Environmental

Approvals Procedure
for a
Industrial Project
Deepak Kumar Jha
EM Participant
December 22 24, 2010

IISc Banglare - LAKE 2010

Development of Environmental
Impact Assessment (EIA)
Process in India
n

The environmental movement in India got a boost from


the Stockholm Conference on Human Environment held
in June 1972

In 1982
1982,, Government of India (Ministry of Environment
and Forest) introduced the need of an Environmental
Impact Assessment (EIA) / Environmental Management
Plan (EMP) for public sector projects

January 4, 2011

IISc Banglare - LAKE 2010

Development of Environmental
Impact Assessment (EIA) Process
in India (contd..)
n

In 1994, EIA Notification under the Environmental Pollution Act 1986


was introduced

NOC (No Objection Certificate) from State Authority


Environmental Clearance from Ministry of Environment & Forests
REIA (Rapid Environmental Impact Assessment)
RRA (Rapid Risk Analysis)
CEIA (Comprehensive Environmental Impact Assessment)

Public Hearing was introduced in 1997

In 2006, the EIA Notification


Notification--1994 has been replaced by a more
comprehensive EIA Notification covering a larger variety of projects
and activities i.e. EIA Notification Sep 14, 2006.
January 4, 2011

IISc Banglare - LAKE 2010

EIA Notification
Notification-- 2006
n

As per EIA notification Sep 14, 2006, a schedule is


provided for list of Projects or Activities requiring prior
Environmental Clearance

All new projects listed in the schedule including


expansion, modernization of the existing projects or
activities and change in product mix shall require prior
Environmental Clearance

Only land can be secured before the Environmental


Clearance, no construction work can be done before
that.
January 4, 2011
IISc Banglare - LAKE 2010

EIA Notification
Notification-- 2006
Categorization of Projects and Activities
n

Categorization of the Projects or Activities is done


based on the spatial extent of the potential impacts on
human health, natural and manmade resources
Category A Projects
Category B Projects

Category A Projects : Requires prior Environment Clearance


from Central Government in the Ministry of Environment and
Forest (MoEF)

Category B Projects : Requires prior Environmental Clearance


from State Environmental Impact Assessment Authority (SEIAA)
January 4, 2011

IISc Banglare - LAKE 2010

Schedule
(List of few Projects or Activities requiring Prior
Environment Clearance)
Project or Activity

Category with threshold limit


Category A

Category B

Offshore and onshore oil and gas exploration,


development & production

All projects

River Valley Projects

>= 50 MW
hydroelectric power
generation

< 50 MW >= 25 MW
hydroelectric power

Thermal Power Plants

>= 500 MW
(Coal/lignite/naphtha &
gas based)

< 500 MW
(Coal/lignite/naphtha
& gas based)

Nuclear power Projects

All Projects

Petroleum refinery industries

All Projects

Petrochemical Complexes

All Projects

January 4, 2011

IISc Banglare - LAKE 2010

Application for
Prior Environmental Clearance (EC)
n

Application to be submitted in prescribed


Form 1 format

Supporting document for Form 1: Pre


feasibility report.

Form 1 to be submitted:
After identification of the prospective site for the
project
Before commencing any construction activity
Before preparation of land at the site

January 4, 2011

IISc Banglare - LAKE 2010

Form 1
(Application for the Project
Consideration)
Contents:
n Size of the Project (Capacity)
n Expected cost of the Project
n Activities involved in the Project
n
n
n

n
n
n
n
n

Demolition work
Dredging
New road, rail or sea traffic during construction or operation

Use of natural resources


Production of solid waste
Release of pollutants, toxic or noxious substances to air
Effluent generation
Generation of noise and vibration
January 4, 2011

IISc Banglare - LAKE 2010

Stages in the Prior Environmental


Clearance (EC) Process
n

Stage (1) Screening (Only for Category B


projects and activities)

