Вы находитесь на странице: 1из 15

Design Guidelines

BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

Electronic Document, only the original archived in Quality Department is signed / Printed copies uncontrolled
Revision

Date

Details

1.0

22/04/12

First issue

1.1

14/05/2015

- Page 3 section 1.1 last paragraph Future population and


Growth rates updated after publication of Population Projection
Sultanate of Oman (2015-2040) by National centre for Statistics
and Information (NCSI)
- Section 1.3 LPCD table updated.

Contents
Introduction............................................................................................................................................................. 2
1. WATER DEMAND FORECAST ................................................................................................................ 3
1.1
Population forecast ................................................................................................................................... 3
1.2
Categories of Water Demand ................................................................................................................... 4
1.3
Domestic Consumption / Pipe Supply...................................................................................................... 4
1.4
Domestic Consumption / Tankers Supply................................................................................................ 5
1.5
Non Domestic Consumption .................................................................................................................... 5
1.6
Leakage and other technical losses........................................................................................................... 6
1.7
Water Used by PAEW in its Normal Operations (after leakage) ............................................................ 6
1.8
Fire Fighting.............................................................................................................................................. 6
1.9
Commercial Losses ................................................................................................................................... 7
1.10 Peak Factors .............................................................................................................................................. 8
2. DISTRIBUTION SYSTEMS ........................................................................................................................ 9
2.1
Future Water demand Design horizon and phasing of Assets .............................................................. 9
2.1.1 General ...................................................................................................................................................... 9
2.1.2 Water Demand .......................................................................................................................................... 9
2.1.3 An `` All-In`` figure for preliminary estimating ...................................................................................... 9
2.2
Pressure in the network ............................................................................................................................. 9
3. TRANSMISSION AND TRUNK MAIN DESIGN ................................................................................... 10
3.1
Headroom ................................................................................................................................................ 10
3.2
Route and elevation ................................................................................................................................ 10
3.3
Desired pressure ...................................................................................................................................... 11
3.4
Velocity ................................................................................................................................................... 11
3.5
Surge ....................................................................................................................................................... 11
3.6
Valves ...................................................................................................................................................... 11
3.7
Air valves ................................................................................................................................................ 12
3.8
Pipe materials .......................................................................................................................................... 12
3.9
Thrust blocks ........................................................................................................................................... 13
3.10 Energy considerations ............................................................................................................................. 13
4. WATER QUALITY .................................................................................................................................... 13
5. CONTROL PHILOSOPHY ........................................................................................................................ 14
6. SECURITY OF SUPPLY RISK MANAGEMENT ............................................................................... 15

1/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

INTRODUCTION
This document has been prepared as a Guide to PAEW engineers and their consultants for the
planning of water transmission and distribution systems.
It is not intended as a complete Manual for pipe design, but is intended to:
1.
2.
3.
4.

Set out the PAEW policy for pipeline design;


Inform upon standard pipeline design criteria;
Provide basic pipeline requirements to ensure the safe operation of the pipeline, and
Act as an aid memoire where specialist design skills are required e.g. surge.

In the event of any doubt concerning the use of this Guide, the advice of the General Manager:
Planning and Asset Management Department should be sought.
Wherever possible, the water demand of an area should be based upon researched data
relating to the specific area under study. Only where such data is not available, should the data
in this Guide be used.
The Guide provides the minimum requirements/standards to be met and the data
provided is to be used as the minimum acceptable.

Authorised
Consumption

System Input
Volume
(Corrected for
known errors)
WATER
DEMAND

Billed
Authorised
Consumption

Unbilled Metered Consumption

Apparent Losses
(Commercial
losses)

Unauthorised Consumption

Unbilled Unmetered
Consumption

Customer Metering Inaccuracies


Leakage on Transmission and /
or Distribution Mains

Real Losses
(technical losses)

Revenue Water

Billed Unmetered Consumption

Unbilled
Authorised
Consumption

Water Losses
Unaccounted for
Water

Billed Metered Consumption


(including water exported)

Non Revenue
Water

Leakage and Overflows at


Utilitys Storage Tanks
Leakage on Service Connections
up to point of Customer
Metering

Table 1: IWA Standard International Water Balance and Terminology

2/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

1. WATER DEMAND FORECAST


1.1

Population forecast

Population
Future water domestic demand depends upon the future population and future per capita
consumption.
Population in an area can be determined in number of ways:
1.
2.
3.
4.

