Вы находитесь на странице: 1из 76

Summary for Slabs

STEEL BARS
A193 WWF
A252 WWF
GROUND SLAB
CONCRETE
HSC 400MM
HSC 200MM
LEAN CONCRETE
POLYTHENE SHEET
ANTITERMITE TREATMENT
50MM THICK SCREED (Above HCS Slab)

50.96
2,933.35
1,609.42
467.29
1,566.44
1,276.42
333.00
158.42
3,194.17
3,194.17
80.47

Tons
M2
M2
M3
M3
M2
M2
M3
M2
M2
M3

Summary for Sub Structure


STEEL BARS
CONCRETE
LEAN CONCRETE
POLYTHENE SHEET
SURFACE AREA FOR SHUTTERING
ANTITERMITE TREATMENT
SHUTTERING FOR LEAN CONCRETE

57.28
899.51
176.18
1,559.11
1,250.22
1,096.16
2,465.58

Tons
m3
m3
m2
m2
m2
lm

Summary for Super Structure


STEEL BARS
CONCRETE
SURFACE AREA FOR SHUTTERING
ANTITERMITE TREATMENT

74.59
685.76
6,254.52
500.50

Tons
m3
m2
m2

Blockworks
100mm Block external wall
200mmmBlock
150mm Block
100mm Block
Fire Rated 200mm block
Backing rod
12mm Bar

2,342.73
2,187.16
222.66
105.73
386.88
1,960.06
8.70

m2
m2
m2
m2
m2
Lm
Tons

Plaster works
100mm Block external wall
200mmmBlock
150mm Block
100mm Block
Fire Rated 200mm block

2,108.01
3,037.69
445.32
253.57
791.39

m2
m2
m2
m2
m2

Concrete Works
Lean concrete for foundation
Lean concrete for grade slab
Foundation concrete
Grade slab concrete
Column, wall, beam concrete
Solid slab concrete
50mm thk screed (above HCS)

176.18
158.42
899.51
467.29
685.76
1566.44
80.47

M3
M3
M3
M3
M3
M3
M3

Polythene sheet for foundation


Polythene sheet for grade slab

1559.11
3194.17

M2
M2

Antitermite treatment for found


Antitermite treatment for G.Slab
Antitermite treatment for wall

1,096.16
3,194.17
500.50

M2
M2
M2

Steel bar for foundation


Steel bar for solid slabs
Steel bar for Column, wall, beam
A193 WWF (grade slab)
A252 WWF (above HCS slab)

57.28
50.96
76.77
2,933.35
1,609.42

Tons
Tons
Tons
M2
M2

HSC 400MM
HSC 200MM

1,276.42
333.00

M2
M2

Blockworks

100mm Block external wall


250mmmBlock

1,846.92
60.00

m2
m2

200mmmBlock

2,187.16

m2

150mm Block

222.66

m2

100mm Block

105.73

m2

Fire Rated 200mm block

386.88

m2

2,108.01
3,037.69
445.32
253.57
791.39

m2
m2
m2
m2
m2

Plaster works
100mm Block external wall
200mmmBlock
150mm Block
100mm Block
Fire Rated 200mm block

Summary*
STEEL BARS
CONCRETE
LEAN CONCRETE
POLYTHENE SHEET
SURFACE AREA FOR SHUTTERING
ANTITERMITE TREATMENT
SHUTTERING FOR LEAN CONCRETE

57.28
899.51
176.18
1,559.11
1,250.22
1,096.16
2,465.58

Tons
m3
m3
m2
m2
m2
lm

Summary*
STEEL BARS
A193 WWF
A252 WWF
GROUND SLAB
CONCRETE
HSC 400MM
HSC 200MM
LEAN CONCRETE
POLYTHENE SHEET
ANTITERMITE TREATMENT
50MM THICK SCREED (Above HCS Slab)

50.96
2,933.35
1,609.42
467.29
1,566.44
1,276.42
333.00
158.42
3,194.17
3,194.17
80.47

Tons
M2
M2
M3
M3
M2
M2
M3
M2
M2
M3

Summary*
STEEL BARS
CONCRETE
SURFACE AREA FOR SHUTTERING
ANTITERMITE TREATMENT

74.59
685.76
6,254.52
500.50

Tons
m3
m2
m2

CORRECTIONAL FACILITIES BUILDINGSMINISTRY OF


BUILDING 1201AQTY's SUMMARY SHEET
INTERIOR
QUANTITIES FOR CORRECTIONAL FECILITIES BUILDING PROJECT

Quantities Summary for Bulinding


ITEM.No SI.NO
1

DESCRPITION
CONCRETE WORKS

Lean concrete for foundation

Lean concrete for grade slab

Foundation concrete

Grade slab concrete

Column, wall, beam concrete

Solid slab concrete

50mm thk screed (above HCS)

POLYTHENE SHEET
A

Polythene sheet for foundation

Polythene sheet for grade slab

WATER PROOFING
A

Bitumen paint 2 coats (Vertical)

Bitumen paint 2 coats (Horizontal)

STEEL WORKS
A

Steel bar for foundation

Steel bar for solid slabs

Steel bar for Column, wall, beam

A193 WWF (grade slab)

A252 WWF (above HCS slab)

