Вы находитесь на странице: 1из 6

Title:

INSPECTION AND TEST PLAN (ITP)

Doc. No.:
DBB-BNCPP-B-M-V29-0015

Rev.:
B

Date:
02.09.2015

Revision Sheet

REVISION

DATE

DESCRIPTION OF CHANGE

23-JULY-2015

Issued for Review

02-SEPT-2015

Issued for Approval

Hold List
HOLD NO.

DESCRIPTION

5.1 (Page 4)

RT status waiting for pending TQ.

5.1 (Page 5)

RT status waiting for pending TQ.

File Name: CCM-QCP-623- ITP

STATUS

Page:
2 of 6

INSPECTION TEST PLAN - GTC/GTG EXHAUST STACK for BARONIA PROJECT

Page: 03 of 06

PROJECT :
BARDEGG-2 & BARONIA
COMPANY :
PETRONAS
PURCHASER: HYUNDAI HEAVY INDUSTRIES CO LTD
TAG No. :
A-2401 / A-2402 (WHRU EXHAUST STACK) - 2units & GT7510 / GT7520 / GT7530 / GT7540 (GTG EXHAUST DUCT) - 4units
INSPECTION: HYUNDAI / PETRONAS

ITEM : GENERAL
Activity No.

CHARACTERISTIC

ITP NO. : CCM05/HHI/2015-03


REV. NO.
B
DATE : 02/09/2015
P.O. NO. : QD546BCQ1A

TYPE OF CHECK

QUANTUM OF
CHECK

REF.DOC.

ACCEPTANCE STANDARD

RECORD

SUB VENDOR

CERS

HHI

PCSB

Contract & Purchase Order

Contract & P.O (PO No.:


QD546BCQ1A)

Contract & P.O (PO No.:


QD546BCQ1A)

1. CONTRACT/PO REVIEW
1.1

Contract & PO Review

2. DOCUMENT APPROVAL
2.1

GA Drawings

Approval of Drawing

100%

GA Drawings (DBB-BNCPP-B-MV29-0005)

Approved Drawings

2.2

WPS/PQR and Welder


Qualifications

Approval of Procedure

100%

WPS/PQR and Welder Certificate


(DBB-BNCPP-B-M-V29-0021) /
CSP-18

Approved WPS/PQR and Welder


Certificate

2.3

NDE Procedure and Operator


Qualification

Approval of Procedure

100%

NDE Procedure and Operator


Certificate (DBB-BNCPP-B-M-V290017)

Approved NDE Procedure and


Operator Certificate

2.4

ITP

Approval of ITP

100%

Inspection & Test Plan (DBBBNCPP-B-M-V29-0015)

Approved Inspection & Test Plan

PIM

Project Specification

GAD,WPS/PQR,Welder
Qualification & ITP

PIM MOM

AS PER DRAWING/ ASME


Material Test Report / Mill
AS PER DRAWING/ ASME SEC.IISEC.II-A (EN10204 Type 3.1) &
Certificate. (CiTECH-QA-03P-01A)
A & PTS 15.10.11
PTS 15.10.11

3. PRE INSPECTION MEETING


3.1

ITEM : GTC EXHAUST STACK - 2 units


1. MATERIAL INSPECTION

1.1

Stainless Steel Materials

Visual,Chemical, Tensile,
Hardness & Heat Treatment
verified with Mill Certificate

100%

1.2

Expansion Joint

Visual,Chemical, Tensile,
Hardness & Heat Treatment
verified with Mill Certificate

100%

AS PER DRAWING

AS PER DRAWING

Material Test Report / Mill


Certificate. (CiTECH-QA-03P-01A)

1.3

Fastners ( Stud & Bolts)

Visual,Chemical, Tensile,
Hardness & Heat Treatment
verified with Mill Certificate

Each Heat No.

