A-System Preparation :
1-Obtain updated construction drawings ,specifications,approved shop drawings.
2-Prepare field data forms to record testing and balancing process.
3-Obtain system leakage rate data where duct leak testing specfied.
4-Verify that fresh air intake type units fan are installed, rotating correctly,controlled to supply the
required airflow rate .
5-Check for clean filters.
6-Volume control dampers are operable, accessible,and are in an open or normal position.
7-Controls are operable and calibrated.
8-Boxes are installed,operable and accessible.