ITEM NO.

CB NO.

ASYA-PPP-AR-CB-001-15MAR15

ASYA-PPP-AR-CB-002-15MAR15

ASYA-PPP-AR-CB-004-15MAR15

ASYA-PPP-AR-CB-005-21MAY15

ASYA-PPP-AR-CB-006-29JUNE15
PPP-DMCI-C15-023

THE PRINCEVIEW PA
SUMMARY OF IS
AS OF 15TITLE
Relocation of pipe chase at 8th floor

Provision of mechanical chase and


relocation of fire exit door.

Revision at fire exit 1

Backfilling Removal for V.E.


New TVR layout padmounted type

THE PRINCEVIEW PARKSUITES PROJECT


SUMMARY OF ISSUANCE OF C.B.
AS OF 15-OCT-2015
DESCRIPTION
Relocation of pipe chase at 8th floor amenity near the fire
exit 2 as per reflected at the FCD of plumbing and sanitary.
This is the relocation of vertical pipe that may obstruct at the podium parking area.
Provision of mechanical chase at roof deck and machine
room for the relocation of smoke evacuation blower from
penthouse utility area to service deck for the exhaust
at residential hallway and the relocation of fire exit door 2 at roof deck.

Revisions of fire exit 1 at mezzanine podium to 6th floor


podium. This is to prevent obstruction at the fire exit stairs
during emergency incidents.

Slab on grade change to suspend slab @ ground floor


area.
New TVR layout at mezzanine floor considering meralsco comments and approval.

ATTACHMENT
8TH Floor amenity key plan w/ blow-up.
Keyplan reflected on FCD.
Roof deck key plan w/ blow-up.
Machine room and service room key plan w/ blow-up.
Blow-up reflected of FCD.
Mezzanine key plan w/ blow-up plans
1st floor key plan w/ blow-up plans.
2nd floor key plan w/ blow-up plans.
3rd floor key plan w/ blow-up plans.
4th floor key plan w/ blow-up plans.
5th floor key plan w/ blow-up plans.
6th floor key plan w/ blow-up plans.
Substructure key plan.
Substructure section.
Architectural key plan
Section
Structural details and schedule

DATE ISSUED
10-Apr-15

7-Apr-15

10-Apr-15

27-May-15
7-Jul-15

ITEM NO.

CB NO.

ASYA-PPP-ST-CB-001-21MAY15

PPP-DMCI-C15-005

PPP-DMCI-C15-007

PPP-DMCI-C15-010

ASYA-PPP-AR-CB-005A-8JUNE15

TITLE
Slab on grade change to suspended
slab.
Mistake in Building Setting Lay-out
Chipping the existing retaining wall and removal
of dowel.
Remedial structural rectification details for the
mispositioned columns
Backfilling removal for V.E.

THE PRINCEVIEW PARKSUITES PROJECT


SUMMARY OF ISSUANCE OF C.B.
AS OF 15-OCT-2015
DESCRI
Slab on grade change to suspended slab at ground floor area. Please

Error in the actual location of casted columns. We therefore require you to submit your methodolo
Some of existing retaining wall and dowels were removed/cut especially at gridline k and

Slab on grade change to suspended slab at ground floor area backfilling for V.E. Ple

ATTACHMENT
S-PV01-702
S-PV01-702A

DATE ISSUED

As-built of Mat foundation.

28-Apr-15

Key plan with cut dowels.

1-Jun-15

27-May-15

Column alignment rectification keyplan.

Substructure key plan.


Substructure section.

11-Jun-15

ITEM NO.
1
2

CB NO.
ASYA-PPP-EE-CB-002-15MAY15
ASYA-PPP-EE-CB-002-23JUN15

ASYA-PPP-EE-CB-004-15MAY15

THE PRINCEVIEW PARKSU


SUMMARY OF ISSUANC
AS OF 15-OCT-2
TITLE
Construction bulletin no. 2 Electrical
Construction bulletin no. 3 Electrical
Bid bulletin no. 4 Electical grounding layout as per site condition

THE PRINCEVIEW PARKSUITES PROJECT


SUMMARY OF ISSUANCE OF C.B.
AS OF 15-OCT-2015

DESCRIPTION
Relocation of grounding layout as per site condition this must be consdered by the b
Relocation of grounding layout as per site condition this must be consdered by

Relocation of grounding layout as per site condition this must be consdered by the b

ATTACHMENT

DATE ISSUED
1-Jun-15
23-Jun-15

ITEM NO.
1

CB NO.
ASYA-PPP-FP-CB-002-23APR15

ASYA-PPP-FP-CB-003-15MAR15

ASYA-PPP-FP-CB-001-15MAR15

ASYA-PPP-FP-CB-003-23APR15
PPP-DMCI-C15-022

THE PRINCEVIEW PARKSUITES PRO


SUMMARY OF ISSUANCE OF C.B
AS OF 15-OCT-2015
TITLE
Relocation of siamese at roofdeck fire exit 2
Removal of sprinkler at 8th floor
amenity
Removal of sprinkler at 8th floor
amenity
Relocation of wet stand pipe at the ground floor

THE PRINCEVIEW PARKSUITES PROJECT


SUMMARY OF ISSUANCE OF C.B.
AS OF 15-OCT-2015
DESCRIPTION
Relocation of stand pipe at roof deck area.
Removal of fire sprinklers at 8th floor amenity for value engineering.
Removal of fire sprinklers at 8th floor amenity for value engineering.
Relocation of stand pipe at ground floor area.

ATTACHMENT
Roofdeck plan w/ blow-up detail.
8th floor key plan reflected to FCD.
8th floor key plan.
8th floor key plan reflected to FCD.
8th floor key plan.
Ground floor plan
Pipe routing layout

DATE ISSUED
26-Jun-15
10-Apr-15
5-Oct-15
30-Jun-15

ITEM NO.
1

CB NO.
ASYA-PPP-PS-CB-004-15MAY15
PPP-DMCI-C15-012

THE PRINCEVIEW PARKSUITES PROJECT


SUMMARY OF ISSUANCE OF C.B.
AS OF 15-OCT-2015
TITLE
Blow-up detail for oil interceptor.

E PRINCEVIEW PARKSUITES PROJECT


SUMMARY OF ISSUANCE OF C.B.
AS OF 15-OCT-2015
DESCRIPTION
Blow-up detail for oil interceptor.

ATTACHMENT
Ground floor plan.
Blow-up plan and section.

DATE ISSUED
11-Jun-15

ITEM NO.

CB NO.

ASYA-PPP-ME-CB-001-14APR15

THE P
SU
TITLE
Provision of gooseneck at 9th floor utility deck.

THE PRINCEVIEW PARKSUITES PROJECT


SUMMARY OF ISSUANCE OF C.B.
AS OF 15-OCT-2015
DESCRIPTION

Provision of gooseneck at 9th floor from the EAD at ground floor commercial a

ATTACHMENT

DATE ISSUED

9th floor key plan w/ blow-up.

26-Jun-15