Академический Документы
Профессиональный Документы
Культура Документы
^ JAN 29 2016
CTourt
Vancouver Registry
I, Michael Savidant, Commercial Manager of the Site C Clean Energy Project, of Suite
600, Four Bentall Centre, 1055 Dunsmuir Street, Vancouver, British Columbia, AFFIRM THAT:
1
1.
1 am employed by British Columbia Hydro and Power Authority ("BC Hydro") as the
Commercial Manager, Site C Clean Energy Project (the "ProjecfO> and as such have personal
knowledge of the facts hereinafter deposed to except where stated to be on information and
belief, in wliich case I verily believe them to be true. My responsibilities under my present
position include management of the financial and commercial aspects of the Project and
economic evaluation of the Project compared to alternatives.
240150.00163/90624881.2
-2-
2.
In January 2015, BC Hydro applied for an expedited hearing schedule in three Federal
Court judicial reviews of the federal Minister of Environment and federal Cabinet's decisions
under CEAA 2012 related to the Project. The applicants that initiated those proceedings were (i)
Peace Valley Landowner Association, (ii) West Moberly and Prophet River First Nations, and
(iii) Mikisew Cree and Athabasca Chipewyan First Nations. The purpose of BC Hydro's motion
was to schedule the hearing of those proceedings prior to the start of construction. In support of
the motion, I affirmed an affidavit setting out what the costs of a one-year delay to the Project
would be at that time, estimating them to be approximately $175 million. Now produced and
shown to me and marked as Exhibit "A" is a copy ofmy affidavit affirmed on January 15,2015.
The facts in that affidavit were true at the time I affirmed them.
3.
In August 2015, West Moberly First Nations and Prophet River First Nation brought an
application in B.C. Supreme Court seeking to enjoin work on the Project pursuant to 36
authorizations issued by various provincial regulatory bodies. For .the purposes of that
application, I updated my estimate on the costs to BC Hydro if the Project in-service date was
delayed by one year now that construction was underway. At that time, I estimated the delay in
Project construction of one-year would result in an estimated $335 million of additional costs.
Now produced and shown to me and marked as Exhibit "B" is a copy of my affidavit filed in
that proceeding (without exhibits), affirmedon August 12,2015. The facts in that affidavit were
true at the time I affirmed them. The application brought by West Moberly First Nations and
Prophet River First Nation was dismissed. Now produced and shown to me and marked as
Exhibit "C" is a copy of the Oral Reasons for Judgment of Mr. Justice Sewell dismissing the
application, dated August 28,2015.
Cost of Delay
4.
In January 2016, when I leamed that a group of people were preventing clearing of an
area on the south bank of the Peace River, west of theMoberly River, I updated the analysis that
I conducted in August, 2015. My current analysis demonstrates that if Projectconstruction were
now delayed by one year, it would result in an estimated further increased costs of $85 million
beyond my August 2015 estimate of $335 million, for a total costimpact of approximately $420
million.
2401SO.00]63/9062488i.2
/
/
- 3 -
/
5.
(a)
(i)
(ii)
(iii)
(iv)
(v)
(b)
$100 million of additional allowance for inflation due to shifting spending into
future periods, which are expected to have higher prices due to underlying
inflation.
(c)
$160 million of increased interest costs due to future higher rates and an
additional year of payments on costs already incurred or expected to incur in the
next year.
6.
The current estimate is larger than the estimate of $335 million provided in August 2015
(a)
At the time of the previous estimate, construction had been ongoing for about
three weeks. Because constmction has now been ongoing for over five months, a
240150.00163/90624881.2
(i)
(ii)
(iii)
BC Hydro awarded the contract for the Main Civil Works on December
18, 2015. The contractor has begun procuring major equipment and
project staff and expects to begin mobilizing to the work site in early
February 2016. These committedplans and procurement increase the cost
of a delay to this contract as it increases the cost of a disruption to the
project schedule and the fixed costs over any period of delay.
(iv)
contract on July 10, 2015 and plans to award this contract in February or
March 2016. A change in the project schedule after financial submissions
are receivedfor this procurement will disrupt the procurement process and
may affect the preferred proponent's proposed approach to delivering the
contract. This increasesthe cost ofa delay to this contract.
(b)
The allowance for inflation due to shifting spending into future periods is slightly
lower than estimated in August 2015 as a portion of work has been completed on
site to date and can no longer be delayed ifthe overall projectschedule is delayed.
Since this spending cannot be shifting into future periods, it does not attract an
inflation adjustment thus reducing the inflation impact of delay. The net
difference is small - less than one million dollars.
2401S0.00I63/9062488I.2
5-
(c)
Interest during construction costs are approximately $25 million higher due to a
hi^er amount of direct costs incurred to date ($695 million as of December 31,
2015), and costs that will be incurred in the next year (e.g., construction ofworker
partially but not fully offset by a decrease in the interest rates expected to be
charged to the project over the construction period due to decreases in market
interest rates.
7.
Beginning in 2015, BC Hydro has entered into 15 contracts for site preparation and site
services work.
Infrastructure ("MOTl") under which work for 4 site preparation and community infrastructure
projects have been procured. The total site preparation and site services work procured to date
has an aggregated value of approximately $130 million. Of these contracts, 10 are direct awards
to companies owned by First Nations, companies owned by members of First Nations, or joint
ventures involving companiesownedby First Nations.
8.
Work under 3 of the site preparation contracts is substantially complete. Workunder the
remaining 12 is ongoing or is expected to begin with the next three months. In addition, work
The existing contracts, including the MOTI contracts, for which work is ongoing are set
out below:
(a)
South Bank Site Clearing (not including Lower Reservoir Area) awarded to Paul
Paquette and Sons Contracting Ltd, on December 19,2014;
(b)
240150.00163/90624881.2
6-
(c)
(d)
(e)
(i5
(g)
(h)
(i)
(j)
(k)
(m)
("MOTI") and its contractors. This consists of road upgrade work done by A.L.
Sims and Sons Ltd. and work on Peace Island Park RV Sites done by Jacob Bros.
p-q
240150.00163/90624S81.2
-7-
Construction. This work is currently shut down for the winter season and is
expected to recommence in spring 2016.
10.
In September 2015, BC Hydro entered into a contract with ATCO Two Rivers
facility to house the majority of workers on Site C for the construction period.
The Worker Accommodation contract is valued at $470 million. Work is ongoing
imder this contract.
