Академический Документы
Профессиональный Документы
Культура Документы
Executive Summary
Chapter 1 Introduction
Background
One of the most critical steps in well completion is cementing. Despite the haste to put the well
on production at the end of drilling, time and commitment must be put in to get a good job done.
This is essential to avoid spending significant amounts of time correcting or battling with the
effects of a bad cement job. The quality of cementing operations will affect the success of
follow-on drilling, completion, production and work-over efforts in the well.
To successfully a liner string to a specific depth the cement slurry needs to be designed based
on down hole a condition which dictates the slurrys density, yield, volume, additives and
rheology.
Problem Definition
Cementing of a 7, P-110 liner string, from 16,000ft back to 11,600ft in drilled with an 8-1/2 bit to
True Depth (TD) of 16,000ft below a 9-5/8 intermediate casing string set and cemented at
12,000ft. A calliper long indicated the hole was actually 9.5 in diameter. Minor seepage lost
problems was encountered while drilling below, 12,000ft, indicating fairly competent formation,
but with high permeability sections. The float collar is to be placed at 15,920ft and the liner will
be run in using a 4-1/2, 16.6 lb/ft drill pipe work string.
Objective
To design a programme for the cementing of a 7, P-110 liner string, from 16,000ft back to
11,600ft in a 9.5 diameter hole.
Scope
Determination of pump rates and pump pressures associated with the cementing of the
amount of water required for the job, assuming an excess of 400ft above the liner top.
Determination of whether a spacer or pre-flush should be used.
Plan of Action
The data provided:
Calculation of slurry weight and yield of both compositions based on additives and their
percentages
Analysis flow regime and flow rates of slurry associated with the regime based on the
1. Adam T. Bourgoyne Jr, Keith K. Millheim, Martin E Chenevert, F.S. Young Jr. Applied
Drilling Engineering, 1st Printing, 1986
Chapters 3 and 4 of this book provided the information needed to successfully complete this
project.
Chapter 3 provides information on the theory of cements with respect to:
Its composition
Additives
Testing and placement techniques.
The physical properties of the class H cement were also obtained
Chapter 4 provided information on cement with respect to cement mud and cement slurries. In
addition to an overview of Newtonian and non- Newtonian fluids. Also presented in the chapter
were equations for:
2. SPE 152, March 1962 - Knox A. Slagle, Halliburton Company, Duncan, OKLA.
Rheological Design of Cementing Operations
This paper described a series of rheological calculations needed in order to determine slurry
properties. The equations assisted in the designing of the cementing job and selection of flow
regime. The rheological calculations presented in this paper which can be done through the
usage of filed date assisted in the selection of a cementing program.
Flow behaviour index, n, and consistency index, K, which is necessary for adequate fluid-flow
calculations was also information provided with respect to the parameters. The paper
furthermore provides a step by step description of how to obtain data that would be used in the
cementing job.
Required properties
Characteristics of cements
Cement additives
Flow properties of cements
Displacement mechanics
Cementing hardware
Cementing operations considerations
Cementing nomenclature
Cement slurries
Field calculations
Cement additives
Chapter 3 Theory
Cement fills and seals the annulus between the casing string and the drilled hole. It has three
general purposes: (1) zone isolation and segregation, (2) corrosion control, and (3) formation
stability and pipe strength improvement (4) To protect the casing from damage or failure
(5) To support the borehole through the productive interval (6) to protect the casing from
damage or failure. A cement slurry is placed in the well by mixing powdered cement and water
at the surface and pumping it by hydraulic displacement to the desired location. Cement forms
an extremely strong, nearly impermeable seal from a thin slurry. The property of the cement
slurry and its behaviour depends on the components and the additives in the cement slurry.
There are 7 classes of cement (A- F) each with different intended uses. However there are a
wide range of chemical additives that can be added to the classes of cement to provide slurry
characteristics for almost any subsurface environment. Currently Class G and H are the most
popular and widely used due to the fact that they can be easily modified through the use of
additives to meet almost any job specification.
Cement additives can be subdivided into groups such as:
1.
2.
3.
