Вы находитесь на странице: 1из 32

Dr.

Farrukh Arif, Assistant Professor, NED UET

CE-591-Cost Engineering and


Control
Lecture 1
Part (a)
________________________________________________

Dr. Farrukh Arif,


Assistant Professor, NED UET
Lecture 1-1

Dr. Farrukh Arif, Assistant Professor, NED UET

Overview
Construction What it is, what it is not
 The Design Process
 Economic Evaluations


Users
Results
Reasons

Business Strategies
 Information
 International Business


Lecture 1-2

Dr. Farrukh Arif, Assistant Professor, NED UET

Construction
What it is, what it is not
 Portable

plant, materials
 Output=immobile structures
 Construction plants vary in size and
complexity
 Difference between construction,
manufacturing, and agriculture plants?
Lecture 1-3

Dr. Farrukh Arif, Assistant Professor, NED UET

Construction
What it is, what it is not

Lecture 1-4

Dr. Farrukh Arif, Assistant Professor, NED UET

Construction
What it is, what it is not
 Construction

projects are broken down


into four groups
Industrial
Heavy engineering and infrastructure
Commercial building
Residential

Lecture 1-5

Dr. Farrukh Arif, Assistant Professor, NED UET

Design
 Every

Design Is a New Combination of


Pre-Existing Knowledge that Satisfies
an Economic Want
New Combination Creativity
Economic Want Driver

Lecture 1-6

Dr. Farrukh Arif, Assistant Professor, NED UET

Elements of Design
 Identification

and Definition of Problem


 Development of Concepts
 Engineering Models
 Evaluation
 Design
 Implementation
Lecture 1-7

Dr. Farrukh Arif, Assistant Professor, NED UET

Design
Process

Lecture 1-8

Dr. Farrukh Arif, Assistant Professor, NED UET

Problem
 Recognize

a Need

Economic Want
 Good

Description = Good Solution


 Detailed Specification of Requirements

Lecture 1-9

Dr. Farrukh Arif, Assistant Professor, NED UET

Concepts
 New

Combinations of Existing
Knowledge
 Need to Collect a Lot of Knowledge
Relative to the Problem
 Unrestricted

Generation of Concepts
 Then Select and Refine
Lecture 1-10

Dr. Farrukh Arif, Assistant Professor, NED UET

Engineering Models
 Representation

to Explain an Aspect

 Prediction
 Discover

Pertinent Parameters

 Flexibility
 Simplistic

Lecture 1-11

Dr. Farrukh Arif, Assistant Professor, NED UET

Evaluation
Asking the right questions
 What is the total cost from design up to
construction?
 Does the construction coincide with the
abilities and experience of the contractor?
 What is the owners profit from the total
investment during the first few years of
production and sales?
 Pay-back period?


Lecture 1-12

Dr. Farrukh Arif, Assistant Professor, NED UET

Economic Evaluation
 Market

Defines Economic Want


 Cost Needs to Satisfy
 Cost Model Should Parallel the Design
 Detail and Accuracy of Estimate
Depends on Amount of Info Available
Depends on the Time for the Estimate
Lecture 1-13

Dr. Farrukh Arif, Assistant Professor, NED UET

Users


Economic Evaluation Produces:


Dollar Estimates
Labor Hour Estimates
Material Requirements

Used By:
Engineering
Manufacturing
Marketing
Materials Mgmt.
Accounting/Financial Planning
Lecture 1-14

Dr. Farrukh Arif, Assistant Professor, NED UET

Results from Economic Evaluation




Requires Answers to Questions


What are the performances, functions and
features of the product?
What Does It Look Like?
How Many?

