Академический Документы
Профессиональный Документы
Культура Документы
4
5
6
7
2. ELECTRIC SUPPLY
8
8
9
10
11
3. ELECTRIC PRINCIPLE
12
4. HOISTING MECHANISM
13
13
14
14
15
16
16
17
17
17
17
17
18
5. SLEWING MECHANISM
20
20
21
22
22
23
24
SHENJIAN
24
24
27
27
27
28
6. TROLLEYING MECHANISM
29
29
30
30
31
31
32
32
7.SAFETY DEVICE
33
7.1 SUMMARY
7.2 SECURITY PARAMETER
7.3 MOMENT LIMITER
7.3.1WORKING PRINCIPLE
7.3.2 ADJUSTMENT
7.4 LOAD LIMITER
7.4.1WORKING PRINCIPLE
7.4.2 ADJUSTMENT
33
34
35
35
36
37
37
38
8. TRAVELLING MECHANISM
40
40
41
41
41
42
42
43
9. LUBRICATION
44
9.1 SYMBOL
9.2 REGULAR LUBRICATION
9.3 SKETCH OF LUBRICATED PARTS
44
44
45
SHENJIAN
46
47
47
48
49
49
50
51
51
51
52
53
55
56
57
59
SHENJIAN
SHENJIAN
Loosen
clamp
the
track
Switch on the
power of tower
crane
NOTE:
SHENJIAN
Check the
emergency
shutdown (shut off
the main power)
Check the
loudspeaker
Someone shall command on site when the object can not be seen clearly.
The safety device is not allowed to change at will.
Stop the operation when the wind speed 72km/h
Switch on the
weathercock when
the dolly moving to
the boom point.
Fasten
clamp
the
track
Hand over the keys to the on-site director and report the situation
SHENJIAN
Check the
Non-planeness of
track by meansof
chassis crossbeam
Check the
Non-planeness of
track by means of
chassis crossbeam
Check the
counterweight
Check the
abrasion of steel
wire rope
SHENJIAN
2. Electric Supply
2.1 Source of power
The source of power adopts three-phase and five-wire power supply system over 90 KVA with 50
HZ 380V or 60HZ 440V, and the distance from power transformer to the cables we provide is S.
When S 100m, the cable section is 3x35mm2+2x10mm2
When 100m S 200m, the cable section is 3x50mm2+2x16mm2
2. Site switch
6. Supply cable
3. Autotransformer
7. Isolating switch
SHENJIAN
SHENJIAN
SHENJIAN
10
Technical requirement:
Either by ground cables or copper braidings with a
minimum section of 28 mm2, bolted or soldered onto
the rails.
Or by iron conductors with a minimum section of 50
mm2,welded onto the rails.
SHENJIAN
11
3. Electric Principle
SEE fig 1-26
SHENJIAN
12
4. Hoisting mechanism
4.1 Principle of 70RCS mechanism
1. a hoist drum
2. a bevel reduction gear
3. two motors
70RCS Hoisting mechanism is made up of two slip-ring motors with brakes self-excitation
generation. The intrinsic characteristic of the two motors connect to the input pole of the
speed-reducer are the same ,but the gear on the shaft of the upper motor has 19 teeth, the lower
motor has 38 ones .So the upper motor called low-speed motor(PV),and the lower one called
high-speed motor(GV).
The hoist winch allows 5 hoisting and 5 lowering speeds. The first 3 speeds are obtained by using
one motor as driving motor, the other motor as brake motor. Changing the amount of the
resistances can make up the first 3 different speeds. The 4th speed is nominal speed of the PV
motor, the 5th speed is the nominal speed of the GV motor.
SHENJIAN
13
2-fall to 4-fall
The top pulley block (1) next to the trolley, double-plate closed, under part pulley block(2) is
two falls traveling block. Manipulate hoisting, press the eliminate limit press untilthe
double-plate of the pulley block was opened, the incline on the double-plate should be guide, put
shaft (4) into the hole (5) of double-plate, the check plate in the two side of the shaft could
provided the double-plate opened. Manipulatelowering, working with 4 falls.