4.
5.
6.
Density Control
Setting Time Control
Lost Circulation Additives
Filtration Control Additives
Viscosity Control Additives
Special Additives for Unusual Problems
classification.
Thought must also be given to heat transfer from the cement rising in the annulus to the cement
coming down the inside of the casing. Pressure has a tendency to accelerate the thickening
time and the set time of the cement, but the effect of pressure is not nearly so pronounced as
that of temperature. The cement must be strong enough to secure the pipe in the hole, to isolate
the zone and to withstand the nominal shock of drilling, perforating and fracturing. More strength
is required in withstanding loading from drill bits and pressure. In designing the cementing
operation, it is imperative that high strength cements be used around the casing shoe (the
bottom end of the pipe) and across potential pay, thief zones (areas of fluid loss) and water
producing zones. Filling the annulus behind pipe and zone separation requires very little
strength and more economical cements or cement extenders may be used. While the cement
slurry is liquid, the hydrostatic force from the weight of the slurry exerts force to prevent entry of
gas into the wellbore annulus. When pumping stops, the cement starts to gel and set and it
begins
to support itself by the initial bond to the formation. This initial attachment, coupled with fluid
loss to the formation, reduces the applied hydrostatic load.13 Fluids can then enter the annulus,
causing
voids and channels in the cement behind the pipe. Methods of control include reaction with the
formation
gas to plug the channels14 and stopping the gas from entering by reducing permeability.15 Use
of an external inflatable casing packer (ECP) is also an option.16 This tool operates like a
hydraulic set
packer between the casing and the open hole.
The necessary volume of cement is the volume of the openhole less the volume of the casing
across the
zone. An excess of 30% to 100% of the total is usually added to the cement volume to allow for
washouts
and mud contaminations. The 30% to 100% range of excess cement volumes is large, even for
the
technology of the oil field. It reflects the variability of drillers expertise and formation conditions.
Hole
volume is calculated from the caliper log. The bit diameter should not be used for hole volume
calculations
since it will not reflect washouts. In most operations, 4-arm caliper tools that give two
independent
diameters are more accurate than 3-arm calipers that give a maximum or averaged reading.
Liner Cementing
A liner is a short string of casing that does not reach the surface. The liner is hung from the
bottom of the previous casing string using a liner hanger that grips the bottom of the previous
casing with a set of slips. The liner is run into the borehole on the drill pipe and the cementing
operation for the liner is carried out through the same drill pipe. The liner assembly is made up
of the following:
1. A float shoe is similar a back-pressure valve is included which prevents any fluid during
running and cement slurry from re-entering the casing after the job is complete. Different
valve designs are available.
2. A float collar is a device placed at least one joint above the cementing shoe. It contains a
back-pressure valve similar to the float shoe and provides a seat for the cementing
plugs. The float collar serves an important function. When only a top plug is used,
cement contamination around the shoe is possible. With a float collar, this mud/cement
mixture remains in the casing and does not contaminate cement around the shoe. Float
shoes and collars are the most common equipment in use.
After the liner is set, a spacer or pre-flush is pumped down hole followed by the bottom plug
then the cement which will be followed by the top plug. The liner cement head and manifold are
installed on the drill pipe with the bottom plug the two inlets. The plug releasing stem holds the
plug in the cement head. After the cementing lines are rigged up and pressure tested, the pre
flush or spacer is pumped down the drill pipe. No bottom wiper plug is used ahead of the spacer
or slurry. Once the slurry is mixed and pumped into the drill pipe, the bottom plug is dropped
and displaced to the liner hanger. At this point, the plug passes through the liner setting tool,
and then latches into and seals the hole in the liner wiper plug.
The surface pressure will rise as an indication of the plug landing. Further applied pressure of)
will shear the pins holding the liner wiper plug in place. When internal volume of the liner has
been completely displaced, the plugs seat on the float collar, and a further pressure rise will
occur, indicating completion of the job.
The drill string is then released from the liner setting tool and withdrawn before the cement
hardens.