Selects from Design Alternatives


 Determines Manufacturing Methods
 Decisions to Proceed


Lecture 1-15

Dr. Farrukh Arif, Assistant Professor, NED UET

Other Reasons
Cost to Manufacture
 Profit Prediction
 Labor Requirements
 Time (Scheduling)
 Control of Operations
 Improvement
 Budgets
 Equipment Justification


Lecture 1-16

Dr. Farrukh Arif, Assistant Professor, NED UET

Strategies
 Mass

Production

Large Quantities / Little Variation


 Batch

Production

Smaller Quantities / Large Variation


Similar Processes
 Projects

Very Small Quantities / Specialized


Lecture 1-17

Dr. Farrukh Arif, Assistant Professor, NED UET

Information
 Available

Information Varies

By Point in the Development


Amount of Uniqueness of Product
 Historical

Data (Accounting Records)


 Measured Data
 Policy Data
Lecture 1-18

Dr. Farrukh Arif, Assistant Professor, NED UET

Sources of Information
Accounting
 Personnel Department
 Operating Departments
 Purchasing
 Sales/Marketing
 Supervisors/Managers
 Trade Associations / Media


Lecture 1-19

Dr. Farrukh Arif, Assistant Professor, NED UET

CE-591-Cost Engineering and


Control
Lecture 1-Part (b)
Introduction to Cost Engineering
________________________________________________

Dr. Farrukh Arif,


Assistant Professor, NED UET
Lecture 1-20

Dr. Farrukh Arif, Assistant Professor, NED UET

What is Cost Engineering?




(AACE) defines cost engineering as


that area of engineering practice where
engineering judgement and experience are
utilized in the application of scientific
principles and techniques to the problems
of cost estimation, cost control, and
profitability.

Lecture 1-21

Dr. Farrukh Arif, Assistant Professor, NED UET

Total Cost Management




The effective application of professional and technical


expertise to plan and control resources, costs, profitability
and risk.

It is a systematic approach to managing cost throughout


the life cycle of any enterprise, program, facility, project,
product or service.

This is accomplished through the application of cost


engineering and cost management principles, proven
methodologies, and the latest technology in support of the
management process.
Lecture 1-22

Dr. Farrukh Arif, Assistant Professor, NED UET

What is a Project?


Projects can cover anything from a 2-day


engineering effort to resolve a minor
technical problem to the present-day super
projects
Multibillion Tunnel Project (Miami Tunnel)

We will relate most of the cost-engineering


principles to an average-size project
Petroleum or chemicals plant in the range of
$100 million to $200 million
Lecture 1-23

Dr. Farrukh Arif, Assistant Professor, NED UET

Project Life Cycle

Lecture 1-24

Dr. Farrukh Arif, Assistant Professor, NED UET

Why are Projects Built?










Favourable analysis of the marketing situation


Future increased demands
Need for new and different products
Research department may develop new
products with high sales potential
New government or social requirements
Ultimate reason in virtually every case in
economic need
Lecture 1-25

Dr. Farrukh Arif, Assistant Professor, NED UET

Why are Projects Built?




Questions needed to be answered


How much product should I make?
Where should the plant be built?
How competitive will a new product be?
If diversification is desirable, where and what?







Answer-Economic studies
Economic studies cannot be made without
investments, which, in turn, requires an estimate,
and that, in, turn requires a cost engineer (CE)
CE needed throughout life cycle
Need for cost control during all phases

Lecture 1-26

Dr. Farrukh Arif, Assistant Professor, NED UET

THE IMPORTANCE OF THE


COST ESTIMATE


Three important documents are critical to the


control of a project
The plan and schedule
The cost estimate
The contract between the owner and the contractor




Represent a major commitment by upper


management
Difficult to change once this commitment
Key tools for control over the much longer period
of project execution
Lecture 1-27

Dr. Farrukh Arif, Assistant Professor, NED UET

THE ROLE OF CEs DURING


THE EVALUATION PHASE



The earlier, the more effective


A period of screening, market evaluations, political and
geographic considerations, and major highlevel decisions
Role of CE
Provides the cost estimates needed in the economic evaluations
Different case studies reflecting alternate processes
Different geographic locations
Evaluation of a preliminary sketch of a new process being
developed

Lecture 1-28

Dr. Farrukh Arif, Assistant Professor, NED UET

THE ROLE OF CEs DURING


THE BASIC-DESIGN PHASE


During the evaluation or screening phase, the main emphasis was


placed on the evaluation of the difference in the costs of alternative
approaches to select the most economical case.
During this phase:
The process or basic design is finalized
The physical layout of the facilities involved is given consideration.
The need for support facilities (utilities and off-plot items, such as storage, roads,
and fire protection) is reviewed.
Timing (schedule) is given more serious consideration.
The project execution strategy is also discussed (who does what, when, where).