SHENJIAN
14
SHENJIAN
15
16
fixed on the three brackets that the plate can slip on it.
Braking: the electric magnet (5) without electric supply, the spring (6) push the plate(3) back .
So the braking wheelbrace is pressed to the plate(2) and the braking ring, the braking ring is
apart of the plate(3)see fig4-5.
Brake release: the electric magnet(5) with electric supply, the plate(3) and the spring are
tightened completely, then loose the braking wheelbrace(1), so it can resume rotating freely.
See fig4-7.
4.3.2 Adjustment
Clearance adjustment: By adjusting the nut (7) and (8) to change the clearance <E>, make sure
that the clearance is 0.6mm.
Braking moment adjustment: The braking moment is 1.5 times than the max load , screw the
three nuts(9) to adjust the flex, check out the length of the three springs are the same.
4.3.4 Maintenance
Maintain per 200 hours or per month
Checkout the abrasion of the braking screw, change it before it out of work.
Be careful to keep the brake clean.
4.4 Limiter
It is used to prevent potential operation faults.
.Stop the hoisting motion when the cliver pulley block is close to dolly of arm frame.
.Prevent the complete loose of steel wire rope and wind the rope around the drum in the opposite
direction during lifting down.
SHENJIAN
17
Note: Each time when starting a new site and before putting into service it is essential to remove
the plug located at the lowest part of the limit switch in order to eliminate the condensation water.
This plug is to be re-placed for crane transport.
4.4.2 Adjustment
Adjustment must be carried out without load. Carry out the adjustment by controlling the rise and
fall, and operate the contact (6) or (10) by hands in order to determine the contact which can
control the motion. (See figure 4-6)
1 Adjust the hoist up hoisting speed reducer(SLH-1):
Control hoisting in 2 fall for(SM-DM) version ,raising the pulley block until the distance between
the jib trolley and the pulley block is 5 m only . Turn the corresponding cam(3), check the
hoisting control ,until it depresses the corresponding contact(4).
(2)Adjust the hoist up hoisting limit switch (SLH):
Control hoisting in 2 fall for(SM-DM) version ,raising the pulley block until the distance between
the jib trolley and the pulley block is 1 m only. Turn the corresponding cam(5) , check the
hoisting control ,until it depresses the corresponding contact(6).
(3)Adjust the hoist down of the hoisting speed reducer (SLD-1):
It is carried out in 4 fall for SM-DM version trolleys. until the distance between the pulley block
And the ground is 5 m, Turn the corresponding cam(7), check the hoist down, until it depresses the
corresponding contact(8).
SHENJIAN
18
SHENJIAN
19
5. Slewing Mechanism
5.1 OMD mechanism working principle
1. a squirrel-cage Motor
6. a tachometer dynamo
7. a slewing limiter
SHENJIAN
20
1) a squirrel-cage Motor
2) a planetary reduction gear
3) the drive pinion
4) a slewing limiter
The CSCT controller adopt three-phase AC regulate voltage timing traveling control device.
SHENJIAN
21
the whole system of the CSCT are composed of controller electric control box the crane
control platform with relay moment motor and reducer. when the joystick is on operation, it
drive the potentiometer, and output an analogy signal to the CSCT controller. it control the
trigger transmit angle of the three-phase AC voltage. Output different voltage by trigger the
transistor module. A pair of line-voltage of the three-phase output voltage feed back to the
controller form the closed loop control. Fig 5-5
Voltage feedback
22
Movable Armature (4), Brake Lining Bearer (5) and Releasing Lever (6) then receive the pressure
from the spring (12). Once stopping on the Trigger Plate (10), the Adjusting Plate will restrict the
motion of the Brake Lining Bearer by right of the nut (8). Upon releasing the button, the
electromagnetic iron will be power off immediately, however, the Trigger Plate (10) will be still at
the position of being attracted due to the pressure of the Control Lever (13).
Upon the completion of above operation, the indicator lamp beside the electric control button
should be still on, indicating that the tower crane is under the Wethervaning Effect.
Upon cutting off the circuit breaker or turning off the breaker switch, the indicator lamp will be off.
When the tower crane is in operation, the brake will restore automatically.
Note:
If the wethervaning device should not operate(lack of current), weathervaning can be obtained see
following page.
1 Inside Box
SHENJIAN
23
5.4.2 Adjustment
(1) Adjustment of Air-gap (E)
A. Loosen the screw (1);
B. Completely loosen the screws of the Movable Frame (2) and then make adjustment on the
SHENJIAN
24
notch outside the screws until it is clung on the yoke iron (3);
C. Re-fix the frame with the screw (1) in the third hold; adjust the clearance to appro. 0.6mm
(E).
(2) Adjustment of Braking Torque:
Have been pre-adjusted before delivery.
(3) Adjustment of Weathercock Device:
The clearance of brake has been adjusted appropriately; remove the plug screw (4); loosen the
nut (5) (with 13 Socket Spanner) until the Releasing Lever (6) can be moved from left to
right and from the top down optionally with a wet finger.
From this time on, there are two conditions for adjustment:
The brake is power on;
The brake is power off.
When power on:
A. Connect the brakes yoke iron (3) with the power so that pulse is generated in the slewing
control combination switch on the right side or left side;
B. Screw down the nut (5) until the Adjusting Plate (7) contacts the Trigger (8);
C. When the Trigger (8) contacts the Adjusting Plate (7), keep it immovable;
D. Slightly loosen the nut (5) until the Trigger (8) returns to the original position under the
action of the Return Spring (9);
E. Make sure that the Trigger (8) can be turned flexibly without any restriction when it
contacts the Adjusting Plate, otherwise slightly loosen the nut (5).
After the completion of the adjustment of Weathercock Device, it is necessary to check the outer
shell (10) and make sure it can rotate flexibly, then re-place the plug screw (4).
When power off:
A. Follow the operation instruction described in the Power Adjustment Column;
B. Re-screw down the nut (5) by 1/3 round (1.5mm pitch), thus the Weathercock can be
ensured;
C. Make sure that the outer shell (10) can rotate flexibly;
D. Re-place the plug screw (4).
Important:
This adjustment must be carried out:
After repair of the brake (parts replaced or air-gap adjusted).
When brake linings are worn out, which can be detected by insufficient brake release and by
the release lever having no play in the braked position.
When the signal light does not work. .(fig 5-9)
SHENJIAN
25
Figure 5-8
Figure 5-9
Figure 5-10
SHENJIAN
26
5.5.2 Adjustments
They are carried out WITHOUT LOAD. Control left slewing or right slewing and act manually
onto the break keys (A) in order to determine which one cuts the controlled motion. Adjusting the
right hand slewing limiter(SRD), slew the jib so that the electric cables are not twisted (jib position
after erecting the crane), carry out 1 1/2 turn to the right, then adjust the cam(4) checking this
movement until it depresses the corresponding contact(5). Adjusting the left hand slewing limiter
(SRG), carry out 3 turns in the reverse direction .adjust the cam (6) until it depresses the contact
(7).
Note: the adjustments must be checked everyday before putting into service.
Every time when the tower crane moved to a new place, must pull out the plug at the end of the
limiter before put to use, drain the water of condensation in it, and must stopper the plug before the
crane move to another workplace.
NOTE:
Install a limit switch on the E flat plate of the slewing mechanism,the mechanism
will stop working when the E flat plate is open.
SHENJIAN
27
Tightening torque
in mkg
Tightening torque
in mkg
BOLT
(IN MM)
SHENJIAN
Max
Nom
Min
Max
Nom
Min
20
55
46
40
40
35
30
22
71
65
58
24
95
85
70
70
64
50
27
144
124
110
100
93
75
33
248
220
190
200
181
160
28
6. Trolleying Mechanism
6.1 4T3V4 mechanism working principle
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
Screw M8
Spring sleeve
Screw 3rd hole and 4th hole
Fan cover
Spline sleeve
Bearing 80212
Transmission shaft
Normal speed ratio of the reducer r =
30.36
21. Bearing 60209
22. Body frame seal PD 115 x 140 x 14
The moment motor, which drives the mechanism 4T3V4, is equipped with an eddy brake and a
direct current disc brake.