Pre-Flushes are fluids with a density and a viscosity very close to that of water or oil. They act
by thinning and dispersing the mud and washed the well bore area. Due to their very low
viscosity, they are particularly easy to put into turbulent flow.
Spacers are carefully designed viscous densities and rheological properties. They have much
higher solid particle content than washes, and are generally more effective buffers for avoiding
contact between the cement slurry and the drilling mud. Some may be pumped in turbulent flow,
and thus share the same cleaning action as pre-flushes. The particles in spacers are also
thought to have a scrubbing effect on the annular surfaces.
Newtonian and non-Newtonian flow.
To calculate the frictional pressure in the annulus and the casing, first the determination of which
fluid model to use. There are the Newtonian model and Non Newtonian Model (the Bingham
Plastic model and Power law model). With the identification of the rheological properties with a
rotational viscometer the flow regime could be established (laminar or turbulent).
The character of flowing fluid is described by the relationship between flow rate (shear rate) and
pressure (shear stress) that caused the movement. There are two basic fluid types, Newtonian
and non-Newtonian. Newtonian fluids, exhibit a linear relationship between flow rate (shear rate)
and pressure (shear stress) while the fluid is in laminar flow. The application of pressure causes
a Newtonian fluid to flow. As pressure increases, flow velocity increases, from laminar, through a
transition zone (part laminar and part turbulent), to fully turbulent flow.
Non-Newtonian fluids exhibit resistance to flow (gel strength) with the application of. Fluids with
gel strength can flow at very low rates in a solid or plug-like manner. Non-Newtonian fluids thus
can have three flow regimes- plug, laminar and turbulent-with transition zones between each.
Drilling muds and oil well cement slurries are non-Newtonian.
Mathematical models have been develop that can be used to predict flow properties and
pressure-velocity relationships of such as the Bingham Plastic Model and the Power Law Model
that are most commonly used. Such models attempt to describe the relationship of shear rate
and shear stress for muds and cement slurries. They are also used to determine flow regime
and pressure requirements for displacement.
Fluid property measurement.
The Fann V-G (viscosity- gel) meter is used to measure plastic viscosity, yield point and gel
strength of mud, and cement slurries.
The viscometer can measure properties over a range of speeds. However, the two speeds of
the field instrument (300 and 600 rpm) are enough to measure plastic viscosity (p.p) and yield
point (ty) used for pressure drop and flow regime determination with the Bingham model, The
Power Law Model requires two different fluid property descriptions. Consistency index (K') and
flow behaviour index (n') are also determined from the Fann V-G meter readings.
Equations
Slurry Density , =
Slurry yeild=
Displacement volume=Volume of the drill pipe+Volume liner top up the float collar
Annular capacity = /4 ( Dh2- Dp2)( 1/144)
Slurry vol, ft3 = number of sacks of cement to be used x slurry yield, ft3/sk
Chapter 4 Methodology
Slurry weight and yield of both compositions
I.
II.
III.
IV.
V.
VI.
Calculations were based on the Power Law Model for Non-Newtonian fluid.
Calculate n and K.
Determine Reynolds number for turbulent and plug flow
Calculate velocity of the slurries both turbulent and plugs flows
The flow rate for the slurry composition was then calculated in cuft/min and bbls/min for
VI.
VII.
VIII.
compositions.
Based on the results of the calculations the flow regime which should be used to pump
the cement slurry will be decided.
IV.
V.
VI.
VII.
VIII.
IX.
X.
XI.
XII.
XIII.
XIV.
Flow Regime
Turbulent
Density
15.9 ppg
Yield
1.53 ft3/sk
5.87 bbl/min
Pressure @ Depth
Pressure @ surface
1,608.63 psi
Spacer or Pre-flush
Spacer
60 bbls
875.55 sks
The discussion should show a sound understanding of the phenomena at work and their
significance to the area of application or enquiry. Adequate discussion of the findings, the
relationships uncovered and explanations of relationships, trends etc. that emerged from the
study should be given. Results should be interpreted with regard to their theoretical and
practical implications to current theory and practice. Application studies should include an
assessment of the costs and benefits involved and address implementation issues.