Вы находитесь на странице: 1из 257

NEELUM-JHELUM HYDROELECTRIC PROJECT

PAKISTAN WATER & POWER DEVELOPMENT AUTHORITY

ENGINEERING SERVICES FOR


CONSTRUCTION SUPERVISION OF
NEELUM-JHELUM HYDROELECTRIC PROJECT
MONTHLY PROGRESS REPORT
JANUARY 2016

NEELUM JHELUMCONSULTANTS

Tel: (+92) 58224 33653


Fax: (+92) 58224 32978
e-mail: njc@njproject.com

[JV between MWH, NORPLAN, NESPAK, ACE & NDC]


Filing:
Owner:

310
Neelum Jhelum Consultants

Printed:

2 March 2016

Author:

M. ASLAM MALIK

Status:

Final

Distribution:

NJHPC
BOM - Members
File

Doc ref: MPR January 2016 Progress V3

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR


CONSTRUCTION SUPERVISION OF
NEELUM-JHELUM HYDROELECTRIC PROJECT
MONTHLY PROGRESS REPORT
JANUARY 2016

Page i

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

TABLE OF CONTENTS
1

EXECUTIVE SUMMARY ................................................................................................................... 1

INTRODUCTION ............................................................................................................................. 12

CLIENT DELIVERABLES ............................................................................................................... 13


3.1

AVAILABILITY OF LAND .................................................................................................... 13

3.2

ACCESS TO SITE ................................................................................................................ 16


3.2.1

Site Roads and Bridges At Site C1 ........................................................................... 16


3.2.1.1

Access into Debris Channel ....................................................................... 16

3.2.1.2

Up-gradation of the Road between Muzaffarabad and Nauseri ................. 16

3.2.1.3

Muzaffarabad-Atthmaqam Road (Landslide above Rockfill dam) .............. 16

3.2.1.4

Crossing of Neelum River near C1 ............................................................. 16

3.2.1.5

Site Roads and Bridges .............................................................................. 17

3.3

ELECTRICITY ....................................................................................................................... 18

3.4

REQUIRED CLIENT INPUTS & APPROVALS .................................................................... 18

CONSULTANTS PROGRESS ....................................................................................................... 19


4.1

MOBILIZATION / MEETINGS .............................................................................................. 19


4.1.1

Site C1 ....................................................................................................................... 19

4.1.2

Site C2 ....................................................................................................................... 19

4.1.3

Site C3 ....................................................................................................................... 19

4.1.4

Possession of Site and Access.................................................................................. 19

4.2

PROJECT ACCOMMODATION ........................................................................................... 19

4.3

SURVEYS ............................................................................................................................. 20

4.4

4.3.1

Site C1 ....................................................................................................................... 20

4.3.2

Site C2 ....................................................................................................................... 23

4.3.3

Site C3 ....................................................................................................................... 24

GEOLOGY & GEOTECHNICAL ........................................................................................... 27


4.4.1

Additional Site Investigations ..................................................................................... 27

4.4.2

Geology...................................................................................................................... 27

4.4.3
4.5

4.4.2.1

Site C1 ........................................................................................................ 27

4.4.2.2

Site C2 ........................................................................................................ 30

4.4.2.3

Site C3 ........................................................................................................ 31

Geotechnical .............................................................................................................. 31

TUNNELLING ....................................................................................................................... 32
4.5.1

Headrace Tunnel Junctions and Bifurcations ............................................................ 32

4.5.2

Headrace Tunnel Plan & Profile Drawings ................................................................ 33

4.5.3

Adit A1 ....................................................................................................................... 33

4.5.4

Adit A2 ....................................................................................................................... 33

4.5.5

Transition from Steel Liner to Concrete ..................................................................... 33

4.5.6

Shop Drawing Review ............................................................................................... 33

4.5.7

Monitoring Data.......................................................................................................... 33

Page ii

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

4.6

STRUCTURAL ENGINEERING ........................................................................................... 33

4.7

HYDRAULICS ....................................................................................................................... 34

4.8

ELECTRICAL WORKS ......................................................................................................... 35

4.9

4.8.1

Powerhouse and Transformer Cavern ...................................................................... 35

4.8.2

525kV Switchyard, Control Building, 11kV Substation, C3 Colony ........................... 35

4.8.3

Intake / DAM / Headwork ........................................................................................... 36

4.8.4

Various Electrical Issues ............................................................................................ 36

4.8.5

Factory Acceptance Tests ......................................................................................... 37

MECHANICAL WORKS ....................................................................................................... 37

4.10 REPORTING ......................................................................................................................... 38


4.11 PROGRAMME AND SCHEDULE ........................................................................................ 38
4.12 DRAFT AMENDMENT NO. 2 ............................................................................................... 41
5

CONSTRUCTION: PROGRAMME & PROGRESS ........................................................................ 42


5.1

PROGRESS OVERVIEW ..................................................................................................... 42

5.2

PROGRESS AT C1 .............................................................................................................. 44

5.3

5.4

5.2.1

Layout and Scope of Works at Lot C1 ....................................................................... 44

5.2.2

Mobilization & Site Establishment ............................................................................. 45

5.2.3

Dam Excavation ......................................................................................................... 79

5.2.4

Intake Block and Desander ........................................................................................ 79

5.2.5

Tunneling ................................................................................................................... 81

5.2.6

Diversion Tunnel / Cofferdam .................................................................................... 90

5.2.7

Monitoring of Water Level of Neelum River ............................................................... 90

5.2.8

Visitors/Meetings/Work Stoppage.............................................................................. 92

5.2.9

Site Photographs ....................................................................................................... 92

PROGRESS AT C2 .............................................................................................................. 95
5.3.1

Mobilization / Meetings .............................................................................................. 95

5.3.2

Steel Liner Fabrication Progress: .............................................................................. 96

5.3.3

Aboveground Activities: ............................................................................................. 97

5.3.4

Tunnelling .................................................................................................................. 97

5.3.4.2

Neelum TBM 697: ....................................................................................... 98

Drill & Blast Excavations .......................................................................................... 100

5.3.6

Headrace Tunnel Concrete Lining: .......................................................................... 102

5.3.7

Site Photographs: .................................................................................................... 105

PROGRESS AT C3 ............................................................................................................ 107


Mobilization & Site Establishment ........................................................................... 107

TUNNELLING ..................................................................................................................... 107


5.5.1

5.6

Jhelum TBM 696: ........................................................................................ 97

5.3.5

5.4.1
5.5

5.3.4.1

Tunnels Excavation Works ...................................................................................... 107

SURFACE WORKS ............................................................................................................ 118


5.6.1

WAPDA Permanent Residential Colony .................................................................. 118

5.6.2

WAPDA Permanent Residential Colony .................................................................. 118

Page iii

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.6.3

Rest House: ............................................................................................................. 118

5.6.4

Retaining wall behind the Rest House: (b/w Rest House & CAT-II) ........................ 118

5.7

Visits/Meetings .................................................................................................................. 122

5.8

Site Photographs .............................................................................................................. 122

5.9

E& M Works ....................................................................................................................... 127


5.9.1

Mechanical Works ................................................................................................... 127

5.9.2

Electrical Works ....................................................................................................... 130

5.9.3

Visits/Meetings ......................................................................................................... 133

5.9.4

Site Photographs E&M Works Site C3 .................................................................... 134

QUALITY ASSURANCE / QUALITY CONTROL ......................................................................... 136


6.1

Site C1: ............................................................................................................................... 136

6.2

Site C2 ................................................................................................................................ 137

6.3

Site C3 ................................................................................................................................ 137

6.4

Quality Management look ahead ..................................................................................... 137

6.5

LABORATORIES ............................................................................................................... 138

6.6

NON-CONFORMANCE REPORTS .................................................................................... 147

HEALTH, SAFETY & ENVIRONMENT ......................................................................................... 156


7.1

OPERATIONAL HEALTH & SAFETY ............................................................................... 156


7.1.1

7.2

MONTHLY PROGRESS REPORT


JANUARY 2016

Accidents & Incidents .............................................................................................. 156

ENVIRONMENT .................................................................................................................. 158


7.2.1

REVIEWS ................................................................................................................ 158

7.2.2

FIELD VISITS .......................................................................................................... 158


7.2.2.1

Site C1: ..................................................................................................... 158

7.2.2.2

Site C2: ..................................................................................................... 158

7.2.2.3

Site C3 ...................................................................................................... 163

7.2.3

Meetings .................................................................................................................. 163

7.2.4

Status Of Non-Compliances By Contractor ............................................................. 174

STAFFING AND RESOURCES .................................................................................................... 187


8.1

THE CONSULTANT ........................................................................................................... 187

8.2

THE CLIENTS COUNTERPART STAFF .......................................................................... 187

8.3

THE CONTRACTOR .......................................................................................................... 187

FINANCE ....................................................................................................................................... 188


9.1

THE CONSULTANT ........................................................................................................... 188

9.2

CONTRACTORS INVOICE ............................................................................................... 191


9.2.1

Invoices & Payments ............................................................................................... 191

9.3

APPROPRIATION REQUESTS AND VARIATION ORDERS ........................................... 218

9.4

CLAIMS............................................................................................................................... 218

LIST OF ANNEXURES

ANNEXURE A: PROJECT SCHEDULE ..................................................................................................... B

Page iv

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

ANNEXURE B: LIST OF DRAWINGS ISSUED DURING THIS PERIOD .................................................. J


ANNEXURE C: STATUS OF APPROPRIATION REQUESTS AND VARIATION ORDERS .................... L
ANNEXURE D: CONTRACTORS CLAIMS ............................................................................................... Z

LIST OF FIGURES
Figure 1-1: Planned versus Actual Progress of the Project Civil Works........................................... 5
Figure 2-1: Project Location .................................................................................................................... 12
Figure 4-1: Planned versus Actual Progress of the Project Civil Works......................................... 40
Figure 5-1: General Layout and Scope of Works at C1 ........................................................................ 44
Figure 5-2: Progress at Debris Channel (looking at Left Dam abutment) .......................................... 58
Figure 5-3: Progress at Debris Channel (D/S Retaining wall for Rockfill Dam) ................................. 59
Figure 5-4: Progress at Debris Channel (Right End Retaining wall for Rockfill dam) ...................... 60
Figure 5-5: Progress at Spillway Bays (Floor) for 2

nd

stage Concrete (Plan View) ........................... 61

Figure 5-6: Progress of Concrete Works in Spillway Block 5-3 .......................................................... 63


Figure 5-7: Progress of Concrete Works in Spillway Block 5-4 .......................................................... 63
Figure 5-8: Progress of Concrete at Spillway Roof Slabs (section looking U/S) .............................. 64
Figure 5-9: Progress of Concrete works at Divide Pier (Block-4) ....................................................... 65
Figure 5-10: Progress of Concrete at Stilling Basin Floor (Plan View)............................................... 66
Figure 5-11: Progress of Concrete at Stilling Basin Left Guide Wall (looking towards Dam left
abutment) ........................................................................................................................... 67
Figure 5-12: Progress of Concrete at Stilling Basin Left Retaining Wall (looking towards Dam left
abutment) ........................................................................................................................... 68
Figure 5-13: Progress of Concrete works at Intake Blocks (Section looking D/S) ............................ 69
Figure 5-14: Progress of Concrete at Sedimentation Basin Base Slab (Plan View) ......................... 70
Figure 5-15: Progress of Concrete at Sedimentation Basin Left End Wall and Divide Wall ............ 71
Figure 5-16: Progress of Concrete at U/S Spillway Protection Slab (Plan View) .............................. 72
Figure 5-17: Material status and progress for Debris Channel & Gantry Cranes .............................. 75
Figure 5-18: Material status and progress for Intake Gates ................................................................ 75
Figure 5-19: Material status for Stoplog of spillway ............................................................................. 76
Figure 5-20: Material status and progress for Radial Gates of Spillway ............................................ 76
Figure 5-21: Material status and progress for Collecting Canal Gates .............................................. 77
Figure 5-22: Jetting system for sedimentation basin ........................................................................... 77
Figure 5-23: Daily and Cumulative Dam Excavation ............................................................................ 79
Figure 5-24: Daily and Cumulative Desander Excavation .................................................................... 80
Figure 5-25: Tunneling in the Downstream Headrace Tunnel (T1A M1L) ........................................... 81
Figure 5-26: Percentage of Q-Values encountered in left head race twin tunnel .............................. 82
Figure 5-27: Tunneling in the Downstream Headrace Tunnel (T1A-M1R) .......................................... 83
Figure 5-28: Rock quality at (T1A-M1R) ................................................................................................. 83
Figure 5-29: Monthly progress of Headrace tunnel (October 2015) .................................................... 84
Figure 5-30: Progress Summary of HRT (Up to 25 January 2015) ...................................................... 90

Page v

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-31: Average Monthly Discharge of Neelum River 2015 ..................................................... 91


Figure 5-32: Backfilling of Rockfill Dam at D/S Zone-3 ....................................................................... 92
Figure 5-33: Removal of silt from Stilling Basin ................................................................................... 93
Figure 5-34: Excavation for U/S RCC River Training works ................................................................ 93
Figure 5-35: Installation of Boom of the tower crane at sedimentation basin .................................. 93
Figure 5-36: Drilling for rock anchors with compressed air drill machine at Right slope............... 94
Figure 5-37: Placing of RCC at U/S training work area ........................................................................ 94
Figure 5-38: Placing of concrete at U/S protection slab (P4) and finishing final surface ................. 94
Figure 5-39: Local Suppliers supplying SS1 for aggregate production at Crush Plant # 2 ............. 95
Figure 5-40: A view of Spillway from U/S............................................................................................... 95
Figure 5-41: TBM Monthly Progress with Rock Burst Locations and Geo-structural Features .... 100
Figure 5-42: Tunnel Progress Chart Upstream HRT T3c-T3aL .......................................................... 101
Figure 5-43: Rock Quality at Downstream Headrace Tunnel (T3c-T3al)........................................... 101
Figure 5-44:Tunnel Progress Chart Upstream HRT T3c-T3aR .......................................................... 102
Figure 5-45: Rock Quality at Downstream Headrace Tunnel (T3c-T3aR) ......................................... 102
Figure 5-46: S-697: Heavy support installation continuously as precautionary measures for rock
burst .................................................................................................................................. 105
Figure 5-47: TBM 696: Goat slaughtering ceremony on re-start of TBM S-696 at 09.16am on
Sunday 10th January 2016 ............................................................................................. 105
Figure 5-48: S-697: Cleaning tunnel invert using mini loader aspreparation of invert shotcrete in
progress ........................................................................................................................... 106
Figure 5-49: S-696: Rock burst occurred on 10th and 13thJan 2015(night shift) ............................ 106
Figure 5-50: S-697: Machine belt conveyor repairing in progress. ................................................... 106
Figure 5-51: Graphical presentation of progress of grouting in Headrace Tunnel ......................... 108
Figure 5-52: Progress of Concrete Works in Powerhouse Cavern ................................................... 109
Figure 5-53: Progress of Concrete Works in Unit-1, Powerhouse Cavern ....................................... 110
Figure 5-54: Progress of Concrete Works in Unit-2, Powerhouse Cavern ....................................... 111
Figure 5-55: Progress of Concrete Works in Unit-3, Powerhouse Cavern ....................................... 112
Figure 5-56: Progress of Concrete Works in Unit-4, Powerhouse Cavern ....................................... 113
Figure 5-57: Tunneling in Tailrace Tunnel from Outlet side .............................................................. 116
Figure 5-58: Tailrace Tunnel A7 (Benching) ........................................................................................ 116
Figure 5-59: Tailrace Tunnel A6 (Benching) ........................................................................................ 116
Figure 5-60: A5 Headrace Surge Branch - A view of demarcation of dowels for backfill concrete at
EL.594 ~ 591 ..................................................................................................................... 122
Figure 5-61: A6 Tailrace Tunnel - Invert cleaning ............................................................................... 122
Figure 5-62: Headrace Tunnel - Cleaning work at Invert Lining ........................................................ 123
Figure 5-63: Headrace Manifold - General view .................................................................................. 123
Figure 5-64: Headrace Manifold and Penstock junction .................................................................... 123
Figure 5-65: A7 Tailrace Tunnel - Fixing of formwork for rail track at Ch: 1+685 ~ 1+715 ............. 124
Figure 5-66: A7 Tailrace Tunnel - Drilling for rock bolts at Ch: 1+812 ~ 1+832 ............................... 124

Page vi

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-67: A7 Tailrace Tunnel - Washing and crack inducer before lining concrete at Ch: 1+565 ~
1+625 ................................................................................................................................. 124
Figure 5-68: A7 Outlet Structure - Base slab ....................................................................................... 125
Figure 5-69: Headrace Surge Branch - Fixing of formwork for backfill ............................................ 125
Figure 5-70: Powerhouse (Unit 3) - Column D/S ................................................................................. 125
Figure 5-71: NJHPC Transformer hall 525kV cable trenches & cable gallery .................................. 126
Figure 5-72: NJHPC Switchyard - View from Control Building cable trenches ............................... 126
Figure 5-73: Control building - Pouring of concrete for trenches ..................................................... 126

LIST OF TABLES

Table 3-1: Status of Land Acquisition .................................................................................................... 13


Table 3-2: Status of Site Roads and Bridges ........................................................................................ 17
Table 4-1: Dam/Intake/stilling Basin/Sedimentation Basin .................................................................. 20
Table 4-2: Construction Drawings Issued to the Contractor ............................................................... 34
Table 4-3: Shop Drawings Reviewed and Commented ........................................................................ 34
Table 5-1: Progress Summary of Adits .................................................................................................. 42
Table 5-2: Excavation Progress Summary for Tunnels ........................................................................ 43
Table 5-3: Progress Summary for Major Works .................................................................................... 44
Table 6-1: Field and Laboratory Testing at C1 .................................................................................... 139
Table 6-2: Field and Laboratory Testing at C2 .................................................................................... 143
Table 6-3: Field and Laboratory Testing at C3 .................................................................................... 145
Table 6-4: Status of Non-Conformance Reports ................................................................................. 148
Table 8-1: Consultant's Staff Deployment in January 2016 ............................................................... 187
Table 9-1: Status of the Consultant Invoices ...................................................................................... 188
Table 9-2: Status of the Contractors Invoices .................................................................................... 192
Table 9-3: Status of the Contractors Invoices (EMH) ........................................................................ 206

Page vii

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

EXECUTIVE SUMMARY

Neelum Jhelum Consultants (NJC) is preparing design and supervising the project construction.
This document reports the progress on the Design Review and Construction of the Neelum
Jhelum Hydroelectric Project for the month of January 2016. Project activities have been geared
to achieve the targets as per revised schedule by working all weekdays continuously round the
clock. Progress for various project components are briefly given below:

Visitors/Meetings: Besides visits by the senior Consultant staff to project sites, the other
important visitors and meetings held at project sites are given below:

Site C1: WAPDA M&S (Monitoring and Surveillance) team visited the site on 06 January 2016.

Chairman WAPDA visited the site on 20 January, 2016. CE/PD-NJHPC, PM-NJC, PMCGGC/CMEC and other site staff accompanied the Chairman.

Meetings: Fortnightly Progress Review/coordination meeting was held on 11 January, 2016.


Minutes of meeting were accepted as corrected.

Site C2: No visitor during the reporting period.

Meeting: Fortnightly Coordination/Progress review meetings were held on regular basis.

Site C3: WAPDA Monitoring & Surveillance Team visited site on 08 January, 2016.

Meetings: Mechanical, Electrical and Civil Liaison Meeting held on 29 December, 2015 and 12
January, 2016.

Structural Engineering Section: 04 original and 16 revised construction drawings were issued
to the Contractor and 82 shop drawings were reviewed and commented upon based on NJC
Construction drawings.

Hydraulics Engineering Section: The Consultants continued with the following tasks during
the month.

The intake arrangement is revised per access road conditions. Alternate options of the
access road to the powerhouse has been made and are under review Drawings are being
updated. The turbine calculations with TurbnPro software have been revised. Memo
about Nauseri Small Hydel Power Station (NSHPS) is also being updated. The power
house has been moved towards the riverside due to road alignment and drawings of
powerhouse section have been revised.

Page 1

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

The hydraulic analysis and design of protection works along Tarbela Fish Point, at Jhelum
River have been completed.

The queries regarding headloss in tunnel system has been duly responded.

Electrical Engineering Section: Electrical related Progress for the Powerhouse and
Transformer Cavern and other Various Electrical Issues are given in the Electrical Section of
this report.

Mechanical Engineering Section: The following drawings/documents were reviewed marked


and returned to the Client/Contractor:

M1 Calculations for the Turbine Guide Bearings

C3 Submit Control Building of HVAC System Layout Plan (D2), Calculation (D1) and
Catalogue

EMH FAT Reports of EMH Equipment

H1 Water Level Measuring Equipment Layout on Intake Block

Electrical & Mechanical Standards to be Supplied by the Contractor

M1 Drawings and Components Lists for Turbine and Generator

C3: Notes & Legend for Water and Supply and Sewerage System in Adit A5 (D2)

H1: The Drainage Pipe and Valve of Adit Bulkhead Plug A4 and A5

C3 H1 AP-057 Permanent Tailrace Dewatering System - 4 Pumps

C3: Area Chatter Kalas Water Treatment Plant Pump Manufacturer\'s Information and
Pump

C3: Report for Power House Bridge Cranes Load Test

H1 Mobile Tunnel Dewatering System - Scope of Supply and Commercial Issues

Geotechnical Engineering Section: The Consultants continued with the following tasks during
the month:

Rockfill dam shop drawings (D3) submitted by contractor vide letter # R-17986 is under
review and comments are being incorporated.

Issued PO-20190 on the Progress of Construction of Rockfill Dam to contractor to


improve progress by allocation of addition resource and proper planning and
management for timely completion of project.

Issued Reply via PO-20168 to contractors letter about expediting construction progress of
Rockfill Dam(R-18021).

Issued letter to WAPDA for the purchase of clay material of Rockfill Dam via PO-20165.

Issued letter to WAPDA about rejection of core material from Shalabagh source via PO20163, since the material does not fulfills the design requirements.

Testing for core material samples from Shalabagh C2 completed under geotechnical
design team supervision in UET Taxila Lab and CMTL WAPDA.

Method statement of quality control of clay submitted by contactor via letter# (R-18013) is
under review and draft comments are being prepared.

Page 2

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Site visit by the geotechnical team to sort out the issues with the Zone 3 backfill and
placement of core material.

Correlation between optimum moisture content and maximum dry density are being
studied for the placement of core material.

Draft filter design memo has been sent for senior review and comments.

Preparation of Fine and Coarse Filter blends for rockfill dam as per availability of material
from crushers at C1 is completed and details gradation envelopes has been sent to
contractor for further processing.

Layout plan and drawings for future mini hydro access roads have been revised and sent
to hydraulics sections for further comments.

Tunnelling Engineering Section:


Headrace Tunnel Junctions and Bifurcations: A complete set of tunnel junction drawings
were developed and issued to the contractor which addresses the junctions of all the access
tunnels with waterway tunnel. This include the junctions T4aL&R, T3L&R, A3aL&R and the
cross cut between points 17 & 18. The drawings reflect the concrete outline, reinforcement
details, backfill details, grouting and the drainage holes locations and depths.

An updated set of drawings for the bifurcation T3c were issued to the Contractor. This set
includes the concrete outline, reinforcement drawings and the excavation profile of the junction.

Headrace Tunnel Plan & Profile Drawings: The plan and profile drawings for the complete
headrace tunnels showing the concrete lining details and respective chainages are being
updated.

Adit A1: Adit A1 is the permanent access to the headrace tunnel. Therefore, this access is
provided with a permanent concrete pavement. A drawing reflecting the pavement details is
being prepared.

Adit A2: Adit A2 is the permanent access to the headrace tunnel. This access shall be left
unplugged. A set of drawings for the general arrangement of various cross sections of the adit
A2 are being worked on. This drawing set also includes the treatment of the abandoned gallery
at station 2+037 in the adit A2.

Transition from Steel Liner to Concrete: A complete set of drawings showing transition
between the headrace concrete and steel liner is being developed. The set includes concrete
outline, cross sections and the reinforcement drawings.

Moreover, a 3D model for this transition is also being developed for the analysis of transition
concrete for the applied and considered loads.

Page 3

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Shop Drawing Review: The Contractor submitted 1 shop drawing under the letter R-18059.
The drawing was carefully reviewed and was stamped as approved except as noted.

Monitoring Data: Monitoring data from various locations of the project was received and
reviewed.

Progress Summary for Adits: All Adits measuring a total excavation of 13,785 meters in
length have been completed 100%. These includes Adit A1, A2, A2a, A3, A4, A4a
(Heading/benching), A5 (Access Tunnel) Access to Headrace Tunnel, A6 (Cable Tunnel),
Probing Tunnel, Access to Downstream Surge Tunnel, A7 and A8.

Progress summary for Tunnels and Major Works is given below:


NEELUM JHELUM HYDROELECTRIC PROJECT
EXCAVATION PROGRESS SUMMARY FOR TUNNELS
No

Site

Description

Total
Length
(m)

C1

HRT (T0A
T1A)

874.1

C1

HRT (LHTT)

4,638

C1

HRT (RHTT)

4,515

C1

C2

C2

C2

HRT (T3'L - 04)

678

C2

HRT (T3'R - 01)

758

C2

10

C2

11

C2

12

C2

13

C2

14

C2

15

C2

16

C2

17

C3

18

C3

19
20
21

C3

Right TBM
Disassembly
Chamber (#16
M1R)
HRT (04 - M1L)
TBM
HRT (01 M1R) TBM

HRT (T3'L T3aL)


HRT (T3'R T3aR)
HRT (T3c T3aL)
HRT (T3c T3aR)
HRT (T4 - T3c)
Heading
HRT (T4 - T3c)
Benching
HRT (T4 - M4)
Heading
HRT (T4 - M4)
Benching
HRT (22A - M4)
Heading
HRT (22A - M4)
Benching
TRT A6
Benching
TRT A7
Benching
TRT (T9 T10A)

96.2

11,098
11,072

3,097
3,164
1,062
1,063
1,664
1,664
2,988
2,988
3,403
3,403
1000
2489
411

Start
Date

15-Aug09
24-Mar11
13-Mar11
17-Nov14
31-Jan13
22-Feb13
01-Apr11
15-Apr11
07-Mar11
11-Mar11
27-Dec12
27-Dec12
24-Jul11
21-Jul14
21-Apr11
10-Oct13
02-Jun10
07-Oct13
1-July2015
30-May2015
19-Sep11

Completion
Date

Progress
till
December
2015 (m)

Progress
in January
2016 (m)

Progress
till January
2016 (m)

Percentage
Completion
(%)

Remarks

18-Feb-14

874.1

874.1

100

Completed

3,795.5

93

3,888.5

83.84

In progress

3,880.4

105.5

3,985.5

88.28

In progress

9.3

9.3

Suspended
for time
being

7436.1

210.0

7646.1

68.9

In
Progress

5,806

18.9

5824.9

52.6

In
Progress

678.0

678.0

100

Completed

758

758

100

Completed

3097.4

19

3097.4

100

Completed

3,164.3

3,164.3

100

Completed

898.7

119.1

1017.8

95.8

In
Progress

1005.2

58.2

1063.4

94.2

In
Progress

1664

1664

100

Completed

1664

1664

100

Completed

25-Jun-14

2988

2988

100

Completed

2,988

2,988

100

Completed

25-Oct-13

3,403

3,403

100

Completed

3,301

3,301

97

In
Progress

375

182

557

55

In
Progress

745

137

882

35

In
Progress

393

393

96

In
Progress

In
progress
In
progress
In
Progress
In
Progress

In
Progress
In
Progress

Page 4

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

22

C3

TRT (T9 - T7A)


3,140

22
23
24

C3

TRT (T7A - T9)

C3

HST (Upper
Leg) Benching
HST (Lower
Leg) Benching

C3

599
350

20-Jul11
17-Jul12
25-Nov2014
14-Nov2014

MONTHLY PROGRESS REPORT


JANUARY 2016

3,140

3,140

100

Completed

568

31

599

100

Completed

263

87

350

100

Completed

NEELUM JHELUM HYDROELECTRIC PROJECT


PROGRESS SUMMARY FOR MAJOR WORKS
No.

3.

4
5

Description

Excavation
Intake Block
& Desander
Excavation
Dam/Spillwa
y/Stilling
Basin
Overall
Concrete
Works (All
Headworks)
Power
House
Transformer
Hall

Total
3
(m )

Start Date

Completion
Date

Progress
till Dcember
2015 (m)

Progress in
January
2016 (m)

Progress
till January
2016 (m)

Percentage
Completion
(%)

Remarks

6-Aug-09

In progress

3,851,903

0.0

3,851,903

Almost
complete

Almost
Completed

624,145

16-Oct11

In progress

610,210

785

610,995

97.89 %

In progress

1,327,774

26-Nov2011

In progress

864,215

36,663

900,878

67.78%

In progress

25-Jul-14

148,463

148,463

100%

Completed

51,725

51,725

100%

Completed

148,463
51,725

21-Nov10
27-Mar11

The exact quantities of excavation in each segment are finalized after monthly survey. For this
reason, the summing up of this months excavation and last months reported to date excavation
might not be equal to the value of this months to date excavation stated in this report.

Planned versus Actual Progress of the Project Civil works is given in Figure 1-1 below:

Figure 1-1: Planned versus Actual Progress of the Project Civil Works

Page 5

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Consultant staff: Overall Staff Strength remained same as in the last month i.e. 554 persons.
Contractors Monthly Statements: Invoices and Payments: EMH-43 was submitted on 11
December 2015 and certified on 18 December 2015. EMH No.44 was submitted on 25 January
2016 and is under certification. EMH -45 was submitted on 19 January 2016 and certified on 25
January 2016. Amount certified

up to EMH No.45=RS.2,908,264,509 & Equivalent

Rs.22,464,707,395.

Monthly Statement No.077 was submitted on 7 September 2015 and certified on 4 October
2015. Monthly Statement No.078, for the months of July and August 2015, was submitted on
20 October 2015 and certified on 14 November 2015 .Monthly Statement No.079 was submitted
on 11 December 2015 and certified on 6 January 2016 Amount certified up to IPC No.79 =
RS. 60,708,688,711, USD 648,843,304 and EURO 8,706,118/-.

Programme and Schedule: A meeting was held at the WAPDA Administrative Staff College,
Islamabad on 23 January 2014 to deliberate on the concerns pertaining to the implementation of
the BEP The Engineer was requested to deliberate on the subject with inputs from the
Contractor and prepare / suggest alternate means to implement the Best Effort Plan. The
Engineer was advised to work out the economic viability of spending the extra money for the
acceleration vis--vis implementing the Project as planned in the PC-1 (Revised) by Mid-2016.
All critical activities issues discussed in the meeting were to be incorporated in the schedule.
Contractor vide letter GZBZJ-NJC-5819 dated 08 February 2014 submitted his Accelerated
Overall Schedule of the Project along with equipment resources, material resources, cost of
accelerated overall schedule and the EMH acceleration cost for Engineers review and
approval. His proposal costs were poorly substantiated and apparently grossly overestimated.

A meeting was held on 12 February 2014 at the WAPDA Administrative Staff College,
Islamabad to deliberate on "Best Efforts Plan prepared by the Consultants in the light of the
decision taken by the Chairman WAPDA in meeting held on 23 January 2014. Engineer
informed that the Contractor was requested to submit a logical schedule that honoured the
agreement made for the "Best Effort Plan" on 18 July 2013.The Contractor submitted a detailed
schedule on 08 February 2014, revised again on 09 February and re-revised again on 11
February 2014. This schedule shows first Generating Unit to be ready for wet testing on June
30, 2016 i.e. a delay of 06-months to the Best Effort Plan. The Contractor commented that they
had missed the best time for its implementation and they cannot do it on the agreed date.
MD/CEO, NJHPC criticized CCGGC-CMEC that despite signing the agreement on Best Effort
Plan, they are now withdrawing from their commitment.

Page 6

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Engineer vide letter No. PO-16426 dated 23 December, 2014 expresses his considerations that
Contractors intransigence is causing funding difficulties for himself, the Employer and the
Project. In continuation of above referred letter Engineer vide letter No. PO-16649 dated 19
January, 2015, believed that the Contractor has an opportunity to improve his construction
management performance by some simple, scientific improvements to his planning techniques
and technology. For the sake of this Engineer also suggested that Contractors Planning Expert
may meet with our Eng. Kalim Ahmad to discuss these opportunities to improve performance.
Engineer vide letter No. PO-16682 appreciated the Contractors compliance with the Employers
request for an updated Performance Guarantee which helps towards obtaining funding.

Construction schedule as per Sub Clause 14.2 for the project is given as per Annex A.

DRAFT AMENDMENT NO. 2 : The draft Amendment No.2 was submitted to the Client on 17
December 2013 (PO-13029) with a ceiling amount of Equivalent Pak Rs. 14,763,785,119/-. The
comments of Chief Engineer Contracts, NJHPC dated 31 December 2013 (R-11574) were
replied on 16 January 2014 (PO-13291). Subsequently, these documents were reviewed by the
officials of the GM/PD, NJHPC in February 2014 and forwarded to GM (CCC) in 2

nd

week of

March 2014. CCC Comments dated 08 April 2014 (R-12356) were replied on 30 May 2014 (PO14530) in which Ceiling Amount of the Draft Amendment No. 2 was increased to Equivalent Pak
Rs. 16,008,132,677.

CCC officials, after site visits/meetings in June/July 2014 signed their interim recommendation
on 28 July 2014 (R-13763) Equivalent Pak Rs. 13,894/- million excluding the amounts for the
input of BOM Members and extra hours working compensation for the NJC local technical staff
posted at site. After a meeting with NJHPC Officials, NJC submitted their replies on 10 October
2014 (PO-15708 & PO-15709). Subsequently, a meeting with NJHPC officials was conducted
on 22 October 2014 (R-14070) and NJC submitted the requested documents on 27 October
2014. BOM NJC also discussed the issue during their meeting with Member (W) and NJHPC
Officials on 27 October 2014 (PO-15841) and requested for an early resolution and signing of
the Amendment No. 2. The issue of compensation for extra hours being worked by NJC local
technical staff was discussed in a number of meetings, lastly in May 2015, but yet not resolved.
NJC has submitted a notice to NJHPC (PO-18215) on 26 June 2015 informing that the
expenditures for local currency and Norwegian Krone (NOK) has exceeded the 80% of the
Ceilings agreed in the signed Amendment No. 2a with a request to early sign the Amendment
No. 2. A meeting with CEO NJHPC was scheduled for 03 August 2015 that was subsequently
postponed. The final version of Amendment No. 2 needs to be discussed and signed at the
earliest whereas client is awaiting approval of ongoing PC-1 revision as Amendment No. 2a has
exceeded the already approved provisions.

Page 7

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Amendment No. 2a; In view of the time required for the detailed evaluation and review of the
WAPDA Officials to recommend the Amendment No. 2, an Amendment No. 2a was signed on
19 June 2014 (PO-14783) with Ceiling Amount of Equivalent Pak Rs. 11,462,522,003/- by
adding the provisions approved subsequent to the signing of the Amendment No. 1 to make an
interim arrangement to help repatriation of funds by expatriate JV partners.

Quality Assurance/Quality Control:


Laboratories C1: Materials: - The Contractor continues to blend one truck load of greenstone
rock with one truck load of SS1 at their Spoil B crusher

Regarding the rock-fill dam clay core, the Contractor is busy establishing quality control
procedures at various borrow pits. The Engineer has explained to them that rejecting out of
spec material at the dam site is wrong, its better to reject and isolate the material at the
concerned borrow pit.

Laboratories C2: NJC took steps to ensure the Contractor at Adit 4 batch plant stopped storing
their cylinder test specimens out in the cold. They were immediately instructed to comply with
ASTM C 31 and store their cylinders in a heated box.

Laboratories C3: At C3 the multi-tester broke down, spare parts had to be flown in from China,
this machine and the one at C1 will be recalibrated as soon as the machine is back in operation.
The Contractor continues to use a small mobile pump to apply shotcrete in confined spaces in
and around the powerhouse where access by shotcrete jumbo is no longer possible.

QA/QC Laboratories: All the laboratories are operational and production tests and quality
monitoring tests are being performed on site. Detail test results for C1, C2 & C3 are given in a
separate report.

Non-Conformance Reports: The Engineer is issuing Non-Conformance Reports in an attempt


to monitor the corrective action of problems as well as to assist in the prevention of similar
problems in the future.

Environment: Environmental Monitoring Plan Implementation at project site(s) is continued.


Chief Environment continues to give his professional input for Environmental monitoring,
imparting training and interaction with Contractor staff and the line agencies/departments.
Details are given in a section of this report.

Summation: Site C1: The concrete works are in progress on all structures like Intake,
sedimentation basin, Spillway (roof slab), Debris Channel, Collecting canal and Headrace
Tunnel. The preparatory works for construction of Rockfill dam also continued with foundation
treatment and other trial procedures. Excavation for U/S RCC River Training works is in

Page 8

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

progress and. 785 m excavation was carried out in Diversion dam area. Thus cumulative
excavation Up to date is 610,995(% Completed= 97.89 %).

No excavation was carried out in the Desander area, Therefore, cumulative quantity of
3

excavation is 3,851,903 m for Intake & Desander.

Excavation in LHTT continued by Drill & Blast method and 93.0 m was excavated. Total
excavated length is 3,888.5 m.

Excavation in RHTT continued by Drill & Blast method and 105.5 m was excavated. Total
excavated length is 3,985.9 m.

Concrete lining at U/S HRT & RHTT continued during the month.

Presently, River is flowing through Diversion tunnel only.

Site C2: Neelum TBM achieved a progress of 210m and the Jhelum TBM achieved a progress
of 18.9m making cumulative progress in left and right headrace tunnel equal to 7646.0m and
5824.9m respectively. Neelum and Jhelum TBM broke through into the junction of Adit A2a on
11th January 2014 and 24th January 2014 respectively.
th

Excavation in Headrace Tunnel downstream of T3 has been completed on 8 Dec, 2015 and 8

th

November, 2015 in left and right headrace tunnel respectively. Right headrace breakthrough
has been successfully achieved on 9

th

January, 2016. Contractor has achieved 119.1m

progress in T3c ~ T3aL and cumulative progress in left tunnel is 1017.8.

Site C3: Tunnelling: Excavation activities of bench in Tailrace Tunnel, Headrace Surge
Tunnel

(Benching) is in- progress. No activity for bench excavation of headrace tunnel

observed. Concrete lining in Headrace Tunnel remained is in progress. PH unit No 1, 2, 3 & 4


civil, mechanical and electrical works are in progress. Transformer hall concrete work 99.12%
is been completed. Excavation cycle in Tunnels, comprising, survey and alignment, drilling
for blast holes, charging, blasting and ventilation, mucking, scaling, geological mappings,
st

Rock support work (1

layer Sc, fully grouted rock bolting, wire mesh and 2

nd

layer

shotcrete) and all other activities were fully supervised by the NJC site staff, round the clock
in two shifts.

Headrace Tunnel (22a-M4): Top heading excavation of 3,403m long headrace tunnel already
been completed. Bench excavation is stopped at Ch: 0+102 but invert concrete and concrete
lining of crown, walls and invert continued during the month. To date Concrete lining (walls &
crown) is 2916m and Concrete of Invert lining is 2675m.

Page 9

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Headrace Manifold (Invert + Wall & Crown): In Headrace Manifold, concrete work in
3

progress. Until now 1451m (66%) concrete complete out of total estimated quantity of 2,200m .

Powerhouse: Excavation completed on 02 July 2014.

Concrete Work: During the month of January 2016, concrete poured at Unit-1 turbine
foundation up to El.588.00, Unit-3 Generation foundation and slab/beams El.594.20 etc. Total
3

quantity of concrete poured till date is 25,964 m (90%) out of total 28,280 m .

Busbar Tunnels: Excavation completed on September 20, 2012.

Concrete Work: During the reporting month, concrete poured at Unit-3 slabs P1 & P2. . To
3

date poured quantity of concrete is 799m (43%) out of 1850 m

Transformer Hall: Excavation completed on June 21, 2013.

Concrete Work: During the reporting month, concrete poured at HVAC cable trenches wall,
Unit-1 & 2 2

nd

stage concrete for rails at crane beam etc. Total quantity of concrete poured
3

toward the end of reporting period is 7,048m (99%).

Penstock Tunnels (1, 2, 3, 4): In penstock Tunnels, concrete work in progress. Until now 396m
(90%) concrete complete out of total estimated quantity of 439m.
3

Draft Tubes (1, 2, 3, 4): In draft tubes, concrete work is in progress. Until now 3,397m (54%)
3

concrete complete out of total estimated quantity of 6,258m .

Water Tank: Excavation has already been completed and the concrete work done is 71%. No
concrete work was done during the reporting period.
A7-Outlet Structure: In A7 outlet structure, concrete work is in progress. Until now 4,302m

(55%) concrete complete out of total estimated quantity of 7,860m . Contractor mainly worked
in sluice structure and Culvert invert slab reinforcement installation.

Tailrace Tunnel: Excavation of 3,551m long Tailrace tunnel continued during the month;
presently contractor is advancing from (A-7) on upstream face T9 to T7A and excavation from
(A-6) towards downstream face T7A to T8. On 30-05-2015, Contractor started excavation of
Bench from Ch: 1+000 towards outlet.

Page 10

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

ACTION REQUIRED FROM CLIENT IN THE MONTH OF JANUARY 2016

Pending Client deliverables that the Client needs to address are as follows:

C1: A small portion of land on two locations in Spoil Deposit B has been awarded to
WAPDA on June 13, 2013 (Award No: 02/2013) but the Employer hasn`t yet been given
the possession of the subject land by Local Administration. Therefore, it is still to be
handed over to the Contractor. The case is under process with the Employer and local
administration.

Engineer has requested the Employer vide Letter Ref. PO-13033, Dated: December 17,
2013 for removal of shops near main Batching Plant that are creating hindrance for
smooth transit of hauling units. The removal these shops was started on November 08,
2015 and completed on November 17, 2015.

VOs requiring approval are given at Annex C.

Page 11

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

INTRODUCTION

The Pakistan Water & Power Development Authority completed the bidding phase for the
construction of the 963 MW Neelum Jhelum Hydroelectric Project, and signed a construction
contract with the successful bidder CGGC-CMEC Consortium 19 December 2007 for an amount
of Rs.90,900,240,404 and a construction period of 93 months. The Contract commenced on
30January 2008 with a scheduled completion date of 30 October 2015.

The Client then appointed Neelum-Jhelum Consultants on 15 May 2008. The Consultant was
appointed to review the design and prepare construction drawings for the Project and supervise
the works. The Consultant started with preliminary support work from early June 2008; the
agreement was only activated on 01 August 2008.

Neelum Jhelum Consultants are a multinational Joint Venture of MWH (USA), NORPLAN
(Norway), NESPAK (Pakistan), ACE (Pakistan) and NDC (Pakistan); with MWH as the Lead
Consultant. Figure 2-1 shows the location of the Project.

Figure 2-1: Project Location

This document reports on the progress of the Project for January 2016 and includes the
progress on design and the supervision works.

Page 12

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

CLIENT DELIVERABLES

The pending Client deliverables that the Client needs to address are as follows:

A small portion of land on two locations in Spoil Deposit B has been awarded to WAPDA
on June 13, 2013 (Award No: 02/2013) but the Employer hasn`t yet been given the
possession of the subject land by Local Administration. Therefore, it is still to be handed
over to the Contractor. The case is under process with the Employer and local
administration.

Engineer has requested the Employer vide Letter Ref. PO-13033, Dated: December 17,
2013 for removal of shops near main Batching Plant that are creating hindrance for
smooth transit of hauling units. These shops are still to be removed and their presence is
creating a bottleneck.
VOs requiring approval is given at Annex C.