(b)
In December 2015, BC Hydro entered into a contract with Peace River Hydro
Partners for construction of the Main Civil Works for the Project. The Main Civil
Works contract is valued at $1.75 billion, and is the largest contract for the
Project, both in duration and value.
11.
In addition to the site preparation, site services, and major construction contracts, BC
In August 2015 BC Hydro signed a contract with Spunky Ventures, a Mdtisowned company, for environmental mitigation work.
(b)
In October 2015 BC Hydro signed a contract with Twin Sisters Native Plants
Nursery, a company owned by two Treaty 8First Nations, for supply and delivery
of native plant seeds.
12.
240150.00163/90624881.2
Undertaking as to Damages
13.
interlocutory injunction and other relief. I am authorized on behalf of BC Hydro to affirm that
m
BC Hydro will abide by any order concerning damages thatthisHonourable Court may make if
it is found that granting of the injunction order sought causes compensable damages to the
defendants.
PATRICK HAYES
Barrister & Solicitor
Fasken Martineau DuMoulin LLP
2900- 550 Burrard Street
Vancouver, BC V6C 0A3
604 631 4971
240150.00163/90624881.2
Michael Savidant
001
<*!
No.T-1393-14
Vancouver Registry
FEDERAL COURT
BETWEEN:
APPLICANTS
AND:
RESPONDENTS
No.T-2292-14
FEDERAL COURT
BETWEEN:
APPLICANTS
AND:
This Is Exhibit
r\
RESPONDENTS
rofefisd to Inthi
affidavit of
ACormifi^ner fortaking
Affidavits for British Columbto
DM VAN/240150.00142/8982425.4
002
-2-
No.T-2300-14
FEDERAL COURT
BETWEEN:
APPLICANT
AND:
No. T-2333-14
FEDERAL COURT
BETWEEN:
British Columbia, commercial manager of the Site C Clean Energy Project,AFFIRM THAT:
1.
1 am employed by British Columbia Hydro and Power Authority ("BC Hydro'*) as the
Commercial Manager, Site C Clean Energy Project (the "Project"), and as such have
personal knowledge of the facts hereinafter deposed to except where stated to be on
informationand belief, in whichcase I verilybelievethemto be true.
DM VANn40150.00142/8982425.4
P
i
TI03r
-3-
2.
3.
As I describe below, delays inthe start ofconstruction will result inincreased costs to BC
Hydro and the risk of indirect costs to BC Hydro's contractors and their employees.
4.
BC Hydro intends to award sixseparate contracts for clearing and site preparation work
in 2015. The totalvalueof those contracts is approximately $110 million.
5.
6.
To date, BC Hydro has entered into a contract with a company owned by a member of
one of the First Nations that is a signatory to Treaty 8, for clearing. Negotiations with
four other contractors owned by First Nations, or joint ventures involving companies
owned by First Nations, including First Nations that are signatory to Treaty 8, are
underway. BC Hydro anticipates reaching agreements with these contractors vnthin the
next few months.
7.
1^,.
8.
" 1
Construction power;
(b)
Site communications;
(c)
(d)
(e)
Site security.
i
i
DM YAN/240l50.00i42/8982425.4
004
-49.
jm
Delays in constniction start will generally increase the construction costs to the project
due to some or all ofthe following:
(a)
'
(b)
(c)
'
(i)
staff, supplies, and rent costs for the additional term of construction;
(ii)
'
(iii)
10.
Cost impacts increase with longer delays as acceleration options become less efficient,
11.
indicative estimates of the cost ofa one month and a two month delay to the construction
start date:
(a)
(i)
(ii)
n
DM VAN/240IS0.00142/89S242S.4
005
-5-
(b)
(i)
(ii)
12.
The actual costs of any delay will depend on several factors, including the timing of
precedent requirements (such as permits), the contractor's ability to execute the work, and
the actual weather conditions.
13.
Any delay of the construction start date increases the risk of missing a construction
season.
14.
r-v
BC Hydro currently estimates that a one year delay to the completion of the Project
would increase the costs of construction of the Project by approximately $175 million.
These costs would consist of:
(a)
(b)
(c)
DM VAN/240130.00142/8982425.4
p
006
jam,
-6-
15.
approximately 500. The jobs required are primarily skilled and semi-skilled positions,
including equipment operators, drivers, labourers, trades, and site support and
supervision.
AFFIRMED, BEFORE ME at Vancouver.
British Columbia, on January 15,2015 .
ROB LONERGAN
Barrister & Solicitor
Fasken Martineau DuMoulin LLP
2900 - 550 Burrard Street
Vancouver, BC V6C0A3
004 6314718
DM VAN/240150.00142/8982425.4
MICHAEL SAVIDANT
1^
DM VANa401S0.00142/898242S.4
APPUCANTS
RESPONDENTS
AFFIDAVIT
AND:
BETWEEN:
FEDERAL COURT
No.T-1393-14
Vancouver Registry
O
o
p-^
008
VWII eBMB*ewiiiiewSPBIw
*iiii*wiiiii
ii^jg jg
jgf Affidavit
Victoria Registry
(W;
RESPONDENTS
AND:
AFFIDAVIT
I, Michael Savidant, of Suite 600, Four Bentall Centre, 1055 Dunsmuir Street, Vancouver
I am employed by British Columbia Hydro and Power Authority ('*BC Hydro*') as the
Commercial Manager, Site C Clean Energy Project (the "Project"), and as such have
personal biowledge of the facts hereinafter deposed to except where stated to be on
information and belief, in which case I verily believe them to be true. My responsibilities
under my present position include management of the financial and commercial aspects
2<IOt50.00142/90392628.1
009
-2-
r
T
of the Project and economic evaluation of the Project compared to alternatives. Now
produced and shownto me and marked at Exhibit "I" to this my affidavit is a copyof my
curriculum vitae.
BC Hvdro
'
2.
BC Hydro is a Crown corporation continued under the Hydro and Power Authority Act,
RSBC 1996, c 212. BC Hydro's purposes are set out in section 12(1.1) of that Act, and
are to generate, manufacture, conserve, supply, acquire and dispose ofpower and related
^
I
3.
4.
established by the British Columbia Utilities Commission. BC Hydro must meet its
obligation to serve within in a legal and policy context provided for in the Hydro and
Power Authority Act, the Utilities Commission Act and the Clean Energy Act SBC 2010,
c22.
The Project
5.