Considered and discussed


CE will be making certain assumptions

Lecture 1-29

Dr. Farrukh Arif, Assistant Professor, NED UET

What is an Estimate?
 An

estimate is a prediction
 Design Basis: A step-by-step plan of
how the project people feel or predict
the job will be done
 For Example;
Petroleum and chemical plant
Flow plan and equipment list
Conceptual-estimating phase

Lecture 1-30

Dr. Farrukh Arif, Assistant Professor, NED UET

IMPORTANCE OF DESIGN
BASIS
 There

are many potential variations

Final site for the project may not yet be


selected
Project schedule
Availability and cost of labour
Source of materials
Final detailed design
Taxes etc.

Lecture 1-31

Dr. Farrukh Arif, Assistant Professor, NED UET

Role of CE During Basic-Design


 The

design basis, are not yet finalized


 The project people are engrossed in
developing the design and execution
basis
 Little time to devote to developing for
CEs
 Jack-of-All-Trades
Lecture 1-32

Dr. Farrukh Arif, Assistant Professor, NED UET

Jack-of-All-Trades


For example, to predict the final hardware that will result


from the basic design, CEs need to visualize what the final
detailed design will look like (i.e., they must be designers
of sorts). They need to develop a time schedule for the
project and, therefore, have to act as schedulers. They
need to gather and analyse historical cost data and act as
data analysts. They must establish costs for different
geographic locations and countries and predict escalation
rates, in effect becoming mini-world-economists. They
must predict contract strategy: what kind of contract, to
how many contractors, under what conditions, and,
therefore, act as contracts engineers.
Lecture 1-33

Dr. Farrukh Arif, Assistant Professor, NED UET

THE ROLE OF CEs DURING


DETAILED ENGINEERING


After contract award, CEs embark on dual roles. We still need an owners CE on the
project (they are needed by the owner throughout the project to protect and monitor the
economic decisions that were made much earlier by the owner), but now contractors
require CEs to assist their project people to exercise cost control on the project.

During the detailed-engineering phase, contractors CEs will prepare the definitive
control estimate.

The estimates for change orders.

Cost-control engineer for the contractors project management team.

Owners CEs will have the responsibility or reviewing and commenting on contractors
detailed control estimates, reviewing their estimates for extra costs and change orders
and, most important on a reimbursable project, appraising and monitoring the
contractors efforts in the area of cost control.
Lecture 1-34

Dr. Farrukh Arif, Assistant Professor, NED UET

ROLE OF CEs DURING


CONSTRUCTION


We have both the owners and the contractors CEs


playing important roles.
The owners CEs continue to appraise the contractors
cost control efforts, monitor changes, and review extras.
The contractors CEs now become more deeply involved
in providing input to the contractors planning and
scheduling team.
Their forecasts of labour work hour requirements are an
essential ingredient for the project schedule and have an
impact on predicting both final costs and final completion
date.
Lecture 1-35

Dr. Farrukh Arif, Assistant Professor, NED UET

SOME BASIC COSTENGINEERING TERMS




Cost Engineer means one thing to an owner and


often something else to a contractor.
Owners definition of a CE is an engineer who can
and, most likely, will be involved in all aspects of
cost engineering.
Most contractors still use the term Cost Engineer
to describe only their cost-control engineer and
refer to the engineer developing the cost
estimates as an estimator.
Lecture 1-36

Dr. Farrukh Arif, Assistant Professor, NED UET

SOME BASIC COSTENGINEERING TERMS


 Types

















of Estimates

Some of the terms often used to describe these estimates are as follows:
Planning/evaluation stage
Screening
Preliminary
Quickie
Order-of-magnitude/guesstimates
Rough, gross, scope, etc.
Basic design stage
Preliminary
Budget
Semidetailed
Detailed engineering construction
Definitive
Appropriation
Lump sum
Detailed