3.1

AVAILABILITY OF LAND

Most of the land has been acquired / taken on lease and handed over to the contractor by
NJHPC but some additional land is yet under acquisition processing. The history of land
acquisition from start of the project and the present status is given in Table 3-1:

Table 3-1: Status of Land Acquisition


Site

Detail

Handover dates

C1

Contractor's Residential Colony

23 March 2008

C1

Steel Fabricated Yard

01 August 2008

C1

Diversion road to Nauseri (Left bank of Nausada Nullah upto

31 July 2008

Ch. 0+370)
C1

Diversion road to Nauseri (Left/right bank of Nausada Nullah

20 February 2009

upto bridge # 02 including crushing & batching plant)


C1

Spoil Deposit ''E''

05 March 2009

C1

Spoil Deposit ''B'' (Portion)

08 April 2009

C1

Explosive Magazine

17 June 2009

C1

Access road to spoil area B through army area along left bank

24 July 2009

of Neelum River
C1

Desander / Sedimentation

24 July 2009

C1

Intake

24 July 2009

C1

Left Abutment of Main Dam

24 July 2009

C1

Spoil Deposit ''C''

24 July 2009

Page 13

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Site

MONTHLY PROGRESS REPORT


JANUARY 2016

Detail

Handover dates

C1

Main Dam, Diversion Tunnel and Coffer dam

5 August 2009

C1

Spoil Deposit ''B'' (Portion)

11 March 2010

C1

Spoil Deposit ''A''

C1

Access road to spoil deposit A and B areas

C1

Temporary carpentry shop in permanent colony area

22 July 2010

C1

Spoil Deposit F

03 April 2011

C1

Enlargement of Spoil B (Only Govt. Land)

24 November 2011

C1

Land for widening the Panjkot Nullah at Ch. 0+350 & Ch. 0+800

To be Handed over

C1

Spoil Deposit G

C1

Part of Diversion road to Panjkot + Small Portion of Desander

10 May 2010
15 December 2009

06 June 2012

Area

08 August 2012
13 November 2014

C1

Land for Greenstone Quarry at Spoil B

C1

Shops near main batching plant

To be acquired

C2

Road from Garhi Dupatta Bridge over Jhelum to Thotha

Govt. Contract

C2

Road from Thotta to Adit A2

Govt. Contract

C2

House near Adit A4

C2

Flour mill near Adit A2

10 December 2010

C2

Land for water tank in contractor camp

3 December 2009

C2

Land for access road to Adit A2

26 November 2008

C2

Land for access road to Adit A3

26 November 2008

C2

Access road for Adit A3

26 November 2008

C2

Possession of portal A4

17 February 2008

C2

Possession of portal A2

26 November 2008

C2

Possession of portal A3

26 November 2008

C2

Spoil deposits

C2

Spoil deposit for Adit A4

C2

Contractors camp

30 August 2008

C2

Leased land for TBM HFO Generator Station

15 August 2011

C2

Leased land for TBM prefabrication yard

14 October 2011

(on lease for 2 years)

28 January 2010

30 July 2008
17 February 2009

Page 14

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Site

MONTHLY PROGRESS REPORT


JANUARY 2016

Detail

Handover dates

C2

TBM Transportation Area

03 December 2011

C2

TBM Conveyor Belt end Area

C2

TBM Staff Residential & Workshop Area

C2

Additional spoil deposit area for Adit A4 (82,163.5m )

C2

Jandarbain Nullah

Accessible

C2

Access to site (from Muzaffarabad to portal A4)

Accessible

C2

Access to site (from Bridge No. 1 to portal A3)

Accessible

C2

Production and accommodation land in the Adit A4a Portal

C2

Steel Process of Jhelum lining and workshop

C2

Land for HV Electrical Poles

Not Handed Over

C2

New land at Tandali Fish Point

Not Handed Over

C3

Contractor camp on left side of Agar Nallah

Handed Over

C3

Contractor camp on right bank of Agar Nallah

07 April 2008

C3

Contractors colony Agar Nallah

07 April 2008

C3

Access to site (from Agar bridge to portal of A5, A6)

30 July 2008

C3

Access to site (from portal A5 & A6 to production camp)

30 July 2008

C3

Spoil deposit

30 July 2008

C3

Production plant & camp

30 July 2008

C3

Cable & access tunnel

7 April 2008

C3

Portal 5, Portal 6

30 July 2008

C3

Residential Colony except shops

30 July 2008

C3

M Deposit Area (currently required portion)

C3

Shops located on road to Komi Kot for C3 Permanent Colony

C3

Additional Land for Spoil Dump A8

09 April 2012
23 December 2011
2

09 April 2012

17 February 2012
10 September 2012

05 October 2009
22 June 2010
03 August 2013

Items of specific interest are:

About 14000m residential & office land for Lot H1 has been requested by the Contractor
to be provided before 31 May 2013 but Engineer and Employer considers that their
contractual demand has been already satisfied and even after finalization of Spoil B and
E, sufficient area will be available for Contractors use. Contractor is presently using
developed spoil G for construction of some of its facilities for CMEC. Some of the
buildings have been constructed there and also CMEC is using this area as a storage

Page 15

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

yard for various mechanical and hydraulics components of the Head works like, trash
racks and under sluice gates etc.

3.2

ACCESS TO SITE

Details about the access to different project sites is given below:

3.2.1

Site Roads and Bridges At Site C1

Access roads to different construction areas at site are maintained manually. Slush is present in
the low lying sections of these roads due to water entering from adjacent construction areas and
slopes. The situation gets even worse after rain. So in general, the conditions of these access
roads are not good.

3.2.1.1

Access into Debris Channel

Access road into Debris Channel through Bailey bridge is serving its purpose.

3.2.1.2

Up-gradation of the Road between Muzaffarabad and Nauseri

The stretch of this road from the junction of contractor`s camp to the Nauseri terrace is in
extremely poor condition. This road upto the batching plant is also used by the heavy hauling
units transporting construction material to the site which play a major role in its deterioration.
After rain, the water get accumulated on the roads due to poor drainage system that brings a lot
of trouble not only to the public/local community but also to the smooth transit of project
movements (machinery, Engineer/Employer`s vehicle etc.).

3.2.1.3

Muzaffarabad-Atthmaqam Road (Landslide above Rockfill dam)

Main access road (Muzaffarabad-Athmaqam) remains intermittently closed when it rains with
consequential slided material. However, the highway department then clears the road as an
excavator (backhoe & Dozer) is permanently deployed there. But unfortunately, the material is
pushed down the hill into the construction area of Rockfill dam and during this period the
activities for Rock-fill dam are suspended due to safety concerns of the workers.

3.2.1.4

Crossing of Neelum River near C1

New Nauseri Bridge was formally inaugurated by PM-AJ&K on May 26, 2014.

Page 16

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

th

Nauseri Bridge is operational since 30 August 2012. The approach road from right abutment of
Nauseri Bridge towards Athmaqam has been completed. Construction of approach road on left
abutment still to be done by the AJK Highway Department.

3.2.1.5

Site Roads and Bridges

The status of site roads and development thereof is given in Table 3-2:

Table 3-2: Status of Site Roads and Bridges


Site

Area / Road

Status

C1

Road from temporary entrance gate to Nausada Bridge

Access road completed/

No. 1

maintenance in progress

Road from Nausada Bridge No. 1 to Intake Dam

Access road completed/

C1

maintenance in progress
C1

New Bridge No. 1 over Nausada Nallah

Access road completed/


maintenance in progress

C1

C1

Road along Desander including ramp from road to Adit

Access road completed/

A1

maintenance in progress

Road from Nausada Bridge No. 1, to Tunnel Adit A1

Access road completed/


maintenance in progress

C1

Connecting Road from Top of Spoil Deposits to

Pending

Existing Panjkot Road


C1

New Bridge No. 2 over Nausada Nallah

Pending

C1

Foot Bridge over Panjkot Nallah

Pending

C2

Road from Garhi Dupatta Bridge over Jhelum to Thotta

Govt. Contract

C2

Road from Thotta to Adit A2

Govt. Contract

C2

Bridge No. 1 (Linking access road to Adit A3 & A2 and

Completed/ operational

laboratory & plant)


C2

Bridge No. 2 (Linking access road to Adit A3 & A2 and

Completed/ operational

Portal Adit A3)


C2

TBM Bridge

Repair work started.

C2

Bridge No. 2 (Dismantling of this bridge is in progress Temporary / Bailey bridge


and its replacement (Bailey Bridge at Ch. 2+005) is Completed and is open for
completed.

C2

traffic.

Bridge No. 3

Pending

Page 17

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Site

MONTHLY PROGRESS REPORT


JANUARY 2016

Area / Road

Status

C2

Bridge No. 4

Pending

C2

New Public Road to Majhoi

Pending

C2

Access Road to Adit A4 at Majhoi

Pending

C2

Access Road to Top of Spoil Deposit at Majhoi

Pending

C3

Temporary access road from Chatter Kalas to Agar Contractor is maintaining it


Nallah

C3

Access road from Chatter Kalas to Agar Nallah

Work in progress

C3

Access road to upper surge tunnel

In process

C3

Access road to outlet at Zaminabad

In process

C3

Agar Nallah Canalization

C3

Permanent access road from the Murree-Muzaffarabad

Retaining & breast walls

road to Adit A7.

completed except slope

Work in progress.

protection works and


culverts.
C3

Temporary access road from Chatter Kalas to Agar Contractor is maintaining it


Nallah

3.3

C3

Access road from Chatter Kalas to Agar Nallah

C3

Access road to upper surge tunnel

Work in progress
In process

ELECTRICITY

At Site C1 HFO Generator remained operational throughout the month.

At C2: The power supply remained steady.

At C3: The power supply remained operational during the reporting period.

3.4

REQUIRED CLIENT INPUTS & APPROVALS

Various requests and recommendations are still with the Client and require his attention
specially for the recommendation on the claims and other matters related with the many
pending appropriation requests filed from time to time in the past (Tables 9-1, 9-2 and Annexes
- C & D).

Page 18

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

CONSULTANTS PROGRESS

4.1

MOBILIZATION / MEETINGS

4.1.1

Site C1

4.1.2

MONTHLY PROGRESS REPORT


JANUARY 2016

Two junior engineers have joined the supervisory staff at C1.

Routinely weekly meetings were continued.

Site C2

The weekly progress meeting with client and contractor regarding Drill & Blast, Concrete
Lining and Above Ground earthwork activities remained continued on each Monday at
10:00 am.

The weekly progress meeting with client and contractor regarding TBM remained
continued on each Tuesday at 10:00 am.

4.1.3

Site C3

One ARE and one site inspector (Electrical) has joined the supervisory staff at C3 during
the reporting period.

4.1.4

Routinely weekly were meetings continued.

Possession of Site and Access

1298 Kanal of land was required at Site C3. The process of handing/taking over of this land
between WAPDA and the Contractor have been completed.

4.2

PROJECT ACCOMMODATION

Muzaffarabad: After completion of all the formalities the Design Office staff has been mostly
shifted to Muzaffarabad in the newly hired office and residential accommodation. This Design
Office is fully operational at Muzaffarabad.

Site C1: Contractor completed the modification of old Engineer`s offices into dormitories as
instructed by Engineer vide letter PO-16034 Dated: 19 November 2014 to accommodate new
staff in future. The room has been occupied by the new staff members. Still some additional
accommodation is required.
Site C2: Engineers staff at C2 moved to CGGC Residential Colony Stage II by December
2011 in the TBM Camp. Additional accommodation is also required with the increased staff
deployments.

Page 19

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Site C3: BOQs item 1.1.3 for C3 provides only two single accommodations (75 m each) for
the Engineer. This has been accommodating some of Engineers staff in the rooms near the
existing office of CRE-C3. To accommodate NJC staff at C3, Engineer rented Hafeez House
with 10 bedrooms on 20 December 2010. The Contractor provided accommodation is still
unlikely to be available soon.

4.3

SURVEYS

Surveys conducted during the month are as below:

4.3.1

Site C1
Headrace Tunnel Excavation:

U/S HRT:

No Activity

Left Side:

Ch: 4+620.5~4+713.5

Right Side:

Ch: 4+713.4~4+818.9

Concrete Lining Headrace Tunnel


U/S HRT: Joint survey for concrete Lining from Ch: 0+18.0~0+005.0

LHTT: No Activity

RHTT: Joint survey for bedding concrete at Ch: 2+511.1~2+600.1, Ch: 2+780.2~2+830.1
& Ch: 1+974.2~2+060.2
st

And Joint survey for lining concrete at 1 formwork from Ch: 1+632.0~1+750.9, 2nd form work
Ch: 2+238.2~2+357.0 & Invert Concrete Ch: 0+894.9~0+906.8 & Ch: 1+974.2~1+998.2

Dam/Desander/Sedimentation Basin/EMH Works


Joint survey for all Electro-mechanical and Hydraulics components (earthing wire, embedded
steel face and base plates and other accessories at spillway piers for radial gates and stoplogs,
steel plates for undersluice gates at intake structure, temperature gauges and other instruments
as when required) prior to their installation at different structures of Headworks.

Joint survey for drainage filter layer in the trenches of sedimentation basin foundation.

Table 4-1: Dam/Intake/stilling Basin/Sedimentation Basin


Structure
Right Bank structure
(Debris Channel floor ,
U/S & D/S Retaining
walls for Rockfill Dam)

Description
U/S Retaining wall

No Activity

Block 6-1

984.8~987.5

Block 6-2

No Activity

Page 20

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Block 6-4
Rockfill Dam
Foundation
Pier 5-1
Pier 5-2

Dam Spillway

Pier 5-3
Pier 5-4
Pier 5-5
Pier 5-6
Pier 5-7
Pier 5-8
Bay # 1
Block 0

Intake Block

MONTHLY PROGRESS REPORT


JANUARY 2016

No Activity
979.5~983.50
No Activity
987.0~984.0 (Tendons Dressing / Close
Packing)
No Activity
No Activity
No Activity
990.0~995.076 (Tendons Dressing / Close
Packing)
No Activity
No Activity
987.7~991.2 (Trunnion Block)
No Activity

1011.6~1014.30 (Deck Slab L/S)

Block 1

1009.9~1013.3 (Deck Slab R/S)

Block 2

No Activity

994.3~998.5 (L/S)

997.6~998.5 (R/S)

991.0~991.5 Intake Block-3 (2nd

Block 3

Stage Concrete)
Block 5-1-4

Stilling Basin /SB left


guide wall / SB left
retaining wall

Block 5-1-5

No Activity
981.156~986.167

Block 5-1-6

979.3~984.5

Block 5-1-7
Block 5-1-8

971.5~980.0
968.2~973.5

Block 5-1-9

969.9~976.8

Block 5-1-10

976.9~980.30

Block 5-1-11

973.50~976.8

Block 5-1-12

970.0~973.5

Block 5-1-13

962.054~966.0
(P1-4) - 991.0~992.85
(S1-5) - 985.63~985.73

D-Block 1

(S1-2) - No Activity
(P2-3) - 1002.55~1004.25
(P2-1) - No Activity
Sedimentation Basin

(P2-6) - No Activity
(S2-3) - 1000.527~1002.227

D-Block 2

(S2-1) - No Activity
(S2-4) - No Activity
(S2-6) - No Activity
(P2-4) - No Activity

Page 21

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

(P3-3) - 999.90~1002.07
(S3-3) - No Activity
(S3-4) - No Activity
D-Block 3

(S3-6) - No Activity
(P3-4) - No Activity
(S3-1) - No Activity
(S4-1) - No Activity
(P4-1) - No Activity

D-Block 4

(P4-3) - 998.35~1000.05
(S4-3) - No Activity
(S5-3) - 996.16~1001.90
(P5-3) - 998.02~999.729
(P5-4) - 984.19~985.91

D-Block 5

(S5-1) - No Activity
(S5-3) - No Activity
(P6-1) - No Activity

D-Block 6

(P6-3) - 999.557~999.406
(P7-1) - 999.73~1002.83
(P7-3) - No Activity

D-Block 7

(S7-3) - 992.28~993.93
(S7-1) - 993.602~996.560
(P8-3) - No Activity
(P8-1) - 996.41~999.41

D-Block 8

(S8-1) - 999.24~1002.2
(S8-3) - 990.087~991.787
(P9-1) - 1002.09~1005.09
(P9-3) - 993.35~996.34

D-Block 9

(S9-1) - 995.914~998.914
(S9-3) - No Activity
(P10-1) - 998.76~1004.75
(S10-1) - 988.1~989.61
(P10-3) - 989.613~993.16

D-Block 10

(P10-2) - 988.0~989.61
(S10-6) - No Activity

Backfill Concrete
Under Sedimentation
Basin

D-Block 11
Intake Block # 2 (R/S)
D/S
(Fill
Concrete)
Intake Block # 3 L/S
D/S
(Fill Concrete)

Page 22

(S11-2) - No Activity
No Activity

No Activity

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Collecting Canal

Intake Block # 3 R/S


D/S
(Fill Concrete)
Block (P-1)
Block B-1

MONTHLY PROGRESS REPORT


JANUARY 2016

992.07~994.05 D-Block -1 (P1-4 & S1-6)


984.005~992.537
981.4~982.9
(P4) - 971.0~972.0

U/S Spillway
Protection slab
U/S River Training
Works (including U/S
Spillway Protection slab)

4.3.2

(P5) - 971.0~972.0
(S6) - 968.9~969.0 (Bedding Concrete)

Intake U/S RCC River


Training wall

Spoil Deposit B- No Activity

Spoil Deposit F- No Activity

Spoil Deposit G- No Activity

982.3~985.0
987.5~990.40 Intake U/S RCC River
Training wall (Behind Intake Block-3)

Site C2

Surveys conducted during the month are as below:

CHECKING OF

224 at Headrace Tunnel T4~M4 CH. D5+3900.7~3889.1 (walls &

NEEDLE BEAM AND

Crown), 225 at Headrace Tunnel T4~M4 CH. D5+1750.9~1739.7

HEAD FORMWORK

(walls & Crown), Panel #. 226 at Headrace Tunnel T4~M4 CH.

OF PANEL NO.:

D5+3889.1~3877.9 (walls & Crown), 166 at Headrace Tunnel


T3L~T3aL CH. D3+3139.0~3150.8 (walls & Crown), 167 at Headrace
Tunnel T3L~T3aL CH. D3+3174.3~3186.1(walls & Roof), 227 at
Headrace Tunnel T4~M4 CH. D5+1739.7~1728.4 (walls & Crown),
211 at Headrace Tunnel T3R~T3aR CH. D3+3644.9~3657.0, 228 at
Headrace Tunnel T4~M4 CH. D5+3877.9~3866.5 (walls & Crown),
168 at Headrace Tunnel T3L~T3aL CH. D3+3186.1~3197.7 (walls &
Roof), 169 at Headrace Tunnel T3L~T3aL CH. D3+3150.8~3162.4
(walls & Roof), 229 at Headrace Tunnel T4~M4 CH.
D5+3866.5~3855.0 (walls & Crown), 212 at Headrace Tunnel
T3R~T3aR CH. D3+3657.0~3669.0, 230 at Headrace Tunnel T4~M4
CH. D5+3855.0~3843.5 (walls & Crown), 231 at Headrace Tunnel
T4~M4 CH. D5+3843.5~3832.5 (walls & Crown), 232 at Headrace
Tunnel T4~M4 CH. D5+3832.5~3820.8 (walls & Crown) & 172 at
Headrace Tunnel T3L~T3aL CH. D3+3209.4~3221.1 (walls & Roof)

CHECKING OF LEVEL

T4~M4 at CH. D5+3946.6~3923.6 (Final invert), T4~T3C at CH.

FOR INVERT

D5+231.4~207.4 (Final invert), T4~T3C at CH. D5+41.5~30.23,

CONCRETE

T4~T3C at CH. D5+207.4~183.5 (Final invert), T4~T3C at CH.

Page 23

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

LOCATED AT:

MONTHLY PROGRESS REPORT


JANUARY 2016

D5+183.5~159.6 (Final invert), T4~T3C at CH. D5+159.6~135.4


(Final invert), T4~T3C at CH. D5+46.0~30.23, T4~T3C at CH.
D5+135.4~111.4 (Final invert), T4~M4 at CH. D5+3923.6~3900.7
(Final invert), T4~T3C at CH. D5+111.4~87.4 (Final invert) &
T3L~T3aL at CH. D3+3056.8~3080.6 (Final invert)

CHECKING OF

(T3aR~T3bR) at CH. D4+73.6~79.9, (T3aR~T3bR) at CH.

EXCAVATION FOR

D4+79.9~85.5, (T3bR~T3aR) at CH. D4+64.2~70.3, T3L~T3aL at

INVERT CONCRETE

CH. D3+3667.0~3682.6, (T3bR~T3aR) at CH. D4+57.6~64.2,

LOCATED AT:

T3L~T3aL at CH. D3+3080.6~3114.3, T3L~T2L at CH.


D3+967.4~956.2, (T3aR~T3bR) at CH. D4+458.5~466.2 &
(T3bR~T3aR) at CH. D4+50.7~57.6
st

st

CHECKING OF

at Ch. 0+000~0+060 1 layer, at Ch.1+227~1+302 1 layer, at Ch.

LENGTH, WIDTH &

0+837~0+918 1 layer and at Ch. 0+000~0+060 2

st

nd

layer.

HEIGHT OF RIP RAP


WALL OF JB
NULLAH:

4.3.3

Site C3

Headrace Tunnel:

Checked levels and alignment of shutter for concrete lining of headrace tunnel at Ch:
0+711.20~0+651.20, 0+615.10~ 0+506.70 & 0+471.10~0+423.20

Powerhouse:

Checked levels and alignment of formwork for bonneted gate of Powerhouse Unit bay-3 at
El. 584.6~585.00.

Checked levels and alignment of Powerhouse Unit bay-3 at El. 591~592.765 & 592.765 ~
594.20.

Checked levels and alignment of formwork for unit-1 (Turbine beam 2nd lift) at
El.586.4.00~588

Transformer Hall:

Checked levels and alignment of Cable trench in Transformer hall (HAVEC Room) from
Ch: 0+00 ~0+14 at El.611.30~612.00

Draft Tube Tunnels:

Checked levels and alignment of formwork for crown of Draft tube-1 at Ch: 21.5~24.00.

Checked levels and alignment of formwork for crown of Draft tube-1 at Ch:
50.613~65.613.

Checked levels and alignment of formwork for crown of Draft tube-1 at Ch:
0+24.0~35.613.

Page 24

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Bus Bar Tunnels:

Checked levels and alignment of formwork for BusBar Tunnel P1 of Powerhouse Unit bay3 at Ch: 0-0.2~0+9.65 at El. 592.60~594.200.

Checked levels and alignment of formwork for BusBar Tunnel P2 of Powerhouse Unit bay3 at Ch: 0+9.65~0+19.5 at El. 592.60~594.200.

Tailrace Tunnel:

Checked levels and alignment for invert concrete of Tailrace Tunnel from Ch:
1+567~1+685 & 0+670~0+700.

Tailrace Outlet Structure:

Checked levels and alignment of gate area.

Water Treatment Plant:

Checked levels and alignment for blinding concrete of WTP chlorination room beam at El.
628.125 ~ 628.50.

Checked levels and alignment for blinding concrete of WTP Sedimentation tank and stairs
columns footing at El. 626.00~626.075 varies.

Checked levels and alignment for wall concrete of WTP Sedimentation tank at El. 625.745
~ 627.095 varies.

Switchyard:

Checked levels and alignment of formwork for blinding concrete of SS-F1, SS-F4

Checked levels and alignment of formwork for footing concrete of SS-F1, SS-F3 & SS-F4.

Checked levels and alignment of formwork for pedestal concrete of SS-F1, CB-F1, SS-F4
& ES-F5.

Checked level and alignment of formwork for blinding concrete base slab and walls of TR1
& TR4.

Checked level and alignment of excavation and invert levels of perforated pipe line No. 3C
& 4D.

Checked level and alignment for blinding concrete of Manhole No. 2 & 3.

Checked level and alignment of formwork for base slab and wall concrete of Manhole No.
1, 3, 4 6, 8, 9, 10, 11, 12.

Checked level and alignment for foot print steel plate of pedestal SS-F1, SS-F3, SS-F4,
CB-F1, ES-F7, ES-F8.

Checked levels and alignment of formwork for blinding and wall concrete of RM-F1.

11kV Sub-Station:

Checked levels and alignment for blinding concrete.

Page 25

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Control Building:

Checked levels and alignment for cable trench of control building.

Agar Nullah:

Checked levels and alignment of protection wall 3rd step L/S from Ch: 0+121.50~0+136.

Checked levels and alignment of protection wall 2nd step L/S from Ch: 0+136~0+146,
0+146

~0+156,

0+198~0+208,

0+220~0+233,

0+248~0+263,

0+248~0+263

&

0+248~0+263.

Admin Building:

Checked levels and alignment for footing and neck column concrete at El. 628.025 ~
629.10.

Checked levels and alignment for footing and neck column concrete at El. 627.80 ~
628.175 and neck column top El. 629.10.

WAPDA Permanent Residential Colony:


CAT-III houses:

Checked level and alignment for excavation of compound wall footing, columns & lean
concrete in between house No. (8, 9, 10, 11), (12, 13) & (7, 12, 13)

Gate and Column:

Checked levels and alignment for gate and column of house No. 1, 2, 3, 4, 5, 6, 12 & 13.

Retaining wall for CAT-III houses:

Checked levels and alignment of retaining wall in between house No. 8, 9 &10, 11.

Boundary Wall:

Checked levels and alignment of formwork of excavation, lean, footing and long column
59 ~ 66.

Market

Checked level and alignment of roof slab bottom for concrete.

Mosque

Checked level and alignment of bracing beam and abutment.

Miscellaneous

Topographic survey on front side of switchyard / A5, A6 Adit for Helipad.

Topographic Survey of colony to Agar Nallah near Chinese camp boundary wall for
drainage.

Page 26

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Observation of section as built after shotcreting of Headrace Surge Branch Tunnel.

Observation of section as built after shotcreting of Draft Tube Tunnel-1, 2, 3 & 4.

Checked level of river water near A7 outlet structure.

4.4

GEOLOGY & GEOTECHNICAL

4.4.1

Additional Site Investigations

Additional site investigations are given below:

4.4.2

Geology

4.4.2.1

Site C1

Headrace Tunnel (T1A T1cL): From Ch: 4+620.5~4+713.5 (Geological mapping was
carried out.

Headrace Tunnel (T1A T1cR): From Ch: 4+713.4~4+818.9 (Geological mapping was
carried out.

Curtain grouting in the rock fill Dam is restarted at 02 Jan.2016.


There are 10 holes which include primary, secondary and
tertiary holes. One primary hole CGRB-2-1-P has been
drilled/completed up to 17 m and successfully grouted. And
CGRB-2-5-P is in progress and drilled up to 3m. Depth of holes
in row U/S-008 is 15m each and depth of holes in row U/S-006
will vary.

In Curtain Row at U/S-008, three primary holes has been


successfully grouted/completed up to 17 m.4th hole (CGRB-2-2-

Curtain Grouting

T) is in progress and drilled up to 7m. Depth of holes in row U/S008 is 15 m each and depth of holes in row U/S-006 will vary
according to site condition

Total
Estimated
amount of
drilling

Progress during
the Month

Total
Progress
Todate

870

66

224

Percent
Completed

25.74 %

Contact grouting in the tunnels is suspended since 29 November,


Contact Grouting

2014 due to prioritization of different activities in the tunnels by the


Contractor.

Page 27

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

4 (Four) Secondary consolidation holes has been drilled and


grouted at location D/S+26~ U/S -3.4 El. 964.0~967.6 (Right
abutment slope).Next row primary consolidation holes drilling is in
progress at El: 969.95
07 (seven) Secondary Holes for Consolidation Grouting on Right
Bank Grout Pad has been drilled and grouted successfully at
location D/S+27.06 ~ U/S -20.6 El. 966.5~969.5 (Right abutment
slope).
4 (Four) Tertiary consolidation holes has been drilled and grouted
at location D/S+26~ U/S -3.4 El. 964.0~967.6 (Right abutment
Consolidation

slope). Fixing of formwork is in progress for next row

Grouting

consolidation holes drilling at El: 969.0 m.


07 (seven) Primary Holes for Consolidation Grouting on Right
Bank Grout Pad has been drilled at location D/S+27.06 ~ U/S 20.6 El. 966.5~969.5 (Right abutment slope). Grouting of these
completed holes will be carried out as soon as possible.

Total Estimated
amount of
drilling

Progress
during the
Month (m)

Total
Progress
Todate

Percent
Completed

2,255

138

738

32.72

MBT Fault treatment has been completed successfully on


January 18, 2016.

Four (4) Rotary drilling machines are working for MBT fault
treatment and Total drilling progress 1096 m during this month.

46 holes were drilled and back filled with Bentonite.

Drilling machines shifted to stilling basin for the drilling of


drainage release holes.

MBT Treatment

Cleaning of MBT Fault treatment area is in progress for concrete


perforation holes.

Drainage Release
Holes at Stilling Basin

Total Estimated
amount of drilling
(m)

Progress
during the
month (m)

Total
Completed
length (m)

Percent
Completed

4,975

1096

4975

100

Drilling for Drainage Release holes started at stilling basin. Three


(03) holes out of 37 drilled up to 7 m.

Page 28

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Floor

MONTHLY PROGRESS REPORT


JANUARY 2016

Total
Estimated
amount of
drilling (m)

Progress
during the
week (m)

Total Progress
To date (m)

Percent
Completed (%)

259

21

21

8.11

Back fill grouting of the 29 PVC pipes have been performed at El:
979.5m.These pipes were placed at El: 975.5m (Bottom of pipes)
18 new PVC pipes have been fixed for back fill grouting at 8thlift
(Elev. 981.5) according to the site condition.
33 PVC pipes (Sleeves) have been installed for consolidation
grouting at 8th lift.
Geological mapping with scan line survey has been carried out at
Ch: U/S -13.19~D/S +19.981Elv: 979.5 ~ 981.5m for 8th lift.
Concrete placement of the 8th lift (El: 979.5~981.5m) has been
completed.
Backfill grouting of the 16 PVC pipes out of 22 was carried out at
El: 981.5m of grout pad. Bottom of these pipes was placed at
El:977.5m
11holes were drilled for anchor bars and 4 anchor bars were
installed seven (7) are remaining because these holes have too
much grout take (Mix design M45 for rock anchors).Due to high
Right slope of Dam

grout take work for anchor installation is suspended at El: 983.5


m (lift 9th). Cavities will be filled before anchor installation
Fixing of formwork is in progress for the next lift (9th) of grout pad
at El: 983.5 m.
Cleaning and washing is in progress for 9th lift of grout pad.
Four Anchor Bars were installed by using M-45 Mix Design.
Total 46 embedded PVC pipes extended for back fill grouting
above 9th lift concrete El: 983.5; ( 7th lift:2, 8th Lift:18, Anchor
Bar holes: 10, 9th Lift: 16)
Pour of 9th lift of concrete along Right Bank slope of Rock fill dam
was completed at location U/S-13.26~D/S+19.25 at El:
981.5~983.5
Cleaning and formwork installation for 10th lift of concrete is in
progress
2 PVC Pipes of 7th lift, 15 of 8th lift and 3 anchor bar holes
extended PVC pipes are Back Filled successfully on 9th lift
concrete El: 983.5

Greenstone Quarry &


Aggregates

The exploitation of the Greenstone Quarry is in progress and


material is supplied to crushing plants No. 2 by subcontractor M/S

Page 29

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

SACHAL Engineering works.


Local suppliers are supplying Greenstone to crushing plant. No.
2. Site supervisors are doing best to get the competent
Greenstone.
Sandstone supply from other sources by local Contractors
continued.
Monitoring of 22 Nos temperature gauges is in progress at
specified time intervals.
Geo-Technical
Instrumentation

Extension of 3 embedded Pendulum pipes along Dam Axis is


continuing with the progress of concrete lifts.
Effective aperture is checked systematically with the lift
concretes.
Geological Mapping has been performed at Up stream Rock
foundation Ch: U/S -197.35 ~ U/S-228.62 (El: 978.5 ~980.2m)
and foundation cleaning work is in progress.

Geological Mapping &


Blasting
for Excavation

Check of blast design at up stream Rock foundation Ch: U/S 197.35 ~ U/S-228.62 (El: 978.5~980.2m).
4 assignments of foundation Geological Mapping has been
carried out at different areas of Dam site as Debris Channel Rock
fill dam zone 3, Sand trap area block S-1/5 and 2 at Intake U/S
Left slope RCC retaining system.

4.4.2.2

Site C2

Neelum TBM: Completion of number 76th TST geological forecasting test.

Jhelum TBM: Completion of number 48th TST geological forecasting test.

Right Headrace Twin Tunnel Downstream (T3R - T3aR): Face mapping and tunnel map
digitizing work on CAD is in progress. Pre-excavation and grouting is also taking place on
this face.

Left Headrace Twin Tunnel Downstream (T3L - T3aL): Face mapping and tunnel map
digitizing work on CAD is in progress. Pre-excavation and grouting is also taking place on
this face.

Right Headrace Twin Tunnel Downstream (T3c - T3aR): Face mapping and tunnel map
digitizing work on CAD is in progress. Pre-excavation and grouting is also taking place on
this face.

Left Headrace Twin Tunnel Downstream (T3c - T3aL): Face mapping and tunnel map
digitizing work on CAD is in progress. Pre-excavation and grouting is also taking place on
this face.

Headrace Single Tunnel Downstream (T4 M4): Face mapping and tunnel map digitizing
work on CAD is in progress.

Page 30

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Instrumentation: Periodic monitoring of all extensometer and convergence station


remained in progress during the month.

4.4.2.3

Site C3

Tailrace Tunnel: Tunnel map digitizing work on CAD continued during the month.

Headrace Surge Shaft: Tunnel map digitizing work on CAD continued during the month.

A10 HEADRACE SURGE TUNNEL:


Excavation of 949.7m long Headrace Surge tunnel break through occurred on 14

th

October

2015

Bench excavation for 949.7m long Headrace Surge Tunnel started from Ch: 0+470 towards A10
(Upper Leg), and stopped at Ch: 0+065.8. During previous Month Contractor excavated from
Ch: 0+65.8 to0+12.1, Bench excavation from 0+12 to 0-25 has done during this month.
Similarly, bench excavation started form Ch: 0+407 towards Surge Shaft (lower leg). Excavation
has done from Ch:0+ 490.3 to 0+585.7 during this month.

HEADRACE SURGE BRANCH:


Bench excavation of 56m long headrace Surge Branch started on 30

th

Sept 2015 and

th

completed on 18 October 2015.

TAILRACE TUNNEL:
Bench excavation of 3,551m long Tailrace Tunnel remained in progress during the month,
presently Contractor is advancing from (A-7) and (A-6) towards outlet. The start chainage of
benching excavation is 1+005. Un-excavated portion in tailrace tunnel between Ch: 3+505.6 ~
3+523.6 (18m) left as plug.

INSTRUMENTATION
No new instrument was installed during this month. Periodic monitoring of instruments in PH,
TH and A7 outlet remained continued.

4.4.3

Geotechnical
The following drawings/documents were reviewed marked and returned to the Client/Contractor:

Rockfill dam shop drawings (D3) submitted by contractor vide letter # R-17986 is under
review and comments are being incorporated.

Issued PO-20190 on the Progress of Construction of Rockfill Dam to contractor to


improve progress by allocation of addition resource and proper planning and
management for timely completion of project.

Page 31

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Issued Reply via PO-20168 to contractors letter about expediting construction progress of
Rockfill Dam(R-18021).

Issued letter to WAPDA for the purchase of clay material of Rockfill Dam via PO-20165.

Issued letter to WAPDA about rejection of core material from Shalabagh source via PO20163, since the material does not fulfills the design requirements.

Testing for core material samples from Shalabagh C2 completed under geotechnical
design team supervision in UET Taxila Lab and CMTL WAPDA.

Method statement of quality control of clay submitted by contactor via letter# (R-18013) is
under review and draft comments are being prepared

Site visit by the geotechnical team to sort out the issues with the Zone 3 backfill and
placement of core material.

Correlation between optimum moisture content and maximum dry density are being
studied for the placement of core material.

Draft filter design memo has been sent for senior review and comments.

Preparation of Fine and Coarse Filter blends for rockfill dam as per availability of material
from crushers at C1 is completed and details gradation envelopes has been sent to
contractor for further processing.

Layout plan and drawings for future mini hydro access roads have been revised and sent
to hydraulics sections for further comments.

Drawings of access road to sedimentation basin berm for EL: 1056 are under review as
per latest available topographic condition.

Revision of Collecting Canal Drainage Plan and Section with revised pipe sizes and surface
drains (C1-C-2293, 2294 Rev-01) and Sedimentation Basin Drainage and Backfill details (C1-C2195 Rev-01) remained under progress.

C1 Backfill (Final Layout Plan) Drawings have remained under review.

Drawing for backfilling of transition section between upstream and downstream of intake slopes
have remained under study with two options.

4.5

TUNNELLING

4.5.1

Headrace Tunnel Junctions and Bifurcations


A complete set of tunnel junction drawings were developed and issued to the contractor which
addresses the junctions of all the access tunnels with waterway tunnel. This include the
junctions T4aL&R, T3L&R, A3aL&R and the cross cut between points 17 & 18. The drawings
reflect the concrete outline, reinforcement details, backfill details, grouting and the drainage
holes locations and depths.

An updated set of drawings for the bifurcation T3c were issued to the Contractor. This set
includes the concrete outline, reinforcement drawings and the excavation profile of the junction.

Page 32

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

4.5.2

MONTHLY PROGRESS REPORT


JANUARY 2016

Headrace Tunnel Plan & Profile Drawings

The plan and profile drawings for the complete headrace tunnels showing the concrete lining
details and respective chainages are being updated.

4.5.3

Adit A1

Adit A1 is the permanent access to the headrace tunnel. Therefore, this access is provided with
a permanent concrete pavement. A drawing reflecting the pavement details is being prepared.

4.5.4

Adit A2

Adit A2 is the permanent access to the headrace tunnel. This access shall be left unplugged. A
set of drawings for the general arrangement of various cross sections of the adit A2 are being
worked on. This drawing set also includes the treatment of the abandoned gallery at station
2+037 in the adit A2.

4.5.5

Transition from Steel Liner to Concrete

A complete set of drawings showing transition between the headrace concrete and steel liner is
being developed. The set includes concrete outline, cross sections and the reinforcement
drawings.

Moreover, a 3D model for this transition is also being developed for the analysis of transition
concrete for the applied and considered loads.

4.5.6

Shop Drawing Review

The Contractor submitted 1 shop drawing under the letter R-18059. The drawing was carefully
reviewed and was stamped as approved except as noted.

4.5.7

Monitoring Data

Monitoring data from various locations of the project was received and reviewed.

4.6

STRUCTURAL ENGINEERING

4 Original and 16 revised construction drawings were issued to the Contractor for construction.
These are summarized in Table 4-2 below.

Page 33

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Table 4-2: Construction Drawings Issued to the Contractor


Original Construction
Drawings

Revised
Construction
Drawings

Headrace Twin Tunnel/Bifurcation

13

Mosque

16

Structure

TOTAL

Listed in Table 4-3 are 82 shop drawings. These drawings have been reviewed and commented
upon based on NJC Construction Drawings.

Table 4-3: Shop Drawings Reviewed and Commented


Structure
Administration Building Beam and Floor Portion Drawings

Shop Drawings
Reviewed
44

Power Station Unit Bay-3, Column C-62 from EL.585.00 to 600.500


m Reinforcement Drawings

Power Station Erection Bay-2 Block Masonry EL.585.00 to 589.50


rd

Reinforcement (3 Area) Drawings

Power Station Unit Bay-3,Block Masonry Wall from


EL.589.5m~594.20m Reinforcement Drawings

Transformer Hall Entrance Fireproofing door wall Reinforcement


Drawings

Tailrace Tunnel Outlet, Wingwall Part1 Concrete Outline Drawing

Power Station Unit Bay-2, Slab at EL.589.50m Reinforcement


Drawings

Tailrace Tunnel Outlet, Sluice Structure Reinforcement Drawings

10

TOTAL

82

Progress for this period is summarized below:

Preparation of revised construction drawings of Power Station is continued based on


contractors information.

Preparation of design report of Dam/Diversion structures, Outlet Structure and Debris


Channel are in progress.

4.7

Review of Structural Calculations of covers of cable trench

Helped site staff in various technical issues.

HYDRAULICS

The Consultants continued with the following tasks during the month.

Page 34

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

The intake arrangement is revised per access road conditions. Alternate options of the
access road to the powerhouse has been made and are under review Drawings are being
updated. The turbine calculations with TurbnPro software have been revised. Memo
about Nauseri Small Hydel Power Station (NSHPS) is also being updated. The power
house has been moved towards the riverside due to road alignment and drawings of
powerhouse section have been revised.

The hydraulic analysis and design of protection works along Tarbela Fish Point, at Jhelum
River have been completed.

The queries regarding headloss in tunnel system has been duly responded.

4.8

ELECTRICAL WORKS

4.8.1

Powerhouse and Transformer Cavern

The following Submittals received from the Contractor were reviewed and returned to the
Contractor with our comments on the same. The status of these submittals is also given below:

Isolated Phase Bus Duct (IPBD) Support Calculation Report stamped AEN

Grounding Grid Layout Drawing at Outdoor Area of C3 Main Workshop and Store
stamped RFC

Technical Documents for DC Power Supply System, reviewed and commented

Administration Building Electrification Shop Drawings (d2) stamped AEN

Excitation Units Design Change Justification reply sent to the Client

Materials Approval Procedures - Control and Communication Cable stamped RFC

Manufacturer Technical Information - Communication System, information sent to


WAPDA

Manufacturer Technical Information - Communication System-DC Battery stamped AEN

Cost Proposal for Plant Security System (CCTV System), reviewed and commented

The following Submittals were received from the Contractor and are presently under review:

4.8.2

Submission of O & M Manual for Lot E1 Main Transformer

Communication Plan between RTU, Energy Metering System and NTDC

Manufacturer Technical Information - Relay Protection and Fault Information System

NJ Hydropower Large Screen Display System and Control Console Proposal

Manufacturer Technical Information - LV Switchgear

Progress on Minutes of Control Systems Design Liaison Meeting - 1-8 June 2015

525kV Switchyard, Control Building, 11kV Substation, C3 Colony

The following Submittals received from the Contractor were reviewed and returned to the
Contractor with our comments on the same. The status of these submittals is also given below:

Page 35

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Laying of the 525kV XLPE Cables stamped RFC

CATV Subscribers Distribution Diagram at C3 Permanent Colony stamped AEN

Outdoor Electrical Layout Drawings of Chattar Kalas Colony, reviewed and commented

Method Statement on Installing Grounding Mesh in the Switchyard (rev. 1) stamped RFC

The following Submittals were received from the Contractor and are presently under review:

525kV Transmission Line from NJHPC 525kv Substation - Ghakkar Substation

Outdoor Electrical Layout Drawings of Chattar Kalas Colony

Installation of Fitting in 525kv Switchyard

Issues about Telecommunication Cable Trench Embedded Conduit Arrangement in C3


Chatter Kalas Colony

4.8.3

Telecommunication Pipe Layout Plan at C3 Chatter Kalas Colony

Telephone Subscribers Distribution Diagram at C3 Permanent Colony

Intake / DAM / Headwork

The following submittals received from the Contractor were reviewed and returned to the
Contractor along with our comments on the same. The status of the submittals is also given
below:

Layout of Buried Conduit for Trashrack Cleaner stamped RFC

Electrical Drawings of Hydraulic Hoist of Gates stamped AEN

Embedded Parts for Camera on Collecting Canal stamped RFC

Lighting Layout and Illumination Calculation for Dam Surface stamped RFC

Telephone Subscribers Distribution Diagram at Dam-intake stamped AEN

The following submittal was received from the Contractor and is presently under review:

4.8.4

Cable Trench and Cable Tray Arrangement in Intake Operator Building

Various Electrical Issues

NJ Project Transmission Line Scheme

The construction of the original 500kV Double Circuit Transmission Line from NJHPP to the
Ghakkar Grid Station could not start in time and it was decided by the WAPDA/ NTDC that for
the time being the two transmission lines from NJHPP will be connected at Domeli to an existing
525kV transmission line going from Ghakkar towards Rewat and construction work is in
progress for these. However, subsequently the above said two (2) transmission lines will be
installed upto 500kV Ghakkar grid station as per the original scheme. Regarding
Communication between NJHPP Control Room and NPCC at Islamabad through OPGW Cable
as well as PLC equipment over 525kV Transmission line, it was decided by WAPDA/NTDC that
OPGW and PLC equipment supply, testing and commissioning would be in the scope of 500kV

Page 36

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Transmission Line Project and NESPAK was assigned to prepare the complete Scope of Work
and BOQ. We have been informed that NESPAK has done the needful and now NTDC has
floated a tender in connection with supply and erection of Power Line Carrier System on above
mentioned two (2) Transmission Lines.

