Table of Contents

1. Project Data................................................................................................................ 2
2. Project Scope and Site Description.........................................................................2
2.1. Location and General Composition...................................................................2
2.2. Scope of Works..................................................................................................... 3
2.2.1. Roads & Site Clearance................................................................................3
2.2.2. Site access and traffic management..........................................................5
2.2.3. Road Markings and Signs.............................................................................5
2.2.4. Pavements...................................................................................................... 6
2.2.5. Utilities............................................................................................................ 6
2.2.6. Street Lighting............................................................................................... 8
2.2.7. Intelligent Transport System (ITS).............................................................8
2.2.8. Surface water Drainage.............................................................................. 10
2.2.9. Environmental.............................................................................................. 10
2.2.10.

Foul Sewerage.......................................................................................... 10

2.2.11.

Treated Sewerage Effluent (TSE)...........................................................10

2.2.12.

Landscape.................................................................................................. 11

2.2.13.

Public Utility Services..............................................................................13

2.2.14.

Inspection of Site..................................................................................... 13

2.2.15.

Protection of Underground Services and Traffic Diversion...............13

2.2.16.Coordination with other Contractors.......................................................13


3. Planning Methodology............................................................................................. 13
4. Construction Approach:.......................................................................................... 14
4.1. Package 1............................................................................................................ 15
4.2. Package 2............................................................................................................ 67
5. Assumptions for the Baseline programme:.......................................................104
6. Baseline Programme Description:.......................................................................104
6.1. General.............................................................................................................. 104
6.1.1. Construction milestone:...........................................................................104
6.1.2. Mobilisation................................................................................................ 104
6.1.3. Permits/Approvals :................................................................................... 105
6.1.4. Provisional Sum Instruction.....................................................................105
Baseline Schedule
Page No: 1

Design and construction of lateral interceptor sewers, Al Wakra

6.2. Engineering....................................................................................................... 105


6.2.1. General Submittals: ................................................................................105
6.2.2. Material Submittal & Approval: ............................................................105
6.2.3. Method Statement Submittal & Approval : .........................................105
6.2.4. Subcontractor Submittal & approval:....................................................105
6.3. Procurement:.................................................................................................... 105
6.4. Construction..................................................................................................... 105
6.4.1. Part-1........................................................................................................... 105
6.4.2. Part 2........................................................................................................... 106
6.5. Project Close Out............................................................................................. 107
6.6. Working hours:................................................................................................. 107
6.7. Programme Requirements:............................................................................ 107
6.8. Critical Path :.................................................................................................... 107
7. Risk Assessment:................................................................................................... 146

Contract:

1. Project Data

Baseline Schedule
Page No: 2

Design and construction of lateral interceptor sewers, Al Wakra

DESIGN AND CONSTRUCTION OF


LATERAL INTERCEPTOR SEWERS, AL
WAKRA
(LIS-02) - (C727/2)

Client:

Public Work Authority

ENGINEER:

CH2M HLL international B.V

2.1.1 The City of Doha is experiencing significant growth, and the need for
an efficient, flexible and reliable wastewater management system is
vital. The current pace of growth is posing major challenges for the
existing drainage infrastructure. The Authority is the service provider

Consultant:

for sewerage services in Doha, including the sewerage collection

Contractor:

QBC Qatar Building Company

Project Start Date:

04th October 2015

Project Completion Date:

15th December 2018

network and associated treatment works.

2.1.2 To address the need for improvements, the Authority has embarked on
a major
programme of expansion and upgrades that consists of numerous

Contract Duration:

1,169 days

works currently in various stages of development and completion. The

Contract Value:

QR. 824,849,867.62

Inner Doha Re-sewerage

Maintenance Period:

365 days.

Implementation Strategy (IDRIS) Programme is a world-class solution


developed by the Authority to upgrade and expand the sewerage
infrastructure in order to accommodate the projected population
growth for an additional 1 million people in Dohas oldest area the
south catchment (around 680 km2).

2.1.3 IDRIS is strategic in nature and was developed to convert the foulsewer drainage in the Doha South Catchment from a pumped network
to a gravity sewer network. The IDRIS Programme both supports and
contributes to achieving the Qatari National Vision 2030 to transform
Qatar into an advanced country capable of sustaining its own
development and providing a high standard of living for its people. The
Authoritys vision calls for the delivery of state-of-the-art, sustainable,
world-class buildings and infrastructure that can fulfil this vision.
2. Project Scope and Site Description
2.1.

