University of Liverpool
MSc, Software Engineering
2009 2012

Nota: Distinction
A Masters Degree in Software Engineering, concentrating on Project Management and
Resource Management in the Software industry

UK Armed Forces
TEC, Instrumentation
1985 1988

Military Instrumentation and optical systems


Actividades y grupos: Music, Reading, Computing, Science & Physics, Home
Automation, Sport

Certificaciones de Kirk Morey

o
o
o

Chartered Engineer
Institute of Measurement and Control
License M-21033
March 2013

Extracto de Kirk Morey


I am a well traveled Commissioning Engineer with nearly 25 years experience in the
I&C Industry. I am currently still working overseas but I intend to move to a home based
position within the next five years, probably doing either project management, or
project controls.
Especialidades
DCS, ICS, SCADA, PLC, Project Management, Project Planning, Site Management,
Commissioning Management, Networks, Instrumentation, Electronics.

Experiencia de Kirk Morey


Senior Instrument & Controls Engineer
Dove Energy Ltd
Privately Held; 1-10 employees; Petrleo y energa industry

May 2012 Present (2 years 3 months) Middle East

Heading up the Instrument and Controls group for everyday works and for two
upcoming major projects, including a Gas Gathering and Treatment plant and a
complete ICSS refit project for the whole field.

Commissioning Manager
Siemens

Public Company; 10,001+ employees; SI; Manufactura elctrica/electrnica industry

January 2011 June 2012 (1 year 6 months)

Commissioning of a new build cement plant and power generation facility in Ogun
State, Nigeria

Commissioning Manager
Initec Energia
Privately Held; 201-500 employees; Petrleo y energa industry

September 2010 February 2011 (6 months) Madrid Area, Spain

Overseeing all Turbine and Steam Cycle commissioning activities for a new build
Thermal Solar facility, Manchasol 1+2, near Alcazar de San Juan, Ciudad Real, Spain

Commissioning Manager
Initec Energia

Privately Held; 201-500 employees; Petrleo y energa industry

December 2009 September 2010 (10 months)

Overall Commissioning Manager on a new construction 700MW Power Station in Cairo


(West), Egypt.

Site Manager
GE Oil and Gas
Public Company; 10,001+ employees; Petrleo y energa industry

April 2009 December 2009 (9 months)

My main duties for this project are to manage the day to day commissioning operations
of one of ten natural gas compression stations on the Reliance Energy "East/West"
pipeline, including personnel planning and all materials handling for site. Further duties
include assisting the commissioning team wherever necessary to commission the
various control systems included in the station. These systems consist of a Mark VI
turbine control system for the three "Nuovo Pignone PGT25 Turbine and 803/2
Compressor packages". Further systems are a GE Fanuc Duplex 90-70 PLC for the ESD,
F&G and process systems and a Versamax PLC for the hydraulic starter system. Four
such stations completed over the course of the project.

Site Manager
Honeywell Control Systems Ltd

October 2008 March 2009 (6 months)

My initial placement was in Honeywell's Bracknell, UK office to plan and set up the site
portion of the Shell Pearl GTL project, to be installed and commissioned in Ras Laffan
Industrial City, Qatar. Subsequent visits included FAT's and site visits to Qatar and New
House, Scotland and eventual mobilization to the project in Qatar. My positions main
emphasis at site is to manage all aspects of the Honeywell project, including the
installation, pre-commissioning and commissioning of both the Honeywell Experion DCS
and Safety Manager IPS systems, in conjunction with the associated Experion,
Foundation Fieldbus and HART managed networks. Other responsibilities include all
planning works and procedure writing to successfully execute the project and materials
handling/load out/construction.

Lead Commissioning Engineer/Area Supervisor


TengizChevroil (Chevron)
Partnership; 1001-5000 employees; Petrleo y energa industry

November 2006 October 2008 (2 years)

I was originally taken on as a Senior Commissioning Engineer to commission two


"Standard Fasel" HRSG's. After my first trip I was promoted to Lead Engineer and put in
charge of the PCO Power group, consisting of two senior commissioning engineers, four
commissioning engineers and upwards of twenty technicians. This new position

included managing the commissioning of all associated Power/Steam equipment


including two GE Frame 9E turbines, HRSG's, Power Island, Fire and Gas systems and
peripherals and filling in for the PCO Group Manager in special circumstances. After this
part of the project was complete, I then went over to the "Gas Treatment" area, again
as Lead Commissioning Engineer, this time supervising four senior engineers, 8
engineers and thirty+ technicians. This includes all of the Amine Treatment area, Sales
Gas Compressors and peripheral equipment. All of these works were carried out on
Chevrons "Second Generation Project-Tengiz" field in Western Kazakhstan.