As provided by a developer in his request for a water supply to be made available;


From the planning proposals of the Omani Planning Authorities;
Existing population + growth rate;
Calculated (NPO) from the number of plots (N), properties per plot (P) and
occupancy rates (O), and
5. Using a population/acre figure
Domestic Occupancy
Domestic occupancy rates are difficult to ascertain due to lack of appropriate data.
Computations are complicated by the large number of empty houses1, holiday homes and for
other reasons.
From the 2010 Population Census and the 2010 water demand study, the following have been
deduced for 2010 and can be used for future developments unless more explicit data is
available.

Parameter
Domestic occupancy

1
2

Governorate
Muscat
Batinah
Buraymi
Dakhliyah
Dhahirah
Sharqiyah
Wusta
Musandam

As assessed
for 2010

5.1
6.0
4.6
6.0
6.1
4.7
7.6
3.7

Accordingtothe2010PopulationCensusofthetotal551,058housingunitsonly396,421wereoccupied
FromPopulationProjectionSultanateofOman(20152040)issuedbyNCSIinSeptember2014.

3/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

Future population and Growth rates


Unless more specific information is available, for the foreseeable future the following growth
rates can be assumed2 and applied. The following table contains the average population
growth rate deducted from the Population Projection Sultanate of Oman (2015-2040) issued by
the National Centre for Statistics and Information (NCSI) published in September 2014.

Omani
Non-Omani

2015/20
13.9%
3.6%

2020/25
12.1%
1.8%

2025/30
10.0%
-0.3%

2030/35
8.8%
-1.6%

2035/40
8.4%
-2.2%

For local evolutions and detailed estimates data published by NCSI can be referred. NCSI is
updating this information regularly, for detailed information the designer should refer to the latest
data published.
1.2
Categories of Water Demand
For designing and planning a water main, the most important factor is to understand the water
requirement of the area to be supplied and the various categories of demand.
There is a distinct difference between water demand, which is the quantity of water required
within an area to satisfy all the water needs of the area, and water consumption, which is the
actual quantity of water drawn by customers through their service pipes.
In some cases due to inadequacies in the water supply system, customers demand may not be
met. In which case, their consumption is referred to as restrained demand. However water
systems shall be designed for unrestrained water demand.
For water demand forecast the following categories can be used.

Domestic consumption by piped supply;


Domestic consumption by tanker supply;
Non domestic consumption;
Unaccounted for water including:
o Leakage and other technical losses;
o Water used by PAEW in its normal operations;
o Fire fighting usage
o Commercial losses
1.3

Domestic Consumption / Pipe Supply

The required water demand of customers to be met by the PAEW for their domestic use, i.e.
within their residences, varies depending on several considerations such as socio-economic,
cultural and climatic.
Water consumption is expressed as per capita consumption, and is the average quantity of
water used per person per day and is generally termed as lpcd.
Wherever data is available, domestic per capita demand should be based upon the
consumption at the time of the design, increased appropriately over the project design horizon,
which is usually 25yrs.

4/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

The following data should be used as guidance.

Parameter

Governorate

Domestic
consumption as
drawn at tap in
litres/head/day

Muscat
Batinah North
Batinah South
Buraymi
Dakhliyah
Dhahirah
Sharqiyah (North and
South)
Wusta
Musandam

2010
from
Water
Balance

2015

2020

2025

2030

2035

2040

175
167
156
180
150
148

180
175
165
180
158
154

185
180
170
180
165
160

190
185
175
180
170
165

195
190
180
185
175
170

200
195
185
190
180
175

200
195
185
190
180
175

134

152

160

165

170

175

175

130
191

135
191

140
191

145
191

155
191

160
191

160
191

These are indicative figures only that apply across a Region. It can be expected that there will
be variations within a Region.
1.4