AS PER DRAWING & PTS


30.10.02.11

AS PER DRAWING & PTS


30.10.02.11

Material Test Report / Mill


Certificate. (CiTECH-QA-03P-01A)

1.4

Positive Material Identification

Stainless Steel Material

100%

PMI Report

As Per Drawing / ASME Sec.II-A As Per Drawing / ASME Sec.II& PMI Procedure (DBB-BNCPP-B- A & PMI Procedure (DBBBNCPP-B-M-V29-0048)
M-V29-0048)

REMARKS

INSPECTION TEST PLAN - GTC/GTG EXHAUST STACK for BARONIA PROJECT


TYPE OF CHECK

QUANTUM OF
CHECK

REF.DOC.

ACCEPTANCE STANDARD

RECORD

SUB VENDOR

CERS

HHI

PCSB

Measure of Dimension

100%

APPROVED CITECH DRAWING

APPROVED CITECH
DRAWINGS & QCP-08.

Fit-up & Edge Preparation of


Exhaust Stack Parts

Dimensions, Edge
Preparations & Alignment

100%

Approved CITECH Drawing

Approved CITECH Drawing

Fit-Up Report ( CITECH-QA-03P03A)

SW/R

Weld Map

Doc. Review

100%

Weld Map

As Per ASME SEC-II C / PTS


Spec. (PTS 31.22.20.31)

Consumable Certificate

CHARACTERISTIC

Activity No.

2. MARKING & CUTTING


2.1

Page: 04 of 06

Marking & Cutting of GTC


Exhaust Stack

3. FIT-UP & EDGE PREPARATIONS


3.1
4. WELDING
4.1
4.2

Welding Consumable

Doc. Review

100%

As Per ASME SEC-II C / PTS


31.22.20.31, CSP-17

4.3

Welding Works

Check on Welding Parameter


and Visual

100%

As Per ASME SEC-XI / PTS


31.22.20.31 / CSP-14/15/16

As Per ASME SEC-XI / PTS


Spec. (PTS 31.22.20.31)

Welding Summary Sheet

5. NON-DESTRUCTIVE TESTING (NDT)


5.1

Long Seam & Circ. Seam Butt


Welds

Radiographic Testing

100%

As Per SEC-V ,VIII Div-1 / PTS


31.22.20.31

As Per ASME SEC VIII Div-1


UW 51/ PTS 31.22.20.31

RT Films & Reports (GI-RT-ASME01)

5.2

Other Joints

Dye Penetrant Testing

10%

As Per SEC-V ,VIII Div-1 / PTS


31.22.20.31

As Per SEC ASME VIII Div-1/


PTS 31.22.20.31

DPT Reports (GI-PT-ASME-01

R/M

Measurement of Dimension &


Welding Visual

100%

Approved CITECH Drawings

Approved CITECH Drawings

Dimensional Report & Visual


Report (CiTECH-QA-03P-09A)

Salt Test and Pull-Off Test

Each Paint
Specification

Painting Procedure (DBB-BNCPP- Painting Procedure (DBBTest Panel Report (Salt Test and
B-M-V29-0019) / PTS 30.48.00.31 BNCPP-B-M-V29-0019) & PTS
Pull-Off Test)
30.48.00.31
/ CSP-10

Painting Procedure (DBB-BNCPP- Painting Procedure (DBBB-M-V29-0019) / PTS 30.48.00.31 BNCPP-B-M-V29-0019) & PTS
30.48.00.31
/ CSP-09

6. FINAL DIMENSION & VISUAL


6.1

Completed Exhaust Stack

7. BLASTING & PAINTING


7.1

Test Panel

7.2

Blasting and Painting

Surface Preparation & Blasting


Internal Coating

100%

External Coating

Painting Report

8. FINAL INSPECTION
8.1

Visual & Cleanliness Inspection

GTC Exhaust Stack

100%

As Per Approved Drawing

As Per Approved Drawing

Review of Stage Inspection


Report/Test Report

100%

As Per PTS 31.22.10.35

As Per PTS 31.22.10.35

All Relevant Doc. & Report

W/R

Packing List

Release Note by HHI

9. FINAL DOCUMENT
9.1

Quality Record Review

10. PACKING & SHIPMENT


10.1

Presevation & Packing


Inspection

Review of Packed Item and


Packing List

100%

10.2

Inspection Release Note

Issuance of IRN

Unpacking & Preservation


Unpacking & Preservation
Procedure (DBB-BNCPP-B-M-V29- Procedure (DBB-BNCPP-B-MV29-0039)
0039)
As Per Approved Drawing &
Packing List

As Per Approved Drawing &


Packing List

REMARKS

INSPECTION TEST PLAN - GTC/GTG EXHAUST STACK for BARONIA PROJECT


ITEM : GTG EXHAUST STACK - 4 units
Activity No.