Page 7

CORRECTIONAL FACILITIES BUILDINGSMINISTRY OF


BUILDING 1201AQTY's SUMMARY SHEET
INTERIOR
5

SHUTTERING WORKS
A

Shuttering materisl supplied by Main


Contractor
BLOCK WORK

100mm Block external wall

250mmmBlock

200mmmBlock

150mm Block

100mm Block

Fire Rated 200mm block

PLASTER WORK
A

100mm Block external wall

200mmmBlock

150mm Block

100mm Block

Fire Rated 200mm block


TOTAL AMOUNT

Page 8

CORRECTIONAL FACILITIES BUILDINGSMINISTRY OF


BUILDING 1201AQTY's SUMMARY SHEET
INTERIOR

ILDING PROJECT -DAMMAM

y for Bulinding 1201 A (01 No only)


QTY

UNIT UNIT RATE

TOTAL AMOUNT

176.18

M3

255

44,925.90

158.42

M3

255

40,397.10

899.51

M3

291

261,757.41

467.29

M3

291

135,981.39

685.76

M3

281

192,698.56

1,566.44

M3

281

440,169.64

80.47

M3

281

22,612.07

3,387.95

M2

2.50

8,469.88

3,194.17

M2

2.50

7,985.43

1,828.84

M2

12

21,946.08

1,329.00

M2

12

15,948.00

57.28

Tons

3,264

186,955.53

50.96

Tons

3,264

166,323.28

76.77

Tons

3,264

250,577.28

2,933.35

M2

18.80

55,146.96

1,609.42

M2

18.80

30,257.14

Page 9

CORRECTIONAL FACILITIES BUILDINGSMINISTRY OF


BUILDING 1201AQTY's SUMMARY SHEET
INTERIOR

AMOUNT

10,500.00

M2

42.00

441,000.00

1,846.92

M2

27.99

51,695.29

60.00

M2

36.65

2,199.00

2,187.16

M2

29.72

65,002.52

222.66

M2

28.57

6,361.40

105.73

M2

27.99

2,959.27

386.88

M2

59.75

23,116.15

2,108.01

M2

5.70

12,015.67

3,037.69

M2

5.70

17,314.86

445.32

M2

5.70

2,538.32

253.57

M2

5.70

1,445.36

791.39

M2

5.70

4,510.94

SAR
AREA(M2)
RATE/M2

Page 10

2,512,310.43
3,860.00
650.86

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-202


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

CONCRETE WORKS
1

Plain Concrete 20 MPA-SRC-thick = 50mm

71

M3

366.00

Plain Concrete 20 MPA-SRC-thick = 100mm

126

M3

350.00

5% Micro Silica

M3

40.00

Mass concrete > 100mm below footings & ground beams (truck measured)

M3

280.00

SUB-TOTAL

SAR

Sub-structure Concrete works 30 MPA-SRC (W/o S.O.G)


1
Isolated Footing
2
Strip Footing
3
Tie Beams/Grade Beam
4
Column Neck
5

Wall Neck (vary thick)


Page 11 of 76

606
193
13

M3
M3
M3
M3

620.00
620.00
900.00
1,125.00

13

M3

1,100.00

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-202


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Slab on grade (20 MPA)-SRC

252

M3

455.00

Vapour Barrier 300 micron Poly Ethylene under slab on grade

M2

3.00

Damp Proofing

M2

6.00

5% Micro Silica

M3

50.00

SUB-TOTAL

SAR

Page 12 of 76

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-202


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Super-structure works 30 MPA-OPC (Height as per drawings & spec max 4.5M)
1

Column/Beams/Walls

388

M3

1,050.00

(Column/Beams/Walls) with Corbel

M3

1,250.00

Suspended Slab (vary thick)

471

M3

975.00

Concrete Ramps, Steps & Landing

15

M3

1,200.00

Fair face finish for Concrete Ramps, Steps & Landing (Saeled Concrete)

M2

135.00

Concrete Screed

M3

550.00

Concrete Parapet

M3

1,050.00

Concrete Coping (Galvanized Accessories)

LM

130.00

Mechanical Pad

M3

600.00

3
SUB-TOTAL

SAR

Page 13 of 76

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-202


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Steel Reinforcement (3% allowable wastage)


1

Supply, Cut, Bend & Install of Straight Reinf bars For 8 & 10,12,14,16mm & above

Ton

3,850.00

Unit Price for Cut, Bend & Installation

Ton

825.00

Unit Price for Installation only

Ton

675.00

4*

Unit Price for Supply,Cut and bend only

Ton

3,175.00

SUB-TOTAL

SAR

BLOCK WORKS AND PLASTER WORKS


BLOCK WORKS, including mortar tools / reinforcement dia 10mm & filling all
height around openings curing.Etc.
1

Supply & Installation of blocks 200mm(CMU), (Non Fire Rated)

3,405

M2

95.00

Supply & Installation of blocks 150mm(CMU), (Non Fire Rated)

1,599

M2

90.00

Supply & Installation of blocks 100mm(CMU), (Non Fire Rated)

1,626

M2

85.00

Page 14 of 76

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-202


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Additional Rate for Fire Rated Solid Block

M2

20.00

Supply & Apply Backing rod (3cm thick) and fire rated seleant above block walls.