Stage (2) Scoping

Stage (3) Public Consultation

Stage (4) Appraisal

January 4, 2011

IISc Banglare - LAKE 2010

Stage (1) Screening


n

Scrutiny of the application (Form 1) seeking


prior Environmental Clearance

Only for Category B Projects or Activities

B1 Sub Category Environmental Impact


Assessment (EIA) report required

B2 Sub Category Environmental Impact


Assessment (EIA) report not required

January 4, 2011

IISc Banglare - LAKE 2010

10

Stage (2) Scoping


n

Process to determine detailed and comprehensive


Terms of Reference (TOR) addressing all relevant
Environmental Concerns for preparation of EIA
report

Generic Structure of EIA report

Basis for determining Terms of Reference (TOR):


Form 1

January 4, 2011

IISc Banglare - LAKE 2010

11

Generic Structure of EIA report


n

Introduction

Project Description

Identification of the project


Nature, Size and Location of the project
Scope of the study i.e. TOR
Type of project
Need of the project
Location Map
Technology and process description

Description of Environment (Study area Baseline Data)

January 4, 2011

Air Environment
Water Environment
Noise Environment
Land Environment
SocioSocio-economic Environment
IISc Banglare - LAKE 2010

12

Generic Structure of EIA report


n

Anticipated Environmental Impacts & Mitigation Measures


Pre - project scenario
Post project scenario

Environmental Management Plan

Additional Studies
Risk Analysis

Project Benefits

January 4, 2011

IISc Banglare - LAKE 2010

13

Stage (3) Public Consultation


n

Process to ascertain the concerns of local affected people and others


who have plausible stake in the environmental impact

All category A and category B1 projects or activities shall undertake


Public Consultation with exemption of followings:
Modernization of irrigation projects
Expansion of road or highways projects
All projects concerning national defence and security etc.

Public Consultation may be exempted by Expert Appraisal Committee


(EAC) if project is not affecting the local people
January 4, 2011

IISc Banglare - LAKE 2010

14

Stage (4) Appraisal


n

Appraisal means detailed scrutiny of EIA report by Expert


Appraisal Committee (EAC) of MoEF or State Level Expert
Appraisal Committee (SEAC) of state level

Outcome of public consultation including public hearing to be


submitted.

In appraisal proceedings, applicant or authorized representative


is invited for necessary clarification

At this stage, recommendations are made to regulatory authority


by EAC either for grant of prior Environmental Clearance (EC)
with stipulated terms of conditions or rejection with reasons for
January 4, 2011
IISc Banglare - LAKE 2010
15
the same

Post Environmental Clearance


Monitoring
n

Submission of half yearly compliance


reports in respect of stipulated prior
environmental clearance terms and conditions
to regulatory authority

All such compliance reports submitted by the


project management shall be public document
to be displayed on the website or concerned
regulatory authority

January 4, 2011

IISc Banglare - LAKE 2010

16

Time schedule
Environmental Clearance Process
Form I submission to MoEF along with draft TOR

Screening for categorization

Within 60 days

Additional TOR after scoping if necessary


Within 3- 6 months for EIA study

Preparation of EIA/EMP
Public Hearing conducted by SPCB
Review by Expert Appraisal Committee
Final Decision of Competent Authority

Within 45 days

Within 60 days of the receipt of


final EIA report
Within 15 days after EAC
recommendations

Environmental Clearance granted

Total approximate time: 1 year to obtain Environmental Clearance from MoEF.


January 4, 2011

IISc Banglare - LAKE 2010

17

Environmental Clearance
Procedure Flow Diagram
Submission of application
to MoEF (Form 1)

Verification of Documents & meeting


for Draft TOR approval

Draft TOR is
ok & complete

Additional TOR will be


prescribed by MoEF

NO

YES
Draft EIA report preparation

Conduct Public Hearing

NO

Public hearing
exemption?
YES

Proceedings & Recommendations


inclusion in EIA report

Submission of EIA & other


information to MoEF
Project Appraisal in
EAC meeting

NO
Project is Ok and
min pollution load
NO

January 4, 2011

IISc Banglare - LAKE Project


2010 Rejection

YES

Information
furnshed is
complete
YES

EC granted

18

January 4, 2011

IISc Banglare - LAKE 2010

19

References: