Академический Документы
Профессиональный Документы
Культура Документы
DATE OF
ISSUE
PROJECT
FEDERAL TRANSFORMER,MUSAF
3/21/2016
METHOD OF STATEMENT
FOR
EXCAVATION AND BACKFILLING WORKS
JS
HSE :
JG
CHECKED BY :
APPROVED BY :
FOR COMPANY
Comments :-
Accepted
Accepted subject to
Rejected
METHOD OF STATEMENT
DATE OF
ISSUE
PROJECT
FEDERAL TRANSFORMER,MUSAF
3/21/2016
TABLE OF CONTENTS
1) PURPOSE
2) REFERENCE DOCUMENTS
3) TOOLS & EQUIPMENT
4) WORK PROCEDURES
5) REVAMPING AREA
6) HEALTH AND SAFETY
7) ATTACHMENT
a)-TRA
b)-Risk Potential Matrix
c)-Drawings
METHOD OF STATEMENT
DATE OF
ISSUE
PROJECT
FEDERAL TRANSFORMER,MUSAF
3/21/2016
1.0
PURPOSE
1.1 GENERAL
The purpose of this method of statement is to describe the
excavation and backfilling activity for the MACWANE GULF LLCfactory at ICAD II
1.2 SCOPE
The work involves digging out for pile caps, excavation to the top of
the piles; foundations, tie beams, trenches etc.
2.0
REFERENCE DOCUMENTS
All relevant civil drawings and specifications.
3.0
4.0
PROCEDURES
4.1 Preparation for Excavation
a, Preparation of equipment tools and manpower for excavation
activities.
b, Secure permit of work from relevant authorities prior to the start
of excavation
d, Record all existing condition within the surrounding of excavation
area.
4.2 Excavation activity
Electrical cable Trench & General excavations.
METHOD OF STATEMENT
DATE OF
ISSUE
PROJECT
FEDERAL TRANSFORMER,MUSAF
3/21/2016
5.0
REVAMPING AREA
o Since some of the adjacent equipments are operational
proper orientation of workers must be done before starting
any activities.
o For existing Wires & Cables affected, proper protection must
be done.
METHOD OF STATEMENT
DATE OF
ISSUE
PROJECT
FEDERAL TRANSFORMER,MUSAF
3/21/2016
6.0
Risk Assessment
1, General Assessment.
o Site safety
There are various risks associated with working on any site
and site regulations as laid down by the Site Owner/
Operator should be observe.
o PPE
The minimum Personal Protective Equipment is as follows :
Safety Helmet
Ear Defenders / Earplugs
Safety footwear
Eye protection
METHOD OF STATEMENT
DATE OF
ISSUE
PROJECT
FEDERAL TRANSFORMER,MUSAF
3/21/2016
Safety Gloves
And any other equipment required by the site operator
or deemed necessary by the task.
2, Safety Precautions
o Barricade the working area
o All safety precautionary signboards must be visibly posted
o Ensure that only authorized personnel are within the
affected area
o The work shall be executed in accordance with the approved
safety.
o Action Plan and Daily Safe work plan.
o Tool Box Meeting must be established at site prior to start of
any activities, detailing potential hazards associated with the
work, and implement necessary action to caution involve
workers.
o Working in confined paces.
Personnel should to enter confined spaces without the
authority and direct supervision of qualified personnel. Site
owners and operators will have their own procedures for
entry into confined spaces and these should always be
followed. Always ensure the correct permit has been issued
and that all correct procedures have been carried out before
continuing. Under to circumstance should a person working
alone enter a confine space.
Excavation with more than 1.2Mtr. in depth are
considered as a confined space.
7.0
ATTACHMENT
a. Task Risk Assessment
b. Risk Potential Matrix
c. Drawings