Domestic Consumption / Tankers Supply

Where water is being distributed by the tankers, the consumption of 22 gallons /capita/day is to
be used.
1.5

Non Domestic Consumption

Where there is not expected to be any specific non-domestic high-usage, there are different
methods to calculate the water consumption, such as:

Commercial user can be converted into the equivalent number of domestic user,
Number of employees at the commercial site divided by the population density per
house in the region to get the equivalent number of properties,
Hotels, clinics and hospitals can be converted into domestic properties by considering
the number of employees so that in turn the usage can be calculated.

Generally the domestic usage uses the greatest volume of water per square meter of any other
type of user.
The following table shows some values of non-domestic consumption for special uses:
Category

Average per Capita consumption

Public office

60 l / c/day (6 days per week)

Hospital

200 500 l / bed / day

School

20 l / pupil / day (5 days per week)

Hotel

200 500 l / person/day

Restaurant

100 l / person/day

Cattle breeding

6 -10 l/ animal/ day

Gardens / plantations

3 -10 l / m2 / day

5/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

A general rule of thumb is to allow 20% of the domestic consumption for non-domestic usage
(including government).
Non Domestic Usage Industrial and High Usage Concerns
Where there are known to be industrial premises that will have a high water consumption or
other developments such as tourist complexes, shopping malls and industrial parks, it is
essential that the anticipated water demand is discussed with the appropriate industrialists,
developers and planning authorities.
Beware that there is a tendency for planners to over-estimate water needs in order to ensure
the adequacy of the water supply to a development.
1.6

Leakage and other technical losses

Water is lost from the PAEWs system through a number of ways:


1. Leakage slow continual loss of water through small holes in the mains, poor joints and
the like;
2. Bursts, where the volume lost can be large but are generally of short duration;
3. Water lost when a mains system has to be drained down in order to repair a leak or
burst, including water used to flush the main and take water quality samples after the
burst;
4. Water lost from reservoirs and other storage facilities due to non-closing inlet valves,
wash-out valves not fully closed, incorrectly set water level recorders when a reservoir is
filled by pumps controlled by the reservoir level and from leakage through the structure,
and
5. Water lost from leaking pump glands, inadequately maintained sluice valves, hydrants
etc.
For a new distribution system that has been correctly designed, installed and commissioned,
losses should be negligible within the early years of the pipe system. In order to allow for some
leakage, especially during the later life of the system, an allowance needs to be made.
This will be the higher of the following two calculations:
15% of total domestic and non-domestic consumption;
10 m3/d/Km of network in dense urban or 5 m3/d/Km in other areas
1.7

Water Used by PAEW in its Normal Operations (after leakage)

The PAEW will use water during its normal day-to-day operations for such activities as mains
cleansing and running hydrants for water quality sample analysis.
Normally, the water used is minimal and can be considered as included within the technical
losses. If there is known to be specific problems in the area, for example with debris settling in
the mains due to the condition of the mains or as sand carried over from the treatment/source
works, an allowance of 2% of customer demand can be assumed.
1.8

Fire Fighting

Omans statutory requirements should be ascertained, and met.


In Oman the Directorate General of Civil Defence set the requirements for fire fighting.

6/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

The design of new distribution network should incorporate fire hydrants in accordance with the
Directorate General of Civil Defence requirements. Each project must get their approval for the
location of fire hydrants.
The additional ground service reservoir capacity for fire fighting is as follows:
3

Population (Capita)

Capacity (m )

Less than 5,000

50

Less than 10,000

100

Less than 20,000

200

Less than 30,000

300

Less than 40,000

350

Less than 50,000

400

Less than 60,000

450

Less than 70,000

500

When designing the flow capacity of a distribution system, the following fire flows shall be
incorporated, depending on the population of the area served.

1.9

Population

Fire flow

(Capita)

(m3/min)

Less than 5,000

Less than 10,000

Less than 20,000

Less than 40,000

Less than 60,000

Less than 80,000

Less than100,000

10

Commercial Losses

Commercial losses are generally included at design stage within domestic and non-domestic
consumptions.
Meter and other income determination errors
In addition to the recorded flow of water to a customer, there might be an additional flow not
recorded by the meter due to wear of the meter; the meter being incorrectly installed or, in
extreme, the meter has become blocked or has stopped recording for some other reason.
A key consideration can be the type of meter installed being one that is not capable of recording
very low flows that can occur when a customers inlet valve to a cistern is not closing off.

7/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

It should be noted that the meter error is included within the above per capita consumption
rates. Thus, meter error normally affects the income received by the PAEW and the historical
records of consumption in a given supply area, not the quantity of water that it has to supply.
Unknown Connections and Theft
These are obviously not known as they would be stopped, disconnected or converted into a
legitimate connection. As such no specific allowance need to be made, unless it is known that
the mains are to be laid in an area where illegal connections may be made.
1.10

Peak Factors

Water demand of customers can vary by the hour, by the day and seasonally.
The total quantity of water supplied or drawn for 365 days, divided by 365 is the average daily
demand. This is the normal reference flow.
Domestic per capita figures quoted relate to the annual average demand.
At various times of the year and as a result of seasonal needs, people will use more water in
some days. A similar higher demand can occur at weekends when customers are at home. This
is known as the peak day demand. The peak can vary from one area to another. Past records
of the study area, or a similar one, should be consulted to determine the historic peak day factor
to be used in the design.
People draw water according to the needs. The PAEW has to meet the instantaneous water
demand when many people wish to draw water at the same time e.g. in the morning before
going to work. This is known as the peak hour demand. The peak hour demand can be
extremely variable, depending as it does on the actions of people in an area. Within a
predominantly residential area where all the customers leave at around the same time each day
to go to work, take children to school, the peak hour factor can be as much as 5 times the
annual average. The peak hour demand can be significantly reduced where water goes first into
a storage tank, and people draw from the storage. The flow to a property is then limited by the
capacity of the service pipe; not the quantity of water used instantaneously.
The amount by which a peak demand exceeds the annual average demand is known as the
peak day or peak hour factor. The peak factors do not apply to all categories of demand. For
example, leakage will not vary. Industrial demand is usually more consistent indeed the
PAEW can ensure a consistent draw-off by requiring the industrial premise to have storage and
by limiting the size of the service pipe to the premise.
Where there is no historic data available, the following can be used as a guide:
Peak day flow = 1.3 annual average demand (based on the average day demand in the peak
week) excluding leakage or 1.24 times water in to supply i.e. inclusive of leakage
Peak hour flow = 2.5 peak day flow.

8/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

2. DISTRIBUTION SYSTEMS

2.1

Future Water demand Design horizon and phasing of Assets


2.1.1

General

Any design must take into account the likely growth in demand in the areas that will be fed from
the new main(s).
Whilst it is normally not desirable to lay a second pipe in the future to allow for future growth,
there can sometimes be an advantage. For example, if the development is to be staged it might
be cost beneficial, if space permits, to lay one main for the immediate development and to
follow this with a duplication when subsequent development takes place. An alternative would
be to convert a gravity main to a pumped main to force through more water.
Such phasing is only likely to be cost effective for large diameter mains and when there will be a
significant time difference between the development phases. The justification can only be after
a cost benefit analysis is made.
A more likely, and advantageous, scenario would be to lay one main along one route and then
duplicate the main along a second, separate route.
In some instances, short sections of main across roads have been installed and left blanked off
allowing an additional main to be laid in the future picking up these blanked off mains. This
allows an extra parallel main to be laid at minimal cost as the difficult sections have been
installed at the time of the original main being laid.
The design horizon for PAEW projects is 25 years. However for consistency issues, horizon
currently used is year 2040.
2.1.2

Water Demand

See above.
2.1.3

An `` All-In`` figure for preliminary estimating

Surprisingly and consistently, a rule of thumb all-in peak day design flow that can be used for
preliminary estimating within an area, is found to be between 300 and 350litres/head/day.
2.2