Senior Software/Commissioning Engineer


GE-PS and Aero derivative U.S Division
Public Company; 10,001+ employees; GE; Manufactura elctrica/electrnica industry

June 2003 October 2006 (3 years 5 months)

The Commissioning of four HP compressor modules on the AKAL Charlie platform C7


and C8 hook up, offshore Gulf of Mexico (final client PEMEX). My main duties are the
commissioning, code modification (PLC and HMI), technical authoring, C&E testing and
final sign off of the control systems for the turbines, WHRU and Siemens compressors,
along with the associated process for the compressors. All systems are controlled by GE
Fanuc 90-70 and 90-30 PLC's running Versa Pro software, with an Intouch 7.11 HMI.
Main platform control by TDC3000 DCS which all units were interfaced to and Auxiliary
systems included Bentley Nevada 3300 vibration and Woodward Netcon 5000 engine
management system.

Commissioning Engineer
GE-PPSD Power Generation

February 2005 October 2005 (9 months)

The commissioning of a BOP (balance of plant) ICS Mark VI system for a 340MW
combined cycle power station in Aceca, Spain for Union Fenosa corporation. My duties
for this project were as a technical consultant to Union Fenosa along with the general
commissioning of the control system. The main ICS equipment was the GE Mark VI
running "Control Systems Toolbox version 11" with a Cimplicity 5.5 graphics package.
Peripheral equipment included Siemens PLC's, PI historian

Site Manager
Sirio Sistemi Elettronici

January 2003 April 2003 (4 months)

The Commissioning of four Nuovo Pignone steam turbines and four reciprocating
compressors for an ammonia plant in Jilin, Northern China (PetroChina as final client).
All systems utilising GE Fanuc 90-30 PLC's running LM90 programming package and
Cimplicity HMI/MMI. All units interfaced to HEMA ESD system and Yokogawa DCS. My
main emphasis for this project was as site co-coordinator and software engineer,
designing and implementing all PLC and HMI modifications, commissioning of all
controls and associated instrumentation, vendor representative controlling all aspects
of the I/C portion of the project and liaising with the client (Linde Impianti

Commissioning Engineer
GE
Public Company; 10,001+ employees; GE; Manufactura elctrica/electrnica industry

April 2002 November 2002 (8 months)

The Commissioning of four GEC Alstom Tornado gas turbines for power generation
(4.15 MW) on the AKAL Bravo complex offshore Mexico (final client PEMEX). All systems
utilising Allen Bradley PLC's running RSLogix with Intouch 7.0 HMI. All units interfaced
to FSI Fire & Gas system, Triconex ESD and TDC3000 DCS. Also utilized Bentely Nevada
Vibration and Speed monitoring system, and Woodward power monitoring and control.
The Commissioning of three LM2500 gas turbines on the Resak platform gas
compression upgrade, offshore Malaysia (final client Petronas). My main duties were
site management of local labour for all electrical and instrumentation systems
associated with the turbines, along with all instrumentation for the associated Elliot
compressors. All systems controlled by Woodward TCP, with Intellution HMI and

Micronet NT based PC running GAP control software. Main platform control by TDC3000
DCS which all units were interfaced to. Auxiliary systems included Bentley Nevada
3500 vibration and speed control.