CHARACTERISTIC

TYPE OF CHECK

QUANTUM OF
CHECK

REF.DOC.

ACCEPTANCE STANDARD

RECORD

Page: 05 of 06

SUB VENDOR

CERS

HHI

PCSB

AS PER DRAWING/ ASME


Material Test Report / Mill
AS PER DRAWING/ ASME SEC.IISEC.II-A (EN10204 Type 3.1) &
Certificate. (CiTECH-QA-03P-01A)
A & PTS 15.10.11
PTS 15.10.11

1. MATERIAL INSPECTION

1.1

Stainless Steel Materials

Visual,Chemical, Tensile,
Hardness & Heat Treatment
verified with Mill Certificate

100%

1.2

Expansion Joint

Visual,Chemical, Tensile,
Hardness & Heat Treatment
verified with Mill Certificate

100%

AS PER DRAWING

AS PER DRAWING

Material Test Report / Mill


Certificate. (CiTECH-QA-03P-01A)

1.3

Fastners ( Stud & Bolts)

Visual,Chemical, Tensile,
Hardness & Heat Treatment
verified with Mill Certificate

Each Heat No.

AS PER DRAWING & PTS


30.10.02.11

AS PER DRAWING & PTS


30.10.02.11

Material Test Report / Mill


Certificate. (CiTECH-QA-03P-01A)

1.4

Positive Material Identification

Stainless Steel Material

100%

PMI Report

Measure of Dimension

100%

APPROVED CITECH DRAWING

APPROVED CITECH
DRAWINGS & QCP-08.

GTG Exhaust Duct Parts

Dimensions, Edge
Preparations & Alignment

100%

APPROVED CITECH DRAWING

APPROVED CITECH
DRAWINGS & QCP-08.

Fit-Up Report (CITECH-QA-03P03A)

SW/R

4.1

Weld Map

Doc. Review

100%

Weld Map

4.2

Welding Consumable

Doc. Review

100%

As Per ASME SEC-II C / PTS Spec.


(PTS 31.22.20.31)

As Per ASME SEC-II C / PTS


Spec. (PTS 31.22.20.31)

Consumable Certificate

4.3

Welding Works

Check on Welding Parameter


and Visual

100%

As Per ASME SEC-XI / PTS Spec.


(PTS 31.22.20.31)

As Per ASME SEC-XI / PTS


Spec. (PTS 31.22.20.31)

Welding Summary Sheet

As Per Drawing / ASME Sec.II-A As Per Drawing / ASME Sec.II& PMI Procedure (DBB-BNCPP-B- A & PMI Procedure (DBBBNCPP-B-M-V29-0049)
M-V29-0049)

2. MARKING,CUTTING & FORMING


2.1

Marking & Cutting of GTG


Exhaust Duct Parts

3. FIT-UP & EDGE PREPARATIONS


3.1
4. WELDING

5. NON-DESTRUCTIVE TESTING ( NDT )


5.1

Long Seam & Circ. Seam Butt


Welds

Radiographic Testing

100%

As Per SEC-V ,VIII Div-1 / PTS


31.22.20.31

As Per ASME SEC VIII Div-1


UW 51/ PTS 31.22.20.31

RT Films & Reports (GI-RT-ASME01)

5.2

Other Joints

Dye Penetrant Testing

10%

As Per SEC-V ,VIII Div-1 / PTS


31.22.20.31

As Per SEC ASME VIII Div-1/


PTS 31.22.20.31

DPT Reports (GI-PT-ASME-01

R/M

REMARKS

INSPECTION TEST PLAN - GTC/GTG EXHAUST STACK for BARONIA PROJECT


TYPE OF CHECK

QUANTUM OF
CHECK

REF.DOC.