The Project is the third dam and hydroelectric generating facility on the Peace River,
downstream from tlie W.A.C. Bennett and Peace Canyon dams and their respective
reservoirs, Williston and Dinosaur. The components ofthe Project are: anearthfill dam,
generating station, and spillways; substation and transmission lines; re-alignment of
Highway 29; quarried and excavated construction materials; worker accommodation;
road and rail access; and a reservoir. Now produced and shown to me and marked as
M
V
240150.00142A)0392628.1
010
T*V
6.
The Site C reservoir will be 83 km long and will extend firom the Peace Canyon dam to
the Site C dam site, whichwill be located approximately 7 km southwest ofFort St. John,
(s**
The reservoir will be, on average,two to three times the width ofthe existing river.
7.
The Project's earliest in-service date is F2024(i.e., fiscal 2024,whichis April 1,2023 to
March 31,2024). The Project is expected to last for more than 100 years.
8.
(a)
The Project is a clean, renewable and reliable power resource that will provide
(b)
The Project, being the third dam onthePeace River, optimizes existing resources
by taking advantage of water already stored in upstream reservoirs to generate
over 35% of tlie energy generated by W.A.C. Bennett dam and associated
generating facility, with only 5% of the reservoir area.
(c)
The Project would produce the lowest greenhouse gas emissions (GHG) per
gigawatt hour of any (non-nuclear) alternative. In addition, GHG emissions firom
hydroelectiic plants are not comparable to emissions from gas and coal-fired
electricity plants. Furtliermore, the specific geography of the Project site results in
lower emissions than even other Canadian boreal hydroelectric facilities, which
(d)
The Project will improve the ability to integrate intermittent clean and renewable
energy resources into the provincial power grid. Power firom intermittent
resources such as wind and run-of-river is dictated by environmental conditions
240150.00142/90392628.1
oil
and therefore cannot be relied on to meet electricity needs when they are needed
(i.e., they have low dependable capacity), nor can they be economically
dispatched in response to changes in market prices. With the addition of the
Project to BC Hydro's system, EC Hydro is able to integrate more intermittent
resources while still beingable to reliably meetits service obligation.
(e)
The Project will create jobs, boost the provincial Gross Domestic Product
("GDP") and increase revenuesto local governments.
(f)
(g)
9.
In addition, the Project was subject to environmental assessment under tlie Canadian
Environmental Assessment Act. That assessment was continued under the Canadian
Environmental Assessment Act^ 2012, when that Act came into force inJuly 2012.
11.
On May 18, 2011, BC Hydro submitted a Project Description Report to the British
Columbia Environmental Assessment Office ("EAO") and the Canadian Environmental
Assessment Agency (the "Agency"), initiating the environmental assessment processes
both provinciaily and federally.
12.
240130.00142/90392628.1
f ^
012
-5-
Also on that day, the Minister and the federal Minister of the
assessment, including a joint review panel (the "Paner). The Ministers released a draft
agreement (the "BC/Canada Agreement") for conducting the cooperative environmental
assessment, which included draft terms of reference ("Terms of Reference") for tihe
Panel..
13.
From October 7 to November 7,2011, the BAG and the Agency sought comments from
Aboriginal groups and tlie public on the draft BC/Canada Agreement, including the
Terms of Reference. The comment period was extended for Aboriginal groups to
December 2,2011.
fS*
14.
On or about February 8, 2012, the provincial and federal Ministers of the Environment
entered into the BC/Canada Agreement. Appendix 1 ofthe BC/Canada Agreement set out
the Panel's Terms of Reference (the "Terms of Reference"). The BC/Canada Agreement
was amended in August 2012 to reflect the Canadian Emironmental Assessment Act,
2012.
15.
The BC/Canada Agreement set out the process for environmental assessment, dividing
the assessment into three components:
(a)
The "Pre-Panel Stage" in whichthe Agency and the EAO oversawthe production
EAO to BC Flydro and set out the issues to be addressed and the information to be
submitted by BC Hydro in the form of an Environmental Impact Statement
("EIS"). The Agency and the EAO were charged with determining when the EIS
was satisfactory and ready for reviewby the Panel.
(b)
Tlie "Joint Review Panel Stage" in which the Panel was appointed. The Panel
determined the sufficiency of the EIS, held public hearings, and produced the
Panel Report; and
240150.00142/90392628.1
r
013
-6\
(c)
The "Post-Panel Stage" in which the Agency and the EAG coordinated public
release of the Panel Report and coordinated referral documentation to federal and
provincial decision makers.
16.
Upon the commencement of the environmental assessment process, the EAG and the
Agency established a Working Group for the environmental assessment of the Project
composed of various local, provincial, federal and territorial government agencies, local
governments and Aboriginal groups, including West Moberly First Nations and Prophet
River First Nations. The Working Group's role was to provide advice to the EAG and
the Agency on issues related to the assessment ofthe Project. The advice was provided
through wntten comments and through meetings including Technical sub-Working
Group meetings.
17.
During the Pre-Panel Stage, which lasted from on or about the beginning of 2012 to
August 2013, the Agency and EAG undertook a consultative and iterative process to
determine the scope of the assessment (set out in the EIS Guidelines), and the adequacy
of the information submitted by BC Hydro in terms of meeting that scope and for
technical merit (set out in BC Hydro's Environmental Impact Statement or "EIS").
18.
The development of the EIS Guidelines took place from Januaiy to September, 2012.
This period included review by the Working Group, a public comment period on the
resulting draft, and another round of review by the Working Group on a further revised
draft. BC Hydro responded to all comments received, including anumber from Treaty 8
Tribal Association.
I
19.
In September, 2012, the federal Minister and the Executive Director ofthe EAG finalized
the EIS Guidelines, and issued them to BC Hydro. Now produced and shown to me and
20.
On January 25, 2013, BC Hydro submitted the EIS to the Agency and EAG, who then
held a review period seeking feedback from the Working Group and the public. BC
Hydro again responded to all comments received including all of the comments fi:om
n
240150.00142/90392628.1
'
014
Following the review period and several technical sub-Working group meetings, the
Agency and EAO directed BC Hydro to amend and supplement the EIS, which EC
Hydro did. On August 1,2013, the Agency and the EAO determined the amended EIS
^
was satisfactory and directed BC Hydro to submit the EIS to the Panel, which BC Hydro
rsfs
did. This commenced the Panel Stage of the environmental assessment. Now produced
and shown to me and marked as Exhibit ^4" is a USB stick that contains an electronic
22.
From August to November, 2013, the Panel undertook a review of the EIS and made a
submittedto the Minister of Energy and Mines in August 2013. This is discussed in more
detail below.
24.
On November 7, 2013, after receiving the additional information from BC Hydro, the
Panel determined tlie amended and supplemented EIS was sufficient to proceed to public
(a|
hearing.
