Академический Документы
Профессиональный Документы
Культура Документы
BUILDING WORKS
Hong Kong Standard Method of Measurement of Building Works - Fourth Edition
Authorised between
The Hong Kong Institute of Surveyors,
The Hong Kong Construction Association Ltd.,
The Hong Kong Government Architectural Services Department,
The Hong Kong Institution of Engineers,
The Hong Kong Electrical & Mechanical Contractors Association,
The Chartered Institution of Building Services Engineers, and
The Association of Cost Engineers (Hong Kong Region).
Copyright:
ISBN:988-98402-4-3
All rights reserved. No part of this publication covered by the above copyright may be reproduced, stored in a retrieval system or
transmitted in any form or by any means without the prior permission of the copyright owners.
BUILDING SERVICES
Representing the Architectural Services Department
Mr. Y. K. Chu
Representing the Hong Kong Construction Association Ltd.
Mr. C. M. Yung
Representing the Hong Kong Institute of Surveyors
Mr. Sam Cheng (Chairman)
Representing the Hong Kong Institution of Engineers
Mr. Howard Lok
Mr. C. K. Wong
Representing the Hong Kong Electrical and Mechanical ContractorsAssociation
Mr. Steve Griffin
Representing the Chartered Institution of Building Services Engineers
Mr. Victor Cheung
Representing the Association of Cost Engineers (Hong Kong Region)
Mr. C. Y. Wong
Representing the Standing Sub-committee for the Building Works SMM
(as Co-ordinating member)
Mr. K.E.N. Goodbourn
ii
January, 1962.
iii
June, 1966.
iv
The Committee expresses its special gratitude to the Sub-Committee responsible for carrying out so enthusiastically and so thoroughly the monumental task of translating the
Second Edition into Chinese. The members of this Sub-Committee were :Patrick D. P. Woo (Chairman),
John S. King (Secretary),
W. K. Chang,
David Y. C. Cheung,
K. S. Lau,
John H. P. Lok,
Charles C. C. Wong.
The members of the Standing Joint Committee are :Representing The Royal Institution of Chartered Surveyors (Hong Kong Branch) :B. J. White (Chairman)
K. E. N. Goodbourn
D. G. Levett
Representing the Building Contractors Association of Hong Kong :John H. P. Lok
Charles C. C. Wong
John W. L. Loo
Other gentlemen who have served on the Committee during the preparation of this edition are :H. Miller, the Chairman of the Joint Committee from its inception until his retirement from Hong Kong, R. B. Hanna and Geoffrey M. T. Yeh.
September, 1978.
vi
vii
SUMMARY OF CONTENTS
Preface
Preface
Preface
Preface
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII
XIII
XIV
XV
XVI
XVII
XVIII
XIX
XX
XXI
XXII
to
to
to
to
i
iii
iv
v
1
3
9
19
25
45
57
75
81
85
91
97
99
117
119
143
153
171
183
191
195
201
205
207
DETAILED CONTENTS
(List of Sections)
(See also the Alphabetical Index on Page 205)
I
II
III
PRELIMINARIES
1
3
7
9
9
10
11
19
(a)
(b)
(c)
(d)
19
21
23
23
APPENDIX A
IV
VI
Demolitions
Alterations
Temporary Screens and Temporary Roofs
Shoring
VII
VIII
IX
X
25
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
25
25
28
30
33
36
39
43
XI
45
XII
Piling General
Steel Sheet Piling
Precast Concrete Piles
Cast In-situ Concrete Piles in Driven Casings
Bored Piles
Steel Piles
Caissons
Diaphragm Walling
EXCAVATION
(a) Excavation
(b) Underpinning
45
53
CONCRETE WORKS
57
(a)
(b)
(c)
(d)
(e)
(f)
(g)
57
64
65
66
70
71
73
Concrete
Gun Applied Reinforced Concrete
Reinforcement
Formwork
Precast Concrete Work
Prestressed Concrete Work
Precast Prestressed Concrete Work
75
75
79
81
85
(a)
(b)
(c)
(d)
85
85
88
88
Asphalt
Liquid Membrane Waterproofing
Felt Roofing
Sheet Membrane Waterproofing
STONE WORKS
91
91
94
ROOF TILING
97
97
98
viii
ix
XIII
XIV
XV
WOOD WORKS
99
(a)
(b)
(c)
(d)
(e)
99
100
101
102
Structural Timber
General Clauses
Flooring
Raised Access Floors
Sheet Linings / Claddings, Timber Suspended Ceilings,
Unframed Trims, Insulation, Proofing Works and Fire Stops
(f) Profiled Sheet Roof Coverings and Wall Claddings
(g) Fixed Partitions and Demountable Partitions
(h) Toilet Cubicle Partitions, Office Cubicle Partitions and Fittings
(i) Doors, Hatches, Ventilators and the like and Frames and Linings
(j) Stairs, Handrails and Balustrades
(k) Furniture, Fittings, Shelving, Racks, Playground Equipment etc.
(l) Minor Buildings and Structures mainly of Timber Construction
(m) Insulation / Proofing Works / Fire Stops
103
107
108
110
111
113
114
115
116
IRONMONGERY
STEEL AND METAL WORKS
117
119
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
119
122
123
124
125
127
128
129
131
Structural Steel
Linings, Coverings and Cladding
Roofing and Flashings etc.
Doors, Gates, Shutters, Grilles and Hatches
Framed Work, Stairs, Handrails and Balustrades
Fencing and Gates
Minor Buildings and Structures mainly of Metal Construction
Sundries
Raised Access Floors
(j)
(k)
(l)
(m)
(n)
(o)
(p)
(q)
XVI
XVII
131
133
135
136
138
139
141
142
143
(a)
(b)
(c)
(d)
(e)
(f)
143
143
144
145
148
Spatterdash
Lathing and Plasterboard
General Clauses
In-situ Surface Finishes and Screeds or Backings
Tile and Slab Finishes
Rubber and Plastic Sheet or Carpet Sheet / Tile Finishes
and the like
151
MECHANICAL INSTALLATIONS
153
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
153
154
155
156
160
161
164
166
169
General Clauses
Equipment
Sanitary and Laboratory Fittings
Pipework
Gutters
Ductwork
Insulation
Protective Coverings and Finishings
Sundries
XIX
General Clauses
Equipment and Switchgear
Conduit (except in Final Circuits)
Trunking and Busbar Trunking
Trays and Ladders
Cables (except in Final Circuits)
Final circuits (Cables etc. in Final Circuits)
Fittings and Accessories
Earthing, Lightning Protection and Bonding
Sundries
171
171
172
173
174
175
176
178
179
180
181
183
(a)
(b)
(c)
(d)
(e)
183
184
185
186
189
General Clauses
Equipment
Distribution and Principal Interconnections
Final Circuit Points
Sundries
XX
XXI
XXII
GLAZING
191
191
193
194
PAINTING
195
(a)
(b)
(c)
(d)
(e)
195
197
198
199
199
General Clauses
Painting and Similar Work
Polishing and Clear Finishing
Signwriting
Paperhanging (including Sheet Plastic and Fabric Linings)
LANDSCAPING
201
(a)
(b)
(c)
(d)
(e)
201
201
202
203
203
1.
2.
GENERALLY
1.1
The rules in this document are set out in tables. Each section of the rules comprises information
(to be) provided, classification tables and supplementary rules.
1.2
Horizontal lines divide the classification tables and supplementary rules into zones to which
different rules apply.
4.
APPLICABILITY OF RULES
2.1
CLASSIFICATION TABLES
3.1
Within the classification tables where a broken line is shown, the rules given above and below the
broken line may be used as alternatives.
3.2
In referring to columns in classification tables, the measurement unit column has been
disregarded. The remaining four columns are herein referred to as the first, second, third and
fourth columns.
3.3
The first column lists the items commonly encountered. Each of these items may have one
qualifying sub-item if there is insufficient capacity in the 2nd, 3rd or 4th columns. The second and
third columns list sub-items into which each item or group of items are divided. These sub-items
may contain one or more descriptive features which are not mutually exclusive. The lists in these
columns are not intended to be exhaustive. The fourth column similarly provides for further subdivision, and in addition lists further sub-items that may be required to complete the total
description of the item.
3.4
3.5
4.
Coverage rules draw attention to particular incidental work (both labour and material) which shall
be deemed to be included in the appropriate items in a Bill of Quantities to the extent that such
work is included in the tender documents.
4.4
The column headed Supplementary Information contains rules governing the information which
shall be given in addition to the information given as a result of the application of rule 3.4.
4.5
A separate item shall be given for any work which differs from other work with respect to any
matter listed as supplementary information.
Rules printed above a double line apply to all work following in the Section or Sub-section within
the Section. Other rules apply only to the particular group of items against which they are shown.
5.
3.
6.
DESCRIPTIONS
5.1
The requirements for information to be provided by the application of rules 3.4 and 4.4 may be
fulfilled by reference to other documents or drawings or published information.
5.2
Headings to groups of items in a Bill of Quantities shall be read as part of the descriptions of the
items to which the headings apply.
5.3
The use of a hyphen between two dimensions in this document or in a Bill of Quantities shall
mean a range of dimensions exceeding the first dimension stated but not exceeding the second.
CROSS-REFERENCES
6.1
Each item description shall identify the work with respect to one sub-item drawn from each of the
first three columns in the classification table and as many of the sub-items in the fourth column
as are applicable to the item. The general principle does not apply to Preliminaries in that it will be
necessary to select as many sub-items as appropriate from each column.
Number
from fourth
column
Example:
Formwork
Where the number of units is required to be stated in the item, as for example 300 metres of
precast concrete lintols, in 268 number or, in Building Services Works, 1,000 kg of fabricated
composite support structures, in 168 number, this is stated in the measurement unit column.
VII (d).2.1.1
Formwork to soffits of slabs
slab thickness 200 mm
horizontal
SUPPLEMENTARY RULES
4.1
4.2
Measurement rules set out when work shall be measured and the method by which quantities
shall be computed.
Definition rules define the extent and limits of the work represented by a word or expression used
in the rules and in a Bill of Quantities prepared in accordance with the rules.
6.2
An asterisk within a cross-reference represents all entries in the column in which it appears.
6.3
The digit 0 within a cross-reference represents no entry in the column in which it appears.
HK SMM 4
II
1.
2.
GENERAL PRINCIPLES
BILLS OF QUANTITIES
1.1
Bills of Quantities shall fully describe the materials and workmanship and accurately represent
the work to be executed; work which by its nature cannot be accurately measured shall be
described as provisional. Provisional quantities, items or sections shall represent the work to be
carried out as accurately as is reasonably possible.
1.2
In order to define the precise nature and extent of the proposed work it will be necessary to give,
in descriptions or elsewhere, certain supplementary information including any limits on
tolerances, method, sequence etc. imposed by the designer.
4.
4.2
5.
Each measurement shall be taken to the nearest 10 millimetres (i.e. 5 millimetres and over shall be
regarded as 10 millimetres and less than 5 millimetres shall be disregarded). This rule shall not
apply to any dimensions stated in descriptions.
The following symbols and abbreviations are used in this method of measurement:
m
= metre
m2
= square metre
2.1
This Standard Method of Measurement, whilst aiming at providing uniform units of measurement
and standard allowances, etc., is a definition of principle rather than an inflexible document. In
particular and exceptional cases the Surveyor is expected to use his discretion and to adopt
special methods, provided the principles of measurement laid down are observed and the
intention is made clear to the Estimator.
m3
= cubic metre
mm
= millimetre
nr
= number
kg
= kilogramme
If it is in the interest of accurate and practical estimating, he may give more detailed information
than is demanded by strict adherence to this document.
The method of measurement for work not covered by the clauses of this Standard Method of
Measurement, and also deviations from, or qualifications to, this Standard Method of
Measurement, shall be stated in the Preambles to the Bills of Quantities or in the description of
the items to which they apply. The method adopted for work not covered shall, as far as possible,
conform to that given in this document for similar work.
>
= Greater than/exceeding
<
= Less than
dia.
= Diameter
min.
= Minimum
max.
= Maximum
3.1
Prov
= Provisional
The methods of measurement laid down shall equally apply to the preparation of Bills of
Quantities before the work is commenced and to the measurement of finished work.
6.
4.
PRINCIPLES OF MEASUREMENT
2.2
3.
UNITS OF MEASUREMENT
4.1
(b)
(c)
(d)
(e)
(f)
Items given by time may be given in Days or Hours - if these items are used, they
should be defined.
7.
The Drawings from which the Bills of Quantities have been prepared shall be listed and reference
shall be made to any Specification on which the Bills of Quantities descriptions are based.
6.2
It should be noted that this is a separate requirement to the necessity of listing the Contract
Drawings and, where required by the Contract Document, the Contract Specification, as these
may, in due course, be varied.
UNITS OF BILLING
7.1
Where the unit of billing is the metre, quantities shall be billed to the nearest whole unit.
Fractions of a unit less than half shall be disregarded and all other fractions shall be regarded
as whole units.
7.
8.
Where the unit of billing is the kilogram, quantities shall be billed to the nearest whole unit.
Fractions of a unit less than half shall be disregarded and all other fractions shall be regarded as
whole units.
7.3
Where the application of this Clause would cause an entire item to be eliminated, such item shall
be billed as one whole unit.
7.4
9.
Unless otherwise stated, all work shall be measured net as fixed in its place.
ORDER OF DIMENSIONS
9.1
10.
12.
In giving dimensions the order should be consistent, and generally in the sequence of length,
width and height.
MINIMUM DEDUCTIONS
12.1 Where minimum deductions of voids are dealt with in this document they shall refer only to
openings or wants detached from the boundaries of the space measured.
12.2 Openings and wants caused by projections from the boundary of the space measured shall
always be the subject of deduction, irrespective of size.
14.
DAYWORKS
14.1 As Contractors have differing practices in:
(a)
(b)
payment of overtime rates for hours worked in excess of a normal working day;
(c)
some provision should be made in Dayworks Schedules for the differentials to be priced,
probably as percentage on-costs over the normal working days and normal working hours 08:00
to 18:00 hours. Where shift work is envisaged that should be separately provided for.
DESCRIPTIONS OF ITEMS
10.2 The descriptions of items in Bills of Quantities may refer to other documents or drawings and any
reference to such information shall be understood to fulfil any requirements of these principles of
measurement; alternatively, reference may be made to published information.
- Labour Holidays
- Sundays
and at times:
- 08:00 to 18:00 hours
11.
HK SMM 4
(a)
(b)
Materials, goods and all costs in connection therewith (e.g. conveyance, delivery,
unloading, storing, returning packings, handling, hoisting, lowering);
(c)
(d)
Use of plant;
(e)
(f)
II
14.
GENERAL PRINCIPLES
DAYWORKS (continued)
15.
14.2 Labour shall be paid for on an hourly basis, in the manner suggested above. There should be no
further percentage addition on , the quoted labour rates which will be deemed to include for:
(a)
(b)
Wages, bonuses and all allowances paid to operatives directly engaged on dayworks
(including gangers and charge hands working with their gangs and those operating
mechanical plant and transport) in accordance with the appropriate employment
agreement, or where no such agreement exists, the actual payments made to the work
people concerned;
(b)
16.
(d)
Use and maintenance of small hand tools and appliances, non-mechanical plant and
equipment, such as ladders, trestles, stages, bankers, scaffolding, temporary track,
wagons, skips, tarpaulins and all similar items.
The term Prime Cost Sum shall mean a sum provided for work or services to be executed
by a Nominated Sub-Contractor or for materials or goods to be obtained from a Nominated
Supplier. Such sum shall be deemed to be exclusive of any profit or attendance required by
the Contractor and provision shall be made for the addition thereof.
Site supervision, including the cost of foremen and walking gangers and staff insurances;
(c)
17.
14.3 The costs of materials in dayworks shall be the nett invoiced costs, including delivery to site.
A schedule may be given containing provisional quantities of different materials for the work to
be carried out on a dayworks basis.
18.
A percentage item shall be given to enable the Contractor to quote for the inclusion of
establishment charges, overhead charges and profit.
14.4 The costs of construction plant and vehicles (excluding the cost of operators and drivers who
19.
shall be included in labour above) shall be paid for at the rates entered in the schedule for the net
working hours during which the plant is engaged on dayworks, and excluding any standing or
idle time, except that plant held on standby by written request from the Architect shall be paid for.
The quoted rates will be deemed to include for:
(a)
(b)
Site supervision, hire charges, insurances, consumable stores, fuel and maintenance.
A percentage item shall be given to enable the Contractor to quote for the inclusion of
establishment charges, overhead charges, profit and for any further costs imposed by the above
limitations.
15.
The term Provisional Sum shall mean a sum provided for work or for costs which cannot
be entirely foreseen, defined or detailed at the time the tendering documents are issued;
20.
TEMPORARY WORKS
20.1 Where the Contractor is required to provide, or to take over existing, temporary works,
descriptions shall include, where appropriate, references to provision and erecting or taking over
and repairing, maintaining (duration stated), adapting (details stated), handing over to the
Employer or succeeding Contractor or clearing away and making good all works disturbed.
HK SMM 4
II
GENERAL PRINCIPLES
Systems, together with their equipment, pipework, ductwork, insulation, trunking, ducting, cable trays, conduits and sundries shall be classified as follows and given under appropriate headings.
The wordings in this list are for reference only, and actual wording should follow those used in the drawings and specifications.
DISPOSAL SYSTEMS
Laboratory/Industrial Waste Drainage
Sewage Pumping/Treatment
Incineration Plant
PLUMBING AND WATER SUPPLY, AIR, PETROL, FUEL OIL AND GAS SYSTEMS
Sanitary & Laboratory Fittings
Soil, Waste, Ventilation and Rainwater Pipes
Gutters
Potable Water
Hot and Cold Water
Pressurised Water
Flushing Water
Irrigation
Grey Water
Fountains/Water Features
Treated/Deionised/Distilled Water
Swimming Pool Water Treatment
Air and Gas Supply and Distribution
Compressed/Instrument Air
Medical/Laboratory Gas
Natural Gas
Liquid Petroleum Gas
Vacuum
Steam
VENTILATION/AIR-CONDITIONING/HEATING/REFRIGERATION SYSTEMS
Sea Water
Cooling Water
Chilled Water
Condensate Drainage
General Supply/Extract
Toilet Extract
Kitchen Extract
Car Parking Extract
Smoke Extract/Smoke Control
Safety Cabinet/Fume Cupboard Extract
Fume Extract
Anaesthetic Gas Extract
Dust Collection
Air-Conditioning
Window/Wall/Split Type Air-Conditioning Units
Air Curtains
Systems, together with their equipment, pipework, ductwork, insulation, trunking, ducting, cable trays, conduits and sundries shall be classified as follows and given under appropriate headings.
The wordings in this list are for reference only, and actual wording should follow those used in the drawings and specifications.
COMMUNICATIONS/SECURITY/CONTROL SYSTEMS
Telecommunications
Staff Paging/Location
Public Address/Sound Amplification
Centralised Dictation
Radio/TV/CCTV
Projection
Advertising Display
Clocks
Data Transmission
Access Control
Security Detection and Alarm
Earthing and Bonding
Lightning Protection
Electromagnetic Screening
Building Automation including Central Control
HK SMM 4
VI
EXCAVATION
45
(a)
Excavation
MEASUREMENT
RULES
INFORMATION PROVIDED
1.
DEFINITION RULES
COVERAGE RULES
Generally
SUPPLEMENTARY
INFORMATION
S.1 Special requirements
in respect of upholding
and maintaining the
sides of earthworks
Where practicable the nature of the soil shall be described and attention drawn to any existing trial holes.
MEASUREMENT
RULES
CLASSIFICATION TABLE
2.
Site clearance
nr
5. Cutting turf to be
preserved
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
nr
Item
m2
m2
(a)
Excavation (continued)
MEASUREMENT
RULES
CLASSIFICATION TABLE
2. Site clearance
(continued)
7. Disposal of existing
spoil heaps or rubbish
dumps left by previous
contractors
Item
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
3.
Excavating
1. Surface excavation
0.20 m in average depth
m2
C.3
D.1 The term planking
and strutting means
(a) This work is deemed
everything requisite to
to include for excavating in
uphold the face of
any ground encountered,
excavation other than
getting out excavated
shoring as required to be
(a) 0.25 m from the face
materials by any means
measured
under
item
of concrete requiring
necessary, all levelling or
(a).5
hereof
and
covers
formwork where the
grading and ramming
formwork does not exceed the Contractors
bottoms, trimming sides,
responsibility for
0.60 m in height
planking and strutting and
upholding and maintaining
any extra excavation
(b) 0.60 m from the face
the sides of earthwork by
required therefor.
of concrete requiring
whatever means are
formwork where the
(b) See item (a).5 hereof
formwork exceeds 0.60 m considered necessary.
for temporary shoring and
in height and the bottom
supports for excavation
of the formwork exceeds
into banks for retaining
0.60 m below the starting
walls and similar
level of the excavation
constructions with a face
(c) 0.60 m from the
height > 1.50 m.
finished face of work
(c) Any additional
below ground level where
excavation for working
externally applied dampspace, to that included in
proof coverings or
protection walls are
M.2, that the Contractor
required or where the
may consider necessary
method of construction
and for the subsequent
requires workmen to
backfilling.
operate from the outside
M.2 In measurement of
excavation, an additional
allowance for working
space is included as
follows:
HK SMM 4
46
VI
EXCAVATION
(a)
Excavation (continued)
47
CLASSIFICATION TABLE
3. Excavating
(continued)
2. Excavation to reduce
levels over site > 0.20 m
in average depth
m3
3. Excavation to reduce
levels into sides of banks
m3
5. Surface trenches
MEASUREMENT
RULES
DEFINITION RULES
COVERAGE RULES
D.1 applies.
C.3 applies.
SUPPLEMENTARY
INFORMATION
1. In successive stages of
1.50 m
m3
m3
6. Trenches below
basement level
m3
m3
nr
S.2 applies.
(a)
Excavation (continued)
MEASUREMENT
RULES
CLASSIFICATION TABLE
3. Excavating
(continued)
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
D.1 applies.
S.2 applies.
HK SMM 4
m2
2. Breaking up and
removing brickwork or
blockwork and the like
met with in excavations
m3
3. Breaking up any
removal of stone masonry
walls or slab foundations
and the like met with in
excavations
m3
4. Breaking up
unreinforced concrete
and the like met with in
excavations
m3
5. Breaking up reinforced
concrete met with in
excavations
m3
48
VI
EXCAVATION
(a)
Excavation (continued)
49
MEASUREMENT
RULES
CLASSIFICATION TABLE
5. Temporary shoring
and supports
6.
1. Of excavated material
1. Deposited on site
m3
1. Specified locations,
details stated
m3
Disposal
Item
M.4 applies.
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
S.2 applies.
m3
(a)
Excavation (continued)
MEASUREMENT
RULES
CLASSIFICATION TABLE
7. Backfilling to
excavation
8. Filling to make up
levels or for forming
embankments or
terraces
9. Filling into planters
and the like, positions
stated if not at ground
level
1. 0.30 m in depth,
average depth stated
m2
1. Selected, details stated M.8 Filling into
excavations is measured
--------2. Obtained from materials
2. Special filling materials,
as equal to the void to be
m3
2. > 0.30 m in depth
on site
details stated
filled.
(where part exceeds 0.30
3. Obtained from specified
3. Top soil
m in depth, the whole is
off-site area
4. Fabricated, details
given cube)
4. To be provided by
stated
Contractor from his own
sources
m2
M.9 Filling to make up
--------levels or for forming
m3
embankments or terraces
is measured after
compaction.
m3
1. Arising from excavation
m2
m
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
C.7 applies.
S.5 Method of
compaction
S.6 If deposited and
compacted in layers this
is stated, giving thickness
of layers.
M.9 applies.