Project Background

2.1.4 The IDRIS scheme is comprised of a number of Lateral Interceptor


Sewers (LIS) that will be used to intercept flows in the existing high-

Baseline Schedule
Page No: 3

Design and construction of lateral interceptor sewers, Al Wakra

level system and transfer them into a new deep-trunk sewer; thereby,
relieving the existing overloaded system. The deep-trunk sewer, known
as the Main Trunk Sewer (MTS), has an internal diameter (ID) ranging
between 3.0 and 4.5 meters (m) and will transfer the flows by gravity
for a distance of over 40 kilometres (km) south to a Terminal Pump
Station (TPS) located at the downstream end of the MTS. The flows will
then be lifted into the New Doha South (NDS) Sewage Treatment Works

2.2.

Scope of Works

Project Location

(STW) for treatment. The reclaimed Treated Sewage Effluent (TSE) will

2.2.1.

be suitable for irrigation purposes and will be returned to Doha

A. The Works, comprises the design, construction, testing, commissioning

metropolitan area.

Summary of scope of services

and handing over of the following works:


1. Approximately 18,900 m of Al-Wakra gravity sewer, of internal
diameter (ID) ranging from 600mm to 2400mm, connected at MTS
shaft WS7
2. Approximately 365 m of 2400mm ID Industrial Area gravity sewer
connected at MTS shaft WS7.
3. Approximately 170 m of 1600mm ID ventilation ducting between the
Industrial Area sewer shaft SH8/60 and the OCF-2 site property
boundary
4. A 1200mm ID connection from shaft SH8/28 to an existing stub out on
the trunk sewer constructed under the LRDP, Project DS016.
5. A 1200mm ID connection from shaft SH8/25/1 to an existing stub out
on the trunk sewer constructed under the LRDP, Project DS007. Shaft
SH8/25/1 contains a vortex drop structure.
6. Diversion chambers at shaft SH8/34/1 (PS W1), SH8/37/10 (PS W2),
SH8/42/1 (PS W5) and SH8/55 (PS W6).
7. Backdrop structures at shaft SH8/34 and SH 8/42
8. Gravity sewer connection points (stub outs), for future connection of
local sewers constructed by a Third Party, at the following approximate
locations:

Baseline Schedule
Page No: 4

Design and construction of lateral interceptor sewers, Al Wakra

8.1.

Shaft SH8/10 vortex drop with stub out

Drive-1 (All lines upstream of SH 32)

8.2.

Shaft SH8/18/1 vortex drop with stub out

Drive-2 (From SH 32 to SH 21)

Drive-3 (From SH 21 to SH 11)

Drive-4 (From SH 11 to WS07 and from SH 60 to WS 07)

9. Connection of both the Al-Wakra and Industrial Area sewers to MTS


shaft WS7 (shaft constructed by an Interfacing Third Party under
contract MTS-02)

The work sequences are elaborately explained in the Baseline Programme

B. Micro tunnelling and pipe jacking works

substantiated with optimum Resources and fully cost loaded work programme.

C. Temporary shafts and permanent manholes

(Refer the details in the Baseline Program of this Submission). While each item of

D. Coordination with other projects undertaken by the Authority and other

the scope of works will be executed and completed then as built drawing also will
be done in parallel to the Project Progress.

utilities or agencies
E. Installation of flow monitoring equipment to measure all inflows from the
local sewer system to LIS-02 at the following locations: PS W1, PS W2, PS

The Project will be closed out with the snagging after addressing of all snagging
works demobilisation and Handing over will be done.

W5, PS W6 and the connections to the project DS007 and DS016 trunk
sewers

4. Construction Approach:
QBC will perform the executions works by drive wise. Were as each drive works

3. Planning Methodology

will start at the same time. Below mentioned network shows the sequence of

QBC will start the work with the submission and approval of necessary pre-

work that will be adopted for each shaft at each drive.

requisite submittals, permits for various pre-construction plans, work method


statements, material submittal for Procurement & Traffic management Plan etc., in
this stage the mobilization of the site offices, the required Manpower & machinery
will be carried out.

Site Preparation

After receiving the approval of RO, Excavation Permits and the traffic Management
Plan & Road diversions approved by traffic police & other authorities and also with
approval from CH2M Hill, QBC will execute the work without disrupting the traffic

Utility Diversion

flow and temporary diversion will be provided to fulfil the necessary traffic
diversion.

Temporary Shaft Construction works

The Lateral interceptor sewer works are majorly divided in to 4 Drives. Below
mentioned are the details of the Drive.

Baseline Schedule
Page No: 5

Micro Tunnelling and Pipe Jacking works

Design and construction of lateral interceptor sewers, Al Wakra

Environmental Protection and Department of Wildlife, at the


MOE, and the concerned Municipality and the Public Works
Manhole Construction work

Authority.

levelling and infilling activities (mud, sand, etc.) that are not

Reinstatement works

reusable shall be transported to dump sites approved by the

Figure 1

concerned

Construction sequence will start from

and

in

coordination

with

that

Site access and traffic management

Site clearance at Drive-1 and Drive-2 are in the residential and densely populated
area, were as Drive-3 and Drive-4 are under development stages. Mostly it is
expected that the requirements for rough grading will effectively remove
vegetation and other superficial surface features. However, it is expected that:

municipality

municipality.

Site clearance

Permit Condition No 10: Residues resulting from excavation,

The Contractor will be responsible for removal and translocation of trees and

Site access will be via the existing highway network as shown on the
drawings provided in the tender documents. Local residents must be
notified accordingly and where necessary.
Temporary traffic management shall be in accordance with the
requirements of the Ashghal Work Zone Traffic Management Guide.

other vegetation to appropriate receptor sites.

Access to existing properties will need to be maintained and the

The Contractor will be responsible for excavating and removing from site the

Contractor shall liaise with local residents to plan the works with

materials

minimal disruption. Where necessary temporary contractor design


prefabricated vehicle 'bridges shall be used to span trenches and

Surfacing materials for existing temporary carriageways, and

Spoil heaps of excavated material. These are shown on the topographical

other excavations.

survey drawings at the time the survey was undertaken, but the contractor
will be required to make his own assessment of the volume of this material
at the time of tender and arrange for its disposal off site.

possible work should be minimised between midnight and 6am and


around mosques during the main Friday prayer period (11:30 to
12:30).

The following permit conditions are applicable;

Work should be undertaken in accordance with QCS 2010. Where

Arrangements for emergency vehicle access are the responsibility of

Permit Condition No 9: Residues resulting from excavation,

the Contractor who should liaise with the relevant authorities, where

levelling and infilling activities (mud, sand, etc.) that are

necessary.

reusable shall be transported and used in government


projects

upon coordination

with the

concerned Private

Engineering Office (Nature Reserves Section), Department of

Baseline Schedule
Page No: 6

Design and construction of lateral interceptor sewers, Al Wakra

Part 1 of the road with TSE, Foul water drainage & ground water pipeline works
(excavation, pipe laying, and backfilling). Manhole excavation will start after
excavation of pipeline and continue with following activities for manhole (blinding,
tanking, protection, base slab, wall concrete, external tanking, cover slab, DI cover
& backfilling). House connection Guiles excavation work will start after wall of
manholes and follow by (Installation of gullies, backfill and grating). Road
excavation at part 1 side will be follow the excavation of road and continue with
(ducts, kerbs, sub-base up to base course), After completion of base course at part
1, work sequence will shift to Part 2 side of the road starting with surface water,
potable water, electricity works, Foul water house connection works, QNBN works,
gully installation & pipe laying works, street light, ITS & Irrigation works if any,
simultaneously works like sub-base, base-course, wearing course, street lighting,
landscaping works will continue as shown in below picture sequence.
5. Assumptions for the Baseline programme:

Baseline programme indicates the planning implementation with Major items


which covers over all scope of the Project. While developing Baseline programme
the following assumptions has been made in order to make a realistic construction
approach and executable work programme as follows but not limited to:
(i)

(ii)

(iii)

Activity durations and resource assignments& assumed daily production


& required logics and their lags for predecessors and successors will be
modified if necessary based on site obstructions/ interfaces and also
unforeseen site conditions and unavoidable changes in QBCs
Construction Methodology. If necessary, programme will be subjected to
modification due to changes in QBCs construction methodology with
information to Atkins.
After the site handing over to QBC, QBC intend to start the work as soon
as possible. Assuming that all the necessary permits and approvals from
the Government/ Ashghal/ Kharamaa/ private authorities will be issued on
time and no obstructions or delay in permits/approvals will stop QBCs
execution and work progress.
QBC assumed that all the client and Government authorities permits/
approvals will be on time without any delays, and no interruptions for the
work to start and the client will provide always necessary work front in
order to progress in execution of works.

QBC assumes that if any scope of the project changes, if any additional works are
incurred it will affect the end date of the project and the client will accept the
required
(iv)

time & cost allocation for such works as positive variations, additional
works and time extension for QBC.

(v)

QBC assumes that there is no electrical work at package-2 in our scope of


work as there is discrepancy in road cross section and layout provided,
which has notified by QBC through email dated 06th July 2015.
(vi) QBC assumes that there is no any requirement of dewatering.
(vii) Sewer house connection for package 2 has considered as a future house
connection as per drawing details.
(viii) Road excavation considered up to sub-grade bottom level.
6. Baseline Programme Description:
The Baseline Programme developed into activities in the following Stages &
divisions:
1.
2.
3.
4.
5.

General
Engineering
Procurement
Construction
Handing Over

For programming and planning purpose each sub division is further divided in to
various levels based on the type of activities involved.
6.1.

6.1.1.

General

Construction milestone:

The contractual milestones are included based on the conditions of the contract.
The programme of works starts with a start milestone as Project Start Date which
represents the commencement of the project as 28 th June 2015. The finish
milestone project Completion Date represents the completion of the project as
16th February 2017 which includes the demobilization and the handing over. The
Project total duration is 600 days.

Baseline Schedule
Page No: 7

Design and construction of lateral interceptor sewers, Al Wakra

6.1.2.

Mobilisation

mainly include for Electrical works, Irrigation works, Rebar works, Survey

The Third party insurance, Contractors all risk insurance, Performance bond etc
are considered. The site office setting ups for Engineer and contractor and gradual

6.3.

works, ITS & Telecommunication works, Micro Tunnelling Works etc.


Procurement:

The construction materials like

mobilisation of manpower & machineries are considered

VC & ESCV Pipes & fittings, DI pipe &

fittings, HDPE pipe & fitting, GRP Pipes, RC Pipes, LV, MV & HV cables, Gully
pots & grating, Street light cable, feeder pillar, street light poles & fittings,
6.1.3.
Permits/Approvals :
Road Opening Permits, Excavation Permit and MMUP permit and their

Potable water valves, Fire hydrants, interlock & kerbs are included in the

respective approvals are considered in order to execute the work.


6.1.4. Provisional Sum Instruction
These are the dates on or before which engineer should pass the

programme.

instruction to execute the work for the particular provisional sum items
to complete the project with in stipulated time frame.
6.2.
Engineering
6.2.1.
General Submittals: All general plans which include Project
Quality Plan, Project Safety Plan, Environment Plan, Project Baseline plan
submission and their respective approvals considered.
6.2.2.
Material Submittal & Approval: The materials for all the

programme and their respective, delivery to site etc. are considered in the
6.4.
Construction
6.4.1. Part-1
6.4.2. Part 2
6.5.

Project Close Out

It demonstrates the handing over for entire project to PWA, snagging list and
as built drawings if any.

items such as, DI pipe, VC pipe and HDPE pipe, UPVC pipes & Ducts etc.
will be submitted and will get the approval.
6.2.3.
Method Statement Submittal

The

6.6.
Working hours:
The calendars considered for the projects, DW013. The official holidays and

construction method statement for all the items are included which are

non-working days as per Qatar Labour Law were considered.. The normal

Surveying works, Dewatering Works, Earthworks, Protection of Existing

working hours will be 8 hours throughout the week except Friday as week

Underground service Utilities, Preparation and laying of sub-base,

end holidays. And the Week starts on Saturday.


6.7.
Programme Requirements:
The Baseline programme has been created according to Clause 14 of the

&

Approval

Preparation and laying of Aggregate base, Asphalting works, Traffic


Signs and Road Markings,

Kerbing & Foot way works, Street Lighting

works, Civil structure works, Surface water drainage works, Manhole for
all works ( TSE/ Sewer/ Drainage),

Ducts works &

Road Crossings

Ducts, Relocation of water pipelines, TSE works & Chambers, Irrigation


& Landscaping works and their respective submission and approvals are
considered.
6.2.4.

Subcontractor Submittal & approval: Subcontractors profile

to be submitted & obtained their respective approvals considered, which


Baseline Schedule
Page No: 8

conditions of contract DW013: Construction of Road & Infrastructure in Al Sailiya


North of Salwa road .

(This also complies according to QCS 2014 clause 7.4

section1 parts, General conditions of contract, clause 8.2.1, the frame work
contract requirement under Vol 2, Schedule 1, Part B, clause 1.18 for
Programme submissions, and Procedure for schedule management for
GEC relevant clauses for construction part).
6.8. Critical Path :
The critical path will be the activities of end stages as per
sequence of work and excavation of ground water pipeline.

Design and construction of lateral interceptor sewers, Al Wakra

Approved electrical
scheme

Approved water and


5

electrical drawings from


Kahramaa

Interface with other


contractor

The delay in approval of electrical


scheme

will

badly

affect

the

construction in site
Any delay in the approval of water
and

electrical

drawings

from

Kahramaa will have a delay in the


project
Whether there is any contractor still
working in site, will badly effect on the
progress in site
Delay in approval of dewatering work

Dewatering work

trench

7. Risk Assessment:
No.

Description

Affect
One way traffic diversion proposed by

Traffic Diversion plan

QBC may be will take long time for

approval

approval by other parties and it will


affect the start of the work at site
The connection of proposed network
to existing may be delayed if the

Connection with existing

existing

connection

consequently

will

not

effect

ready,
on

the

completion of the project


The instruction of the provisional sum
3

Instruction of provisional
sum items

items must be on time as identified in


the baseline programme and whether
there is a delay will badly affect the
construction in site

Baseline Schedule
Page No: 9

will badly affect the work in deep

Design and construction of lateral interceptor sewers, Al Wakra