25.
The Panel held public hearings spanning 26 days from December 9,2013 to January 23,
2014. The Panel held general sessions in different communities and community sessions
aimed at hearing directly from Aboriginal community members, including a day in the
West Moberly community (December 16). Theremaining hearing days were dedicated to
specific topics identified by the Panel.
26.
On May 1, 2014, the Panel issued the Panel Report. On May 8,2014, the EAO andthe
Agency released the Panel Report to the public.
240150.00142/90392628.1
015
27.
On October 14,2014, the Ministers issued the Certificate for the Project pursuant to s. 17
of BCEAA. Schedule Bto tlie Certificate isa list of77 conditions with which BC Hydro
must comply. Now produced and shown to me and marked as Exhibit "5** is a copy of
the Enviromnental Assessment Certificate issued to BC Hydro for the Project.
28.
2014-1105 recording his decision under s. 52(4) of CEAA 2012, that "the significant
adverse environmental effects ofthe Site CClean Energy Project proposed by BC Hydro
in British Columbia is likely to cause are justified in the circumstances." The federal
Minister ofEnvironment also released her Decision Statement which included conditions
with which BC Hydro must comply. The Decision Statement was re-issued on November
25, 2014 due to an error establishing the date of the conditions. Now produced and
shown to me and marked as Exhibit "6" is acopy ofthe Decision Statement.
Assessment ofthe Need for the Proiect and Timing ofthe Need for the Project
29.
In Chapter 5of the EIS, BC Hydro described the need for the Project and presented a
comparative analysis of alternatives to the Project. Now produced and shown to me and
marked as Exhibit "7" is acopy ofChapter 5ofthe EIS.
30.
Beginning in January 2011, afew montlis prior to initiating the environmental assessment
above in paragraph 21) is aUSB key that contains an electronic copy ofthe IRP.
The IRP was prepared by a team of BC Hydro employees and consultants with
pieparation of the sections of the IRP that deal with the Project. It is an extensive
document encompassing thousands of pages that underwent thorough review from 2011
until its approval in November 2013.
32.
The IRP includes BC Hydro's long-term forecasts of its energy and capacity
requirements and BC Hydro's plans to meet those forecasts with new energy and capacity
016
resources. Energy is the amount of electrical energy that can be generated over a period
of time. Capacity is the rate at whichelectrical energy can be generated at any one time.
Dependable capacity is the capacity that can reliably be counted on during peak demand,
and firm energy is the energy that can reliably be counted on as being available &om a
facility over a one-year period. In order to meet its service obligation, BC Hydro must at
all times be able to reliably count upon a certain amount of energy and capacity, which
means a certain amount of firm energyand dependable capacity. The Project will provide
5,100 gigawatt hours of energy, over 90% of which is firm energy, and 1,100 megawatts
of dependable capacity.
33.
As required by the Clean Energy Act, the IRP addresses how muchcapacity and energy
will be required to meet future electricity needs of BC Hydro's customers while
achieving self-sufficiency, and what new resources should be advanced to meet those
needs. Now produced and shown to me and collectively marked as Exhibit "8" is a copy
The analysis in the IRP demonstrates that new capacity resources will be required by
F2019 and new energy resources will be required by F2027 when no demand (or load)
for liquid natural gas ("LNG")facilities is takeninto account Whentaking into account a
low-load arising from LNG facilities (800 GWh/year energy),capacity resourcesare still
required by F2019 and energy resources will be required by F2024. Under what BC
Hydropredicted to be the expected demand from LNG facilities (3,000 GWh/year energy
and 360 MW capacity), the analysis in the IRP demonstrates thatagain capacity resources
are required in F2019, and energy resources will be required by F2022.
r=n
35.
The IRP ultimately made a number of recommendations flowing from these analyses and
the otheranalyses found in the plan, including thatthe Project be advanced for its earliest
in-service date.
36.
A draftof the IRP was submitted to theMinister of Energy andMines pursuant to section
3 of tlie Clean Energy Act on August 2, 2013, who then sought further revisions. BC
Hydro revised the IRP, sought input on the revisions from the public and Aboriginal
240150.(10142/90392628.1
017
-10-
groups, and a final version of the IRP was submitted to the Minister in November, 2013.
On November 25, the Lieutenant Governor in Council issued Order in Council No. 514
approving tlie IRP pursuant to section 4(1 )(a) of the Clean Energy Act. Now produced
and shown to meand marked as Exhibit "9" is a copy of Order in Council No. 514.
37.
lower and higher new electricity requirements, lower and higher electricity and gas
market prices, higher Project costs, reduced cost of capital of IPP resources, and lower
and higher costs associated witli integrating wind resources into the BC Hydro system.
Now produced and shown to me and marked as Exhibit "10** Is acopy ofthe Evidentiary
Update to the EIS that BC Hydro submitted to the EAO and Agency.
38.
In the EIS( and updated in the Evidentiary Update), BC Hydro conducted an analysis of
alternatives to the Project, and concluded the Project provides the best combination of
39.
The Panel similarly concluded that B.C. will need new energy and new capacity at some
point, and that the Project would be the least expensive ofthe alternatives and that its cost
advantages would increase with passing decades as inflation makes alternatives more
costly (page 305 ofthe Panel Report).
40.
With respect to the timing oftlie need for the Project, the Panel concluded that "the
Proponent has not fully demonstrated the need for the Project on the timetable set forth"
(at page 306). This latter conclusion was based on a finding set out earlier in the Panel
Report, in which the Panel found "under the Low Liquefied Natural Gas case, available
resources could provide adequate energy and capacity until at least 2028" (page 304).
240150.00142/90392628.1
018
-11 -
41,
There are two things to note with respect to this conclusion of the Panel, one relating to
tlie Panel's conclusion on when new energy will be required, and one relating to the
Panel's conclusion when new capacity will be required.
42,
First, after reviewing the analysis of the Panel that led to the conclusion that available
resources could provide adequate energy until at least 2028, a numberof persons at BC
Hydro, includingmyself, identified an error in the Panel's calculations.
43,
issue ofthe timing ofneed for the Project. I assisted inthe preparation ofthat letter. Now
produced and shown to me and marked as Exhibit "11" is a copy of Ms. MelcWor's
letter dated May 9,2014.
44.