Pressure in the network

In a distribution system water should be supplied with adequate pressure and flow. However,
pressure is lost by the action of friction at the pipe wall and in pipe line components such as
valves. The amount of pressure loss is also dependant on the water demand from customers,
pipe material, length, gradient and diameter.
To deliver sufficient quantities of water the pressure head in the network should, wherever
possible, be at least 1.5 bar (15 m.w.c., worst point peak day, peak hour) in all parts of the
network, including the remotest and highest points. The maximum pressure should not exceed
6 bar (60 m.w.c.).
In case of fire fighting flows, pressure in the network shall be maintained as minimum positive
value i.e. negative pressure should not be developed in the network.

9/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

3. TRANSMISSION AND TRUNK MAIN DESIGN


3.1

Headroom

Not used in the design of distribution mains, but used for source/treatment works, pumping
stations and transmission mains, is the concept of headroom.
Following a major incident, the PAEWs reservoirs and mains will be depleted. The quantity of
water to be supplied by the PAEW in these conditions must be such as to not only meet
demand, but also to refill the reservoirs and re-charge the mains.
Customers may have been without water for a considerable time. They will want to use water
for a backlog of purposes, and their storage will need to be re-filled.
In order to provide for this addition demand, a treatment works etc. is designed to meet the
average daily flow not over 24 hours, but over 21 hours i.e. the works are designed to supply
24/21 (1.14) times the annual daily flow or, put another way, with 15% extra capacity than would
otherwise be provided. This ratio can be refined for large systems where several sources of
water or pumping stations may be used concurrently to supply the demand.
3.2
Route and elevation
In consideration of the route of a pipeline, a number of factors must be taken into account:
1. The hydraulic gradient along the pipeline;
2. Where there is space to lay a main and to subsequently maintain the pipeline;
3. Ground conditions;
4. Obstructions are other difficulties to be overcome both in the laying and continued
operation of the main, such as wadis;
5. Major road crossings;
6. Environmentally sensitive areas;
7. Safety of the PAEW staff in gaining access to the pipeline, and
8. The proximity of areas that could be serviced from the main.
9. Other existing or planned utilities (sewer, oil/gas pipelines, cables) should be taken
into consideration;
10. Roads easements standards should be considered.
Sometimes it will be necessary to consider alternative routes and also intermediate boosters to
re-lift the pressure.
Sometimes it is necessary to tunnel under obstacles with a relatively short section of smaller
diameter main. Directional boring of large diameter pipes can be a major cost and so reducing
the size of the main at such crossing points is often desirable. Often for security of supply such
crossings are duplicated. For example a 400mm main could cross a major road with 2 parallel
300mm diameter mains. If this action is taken, the twin bores should be suitably distanced apart
so that an incident to the first bore does not affect the second. The water carrier pipe should be
laid within a sleeve to enable a failed pipe to be readily removed and replaced. For the same
reason, two adjustable couplings with a connecting piece should be provided.
All crossings of major obstacles should be guarded by in-line valves either side of the obstacle.
All branches off a transmission and trunk mains should be metered, as required by the PAEW
Non-Revenue Water Manager, within the Planning and Asset Management Department.

10/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

No service connection should be taken directly off a transmission or trunk main. A fault with the
connection may require the main to be shut down, with possible consequences on maintaining
supplies. If a connection is required, it should be taken from a tapping drilled into a blank flange
on a branch tee, guarded by a valve.
3.3

Desired pressure

The pressure within a pipeline is determined by the pressure at the start of the pipeline and at
the terminal point. Pressure at various points along the pipeline is shown on the hydraulic
gradient that must be prepared for all transmission or trunk mains during preliminary design at
the latest.
The hydraulic gradient can be used to determine the pressure rating of the pipe to be used.
It is important to ensure that:
1. Pipeline profile should go above the gradient line at any point;
2. The pipeline does not empty into a receiving reservoir due to the hydraulic
conditions at the end of the pipeline;
3. At no place must the pressure within the pipeline exceed the manufacturers
pressure rating for the pipe.
To avoid the above happening, a break pressure tank may be required, or an elaborate control
system installed at the terminal reservoir.
If branches are to be taken off the main under design, the adequacy of the pressure at the takeoff must be determined and, if necessary, a booster pump(s) or a pressure reducing valve
installed.
Normally the aim of the design is to transfer a desired flow down the main whilst achieving a
minimum pressure at the far end. This minimum pressure could be the top water level of a
service reservoir or water tower. The pressure could be a service level required to feed
properties or the desired suction pressure of a transfer pump at the end of the main being
designed.
3.4

