Вы находитесь на странице: 1из 33

FACILITIES BUILINDG 8

Brock Horsley
Jack Judson
Roger Viticoski

Roadmap
Inspections
1. Site Description
2. Erosion Control
3. Sediment Control
4. Failures & Problem Areas
Design
1. Perimeter Controls
2. Entrance/Exit Pads
3. Stockpile Management & Washout
4. Diversions
5. Slope Protection
6. Channel Design & Protection
7. Soil Stabilization
8. Sediment Barriers
9. Site Maps/Planning

Inspections

1. Site Description
2. Erosion Control
3. Sediment Control
4. Failures & Problem Areas

1. Site Description

Total site area = 1.70 acres


No undisturbed area

Stockpile
Northwest corner of site

Construction Exit Pad


Northern perimeter of site

Wetland area
East & Southeast of site

Gradual slope from Northwest to southeast

2. Erosion Controls

Erosion Control Blankets


Channel on eastern perimeter of site lined with ECB
Eastern slope of site

Permanent Vegetation
Seeded on eastern and southern side of site

Mulching
Placed on eastern and southern side of site while waiting for growth of vegetation

3. Sediment Controls

Silt Fences
Improper tie in installation
Perimeter control running along entirety of eastern and southern side of site
Double layered

Sediment Barriers
Installed in channel on eastern side of site

Construction Exit pad


Northern perimeter of site

4. Failures and Problem Areas

4. Failures and Problem Areas


Rills forming under erosion control blanket

4. Failures and Problem Areas


Improper installation on silt fences as well as tears in fence that were not fixed

4. Failures and Problem Areas

Uncovered soil and stockpile

Design

1. Perimeter Controls
2. Entrance/Exit Pads
3. Stockpile Management & Washout
4. Diversions
5. Slope Protection
6. Channel Design & Protection
7. Soil Stabilization
8. Sediment Barriers
9. Site Maps/Planning

1. Perimeter Controls

820ft of Type B silt fence on southern &


eastern borders
137 wooden posts, spaced 6ft OC
5 staples per post (685 total)
Trench fabric 6 into 6x6 trench, 24
height

150ft of Type B at Problem Area for


double fence
25 wooden posts, spaced 6ft OC
5 staples per post (125 staples)
Trench fabric 6 into 6x6 trench, 24
height

TOTAL:
970ft of Type B Silt Fence
162 wooden posts
810 staples

2. Entrance/Exit Pads
3 Pads, 6 deep and 50ft long
Located at north, southwest, &
southeast entrances & exits

2. Entrance/Exit Pads

CEP
Location

Fabric Underlay
(ft2)

#1 AL Hwy Dept.
Coarse Aggregate
(ft3)

North

3300

1650

Southwest

2400

1200

Southeast

1600

800

TOTAL

7300

3650

3. Stockpile Management & Washout

Stockpile

Washout Area

Located in northwest
corner
Flattest pre-construction
contours
Should be covered with
tarp
40ft x 80ft
West side of northern
CEP
most trafficked CEP based
on inspections

4. Diversions

Routes parking lot runoff


around site

750ft total length

Northern and western


perimeter

4. Diversions

1ft tall RAP berm


(recycled asphalt pavement)

1125ft3 of RAP needed

5. Slope Protection

The site area was divided into 10 sub-areas based on site topography.

5. Slope Protection

Aim: find the most adequate Erosion Control Blanket

Assumptions:
the site has a surface covered with short grass (n= 0.15)
25-yr Storm Event assumed in Peak Discharge (cfs) calculations

5. Slope Protection
Facilities
Post Construction
Section

Slope

Soil Type

Min Mat N

Suggested Product (table 5.9)

1a

0.300

Pacolet Sandy Loam

0.045742942

SC150

1b

0.300

Pacolet Sandy Loam

0.045742942

SC150

1c

0.018

Marvyn Loamy Sand

0.200

Pacolet Sandy Loam

0.05142747

SC150

0.140

Pacolet Sandy Loam

0.053689689

SC150

0.050

Marvyn Loamy Sand

0.021608349

SC150

0.125

Pacolet Sandy Loam

0.038094719

SC150

0.010

Pacolet Sandy Loam

0.014339589

SC150

0.007

Marvyn Loamy Sand

0.01227767

SC150

0.020

Marvyn Loamy Sand

0.017729323

SC150

0.040

Marvyn Loamy Sand

0.027152656

SC150

10

0.125

Pacolet Sandy Loam

0.048260474

SC150

The SC150 is a straw ECB with an effective life of 24 months and


maintains 424 g/m^2 mass per unit area.

6. Channel Design and Protection

The soil in the channel was assumed to be a non-colloidal sandy loam


- v = 1.75 ft/s
- = 0.037 lb/ft2

Channel Dimensions:

6. Channel Design and Protection


Side Slope (z)

Bottom
Width (b)

AR^(2/3)
y/b
/ B^(8/3)
0.00254 0.025

Maximum Shear
Stress

Safety
Factor

0.2

0.209

0.177

SF <1! Channel will need a reinforced liner as well as vegetation

The P300 phase 3 was suggested as the NAG material. With this material, the SF will be higher
than 1
y

Effective Shear Stress

SF

0.2

0.0049

7.61

7. Soil Stabilization

1ST Phase - Initial grubbing


From November 15th to January 15th

2nd Phase Rough Grading


From January 16th to February 15th

7. Soil Stabilization

3rd Phase Final Grading


From February 16th to April 15th

TOTALS
Phase

Soil Loss (cubic yards)

Initial Grubbing (Nov 15 - Jan15)

6.50

Rough Grading (Jan 16 - Feb 15)

0.69

Final Grading (Feb 16 - April 15)


TOTAL

0.84
8

7. Soil Stabilization

Recommendations:
No seeding After Rough Grading (due to weather)
Phase
Initial Grubbing
(Nov 15 - Jan15)
Rough Grading
(Jan 16 - Feb 15)
Final Grading
(Feb 16 - April 15)

Cover Recommendation
(none)
Hay mulch
Bermuda Grass Hybrid

8. Sediment Barriers

Four rock dam barriers


using Erosion Eels

8. Sediment Barriers

Four rock dam barriers


using Erosion Eels
Two in northeastern channel,
30ft spacing
Two in problem area slope, 15ft
spacing

8. Sediment Barriers

Four rock dam barriers


using Erosion Eels
Two in northeastern channel
Two in problem area slope

Specifications
For each barrier, stack three
pyramid-style
Total needed: 12 Erosion
Eels

9. Site Maps/Planning

Pre-construction//Initial Grubbing
Nov 15 Jan 15

9. Site Maps/Planning

Pre-construction//Initial Grubbing
Nov 15 Jan 15

Active construction
Jan 16 Feb 15

9. Site Maps/Planning

Pre-construction//Initial Grubbing
Nov 15 Jan 15

Active construction
Jan 16 Feb 15
Feb 15 Apr 15

Post-construction
April 16+

Вам также может понравиться