LM

55.00

PLASTER WORKS, including materials, angle beds, wire mesh & all related
accessories and curing.Etc.
1

Supply & Installation of Cement Plaster (Internal)

M2

42.00

Supply & Installation of Cement Plaster (External)

M2

46.00

Galvanized Steel Grooves in Plaster

LM

15.00

SUB-TOTAL

SAR

GRAND TOTAL

SAR

Page 15 of 76

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

Current

Total
Amount(SAR)

Total

26,000.64

44,096.50

70,097.14

375,906.00
173,646.00
14,681.25

14,168.00

Page 16 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

114,705.50

Current

Total
Amount(SAR)

Total
-

693,106.75

Page 17 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

407,736.00

Current

Total
Amount(SAR)

Total

459,147.00

18,444.00

1,842.00
887,169.00

Page 18 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

Current

Total
Amount(SAR)

Total

323,496.85

143,866.80

138,189.60

Page 19 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

Current

Total
Amount(SAR)

Total

605,553.25

2,255,926.14

Page 20 of 76

Remarks

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-1302


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

CONCRETE WORKS
1

Plain Concrete 20 MPA-SRC-thick = 50mm

81

M3

366.00

Plain Concrete 20 MPA-SRC-thick = 100mm

91

M3

350.00

5% Micro Silica

M3

40.00

Mass concrete > 100mm below footings & ground beams (truck measured)

M3

280.00

SUB-TOTAL

SAR

Sub-structure Concrete works 30 MPA-SRC (W/o S.O.G)


1
Isolated Footing
2
Strip Footing
3
Tie Beams/Grade Beam
4
Column Neck
5

Wall Neck (vary thick)


Page 21 of 76

86
157
78
8

M3
M3
M3
M3

620.00
620.00
900.00
1,125.00

60

M3

1,100.00

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-1302


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Slab on grade (20 MPA)-SRC

289

M3

455.00

Vapour Barrier 300 micron Poly Ethylene under slab on grade

M2

3.00

Damp Proofing

M2

6.00

5% Micro Silica

M3

50.00

SUB-TOTAL

SAR

Page 22 of 76

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-1302


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Super-structure works 30 MPA-OPC (Height as per drawings & spec max 4.5M)
1

Column/Beams/Walls

334

M3

1,050.00

(Column/Beams/Walls) with Corbel

M3

1,250.00

Suspended Slab (vary thick)

395

M3

975.00

Concrete Ramps, Steps & Landing

29

M3

1,200.00

Fair face finish for Concrete Ramps, Steps & Landing (Saeled Concrete)

M2

135.00

Concrete Screed

M3

550.00

Concrete Parapet

M3

1,050.00

Concrete Coping (Galvanized Accessories)

LM

130.00

Mechanical Pad

M3

600.00

8
SUB-TOTAL

SAR

Page 23 of 76

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-1302


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Steel Reinforcement (3% allowable wastage)


1

Supply, Cut, Bend & Install of Straight Reinf bars For 8 & 10,12,14,16mm & above

Ton

3,850.00

Unit Price for Cut, Bend & Installation

Ton

825.00

Unit Price for Installation only

Ton

675.00

4*

Unit Price for Supply,Cut and bend only

Ton

3,175.00

SUB-TOTAL

SAR

BLOCK WORKS AND PLASTER WORKS


BLOCK WORKS, including mortar tools / reinforcement dia 10mm & filling all
height around openings curing.Etc.
1

Supply & Installation of blocks 200mm(CMU), (Non Fire Rated)

M2

95.00

Supply & Installation of blocks 150mm(CMU), (Non Fire Rated)

M2

90.00

Supply & Installation of blocks 100mm(CMU), (Non Fire Rated)

M2

85.00

Page 24 of 76

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Building No. B-1302


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Additional Rate for Fire Rated Solid Block

M2

20.00

Supply & Apply Backing rod (3cm thick) and fire rated seleant above block walls.

LM

55.00

PLASTER WORKS, including materials, angle beds, wire mesh & all related
accessories and curing.Etc.
1

Supply & Installation of Cement Plaster (Internal)

M2

42.00

Supply & Installation of Cement Plaster (External)

M2

46.00

Galvanized Steel Grooves in Plaster

LM

15.00

SUB-TOTAL

SAR

GRAND TOTAL

SAR

Page 25 of 76

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

Current

Total
Amount(SAR)

Total

29,726.52

31,703.00

61,429.52

53,580.40
97,333.80
69,822.00
8,640.00

66,220.00

Page 26 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

131,399.45

Current

Total
Amount(SAR)

Total
-

426,995.65

Page 27 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

350,794.50

Current

Total
Amount(SAR)

Total

385,076.25

34,836.00

4,632.00
775,338.75

Page 28 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

Current

Total
Amount(SAR)

Total

Page 29 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

Current

Total
Amount(SAR)

Total

1,263,763.92

Page 30 of 76

Remarks

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Segment No. 14, Building No. B-1702


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

CONCRETE WORKS
1

Plain Concrete 20 MPA-SRC-thick = 50mm

74

M3

366.00

Plain Concrete 20 MPA-SRC-thick = 100mm

79

M3

350.00

5% Micro Silica

M3

40.00

Mass concrete > 100mm below footings & ground beams (truck measured)

M3

280.00

SUB-TOTAL

SAR

Sub-structure Concrete works 30 MPA-SRC (W/o S.O.G)


1
Isolated Footing
2
Strip Footing
3
Tie Beams/Grade Beam
4
Column Neck
5

Wall Neck (vary thick)


