Introduction
Morocco now has one of the largest ore slurry pipeline
systems in the world
The main delivery pipeline is 187 km long and transports
4400t/h of phosphate ore
The system has become an integral part of the OCP value
chain and their expansion plans
Introduction
Client: OCP
Client representative: JESA
EPC Contractor: Tekfen Construction
Design engineers: Paterson & Cooke and Tekfen
Engineering
Construction Statistics
50 000 tons of pipeline steel
1.7 million man days
At the peak of construction - 1800 people and 800
construction machines were employed
This paper provides a system overview and highlights some
of the challenges
Location
Diameter
Nominal Length
Daoui Feeder
DN450
22 km
DN400
1.8 km
DN300
1.8 km
Halassa Feeder
DN500
15 km
DN500
10 km
DN900
187 km
Total
227 km (10 km
future)
System Description
22.2 km pipeline
1400 t/h
2 trains of 4 pumps
each
Variable choke
station
1.8 km pipeline
700 & 1400 t/h
Utilises thickener
underflow pumps
14.9 km pipeline
1500 t/h
2 trains of 5 pumps
each
187 km
pipeline
4400 t/h
2 trains of 6
pumps each
Valve Station
Pressure
Monitoring
Stations
Variable
choke station
8 Storage
Tanks
Feeder Pipelines
Equipment Piping
Overland piping dimensional standard according to API 5L
Main line has API 5L X70 material
Feeders have API 5L Grade B material
Flanges are ASME B16.5 and B16.47 Series A with ASTM
A105 and ASTM A694 F70 material
Overland pipelines are internally lined with HDPE
Slurry station pipelines are lined with Polyurethane or
rubber
Water pipeline are internally lined with Epoxy
Equipment Piping
The test loop is used to monitor
the pipeline hydraulic losses
before the slurry enters the
main pipeline. The
requirements made design and
manufacture a challenge:
Matches the mainline ID
Smooth joints despite being
made up of several
relatively tight radius bends
HDPE liner sections were
custom made for each
spool and have a finely
grooved surface finish
creating smooth join
Slurry Pipelines Conference 2015, Khouribga to Jorf Lasfar Pipeline , Slide 19
Equipment Piping
High pressure PU-lined pipe spools for pump and
choke stations
Cast into straights, bends and tees using unique, removable patterns
Special rubber lined steel gaskets with inward facing ears contain
the pressure while allowing a smooth transition between spools
Fixed
chokes
Bursting
disk take-off
Variable choke
bypass
Choke
loops
Slurry feed
line
Low flow
High flow
Pumping
head
Pumping
head
Choke
head
Choke
head
Equipment Tanks
Each tank is 20m x 20m
250 kW agitators
Head Station: 4 tanks
(2 groups of 2 tanks each)
Hydrostatic Testing
Pipeline must be pressure tested to 1.1 the design pressure
for not less than 4 hours (ASME B31.4)
With multiple elevation changes, pipeline must be divided
into sections for testing
Plan was devised to
Minimize number of test sections
Allow filling from Oum er Rbia River
Minimize water discharge
Allow test and filling equipment to be removed after
testing
Hydrostatic Testing
Test Plan
showing test
sections, transfer
points and test
heads
Transfer point
between
sections 2 and 3
Conclusion
The sheer size and complexity of the OCP Khouribga to Jorf
Lasfar phosphate slurry pipeline presented a number of unique
engineering challenges, all of which were overcome. The
system has since been commissioned and it provides OCP
with a highly efficient transport system which is an essential
component of their value chain.
Pipeline
ROW