Regarding Fibre Optic Cable to be installed between C3 Control Building and C1- DAM
/Intake Operator Building, some information has been requested by the Contractor for
preparing their Technical and Commercial proposal and the same was provided to him.
The Contractor has been asked to submit the Technical and Commercial proposal at the
earliest. The Contractor has now submitted revised Technical and Commercial proposals
and the same are under review.

4.8.5

Factory Acceptance Tests

In the Factory Acceptance Tests (FATs) Witness Report regarding Generator Circuit
Breaker M/s.ABB indicated that they will not provide 3 Sets of Spare Contacts due to their
Warranty and Proprietary policy and they would themselves exclusively replace the
Contacts after 10 years. However, the Engineer and the Client has not agreed to their
point of view due to some Contract clauses and asked the Contractor to provide these
Contacts from ABB as per Contract requirement. Engineer also sent some more
comments to the Contractor. Contractors reply is still awaited.

During FAT of 525kV Outdoor Type Circuit Breaker minor deviation were noted by the
Engineer. The Contractors revised reply in this regard is being reviewed by the Engineer.

Factory Acceptance Tests (FATs) of LV Switchgear were performed in China and


witnessed by NJC and Clients representatives.

4.9

MECHANICAL WORKS

The following drawings/documents were reviewed, marked and returned to the Contractor:

M1 Calculations for the Turbine Guide Bearings

C3 Submit Control Building of HVAC System Layout Plan (D2), Calculation (D1) and
Catalogue

EMH FAT Reports of EMH Equipment

H1 Water Level Measuring Equipment Layout on Intake Block

Electrical & Mechanical Standards to be Supplied by the Contractor

M1 Drawings and Components Lists for Turbine and Generator

C3: Notes & Legend for Water and Supply and Sewerage System in Adit A5 (D2)

H1: The Drainage Pipe and Valve of Adit Bulkhead Plug A4 and A5

C3 H1 AP-057 Permanent Tailrace Dewatering System - 4 Pumps

C3: Area Chatter Kalas Water Treatment Plant Pump Manufacturer\'s Information and
Pump

Page 37

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

C3: Report for Power House Bridge Cranes Load Test

H1 Mobile Tunnel Dewatering System - Scope of Supply and Commercial Issues

The following documents/drawings remained under review:

H1: General Drawing of Flap Gate Ladders (For Lock Device)

M1: Manual Water Strainer

M1: Layout of Pressure Relief Pipe and Exhausting Pipe of CO2 Fire

C3/H1: Installation Statement of 2x250KN Electric Hoist of Bonneted Gate (R0)

EMH: Drawings and Components Lists for Inlet Valve

H1: The Drainage Pipe and Valve of Adit Bulkhead Plug A4 and A5

C1: Submission of Method Statement of Watertight Door for Diversion Dam Gallery to the
Flap Gate

C1/H1: Steel Corbel and Embedded Parts for Gantry Crane

M1: FAT Testing Procedure for Automatic Water Filter and Vaccum Oil Purifier

C3: Control Building Water Supply and Drainage Plan (D4)

C1/H1: Dam gantry crane and trashrack Cleaner rail assembly

Correspondence were made to Contractor/Client on C3/M1 regarding , Turbine Governor Unit


No 3 and 4 FAT, Needle Valve, oil purifier and water strainer FAT are planned in the month of
January 2016.

4.10

REPORTING

Reports/drawings issued include:

Monthly Progress Report December 2015.

Structure Section has issued 04 original , 16 Revised Construction Drawings and 82 Shop
Drawings. Other drawing details are given in Annex-B.

4.11

PROGRAMME AND SCHEDULE


The Contractors last Clause 14.2 Schedule was submitted in April 2012 vide letter GZBZJ-NJC2947 dated 23 April 2012, which was conditionally consented to by the Engineer and was used
to monitor progress.

After the visit of Honourable Prime Minister of Pakistan, Mr Nawaz Sharif to Neelum Jhelum
Hydroelectric Project in June 2013, the Contractor agreed to make efforts to have the First Unit
ready for Wet Testing by 31 December 2015.

Page 38

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

The document for Best Effort Plan was agreed to and signed on 18 July 2013 by the Employer,
Contractor and the Engineer; where in the first Unit was ready for wet testing by 31 December
2015. The Contractor submitted a construction schedule based on his interpretation of the Best
Effort Plan vide letter GZBZJ-NJC-5367 dated 22 November 2013 for Engineers review and
approval.

The submitted schedule had a data of 26 October 2013 and showed 30 June 2016 as the date
for start of wet testing of 1st Unit. Contractors 22 November 2013 Best Efforts Plan shows a
delay of 04-months with respect to VO-022 schedule completion milestones and 06-months
delay with respect to the Best Efforts Plan that the Contractor endorsed on 18 July 2013. This
creates the impression that the Contractor accumulated a 06-month delay during a 04-month
period (18 July to 22 November 2013) which is not acceptable.
Engineer vide letter PO-12927 dated 18 December 2013 forwarded his review of Contractors
submitted schedule and requested the Contractor to submit a schedule that is consistent with
the logical sequencing and the production rates that were considered when Engineer and
Contractor co-developed the Best Effort Plan which the Contractor endorsed on 18 July 2013.
Engineer also requested the Contractor to include appropriate resources allocated to each
working front and histograms of work quantities planned for each month.

A meeting was held at the WAPDA Administrative Staff College, Islamabad on 23 January 2014
to deliberate on the concerns pertaining to the implementation of the Best Effort Plan (BEP).
The Engineer was requested to deliberate on the subject with inputs from the Contractor and
prepare / suggest alternate means to implement the Best Effort Plan. The Engineer was advised
to work out the economic viability of spending the extra money for the acceleration vis--vis
implementing the Project as planned in the PC-1 (Revised) by Mid-2016. All critical activities
issues discussed in the meeting were to be incorporated in the schedule.
Contractor vide letter GZBZJ-NJC-5819 dated 08 February 2014 submitted his Accelerated
Overall Schedule of the Project along with equipment resources, material resources, cost of
accelerated overall schedule and the EMH acceleration cost for Engineers review and
approval. His proposal costs were poorly substantiated and apparently grossly overestimated.

A meeting was held on 12 February 2014 at the WAPDA Administrative Staff College,
Islamabad to deliberate on "Best Efforts Plan prepared by the Consultants in the light of the
decision taken by the Chairman WAPDA in meeting held on 23 January 2014. Engineer
informed that the Contractor was requested to submit a logical schedule that honoured the
agreement made for the "Best Effort Plan" on 18 July 2013.The Contractor submitted a detailed
schedule on 08 February 2014, revised again on 09 February and re-revised again on 11
February 2014. This schedule shows first Generating Unit to be ready for wet testing on June
30, 2016 i.e. a delay of 06-months to the Best Effort Plan. The Contractor commented that they

Page 39

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

had missed the best time for its implementation and they cannot do it on the agreed date.
MD/CEO, NJHPC criticized CCGGC-CMEC that despite signing the agreement on Best Effort
Plan, they are now withdrawing from their commitment.

The Engineer was asked to prepare another presentation based on the outcome of this meeting
to be presented on 17 February 2014 in the office of MD/CEO, NJHPC. During this meeting a
presentation for the meeting with Chairman WAPDA on best Effort Plan was finalized. The main
conclusions were that (1) the Best Effort Plan appears to be no longer viable, (2) the TBM is
likely to push out the completion milestones well beyond the Best Effort Plan dates and (3)
consequently, there is no point in making large acceleration outlays at the dam and
powerhouse.

Engineer vide letter No. PO-16426 dated 23 December, 2014 expresses his considerations that
Contractors intransigence is causing funding difficulties for himself, the Employer and the
Project. In continuation of above referred letter Engineer vide letter No. PO-16649 dated 19
January, 2015, believed that the Contractor has an opportunity to improve his construction
management performance by some simple, scientific improvements to his planning techniques
and technology. For the sake of this Engineer also suggested that Contractors Planning Expert
may meet with our Eng. Kalim Ahmad to discuss these opportunities to improve performance.
Engineer vide letter No. PO-16682 appreciated the Contractors compliance with the Employers
request for an updated Performance Guarantee which helps towards obtaining funding.
Construction schedule as per sub clause 4.2 for the project is given as per Annex A.

Planned versus Actual Progress of the Project Civil works is given in Figure 4-1 below:

Figure 4-1: Planned versus Actual Progress of the Project Civil Works

Page 40

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

A marked up schedule of the works along with financial targets and achievements (Table) is
included as per Annexure A.

4.12

DRAFT AMENDMENT NO. 2

The draft Amendment No.2 was submitted to the Client on 17 December 2013 (PO-13029) with
a ceiling amount of Equivalent Pak Rs. 14,763,785,119/-. The comments of Chief Engineer
Contracts, NJHPC dated 31 December 2013 (R-11574) were replied on 16 January 2014
(PO-13291). Subsequently, these documents were reviewed by the officials of the GM/PD,
NJHPC in February 2014 and forwarded to GM (CCC) in 2

nd

week of March 2014. CCC

Comments dated 08 April 2014 (R-12356) were replied on 30 May 2014 (PO-14530) in which
Ceiling Amount of the Draft Amendment No. 2 was increased to Equivalent Pak Rs.
16,008,132,677.

CCC officials, after site visits/meetings in June/July 2014 signed their interim recommendation
on 28 July 2014 (R-13763) Equivalent Pak Rs. 13,894/- million excluding the amounts for the
input of BOM Members and extra hours working compensation for the NJC local technical staff
posted at site. After a meeting with NJHPC Officials, NJC submitted their replies on 10 October
2014 (PO-15708 & PO-15709). Subsequently, a meeting with NJHPC officials was conducted
on 22 October 2014 (R-14070) and NJC submitted the requested documents on 27 October
2014. BOM NJC also discussed the issue during their meeting with Member (W) and NJHPC
Officials on 27 October 2014 (PO-15841) and requested for an early resolution and signing of
the Amendment No. 2. The issue of compensation for extra hours being worked by NJC local
technical staff was discussed in a number of meetings, lastly in May 2015, but yet not resolved.
NJC has submitted a notice to NJHPC (PO-18215) on 26 June 2015 informing that the
expenditures for local currency and Norwegian Krone (NOK) has exceeded the 80% of the
Ceilings agreed in the signed Amendment No. 2a with a request to early sign the Amendment
No. 2. A meeting with CEO NJHPC was scheduled for 03 August 2015 that was subsequently
postponed. The final version of Amendment No. 2 needs to be discussed and signed at the
earliest whereas client is awaiting approval of ongoing PC-1 revision as Amendment No. 2a has
exceeded the already approved provisions.

Amendment No. 2a; In view of the time required for the detailed evaluation and review of the
WAPDA Officials to recommend the Amendment No. 2, an Amendment No. 2a was signed on
19 June 2014 (PO-14783) with Ceiling Amount of Equivalent Pak Rs. 11,462,522,003/- by
adding the provisions approved subsequent to the signing of the Amendment No. 1 to make an
interim arrangement to help repatriation of funds by expatriate JV partners.

Page 41

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

CONSTRUCTION: PROGRAMME & PROGRESS

5.1

PROGRESS OVERVIEW

MONTHLY PROGRESS REPORT


JANUARY 2016

The Contractor submits monthly progress reports to the Client through the Engineer. Necessary
corrective actions are required on some aspects as suggested from time to time by the
Consultant to the Contractor for further follow up actions.

All Adits are measuring a total excavation of 13,785 meters in length. All these Adits have been
completed 100%.These includes Adit A1, A2, A2a, A3, A4, A4a (Heading/benching), A5
(Access Tunnel) Access to Headrace Tunnel, A6 (Cable Tunnel), Probing Tunnel, Access to
Downstream Surge Tunnel, A7 and A8. The status of progress in Adits and various sections of
the Tunnel and other major works is given as per Table 5-1 to 5-3.

Table 5-1: Progress Summary of Adits


NEELUM JHELUM HYDROELECTRIC PROJECT
PROGRESS SUMMARY FOR ADITS
No.

Description

Total
(m3)

Start Date

Completion
Date

Percentage
Completion
(%)

Remarks

Adit A1

385

22-Feb-09

25-Aug-09

100%

Completed

Adit A2

2,136

27-Mar-09

25-Jul-11

100%

Completed

Adit A2a

336

24-Feb-13

07-Sep-13

100%

Completed

Adit A3

1891

14-Mar-09

25-Apr-11

100%

Completed

Adit A4

2,082

1-Jul-09

25-Apr-11

100%

Completed

2,171

30-Jul-12

25-Jan-14

100%

Completed

2,171

5-Jul-13

25-May-14

100%

Completed

765

25-Apr-09

25-Aug-10

100%

Completed

284

13-Dec-10

25-May-11

100%

Completed

687

19-Feb-09

25-Jun-10

100%

Completed

5
6
7
8
9
10

Adit A4a
Heading
Adit A4a
Benching
Adit A5 (Access
Tunnel)
Access to
Headrace
Tunnel
Adit A6 (Cable
Tunnel)

11

Probing Tunnel

154

24-May-10

25-July-10

100%

Completed

12

Access to
Downstream
Surge Tunnel

298

13-Dec-09

25-Jun-10

100%

Completed

13

Adit A7

370

10-Jun-10

25-Jul-11

100%

Completed

14

Adit A8

56

30-Jun-10

25-Oct-10

100%

Completed

Page 42

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Table 5-2: Excavation Progress Summary for Tunnels


NEELUM JHELUM HYDROELECTRIC PROJECT
EXCAVATION PROGRESS SUMMARY FOR TUNNELS

No

Site

Description

Total
Length
(m)

C1

HRT (T0A
T1A)

874.1

C1

HRT (LHTT)

4,638

C1

HRT (RHTT)

4,515

Right TBM
Disassembly
Chamber (#16
M1R)
HRT (04 - M1L)
TBM
HRT (01 - M1R)
TBM

C1

C2

C2

C2

HRT (T3'L - 04)

678

C2

HRT (T3'R - 01)

758

C2

10

C2

11

C2

12

C2

13

C2

14

C2

15

C2

16

C2

17

C3

18

C3

19
20
21

C3

22

C3

HRT (T3'L T3aL)


HRT (T3'R T3aR)
HRT (T3c T3aL)
HRT (T3c T3aR)
HRT (T4 - T3c)
Heading
HRT (T4 - T3c)
Benching
HRT (T4 - M4)
Heading
HRT (T4 - M4)
Benching
HRT (22A - M4)
Heading
HRT (22A - M4)
Benching
TRT A6
Benching
TRT A7
Benching
TRT (T9 T10A)

96.2

11,098
11,072

3,097
3,164
1,062
1,063
1,664
1,664
2,988
2,988
3,403
3,403
1000
2489
411

TRT (T9 - T7A)


3,140

22
23
24

C3

TRT (T7A - T9)

C3

HST (Upper
Leg) Benching
HST (Lower
Leg) Benching

C3

599
350

Start
Date

15-Aug09
24-Mar11
13-Mar11
17-Nov14
31-Jan13
22-Feb13
01-Apr11
15-Apr11
07-Mar11
11-Mar11
27-Dec12
27-Dec12
24-Jul11
21-Jul14
21-Apr11
10-Oct13
02-Jun10
07-Oct13
1-July2015
30-May2015
19-Sep11
20-Jul11
17-Jul12
25-Nov2014
14-Nov2014

Completion
Date

Progress
till
December
2015 (m)

Progress in
January
2016 (m)

Progress
till January
2016 (m)

Percentage
Completion
(%)

Remarks

18-Feb-14

874.1

874.1

100

Completed

3,795.5

93

3,888.5

83.84

In progress

3,880.4

105.5

3,985.5

88.28

In progress

9.3

9.3

Suspended
for time
being

7436.1

210.0

7646.1

68.9

In Progress

5,806

18.9

5824.9

52.6

In Progress

678.0

678.0

100

Completed

758

758

100

Completed

3097.4

19

3097.4

100

Completed

3,164.3

3,164.3

100

Completed

898.7

119.1

1017.8

95.8

In Progress

1005.2

58.2

1063.4

94.2

In Progress

1664

1664

100

Completed

1664

1664

100

Completed

25-Jun-14

2988

2988

100

Completed

2,988

2,988

100

Completed

25-Oct-13

3,403

3,403

100

Completed

3,301

3,301

97

In Progress

375

182

557

55

In Progress

745

137

882

35

In Progress

393

393

96

In Progress

3,140

3,140

100

Completed

568

31

599

100

Completed

263

87

350

100

Completed

In
progress
In
progress
In
Progress
In
Progress

In
Progress
In
Progress

Page 43

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Table 5-3: Progress Summary for Major Works


NEELUM JHELUM HYDROELECTRIC PROJECT
PROGRESS SUMMARY FOR MAJOR WORKS
No.

3.

4
5

Description

Excavation
Intake Block
& Desander
Excavation
Dam/Spillwa
y/Stilling
Basin
Overall
Concrete
Works (All
Headworks)
Power
House
Transformer
Hall

Start Date

Completion
Date

Progress
till
November
2015 (m)

Progress in
December
2015 (m)

Progress
till
December
2015 (m)

Percentage
Completion
(%)

Remarks

6-Aug-09

In progress

3,851,903

0.0

3,851,903

Almost
complete

Almost
Completed

624,145

16-Oct11

In progress

600,850

9,360

610,210

97.77 %

In progress

1,327,774

26-Nov2011

In progress

824,958

39,257

864,215

65.09 %

In progress

25-Jul-14

148,263

148,463

100%

Completed

51,725

51,725

100%

Completed

Total
(m3)

148,463
51,725

21-Nov10
27-Mar11

The exact quantities of excavation in each segment are finalized after monthly survey. For this
reason, the summing up of this months excavation and last months reported to date excavation
might not be equal to the value of this months to date excavation stated in this report.

5.2

PROGRESS AT C1

5.2.1

Layout and Scope of Works at Lot C1

Shown in Figure 5-1, is the general layout and scope of works at Lot C1. This includes the main
Dam, intake structure, sedimentation basin, the headrace and diversion tunnel.

Figure 5-1: General Layout and Scope of Works at C1

Page 44

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.2.2

MONTHLY PROGRESS REPORT


JANUARY 2016

Mobilization & Site Establishment

Crush Plant # 1: The production was suspended on 29 December, 2015 & 01 January, 2016
(day shift only). Rest of the week, it remained operational.

Crush Plant # 2: The production was suspended on 28 December, 2015, 13 January, 2016
(Day shit). Rest of the week, it remained operational.

PROGRESS

Following activities regarding concrete works were performed in different structures during the
month.
STRUCTURE

Rockfill Dam
Construction

DESCRIPTION

The construction of Rockfill dam was started on January 14,


2016 at the D/S Zone-3.
3

595 m was backfilled with River Bed Material.

Block 6-1
Start Date:26-Dec-2015
Finish Date: 27-Dec-2015
Elevation:984.8~985.50
Qty of Concrete= 689 m

Start Date: 09-Jan-2015


Finish Date: 12-Jan-2015
Elevation:985.5~986.50
Qty of Concrete= 1,031 m

Start Date: 21-Jan-2015


Finish Date: 24-Jan-2015
Elevation:986.5~987.5
Right Bank Structures

Qty of Concrete= 968 m

(Debris Channel, U/S &


D/S Retaining walls of

MBT Concrete Grouting Pad

Rockfill Dam)

Start Date:30-Dec-2015
Finish Date: 31-Dec-2015
Elevation:979.5~981.5

Page 45

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Qty of Concrete= 333 m

MONTHLY PROGRESS REPORT


JANUARY 2016

Start Date: 13-Jan-2015


Finish Date: 14-Jan-2015
Elevation:981.50~983.50
Qty of Concrete= 271 m

Total Concrete During the Month = 3,291 m

nd

Stage Concrete

Bay # 1 Trunnion Block


Start Date: 02-Jan-2015
Finish Date: 02-Jan-2015
Elevation:987.7~991.2
Qty of Concrete= 11 m

Pier (P5-2)(Tendons Dressing / Close Packing)


Start Date: 05-Jan-2015
Finish Date: 05-Jan-2015
Elevation:987.0~984.0
Dam Spillway / Divide Pier

Qty of Concrete= 1.5 m

Concrete
Pier (P5-6)(Tendons Dressing / Close Packing)
Start Date: 05-Jan-2015
Finish Date: 05-Jan-2015
Elevation:990.0~995.076
Qty of Concrete= 1.5 m

Total Concrete During the Month = 14 m

STILLING BASIN SLAB/FLOOR WAS COMPLETED ON


Stilling basin slab concrete

MARCH 21, 2015.

De silting and dewatering is in progress


Block 5-1-5
Start Date:28-Dec-2015

Page 46

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Finish Date: 30-Dec-2015


Elevation:981.156~982.70
Qty of Concrete= 750 m

Start Date: 11-Jan-2015


Finish Date: 12-Jan-2015
Elevation:982.7~984.4
Qty of Concrete= 689 m

Start Date: 17-Jan-2015


Finish Date: 18-Jan-2015
Elevation:984.4~986.167
Stilling basin Left Guide

Qty of Concrete= 736.5 m

Wall
Block 5-1-6
Start Date:30-Dec-2015
Finish Date: 31-Dec-2015
Elevation: 979.3~981.10
Qty of Concrete= 632 m

Start Date: 12-Jan-2015


Finish Date: 13-Jan-2015
Elevation:981.10~982.80
Qty of Concrete= 636.5 m

Start Date: 22-Jan-2015


Finish Date: 23-Jan-2015
Elevation:982.8~984.5
Qty of Concrete= 630 m

Block 5-1-7
Start Date:25-Dec-2015
Finish Date: 26-Dec-2015
Elevation:971.5~973.2
Qty of Concrete= 97 m

( Total Qty =562 m )

Start Date: 02-Jan-2015


Finish Date: 03-Jan-2015
Elevation:973.2~974.9
Qty of Concrete= 615 m

Page 47

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Start Date: 10-Jan-2015


Finish Date: 10-Jan-2015
Elevation:974.9~976.6
Qty of Concrete= 602 m

Start Date: 18-Jan-2015


Finish Date: 19-Jan-2015
Elevation:976.6~978.3
Qty of Concrete= 576 m

Start Date: 23-Jan-2015


Finish Date:24-Jan-2015
Elevation: 978.30~980.0
Qty of Concrete= 582 m

Total Concrete During the Month = 6,546 m

Block 5-1-8
Start Date:27-Dec-2015
Finish Date:28-Dec-2015
Elevation:968.2~969.9
Qty of Concrete=621.7 m

Start Date: 08-Jan-2015


Finish Date: 09-Jan-2015
Elevation:969.9~971.60
Qty of Concrete= 615.9 m

Start Date: 14-Jan-2015


Finish Date: 15-Jan-2015
Stilling basin Left End

Elevation:971.6~973.5

Retaining wall (D/S of

Qty of Concrete= 656.4 m

stilling basin i.e starts from


Block 5-1-8 ~ 5-1-16)

Block 5-1-9
Start Date:26-Dec-2015
Finish Date: 27-Dec-2015
Elevation:969.9~971.8
Qty of Concrete= 415.8 m

Page 48

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Start Date: 05-Jan-2015


Finish Date: 06-Jan-2015
Elevation:971.80~973.50
Qty of Concrete= 384.7 m

Start Date: 13-Jan-2015


Finish Date: 14-Jan-2015
Elevation:973.50~975.0
Qty of Concrete= 366.9m

Start Date: 20-Jan-2015


Finish Date: 21-Jan-2015
Elevation:975.0~976.8
Qty of Concrete= 754.5m

Start Date: 25-Jan-2015


Finish Date: In Progress
Elevation:975.0~976.8
Qty of Concrete= 31.5m

Block 5-1-10
Start Date: 06-Jan-2015
Finish Date: 07-Jan-2015
Elevation:976.9~978.6
Qty of Concrete= 735 m

Start Date: 15-Jan-2015


Finish Date: 16-Jan-2015
Elevation:978.6~980.30
Qty of Concrete= 727.5 m

Block 5-1-11
Start Date: 04-Jan-2015
Finish Date: 05-Jan-2015
Elevation:973.50~975.0
Qty of Concrete= 318 m

Start Date: 19-Jan-2015


Finish Date: 21-Jan-2015
Elevation:975.0~976.8
Qty of Concrete= 705 m

Page 49

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Block 5-1-12
Start Date: 03-Jan-2015
Finish Date: 04-Jan-2015
Elevation:970.0~971.8
Qty of Concrete= 264.7 m

Start Date: 23-Jan-2015


Finish Date: 24-Jan-2015
Elevation: 971.8~973.5
Qty of Concrete= 305.4 m

Block 5-1-13 (Bedding Concrete)


Start Date:01-Jan-2015
Finish Date: 01-Jan-2015
Elevation:961.90~964.0
Qty of Concrete= 18 m

Block 5-1-13
Start Date: 12-Jan-2015
Finish Date: 13-Jan-2015
Elevation:962.054~964.0
Qty of Concrete= 231 m

Start Date: 25-Jan-2015


Finish Date: 25-Jan-2015
Elevation: 964.0~966.0
Qty of Concrete= 608 m

Total Concrete During the Month = 7,759m

Intake Block-1 L/S (Roof Slab)


Start Date:27-Dec-2015
Finish Date: 28-Dec-2015
Elevation:1011.6~1013.30
Qty of Concrete= 228 m

Start Date: 15-Jan-2015


Finish Date: 16-Jan-2015

Page 50

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Elevation:1013.3~1014.30
Qty of Concrete= 162 m

Intake Block-1 R/S (Roof Slab)


Intake Structure concrete

Start Date: 03-Jan-2015


Finish Date: 05-Jan-2015
Elevation:1009.9~1011.60
Qty of Concrete= 277.5 m

Start Date: 18-Jan-2015


Finish Date: 19-Jan-2015
Elevation:1011.60~1013.3
Qty of Concrete= 250 m

Intake Block-3 (L/S)


Start Date:28-Dec-2015
Finish Date: 30-Dec-2015
Elevation:994.3~996.4
Qty of Concrete=421 m

Start Date: 11-Jan-2015


Finish Date: 12-Jan-2015
Elevation:996.4~998.5
Qty of Concrete= 166 m

Intake Block-3 (R/S)


Start Date: 05-Jan-2015
Finish Date: 05-Jan-2015
Elevation:997.6~998.5
Qty of Concrete= 204 m

Intake Block-3 (2

nd

Stage Concrete)

Start Date: 20-Jan-2015


Finish Date: 20-Jan-2015
Elevation:991.0~991.5
Qty of Concrete= 2 m

Total Concrete During the Month = 1,710 m

Page 51

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

D-Block 1
D-Block 1 (P1-4)
Start Date: 19-Jan-2015
Finish Date: 20-Jan-2015
Elevation: 991.0~992.85
Qty of concrete= 291 m

D-Block 1 (S1-5)
Start Date: 21-Jan-2015
Finish Date: 21-Jan-2015
Elevation: 985.63~985.73
Qty of concrete= 45 m

D-Block 2
D-Block 2 (S2-3)
Start Date: 07-Jan-2015
Finish Date: 07-Jan-2015
Elevation:1000.527~1002.227
Qty of concrete= 99 m

Sedimentation Basin

D-Block 2 (P2-3)

foundation slab & dividing

Start Date: 21-Jan-2015

walls

Finish Date: 22-Jan-2015


Elevation: 1002.55~1004.25
Qty of concrete= 79 m

D-Block 3
D-Block 3 (P3-3)
Start Date: 16-Jan-2015
Finish Date: 17-Jan-2015
Elevation: 999.90~1002.07
Qty of concrete= 89 m

D-Block 4
D-Block 4 (P4-3)
Start Date: 17-Jan-2015
Finish Date: 18-Jan-2015
Elevation: 998.35~1000.05
Qty of concrete= 112.5 m

Page 52

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

D-Block 5
D-Block 5 (S5-3)
Start Date:25-Dec-2015
Finish Date:26-Dec-2015
Elevation: 996.16~997.857
Qty of concrete= 45 m

(Total QTY= 108 m )

Start Date: 24-Jan-2015


Finish Date: 25-Jan-2015
Elevation: 1000.20~1001.90
Qty of concrete= 98 m

D-Block 5 (P5-3)
Start Date: 05-Jan-2015
Finish Date: 06-Jan-2015
Elevation: 998.02~999.729
Qty of concrete= 90 m

D-Block 5 (P5-4)
Start Date: 23-Jan-2015
Finish Date: 24-Jan-2015
Elevation: 984.19~985.91
Qty of concrete= 109.5 m

D-Block 6
D-Block 6 (P6-3)
Start Date:12-Jan-2015
Finish Date: 13-Jan-2015
Elevation: 999.557~999.406
Qty of concrete= 98 m

D-Block 7
D-Block 7 (P7-1)
Start Date: 13-Jan-2015
Finish Date: 13-Jan-2015
Elevation: 999.73~1002.83
Qty of concrete= 135 m

D-Block 07 (S7-1)
Start Date:01-Jan-2016
Finish Date:02-Jan-2016

Page 53

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Elevation:993.602~996.560
Qty of concrete= 239.5 m

D-Block 7 (S7-3)
Start Date: 16-Jan-2015
Finish Date: 16-Jan-2015
Elevation: 992.28~993.93
Qty of concrete= 129 m

D-Block 8
D-Block 8 (P8-1)
Start Date: 06-Jan-2015
Finish Date: 07-Jan-2015
Elevation: 996.41~999.41
Qty of concrete= 148.5 m

D-Block 8 (S8-3)
Start Date: 06-Jan-2015
Finish Date: 06-Jan-2015
Elevation: 990.087~991.787
Qty of concrete= 134 m

D-Block 8 (S8-1)
Start Date: 15-Jan-2015
Finish Date: 15-Jan-2015
Elevation: 999.24~1002.2
Qty of concrete= 178 m

D-Block 9
D-Block 9 (P9-1)
Start Date: 11-Jan-2015
Finish Date: 11-Jan-2015
Elevation: 1002.09~1005.09
Qty of concrete= 128 m

D-Block 9 (P9-3)
Start Date: 16-Jan-2015
Finish Date: 17-Jan-2015
Elevation: 993.35~996.34
Qty of concrete= 192 m

Page 54

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

D-Block -9 (S9-1)
Start Date: 08-Jan-2015
Finish Date: 09-Jan-2015
Elevation: 995.914~998.914
Qty of concrete= 197.5 m

D-Block 10
D-Block 10 (P10-1)
Start Date: 02-Jan-2015
Finish Date: 03-Jan-2015
Elevation: 998.76~1001.763
Qty of concrete= 140.5 m

Start Date: 22-Jan-2015


Finish Date: 22-Jan-2015
Elevation: 1001.8~1004.75
Qty of concrete= 126 m

D-Block 10 (P10-2)
Start Date: 22-Jan-2015
Finish Date: 23-Jan-2015
Elevation: 988.0~989.61
Qty of concrete= 171.5 m

D-Block 10 (P10-3)
Start Date: 02-Jan-2015
Finish Date: 02-Jan-2015
Elevation: 989.613~991.313
Qty of concrete= 95 m

Start Date: 09-Jan-2015


Finish Date: 10-Jan-2015
Elevation: 993.0~993.16
Qty of concrete= 121.5 m

D-Block 10 (S10-1)
Start Date: 07-Jan-2015
Finish Date: 08-Jan-2015
Elevation: 988.1~989.61
Qty of concrete= 222 m

Page 55

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Bedding Concrete at P4-4/S4-4


Start Date: 10-Jan-2015
Finish Date: 11-Jan-2015
Elevation: 986.0~986.10
Qty of concrete= 217.5 m

Backfill Concrete Under Sedimentation Basin

D-Block -1 (P1-4 & S1-6)


Start Date: 06-Jan-2015
Finish Date: 06-Jan-2015
Elevation: 992.07~994.05
Qty of concrete= 157 m

Total Concrete During the Month = 3,932 m

Block (P-1)
Start Date: 28-Dec-2015
Finish Date:30-Dec-2015
Elevation: 984.005~992.537
Collecting Canal

Qty of concrete= 1070 m

Block B-1
Start Date: 12-Jan-2015
Finish Date: 12-Jan-2015
Elevation: 981.4~982.9
Qty of concrete= 27 m

Total Concrete During the Month = 1,097 m

U/S Protection Slab (S6) Bedding Concrete


Start Date: 22-Jan-2015
Finish Date: 22-Jan-2015
U/S River Training works

Elevation:968.9~969.0

(Ref Dwg: C1-C-

Qty of Concrete= 7.5 m

2004~2008).
U/S Protection Slab (P4)
Start Date: 04-Jan-2015
Finish Date: 05-Jan-2015

Page 56

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Elevation:971.0~972.0
Qty of Concrete= 353 m

U/S Protection Slab (P5)


Start Date: 12-Jan-2015
Finish Date: 12-Jan-2015
Elevation:971.0~972.0
Qty of Concrete= 207.4 m

Intake U/S RCC River Training wall


Start Date:30-Dec-2015
Finish Date: 02-Jan-2016
Elevation:982.3.0~985.0
Qty of concrete= 3,762 m

Intake U/S RCC River Training wall (Behind Intake Block-3)


Start Date:10-Jan-2015
Finish Date: 11-Jan-2016
Elevation:987.5~988.5
Qty of concrete= 603 m

Start Date:15-Jan-2015
Finish Date: 18-Jan-2015
Elevation: 988.50~990.40
Qty of concrete= 2,664.5 m

Start Date:21-Jan-2015
Finish Date: 22-Jan-2015
Elevation: 985.08~987.5
Qty of concrete= 456 m

Total Concrete During the Month = 8,379 m

SUMMARY OF CONCRETE WORKS


Total Estimated Concrete Quantity

1,327,774

Concrete Quantity poured previously

864,215

Concrete Quantity poured during this Month

36,663

900,878

(Aboveground & Underground)

Total Concrete Quantity Poured Up to


Date(Aboveground & Underground)
Percent Completed

Page 57

67.78

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-2: Progress at Debris Channel (looking at Left Dam abutment)

Page 58

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-3: Progress at Debris Channel (D/S Retaining wall for Rockfill Dam)

Page 59

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-4: Progress at Debris Channel (Right End Retaining wall for Rockfill dam)

Page 60

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-5: Progress at Spillway Bays (Floor) for 2

Page 61

nd

stage Concrete (Plan View)

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Page 62

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-6: Progress of Concrete Works in Spillway Block 5-3

Figure 5-7: Progress of Concrete Works in Spillway Block 5-4

Page 63

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-8: Progress of Concrete at Spillway Roof Slabs (section looking U/S)

Page 64

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-9: Progress of Concrete works at Divide Pier (Block-4)


(Section looking towards left abutment)

Page 65

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-10: Progress of Concrete at Stilling Basin Floor (Plan View)

Page 66

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-11: Progress of Concrete at Stilling Basin Left Guide Wall (looking towards Dam left abutment)

Page 67

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-12: Progress of Concrete at Stilling Basin Left Retaining Wall (looking towards Dam left abutment)

Page 68

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-13: Progress of Concrete works at Intake Blocks (Section looking D/S)

Page 69

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-14: Progress of Concrete at Sedimentation Basin Base Slab (Plan View)

Page 70

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-15: Progress of Concrete at Sedimentation Basin Left End Wall and Divide Wall

Page 71

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-16: Progress of Concrete at U/S Spillway Protection Slab (Plan View)

Page 72

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

ELECTROMECHANICAL WORKS (EMH)


2

Installation of Earthing Copper Standard wire 150 mm at


following locations were installed during the month.

Electrical Works

Pier P5-6, EL: 995.5~996.0

Intake Block-1 (R/S) , El: 1009.9~1013.3

Intake Block-1 (L/S) , El: 1013.3~1016.0

Intake Block-3 (R/S) , El: 997.5~998.5

Intake Block-3 (L/S) , El: 996.0~998.5

Sedimentation Basin (S2-3), EL: 1000.7~1002.4

Sedimentation Basin (P6-3), EL: 997.9~999.5

Sedimentation Basin (P8-1), EL: 996.7~999.7

Sedimentation Basin (S10-1), EL: 988.2`989.6

Sedimentation Basin (P10-1), EL: 998.9~1004.8

Sedimentation Basin (P10-2), EL: 988.0~989.6

Sedimentation Basin (P10-3), EL: 998.76~993.3

Debris Channel Block 6-1, EL:985.8~987.5

Intake U/S RCC of Block 3, EL:985.5~990.4

Calibration of HFO energy meter was done by NTDC team


and found ok.

Installation of Trash rack cleaner conduits at Intake Block-0,


El: 1019.0

Mechanical/Hydraulics Works at the following locations were


carried out during the month.

Installation of Radial Gate # 1 at Spillway remained in


progress.

Installation of Trunnion of Radial Gate (L/S & R/S) at Bay


# 1, El: 988.05~991.03

Radial gate hydraulic hoist cylinder connected with


cylinder hinge (L/S & R/S) at Bay # 1 EL: 996

Installation of spillway stoplog lintel beam at Bay # 2 EL:


996~997.459

Installation of spillway radial gate stoplog side guides at


Bay # 3 EL: 999.66~1019

Installation of 1st stage embedded plates for Gate ladder


at Intake Block-1 (R/S), El: 1009.9~1013.3

Installation of 1st stage embedded plates for Gate ladder

Page 73

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

at Intake Block-1 (L/S), El: 1013.3~1016.0

Installation of 1st stage embedded plates for Intake


Stoplog at Intake Block-1 (L/S), El: 1013.3~1014.4

Mechanical/Hydraulic

Works

Installation of 1st stage embedded plates for Stoplog at


Intake Block-1 (R/S), El: 1009.9~1016.0

Installation of 1st stage embedded parts for Stoplog


Storage Guides at Intake Block-1 (R/S), El: 1012.0~1018.8

Installation of 1st stage embedded plates for Trash rack at


Intake Block-3 (L/S), El: 997.5~998.5

Installation of 1st stage embedded plates for Intake Trash


rack at Intake Block-3 (R/S), El: 998.5~999.5

Installation of 1st stage embedded plates for Stoplog at


Intake Block-3 (L/S), El: 996.0~998.5

Installation of 1st stage embedded plates for stoplog side


guides at Intake Block-3 (R/S), El: 998.5~999.5

Installation of 2ndstage embedded plates for undersluice


gate Sill beam at Intake Block-3, El: 991.0~991.5

Installation of 1st stage embedded pipe for sediments


measuring equipment at Intake Block 3 (L/S) EL:
996.5~998.8

Installation of 1st stage embedded pipe for water level


measuring

equipment

at

Intake

Block-1

(L/S),

El: 1013.64~1016.7

Installation of 1st stage embedded pipe for water level


measuring at Intake Block 3 (L/S) EL: 997.88~1003.88

Installation of 1st stage embedded pipe for Sedimentation


Basin

jetting

system

El: 1013.64~1016.7

Page 74

at

Intake

Block-1

(L/S),

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

STATUS OF EMH PARTS AVAILABLE AT SITE

Figure 5-17: Material status and progress for Debris Channel & Gantry Cranes

Figure 5-18: Material status and progress for Intake Gates

Page 75

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-19: Material status for Stoplog of spillway

Figure 5-20: Material status and progress for Radial Gates of Spillway

Page 76

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-21: Material status and progress for Collecting Canal Gates

Figure 5-22: Jetting system for sedimentation basin

Page 77

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

INSTRUMENTATIONS

Presently, 22 temperature gauges are being installed and monitored according to the design
drawings. 03 Pendulum pipes embedment and measurement of effective aperture is continued
systematically.
SPILLWAY STRUCTURE
Designatio

Location

Elevation

Pier P5-3

El: 975.5

Pier P5-5

El: 975.5

TG-01

Block 5-1 (Roof/Deck Slab)

El: 1008

TG-04

Block 5-2 (Roof/Deck Slab)

El: 1008

TG-07

Block 5-3 (Roof/Deck Slab)

El: 1008

Permanent Temperature

TG-10

Block 5-4 (Roof/Deck Slab)

El: 1008

Gauges in Concrete

TG-02

Block 5-1 & 5-2 (Roof/Deck

TG-05

Slab)

TG-08

Block 5-3 & 5-4 (Roof/Deck

TG-11

Slab)

n
TG-03
TG-06
TG-09
TG-12

El: 999.0

El: 999.0

INTAKE STRUCTURE
Designation
TG-17

Location

Elevation

Intake Block-1 (R/S)

El. 985.00

TG-18
TG-21

TG-22
TG-23

Intake Block-2 (R/S & U/S of


Flushing Duct)
Intake Block-2 (R/S & D/S of
Flushing Duct)

El. 995.5

El. 995.5

Intake Block-2 (R/S)

El. 985.00

Intake Block-1 (L/S)

El. 1006.0

TG-16

Intake Block-1 (L/S)

El. 996.0

TG-17

Intake Block-1 (L/S)

El. 985.0

TG-24
TG-13
TG-14

Page 78

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.2.3

MONTHLY PROGRESS REPORT


JANUARY 2016

Dam Excavation

785 m

excavation was carried out during the month. Therefore, cumulative quantity of
3

excavation is 610,995 m .

Figure 5-23 shows daily and cumulative progress of the Dam excavation against the machinery
during the month of January 2015.

Figure 5-23: Daily and Cumulative Dam Excavation

5.2.4

Intake Block and Desander

No excavation was carried out during the month. Therefore, cumulative quantity of excavation is
3

3,851,903 m .

Figure 5-24 shows daily and cumulative progress of the Desander excavation against
machinery during the month of January 2016.

Page 79

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-24: Daily and Cumulative Desander Excavation

SS1 SUPPLY FOR AGGREGATE PRODUCTION


Collection of SS1 rock & boulders by local suppliers

Supply of SS1 Stone/boulders of size less than 50 cm by 7


suppliers nominated by CGGC continued at crushing plants 1
SS1 supply for aggregate

& 2. The material is supplied from the Panjkot Nullah,

production

Nausadda Nullah and some other areas in the vicinity of the


project. This activity started from 27 November 2013. This
action is taken to mitigate the shortage of aggregate.
3

Total Volume of SS1 supplied this month

38,034 m

Total Weight of SS1 supplied this month

76,069 Tons

Cumulative Volume to date

400,967 m

Cumulative Weight to date

801,934 Tons

SACHAL Engineering works (subcontractor) started


exploitation of Greenstone Quarry on June 22, 2015.
3

Aggregate supplied during this month:

5,216 m

Total aggregate supplied Todate :

27,752 m

Page 80

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Tunneling

Headrace Tunnel section C1 to M1 has been split into two tunnels at point T1A.

Downstream Headrace Tunnel, (ST 0 + 825.00 to 5+463.0)


Excavation resumed on October 23, 2015 and progress achieved was from

Ch:

4+620.5~4+713.5 (93 m) (Geological mapping was carried out).

Total Length (ST 0 + 825.00 to Ch: 5+463.0)

4,638 m

Progress during month of January 2016

93 m

Per day progress

3.1 m/day

Total Excavated length

3,888.5 m

Work Done

83.84 %

HEADRACE TUNNEL
PROGRESS (T1A~M1L)

DAILY PROGRESS (m)

14

ROCK CLASS (Q)

DATE
Rock Class

Daily Progress

7 day avg

Figure 5-25: Tunneling in the Downstream Headrace Tunnel (T1A M1L)

Page 81

25-Jan-16

24-Jan-16

23-Jan-16

22-Jan-16

21-Jan-16

20-Jan-16

19-Jan-16

18-Jan-16

17-Jan-16

16-Jan-16

15-Jan-16

14-Jan-16

13-Jan-16

12-Jan-16

11-Jan-16

10-Jan-16

09-Jan-16

08-Jan-16

07-Jan-16

06-Jan-16

05-Jan-16

04-Jan-16

03-Jan-16

02-Jan-16

01-Jan-16

31-Dec-15

30-Dec-15

29-Dec-15

28-Dec-15

27-Dec-15

26-Dec-15

5.2.5

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

PERCENTAGES OF Q-VALUES ENCOUNTERED IN


LEFT HEADRACE TWIN TUNNEL DURING MONTH
OF JANUARY 2016

PERCENTAGES OF ROCK UNITS ENCOUNTERED


IN LEFT HEADRACE TWIN TUNNEL DURING
MONTH OF JANUARY 2016
100%
90%

80%
70%

SS1
38%

60%
50%

Silt st.
62%

40%
30%
20%

Q2
19%

Q3
74%

10%

Q4
7%

Q5
0%

0%

SS1

Silt st.