Velocity

Normal design velocity is 1 m/s. This figure is the point at which particles in the main will be
picked up. This helps to ensure that the main is self-cleaning and reduces long term build up
inside the main.
A peak velocity as high as 2.5 m/s is possible but is seldom considered due to the high stresses
this can cause and high pressure loss than can be generated over short distances. A peak
velocity of 2 m/s is more common but will depend on pipe diameter (more acceptable for large
pipes than small diameters).
3.5

Surge

Surge is a specialist subject for which advice should be taken.


All transmission and trunk mains, pumped or gravity, should be evaluated for the risk of
excessive surge pressures developing. If required, anti-surge measures should be adopted and
necessary protection provided to the pipeline.
3.6

Valves

11/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

Valves should be installed so that, where possible, all parts of the network can be controlled
without adversely affecting another part. As a minimum valve shall be installed:
On all branch connections,
On all branches from feeder mains,
Between feeder pipes and hydrants;
Not more than 2 valves at a tee,
Preferably at a uniform distance from pipe intersections;
Not more than 3 valves at a cross,
Washouts at all valley points.
The frequency of in-line isolation valves should be determined for each pipeline and shall be
located strategically. A maximum spacing of line valves for transmission main should not
exceed 5km and 2 km for primary trunk mains and maximum 1 km for distribution lines.
The following types of valves are used in a water supply system:

Isolating valves (Gate valves, butterfly valves);


Non-return valves;
Air release valves;
Washout valves;
Pressure regulating valves;
Flow control valves.

Gate valves with flange joints shall be used on pipelines DN 400. For pipelines > DN 400
butterfly valves shall be used.
All valves must be located with due concern for the safety of the PAEW staff/contractor during
their operation.
Valves can be buried or installed in a chamber. The criteria for chambers are given in the
Design Guidelines for Transmission and distribution pipelines TET/DG/5005.
The chambers should be constructed to take the end thrust of the pipe against the closed valve.
Some in-line valves may be electrically operated and some provided with a by-pass
(systematically above DN 400).
3.7

Air valves

In order to prevent an air lock in the pipeline, an adequate number of suitably designed air
valves need to be incorporated into the pipeline design.
See TET/SS/5008 for technical specifications of air valves.
Air valve design is a special subject but generally air valves require to be located:
1.
2.
3.
4.

At high points on a pipeline;


Where the gradient of a pipeline significantly increases or decreases;
On pumping mains close to the outlet from a pumping station;
Between inline valves to allow for mains to be drained and re-charged.
3.8
Pipe materials

12/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

Consideration needs to be given to the pipe material.


PAEW recommend the following:
Distribution pipes
o HDPE up to 300 mm diameter (OD 110mm, 180mm and 225mm shall be
used);
o Ductile Iron above 300 mm diameter;
o And DI for special locations like road/wadi crossings.

Transmission Lines
o Ductile Iron up to 600 mm diameter;
o Above 600 mm dia comparison should be made with MS pipes (generally
epoxy coated in and out or 3 layers PPE);
o In special cases like high pressure, small diameter pipes MS pipes may also
be used.

Pre-stressed Concrete, GRE and GRP are not in use yet.