Page 31 of 76

158
169
13

M3
M3
M3
M3

620.00
640.00
950.00
1,250.00

M3

1,150.00

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Segment No. 14, Building No. B-1702


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Slab on grade (20 MPA)-SRC

279

M3

480.00

Vapour Barrier 300 micron Poly Ethylene under slab on grade

M2

3.00

Damp Proofing

M2

6.00

5% Micro Silica

M3

60.00

SUB-TOTAL

SAR

Page 32 of 76

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Segment No. 14, Building No. B-1702


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Super-structure works 30 MPA-OPC (Height as per drawings & spec max 4.5M)
1

Column/Beams/Walls

190

M3

1,150.00

(Column/Beams/Walls) with Corbel

M3

1,400.00

Suspended Slab (vary thick)

250

M3

1,050.00

Concrete Ramps, Steps & Landing

42

M3

1,350.00

Fair face finish for Concrete Ramps, Steps & Landing (Saeled Concrete)

M2

135.00

Concrete Screed

M3

600.00

Concrete Parapet

M3

1,150.00

Concrete Coping (Galvanized Accessories)

LM

140.00

Mechanical Pad

M3

600.00

23
SUB-TOTAL

SAR

Page 33 of 76

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Segment No. 14, Building No. B-1702


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Steel Reinforcement (3% allowable wastage)


1

Supply, Cut, Bend & Install of Straight Reinf bars For 8 & 10,12,14,16mm & above

Ton

4,300.00

Unit Price for Cut, Bend & Installation

Ton

915.00

Unit Price for Installation only

Ton

750.00

4*

Unit Price for Supply,Cut and bend only

Ton

3,550.00

SUB-TOTAL

SAR

BLOCK WORKS AND PLASTER WORKS


BLOCK WORKS, including mortar tools / reinforcement dia 10mm & filling all
height around openings curing.Etc.
1

Supply & Installation of blocks 200mm(CMU), (Non Fire Rated)

M2

95.00

Supply & Installation of blocks 150mm(CMU), (Non Fire Rated)

M2

90.00

Supply & Installation of blocks 100mm(CMU), (Non Fire Rated)

M2

85.00

Page 34 of 76

CORRECTIONAL FECILITIES BUILDING PRO


CONTRACT No.1182

Segment No. 14, Building No. B-1702


COST SUMMARY

SI.NO

DESCRPITION

Qty

Unit

Installation
unit
rate
SAR

Additional Rate for Fire Rated Solid Block

M2

20.00

Supply & Apply Backing rod (3cm thick) and fire rated seleant above block walls.

LM

55.00

PLASTER WORKS, including materials, angle beds, wire mesh & all related
accessories and curing.Etc.
1

Supply & Installation of Cement Plaster (Internal)

M2

42.00

Supply & Installation of Cement Plaster (External)

M2

46.00

Galvanized Steel Grooves in Plaster

LM

15.00

SUB-TOTAL

SAR

GRAND TOTAL

SAR

Page 35 of 76

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

Current

Total
Amount(SAR)

Total

27,219.42

27,594.00

54,813.42
98,040.60
160,341.00
16,812.50
-

Page 36 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

133,728.00

Current

Total
Amount(SAR)

Total
-

408,922.10

Page 37 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

218,327.50

Current

Total
Amount(SAR)

Total

262,206.00

56,929.50

13,518.00
550,981.00

Page 38 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

Current

Total
Amount(SAR)

Total

Page 39 of 76

Remarks

CILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Works Executed

Total Installation
Amount(SAR)

Previous

Current

Total
Amount(SAR)

Total

1,014,716.52

Page 40 of 76

Remarks

Segment No.14, Building No. B-1002

CORRECTIONAL FECILITIES BUILDING PROJECT


DAMMAM
CONTRACT No.1182

COST SUMMARY

Installation
unit
SI.NO

DESCRPITION

Qty

Unit

rate
SAR

CONCRETE WORKS
1 Plain Concrete 20 MPA-SRC-thick = 50mm
2 Plain Concrete 20 MPA-SRC-thick = 100mm
3 5% Micro Silica
4 Mass concrete > 100mm below footings & ground beams (truck measured)
SUB-TOTAL
Sub-structure Concrete works 30 MPA-SRC (W/o S.O.G)
1 Isolated Footing
2 Strip Footing
3 Tie Beams/Grade Beam
4 Column Neck
5 Wall Neck (vary thick)
6 Slab on grade (20 MPA)-SRC
7 Vapour Barrier 300 micron Poly Ethylene under slab on grade
8 Damp Proofing
9 5% Micro Silica
SUB-TOTAL
Super-structure works 30 MPA-OPC (Height as per drawings & spec max
4.5M)
1 Column/Beams/Walls
2 (Column/Beams/Walls) with Corbel
3 Suspended Slab (vary thick)
4 Concrete Ramps, Steps & Landing

Total
Installation
Amount(SAR)