Lecture 1-37

Dr. Farrukh Arif, Assistant Professor, NED UET

It should be noted that the above terms,


although commonly used, can often be
confusing and misleading. For example,
describing an estimate as a budget
estimate provides very little information
regarding the estimate quality, the amount
of detail or effort involved, or when, within
the development of the project, the estimate
was prepared.
Lecture 1-38

Dr. Farrukh Arif, Assistant Professor, NED UET

INCENTIVES TO CENTRALIZE
COST ENGINEERING









Centralizing Cost Engineering within a company has some very distinct advantages
It provides a focal point within the company for all cost related matters.
Over time, Cost Engineering expertise is developed, resulting in effective cost estimating and cost
control.
With the assignment of CEs to projects, full time follow-up of the Cost Engineering area results on all
projects.
Estimating methods development and maintenance will be ongoing.
Central data collection, analyses, and maintenance will occur.
Estimates and cost control results will be reliable and consistent.
Finally, the Cost Engineering function will be elevated to professional status within the company with

full recognition by management and others of its importance to the success of project management

Lecture 1-39

Dr. Farrukh Arif, Assistant Professor, NED UET

THE SUCCESS FORMULA


THE THREE Ds
 Definition,
 Documentation
 Discipline

Lecture 1-40

Dr. Farrukh Arif, Assistant Professor, NED UET

Overview of Cost Budgeting &


Cost Control
CE-591 Construction Engineering and
Control
Lecture-1

Lecture 1-41

Dr. Farrukh Arif, Assistant Professor, NED UET

Cost Budgeting
Allocation of overall cost estimates
to individual work items in order to
establish a cost baseline for
measuring project performances.

Lecture 1-42

Dr. Farrukh Arif, Assistant Professor, NED UET

Inputs to Cost Budgeting


 Cost

Estimates
 Work Breakdown Structure
 Project Schedule

Lecture 1-43

Dr. Farrukh Arif, Assistant Professor, NED UET

Tools and Techniques for Cost


Budgeting
Tools
and
Techniques
for
developing project Cost Estimates
are used to develop budgets for
work items as well.

Lecture 1-44

Dr. Farrukh Arif, Assistant Professor, NED UET

Outputs from Cost Budgeting


 Cost

Baseline
A time-phased budget that will be used
to measure and monitor cost
performance on the project. It is
developed by summing
estimated
costs by period and is
usually
displayed in the form of an S-curve.
Lecture 1-45

Dr. Farrukh Arif, Assistant Professor, NED UET

Lecture 1-46

Dr. Farrukh Arif, Assistant Professor, NED UET

Cost Control

Project cost control begins with the preparation of


the cost estimate and the construction budget.
The information that is generated for estimating
purposes can be in terms of productivity rates, unit
costs, or both.
Small contractors frequently work in terms of unit
costs while large contractors base their estimating
on productivity rates
Lecture 1-47

Dr. Farrukh Arif, Assistant Professor, NED UET

Cost Control (contd)


Cost Control is concerned with
(a) Influencing the factors which create changes to
the cost baseline to ensure that changes are
beneficial.
(b) Determining that the cost baseline has
changed.
(c) Managing the actual changes when and as
they occur.

Lecture 1-48

Dr. Farrukh Arif, Assistant Professor, NED UET

Cost Control (contd)


Cost Control includes:

Monitoring cost performances to detect variances from


plan.

Ensuring that all appropriate changes are recorded


accurately in the cost baseline.

Preventing incorrect, inappropriate, or unauthorized


changes from being included in the cost baseline.

Informing appropriate stakeholders of authorized


changes.

Lecture 1-49

Dr. Farrukh Arif, Assistant Professor, NED UET

Inputs to Cost Control





Cost Baseline
Performance Reports
Provide information about cost performance
such as which budgets have been met and
which have not. It also alerts the project team
to issues which may cause problems in the
future.

Lecture 1-50

Dr. Farrukh Arif, Assistant Professor, NED UET

Inputs to Cost Control (contd)




Change Requests
These may occur in many forms-oral
or written, direct or indirect, externally
or internally initiated, and legally
mandated or optional. These may
require increasing
the budget or
may allow decreasing it.