M.10Thickness of beds
and filling to make up
levels etc. is measured
after compaction.
m2
m2
HK SMM 4
1. Materials to be used
stated
50
VI
EXCAVATION
(a)
Excavation (continued)
51
MEASUREMENT
RULES
CLASSIFICATION TABLE
13. Surface treatments
1. Formation of slopes
in filling
m2
2. Formation of slopes
to cuttings
m2
3. Trimming exposed
surfaces of rock to
produce fair face
m2
4. Preparation of existing
ground or subsoil areas
for application of top soil
for turfing
1. Method of preparation
stated
m2
6. Herbicide, selective
weed killer or insecticide
treatments
m2
1. Sloping 1 in 7
3. Formation of weep
holes
1. Thickness stated
SUPPLEMENTARY
INFORMATION
S.8 Tolerances
COVERAGE RULES
m2
DEFINITION RULES
m2
1. Fully described
nr
m2
m2
(a)
Excavation
CLASSIFICATION TABLE
MEASUREMENT
RULES
M.14 Measured in
accordance with Section
V (b).6
M.15 Measured in
accordance with Section
V (b).8
M.16 Measured in
accordance with Section
V (c).12
M.17 Measured in
accordance with Section
V (d).11
3. Bored piles
M.18 Measured in
accordance with Section
V (e).8
M.19 Measured in
accordance with Section
V (f).8
M.20 Measured in
accordance with Section
V (g).9
HK SMM 4
nr
M.21 Measured in
accordance with Section
V (h).7
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
S.10 Requirements in
respect of preparation of
surface, straightening
and bending projecting
reinforcement and any
necessary protection
52
VI
EXCAVATION
(b)
Underpinning
53
INFORMATION PROVIDED
MEASUREMENT
RULES
1.
Generally
A description of the work to be underpinned shall be given, stating the length, the depth of the underpinning
and the limit of the length to be carried out in one operation.
MEASUREMENT
RULES
CLASSIFICATION TABLE
2. Temporary supports
to work to be
underpinned
Item
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
S.1 Particulars given
where practicable
(b)
Underpinning (continued)
MEASUREMENT
RULES
CLASSIFICATION TABLE
3.
Excavation
1. Preliminary excavation
down to the base of work
to be underpinned
2. Excavation below the
base of work to be
underpinned
1. In successive stages of
1.50 m, commencing
levels stated
m3
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
HK SMM 4
54
VI
EXCAVATION
(b)
Underpinning (continued)
55
CLASSIFICATION TABLE
MEASUREMENT
RULES
5. Cutting away
projecting foundations
1. Brickwork
2. Stonework
3. Mass Concrete
4. Reinforced concrete,
including cutting
reinforcement
6.
Concrete
7.
Formwork
8.
Reinforcement
9.
Brickwork
10. Tanking
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
CLASSIFICATION TABLE
HK SMM 4
MEASUREMENT
RULES
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
56
VII
CONCRETE WORKS
(a)
Concrete
57
INFORMATION PROVIDED
MEASUREMENT
RULES
1.
Generally
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
(a)
Concrete (continued)
INFORMATION PROVIDED
MEASUREMENT
RULES
1.
Generally (continued)
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
HK SMM 4
58
VII
CONCRETE WORKS
(a)
Concrete (continued)
59
MEASUREMENT
RULES
CLASSIFICATION TABLE
2. Small bases for
fencing posts etc.
1. Sizes stated
nr
3.
1. Thickness stated
m3
Concrete beds
DEFINITION RULES
COVERAGE RULES
4. Thickening to
1. Width and thickness
concrete beds, under
stated
walls, partitions and the
like and under channels
5. Surface water
channels
1. Shape, width,
thicknesses of sides and
base and average depth
stated. Expansion joints
and spacing described
1. Excavation, disposal,
formwork and rendering
described
2. Curved channels
7. Channels formed in
concrete beds
8.
Foundations
9. Isolated stanchion
or column bases
10. Pile caps
1. Formwork described
1. Straight channels
m3
1. Foundations include
attached stanchion or
column bases
SUPPLEMENTARY
INFORMATION
(a)
Concrete (continued)
MEASUREMENT
RULES
CLASSIFICATION TABLE
11. Blinding under
1. Thickness stated
foundations and beams
m3
m2
13. Curbs
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
m3
14. Copings
15. Projecting cills
16. Strings
17. Similar items
HK SMM 4
60
VII
CONCRETE WORKS
(a)
Concrete (continued)
61
MEASUREMENT
RULES
CLASSIFICATION TABLE
18. Suspended slabs
m3
1. Horizontal
2. Sloping 15
m3
COVERAGE RULES
20. Beams
DEFINITION RULES
SUPPLEMENTARY
INFORMATION
(a)
Concrete (continued)
MEASUREMENT
RULES
CLASSIFICATION TABLE
m3
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
1. Casings to beams
2. Casings to stanchions
1. Thickness stated
m3
1. Walls
2. Retaining walls
m3
24. Columns
m3
m3
HK SMM 4
1. Fully described
nr
62
VII
CONCRETE WORKS
(a)
Concrete (continued)
63
MEASUREMENT
RULES
CLASSIFICATION TABLE
28. Structural movement 1. Between two wall faces 1. Descriptions include
joints
steel dowels, formwork,
fillers, temporary fillets
and surface coatings and
formation of rebates or
other labours.
2. In beds
3. In suspended slabs
4. In walls
5. In beams
6. In columns
7. Across beams
8. Across curbs
9. Similar items
1. Cover strips
1. Straight
m2
1. Plane
2. Curved
1. Sizes stated,
descriptions include steel
dowels, formwork, fillers,
temporary fillets and
surface coatings and
formation of rebates or
other labours.
nr
1. Descriptions include
backing rods or materials
DEFINITION RULES
COVERAGE RULES
1. Straight
2. Curved
2. Cover plates
3. Fire stops
2. Curved
3. Joints at intersections
4. Special junction pieces,
including joints
1. Dimensioned
description
m
nr
SUPPLEMENTARY
INFORMATION
(a)
Concrete (continued)
MEASUREMENT
RULES
CLASSIFICATION TABLE
32. Accessories and
sundry items cast into
in-situ concrete
1. Bonding ties
1. Dimensioned description
m2
1. Spacing dimensions
-------- stated
m
-------nr
4. Step irons
5. Others, details stated
SUPPLEMENTARY
INFORMATION
MEASUREMENT
RULES
SUPPLEMENTARY
INFORMATION
CLASSIFICATION TABLE
1.
COVERAGE RULES
nr
1. Dimensioned description,
--------description to include for
m
bedding and holding down
bolts as appropriate
(b)
DEFINITION RULES
Slabs
1. Thickness stated
1. Tops
m2
2. Soffits
2.
Walls
3.
Beams
4.
Columns
5.