57
61

M3
M3
M3
M3

366.00
350.00
40.00
280.00
SAR

20,770.50
21,476.00
42,246.50

44
115
58
5
48
203

M3
M3
M3
M3
M3
M3
M2
M2
M3

620.00
640.00
950.00
1,250.00
1,150.00
480.00
3.00
6.00
60.00
SAR

27,497.00
73,747.20
55,166.50
6,012.50
54,694.00
97,507.20
314,624.40

210

M3
M3
M3
M3

1,150.00
1,400.00
1,050.00
1,350.00

241,109.00
258,037.50
26,001.00

246
19

5
6
7
8
9

Fair face finish for Concrete Ramps, Steps & Landing (Saeled Concrete)
Concrete Screed
Concrete Parapet
Concrete Coping (Galvanized Accessories)
Mechanical Pad
SUB-TOTAL
Steel Reinforcement (3% allowable wastage)
1 Supply, Cut, Bend & Install of Straight Reinf bars For 8 & 10,12,14,16mm & above
2 Unit Price for Cut, Bend & Installation
3 Unit Price for Installation only
4* Unit Price for Supply,Cut and bend only
SUB-TOTAL
BLOCK WORKS AND PLASTER WORKS
BLOCK WORKS, including mortar tools / reinforcement dia 10mm & filling
all height around openings curing.Etc.
1 Supply & Installation of blocks 200mm(CMU), (Non Fire Rated)
2 Supply & Installation of blocks 150mm(CMU), (Non Fire Rated)
3 Supply & Installation of blocks 100mm(CMU), (Non Fire Rated)
4 Additional Rate for Fire Rated Solid Block
5 Supply & Apply Backing rod (3cm thick) and fire rated seleant above block walls.
PLASTER WORKS, including materials, angle beds, wire mesh & all related
accessories and curing.Etc.
1 Supply & Installation of Cement Plaster (Internal)
2 Supply & Installation of Cement Plaster (External)
3 Galvanized Steel Grooves in Plaster
SUB-TOTAL
GRAND TOTAL

M2
M3
M3
LM
M3

135.00
600.00
1,150.00
140.00
600.00
SAR

Ton
Ton
Ton
Ton

4,300.00
915.00
750.00
3,550.00
SAR

M2
M2
M2
M2
LM

95.00
90.00
85.00
20.00
55.00

M2
M2
LM

42.00
46.00
15.00
SAR

SAR

1,950.00
527,097.50

883,968.40

LDING PROJECT

82

RY
Works Executed
Previous Current Total

Total
Amount(S Remarks
AR)

Segment No. 14, Building No. B- 602

SI.NO

DESCRPITION

CONCRETE WORKS
1
Plain Concrete 20 MPA-SRC-thick = 50mm
2
Plain Concrete 20 MPA-SRC-thick = 100mm
3
5% Micro Silica
4
Mass concrete > 100mm below footings & ground beams (truck measured)
SUB-TOTAL
Sub-structure Concrete works 30 MPA-SRC (W/o S.O.G)
1
Isolated Footing
2
Strip Footing
3
Tie Beams/Grade Beam
4
Column Neck
5
Wall Neck (vary thick)
6
Slab on grade (20 MPA)-SRC
7
Vapour Barrier 300 micron Poly Ethylene under slab on grade
8
Damp Proofing
9
5% Micro Silica
SUB-TOTAL
Super-structure works 30 MPA-OPC (Height as per drawings & spec max
4.5M)
1
Column/Beams/Walls
2
(Column/Beams/Walls) with Corbel
3
Suspended Slab (vary thick)
4
Concrete Ramps, Steps & Landing
5
Fair face finish for Concrete Ramps, Steps & Landing (Saeled Concrete)
6
Concrete Screed
7
Concrete Parapet
8
Concrete Coping (Galvanized Accessories)
9
Mechanical Pad
SUB-TOTAL
Steel Reinforcement (3% allowable wastage)
1
Supply, Cut, Bend & Install of Straight Reinf bars For 8 & 10,12,14,16mm & above
2
Unit Price for Cut, Bend & Installation
3
Unit Price for Installation only
4*
Unit Price for Supply,Cut and bend only
SUB-TOTAL
BLOCK WORKS AND PLASTER WORKS
BLOCK WORKS, including mortar tools / reinforcement dia 10mm & filling all
height around openings curing.Etc.

1
Supply & Installation of blocks 200mm(CMU), (Non Fire Rated)
2
Supply & Installation of blocks 150mm(CMU), (Non Fire Rated)
3
Supply & Installation of blocks 100mm(CMU), (Non Fire Rated)
4
Additional Rate for Fire Rated Solid Block
5
Supply & Apply Backing rod (3cm thick) and fire rated seleant above block walls.
PLASTER WORKS, including materials, angle beds, wire mesh & all related
accessories and curing.Etc.
1
Supply & Installation of Cement Plaster (Internal)
2
Supply & Installation of Cement Plaster (External)
3
Galvanized Steel Grooves in Plaster
SUB-TOTAL
GRAND TOTAL

CORRECTIONAL FECILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Installation
unit

Qty

16mm & above

Unit

rate
SAR

Total
Installation
Amount(SAR)

Works Executed
Previous Current

Total

24
25

M3
M3
M3
M3

366.00
350.00
40.00
280.00
SAR

8,659.56
8,676.50
17,336.06

45

M3
M3
M3
M3
M3
M3
M2
M2
M3

620.00
620.00
900.00
1,125.00
1,100.00
455.00
3.00
6.00
50.00
SAR

27,720.20
35,982.00
5,512.50
38,129.00
107,343.70

M3
M3
M3
M3
M2
M3
M3
LM
M3

1,050.00
1,250.00
975.00
1,200.00
135.00
550.00
1,050.00
130.00
600.00
SAR

48,384.00
88,705.50
7,440.00
144,529.50

Ton
Ton
Ton
Ton

3,850.00
825.00
675.00
3,175.00
SAR

40
5
84

46
91
6

ve block walls.

