay between
dependent activity
Eg: FS + 2 d
Act. A
Act. B
2d
ACTIVITY
DURATION(DAY)
PREDECESSOR
START
D,E
C(+2),F
ES
LS
Activity
LS
EXAMPLE 1
2
A
6
B
TF
LF
6
C
ACTIVITY
DURATION
(DAY)
PREDECESSOR
START
D,E
C(+2),F
FS +2
G
1
D
3
F
3
E
EXAMPLE 1
FORWARD PASS
0
2
A
6
B
6
C
14
16,12
16 2 18
G
FS +2
8
1
D
9
5,9
9
3
E
3
F
12
EXAMPLE 1
BACKWARD PASS
0
2
A
6
B
6
C
14
16,12
16 2 18
G
FS +2
8
1
D
16
5,9
9
3
E
3
F
12
16
18
EXAMPLE 1
BACKWARD PASS
0
2
A
2
2,10
6
B
6
C
14
16,12
14
8,12
16 2 18
G
FS +2
8
1
D
12
9
13
16
5,9
9
2
10
3
E
5
13
13
3
F
12
16
18
EXAMPLE 1
BACKWARD PASS
0
2
A
2
2,10
6
B
6
C
14
16,12
14
8,12
16 2 18
G
FS +2
8
1
D
12
9
13
16
5,9
9
2
10
3
E
5
13
13
3
F
12
16
18
EXAMPLE 1
COMPLETED
0
0
2
A
2,10
6
B
6
C
14
16,12
14
8,12
16 2
FS +2
18
G
8
1
D
12
9
13
16
5,9
9
2
10
3
E
5
13
13
3
F
12
16
18
EXAMPLE 1
127
TOTAL FLOAT
TFC
2
A
6
B
6
C
14
14
= LF-EF
=14-14
=0
TFG
=0
16 2
FS +2
TFB
TFA
= LF-EF
=2-2
=0
= LF-EF
=8-8
=0
1
D
12
13
TFD = LF-EF
=13-9
=4
2
10
3
E
8 13
16
3
F
13
TFE = LF-EF
=13-5
=8
= LF-EF
=18-18
12
16
18
G
0 18
TFF = LF-EF
=16-12
=4
EXAMPLE 1
128
FREE FLOAT
0
0
2
A
2
2
6
B
8
8
6
C
14
14
FFC
Lag
= ESSUCC-EF=16-14-2
=0
16 2
FS +2
FFA = ESSUCC-EFLag
=2-2-0
=0
FFB
Lag
= ESSUCC-EF=8-8-0
=0
FFD
Lag
1
D
12
13
FFF = ESSUCC-EFLag
=16-12-0
=4
= ESSUCC-EF=9-9-0
=0
2
10
3
E
8 13
13
3
F
4
16
18
G
0 18
12
FFA
16
= ESSUCCEF- Lag
=18-18-
0
=0
EXAMPLE 1
CRITICAL PATH
0
2
A
6
B
6
C
14
14
2,10
16,12
8,12
16 2
FS +2
8
1
D
12
13
2
10
3
E
8 13
16
5,9
9
3
F
13
12
16
18
G
0 18
Example 2 (PDM)
Activity
Duration (day)
Predecessor (s)
Act. A
10
Act. B
11
Act. C
Act. D
Act. E
12
Act. F
C,D
Act. G
Act. H
11
Act. I
G,H
Example 2 (PDM)
5
11
D
10
12
11
H
ES
LS
Activity
LS
TF
LF
11
26
21
26
29
36
F
21
29
25
D
0
10
10
36
10
12
22
22
11
33
H
ES
LS
Activity
LS
TF
LF
40
11
26
21
21
B
10
21
21
26
26
29
29
36
F
26
25
29
29
36
D
0
10
10
22
36
26
A
0
40
I
10
36
10
12
22
22
33
E
13
11
40
25
25
36
ES
LS
Activity
LS
TF
LF
11
26
21
21
B
10
21
21
26
26
29
29
26
36
25
29
29
36
D
0
10
10
22
36
26
A
0
40
I
10
10
12
22
22
or
LS
33
25
25
36
ES
TF = LF ES D
E
13
11
36
TF = LS ES
or
TF = LF EF
Critical path
Activity
LS
TF
LF
40
Example 3 (PDM)
Activity
Duration (week)
Predecessor (s)
Act. A
Act. B
A (FS+2),
C (FF+1),
D(FF)
Act. C
Act. D
C (SS)
+2
0
A
2
+1
+2
2
B
4
A
0
C
4
+1
Total Float = LF ES D
TF(A) = 2-0-2 = 0
TF(B) = 7-4-3 = 0
TF(C) = 6-2-2 = 2
TF(D) = 7-2-1 = 4
D
6
Critical path
Exercise 4(PDM)
Activity
Duration (day)
Predecessor (s)
Act. A
Act. B
Act. C
Act. D
Act. E
B,C
Act. F
Act. G
C,D
Act. H
E,F,G
Exercise (PDM-Solution)
3
B
6
A
0
11
10
11
11
13
D
3
11
C
2
11
11
13
BUT WAIT!!
Are there any other type of Scheduling
method??
How if the Gantt Chart and CPM did not
actually work/represent well with the
nature/requirement of the particular
construction project??
Kilometer (km)
We have 5 linear
activities:
1.
Clear & strip
2.
Drainage
3.
Subgrade
4.
Base course
5.
Pave
Width of B:
At 40km, the subgrade
works will starts at week
4.4 until week 5.
Height of A:
At week 3, subgrade
works from 13km to
21km.
Distance of C:
It is a time lag / time
float for 10km; between
subgrade works and base
course works.
1.4 weeks to be exact.
ACTIVITY
A
B
C
D
E
F
G
H
I
J
K
L
M
PREDECESSOR
A
B
C
D
D,E
D,E,F
G
H
I
J,K,L
DURATION (WEEK)
3
1
2
3
1
4
2
1
2
3
2
1
2
QUESTION 2
A project have a detail as below:
1. Draw the precedence diagram for the schedule shown next.
2. Determine the duration of project required.
3. Determine the Total Float for each activities and give the critical path for this project.
4. Draw a bar chart.
ACTIVITY
A
B
C
D
E
F
SUCESSOR
A-B (S-S),L=5
A-C (F-S),L=2
B-E (F-S),L=3
C-E (F-S),L=0
D-E (F-S),L=0
E-F (F-S),L=0
DURATION
(WEEK)
3
1
2
2
3
2
Duration
(week)
5
2
3
B
C
4
3
E
F, G
4
5
D
E
2
7
H
F, G
6
7
8
9
F
G
H
I
2
5
3
6
I
I
I
-
No. Activity
Successor
Relationship
B, C, D
AB (SS)
AC (FS)
AD (FS)
BE (FS)
CF (FS)
CG (FS)
DH (FS)
EF (FS)
EG (FS)
FI (FS)
GI (FS)
HI (FS)
-
Lag
(week)
1
2
0
0
0
0
0
0
0
0
0
3
-