Lecture 1-51

Dr. Farrukh Arif, Assistant Professor, NED UET

Tools and Techniques for Cost


Control
 Cost

Change Control System

It defines the procedures by which the cost


baseline may be changed. It includes the
paperwork, tracking systems, and approval
levels necessary for authorizing changes.
Performance Measurement
It helps to assess the magnitude of any
variations which do occur.

Lecture 1-52

Dr. Farrukh Arif, Assistant Professor, NED UET

Tools and Techniques for Cost


Control (contd)
 Additional

Planning
Perspective
changes
may
require new or revised
cost
estimates or analysis of alternate
approaches.
 Computerized Tools

Lecture 1-53

Dr. Farrukh Arif, Assistant Professor, NED UET

Outputs from Cost Control


 Revised

Cost Estimates
 Budget Updates
 Corrective Action
 Estimate at Completion
It is a forecast of total project costs
based on project performance.
 Lessons Learned
Lecture 1-54

Dr. Farrukh Arif, Assistant Professor, NED UET

Objects of Cost Control


1 To have a knowledge of the profit and loss of the
project throughout the duration of the project.
PROJECT PROFITS
1. Client payments.
2. Sale of surplus or scrap material and plant
3. Payments for plants or labor by others, where, this plant or labor
is , from time to time not required for the project.
PROJECT LOSSES
1) Labor and site office costs
2) Plant costs
3) Site overheads i.e. site facilities, access roads and office etc
4) Cost of tendering including bonds, insurance, etc.
5) Material costs.
6) Head office overheads proportioned over all current projects.
Lecture 1-55

Dr. Farrukh Arif, Assistant Professor, NED UET

Objects of Cost Control (contd)


2 To have a comparison between the actual project
performance and that conceived in the original
project plan.
Comparison is basically done according to the following
bases:
1)
2)

According to units of production


According to line items; e.g., labor, material, equipment, overheads, ---

3 Provides feedback data on actual project


performance to future project planning.

Lecture 1-56

Dr. Farrukh Arif, Assistant Professor, NED UET

The Project Cost System


Objectives of Establishing Project Cost
System.
1.

Keep the construction costs of the project within the


established budget.

2.

Develop labor and equipment productivity


information for estimating the cost of future work.

Lecture 1-57

Dr. Farrukh Arif, Assistant Professor, NED UET

Cost Codes


Each account of a contractor's accounting


system is assigned its own code designation
as a means of identification and
classification.

The most widely used cost codes are


CSI (Construction Specifications Institute)
and UCI (Uniform Construction Index).
Lecture 1-58

Dr. Farrukh Arif, Assistant Professor, NED UET

Cost Code and Cost Control

All items of expense are charged to the project


where they are incurred.
"General" or "miscellaneous" cost accounts should
not be used, is poor practice, and should be
avoided.
The cost code is to serve its basic purpose, it must
be understood and used consistently by all
company personnel.
Lecture 1-59

Dr. Farrukh Arif, Assistant Professor, NED UET

Cost Accounting Reports

Labor and equipment summary cost reports must be


prepared often enough so that excessive costs can be
detected while there is time to do something about them.

Cost report intervals are a function of the project size,


nature of the work, and the type of contract involved.

There must be a balance between the cost of generating


the reports and the value of the management information
received.

Lecture 1-60

Dr. Farrukh Arif, Assistant Professor, NED UET

Cost Accounting Reports


(contd)


Cost reports are frequently prepared daily on complex


projects involving multiple shifts.

Most contractors match their cost control system to their


payroll periods and to their time-monitoring system.

Lecture 1-61

Dr. Farrukh Arif, Assistant Professor, NED UET

Labor/Equipment Cost & Cost


Control


The job costs associated with materials,


subcontracts, and non-labor items of project
overhead are of a reasonably fixed nature.

Labor

and

considerable

equipment
uncertainty

costs
and

have
fluctuate

substantially during the construction period.


Lecture 1-62

Dr. Farrukh Arif, Assistant Professor, NED UET

Labor/Equipment Cost & Cost


Control (contd)


Contractor can control labor and equipment


to some extent, and require constant
management attention.

Detailed cost accounting methods must be


used with labor and equipment expenses if
effective management control over them is to
be obtained.
Lecture 1-63

Вам также может понравиться