M2
M2
M2
M2
LM

95.00
90.00
85.00
20.00
55.00

M2
M2
LM

42.00
46.00
15.00
SAR

SAR

269,209.26

Total
Amount( Remarks
SAR)

Segment No. 14, Building No. B- 201

SI.NO

DESCRPITION

CONCRETE WORKS
1
Plain Concrete 20 MPA-SRC-thick = 50mm
2
Plain Concrete 20 MPA-SRC-thick = 100mm
3
5% Micro Silica
4
Mass concrete > 100mm below footings & ground beams (truck measured)
SUB-TOTAL
Sub-structure Concrete works 30 MPA-SRC (W/o S.O.G)
1
Isolated Footing
2
Strip Footing
3
Tie Beams/Grade Beam
4
Column Neck
5
Wall Neck (vary thick)
6
Slab on grade (20 MPA)-SRC
7
Vapour Barrier 300 micron Poly Ethylene under slab on grade
8
Damp Proofing
9
5% Micro Silica
SUB-TOTAL
Super-structure works 30 MPA-OPC (Height as per drawings & spec max
4.5M)
1
Column/Beams/Walls
2
(Column/Beams/Walls) with Corbel
3
Suspended Slab (vary thick)
4
Concrete Ramps, Steps & Landing
5
Fair face finish for Concrete Ramps, Steps & Landing (Saeled Concrete)
6
Concrete Screed
7
Concrete Parapet
8
Concrete Coping (Galvanized Accessories)
9
Mechanical Pad
SUB-TOTAL
Steel Reinforcement (3% allowable wastage)
1
Supply, Cut, Bend & Install of Straight Reinf bars For 8 & 10,12,14,16mm & above
2
Unit Price for Cut, Bend & Installation
3
Unit Price for Installation only
4*
Unit Price for Supply,Cut and bend only
SUB-TOTAL
BLOCK WORKS AND PLASTER WORKS
BLOCK WORKS, including mortar tools / reinforcement dia 10mm & filling all
height around openings curing.Etc.

1
Supply & Installation of blocks 200mm(CMU), (Non Fire Rated)
2
Supply & Installation of blocks 150mm(CMU), (Non Fire Rated)
3
Supply & Installation of blocks 100mm(CMU), (Non Fire Rated)
4
Additional Rate for Fire Rated Solid Block
5
Supply & Apply Backing rod (3cm thick) and fire rated seleant above block walls.
PLASTER WORKS, including materials, angle beds, wire mesh & all related
accessories and curing.Etc.
1
Supply & Installation of Cement Plaster (Internal)
2
Supply & Installation of Cement Plaster (External)
3
Galvanized Steel Grooves in Plaster
SUB-TOTAL
GRAND TOTAL

CORRECTIONAL FECILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Installation
unit

Qty

rate
SAR

Total
Installation
Amount(SAR)

Works Executed
Previous Current

Total

112
165

M3
M3
M3
M3

366.00
350.00
40.00
280.00
SAR

40,827.30
57,655.50
98,482.80

638

M3
M3
M3
M3
M3
M3
M2
M2
M3

620.00
620.00
900.00
1,125.00
1,100.00
455.00
3.00
6.00
50.00
SAR

395,405.00
262,044.00
27,213.75
10,263.00
185,835.65
880,761.40

M3
M3
M3
M3
M2
M3
M3
LM
M3

1,050.00
1,250.00
975.00
1,200.00
135.00
550.00
1,050.00
130.00
600.00
SAR

490,329.00
1,120,362.75
65,436.00
1,676,127.75

Ton
Ton
Ton
Ton

3,850.00
825.00
675.00
3,175.00
SAR

291
24
9
408

467
1,149
55

16mm & above

Unit

ve block walls.

M2
M2
M2
M2
LM

95.00
90.00
85.00
20.00
55.00

M2
M2
LM

42.00
46.00
15.00
SAR

SAR

2,655,371.95

Total
Amount( Remarks
SAR)

Building No. B- 2201

SI.NO

DESCRPITION

CONCRETE WORKS
1
Plain Concrete 20 MPA-SRC-thick = 50mm
2
Plain Concrete 20 MPA-SRC-thick = 100mm
3
5% Micro Silica
4
Mass concrete > 100mm below footings & ground beams (truck measured)
SUB-TOTAL
Sub-structure Concrete works 30 MPA-SRC (W/o S.O.G)
1
Isolated Footing
2
Strip Footing
3
Tie Beams/Grade Beam
4
Column Neck
5
Wall Neck (vary thick)
6
Slab on grade (20 MPA)-SRC
7
Vapour Barrier 300 micron Poly Ethylene under slab on grade
8
Damp Proofing
9
5% Micro Silica
SUB-TOTAL
Super-structure works 30 MPA-OPC (Height as per drawings & spec max
4.5M)
1
Column/Beams/Walls
2
(Column/Beams/Walls) with Corbel
3
Suspended Slab (vary thick)
4
Concrete Ramps, Steps & Landing
5
Fair face finish for Concrete Ramps, Steps & Landing (Saeled Concrete)
6
Concrete Screed
7
Concrete Parapet
8
Concrete Coping (Galvanized Accessories)
9
Mechanical Pad
SUB-TOTAL
Steel Reinforcement (3% allowable wastage)
1
Supply, Cut, Bend & Install of Straight Reinf bars For 8 & 10,12,14,16mm & above
2
Unit Price for Cut, Bend & Installation
3
Unit Price for Installation only
4*
Unit Price for Supply,Cut and bend only
SUB-TOTAL
BLOCK WORKS AND PLASTER WORKS
BLOCK WORKS, including mortar tools / reinforcement dia 10mm & filling all
height around openings curing.Etc.