SS2

Mud st.

Q2

Q3

Q4

Q5

Figure 5-26: Percentage of Q-Values encountered in left head race twin tunnel

Downstream Headrace Tunnel, (ST 0 + 833.0 to 5+348.0):

Excavation progress achieved was from Ch: 4+713.4~4+818.9 (105.5 m) (Geological mapping
was carried out)

Total Length (ST 0 + 833.00 to Ch: 5+348.0)

4,515 m

Progress during month of November 2015

105.5 m

Per day progress

3.52 m/day

Total Excavated length (completed)

3,985.9 m

Work Done

88.28 %

Page 82

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

HEADRACE TUNNEL
PROGRESS (T1A~M1R)

DAILY PROGRESS (m)

12

ROCK CLASS (Q)

25-Jan-16

24-Jan-16

23-Jan-16

22-Jan-16

21-Jan-16

20-Jan-16

19-Jan-16

18-Jan-16

17-Jan-16

16-Jan-16

15-Jan-16

14-Jan-16

13-Jan-16

12-Jan-16

11-Jan-16

10-Jan-16

09-Jan-16

08-Jan-16

07-Jan-16

06-Jan-16

05-Jan-16

04-Jan-16

03-Jan-16

02-Jan-16

01-Jan-16

31-Dec-15

30-Dec-15

29-Dec-15

28-Dec-15

27-Dec-15

26-Dec-15

DATE
Rock Class

Daily Progress

7 day avg

Figure 5-27: Tunneling in the Downstream Headrace Tunnel (T1A-M1R)

PERCENTAGES OF Q-VALUES ENCOUNTERED IN


RIGHT HEADRACE TWIN DURING MONTH OF
JANUARY 2016

PERCENTAGES OF ROCK UNITS ENCOUNTERED


IN RIGHT HEADRACE TWIN TUNNEL DURING
MONTH OFJANUARY 2016
100%
90%
80%
70%
60%

SS1
51%

50%

Silt st.
49%

Q3
74.0%

40%
30%
20%
10%

Q4
11%

Q2
15.0%

Q5
0%

0%

SS1

Silt st.

Q2

SS2

Figure 5-28: Rock quality at (T1A-M1R)

Page 83

Q3

Q4

Q5

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-29: Monthly progress of Headrace tunnel (October 2015)

UNDERGROUND CONCRETE WORKS


Cushion Concrete:
Nil
Amount of cushion concrete poured during the

month
Total Length of LHTT

4,638 m

Length completed during the month

0m

Total Length of LHTT completed to date

3,580 m

Percent Completed

77.18 %

Concrete lining
th

The concrete lining has been completed Up to 6 cross cut.


Left Headrace Tunnel
Concrete Lining & Cushion

Now the formworks are shifted to the Right Twin Tunnel for
expediting the concrete lining in RHTT.

Concrete
(Ch: 0+825.00 ~ 5+463.0)

Amount of concrete for lining poured during the


month
No.s of Pours completed during the month

Page 84

0 m

00 No.s

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Total No.s of Pours completed to date

258 No.s

Total Length of LHTT

4,638 m

Length completed during the month

0 m

Total Length of LHTT lined/completed to date

3,096 m

Percent Completed

66.75 %

Concrete Backfilling of Niche:


Nil
Cushion Concrete:

Ch: 2+804.2~2+830.1
Start Date:30-Dec-2015
Finish Date: 30-Dec-2015
Length: 25.9 m

Ch: 2+780.2~2+804.2
Start Date: 07-Jan-2015
Finish Date: 07-Jan-2015
Length: 24m
Right Headrace Tunnel

Ch: 2+574.1~2+600.1

Concrete Lining & Cushion

Start Date: 11-Jan-2015

Concrete

Finish Date: 11-Jan-2015

(Ch: 0+833.274 ~ 5+348.0)

Length: 26m

Ch: 2+550.1~2+574.1
Start Date: 15-Jan-2015
Finish Date: 15-Jan-2015
Length: 24 m

Ch: 2+522.2~2+550.0
Start Date: 19-Jan-2015
Finish Date: 19-Jan-2015
Length: 27.8m

Ch: 2+511.1~2+522.2
Start Date: 22-Jan-2015
Finish Date: 22-Jan-2015
Length: 11.1m

Page 85

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Ch:2+035.1~2+060.2
Start Date: 14-Jan-2015
Finish Date: 15-Jan-2015
Length: 25.1 m

Ch:1+998.3~2+035.1
Start Date: 21-Jan-2015
Finish Date: 22-Jan-2015
Length: 36.8m

Ch: 1+974.2~1+998.2
Start Date: 24-Jan-2015
Finish Date: 24-Jan-2015
Length: 24 m

Amount of cushion concrete poured during


the month

409 m

Total Length of RHTT

4,515 m

Length completed during the month

225 m

Total Length of RHTT completed to date

1,849 m

Percent Completed

40.95 %

Concrete lining

Formwork # 1 (Full section)


Ch: 1+632.0~1+643.9
Start Date:25-Dec-2015
Finish Date: 26-Dec-2015

Ch: 1+643.9~1+655.8
Start Date:28-Dec-2015
Finish Date: 29-Dec-2015

Ch: 1+655.8~1+667.7
Start Date:31-Dec-2015
Finish Date: 01-01-2016

Ch: 1+667.7~1+679.5
Start Date: 03-Jan-2015
Finish Date: 04-Jan-2015

Page 86

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Ch:1+679.5~1+691.4
Start Date: 06-Jan-2015
Finish Date: 07-Jan-2015

Ch: 1+691.4~1+703.3
Start Date: 10-Jan-2015
Finish Date: 11-Jan-2015

Ch: 1+703.3~1+715.2
Start Date: 13-Jan-2015
Finish Date: 13-Jan-2015

Ch: 1+715.2~1+727.1
Start Date: 16-Jan-2015
Finish Date: 17-Jan-2015

Ch: 1+727.1~1+739.0
Start Date: 20-Jan-2015
Finish Date: 21-Jan-2015

Ch: 1+739.0~1+750.9
Start Date: 24-Jan-2015
Finish Date: 24-Jan-2015

Formwork # 2 (Full section)


Ch: 2+238.2~2+250.1
Start Date:27-Dec-2015
Finish Date: 28-Dec-2015

Ch: 2+250.1~2+262.0
Start Date:31-Dec-2015
Finish Date: 31-Dec-2015

Ch: 2+262.6~2+273.9
Start Date: 03-Jan-2015
Finish Date: 04-Jan-2015

Ch: 2+273.9~2+285.8
Start Date: 05-Jan-2015
Finish Date: 06-Jan-2015

Page 87

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Ch: 2+285.8~2+297.7
Start Date: 09-Jan-2015
Finish Date: 09-Jan-2015

Ch: 2+297.7~2+309.5
Start Date: 12-Jan-2015
Finish Date: 12-Jan-2015

Ch: 2+309.5~2+321.3
Start Date: 14-Jan-2015
Finish Date: 15-Jan-2015

Ch:2+321.3~2+333.2
Start Date: 18-Jan-2015
Finish Date: 19-Jan-2015

Ch: 2+333.2~2+345.1
Start Date: 21-Jan-2015
Finish Date: 22-Jan-2015

Ch: 2+345.1~2+357.0
Start Date: 25-Jan-2015
Finish Date: 25-Jan-2015

Invert Concrete (by Slip Formwork)


The section for which walls & crown was lined already, the
invert is now lined.

Ch: 0+894.9~0+906.8
Start Date: 06-Jan-2015
Finish Date: 06-Jan-2015

Ch: 1+974.2~1+998.2
Start Date: 25-Jan-2015
Finish Date: 25-Jan-2015

Amount of concrete for lining poured during


the month

3,242 m

No.s of Pours completed during the month

19 No.s

Total No.s of Pours completed to date

85 No.s

Page 88

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Total Length of RHTT

4,515 m

Length completed during the month

228 m

Total Length of RHTT lined/completed to


date
Percent Completed

1020 m
22.58 %

Concrete Backfilling of Niche:


Ch: 2+178.3~2+194.5
Start Date:29-Dec-2015
Finish Date: 29-Dec-2015
Concrete Qty = 94 m

Cushion Concrete:
Total Length of U/S HRT

502 m

Total Length of U/S HRT completed to date

502 m

Percent Completed

100 %

Concrete lining

Ch: 0+18.0~0+11.0 (Full face 6 m Section)


Single Headrace Tunnel
Including U/S Headrace

Start Date: 08-Jan-2015


Finish Date: 08-Jan-2015

Tunnel
Concrete Lining & Cushion
Concrete
(Including HRT Portal)

Ch: 0+11.0~0+005 (Full face 6 m Section)


Start Date: 18-Jan-2015
Finish Date: 18-Jan-2015

T0A ~ T1a (Ch: 0-49.10 ~


0+825.0)
Amount of concrete for lining poured during the
month
Total Length of Single HRT (including U/S
HRT)

285 m

874.1 m

Length of Tunnel lined (walls & crown only)

236 m

Progress during this month (Completely lined)

12 m

Previous Progress (Completely lined)

120 m

Progress To date (Completely lined)

132 m

Page 89

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-30: Progress Summary of HRT (Up to 25 January 2015)

5.2.6

Diversion Tunnel / Cofferdam

Presently, River is flowing through Diversion tunnel only. Construction of U/S & D/S
temporary earthen dykes has been completed.

5.2.7

Monitoring of Water Level of Neelum River

Water level of Neelum River is being monitored daily and the following graph shows the
average monthly discharge of Neelum River. As the weather is changing and spring season is
approaching, significant increase in the discharge of the river is obvious.

Page 90

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

PROJECT:

NJHP - SITE C-1

SERIES:

AVERAGE MONTHLY DISCHARGE OF RIVER NEELUM (cumecs)

PERIOD:

2016

700
630
560

420
350
280
210

140

89.7

70

Sr No

Month

January, 2016

February, 2016

March,2016

April,2016

May,2016

June,2016

July,2016

August,2016

September,2016

10

October,2016

11

November,2016

12

December,2016

Average Monthly
Flow (m3/s)

Remarks

89.7

Figure 5-31: Average Monthly Discharge of Neelum River 2015

Page 91

December,2016

November,2016

October,2016

September,2016

August,2016

July,2016

June,2016

May,2016

April,2016

March,2016

February, 2016

January, 2016

Flow (m/s)

490

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.2.8

MONTHLY PROGRESS REPORT


JANUARY 2016

Visitors/Meetings/Work Stoppage

Visitors

WAPDA M&S (Monitoring and Surveillance) team visited the site on 06 January, 2016.

Mr. Paul Snook (QA/QC-NJC) visited the site on 09 January, 2016.

Mr. J. R Stevenson (DTL) visited the site on 14 January, 2016.

Chairman WAPDA visited the site on 20 January, 2016. CE/PD-NJHPC, PM-NJC, PMCGGC/CMEC and other site staff accompanied the Chairman.

Meetings

Meeting regarding explosion of geyser in Engineer`s accommodationLot C1 was held on


04 January, 2016. Minutes of meeting were accepted as corrected.

Fortnightly Progress Review/coordination meeting was held on 11 January, 2016. Minutes


of meeting were accepted as corrected.

5.2.9

Site Photographs

Figures 5-32 to 5-40 are progress photos taken during this reporting period at C1.

Figure 5-32: Backfilling of Rockfill Dam at D/S Zone-3

Page 92

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-33: Removal of silt from Stilling Basin

Figure 5-34: Excavation for U/S RCC River Training works

Figure 5-35: Installation of Boom of the tower crane at sedimentation basin

Page 93

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-36: Drilling for rock anchors with compressed air drill machine at Right slope.

Figure 5-37: Placing of RCC at U/S training work area

Figure 5-38: Placing of concrete at U/S protection slab (P4) and finishing final surface

Page 94

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-39: Local Suppliers supplying SS1 for aggregate production at Crush Plant # 2

Figure 5-40: A view of Spillway from U/S

5.3

PROGRESS AT C2

5.3.1

Mobilization / Meetings

The weekly progress meeting with client and contractor regarding Drill & Blast, Concrete
Lining and Above Ground earthwork activities remained continued on each Monday at
10:00 am.

The weekly progress meeting with client and contractor regarding TBM remained
continued on each Tuesday at 10:00 am..

Page 95

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.3.2

MONTHLY PROGRESS REPORT


JANUARY 2016

Steel Liner Fabrication Progress:

Overall Grit Blasting & Painting of Thirty five (35) 12m CANS have been completed.

Operation

Plate
Cutting

Plate
Rolling

Fabrication
of Can (3m)

Fabrication
of Can (6m)

Fabrication
of Can (12m)

Grit Blasting/
Painting
Can(12m)

Total
Required

1072

1072

536

268

134

134

Progress

769

769

384

192

96

35

%Age

71.73
%

71.73
%

71.64 %

71.64 %

71.64 %

26.11%

Pi-Chart representing the progress of fabrication work in steel lining factory

Present Fabrication Progress (71.64 % Progress of Section till date)

Note: The percentage 71.64 % is the progress of fabrication work only.

Page 96

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.3.3

MONTHLY PROGRESS REPORT


JANUARY 2016

Aboveground Activities:

TBM Reservoir

Both tanks are in operation and supplying clean water to the both TBMs.

Spoil Deposits:

Shifting of muck material from spoil deposit Koroli to Adit A4a

Shifting of muck material from spoil deposit J to G.

4x4 MW (MAN) Power Plants (for TBM)

HFO generators remained operation for electricity.

Road hardening and landscape work is 100% complete.

Curbs construction from Bailey bridge to HFO power plant 100% completed.

Firefighting equipment tested and confirmed acceptable.

Sedimentation Tanks

Sedimentation tanks at A3, A4, and A4a and near vehicles, washing area along
Janderbain Nullah cleaned and improved.

Canalization of Janderbain Nullah

Placing and grouting of stones at slope along Janderbain Nullah.

Construction of Retaining Wall Opposite to Steel Lining Factory

Fixing of reinforcement from Ch. 0+120 ~ 0+131

Fixing of reinforcement and pouring of concrete of the panel (from Ch. 0+170 ~
0+180

Excavation of foundation for the panel from Ch. 0+050 ~ 0+060

Fixing of formwork for the panel from Ch. 0+180 ~ 0+190

TBM Bridge
th

Repair of TBM bridge has been completed and opened for traffic on January 20 ,
2016.

Underground Activities

5.3.4

Tunnelling

5.3.4.1

Jhelum TBM 696:

After severe rock burst happened on May 31, 2015, TBM 696 started mining from January 10,
2016.

In the month of January, TBM 696 excavated 18.9m from chainage 9+712.07 ~

Page 97

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

9+693.17. TST report Number 48 and continues probe drilling use to assess the rock condition
in front of TBM cutter head. Vertical and horizontal relief holes also drill to release the stresses
from potential rock burst areas.

In this 18.9m excavated section, the rock lithology is totally Sandstone. Minor to major rock
burst events observed from the sandstone. About 16 rock burst events noted in this month. Two
were major rock burst which produce damage in support and rock in the crown. In the
excavated section, the Rock class is Q4.

Description
Progress on Jan
2016 (m)
Cumulative
Progress (m)
Total Percentage
(%)

TBM
Q2

TBM
Q3

TBM
Q4

TBM
Q5

D&B
- C1

Total

0.0

0.0

18.9

0.0

105.5

124.4

511.

3008

2197

110.

.1

.0

462.8

6289.9

8.1

47.8

34.9

1.8

7.4

56.4

C1 Ch.

Delay
time

TBM Ch.

Delay

9690.87

Progress

(m)
4871.97

Description

Stage
Phase

01

01

Stage

Invert cleaning

Invert concrete

02

Phase
02

Stage

Inspection & Repair at

01

Accessible Location

-491

Days

-5408

Metres

VO-22 Programme exceeded


dated 30th June 2015.

Total
meter
s (m)

Total
previous
months
(m)

Total this
month (m)

New Total
(m)

Percentage
completed
(%)

6289.9

1048

190

1238

19.68 %

2536

369

144

513

20.22%

11070

25

25

11070

6289.9

600

600

Remarks

0.22%

Repair & Remedial

Stage
02

Variance with Program (VO22) on 30th June 2015

4818.90

Remain

Phases/ Stages

measures at
accessible Location

Phase 08

5.3.4.2

Chainage
(m)

Removal Debris

9.53%

Neelum TBM 697:


In the month of January 2016, TBM 697 excavated 209.94m from Chainage 8+220.77 ~
8+010.83. TST reports (Numbers 73, 74, 75 & 76) and continues probe drilling use to assess
the rock condition in front of TBM cutter head for the said excavated section. Vertical and
horizontal relief holes also drill to release the stresses from potential rock burst areas.
In this 209.94 m excavated section, the rock lithology is siltstone, Sandstone and mudstone.
The siltstone is about 51.39% and it is massive and fractured at some locations. The sandstone
is about 42.13 % and mudstone is about 6.47 %. Minor to medium rock burst observed from
the sandstone and some time from siltstone. About 15 minor rock burst events noted in this

Page 98

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

month. No damage produce by these rock burst events. In the excavated section, the Q3 rock
class is 34.52 % and Q4 rock class is 65.47 %.
For over-coring test, bore hole number 07 drilled up to 19m with 130mm dia at chainage
08+422. The overburden in this area is about 1700 m. Up to 15 m depth the rock condition was
good. Core recovery and RQD up to 15 m is about 95 %. But after 15 m depth core disking start
up to 19. 5 m. This rock condition is not suitable for over-coring test and hole terminate. Now
new location will be given to contractor.

Utilization TBM 697

Avg. 2013

Avg. 2014

Avg. 2015

Jan-16

Avg. 2016

Min/Day

Hr./Day

Excavation

13.1

18.1

14.6

21.7

21.7

312.4

5.21

Specified Maintenance

16.7

16.7

16.7

16.7

16.7

240.0

4.00

Extended Maintenance

12.4

7.7

4.2

6.9

6.9

99.4

1.66

Delay

57.9

57.6

64.5

54.7

54.7

788.2

13.14

100.00

100.00

100.00

100.00

100.00

1440

24.0

TOTAL

Description
Progress on Jan
2016 (m)
Cumulative
Progress (m)
Total
Percentage (%)

TBM
Q2

TBM
Q3

TBM
Q4

0.0

79.2

586.

3752

3156

152.

.2

.3

7.4

47.5

40.0

1.9

130.
8

TBM
Q5

D&B
- C1

0.0

93.0

250.5

Total

Chainage
(m)

302.9

C1 Ch.

4713.50

7897.

TBM Ch.

Delay

17

8010.24

Progress

Remain
3.2

70.55

(m)
3296.74

Page 99

Variance with Program (VO-22)


on 3rd July 2015
Delay time

-457

Days

-5017

Metres

VO-22 Programme exceeded


dated 3rd July, 2015.

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-41: TBM Monthly Progress with Rock Burst Locations and Geo-structural
Features
5.3.5

Drill & Blast Excavations

The major activities involve pre excavation grouting, roof support, tunnel excavation, rock
support, and investigation works. Excavation in Headrace Tunnel downstream of T3 has been
completed on 8

th

December 2015 and 8

th

November, 2015 in left and right headrace tunnel

respectively. Right headrace breakthrough has been successfully achieved on 9

th

January

2016. Contractor has achieved 119.1m progress in T3c ~ T3aL and cumulative progress in left
tunnel is 1017.8m.

The breakthrough of the 31m plug at T4~M4 has been done successfully on 14th June, 2014
th

and benching at T4~M4 section completed on Jan 11 , 2015.

The excavation cycle in the Headrace Tunnels (Single & Twin) is comprising of drilling, charging
& blasting, ventilation, mucking of blasted material, scaling, geological mapping of tunnel faces,
excavation profile surveying, installation of rock bolts & Wire-mesh wherever required and
st

shotcreting (1 and 2

nd

layers) of cleared parts. All these activities fully supervised by NJC site

supervisory staff, who remained busy in geological mapping of tunnel faces and supervising &
verifying recording each activity in details in Daily Progress Reports & Tunnel Shift Reports
round the clock in 2 shifts (each shift of 12 hours). The finalization of upto date completed
geological maps, geotechnical maps, production spread sheets, progress charts and sketch
drawings of each tunnel work site in the site office, remained in progress.

Access Adit A2a:


Contractor completed excavation of Adit A2 Extension on 07 September 2013.

Page 100

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Headrace Twin Tunnel Section between T3cT3aL (HRT3c u/s):


1062.46 m

Progress during the month

119.1 m

Per day progress

4.0 m

To date excavated length

1017.8 m

To date percent progress

95.8%

DAILY PROGRESS (m)

Total length

Twin HRT part T3c-T3aL (U/S)


PROGRESS (Dec. 26, 15 ~ Jan. 25, 16)

10

8
6
4
2

2
4

Daily Progress

Tunnel Exc

S-HRT Ch. D5+

7 day avg

Figure 5-42: Tunnel Progress Chart Upstream HRT T3c-T3aL

PERCENTAGES OF ROCK UNITS ENCOUNTERED IN D/S T3c~T3aL


A4 Side DURING MONTH OF (Dec. 26, 15 ~ Jan. 25, 16)

PERCENTAGES OF Q-VALUES ENCOUNTERED IN D/S T3c~T3aL


A4 Side DURING MONTH OF (Dec. 26, 15 ~ Jan. 25, 16)
100%

90%

2%

80%

70%

60%

62.38%

50%
48%

51%
40%
37.62%
30%

20%

10%
0%

0%
0.00%

SS1

SS-2

Silt st.

0.00%

Q2

Mud st.

Q3

Q4a

Q4b

Q4b

Figure 5-43: Rock Quality at Downstream Headrace Tunnel (T3c-T3al)

Headrace Twin Tunnel Section between T3cT3aR (HRT3c u/s):


Designed length

1063.4 m

Progress during the month

58.2 m

Per day progress

1.8 m

To date excavated length

1063.4 m

To date percent progress

100%

Page 101

0.00%

25-Jan-16

24-Jan-16

23-Jan-16

22-Jan-16

21-Jan-16

20-Jan-16

19-Jan-16

18-Jan-16

17-Jan-16

16-Jan-16

15-Jan-16

14-Jan-16

13-Jan-16

12-Jan-16

11-Jan-16

9-Jan-16

DATE
Rock Class

10-Jan-16

8-Jan-16

7-Jan-16

6-Jan-16

5-Jan-16

4-Jan-16

3-Jan-16

2-Jan-16

1-Jan-16

31-Dec-15

30-Dec-15

29-Dec-15

28-Dec-15

27-Dec-15

6
26-Dec-15

ROCK CLASS (Q)

DAILY PROGRESS (m)

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Twin HRT part T3c-T3aR (U/S)


PROGRESS (Dec. 26, 15 ~ Jan. 25, 16)

10
8
6
4

2
4

Tunnel Exc

25-Jan-16

24-Jan-16

23-Jan-16

22-Jan-16

21-Jan-16

20-Jan-16

19-Jan-16

18-Jan-16

17-Jan-16

16-Jan-16

15-Jan-16

14-Jan-16

13-Jan-16

12-Jan-16

11-Jan-16

9-Jan-16

DATE
Daily Progress

Rock Class

10-Jan-16

8-Jan-16

7-Jan-16

6-Jan-16

5-Jan-16

4-Jan-16

3-Jan-16

2-Jan-16

1-Jan-16

31-Dec-15

30-Dec-15

29-Dec-15

28-Dec-15

27-Dec-15

6
26-Dec-15

ROCK CLASS (Q)

7 day avg

Figure 5-44:Tunnel Progress Chart Upstream HRT T3c-T3aR

PERCENTAGES OF ROCK UNITS ENCOUNTERED IN D/S T3c~T3aR


A4 Side DURING MONTH OF (Dec. 26, 15 ~ Jan. 25, 16)

PERCENTAGES OF Q-VALUES ENCOUNTERED IN D/S T3c~T3aR


A4 Side DURING MONTH OF (Dec. 26, 15 ~ Jan. 25, 16)
100%

90%
6%

88.05%
80%

70%

60%

27%

50%

40%

30%

66%
0%

20%
10%

11.95%

0%
0.00%

SS1

SS-2

Silt st.

0.00%

Q2

Mud st.

Q3

Q4a

Q4b

Figure 5-45: Rock Quality at Downstream Headrace Tunnel (T3c-T3aR)

5.3.6

Headrace Tunnel Concrete Lining:

Full face tunnel lining has been selected in order to reduce the hydraulic losses and reduce the
maintenance and repair cost associated with an unlined tunnel.

Concrete lining of headrace tunnel shall be carried out where excavation has been done by drill
and blast, and does not include the section/portion of headrace tunnel which is to be excavated
by TBM. The Jhelum River crossing which would be lined by steel and have to encasement with
Concrete lining.

The scheduled commencement dates of concrete lining in twin tunnels (T3,T3aL and T3, T3aR)
was August 15, 2012 and December 12, 2012 respectively. The contractor has allocated 04
sets of needle beam formwork in his method statement i.e. 02 sets for each sections.

Page 102

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

The first and second needle beam formwork has been operational since August 15, 2013 and
November 22, 2013 respectively in right headrace tunnel and the third and fourth shutter in left
headrace tunnel has been operational since October 20, 2014 and June 01, 2015 respectively.
Contractor has allocated 04 sets of steel trolley formwork for single headrace tunnel (T3c~M4).
All the four shutters are operational since July 15, 2014, September 04, 2014, January 23, 2015
and February 16, 2015, respectively.

Contractor has allocated 04 sets of trolley formwork for single headrace tunnel (T3c~M4). All
the four shutters are operational since July 15, 2014, September 04, 2014, January 23, 2015
and February 16, 2015, respectively.

Headrace Twin Tunnel Section between T3L-T3aL (HRT3 d/s):


Progress remained slow due to the shortage of skilled labour and construction resources.
Labours strike after rock burst in TBM section.
Designed length

3098 m

Progress during the month

82.2 m

Per day progress

2.9 m

To date lined length

2004.7 m

Work Done

52.6 %

Headrace Twin Tunnel Section between T3R-T3aR (HRT3 d/s):


Progress remained slow due to the severe shortage of skilled labour and construction
resources.
Designed length

3165 m

Progress during the month

36.1 m

Per day progress

1.2 m

To date lined length

2542.3 m

Work Done

78.6 %

Headrace Single Tunnel Section between T4~M4:


Designed length

2968 m

Progress during the month

160.4 m

Per day progress

5.7 m

To date lined length

2757.3 m

Work Done

92.3 %

Headrace Single Tunnel Section between T4~T3c:


Designed length

1695 m

Progress during the month

0.0 m

Per day progress

0.0 m

Page 103

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

To date lined length

1578.7 m

Work Done

93.1 %

Concrete Lining Works

Sr.#

Work Description

Unit(m)

Total
Qty
(m)

Total Up to
Previous
month
(m)

During
this
month
(m)

Total
Qty.
to date

3165

2506.2

36.1

2542.3

3165

2618.1

35

2653.1

3098

1922.7

82.2

2004.7

3098

1104.3

33.7

1138

3098

21801.

21.1

2201.2

679

45.1

45.1

2968

2596.9

160.4

2757.3

2968

729.9

90.5

820.4

2968

2968

2968

1695

1578.7

1578.7

1695

1249

187.2

1436.2

1695

1569.3

11.3

1580.6

519

519

436.7

11.9

448.6

Concrete
Lining (full
1

T3R-T3aR

section)
Invert Blinding
Concrete
Concrete
Lining Walls &
Crown

T3L-T3aL

Invert
Concrete
Invert Blinding
Concrete

T3L-T2aL

Invert Blinding
Concrete
Concrete
Lining Walls &
Crown

T4-M4

Invert
Concrete
Invert Blinding
Concrete
Concrete
Lining Walls &
Crown

T3c-T4

Invert
Concrete
Invert Blinding
Concrete
Concrete
Lining (full

T3bL - T3c T3bR

section)
Invert Blinding
Concrete

Page 104

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.3.7

MONTHLY PROGRESS REPORT


JANUARY 2016

Site Photographs:

Figures 5-46 to 5-50 are progress photos taken during this reporting period at C2.

Figure 5-46: S-697: Heavy support installation continuously as precautionary measures


for rock burst

Figure 5-47: TBM 696: Goat slaughtering ceremony on re-start of TBM S-696 at 09.16am
on Sunday 10th January 2016

Page 105

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-48: S-697: Cleaning tunnel invert using mini loader aspreparation of invert
shotcrete in progress

Figure 5-49: S-696: Rock burst occurred on 10th and 13thJan 2015(night shift)

Figure 5-50: S-697: Machine belt conveyor repairing in progress.

Page 106

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.4

PROGRESS AT C3

5.4.1

Mobilization & Site Establishment

MONTHLY PROGRESS REPORT


JANUARY 2016

Possession of Site and Access: 1298 Kanal of land was required at site C3. The process of
handing / taking over of this land between WAPDA and the Contractor have been completed.

5.5

TUNNELLING

5.5.1

Tunnels Excavation Works

Excavation activities of bench in Tailrace Tunnel, Headrace Surge Tunnel (Benching)


remained

in- progress. No activity for bench excavation of headrace tunnel observed.

Concrete lining in Headrace Tunnel remained is in progress. PH unit No 1, 2, 3 & 4 civil,


mechanical and electrical works remained in progress. Transformer hall concrete work
99.12% is been completed. Excavation cycle in Tunnels, comprising, survey and alignment,
drilling for blast holes, charging, blasting and ventilation, mucking, scaling, geological
st

mappings, Rock support work (1 layer Sc, fully grouted rock bolting, wire mesh and 2

nd

layer shotcrete),all mentioned activities were fully supervised by the NJC site staff, round the
clock in two shifts.

Following tunnels have already been completed.

Access to Power House, Powerhouse Cavern, Drainage Gallery, Headrace Manifold Tunnel,
Headrace Surge Branch, Access to Headrace Tunnel, Access to Water Tank, Water Tank
Shaft, Probe Tunnel, Cable Tunnel, Access to Tailrace surge Tunnel, Access Tunnel A8,
Access Tunnel A7, Headrace Surge Branch, Access Gallery A5, HVAC Tunnel, Penstock # 1, 2,
3 & 4, Tailrace manifold, Bonneted gate/bus bar Tunnel # 1, 2, 3 & 4, D/S surge tunnel, HR
bypass tunnel Surge Shaft.

Headrace Tunnel (22a-M4):


Top heading excavation of 3,403m long headrace tunnel already been completed. Bench
excavation is stopped at Ch: 0+102 but invert concrete and concrete lining of crown, walls and
invert continued during the month.
To date Bench excavation

3,301m

Bench excavation during month of January 2016

0m

To date Invert Concrete

3,346m

Invert Concrete during month of January 2016

0m

To date Concrete lining (walls & crown)

2916m

Concrete lining during month of January 2016 (walls & crown)

192m

To date Concrete of Invert lining

2675m

Page 107

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Concrete invert lining during month of January 2016

192m

Headrace Manifold (Invert + Wall & Crown):


3

In Headrace Manifold, concrete work in progress. Until now 1451m (66%) concrete complete
3

out of total estimated quantity of 2,200m .

Headrace Surge Branch Tunnel (Invert Concrete Lining):


In Headrace Surge Branch, concrete work in progress. Until now 12m (24%) concrete complete
out of total estimated quantity of 47.92m.

Figure 5-51: Graphical presentation of progress of grouting in Headrace Tunnel


Powerhouse
A)

Excavation:

Excavation completed on 02 July 2014.

B)

Concrete Work:

During the month of January 2016, concrete poured at Unit-1 turbine foundation up to
El.588.00, Unit-3 Generation foundation and slab/beams El.594.20 etc.
Total concrete quantity

28,280m

Progress during month of January, 2016

774m

Total poured quantity of concrete

25,964m

Work Done

92%

Page 108

3
3

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2015

Figure 5-52: Progress of Concrete Works in Powerhouse Cavern

Page 109

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2015

Figure 5-53: Progress of Concrete Works in Unit-1, Powerhouse Cavern

Page 110

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2015

Figure 5-54: Progress of Concrete Works in Unit-2, Powerhouse Cavern

Page 111

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2015

Figure 5-55: Progress of Concrete Works in Unit-3, Powerhouse Cavern


Page 112

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2015

Figure 5-56: Progress of Concrete Works in Unit-4, Powerhouse Cavern


Page 113

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Busbar Tunnels:
A)

Excavation: Excavation completed on September 20, 2012.

B)

Concrete Work:

During the month of January 2016, concrete poured at Unit-3 slabs P1 & P2.
Total concrete quantity

1850m

Progress during month of January, 2016

108m

Total poured quantity of concrete

799m

Work Done

43%

Transformer Hall:
A)

Excavation: Excavation completed on June 21, 2013.

B)

Concrete Work:

During the month of January 2015, concrete poured at HVAC cable trenches wall, Unit-1 & 2 2

nd

stage concrete for rails at crane beam etc.


Total concrete quantity

7,095m

Progress during month of January 2016

29m

Total poured quantity of concrete

7,048m

Work Done

99%

3
3

Penstock Tunnels (1, 2, 3, 4):


In penstock Tunnels, concrete work in progress. Until now 396m (90%) concrete complete out of
total estimated quantity of 439m.

Draft Tubes (1, 2, 3, 4):


3

In draft tubes, concrete work is in progress. Until now 3,397m (54%) concrete complete out of total
3

estimated quantity of 6,258m .

Water Tank:
A)

Excavation: Excavation has already been completed.

B)

Concrete Work:

There was no activity during this period.


To date concrete status in Water Tank is as under:
Total concrete quantity

650 m

Progress during the month of January, 2016

Nil

Total poured quantity of concrete

462 m

Work Done

71%

A7-Outlet Structure:
3

In A7 outlet structure, concrete work is in progress. Until now 4,302m (55%) concrete complete out
3

of total estimated quantity of 7,860m . Contractor mainly worked in sluice structure and Culvert
invert slab reinforcement installation.

Page 114

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Tailrace Tunnel: Excavation of 3,551m long Tailrace tunnel remain continued during the month;
presently contractor is advancing from (A-7) on upstream face T9 to T7A and excavation from (A6) towards downstream face T7A to T8. On 30-05-2015, Contractor started excavation of Bench
from Ch: 1+000 towards outlet.

Heading
Total Length

3,551m

Progress during month of January 2016

(Ch: 3+505.6)

0m

Per day, progress

0m

Total Excavated length (To date)

3,533m

Work Done

99%

Benching
A7 Tailrace Tunnel (Benching from Ch: 1+000 towards 3+523):
Total length

2489m

Progress during month of January 2016

(From Ch: 1+745~1+882)

137m

Total Excavated length (To date)

882m

Work Done

35%

A6 Tailrace Tunnel (Benching from Ch: 1+000 towards 0+000):


Total length

1000m

Progress during month of January 2016

(From Ch: 0+627~0+443)

184m

Total Excavated length (To date)

557m

Work Done

56%

Lining
A7 Tailrace Tunnel (Invert Lining from Ch: 1+034 towards 3+523):
Total length

2489m

Progress during month of January 2016

(From Ch: 1+505~1+625)

120m

Total invert concrete lining poured (To date)

591m

Work Done

24%

A6 Tailrace Tunnel (Invert Lining from Ch: 1+034 towards 0+000):


Total length

1034m

Progress during month of January 2016

(From Ch: 0+700~0+670)

30m

Total invert concrete lining poured (To date)

103m

Work Done

10%

Page 115

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-57: Tunneling in Tailrace Tunnel from Outlet side

Figure 5-58: Tailrace Tunnel A7 (Benching)

Figure 5-59: Tailrace Tunnel A6 (Benching)

Page 116

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Headrace Surge Tunnel + A10 Adit: Excavation activity of 926m long Headrace Surge tunnel
again started on 06/04/2014. To date progress is given below:

Heading:
Total Length (Excluding wing walls 17m)

932m

Work Done

100%

Benching:
Total length (Including wing walls 17m)

949

Work Done

100%

Lining:
A10 Headrace Surge Tunnel (upper leg)
Total length

597m

Progress during month of January 2016

(from different chainages)

41m

Total invert concrete poured (To date)

110m

Work Done

18%

Headrace Surge Branch: Bench excavation of 56m long Headrace Surge Branch started on
30/09/2015 and completed on 18/10/2015. To date progress is given below:

Benching
Total Length

56m

Work Done

100%

Surge Shaft: Excavation of sinking shaft started on 1

st

February 2013. Shaft excavation

completed. To date progress is given below.

Total height

353m

Work Done

100%

Page 117

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.6

SURFACE WORKS

5.6.1

WAPDA Permanent Residential Colony

5.6.2

WAPDA Permanent
5.6.3
Residential Colony

MONTHLY PROGRESS REPORT


JANUARY 2016

Rest House:

Installation of false ceiling, wood work for


wardrobe, plumbing work, electrical work, paint
work, fixing of doors, safety grills, polishing for
doors/wardrobe and marble work for stairs
continued during this period.

Pouring of concrete (C-30) for sewer line at


east side completed.

5.6.4

Retaining wall behind the Rest House: (b/w Rest


House & CAT-II)

Pouring of lean concrete (F-12) for stitching of


stones of base slab completed.

Pouring of concrete (C-30) for base slab of


retaining wall completed.

Pouring of concrete (C-30) for half (one part)


portion of retaining wall completed.

Fixing of formwork for 2

nd

half of retaining wall

continued during this period.


CAT-II:

49.00%
No activity.

CAT-III:

Plaster repairing work of house # 01~06, 07,


08, 12, laying of sewerage line of house # 03
04, 05, 06, 07, 11, 12, 13, block masonry of
house # 08, 09 and for manhole of house # 04,
10, 12, 13, paint work of house # 01 ~ 06, 09 ~
13, plumbing work of house # 02, 03, 05, 06,
07, 09, 10, 11, 13, electrical work of house #
01~06, plinth protection at house # 07, 08, tile
work of house # 01, 03, wood work of house #
01~13, fixing of door of house # 01~06, 07~10
and plaster for manhole continued during this
period.

Pouring of concrete (C-30) for copping of


house # 05 completed.

CAT-IV:

Plaster work of house # 04, 05, 06, 07, 08, 13,

Page 118

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

14, 15, 16, block masonry of house # 02, 11,


12,13, 14, 15, 19, electrical work of house # 07,
08, 09, 11, 12, 13, 14, 15, plumbing work of
house # 06, 07, 08, 13, 14, roof treatment of
house # 15, fixing of door frames of house #
13, 14 and tile work of house # 03, 04
continued during this period.
CAT-V:

Plaster work of house # 04, 05, 06, 07, 09, 13,


14, 15, 16, 23, 24, 27, 28, 30, 31, electrical
work of house # 07, 08, 09, 13, 14, 15, 16, 25,
26, 27, 28, 30, 31, 32, 33, block masonry of
house # 06, 07, 08, tile work of house # 01, 02,
06, 04, 05, 06, fixing of door frame of house #
05, 06, 09, 11, 12, 15, 21, 22, 23, 24, plumbing
work of house # 01~12, 27, 28, 32, 33, kitchen
shelves

of

house

11,

12,

15

and

grinding/polishing of marble of house # 01, 02,


03, 04 continued during this period.

Pouring of concrete (1:2:4) for flooring of house


# 07, 08 completed.

Boundary Wall:

Pouring of concrete (C-30) for bracing beams


and columns (column 59~67) completed.

Septic Tank and Sewers:

Pouring

of

concrete

(C-30)

for

footing

completed.

Fixing of formwork and reinforcement for


manhole # 3 continued during this period.

Internal Retaining wall and compound wall:

Block masonry of house # 05, 08, 07, 09, 10,


12, 13 (CAT-III), fixing of formwork for RCC
wall of house # 08 and fixing of gates from
house # 01~06 continued during this period.

Pouring of concrete (C-30) for columns and


base slab of house # 08, 09, 13 of compound
wall, for RCC retaining wall between house #
08, 09, for columns of house # 07, 09, 11, 13,
main gate columns of house # 01~06, 13,
retaining wall at front side of house # 12, for
base slab at front side of house # 08, 09, 11

Page 119

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

and for copping of house # 03, 04 completed.

Pouring of concrete (F-12) for courtyard of


house # 07, 08 and for base slab of compound
wall of house # 11, 12 completed.

Water Tank:

No activity.

Market:

Fixing of formwork and reinforcement for roof


slab continued during this period.

Mosque:

Pouring of concrete for 06 Nos. of long columns


completed.

Fixing of formwork and reinforcement for bracing


beams and block masonry for arches continued
during this period.

Dispensary:

Pouring of concrete(B-20) for roof slab


completed.

Spoil Deposit

A5, A6 New Spoil Area: No activity.


A7: No activity.
A8 New Spoil Deposit (Soy Nullah): No activity.

Water Treatment

Slow Sand Filter:

Plant

Pouring of concrete (C-30) for outflow boxes


completed.
Chlorination Room:
Pouring of concrete (C-30) for plinth beams completed.
Infiltration Gallery:
Backfilling of area between slow sand filter and
chlorination room completed.
Water Storage Tank:
Pouring of concrete (C-30) for pickup columns
completed.
Sedimentation Tank:
Pouring of blinding concrete (F-12) for base slab
completed.
Fixing of reinforcement for base slab continued during
this period.

Page 120

71.20%

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Agar Nullah Slope

Protection

MONTHLY PROGRESS REPORT


JANUARY 2016

Pouring of concrete (B-20) for 2nd step of


protection wall at Ch: 0+146~0+156 (L/S),
0+136~0+146, 0+198~0+208, 0+220~0+248,
0+248~0+263

and

for

1st

step

at

Ch:

0+125~0+165.

55.25%

Fixing of formwork for 3rd lift of protection wall


at Ch: 0+125 ~ 0+165 continued during this
period.

Control Building of

Agar Nullah

Pouring of concrete (C-30) for cable trenches


walls and stair footing completed.

Fixing of formwork for columns and plinth

18.97%

beams continued during this period.


A8-Spoil Area

No activity.

100%

Retaining wall
A7 Access Road

No activity.

Boulder Collection

Boulder collection from Agar Nullah continued

NA

during this period.


Administration

Building

NA

Pouring of concrete (C-30) for 21 Nos. of


footings

and

30

Nos.

of

neck

columns

4.80%

completed.
525 kV Switchyard

11 kV Sub-Station

Pouring of concrete (C-30) for TR-1 walls


between 14~15, 09~10, 04~05 and 60m wall
segments completed.
Pouring of concrete (C-30) for TR-1 base slab
between 09~10, 04~05 and 36m segments
completed.
Pouring of concrete for footings SS-F3/H-8,
ES-F7/PQ, QR, RM-F1, for pedestals 34 Nos.
for manhole 07, 08, 09, 10, D4, manhole/06, 03
completed.
Pouring of concrete (F-12) for TR-1 between
(4~5) and 02 Nos. of manholes, for TR-4
trench completed.
Excavation for pipeline 4D, laying of filter
material for perforated pipes, backfilling, fixing
of reinforcement for footings ES-F7/EF, QR,
FG, ML, LN, fixing of formwork for TR-1 base
slab between 4~5, for manhole # 11, 12 and
laying of pipe 3C for drainage continued during
this period.
Pouring of concrete (F-12) for sub-station
blinding completed.

Page 121

54.63%

0.5%

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.7

MONTHLY PROGRESS REPORT


JANUARY 2016

Visits/Meetings

Visits:

WAPDA Monitoring & Surveillance Team visited site on 08 January, 2016.

Meetings:

Mechanical, Electrical and Civil Liaison Meeting held on 29 December, 2015 and 12 January,
2016.

5.8

Site Photographs

Figures 5-60 to 5-73 are progress photos taken during this reporting period at C3.