3.9

Thrust blocks

Where a pipeline contains flexible joints, concrete thrust blocks must be designed and
constructed at all changes in pipe direction horizontal and vertical. The thrust block must be
capable of resisting the pipe test pressure; not the operating pressure which will be lower.
3.10

Energy considerations

Sometimes along long sections of trunk main it is necessary to re-lift the pressure.
For a pumping main, there is normally a choice between a large pipe diameter with a
corresponding low pumping head a high CAPEX/low OPEX option - or a smaller pipe
diameter with a larger pumping requirement a low CAPEX/high OPEX option.
In order to evaluate the options and determine the most suitable, a cost benefit analysis is
required considering both OPEX and CAPEX, over the whole life of the assets. The cost of the
booster maintenance, replacement and running costs should be considered.
Having a transfer booster mid-point along a transmission main can have a dramatic impact on
pressures along the length of the main. It is possible to use mains with lower pressure rating
and background leakage may also be reduced. Additionally future mains breaks should be
reduced as a result of operating at a lower average operating pressure along the length of the
main.
4. WATER QUALITY
Consideration to water age should be made at design stage. Increased residence may lead the
deterioration in water quality e.g. reduce chlorine content, taste ,odour and microbiological
growth.
Hydraulic modelling should be used to assess age and potential water quality impact.
Designing pipeline`s future growth should consider range of flows (retention time) over the life
time of the pipe e.g. initially residence time may be significant due to low demand.

13/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

5. CONTROL PHILOSOPHY
There are numerous methods of controlling a transmission main:
Simple transmission main to a demand area
In this instance the demand from the customers determines how much water will flow down the
main. There is little control that can be used on such a system other than pressure control.
The main will have been sized to meet peak demand usage however at night demand is much
lower. Therefore the pressure loss across the main will be lower and the pressure on the main
and within the demand area will increase.
It is possible to install a pressure reducing valve at a point along the new main that will reduce
pressures at night to minimize leakage and burst rate.
In most PAEW systems, transmission main do not feed directly distribution zones.
Transmission main into storage
Within PAEW the water is generally not directly sent to distribution mains in demand areas.
Generally all the water reaches the storage service reservoir and is distributed by gravity.
In this case the normal method of control is to install a control valve on the inlet to the reservoir.
This can be controlled in three ways:
1. A valve When water level in the reservoir falls below certain level the valve opens
automatically and allowing unrestricted flow into the reservoir. If the level exceeds an
upper control point the inlet valve shuts. This can be a Floating valve. However this
system is not desired as it often generate overflow if the valve is not closing properly. An
electrical valve controlled by the level in the reservoir is therefore preferred.
2. Flow Control A modulating control valve on the inlet to the reservoir operates such that
a set flow is allowed into this reservoir. This control can be adjusted remotely from an
operational control room.
3. Pressure Sustaining Valve A modulating control valve on the inlet to the reservoir that
maintains a set pressure upstream on the transmission main. This form of control is
most common where there is a high point on the transmission main that prevents
unrestricted flow from going into the reservoir. A PSV will ensure that positive pressure
always exists on the transmission main.
Transmission main to the suction of a booster
This can occur if there is a high point at the end of the transmission route which requires a
booster to lift the water or if the transmission main is of such a long length that a simple
transmission system with realistic mains diameters is not possible.
It is possible that an economic assessment of mains capacity vs. boosting energy indicates that
this is the preferred solution.
The size of the transmission main will influence the suction and delivery at the transfer booster.

14/15

Design Guidelines
BASIC DESIGN CRITERIA

TET/SS/5501
Date: 14/05/2015
Issue: 1.1

It is possible to combine all these elements and controls to ensure that it is possible to transfer a
given amount of water along any feasible construction route.
6. SECURITY OF SUPPLY RISK MANAGEMENT
See also the Emergency Response Manual.
Wherever possible, risk should be designed out of the water supply system.
Reservoir provides adequate security of supply to a network allowing enough time for a
transmission repair to take place, or a treatment works failure rectified. All supply areas should
have a minimum of 48 hours storage located after the transmission system and as close as
possible to the area of supply.
Whenever possible and providing a significant risk reduction effect compared with additional
costs the design of the system will take into account the following considerations:
Alternative supply routes;
Limiting repair time through the use of standard pipe diameters and adequate provision
of inline valves and corresponding fittings (washout and air valves);
Parallel pipes or ring main arrangements.

15/15

Вам также может понравиться