ACCEPTANCE STANDARD

RECORD

SUB VENDOR

CERS

HHI

PCSB

Measurement of Dimension &


Welding Visual

100%

Approved CITECH Drawings

Approved CITECH Drawings

Dimensional Report & Visual


Report (CiTECH-QA-03P-09A)

Salt Test and Pull-Off Test

Each Paint
Specification

Painting Procedure (DBB-BNCPP- Painting Procedure (DBBTest Panel Report (Salt Test and
B-M-V29-0019) / PTS 30.48.00.31 BNCPP-B-M-V29-0019) & PTS
Pull-Off Test)
30.48.00.31
/ CSP-10

Painting Procedure (DBB-BNCPP- Painting Procedure (DBBB-M-V29-0019) / PTS 30.48.00.31 BNCPP-B-M-V29-0019) & PTS
30.48.00.31
/ CSP-09

CHARACTERISTIC

Activity No.

Page: 06 of 06

6. FINAL DIMENSION & VISUAL


6.1

Completed GTG Exhaust Stack

7. BLASTING & PAINTING


7.1

Test Panel

7.2

Blasting and Painting

Surface Preparation & Blasting


Internal Coating

100%

Painting Report

External Coating
8. FINAL INSPECTION

8.1

Visual & Cleanliness Inspection

GTG Exhaust Stack

100%

As Per Approved Drawing

As Per Approved Drawing

Review of Stage Inspection


Report/Test Report

100%

As Per PTS Spec. (PTS


31.22.10.35)

As Per PTS Spec. (PTS


31.22.10.35)

All Relevant Doc. & Report

W/R

Packing List

Release Note by HHI

9. FINAL DOCUMENT
9.1

Quality Records Review

10. PACKING & SHIPMENT


10.1

Presevation & Packing


Inspection

Review of Packed Item and


Packing List

100%

10.2

Inspection Release Note

Issuance of IRN

Unpacking & Preservation


Unpacking & Preservation
Procedure (DBB-BNCPP-B-M-V29- Procedure (DBB-BNCPP-B-MV29-0039)
0039)
As Per Approved Drawing &
Packing List

As Per Approved Drawing &


Packing List

GENERAL
NOTES

1. ALL MEASURING INSTRUMENTS SHALL BE CALIBRATED


2. ALL COLUMN IN ITP SHALL BE SIGNED-OFF AFTER COMPLETION OF INSPECTION
3. ALL MATERIAL ORIGIN FROM CHINA, INDIA, AND EASTERN EUROPE SHALL NOT BE USED
4. INSPECTION NOTIFICATION SHELL BE SUBMITTED FOR "H", "W", "SW" POINT IN THE ITP 10 WORKING DAYS IN ADVANCE USING INSPECTION NOTIFICATION TO HHI INSPECTION CO-ORDINATOR.
5. ALL SHARP EDGES SHALL BE ROUNDED (MIN. RADIUS > 2mm)
6. IN CASE INSPECTION POINT SHOWS TWO (2) KIND OF INSPECTION POINTS WITH FORWARD SLASH ("/") THIS MEANS "AND", NOT "OR".
7. INSPECTION POINTS IN APPROVED ITP CAN BE CHANGED WHEN REQUIRED BY PROJECT

LEGENDS

CERS=CITECH ENERGY RECOVERY SYSTEM ; HHI= HYUNDAI HEAVY INDUSTRIES ; PCSB= PETRONAS CARIGALI SDN BHD; PTS= PETRONAS TECHNICAL SPECIFICATION.
H=HOLD ; SW=SPOT WITNESS ;R=REVIEW;M=MONITORING;W=WITNESS ; RW=RANDOM WITNESS; A=APPROVAL

SUDHANKUMAR
Prepared by CITECH

VEERABATHIRAN
Reviewed by CITECH

Approved by HYUNDAI

REMARKS

Вам также может понравиться