Figure 5-60: A5 Headrace Surge Branch - A view of demarcation of dowels for backfill
concrete at EL.594 ~ 591

Figure 5-61: A6 Tailrace Tunnel - Invert cleaning

Page 122

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-62: Headrace Tunnel - Cleaning work at Invert Lining

Figure 5-63: Headrace Manifold - General view

Figure 5-64: Headrace Manifold and Penstock junction

Page 123

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-65: A7 Tailrace Tunnel - Fixing of formwork for rail track at Ch: 1+685 ~ 1+715

Figure 5-66: A7 Tailrace Tunnel - Drilling for rock bolts at Ch: 1+812 ~ 1+832

Figure 5-67: A7 Tailrace Tunnel - Washing and crack inducer before lining concrete at Ch:
1+565 ~ 1+625

Page 124

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-68: A7 Outlet Structure - Base slab

Figure 5-69: Headrace Surge Branch - Fixing of formwork for backfill

Figure 5-70: Powerhouse (Unit 3) - Column D/S

Page 125

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Figure 5-71: NJHPC Transformer hall 525kV cable trenches & cable gallery

Figure 5-72: NJHPC Switchyard - View from Control Building cable trenches

Figure 5-73: Control building - Pouring of concrete for trenches

Page 126

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.9

E& M Works

5.9.1

Mechanical Works

MONTHLY PROGRESS REPORT


JANUARY 2016

POWER HOUSE

UNIT NO.1

Cooling water inlet and outlet pipes of 89mm for turbine guide bearing installed at
EL.586.8m to EL.590.46m were pressure tested at 1.5MPa as per drawing no.278E53-0203-223~228; PO-13000.

Air supply pipe of 27mm for maintenance seal installed at EL.587m to EL.589.5m was
pressure tested at 1.2MPa as per drawing no.278E53-02-03-101~103/2; PO-14451.

Water outlet header pipe of 377mm from cooling water supply pumps installed at EL.587m
to EL.589.5m was pressure tested at 1.5MPa as per drawing no.278E53-02-03-223~228;
PO-13000.

05 steel plates of size 200x200x10mm of turbine oil header pipe and high pressure air for oil
have been installed at EL.587m and inspected as per drawing no.278E53-02-03-406~409;
PO-18153 & 278E53-02-03-616~620; PO-15417.

UNIT NO.3

Wrapping for insulation of Water supply branch pipe 377mm to water tank & water supply
header pipe 144mm for firefighting system from water tank through Booster pumps in bus
bar Tunnel, has been completed and quantity is verified as per site instruction EMH-M-012
under day work.

18 pieces of I steels have been installed at EL.592.515m for foundation of lower guide
bearing as per drawing no. Z1b002298S & QCR-03-MJ158.

Frame for Main inlet valve (MIV) has been shifted to erection bay-1 for assembling (EL600.5m).

02 Sleeves having 273mm for fire water system installed at EL. 593.7m to EL.594.2m as
per drawing no. 278E53-02-03-004~013; PO-13951.

Sleeve

having

168mm

for

powerhouse

service

air

pipe

installed

at

EL. 593.7m to EL. 594.2m as per drawing no. 278E53-02-03-004~013; PO-13951.

Sleeve

having

70mm

for

generator

fire

extinguishing

system

installed

at

EL. 593.405m as per drawing no. Z1b004929.

02 Sleeves having 219mm for turbine oil system installed at EL. 593.7m to
EL.594.2masperdrawing no. 278E53-02-03-406~609; PO-18153.

Assembling

of

Main

inlet

valve

(MIV)

is

in

progress

at

erection

bay

(EL-600.5m).On 13th January 2016 commencement of the erection of MIV issued.

Cooling water inlet and outlet pipes of 89mm for upper guide bearing installed at
EL.595.1m to EL.598.77m were pressure tested at 1.5MPa as per drawing no.278E53-0203-223~228;PO-13000.

Page 127

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Cooling water inlet and outlet pipes of 168mm for thrust bearing installed at EL.595.1m to
EL.599.6m were pressure tested at 1.5MPa as per drawing no.278E53-02-03-223~228;PO13000.

10 steel plates of size 200x200x10mm of supply & return oil pipe for upper guide bearing and
thrust bearing have been installed at EL.594.6m to EL.595.6m and inspected as per drawing
no.278E53-02-03-406~409; PO-13000.

UNIT NO.4

Internal assembly of inlet valve has been completed; the ball of inlet valve has been
connected with arm levers and rotated manually with the help of bridge crane at erection bay
(EL-600.5m).

Downstream section of main inlet valve (MIV) has been assembled at erection bay (EL600.5m).

Contractor has shifted Draft tube cone at unit bay-4 (EL-579.5m) from erection by (EL600.5m).

Cutting of spider sports inside the draft tube section is in progress.

Dust proof cover for generator and platform for stator erection has been installed by the
contractor.

Verticality and Concentricity of stator roundness measuring device was checked before
major key bars & remaining 70 Nos. key bars erection as per drawing no. S1681 and QCR04ST-002 & QCR-04ST-005.

Verticality and radius of the 1st key bar of stator has been checked as per drawing no.
Z1b004712s & QCR-04ST-003.

Radius, chord length & radial torsion of the major key bars & remaining 70 Nos. key bars for
stator have been checked as per drawing no. Z1b004712s and QCR-04ST-004 & QCR04ST-006.

MIV has been shifted at EL 579.50m from erection bay (EL-600.5m) to make a space for the
assembling of other MIV at erection bay.

Installation of 75 key bars (Length 2835mm, 50*50mm each) for stator frame is in progress.

Draft tube section cone (upper part) is shifted from erection bay (EL-600.5m) to unit bay (EL579.5m).

Marking and drilling of holes in stator frame and welding of key bars for stator is in progress.

TRANSFORMER HALL

Welding and alignment of Transformers cooling water header pipe 426mm completed.

A7 TAILRACE TUNNEL OUTLET GATE

44 steel plates comprising of 24 pieces each of size 150x150x16mm & weight 4.07kg, 08
pieces each of size 150x250x16mm & weight 6.11kg and 12 pieces each of size
150x150x16mm & weight 6.9kg have been installed at outlet gate slots from EL.599.05 to
EL.602.05m as per drawing no. 278E66-02-3-22-3(1/2); PO-12928.

Page 128

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

08 steel plates each of size 200x150x16mm & weight 4.49 kg and 30 steel plates each of
size 150x150x16mm & weight 6.11 kg for outlet gate structure from chainage (0+19.5 to
0+25) have been installed at EL.602.05m to EL.606.0m and inspected as per drawing
no.278E66-02-03-22-5 & 278E66-02-03-22-1; PO-12928.

METHOD STATEMENTS

Comments were made on Method Statement for Stator Assembly (REV-1) as per PO-19907.
Method Statement is Approved Except as Noted (AEN).

Comments were made on Method Statement for review of methodology for installation of the
transformer hall false ceiling (Rev-0) as per PO-19958. Method Statement is Approved
Except as Noted (AEN).

FIELD CHANGE REQUEST

The door of generator housing will be fixed by expansion bolts instead of foundation
embedded plates (Unit No 1 to 4) as per FCR No-311.

The location of CO2 embedded pipe of generator will be consistent with drawings
Z1b004852S (Unit No 1 to 4) as per FCR No-310.

The location of the plan route of the cooling water pipes for turbine guide bearing will be
changed to avoid conflict with the reinforcement of unit pit. (Unit No 1 to 2) as per FCR No306.

The diameter of the steel bar changed from 25mm to 16mm and length of the steel bar
changed from 71mm to 100mm for the eye of wire rope, which was welded with embedded
steel pipe of fence in Switch Yard as per FCR No-305.

Make use of 75x38x6mm (height x width x thickness) C channel instead of 80x43x5mm


(height x width x thickness) and pipes of 50x4mm (thickness) & 80x4mm (thickness)
instead of 50x4.5mm (thickness) & 80x4.5mm (thickness) in outlet gates of tailrace
tunnel EL.606m as per FCR No-304.

MATERIAL INSPECTION

The shipment under bill of lading QSKN6042639, containing parts of Cooling and Fire water
equipment including parts of hanger arrived at site and inspected on 5th January, 2016.

The shipment under bill of lading 156101F01, containing parts of Turbines & Inlet Valves
including parts of distributor, shaft assembly, rotating parts, bottom ring, head cover,
operating ring, inlet valve arrangement assembly, valve oil water pipe, spare parts and tools,
etc arrived at site and inspected in the presence of Deputy Director WAPDA on 11th January
2016. Up till now major parts are one Runner, three Turbine main shafts and four Main Inlet
Valves arrived at site.

Page 129

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.9.2

MONTHLY PROGRESS REPORT


JANUARY 2016

Electrical Works

UNIT No.1

According to DWG#278E54-C3-3039-3040R2 at El.587.2m, ( 32) 36 meters conduits for


lighting system of pit liner embedded.

According to DWG#278E54-C3-3011~3014R2 at El.588.2m, ( 25) 44 meters conduits for


lighting system embedded.

According to DWG#278E55-C3-20-003R3 at El.587.3m, ( 32) 40 meters conduits for


secondary system embedded.

According to DWG#278E54-C3-4039R2, equipment grounding of penstock with 04 pieces of


copper terminals (185mm2) along with 04 sets of copper bolts (16) and connection plates
(10mm) embedded.

UNIT NO.2

According to DWG#278E54-C3-4039R2, equipment grounding of spiral case, 04 pieces of


copper terminals (185mm2) along with 4 sets of copper bolts (16) and connection plates
(10mm) embedded.

UNIT NO.3

According to DWG#27854-C3-3015R2 at El.594.2m, ( 25) 166.5 meters conduits for


lighting system embedded.

According to DWG#278E55-C3-20-012R2 at El.594.2m, ( 25) 87.4 meters conduits for fire


alarm system embedded.

According to DWG#278E55-C3-20-017R5 at El.594.2m, ( 32) 21 meters conduits for


security system embedded.

According to DWG#278E54-C3-2019R2 at El.594.2m, ( 80) 3.6 meters conduits for


secondary system (Distribution Box) embedded.

According to DWG#278E55-C3-20-026R6 at El.584.5m, ( 32) 36 meters, ( 50) 71 meters


and ( 80) 98 meters conduits for secondary system embedded.

According to DWG#278E54-C3-4026 at El.592.765~594.2m, 11 meters (185mm2) copper


conductor laid.

According to DWG#278E54-C3-4020 at El.592.765~594.2m, 25.3 meters (95mm2) copper


conductor laid.

According to DWG#278E54-C3-4026 at El.592.765~594.2m, 280 meters (185mm2) and 15.6


meters (95mm2) copper conductor installed.

According to DWG#278E55-C3-20~005R2 at EL.594.205m, C-channel steel 2.8 meters


(80mm x 43mm x 5mm) and round steel (12, L=200mm) 08 pieces

panel base for

secondary system embedded.

According to DWG#278E54-C3-2032~2040R2 at El.594.210 m, C-channel steel 24.56


meters (80mm x 43mm x 5mm) and round steel (12, L=230mm) 82 pieces panel base for
11KV switchgear embedded.

Page 130

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

According to DWG#278E54-C3-2032~2040R2 at El.594.210 m, C-channel steel 16 meters


(80mm x 43mm x 5mm), 6.08 meters (100mm x 43mm x 5.3mm) and round steel (12,
L=230mm) 72 pieces panel base for 400V switchgear and station transformer embedded.

UNIT NO.4

According to DWG#278E54-C3-4039R2, equipment grounding of penstock with 04 pieces of


copper terminals (185mm2) along with 04 sets of copper bolts ( 16) and connection plate
(10mm) embedded.

BUS BAR TUNNEL NO.3

According to DWG#278E54-C3-4013 at El.592.765~594.2m, 25.3 meters (95mm2) copper


conductor laid.

According to DWG#278E55-C3-20-023R0 at El.594.2m, (32) 06 meters conduits for fire


alarm system embedded.

According to DWG#278E55-C3-20-028R1 at El.594.2m, (40) 10.8 meters and (50) 5.4


meters conduits for Air Condition system embedded.

According to DWG#278E54-C3-3004R7 at El.594.2m, (50) 22 meters and (100) 23.7


meters conduits for Secondary system embedded.

TRANSFORMER HALL

Six (06) main power transformers have been shifted in transformer hall from store yard with
impact recorders fitted.

CONTROL BUILDING

According to DWG#278E54-C3-3035~3038R3 at EL.662.45m, ( 75, L=220mm) 03 pieces


PVC pipe for lighting system embedded.

According to DWG#278E55-C3-20~032R3 at EL.662.4m, ( 75, L=220mm) 2 pieces PVC


pipe for communication system embedded.

SWITCHYARD

According to DWG#278E54-C3-3041R0 at El.661.70m, ( 75, L=220mm) 01 piece in the


03rd part of cable trench TR-1/ (14~15) and ( 75, L=220mm) 02 piece PVC pipe in the 05th
and 07th part of cable trench TR-1/ (09~10) for lighting system embedded.

According to DWG#278E54-C3-3041R0 at El.661.70m, ( 25) 4.5 meters conduits for


lighting system in SS-F3/M-8, SS-F3/H-8 and SS-F1/B-8 embedded.

According to DWG#278E55-C3-20~041R5 at EL.662.21m, C-channel steel 2.8 meters


(80mm x 43mm x 5mm) and round steel (12, L=200mm) 08 pieces

panel base for

secondary system installed in the 5th part of cable trench TR-1/(14~15).

According to DWG#278E55-C3-20~041R5 at EL.662.21m, C-channel steel 8.4 meters


(80mm x 43mm x 5mm) and round steel (12, L=200mm) 24 pieces

panel base for

secondary system installed in the 2nd, 5th and 7th part of cable trench TR-1/ (09~10).

Page 131

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

According to DWG#278E55-C3-20~041R5 at EL.661.70m, ( 115, L=220mm) 03 pieces


PVC pipe for secondary system in the 03rd and 05th part of cable trench TR-1/ 14~15
embedded.

According to DWG#278E55-C3-20~041R5 at EL.661.70m, ( 115, L=220mm) 32 pieces,


(125, L=220mm) 10 pieces and ( 75, L=220mm) 02 pieces PVC pipe in the 01st, 02nd,
03rd, 4th, 06th and 07th part of cable trench TR-1/ (09~10) embedded.

According to DWG#278E55-C3-20-041R5 at El.661.70m, (125, L =220mm) 03 pieces and


(115, L=220mm) 06 pieces and (115, L=220mm) 03 pieces PVC pipe in the 06th part of
cable trench TR-1/ (04~05) for secondary system embedded.

According to DWG#278E66-C3-02-5.01~5.04/PO-15973 at El.662.2m, Anchor bolts


structure including flange, bolts and nuts for the foundation of SS-F4/C-13 and SS-F1/B-8
embedded.

According to DWG#278E54-C3-4036~4037 at EL660.35~662.0m, 20 meters (185mm2)


copper conductor in the cable trench TR-1/ (9-10) laid.

According to DWG#278E54-C3-4036~4037 at EL660.35~662.0m, 1822.6 meters (185mm2)


copper conductor and 12 pieces of vertical grounding rod (DN=20mm, L=2500mm) in
grounding gird mess location A-S/32~39 laid.

Assembly and installation of 4 legs Steel Gantry Structure SS-F1/B-24 and B-33 has been
completed.

Assembly

and

installation

of

Truss/beam

between

Steel

Gantry

Structure

SS-F1/B-33 and SS-F3/H-33, SS-F3/H-24 and SS-F3/M-24 have been completed.

Assembly and installation of Truss/beam between Steel Gantry Structure SS-F4/B-24 and
SS-F3/H-24 is in progress.

Request for commencement of the Equipment Installation in outdoor switchyard was


submitted by Contractor as per request no. NJ-KG-020 dated 13-01-2016 and signed by
NJC.

Installation of Steel Support Structure of Current Transformers (27 No.) have been
completed.

Placing of Current Transformers (02 No.) on their steel support structure done.

WAPDA COLONY

Inspection of PVC wall conduits in category-V (House No 23, 24) first floor carried out.

Inspection of slab conduits in dispensary carried out.

Insulation testing (meggering) of cables in category-III (House No. 1 to 3) carried out.

HFO

Export energy meters (all sites) were calibrated by team of National Transmission and
Dispatch Company (NTDC).

Page 132

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

ISSUED FCR

FCR:FCR-C3-301 issued on 30-12-2015 regarding lighting layout and embedded parts for
main power house unit no.2 and 3 on El.589.50m, reference DWG# 278E66-C3-3016R2 ,
PO-14706.

ISSUED DCN

DCN-C3-307 issued on 13-01-2016 regarding Excitation System, reference Contract


Document Vol-2(D), Clause 2.6.64 and 2.6.6.5.

SITE INSTRUCTION

EMH-E-24 issued on 20-01-2016 regarding Warranty Certificate for Switches / Dimmers in


WAPDA colony.

EMH-E-25 issued on 20-01-2016 regarding Fire Alarm System in Rest House.

MATERIAL INSPECTION

The shipment under bill of lading No.155900F01, 01 main power transformer has arrived at
site and inspected.

The shipment under bill of lading No.QSKN6042639, containing 24 marshalling cubicles of


525KV Switchgear have arrived at site and inspected.

The shipment under bill of lading No.156101F01, containing parts of stator core, 01
generator shaft, parts for rotor assembly, upper clamping plate of rim, parts for upper
bracket, parts for thrust bearing, auxiliary accessories, spare parts and tools have arrived at
site and inspected.

5.9.3

Visits/Meetings

VISITS:

On Friday 08 January 2016, WAPDA delegation of M&S department visited site C3 to


monitor the physical work progress of the project.

On 20 January 2016, Chairman WAPDA accompanied with CEO (NJHPC) and PM (NJC)
visited switchyard and power house and was briefed about work progress.

MEETING

On 28 December 2015, 4, 11 & 19 January 2016, M/E internal coordination meeting was
held in the office of CRE-EMH wherein various M&E issues discussed.

On 08 and 22 January 2016, scheduled Fortnightly Coordination Meeting was held with the
M/E Contractor at Contractors Conference Hall, wherein various issues discussed.

Page 133

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

5.9.4

MONTHLY PROGRESS REPORT


JANUARY 2016

Site Photographs E&M Works Site C3

Assembling of Main Inlet Valve (MIV) for Unit No.


4 Erection bay 2

Insulation Wrapping for branch pipe 377mm


to Water Tank Unit No. 4

Verticality/Concentricity Check of Stator


Roundness Measuring Device Unit No. 4

Pressure test of cooling water pipes for


turbine guide bearing Unit No. 1

I section steel for foundation of lower guid


bearing Unit No. 3

Verticality & gap adjustment of stator key bars


Unit No. 4

Page 134

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Visit of Chairman WAPDA along with CEO


(NJHPC) & NJC officials-Switchyard

Page 135

MONTHLY PROGRESS REPORT


JANUARY 2016

Visual inspection of welding for Stator Key Bars


Unit No.4

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

QUALITY ASSURANCE / QUALITY CONTROL

This month the Contractor placed 35,488m of concrete, shotcrete and RCC in the permanent
works at C1. This is the second month in a row where production has exceeded 30,000m, the
local rock suppliers and aggregate crushing plants managed to keep up with this production. At C3
complicated concrete placements took place in the penstock manifold area and normal headrace
tunnel lining concrete placements continued.

Pump able mortar mixes were trailed for filling large cavities where they might have arisen in the
tunnel crown.

6.1

Site C1:

Materials - The Contractor continues to blend one truck load of greenstone rock with one truck load
of SS1 at their Spoil B crusher.

Greenstone quarry widening of the first bench is taking place.

Summary of the compressive strength results carried out during the month are given in the table
below. The shotcrete result is based on six 6 sets of results.

Page 136

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Lot C1 - A summary of compressive strength test results based on January 2016 monthly report
Specified MSA Batch
Mean
Standard
compressive
Plant strength for Deviation for
strength
January
January
ACI 214-11 notation fc' age
X'
s'

Concrete Class

MPa days mm

1%
1 in 100 chance of falling below fcr-z
fcr'

X'-fcr'

MPa

MPa

15.6

0.7

1.8
2.2
2.3
2.1

1.65
1.65
1.65
1.65
1.65
1.65

23.0
23.6
23.8
23.5

1.7
1.1
1.2
1.9

No action required

MPa

MPa

16.3

2.2

24.7
24.7
25.0
25.4

z'

Comment

Frequency
of use

5%
1 in 20 chance of falling below fcr-z
z'

fcr'

X'-fcr'

MPa

MPa

2.33
2.33
2.33
2.33
2.33
2.33

17.1

-0.8

24.2
25.1
25.4
24.9

0.5
-0.4
-0.4
0.5

2.33
2.33
2.33

34.0
34.4
34.2

0.9
-0.1
1.4

Often
Decrease cement Often

2.33
2.33
2.33

34.9
33.7
34.2

-0.5
2.0
1.4

Often

2.33

44.8

-5.0

2.33
2.33
2.33

23.8
19.3

-9.5
-5.2

Class F Blinding (70 to 110)


Class F Blinding pump (120 to 180)
Class A 63mm agg
Class B telebelt (30 to 70)
Class B mixer truck
Class B pumped

12
12
20
20
20
20

28
28
28
28
28
28

38
63
38
38
38

M
M
M
M
M
M

No action required Often

Class C telebelt (30 to 70)


Class C dump truck
Class C (70 to 110)

30
30
30

28
28
28

38
63
38

M
M
M

34.9
34.3
35.6

1.7
1.9
1.8

1.65
1.65
1.65

32.8
33.1
33.0

2.1
1.2
2.6

No action required Often

Class C pump (180 to 240) tunnel


Class C pump (180 to 240) tunnel
Class C pump (100 to 140) tunnel

30
30
30

28
28
28

19
38
38

A1
A1
A1

34.4
35.7
35.6

2.1
1.6
1.8

1.65
1.65
1.65

33.5
32.6
33.0

0.9
3.1
2.6

No action required Often

Shotcrete steel fibre (small pop)

35

28

10

A1

39.8

4.2

1.65

41.9

-2.1

Improve SD

RCC Bedding concrete


RCC 20% Slag (7day)
RCC 50% Slag (7day)

17
17
17

90
90
90

19
63
63

M
M
M

14.3
14.1

2.9
1.0

1.65
1.65
1.65

21.8
18.7

-7.5
-4.6

90 day strength ?

No action required
No action required
No action required

Seldom
Often
Often
Often
Often

No action required Often


Decrease cement

Often

Decrease cement

Seldom
Often
90 day strength ? Often

Regarding the rock-fill dam clay core, the Contractor is busy establishing quality control procedures
at various borrow pits. The Engineer has explained to them that rejecting out of spec material at
the dam site is wrong, its better to reject and isolate the material at the concerned borrow pit.

6.2

Site C2

NJC took steps to ensure the Contractor at Adit 4 batch plant stopped storing their cylinder test
specimens out in the cold. They were immediately instructed to comply with ASTM C 31 and store
their cylinders in a heated box.

6.3

Site C3

At C3 the multi-tester broke down, spare parts had to be flown in from China, this machine and the
one at C1 will be recalibrated as soon as the machine is back in operation. The Contractor
continues to use a small mobile pump to apply shotcrete in confined spaces in and around the
powerhouse where access by shotcrete jumbo is no longer possible.

6.4

Quality Management look ahead

SUBJECT
Quality Plan

STRATEGY
A workable plan must still be submitted by both Civil and E&M
Contractors, the Contractor has shown no willingness to

Page 137

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

compile such a plan this is despite many reminders. Mr Wang


Wenqiao is heading up the Civil work Contractors team and
Mr Sun Xiangyue is heading up the E&M Contractors team.
An approved plan is in place for TBM work.

Method statements

The Contractor continues to supply method statements; which


are reviewed and discussed. This month the Engineer
commented on Contractors 4

th

revision of their shaft lining

method statement

Laboratory compliance with test

All testing outcomes are constantly reviewed. The Contractor

methods

is only procuring reinforcing steel from PSQCA approved


companies. Both multi-testers have to be calibrated, this work
will be performed by PCSIR

Meetings

At all sites our CREs are habitually raising quality issues


during their meetings.

Paint technology

Two suppliers products were approved for use.

When

painting starts in earnest ICI Dulux will send their trainer to


site.

The Contractor has been asked to establish a well-

trained painting team.


Concrete mix designs

At C1 the Contractor is only using Fauji LA cement. At C2 the


Contractor is experimenting with a 20MPa pump mix.

NCRs potential and actual

Issues flagged up at each site are followed up, resolved or


converted into an NCR.

Material approval

A register of approved materials is in use and regularly


updated by NJC Quality Manager. This month Sika 114
machine grout was approved for use

Document archive

NJCs Document Engineers are archiving all correspondence;


drawings;

site

instructions;

NCRs;

accident

reports;

environmental reports; quality reports; approved material


register and ensuring this information is traceable.

6.5

LABORATORIES

All the laboratories are operational and production tests and quality monitoring tests are being
performed on site. Detail test results for C1, C2 & C3 are given in a separate report.

Laboratory and Field Testing: Status of tests performed at C1, C2 and C3 are shown in Tables
6-1 to 6-3 respectively.

Page 138

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Table 6-1: Field and Laboratory Testing at C1


Sr.
No.

Material Description

Sources &
Location

Test &
Description

No. of
Tests

Test Results
Accept
Reject

Aggregate Testing
1

Aggregate

Site C1

Gradation

171

171

Aggregate

Site C1

Clay Lumps

09

09

Aggregate

Site C1

171

171

Aggregate

Site C1

Sp. Gravity

03

03

Aggregate

Site C1

Unit weight

00

00

Aggregate

Site C1

Flakiness

00

Aggregate

Site C1

Soundness

03

03

Aggregate

Site C1

03

03

Aggregate

Site C1

00

00

62

62

% Passing #
200 Sieve

Water
Absorption
Los Angles
Abrasion
Total Moisture

10

Aggregate

Site C1

Content of
Aggregate by
Drawing

11

Rock Classification

Site C1

Classification

09

09

Sand Testing
1

Sand

Site C1

Gradation

58

58

Sand

Site C1

Specific Gravity

01

01

Sand

Site C1

155

155

Sand

Site C1

04

04

Sand

Site C1

58

58

Sand

Site C1

01

01

Sand

Site C1

04

04

Sand

Site C1

00

00

00

00

00

00

Moisture
Content
Clay Lumps
% Passing #
200 Sieve
Soundness
Organic
Impurities
Unit Weight
Sieve Analysis

River Deposit Material

Site C1

Particle Size
Distribution
Density &

10

River Deposit Material

Site C1

Moisture
Content

Page 139

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Steel Testing
1

Tensile, Yield &

Fazal Steel,

Tensile & Yield

Elongation

Mughal & Pak

Strength

97

97

97

97

97

97

Steel
2

Bend test

Fazal Steel,

Bend Test

Mughal & Pak


Steel
3

Unit weight

Fazal Steel,

Unit Weight

Mughal & Pak


Steel
4

Deformation / Spacing

Fazal Steel,

Deformation /

Mughal & Pak

Spacing

97

97

Tensile

00

00

00

00

07

07

04

04

717

717

540

540

101

101

00

00

Steel
5

Tensile (Couplers)

China

7 Wire Steel Strand

Steel Strand

Galvanizing thickness

Rock Bolts

Galvanizing
thickness

Concrete / Shotcrete / Cement testing


1

Shotcrete

Compressive strength
2

Cores from

Compressive

panels

strength

All works at C1

Compressive

Concrete & RCC

strength

Cylinders
3

Air Content & Density

All works at C1

Air Content

Site C1

Compressive

of Fresh Concrete
Cement (OPC)

Strength
Cement (OPC)

Site C1

Heat of
Hydration

Cement (OPC)

Site C1

Soundness

101

101

Cement (OPC)

Site C1

Setting Time

101

101

Cement (OPC)

Site C1

101

101

Shotcrete

Site C1

Unit Weight

03

03

10

Shotcrete

Site C1

Fiber Content

03

03

00

00

Blaine Sp.
Surface

Flexural
11

Shotcrete

Site C1

toughness of
Shotcrete beam

Page 140

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

12

Grout

Site C1

13

Grout

Site C1

14

Grout

Site C1

15

Grout

16

MONTHLY PROGRESS REPORT


JANUARY 2016

Compressive

01

01

00

00

Viscosity

01

01

Site C1

Density

01

01

Grout

Site C1

Consistency

00

00

17

Concrete / Shotcrete

Site C1

Mix Design

00

00

18

Concrete / Shotcrete

Site C1

02

02

19

Concrete

Concrete

540

540

20

RCC

RCC

164

164

21

Concrete

Concrete

00

00

22

RCC

RCC

137

137

00

00

02

02

02

02

02

02

00

00

00

00

00

00

00

00

00

00

00

00

Strength
Bleeding /
Expansion

Permeability /
Blocks
Air Content %
Compaction
Test
Setting time of
concrete
Vebe Time
Hard Fill

23

Hard Fill

Hard Fill

Concrete
Compaction

24

25

Structural Backfill

Structural

(Drainage Trench)

Backfill

Structural Backfill

Structural

Moisture

(Drainage Trench)

Backfill

Content

Structural Backfill
26

(River Deposit
Material)

Structural
Backfill

Compaction

Gradation

Asphalt / Concrete
1

Gradation

Bridge

Extraction

Bridge

Bulk Sp. Gravity

Bridge

Max Sp. Gravity

Bridge

Air Voids

Bridge

Flow

Bridge

Page 141

New Nauseri
Bridge
New Nauseri
Bridge
New Nauseri
Bridge
New Nauseri
Bridge
New Nauseri
Bridge
New Nauseri
Bridge

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

New Nauseri

Stability

Bridge

Loose Unit Weight &

River Deposit

Moisture Content

Material

Bridge

00

00

00

00

Density /
Moisture
Content

Field Tests
1

Shotcrete & Concrete

Batching plant

Slump

760

760

Shotcrete & Concrete

Batching plant

temperature

760

760

Admixture

China

PH Value

08

08

Admixture

China

Setting Time

08

08

Admixture

China

Specific Gravity/

08

08

00

00

00

00

00

00

00

00

Gradation

00

00

FDT

00

00

00

00

09

09

09

09

00

00

00

00

Density
6

Setting Time of

Setting Time of

Setting Time of

Concrete

Concrete

Concrete

Bleeding by Blaine &

Concrete

Concrete

China

Density

Sieving
8

Admixture

Soil
1

Green Stone Quarry

Moisture

Material

Content

Green Stone Quarry


Material
Field Density test

(Sand/Water
Replacement Method

Soil / Clay

Soil / Clay

Soil / Clay

Soil / Clay

Structural
Backfill

Moisture
Content
Double Hydro
Meter
Hydro Meter
Moisture
Density
Water Stop

01

PVC water stop Send to PSQCA for physical testing


Stone / Rock

01

Compressive Strength

00

00

02

Petrography Test of Rock

00

00

03

Green Stone Sieve Analysis

00

00

Page 142

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Batching Plant
01

Calibration of batching plant

01

01

02

Calibration of Oven

00

00

03

Calibration of Vibrating Table

00

00

04

Calibration of Compressive Strength Machine

00

00

00

00

00

00

00

00

Sulphur Mortar
01

Sulphur Mortar Compressive Strength


Silica Fume

01

Silica Fume
Granite Block

01

Granite Block Compressive Strength

Table 6-2: Field and Laboratory Testing at C2


Sr.
No

Material

Source of
Sample

Test Result

Standard

This
month

Gradation

ASTMC-136

12

12

Specific Gravity

ASTMC-127

Clay Lumps

ASTMC-142

Absorption

ASTMC-127

Unit Weight (Loose)

ASTMC-29

Unit Weight (Rodded)

ASTMC-29

Passing # 200

ASTMC-117

12

12

Specific Gravity

ASTMC-127

Gradation

ASTMC-136

12

12

Unit Weight (Loose)

ASTMC-29

Unit Weight (Rodded)

ASTMC-29

Los Angeles Abrasion

ASTMC-131

BS-812

Passing # 200

ASTMC-117

12

12

Specific Gravity

ASTMC-127

BS-812

Unit Weight (Loose)

ASTMC-29

Unit Weight (Rodded)

ASTMC-29

Gradation

ASTMC-136

12

12

Los Angeles Abrasion

ASTMC-131

Passing # 200

ASTMC-117

12

12

Gradation

ASTMC-136

16

16

Specific Gravity

ASTMC-128

Test Conducted

Accept

Reject

1. Aggregate Testing

ii

Coarse Agg 5-8


mm

Batching Plant

Coarse Agg.5 19 mm

Flakiness & Elongation


Index
Batching Plant

Flakiness & Elongation


Index
iii

iv

Coarse Agg.1938mm

Fine Agg. (Sand)

Batching Plant

Page 143

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Absorption

ASTMC-128

Organic Impurities

ASTMC-40

ASTMC-2419

Unit Weight (Loose)

ASTMC-29

Unit Weight (Rodded)

ASTMC-29

Passing # 200

ASTMC-117

16

16

F. M

ASTMC-136

16

16

187

187

ASTMC-42

ASTMC-42

ASTMC-42

13

13

ACI-506R

28

28

200

200

200

200

31

31

10

10

10

10

Sand Equivalent

2. Concrete & Cement/Slag


i

Cement / Slag

Stock

Soundness, Compr.
Strength
Strength C-30/38mm

ii

Concrete

FDT/ RCC Concrete


Compressive Strength (3
days)
Compressive Strength (7
days)
Compressive Strength
(28 days)
Combined Gradation

iv

Shotcrete

A3 & A4

ASTMC191
ASTM C-39
ASTM D1556

Fiber Content
Slump

Temperature
Moisture content of
Aggregate
Flexural Toughness

ASTM C143
ASTM C143
ASTM C566
ASTM C1018

3. Admixture
Setting Time

Accelerator BASF
i

Meyco

SA-

Stock

160

Specific Gravity

ASTMC1102
ASTMC1102

4. Steel
Steel Grade 60
i

Rock Bolt / Wire

Stock

Yield,Tensile, elongation

ASTM A-

and Bend Test

615

Mesh

Page 144

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Table 6-3: Field and Laboratory Testing at C3


Sr.
No.

Material Description

Source &
Location

Test & Description

Test Results

No. of
Tests

Accept

Reject

30

30

30

30

30

30

30

30

Aggregate Testing
1

Crushed Sand

SS-1

Grading and FM

SS-1

Sp. Gravity &


absorption

SS-1

Clays Lumps &


Friable particles

SS-1

Organic Impurities

SS-1

Mat. Finer than


75m Sieve

Aggregate (5 To 8mm)

SS-1

Grading

SS-1

Sp. Gravity &


absorption

SS-1

Clays Lumps &


Friable particles

SS-1

Mat. Finer than


75m Sieve

SS-1

L.A. Abrasion

SS-1

Flakiness &
Elongation

Aggregate (5 To 19mm)

SS-1

Grading

SS-1

Sp. Gravity &


absorption

SS-1

Clays Lumps &


Friable particles

SS-1

Mat. Finer than


75m Sieve

SS-1

L.A. Abrasion

SS-1

Flakiness &
Elongation

Aggregate (19 To 38mm)

SS-1

Grading

SS-1

Sp. Gravity &


absorption

Page 145

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Sr.
No.

Source &
Location

Material Description

SS-1

MONTHLY PROGRESS REPORT


JANUARY 2016

Test & Description


Clays Lumps &
Friable particles

SS-1

Mat. Finer than


75m Sieve

SS-1

L.A. Abrasion

SS-1

Flakiness &
Elongation

Steel Fibre Shotcrete

Shotcrete Cores from Panel

Compressive
Strength

In situ Cores

Compressive
Strength

Concrete Cylinder

Cement

Shotcrete Beams

Flexural Toughness

Class B

Compressive

(C-20)

Strength

Class C

Compressive

(C-30)

Strength

Maple Leaf & Fauji

Compressive
Strength

Grout

Steel Bar

Accept

Reject

39

39

15

15

36

36

993

993

294

294

Maple Leaf & Fauji

Consistency

34

34

--

Maple Leaf & Fauji

Setting Time

34

34

Maple Leaf & Fauji

Soundness

34

34

Maple Leaf & Fauji

Fineness by Blain

30

30

Maple Leaf & Fauji

Fineness by

30

30

Sieving
2

Test Results

No. of
Tests

Grade-30

Compressive

And Grout

Strength

Fazal , Pak & Agha Steel

Elongation

162

162

Fazal , Pak & Agha Steel

Unit Weight

162

162

Page 146

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Sr.
No.

Source &
Location

Material Description

MONTHLY PROGRESS REPORT


JANUARY 2016

Test & Description

Anchor Bolts

162

162

Fazal, Pak & Agha Steel

Deformation

162

162

Fazal, Pak & Agha Steel

Yield & Ultimate

162

162

Density

18

18

pH value

18

18

Solid content

18

18

Batching Plant

Temperature

223

223

Batching Plant

Slump

223

223

Batching Plant

Fibre Content %

Batching Plant

Temperature

1770

1770

Batching Plant

Slump

1770

1770

Batching Plant

Air %

260

260

Switch Yard Embankment

Field Density

Switch Yard Embankment

Gradation

Mughal Steel

Elongation

Mughal Steel

Yield & Ultimate

6.6

Water Reducing (WRA) Chinese JG-2H

Shotcrete

Concrete

Soil

Reject

Bend

Strength Test

Accept

Fazal , Pak & Agha Steel

Strength Test
2

Test Results

No. of
Tests

NON-CONFORMANCE REPORTS

The Engineer is issuing Non-Conformance Reports in an attempt to monitor the corrective action of
problems as well as to assist in the prevention of similar problems in the future. The status of these
Non-Conformance Reports are given in Table 6-4.

Page 147

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

SITE C1:
Table 6-4: Status of Non-Conformance Reports
Total NCRs issued to date

205 (Excluding NCR-073 & NCR-106


which were allotted numbers but not
issued)

NCR issued during this month

09 (NCR-199, 200, 201, 202, 203, 204,


205 & 206)

NCR closed during this month

03 (NCR 163, 171, & 202, )

No. of Closed NCRs

171

No. of open NCRs

34

NCRs

NCR No.

Dated

Description

Compliance

Remarks

Area C1
C1-121

29 June 2013

Dam Spillway Block 5-4-1 Contractor has not Action Awaited


given the proposal
to rectify the
problem

C1-127

8 November
2013

Repair of drainage gallery


concrete in spillway

Contractor has not Action Awaited


given the proposal
to rectify the
problem

C1-136

27 July 2014

Demage of the Skin Plate


surface Elevation 974.66

Contractor has not Action Awaited


given the proposal
to rectify the
problem

C1-155

17 January
2015

Stilling Basin Block 5-1-5

C1-158

04 February
2015

Contractor has not


given the proposal
Main batching & crush plant
Action Awaited
to rectify the
problem

01 April 2015

Contractor has not


Installation of Granite
given the proposal
Blocks in Spillway Blocks 5Action Awaited
to rectify the
1-3, 5-2-3 & 5-3-3
problem

01 April 2015

Upstream spillway
Protection slab (P5) Contractor has
Closed on
Concrete suspended due to rectify the problem 05-Jan-2016
inundation

C1-164

13 April 2015

EMH Not adjustable Seals


for radial gates

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

C1-166

16 April 2015

Blocked Conduits at Pier


P5-6

Contractor has not


Action Awaited
given the proposal

C1-162

C1-163

Page 148

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

NCR No.

Dated

Description

MONTHLY PROGRESS REPORT


JANUARY 2016

Compliance

Remarks

to rectify the
problem

17 April 2015

Stilling Basin and Debris


Channel (required
compressive strength not
achieved)

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

21 April 2015

Installation of drainage
pipes in right retaining wall
at Debris Channel at Block
6-4, 6-5 & 6-6

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

C1-169

04 May 2015

Curtain Grouting at Left


Abutment of Dam

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

C1-171

26 May 2015

C1/EMH-HPU Bed Storage Contractor has


Closed on
Conditions
rectify the problem 13-Jan-2016

27 May 2015

C1/ EMH-Dirt Inside Radial


Gate # 3's HPU

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

03 June 2015

C1/HPU # 3 Electrical
Issues

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

14-Aug-15

Debris Channel-Right end


retaining wall (Block 6-6)
and Block P1-S1 D/S
Retaining wall

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

21-Aug-15

C1 Electrical Issues

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

25-Aug-15

Flushing Gallery Part 2


Walls El.984.65~987.46 Ch
D/S +52.0~D/S 68.75 L/B57.2 L/B-64.2

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

04-Sep-15

Concrete Works at Access


Gallery in Spillway Area

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

11-Sep-15

Poor performance of
crushing plants(washing
arrangements and Sieving
Mechanism)

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

C1-189

18-Sep-15

Conduits Bed Cutting with


no intimation

Contractor has not


given the proposal
Action Awaited
to rectify the
problem

C1-190

24-Oct-15

Rusted Elements In Radial


Gate # 2 & 3

Contractor has not


Action Awaited
given the proposal

C1-167

C1-168

C1-172

C1-174

C1-181

C1-183

C1-184

C1-187

C1-188

Page 149

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

NCR No.

Dated

Description

MONTHLY PROGRESS REPORT


JANUARY 2016

Compliance

Remarks

to rectify the
problem

C1-191

Excavation for RCC U/S


River Training Works
El.972.0

Contractor has not Action Awaited


given the proposal
to rectify the
problem

09-Nov-15

Debris Channel Block 6-2

Contractor has not Action Awaited


given the proposal
to rectify the
problem

10-Nov-15

Contractor has not Action Awaited


C1/EMH-Material on Soil G- given the proposal
Store
to rectify the
problem

28-Oct-15

C1-193

C1-194

C1-195

26-Nov-15

C1-196

10-Dec-15

C1-197

Contractor has not Action Awaited


19 mm crush at Crush Plant given the proposal
#1
to rectify the
problem
Intake Block-1 & 2 - Poor
workmanship and Survey
control

Contractor has not Action Awaited


given the proposal
to rectify the
problem

09-Dec-15

Deviation in Alignment in
Invert Lining concrete at
U/S Soft Ground (Ch:
0+027~0+038)

Contractor has not Action Awaited


given the proposal
to rectify the
problem

C1-199

22-Dec-15

Safety Conditions in Head


Race Tunnel U/S During
Concrete Lining at Ch:
0+018~0+024

Contractor has not Action Awaited


given the proposal
to rectify the
problem

C1-200

27-Dec-15

Muddy / Unclean Water


Used by the Contractor for
Rock Bolts Grouting in the
Tunnel

Contractor has not Action Awaited


given the proposal
to rectify the
problem

C1-201

28-Dec-15

Big Deviation in Alignment


of Both Left and Right Walls
of Lining Concrete at U/S
(Soft Ground)

Contractor has not Action Awaited


given the proposal
to rectify the
problem

C1-202

04-Jan-2016

C1-EMH- Bad Storage


Conditions of Electrical
Equipment at G Store

Contractor has
Closed on
rectify the problem 13-Jan-2016

C1-203

19-Jan-2016

Contractor has not Action Awaited


Sedimentation Basin D.
given the proposal
Block 11 (Base Slab P11-1,
to rectify the
Elevation 982.61~985.11
problem

C1-204

19-Jan-2016

C1-205

19-Jan-2016

Safety Health and


Environment

Contractor has not Action Awaited


given the proposal
to rectify the
problem

Safety Health and

Contractor has not Action Awaited

Page 150

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

NCR No.

Dated

C1-206

23-Jan-2016

C1-207

25-Jan-2016

MONTHLY PROGRESS REPORT


JANUARY 2016

Description

Compliance

Remarks

Environment

given the proposal


to rectify the
problem

Poor Lining Condition at


U/S Headrace Tunnel (Soft
Ground) Ch:
0+011.0~0+005.0

Contractor has not Action Awaited


given the proposal
to rectify the
problem

Upstream Spillway
Protection Slab P5 & S6

Contractor has not Action Awaited


given the proposal
to rectify the
problem

SITE C2:

NCRs

Total NCRs issued to date

197

NCR closed during this reporting period

04

No. of closed NCRs

181

No. of Open NCRs

16

NCR No.

Issue
Date

NCR-C2-050

14-Dec-12

CRACKS & HANGING SC PLATES

NCR-C2-139

14-Feb-14

Access Adit A4 - Remedial Works

NCR-C2-142

30-Oct-14

C2-696 - 50 % Core Sample Failed due


to Extra Shotcrete Rebound.

8-Aug-14

TBM 697 Tunnel - Replacement of


Defective Construction Joint b/w Invert
& Walls & improvement of
Workmanship.

NCR-C2-150

NCR-C2-157

16-Dec-14

Description

Concrete Lining in HRTTR from


T3~T3aR.