1
Supply & Installation of blocks 200mm(CMU), (Non Fire Rated)
2
Supply & Installation of blocks 150mm(CMU), (Non Fire Rated)
3
Supply & Installation of blocks 100mm(CMU), (Non Fire Rated)
4
Additional Rate for Fire Rated Solid Block
5
Supply & Apply Backing rod (3cm thick) and fire rated seleant above block walls.
PLASTER WORKS, including materials, angle beds, wire mesh & all related
accessories and curing.Etc.
1
Supply & Installation of Cement Plaster (Internal)
2
Supply & Installation of Cement Plaster (External)
3
Galvanized Steel Grooves in Plaster
SUB-TOTAL
GRAND TOTAL

CORRECTIONAL FECILITIES BUILDING PROJECT


DAMMAM
CONTRACT No.1182

COST SUMMARY
Installation
unit

Qty

16mm & above

Unit

rate
SAR

Total
Installation
Amount(SAR)

Works Executed
Previous Current

Total

65
67

M3
M3
M3
M3

366.00
350.00
40.00
280.00
SAR

23,925.42
23,520.00
47,445.42

134

M3
M3
M3
M3
M3
M3
M2
M2
M3

620.00
620.00
900.00
1,125.00
1,100.00
455.00
3.00
6.00
50.00
SAR

83,377.60
111,942.00
11,868.75
104,458.90
311,647.25

M3
M3
M3
M3
M2
M3
M3
LM
M3

1,050.00
1,250.00
975.00
1,200.00
135.00
550.00
1,050.00
130.00
600.00
SAR

159,600.00
245,222.25
28,704.00
433,526.25

Ton
Ton
Ton
Ton

3,850.00
825.00
675.00
3,175.00
SAR

124
11
230

152
252
24

ve block walls.

M2
M2
M2
M2
LM

95.00
90.00
85.00
20.00
55.00

M2
M2
LM

42.00
46.00
15.00
SAR

SAR

792,618.92

Total
Amount( Remarks
SAR)

Segment No. 14, Building No. B- 2202

SI.NO
CONCRETE WORKS
1
2
3
4
SUB-TOTAL
Sub-structure Concrete works 30 MPA-SRC (W/o S.O.G)
1
2
3
4
5
6
7
8
9
SUB-TOTAL
Super-structure works 30 MPA-OPC (Height as per drawings & spec max 4.5M)
1
2
3
4
5
6
7
8
9
SUB-TOTAL
Steel Reinforcement (3% allowable wastage)
1
2
3
4*
SUB-TOTAL
BLOCK WORKS AND PLASTER WORKS
BLOCK WORKS, including mortar tools / reinforcement dia 10mm & filling all
height around openings curing.Etc.

1
2
3
4
5
PLASTER WORKS, including materials, angle beds, wire mesh & all related
accessories and curing.Etc.
1
2
3
SUB-TOTAL
GRAND TOTAL

Segment No. 14, Building No. B- 2202

DESCRPITION

ONCRETE WORKS
Plain Concrete 20 MPA-SRC-thick = 50mm
Plain Concrete 20 MPA-SRC-thick = 100mm
5% Micro Silica
Mass concrete > 100mm below footings & ground beams (truck measured)
SUB-TOTAL
ub-structure Concrete works 30 MPA-SRC (W/o S.O.G)
Isolated Footing
Strip Footing
Tie Beams/Grade Beam
Column Neck
Wall Neck (vary thick)
Slab on grade (20 MPA)-SRC
Vapour Barrier 300 micron Poly Ethylene under slab on grade
Damp Proofing
5% Micro Silica
SUB-TOTAL
uper-structure works 30 MPA-OPC (Height as per drawings & spec max 4.5M)
Column/Beams/Walls
(Column/Beams/Walls) with Corbel
Suspended Slab (vary thick)
Concrete Ramps, Steps & Landing
Fair face finish for Concrete Ramps, Steps & Landing (Saeled Concrete)
Concrete Screed
Concrete Parapet
Concrete Coping (Galvanized Accessories)
Mechanical Pad
SUB-TOTAL
teel Reinforcement (3% allowable wastage)
Supply, Cut, Bend & Install of Straight Reinf bars For 8 & 10,12,14,16mm & above
Unit Price for Cut, Bend & Installation
Unit Price for Installation only
Unit Price for Supply,Cut and bend only
SUB-TOTAL
LOCK WORKS AND PLASTER WORKS
LOCK WORKS, including mortar tools / reinforcement dia 10mm & filling all
eight around openings curing.Etc.

