Вы находитесь на странице: 1из 2

Electrical work

The Contractor shall carry out all the acts mentioned drawings in
accordance with the specifications and regulations of the State of
Qatar and outgoing Electricity and Water Company ( Kahramaa ) ,
and must provide samples mentioned materials for approval from
the owner and the consultant before Installation.
The installation of the course of the plastic ( PVC) cables inside the
building that is not less than the diameters of sewage Plastic 100
mm .
The Contractor shall supply and installation of cans Alsokitat and
installed well before the start of works of plaster .
The Contractor Albebat supply and installation of equipment for
electricity in the walls and roofs
All electricity businessman Pipat ( Emirates - Daiko flattened - or A
Country or Jordan ) synthesis of etymology .
Work phone :
The Contractor shall supply and installation of all the points as
shown in the drawings with the supply and installation of special
Alsuchitat Out of the same type of electrical Alsuchitat
Albebat installation of plastic inside the walls only without cables or
wires
Acts of plumbing and sanitary works : All nutrition internal and external water pipes are of a material
polypropylene industry a German
Supply and installation of Dynamo raise water Grundfos or Spa or its
equivalent with the installation of the tanks Brcher headlights
Water tanks ( Qatar Rotamold - dew ) according to specifications
approved by the listed capacity in the charts with Adopted by the
supply and installation
Almnholat coverings and Jerlat : The supply of heavy coverings
Manholat cast type (HEAVY DUTY)
For places Cars and Type Average Medium Duty For the rest of the
places
All Pipat sewage inside and outside the building of the kind UBVC
Bahrain
Inspections Rooms: The contractor drilling , construction and
finished to work is done by the assets of the workmanship and the
contractor Make sure inclinations on nature
Sizes and locations of manholes as requested by the management
of sewage In the case of conflict with the graphics are taking the
opinion of Supervising engineer on the project
Electricity works :
All electrical wiring work according to regulations Kahramaa and the
work necessary tests and get the consent of the Kahramaa circle .
Cables and wires Omani du Cap ( Dubai ) and Albaibat internal
industry Emirati sweatshirt ( Dikocanut ) .
Business phones paths and jerk cam satellite
Obtain successful supervising engineer on the quality of materials
used
The contractor following work :
Piping empty for cleaning pipelines and electric cables and
connected units adapt

Exchange of water conditioner and all the drainage pipes buried in


the work of the wall is connected to the nearest exchange
The work of all the connections and exits and the keys needed to
adapt to devices.

Вам также может понравиться