Site Manager
Silvertech Systems, Europe

July 1997 February 2002 (4 years 8 months)

Installation and Commissioning/Start Up of Fire and Gas/ESD/PSD/PCS system for new


FPSO vessel, utilising UNIX/NT based Cimplicity top end graphics and GE Fanuc 90-70
and 90-30 PLC's. Project initially based in Mitsui Zosens shipyard in Chiba, Japan where
I became the Site manager for the PDS portion of the project and sea trials. Topsides
were completed in Swan Hunter Shipyard, Newcastle upon Tyne and remaining
commissioning and start up work completed in North Sea on location. This position
included making and authorising all PLC and HMI changes requested by the client (Kerr
McGee) and commissioning of all controls and instrumentation.
I was seconded to the U.S office in September 98 to begin commissioning of MUX IV
subsea BOP control systems. Five such systems completed in various shipyards around
the world over three years. Inclusive are Reading and Bates Drilling, Noble Drilling,
Diamond Offshore Drilling and Saipem Drilling whilst subcontracted to Varco Systems.
This position included managing/making all installation, field engineering,
commissioning, software Modification using the LM90 programming package on GE
Fanuc 90-70/90-30 PLC's and Allen Bradley PLC's using RSLogix, all graphics
modifications using Windows NT based Cimplicity top end graphics package and
WGS/QNX, also eventual offshore subsea and sign off testing.
My position for these projects was as the head of the commissioning team overseeing
all aspects of the project, including making and authorising all drawing, software and
HMI/MMI modifications.
I then transferred to the Siemens/SKU Cadereyta, Mexico refinery refit project as a
Software Engineer/Site Manager. The main emphasis of the project being
commissioning Burner management and Cooling tower systems utilising GE Fanuc
PLC's with GE Fanuc Cimplicity HMI and interfacing to Siemens Teleperm DCS and S7400 PLC's . All PLC software and HMI modifications carried out by myself on site.

Idiomas de Kirk Morey

Spanish

Aptitudes y conocimientos de Kirk Morey


1.

DCS

2.

PLC

3.

Instrumentation

4.

Electronics

5.

Microsoft Office

6.

Network Engineering

7.

Software Engineering

8.

Commissioning

9.

Software Project Management

10.

commissioning management

11.

Project Planning

12.

SCADA

13.

Project Management

14.

Commissioning Management

15.

Petrochemical

16.

Gas Turbines

17.

Power Plants

18.

Turbines

19.

Steam Turbines

20.

Engineering
Ver todas las aptitudes (44)

Informacin adicional de Kirk Morey


Grupos y asociaciones:
Institute of Measurement & Control

All Industry Jobs

Audra's Chemical Manufacturing Club (Texas)

Automation Engineers

Automation Engineers Technical Group

AutomationEngineerSCADA_PLC

AutomationJob.com - Industrial Automation, Robotics, Process Control and


Industrial IT Job

BOLASHAK JOB GROUP

Chronos Oil and Gas

Connectus - Controls & Automation

Control & Automation TPN

DCS Contractors (Distributed Controls Systems Engineers)

Drilling People

Electrical Control and Instrumentation Jobs

Energy & Power Hub Jobs

Energy Recruitment

Energy, Oil & Gas Careers

Expat Network

Expat Web

Global Engineering Recruitment

Houston - Offshore & Subsea

Houston Energy Professionals

Houston Oil & Gas Networking Center

Industry Jobs

Institute of Measurement and Control

International Energy Professionals

Oil and Gas Control & Instrumentation Engineer

Oil and Gas Jobs and Recruitment Network

Oil and Gas People

Oil and Gas Pros - Contractors and Freelancers

PLC / SCADA / MES World Wide Community

Petrogate Jobs

Power and Energy Worldwide

Regalgreen

Steam Turbine Professionals

Turner Lovell Energy Jobs

University of Liverpool Online Students and Alumni

Publicaciones de Kirk Morey

Designing and implementing a methodology for standardizing and


aiding design for industrial control system architecture, using common
templates, objects and OOD methodologies.

o
o

University of Liverpool
January 1, 2012
Authors: Kirk Morey

A Method of designing control systems in the same manner that we design industrial
software, using predetermined templates in a 'Drag & Drop' scenario, using
inexpensive off the shelf software.

Voluntariado y causas benficas de Kirk Morey

Causas benficas que me importan:


Arts and Culture
Science and Technology
Civil Rights and Social Action
Education
Environment
Health

Comuncate con Kirk para:

oportunidades profesionales

ofertas de consultora

preguntas de empleo

peticiones de referencias

retomar el contacto

Ve el perfil completo de Kirk Morey y...

Descubre a quin Kirk Morey y t conocis en comn


Haz que te presenten a Kirk Morey
Contacta con Kirk Morey directamente

Вам также может понравиться