Supply & Installation of blocks 200mm(CMU), (Non Fire Rated)


Supply & Installation of blocks 150mm(CMU), (Non Fire Rated)
Supply & Installation of blocks 100mm(CMU), (Non Fire Rated)
Additional Rate for Fire Rated Solid Block
Supply & Apply Backing rod (3cm thick) and fire rated seleant above block walls.
LASTER WORKS, including materials, angle beds, wire mesh & all related
ccessories and curing.Etc.
Supply & Installation of Cement Plaster (Internal)
Supply & Installation of Cement Plaster (External)
Galvanized Steel Grooves in Plaster
SUB-TOTAL
GRAND TOTAL

m & above

CORRECTIONAL FECILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY
Installation
unit

Qty

Unit

rate
SAR

Total
Installation
Amount(SAR)

Works Executed
Previous Current

Total

74
66

M3
M3
M3
M3

366.00
350.00
40.00
280.00
SAR

27,094.98
23,082.50
50,177.48

144

M3
M3
M3
M3
M3
M3
M2
M2
M3

620.00
620.00
900.00
1,125.00
1,100.00
455.00
3.00
6.00
50.00
SAR

89,118.80
125,046.00
17,347.50
115,615.50
347,127.80

M3
M3
M3
M3
M2
M3
M3
LM
M3

1,050.00
1,250.00
975.00
1,200.00
135.00
550.00
1,050.00
130.00
600.00
SAR

172,053.00
215,455.50
26,568.00
4,146.00
418,222.50

Ton
Ton
Ton
Ton

3,850.00
825.00
675.00
3,175.00
SAR

139
15
254

164
221
22

M2
M2
M2
M2
LM

95.00
90.00
85.00
20.00
55.00

M2
M2
LM

42.00
46.00
15.00
SAR

SAR

815,527.78

Total
Amount( Remarks
SAR)

Building No. B- 3209 (R1)

SI.NO

DESCRPITION

CONCRETE WORKS
1
Plain Concrete 20 MPA-SRC-thick = 50mm
2
Plain Concrete 20 MPA-SRC-thick = 100mm
3
Plain Concrete 20 MPA-SRC-thick = 150mm
4
5% Micro Silica
5
Mass concrete > 100mm below footings & ground beams (truck measured)
SUB-TOTAL
Sub-structure Concrete works 30 MPA-SRC (W/o S.O.G)
1
Isolated Footing
2
Strip Footing
3
Tie Beams/Grade Beam
4
Column Neck
5
Wall Neck (vary thick)
6
Slab on grade (20 MPA)-SRC
7
Vapour Barrier 300 micron Poly Ethylene under slab on grade
8
Damp Proofing
9
5% Micro Silica
SUB-TOTAL
Super-structure works 30 MPA-OPC (Height as per drawings & spec max 4.5M)
1
Column/Beams/Walls
2
(Column/Beams/Walls) with Corbel
3
Suspended Slab (vary thick)
4
Concrete Ramps, Steps & Landing
5
Fair face finish for Concrete Ramps, Steps & Landing (Saeled Concrete)
6
Concrete Screed
7
Concrete Parapet
8
Concrete Coping (Galvanized Accessories)
9
Mechanical Pad
SUB-TOTAL
Steel Reinforcement (3% allowable wastage)
1
Supply, Cut, Bend & Install of Straight Reinf bars For 8 & 10,12,14,16mm & abo
2
Unit Price for Cut, Bend & Installation
3
Unit Price for Installation only
4*
Unit Price for Supply,Cut and bend only
SUB-TOTAL

BLOCK WORKS AND PLASTER WORKS


BLOCK WORKS, including mortar tools / reinforcement dia 10mm & filling all
height around openings curing.Etc.
1
Supply & Installation of blocks 200mm(CMU), (Non Fire Rated)
2
Supply & Installation of blocks 150mm(CMU), (Non Fire Rated)
3
Supply & Installation of blocks 100mm(CMU), (Non Fire Rated)
4
Additional Rate for Fire Rated Solid Block
5
Supply & Apply Backing rod (3cm thick) and fire rated seleant above block walls.
PLASTER WORKS, including materials, angle beds, wire mesh & all related
accessories and curing.Etc.
1
Supply & Installation of Cement Plaster (Internal)
2
Supply & Installation of Cement Plaster (External)
3
Galvanized Steel Grooves in Plaster
SUB-TOTAL
GRAND TOTAL

CORRECTIONAL FECILITIES BUILDING PROJECT DAMMAM


CONTRACT No.1182

COST SUMMARY

Installation
unit
Qty

Unit

37

71

884
1,470
2

400

M3
M3
M3
M3
M3

Works Executed

rate
SAR

29
11
906

Total Installation
Amount(SAR)

366.00
350.00

10,562.76
3,825.50

40.00
280.00
SAR

14,388.26

M3
M3
M3
M3
M3
M3
M2
M2
M3

620.00
620.00
900.00
1,125.00
1,100.00
455.00
3.00
6.00
50.00
SAR

23,175.60
32,487.00
55,662.60

M3
M3
M3
M3
M2
M3
M3
LM
M3

1,050.00
1,250.00
975.00
1,200.00
135.00
550.00
1,050.00
130.00
600.00
SAR

927,958.50
1,433,250.00
2,880.00
2,364,088.50

Ton
Ton
Ton
Ton

3,850.00
825.00
675.00
3,175.00
SAR

1,540,000.00
1,540,000.00

Previous

lock walls.

M2
M2
M2
M2
LM

95.00
90.00
85.00
20.00
55.00

M2
M2
LM

42.00
46.00
15.00
SAR

SAR

3,974,139.36

Works Executed
Current

Total

Total
Amount( Remarks
SAR)