To slopes
HK SMM 4
1. Straight
DEFINITION RULES
COVERAGE RULES
2. Curved
m2
64
VII
CONCRETE WORKS
(c)
Reinforcement
65
CLASSIFICATION TABLE
MEASUREMENT
RULES
1.
Generally
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
S.1 Quality of steel stated
S.2 Particulars given of
any tests required
S.3 Any special
restrictions in regard to
hot or cold bending
2.
Bar reinforcement
1. General reinforcement
kg
2. General reinforcement
> 12 m in length, given in
stages of 3 m
1. Round bars
2. Indented bars
3. Square bars
3. Threading ends of
bars for couplers by
others
4.
nr
1. Fully described
Couplers
nr
5.
m2
1. Flat fabric
2. Fabric specially bent to
curve.
1. Described in detail
including manufacturers
reference
(d)
Formwork
INFORMATION PROVIDED
MEASUREMENT
RULES
DEFINITION RULES
1.
Generally
M.2 Formwork is
measured super except
as hereinafter provided.
M.3 No deductions made
for openings 1.00 m2.
M.4 Formwork left-in and
permanent formwork are
each measured
separately, except where
more detail is required in
item (d).5 and 6 hereof.
M.5 Formwork to produce
a formed finish is
measured separately and
the finish described.
HK SMM 4
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
S.1 Kind and quality of
materials and propping
requirements for
permanent formwork
S.2 Construction and/or
lining of formwork which
is not at the discretion of
the Contractor.
S.3 Kind and quality of
the formed finishes
required
66
VII
CONCRETE WORKS
(d)
Formwork (continued)
67
MEASUREMENT
RULES
CLASSIFICATION TABLE
2.
Soffits of slabs
Soffits of landings
4. Soffits of coffered
or troughed slabs
5. Wall faces and the
like
1. Horizontal
m2
2. Sloping
3. Curved
4. Curved in more than
one direction
1. Vertical
m2
2. Sloping
3. Curved ( For work
curved in more than one
direction see item 17,
Complex shapes below)
6. Sides of piers,
columns and
stanchions
1. Height to soffit 3.50 m M.6 The heights of soffits D.3 Formwork to soffits of
are measured from the
slabs includes formwork
2. Thereafter in 1.50 m
structural concrete level,
to landings occurring at
stages
or from the existing
floor levels.
ground, or formation level
immediately below the
soffit.
m2
1. Vertical
2. Sloping
3. Curved, radii stated
(For work curved in more
than one direction see
item 17, Complex
shapes below)
m2
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
(d)
Formwork (continued)
MEASUREMENT
RULES
CLASSIFICATION TABLE
7. Sides and soffits of
beams
1. Depth of beams
0.75 m (below soffit of
slab)
2. Depth of beams >
0.75 m (below soffit of
slab)
1. Horizontal beams
m2
2. Sloping beams
3. Curved beams
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
8.
Top formwork
HK SMM 4
1. Straight
2. Curved
2. Width 100 mm
3. Width > 100 mm and
200 mm
m2
--------m
2. Thereafter in stages of
100 mm
68
VII
CONCRETE WORKS
(d)
Formwork (continued)
69
MEASUREMENT
RULES
CLASSIFICATION TABLE
11. Edges and soffits of
copings, cills, strings,
cornices, eaves
overhangs, and the like
0.50 metre wide,
grouped together
1. Straight
2. Curved
nr
1. Thickness of concrete
and size of pipe or cable
etc. stated
nr
1. Thickness of concrete
and size in stages of
0.10 m2.
nr
1. Dimensioned
description
nr
2. Dimensioned diagram
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
(e)
INFORMATION PROVIDED
MEASUREMENT
RULES
1. Generally
nr
2. Curved
nr
m
1. Dimensioned
description, extreme
sizes stated
1. Dimensioned
description
SUPPLEMENTARY
INFORMATION
M.1 Reinforcement is
described and included
with the item.
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
1. Reinforcement details
stated
2. Cast-in accessories,
details stated
1. Straight
COVERAGE RULES
MEASUREMENT
RULES
CLASSIFICATION TABLE
DEFINITION RULES
nr
1. Straight units
8. Dropper kerbs
nr
HK SMM 4
70
VII
CONCRETE WORKS
(f)
71
INFORMATION PROVIDED
MEASUREMENT
RULES
1.
Generally
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
S.1 A general description
of the prestressed work
and of the system and
method of tensioning
S.2 Particulars of:
(a) Tendons and any
preparatory treatment
(b) Whether tendons are
to be tensioned as the
load is applied
(c) Maturity of concrete
before post-tensioning is
applied
(d) Tests to be applied
CLASSIFICATION TABLE
MEASUREMENT
RULES
2. Structural in-situ
members
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
(f)
CLASSIFICATION TABLE
3.
4.
Tendons
1. Supplying tendons,
ultimate strength and
size of tendon stated
kg
1. Straight ducts
2. Curved ducts
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
5.
Anchorages
HK SMM 4
nr
3. Tensioning each
tendon, size, length and
jacking force stated
nr
1. Anchorages are
described as a complete
assembly, description to
include anchor plate,
cones, wedges and the
like.
C.2 Degreasing,
straightening, cutting to
lengths and assembling
tendons deemed to be
included
1. Tensioned from one end
2. Tensioned from both
ends
nr
1. Live anchorages
2. Dead anchorages
72
VII
CONCRETE WORKS
(g)
73
INFORMATION PROVIDED
MEASUREMENT
RULES
1.
M1 Precast prestressed
concrete units and
associated work, including
hoisting and fixing are
given separately under an
appropriate heading.
Generally
A general description of the precast prestressed units and the system and method of tensioning shall be
given.
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
MEASUREMENT
RULES
CLASSIFICATION TABLE
2.
Precast units
nr
1. Pre-tensioned in the
mould
2. Post-tensioned on the
ground after casting
3. Cast in sections,
assembled and posttensioned before erection
4. Cast in sections for
assembly in-situ and posttensioned after erection
5. Post-tensioned after
hoisting but capable of
self support
6. Post-tensioned after
hoisting but requiring
support until tensioning is
complete
(g)
CLASSIFICATION TABLE
3.
nr
2. Special temporary
1. Size and span of unit
supports required in
stated
connection with posttensioned units which are
tensioned after hoisting
nr
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
4. Reinforcement,
ducts, tendons and
anchorages
HK SMM 4
74
VIII
75
(a)
INFORMATION PROVIDED
MEASUREMENT
RULES
1.