The letter identifies that, although the Panel's view was that the correct load forecast to
use was the low-LNG load scenario, it did not incorporate low-LNG load into its load
resource balance figures in its calculations (shown in Tables 16 and 18 of the Panel
Report). As a result of tliis exclusion, the Panel Reportshowsthat there is a need for new
energy resources in 2028. However, as shown by the revisedtables in BC Hydro's May 9
letter, when low-LNG load is incorporated tlie need for new energy resources is 2024.
Tliis is consistent with the IRP and tlie Evidentiary Update.
45.
On June 10, 2014, the Panel issued an errata to the Panel Report on a number of matters
including correcting the error identified by BC Hydro. The Panel's errata confirms the
calculation error in the Panel Report, but states, without explanation, its conclusions
remain the same. Nowproduced and shown to me and marked as Exhibit"12" is a copy
of the Errata issued the Panel on June 10,2014.
46.
The second point is with respect to the need for new capacity resources. The Panel's
reference to "available resources" includes two resources that it refers to as "capacity
additions" that are not yet in existence and that BC Hydro does not currently intend to
construct. Those are "Revelstoke 6" which is the addition of a new turbine in the
Revelstoke Dam, and upgrades to five of the turbines at GM Shrum power plant ("GM
240150.C0142y^0392628.I
019
-12-
Shrum upgrades"), which is the facility associated with the W.A,C. Bennett dam. While
each of these resources would provide additional edacity, they would provide littleto no
energy. Eachof these projects would require anenvironmental assessment certificate and
consultation witli any potentially impacted First Nations before they could proceed.
47.
In the IRP, advancing Revelstoke 6 and GM Shrum upgrades were considered in the
resource planning analysis. The IRP concluded tliat Revelstoke 6 and GM Shrum were
48.
best viewed as contingency resources (i.e., a potential future resource should the need
arise), and not asresources to actively pursue.
'
In contrast, with respect to the Project, the IRP stated: "The IRP analysis demonstrates
that, even in a no LNG load scenario, portfolios with Site Care more cost competitive
than portfolios without Site Cregardless of whether the 7 per cent natural gas-fired
generation headroom is used. Based on these results, it is prudent to continue with the
current regulatoiy window and maintain Site C's earliest ISD ofF2024, given that it is
cost-effective at its earliest ISD, and there is a need for capacity prior to and a need for
energy shortly after the earliest ISD." (p. 6-70)
Harm toBC Hydro and Others Arising from Delay in Construction
49.
50.
51.
In this affidavit, Iexplain the cost ofpotential delay to construction activities of3months
and 6months, both ofwhich are expected to result in an overall project delay ofone year.
If the delay is longer than one year, the cost of delay would be substantially higher than
what is set out in this affidavit.
52.
BC Hydro has awarded or intends to award an estimated 22 contracts for site prqparation
and site services work in 2015, including for: clearing and other general site preparation
work; construction power; site communications; upgrades to public roads; public safety
240150.00142y110392628.1
020
-13-
buoys and booms; security and other site services. The total estimated value of diese
contracts is approximately $185 million. The total aggregated value of the contracts
entered into after January 2015 is approximately $100 million. These contracts were
vr?>
53.
companies owned by First Nations. The remaining contracts are to be awarded through a
competitive procurement process.
54.
fSsj
To date, BC Hydro has entered into 4 contracts with 3 different companies either owned
by a member of one oftheFirst Nations that isa signatory to Treaty 8 or injointventures
>vith signatories to Treaty 8. These contracts are for clearing, construction ofa temporary
bridge, and security services. They are:
F\
(a)
North Bank Clearing awarded to Paul Paquette and Sons Contracting Ltd. on
December 19,2014;
(b)
(c)
(d)
55.
56.
In addition to the site preparation and site services contracts, BC Hydro has completed a
240150.00142/90392628.1
021
14 -
Hydro selected ATCO Two Rivers Lodging Group ("ATCO") as the preferred proponent.
BC Hydro has entered into an interim contractual secernent with ATCO, and the full
contract is expected to be awarded in September 2015.
57.
58.
BC Hydro has also funded a contract between the Ministry of Transportation and
Infrastructure ("MOTr) and private contractor for upgrades to existing roads. This
'
the contracts listed below and expects it will be entering additional contracts in the near
future. In particular:
(a)
activities on the South Bank, including construction of site roads and the south
communications tower. Note that this is a direct award and is further to First
Nations commitments.
(b)
(c)
(d)
59.
activities in 2015:
(a)
(b)
240I50.00I42/90392628.
-I
022
-15-
(c)
60.
Environmental monitoring;
In the next 12 months, BC Hydro also intends toaward large contracts for thefollowing:
(a)
(b)
(c)
frtV
(d)
61.
Delays in construction start will gaierally increase the cost of construction of theProject
There are several reasons why this is the case. The extent to which each may result in a
cost increase will vary witli the circumstances. The reason for increases in cost are as
follows:
(a)
Direct costs incuned because construction activities have commenced and costs
have been incurred, including demobilization and remobilization, standby costs,
additional management costs of contractors currently working on site, and costs
associated with tlie requirements to find new sources ofwater and site power that
will be required as the current sources of water and power rely on provincial
permits;
(b)
F*!
(c)
240150.00t42ffl0392628.1
023
-16-
(d)
staff, supplies, and rent costs for the additional term ofconstruction;
(ii)
^ .
(iii)
62.
Longer delays will result in relatively greater cost increases because the options for
accelerating work become more constrained. They will be less efficient, require more
costly measures, and have higher risks associated with them.
63.
64.
^
.a
on procurement processescurrentlyunderway.
BC Hydro currently plans toreceive technical and financial submissions from proponents
for the Main Civil Works contract on September 19and October 11,2015 respectively.
The anticipated value of this contract is greater than $I billion, and is the largest and
^
^
longest contract to be awarded as part of the Project. The procurement process has been
underway since April 2014.
I
65.
A 1 month, or longer, suspension of work pursuant to the provincial permits would result
in proponent submissions for tliis significant contract to be delivered while work on the
Project is largely stopped and would create uncertainty regarding the site conditions on
which the proponents based their bids. The inability to continue with work and the
1 *
66.
In these circumstances, it would not be prudent to close the bidding on the Main Civil
Works contract during aperiod ofwork suspension. BC Hydro would therefore delay the
delivery of the proponents' bids until such time as sufficient certainty existed, which
js
240150.00142/90392628.1
'
024
-17-
would not arise until any injunction was lifted. The delay in the delivery of bids would
subsequently delay the award of the contract and the date when the Main Civil Works
contractor can begin work.