NCR-C2-164

30-Mar-15

SL - Contact of Roller with Stiffener


Ring and Cane.

NCR-C2-176

23-Jun-15

A/G / Electrical - Metering of Electricity


at Lot C2.

Page 151

Contractor
Action
Contractor has
not given the
proposal to
correct NCR
Contractor has
not given the
proposal to
correct NCR
Contractor has
not given the
proposal to
correct NCR
Contractor has
not given the
proposal to
correct NCR
Contractor has
not given the
proposal to
correct NCR
Contractor has
not given the
proposal to
correct NCR
Contractor has
not given the
proposal to
correct NCR

Status

Action
Awaited

Action
Awaited

Action
Awaited

Action
Awaited

Action
Awaited

Action
Awaited

Action
Awaited

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

NCR-C2-181

21-Aug-15

Site A3, Tunnel T3L~T3aL, Sta.


D3L+4023.0 ~ 4027.1 - Several
Violations during Tunnel Excavation &
Support.

NCR-C2-182

22-Aug-15

Site A3, Tunnel T3L~T3aL, Sta.


D3L+4023.0 ~ 4027.1 - Slow Reaction
& Mishaps during Face Instability.

NCR-C2-186

10-Sep-15

A3, T3R~T3aR, STA D3R+4055.4 ~


4058.4 - Bad SFR Spraying Practices

NCR-C2-191

30-Oct-15

Exposed Rock Mass at Tunnel Feet Poorly Spraying Practices - Initial


Support Defects.

18-Nov-15

Site A3, Tunnels 06~T3aL &


T3aR~T3bR (A3)
Mucking/Blasting During Fully Damaged
Ventilation, Discarding Engineer's
Instructions.

Contractor has
not given the
proposal to
correct NCR

Action
Awaited

9-Dec-15

Site A3, X-Cut No. 05 (XC5)


Water Line Supply Leakages in XC5 &
Adjacent HRT,s.

Contractor has
not given the
proposal to
correct NCR

Action
Awaited

Contractor has
not given the
proposal to
correct NCR

Action
Awaited

Contractor has
not given the
proposal to
correct NCR

Action
Awaited

Contractor has
not given the
proposal to
correct NCR

Action
Awaited

NCR-C2-193

NCR-C2-194

NCR-C2-195

NCR-C2-196

NCR-C2-197

22-Dec-15

4-Jan-16

24-Jan-16

Site A3, Tunnel T3aR~T3bR (A3), STA


D4R+39.6 - Poor Construction
Practices: Inadequate Dewatering &
Contamination of Accelerator Pod with
Water.
Site A3, Tunnel T3aL~T3bL (A3), STA
D4L+42.9 - Poor Blasting Safety
Practices: Blasting a Tunnel Face
without Prior Warning to Adjacent
Tunnel
Lack of Safety Measures / Precautions
during Working on Heights in Tunnels.

Contractor has
not given the
proposal to
correct NCR
Contractor has
not given the
proposal to
correct NCR
Contractor has
not given the
proposal to
correct NCR
Contractor has
not given the
proposal to
correct NCR

Action
Awaited

Action
Awaited

Action
Awaited

Action
Awaited

SITE C3:

NCRs

Total NCRs issued to date

418

No. of closed NCRs

375

No. of Open NCRs

43

Area C3
C3-257

13 May 2014

Powerhouse erection bay # 1


at El. 600.50m- Top surface
finishing not meeting

Page 152

Contractor has not Action Awaited


given the proposal
to correct NCR

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

permissible tolerance
C3-258

13 May 2014

Transformer Hall Entrance


slab at El. 600.50m- Top
surface finishing not meeting
permissible tolerance

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-268

19 July 2014

C3- A7 Spoil Dump

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-274

06 August 2014

C3-Transformer Hall HVAC


Room- Bulging of concrete of
columns due to opening of
shutters

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-299

23 September
2014

C3 - Lack of PPE underground Contractor has not Action Awaited


given the proposal
to correct NCR

C3-315

09 December
2014

C3 Low Electricity Voltages


in Office Premises

C3-317

06 February 2015 C3 Tailrace Tunnel


Dewatering pipe in Adit A7

C3-335

4 May 2015

C3 Headrace A5-Hydraulic
Oil as mould released in Arch
Shutter

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-351

15 June 2015

C3 Transition of Tailrace
Tunnel to outlet structure

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-353

29 June 2015

C3 - Headrace Tunnel A5

C3-359

6 July 2015

C3 - Penstock # 2 from
Contractor has not Action Awaited
beginning to TP reinforcement given the proposal
to correct NCR

C3-361

11 July 2015

C3 - Construction and
Contractor has not Action Awaited
backfilling of internal Retaining given the proposal
Walls and dewatering in
to correct NCR
WAPDA Residential Colony

C3-366

6 August 2015

C3 A6 Tailrace

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-371

13 August 2015

C3 A7 Tailrace Tunnel
Access Road

Contractor has not Action Awaited


given the proposal
to correct NCR

Page 153

Contractor has not Action Awaited


given the proposal
to correct NCR
Contractor has not Action Awaited
given the proposal
to correct NCR

Closed on 22-012016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

C3-378

28 August 2015

C3 - Permanent WAPDA
Colony Chatter Kalas

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-379

5 September
2015

C3 - Tailrace A6

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-387

23 September
2015

C3-525 KV Switchyard
Equipment

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-400

23 November
2015

C3 A6

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-401

23 November
2015

C3 A7

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-405

27 November
2015

C3 - A7 Tailrace

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-406

28 November
2015

C3 - A7 Tailrace

Closed on 25-012016

C3-407

28 November
2015

C3 - A5 Headrace

Closed on 25-012016

C3-408

1 December 2015 C3 - Laying of Internal


sewerage line for CAT-III
house and roof treatment for
CAT-IV houses in WAPDA
Residential Colony

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-409

3 December 2015 C3 - Penstock 3

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-410

7 December 2015 C3 - Headrace Surge Branch


Junction Foundation

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-411

8 December 2015 C3 - Headrace Manifold S2

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-412

11 December
2015

Paint work on Rough and


Contractor has not Action Awaited
uneven surfaces in the houses given the proposal
of WAPDA Residential Colony to correct NCR

C3-413

10 December
2015

C3 - Headrace Manifold S3

Page 154

Contractor has not Action Awaited


given the proposal
to correct NCR

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

C3-414

10 December
2015

C3 - Headrace Manifold
Tunnel Rebars

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-415

10 December
2015

C3 - Headrace Wall & Crown


Lining

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-416

14 December
2015

C3 - Solid Blocks for manholes Contractor has not Action Awaited


in WAPDA Colony
given the proposal
to correct NCR

C3-417

16 December
2015

C3 - Powerhouse Unit-4 Lower Contractor has not Action Awaited


bearing bracket Foundation
given the proposal
to correct NCR

C3-418

23 December
2015

C3 - A8 Surge Tunnel

C3-419

8 January 2016

C3 Electrical Safety in
Tailrace Tunnel

C3-420

11 January 2016

C3 - Headrace Wall & Crown

C3-421

11 January 2016

C3 - Headrace Wall & Crown

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-422

15 January 2016

C3 Tailrace A6

Contractor has not Action Awaited


given the proposal
to correct NCR

C3-423

19 January 2016

C3 A6 Tailrace

C3-424

21 January 2016

C3 A7 Tailrace

Page 155

Closed on 16-012016
Contractor has not Action Awaited
given the proposal
to correct NCR
Closed on 22-012016

Closed on 25-012016
Contractor has not Action Awaited
given the proposal
to correct NCR

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

HEALTH, SAFETY & ENVIRONMENT

The NJC Environmental Monitor is regularly monitoring the Environmental Management Plan
(EMP) at site for which he generates weekly assessment reports. Contractor is provided with a
copy of this report whereby he is brought into notice of the deficiencies in his Safety, Health and
Environment arrangements at site.

7.1

OPERATIONAL HEALTH & SAFETY

7.1.1

Accidents & Incidents

The following incidents/accidents were reported during the month.

C1-001/2016: On Sunday, Jan 03, 2016 at about 16:10 Hrs. Water Heater (Geyser) of Mr.
Huseyin Karaoglan (R.E Tunnel) room was suddenly burst into atmosphere. As a result of
the incident Two Water Geysers (Mr. Huseyin and Mr. Joseph Kovacich room), 15 Windows
Glasses (including window of Mosque 27m away), 4 room doors along with fixed locks, Roof
Ceiling of Mr. Huseyin Karaoglan room, Roof Ceiling of Mr. Joseph Kovacich Washroom and
Mr. Huseyin Karaoglan Sleeping Bed were damaged. The lid of the bursted geyser hit the
dispensary room at about 29m away.
On query to Mr. Miskeen (attendant of Mr. Husseins room), he informed that as Mr. Huseyin
was on leave and expected to arrive today (03-01-2016) he switched on the water geyser at
about 9 Oclock in the morning. During lunch time CRE-C1 informed him that Mr. Huseyin
was not coming today, therefore he switched off the pertinent geyser at 3 Oclock.
Unfortunately this incident took place at about 16:10 hrs. Luckily no injury took place
excepting damage of property.

Possible reasons of Incident:

Faulty geyser.

Automatic system of Thermostat of Geyser not working

No safety valve was install along with Geyser

No regular flushing of mud material inside the Geyser was carried out.

C1-002/2016: On January 12, 2016 at about 1400 Hrs. an accident took place in LHTT near
face during spoil Mucking at Ch: 4+677.5-4+681.5 was in progress.

This accident took place exactly when dumper of CGGC (# 41) was fully loaded and starts to
move outside. Suddenly tie-rod of dumper was broken and dumper was out of drivers
control and struck with wall of tunnel. As a result of this incident door of drivers side

Page 156

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

damaged and driver Mr. Zahid Sarfaraz got minor injuries on his right leg. Fortunately all
other people on site are safe. After first aid treatment at site Injured driver was sent to his
home for rest. The drivers condition is out of danger.

th

C1-003/2016: On Thursday 14 January, 2016 at about 06:30 Hrs. an incident took place at
Contractors Labor Camp (near Nauseri Dam site). According to Contractors (CGGC) Safety
Department A Chinese worker Zhang Bao Hong, working with work team # 03 in night shift,
drank approximately 50g of White Wine after his breakfast and went to sleep/ rest. During
sleep his right foot unconsciously rubbed with his bed, which was made with Iron rebar, and
bruised resulting into profuse bleeding. At about 10:30 Hrs. Mr. Li Gang (roommate of Mr.
Zhang Bao Hong) came back to his dormitory and founded that Mr. Zhang Bao Hong foot
was bleeding plenteously. Mr. Zhang Bao Hong was shifted to C-1 Camp dispensary, where
Dr. Riaz provided first aid and further referred to CMH Muzaffarabad for detail examination.
No serious injury took place to Mr. Zhang except surgical wounds. His condition is better
now.

Site C2:
C2-01/2016: On January 02, 2016, 2:50 pm, one CGGC labour named Muhammad Latif Sheikh
fell from wooden planks height about 3m at TBM Bridge and got injuries on right hand. He was
st

immediately shifted to C2 Dispensary for 1 aid and then shifted to CMH MZD via ambulance for
further treatment and diagnosis. His hand was diagnosed fractured.

C2-02/2016: On January 03, 2016, 09:00 am, Vehicle GO-590 was in Tunnel T3aR~T3bR (A3). It
was in standing condition while a jeep No. 361 collided with it and damaged the left back light.

C2-03/2016: On January 20, 2016, at about 09:00 am an accident took place, when two labours
(Malik Sajeel S/O Muhammad Jameel and Javed Shah S/O Gul Hassan Shah, R/O Thotha) were
removing the ventilation pipes from Adit A4a standing on a platform which was tied/fixed with
bucket of the loader with loose and less quantity of wires. In the meanwhile, when the loader
operator attempted to bring down the bucket towards ground on labour's indication, both the
workers fell to the ground and suddenly after them the loose wires were broken and platform also
fell on them due to jerkiness of the bucket. As a result the workers were intensely injured. They
were immediately brought to C2 infirmary for first aid and then, from there, they both were sent to
CMH MZD for further diagnosis/treatment. Mr. Javeds left leg and jaws were found fracture in his
x-ray report, so he was referred from there to Shifa International Hospital Islamabad for further
treatment. Whereas, Sajeels waist and stomach have some internal injuries, so his treatment is
under review at the CMH MZD.

Page 157

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Action Taken: Contractor has been instructed to use proper methods (according to HSE) of
working on crowns of the tunnel and deploy well trained and authorized drivers/operators for
vehicles/machines.

C2-04/2016:During support work at L1 (Rock Bolt Drilling) near to the Shield, suddenly rock burst
occurred at location 10 to 01 oclock position above the shield. At that time three Pakistani workers
named (Nisar, Amroz & Kamran) and one Chinese person named Qing was injured due to rock
burst, out of four persons one Pakistani named Kamran was severely injured. First aid provided to
injured persons by doctor present on TBM and immediately shifted to Assembly Chamber and
afterwards to C2 infirmary. From C2 all were shifted to CMH MZD for further treatment and
diagnosis. After diagnosing and treatment at CMH, all were discharged and sent to their homes for
rest. It is noted with concern that despite contractor having bullet proof jacket and helmet in store,
workers were not wearing these.

C2-04/2016: On 24th January 2016, at about 1800 hours, vehicle GO-671 driven by Mumtaz
Mughal, hit the C3 police barrier and in a result front screen got damaged. When the driver was
interrogated, he told that when he reached at the barrier the brakes did not work. But after the
accident, the brakes were found normal and the vehicle has not been sent for brakes repairing yet
now.

Site C3: Nil during the reporting period

7.2

ENVIRONMENT

7.2.1

REVIEWS

EIA of NJHP for identifying instruments provided for Environmental Monitors.

PC-1 (Revised) of NJHP fir identifying equipment and instruments provided for Environmental
Monitors.

OECD studies in Risk Management, Norway, and Tunnel Safety (OECD 2006).

7.2.2

FIELD VISITS

7.2.2.1

Site C1:
Environmental team did not visit the site during the reporting period.

7.2.2.2

Site C2:

The Environmental Monitoring Team visited various work sites on Lot-C1 and made following
observations:-

Page 158

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Traffic Plan Implementation at Baily Bridge Majhoi

During the re-construction period of TBM Bridge, the Contractors vehicles were using Baily
Public Bridge at Majhoi. On checking vehicles on the bridge it was noticed that some of the
drivers deployed on heavy vehicles were not carrying their driving license with them. It
appeared to be due to a poor control of the concerned Foreman/ Supervisor of the
Contractor.

Some drivers were carrying expired driving license. This license, however, was valid up to
July 2016. The contractor was advised to keep a check that all the drivers employed on
NJHP work get their driving licenses renewed well in time. No valid driving license should
mean no permission to sit in the driving seat.

Seven workers standing in an open truck were exposed to serious safety risk. On application
of brake or while the truck would take a sharp turn, they could fall within or outside the truck.
The Contractor was advised not to encourage such a risk free lift.

Sitting on the edge of the body of the truck two workers were taking a free ride, but were
exposed to a serious safety risk. On an abrupt brake or while the truck would take a sharp
turn the workers could fall off the edge and be overrun by hind wheel. The Contractor was
advised to avoid such fatal favours.

Passing over Majohi Bridge and heading towards Adit A-3, was a blind vehicle which had
no Registration Plate (Number Plate) and no lights. Inside the tunnel such a vehicle was a
safety risk for everyone moving into the tunnel. The Contractor was advised to dehire such
vehicles.

Even the hind lights of the blind vehicle were missing. The Contractor promised to de-hire
such defective vehicles. Until then, their presence would be marked as hazardous, noncompliance on the score table of the Contractor.

The maximum speed limit for all vehicles on Majhoi Bridge was fixed as a 5km/ hour.
Invariably the Contractors vehicle would not observe that. The Contractor was advised to
train his drivers to respect the speed limit. Any excess would be treated as a safety noncompliance and reflected in the Contractors score table.

A maximum load limit on Majhoi Bridge was 35 tons. Some of the vehicles of the Contractor,
especially those carrying stones to TBM Crushing Plant, were overloaded. Such an excess
could damage Public Baily Bridge, which had been allowed to be used to Contractor, in the
absence of functional TBM Bridge. In case the Baily Bridge collapsed, the Contractor would
lose the only alternate available in the absence of TBM Bridge. A serious public
inconvenience and a strong public reaction would be in addition.

New TBM Workshop at C-2

It was a standing order at the New Workshop C-2 that the shift Foreman would follow four
step SOP before starting the work

Line up the workers and welcome them to work by shaking hands with each one of them.

Checking their PPE. No PPE, no work.

Page 159

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Explain the Task and any safety risks involved in performing the task.

Explain/ demonstrate the safeguard/ Mitigation required to be adapted by the workers


for their safety.

In simulation exercise, the Foreman Wu Suoli demonstrated the implementation of the SOP for
observation by the visiting monitoring team. The demonstration was up to the mark.

At New Workshop availability of clean drinking water had been ensured. But the cooler had
gone too old to present a clean look and required to be replaced.

At New Workshop, the welders working on preparation of wire mesh were well equipped with
proper PPE for their work. They had dark eyes and face covers, overalls, gloves, safety
shoes and small seats (Chawkees). The contractor was advised to maintain that good
practice

At the New Workshop at C-2, Fire Extinguishers after recharging had been placed in a
corner of the Workshop store rather than fixing them at required fire safety points throughout
the Workshop. The contractor was advised to do the needful forthwith because in case of fire
emergency the fire extinguishers lying in the store could not be of an expedient use.

TBM Crushing and Batching Plant at C-2

At TBM Crushing and Batching Plant at C-2 the Foreman Hu Dong satisfactorily
demonstrated in a simulation drill that the pre- work SOP was being followed as follows:

All workers were lined greeted and their PPE was checked. No PPE meant no
work.

The Tasks were explained to individuals or groups as was the case.

Possible Safety hazards involved in the work were explained to each individual or
group.

Safety precautions/ mitigation of such risks were explained/ demonstrated to


workers.

Mr. HU Dong at TBM Crushing and Batching Plant C-2 also explained some risky task
specific safeguards to workers working on crushers. He warned them to save themselves
from Silicosis by using mouth and nose masks. Interestingly, the Chinese Foreman was
conveying his message in broken English and Urdu but the message was delivered loud and
clear due to a high tone and body language adapted by him.

At TBM Crushing and Batching Plant the sedimentation tanks were rather small. Therefore
the tanks had to be cleaned at least twice a week. Whereas the water flowing through the
series of sedimentation tanks was comparatively clean, water from a broken water channel
of the nearby farmer village was bringing in a lot of eroded soil. The RE earthwork promised
to approach the farmers concerned and get the water channel closed.

Page 160

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

At TBM Crushing and Batching Plant C-2, housekeeping had been reasonably improved by
removing the empty bags and storing those at a pre-designated place. Empty cement bags
were auctioned every month by the contractor.

At TBM Crushing and Batching Plant, the drain taking water to the sedimentation tanks had
been kept clean. A marked improvement could be observed as compared to the previous
monitoring visit.

At Crushing and Batching Plant C-2, the handling of Fire Extinguishers is rather poor.
Throughout the visit to the Plant. Only one Foam Fire Extinguisher could be seen which was
not approachable, due to scrap dumped in front of it. That showed a lack of awareness about
the significance and use of Fire extinguishers at the Plant.

At TBM Crushing and Batching Plant at C-2, the cement store storing cement bags, made of
paper, was without a Fire Extinguisher.

The First Aid Box at Crushing and Batching Plant at C-2 was well stocked and a list of
medicines therein, signed by C-2 dispensary Doctor had been displayed on the underside of
the cover of the box. It was reported that following four persons had received First Aid
Training from the Doctor at C-2 dispensary.
1.

Hu Dong (The Foreman).

2.

Guo Baodong.

3.

Wan.

4.

Zhao.

The Contractor was advised to get some Pakistani Workers also trained in First Aid dispensary.

At Crushing and Batching Plant at C-2, the Laboratory scientists had managed their Plant
beds for raising coriander. It was an environmental friendly trend

TBM Bridge under reconstruction

TBM Bridge under reconstruction could be seen from TBM Crushing and Batching Plant.
Previous TBM Bridge was washed away during the 2014 flood in the Jhelum River during
monsoon season. The stated cause was the converging of the river water to pass through a
narrow and lower bridge. On the bridge under reconstruction, four spans have been
maintained as before, but the bridge height had been increased up to the highest flood mark.
An early completion of the TBM Bridge was necessary so as to save the Majohi Baily Bridge
from the heavy load of Contractors vehicle. Reportedly the TBM Bridge would become
functional by the last week of January, 2016.

Protection wall below Nagra habitation

In response to a demand by local inhabitants of Nagra village, which was endorsed by the
Government of AJK, a protection wall below the village on the right bank of Jhelum River
was under construction. The construction site was located opposite to the Steel Liner Factory
reported by the RCC. Protection wall, expected to be completed by the end of February
2016. The protection wall on completion would be 170 m long, 8 m high and 5 m wide at the

Page 161

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

base. Towards the top it would slant on the outside (towards the hill slope). The Space
between the hill slope and the protection wall would be filled with grouted stone masonry. Of
the total concrete as 1700 m, nearly 800m (47%) had been poured till mid January 2016.
The total cost of the structure had been estimated at Rs 40 million.

Kumikote Road, Stone Quarry

Near Gari Dopatta on Kumi Kote road, Contractors (CGGC) stone suppliers at C-2 had
taken land on lease from Revenue Department and on recommendation of Mineral Resource
of the Government of Azad Jammu and Kashmir. Mineral Development Dept. had signed a
contract with stone suppliers Muhammad Suleman Abdullah and Muhammad Abdullah.
Major provisions of the contract had been displayed on a notice board under the direction of
the Deputy Commission Muzaffarbad. There were 5 such sites in the proximity of Kumikote
road.

The Contractors produced an Initial Environmental Examination (IEE) report, for clearance of
their stone extraction operation, from the Environmental Protection Agency (EPA) Azad
Kashmir. The clearance to IEE was granted, but the Environmental Management Safeguard
provided in the IEE were being ignored by the stone extractors/ suppliers. A water channel
(nullah) had been choked with waste soil produced as a result of stone extraction. That was
not the only nullah choked permanently in the area.

The stone quarrying on Kumikote road was providing stones to Crushing Plant at C-2 but all
the same was violating all environmental prescriptions agreed with IEE. The quarry was
closer than 50 m to the road. Hillocks with a slope bigger than 60 were being cut vertically.
The waste soil so produced was not being terraced and planted. The best course would be
that stone quarry should continue in the interest of NJHP, but the stone extractors should
start honouring their commitments in IEE.

Right next to the KumiKote road, the waste soil was being thrown into stream beds. Rain
would take that down during very next monsoon rains to Jhelum River and all these
sediments would end up in the Mangla Dam reservoir nullifying the heavy expenses and
enormous efforts out into Mangla Raising Project. The EPA was rightly concerned against
such a bad practice and had lodged a case against the stone suppliers in the Environmental
Tribunal AJK.

Massive amount of muck material falling into the streamlets of the watershed area adjacent
to kumikote road was increasing in size every day due to heavy blasting and stone extraction
in the area next to Kumikote road. Whereas the idea is not to stop stone supply to CGGC but
to make the stone extraction process environmental friendly as committed in IEE.

Due to environmental unfriendly stone extraction process by CGGCs stone suppliers, the
social conditions of the area adjacent to Kumikote road were also being adversely affected.
Kumikote road is getting narrow, heavy machinery of the Contractor is parked right on a part
of the road and the jittery and old machines are emitting toxic smoke. Such an adverse social
environmental impact was not being considered anywhere along the line.

Page 162

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

At stone quarry

MONTHLY PROGRESS REPORT


JANUARY 2016

site No. 4 along Kumikote road, Sub- Contractor of the CGGC stone

supplier, Mr. Muhammad Tahir proudly told Mr. Wafa Windur Ali, Environmental Monitor C-2,
that earlier they had the experience of blasting the Margalla Hills in Islamabad and the same
practice was being repeated in KumiiKote Hills. Mr Tahir was not aware of the IEE or any
provisions contained therein. His total interest was Stone only.

The stone extractor had encroached the KumiKote roadway to construct a room for his
electric generator operator and equipment.

Sometimes under pressure of the EPA the waste soil, fallen on the Kumikot roadway was
collected and put in a dumper. The dumper was then sent a few Kilometers downward and
the waste soil was dumped into a stream course below the road, at an unauthorized site.
That amounted to spreading of negative impacts of stone extraction quarry to areas outside
the authorized lease.

At site 2 of the stone quarry lease, along Kumikot road, a notice board had been fixed under
the orders of the Deputy Commissioner Muzaffarbad. The notice displayed the undertakings
given by the stone extractors to the Department of Mineral Resource:

(1) No obstruction to traffic (2) Total responsibility of any kind of loss. (3) Extraction
from safe areas. (4) Lease to be cancelled in case of any non- compliance.

None of the undertakings were being implemented faithfully.

A stone carrier carrying truck, carrying stones from quarry site 2, had no tailgate. The stones
were free to fall on anything moving behind the truck. Stones falling on the road could offer
an unexpected obstacle to fast moving traffic. Above 50% of stone supplier vehicles were
being operated without tailgate reportedly for ease of loading and unloading, but were
causing a major safety risk.

7.2.2.3

Site C3

Environmental team did not visit the site during the reporting period.

7.2.3

Meetings
Environmental Monitoring Meeting was held at C-2 Dengs Hall as follows:Presentations given were:

Presentation by Environmental Guardian C-2, on Compliances

Presentation by Environmental Monitor C-2 on non-compliances

Presentation by Environmental Guardian C-1 on Compliances

Presentation by Environmental Monitor C-1 on Non-Compliances

Presentation by Environmental Guardian C-3 on Compliances

Presentation by Environmental Monitor C-3 on Non-Compliances

Presentation by representative of CMEC Regarding Compliances

Page 163

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Salient points on non-compliances as brought up by EMs, CREs and other participants of the
meeting were as follows:

C-1 Non-Compliances
No as per
NCR Register

Action Required

Action Taken

Latest Compliance Status

1
C-1/50

The Contractor tends

Contractor has not

September 5,

to hide reports about

started submitting

COMPLIED

2015

accidents.

reports on all

AND

Unreported accidents

accidents.

CLOSED

can lead to more


serious accidents.
C-1/58

Oil spillage at Nauseri

Contractor instructed to

December 01,

Dam block 5-1-4

control oil spills and

COMPLIED

leakages and dispose

AND

inevitable spills

CLOSED

2015

adopting proper
procedure
C-1/60

Personal

Contractors attention

December 10,

identification cards

was drawn to this

COMPLIED

2015

not being collected

highly objectionable

AND

and returned properly

practice. He promised

CLOSED

at Adit-A3 and other

to improve the practice

tunnel portal. The

and issue warning to

security guards on

delinquents

duty not performing


their duty properly
C-1/51

No usage of PPE,

NCR was issued to

October 10,

especially safety

Contractor but to no

2015

shoes or provision of

avail. A repeated by

Being now four months old

substandard shoes

name NCR should be

the non-compliance

for workers as well as

issued so as to draw

continues to be

the drivers working

personal attention of

HAZARDOUS

with Engineers staff.

SHE in charge to this


unresolved issue.

Page 164

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

C-1/52

Noncompliance to

NCR was issued to

October 10,

SHE regulation by

Contractor but no

2015

Chinese workers at

improvement has been

main Nauseri Dam

noticed. The Foreman /

Being now four months old

RCC work. In

supervisor at main

the non-compliance

particular the

Nauseri Dam needs to

continues to be

Foreman and

be pulled up or

HAZARDOUS

supervisors

replaced to get safety

themselves neglect

regulations respected.

proper safety
regulations..
C-1/57

Inadequate and

NCR was issued to the

November 15,

below quality drinking

Contractor. Despite

2015

water to labour

assurance to improve,

Being one month old the

working at Nauseri

no change has been

category of non-compliance

Dam

noticed as yet. The

is now

labour going either

MODERATE

thirsty or drinking
below quality unclean
water.
C-1/59

Poor dust control at

S.I was issued. The

December 01,

Crush plant-2 and

Contractor promised to

2015

spoil Area B

deploy two water

OLD

sprinklers instead of

MODERATE

one and ensure water


sprinkling twice a day
on all dust prone sites
at C-1
C-1/59 (A)

Jittery and old vehicle

The Non-Complainces

December 10,

without proper front

which are vehicle

2015

or back lights and

related have to be

OLD HAZARDOUS

tailgate being used

treated directly as

BEING VEHICLE RELATED

inside as well as

Hazardous. NCR was

outside the tunnel

issued to the
contractor, but
compliance not seen
so far

Page 165

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

C-1/61

Poor implementation

S.I was issued. The

December 10,

of tunnel entrance

Contractor requires to

2015

and exit system by

train his safety staff

OLD

Contractors labour

properly. The identity

MODERATE

and vehicles at Adit

card collection and

A-1 portal

return system must be


implemented as a good
safety practice

C-1/62

All equipped vehicle

S.I was issued.it is

December 10,

maintenance

difficult for all vehicles

2015

workshop sub-unit.

requiring oil change or

The Contractors and

other services/ repairs

OLD

project vehicle cannot

to reach all the way at

MODERATE

receive even oil

the C-3 central

change or

workshop. The

replacement of lost

Workshop subunit at

wheel nuts

C-1 must be
strengthened.

C-2 Non-Compliances
No as per
NCR Register
C-2/56
December 4,
2015

C-2/57
December 7,
2015

C-2/58
December 7,
2015

C-2/53
December 1,
2015

Action Required

Action Taken

The temperature (3032C ) and dust (6.7


mg/m) higher than
specified upper limit, in
T3-T3-al,Tunnel faces
and tunnel cross cuts

The Contractor informed


that measures were on the
way to being temperature
and dust lower by
improving ventilation and
air circulation

The First Aid box was


empty in the right tunnel
A4 face. Replenishment
of medicines and
training was not received
from the C-2 Dispensary
Doctor
Clean drinking water not
available I Right Tunnel
A4 at face. Empty water
cooler had been thrown
horizontally

The Contractor was


instructed to get the First
Aid Box replenished and at
least 4 workers trained by
the Dispensary Doctor at
C-2

Scaffolding and platform


in A3 left tunnel not
properly secured. A hole

Contractors attention
drawn to the dispensary
who promised to fix the

Page 166

Attention of Contractor
was drawn to supply clean
drinking water to all labour,
especially at A4 at face.
He promised to comply

Latest Compliance
Status
COMPLIED
AND
CLOSED

COMPLIED
AND
CLOSED

COMPLIED
AND
CLOSED

COMPLIED
AND

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

CLOSED

in the platform could


lead to a free of works.

scaffolding and the


platform

C-2/53 A
December 1,
2015

Scaffolding and platform


in Right A3 left tunnel
not properly secured.
Steel floor pieces not
securely fixed

Contractors attention
drawn to dispensary who
promised to fix. The
scaffolding and pieces of
Steel floor

COMPLIED
AND
CLOSED

C-2/54
November 27,
2015

Safety precaution still


not taken by Contractor
near landslide area in
front of portal A3. Rather
vehicle were being
washed at
sedimentation tank A3
aggravating the
situations
Electric wires naked n
the right tunnel (A3 near
X- cut No.6 in front of
chain age 3+ 3740

The staff posted on the job


required training. They
precisely did not know
their job. Reportedly they
had been posted the same
day to show them to the
monitoring team

COMPLIED
AND
CLOSED

Action awaited from


contractor who promised
to do the needful at
earliest

COMPLIED
AND
CLOSED

The electric board not


secured are naked and
without cover door and
lock and key ) in front of
A3 in cabin below
conveyor belt
Unsecured electricity
distribution boxes
(without cover doors ad
lock and key) in Pakistan
labour block

Action awaited from


Contractor who promised
to do the needful at the
earliest

COMPLIED
AND
CLOSED

Action awaited from


Contractor who promised
to do the needful at the
earliest

COMPLIED
AND
CLOSED

C-2/60
December 7,
2015

Unsecured electricity
distribution boxes
(without cover doors ad
lock and key) at chain
age D4 + 1020

Action awaited from


Contractor who promised
to do the needful at the
earliest

COMPLIED
AND
CLOSED

C-2/51
November 12,
2015

Careless handling of gas


cylinders in tunnel 3-T3a
R at ch.D3+3950 while
cutting operation. A blast
followed by a fire broke
out. Gas cylinders did
not have flashback
arresters the worker had
no hot-work permit
Safety helmets, not
being used by labour

A strong Site Instruction


issued to the Contractor.
The Foreman of the
operation should be
directed to improve.

C-2/52
November 27,
2015

C-2/52 A
November 27,
2015

C-2/56
December 7,
2015

C-2/63
December 30,

Page 167

Site instruction issued to


the Contractor for

OLD
MODERATE

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

2015

inside tunnel A-3. No


PPPE, no work not
being observed by the
Foreman

reinforcing his discipline on


the Foreman who should
enforce the rule that no
PPE, No work

C-2/74
January 12,
2016

Gloves and goggles and


safety shoes not being
used by the workers
during cutting work in
the Adit A4 workshop.
The Forman careless
about use of PPE in the
workshop
At portal Adit A3, the
card system had
collapsed. Old and
unrenewed cards and
photocopies of old cards
were being used.
No barrier and no stop
sign at A3 portal. As a
result the drivers do not
stop for any checking

A strong Site instruction


should be issued to
contractor to keep the
Foreman on the track. The
principle of No PPE, No
Work should be followed in
letter and spirit.

C-2/70
January 11,
2016

Unsecured (i.e. Without


cover and lock) electric
box at Pakistani Labour
camp

Site instruction issued to


the Contractor to provide
full protection to electrical
boards in Pakistani Camp

C-2/66
January 6,
2016

Solid waste not collected


and disposed from the
Pakistani Labour Block

Site instruction issued to


the Contractor to devise a
proper system of collection
and disposal of solid waste
from Pakistani Camp

C-2/66 (a)
January 6,
2016

Solid waste not collected


and disposed in
accommodation areas of
A3

Site instruction issued to


the Contractor to devise a
proper system of collection
and disposal of solid waste
at a pre-designated place

C-2/68
January 10,
2016

Solid waste not collected


and disposed in
accommodation areas of
A4

Site instruction issued to


the Contractor to devise a
proper system of collection
and disposal of solid waste
at a pre-designated
dumping pit which could
later be covered with earth

C-2/62
December 30,
2015

C-2/62 (a)
December 30,
2015

Page 168

Site instruction issued to


the Contractor. Basically, it
is laxity on the part of
Foreman.

Site instruction issued to


the Contractor. Basically,
the Foreman does not
check the safety staff and
drivers

NEW
MINOR

NEW
MINOR

NEW
MINOR

NEW
MINOR

NEW
MINOR

NEW
MINOR

NEW
MINOR

NEW
MINOR

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

C-2/71
January 11,
2016

C-2/71 (a)
January 11,
2016

C-2/72
January 11,
2016

Sedimentation Tank at
TBM Crushing and
Batching Plant too small
and then not cleaned as
often as required to
remove the sediments
from the out-flowing
water
Sedimentation Tank
near bridge No.1. Junder
bane Nullah not deep
enough to help the
settlement of sediments.
Frequency of removal of
sediments less than that
required
Oil getting spilled
continuously from Road,
Mill at TBM Batching
Plant

MONTHLY PROGRESS REPORT


JANUARY 2016

Site instruction issued to


the Contractor to deepen
the sedimentation tank and
increase the frequency of
removal of sediments from
the tank

Site instruction issued to


the Contractor to deepen
the sedimentation tank and
increase the frequency of
removal of sediments from
the tank

Site instruction issued to


the Contractor to take
preventive measures to
stop oil spills. But if some
oil does spill, it should be
disposed off by adapting a
prescribed standard
method
Site instruction issued to
the Contractor to get fitted
new and proper lights in
the form and behind all
vehicles playing in tunnels

C-2/61
December 27,
2015

Missing or defective
back lights in vehicle of
Contractor in Tunnel A3

C-2/73
January 11,
2016

Missing or defective
back lights in Adit A3
and in front of it.

Site instruction issued to


the Contractor to get fitted
new and proper lights in
the form and behind all
vehicles playing in tunnels

C-2/73 (a)
January 12,
2016

Missing 1-2 nuts from


the wheels of a number
of vehicles, particularly
those playing in Adit A4

C-2/69
January 10,
2016

Emission of heavy
smoke and noxious
gases out of vehicle No.
B 8 at C-2

Site instruction issued to


the Contractor to direct
their workshop mechanics
to check the nuts of all
wheels of vehicles before
allowing them to go to
tunnels or outside field
NCR issued because the
non- compliance is vehicle
related. The Contractor
was instructed to get the
vehicle properly tuned or
put that off the road

Page 169

NEW
MINOR

NEW
MINOR

NEW
MINOR

Vehicle related
HAZARDOUS

Vehicle related
HAZARDOUS

Vehicle related
HAZARDOUS

Vehicle related
HAZARDOUS

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

C-2/69 (A)
January 10,
2016

Emission of heavy
smoke and noxious
gases out of vehicle No.
BOU -030

C-2/51 (A)
January 10,
2016

IN Tunnel 3 Ta R at
Ch. 3+ 3950 in cutting
work area a gas cylinder
blast took place.
The gas cylinder did not
have flashback arrestors

C-2/67
January 8,
2016

Gas cylinders had been


stored in large number in
cutting work area in
Tunnel 03- T3Ar AT Ch.
3+3950. Cylinders under
use may be kept there
Workers doing cutting
work in Tunnel 03-T3AR
had no carrying out hard
work

C-2/67 (A)
January 8,
2016

C-2/64
January 4,
2016

Stagnant water and


slush on Main Sirinagar
to Muzaffarbad Road in
front of Adit A4

C-2/65
January 4,
2016

Scrap material yet not


separated by the
Contractor

MONTHLY PROGRESS REPORT


JANUARY 2016

NCR issued because the


non- compliance is vehicle
related. The Contractor
was instructed to get the
vehicle properly tuned or
put that off the road
A strong Site Instruction
was issued to Contractor
for not fitting flash back
arrestors to gas cylinders
in cutting work area. The
non- compliance has
grown 2 months old
Site Instruction was issued
to the Contractor for
removing the cylinders not
in use from the cutting
area in tunnel 03-T3aR
Site Instruction issued to
Contractor for allowing
workers without permit to
be deployed to do the hard
work
Site Instruction issued to
the Contractor. The
Contractor was instructed
to divert the stagnant
water and slush to the
nearest drain
Site Instruction issued to
the Contractor to identify
the scrap type and to be
placed at its proper place

Vehicle related
HAZARDOUS

OLD
MAJOR

NEW
MINOR

NEW
MINOR

NEW
MINOR

NEW
MINOR

C-3 Non-Compliances
No as per
NCR
Register
C-3/104

Vehicles not properly

No action is possible on a

November 16,

inspected and not

sustained basis because

COMPLIED

2015

carefully repaired in the

there was no qualified

AND

vehicle maintenance

mechanics available in the

CLOSED

workshop as none of the

workshop. The contractor

mechanics working there

was instructed to avoid

are qualified. Missing

such careless mistakes

nuts of vehicles not

and employ some

Action Required

Action Taken

Page 170

Latest Compliance
Status

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

replaced and such

MONTHLY PROGRESS REPORT


JANUARY 2016

qualified person

vehicles were going into


the tunnel
C-3/107

Drain at C-3 camp not

Contractor instructed to

December 5,

being cleaned properly.

keep all drain clear and

COMPLIED

2015

The drain outside

especially the one passing

AND

Pakistani Canteen is

in front of Pakistani

CLOSED

filthy in particular

canteen

C-3/107(B)

In sub contractor 4 area

Contractor advised to

December 5,

there are water pipes

provide valued taps at the

COMPLIED

2015

which are flowing

end of overflowing taps to

AND

continuously causing

which he agreed

CLOSED

huge water losses


C3/80 (C)

Poor house keeping in

NCR issued to Contractor,

August 13,

WAPDA colony, steel

it was consistently being

OLD

2015

bars, wooden pieces and

ignored by the Contractor.

HAZARDOUS

other scrap thrown

The Subcontractor

randomly

reluctant to get guidance


from SHE Staff of
Contractor or Engineer

C-3/80 (F)

Poor dust control in

NCR issued to the

November 12,

WAPDA Colony. Water

Contractor. The

OLD

2015

sprinkling was avoided

Subcontractor has an

MAJOR

as much as possible.

attitude problem. He is not

Subcontractor not ready

receptive to any guidance

to be guided by SHE

given by SHE Staff of

Staff

Contractor or the
Engineer

C-3/80 (G)

No signage displayed in

NCR issued to the

November 12,

the entire colony as the

Contractor along with

OLD

2015

work was not properly

sketches of required

MAJOR

organized. Main board

signboards could not

was also old and faded.

create a dent in the denial

No guidance to workers

plan of the subcontractor.

through signage

Contractor reminded to
take initiative

C-3/93

Security guard not

NCR issued to CGGC, the

November 12,

provided at the gate of

contractor, had failed to

OLD

2015

vehicle maintenance and

motivate them to provide

MAJOR

repair workshop at C-3.

a whole time protection at

Page 171

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Costly vehicles exposed

MONTHLY PROGRESS REPORT


JANUARY 2016

the Workshop gate

to theft and spare parts


from workshop stone
liable to pilferage
C-3/95

There was no defined

NCR was issued the

November 12,

system/ policy for the

contractor to produce and

2015

time period after which

announce a plan for

tyres should be changed

change of tyres and

OLD

or oil should be changed

change of oil. There was a

MAJOR

even for NJC vehicles.

tendency of using

Old tyres and unchanged

retreaded tyres and

oil could prove safety

change oil after long

risk

intervals

C-3/96

No sanitary convenience

NCR issued, but no

November 12,

or a toilet had been

action taken so far.

2015

provided in the vehicle

Nearby toilets in the camp

maintenance Workshop.

were already

OLD

The workers and the

overcrowded. Urinating in

MAJOR

visiting drivers had to go

the open was neither

to to someone else toil or

decent nor environment

urinate in nearby open

friendly. A simple,

places

inexpensive toilet way


essentially required

C-3/101

Only one overall and set

NCR issued to contractor

November 12, of safety shoes was

to issue another new

2015

provided to the

overall and shoes to each

OLD

mechanics in the vehicle

mechanic in vehicle

MAJOR

maintenance workshop

maintenance workshop.

at C-3. The overall and

Failure to provide PPE

the safety shoes had

well in time is the

become old and was torn

responsibility of the

out

Contractor

C-3/102

There was only one

NCR issued to the

November 12,

central vehicle

contractor to strengthen

2015

maintenance workshop

the sub-units of workshop

OLD

at C-3. The subunits at

at C-1 and C-2 for better

MAJOR

C-1 and C-2 were almost

maintenance of vehicles

non- functional. The

there

vehicles have to come all

Page 172

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

way to C3 from C1 and


C-2 for even small
repair.
C-3/105

The contractor was

Site instruction was

November 16,

instructed to improve

issued to the contractor

OLD

2015

signage in the Dumper

for improving the signage

MODERATE

workshop at C-3

at the Dunper workshop


C-3. No feedback had
been received. A Situation
to be verified during the
next visit by
Environmental monitor

C-3/106

All over C-3 the

Site instruction issued to

November 16,

contractors camp the

the contractor. It was

2015

solid waste was dumped

more of an attitude

anywhere outside the

problem. The contractor

OLD

collection boxes. At

was instructed to run any

MODERATE

times the people carrying

awareness campaign

solid waste so reach the

through the formation of

box, but prefer to throw it

solid waste disposal

just outside the box

committees from amongst


the workers

C-3/108

Lack of usage of PPE by

Site instruction issued to

December 26,

labour working in the

the contractor. After

2015

new WAPDA Colony at

improving once, the use of

C-3

PPE in WAPDA Colony

NEW

had again declined.