The trolley has 3 trolley out speeds and 3 trolley in speeds, for these speeds are obtained by
successively putting under voltage the 3 windings and the eddy brake corresponding to the 3 motor
speeds.
The 1st notch MV is the eddy brakes max-excitation in combination with the motors step-down
control.
The 2nd notch PV is the eddy brakes mid-excitation in combination with the full staring motor.
The 3rd notch GV is in self-control of the full starting motor. No excitation from eddy.
SHENJIAN
29
(1) Shaft
(2) Flange cover
(3) Bearing
(4) Claw magnetic
(5) Field coil (I)
(6) Armature
(7) Body (I)
(8) Stator winding
(9) Stator core
(10) Rotor
(11) Body (II)
(23) Nut
(24) Nut
(25) Spring box
(26) Release screw
(27) Release nut
(28) Brake spring
(29) Field coil (II)
(30) Armature
(31) Spline sleeve
(32) Terminal Box (II)
The friction screw of the electromagnetic brake would be abraded after a long time usage, and the
air-gap between the armature and the field core increased, the length of the brake spring increased
and the braking moment decreased, so the armature is not easy to be attracted, even un-attracted if
seriously, so that the motor will be stalled and then burn out. Therefore, the air-gap must be
checked daily. When the fixed braking torque is less than the rated value or the air-gap is more
than 1.2 mm, adjust them. Replace the friction material by a new one when the metal surface will
be worn.
SHENJIAN
30
c.
d.
e.
f.
J. Tighten two release nuts (27) and lock them at the spring box (25) about 5 mm apart.
After adjusting the electromagnetic brake, check the manual released device and the armature
could be attracted or not when the power is supplied. If the adjustment is all right, then put the
motor into service.
6.3 Limiter
The purpose of the trolley limit switch is to avoid any possible driving error and to stop the trolley
motion before reaching the stops of the jib nose or foot.
SHENJIAN
31
6.3.2 Adjustments
Adjusting the trolley out-slowing down safety device(RDAv)
Move the trolley to a distance of 1.50m form the jib nose rubber stops. Turn cam(3) until it
depresses the corresponding contact.
Important: Adjust so that the 2 cams are overlapping in order to avoid any interruption of slowing
down before the motion is cut off.
Adjusting the trolley out limit switch (SDAv)
Move the trolley to about 20cm from the jib nose rubber stops, Turn cam(5) until it depressed the
corresponding contact(6) without however modifying the adjustment of cam(3).
Adjusting the trolley in- slowing down safety device(RDAr)
Move the trolley to the jib foot and operate the slowing down cam(7) to depressed the contact(8).
Adjusting the trolley in limit switch(SDAr)
Proceed as described above turn cam(9) until it depressed the contact(10).
NOTE: the adjustments must be checked daily at each putting into service.
SHENJIAN
32
7.Safety Device
7.1 Summary
Safety device is specially used to avoid the wrong operation. It includes a limiter and an overload
limiter.
The overload limiter adjusted order: a. Moment Limiter b. Max. Working Load and Speed Limiter
I. Limiter
A) Hoisting Limiter
B) Slewing Limiter
C) Trolleying Limiter
D) Traveling Limiter
II. Overload Limiter
E) Moment Limiter
F) Max. Working Load and Speed Limiter
SHENJIAN
33
7.2 Security
parameter
Lf
HOISTING
MOMENT LIMITER
SLMO
2-FALL
SM
Lf
Lm
L m Dm
+10% 80%
50
2600
2860
2340
5000
28.2
31
45
2950
3245
2655
5000
28.2
31
40
3400
3740
3060
5000
28.2
31
32
35
3950
4345
3555
5000
28.2
31
28
30
4700
5170
4230
5000
28.2
31
24
2/4FALL
SM/DM
Lf
TROLLEYING MOMENT
LIMITER
SDMO
HOISTING
MOMENT LIMITER
SLMO
40
36
TROLLEYING MOMENT
LIMITER
SDMO
Lf m
X(kg)
Y(kg)
Z(kg)
W(kg)
Lm
Lm
Dm
50
2300
2530
2070
5000
26.8
29.4
40
45
2650
2915
2385
5000
26.8
29.4
36
40
3100
3410
2790
5000
26.8
29.4
32
35
3650
4015
3285
5000
26.8
29.4
28
30
4400
4840
2960
5000
26.8
29.4
24
5500
SHENJIAN
34
7.3.1Working Principle
The device has a pair of spring plates (1) which may bend to a certain extent under the action of
load moment. As there are several adjustable bolts on the spring plates, when the load is excessive,
the adjustable bolts will press down switch.