Generally
DEFINITION RULES
COVERAGE RULES
C.1 Each item of
Brickwork and Block
Walling is deemed to
include:
(a) All rough and fair
cuttings
(b) Wedging and pinning
(c) Raking out joints to
form key
(d) Raking out joints for
and pointing flashings
(e) Labour eaves filling
(f) Plumbing angles and
forming square and
rebated reveals
(g) Notches, forming or
leaving or cutting chases
(h) Holes and mortices
and cutting and pinning
and making good
(i) Centering
(j) And any other sundry
items of a like nature
SUPPLEMENTARY
INFORMATION
(a)
CLASSIFICATION TABLE
2.
Brick walls
3. Brickwork in filling
openings
m2
1. Vertical walls
5. Dwarf walls
supporting fittings,
tanks and the like,
grouped together
2. Walls one and a half
bricks thick
1. Thickness stated
m2
1. Thickness stated,
description includes for
all cutting
m2
4. Hollow walls
m2
m2
m2
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
S.1 Kind and quality and
size of bricks
S.2 Bond
S.3 Composition and mix
of mortar
S.4 Type of pointing
1. General faces
S.5 Bond
2. Built overhand
3. To battering faces,
described
4. To curved faces
7. Closing cavities of
brick hollow walls, at
ends or at openings
8.
Arches
9. Arches of unusual
outline
HK SMM 4
1. Fully described
1. Arches of varying
shapes and types are
given separately
nr
76
VIII
(a)
77
MEASUREMENT
RULES
CLASSIFICATION TABLE
10. Cills, copings etc.
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
1. Cills
2. Cornices
3. Plinth cappings
4. Copings
5. Others, described
1. Dimensioned
description
nr
1. Key blocks
2. Corbels
3. Pier caps
4. Others, described
1. Walls or partitions
1. Blocks described
formed of concrete blocks including size and finish
m2
2. Walls or partitions
formed of hollow tiles
3. Walls or partitions
formed of patent blocks
m2
16. Joints
1. Bedding at perimeter
2. Reinforcement,
described
1. In brick walls
2. In block walls
3. In glass block walls or
panels
1. Dimensioned
description
(a)
CLASSIFICATION TABLE
17. Cutting and bonding 1. Both walls described
walls of different
construction
18. Labours to existing
brickwork or
blockwork
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
2. Preparation of existing
walls for raising
19. Reinforcement in
1. Material and width
brickwork or blockwork stated
20. Damp-proof courses
(except asphalt)
m
1. Courses > 225 mm
wide
m2
1. Horizonta
2. Vertical
3. On curved walls
(description includes all
extra cutting)
2. Courses 225 mm
wide, width stated
21. Flues
1. Thickness stated
1. Description includes
and describes bonding to
backing if required
m2
nr
1. Dimensioned
description
HK SMM 4
78
VIII
(b)
79
INFORMATION PROVIDED
MEASUREMENT
RULES
1.
Generally
DEFINITION RULES
COVERAGE RULES
SUPPLEMENTARY
INFORMATION
MEASUREMENT
RULES
CLASSIFICATION TABLE
2. Brick or block
pavings
m2
DEFINITION RULES
S.5 Bedding
(e) Grouting
COVERAGE RULES
1. Straight
2. Curved
(c) Cutting
3.
SUPPLEMENTARY
INFORMATION
HK SMM 4
80
205
ALPHABETICAL INDEX
A
Abbreviations
Accessories (Electrical)
Acrylic Sheet Glazing
Air Handling Units
Alterations
Ancillary Fittings (Electrical)
Artificial Plants
Asphalt Work
B
Backfilling to Excavations
Balustrades, Glazed Balustrades, Metal
Balustrades, Wood
Bitumen Emulsion, Asphaltic Concrete
Boilers
Bonding (Electrical)
Bored Piles
Boulders, Supplying and Placing
Brick or Block Paving
Brickwork & Blockwork
Building Services, Classification in Billing
Busbar Trunking
C
Cables (except in Final Circuits)
Caissons
Carpet Sheet/Carpet Tile Finishes
Cast in-situ Concrete Piles in Driven Casings
Cast Stone Facings
Ceramic Tilling
Cesspools
Chillers
Chimneys
Chinese Tile Roofing
Chunam Surfacing
Claddings, Sheet Metal
Communications Systems
Communications Systems, Equipment
Communications Systems, Final Circuits
II
XVIII
XX
XVII
IV
XVIII
XXII
X
P.3
P.179
P.191
P.154
P.19
P.179
P.203
P.85
VI
XV
XIII
XVI
XVII
XVIII
V
XXII
VIII
VIII
II
XVIII
P.50
P.125
P.113
P.145
P.154
P.180
P.33
P.203
P.79
P.75
P.7
P.174
XVIII
V
XVI
V
XI
XVI
IX
XVII
XVII
XII
VI
XV
XIX
XIX
XIX
P.176
P.39
P.151
P.30
P.94
P.148
P.83
P.154
P.154
P.97
P.51
P.120
P.183
P.184
P.186
XIX
VII
VIII
VII
VII
VII
VII
IX
VII
VII
VII
VII
V
VII
VII
VII
VII
VII
XVIII
XIX
XIX
XIX
XIX
XVII
II
XV
XV
VI
P.189
P.61
P.77
P.62
P.62
P.59
P.60
P.81
P.60
P.60
P.59
P.61
P.30
P.61
P.66
P.65
P.63
