Академический Документы
Профессиональный Документы
Культура Документы
SITE EXPLANATION
(MECHANICAL WORK)
1. Project overview
1.1 General
Project Name
Owner
Location
Description
O Mon Thermal Power Plant Unit No.2 Construction Project
Owner : EVNGENCO 2
Contract period
Warrant period
Advance payment
Selecting
Subcontractor
10%
June 15, 2013
1. Project overview
1.2 Site location
150km
Can Tho City 18km
1. Project overview
1.3 Overall Site photo
Unit No. 1
Power Plant
Unit No. 2
Location
1. Project overview
1.4 Overall Plot Plan
590m
850m
Power Block
*See the next slide
Switchyard
1. Project overview
1.5 Plot Plan (Power Block)
85m
208m
FGD
ESP
Boiler
CCB
Power(STG) House
Main Transformer
1. Project overview
1.6 Section View (Power Block)
208m
2. Inquiry package
2.1 Composition of Inquiry package
2. Inquiry package
2.2 Letter of Tender
Subcontractor to input is
1. Tender cost
2. Expiry date of the Tender
3. Signature and address
2. Inquiry package
2.3 Schedule
Subcontractor to input is
1. Bill of Quantities
2. Daywork Schedule
3. Break down of Price
2. Inquiry package
2.3 Schedule
Price schedule
1. Unit rate in Bill of Quantity shall include indirect cost and O&P
2. Total cost from BILL OF QUANTITY(SUMMARY), Break down of
Price (Summary 1) and Break down of Price (Summary 2) shall
be same
2. Inquiry package
2.3 Schedule
Optional price 3 sets of field erection tank (PKG B)
Material, pre-fabrication and primer coating
2. Inquiry package
2.3 Schedule
Optional price for NDE (Will be included in Addendum for PKG A)
RT, PT, UT and MT
Description
Qty
RT
7,000 films
PT
25,000 m
UT
20 m
MT
30 m
Unit Rate
(USD)
Amount
(USD)
2. Inquiry package
2.4 Condition of Subcontract
Condition of Subcontract is general condition, and referred by Letter of
Tender
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Content
1. General
2. Scope of Works and Measurement
3. Free-Issue Materials
4. Technical Specification
5. Other condition
Annex
1. Detail scope of Work
2. Conceptual Drawing for Definition of Package A and B
3. Measurement Formula for Piping Works
4. Preliminary Construction Schedule
5. Special tools and consumables to be provided by Contractor
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Scope of Works and Measurement
1. Mechanical work is divided into 2 packages
2. Package A : Power Block (T/G and BLR, up to GAH outlet)
3. Package B : Non Power Block (EP, FGD and others, from GAH outlet)
4. Mechanical work includes piping, equipment installation, painting and
commissioning assistance
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Piping work
1. Installation of pipe, fitting, flanges, valves, bolts/nuts, inline
instruments and other piping components
2. Installation of support, performing NDE and heat treatment
3. Flushing, blowing and any other pre-commissioning activities.
4. Detail scope as per Specification and Annex 1 (In case any conflicts
arise between Specification and Annex 1, Specification will prevail)
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Equipment erection
1. Installation of equipment including piping
2. Delivery condition of pipe, condenser, steam turbine and other
equipment, if available, is stated in Contractor-furnished data
3. Erection of procedure based on Unit No. 1, if available, is stated in
Contractor-furnished data
4. Preparation, temporary structure and any pre-commissioning activities
are Subcontractor scope of work
5. Detail scope as per Specification and Annex 1 (In case any conflicts
arise between Specification and Annex 1, Specification will prevail)
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Equipment delivery condition <Main item>
Piping for Boiler and Steam turbine <MHI Piping>
Condenser
Steam turbine
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Equipment erection procedure for Unit No. 1 <Main item as reference>
Generator, steam turbine, condenser, steam drum, heater and etc .
For condenser installation, some tools and consumables as stated in 2.2.5 Special
tools and consumables to be provided by Contractor will be supplied by
Contractor
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Preparation for erection of main equipment
Jack-up system for Generator and Steam drum
Temporary structure for Generator, steam drum, condenser and etc.
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Generator Installation
SPMT
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Route of SPMT for Generator Installation
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Equipment erection
Adjustments to tonnage of Equipment
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Painting work
1. Surface preparation, preservation and coating
2. Painting and blasting material
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Free issue materials
As per Specification
Technical Specification
As per Specification
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Other conditions
Acquisition of permit by Subcontractor
Temporary facility and utility for Work by Subcontractor
(including sufficient number of portable toilets at Site)
Office area by Contractor
(Subcontractor shall carry out back-filling, compaction and gravelling if required)
Shop area by Contractor
(Subcontractor shall carry out glass cutting, grubbing and moving existing material to
Contractor designated place)
Material handling, transportation and storage by Subcontractor
Preservation of Equipment and material by Subcontractor including periodic manual shaft
rotation of Rotating equipment.
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Other conditions Location for Subcontractor office and shop
Shop area
Shop area
2. Inquiry package
2.5 Specification (Special condition of Subcontract)
Construction schedule
Critical Path (will be included in Addendum)
2. Inquiry package
2.6 Drawing, Clauses of Contract
Drawings
Bid drawings for reference
Clauses of Contract
1) General Condition of Contract
2) Special Condition of Contract
3) General Technical Provisions
4) Technical provision for Civil and Architectural works
2. Inquiry package
2.7 Contractor-Furnished data
Package A
1) General inspection requirement with inspection and test plan
2. Inquiry package
2.7 Contractor-Furnished data
Package A
13) Boiler leaving out steel structure division instruction
2. Inquiry package
2.7 Contractor-Furnished data
Package B
1) General inspection requirement with inspection and test plan
2. Inquiry package
2.8 Clarification (will be included in Addendum)