67.
lasted for 1 or more months would cause the Main Civil Works procurement process to
be delayed for that same period of time until the process could be resumed. At thattime,
the proponents would require additional timeto revise their bids, which are almost final,
based on whatever changes incircumstances arose asa result of the delay (e.g, because a
number of activities, such as clearing, are constrained byseason, a 3-month delay would
involve re-consideration ofconstruction sequencing). For example, a 3-month injunction
at this point in tlie procurement process, therefore, at best is likely to result in a delay in
the procurement process of 4 to 5 montlis.
68.
Due to the delay in the procurement process, the Main Civil Works contractor selected
would also lose time from its construction schedule. A delay of this duration risks
missing critical deadlines for river diversion (fall 2019) and construction of the RCC
_
rss,
buttress (fall 2017). Construction ofthe RCC buttress, for example, requires the purchase
and delivery of an RCC batch plant, used to process the roller compacted cement This
plant require a long lead-time inthe vicinity of 12 months from ordering towhen they are
operational (for fabrication, delivery and trial placements). These batch plants must be
operational before the end of the 2016 construction season to meet the deadline for
^
^
69.
Given these ti^t schedules, an injimction of any length will potentially result in a one-
year delay to the overall project schedule due to the need toperform certain construction
within a single season and because of the limited diversion window. If a delay of more
than one montli results from the injunction, BC Hydro believes it highly likely that the
current project schedule could not be maintained, and there would likely be a one-year
delay in the overall project schedule and in-service date A longer delay of 6 months or
more would make a one-year delay to the project schedule virtually certain. The impact
pa,
240I50.00I42/90392628.I
025
18-
70.
somewhere between $100 million of additional costs and a one year delay in the overall
procurement process for the Turbines and Generators, negotiating a final Project
processes for the permanent substation and transmission lines. These contracts represent
approximately $1 billion in cost in total. A delay of one year to the project schedule
would require substantial changes to the schedule of this work while within the
71.
procurement process, would likely delay the finalization of these contracts by several
'
Aone year delay to die construction of the Project will significantly increase the capital
costs of the Project. In January and February 2015, BC Hydro provided affidavits swom
as part ofthe judicial review proceedings in Federal Court and B.C. Supreme Court
respectively. BC Hydro estimated that the anticipated cost ofa one-year delay, effective
at that time, was $175 million. Now produced and shown to me and marked as Ebthibit
"13" is a copy ofmy affidavit (without exhibits) that 1affirmed on February 13, 2015,
filed by BC Hydro in British Columbia Supreme Court No. 14 4690 in the Victoria
^
'
Registry (moved to Vancouver Registry SI53242). The facts contained in that affidavit
were true at the date on which it was affirmed.
72.
After receiving West Moberly First Nations and Prophet River First Nation^s Notice of
Application, BC Hydro has updated its analysis ofthe capital cost impact ofa one-year
delay in Project construction based on the current stale of constmction. The analysis
demonstrates that a delay in the project completion date by one year would be expected
to result in further increased costs of $160 million beyond the original $175 million
estimate, for a total cost impact of$335 million. The $335 million cost impact is broken
down as follows:
(a)
240I50.00I42/90392628.I
026
19
(i)
f=i
(ii)
(iii)
(iv)
(b)
$100 million of additional allowance for inflation due to shifting spending into
future periods, which are expected to have higher prices due to und^lying
IpSfi
inflation.
(c)
$135 million of increased interest costs due to future higher rates and an
next year.
73,
This analysis assumes that a delay of one-year would be known by the end of August
2015, allowing BC Hydro to mitigate even further costs by rescheduling key work and
delay procurement of major contracts. If BC Hydro proceeds on the basis that it will be
subject to a shorterdelay that will not cause it to losea construction season,then a longer
This estimate is substantially larger than the estimate of$175 million for a one-year delay
in construction that I provided in January and February 2015 in affidavits sworn as part
{ssl
of the judicial review proceedings in Federal Court and B.C. Supreme Court seeking to
quash the Decision Statement and Environmental Assessment Certificate respectively.
There are several reasons for the increased costs at this time:
(a)
At the time of the previous estimate, construction had not commenced. Because
construction has now commenced, a delay at this time will result in a number of
directcosts that did not existin January and February 2015. In particular,
240150,00142/90392628.1
Ml
027
-20
(i)
(ii)
Several contracts are underway and pausing tliese contracts for any period
of time will result in demobilization and remobilization costs;
(iii)
(b)
Costs due to inflation are liigher based on current indicators than when the
analyses in January and February were conducted;
(c)
Interest once construction has commenced ishigher due todirect costs incurred to
date, and costs that will be incurred in the next year (e.g., construction of worker
accommodation camp and upgrade topublic roads will continue asthose contracts
have been entered into and the work does not require permits).
75.
The number of persons expected to be employed during construction in the next three
months that will be directly impacted due to a suspension of construction activities
requiring provincial permits isestimated to be 349 persons. This includes:
(a)
60 persons employed by Paul Paquette and Sons, who is conducting the North
Bank Clearing and South Bank Clearing work;
(b)
(c)
An average of83 persons employed by the South bank site preparation contractor.
A contract for this work isanticipated to be signed later this week;
(d)
(e)
2<tOfSO.OOI42/90392628.1
028
- 21 -
(f)
76.
In addition to the impact on individuals duectly employed at site, a delay will have a
77.
In addition, there are other contractors working on site conducting construction activities
that do not require provincial permits. An extended delay maymean BC Hydro will be
forced to suspend work on these contracts to avoid incurring additional costs to
ratepayers. Tliese include the construction of the worker accommodation camp, being
conducted by ATCO Two Rivers Lodging Group who employs an average of 133
persons for August to October 2015 under its contract with BC Hydro with respect to the
Project; security services conducted by Saulteau Securiguard Security who employs an
78.
I have reviewed the affidavit of Philip Raphals affirmed on July 7, 2015 filed in this
proceeding by West Moberly FirstNations and ProphetRiverFirst Nation, including the
report Mr. Raphals attached as Exhibit 2.
79.
The analysis set out in Mr. Raphals' report is fundamentally flawedthroughits assertion
that costs avoided in a specific year are costs that ratepayers will not ever pay. This is
incorrect as tlie costs are only deferred and not avoided. Mr. Raphals achieves this result
by limiting his analysis to a small period around the Project's in-service date ratherthan
looking at the full costs to ratepayers.
80.