P.63
P.173
P.183
P.184
P.186
P.189
P.154
P.4
P.122
P.141
P.45
II
IV
IV
XV
XIII
V
VI
XIII
XV
P.4
P.20
P.20
P.133
P.108
P.43
P.49
P.111
P.124
IX
IX
II
XVII
XVII
XVII
P.81
P.81
P.3
P.161
P.162
P.162
XVIII
XVIII
XVIII
XVIII
XVIII
XVIII
VI
VI
VI
VI
VI
VI
VI
II
P.180
P.172
P.179
P.171
P.181
P.171
P.46
P.47
P.46
P.47
P.47
P.48
P.47
P.5
XXI
XVII
X
XV
XIX
XIX
XIX
XVIII
XIII
XIII
XV
XV
XIII
XV
III
III
P.199
P.154
P.88
P.127
P.187
P.187
P.187
P.178
P.103
P.114
P.142
P.133
P.108
P.123
P.10
P.10
HK SMM 4
XV
XIII
XV
XIII
P.125
P.111
P.142
P.114
XV
XX
XX
VIII
XX
XIII
XX
XI
XVI
XVI
XXII
XV
VII
XVII
P.124
P.194
P.193
P.77
P.193
P.108
P.191
P.94
P.148
P.145
P.201
P.124
P.64
P.160
XV
XIII
VI
XIII
XVII
XXII
P.125
P.113
P.50
P.111
P.154
P.201
XVI
XVII
XVII
XVII
XIII
XIV
P.145
P.165
P.165
P.164
P.103
P.117
XVII
XXII
P.155
P.201
Lathing
XVI
Lightning Protection
XVIII
Linings, Sheet Metal
XV
Liquid Membrane Waterproofing
X
Luminaires
XVIII
M
Macadam
XVI
Marble Facings
XI
Marble Tiling
XVI
Mechanical Equipment
XVII
Mechanical Installations, Sundries
XVII
Mechanical Installations
XVII
Mechanical Section General Clauses
XVII
Metal Doors, Gates, Shutters, Grilles
XV
Metal Hatches
XV
Metal Works for Structural Timber
XVII
Minimum Deductions
II
Minor Buildings & Structures, Metal
XV
Minor Buildings & Structures, Wood
XIII
Mirror Wall Linings
XX
Mirrors
XX
Moon Gates, Stone
XI
Mosaic Tiling
XVI
Mulching Planting Areas
XXII
N
O
Office Cubicle Partitions, Metal
XV
Office Cubicle Partitions, Wood
XIII
Overhead Crane Rails
XV
P
Painting, General Clauses
XXI
Paperhanging including Sheet Plastic & Fabric Linings
XXI
Parquet Flooring
XIII
Partitions, Demountable, Wood
XIII
Partitions, Fixed, Wood
XIII
Partitions, Office Cubicle
XIII
Partitions, Sliding and Folding
XIII
P.143
P.180
P.122
P.85
P.179
P.145
P.94
P.148
P.153
P.169
P.153
P.153
P.124
P.124
P.99
P.4
P.128
P.115
P.193
P.194
P.93
P.148
P.203
P.135
P.110
P.120
P.195
P.199
P.101
P.108
P.108
P.110
P.109
XIII
XIII
XVII
XVII
XVII
XVII
VI
XXII
XXII
XVI
XVI
XVI
XIII
XV
XXI
XX
VII
V
VII
VII
II
XV
XIII
XV
XII
XVII
II
XVII
P.110
P.108
P.156
P.158
P.158
P.157
P.46
P.203
P.202
P.143
P.143
P.151
P.114
P.142
P.198
P.191
P.70
P.28
P.73
P.71
P.5
P.131
P.107
P.131
P.98
P.166
P.5
P.154
XIII
XV
XIII
III
XVI
II
II
XVI
P.114
P.131
P.102
P.16
P.145
P.5
P.5
P.145
206
207
Roof Tiling
Roofing and Flashings, Sheet Metal
Rubber Sheet Finishes
S
Sanitary & Laboratory Fittings
Sea Water, Works Under
Security Systems
Security Systems, Equipment
Security Systems, Final Circuits
Security Systems, Sundries
Septic Tanks
Service Ducts
Sheet Linings & Claddings
Sheet Membrane Waterproofing
Sheet Plastic Paperhanging
Shelving, Wood
Shelving, Racks, Metal
Shop Fronts, Metal
Shoring
Shutters, Folding, Rolling, Metal
Sign Boards & Signage, Wood
Sign Boards & Signage, Metal
Signwriting
Site Clearance
Slate Tiling
Sliding and Folding Partitions
Spatterdash
Specification, Used for BQ preparation
Sprayed Concrete to Slopes
Squash Court Armoured Glass Walls
Stairs, Wood
Stairs, Metal
Steel & Metal, Sundries
Steel Piles
Steel Sheet Piling
Stone Arches
Stone Beds & Sides to Water Courses
Stone Construction
XII
XV
XVI
P.97
P.123
P.151
XVII
II
XIX
XIX
XIX
XIX
IX
IX
XIII
X
XXI
XIII
XV
XV
IV
XV
XIII
XV
XXI
VI
XVI
XIII
XVI
II
VI
XX
XIII
XV
XV
V
V
XI
XI
XI
P.155
P.5
P.183
P.184
P.186
P.189
P.83
P.81
P.103
P.88
P.199
P.114
P.142
P.139
P.23
P.124
P.114
P.142
P.199
P.45
P.148
P.109
P.143
P.3
P.51
P.193
P.113
P.125
P.129
P.36
P.25
P.93
P.92
P.91
XI
XI
XI
XI
XI
XIII
XV
XVI
VII
XV
VII
XVIII
II
XVI
P.92
P.94
P.93
P.92
P.91
P.99
P.119
P.145
P.59
P.136
P.61
P.172
P.3
P.148
XVII
IV
IV
VI
XVI
XVI
XIII
XV
XVIII
IX
IX
XVIII
XXII
P.154
P.23
P.23
P.49
P.145
P.148
P.110
P.133
P.173
P.81
P.81
P.174
P.201
VI
XIX
II
II
P.53
P.184
P.3
P.3
XIII
P.111
V
XV
P.43
P.138
Wood Balustrades
Wood Block Flooring
Wood Handrails
Wood Doors
Wood Framed Suspended Ceilings
Wood Frames & Linings
Wood Hatches
Wood Stairs
Wood Strip Flooring
Wood Trims
Wood Ventilators
Working Space, for Excavation
Work in Compressed Air
Work in Existing Buildings
Work outside the Site
Work under Reservoir, River or Sea Water
X
Y
Z
XIII
XIII
XIII
XIII
XIII
XIII
XIII
XIII
XIII
XIII
XIII
VI
II
II
II
II
P.113
P.101
P.113
P.111
P.103
P.111
P.111
P.113
P.101
P.103
P.111
P.46
P.5
P.5
P.5
P.5