MINOR

Safety helmet and


protective hand gloves
were particularly avoided.
No PPE, No Work was not
being followed
C-3/109

In WAPDA Colony, the

Site Instruction issued to

December 2,

workers working at

the contractor for securing

2015

heights were not using

the persons working at

NEW

safety belts. Even the

heights and placing the

MINOR

ladders were placed at

ladders at proper angle

wrong angles. The feet

and with secured feet

of the ladder were never


secured

Page 173

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

C-3/110

The railing was missing

Site Instruction issued to

November 12,

from scaffolding, work-

the contractor to provide a

2015

platforms at a height and

safe railing at scaffolding

NEW

a number of ladders, in

working platforms at

MINOR

Transformer Hall

heights and ladders in


Transformer hall

7.2.4

Status Of Non-Compliances By Contractor

Joint Monthly Environmental Monitoring Meetings was held on January 13, 2016 at site C2, which
was chaired by the Chief Environment NJC. It mainly took cognizance of the environmental noncompliances committed by Contractor (CGGC and CMEC). Following was the status of
environmental non-compliances, on various sites, up to January 12, 2016

Status of Non-Compliances
Minor (Under one month old)
Moderate (Over one month but under 2 months old)
Major (Over two months but under 3 months old)
Hazardous (Over three months old)
NCR Dropped

Sr.
#

1.

No. as per
NCR

Site

Non-Compliance

Register

C1

C-1/50

The Contractor tends to

September

hide reports about

5, 2015

accidents. Unreported

C2

Action Required

Responsibility

C3

COMPLIED

CLOSED

accidents can lead to


more serious accidents.
2.

C-1/58

Oil spillage at Nauseri

December

Dam block 5-1-4

CLOSED

01, 2015

3.

C-1/60

Personal identification

December

cards not being

10, 2015

collected and returned


properly at Adit-A3 and

COMPLIED

COMPLIED

other tunnel portal. The


security guards on duty
not performing their

Page 174

CLOSED

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

duty properly
4. C-1/51

No usage of PPE,

Foreman to

Contractor to

October

especially safety shoes

check PPE,

follow up by

10, 2015

or provision of

No PPE, No

EM-C1 and

Work

EG C1

substandard shoes for


workers as well as the
drivers working with
Engineers staff.
5.

C-1/52

Noncompliance to SHE

Foreman should

Contractor to

October

regulation by Chinese

ensure that

follow up by

10, 2015

workers at main

Chinese labour

EM-C1 and

Nauseri Dam RCC

does follow SHE

EG C1

work. In particular the

regulation

Foreman and
supervisors themselves
neglect proper safety
regulations..
6.

7.

8.

9.

C-1/57

Inadequate and below

Supply adequate

Contractor to

November

quality drinking water to

clean drinking

follow up by

15, 2015

labour working at

water to the

EM-C1 and

Nauseri Dam

workers

EG C1

C-1/59

Poor dust control at

Effective dust

Contractor to

December

Crush plant-2 and spoil

control at

follow up by

01, 2015

Area B

crushing Plant 2

EM-C1 and

and Spoil Area B

EG C1

C-1/59 (A)

Jittery and old vehicle

Vehicles to have

Contractor to

December

without proper front or

a front, hind and

follow up by

10, 2015

back lights and tailgate

indicator lights.

EM-C1 and

being used inside as

Tailgates to be

EG C1

well as outside the

fitted. Vehicles to

tunnel

be repaired

C-1/61

Poor implementation of

Card collection

Contractor to

December

tunnel entrance and

and return

follow up by

10, 2015

exit system by

system at Portals

EM-C1 and

Contractors labour and

of all tunnels to

EG C1

vehicles at Adit A-1

be regulated

portal
10.

C-1/62

All equipped vehicle

Workshop

Contractor to

December

maintenance workshop

subunit to be

follow up by

10, 2015

sub-unit. The

upgraded and

EM-C1 and

Page 175

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Contractors and project

MONTHLY PROGRESS REPORT


JANUARY 2016

made functional

EG C1

COMPLIED

CLOSED

COMPLIED

CLOSED

COMPLIED

CLOSED

COMPLIED

CLOSED

COMPLIED

CLOSED

COMPLIED

CLOSED

vehicle cannot receive


even oil change or
replacement of lost
wheel nuts
11.

C-2/56

The temperature (30-

December

32C ) and dust (6.7

4, 2015

mg/m) higher than

specified upper limit, in


T3-T3-al,Tunnel faces
and tunnel cross cuts
12.

C-2/57

The First Aid box was

December

empty in the right

7, 2015

tunnel A4 face.

Replenishment of
medicines and training
was not received from
the C-2 Dispensary
Doctor
13.

C-2/58

Clean drinking water

December

not available I Right

7, 2015

Tunnel A4 at face.

Empty water cooler had


been thrown
horizontally
14.

C-2/53

Scaffolding and

December

platform in A3 left

1, 2015

tunnel not properly

secured. A hole in the


platform could lead to a
free of works.
15.

C-2/53 A

Scaffolding and

December

platform in Right A3 left

1, 2015

tunnel not properly

secured. Steel floor


pieces not securely
fixed
16.

C-2/54

Safety precaution still

November

not taken by Contractor

27, 2015

near landslide area in

Page 176

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

front of portal A3.


Rather vehicle were
being washed at
sedimentation tank A3
aggravating the
situations
17.

C-2/52

Electric wires naked In

November

the right tunnel (A3

27, 2015

near X- cut No.6 in front

COMPLIED

CLOSED

COMPLIED

CLOSED

COMPLIED

CLOSED

COMPLIED

CLOSED

of chain age 3+ 3740


18.

C-2/52 A

The electric board not

November

secured are naked and

27, 2015

without cover door and

lock and key ) in front of


A3 in cabin below
conveyor belt
19.

C-2/56

Unsecured electricity

December

distribution boxes

7, 2015

(without cover doors ad

lock and key) in


Pakistan labour block
20.

C-2/60

Unsecured electricity

December

distribution boxes

7, 2015

(without cover doors ad

lock and key) at chain


age D4 + 1020
21.

C-2/51

Careless handling of

Excess gas

Contractor to

November

gas cylinders in tunnel

cylinders to be

follow up by

12, 2015

3-T3a R at Ch.s3+350

removed from

EM-C2 and

Tunnel T3R Ch.

EG C2

while cutting operation.

A blast followed by a

3+350

fire broke out. Gas


cylinders did not have
flashback arresters the
worker had no hot-work
permit
22.

C-2/63

Safety helmets, not

Safety helmets, to

Contractor to

December

being used by labour

be used by

follow up by

30, 2015

inside tunnel A-3. No

Page 177

workers at Adit A3 EM-C2 and

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

EG C2

PPPE, no work not


being observed by the
Foreman

23.

C-2/74

Gloves and goggles

Workers at cutting Contractor to

January

and safety shoes not

work in Adit A4 to

follow up by

12, 2016

being used by the

use gloves and

EM-C2 and

goggles

EG C2

Contractor to

workers during cutting


work in the Adit A4
workshop. The Forman
careless about use of
PPE in the workshop
24.

C-2/62

At portal Adit A3, the

Regulate the

December

card system had

identification card follow up by

30, 2015

collapsed. Old and

collection and

EM-C2 and

Unrenewed cards and

returning system

EG C2

photocopies of old

at Adit A3

cards were being used.


25.

26.

27.

C-2/62 (a)

No barrier and no stop

Barrier with the

Contractor to

December

sign at A3 portal. As a

stop sign to be

follow up by

30, 2015

result the drivers do not

fixed at Portal of

EM-C2 and

stop for any checking

Adit A3

EG C2

C-2/70

Unsecured (i.e. Without

Electric box at

Contractor to

January

cover and lock) electric

11, 2016

box at Pakistani Labour

be provided cover, EM-C2 and

camp

lock and key

EG C2

C-2/66

Solid waste not

Solid waste to be

Contractor to

January 6,

collected and disposed

deposited in

follow up by

2016

from the Pakistani

Labour Block

Pakistani Camp to follow up by

designated dustbin EM-C2 and


and boxes in

EG C2

labour Block
28.

29.

C-2/66 (a)

Solid waste not

Solid waste thrown Contractor to

January 6,

collected and disposed

to be collected at

follow up by

2016

in accommodation

accommodation

EM-C2 and

areas of A3

area of A3

EG C2

C-2/68

Solid waste not

Solid waste to be

Contractor to

January

collected and disposed

collected and

follow up by

10, 2016

in accommodation

disposed properly

EM-C2 and

accommodation

EG C2

areas of A4

Page 178

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

area of A3
30.

C-2/71

Sedimentation Tank at

Clean

Contractor to

January

TBM Crushing and

sedimentation

follow up by

11, 2016

Batching Plant too

Tank at TBM

EM-C2 and

Crushing and

EG C2

small and then not


cleaned as often as

Batching Plant

required to remove the

twice a week

sediments from the outflowing water


31.

C-2/71 (a)

Sedimentation Tank

Clean

Contractor to

January

near bridge No.1.

sedimentation

follow up by

11, 2016

Jander bane Nullah not

Tank near Bridge

EM-C2 and

deep enough to help

No. 1 twice a

EG C2

the settlement of

week

sediments. Frequency
of removal of sediments
less than that required
32.

33.

C-2/72

Oil getting spilled

Stop oil spill from

Contractor to

January

continuously from

road Mill Plant at

follow up by

11, 2016

Road, Mill at TBM

TBM Batching

EM-C2 and

Batching Plant

Plant

EG C2

C-2/61

Missing or defective

Replace missing

Contractor to

December

back lights in vehicle of

back lights in the

follow up by

27, 2015

Contractor in Tunnel A3

vehicle of the

EM-C2 and

Contractor in

EG C2

Tunnel A3
34.

35.

C-2/73

Missing or defective

January

back lights in Adit A3

11, 2016

and in front of it.

Missing or

Contractor to

defective back

follow up by

lights in Adit A3

EM-C2 and

to be replaced

EG C2

C-2/73 (a)

Missing 1-2 nuts from

Replace missing

Contractor to

January

the wheels of a number

nuts from the

follow up by

12, 2016

of vehicles, particularly

wheels of a

EM-C2 and

number of

EG C2

those playing in Adit A4

vehicles, playing
in Adit A4
36.

C-2/69

Emission of heavy

Tune vehicle No.

Contractor to

January

smoke and noxious

B 8 at C-2 to stop

follow up by

10, 2016

gases out of vehicle

emissions of toxic

EM-C2 and EG

Page 179

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

37.

38.

MONTHLY PROGRESS REPORT


JANUARY 2016

No. B 8 at C-2

smoke

C2

C-2/69 (A)

Emission of heavy

Tune vehicle No.

Contractor to

January

smoke and noxious

BOU -030 at C-2

follow up by

10, 2016

gases out of vehicle

to stop emissions

EM-C2 and EG

No. BOU -030

of toxic smoke

C2

C-2/51 (A)

IN Tunnel 3 Ta R at

Provide flashback

Contractor to

January

Ch. 3+ 3950 in cutting

arrestors at

follow up by

10, 2016

work area a gas

Tunnel 3 Ta R

EM-C2 and EG

at Ch. 3+ 3950

C2

cylinder blast took

place.
The gas cylinder did not
have flashback
arrestors
39.

C-2/67

Gas cylinders had been

Remove excess

Contractor to

January 8,

stored in large number

cylinders from

follow up by

2016

in cutting work area in

Tunnel 03- T3Ar

EM-C2 and EG

AT Ch. 3+3950.

C2

Tunnel 03- T3Ar AT Ch.

3+3950. Cylinders
under use may be kept
there
40.

C-2/67 (A)

Workers doing cutting

Workers with

Contractor to

January 8,

work in Tunnel 03-

permits to work

follow up by

2016

T3AR had no carrying

on hot works to

EM-C2 and EG

be allowed in

C2

out hard work

cutting area of
03- TaR
41.

C-2/64

Stagnant water and

Stagnant water

Contractor to

January 4,

slush on Main Sirinagar

and slush on

follow up by

2016

to Muzaffarbad Road in

Main Sirinagar to

EM-C2 and EG

Muzaffarbad

C2

front of Adit A4

Road to be
diverted to the
nearest drain
42.

43.

C-2/65

Scrap material yet not

January 4,

separated by the

2016

Contractor

C-3/104

Vehicles not properly

November

inspected and not

Page 180

Scrap material to

Contractor to

be separated and

follow up by

to be placed at

EM-C2 and EG

proper place

C2

COMPLIED

CLOSED

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

16, 2015

MONTHLY PROGRESS REPORT


JANUARY 2016

carefully repaired in the


vehicle maintenance
workshop as none of
the mechanics working

there are qualified.


Missing nuts of vehicles
not replaced and such
vehicles were going
into the tunnel
44.

C-3/107

Drain at C-3 camp not

December 5, being cleaned properly.


2015

The drain outside

COMPLIED

CLOSED

COMPLIED

CLOSED

Pakistani Canteen is
filthy in particular
45.

C-3/107(B)

In sub contractor 4 area

December 5, there are water pipes


2015

which are flowing


continuously causing
huge water losses

46.

C3/80 (C)

Poor house keeping in

Improve house

Contractor to

August 13,

WAPDA colony, steel

keeping in

follow up by

2015

bars, wooden pieces

WAPDA colony

EM-C3 and EG

C3

and other scrap thrown


randomly
47.

C-3/80 (F)

Poor dust control in

Improve dust

Contractor to

November

WAPDA Colony. Water

control in

follow up by

12, 2015

sprinkling was avoided

WAPDA Colony

EM-C3 and EG

as much as possible.

C3

Subcontractor not
ready to be guided by
SHE Staff
48.

C-3/80 (G)

No signage displayed in

Improper signage Contractor to

November

the entire colony as the

at WAPDA

follow up by

12, 2015

work was not properly

colony

EM-C3 and EG

organized. Main board

C3

was also old and faded.


No guidance to workers
through signage
49.

C-3/93

Security guard not

Make a Guard

Contractor to

November

provided at the gate of

room (cabin) and

follow up by

Page 181

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

12, 2015

MONTHLY PROGRESS REPORT


JANUARY 2016

vehicle maintenance

post a security

and repair workshop at

Guard at the gate C3

C-3. Costly vehicles

EM-C3 and EG

of the vehicle

exposed to theft and

maintenance

spare parts from

Workshop

workshop stone liable


to pilferage
50.

C-3/95

There was no defined

Make tyre

Contractor to

November

system/ policy for the

change and oil

follow up by

12, 2015

time period after which

change plan for

EM-C3 and EG

all vehicles

C3

tyres should be
changed or oil should
be changed even for
NJC vehicles. Old tyres
and unchanged oil
could prove safety risk

51.

C-3/96

No sanitary

Construct a low

Contractor to

November

convenience or a toilet

cost toilet at a

follow up by

12, 2015

had been provided in

vehicle

EM-C3 and EG

the vehicle

maintenance

C3

maintenance

workshop

Workshop. The workers

and the visiting drivers


had to go to to
someone else toil or
urinate in nearby open
places
52.

C-3/101

Only one overall and

Provide new

Contractor to

November

set of safety shoes was

overall to

follow up by

12, 2015

provided to the

mechanics in

EM-C3 and EG

vehicle

C3

mechanics in the
vehicle maintenance

maintenance

workshop at C-3. The

workshop at C-3

overall and the safety


shoes had become old
and was torn out
53.

C-3/102

There was only one

Strengthen

Contractor to

November

central vehicle

Vehicle

follow up by

12, 2015

maintenance workshop

maintenance at

EM-C3 and EG

Page 182

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

at C-3. The subunits at

MONTHLY PROGRESS REPORT


JANUARY 2016

C1 and C2

C3

C-1 and C-2 were


almost non- functional.
The vehicles have to
come all way to C3
from C1 and C-2 for
even small repair.
54.

C-3/105

The contractor was

Improve signage

Contractor to

November

instructed to improve

at Dumper

follow up by

16, 2015

signage in the Dumper

Workshop at C-3

EM-C3 and EG

C3

workshop at C-3
55.

C-3/106

All over C-3 the

Collect and

Contractor to

November

contractors camp the

dispose solid

follow up by

16, 2015

solid waste was

waste properly

EM-C3 and EG

from all over C-3

C3

dumped anywhere
outside the collection

Camp

boxes. At times the


people carrying solid
waste so reach the box,
but prefer to throw it
just outside the box
56.

C-3/108

Lack of usage of PPE

Subcontractor

Contractor to

December

by labour working in the

and Foreman to

follow up by

26, 2015

new WAPDA Colony at

ensure use of full

EM-C3 and EG

PPE, No PPE,

C3

C-3

No Work
57.

C-3/109

In WAPDA Colony, the

In WAPDA

Contractor to

December 2, workers working at

colony, the

follow up by

2015

heights were not using

labour, working

EM-C3 and EG

safety belts. Even the

on heights to use

C3

ladders were placed at

safety belts

wrong angles. The feet


of the ladder were
never secured
58.

C-3/110

The railing was missing

Provide railing on Contractor to

11 January,

from scaffolding, work-

scaffolding,

follow up by

2016

platforms at a height

raised Platform

EM-C3 and EG

and a number of

and ladders in

C3

ladders, in Transformer

Transformer Hall

Hall

Page 183

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Score Status for Non-Compliances For the Month of January, 2016

Non-Compliances (N.C)

Lot

Aspect

C-1

No. of N.C.s

Rate of Deduction

-1

-2

-4

-5

--

Total Deduction

-8

-15

-23

Minor

Moderate

Major

(a) 100 23= 77%

Payment %
C-2

No. of N.C.s

-15

22

Rate of Deduction

-1

-2

-4

-5

--

Total Deduction

-15

-2

-4

-25

-46
(b) 100 46 = 54%

Payment %
C-3

No. of N.C.s

13

Rate of Deduction

-1

-2

-4

-5

--

Total Deduction

-3

-4

-28

-5

-40
(c) 100 40 = 60%

Payment %

Total

Hazardous

The Contractor after fully complying with the non-compliances shall make a formal and
express request to CRE concerned to close the non-compliance. If such written
request is not received, by the end of the current month, It will get shifted to next
month the CRE may not close a non-compliance.

The non-compliance shall not be closed automatically. Unless it is not done by CRE,
an unclosed non-compliance shall stay on record and shall continue to be the basis of
the deductions in the score.

So it is in Contractors own interest that he promptly complies with non-compliances


and gets those closed.

Notification of closure of non-compliance must be conveyed in writing to respective EM as well as


EG to enable them to make necessary entries in their report/presentation.

DELIVERABLES

A: Monthly presentation of report by Environmental Guardian of Site C-1 on


compliances by Contractor during the month under report.
B:

Monthly presentation of report by Environmental Monitor of Site C-1 on non-

compliances by Contractor during the month under report.

A:

Monthly presentation of report by Environmental Guardian of Site C-2 for

compliances by the Contractor for the month under report.


B:

Monthly presentation of report by Environmental Monitor of Site C-2 for non-

compliances by the Contractor for the month under report.

Page 184

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

A:

MONTHLY PROGRESS REPORT


JANUARY 2016

Monthly presentation of report by Environmental Guardian of Site C-3 for

compliances by Contractor for the month under report.


B:

Monthly presentation of report by Environmental Monitor of Site C-3 for non-

compliances by the Contractor for the month under report.

Monthly compliance and non- compliance by CMEC

Monthly Environmental Monitoring Report for NJHP for the month of December, 2015.

RECOMMENDATIONS
To enable the Environmental Monitoring Team to carry out monitoring of NJHP activities they must
have their own equipment, instruments and transport so that they may not depend upon the
Contractors Labs and instruments for data collection. Purchase of instruments may be authorized.
A list to that effect has already been submitted. To estimate cost of the proposal is approximately
Rs. 3.0 million. This matter was discussed with CED/PD NJHP also

Proposed Programme for next Month i.e. February 2016


S.
No
1.

Objects
Reviews

Proposed Activities
1. Review of EIA and new revised PC-1 shall be carried out for identifying
funds allocation for EMP implementation particularly for purchase of
instruments and equipment. A follow up shall be given to request
already sent. (Approximate Cost Rs. 3.0 million).
2. Any other document which is referred to Environmental Wing for review,
information and necessary action.
3. OECD Studies in Risk Management (to be continued).

2.

Field Visits
and
Meetings

Date

S.O.P

January 12, 2016

I. 09:00 hrs.

(Tuesday)

Visit to 5 most sensitive points of Lot-C-2 from


SHE points of view.
II. 14:00 hrs.
Environmental Monitoring meeting for Lot-C-2
in Dengs Hall.

In addition to above scheduled and structured visits and meetings, all


such meetings which are required by PD or DG EPA or any other
Government agency related to SHE, shall be attended as per date and
time given in the meeting notice.
1. Monthly Environmental Monitoring Report, covering period upto
3.

Deliverables

January 11, 2016.


2. Monthly Environmental Progress Report for the month of January,
2016.

Page 185

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

3. Compliance Reports by Environmental Guardians C-1, C-2 and C-3


4. Non-Compliance Reports by Environmental Monitors for C-1, C-2 and
C-3
5. Quarterly Environmental Monitoring Report for Period ending
December 31, 2015
6. Quarterly Environmental progress Report for quarter ending December
31, 2015

Page 186

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

STAFFING AND RESOURCES

8.1

THE CONSULTANT

MONTHLY PROGRESS REPORT


JANUARY 2016

The Consultants staff strength on the Project remained same as reported in the last month (with
minor internal shuffling) and as shown in Table 8-1 below:

Table 8-1: Consultant's Staff Deployment in January 2016


Location

Management

Technical

Support

Total

Lahore

23

23

46

16

21

Muzaffarabad

22

46

68

C1

86

32

119

C2

125

23

148

C3

118

34

152

Total

22

369

163

554

Muzaffarabad
Design Office

8.2

THE CLIENTS COUNTERPART STAFF

Due to the initiation of additional works like TBM, Steel / Concrete Lining and other activities at the
sites; additional staff requirements for different project sites have been worked out and being
processed. Staff from the Client, specialised in the Health & Safety (HS) is required to impart
training and augment the efforts for HS of the Contractor and also for close monitoring at all the
project operational sites.

8.3

THE CONTRACTOR

Some inconsistency has been observed in the contractors monthly progress report, hence it is not
reproduced for want of clarification from the Contractor.

Page 187

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

FINANCE

9.1

THE CONSULTANT

MONTHLY PROGRESS REPORT


JANUARY 2016

The status of invoices and payments to the Consultants are given in Table 9-1. Currently the last
month invoice remains to be paid by the Client.

Table 9-1: Status of the Consultant Invoices


Inv.

Detail

No.

Date

Invoice
Amount

Remarks
Submitted

Due

Payment

17

July 2009

47,689,904 20 Aug 09

20 Sept 09

16 Sept 09

Paid

18

August 2009

41,160,866 24 Sept 09

24 Oct 09

27 Oct 09

Paid

19

September

52,767,384 22 Oct 09

22 Nov 09

23 Nov 09

Paid

2009
20

October 2009

57,939,783 23 Nov 09

23 Dec 09

23 Dec 09

Paid

21

November 2009

55,861,363 21 Dec 09

21 Jan 10

21 Jan 10

Paid

22

December 2009

47,546,047 26 Jan 10

26 Feb 10

26 Feb 10

Paid

23

January 2010

50,514,513 1 Mar 10

30 Mar 10

29 Mar 10

Paid

24

February 2010

47,728,251 22 Mar 10

21 Apr 10

19 Apr 10

Paid

25

March 2010

54,419,379 21 Apr 10

20 May 10

19 May 10

Paid

26

April 2010

57,419,448 21 May 10

20 Jun 10

25 Jun 10

Paid

27

May 2010

44,077,144 16 Jun 10

16 Jul 10

21 Jul 10

Paid

28

June 2010

43,862,870 29 Jul 10

20 Aug 10

20 Aug 10

Paid

29

July 2010

53,153,596 23 Aug 10

23 Sept 10

29 Sept 10

Paid

30

August 2010

39,326,863 27 Sept 10

27 Oct 10

4 Nov 10

Paid

31

September

43,492,297 25 Oct 10

25 Nov 10

26 Nov 10

Paid

2010
32

October 2010

45,731,992 29 Nov 10

29 Dec 10

11 Jan 11

Paid

33

November 2010

68,406,047 28 Dec 10

27 Jan 11

20 Feb 11

Paid

34

December 2010

70,425,943 29 Jan 11

28 Feb 11

24 Feb 11

Paid

35

January 2011

69,904,095 23 Feb 11

24 Mar 11

28 Mar 11

Paid

Page 188

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Inv.

Detail

No.

Date

Invoice
Amount

MONTHLY PROGRESS REPORT


JANUARY 2016

Remarks
Submitted

Due

Payment

36

February 2011

71,531,412 29 Mar 11

28 Apr 11

26 Apr 11

Paid

37

March 2011

88,551,585 29 Apr 11

29 May 11

25 May 11

Paid

38

April 2011

74,875,656 20 May 11

29 Jun 11

30 Jun 11

Paid

39

May 2011

101,578,012 29 Jun 11

29 Jul 11

1 Aug 11

Paid

40

June 2011

97,535,370 29 Jul 11

28 Aug 11

20 Aug 11

Paid

41

July 2011

88,041,221 8 Sept 11

08 Oct 11

06 Oct 11

Paid

42

August 2011

89,413,945 01 Oct 11

31 Oct 11

30 Oct 11

Paid

43

September

94,578,721 31 Oct 11

30 Nov 11

02 Dec 11

Paid

89,824,008 08 Dec 11

07 Jan 12

06 Jan 12

Paid

2011
44

October 2011
(Revised.)

45

November 2011

91,691,709 26 Dec 11

25 Jan 12

06 Feb 12

Paid

46

December 2011

93,966,379 27 Jan 12

26 Feb 12

29 Feb.12

Paid

47

January 2012

100,807,604 24 Feb 12

24 Mar 12

26 Mar 12

Paid

48

February 2012

119,551,402 26 Mar. 12

25 Apr 12

25 Apr 12

Paid

49

March 2012

118,113,557 30 Apr 12

30 May 12

04 Jun 12

Paid

50

April 2012

122,588,351 28 May 12

27 Jun 12

29 Jun 12

Paid

51

May 2012

123,786,684 28 Jun 12

28 Jul 12

27 Jul 12

Paid

52

June 2012

112,816,311 30 Jul 12

29 Aug 12

30 Aug 12

Paid

53

July 2012

111,458,321 31 Aug 12

30 Sep 12

28 Sep 12

Paid

54

August 12

125,348,617 26-Sep-12

26-Oct-12

25 Oct. 12

Paid

55

September'12

131,884,797 5-Nov-12

5-Dec-12

6-Dec-12

Paid

56

October'12

135,586,169 27-Nov-12

27-Dec-12

9 Jan 13

Paid

57

November'12

132,656,697 26-Dec-12

25-Jan-13

30 Jan.13

Paid

58

December 13

123,858,712 26 Jan.13

25 Feb.13

3 March 13

Paid

59

January 13

133,899,906 28 Feb 13

30 March 13

8 April 13

Paid

60

February 13

127,371,057 27 March 13

26 April 13

6 May 13

Paid

Page 189

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Inv.
No.

Detail

Date

Invoice
Amount

MONTHLY PROGRESS REPORT


JANUARY 2016

Remarks
Submitted

Due

Payment

61

March 13

140,321,063 29 April 13

29 May 13

3 June 13

Paid

62

April 13

140,745,206 30 May 13

29 June 13

3 Jul 13

Paid

63

May 13

177,645,056 8 July 13

7 Aug 13

6 Aug 13

Paid

64

June 13

156,633,146 29 July 13

25 August

3 Sep 13

Paid

13
65

July 13

155,256,671 9 Sep 13

9 Oct 13

1 Oct-13

Paid

66

August 13

153,134,685 30 Sep 13

30 Oct 13

12 Nov. 13

Paid

67

September 13

151,642,963 4 Nov. 13

4 Dec 13.

2 Dec 13

Paid

68

October 13

213,515,379 2 Dec 13.

1 Jan. 14

2 Jan 13

Paid

69

November 13

191,380,132 30 Dec 13

29 Jan 14

4 Feb.14

Paid

70

December 13

195,159,570 24 Jan 14

23 Feb.14

4 March 14

Paid

January 14

100,000,000 28 Feb.14

30 March 14

2 April 14

Paid

st

( 1 Instt.)
71

January 14

106,477,073 28 Feb.14

30 March 14

7 April 14
nd

(2
72

February 14

110,456,000 3 April 14

3 May 14

Paid

Instt.)

24 April 14

Paid

First Inst.
72

February 14

86,976,191 3 April 14

3 May 14

7 May 14

Paid

Second Inst.
73

March 14

181,053,127 30 April 14

30 May 14

26 May 14

Paid

74

April 14

179,095,273 27 May 14

26 June 14

26 July 14

Paid

75

May 14

175,804,395 25 June 14

25 July 14

15 July 14

Paid

76

June 14

188,740,060 25 July 14

24 Aug 14

20 August 14

Paid

77

July 14

177,125,597 26 Aug 14

25 Sept 14

26 Sep 14

Paid

78

August 14

181,875,996 26 Sept 14

25 Oct 14

26 Oct. 14

Paid

79

September 14

184,410,376 27 Oct 14

26 Nov 14

26 Nov.14

Paid

80

October 14

197,455,888 27 Nov.14

27 Dec.14

23 Dec. 14

Paid

81

November 14

176,695,102 22 Dec.14

21 Jan 15

2 Feb. 15

Paid

Page 190

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Inv.
No.

Date

Invoice

Detail

MONTHLY PROGRESS REPORT


JANUARY 2016

Remarks

Amount

Submitted

82

December 14

188,446,818 22 Jan 15

83

January'15

84

February'15

85

March 15

86

April'15

85,969,971

21-May-15

87

May'15

212,976,696

88

June 15

89

189,236,589

Payment

21 Feb 15

24 Feb. 15

19-Feb-15

21-Mar-15

20-Mar-15

19-Apr-15

19-Mar-15

Paid
Paid

5 May 15

Paid

25 May 15

Paid

20-Jun-15

6 July 15

Paid

19-June-15

19 July -5

10 Aug-15

Paid

205,460,877

22-July -15

21- Aug-15

27 Aug-15

Paid

July 15

197,451,725

26 Aug -15

25 Sep-15

23 Sept-15

Paid

90

August15

194,817,721

25-Sep-15

21-oct-15

28 Oct-15

Paid

91

September15

207,433,002

27-Oct-15

26 Nov-15

27-Nov-15

Paid

92

October 2015

212,316,053

20-Nov-15

20-Dec-15

28-Dec-15

Paid

93

November 2015 203,808,807

21-Dec-15

20-Jan-16

27-Jan-16

Paid

94

December 2015 210,929,438

21-Dec-15

20-Jan-

Awaited

Total

182,609,215

Due

186,440,584

23 April 15

23 May 15

10,688,735,552

9.2

CONTRACTORS INVOICE

9.2.1

Invoices & Payments

EMH-43 was submitted on 11 December 2015 and certified on 18 December 2015. EMH No.44
was submitted on 25 January 2016 and is under certification. EMH -45 was submitted on 19
January 2016 and certified on 25 January 2016.

Amount certified up to EMH No.45=RS.2,908,264,509 & Equivalent Rs.22,464,707,395.

Monthly Statement No.077 was submitted on 7 September 2015 and certified on 4 October 2015.
Monthly Statement No.078, for the months of July and August 2015, was submitted on 20 October
2015 and certified on 14 November 2015 .Monthly Statement No.079 was submitted on 11
December 2015 and certified on 6 January 2016

Amount certified up to IPC No.79 =RS.60, 708,688,711, USD 648,843,304 and EURO 8,706,118/-

Page 191

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Table 9-2: Status of the Contractors Invoices

IPC
No.

Period

For the Months

CURRENCY DISTRIBUTION

Date of
Submission
by the
Contractor

Date of
Certification by
the Engineer

14 June 2008

27 June 2008

of February &

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

Remarks

IPC was issued within the specified time


504,447,779.55

4,500,840.55

March 2008
2

For the Months

16 June 2008

08 August 2008

The Engineer wanted proof that the

of April & May

Insurance was in place and approved

2008

301,765,258.03

2,698,073.74

by the Employer before any


certification. The Contractor caused the
delay.

For the Month of


June 2008

17

22 September

September

2008.

IPC was issued within the specified


53,103,422.70

473,805.31

time.

2008
4

For the Months

09 October

09 October

of July, August

2008

2008.

31 October

06 November

2008

2008

For the Month of

01 December

02 December

November 2008

2008

2008

& September

IPC was issued within the specified


34,162,804.58

312,339.83

7,833,401.72

100,111.42

9,815,608.98

89,963.04

time.

2008
5

For the Month of


October 2008

Page 192

IPC was issued within the specified time

IPC was issued within the specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

Date of
Certification by
the Engineer

For the Month of

06 January

19 January 2009

December 2008

2009

For the Month of

04 February

11 February

2009

2009

21 April 2009

28 April 2009

January 2009
9

CURRENCY DISTRIBUTION

Date of
Submission
by the
Contractor

Period

For the Month of

MONTHLY PROGRESS REPORT


JANUARY 2016

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

39,505,414.80

352,479.64

29,989,336.49

135,941.93

Remarks

IPC was issued within the specified time

IPC was issued within the specified time

The Engineer raised many objections

February &

on the Monthly Statement of February

March 2009

2009. The Contractor deleted all the


objectionable items and resubmitted the
108,409,623.71

668,820.00

Monthly Statement for certification. IPC


was issued within the specified time.
The Project Director has some
apprehensions on IPC No. 09, which
were clarified before settlement by the
Employer.

10

For the month of

20 May 2009

15 June 2009

April 2009
11

For the month

21 June 2009

13 July 2009

of May 2009
12

For the month of


June 2009

16 July 2009

04 August 2009

362,832,032.84

3,237,300.65

83,021,147.43

658,715.91

138,756,016.73

1,100,840.18

Page 193

IPC No. 10 was issued within the


specified time.
IPC No. 11 was issued within the
specified time
IPC No. 12 was issued within the
specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

13

Period

For the month of


July 2009

14

For the month of


August 2009

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION

Date of
Submission
by the
Contractor

Date of
Certification by
the Engineer

10 August

01 September

2009

2009

19

03 October 2009

September

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

286,471,982.19

2,532,930.66

Remarks

IPC No. 13 was issued within the


specified time
IPC No. 14 was issued within the

129,765,823.28

1,161,396.15

189,405,187.37

1,630,163.66

specified time.

2009
15

16

For the month of

16 October

10 November

September 2009

2009

2009

For the month of

24 November

18 December

2009

2009

October 2009

IPC No. 15 was issued within the


specified time.
IPC No. 16 was resubmitted on 16

162,386,269.92

1,369,511.84

December 2009 and was issued within


the specified time.

17

18

19

For the month of

05 January

November 2009

2010

For the month of

02 February

17 February

December 2009

2010

2010

For the month of

09 March

25 March 2010

January 2010
20

For the month of


February 2010

21

For the month of


March 2010

25 January 2010

2010
06 April

26 April 2010

2010
27 April
2010

15

May 2010

199,339,828.05

1,741,543.85

226,953,751.17

2,017,078.54

145,259,891.48

1,276,424.15

185,846,979.68

1,643,622.64

196,164,120.11

1,747,413.45

Page 194

IPC No. 17 was issued within the


specified time.
IPC No. 18 was issued within the
specified time.
IPC No. 19 was issued within the
specified time.
IPC No. 20 was issued within the
specified time.
IPC No. 21 was issued within the
specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

22

Period

For the month of

CURRENCY DISTRIBUTION

Date of
Submission
by the
Contractor

Date of
Certification by
the Engineer

17 May 2010

07 June 2010

April 2010
23

For the month of

11 June 2010

28 June 2010

May 2010
24

For the month of

07 July 2010

21 July 2010

June 2010
25

For the month of


July 2010

26

For the month of


August 2010

MONTHLY PROGRESS REPORT


JANUARY 2016

07 August

1 September

2010

2010

14

05 October 2010

September

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

87,532,902.15

780,995.87

289,835,278.80

2,586,000.83

120,125,612.49

1,067,863.88

171,312,601.44

1,529,445.97

Remarks

IPC No. 22 was issued within the


specified time.
IPC No. 23 was issued within the
specified time
IPC No. 24 was issued within the
specified time
IPC No. 25 was issued within the
specified time
IPC No. 26 was issued within the

217,603,760.05

1,921,781.55

133,205,369.64

1,028,722.51

127,701,702.53

1,070,147.14

243,985,237.33

2,362,502.26

325,088,272.90

3,225,587.60

210,403,445.22

1,554,022.02

specified time.

2010
27

28

For the month of

13 October

08 November

September 2010

2010

2010

For the month of

15 November

11 December

2010

2010

For the month of

23 December

11 January 2011

November 2010

2010

For the month of

23 January

07 February

December 2010

2011

2011

For the month of

17 February

09 March 2011

October 2010
29

30

31

Page 195

IPC No. 27 was issued within the


specified time.
IPC No. 28 was issued within the
specified time.
IPC No. 29 was issued within the
specified time.
IPC No. 30 was issued within the
specified time
IPC No. 31 was issued within the

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

Period

January 2011
32

For the month of


February 2011

32/2

For the month of

Date of
Submission
by the
Contractor

CURRENCY DISTRIBUTION
Date of
Certification by
the Engineer

34

For the month of

For the month of


May 2011

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

18 March

09 April 2011

2011
11 April 2011

11 April 2011

For the

Resubmitted by

month of

the Contractor

March 2011

on 01 May 2011.

23 May 2011

12 June 2011

17 June 2011

Remarks

specified time

April 2011
35

Local Component

2011

February 2011
33

MONTHLY PROGRESS REPORT


JANUARY 2016

208,330,426.78

1,831,077.42

9,380,199.60

IPC No. 32 was issued within the


specified time.

IPC No. 33 was certified on 21 May


265,519,026.22

2,279,980.04

235,523,319.17

1,922,405.15

08 July 2011

2011 within the specified time.

IPC No. 34 was certified on 12 June


2011 within the specified time.
IPC No. 35 was certified within the

but returned

specified time.

for correction.
It was

889,965,195.58

7,822,874.80

500,903,467.16

4,346,113.11

507,942,858.12

4,578,024.45

resubmitted
on 21 June
2011
36

For the month of

13 July 2011

01 August 2011

June 2011
37

For the month of

11 August

27 August 2011

Page 196

IPC No. 36 was certified within the


specified time
IPC No. 37 was certified within the

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

Period

July 2011
37-2

For the month of


July 2011

Date of
Submission
by the
Contractor

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION
Date of
Certification by
the Engineer

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

2011

Remarks

specified time

08

15 September

September

2011

IPC No. 37-2 was certified within the


2,066,958.43

specified time

2011
37-2

For the month of


July 2011

08

15 September

September

2011

IPC No. 37-2 was certified within the


366,496.37

specified time

2011
38

For the month of


August 2011

19

03 October 2011

September

IPC No. 38 was certified within the


386,891,796.62

3,198,177.59

408,631,432.33

3,456,438.83

specified time

2011
39

40

For the month of

12 October

September 2011

2011

For the month of

17/28

14 December

November

2011

October 2011

31 October 2011

IPC No. 39 was certified within the


specified time
IPC No. 40 was certified within the

907,115,498.87

7,714,081.92

specified time.

2011
40-2

For the month of


October 2011

21/29

19 December

IPC No. 40-2 returned to the Contractor

November

2011

twice due to incomplete submission and

2011 and 18

December

22,622,157.29

certified the following day when the


submission was complete. The delay

2011

was caused by the Contractor.

Page 197

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

40-3

Period

For the month of


October 2011

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION

Date of
Submission
by the
Contractor

Date of
Certification by
the Engineer

30

02 January 2012

December

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

Remarks

IPC No. 40-3 was certified within the


-

3,100,437.65

475,922,801.93

3,942,722.94

739,332,373.83

6,540,124.21

4,421,273.40

917,225.55

504,261.22

839,543.57

439,464,941.90

3,699,524.00

637,910.45

522,186,367.48

4,850,056.01

specified time.

2011
41

42

42-2

42-3

42-4

42-5

43

For the month of

19 December

November 2011

2011

For the month of

17 January

08 February

December 2011

2012

2012

For the month of

20 January

25 January 2012

December 2011

2012

For the month of

30 January

December 2011

2012

For the month of

02 February

03 February

December 2011

2012

2012

For the month of

20 February

08 March 2012

December 2011

2012

For the month of

15 February

January 2012
43-2

For the month of


January 2012

44

For the month of

10 January 2012

31 January 2012

09 March 2012

2012
08 March

27 March 2012

2012
19 March

13 April 2012

Page 198

IPC No. 41 was certified within the


specified time.
IPC No. 42 was certified within the
specified time.
IPC No. 42-2 was certified within the
specified time.
IPC No. 42-3 was certified within the
specified time.
IPC No. 42-4 was certified within the
specified time
IPC No. 42-5 was certified within the
specified time
IPC No. 43 was certified within the
specified time
IPC No. 43-2 was certified within the
specified time
IPC No. 44 was certified within the

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

Period

February 2012
44-2

45

For the month of

Date of
Submission
by the
Contractor

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION
Date of
Certification by
the Engineer

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

2012
30 March

February 2012

2012

For the months

30 April 2012

specified time
20 April 2012

141,645,327.67

9,865,899.96

21 May 2012

of March & April

For the months

IPC No. 44-2 was certified within the


specified time
IPC No. 45 was certified within the

1,073,426,688.40

9,849,028.09

2012
45-2

Remarks

specified time (adjustments have been


incorporated in forex components)

04 May 2012

17 May 2012

of March& April

IPC No. 45-2 was certified within the


117,689,332.88

10,891,721.99

4,133,916.86

819,331,380.34

7,856,930.03

25,710,057.56

5,888,827.70

871,852,501.42

7,867,549.33

149,794,918.70

2,652,636.63

1,157,393,292.74

10,378,613.19

160,574,557.33

3,567,719.29

specified time

2012
46

For the month of

04 June 2012

25 June 2012

May 2012
46-2

For the month of

04 June 2012

14 June 2012

May 2012
47

For the month of

13 July 2012

07 August 2012

June 2012
47-2

For the month of

07July 2012

01 August 2012

June 2012
48

For the month of


July 2012

48-2

For the month of

17 August

11 September

2012

2012

23 August

17 September

Page 199

IPC No. 46 was certified within the


specified time
IPC No. 46-2 was certified within the
specified time
IPC No. 47 was certified within the
specified time
IPC No. 47-2 was certified within the
specified time
IPC No. 48 was certified within the
specified time
IPC No. 48-2 was certified within the

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

Period

July 2012
49

For the month of


August 2012

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION

Date of
Submission
by the
Contractor

Date of
Certification by
the Engineer

2012

2012

19

13 October 2012

September

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

Remarks

specified time
IPC No. 49 was certified within the
815,363,479.52

10,418,189.52

specified time

2012
49-2

For the month of


August 2012

19

20 September

September

2012

IPC No. 49-2 was certified within the


-

3,386,240.00

specified time

2012
50

For the month

22 October

15 November

of September

2012

2012

26 November

18 December

2012

2012

For the month of

26 December

21 January 2013

November 2012

2012

For the month of

15 February

26 February

December 2012

2013

2013

6 March 2013

08 April 2013

IPC No. 050 was certified within the


677,539,788.67

7,332,392.03

812,514,308.17

5,449,864.53

864,219,917.88

6,790,176.88

869,938,331.74

10,847,515.10

02 April 2013

812,147,228.70

8,018,756.01

02 May 2013

485,920,083.65

5,784,229.85

specified time

2012
51

For the month of


October 2012

52*

53

54

55

For the month of


January 2013
For the month of
February 2013

Page 200

IPC No. 051 was certified within the


specified time
IPC No.052 was certified within the
specified time
IPC No.053 was certified within the
specified time
IPC No. 054 was certified within the
specified time
IPC No. 055 was certified within the
specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

Period

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION

Date of
Submission
by the
Contractor

Date of
Certification by
the Engineer

14 May 2013

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

06 June 2013

2,812,540,756.89

25,288,977.26

13 May 2013

15 May 2013

2,034,611.12

17 June 2013

15 July 2013

514,554,175.08

12,636,135.19

For the month of


56

March and April


2013
For the month of

56-2

March and April


2013

57

For the month of


May 2013

For the month of


May 2013

04 July 2013

IPC No. 056 was certified within the


specified time

IPC No. 056-2 was certified within the


specified time
IPC No. 057 was certified within the
specified time

22-July 2013
57-2

Remarks

IPC No. 057-2 was certified within the


-

11,175,345.72

specified time with the remarks that the


original invoices were not attached by
the Contractor

58

59

59-2

For the month of


June 2013
For the month of
July 2013
For the month of
July 2013

IPC No. 058 was certified within the


21 July 2013

16 August 2013

27 August

21 September

2013

2013

23
September
2013

26 September
2013

1,218,145,028.90

12,634,145.17

1,026,090,023.53

9,438,927.80

specified time

I IPC No. 059 was certified within the


specified time
IPC No. 059-2 was certified within the

Page 201

11,175,345.71

specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

60

61

Period

For the month of


August 2013

64

64-2

64-3

September

24 October 2013

2013

2013

16 December
2013

11 January 2014

28 January

24 February

December 2013

2014

2014

For the month


of January 2014
For the month
of January 2014

(Pak Rs.)