SHENJIAN
35
7.3.2 Adjustment
(1)
Lift down the load, and then hoist the load Y=X+10%
at the min. speed of 4-rope. The hoisting motion should
be stopped, otherwise make readjustment.
(3)
Note: Check SDMO Safety Device (it is not necessary to check SLMO) and stop the outward
trolleying motion.
For the different load value and jib length, see the initial part of this section.
SHENJIAN
36
4)Adjustment method
Adjustment of Device A, C, D:
Screw the nut (1) and the bolt (2) to make the bolt to contact the switchs contact (3), but not cause
short circuit.
7.4.1Working Principle
The hoisting ropes running through the sheave transmit the stress to the dynamometer link which is
connected with the sheave in way of rigid connection so that the dynamometer link distorts along
with the change of load. On the metal bar mounted in the link there is a switch and adjustable bolt
SHENJIAN
37
which may record the distortion. After appropriate adjustment, the switch may play the function of
safety circuit. What the safety circuit controls is the load.
Adjustment
7.4.2
Adjust Speed Limiter (SLCHGV)
X
To lift down the load, add the load
by 10% and hoist the new load at
medium speed and then at high speed.
At this moment, there should not be
high speed hoisting action, otherwise
readjustment.
Adj
ust Speed Limiter (SLCHPV)
SHENJIAN
38
X
To lift down the load, add the load
by 10% and hoist the new load at low
speed At this moment, there should not
be any hoisting action, otherwise make
readjustment.
SHENJIAN
39
8. Travelling mechanism
8.1 working principle
The crane is fitted with a traveling mechanism which comprises:
4 motor bogies(1), each made up of:
1 squirrel cage motor(2) with a double acting brake, 1 reduction gear (3) directly meshing the
powered wheel, rail cramps for non-working condition, a limit switch(5) with its ramps(6).
40
8.2.2 Adjustment
a) air gap coil(6):
remove screw(8). Unscrew the plate (2) completely acting on its outer notches until it is hard
against the yoke(12). Screw up the plate pushing on the screw(8); at the 3rd hole encountered,
block(8).
b) air gap (5):
remove screw(10) so that the plate can be reached. Remove screw(9). Unscrew the plate(1)
completely acting on its outer notches until it is hard against the yoke. Screw up the plate
pushing on the screw(9); at the 2nd hole encountered, block(9). Screw up the screw(10).
SHENJIAN
41
NOTE: if the plate is attracted when depressing the ON button, increase the air gap(3rd and 4th
hole).
c) brake moment :
the brake moments are defined by the springs(3) and (4) ,spring box completely tightened.
42
8.3.2 Adjustments
Position the ramps(6)and (7)
requested:
The crane being at nominal
speed and taking into
account that it works under
wind, after slowing down
its sped over a distance L,
comes to rest 50 cm before
the stops (10).
The lever(4) of the limit
switch and of the overrun
limit
switch
whilst
controlling the motion cut
off, still has a minimum
clearance before reaching
the
mechanical
stop.
Position the ramps(8) and
(9) so that the overrun limit
switch cuts off the motion
immediately after the limit
switch.