~
Mr. Raphals asserts that bybuilding the Project oneyearlater, ratepayers will avoid $500
million in costs. He relies on the fact that when the Project enters service it will begin
recovering itsaimual costs offrom ratepayers, and asserts that ifthe project enters service
one year later this means that ratepayers will avoid paying the annual costs for this year
ofdelay. Delaying the Project by one year does not avoid costs. Itonly shifts the recovery
24OISO.O0M2/9O392628.I
t=
029
-22-
^
'i
of costs into the future by one year. At the same time such a delay will increase the
capital costs of the Project and require the purchase or construction of additional
electricity resources. All of these effects serveto increasethe overall cost to ratepayers,
n
81.
Mr. Raphals' analysis also assumes that dependable capacity can be found on the open
market In the electricity market that BC Hydro primarily trades with for imports and
exports (the Mid-C market), capacity is notgenerally found as a firm product similar to a
BC-based generation resource. The Mid-C market for capacity is an undeveloped and
illiquid market, and it would not be prudent for BC Hydro to rely on this market for a
Hydro would likely instead look to potential other generation options, such as
construction of Revelstoke 6 or the GM Shrum upgrades, either of whichhas capitalcosts
82.
If the Project is subject to a delay of one year beginning this month, capital costs of the
additional independent power producer contracts that are not required if the in-service
date ofthe Project isnot delayed. Under BC Hydro's expected load forecast and mid-case
83.
The one mitigating factor of delaying by one year is that recovery of some of the capital
costs from ratepayers would also be delayed by one year. This later recovery has some
benefits because ofthe time value of money. BC Hydro undertook an analysis reflecting
the time value of money in thefall of 2014. Under its expected load forecast, the analysis
demonstrated that delay would result in harm to BC Hydro ratepayers. BC Hydro
reviewed the sensitivity of this result to low and high loadsand determined that, at best,
BC Hydro ratepayers would see no substantial costs or benefits in the low load scenarios
and significant costs in the expected and high load scenarios. This is consistent with the
84.
n
i 1
Under Mr. Raphals' analysis, it would not be economical to build any new project of
significant size because in the first years of service it would result in a surplus of energy.
1^
240150.00142/90392628.1
030
23-
and based on current forecasts the spot market prices are cheaper than the cost of new
FH
achieve self-sufficiency set out in the Clean Energy Act and does not take restrictions on
tlie amount of electricity BC Hydro can reliably import.
85.
A two year delay would result in further increased costs to ratepayer as a result of
additional increases to the project capital costs as well as increased requirements
electricity purchases that would not otherwisebe required.
^^tish Colurabi^
240150.00142/90392628.1
MICHAEL SAVIDANT
031
Registry: Victoria
In the Matter of the Judicial Review Procedure Act,
R.S.B.C. 1998, c. 241
Between:
PS
PS
And
E.K. Christie
J.J. Oliphant
Counsel for the Respondent, BC Hydro:
C.F.WIIIms
Victoria, B.C.
August 18-20,2015
msdSbdWiiBMiieili
A CelwlitadofitriBrMdfiil
Mdtvlts for BrilMiColUfrM
Vancouver, B.C.
032
n
i
Prophet River First Nahon v. British Coiumbia (Forests, Lands and Natural
Resource Operations)
[1]
Page 2
injunction restraining the respondent, BO Hydro, from carrying out any work
p(
pursuant to the permits listed atAppendix Ato the petition until the petition is
decided on its merits or further order of the court. As this is an urgent application that
seeks immediate relief, I have elected todeliver brief reasons today rather than take
a longer time to prepare reasons commenting fully on the lengthy arguments made
before me. In arriving at my decision Ihave, however, taken all of the submissions
^
i
[2]
The petitioners are First Nations who are adherents to Treaty 8and have
traditional territories and treaty rights to hunt, trap, andfish in areas thatwill be
adversely affected by construction of the Site 0 dam on the Peace River. The
to permits issued to itby the Province of British Columbia. The permits authorize BO
Hydro to begin site preparation, theclearing ofsome areas, construction ofroads,
and begin construction oftheworks necessary to divert the Peace River to permit
[3]
The petitioners allege that the permits were issued without adequate
m
consultation and accommodation with respect to their Aboriginal and treaty rights
and that they should, accordingly, be quashed or suspended until the Government
and BC Hydro meet their constitutional obligations to them. BC Hydro submits that
the permits have been validly issued and that it is entitled to proceedwith the work
authorized by them. It, supported bythe Attorney General,submitsthat the
petitioners have had ample time to consult with respect to the permits and that the
petitioners' real objective is to stop the Site-C project from proceeding at all rather
than to be consulted about the merits of the permits in issue on this application.
[4]
The petitioners submit that they will suffer irreparable harm if the work
continues until a hearing ofthispetition from the destruction of habitat necessaryfor
the carrying outoftheir traditional activities and from the very fact ofbeing deprived
r?
033
Prophet River First Nation v, British Coiumbia (Forests, Lands and Naturai
Resource Operations)
Page 3
[5]
BC Hydro submits that it will suffer irreparable harm ifthe work is delayed for
any significant period because it has already mobilized the resources necessary to
construct the massive project involved and has, in fact, commenced with
construction of the project and that itwili cause serious damage to its construction
schedule ifwork is halted even for a short time pending a decision in this case.
[6]
r
The hearing of the injunction application occupied three days. In their able
submissions, counsel for all parties raised many interesting arguments both factual
and legal. In these reasons, as I have already indicated, I do not find it necessary to
refer to most of the submissions, particularly those dealing with the merits of the
underlying petition. In my view, the outcome of this application turns on the
r=^
as in many such cases involving injunctions, I must decide which party will suffer the
greater harm from any decision I make in this case.
[7]
consultation with respect to the permits in issue in this case. Their position is that the
parties agreed from an early stage that consultation with respect to the permits
would be complex. They submit that the Government and, in this context, I include
p-t
project.
[8]
The petitioners say that the Government agreed that consultation with respect
fn
specifically for Site-C. However, the only process agreement that was concluded
was an agreement known as the Site-C custom consultation process negotiation
agreement, which I will refer to as the negotiation agreement, which was signed on
April 14,2015. This agreement was intended to guide the negotiation of a further
034
Prophet River First Nation v. British Columbia (Forests, Lands and Natural
Resource Operations)
Page 4
H
(B)
'
[9]
theirposition that the parties only intended to conduct limited consultation prior to
execution of the consultation agreement. Theysay they were handicapped even in
that limited scope of consultation by the failure of the Government to provide
$350,000 in capacity funding that itagreed to pay in the negotiation agreement until
fim
one month after the execution of the negotiation agreement. They say that the
agreed limited scope of consultation inthe first group of permits supplied to them for
consultation. The petitioners say that, despite the terms of the negotiation
agreement, the late payment ofcapacity funding and the increased scope ofpermits
under consideration by BC Hydro and the Government, the Government issued the
^
^
[10]
'
disruption of water quality from the clearing operations in which BC Hydro will be
/H
engaged will cause irreparable harm to the exercise of their treaty and constitutional
rights.