(US Dollars)

(Euro)

Remarks

1,225,096,550.28

10,979,759.55

specified time

06 March
2014
15 March
2014
15 March
2019

IPC No. 061 was certified within the


781,348,401.61

7,512,092.54

169,170.72

specified time

IPC No. 062 was certified within the

For the month of

of January 2014

Foreign
Component

2013

September 2013

For the month

Foreign
Component

IPC No. 060 was certified within the

02 December

October and

Local Component

30

05 November

November 2013

63

CURRENCY DISTRIBUTION
Date of
Certification by
the Engineer

For the month of

For the Month of


62

Date of
Submission
by the
Contractor

MONTHLY PROGRESS REPORT


JANUARY 2016

1,726,376,861.88

13,487,242.66

specified time

IPC No. 063 was certified within the


829,139,497.01

9,558,159.44

31 March 2014

814,342,583.87

7,441,521.65

19 March 2014

1,349,087.42

01 April 2014

5,334,484.54

47,595.93

Page 202

specified time

IPC No. 064 was certified within the


specified time
IPC No. 064-2 was certified within the
specified time
IPC No. 064-3 was certified within the
specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

Period

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION

Date of
Submission
by the
Contractor

Date of
Certification by
the Engineer

9 April 2014

1 May 2014

13 May 2014

07 June 2014

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

832,095,516.17

6,854,557.87

11,599,222.81

292,203.95

1,629,531.19

For the month


65

of February
2014

66

For the month of


March 2014

3 June2014
Monthly
66-2

For the month of


March 2014

Statement
was objected
to for further
information

*
1,265,204,935.06

Of April and

68-2

For the month of


June 2014
For the month of
June 2014

specified time
IPC No. 066 was certified within the
specified time

responded on
25 June 2014
and IPC issued
on 5 July

. IPC No. 066-2 was certified within the


specified time

2014vide
PO-14821

17 June 2014

12 July 2014

1,521,384,963.58

12,293,602.84

24 July 2014

19 August 2014

1,427,996,673.59

10,044,505.19

28 July 2014

5 August 2014

1,175,519.55

May 2014
68

IPC No. 065 was certified within the

The Contractor

For the month


67

Remarks

Page 203

.IPC No. 067 was certified within the


specified time.
IPC No. 068 was certified within the
specified time
IPC No. 068-2 was certified within the
specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

69

70

70-2

71

Period

For the month of


July 2014
For the Month of
August 2014
For the Month of

74

28 August

23 September

2014

2014

2014

24 October 2014

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

1,892,652,632.83

16,831,327.45

1,257,103,932.98

11,080,188.84

30 October

2014

2014

For the Month of

10 November

04 December

September 2014

2014

2014

1,879,356,037.35

August 2014

October &
November 2014

73

Date of
Certification by
the Engineer

23 October

For the month of


72

CURRENCY DISTRIBUTION

Date of
Submission
by the
Contractor

1 October

MONTHLY PROGRESS REPORT


JANUARY 2016

18 December
2014

12 January 2015

29 January

23 February

December 2014

2015

2015

For the month of

11 March
2015

18,957,487.84

2,410,694,409.43

20,579,773.41

1,365,896,950.80

12,464,747.63

IPC-69 was certified within the


specified time
IPC No. 070 was certified within the
specified time
IPC No. 070-2 was certified within the
specified time
IPC No.071 was certified within the
specified time

For the month of

January 2015

2,255,635.64

Remarks

IPC was certified within the specified


time

IPC was certified within the specified


time
IPC was certified within the specified

6 April 2015

1,035,215,964.00

Page 204

7,104,726.00

time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC
No.

75

76

Period

For the month of


February 2015

For the month of


April 2015
For the months

77

of May and June


2015
For the months

78

of July and
August 2015

7802

For the months


of July and
August 2015
For the months

79

of September &
October 2015

Date of
Submission
by the
Contractor

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION
Date of
Certification by
the Engineer

Local Component

Foreign
Component

Foreign
Component

(Pak Rs.)

(US Dollars)

(Euro)

Remarks

IPC was certified within the specified


23April 2015

18 May 2015

2,390,023,815.00

20,394,619,00

time

IPC was certified within the specified


11 July 2015

7 September
2015

24 August 2015-

3,171,569,730.00

24,876,267.00

4 October 2015

3,143,685,805.00

26,704,466.00

1,783,518,392.00

9,638,505.00

26531443

308,497

2,714,500,025.00

28,841,372.00

60,708,688,711

650,843,304

20 October

14 November

2015

2015

30 October

04 November

2015

2015

11 December
2015
Total

6 January 2016

Page 205

time

IPC was certified within the specified


time

IPC was certified within the specified


time

IPC was certified within the specified


time

IPC was certified within the specified


time
8,706,118

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

Table 9-3: Status of the Contractors Invoices (EMH)

IPC No.
SC-02

Period
5% Advance

Date of
submission
to the
Consultant
13 June 2008

Date of
Certification by
the Consultant

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

Remarks

(Eq. Pak Rs)

25 June 2008

Payment was made

Payment Ref Sub

within the specified

Clause 60.1 A (a)

time

(ii) of Part II B-

0.00

0.00

910,319,400.00

Conditions of
Particular
Application
EMH-01

For the Month of

28 October

OCTOBER 2008

2008

31 October
2008

IPC was issued


0.00

0.00

298,154,000.00

within the specified


time

EMH-02

Turbine Model

10 May 2009

18 May 2009

Test-Lot M1 BOQ

IPC was issued


0.00

0.00

238,520,000.00

M1: Item 9
EMH-03

25% Advance

within the specified


time.

30 May 2009

Not certified at

Laid down conditions

Payment Ref Sub

this stage (ref

0.00

0.00

0.00

not fulfilled

Clause 60.1 A (a)

NJCS letter No

particularly regarding

(ii) of Part II B-

PO-2367 dated

Engineers

Conditions of

18 June 2009.

confirmation of the

Particular

satisfactory progress

Application

made on the
manufacturing of the

Page 206

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.

Period

Date of
submission
to the
Consultant

Date of
Certification by
the Consultant

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

Remarks

(Eq. Pak Rs)


relevant equipment
by the Contractor.

EMH-03(A)

26 April 2010

Certified vide

IPC certified within

10 % of advance

PO-4211 dated

the specified time.

payment, Ref Sub

7 May 2010

Clause 60.1 A (a)


(ii) of Part II BConditions of

0.00

Particular

13,412.74

1,820,637,498.72

Application, FOB
value of all plants
against bank
guarantee of equal
amount
EMH-03(B)

5 % of advance

Certified vide

IPC certified within

payment, Ref Sub

PO-7180

the specified time

Clause 60.1 A (a)

dated

(ii) of Part II B-

10 August 2011

Conditions of

20 July 2011

831,246.00

Particular
Application, FOB
value of all plants

Page 207

245.21

910,318,098.72

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.

MONTHLY PROGRESS REPORT


JANUARY 2016

Date of
submission
to the
Consultant

Date of
Certification by
the Consultant

10% of advance

02 November

Certified vide

IPC certified within

payment Ref Sub

2011

PO-7692 dated

the specified time.

Period

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

Remarks

(Eq. Pak Rs)

against bank
guarantee of equal
amount
EMH-03(C)

Clause 60.1 A(a)(ii)

04 November

of Part II B-

2011

Conditions of
Particular

0.00

Application as

0.00

1,820,637,498.72

sanctioned in the
meeting with the
Contractor (Ref.
CEO(NJHPC)/DT/1
898-1907)
EMH No 04

5% advance

Certified vide

IPC certified within

payment of

PO-8944 dated

the specified time.

Contract Value

16 May 2012

(Erection and

30 April 2012

84,049,128.20

Other Works) as
per Clause
60.1A(e)(i) of

Page 208

102,749,929.15

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.

MONTHLY PROGRESS REPORT


JANUARY 2016

Date of
submission
to the
Consultant

Date of
Certification by
the Consultant

12 June 2012

Certified vide

IPC certified within

Erection

PO-9186 dated

the specified time

Equipment and

27 June 2012

Period

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

Remarks

(Eq. Pak Rs)

COPA Part II B.
EMH No.05

FOB any Plant &

FOB Insurance &


shipping for Lot M1

0.00

as per Sub-

0.00

50,688,462.90

Clauses 60.iA
(a)(iii) and
60.1A(b)(i of
COPA part II B.
EMH No. 06

Supply of Lot M-1

04 September

Equipment (Partial

2012

Certified vide

IPC certified within

PO-9590 dated

the specified time

shipment of

08 September

Turbine and Bridge

2012

3,366,240.00

0.00

113,560,240.30

Crane)
EMH No.07

Erection and other


works etc.

02 October
2012

Certified vide
PO-9770 dated
10 October

IPC certified within


104,161,206.06

0.00

124,075,386.22

226,798,485.71

107,396.27

221,424,934.26

the specified time

2012
EMH No.08

Erection and other


works etc.

02 February
2013

Certified vide
PO-10735

Page 209

IPC certified within


the specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.

Period

Date of
submission
to the
Consultant

Date of
Certification by
the Consultant

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

Remarks

(Eq. Pak Rs)

dated 21
February 2013
EMH No.09

Erection and other


works etc.

07 February
2013

Certified vide
PO-10800
dated 04 March

IPC certified within


2,373,795.89

0.00

140,204,307.25

the specified time

2013
EMH No.10

Erection and other

09 April 2013

works etc.

Certified vide
PO-11161
dated 27 April

IPC certified within


92,096,843.09

0.00

139,982,967.92

the specified time

2013
EMH No.11

Erection and other

05 July 2013

works etc.

Certified vide
PO-11837
dated 28 July

IPC certified within


125,843,426.63

0.00

138,725,781.35

the specified time

2013
EMH No.12

Erection and other

05 July 2013

works etc.

Certified vide
PO-11868
dated 30 July

IPC certified within


13,579,177.40

0.00

358,608,016.72

the specified time

2013
EMH No.13

Erection and other


works etc.

28 September
2013

PO-12507
dated 23
October 2013

IPC certified within


121,178,220.74

Page 210

40,677.07

222,333,843.72

specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.
EMH No.14

Payment of FOB

Date of
submission
to the
Consultant
11 October

Plant and Erection

2013

Period

Equipment etc
EMH No.15

Erection and other


works etc.

Date of
Certification by
the Consultant

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

(Eq. Pak Rs)

PO-12631
dated 05

Remarks

IPC certified within


14,025,954.57

0.00

556,053,166.67

specified time

November 2013
21 November
2013

PO-13018
dated
17 November

IPC certified within


93,293,527.53

136,375.58

109,807,593.58

specified time

201`3
EMH No.16

Erection and other


works etc

03 January
2014

PO-13421
dated
30 January

IPC certified within


116,257,409.47

51,107.56

109,807,593.58

specified time

2014
EMH No.17

Erection and other


works etc

28 January
2014

PO- 13543
dated 14

IPC certified within


1,987,230.13

0.00

332,547,723.33

specified time

February 2014
EMH No. 18

Adjustment of
(5%+25%)FOB and

18 February
2014

5% Erection Works

PO-13732

IPC certified within

dated 05 March

specified time

2014

18,591,600.24

0.00

1,491,178,213.86

increase inH1
Equipment
EMH N0. 19

Payment of FOB

01 March

Plant and erection

2014

equipment,

PO-13895
dated18 March

IPC-19 was certified


16,539.21

2014

Page 211

0.00

224,795,683.35

within specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.

Period

Date of
submission
to the
Consultant

Date of
Certification by
the Consultant

MONTHLY PROGRESS REPORT


JANUARY 2016

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

Remarks

(Eq. Pak Rs)

Insurance,
transportation and
price adjustment
EMH No.20

Payment of FOB
Plant and erection
equipment,

04 March
2014

Insurance,

PO-13939
dated 27 March
2014

The IPC-20 was


95,976,928.60

47,284.12

129,361,873.19

certified within the


specified time

transportation and
price adjustment
EMH No.21

EMH No.22

Payment of FOB

Resubmitted

Plant and erection

on 08 April

equipment.

2014

Payment of

25 April 2014

PO-14571
dated 5 June
2014

The IP-21 was


3,746,370.85

0.00

452,919,042.63

PO-14423

erection works

dated 20 May

Monthly cost and

2014

certified within the


specified time

The IPC-22 was


95,911,556.06

0.00

117,629,220.02

certified within the


specified time

price adjustment
EMH No.23

Payment of

27 June 2014

PO-14975

The IPC-23 was

erection works

dated 21 July

certified within the

Monthly cost and

2014

95,911,556.06

price adjustment

Page 212

0.00

116,253,026.05

specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.
EMH No.24

Period
Payment of

Date of
submission
to the
Consultant
8 July 2014

MONTHLY PROGRESS REPORT


JANUARY 2016

Date of
Certification by
the Consultant

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

(Eq. Pak Rs)

PO-14979

erection works

dated

Monthly cost and

2014

21 July

Remarks

The IPC-24 was


30,838.08

0.00

81,073,065.11

certified within the


specified time

price adjustment
EMH No.25

Reimbursement of

28 July 2014

Customs Duties

EMH No.26

September

Import

2014

Payment of

5 September
2014

and Taxes on Plant

specified time

certified within the

2014

2014

0.00

dated 30

price adjustment

Customs Duties

0.00

The IPC-26 was

September

18 October

certified within the


15,690,020.00

PO-15614

Monthly cost and

Reimbursement of

The IPC-25 was

dated 12

and Taxes on Plant

erection works

EMH No.27

PO-15475

148,382,513.74

0.00

118,317,209.72

PO-15970
dated 11
November 2014

specified time

The IPC-27 was


6,279,781.92

0.00

412,089,624.94

certified within the


specified time

Import
EMH No.28

Payment of
erection works
Monthly cost and

23 October
2014

PO-16019
dated19
November 2014

The IPC-28 was


106,338,493.78

price adjustment

Page 213

0.00

117,629,220.02

certified within the


specified time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.
EMH N0.29

Period
Reimbursement of
Customs Duties
and Taxes on Plant

Date of
submission
to the
Consultant
5 November
2014
Engineer

Import under

objected and

Clause 73.5

Contractor

MONTHLY PROGRESS REPORT


JANUARY 2016

Date of
Certification by
the Consultant

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

Remarks

(Eq. Pak Rs)

PO-16409

IPC-29 was certified

dated

within the specified

23 December

time

2014
266,840,345.21

0.00

0.00

resubmitted
on11
December
2014
EMH No.30

Erection and other

24 December

works, adjustment

2014

under Clause 70

PO-16660

The IPC was certified

dated 19
January 2015

106,338,493.78

0.00

117,629,220.02

within the specified


time.

etc
EMH No.31

Payment of FOB
Plant and erection

12 January
2015

Equipment,

PO-16794

The IPC was certified

dated 2

within the specified

February 2015

Insurance and

22,779,544.38

0.00

1,661,616,474.39

time.

Shipping & Local


transportation etc.
EMH No.32

Reimbursement of
Expenditure (Fat
and Inspections)

28 January
2015

PO-16971
dated

The IPC was certified


19

2,643,266.00

February 2015

52,978.78

0.00

within the specified


time

Page 214

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.
EMH No. 33

Period
Customs duty and

Date of
submission
to the
Consultant
6 February

Taxes on Plant

2015

Import
EMH No.34

Erection and other

MONTHLY PROGRESS REPORT


JANUARY 2016

Date of
Certification by
the Consultant

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

Remarks

(Eq. Pak Rs)

PO-16972

The IPC was certified

dated 23

74,119,070.19

0.00

0.00

within the specified

February 2015

time

28 February

PO-1727dated

The IPC was certified

2015

26 March 2015

Works

131,144,914.84

0.00

123,773,258.07

within the specified


time

EMH No. 35

FOB Plant and

Rev 1

Erection

dated 13 May

Equipment

2015

time

PO-7871 dated

The IPC was certified

EMH No. 36

Erection and other

16 April 2015

01 May 2015

works

PO-17551

The IPC was certified

25 May 2015

15,709,537.29

106,478,538.89

0.00

0.00

2,479,323,534.13

121,792,297.94

within the specified

within the specified


time

EMH No.37

EMH No.38

Customs duty and

13 June 2015

The IPC was certified

Taxes on Plant

Dated19 June

Import

2015

time
The IPC was certified

Customs duty and

06 August

PO-18620

Taxes on Plant

2015

Dated 12

Import
EMH No.39

PO-18136

Payment of Plant

29

Erection

2015

August

91,470,358.76

134,609,450.23

within the specified

within the specified

August 2015

time

PO-18928

The IPC was certified

dated

Equipment

September

,Insurance,

2015

14

9,477,896.50

Page 215

2,430,985,105.32

within the specified


time

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.

Date of
submission
to the
Consultant

Period
Shipping

MONTHLY PROGRESS REPORT


JANUARY 2016

Date of
Certification by
the Consultant

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

(US Dollars)

Remarks

(Eq. Pak Rs)

,Local

transport and Price


Adjustment
EMH No.40

Arranging

05 September

PO-19088

Performance

2015

dated

Security for VO-

The IPC was certified


05

within the specified

October 2015

time

024 Lot H1

67,450,692.33

Changes in
Hydraulic Steel
Works
EMH-No.41

Payment of FOB,

17 October

PO-

Plant and Erection

2015

Dated

Equipment ETC.
EMH-No.42

EMH-No.44

Plant and Erection

2015

dated

20

104,528,608

121,553,109.92

within the specified

November 2015

time
The IPC was certified

Payment of FOB,

11 December

PO-19819

Plant and Erection

2015

dated

25 January

within the specified

The IPC was certified

PO-19525

Payment of FAT

time

29 October

Equipment ETC

The IPC was certified

November 2015

Payment of FOB,

Equipment ETC
EMH-No.43

19386

18

within the specified

December 2015

time

Under Process

IPC is under

2016

Process.

Page 216

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

IPC No.
EMH-No.45

Period
Customs Duties

MONTHLY PROGRESS REPORT


JANUARY 2016

Date of
submission
to the
Consultant
19 January

PO-20141

The IPC was certified

2016

dated 25

within the specified

January 2016

time

Total Certified

Date of
Certification by
the Consultant

CURRENCY DISTRIBUTION
Local Component
Foreign Component Foreign Component
(Pak Rs.)

2,908,264,509

Page 217

(US Dollars)

449,477.33

Remarks

(Eq. Pak Rs)

22,464,707,395

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

9.3

MONTHLY PROGRESS REPORT


JANUARY 2016

APPROPRIATION REQUESTS AND VARIATION ORDERS

Appropriation Requests and Variation Order Log details are given as per Annex C.

9.4

CLAIMS

The log for the Claims is given as per Annex D.

Page 218

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

ANNEXURES

Page A

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

ANNEXURE A: PROJECT SCHEDULE

Page B

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Page C

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Page D

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Page E

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Page F

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Page G

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Page H

MONTHLY PROGRESS REPORT


JANUARY 2016

32,174,143,741
10,961,758,919
21,212,384,822

Certified Value Value IPC-79 / IPC-43

Escalation

Certified Value (No Escalation)

Page I

10,000,000,000

20,000,000,000

30,000,000,000

40,000,000,000

50,000,000,000

60,000,000,000

70,000,000,000

80,000,000,000

C1

32,339,394,634

Total Contract Value (No Escalation)

Financial Progress

14,026,604,162

VO's (Approved & Pending)

65.6%

-485,000,000
9,361,810,050
25,125,590,802
22,189,064,649
6,643,490,254
15,545,574,395

52,641,464,271
75,652,063,615
56,582,114,855
15,612,202,097
40,969,912,758

58.4%

77,727,871,974

33,217,451,271

110,945,323,245

133,117,049,051

76,029,878,483

-3,800,000,000

60,887,170,568

68.0%

6,540,745,631

428,496,929

6,969,242,560

10,250,096,770

6,148,224,450

-760,000,000

4,861,872,320

73.2%

2,962,210,685

1,282,107,285

4,244,317,970

5,802,148,000

-820,000,000

6,622,148,000

M1

C2

C3

H1

(Unit:PKRs & No Escalation)


Cumulative Ammounts Certified by the Engineer till 31 October 2015

Histogram for Financial Progress


Up To IPC-79 (Civil), IPC-43 (EMH)

61.9%

-1,940,000,000

-1,375,000,000

54.2%

17,703,780,752

24,385,599,344

40,969,912,758

18,797,790,472

25,125,590,802

Contract Escalation

15,545,574,395

Contract BOQ Value Rs.

32,339,394,634

H1

10,250,096,770

21,212,384,822

Total Civil Works

6,540,745,631

75,652,063,615

C3

E1

51.9%

17,995,516,251

5,209,655,539

23,205,171,790

34,688,205,999

7,075,136,163

-2,400,000,000

30,013,069,836

Total EMH

M1

Certified Value (No Escalation)

E1

Total Contract Value (No Escalation)

64.3%

8,492,559,935

3,499,051,326

11,991,611,260

18,635,961,229

926,911,713

-820,000,000

18,529,049,516

5,802,148,000

C2

2,962,210,685

C1

18,635,961,229

Item

57.0%

95,723,388,224.59

38,427,106,810.43

134,150,495,035.03

167,805,255,050.24

83,105,014,646.26

-6,200,000,000.00

90,900,240,403.98

Total Contract

8,492,559,935

S.No

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT
MONTHLY PROGRESS REPORT
JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

ANNEXURE B: LIST OF DRAWINGS ISSUED DURING THIS PERIOD

Page J

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

Page K

MONTHLY PROGRESS REPORT


JANUARY 2016

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


DECEMBER 2015

ANNEXURE C: STATUS OF APPROPRIATION REQUESTS AND VARIATION ORDERS

Page L

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

NEELUM JHELUM HYDROELECTRIC PROJECT


STATUS OF APPROPRIATION REQUESTS/VARIATION ORDERS
AS ON 25 JANUARY 2016

VO
No.

Amounts (Rs)
Description

Engineer's
Estimate
Consolidated fuel

VO-01

cost for the


Client/Consultants
vehicles

VOC3:04

Lot

Submission of AR
to Employer
Ref

Date

Employer's
Approval of
AR
Date

C1,
C2,
C3

Increased tunnel

001

capacity

Date

PO-1016

29-Sep-08

30-Sep-08

By
hand

VO was raised to rationalize


15-Oct-08

cost of fuel at all three sites.


There was no resultant effect
on the cost of project.

C3

Contractor's scope

VO-

Ref

Remarks

Approved by the Employer.

Deletion of Design
office building from

Issuance of VO
to Contractor

(12,886,247)

PO-2839

10-Sep-09

12-Oct-09

PO2975

12-Oct-09

Dropped as merged in VO-017.

C1,
C2,
C3

Approved by the Employer.

PO-3701

17-Feb-10

Not required

Not required

Cost of Rs 9,007,110,498 was


debited to this VO and credited
to VO-017.

Increase in
VO-

Diversion Tunnel

002

length from 150m

C1

488,391,768

PO-13937

31-Mar-14

to 500m

Page M

Not required

Not required

Employer's Approval Awaited

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Amounts (Rs)
Description

Engineer's
Estimate

VO-

Contractor's plant

003

erection area
Independent

VO-

survey through

004

nominated subcontractor

VO005

Lot

C1

101,655,333

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer

Employer's
Approval of
AR

Ref

Date

Date

PO-3767

25-Feb-10

21-Feb-13

PO-3736

22-Feb-10

05-May-10

PO-3738

22-Feb-10

29-May-12

C1,
C2,
C3

553,929

Additional
Engineer's

C2

accommodation

25,876,899

Issuance of VO
to Contractor
Ref
PO10774

PO9496

PO9758

Remarks

Date
27-Feb-13

Approved by the Employer.

23-Aug-12

Approved by the Employer.

03-Oct-12

Approved by the Employer.

Dropped as disapproved by the


Employer vide letter ref.
VO-

Spare runner for

006

turbines

M1

PO-3883

22-Mar-10

22-Feb-13

PO10827

MD/CEO/NJHPC/Dir(E&M)/W6-Mar-13

21/4458-66 dated 22 February


2013. Communicated to the
Contractor vide PO-10827.

VO-

Geodetic survey

007

network

VO-

Access road for

008

Adit A7 portal and

C1,
C2,
C3
C3

Queries raised by the Client


184,160,244

39,385,824

PO-4150

26-Apr-10

vide CEO(NJHPC/DT/1562-63
responded by PO-8828.

PO-4622

22-Jul-10

Page N

21-Feb-13

PO10775

27-Feb-13

Approved by the Employer.

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Amounts (Rs)
Description

Lot
Engineer's
Estimate

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer

Employer's
Approval of
AR

Ref

Date

Date

PO-15481

12-Sep-14

3-Jul-15

PO-4624

22-Jul-10

20-Aug-13

PO-4606

17-Jul-10

30-Sep-11

PO-18569

15-Aug-15

PO-4660

24-Jul-10

Issuance of VO
to Contractor
Ref

Remarks

Date

exit of tailrace
VO-

Slope protection of

009

Agar Nullah

VO-

Backfill of 500 KW

010

switchyard at C3

C3

C3

143,891,528

117,085,498

PO18306
PO12031

5-Jul-15

Approved by the Employer.

22-Aug-13

Approved by the Employer.

21-Oct-13

Approved by the Employer.

Provide furnished
VO011

Prayer Hall ,
Laundry, Dining

C1

Hall, Living Room

5,410,284

PO7580

& Kitchen at C1
VO012

Changes in
Tunnels in Power

C3

House Area

1,608,653,402

Revised submission sent to the


Employer for approval

Retaining wall at
VO-

Permanent

013

Diversion Access

C1

19,883,974

21-Feb-13

PO10776

27-Feb-13

Approved by the Employer.

Road to Desander
VO014

Additional works at
Adit A5, A6, A7 &
A8

C3

Under preparation. Required


13,666,795

data from Contractor is awaited.

Page O

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

VO015

Amounts (Rs)
Description

Lot
Engineer's
Estimate

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer

Employer's
Approval of
AR

Ref

Date

Date

PO-5299

22-Nov-10

09-Dec-10

PO-5815

5-Feb-11

17-Sep-11

PO-13629

27-Feb-14

18-Mar-14

PO-5887

15-Feb-11

30-Sep-11

PO-7313

24-Aug-11

09-Dec-13

New Bridge Over


Neelum River at

C1

Nauseri

510,000,000

Issuance of VO
to Contractor
Ref
PO7626

Remarks

Date

26-Oct-11

Approved by the Employer.

21-Apr-12

Approved by the Employer.

Redesign of
VO016

diversion dam,
intake and

C1

sedimentation

7,488,000,000

PO8808

basin at C1
Increased
VO-

Hydraulic Capacity

C1,

017

for the Transfer

C2

9,963,301,194

PO-

19-Mar-

13917

14

Approved by the Employer.

Tunnels
VO018

To change the
status of strands

C3

anchors

2,176,500

PO7604

24-Oct-11

Approved by the Employer.

13-Dec-13

Approved by the Employer.

Construction of
retaining wall at
VO-

upstream intake

019

block along

C1

19,272,040

permanent access
diversion road

Page P

PO13004

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Amounts (Rs)
Description

Lot
Engineer's
Estimate

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer
Ref

Date

Employer's
Approval of
AR
Date

Issuance of VO
to Contractor
Ref

Remarks

Date

Widening of
VO020

existing narrow
access passing

C1

through Nauseri

954,981

PO-6700

30-May11

03-Jul-13

PO11671

06-Jul-13

Approved by the Employer.

28-Aug-13

Approved by the Employer.

village
Construction of
VO-

retaining wall

021

above Adit A1

C1

930,449

PO-7260

18-Aug-11

28-Aug-13

PO12105

portal
VO-

Procurement and

C1,

022

deployment of TBM

C2

23,000,473,174

c2

140,183,455

PO-8499

9-Mar-12

04-Jul-12

PO9479

Approved by the Employer.


16-Aug-12

Contractors approval is
awaited.

Microseismic
VO022-4

Monitoring and
Rock Burst

PO-18935

11-Sep-15

PO-8032

5-Jan-12

21-Feb-13

PO-10057

12-Nov-12

29-Jul-13

Prediction
VO-

Slope protection of

023

Deposit B

VO-

Gates and metal

024

works

C1

H1

151,696,239

1,779,276,437

Page Q

PO10777
PO11915

27-Feb-13

Approved by the Employer.

05-Aug-13

Approved by the Employer.

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Amounts (Rs)
Description

Lot
Engineer's
Estimate

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer
Ref

Date

Employer's
Approval of
AR
Date

Issuance of VO
to Contractor
Ref

Remarks

Date

Tuff boom log


VO-

barrier at intake for

025

controlling surface

C1

12,097,220

PO-9008

26-May-

Employer's Approval Awaited

12

debris
VO026

VO027

Concrete Lining of

C1,

Headrace Tunnel

C2,

(non-TBM section)

C3

10,194,001,365

PO-12173

07-Sep-13

13-Sep-13

12173

07-Sep-13

Approved by the Employer.

Approved by the Employer.

Steel liner on
Jhelum River

PO-

C2

9,689,029,025

PO-12345

27-Sep-13

10-Jan-14

Crossing

PO13266

13-Jan-14

Note: In calculation US $ rate


:Rs. 60.35 (PO-13507) dated
07 Feb 2014.

Jandarbain Nullah VO-

Channelization and

028

construction of

22-May-

C2

129,817,430

PO-14442

C2

179,762,000

PO-14980

20-Jul-14

16-Feb-15

C1

247,958,342

PO-9173

27-Jun-12

4-Sep-13

14

15-Apl-15

PO17536

18-Apl-15

Approved by Employer

17-Feb-15

Approved by Employer

4-Sep-13

Approved by the Employer.

bridges
VO029

VO030

Additional haulage
from Adit A4 to new
spoil deposit
Cofferdam Change from earth
to concrete dam

Page R

PO16962

PO12153

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Amounts (Rs)
Description

Lot
Engineer's
Estimate

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer

Employer's
Approval of
AR

Ref

Date

Date

Issuance of VO
to Contractor
Ref

Remarks

Date

Extension of
VO031

retaining wall at
Agar Nullah for

C3

172,518,481

PO-9247

8-Jul-12

3-Jul-13

C2

4,262,200

PO-9132

20-Jun-12

4-Sep-13

427,012,913

PO-17679

6-May-15

27-May-15

protection of

PO11700

10-Jul-13

Approved by the Employer.

6-Sep-13

Approved by the Employer.

1-Jun-15

Approved by Employer

switchyard
VO032

Retaining wall for


protection of TBM
camp

PO12165

Increased
VO-

thickness of wire

033

mesh from 4.2mm

C1,C2
,C3

PO17951

to 6mm
VO-

Self drilling rock

034

bolts

VO035

VO036

Under preparation. Rates to be

C2,C3

15,000,000

C3

115,930,937

PO-9455

10-Aug-12

23-Jul-13

C1

17,426,430

PO-9164

26-Jun-12

22-Oct-13

finalized with Contractor.

Installation of
multipoint
extensometers
Improvement of
access road to
Contractor's camp.

Page S

PO11832

PO12548

27-Jul-13

Approved by the Employer.

29-Oct-13

Approved by the Employer.

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Amounts (Rs)
Description

Lot
Engineer's
Estimate

HSFO WARTSILA
VO-

Gensets for

037

alternate power
supply to sites
Provision,

VO-

operation and

038

maintenance of
eight (8) vehicles

VO-

Deletion of 11 kV

039

Transmission Line

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer

Employer's
Approval of
AR

Ref

Date

Date

PO-9201

30-Jun-12

27-Sep-13

C1,
C2,

6,475,614,423

C3

Issuance of VO
to Contractor
Ref

PO12385

Date

1-Oct-13

PO-11065

11-Apr-13

Employer vide letter ref.

16-Jul-13

MD/CEO/NJHPC/DC/W-

C3

C1

Approved by the Employer.

Dropped as disapproved by the

C1,
C2,

Remarks

21/6075-79 dated 16 July 2013.


(16,600,588)

PO-12344

27-Sep-13

11-Sep-13

1,310,000,000

PO-12466

11-Oct-13

9-Jun-14

PO12344

27-Sep-13

Approved by the Employer.

Procurement of
VO-

SS-1 Raw Stone

C1,

040

for Aggregate on

C2

PO-

2 -Apl-

17372

2015

Approved by the Employer.

Lots C1 & C2
Additional Works
VO041

for Supply and


Erection of

E1

Under preparation (Escalatable

173,147,779

@ 1.5)

Auxiliary Power
Supply

VO-

Import of 35,000

C1,

042

ton of Grade 80

C2,

236,600,711

PO-14063

7-Apr-14

Page T

14-May-14

PO-

15-May-

14368

14

Approved by the Employer.


Calculated $ @ Rs 97.78 (Refer

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Amounts (Rs)
Description

Lot
Engineer's
Estimate

Slag from China

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer
Ref

Date

Employer's
Approval of
AR
Date

Issuance of VO
to Contractor
Ref

Date

C3

PO-14203) Increased to 35,000

and UAE
VO-

525 kV XPLE

043

Cables

VO-

Post tensioning

044

Work at Spillway

VO045

Green Stone

046

quarry Exploitation

VO-

Concrete Class-E

047

spillway

VO-

Dumping at Cadet

048

College

049

E1

753,763,934

PO-15140

8-Aug-14

7-Oct

C1

186,858,054

PO-18240

29-Jun-15

C3

49,029,429

PO-17385

3-Apl-15

22-Jul-15

C1

782,682,911

PO-15947

7-Nov-14

C1

304,539,496

PO-16551

7-Jan-15

C3

2,589,884

Po-17289

9-Jan-15

PO-17093

28-Feb-15

NOT USED

VO-

Drainage Gallery

050

C1

VO-

Water Supply,

C1

114,919,663

PO-17093

28-Feb-15

C3

33,060,791

PO-17633

28-Apr-15

Page U

PO19072

13-Oct-15

Submitted to the Employer

Building

VO-

VO-

Ton

Construction of
Administration

Remarks

2-Mar-15

PO18454

PO17116

27-Jul-15

Approved by the Employer

5-Mar-15

Approved by the Employer

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

051

Amounts (Rs)
Description

Lot
Engineer's
Estimate

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer

Employer's
Approval of
AR

Ref

Date

Date

PO-17539

18-Apl-15

27-May-15

PO-18807

31-Aug-14

Issuance of VO
to Contractor
Ref

Remarks

Date

Sewerage &
Surface work C3

VO052

Galvanized Steel
Stair Nozing,

C3

566,472

Power House C3

VO-

Drainage Gallery

C1

053

C3

C3

PO17970

2-Jun-15

Approved by Employer

720,000 *

Earthing at lot C1 &


VO-

C3 (Contractor

054

Value) : C1

C1,C3

205,751,859 *

C3

35,694,328 *

:C3
Power House
VO-

ceiling (No Detail

055

from Contractor
Yet)

VO056

VO057

Closed Cell
Polyurethane

448,000 *

sheets
Tailrace Tunnel
Dewatering System
( by DTL)

C3/H1
9

229,569,358

Page V

Us$ 2,546,188.52 (2015)


Rs: 11,563,931.14 (2015)

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Amounts (Rs)
Description

Lot
Engineer's
Estimate

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer
Ref

Date

PO-17452

10-Apl-15

PO-17649

29 Apl-15

PO-19134

9-Oct-15

PO-19458

10-Nov-15

Employer's
Approval of
AR
Date

Issuance of VO
to Contractor
Ref

Date

Bridge Crain Rail


setting in Power
VO-

House area C3

058

(Awaiting complete

C3

12,635,967 *

C2

75,974,357 *

submission from
the Contractor)
VO-

Pipe Canopy Under

059

Jhelum crossing

VO060

Protective works in
front of Lining

C2

66,623,909

Factory-C2
Earthing Grid

VO-

Chatter Class

061

water works Check

C3

208,427,516 *

#61 & 54
VO062

Geotextile Strips

VO-

A8(old) Spoil Area

063

Retaining Wall

VO-

Crack Inducer in

064

Construction Joints

C1,C2
,C3
C3
C1,C2
,C3

9,356,552

16,174,060 *

6,141,646

Page W

28-Sep-15

PO19054

30-Sep-15

Remarks

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Amounts (Rs)
Description

Lot
Engineer's
Estimate

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer
Ref

Date

of the Inverts

VO-

Load Cell in

065

Powerhouse Area

VO-

Boulder Collection

066

from Agar Nullah

VO-

Protection of Soil

067

Deposit at Koroli

VO-

Grouting Gallery at

068

Lot C1

V0-

Clay Material for

069

C1

Total

C3

6,023,515

PO-19587

25-Nov-15

C3

271,965,980

PO-19243

21-Oct-15

C2

33,624,291

Po-19548

23-Nov-15

C1

14,624,322

PO-19756

25-Nov-15

C1

135,638,298

PO-20165

26-Jan-16

78,736,066,632

Total VOs

71

Dropped / Disapproved

Approved by Employer

39

Employer's Approval Awaited

19

Under Preparation by Engineer

10

Page X

Employer's
Approval of
AR
Date

Issuance of VO
to Contractor
Ref

Date

Remarks

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

VO
No.

Not Used

Amounts (Rs)
Description

Lot
Engineer's
Estimate

MONTHLY PROGRESS REPORT


JANUARY 2016

Submission of AR
to Employer
Ref

Date

Page Y

Employer's
Approval of
AR
Date

Issuance of VO
to Contractor
Ref

Date

Remarks

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

ANNEXURE D: CONTRACTORS CLAIMS

Page Z

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

NEELUM JHELUM HYDROELECTRIC PROJECT


STATUS OF CLAIM
AS ON 25 JANUARY 2015

AMOUNT (Rs)

Claim
No.

1-T

Description

EOT due to
non- availability
of land and
electricity etc.

Lot

C1
C2
C3

Amount
Claimed by
Contractor

2,010,566,88
2

Amount
Recommende
d by
Engineer

1,428,804,800

Page AA

Amount
approved by
Employer

Remarks

1,428,804,800

Early in the project,


the
Contractor
submitted a claim for
extension of time due
to the late handing
over of the land. At
that
stage,
the
Engineer
indicated
that the motivation
was inadequate for
the claim to be
successful but the
Contractor was not
prepared to accept
the ruling at the time.
With the continuation
and increase in the
problems relating to
non-availability
of
land and electricity
supply, it became
apparent that this will
have an effect on the
schedule and the
parties agreed to
enter
into
negotiations
to
resolve
the
contractual
ramifications
amicably at a time
when the most of the
problems
were
successfully
addressed
and
resolved.
Toward the middle of
2009,
indications
were
that
the
problems would be
solved in the near

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

AMOUNT (Rs)

Claim
No.

Description

Lot

Amount
Claimed by
Contractor

Amount
Recommende
d by
Engineer

Amount
approved by
Employer

Remarks
future
and
the
decision was made to
re-approach
the
subject to determine
the
influence
of
mainly
the
late
availability of land
and electricity from
the start of the project
to 30 June 2009.
The
Contractor
submitted
a
motivated statement
requesting
an
extension of 419
days to the project
completion date.
Engineer evaluated
EOT of 304 days and
forwarded
to
the
Employer vide PO3966 dated 31 March
2010. The same was
approved
by
the
Employer.
Contractor submitted
EOT
cost
vide
GZBZJ-NJC-1731 (R4390) dated 14 Dec
2010. Engineer vide
PO-8723 dated 25
April 2012 estimated
cost of Contractor's
Chinese
Support
Staff covered by EOT
and proposed onaccount
payment
which
would
be
adjusted while the
claim is evaluated in
detail.
Employer accorded
approval
vide
MD/CEO/NJHPC/DC/
W-21/4449-57
(R-

Page BB

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

AMOUNT (Rs)

Claim
No.

2-T

Description

EOT due to
suspension of
work at
Contractor's
camp etc.

Lot

Amount
Claimed by
Contractor

Amount
Recommende
d by
Engineer

Amount
approved by
Employer

9038) dated 22 Feb


2013
and
made
payment under IPC #
54.
The
Engineer
recommended
$12,000,000 and the
Employer
paid
$
40,000,000 on 27
Nov 2014 @ Rs.
101.9376
and
$
8,000,000 on 25 May
2015
@
Rs.
102.1318.
Engineer evaluated
47 days EOT and
forwarded
to
the
Employer
for
approval vide PO3640.

C2

3-T

EOT due to
Contractor's
labour strike

C1

4-C

Compensation
cost due to
Electricity
Supply by
Contractor

C1
C2
C3

Remarks

388,892,120

330,270,204

330,270,204

Employer's approval
is awaited.
Contractor's
response
to the
Engineer's
queries
vide
PO-4288
is
awaited.
Engineer evaluated
initial claim (NJC2159 & 2355) for
period from Jan 2008
to June 2011 and
recommended
Rs
275,597,699
vide
PO-6999. Employer
approved the same
and paid under IPC #
35.
Engineer evaluated
2nd
claim
(NJC2919) for period from
July 2011 to Feb
2012
and

Page CC

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

AMOUNT (Rs)

Claim
No.

5-C

6-C

Description

Lot

Amount
Claimed by
Contractor

Amount
Recommende
d by
Engineer

Amount
approved by
Employer

Remarks
recommended
Rs.
54,672,505 vide PO8988.
Employer accorded
approval
vide
MD/CEO/
NJHPC/DC/W21/4449-57
and
made payment under
IPC # 54.
Engineer evaluated
claim (NJC-1171 &
2249)
and
recommended
the
compensable
cost
vide
PO-8913.

Compensation
Cost due to
External
Aggregate
brought at C1

C1

Compensation
cost for
Diversion
Tunnel

C1

95,514,964

510,943,500

1,960,526

494,169,721

1,960,526

488,116,377

Employer accorded
approval
vide
MD/CEO/NJHPC/DC/
W-21/4449-57
and
made payment under
IPC # 54.
Contractor
made
submission vide his
letter No. NJC-2195.
Engineer evaluated
Rs. 481,867,874 for
diversion tunnel and
Rs 6,523,895 for
temporary bridge vide
PO-6924. Employer
approved the same
and paid IPC # 35.
Engineer evaluated
Rs 6,053,344 for
dedicated batch plant
vide PO-7605. The
Employer's approval
for this amount is
awaited.

Page DD

ENGINEERING SERVICES FOR CONSTRUCTION SUPERVISION OF


NEELUM-JHELUM HYDROELECTRIC PROJECT

MONTHLY PROGRESS REPORT


JANUARY 2016

AMOUNT (Rs)

Claim
No.

Description

Lot

Amount
Claimed by
Contractor

Amount
Recommende
d by
Engineer

Amount
approved by
Employer

7-C

Insurance
Deductible Flood (July
2010)

C1
C2
C3

30,175,000

30,175,000

8-C

Stoppage of
Work due to
strike of 17
May 2013

C1
C2
C3

397,906,902

95,304,956

9-C

Subsequent
Legislation Increase in
Rate of
CED/FED

C1
C2
C3

22,297,962

10-C

Work Stoppage
at Steel Liner
Yard

C2

675,099

380,523

11 C

Claim for idle


personnel in
Steel Liner
factory

C2

33,755,099

3,727,364,553

2,381,341,122

2,249,151,907

Total (Rs)

Page EE

Remarks
Contractor
made
submission thru letter
No.
NJC-3546.
Engineer determined
vide
PO-10063.
Employer's approved
awaited.
Contractor
made
submission thru letter
No.
NJC-4576;
followed by other
submissions.
Contractor
made
submission thru letter
No.
NJC-1930.
Engineer rejected the
claim vide PO-12602.
Contractor
made
submission thru letter
No. NJC-5035; Under
Engineer review.
The
Contractor
submitted claim vide
GZBZJ-NJC-8066
dated 8 March 2015
(R-15201)
under
Engineer's review.

Вам также может понравиться