SHENJIAN
43
9. Lubrication
9.1 Symbol
M ---- Before use;
N ---- Oil level control;
V ---- Discharge oil;
R ---- Inject oil;
G ---- lubricating grease
----ZL45-2,2# Aviation Grease
----R MIL-L2105BSAE80
----MOS2,Complex calcium base grease MOS2 4#
--YH10SY1181-65 10# Aviation Hydraulic Grease(N46 unti-abraded hydraulic grease )
, In
MIL-H5606B
SHENJIAN
44
1
2
3
6
7
8
9
10
SHENJIAN
45
SHENJIAN
46
Explanation: life-time lubrication for the decelerator; check the abrasion of the brush (A) every
year or every 2400 hours, and when the brushs length is less than 15mm, it should be replaced;
SHENJIAN
47
SHENJIAN
48
of
,but
before
each
1month 1year
SHENJIAN
49
fig 9-8
Lubrication of the hoist device and the pedestal:
Everytime lubricate the wheel before fixing mast, the slewing part also need to oil.
The rotating parts of the pedestal also need to lubricate.
SHENJIAN
50
51
10.1.2 Maintenance
Adjustment of the high pressure regulator(fig 10-2):
unscrew the knurled cap(1), then hold the control
lever to the hoist up position. Re-screw it until
telescoping is possible, then screw it again slightly so
as to adjust it to a somewhat higher value. If the
maximum pressures couldnt reached after having
screwed in the knurled cap(1) completely, un-screw
the cap(1) completely and screw the adjusting nut(2)
to the place of cap(1) before un-screwed, and restart
the adjustment procedure.
The high pressure regulator shouldnt adjust to the
maximum pressure frequently.
The low pressure regulator is calibrated at the
factory and mustnt be adjusted.
SHENJIAN
1
2
52
SHENJIAN
53
SHENJIAN
54
10.2 Ram
1) ram body
6) piston
2) ram piston
3) piston rod
8) piston
4) ram bottom
9) throttle-valve
SHENJIAN
55
When controlling the movement, the oil flows under high pressure to (A), forces back the
non-return valves (5) and (7) enters into the great ram chamber and pushes the piston. The oil in
the small ram chamber returns to the hydraulic group through the pipe(C) and the low pressure
circuit (B). The hoist speed depends on the pump flow. When the operation is stopped, the valves
(5) and (7) are closed under the pressure of the load which remains in position.
As soon as operated, the oil arrives under low pressure at (b) and (c). In (c), the low pressure is
added to the pressure produced by the load. In (b), it controls the piston(8), which opens the
valve(7); but it cannot open the valve(5) with the piston (6) (the force of the pressure on (6) is
smaller than the effort due to the pressure in the great ram chamber). So the oil of the great ram
chamber returns to the group through the throttle-valve(9), the valve(7) and the high pressure
circuit(a).
NOTE: We emphasize that it is dangerous to invert the high and low pressure hoses. As a matter of
fact, if the lowering down operation was controlled under high pressure, the piston(6) would force
open the valve(5), and the return flow would not be limited any longer. The lowering down
operation would take place at an uncontrolled high speed, with shocks and pump cavitation.
SHENJIAN
56
The weight of the telescoping beam is resisting. The procedure is the same as for telescoping down.
The raising speed depends on the pump flow.
a: fixed part
P: weight of the telescoping beam
b: moving part
R: resisting
P: weight of the slewing crane part
r: driving
Throttle-valve adjustment:
Check first that the hydraulic oil in the ram has been cleared, take off the domed cap (a). Unscrew
the lock nut (b). Completely screw up the needle pin(5). Unscrew 1/4 turn (not more when starting
the telescoping) and block the lock nut. If it doesnt fit very well, adjust again by 1/4 turn
maximum at a time. Then lock the nut and refit the domed cap nut.
Never adjust the throttle-valve when the ram is operating under load:
SHENJIAN
57
SHENJIAN
58
SHENJIAN
59
SHENJIAN
60
SHENJIAN
61
SHENJIAN
62
SHENJIAN
63
SHENJIAN
64
SHENJIAN
65
SHENJIAN
66
SHENJIAN
67
SHENJIAN
68
SHENJIAN
69
SHENJIAN
70
SHENJIAN
71
SHENJIAN
72
SHENJIAN
73
SHENJIAN
74
SHENJIAN
75
SHENJIAN
76
PE
SHENJIAN
77
SHENJIAN
78