[11 ] The petitioners are not in a position to offer the usual undertaking as to
damages in this case, but submit that this is an exceptional case in which the court
can and should exercise its discretion to dispense with the undertaking.
[12]
The respondents submit that the petitioners have had adequate time to
consult on the permits and have known since 2014 that BC Hydro intended to
proceed with preliminary work on the project beginning in the summer of 2015. The
respondents say that the petitioners have not pursued consultation with respect to
n
p
p-1
035
Prophet River First Nation v. British Coiumbia (Forests, Lands and Naturai
Resource Operations)
Page 5
the permits diligently or in good faith. The implication that I took from submissions on
behalf of BC Hydro, in particular, is that this application is part of a Fabian tactic on
the part of the petitioners to delay the project from proceeding until circumstances
change and the project may be permanently shelved.
[13]
On the view I take of the dispositive issue on this application, 1do not find it
necessary to explore the merits of the parties' positions any further. I am, however,
satisfied that the petitioners have raised a fair question with respect to the adequacy
of consultation and as to whether the Government has complied with the terms of
the negotiation agreement and the other understandings with respect to consultation
with respect to the permits.
[14]
The parties agree on the essential test for the granting of interlocutory
injunctive relief. The test has been described as having either two elements in
Attorney General v. Wale (1986), 9 B.C.L.R. (2d) 333, or three elements in RJR"
MacDonald Inc. v. the Attorney General of Canada, [1994] 1 S.C.R. 311. The
difference between the two formulations of the test is over whether the questions of
irreparable harm and balance of convenience are elements to be considered
separately by the court or whether they should be considered together under the
1.
Has the applicant raised a fair question for trial or, in this case,
disposition at the hearing of the petition;
2.
3.
[15]
036
Resource Operations)
Page 6
these two elements together because, in this case, there is evidence from both
parties indicating that a decision adverse to them would cause them irreparable
harm. In this case, however, I am satisfied that the balance of convenience weighs
'
^
r
/
[18]
harm rather than the magnitude of harm that must be considered. However, in
p,
great importance. I am simply not satisfied that the petitioners have shown that any
serious long-term harm will be caused to their interests ifthe work contemplated
over the next three months proceeds pending the hearing of the petition in this case.
^
fn
In the course of argument, Iwas struck by the lack of specificity in the evidence
about harm to the petitioners' interest. Iwas presented with no evidence of any
impacted in the three months between this hearing and the date set forthe hearing
of the petition.
i
[19]
037
Resource Operations)
effects if the work proceeds, it nevertheless issued the permits. In my view, the
information referred to bycounsel did not provide an adequate basis on which I
could conclude that serious long-term harm will be suffered bythe petitioners if the
works proceed pending the resolution ofthe issues raised in this petition.
[20] The most serious harm addressed in the petitioners' evidence related to the
loss ofold growth ornear-old-growth forest that would result from the clearing of
forests in preparation for an inundation by the reservoir. However, almost all of that
evidence related to clear-cutting along the Moberly River in the area to be inundated
ifthe reservoir is created. In the course of the hearing, BC Hydro gave a formal
[21] In my view, the other examples of harm relied upon by the petitioners were
largely theoretical and speculative. In addition, the evidence thatwas before the
court seemed generally to support the submissions of BC Hydro that there would be
a relatively minor impact on important values from the activities that will be
undertaken between now and the end of the year.
p-r,
1*1
[22] I also accept the submission of BC Hydro that the loss ofan adequate
opportunity to be consulted is not in and ofitself irreparable harm. This is particularly
so In a case such as this when the adequacy of consultation is the very issue that
the court will be asked to decide at the petition hearing and when the court is not in a
position to make any finding with respect tothat question on the application for the
injunction. In this regard, Irespectfully adopt the analysis ofWilcock J., as he then
was, of this court in Sunshine Logging v. Prior, 2011 BCSC 1044, at paragraphs 30
to 34.
[23]
On the other hand, BC Hydro has satisfied me that both itand its contractors
and suppliers will suffer considerable harm from even a relatively short disruption of
the construction schedule. I need not recite the evidence in detail with respect to this
038
Prophet River First Nation v. British Coiumbia (Forests, Lands and Natural
Resource Operations)
Pag 8
Watson that a delay ofthree months would result in a serious risk that the project will
be delayed for a full year and the evidence of Mr. Savldantthat a one-year delay on
the duration of the project will result In very substantial Increases In project costs,
[24]
cases Involving Aboriginal rights with respect to the requirement for an undertaking
[25]
I am aware that the petitioners have tendered evidence from Mr. Raphals to
the effect that there will be no net loss to the petitioners or the public from a oneyear delay In the completion of the project. However, I have decided that I cannot
receive that evidence because Iam notsatisfied that Mr. Raphals has the necessary
qualifications to give theopinion relied upon by the petitioners. The opinion given by
Mr. Raphals Involves sophisticated financial analysis offuture costs and the
availability of future alternative sources of power as well as future demand. There is
n
n
11
[26] I am, therefore, left with theonly evidence ofthefinancial Impact ofthe delay
and disruption ofthe construction schedule coming from BC Hydro's witnesses.
While I appreciate that that evidence Isdesigned to showthe worst case scenario for
BC Hydro, I am satisfied that, even viewed conservatively. It shows that serious
harm will be suffered by BC Hydro and Its suppliers and subcontractors Ifwork Is
enjoined for the three to five months necessary to hear and decide the petition.
039
Prophet River First Nation v. British Coiumbia (Forests, Lands and Naturai
Resource Operations)
Page 9
[27] Finally, with regard to the balance ofconvenience, I take into accountthe
impact of the order sought on BC Hydro's suppliers and the public in general as well
as theiremployees. As in the case of BC Hydro, the persons in this category will
have no remedy for any losses theysuffer as a result ofthe granting ofthe relief
sought by the petitioners.
[28]
Forall of the above reasons, I have decided that the application for injunctive
[29]
No. S-160488.
Vancouver Registry
IN THE SUPREME COURT OF BRITISH COLUMBIA
BETWEEN;
AFFIDAVIT
240150.00163/90624881.2